Typical Installation Schedule<br />
13. Typical Installation Schedule<br />
One Lane of 8 Sensors<br />
Ideal conditions with a pavement and air temperature<br />
above +20 °C, dry condition of weather and pavement.<br />
This is an example of an installation schedule. The time for<br />
the grout curing depends on ambient air- and pavement<br />
temperatures. The lane must not be opened before the<br />
grouting has completely cured, refer the Installation<br />
<strong>Instruction</strong>s 002-301 (EV06.<strong>9195E</strong>).<br />
Time Work Personnel required<br />
00:00 Lane closure Police or authorized company for<br />
lane closure<br />
00:15 Marking, cut and clean slots for<br />
the Lineas sensor and for the<br />
inductive loops<br />
02:00 Heat and dry slots, pull cables<br />
through tube, install sensors<br />
1 men cutting, 3 to 4 men for slot<br />
preparation, tube preparation for<br />
the cables (if applicable)<br />
3 to 4 men<br />
04:00 Cable terminations 3 to 4 men<br />
06:30 Grind surface off, clean up 2 men<br />
07:30 Sensor tests 2 men<br />
08:00 Lane opening Police or authorized company<br />