Typical Installation Schedule<br />

13. Typical Installation Schedule<br />

One Lane of 8 Sensors<br />

Ideal conditions with a pavement and air temperature<br />

above +20 °C, dry condition of weather and pavement.<br />

This is an example of an installation schedule. The time for<br />

the grout curing depends on ambient air- and pavement<br />

temperatures. The lane must not be opened before the<br />

grouting has completely cured, refer the Installation<br />

<strong>Instruction</strong>s 002-301 (EV06.<strong>9195E</strong>).<br />

Time Work Personnel required<br />

00:00 Lane closure Police or authorized company for<br />

lane closure<br />

00:15 Marking, cut and clean slots for<br />

the Lineas sensor and for the<br />

inductive loops<br />

02:00 Heat and dry slots, pull cables<br />

through tube, install sensors<br />

1 men cutting, 3 to 4 men for slot<br />

preparation, tube preparation for<br />

the cables (if applicable)<br />

3 to 4 men<br />

04:00 Cable terminations 3 to 4 men<br />

06:30 Grind surface off, clean up 2 men<br />

07:30 Sensor tests 2 men<br />

08:00 Lane opening Police or authorized company<br />