OPTIMUM COLLIERIES INVESTMENT - Optimum Coal
OPTIMUM COLLIERIES INVESTMENT - Optimum Coal
OPTIMUM COLLIERIES INVESTMENT - Optimum Coal
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>OPTIMUM</strong> COAL INVESTS IN SUSTAINABILITY<br />
<strong>Optimum</strong> <strong>Coal</strong> Water Reclamation Plant Project<br />
<strong>Optimum</strong> <strong>Coal</strong> commenced with the construction of a water desalination plant in<br />
October 2009. The purpose of the plant is to treat the surplus of affected water that is<br />
generated by the mine and its associated activities. The plant is designed to treat on<br />
average 15 Ml per day, with a peak fl ow capacity of 18 Ml per day.<br />
The construction of this plant will assist the mine<br />
to operate successfully and to mitigate its current<br />
impact on the downstream environment. The<br />
project comprises the following components:<br />
• Mine Water Collection and Site Infrastructure<br />
• Water Treatment Module<br />
• Reclaimed Water Storage and Distribution<br />
• Sludge and Brine Disposal Facilities<br />
• Offi ce, Laboratory and Workshop<br />
• Bulk Electrical Power<br />
Construction of the facility that is located next to the<br />
Opencast Workshop Complex is progressing well<br />
and commissioning of the facility will be completed<br />
by April 2010. The total amount of capital that will<br />
be spend to complete this facility is in the order<br />
of R597 million. Progress on the facility can be<br />
summarised as follows:<br />
• The construction of the potable water reservoirs<br />
is moving along rapidly.<br />
• Road works on the terrace have started along the<br />
western side while the pond road works are also<br />
progressing well.<br />
• CUSA are on site and the main electrical cable<br />
has been laid from 15MVA to 6.6KVA.<br />
• Construction of the gravity feed line has<br />
commenced.<br />
• Clarifi er 1 is virtually completed and work is<br />
progressing well on the other clarifi ers.<br />
• Lining of both Brine Pond 1 and the Sludge Dam<br />
has commenced.<br />
• Pipe work from the Intake tower has been placed<br />
through the dam wall and concrete encasement<br />
started.<br />
• Topsoiling of the pond walls is nearly complete.<br />
July/August/September 2009 7