3.0 Staged Work Plan and Indicative Costing<br />

Each piece <strong>of</strong> equipment installed at play spaces within the <strong>City</strong> <strong>of</strong><br />

<strong>Greater</strong> <strong>Geelong</strong> will eventually reach the end <strong>of</strong> its serviceable life.<br />

Nominal replacement dates for specific types <strong>of</strong> equipment may indicate<br />

approximately when replacement should occur, however an annual audit<br />

will define more accurately when the trigger point occurs. As the<br />

majority <strong>of</strong> equipment reaches its replacement date at each given play<br />

space, the opportunity to redesign and redevelop the entire space will be<br />

presented. The cost <strong>of</strong> redevelopment varies considerably depending on<br />

the classification <strong>of</strong> the play space. The estimates below have been used<br />

in the work plan.<br />

Table 3 Indicative Play Space Redevelopment Costs<br />

approximately $500,000 per stage ($250,000 for infrastructure and<br />

$250,000 for play space redevelopments).<br />

3.2 Play space rationalisation<br />

Some existing play spaces were identified as having low viability in terms<br />

<strong>of</strong> effective catchment, apparent low usage, safety issues or poor siting.<br />

In these cases it is recommended that the play space be decommissioned.<br />

Where practicable, equipment in other nearby play spaces should be<br />

enhanced or the original equipment reinstated in a more suitable location<br />

(provided equipment is in serviceable condition). Table 4 lists<br />

recommendations for specific play space rationalisation.<br />

Hierarchical classification<br />

Indicative cost<br />

Local / Neighbourhood $28,000<br />

District $75,000<br />

Sub-regional $250,000<br />

Regional $750,000<br />

State / National $1,000,000<br />

The actual cost however, will vary depending on the specific nature <strong>of</strong><br />

each development and will be defined more precisely as each stage is<br />

tackled. Hence the cost estimates provided with the work plan are<br />

indicative only.<br />

Works that have been defined as having medium-low priority or higher<br />

(i.e. does not include low priorities) have been costed and divided into<br />

ten stages. The estimated cost for these stages is around $5M or<br />

<strong>City</strong> <strong>of</strong> <strong>Greater</strong> <strong>Geelong</strong> Play Strategy <strong>Appendix</strong> 2 – Page 42