necessary by the Engineer in charge <strong>for</strong> process lines. The details <strong>for</strong> the type <strong>of</strong> connections to<br />

be adopted shall be given to the contractor at the time <strong>of</strong> work.<br />

After the <strong>piping</strong> is erected in final position, it shall be cleaned, tested <strong>for</strong> tightness <strong>and</strong> kept dry<br />

wherever instructed, as described in this <strong>specification</strong>.<br />

Valves<br />

The valve spindle positions are shown in the arrangement drawings <strong>and</strong> the contractor shall be<br />

required to follow them. He shall, however, bring it to the notice <strong>of</strong> the Engineer in charge in<br />

case he encounters some difficulty in installing them.<br />

Where practicable <strong>and</strong> except when otherwise shown on the drawings, valve stems shall be<br />

installed in a vertical direction <strong>and</strong> shall not be installed with stems below the horizontal axis.<br />

Supports<br />

Supports, guides <strong>and</strong> anchors <strong>for</strong> <strong>piping</strong> shall be fabricated <strong>and</strong> provided as shown in the<br />

drawings. No anchors on <strong>piping</strong> shall be used except at locations shown in the drawings. The<br />

pipe shall be secured firmly at anchor supports.<br />

Fabrication <strong>and</strong> <strong>erection</strong> <strong>of</strong> supporting elements <strong>and</strong> structural fixtures wherever required <strong>and</strong><br />

pointed out by the Engineer in charge, whether indicated in drawing or not, to prevent vibration,<br />

excess sag etc. shall be carried out by the contractor. No separate payment will be made <strong>for</strong><br />

erecting <strong>of</strong> these additional supports <strong>and</strong> it will be deemed as part <strong>of</strong> <strong>piping</strong> <strong>erection</strong> work.<br />

4. LAYING OF UNDERGROUND PIPING<br />

The Contractor shall lay the underground <strong>piping</strong> in accordance with the following clauses <strong>and</strong> as<br />

per the <strong>piping</strong> arrangement drawings/stetches issued during the course <strong>of</strong> construction. Coating<br />

<strong>and</strong> wrapping <strong>of</strong> the underground lines shall be in accordance with <strong>specification</strong>.<br />

The contractor shall dig the pipe line trenches where necessary according to the drawing, true to<br />

the line <strong>and</strong> gradient as per <strong>specification</strong>s <strong>and</strong> as directed by the Engineer-in-charge.<br />

The contractor shall be responsible <strong>for</strong> correct layout <strong>and</strong> gradient <strong>of</strong> the line. Errors, if any, shall<br />

be rectified by the Contractor at his own cost.<br />

Trenching: (Refer <strong>specification</strong> <strong>for</strong> Earthwork in underground <strong>piping</strong>)<br />

The trench shall be cut true to the line leveled with the help <strong>of</strong> sight rails provided at every 30 M at<br />

change <strong>of</strong> direction, gradient <strong>and</strong> at any suitable distance as directed by Engineer in charge.<br />

If the trench is excavated below the required level indicated in the drawing, the extra depth shall<br />

be filled with concrete or approved equivalent material as directed by the Engineer in charge at<br />

no extra cost to owner.<br />

The trench shall be excavated so as to provide an average cover <strong>of</strong> 1000 mm or equal to the<br />

diameter <strong>of</strong> the largest pipe to be laid in the trench, or as shown in drawings whichever is greater.<br />

The average cover will be reckoned from top <strong>of</strong> the pipe <strong>of</strong> the largest diameter to be laid in the<br />

trench, to the finished grade. The width <strong>of</strong> the trench shall be sufficient to give free working