What in the Drilling Contractor’s Management System demonstrates assurance to external<br />
stakeholders that these expectations are achieved?<br />
‣ Statement of the Drilling Contractor’s commitment to review and update the <strong>HSE</strong> <strong>Case</strong>.<br />
‣ Description of the criteria which would initiate a review of the <strong>HSE</strong> <strong>Case</strong> information.<br />
‣ Description of the arrangements (including responsibilities) for reviewing and updating<br />
the <strong>HSE</strong> <strong>Case</strong> information.<br />
1.2.6 Continuous Improvement<br />
External Stakeholder Expectations<br />
Demonstration that the Drilling Contractor is committed to continually improving the<br />
management of risks and environmental impacts associated with MODU or rig operations.<br />
What in the Drilling Contractor’s Management System demonstrates assurance to external<br />
stakeholders that these expectations are achieved?<br />
‣ Statement of the Drilling Contractor’s commitment to continuous improvement, by:<br />
applying and contributing to the identification and development of industry standards<br />
and best practices.<br />
participating in the development of legislation and regulations.<br />
reviewing and assessing new technology.<br />
reviewing and assessing the application of new legislations and regulations and<br />
implementing necessary changes within their management system.<br />
1.2.7 Action Plan / Recommendations<br />
External Stakeholder Expectations<br />
Demonstration that the Drilling Contractor addresses recommendations and gaps in <strong>HSE</strong><br />
performance; such as those identified as part of the Risk Assessment process within the<br />
<strong>HSE</strong> <strong>Case</strong>, and follows-up and closes-out agreed corrective actions.<br />
What in the Drilling Contractor’s Management System demonstrates assurance to external<br />
stakeholders that these expectations are achieved?<br />
‣ Arrangements for the review of recommendations identified during the Risk Assessment<br />
process (Part 4), including:<br />
References to the studies or sources from which each recommendation originated.<br />
‣ Arrangements for follow-up and close-out of agreed corrective actions, including:<br />
Persons/positions responsible for implementing each recommendation.<br />
Target dates for completion of each recommendation.<br />
‣ Arrangements for verifying the close-out of all recommendations.<br />
1.2.8 <strong>HSE</strong> <strong>Case</strong> Presentation<br />
External Stakeholder Expectations<br />
A means of providing the <strong>HSE</strong> <strong>Case</strong> information to internal and external stakeholders.<br />