Major tasks completed during the<br />

first quarter, 2011<br />

Tasks Completed February March April<br />

FCC approves three microwaves licenses for Loma Ridge,<br />

Construction Circle, and Garden Grove<br />

Harris Corporation completes installation of T-1 lines at all<br />

communications towers<br />

Harris Corporation begins microwave factory acceptance<br />

testing at San Antonio, Texas<br />

Harris Corporation completes staging of OpenSky2 radio at<br />

Lynchburg, Virginia<br />

OCTA receives 11 pallets of radio equipment<br />

Began demolition of room inside Central Communication to<br />

add two more consoles<br />

GIRO begins testing schedule data export from HASTUS 2010<br />

to OrbCAD system<br />

FCC grants license for 700 MHz radio, LA County approves<br />

change of frequency to 700 MHz at Black Jack Mountain<br />

3