Economy Profile: Burundi - Doing Business
Economy Profile: Burundi - Doing Business
Economy Profile: Burundi - Doing Business
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>Doing</strong> <strong>Business</strong> 2013<br />
<strong>Burundi</strong><br />
40<br />
No.<br />
Procedure<br />
Time to<br />
complete<br />
Cost to complete<br />
At that time, REGIDESO measures the distance from the site of the future<br />
transformer to the electrical grid.<br />
Purchase the transformer<br />
3<br />
A transformer needs to be built to accommodate the 140kVA to pass<br />
from medium voltage to low voltage. If the utility has transformers in<br />
stock, the customer simply goes to the warehouse of the utility and<br />
purchases the transformer. If there is no transformer available at the<br />
utility, the customer buys it himself on the market. It takes several<br />
months to fabricate and import a transformer from Europe.<br />
REGIDESO carries out the external connection works and installs the<br />
meter<br />
135 calendar days no charge<br />
4<br />
The utility is doing all the external connection works including the design<br />
of the connection from the electrical grid to the transformer. The meter<br />
is installed before the actual connection takes place. The meter is rented<br />
from REGIDESO; a flat fee is paid for this. In the event that the meter<br />
breaks, it is replaced free of charge.<br />
* Client signs supply contract with REGIDESO<br />
37 calendar days BIF 73,193,616.9<br />
5 The client usually signs the supply contract with the utility at the end of<br />
the external connection works, but can sign the contract also during the<br />
works.<br />
* Takes place simultaneously with another procedure.<br />
Source: <strong>Doing</strong> <strong>Business</strong> database.<br />
1 calendar day no charge