The test pressure is to be maintained <strong>for</strong> sufficient time to permit complete inspection <strong>of</strong> the<br />

system under test but in no case shall the time be less than ten minutes. Test shall be considered<br />

complete only when approval is given by the Engineer in charge.<br />

Test Gauges:<br />

Draining<br />

Contractor’s own test gauge shall be installed as close as possible to the lowest point in the system<br />

being tested. Prior to installation, the test gauge shall be checked against a <strong>st<strong>and</strong>ard</strong> gauge or<br />

calibrated with the aid <strong>of</strong> a dead weight tester. Calibration <strong>of</strong> test gauges shall be the<br />

responsibility <strong>of</strong> the contractor.<br />

All lines <strong>and</strong> equipments shall be completely drained after the hydrostatic test <strong>of</strong> a system has<br />

been completed. High point vents shall be open to prevent excessive vacuum <strong>and</strong> permit<br />

complete draining.If it becomes necessary to leave a system filled with the testing medium <strong>for</strong><br />

any abnormal length <strong>of</strong> time, such as venting shall be made to provide <strong>for</strong> possible liquid<br />

expansion with change in ambient temperatures.<br />

10.0 RECORDS<br />

Records in triplicate shall be made <strong>for</strong> each <strong>piping</strong> system as follows:<br />

10.1 In case <strong>of</strong> underground <strong>piping</strong>, layouts giving actual elevations or pipeline as laid.<br />

10.2 Test certificates containing date or test, identification <strong>of</strong> the <strong>piping</strong> system, test fluid used, test<br />

pressure <strong>and</strong> approval <strong>of</strong> owner’s inspector.<br />

Certificates <strong>for</strong> flushing containing flushing medium used, identification <strong>of</strong> the <strong>piping</strong> system, date<br />

<strong>of</strong> flushing <strong>and</strong> approval by owner’s inspector.<br />

PAYMENT<br />

Payment <strong>for</strong> <strong>piping</strong> shall be based on linear measurements calculated on the basis <strong>of</strong> the execution<br />

drawings. The length shall be measured along the centre lines <strong>of</strong> pipes, centre lines <strong>of</strong> bends <strong>and</strong><br />

elbows, tees, reducer, SW, flanged joints. All types <strong>of</strong> valves shall be excluded from this<br />

measurement. Branch connections shall be measured from the outer surface <strong>of</strong> the header.<br />

The payment shall be made on per metre basis <strong>of</strong> <strong>piping</strong> work erected, measured to the nearest<br />

centimeter.<br />

The unit rates <strong>for</strong> the underground <strong>piping</strong> shall be inclusive <strong>of</strong> earthwork excavation, backfilling,<br />

<strong>and</strong> compaction, disposal <strong>of</strong> surplus earth, coating <strong>and</strong> wrapping including supply <strong>of</strong> materials.<br />

The unit rates <strong>for</strong> above ground carbon steel <strong>piping</strong> shall be exclusive <strong>of</strong> <strong>erection</strong> <strong>of</strong> all types <strong>of</strong><br />

supports but inclusive <strong>of</strong> supply <strong>of</strong> necessary bolts nuts <strong>and</strong> washers gaskets etc as per respective<br />

<strong>specification</strong>.<br />

Payment <strong>for</strong> the installation <strong>of</strong> sluice valves, check valves, butterfly valves, expansion bellows<br />

will be made on number basis <strong>and</strong> the unit rates shall be inclusive <strong>of</strong> supply <strong>of</strong> necessary bolts<br />

nuts, washers <strong>and</strong> gaskets, etc.