<strong>OPTIMUM</strong> COAL INVESTS IN SUSTAINABILITY<br />

<strong>Optimum</strong> <strong>Coal</strong> Water Reclamation Plant Project<br />

<strong>Optimum</strong> <strong>Coal</strong> commenced with the construction of a water desalination plant in<br />

October 2009. The purpose of the plant is to treat the surplus of affected water that is<br />

generated by the mine and its associated activities. The plant is designed to treat on<br />

average 15 Ml per day, with a peak fl ow capacity of 18 Ml per day.<br />

The construction of this plant will assist the mine<br />

to operate successfully and to mitigate its current<br />

impact on the downstream environment. The<br />

project comprises the following components:<br />

• Mine Water Collection and Site Infrastructure<br />

• Water Treatment Module<br />

• Reclaimed Water Storage and Distribution<br />

• Sludge and Brine Disposal Facilities<br />

• Offi ce, Laboratory and Workshop<br />

• Bulk Electrical Power<br />

Construction of the facility that is located next to the<br />

Opencast Workshop Complex is progressing well<br />

and commissioning of the facility will be completed<br />

by April 2010. The total amount of capital that will<br />

be spend to complete this facility is in the order<br />

of R597 million. Progress on the facility can be<br />

summarised as follows:<br />

• The construction of the potable water reservoirs<br />

is moving along rapidly.<br />

• Road works on the terrace have started along the<br />

western side while the pond road works are also<br />

progressing well.<br />

• CUSA are on site and the main electrical cable<br />

has been laid from 15MVA to 6.6KVA.<br />

• Construction of the gravity feed line has<br />

commenced.<br />

• Clarifi er 1 is virtually completed and work is<br />

progressing well on the other clarifi ers.<br />

• Lining of both Brine Pond 1 and the Sludge Dam<br />

has commenced.<br />

• Pipe work from the Intake tower has been placed<br />

through the dam wall and concrete encasement<br />

started.<br />

• Topsoiling of the pond walls is nearly complete.<br />

July/August/September 2009 7