Purpose<br />

Chapter III<br />

PHASE I INVESTIGATION<br />

3.1 The primary purpose <strong>of</strong> the Phase I investigation programme is<br />

to identify expeditiously those dams which may pose hazards to<br />

human life or property.<br />

Scope<br />

3.2 The Phase I investigation will develop an assessment <strong>of</strong> the<br />

general condition with respect to safety <strong>of</strong> the project based upon<br />

available data and a visual inspection, determines any need <strong>for</strong><br />

emergency measures and conclude if additional studies,<br />

investigation and analyses are necessary and warranted. A<br />

review will be made <strong>of</strong> pertinent, existing and available<br />

engineering data relative to the design, construction and<br />

operation <strong>of</strong> the dam and appurtenant structures, including<br />

electrical and mechanical operating equipment and measurement<br />

from inspection and per<strong>for</strong>mance instruments and devices and a<br />

detailed systematic visual inspection will be per<strong>for</strong>med <strong>of</strong> those<br />

features relating to the stability and operational adequacy <strong>of</strong> the<br />

project. Based upon the findings <strong>of</strong> the review <strong>of</strong> engineering<br />

data and the visual inspection, an evaluation will be made <strong>of</strong> the<br />

general condition <strong>of</strong> the dam, including where possible the<br />

assessment <strong>of</strong> the hydraulic and hydrologic capabilities and the<br />

structural stability.<br />

Engineering data<br />

3.3 To the extent feasible the requisite engineering data listed in<br />

Appendix I relating to the design, construction and operation <strong>of</strong><br />

the dam and appurtenant structures, should be collected from<br />

existing records and reviewed to aid in evaluating the adequacy<br />

<strong>of</strong> hydraulic and hydrologic capabilities and stability <strong>of</strong> the dam.<br />

Where the necessary engineering data are not available,<br />

inadequate or invalid, a listing should be made <strong>of</strong> these specific<br />

additional data deemed necessary by the engineer in charge <strong>of</strong><br />

the investigation and included in the Phase I report.<br />

Field inspections<br />

3.4 The field inspection <strong>of</strong> the dam, appurtenant structures, reservoir<br />

area and downstream channel in the vicinity <strong>of</strong> the dam should<br />