11.04.2014 Views

Advance Terminal Planning Study Program Criteria Document

Advance Terminal Planning Study Program Criteria Document

Advance Terminal Planning Study Program Criteria Document

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

DRAFT


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

TABLE OF CONTENTS<br />

Page<br />

INTRODUCTION ................................................................................. 1<br />

BACKGROUND .................................................................................... 1<br />

PURPOSE ........................................................................................... 2<br />

1 ADVANCED PLANNING PARAMETERS......................................... 2<br />

1.1 Goals and Objectives .................................................................... 2<br />

1.2 Passenger Surveys ....................................................................... 4<br />

1.3 Aviation Demand Forecast ............................................................ 5<br />

1.4 Benchmarking ........................................................................... 13<br />

2 AIRFIELD REQUIREMENTS ...................................................... 15<br />

2.1 Design Aircraft .......................................................................... 15<br />

2.2 Aircraft Gates and Loading Bridge Requirements ............................ 17<br />

2.3 Apron Service Road .................................................................... 22<br />

2.4 Airside Security Requirements ..................................................... 22<br />

2.5 Aircraft Deicing .......................................................................... 23<br />

2.6 Fueling Requirements ................................................................. 30<br />

3 TERMINAL REQUIREMENTS ..................................................... 36<br />

3.1 Methodologies ........................................................................... 36<br />

3.2 <strong>Terminal</strong> Facility Requirements .................................................... 39<br />

3.3 Concessions Requirements .......................................................... 68<br />

3.4 Specialty Systems and New Technology ........................................ 83<br />

3.5 Utilities, Infrastructure and MEP Requirements ............................. 115<br />

DRAFT<br />

4 LANDSIDE REQUIREMENTS ................................................... 124<br />

4.1 Regional Access ........................................................................ 125<br />

4.2 <strong>Terminal</strong> Area Landside Requirements ......................................... 142<br />

4.3 Vehicular Parking ...................................................................... 146<br />

5 TERMINAL SUPPORT REQUIREMENTS ................................... 149<br />

5.1 Fleet Maintenance ..................................................................... 150<br />

5.2 Fuel/Wash Facility ..................................................................... 151<br />

5.3 Aviation Facilities Maintenance ................................................... 152<br />

5.4 Airport Police Department .......................................................... 152<br />

5.5 Flight Kitchens .......................................................................... 153<br />

5.6 Airport Hotel ............................................................................ 154<br />

5.7 Ground Service Equipment (GSE) Facilities .................................. 154<br />

5.8 Airside Snow Storage and Melting Areas ...................................... 155<br />

5.9 Ramp Control Tower .................................................................. 157<br />

5.10 Remain Overnight (RON) Parking ................................................ 160<br />

Landrum & Brown<br />

April 2013<br />

Page i


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

TABLE OF CONTENTS (Continued)<br />

Page<br />

6 REFINE CONCEPTUAL TERMINAL COMPLEX SITE PLAN .......... 161<br />

6.1 Airside Site Plan ....................................................................... 161<br />

6.2 Ground Access Site Plan for the New <strong>Terminal</strong> .............................. 178<br />

6.3 <strong>Terminal</strong> Support and Collateral Development Site Plan ................. 198<br />

6.4 FAA Navigational Aids ................................................................ 214<br />

7 REFINE CONCEPTUAL TERMINAL BUILDING PLANS ............... 216<br />

7.1 Conceptual <strong>Terminal</strong> and Concourse Plans.................................... 216<br />

7.2 Refined Alternative 1B Building Plans .......................................... 235<br />

7.3 Conceptual <strong>Terminal</strong> Building Cross Sections ................................ 245<br />

7.4 Conceptual Building Mass Elevations ........................................... 252<br />

7.5 Conceptual Illustrations ............................................................. 253<br />

7.6 New <strong>Terminal</strong> Mechanical & Electrical Improvements/<br />

Alternatives.............................................................................. 260<br />

7.7 Baggage Handling System (BHS) ................................................ 288<br />

8 ENVIRONMENTAL CONSIDERATIONS .................................... 293<br />

8.1 Alternative Evaluation – Environmental Resources ........................ 293<br />

8.2 Implementation <strong>Planning</strong> – Environmental Considerations .............. 293<br />

8.3 Sustainability <strong>Planning</strong> .............................................................. 295<br />

9 PROGRAM IMPLEMENTATION ................................................ 306<br />

9.1 Introduction ............................................................................. 306<br />

9.2 <strong>Terminal</strong> Development Phasing Summary .................................... 306<br />

9.3 Capital Costs of the New <strong>Terminal</strong> <strong>Program</strong> .................................. 308<br />

9.4 Enabling Projects ...................................................................... 308<br />

9.5 LEED Gold Certification .............................................................. 310<br />

9.6 Implementation Timeline ........................................................... 312<br />

9.7 <strong>Program</strong> Delivery Methods ......................................................... 313<br />

DRAFT<br />

10 FINANCIAL IMPLEMENTATION PLAN ..................................... 316<br />

10.1 Cost and Affordability of New Replacement <strong>Terminal</strong> ..................... 316<br />

10.2 Determinations of Affordability ................................................... 320<br />

Landrum & Brown<br />

April 2013<br />

Page ii


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

PROGRAM CRITERIA DOCUMENT (PCD)<br />

INTRODUCTION<br />

This <strong>Program</strong> <strong>Criteria</strong> <strong>Document</strong> (PCD) provides the overall guidance for the design<br />

of the New <strong>Terminal</strong> Complex (New <strong>Terminal</strong>) facilities at the Kansas City<br />

International Airport (KCI or Airport). The New <strong>Terminal</strong> is envisioned as a<br />

consolidated single facility that will replace the existing three unit terminal used<br />

today. The PCD contains all of the pertinent information identified and researched<br />

for the development of the project including any infrastructure enabling projects<br />

needed to allow implementation of the New <strong>Terminal</strong> and the necessary regulatory<br />

information. The conceptual plans for the refined airside, terminal, and landside<br />

requirements are the basis for the PCD, which is designed to serve as the guidelines<br />

for the design and implementation of the New <strong>Terminal</strong> facilities.<br />

BACKGROUND<br />

The Airport was built by the City of Kansas City, Missouri (KCMO or City) and has<br />

served the needs of air travelers in the Midwest since the opening in 1972.<br />

The KCI complex spans more than 10,000 acres, making it one of the largest<br />

airports in the U.S.<br />

The Airport is situated 15 miles northwest of the City’s central business district and<br />

currently, the closest scheduled commercial passenger service airport is Omaha<br />

Eppley Airfield (OMA), located 152 miles away. The Metropolitan Statistical Area<br />

(MSA) for the City, as defined by the U.S. Census Bureau for Kansas City,<br />

encompasses 15 counties including Bates, Caldwell, Cass, Clay, Clinton, Jackson,<br />

Lafayette, Platte, and Ray counties in Missouri; and Franklin, Johnson,<br />

Leavenworth, Linn, Miami, and Wyandotte counties in Kansas. The Kansas City<br />

Aviation Department (KCAD) defines KCI’s Air Service Area (ASA) as all counties in<br />

the MSA, and additionally Buchanan County in Missouri and Douglas County in<br />

Kansas.<br />

DRAFT<br />

KCAD completed an Airport Master Plan (MP) in 2008 that provided a vision for the<br />

growth and development of KCI over the following 20 years, and established a<br />

framework for the development of facilities and a guide for long-term on-airport<br />

land use and development decisions. The MP identified the need for an updated<br />

passenger terminal complex to serve a projected increase in passenger demand<br />

and provide a passenger processing facility that would meet and exceed customer<br />

service expectations.<br />

Several terminal options were selected for development sites and design<br />

alternatives were developed and presented to KCAD for review. The MP identified a<br />

South <strong>Terminal</strong> project that included a new 59-gate terminal south of Runway 9/27<br />

and a new terminal curb front and loop roadway system, a new south access<br />

roadway from Missouri Route 152 (M-152), and an upgrade of I-435 and I-29<br />

ramps connecting to M-152.<br />

Landrum & Brown Page 1<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

As a result of the MP, the New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong> <strong>Study</strong> (the <strong>Study</strong>) was<br />

initiated November 28, 2011 to research, explore, and consider the new South<br />

<strong>Terminal</strong> option developed in the MP. However, in June 2012 KCI officials, due to<br />

the high cost of the South <strong>Terminal</strong> project, announced that the existing <strong>Terminal</strong> A<br />

site was being considered for the proposed main terminal location. This site would<br />

take advantage of infrastructure that currently exists and as a result would cost<br />

significantly less and be implemented more quickly.<br />

PURPOSE<br />

The desired result of the <strong>Study</strong> is to identify, programmatically define, and<br />

conceptually depict a planning and design direction for the Preferred Alternative’s<br />

future phase developments. Therefore, this PCD provides all of the key background<br />

research and analysis, facility requirements, and detailed planning and design<br />

guidelines to facilitate the design and construction needs of the new passenger<br />

terminal complex.<br />

1. ADVANCED PLANNING PARAMETERS<br />

Identifying advanced planning parameters will lay the foundation for the project.<br />

To address the unique operating needs of KCI, the specific goals, objectives, and<br />

passenger demand characteristics that guided the development of alternatives and<br />

the choice of the Preferred Alternative are identified in this section.<br />

1.1 Goals and Objectives<br />

The project information contained in the MP was supplemented by new and more<br />

detailed information for this <strong>Study</strong>. Meetings and discussions with key City<br />

Stakeholders, the FAA, three of the primary airlines serving KCI, and key<br />

concessionaires were conducted. The goals and objectives formulated from these<br />

meetings and discussions combined with comments provided by KCAD, are the<br />

basis for determining the various goals and objectives of the <strong>Study</strong>.<br />

The overall Project Goal is to develop a plan for the design and construction of a<br />

new terminal at KCI, which will enhance the City’s ability to provide a high level of<br />

air service, as well as a source of community pride for the City and the Metro<br />

Region. This will be accomplished by providing a first class arrivals destination and<br />

new, efficient, and technologically advanced airside, terminal, and landside facilities<br />

that promote the highest level of passenger processing conveniences and customer<br />

service. The primary goals and their associated objectives of the <strong>Study</strong> are:<br />

<strong>Terminal</strong> Goals:<br />

<br />

<br />

<br />

DRAFT<br />

Most importantly, replace the three existing passenger terminals with one<br />

integrated state-of-the-art facility<br />

Achieve a balanced capacity of gates, terminal processing, and landside<br />

facilities<br />

Incorporate the latest in passenger processing technology<br />

Landrum & Brown Page 2<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Plan facilities that meet a minimum Level of Service (LOS) C during peak<br />

hours<br />

Plan for flexibility to expand as demand changes<br />

Develop facilities that can adapt to a rigorous and changing security<br />

environment<br />

Design passenger-friendly flows and way-finding<br />

Minimize walking distances<br />

Develop operationally efficient gates for the airlines<br />

Provide efficient baggage handling and delivery<br />

Improve international facilities and their connection to domestic service<br />

Minimize the complexity of construction phasing<br />

Airside Goals:<br />

<br />

<br />

<br />

<br />

Maximize the uses of the new terminal site and airfield efficiencies<br />

Plan facilities that meet or exceed FAA design standards<br />

Accommodate aircraft that utilize the Airport, both now and in the future<br />

Provide efficient operational requirements such as vehicle service roads and<br />

uncongested ramp areas<br />

Regional and Landside Access Goals:<br />

<br />

<br />

<br />

<br />

<br />

<br />

Financial:<br />

<br />

<br />

<br />

<br />

<br />

Integrate the New <strong>Terminal</strong> into the existing roadway and regional<br />

transportation system with minimal interruption to on-going operations<br />

DRAFT<br />

Maximize on-airport parking<br />

Provide for convenient passenger access and transfers<br />

Minimize walking distances to the New <strong>Terminal</strong><br />

Provide a high LOS for rental car patrons<br />

Provide a high LOS at Arrivals and Departures curbsides<br />

Periodically evaluate a Rough Order of Magnitude to ensure the New <strong>Terminal</strong><br />

is a financially feasible plan<br />

Develop a cost-effective and realistically affordable plan<br />

Utilize common-use systems to minimize capital and operating costs<br />

Maximize non-aviation revenue opportunities including concessions and<br />

parking<br />

Maximize eligibility for FAA funding of proposed improvements<br />

Landrum & Brown Page 3<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

1.2 Passenger Surveys<br />

Passenger surveys were conducted at the Airport between March 4 th and<br />

March 10 th , 2012 to gain an understanding of the passengers using KCI and develop<br />

a current passenger profile. The surveys confirmed KCI’s ASA and provided<br />

additional data such as check-in, baggage check, parking, and concessions<br />

planning, to name a few. All of the information collected from the surveys is<br />

beneficial and will be used in the future for demand forecasting, airport planning,<br />

and policy and investment decisions.<br />

The passenger surveys were conducted in the holdrooms at the gates prior to flight<br />

departure. Passengers were selected from a balanced mix of flights in all of the<br />

current terminals, and flights were selected by airlines, day of week, time of day,<br />

and destination market, providing a statistically valid method of identifying a<br />

representative passenger profile for departing passengers at KCI.<br />

Thirty questions including passenger characteristics, local trip origin, ground<br />

transportation mode and parking, concessions, resident or visitor status, purpose<br />

and propensity for travel, airline elite status, check-in location, number of bags<br />

carried on or checked, bag check location, travel group size, and final destination<br />

were included in the survey. Twenty-one hundred surveys were collected and<br />

analyzed.<br />

The survey results confirmed many facts and statistics that helped to describe<br />

current passengers at KCI. These results, summarized below, provide important<br />

information for the planning of the future New <strong>Terminal</strong>.<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

DRAFT<br />

80 percent travel from a local origin within the ASA<br />

62 percent are considered residents and 38 percent are visitors<br />

56 percent are male and 44 percent female<br />

The largest percentage were between 45 and 54 and the largest percentage<br />

of household income was between $50,000 and $99,999<br />

93 percent had a final destination in the U.S and seven percent had an<br />

international final destination<br />

56 percent were traveling for business and 42 percent were on leisure travel<br />

with more than half of leisure travelers visiting friends and family<br />

85 percent came in a private car or rental car and 63 percent of those in a<br />

private car (excluding rental cars) used one of the on- or off-airport parking<br />

lots with 42 percent using the KCI economy lot<br />

Almost two-thirds were on non-stop flights<br />

The majority of destinations on connecting flights were to Chicago, Denver,<br />

and Dallas<br />

42 percent used on-line check-in, 29 percent checked in with ticket agents,<br />

and 28 percent used E ticket kiosks<br />

Landrum & Brown Page 4<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

46 percent checked bags at the ticket counter, while 44 percent did not<br />

check any bags<br />

The average number of bags checked by each passenger was 0.6 bags<br />

Most passengers used highways I 29 and I-435<br />

<br />

<br />

Approximately 31 percent made a purchase at one of the food concessions<br />

and 11 percent made purchases from a retail store<br />

Average passenger dwell time in the terminals was approximately 1 hour<br />

40 minutes, although residents and business travelers allowed for less time<br />

due to familiarity and frequency of use<br />

Information from these surveys will be discussed throughout this document.<br />

1.3 Aviation Demand Forecast<br />

Comprehensive aviation demand forecasts were developed for KCI for the years<br />

2015, 2020, 2025, and 2030. Annual passenger enplanements, annual aircraft<br />

operations, and aircraft fleet mix have been projected, as well as aircraft and peak<br />

period activity projections. The aviation activity projections are a critical<br />

component in the facility planning process and serve as a basis for:<br />

• Determining the role of the Airport with respect to the type of aircraft to be<br />

accommodated in the future,<br />

• Evaluating the capacity of existing Airport facilities and its ability to<br />

accommodate projected aviation demand, and<br />

DRAFT<br />

• Estimating the development requirements of the future terminal, airside, and<br />

landside facilities.<br />

1.3.1 ENPLANED PASSENGERS<br />

Table 1.3-1, Summary of Enplaned Passenger Forecast, shows a summary<br />

projection of enplaned passengers through 2030. Total enplaned passengers are<br />

forecast to grow from 5.1 million enplanements in 2011 to 7.2 million by 2030,<br />

representing an average annual growth rate of 1.9 percent. Almost all of the traffic<br />

at KCI is expected to be originating (i.e. passenger trips beginning or ending at the<br />

Airport) with only limited connecting activity. The enplanement forecast is<br />

presented in Figure 1.3-1, Summary of Enplaned Passenger Forecast.<br />

Landrum & Brown Page 5<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 1.3-1<br />

SUMMARY OF ENPLANED PASSENGER FORECAST<br />

Source:<br />

Landrum & Brown<br />

Figure 1.3-1<br />

SUMMARY OF ENPLANED PASSENGER FORECAST<br />

DRAFT<br />

Source:<br />

Landrum & Brown<br />

1.3.2 PASSENGER OPERATIONS<br />

Passenger aircraft operations were derived from the enplaned passenger forecast.<br />

The aggregate number of commercial passenger operations at an airport depends<br />

on three factors: total passengers, average aircraft size, and average load factor<br />

(percent of seats occupied).<br />

In order to develop reasonable load factor and aircraft gauge assumptions, the<br />

same categories of activity were used as in the enplaned passenger forecast<br />

(see Table 1.3-1 above). To derive the passenger operations forecast, assumptions<br />

Landrum & Brown Page 6<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

are inherently different at airports due to differences in how airlines choose to<br />

strategically serve the demand for air travel at each airport. At KCI, aircraft size,<br />

passenger load factors, and Average Seats per Departure (ASPD) were used.<br />

Airlines continually work to align capacity with demand. At KCI, average aircraft<br />

size reflects a mix of narrowbody and regional jet aircraft. Since 2007, average<br />

aircraft size has increased as Low Cost Carriers (LCCs) have continued to capture a<br />

larger share of the KCI market and network airlines have deployed a higher<br />

percentage of large regional jets. Enplaned passenger load factors have increased<br />

24 percent from 60 percent in 2000 to almost 75 percent in 2011 as airlines make<br />

better use of their aircraft assets.<br />

ASPD for each of the major groups of passenger activity was calculated from total<br />

departures and total departing seats. Aircraft load factors were calculated for each<br />

group of passenger operations by dividing total enplaned passengers by total<br />

departing seats. To calculate total operations, the total number of departures was<br />

multiplied by a factor of two. Figure 1.3-2, Historical Passenger Operations<br />

with ASPD, displays historical passenger operations and average seats per flight.<br />

Figure 1.3-2<br />

HISTORICAL PASSENGER OPERATIONS WITH ASPD<br />

DRAFT<br />

Source:<br />

Landrum & Brown<br />

Landrum & Brown Page 7<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

1.3.3 FLEET MIX<br />

As passenger traffic volumes increase at KCI, airlines will shift to larger, more<br />

efficient aircraft, where possible, to reduce unit costs and increase revenues.<br />

Significant fleet renewal is expected to occur over the forecast period. The average<br />

number of seats per flight is projected to increase from 104 seats in 2011 to<br />

114 seats by 2030. Enplaned load factors are projected to increase from<br />

75 percent in 2011 to 80 percent in 2012 and remain relatively constant thereafter.<br />

Narrowbody aircraft are expected to account for an increasing share of passenger<br />

flights as LCCs continue to increase market share at KCI. Legacy carriers will<br />

increasingly use large regional jets as a replacement for small regional jets. Fleet<br />

mix and load factor assumptions result in a 1.0 percent average annual growth rate<br />

for passenger flights at KCI over the forecast period. The change in projected fleet<br />

mix is represented in Figure 1.3-3, Aircraft Fleet Mix.<br />

Figure 1.3-3<br />

AIRCRAFT FLEET MIX<br />

DRAFT<br />

Source:<br />

Landrum & Brown<br />

1.3.4 AIR CARGO<br />

The cargo tonnage forecast is predicated on the assumption that changes to the air<br />

cargo industry and emerging trends for air cargo security will continue.<br />

Additionally, it is assumed that long-term economic growth in the Kansas City MSA<br />

and the broader U.S. economy will increase the demand for the shipment of goods<br />

and services over the forecast period. The air cargo tonnage forecast also reflects<br />

the current global economic outlook from the Boeing, Airbus, and FAA Aerospace<br />

forecasts.<br />

Landrum & Brown Page 8<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Average annual growth of 2.2 percent per year was applied from 2011 to 2030,<br />

resulting in total KCI cargo volumes increasing to 130,817 metric tons in 2030.<br />

Figure 1.3-4, Cargo Tonnage Forecast Results, shows cargo forecast results.<br />

Figure 1.3-4<br />

CARGO TONNAGE FORECAST RESULTS<br />

Source:<br />

Landrum & Brown<br />

DRAFT<br />

In 2011, 86,001 cargo metric tons were handled at KCI. Integrated cargo carriers,<br />

FedEx and UPS, account for 89 percent of total air cargo handled at KCI. A shift to<br />

widebody aircraft such as the A300 and MD11 has occurred at KCI over the past<br />

five years as integrated carriers have shifted away from narrowbody B727 and DC9<br />

aircraft. Figure 1.3-5, 2011 Air Cargo Tonnage by Carrier, depicts the tonnage<br />

splits by carrier.<br />

Figure 1.3-5<br />

2011 AIR CARGO TONNAGE BY CARRIER<br />

Source:<br />

Landrum & Brown<br />

Landrum & Brown Page 9<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

1.3.5 AIRCRAFT OPERATIONS<br />

Aircraft operations are forecast to increase from 141,700 operations in 2011 to<br />

172,611 operations in 2030, which is an average growth of 1.0 percent per year as<br />

seen in Figure 1.3-6, Summary of Aircraft Operations Forecast. Commercial<br />

passenger operations are expected to grow 1.0 percent per year which will drive<br />

growth in aircraft operations at KCI. However, passenger enplanements are<br />

expected to grow 1.9 percent per year, reflecting an expected increase in average<br />

aircraft size and higher average load factors. The other four primary components<br />

of operations - all-cargo, non-commercial air taxi, general aviation, and military -<br />

are expected to experience positive activity growth at KCI over the forecast period.<br />

Figure 1.3-6<br />

SUMMARY OF AIRCRAFT OPERATIONS FORECAST<br />

Source: Landrum & Brown<br />

DRAFT<br />

Landrum & Brown Page 10<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

1.3.6 PEAK ACTIVITY FOR ENPLANEMENTS<br />

Airport traffic demand patterns are subject to seasonal, monthly, daily, and hourly<br />

variations. These variations result in peak periods when the greatest amount of<br />

demand is placed upon facilities required to accommodate passenger and aircraft<br />

movements. Peaking characteristics are critical in the assessment of existing<br />

facilities to determine the ability to accommodate forecast increases in passenger<br />

and operational activity throughout the study period. The objective of developing<br />

peak period forecasts is to provide facility designs that are not under-utilized nor<br />

over-crowded too often.<br />

Table 1.3-2, KCI Peak Period Enplanement Forecast, shows the peak month,<br />

design day, and peak hour ratios used to develop the peak period enplanement<br />

forecasts for KCI. July is the peak month for passenger enplanements at KCI,<br />

accounting for 9.8 percent of annual traffic. The flight schedule for Thursday,<br />

July 14, 2011 was identified as being representative of a typical day of the peak<br />

month activity and analyzed to determine the hourly peaking patterns at KCI.<br />

Departing seats were used as a proxy for enplanements. The flight schedule data<br />

suggested that the peak hour accounts for 11.3 percent of daily passenger<br />

enplanements. It was assumed that the monthly, daily, and peak hour factors<br />

would remain constant over the forecast period. As a result, peak hour<br />

enplanements are forecast to increase from 1,900 enplanements in 2011 to<br />

2,700 enplanements in 2030.<br />

Table 1.3-2<br />

KCI PEAK PERIOD ENPLANEMENT FORECAST<br />

DRAFT<br />

Source:<br />

Landrum & Brown<br />

1.3.7 PEAK ACTIVITY FOR OPERATIONS<br />

Like passenger traffic, the operations peak has historically occurred in July. Design<br />

day factors were developed to provide activity that represented a typical day in the<br />

peak month. For the passenger activity, Official Airline Guide (OAG) flight<br />

schedules were used to determine peak hour operations. For cargo, general<br />

aviation, air taxi, and military, radar data was used to determine design day and<br />

peak hour factors. Table 1.3-3, KCI Peak Period Aircraft Operations<br />

Forecast, presents the peak month, design day, and peak hour ratios used to<br />

develop the peak period aircraft operations forecast for each of the key operation<br />

segments at KCI: commercial passenger, air cargo, general aviation including noncommercial<br />

air taxi, and military.<br />

Landrum & Brown Page 11<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 1.3-3<br />

KCI PEAK PERIOD AIRCRAFT OPERATIONS FORECAST<br />

DRAFT<br />

Source:<br />

Landrum & Brown<br />

Landrum & Brown Page 12<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

1.4 Benchmarking<br />

In order to better understand and identify the future needs of KCI, a Benchmarking<br />

<strong>Study</strong> was performed that compared the existing facilities at KCI to nine<br />

comparable domestic airports. The following airports were used for comparison in<br />

the study:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Cincinnati / Northern Kentucky International Airport (CVG)<br />

Indianapolis International Airport (IND)<br />

San Jose International Airport (SJC)<br />

Memphis International Airport (MEM)<br />

Sacramento International Airport (SMF)<br />

Austin-Bergstrom International Airport (AUS)<br />

Cleveland Hopkins International Airport (CLE)<br />

Raleigh-Durham International Airport (RDU)<br />

Kansas City International Airport (KCI)<br />

Lambert – St. Louis International Airport (STL)<br />

The parameters compared in the study included:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Million Annual Passengers (MAP)<br />

Number of gates<br />

Number of terminals<br />

Number of Security Screening Checkpoints (SSCP)<br />

<strong>Terminal</strong> square feet<br />

Concession square feet<br />

DRAFT<br />

Number of parking spaces, by type<br />

Figure 1.4-1, Existing Facilities At Comparable Domestic Airports,<br />

summarizes the data collected for each airport and used as the basis for the results<br />

from the Benchmarking <strong>Study</strong>. Also included in the table are images of the airfield<br />

layout and terminal layout at each airport. The results of the study were used to<br />

assist in the planning and design of the size and location of the New <strong>Terminal</strong> and<br />

associated facilities, such as on- and off-airport parking, gates, security, and<br />

concessions, to name a few.<br />

Landrum & Brown Page 13<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

MAP Level 6.9 7.4 8.3 8.6 8.7 9.0 9.0 9.1 10.4 12.5<br />

Gates 36 40 28 79 32 25 62 45 66 88<br />

<strong>Terminal</strong>s 2 1 2 3 2 1 1 2 3 2<br />

Number of SSCP 2 2 2 3 3 3 3 2 13 3<br />

<strong>Terminal</strong> SQFT 2,000,000 1,200,000 1,050,000 1,300,000 740,000 600,000 1,073,357 550,000 1,100,000 1,500,000<br />

Concession SQFT 109,200 59,738 12,784 68,046 42,885 37,976 40,024 56,465 61,186 71,979<br />

Parking - Short/Economy/Valet 7,750 13,918 2,358 870 9,890 4,212 5,170 6,087 21,555 4,097<br />

Parking - Long 6,000 4,403 3,991 3,550 10,059 5,923 2,746 9,925 1,750 4,672<br />

Parking - Total 12,000 18,268 6,349 4,425 19,949 10,135 7,916 18,763 23,305 8,769<br />

Landrum & Brown Page 14<br />

April 2013<br />

Figure 1.4-1<br />

EXISTING FACILITIES AT COMPARABLE DOMESTIC AIRPORTS<br />

Totals<br />

Airport Name CVG IND SJC MEM SMF AUS CLE RDU KCI STL<br />

Airfield Layout<br />

DRAFT<br />

<strong>Terminal</strong> Layout<br />

Source: Landrum & Brown


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

2. AIRFIELD REQUIREMENTS<br />

The proposed New <strong>Terminal</strong> is to be constructed at the existing <strong>Terminal</strong> A location.<br />

This section includes discussions of the following:<br />

<br />

<br />

<br />

<br />

<br />

<br />

Design Aircraft<br />

Aircraft Gates and Passenger Loading Bridges<br />

Service Roads<br />

Airfield Security<br />

Aircraft Deicing<br />

Fueling<br />

2.1 Design Aircraft<br />

When planning changes and/or improvements to an airport, a “design aircraft” must<br />

be identified that represents the size of aircraft typically using the airport, based on<br />

information from the airport and the airlines that use the airport. There are three<br />

parameters used in the selection of a design aircraft at KCI that include: Aircraft<br />

Approach Category (AAC), Airplane Design Group (ADG), and Taxiway Design<br />

Group (TDG). AAC is used for airspace planning, and approach and departure<br />

paths. For apron, taxilane, and taxiway design, the ADG and TDG define the design<br />

parameters for horizontal and vertical alignments.<br />

AAC is based on a speed of 1.3 times the stall speed in the landing configuration at<br />

maximum gross landing weight. The categories are summarized in Table 2.1-1,<br />

Aircraft Approach Categories, as defined in 14 Code of Federal Regulations<br />

(CFR) Part 97.<br />

Table 2.1-1<br />

AIRCRAFT APPROACH CATEGORIES<br />

Category<br />

A<br />

B<br />

C<br />

D<br />

E<br />

Speed<br />

≤ 91 knots<br />

≥ 91 knots and ≤ 121 knots<br />

≥ 121 knots and ≤ 141 knots<br />

≥ 141 knots and ≤ 166 knots<br />

≥ 166 knots<br />

Source: FAA AC 5300-13A, Table 1-1<br />

DRAFT<br />

ADGs are based on wingspan and tail height that determine separation<br />

standards. Table 2.1-2, Airplane Design Groups (ADG), summarizes the<br />

dimensions for each classification of ADGs, as defined in FAA Advisory Circular (AC),<br />

150/5300-13A, Airport Design. Based on information from the Airport and airlines,<br />

the typical airplane using KCI is an ADG III. Therefore, the design aircraft used for<br />

planning at KCI is an ADG III. Table 2.1-3, Design Aircraft, describes aircraft<br />

types and the percentage used at KCI.<br />

Landrum & Brown Page 15<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 2.1-2<br />

AIRPLANE DESIGN GROUPS (ADG)<br />

Group # Tail Height (ft) Wingspan (ft)<br />

I < 20ʹ < 49ʹ<br />

II 20ʹ - < 30ʹ 49ʹ - < 79ʹ<br />

III 30ʹ - < 45ʹ 79ʹ - < 118ʹ<br />

IV 45ʹ - < 60ʹ 118ʹ - < 171ʹ<br />

V 60ʹ - < 66ʹ 171ʹ - < 214ʹ<br />

VI 66ʹ - < 80ʹ 214ʹ - < 262ʹ<br />

Source: FAA Advisory Circular (AC), 150/5300-13A, Table 1.2.<br />

Table 2.1-3<br />

DESIGN AIRCRAFT<br />

DRAFT<br />

Aircraft Type ADG TDG Wingspan (ft) Length (ft) Percent of Operations<br />

Widebody<br />

B-767-400 IV 5<br />

170.3<br />

201.4<br />

>1%<br />

B787-8<br />

V 5<br />

197.3<br />

186.1<br />

Narrowbody<br />

58%<br />

B-7373-900ER III 3 117.5 138.2<br />

Large Regional<br />

CRJ-900 III<br />

81.5<br />

119.3<br />

29%<br />

Embraer 190 III<br />

94.3<br />

118.9<br />

Small Regional<br />

CRJ-200 II<br />

69.6<br />

87.8<br />

11%<br />

Embraer 145 II<br />

65.7<br />

98.0<br />

Source: HNTB<br />

TDGs are based on main gear width and cockpit-to-main gear distance, and<br />

determine taxiway width and fillet design (See Figure 2.1-1, Taxiway Design<br />

Groups). Although wingspan typically determines taxiway/taxilane to<br />

taxiway/taxilane separations, in some instances, the separation is determined by<br />

TDG due to turning requirements. At least one Taxiway route should meet the<br />

requirements of the most demanding TDG, not only to the design aircraft TDG<br />

requirements.<br />

Landrum & Brown Page 16<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 2.1-1<br />

TAXIWAY DESIGN GROUPS<br />

Source:<br />

FAA AC 150/5300-13A<br />

2.2 Aircraft Gates and Loading Bridge Requirements<br />

2.2.1 METHODOLOGY<br />

One of the most reliable methodologies for projecting the number of aircraft<br />

parking positions at a terminal facility involves analyzing the projected peak hour<br />

aircraft operations in the form of an aircraft ramp chart. The ramp chart attempts<br />

to optimally schedule aircraft operations at all available terminal gate parking<br />

positions or at a Remain Overnight (RON) parking positions. The ramp chart<br />

methodology assumes an average ground occupancy time at the gate for the<br />

various types of aircraft to be serviced combined with a minimum time between<br />

when that aircraft leaves and when another aircraft can arrive at the same aircraft<br />

parking position. This methodology assumes that the airlines will attempt to<br />

maximize aircraft turns during its peak periods of operations within these base<br />

parameters of aircraft servicing times and a reasonable time allowance between<br />

turns referred inter gate time<br />

DRAFT<br />

The Ramp Chart relies heavily on the future flight schedules that are based on the<br />

existing July 14, 2011 flight schedule. The future flight schedules for 2025 and<br />

2030 are developed by growing the existing arrival and departure patterns of<br />

aircraft flights taking into account their seat capacities based on the future aircraft<br />

fleet mix needed to reach the future passenger and aircraft operation volumes.<br />

The peak hour aircraft operations used in preparing the ramp chart are shown in<br />

Section 1.3.7, Peak Activity for Operations; Table 1.3-3, KCI Peak Period Aircraft<br />

Operations Forecast; and the peak month, average day, and peak hour passengers<br />

are provided in Table 1.3-2, KCI Peak Period Enplanement Forecast.<br />

Landrum & Brown Page 17<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Aircraft ramp charts for the New <strong>Terminal</strong> were developed using the 2025 and 2030<br />

design day flight schedules. Ramp charts were used to determine the number and<br />

size of aircraft parking positions both at the terminal as a contact gate or as a<br />

remote aircraft stand. Contact gates are serviced by a passenger loading bridge<br />

that connects the aircraft to the terminal holdroom while a remote aircraft is<br />

serviced by a busing connection that moves passengers to and from the terminal<br />

holdroom.<br />

The facility requirements analysis in this <strong>Study</strong> focused on using a combination of<br />

Preferential and Common Use peak passenger levels for the gate requirements.<br />

Preferential Use refers to those portions of the terminal, concourse, aircraft loading<br />

bridges, aircraft parking positions, apron, etc., that a single airline has priority over<br />

other airline users. Conversely, Common Use refers to those same facilities of the<br />

terminal, concourses and apron that are not assigned by lease to a single airline,<br />

but are used in common by multiple airlines. These areas include common use<br />

ticket counters, gates, and associated support space not otherwise held under an<br />

exclusive or preferential airline lease agreement with the Airport.<br />

The specific use assumptions in the development of facility requirements for the<br />

KCI Airport were that the three primary market share airlines would be assumed to<br />

be preferential users and that all other airlines would be treated as common use<br />

carriers. It should be noted that if all airlines at KCI were assumed as common use<br />

carriers the holdroom and gate areas could be reduced as a result of a higher<br />

utilization factor associated with shared facilities.<br />

Other functional projections are determined their relationship to the number and<br />

type of aircraft or the number of gates/seats serving the terminal area.<br />

Standardization of aircraft utilization and apron requirements are developed by<br />

using the Narrowbody Equivalent Gate (NBEG) index. This index converts the gate<br />

requirements of diverse aircraft types, from commuter aircraft to new large aircraft,<br />

so that they are equivalent to the apron capacity of a narrowbody aircraft gate.<br />

The amount of space or linear frontage each aircraft requires is based on the<br />

maximum wingspan of aircraft in its respective Aircraft Design Group (ADG).<br />

Aircraft are classified according to FAA Taxiway Design Groups as shown in<br />

Table 2.2-1, Narrowbody Equivalent Gate (NBEG) Index.<br />

DRAFT<br />

Landrum & Brown Page 18<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 2.2-1<br />

NARROWBODY EQUIVALENT GATE (NBEG) INDEX<br />

FAA TAXIWAY DESIGN<br />

GROUP<br />

MAXIMUM<br />

WINGSPAN<br />

TYPICAL AIRCRAFT<br />

NBEG<br />

INDEX<br />

I Small Commuter 49’ Cessna 0.4<br />

II Medium Commuter 79’ SF340/CRJ 0.7<br />

III<br />

Narrowbody/Large<br />

Commuter<br />

118’ A320/B737/MD-80/ATR 1.0<br />

IIIa B757 125’ B757 1.1<br />

IV Widebody 171’ DC-10/MD-11/B767 1.5<br />

V Jumbo 214’ B747/A330,340/B777/B787 1.9<br />

VI NLA 262’ A380 2.3<br />

Source:<br />

FAA AC 150/5300-13 and Hirsh & Associates<br />

Physical location and proximity to the gate are important factors to consider when<br />

estimating the spatial requirements of gate holdrooms. The available holdroom<br />

area needs to be in close proximity to the gate being used. There is an advantage<br />

to having a configuration that locates holdroom seating in an open and contiguous<br />

manner since it allows the potential overflow of one holdroom into the adjacent<br />

holdroom, particularly if the adjacent holdroom does not have passengers at that<br />

moment awaiting a near term aircraft departure. These factors were taken into<br />

consideration when evaluating the future KCI requirements. The majority of the<br />

future KCI aircraft fleet mix is envisioned as narrowbody aircraft, however, select<br />

aircraft contact positions have the flexibility to accommodate widebody aircraft.<br />

For these infrequent occurrences it is assumed that the additional holdroom seating<br />

capacity needed for these infrequent widebody operations will be accommodated<br />

with a shared holdroom philosophy and nearby food and beverage seating capacity.<br />

DRAFT<br />

2.2.2 CURRENT CONDITIONS<br />

Currently, KCI operates out of its three separate terminals. The original terminals<br />

opened in 1972 with the capability of 30 gate doors on each terminal for a total of<br />

90 loading positions. The signage at the gates still reflects this original numbering<br />

system from 1 through 90. In actuality, KCI is only using 30 gates today out of a<br />

total of 62 available gates from all three terminals. There are 66 aircraft parking<br />

positions in total immediately adjacent to the three terminals but four of these<br />

positions are loaded from ground level. KCI has one international gate located at<br />

<strong>Terminal</strong> C. Narrowbody aircraft were 56 percent of passenger operations in 2012<br />

with less than one percent B757s, and the remaining 43 percent regional jets.<br />

The use of multiple terminals has become inefficient due to the number of unused<br />

gates (32 gates).<br />

Holdroom space within the KCI terminals is limited in size due to narrow overall<br />

depth of all three terminals at roughly 75 feet. The narrow depth comes from the<br />

original narrow curvilinear design of the Drive-to-Gate concept which attempted to<br />

minimize the walking distances between the vehicle curb and the gates.<br />

Landrum & Brown Page 19<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

This original design did not anticipate the need for passenger and hand luggage<br />

security screening. Today’s retrofit of the terminals now divides this limited 75 feet<br />

into separate non-secure landside and secure airside operations. In order to<br />

minimize the number of Transportation Security Administration’s (TSA) mandated<br />

Security Screen Checkpoints (SSCP), holdrooms were grouped together in small<br />

clusters and then each cluster was equipped with its own SSCP. This retrofit is<br />

cumbersome for several reasons:<br />

<br />

<br />

Separate secured holdroom clusters still generate the need for 14 SSCPs.<br />

Passengers are required to pass back through the SSCP after leaving the<br />

holdroom cluster.<br />

Due to the limited space in the holdroom clusters, the retrofitted<br />

configuration trades off holdroom space for secure restrooms and limited<br />

concessions.<br />

This tradeoff results in inadequate holdroom space, severely limited restroom<br />

facilities, and substandard concession offering inside the cluster resulting in a<br />

low LOS for passengers and a restricted ability to generate concession<br />

revenues for the Airport.<br />

2.2.3 FUTURE AIRCRAFT PARKING POSITIONS<br />

Domestic Service Requirements<br />

Based on the 2030 forecast, 41 contact gate aircraft parking positions are needed<br />

to accommodate the anticipated peak hour operations demands. For 2025, a total<br />

of 37 contact gate parking positions are needed. The future fleet mix envisioned<br />

for 2030 is not anticipated to vary significantly from the 2013 fleet which is<br />

dominated by narrowbody and smaller wingspan aircraft which was over 99 percent<br />

in 2012. As a consequence, all aircraft parking positions are planned to<br />

accommodate a minimum of an ADG III aircraft to allow for gate use flexibility.<br />

The maximum ADG III aircraft (B737-800/900 aircraft with a wingspan of 117 feet<br />

5 inches) was assumed for gate planning along with an associated wingtip clearance<br />

of 25 feet.<br />

DRAFT<br />

International Service Requirements<br />

The exception to having all narrowbody contact gates at KCI is the international<br />

arrivals capable gates. In the New <strong>Terminal</strong>, four gates will provide access to a<br />

sterile corridor leading to the Customs and Border Protection facilities. These four<br />

international-arrivals capable contact gates will be configured with multiple doors to<br />

allow for a “swing” capability between either a domestic or international operation.<br />

Two of these gate positions will also be configured to allow as large as an ADG V<br />

aircraft (B787-800) and will be paired with adjacent narrowbody aircraft positions<br />

to form a Multi-Aircraft Ramp System (MARS) gate. This will allow two narrowbody<br />

aircraft parking positions to accommodate a single widebody aircraft in the same<br />

apron location. Providing “swing” gates provides the Airport with a facility that can<br />

grow international air service to the passenger capacity of four simultaneous<br />

narrowbody aircraft or two widebody aircraft. The Federal Inspection Services (FIS)<br />

facilities were sized in relationship to this theoretical demand.<br />

Landrum & Brown Page 20<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Remain Overnight (RON) Requirements<br />

Based on the 2030 forecast, 31 RON aircraft parking positions will be needed to<br />

stage access to the 41 contact gates at the New <strong>Terminal</strong> during the morning peak.<br />

For 2025 the number of RONs drops to 28. RON operations will require aircraft<br />

movement to an open contact gate for passenger loading and unloading<br />

Summary of Future Aircraft Parking Positions<br />

As shown in Table 2.2-2, Summary of Future Aircraft Parking Positions, a<br />

total of 41 contact gates and 31 RON aircraft parking positions will be necessary at<br />

KCI to handle the forecast 14 Million Annual Passengers (MAP) in 2030. All contact<br />

gates need to be capable of handling the majority of narrowbody aircraft types<br />

designated by the 2030 forecast in order to maximize flexibility of a common use<br />

operation. In 2025 a total of 37 contact gate parking positions and 28 RON parking<br />

positions are needed. Four out of the initial 37 gates will need to be capable of<br />

accommodating international operations. The passenger loading bridges on these<br />

four international-capable aircraft parking positions will also be configured to allow<br />

two of the gates to be used by a potential ADG V aircraft, the largest of which is<br />

anticipated to be a B787-800 aircraft.<br />

Table 2.2-2<br />

SUMMARY OF FUTURE AIRCRAFT PARKING POSITIONS<br />

Aircraft Parking Positions<br />

Forecast Year<br />

2025 2030<br />

<strong>Terminal</strong> Contact Gates 37 41<br />

Remote Overnight Stands (RONs) 28 31<br />

Source:<br />

Landrum & Brown<br />

DRAFT<br />

2.2.4 PASSENGER LOADING BRIDGE REQUIREMENTS<br />

The pathway to and from the contact gate door to the parked aircraft must meet<br />

Americans with Disabilities Act (ADA) requirements. This means that any fixed<br />

section and the passenger loading bridge at any of the contact gate positions may<br />

not exceed a 1-in-12 (8.33 percent) slope along its pathway. With ADG III aircraft<br />

(B737s) and smaller as the predominant aircraft through 2030, a finished floor<br />

height for gates of approximately 13 feet 6 inches above the apron has been<br />

assumed in order to minimize the length of the loading bridge required to reach the<br />

lowest and highest door sill height of the primary passenger loading of the aircraft<br />

types serving the Airport. Door sill heights for forecast aircraft range from five feet<br />

(CRJ-200) to 15 feet 2 inches (B787-800). Currently, used Jetbridge models,<br />

predominantly the A3-58/110, would be able to accommodate these sill heights<br />

with a maximum extension of 102 feet. Currently, 30 contact gates are used but<br />

by 2025 37 gates will be required and 41 contact gates are projected for 2030, all<br />

of which will require passenger loading bridges. Currently, there are no bussing<br />

operations to remote aircraft parking positions for commercial passenger operations<br />

and none are anticipated over the forecast horizon.<br />

Landrum & Brown Page 21<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

2.3 Apron Service Road<br />

Designated service roads are provided on or near aprons to restrict service vehicle<br />

movements to a confined area(s) where the pilot is familiar with seeing vehicle<br />

activity. Proper layout of service roads on an airfield contributes to airport safety<br />

and the reduction in runway incursions.<br />

Factors to consider when designing service roads include items such as<br />

current/future vehicle and ground-service equipment movement, space, bearing<br />

strength, height clearance, separation standards from runways/taxiways, and<br />

access. The width of service roads depends on the projected traffic levels, and the<br />

widest equipment expected to use the service road, etc.<br />

A proposed service road, for vehicles permitted to operate within the terminal area<br />

such as ground support equipment and other vehicles, will be located behind the<br />

aircraft parking positions and outside the taxilane object free areas 1 for access to<br />

aircraft. The service road should be designed to avoid crossing runways and<br />

taxiways/taxilanes to the extent possible. However, when a crossing is necessary,<br />

proper marking must be in place to ensure vehicles stop or yield to aircraft.<br />

2.4 Airside Security Requirements<br />

Airfield security will be maintained throughout the construction of the New <strong>Terminal</strong><br />

and continue when the new facilities are in operation. Security screening of<br />

construction personnel to meet FAA, Department of Homeland Security (DHS), and<br />

KCAD requirements will continue to be implemented. KCAD will develop a staffing<br />

plan to support the increased security screening of construction personnel for the<br />

program.<br />

DRAFT<br />

Where possible, facilities that require separate landside and airside access should<br />

be constructed along the Airport perimeter fence line to reduce unnecessary access<br />

to the airfield and potential security breaches. Temporary security fencing can be<br />

installed around the proposed terminal construction area during construction<br />

outside the AOA. Maximizing the amount of construction outside the AOA would<br />

result in an additional benefit: more personnel eligible to perform construction.<br />

Permanent AOA security fence and gates will be composed of chain link fence<br />

materials with barbed wire overguard to meet FAA and KCAD requirements. Chain<br />

link fences will be a minimum of eight feet tall with a three-strand barbed wire<br />

overguard. Any fence and gate modifications will interface with the Airport’s<br />

existing access control and monitoring system.<br />

1<br />

A two dimensional ground area surrounding taxiways and taxilanes which is clear of objects except<br />

for Navigation Aids (NAVAIDs) and objects whose location is fixed by function.<br />

Landrum & Brown Page 22<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

2.5 Aircraft Deicing<br />

Currently at KCI, aircraft are pushed back from the gate to deice. The glycol<br />

contaminated runoff is collected in trench drains along the perimeter of each<br />

terminal apron. Based on the apron pavement grades, the trench drains collect<br />

runoff from a significant portion of the apron as well as the gate deicing areas.<br />

Collection from a large area dilutes the concentration of the glycol-contaminated<br />

runoff and also increases the capacity need of the retention basins used for initial<br />

storage of glycol-contaminated runoff.<br />

KCI operates in accordance with the requirements of a National Pollutant Discharge<br />

Elimination System (NPDES) permit issued by the Missouri Department of Natural<br />

Resources (MDNR). The NPDES permit imposes controls intended to ensure that<br />

stormwater discharges at KCI meet applicable water quality standards. Conditions<br />

of the permit are implemented at the Airport through a Storm Water Pollution<br />

Prevention Plan (SWPPP). Under the terms of the permit, the Airport is responsible<br />

to the State of Missouri for all industrial and stormwater discharges originating on<br />

the property with the exception of the former American Airline Overhaul Base.<br />

KCAD is currently in negotiations with the MDNR regarding the outfall permit.<br />

The MDNR permit is a numerical limit-based permit focused on Biochemical Oxygen<br />

demand (BOD), Chemical Oxygen demand (COD), Total Suspended Solids (TSS),<br />

Oil and Grease (O/G), and Total Petroleum Hydrocarbons (TPH). Table 2.5-1,<br />

MDNR Operating Requirements, summarizes the current KCI MDNR Operating<br />

Permit.<br />

DRAFT<br />

In an effort to collect glycol-impacted stormwater during deicing operations at KCI,<br />

KCAD has installed an underground drainage system that directs<br />

glycol-contaminated runoff from the existing terminal aprons to a 2.4-million<br />

gallon, concrete lined retention basin. At this basin the glycol concentrations are<br />

measured to determine how the runoff should be discharged off of airport property.<br />

Landrum & Brown Page 23<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 2.5-1<br />

MDNR OPERATING REQUIREMENTS<br />

Effluent Parameter<br />

Unit<br />

Final Effluent<br />

Limitations<br />

Daily<br />

Max.<br />

Monthly<br />

Average<br />

Monitoring Requirements<br />

Monitoring<br />

Frequency<br />

Sample<br />

Type<br />

Flow MGD * * once/month 24 hr. est.<br />

Precipitation Inches * * once/month 24 hr. est.<br />

BOD mg/L 45 30 once/month grab<br />

COD mg/L 120 90 once/month grab<br />

TSS mg/L 100 50 once/month grab<br />

TPH mg/L 15 10 once/month grab<br />

O/G mg/L 15 10 once/month grab<br />

pH-Units SU ** ** once/month grab<br />

Total BETX mg/L 0.75 0.75 once/month grab<br />

Benzene mg/L 0.07 0.07 once/month grab<br />

Methyl Tertiary Butyl<br />

Ether (MTBE)<br />

mg/L * * once/month grab<br />

Total Glycols mg/L * * once/month*** grab<br />

Ethylene Glycol mg/L * * once/month*** grab<br />

Propylene Glycol mg/L * * once/month*** grab<br />

Notes: * Monitoring Requirement Only<br />

** pH is measured in pH units and is not to be averaged.<br />

*** The pH is limited to the range of 6.0 9.0 pH units.<br />

Source: HNTB Corporation<br />

DRAFT<br />

Low concentrations of glycol are discharged into a pond east of the retention basins<br />

and ultimately into the Berlin Reservoir. At the north end of the reservoir, the<br />

overflow discharges into a tributary of Todd Creek. A monitoring station is located<br />

on the north end of the reservoir to measure compliance to KCI’s MDNR permit.<br />

Medium concentrations are gravity fed through a series of pipes to the Todd Creek<br />

wastewater treatment facility. Highly concentrated runoff is pumped from the<br />

retention basins into trucks and hauled directly to the Todd Creek wastewater<br />

treatment facility.<br />

The goal of the proposed aircraft deicing operations is to reduce the amount of<br />

surface area collecting glycol-contaminated runoff and increase the concentration of<br />

deicing fluids in the runoff. The higher concentrations will allow KCAD to develop a<br />

program that has one type of discharge method. Methods for achieving the goals<br />

are discussed in the following paragraphs.<br />

Landrum & Brown Page 24<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

2.5.1 CENTRALIZED DEICING OPERATIONS<br />

A centralized deicing facility is an aircraft deicing facility located at the terminal<br />

apron or along taxiways serving departure runways. Gate deicing operations will<br />

not be permitted at the New <strong>Terminal</strong> but centralized deicing locations will be<br />

utilized that will reduce the area to collect glycol-contaminated runoff.<br />

All centralized deicing facilities will meet the requirements of FAA Advisory Circular<br />

(AC) 150/5300-14B, Design of Aircraft Deicing Facilities.<br />

The design of deicing facilities should, to the extent practicable, meet the needs of<br />

air carriers, as outlined in FAA-approved aircraft ground deicing/anti-icing<br />

programs, and all other aviation community users. A key element in this effort is<br />

designing a facility that is efficient and offers users operational flexibility.<br />

Coordination of an airport owner’s Snow and Ice Control Plan and user’s ground<br />

deicing/anti-icing programs, with input from the FAA, will ensure that icing<br />

conditions affecting the safety of flight are better met.<br />

The forecasted peak hour of aircraft departures is from 06:05 to 07:05, with<br />

thirty-four departures. To determine the total number of deicing pads necessary to<br />

accommodate the peak hour traffic, it is necessary to understand the aircraft<br />

deicing process. Through discussions with aircraft deicing experts and analysis of<br />

deicing pad throughput at commercial service airports, it was determined that an<br />

average time for an aircraft to enter a deicing pad, complete the deicing process,<br />

and exit is 20 minutes.<br />

Based on the 20-minute deicing pad occupancy duration, three aircraft can be<br />

deiced per hour per pad. With a peak hour of thirty-four departures, twelve deicing<br />

pads will accommodate the peak hour. The proposed aircraft utilizing the deicing<br />

pads is summarized in Table 2.5-2, Projected Aircraft Fleet Mix, and the last<br />

column details the number of deicing pads required to accommodate each aircraft<br />

type.<br />

Table 2.5-2<br />

PROJECTED AIRCRAFT FLEET MIX<br />

Aircraft Type ADG Wingspan (ft) Length (ft)<br />

Wide Body<br />

B-767-400<br />

B787-8<br />

Narrow Body<br />

B-737-900ER<br />

Large Regional<br />

CRJ-900<br />

Embraer 190<br />

Small Regional<br />

CRJ-200<br />

Embraer 145<br />

DRAFT<br />

IV<br />

V<br />

170.3<br />

197.3<br />

201.4<br />

186.1<br />

Percent of<br />

Operations<br />

Necessary<br />

Deicing Pads<br />

>1% 1<br />

III 117.5 138.2 58% 8<br />

III<br />

III<br />

II<br />

II<br />

81.5<br />

94.3<br />

69.6<br />

65.7<br />

119.3<br />

118.9<br />

87.8<br />

98.0<br />

29% 3<br />

11% 1<br />

Source:<br />

HNTB Corporation<br />

Landrum & Brown Page 25<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

2.5.2 DEICING PAD SIZE REQUIREMENTS<br />

The size of an aircraft deicing pad is determined by the aircraft parking area and<br />

the maneuvering area for mobile deicing vehicles. The aircraft parking area is the<br />

inner area used for parking aircraft to receive deicing/anti-icing treatment.<br />

The width of the parking area equals the upper wingspan of the most demanding<br />

aircraft ADG using the deicing pad. The length of the parking area equals the<br />

fuselage length of the most demanding aircraft using the deicing pad.<br />

Widebody deicing pads will be sized based on the B787-8 aircraft dimensions.<br />

The 11 deicing pads to serve ADG III aircraft will be sized based on the B737-<br />

900ER aircraft. Deicing pads for the small regional jets (ADG II) will be sized based<br />

on the CRJ-200 aircraft.<br />

The Vehicle Maneuvering Area (VMA) for mobile deicing vehicles is the outer area<br />

that provides the “vehicle lane width” necessary for two or more mobile deicing<br />

vehicles to satisfactorily perform simultaneous, and complete left- and right-side<br />

uniform fluid distribution techniques for removing deposits of frost, ice, slush, and<br />

snow from aircraft surfaces and for anti-icing operations. The vehicle lane width<br />

must be 12.5 feet (3.8 m) and be mutually exclusive of any adjacent deicing pad.<br />

Adjacent deicing pads will be separated by a ten-foot wide vehicle safety zone<br />

(VSZ). A VSZ will also be located on the outboard edge of any outer deicing pad.<br />

Centralized deicing facilities will be located within the non-movement area in close<br />

proximity to the adjacent taxiway network. Deicing pads will be sized to<br />

accommodate the critical aircraft detailed previously. Table 2.5-3, Deicing Pad<br />

Dimensional <strong>Criteria</strong>, summarizes the deicing pad separation requirements<br />

defined in AC 150/5340-14A, Design of Aircraft Deicing Facilities.<br />

Table 2.5-3<br />

DEICING PAD DIMENSIONAL CRITERIA<br />

ADG<br />

DRAFT<br />

Outer Deicing Pads<br />

Taxi Centerline to Edge of Vehicle<br />

Safety Zone (VSZ)<br />

Interior Deicing Pads<br />

Taxi Centerline to Taxi Centerline<br />

V 138 ft. 286 ft.<br />

IV 112.5 ft. 235 ft.<br />

III 81 ft. 172 ft.<br />

II 57.5 ft. 125 ft.<br />

Source:<br />

FAA AC 150/5340-1B<br />

Aircraft deicing pads for off-gate facilities will have parallel taxiway centerlines to<br />

permit flow-through deicing operations. Separation criteria provided in Table 2.5-3<br />

takes into account the need for individual deicing pads to provide adequate wingtip<br />

clearance, sufficient maneuvering area around the aircraft to allow simultaneous<br />

treatment by two or more mobile deicing vehicles, and sufficient non-overlapping<br />

space for the VSZ between adjacent deicing pads and for outer deicing pads.<br />

Landrum & Brown Page 26<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

2.5.3 DEICING SUPPORT FACILITIES<br />

The proposed centralized deicing pad will require an efficient support network for<br />

chemical off-loading from transport vehicles and loading to deicing trucks.<br />

These facilities should provide close proximity to the centralized deicing pads to<br />

maintain efficient deicing operations. Described below are the required de-icing<br />

support facilities.<br />

Nighttime/Low-Visibility Lighting: All facilities will require permanent nighttime<br />

lighting structures or portable nighttime lighting systems are available so ground<br />

crews have the necessary illumination for deicing/anti-icing operations and<br />

pre-takeoff inspections during night or low-visibility conditions. One portable<br />

alternative is mobile deicing vehicles with modified lights that provide sufficient<br />

illumination for deicing/anti-icing treatments and pre-takeoff inspections during<br />

night or low visibility. AC 150/5360-13, <strong>Planning</strong> and Design Guidelines for Airport<br />

<strong>Terminal</strong> Facilities, Table 4-1, provides general lighting requirements for<br />

apron-related functions. The height of lighting poles must be in accordance with<br />

AC 150/5300-13, Object Clearing <strong>Criteria</strong>. Permanent nighttime lights should be<br />

aimed and shielded to avoid glare to pilots and the Air Traffic Control Tower (ATCT)<br />

line-of-sight without reducing the illumination of critical areas.<br />

Electronic Message Boards: The use of electronic message boards (EMBs) at<br />

off-gate deicing facilities by the service provider have increased the overall<br />

efficiency of deicing aircraft and improved the transfer of information between flight<br />

crews and service providers. In general, the primary purpose for installing EMBs is<br />

to: (1) reduce verbal communication between all involved parties; (2) provide<br />

flight crews with clear, concise information; (3) improve deicing pad operational<br />

safety and efficiency; and (4) reduce ground congestion by removing personnel and<br />

equipment from the deicing pad area after completing deicing/anti-icing operations.<br />

If EMBs are installed, they should be installed in accordance with SAE AS 5635,<br />

Message Boards (Deicing Facilities). The SAE aerospace standard defines the<br />

minimum content and appearance of the electronic display, functional capabilities,<br />

design requirements, and inspection and testing requirements for EMBs.<br />

One acceptable location for EMBs is within the VSZ.<br />

DRAFT<br />

Administrative Building: An administrative building is necessary to support the<br />

deicing operations that can include administrative areas, training rooms, and break<br />

areas for the deicing vehicle operators.<br />

Maintenance Building: A maintenance building is necessary for maintenance of the<br />

deicing vehicles that will include ample service bays. The building will also need to<br />

provide parking for the deicing vehicles.<br />

Loading Areas: A location for deicing vehicles to be loaded with glycol and water.<br />

Glycol Storage Tanks: Storage tanks are necessary to support the glycol loading<br />

and blending operations. The tanks need to be accessed from the landside to<br />

support delivery operations. To protect the performance characteristics of deicing<br />

fluids from degradation, storage tanks and fluid transfer systems installed at<br />

Landrum & Brown Page 27<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

deicing facilities must be designed in accordance with the fluid manufacturer’s<br />

recommendations. Fluid transfer systems must be dedicated to the specific fluid<br />

being handled to prevent the inadvertent mixing of fluids of different types or<br />

different manufactures.<br />

Access Road: A dedicated access road from the deicing pads to the truck loading<br />

area and maintenance building is necessary for the de-icing vehicle use.<br />

Employee Parking: An employee parking lot, outside the AOA fence, is needed for<br />

administration, maintenance, and deicing service operation employees.<br />

2.5.4 DEICING COLLECTION SYSTEM REQUIREMENTS<br />

Collection of glycol-contaminated runoff begins with reducing the application area of<br />

deicing fluids, grading the application area to collect the entirety of the deicing<br />

pad(s) runoff, and incorporating collection areas and pipe networks to convey the<br />

contaminated runoff to a retention facility for ultimate treatment or disposal.<br />

Pavement: The pavement must be either concrete or asphalt and designed for the<br />

aircraft fleet mix. The pavement should be grooved to assist in channeling deicing<br />

fluids for collection and to provide aircraft and personnel better traction.<br />

Apron grades and adjacent surface gradients are a maximum of one percent in<br />

accordance with AC 150/5300-13, Airport Design. Apron areas should direct flows<br />

away from deicing pad centerlines, fixed-fluid applicators, vehicle safety zones, and<br />

crew shelter. If interior covered drains are used, they must not create a hazard to<br />

aircraft and personnel.<br />

DRAFT<br />

The perimeter of the deicing pad must extend beyond the aircraft so no aircraft<br />

surface being deiced extends beyond the perimeter.<br />

Collection System: Diversion manholes will be installed within or immediately<br />

adjacent to the deicing pad, which will divert seasonal glycol runoff to the glycol<br />

collection system during the deicing season. Throughout the remainder of the year,<br />

valves within the diversion manholes can be adjusted to direct the stormwater<br />

runoff collected within the deicing pads to the stormwater collection system.<br />

Additionally, the valves within the diversion manholes will be manufactured of<br />

materials that prevent accelerated corrosion due to the high concentration of<br />

glycols.<br />

Area inlets and the diversion manholes need to be constructed of materials that are<br />

not susceptible to damage from the deicing materials. Concrete structures may<br />

require a special treatment to prevent the glycols from reacting with the cement<br />

materials and degrading the integrity of the structures. All pipes installed to<br />

convey glycol-contaminated runoff will be manufactured of High-density<br />

polyethylene (HDPE) or a similar material that cannot be damaged by the deicing<br />

materials.<br />

Landrum & Brown Page 28<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Storage: Currently, glycol-contaminated runoff from the terminal apron is initially<br />

discharged into retention basins on the north side of the terminal apron adjacent to<br />

Bogota Avenue. Additionally, a three-million gallon above-ground storage tank<br />

(AST) is located west of the retention basins to collect glycol-contaminated runoff<br />

from the cargo and general aviation aprons located along Taxiway B, north of the<br />

terminal area. The runoff is stored in these facilities and analyzed for glycol<br />

concentration to determine the proper discharge method based on the level of<br />

glycol concentration.<br />

A similar concept is necessary for storage of the runoff from the centralized deicing<br />

facilities. Storage tanks are proposed to store the runoff and also assist in<br />

maintaining higher concentrations of glycol in the runoff by preventing precipitation<br />

from diluting the stored fluids.<br />

Discharge: Since deicing/anti-icing fluids are chemical products that affect the<br />

water quality of receiving waters and the aquatic communities that use those<br />

waters, the runoff collected needs to be discharged to meet the MDNR permit<br />

requirements and meet the requirements of Federal, state, and local environmental<br />

jurisdictions.<br />

There are multiple options to mitigate the higher concentrations of glycol runoff<br />

anticipated with the centralized deicing operations, as discussed below. However, a<br />

detailed benefit-cost analysis is necessary to identify a preferred alternative that<br />

has the least impact on the environment and provides the most economic benefit to<br />

the Airport.<br />

The concentrated glycol runoff can be sold to vendors that will haul the highly<br />

concentrated runoff directly from the storage tanks to the vendor’s facilities to be<br />

repurposed in accordance with all environmental jurisdictions.<br />

DRAFT<br />

The concentrated glycol runoff can be discharged directly to the sanitary sewer<br />

treatment plant for biochemical treatment. This would require the construction of a<br />

dedicated line from the storage tanks to the sanitary sewer system or the<br />

incorporation of haul trucks to transport the runoff to the treatment facility.<br />

A pump station can be utilized to discharge metered runoff to receiving waters such<br />

as Todd Creek. However, the higher concentrations anticipated would make<br />

meeting the MDNR permit requirements for discharge very difficult.<br />

On-airport anaerobic biochemical reactors can be incorporated to pre-treat runoff<br />

prior to discharge. The bioremediation system generally consists of a glycol<br />

contaminated stormwater collection and storage system, a bioreactor treatment<br />

system, and a gas/heat recovery system. Many treatment plants will only accept<br />

limited quantities of glycol-contaminated stormwater. Anaerobic systems,<br />

depending on the airport’s discharge permit, can reduce BOD concentration levels<br />

sufficiently to permit unrestricted disposal to a sanitary sewer treatment facility.<br />

Landrum & Brown Page 29<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Recycling glycol provides airport management with recycled glycol and water, and<br />

may lower disposal cost of effluent through the resale of recovered product to fluid<br />

manufacturers or to other secondary markets. In addition, sludge disposal costs<br />

may be reduced that are incurred by other mitigation alternatives and less physical<br />

space may be needed for equipment. Typically a third party vendor conducts the<br />

recycling operations through a service agreement with the airport owner.<br />

2.6 Fueling Requirements<br />

2.6.1 EXISTING FUEL FACILITY<br />

The KCI Fuel Farm, located north of <strong>Terminal</strong>s A, B, and C, is operated and<br />

maintained by Allied Fuel and bounded by Brasilia Avenue, Mexico City Avenue, and<br />

Bern and Paris streets. Fuel is supplied to the facility by pipeline and trucks and<br />

receives daily fuel batch supplies equal to 220,000 gallons. The KCI Fuel Farm has<br />

adequate capacity to both receive, store, and settle fuel per ATA 103.<br />

Magellan Mainstream Partners own and operate a single six-inch Class 300 pipeline<br />

with a maximum delivery rate of 22,000 gallons per hour (gph) or 367 gallons per<br />

minute (gpm), and is used to transfer average batch fuel supplies equal to<br />

220,000 gallons per day (gpd) to the Airport. This flow rate can be maintained for<br />

ten hours. The pipeline filter separator is a Clay Treater rated at 840 gpm and a<br />

Coalescer Water/Sediment Filter rated at 800 gpm. The pipeline includes a turbine<br />

meter and a prover loop located at the KCI fuel facility.<br />

The fuel farm includes one truck off-load position rated for up to 2,000 gallons per<br />

minute (gpm) and six ASTs. Tank capacities include:<br />

<br />

<br />

<br />

DRAFT<br />

Four each 5,000 barrel (bbl) AST (210,000 gallons/each)<br />

Two each 8,000 bbl AST (336,000 gallons/each)<br />

Gross Capacity: 36,000 bbls.<br />

Net Usable Capacity into hydrant distribution system: 90% x 36,000 bbls =<br />

32,400 bbls (1,360,800 Gal).<br />

Fuel receipts are transferred to one 8,000 bbl and one 5,000 bbl on the first day.<br />

The fuel in these two tanks settle on the second day and the pipeline batch fuel<br />

receipt alternates into two additional 5,000-barrel tanks. The process repeats on<br />

the third day.<br />

The fuel farm transfer and hydrant distribution systems include equipment to move<br />

fuel from tank storage into other tanks, trucks, or to the aircraft gates at the<br />

terminal buildings. The system includes three types of distribution: transfer<br />

system, truck offload system, and hydrant distribution main lines.<br />

Landrum & Brown Page 30<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Transfer System: Four 900 gpm Bingham 100 hp vertical turbine type pumps and<br />

four 900 gpm Facet Filter Separators are used to remove sediment and water from<br />

the fuel. The transfer system is used to transfer fuel from one tank to another, to<br />

clean up fuel through a filter separator, and to load Airport trucks to fuel cargo<br />

aircraft.<br />

Truck Offload System: Two positive displacement pumps are installed, each with a<br />

Facet Filter. A Clay Treater is also installed for removal of surfactants from tanker<br />

truck fuel receipts.<br />

Hydrant System: There are seventeen 1,000-gpm into-hydrant pumps.<br />

Nine pumps have been taken out of service, leaving eight 1,000-gpm pumps in<br />

service. An equal number (17) of Facet Filter Separators, one per pump, are<br />

installed with eight in operation. The hydrant system is used to supply fuel to the<br />

terminal gates to fuel aircraft.<br />

2.6.2 EXISTING FUEL CONSUMPTION<br />

The fuel consumption data for recent 12 months (April 2011 to March 2012) at KCI<br />

totaled 81,237,127 gallons. The average daily consumption for the same period<br />

was 222,567 gallons. Peak hourly fuel consumption during the busiest time period<br />

was 15,000 gpm. Current 2012 hourly peak fuel consumption is less than<br />

8,000 gpm.<br />

Five 16-inch main fuel hydrant distribution lines (mains) run from the fuel farm and<br />

south on Brasilia Avenue to <strong>Terminal</strong>s A, B, and C. The five mains are designated<br />

as Line A, B, C, D, and E. Lines A and B are currently 18-inch nominal diameter<br />

between the fuel farm and Gate C90. The other three lines (C, D, and E) vary in<br />

size but start out from the fuel farm as 18 inches, 16 inches, and 14 inches,<br />

respectively. However, Lines C, D, and E have been taken out of service and<br />

reported to be filled with nitrogen.<br />

DRAFT<br />

Line A feeds the outside of <strong>Terminal</strong> A, the inside loop of <strong>Terminal</strong> B, and half of the<br />

inside of <strong>Terminal</strong> C. The B Line feeds the inside of <strong>Terminal</strong> A, the outside of<br />

<strong>Terminal</strong> B, and the outside and part of the inside of <strong>Terminal</strong> C. The other lines<br />

(C, D, and E) are tied into the three terminal buildings through isolation valve<br />

vaults. All five lines dead end in an isolation valve vault located near <strong>Terminal</strong> C.<br />

Hydrant pressure in the mains is 150PSI.<br />

Table 2.6-1, Hydrant Distribution, compares multiple 16-inch lines to determine<br />

adequate pipe velocities given equal flow in each line.<br />

Landrum & Brown Page 31<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 2.6-1<br />

HYDRANT DISTRIBUTION<br />

EVENT<br />

TERM A<br />

FLOW<br />

(GPM)<br />

TERM B<br />

FLOW<br />

(GPM)<br />

TERM C<br />

FLOW<br />

(GPM)<br />

TOTAL<br />

FLOW<br />

(GPM)<br />

Velocity<br />

2 - 16”<br />

Mains<br />

(FPS)<br />

Velocity<br />

3 - 16”<br />

Mains<br />

(FPS)<br />

Velocity<br />

4 - 16”<br />

Mains<br />

(FPS)<br />

Velocity<br />

5 - 16”<br />

Mains<br />

(FPS)<br />

Comments<br />

Current 2670 2670 2670 8010 6.4 4.2 3.2 2.6<br />

All Time<br />

Max<br />

Design<br />

Max<br />

Future<br />

New<br />

Term<br />

Source:<br />

5000 5000 5000 15,000 12.0 8.0 6.0 4.8<br />

5666 5667 5667 17,000 14.1 9.4 7.1 5.7<br />

7560 0 0 7560 6.0 4.1 3.1 2.5<br />

2 – 16”<br />

Good<br />

3 – 16”<br />

Needed<br />

4 – 16”<br />

Needed<br />

2 – 16”<br />

Good<br />

HNTB Corporation analysis based on Allied Aviation and Flow of Fluids through Valves, Fittings and Pipe,<br />

CRANE Technical Paper No. 410.<br />

Table 2.6-2, Flow Rates by Pipe Size, is a general listing of flow rates and<br />

velocities per SCH40 Carbon Steel pipe size.<br />

Table 2.6-2<br />

FLOW RATES BY PIPE SIZE<br />

PIPE DIAMETER 6 Feet per Second<br />

7 FPS 10 FPS<br />

(Inches)<br />

(FPS)<br />

6 530 620 880<br />

DRAFT<br />

8 940 1100 1600<br />

10 1500 1700 1700<br />

12 2100 2500 2500<br />

14 2900 3400 3400<br />

16 3800 4400 6300<br />

18 4800 5500 8000<br />

20 5875 6855 9790<br />

Source:<br />

HNTB Corporation analysis based on Allied Aviation and Flow of Fluids through Valves, Fittings and Pipe,<br />

CRANE Technical Paper No. 410.<br />

2.6.3 FUTURE PEAK FLOW ESTIMATE APPROACH<br />

The following assumptions are considered accurate at this time, but may change as<br />

the project’s planning and design phases occur. The total number of gates at the<br />

new terminal will be 41. There are an estimated 39 gates sized for Group III<br />

aircraft (B737) and two gates sized for Group V (B777 and B747) aircraft.<br />

The typical Group III gate turnaround average time is 30 minutes and the typical<br />

Group V average turnaround time is 60 minutes. The desired velocity in the<br />

hydrant main is between six and seven feet/second.<br />

Landrum & Brown Page 32<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Peak fuel rate calculations are based on the assumed number and type of aircraft<br />

fueling at any one peak period. The estimated peak fuel flow is 8,000 gpm<br />

(Group III), plus 1,200 gpm (Group V) which equals 9,200 gpm. The New <strong>Terminal</strong><br />

design will use this estimate to calculate the components necessary to deliver that<br />

demand. As a check and balance, the highest recorded Peak Fuel Flow Rate during<br />

busiest operations was 15,000 gpm based on information provided by Allied<br />

Aviation.<br />

One 18-inch line is recommended to serve <strong>Terminal</strong>s B and C during the<br />

construction of the New <strong>Terminal</strong> based on the current peak demand on <strong>Terminal</strong>s<br />

B and C equal to 5,340 gpm. In addition, two 16-inch lines are recommended to<br />

serve the proposed New <strong>Terminal</strong> based on an estimated peak demand equal to<br />

7,560 gpm.<br />

2.6.4 EXPAND EXISTING FUEL FARM<br />

The KCI Fuel Farm is currently adequate with the estimated net reserve being<br />

6.1 days, based on a 222,567 GPD fuel consumption rate. Fuel reserves of less<br />

than four days create an undue risk for meeting airport fueling demands as a result<br />

of planned and/or unplanned events. To determine when reserves fall below four<br />

days, the existing Fuel Farm net days shortage was calculated for the following<br />

three growth scenarios:<br />

A. 300,000 Gallons per Day (GPD)<br />

B. 300,000 GPD + 10% = 330,000 GPD<br />

C. 300,000 + 20% = 360,000 GPD<br />

DRAFT<br />

Scenario A: (90% * 36,000 bbls * 42 gal/bbl)/300,000 GPD = 4.5 days<br />

Scenario B: (90% * 36,000 bbls * 42 gal/bbl)/330,000 GPD = 4.1 days<br />

Scenario C: (90% * 36,000 bbls * 42 gal/bbl)/360,000 GPD = 3.8 days<br />

Daily fuel consumption would need to increase 161 percent before the current fuel<br />

farm reserves would fall below four days. However, other risks, listed below,<br />

should be considered when planning fuel storage and may have a significant impact<br />

on the decision to add tanks.<br />

2.6.5 PLANNED PIPELINE SHUTDOWNS<br />

Consideration should be given to how reliable the pipeline supply is to the Airport.<br />

If deemed unreliable, fuel tanks could be added in order to maintain operations<br />

during an extended pipeline shutdown. Currently, a single six-inch pipeline<br />

provides over 90 percent of the fuel demands to the KCI Fuel Farm. So, while a<br />

single tanker offload island can supply between 1,600 and 2,000 gpm into tank<br />

storage that would not be practical to meet the demands of the fuel farm when the<br />

pipeline provides 220,000 GDP.<br />

Landrum & Brown Page 33<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Regular visual inspections (fly overs) of the pipeline route are required of the<br />

pipeline owner and are necessary to determine anomalies that may have occurred<br />

along the route. Anomalies may include sink holes, flooding, and/or construction<br />

projects encroaching near, or on top of the pipeline. It is also required to launch<br />

“pigs” into the pipeline to determine and document pipe condition. It is common<br />

for pipeline owners to schedule “planned” shutdowns, typically up to five per year<br />

are scheduled with the Airport, to perform pipeline maintenance and make<br />

necessary repairs. These planned shutdowns typically do not last longer than<br />

ten hours. Shutdowns that last longer than two days will put the Fuel Farm<br />

operations at risk of not meeting fuel supply demands at KCI.<br />

2.6.6 UNPLANNED PIPELINE SHUTDOWNS<br />

An unplanned pipeline shutdown may be caused from a pump fire or severe<br />

weather incident, such as a lightning strike. Currently, none of the pumps have<br />

UVIR heat sensors to detect overheating bearings and alert operators, or to shut<br />

down the pumps. The ASTs do not have redundant high and high-high level<br />

detection and alarm. Tank suction and supply lines do have fusible link closure<br />

valves to prevent fuel from discharging out of the tank if the isolation valve seal<br />

fails.<br />

Hazard risks are very real, as experienced at Miami International Airport (MIA) on<br />

March 27, 2011, the Fuel Facility caught fire and was very disruptive to airport<br />

operations. Per News Week article, “MIAMI, March 27, 2011 (UPI) – Flight<br />

cancellations and delays at Miami International Airport will remain in place for some<br />

time due to a huge fire at its fuel depot, officials said Sunday.”<br />

DRAFT<br />

A review of the risks to the KCI fuel farm and reserves is recommended during the<br />

planning and design phase of the project. (See Exhibit X-4, Plan Fuel Storage<br />

Expansion, in Appendix X), regarding a future expansion concept to show how two<br />

8,000 bbl ASTs could be added to the existing fuel facility.<br />

2.6.7 COMMERCIAL VEHICLE STAGING AND DELIVERY LAYOUT<br />

The fuel farm is located to the north of the Airport on Brasilia Avenue and Bern<br />

Street. The fuel farm control building has a parking lot capacity for 35 vehicles.<br />

Commercial vehicles stage at the fuel farm to make deliveries. No additional<br />

commercial vehicle staging is needed.<br />

2.6.8 CONTROL VALVE VAULTS<br />

Control valve vaults will be equipped with motor-operated double block and bleed<br />

plug valves, low and high flow terminal control valves, and fuel shutoff capability.<br />

This protocol will be retained for each of the five new Control Valve Vaults installed<br />

on the airfield. The permanent valve control connectivity and power for all vault<br />

electrical equipment will be supplied from two dedicated Fuel Control Rooms at<br />

ramp level in the New <strong>Terminal</strong>.<br />

Landrum & Brown Page 34<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

2.6.9 EMERGENCY FUEL SHUTOFF (EFSO)<br />

Emergency fuel shutoff stations will be located in the vicinity of each aircraft gate.<br />

When activated, the EFSO station will stop the flow of fuel on that side of the New<br />

<strong>Terminal</strong>. Fuel flow shutdown will be accomplished by closing motor-operated<br />

valves in the associated control valve vault.<br />

2.6.10 FUELING PLANS<br />

For additional information about fueling, please refer to Appendix X, Fueling<br />

Exhibits lly this includes the following plans:<br />

<br />

<br />

<br />

<br />

Exhibit F-1: Fuel Site Plan<br />

Exhibit F-2: Fuel Storage Expansion Plan<br />

Exhibit F-3: Hydrant Distribution Plan – Temporary Term B&C Fueling<br />

Exhibit F-4: Hydrant Distribution Plan – Term A Fueling<br />

DRAFT<br />

Landrum & Brown Page 35<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3. TERMINAL REQUIREMENTS<br />

3.1 Methodologies<br />

The existing and future capacities of the various functional components of the<br />

terminal complex were identified for the 2025 and 2030 passenger activity levels<br />

(PALs) during the KCI <strong>Advance</strong>d <strong>Terminal</strong> <strong>Planning</strong> <strong>Study</strong>. As described in<br />

Section 1.3.6, Peak Activity for Enplanements, the design day schedule of July 14,<br />

2011 was used as a starting point to determine peak hour forecast<br />

Major data inputs into the New <strong>Terminal</strong> facility requirements include annual<br />

enplanements and peak hour passengers both enplaning and deplaning, which are<br />

shown in Table 3.1-1, Peak Hour Activity Forecast. An assumption for the<br />

development of the KCI terminal facility requirements included using two types of<br />

airline operations and their associated peak hour passenger levels, “Preferential<br />

Use” and “Common Use.”<br />

Preferential Use passenger levels refer to the peak period for a specific air carrier’s<br />

operation which may actually occur in a different clock hour than the other carriers.<br />

These airline specific peak passenger demands reflect an airline’s use agreement<br />

with the Airport that provides them with the preferred use of certain terminal<br />

facilities over the other air carriers. Preferential facilities identified included ticket<br />

and check-in counters, aircraft gates and their holdrooms, baggage claim units, and<br />

operations offices.<br />

Table 3.1-1<br />

PEAK HOUR ACTIVITY FORECAST<br />

DRAFT<br />

Passenger Enplanements: 2011 2015 2020 2025 2030<br />

Annual 5,103,664 5,536,000 6,042,000 6,608,500 7,237,900<br />

Peak Month Percent of Annual 9.8% 9.8% 9.8% 9.8% 9.8%<br />

Peak Month 501,630 544,100 593,900 649,500 709,300<br />

Peak Day Percent of Peak Month 3.4% 3.4% 3.4% 3.4% 3.4%<br />

Design Day 17,100 18,600 20,300 22,200 24,100<br />

Peak Hour Percent of Design Day 11.3% 11.3% 11.3% 11.3% 11.3%<br />

Peak Hour 1,900 2,100 2,300 2,500 2,700<br />

Source:<br />

KCAD, Official Airline Guide, Landrum & Brown analysis.<br />

Common Use peak passenger levels refer to the peak passenger volumes in a given<br />

“rolling” hour, associated with a group of airlines that share certain facilities in<br />

common such as aircraft gates and their holdrooms, ticket and check-in counters,<br />

and baggage claim units. Each airlines’ business model at a particular airport<br />

station defines whether an airline falls into the category of Preferential Use or<br />

Common Use. With new emerging technologies such as Common Use Self Service<br />

(CUSS) and Common Use Passenger Processing System (CUPPS), airports are able<br />

to use space and facilities more efficiently by allowing each air carrier to share the<br />

terminal subcomponents such as check-in counters/kiosks and aircraft gates and<br />

their holdrooms with other airlines on a Common Use basis.<br />

Landrum & Brown Page 36<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Since the specific future use airline agreements with KCI are expiring in 2014 and<br />

are therefore undefined for the 2025 and 2030 forecast horizons, it has been<br />

assumed that the New <strong>Terminal</strong> will be a combination of Preferential and Common<br />

Use agreements. The future terminal facility requirements included in this <strong>Study</strong><br />

assumed that the top three passenger volume airlines will decide to enter into<br />

Preferential Use agreements with the Airport while the remaining airlines will have<br />

certain facilities under a Common Use agreement with the Airport. This was<br />

considered a conservative planning approach for KCI. One of the purposes of the<br />

requirements program is to reserve sufficient areas for airside, terminal, and<br />

landside facilities while simultaneously representing a reasonable facilities<br />

requirement target for generating Rough Order of Magnitude (ROM) capital and<br />

operations costs for ensuring the New <strong>Terminal</strong>’s affordability. With this in mind, it<br />

should be mentioned that if Common Use lease agreements between all of the<br />

airlines and Airport turn out to be the norm, this could reduce the size of some<br />

facility requirements, for example check-in counters and baggage claim.<br />

Other functional area projections in the terminal facility requirements are<br />

determined by their relationship to the number and type of aircraft or the number<br />

of gates/seats serving the terminal. These areas of the terminal include airline<br />

operations space, inbound/outbound baggage operations, and secure public<br />

restrooms.<br />

The lack of consistency for the definition of the term “gate” has led to a need to<br />

standardize the definition when evaluating aircraft utilization and apron<br />

requirements. It is for this reason that the industry identified and defined the<br />

NBEG index (see Table 2.2-1, Narrowbody Equivalent Gate Index). This index<br />

converts gate requirements of diverse aircraft types such as small commuters to<br />

large widebody aircraft, to an equivalent of the apron capacity of a narrowbody<br />

aircraft gate. The amount of space or linear frontage each aircraft requires is based<br />

on the maximum wingspan of aircraft in its respective aircraft group.<br />

DRAFT<br />

Another method used for terminal facility comparisons is Equivalent Aircraft (EQA)<br />

Index. This is a way to look at the capacity of a gate. A good example would be<br />

ramp equipment (bag carts/containers) required for aircraft arrivals and departures<br />

at the gate. With EQA, each gate is converted based on the seating capacity of the<br />

aircraft that can be accommodated. Originally developed in the 1970’s, EQA was a<br />

technique for sizing terminal facilities when the majority of the aircraft in service<br />

had 80 to 110 seats, and some larger narrowbody aircraft had up to 150 seats.<br />

With new larger fleet mixes of regional and jet aircraft, the basis for EQA was<br />

revised. The EQA is still that of an ADG III narrowbody; however, this aircraft<br />

category now typically has seats in the range of 145 to 150. The new EQA of<br />

1.0 that was established uses 145 seats as the baseline denominator. While<br />

smaller aircraft may use the gate, the EQA capacity is based on the largest<br />

aircraft/seating typically in use. Table 3.1-2, Equivalent Aircraft (EQA) Index,<br />

summarizes the EQA of each aircraft group.<br />

Landrum & Brown Page 37<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 3.1-2<br />

EQUIVALENT AIRCRAFT (EQA) INDEX<br />

FAA TAXIWAY DESIGN<br />

GROUP<br />

TYPICAL<br />

SEATS<br />

TYPICAL AIRCRAFT<br />

EQA<br />

INDEX<br />

I Small Commuter 25 Cessna 0.2<br />

II Medium Commuter 50 SF340/CRJ 0.4<br />

III Large Commuter 50 ATR/Dash8 0.4<br />

III Narrowbody 145 A320/B737/MD-80 1.0<br />

IIIa B757 185 B757 1.3<br />

IV Widebody 280 DC-10/MD-11/B767/B787 1.9<br />

V Jumbo 400 B747/A330,340/B777 2.8<br />

VI NLA 550 A380 3.8<br />

Source:<br />

The Apron & <strong>Terminal</strong> Building <strong>Planning</strong> Manual for US DOT, FAA by The Ralph M. Parsons Company:<br />

July 1975 and updated values based on Hirsh & Associates data.<br />

<strong>Program</strong>matic spatial requirements are also based on a particular LOS.<br />

This analysis represents a LOS C criteria or greater which is considered a good level<br />

of service with a stable passenger flow, acceptable delays, and good levels of<br />

comfort during peak periods. The LOS methodology identifies a range of values or<br />

the ability of capacity to meet demand.<br />

This type of programmatic approach to sizing facility areas is commonly used as the<br />

first step during the conceptual planning and can serve as a baseline program for<br />

the preliminary design of terminal projects. As the process proceeds through<br />

design areas such as holdrooms, circulation areas, concessions, and other various<br />

specific use areas, space-based requirements change as a result of professional<br />

judgment, physical configuration, and cost issues. Additionally, during architectural<br />

design/development the specific operating requirements of each individual airline is<br />

taken into account which further refines the overall size of the terminal. The facility<br />

requirements in this <strong>Study</strong> is what is needed to support the peak hour passenger<br />

activity levels and operating assumptions and as such does not represent any<br />

specific terminal configuration or aircraft gating plan. For this reason the actual<br />

physical design of the New <strong>Terminal</strong> may have a square footage total above or<br />

below the baseline conceptual facility requirements represented in this <strong>Study</strong>.<br />

DRAFT<br />

Landrum & Brown Page 38<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.2 <strong>Terminal</strong> Facility Requirements<br />

The New <strong>Terminal</strong> facility requirements are organized into seven general categories<br />

with various subcomponents in the proposed facilities program which is<br />

summarized in Table 3.2-1, Existing Facility Inventory and Future <strong>Terminal</strong><br />

Requirements.<br />

1. General<br />

o<br />

o<br />

Airport Statistics (Annual Enplanements, Peak Hour Enplanements)<br />

Gates<br />

2. Airline Space<br />

o<br />

o<br />

o<br />

Domestic/International Airline Space (Ticketing, Baggage Claim, etc.)<br />

Other Airline Space (Operations, Checked Bag Screening, etc.)<br />

Departure Lounges<br />

3. Concessions Space<br />

o<br />

o<br />

Non-Secure Concessions Space<br />

Secure Concessions Space<br />

4. Customs and Border Protection (CBP)<br />

5. Public Space<br />

o<br />

o<br />

o<br />

o<br />

Security Screening<br />

Circulation (Secure, Non-Secure, General)<br />

Restrooms<br />

Other Space<br />

6. Non-Public Space<br />

o<br />

o<br />

o<br />

Non-Airline Tennant Space (Airport Admin, Other Tenants)<br />

Other Space (Misc.)<br />

<strong>Terminal</strong> Functions (Maintenance/Janitorial/Storage,<br />

Mechanical/Electrical/Plumbing (MEP), Structure/Non-Net)<br />

7. Overall Summary<br />

DRAFT<br />

The Table 3.2-1 data compares existing terminal areas based on the 2012<br />

utilization of existing terminal facilities from KCI lease exhibits to the future<br />

terminal facility requirements for 2025 and 2030. The table provides this<br />

comparison in order to identify any deficiencies in the existing facilities relative to<br />

meeting future demands.<br />

Landrum & Brown Page 39<br />

April 2013


KANSAS CITY INTERNATIONAL AIRPORT PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 40<br />

April 2013<br />

Table 3.2-1<br />

EXISTING FACILITY INVENTORY AND FUTURE TERMINAL REQUIREMENTS<br />

MCI Airport<br />

<strong>Terminal</strong> <strong>Program</strong><br />

General<br />

Units<br />

2012 Existing<br />

Facilities<br />

2025<br />

Recommended<br />

Facilities<br />

2030<br />

Recommended<br />

Facilities<br />

General 1<br />

Overall Airport Statistics<br />

Annual Passengers 10,207,328 13,217,000 14,475,800<br />

Annual Enplanements 5,103,664 6,608,500 7,237,900<br />

Annual Domestic Enplanements 5,059,794 - -<br />

Annual International Enplanements 43,870 72,000 85,800<br />

O&D Passengers 4,646,770 6,017,300 6,590,700<br />

Connecting Passengers 456,894 591,200 647,200<br />

Peak Hour Passenger Statistics<br />

Peak Hour Enplaned - Domestic 2,159 2,688 2,944<br />

Peak Hour Enplaned - International 125 235 257<br />

Total Peak Hour Enplaned 2 2,159 2,688 2,944<br />

Peak Hour Deplaned - Domestic 1,619 2,293 2,511<br />

Peak Hour Deplaned - International - - -<br />

Total Peak Hour Deplaned 2 1,619 2,293 2,511<br />

Total Peak Hour 2 3,283 4,282 4,690<br />

Gates/Positions<br />

Aircraft Gates/Positions (International in parenthesis) Excl + ComUse Exclusive Use Exclusive Use<br />

Small Commuter (Cessna) - - -<br />

Medium Commuter (CRJ/ERJ/BE1) - 4 4<br />

Large Commuter (CR7/E70) - - -<br />

Narrowbody (B737/A320) 16 33 37<br />

B-757 12 - -<br />

Widebody (B767) 2 - -<br />

Jumbo (B777/A340/B747) - - -<br />

NLA (A380) - - -<br />

Total Gates: 62 37 41<br />

1 1 Annual Passenger numbers are taken from the Demand Scenario Summary.<br />

DRAFT<br />

Total EQA 3 : 69.8 34.6 38.6<br />

Total NBEG 4 : 64.8 35.8 39.8<br />

Total Positions: 62 37 41<br />

2 2 The total peak hour numbers represent the total enplanement/deplanements peak hour and not the sum of the components as each may occur in separate hours.<br />

3 3 EQA (Equivalent Aircraft) normalizes gate based on seating capacity of accommodated aircraft.<br />

4 4 NBEG (Narrow Body Equivalent Gate): Used to normalize the apron frontage demand and capacity to that of a typical narrowbody aircraft gate.


KANSAS CITY INTERNATIONAL AIRPORT PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 41<br />

April 2013<br />

Table 3.2-1 (continued)<br />

EXISTING FACILITY INVENTORY AND FUTURE TERMINAL REQUIREMENTS<br />

MCI Airport<br />

<strong>Terminal</strong> <strong>Program</strong><br />

Airline Space<br />

Units<br />

2012 Existing<br />

Facilities<br />

2025<br />

Recommended<br />

Facilities<br />

2030<br />

Recommended<br />

Facilities<br />

Domestic Airline Space<br />

Ticket Counter Exclusive Use Excl+ComUse Use Excl+ComUse Use<br />

Linear Counter Check-in Positions (Kiosk) pos 142 57(64) 65(72)<br />

Total Check-in Locations (Kiosk) pos 169 124(128) 138(144)<br />

Total Linear Position Length lf 650 400 430<br />

Number of Unassigned Check-in Positions pos - - -<br />

Total Unassigned Position Length lf - - -<br />

Counter Area (Includes any curb check) sf 10,210 4,200 4,600<br />

Ticketing Queue (including any free standing kiosks) sf 12,844 11,700 12,700<br />

Curbcheck Positions pos 0 6 8<br />

Airline Ticket Offices sf 12,978 12,000 12,900<br />

Baggage Claim Common Use Common Use Common Use<br />

Claim Devices units 14 8 8<br />

Linear Frontage Required lf 680 980 1,080<br />

Linear Frontage <strong>Program</strong>med lf 1,403 1,280 1,280<br />

Baggage Claim Hall (Includes Device, Queues & Circulation w/in Positive Claim area ) sf 29,092 48,600 48,600<br />

Baggage Services sf 9,600 3,900 4,300<br />

Airline Clubs/VIP Lounges sf 5,742 2,000 2,000<br />

SubTotal: 80,466 82,400 85,100<br />

International Airline Space<br />

Ticket Counter<br />

Linear Counter Check-in Positions (Kiosk) pos 0 8(0) 12(0)<br />

Total Check-in Locations (Kiosk) pos 0 8(0) 12(0)<br />

Total Linear Position Length lf 0 40 60<br />

Counter Area (Includes any curb check) sf - 400 600<br />

Ticketing Queue (including any free standing kiosks) sf - 1,000 1,500<br />

Curbcheck Positions pos 0 0 0<br />

Airline Ticket Offices sf - 1,200 1,800<br />

Airline Clubs/VIP Lounges sf - 2,000 2,000<br />

SubTotal: - 4,600 5,900<br />

Other Airline Space<br />

Outbound Bag Make-Up 4 sf 65,483 69,200 81,100<br />

Inbound Bag Delivery sf 36,464 19,200 19,200<br />

Baggage Train Circulation sf - 13,800 15,000<br />

Checked Baggage Screening (TSA Space) 5 sf 20,725 16,400 16,400<br />

Level 1 Inspection Units (EDS) 6 no 1 3 3<br />

Airline Operations sf 100,338 93,400 104,200<br />

Other Airline Offices/Systems and Support sf 19,285 14,000 15,600<br />

SubTotal: 242,295 226,000 251,500<br />

Departure Lounges<br />

DRAFT<br />

Gates/Positions Excl + ComUse Exclusive Use Exclusive Use<br />

Small Regional (Cessna/Metro) sf - - -<br />

Medium Regional (BE1/CRJ,CR7,9/ERJ/SF340) sf 18,447 3,600 3,600<br />

Large Regional (Q400/E170,175,190) sf - - -<br />

Narrowbody (A320/B737w) sf 98,535 72,600 81,400<br />

B-757(winglets) sf 15,636 - -<br />

Widebody (B767/MD11) sf 6,800 - -<br />

Jumbo (B747,787,777/A330,340) sf - - -<br />

Super Jumbo (A380) sf - - -<br />

SubTotal: 139,418 76,200 85,000


KANSAS CITY INTERNATIONAL AIRPORT PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 42<br />

April 2013<br />

Table 3.2-1 (continued)<br />

EXISTING FACILITY INVENTORY AND FUTURE TERMINAL REQUIREMENTS<br />

MCI Airport<br />

<strong>Terminal</strong> <strong>Program</strong><br />

US Customs & Border Protection Services (CBP)<br />

Concessions Space<br />

DRAFT<br />

2025<br />

2030<br />

2012 Existing<br />

Recommended Recommended<br />

Facilities<br />

Units<br />

Facilities<br />

Facilities<br />

Non-Secure Concessions Space<br />

Rental Car<br />

Number of Counters pos 5 6 7<br />

Counter Area/Offices sf - 2,400 2,800<br />

Queue sf - 1,800 2,100<br />

Non-Secure Concessions sf 25,780 10,600 11,700<br />

Non-Secure Storage sf 8,811 2,700 2,900<br />

SubTotal: 34,591 17,500 19,500<br />

Secure Concessions Space<br />

Secure Concessions sf 18,157 67,577 67,577<br />

Secure Storage sf 5,722 16,193 16,193<br />

SubTotal: 23,879 83,770 83,770<br />

Primary Processing<br />

Units<br />

Primary Inspection Booths (Double Counters) units 3 0 4<br />

Area Primary Inspection Booths sf 837 - 1,500<br />

Primary Inspection Queue sf 1,186 - 3,800<br />

Primary Inspection Support sf 2,318 700 700<br />

SubTotal: 4,341 700 6,000<br />

Baggage Claim<br />

Claim Devices Required units 1 0 1<br />

Linear Frontage Required lf 166 0 450<br />

Linear Frontage <strong>Program</strong>med lf 0 0 300<br />

Baggage Claim Hall sf 5,182 - 11,400<br />

SubTotal: 5,182 - 11,400<br />

Secondary Processing<br />

Passport Control Check Positions pos 0 1 1<br />

Area Passport Control Check sf - 200 200<br />

Area Secondary Waiting sf - 400 800<br />

Exam Podiums and Baggage Belts (2 belts per unit) units 2 0 0<br />

Area Secondary Inspection sf 1,146 - -<br />

Baggage X-Ray Processing (1 X-Ray per unit) units 0 1 1<br />

Area X-Ray Inspection sf . 1,500 1,500<br />

Secondary Inspection Support sf 1,075 1,100 1,100<br />

SubTotal: 2,221 3,200 3,600<br />

Support Space<br />

CBP Administration sf 3,554 700 800<br />

CBP Administration Support sf 2,016 600 600<br />

SubTotal: 5,570 1,300 1,400<br />

Other Space<br />

Sterile Corridor Circulation sf 851 100 3,000<br />

In-Transit/Sterile Holding Areas sf - - -<br />

Public Sterile Restrooms sf 727 - 1,000<br />

General Circulation sf 319 100 2,600<br />

Greeter Lobby<br />

Greeter Waiting Area sf 697 - 600<br />

Other sf - - -<br />

Baggage Recheck<br />

Number Recheck Positions pos 0 0 0<br />

Area Recheck Positions sf - - -<br />

Queue Baggage Recheck sf - - -<br />

SubTotal: 2,594 200 7,200


KANSAS CITY INTERNATIONAL AIRPORT PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 43<br />

April 2013<br />

Table 3.2-1 (continued)<br />

EXISTING FACILITY INVENTORY AND FUTURE TERMINAL REQUIREMENTS<br />

MCI Airport<br />

<strong>Terminal</strong> <strong>Program</strong><br />

Public Space<br />

Units<br />

2012 Existing<br />

Facilities<br />

2025<br />

Recommended<br />

Facilities<br />

2030<br />

Recommended<br />

Facilities<br />

Security Screening Checkpoint (SSCP)<br />

Number of Lanes pos 23 14 16<br />

Queuing Area sf 2,573 6,300 7,600<br />

Checkpoint Screening Area sf 24,364 24,000 27,100<br />

TSA Offices sf 5,463 3,000 3,500<br />

SubTotal: 32,400 33,300 38,200<br />

Circulation<br />

Ticket Lobby Circulation sf - 8,800 9,500<br />

Baggage Claim Circulation sf - 8,500 8,500<br />

Secure Circulation (Incl. Fire/Service Stairs to Apron) sf - 96,700 107,500<br />

General Public Circulation (Includes Vestibules, Vert Circ, Corridors) sf 174,378 64,300 69,900<br />

Public Seating sf 16,129 2,000 2,200<br />

Domestic Meeter/Greeter Lobby sf 7,000 10,000 10,900<br />

Transportation (Shuttle Service) & Hotel Courtesy Phones sf 1,144 700 700<br />

SubTotal: 198,651 191,000 209,200<br />

Restrooms<br />

Public Restrooms - Secure sf 5,040 5,600 7,000<br />

Public Restrooms - Non-Secure sf 17,977 10,900 12,000<br />

SubTotal: 23,017 16,500 19,000<br />

Other Space<br />

Misc Tenant<br />

American Credit Union (AAFCU), Central Carts, Chapel, USO, USPS sf 8,900 8,900<br />

Smoking Lounge sf 1,500 1,500<br />

Other (Displays, Information Counters, Visitors Commission etc) sf 702 700 700<br />

SubTotal: 702 11,100 11,100<br />

DRAFT<br />

Non-Public Space<br />

Non-Airline Tenant Space<br />

Airport Administration<br />

Offices/Support (City) sf 29,326 5,100 5,100<br />

Airport Police (Includes Locker Facilities) sf 413 2,000 2,000<br />

Other Tenants<br />

Misc Tenant sf 3,093 6,600 6,600<br />

SubTotal: 32,832 13,700 13,700<br />

Other Space<br />

Non-Public Restrooms / Lockers sf 22,197 2,700 3,000<br />

Non-Public Circulation sf 92,993 27,100 29,900<br />

Other sf 2,642 - -<br />

SubTotal: 117,832 29,800 32,900<br />

<strong>Terminal</strong> Function<br />

Maintenance/Janitorial/Storage/Shops sf 16,826 7,500 8,500<br />

Mechanical/Electrical/Telephone/Plumbing sf 101,710 91,900 103,300<br />

Building Systems (Structure/Non-net/Void) sf 23,533 21,800 24,600<br />

Exterior - Other (ie Public Gardens, etc) sf - - -<br />

SubTotal: 142,069 121,200 136,400


KANSAS CITY INTERNATIONAL AIRPORT PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 44<br />

April 2013<br />

Table 3.2-1 (continued)<br />

EXISTING FACILITY INVENTORY AND FUTURE TERMINAL REQUIREMENTS<br />

MCI Airport<br />

<strong>Terminal</strong> <strong>Program</strong><br />

Summary<br />

2008-2028<br />

Source: Landrum & Brown<br />

Units<br />

2012 Existing<br />

Facilities<br />

2025<br />

Recommended<br />

Facilities<br />

2030<br />

Recommended<br />

Facilities<br />

General<br />

Annual Enplanements 5,103,664 6,608,500 7,237,900<br />

Annual O&D Enplanements (%) 4,646,770 (91.%) 6,017,300 (91.1%) 6,590,700 (91.1%)<br />

Annual Connecting Enplanements (%) 456,894 (9.%) 591,200 (8.9%) 647,200 (8.9%)<br />

Peak Hour Enplaned Domestic 2,159 2,688 2,944<br />

Peak Hour Enplaned International 125 235 257<br />

Peak Hour Deplaned Domestic 1,619 2,293 2,511<br />

Peak Hour Deplaned International - - -<br />

Gates/Positions 62 37 41<br />

Airline Space<br />

Domestic Airline Space sf 80,466 82,400 85,100<br />

International Airline Space sf - 4,600 5,900<br />

Other Airline Space sf 242,295 226,000 251,500<br />

Departure Lounges sf 139,418 76,200 85,000<br />

SubTotal: 462,179 389,200 427,500<br />

Concessions<br />

Non-Secure Concessions Space sf 42,322 17,500 19,500<br />

Secure Concessions Space sf 23,879 83,770 83,770<br />

SubTotal: 66,201 101,270 103,270<br />

US Customs & Border Protection Services 7<br />

Design Hour Passengers pax 45 - 257<br />

Primary Processing sf 4,341 700 6,000<br />

Baggage Claim sf 5,182 - 11,400<br />

Secondary Processing sf 2,221 3,200 3,600<br />

Support Space sf 5,570 1,300 1,400<br />

Other Space sf 2,594 200 7,200<br />

SubTotal: 19,908 5,400 29,600<br />

Public Space<br />

Security sf 32,400 33,300 38,200<br />

Circulation sf 198,651 191,000 209,200<br />

Restrooms sf 23,017 16,500 19,000<br />

Other Space sf 702 11,100 11,100<br />

SubTotal: 254,770 251,900 277,500<br />

Non-Public Space<br />

Non-Airline Tenant Space sf 32,832 13,700 13,700<br />

Other Space sf 117,832 29,800 32,900<br />

<strong>Terminal</strong> Functions sf 142,069 121,200 136,400<br />

SubTotal: 292,733 164,700 183,000<br />

Total<br />

DRAFT<br />

Total Functional <strong>Terminal</strong> Area: 953,722 791,270 884,470<br />

Total Gross <strong>Terminal</strong> Area: 1,095,791 912,470 1,020,870


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.2.3 TERMINAL AREA REQUIREMENTS<br />

The overall passenger enplanements were forecasted to grow at an annual average<br />

rate of 1.9 percent per year from approximately 5.1 million enplanements in 2011<br />

to 7.2 million enplanements in 2030. Peak hour enplanements are forecasted to<br />

grow from 1,900 passengers in 2011 to 2,900 passengers by 2030.<br />

As mentioned in Section 2.2.2, Current Conditions, of the 62 available gates<br />

(66 positions) KCI is currently operating from 30 gates as of 2012 and is forecasted<br />

to grow to 41 gates by 2030. Widebody aircraft are not predicted to operate<br />

commercial passenger service over the forecast period with limited B757<br />

operations, less than one percent, in 2030. However, one gate is held throughout<br />

the planning horizon for future operating flexibility.<br />

The narrowbody aircraft was used as the design aircraft and is expected to account<br />

for the predominant share of passenger operations maintaining 56 percent in 2012<br />

and 58 percent by 2030. Regional jets are expected to continue to account for a<br />

steady share of the passenger operations decreasing slightly from 44 percent in<br />

2011 to 42 percent by 2030. Large regional jets such as the 100-seat Embraer are<br />

assumed to potentially replace, or offer incremental capacity for the current aging<br />

100-seat aircraft such as the B717 and DC9 fleets.<br />

3.2.3.1 Airline Space<br />

The need for airline service represents a major portion of the passenger processing<br />

functions of a terminal. It contains all the exclusive areas typically required and<br />

leased by the airline tenants to support their operations. These functions include<br />

ticketing, baggage claim, airline operations and support, and departure lounges<br />

(holdrooms).<br />

DRAFT<br />

Airport tenant interviews were held with various station managers during the 2008<br />

Master Plan. These discussions along with on-site observations during this <strong>Study</strong><br />

were used to determine the adequacy of the various airline functions for conceptual<br />

planning purposes. It is anticipated that as the New <strong>Terminal</strong> concept moves into<br />

the subsequent architectural design/development phase, each individual airline will<br />

be consulted relative to their individual operational requirements. The airline<br />

requirements for the New <strong>Terminal</strong> that represent a conceptual baseline for<br />

planning purposes are discussed in the following paragraphs.<br />

Domestic/International Airline Space<br />

Airline Ticket Counters refers to the area occupied by the ticket counter, ticket<br />

agents, and the ticket counter baggage belt. It is typically assumed as an exclusive<br />

use operation for most U.S. airlines. This airline function is based on the peak hour<br />

origin and destination (O&D) enplaning (departing) passengers, their associated<br />

early arrival profiles, acceptable service times associated with the check-in process,<br />

and the percentage of the originating passengers that actually check-in at the<br />

terminal versus going directly to the gate or checking in at any offsite location.<br />

Industry accepted planning factors were used in this baseline analysis.<br />

Landrum & Brown Page 45<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The typical airline ticket counter has evolved over the past years to include both<br />

standard agent positions and the self-service electronic kiosk. These kiosks can<br />

either be converted from in-line counter positions, be free standing in the ticketing<br />

queue area, or be a combination of both. Each airline typically has their own<br />

arrangement within the ticketing area, which has reduced the need for some in-line<br />

counter positions but has increased the amount of queue space needed in the ticket<br />

lobby. The free standing kiosk is typically referred to as a “Two-Step” process<br />

where the passenger checks in at the kiosk and the traditional in-line counter<br />

position becomes the bag drop and additional assistance location.<br />

Based on a review of the lease drawings and discussions with the Airport, the<br />

existing terminals have a combined total of approximately 169 possible check-in<br />

locations for passengers made up of 142 traditional staffed counter positions,<br />

30 self-service counters or kiosks, and 16 free-standing kiosks. However, with<br />

FAA’s current 100 percent baggage screening requirements, this number is slightly<br />

less than what is potentially available with some Explosive Detection Screening<br />

(EDS) machines occupying the space of potential counter positions and queue area.<br />

The airlines currently lease around 78 traditional staffed in-line counter positions.<br />

The 27 in-line kiosks mentioned above were converted from 24 staffed positions for<br />

a total of 105 linear counter positions. There are also an additional 16<br />

free-standing kiosks which have various configurations in the ticketing queues for a<br />

total of 121 equivalent check-in locations. In order to plan for future “equivalent<br />

positions,” the existing ratio of 1.2 has been retained. This ratio is calculated by<br />

dividing 121 possible check-in locations by 105 linear positions.<br />

International check-in functions are included in these domestic totals. Current air<br />

traffic at KCI includes flights by Air Canada which are handled by United’s check-in<br />

area, Frontier, and charters.<br />

DRAFT<br />

The existing ticket counters at KCI vary in length and configuration based on<br />

individual airline preferences. Generally they consist of a 6.5-foot double counter<br />

plus a shared 30-inch bag drop for an average of 4.5 feet per ticket agent position<br />

compared to a domestic carrier average of 4.25 feet per agent. A planning factor of<br />

5.5 feet has been assumed for future requirements which also accounts for counter<br />

breaks for agent access.<br />

The current 142 traditional linear check-in counter positions between the three<br />

terminals at KCI account for a total length of 650 feet. The future requirement of<br />

430 linear feet is based on an exclusive and common use of 65 standard in-line<br />

counter positions which were calculated from the individual airline’s peak hour<br />

requirements. Equivalent positions would translate to 72 check-in locations of<br />

which eight would occupy ticket queue space based on the current ratio.<br />

Landrum & Brown Page 46<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The existing ticket counter area measures approximately 10,210 square feet, of<br />

which 4,690 square feet is unoccupied. Most of the existing counter areas measure<br />

between ten and 16 feet from ticket counter face to the back wall and are<br />

dependent on each airline’s operational setup. Based on an industry standard<br />

depth of ten feet from the face of the ticket counters to the back wall behind the<br />

counters, 4,600 square feet would be needed by 2030.<br />

The ticketing queue is a function of the counter frontage and the acceptable<br />

planning depth for passenger queuing in front of the counter positions.<br />

The existing depth for all three terminals at KCI varies based on each airlines’<br />

ticketing configuration but is generally 21 feet deep on average. A future depth of<br />

30 feet has been used to account for required queue space needed for the area<br />

taken up by any free standing kiosks and their passengers. The existing area<br />

measures 12,840 square feet and accommodates the recommended existing facility<br />

requirement of 12,800 square feet. By 2030 an area of 12,700 square feet will be<br />

needed to adequately handle the 65 linear counter positions or 72 equivalent<br />

check-in locations.<br />

The Airline Ticket Office (ATO) refers to the office area leased to the airlines and is<br />

generally located directly behind or adjacent to the ticket counter to provide<br />

support functions for the ticket agents and other airline administrative space.<br />

However, this space can be located in other terminal areas, as necessary.<br />

Typically, the ATO space is 25 to 30 feet deep along the full length of the ticket<br />

counters. At KCI, all of the airline ATO offices are located adjacent to the counters<br />

or up on the mezzanine levels. The existing offices are located in 12,978 square<br />

feet with most of this space accounted for on the mezzanine levels of the terminals.<br />

However, the offices located adjacent to the ticket counters are generally too small.<br />

The future ATO requirement of 12,900 square feet is based on a depth of 30 feet<br />

along the 430 linear feet of required ticket counter.<br />

DRAFT<br />

The Baggage Claim (Domestic) area is occupied by the baggage claim devices and<br />

the queuing area for active claiming. Baggage claim requirements are primarily<br />

based on the percentage of deplaned terminating passengers in a peak 20-minute<br />

period, the percentage of those passengers checking bags, and to a lesser extent<br />

the number of bags checked. Because most passengers arrive at the claim area<br />

before their baggage arrives there should be sufficient claim frontage to<br />

accommodate the concentration of these peak passengers. This analysis focused<br />

on using the existing preferential use claim areas for future requirements.<br />

The existing claim devices range in size from 85 linear feet of frontage to 150 feet<br />

with an overall length for all devices of 1,403 feet. Analysis shows that American<br />

and Northwest’s small claim devices of less than 100 linear feet are generally too<br />

small for their current demand. The future recommended size of claim devices is<br />

150 linear feet, which would adequately handle passengers from a typical<br />

narrowbody aircraft with multiple flights by smaller regional aircraft. The existing<br />

recommended claim frontage was 1,400 linear feet, or 12 devices, suggesting that<br />

the existing planning factor of 0.5 linear feet per peak hour terminating passenger<br />

is adequate to handle the current activity at KCI. However, given the larger<br />

suggested devices, the future planning factor has been increased to a more typical<br />

Landrum & Brown Page 47<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

1.5 linear-foot per peak hour terminating passenger. This results in a need of<br />

1,080 linear feet by 2030. The total provided claim length of 1,280 linear feet<br />

results in eight claim devices.<br />

The recommended size of the baggage claim hall area is 35 square feet per linear<br />

foot of claim area to provide adequate queuing and circulation space. The existing<br />

claim area of approximately 29,092 square feet is undersized to meet the<br />

suggested 42,600-square foot requirement. This is primarily due to the shallow<br />

claim retrieval areas which often measure between 3.5 feet and 14 feet.<br />

The existing general circulation area often serves as the retrieval and circulation<br />

area for most of these devices. The future demand will require 48,600 square feet<br />

of claim hall or approximately 16 square feet per peak hour deplaned terminating<br />

passenger.<br />

Baggage Services includes the area of baggage service offices which are leased to<br />

the airlines. Typically these offices are only required by airlines with sufficient<br />

activity to warrant staffing. Currently, there are 11 offices totaling 9,600 square<br />

feet that include 3,911 square feet in four unassigned offices resulting in a planning<br />

factor of 720 square feet per leased office. The future planning factor of<br />

one-square foot per design hour passenger results in a need of 4,300 square feet<br />

by 2030.<br />

Presently there are no Airline Clubs/V.I.P. Lounges operating at KCI. Such facilities<br />

are typically, but not exclusively provided by the dominant carrier at an airport.<br />

These facilities are generally determined by each airline’s criteria for level of<br />

passenger activity and the type of markets being served by the airport.<br />

The current planning ratio of 2,000 square feet per club was used to determine the<br />

future 2030 requirement of 2,000 square feet.<br />

Other Airline Space<br />

DRAFT<br />

The Outbound Bag Make-Up area is directly behind the airline offices and is used for<br />

the accumulation, storage, and make-up of outbound baggage from the ticket<br />

counter and curbside check-in areas. This space typically consists of the make-up<br />

units, baggage train circulation and maneuvering lanes, the tug/cart staging areas,<br />

and in some cases, the Transportation Security Administration (TSA) baggage<br />

screening EDS devices. Most of the airlines at KCI reported having adequate<br />

operation space except for U.S. Airways and Southwest Airlines that reported<br />

having inadequate space during the 2008 MP. A method for providing a consistent<br />

basis for baggage system planning involves using the EQA as previously described<br />

in Section 3.1, Methodologies. The existing leased preferential make-up areas<br />

totaled 70,740 square feet for a planning ratio of 2,000 square feet per EQA. Using<br />

this existing ratio, the future 2030 demand would require 81,100 square feet of<br />

space.<br />

The Inbound Bag Delivery area is used to feed bags to the baggage claim devices.<br />

The existing area measures 36,464 square feet and most airlines reported this as<br />

adequate although, as with their outbound area, US Airways and Southwest Airlines<br />

reported a shortage of space as did American Airlines during the 2008 MP.<br />

Landrum & Brown Page 48<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

This existing area of 36,464 square feet resulted in a planning factor of 22 square<br />

feet per peak hour deplaned terminating passenger compared to an industry<br />

standard of eight to ten square feet, which suggests the existing area is adequate<br />

to handle the current demand. Using a more typical 8.4 square feet, the 2030<br />

demand would need 19,200 square feet of area.<br />

Currently, Checked Baggage Screening for possible explosives is being<br />

accomplished via nine stand-alone units on the passenger service level in the<br />

ticketing area. Future program requirements assumed a centralized screening area<br />

that would operate on an in-line system integrated into the make-up system. EDS<br />

requirements were based on 63 percent of the 2007 schedule departing passengers<br />

in the peak 30 minutes of the peak hour. A processing rate of 400 bags per hour<br />

per EDS unit with 60 percent of the originating passengers checking bags and<br />

1.5 bags per passenger has been assumed. The 2030 demand year results in a<br />

need for 16,400 square feet which includes the area needed for primary and<br />

secondary units, conveyors, offices, and circulation.<br />

The Airline Operations area is used by the airlines for their everyday operations<br />

which includes the apron level support spaces for aircraft crew, aircraft servicing,<br />

and other related support facilities. A program area is typically based on the<br />

number of gates determined by using an EQA related methodology. The demand<br />

for operations space is a function of the size and number of aircraft being served<br />

based on individual airline operating policies.<br />

There are currently 100,300 square feet of apron level operations, of which<br />

approximately 32,740 square feet is leased to the airlines. Most of the airlines<br />

reported having adequate operations space with the exception of Southwest and US<br />

Airways during the 2008 MP. The current leased square foot per EQA ratio is 950<br />

which is at the lower range for spoke airports. The existing available ratio is a<br />

more reasonable 2,700 square feet per EQA and this has been used for future<br />

planning requirements. The 2030 demand level requires 104,200 square feet of<br />

space.<br />

Other Airline Offices/Systems and Support areas, such as centralized ground power,<br />

preconditioned air, computer rooms, etc. have been included in this category.<br />

A typical allowance of fifteen percent of the airline operations space has been used<br />

and should be considered as supplemental to the overall mechanical and electrical<br />

systems area in the program. The future 2030 demand level requires<br />

15,600 square feet.<br />

Departure Lounges (Holdrooms)<br />

DRAFT<br />

In evaluating the capacity of the holdrooms, physical location and proximity to the<br />

gate are important factors to consider. The available holdroom space needs to be<br />

relatively close to the gate. Multiple gates with adjacent holdrooms typically have<br />

additional boarding space capacity resulting from sharing holdroom seating<br />

between the gates. These factors were taken into consideration when evaluating<br />

the future requirements.<br />

Landrum & Brown Page 49<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Holdrooms are based on the mix of gates and the average seating capacity of each<br />

aircraft design category. These areas generally consist of the passenger seating<br />

area, the airline’s podium and associated queue space, the loading bridge egress<br />

corridor, circulation, and any additional square footage allowances for areas such as<br />

telephone banks, child play areas, etc.<br />

When sizing these areas the amount of seating area is typically based on an<br />

industry standard of 80 percent of the aircraft seating capacity. Of this percentage<br />

a range from 50 to 80 percent is allocated to the number of passengers seated with<br />

the remaining 20 to 50 percent standing. At KCI, a typical planning ratio of<br />

80 percent seated and 20 percent standing has been applied.<br />

The physical layout of the holdroom consists of a 180-square foot wide (six feet)<br />

loading bridge egress corridor with an assumed average 30-foot deep holdroom.<br />

Current holdrooms average a 45-foot depth which accounts for the unique<br />

operational layout of the three terminals. This extra depth is needed to allow for<br />

the inclusion of the decentralized security screening checkpoints, restrooms, and<br />

small concessions areas that occupy space within the secure perimeter.<br />

The podium position area and associated queue space is allocated at between 90 to<br />

115 square feet. Existing holdrooms are paired or clustered. This grouping<br />

together of holdrooms has made it possible to reduce the physical amount of<br />

holdroom seating area needed. A ten percent reduction in the seating areas at KCI<br />

has been assumed for the future requirements. Additionally, to reflect the specific<br />

operating characteristics of airlines with frequent flights and short ground times,<br />

like Southwest’s operation, a heavy utilization factor of 30 percent has been used.<br />

This factor takes into account the additional passengers from more than one flight<br />

at the gate at the same time.<br />

The average seating capacities and recommended holdroom sizes are summarized<br />

in Table 3.2-2, Passenger Holdroom Typical Areas, below.<br />

Table 3.2-2<br />

PASSENGER HOLDROOM TYPICAL AREAS<br />

FAA TAXIWAY DESIGN GROUP<br />

DRAFT<br />

TYPICAL<br />

SEATS<br />

TYPICAL AIRCRAFT<br />

AREA (SF)<br />

I Small Commuter 25 Cessna 550<br />

II Medium Commuter 50 SF340/CRJ 810<br />

III Large Commuter 50 ATR/Dash8 1,240<br />

III Narrowbody 150 A320/B737/MD-80 2,400<br />

IIIa B757 185 B757 3,000<br />

IV Widebody 280 DC-10/MD-11/B767/B787 3,700<br />

Source:<br />

FAA AC 150/5300-13, Airport Design, Hirsh & Associates, and Landrum & Brown<br />

Landrum & Brown Page 50<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The existing holdroom capacity at KCI is approximately 132,618 square feet, of<br />

which 86,826 square feet is currently being leased by the airlines.<br />

The recommended holdroom area is 68,200 square feet which is less than the<br />

existing available area. During the 2008 MP most of the airlines reported having<br />

adequate holdroom area, but United has said their holdrooms are generally too<br />

small. Analysis of their existing holdroom area suggests the area is adequate to<br />

handle their current schedule. However, given the fact that area includes security<br />

and restrooms along with the varying depth of the seating area, this could suggest<br />

there are times when the area is at, or over capacity. This could generally be said<br />

for all the holdroom areas. The 2030 demand level requires 85,000 square feet.<br />

3.2.3.2 Concessions Space<br />

This category of the terminal space program represents all of the areas devoted to<br />

commercial concessions that generate revenue for the Airport. In general, these<br />

include food/beverage, news/gift/sundry (business centers, shoe shine, barber<br />

shops, specialty stores, etc.), rental car (RAC), and other revenue-generating<br />

functions. These amenities provide the passenger with necessary services and<br />

discretionary goods and services during the processing function, and provide vital<br />

revenue to the Airport.<br />

A general planning rule suggests approximately ten percent of public space should<br />

be allocated to concessions with a recommended 80 to 90 percent of the total<br />

concessions area allocated to the secure side of the terminal beyond security.<br />

The remaining 10 to 20 percent should be in the non-secure or landside area of the<br />

terminal area. Approximately four percent of the public area at KCI is allocated to<br />

concessions space and about 90 percent of the revenue generating area in the<br />

non-secure area of the terminals, with the majority of this being allocated to the<br />

mezzanine levels. This is due to the unique operational layout of the three<br />

terminals and suggests a need for more revenue generating concessions space.<br />

DRAFT<br />

Accepted industry standards recommend approximately 1,500 square feet of total<br />

concessions space per 100,000 annual enplanements (ANNEP). KCI currently has<br />

44,460 square feet of concessions resulting in a ratio of 620 square feet per<br />

100,000 ANNEP. For future terminal area space requirements a ratio of<br />

1,300 square feet per 100,000 ANNEP, with a split of 80 percent secure and<br />

20 percent non-secure has been used. The existing recommended concessions<br />

program results in an area of 66,350 square feet or approximately ten percent of<br />

the public area. The future 2030 demand requires 83,770 square feet of space.<br />

An additional area is typically reserved for storage and service areas which is equal<br />

to 25 to 35 percent of the total concessions space program. These areas typically<br />

include storage areas, preparation kitchens, employee lockers, loading docks, trash<br />

compactors, and concessionaires’ administrative offices. At KCI this existing area<br />

equals approximately 14,010 square feet or 55 percent of the public area. A more<br />

typical 25 percent has been used for future space requirements, which reflects the<br />

type of concession operations at KCI. The result is a need for 16,200 square feet<br />

by 2030. However, this initial estimate for future requirements should be reviewed<br />

by the concession operators.<br />

Landrum & Brown Page 51<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

It should be noted that this space does not account for any RAC facilities because<br />

this area will be located in the new remote consolidated RAC site. Any future<br />

requirements are still considered to be remote.<br />

3.2.3.3 U.S. Customs and Border Protection Services (CBP)<br />

The CBP, often referred to as Federal Inspection Services (FIS), are required by law<br />

for the processing of international passengers into the U.S. and its priority mission<br />

is homeland security. It consists of U.S. government agencies which include<br />

U.S. Immigration and Naturalization Services (INS), U.S. Customs Services (USCS),<br />

Animal and Plant Health Inspection Services (APHIS), and Public Health Services<br />

(PHS). CBP facilities consist of passenger processing areas for each agency as well<br />

as required support space for offices, maintenance, and other areas.<br />

The future program’s facility requirements and processing functions are assumed to<br />

reflect that of a two-step process adopted nationally. In this procedure all<br />

international arriving passengers are subject to primary inspection by the INS and a<br />

secondary more selective inspection in the secondary processing function by<br />

U.S. Customs. Although this is a national policy, implementation may vary at each<br />

airport based on local conditions and annual activity levels. This is the case at KCI<br />

where currently the INS and Customs are combined in the same space.<br />

An interview with CBP, held during the 2008 MP, revealed annual activity at<br />

35,000 to 40,000 passengers as compared to the current 43,870 passengers per<br />

year. The majority of passengers are U.S. citizens coming from Mexico for which<br />

processing is fairly simple. The CBP estimated an average throughput of<br />

approximately 100 passengers per half hour. The current international service is<br />

provided by Air Canada through their contract carrier, Jazz, year round and<br />

seasonally by Frontier. Southwest is assumed as a potential international service<br />

carrier in the future. All flights from Canada into KCI are pre-cleared. Gate 90 in<br />

<strong>Terminal</strong> C handles these international inbound arriving passengers. This is an<br />

arrival gate only with no associated holdroom space for outbound passengers,<br />

which means the CBP can handle only one arrival flight at a time. They have<br />

operated in their current configuration for years and for the most part this facility is<br />

adequate for the current passenger volumes. Some exceptions have been noted<br />

such as:<br />

<br />

<br />

DRAFT<br />

Inadequate exit area to the meeters/greeters hall. Line-of-sight issues to the<br />

Immigration/Customs area allows visitors to take pictures of passengers as<br />

they process, which is considered a security issue for the agencies.<br />

CBP would like some sort of visual barrier to prevent this from occurring.<br />

CBP has expressed a desire for more record storage, electrical outlets, and<br />

functioning shower/locker facilities. Currently there is no hot water for these<br />

areas.<br />

The future CBP agency inspection and support area requirements are based on the<br />

CBP, Airport Technical Design Standards Passenger Processing Facilities,<br />

August 2006 document. CBP space requirements are sized for a capacity stated in<br />

terms of passengers per hour and the type of facility planned for such as small<br />

(under 800 passengers/hour), medium (800 to 2,000 passengers/hour), and large<br />

Landrum & Brown Page 52<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

(greater than 2,000 passengers/hour) airports. KCI, under these scenarios, would<br />

fall under the small airport category processing, less than 200 passengers/hour.<br />

The recommended future layout, space permitting, would have Primary Inspection,<br />

baggage claim, and Secondary Inspection on one level with other offices and<br />

support space on different levels as needed. At a minimum the Secondary<br />

Inspection and Support area needs to be on the passenger processing level for<br />

direct access.<br />

As previously mentioned, CBP considers the current 19,910 square feet to be<br />

adequately sized for the current passenger volumes. However, the current<br />

recommended size for this function is 29,100 square feet which in turn represents a<br />

need for more space in the individual agency areas such as in their support<br />

functions. For future planning the CBP functions have been sized to handle the<br />

future 2030 forecast level of 275 passengers per hour resulting in a facility of<br />

approximately 29,600 square feet. Fully staffed however, the CBP facilities can<br />

handle 400 passengers an hour with a 90 second per passenger turn over time.<br />

The baggage carousels are sized to roughly the same capacity (450-600 passenger<br />

per hour assuming two bags per passenger). CBP may evaluate the airport’s traffic<br />

projections on a case-by-case basis and update any requirements as needed. As a<br />

result, certain agency functions may be combined or left out of the program all<br />

together.<br />

3.2.3.4 Public Space<br />

Security Screening Checkpoint (SSCP)<br />

DRAFT<br />

This area of the program is dedicated to the TSA space for screening departing<br />

passengers. Future planning requirements are based on the Recommended<br />

Security Guidelines for Airport <strong>Planning</strong>, Design and Construction, March 2011,<br />

document published by the TSA.<br />

These areas generally include two types of screening configurations. The “2 to 2”<br />

module includes two lanes with two x-rays per two magnetometers with a footprint<br />

of 29 feet by 42 feet. An additional ten feet of depth has been added downstream<br />

for reconciliation of passenger baggage and personal belongings. Overall, this area<br />

requires 754 square feet of space.<br />

The second module type is the “2 to 1” or two lanes consisting of two x-rays per<br />

one magnetometer with a footprint of 22 feet by 44 feet with an additional ten feet<br />

of depth downstream for a total of 594 square feet of space. The “2 to 1” module<br />

type is becoming more prevalent, according to TSA, in that it provides greater<br />

flexibility for staffers to work among different checkpoint lanes. These modules<br />

generally consist of the primary screening areas and their equipment, and a<br />

secondary search area (holding or wanding area). Additional area needs to be<br />

added will be for passenger queuing and exits, and space permitting, area for TSA<br />

offices.<br />

Landrum & Brown Page 53<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Currently KCI has nine security checkpoints, one for each airline, down from 11 in<br />

2006. Southwest uses two checkpoints for their holdroom areas. This operation is<br />

unique only to KCI in that it decentralizes security to each of the boarding gate<br />

areas thereby reducing the capacity of the holdrooms themselves. KCI currently<br />

has at least one x-ray machine per checkpoint but if that one machine goes down it<br />

essentially delays the airline until the machine is fixed. In some cases they have<br />

changed the current setup to include one magnetometer per two x-ray machines<br />

which has saved valuable space. Another disadvantage to this operation is that it<br />

spreads the function between three terminals, making it difficult to move TSA staff<br />

between positions. KCI also has a very high re-screen rate of 25 to 30 percent<br />

compared to the national average of just four percent. This is generally attributed<br />

to passengers leaving the holdroom area to go to the concessions area. It should<br />

be noted that this percentage was reduced from about 34 percent with the addition<br />

of bathrooms in the holdroom areas which again reduced the effective passenger<br />

capacity of the area. TSA has also expressed an interest in having a centralized<br />

training area in each terminal and more break rooms. TSA at KCI is capable of<br />

processing around 200 passengers per hour and in some instances have done as<br />

many as 300 per hour.<br />

For future planning requirements, a throughput of 150 passengers per lane per<br />

hour has been used which is more typical of what is being surveyed in the industry<br />

but should be reviewed periodically as activity levels change. A more centralized<br />

security area has also been established in the terminal core, split between two<br />

checkpoints, but it is also dependent on the final terminal conceptual layout.<br />

A module of “2 to 1” with a queuing depth of 30 feet has been used. Security<br />

screening lanes and area requirements are a function of the peak ten-minute<br />

throughput per number of required check-in positions. A processing time of<br />

20 seconds per passenger has been used for this analysis.<br />

The combined total of the security screening functions at KCI equals approximately<br />

24,200 square feet between the three terminals. The existing recommended total<br />

of 9,600 square feet is a direct result of a more centralized security screening area.<br />

The future 2030 demand requires an area of approximately 38,200 square feet.<br />

Circulation<br />

DRAFT<br />

The following categories represent the public circulation areas within the terminal<br />

and concourse areas which include the ticket lobby, baggage claim, secure<br />

circulation, general circulation, public seating areas, a meeters/greeters lobby for<br />

arriving passengers, and additional space for areas such as transportation and hotel<br />

courtesy phones. Each of these categories is described below.<br />

Ticket Lobby Circulation space is within the ticket lobby area leading up to the ticket<br />

counter queue. It is generally used for cross-circulation from the ticket counter to<br />

the security checkpoint areas. The current circulation depth within the three<br />

terminals ranges from 15 to 25 feet. A future planning requirement of 25 feet has<br />

been used for this analysis. Given KCI’s operational layout, what is considered<br />

Landrum & Brown Page 54<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

general circulation in the programmed area is used for the ticketing areas as well.<br />

Therefore, no existing ticket lobby circulation area is tabulated. The 2030 demand<br />

year requires 9,500 square feet of space.<br />

Baggage Claim Circulation represents the main circulation area adjacent to the<br />

claim area. As with the ticket lobby, the general circulation area handles the claim<br />

area circulation and, therefore, no square footage areas have been tabulated in the<br />

existing facility program. A depth of 25 feet for cross circulation along the full<br />

length of the claim area has been used for this analysis. By 2030 an area<br />

8,500 square feet would be required.<br />

Secure Circulation is all the area beyond the security checkpoint areas and consists<br />

primarily of the central corridor of the concourses and any adjacent egress stairs on<br />

the holdroom level. Again, given the unique operational layout of the three<br />

terminals, there are essentially no secure circulation areas except those areas that<br />

include any connecting holdrooms and vertical circulation elements such as those<br />

found in <strong>Terminal</strong> A, leading from Gate 6 down to the apron level holdroom area for<br />

Air Midwest on Gates 1 through 5. For future planning 45-foot, double-loaded<br />

corridors (i.e. gate holdrooms on both sides of the concourse) have been assumed<br />

which is a typical planning standard for longer concourses requiring moving walks.<br />

For areas not requiring assisted passenger movement a single-loaded corridor of<br />

30 feet is standard.<br />

The future calculated area is based on NBEG or an area per equivalent concourse<br />

length determined by gates. However, the actual amount of secure circulation will<br />

depend on the specific proposed concourse configurations and whether they consist<br />

of gates on one or both sides of the corridor. Using a 45-foot double-loaded<br />

concourse requires approximately 2,700 square feet per NBEG. The future 2030<br />

demand year requires 107,500 square feet of secure circulation.<br />

DRAFT<br />

The General Circulation area of the program includes all the other areas of<br />

circulation that make up the non-secure public functions of the terminal and include<br />

areas such as vertical circulation elements, corridors, and any other architectural<br />

spaces that tie the functional elements of the terminal together. For the New<br />

<strong>Terminal</strong> a planning standard of 15 percent has been used, which is typical for<br />

similarly sized terminals. The future requirement of 69,900 square feet is<br />

recommended to meet the 2030 planning level year.<br />

Public Seating includes the general waiting areas near the ticket lobby, baggage<br />

claim area, and concessions. Currently, the public seating areas are located in<br />

between the vestibules and diagonally across from each of the airlines’ baggage<br />

claim areas. The typical planning standard is to provide seating for approximately<br />

15 percent of the peak hour departing passengers and their well-wishers along with<br />

the meeters/greeters for the arriving passengers. Since no survey data was<br />

available for the historic ratio of visitors to passengers, a typical ratio of<br />

.05 visitors/passengers was used along with a LOS C standard of 15 square feet per<br />

seated passenger/visitor. Analysis shows the existing area of 16,129 square feet of<br />

seating is more than adequate to meet the current demand and exceeds the<br />

Landrum & Brown Page 55<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

recommended existing area of 1,400 square feet. This is generally due to the<br />

operational layout of the terminal and the dedicated baggage claim areas.<br />

The future 2030 demand year requires 2,200 square feet of space.<br />

The Domestic Meeters/Greeters Lobby includes the functional space required to<br />

accommodate the arriving passenger’s meters/greeters in and around the baggage<br />

claim area of the terminal. The calculations include factors such as peak hour<br />

arriving passengers, visitor to passenger ratios, square feet per visitor, and average<br />

dwell time per arriving passenger and their visitors. For this analysis a typical<br />

15 visitor per passenger ratio has been assumed along with a LOS C standard of<br />

20.5 square feet per passenger/visitor factor. Dwell times used for passengers and<br />

visitors were five minutes and 30 minutes, respectively. As stated previously, since<br />

the general circulation area of the existing terminals serve the ticket lobby and<br />

baggage claim area, circulation requirements for meters/greeters lobbies do not<br />

exist. The 2030 demand year requires a total area of 10,900 square feet for a<br />

domestic meeters/greeters lobby to meet the projected peak hour level of activity.<br />

Currently KCI has approximately 1,144 square feet of area allocated to<br />

Transportation and Hotel Courtesy Phones which is located in each of the airlines’<br />

baggage claim areas. With the replication of terminals and exclusive claim areas,<br />

this area is generally oversized to meet current demand levels of activity. A typical<br />

planning standard of 90 to 110 square feet per 1,000,000 annual enplanements is<br />

used. For this analysis a factor of 110 square feet has been used. This results in<br />

an area of approximately 700 square feet required for the transportation and hotel<br />

courtesy phone area by the year 2030.<br />

Restrooms<br />

DRAFT<br />

This category represents the area of public space allocated to passenger restroom<br />

facilities. The program has been divided between the non-secure (ticketing,<br />

baggage claim, and concessions areas) and secure (concourse areas beyond<br />

security) portions of the terminal and related concourses.<br />

Restrooms by code should have as many toilets for women as toilets and or urinals<br />

for men. Based on the airport’s lease drawings the majority of the restrooms have<br />

more fixtures for men than women. The exception is where restrooms have been<br />

located inside the holdroom areas where the ratio is equal. <strong>Planning</strong> factors are<br />

based on a typical 2.5-square foot per peak hour total O&D passenger and their<br />

visitors for non-secure areas, and a restroom module located in the secure<br />

concourse areas for every eight EQA. The typical module for concourses serving<br />

O&D activity is 1,600 square feet which includes both men’s and women’s facilities.<br />

The existing non-secure area measures approximately 17,977 square feet while the<br />

secure area measures only 5,040 square feet. This is due to the current functional<br />

layout of the terminals because of the limited area available inside the secure<br />

holdroom areas. An existing recommended non-secure/secure area requirement is<br />

8,400 and 5,600 square feet, respectively. The 2030 demand level year requires<br />

an area of 10,900 square feet for non-secure areas of the terminal and<br />

5,600 square feet for the secure concourse area locations.<br />

Landrum & Brown Page 56<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Other Space<br />

This category accounts for miscellaneous tenant space which includes areas such as<br />

business centers and shuttle services. Other areas accounted for include display<br />

areas, information counters, etc. A planning factor of ten square feet per 100,000<br />

ANNEP has been assumed for the miscellaneous tenant and business center<br />

requirement, 20 square feet for shuttle services, and five square feet for the<br />

information counters and display areas. The total 2030 requirement is for<br />

approximately 11,100 square feet.<br />

3.2.3.5 Non-Public Space<br />

Non-Airline Tennant Space<br />

This category includes the “back of house” area that is not accessible to the public<br />

and generally consists of areas such as airport administration (if not in a remote<br />

location), airport police, and any airport-related offices and support space.<br />

Airport Administration represents the total area devoted to airport administration<br />

including city space functions. It generally consists of reception areas, offices,<br />

conference rooms, storage areas, work areas, and rooms for special events such as<br />

VIP press conferences, and other airport-related operations space such as airport<br />

police. The requirements for airport administration are a function of staffing<br />

generated by the airport. This area is principally located in an office complex<br />

adjacent to the terminal; however, some space can be allocated within the terminal<br />

area itself. A review of the airport lease drawings shows there is approximately<br />

29,300 square feet of administration/operations space within the terminal area.<br />

No change is anticipated for the New <strong>Terminal</strong>, but future space requirements<br />

should be reviewed by the KCAD.<br />

Other Tenants accounts for any other miscellaneous tenant space within the<br />

terminal area. A planning factor of ten square feet per 100,000 ANNEP has been<br />

used for the analysis. The 2030 demand year requires approximately 6,600 square<br />

feet of additional space.<br />

Other Space<br />

DRAFT<br />

This category accounts for the non-public restroom facilities and circulation areas<br />

typically found in airline operations and airport administrative space.<br />

The majority of Non-Public Restrooms, which in some areas include locker space,<br />

are accounted for on the apron level of all three terminal buildings. The existing<br />

area is approximately 22,197 square feet. The current ratio of non-public space to<br />

non-public restrooms has been used for future planning requirements and results in<br />

an area of 2,900 square feet required for non-public restrooms by 2030.<br />

The Non-Public circulation area provides access to the airline operations, airport<br />

administration areas, concessions, support, and other areas typically not used by<br />

the traveling public. Typical planning standards base this on 10 to 15 percent of<br />

Landrum & Brown Page 57<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

the non-public functional areas. KCI has a relatively high ratio of 30.4 percent<br />

which can be attributed to the overall operational layouts of the three terminals.<br />

It should also be noted that this area of the program is often a matter of<br />

interpretation by the consultant as to whether or not to include this space in the<br />

public or non-public category. For future planning requirements a ratio of ten<br />

percent has been used requiring an area of 26,400 square feet for non-public<br />

circulation by 2030.<br />

<strong>Terminal</strong> Function<br />

This category accounts for all the mechanical, electrical, utility, janitorial, storage,<br />

and shop areas as well as the structure and non-net areas of the building.<br />

These areas combined with the other functional areas of the terminal and concourse<br />

locations create the total gross footprint of the building.<br />

The Maintenance/Janitorial/Storage/Shops area accounts for the building<br />

maintenance facilities and consists of shops, storage, office space, circulation, and<br />

janitorial closets. Typical planning standards require one to two percent of the total<br />

functional areas. For this analysis 1.5 percent has been used, which closely reflects<br />

the existing ratio of 1.6 percent. The existing recommended area of 11,200 square<br />

feet reflects the future consolidation of a single terminal building.<br />

The 2030 demand level requires 8,500 square feet for the building maintenance<br />

facilities.<br />

The Mechanical/Electrical/Telephone/Plumbing area of the program includes all the<br />

utility support areas for the terminal and is generally a percentage of the enclosed<br />

functional areas of the terminal, typically 10 to 12 percent. Recent trends in<br />

computer systems, telecommunications, and other building-related systems have<br />

increased the demand for these areas within the terminal building. Some of these<br />

areas can be accommodated in the airline operations area, whereas common use<br />

systems need to be located in the airport-controlled areas. For this analysis<br />

12.2 percent of the functional area has been used which is an increase from the<br />

existing 11.2 percent ratio. The existing area of 101,710 square feet is adequate to<br />

meet the current activity level experienced by the Airport. The total 2030<br />

requirement is 103,200 square feet for utility support areas.<br />

DRAFT<br />

The Building Systems (Structural/Non-Net/Void) ties together all the previous<br />

functional elements of the program to provide a better estimate of the total gross<br />

building area. Unusable space or special structures, often make up this category of<br />

the program, and depending on how the gross areas are determined, a factor of<br />

two to five percent is typically added for this category.<br />

The existing terminal gross area was taken from the airport terminal space<br />

allocation drawings. All functional elements were then added together and<br />

subtracted from the gross area footprint per terminal to calculate the non-net areas<br />

of the three buildings. A ratio of three percent has been used for this analysis<br />

resulting in a requirement of approximately 24,500 square feet by 2030 for building<br />

systems area.<br />

Landrum & Brown Page 58<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.2.4 SECURITY SCREENING CHECKPOINT CONSIDERATIONS<br />

Since the formation of the TSA, the layout of Security Screening Checkpoints<br />

(SSCP) has evolved. Some of this evolution is due to equipment standardization by<br />

the TSA, but some is due to advancements in technologies. For example, the<br />

traditional x-ray machines are being replaced by dual-view machines that can<br />

provide images in two directions as well as classify objects based on molecular<br />

weights. Another example of technology changes includes the addition of<br />

equipment such as the <strong>Advance</strong>d Imaging Technology (AIT) equipment and<br />

Explosive Trace Detection (ETD). The future will continue to see the advancement<br />

of technology that could include Liquid Explosive Detection (LED) equipment, as<br />

well as further advances in the carry-on baggage x-ray technology, and higher<br />

capacity/higher speed AIT type equipment.<br />

3.2.4.1 Checkpoint Layout<br />

TSA currently publishes guidelines for SSCP layouts that include the various<br />

equipment types being utilized across the country. The latest version of the<br />

standard was issued in October 2012, and provides the overall equipment base<br />

configurations. The space planning criteria has continued to evolve based upon the<br />

information gathered about the overall operation of the current configurations.<br />

One of the parameters noted recently pertains to throughput in lanes that utilize<br />

AIT units as the primary passenger screening device. The traditional lane<br />

configuration included two x-ray machines to screen carry-on baggage, with a<br />

single, shared Walk Through Metal Detector (WTMD) between the two x-ray lines.<br />

This was based upon the x-ray machine throughput versus the WTMD throughput.<br />

The WTMD throughput was fairly high, but the WTMD units have been supplanted<br />

by AIT units that have much lower throughput. At the same time, airlines have<br />

implemented checked baggage fees, which increased the quantity of screened<br />

carry-on baggage. Between these two factors, the TSA now recommends that each<br />

x-ray machine have a dedicated AIT/WTMD instead of the shared lane to equalize<br />

throughput. This approach increases the overall width of each processing lane.<br />

3.2.4.2 Throughput<br />

DRAFT<br />

The throughput of a SSCP lane is based upon several factors that include travel<br />

experience of the passengers, the type of equipment in use at each airport, and the<br />

overall configuration among other factors. One consideration to study is the impact<br />

of implementing the TSA Pre✓ program. This program is used to pre-screen<br />

frequent flyer passengers and determine the possible threat that each passenger<br />

could pose to commercial aviation. For passengers that are part of the Pre✓<br />

program, the screening requirements are reduced, allowing the passenger to leave<br />

liquids and electronics within bags, leave on shoes and belts, and use WTMD type<br />

equipment instead of AIT equipment. This equates to faster throughput for these<br />

lines than that of a standard SSCP lane. However, the current TSA randomly<br />

selects people in the Pre✓ program to process through the more stringent regular<br />

passenger screening lanes. This also holds true for some international flight<br />

exclusions as well. Based on experience with the program, the percentage of<br />

people allowed through the Pre✓ lane is far lower than the percentage that are<br />

Landrum & Brown Page 59<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

enrolled, creating much longer queue lines and much slower processing times than<br />

would be expected. While it is expected that this will improve in the future, it is<br />

important to note that being in the Pre✓ program does not automatically ensure<br />

that a person will be allowed to process through the Pre✓ lane. For purposes of<br />

this analysis, the throughputs shown in Table 3.2-3, Expected Passenger<br />

Throughputs per Lane Type, are expected. Also, in order to account for different<br />

possible scenarios, percentages will be calculated for each year to show a possible<br />

range of lane requirements, as shown in Table 3.2-4, Checkpoint Lane<br />

Requirements.<br />

Table 3.2-3<br />

EXPECTED PASSENGER THROUGHPUTS PER LANE TYPE<br />

Lane Type Throughput Notes:<br />

TSA Pre✓ Lane/Trusted Traveler 5.0<br />

Standard Passenger Lane with AIT 2.4<br />

Special Assistance/Family Passenger<br />

Lane<br />

Source:<br />

Ross & Baruzzini<br />

Table 3.2-4<br />

CHECKPOINT LANE REQUIREMENTS<br />

1.5<br />

Based on observed throughputs at<br />

existing facility at KCI<br />

Based on observed throughputs at<br />

existing facility at KCI<br />

Checkpoint Lane Types<br />

Percentage of Passengers<br />

TSA Pre✓ Lane/Trusted Traveler 10% 25% 50%<br />

Standard Passenger lane with AIT 85% 70% 45%<br />

Special Assistance/Family Passenger Lane 5% 5% 5%<br />

Source:<br />

Ross & Baruzzini<br />

DRAFT<br />

The TSA Pre✓ program is still fairly new, so the long-term percentage of<br />

passengers that will enroll in this program is unknown. Some estimates place<br />

participation as high as 75 percent of the passenger population, but this is<br />

considered an optimistic estimate. Likewise, the current population of passengers<br />

enrolled in Pre✓ is still fairly low. For the comparison of various scenarios, the<br />

quantity of lanes is calculated using differing percentages of passengers in the Pre✓<br />

program.<br />

Landrum & Brown Page 60<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.2.4.3 Calculations<br />

Current passenger counts and predicted passenger counts for 2025 and 2030 are<br />

based on the KCI Forecast Update dated April 27, 2012 as provided by L&B.<br />

Table 3.2-5, Peak Hour Passenger Statistics, indicates the expected Peak Hour<br />

Enplanements forecasted for the years noted. The numbers indicate the worst case<br />

scenario for peak hour, and this was used to determine the maximum number of<br />

lanes required for the quantities shown.<br />

Table 3.2-5<br />

PEAK HOUR PASSENGER STATISTICS<br />

Year<br />

2012<br />

Year<br />

2025<br />

Year<br />

2030<br />

Peak Hour Enplanements - Domestic 2,159 2,688 2,944<br />

Peak Hour Enplanements - International 125 235 257<br />

Total Passengers Enplaned 2,284 2,923 3,201<br />

Checkpoint Throughput – Passengers per<br />

Minute<br />

Passenger Processing Queue Time (Maximum) – 10<br />

Minutes Adjusted Load Factor<br />

Source:<br />

Adjusted Checkpoint Throughput – Passengers<br />

per Minute<br />

Ross & Baruzzini<br />

38.1 48.8 53.4<br />

0.86 0.86 0.9<br />

32.8 42 46<br />

DRAFT<br />

The calculation for SSCP lane quantity requirements will include three different<br />

percentages to account for the passengers enrolled in the TSA Pre✓ program – ten<br />

percent, 25 percent, and 50 percent. These percentages are meant to fulfill two<br />

roles. First, this allows for an assessment of the current situation where only a<br />

small percentage of passengers are enrolled in Pre✓, which is the main reason for<br />

the inclusion of the ten percent figure. Second, the 25 percent and 50 percent<br />

figures account for the impact of the Pre✓ program for year 2025 and 2030.<br />

Overall, it is expected that the enrollment will continue to grow, but the top figure<br />

of 50 percent is intended to be conservative to ensure that sufficient lanes are<br />

provided.<br />

As with all calculations of this type, it is important to bear in mind that the<br />

calculation is based on the peak hour. The quantity of lanes required for non-peak<br />

times are expected to be much lower. The checkpoint throughput in passengers<br />

per minute is noted above, assuming that all passengers for the peak hour are<br />

processed within that hour. This assumes that the overall queue will be very<br />

limited, with little to no queue time. The Adjusted Checkpoint Throughput is based<br />

upon allowing for the peak load to be processed over the course of 70 minutes,<br />

allowing for a ten-minute average queue to form during peak screening times, as<br />

shown in Table 3.2-6, Lane Requirements for Minimal Queue Time – 2012.<br />

Landrum & Brown Page 61<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Currently the existing SSCPs in the KCI terminals are distributed throughout each<br />

terminal facility with approximately four SSCPs per terminal, for a total of<br />

16 SSCPs. Because of this arrangement, the perception is that the wait times are<br />

low. It would be a customer service policy decision to increase the allowable wait<br />

time at the checkpoint.<br />

Table 3.2-6<br />

LANE REQUIREMENTS FOR MINIMAL QUEUE TIME - 2012<br />

Expected Lane Requirements -2012<br />

Population in TSA Pre✓/Trusted<br />

Traveler<br />

Percentage<br />

Total<br />

Passengers<br />

Expected<br />

Throughput<br />

Total<br />

Lanes<br />

10% 3.9 5.0 0.8<br />

Standard Passenger lane with AIT 85% 32.4 2.4 13.5<br />

Special Assistance/Family Passenger<br />

Lane<br />

Expected Lane Requirements – 2012<br />

Population in TSA Pre✓/Trusted<br />

Traveler<br />

5% 2 1.5 1.4<br />

15.7<br />

25% 9.6 5.0 2<br />

Standard Passenger lane with AIT 70% 226.7 2.4 11.2<br />

Special Assistance/Family Passenger<br />

Lane<br />

Expected Lane Requirements – 2012<br />

Population in TSA Pre✓/Trusted<br />

Traveler<br />

5% 211.2 1.5 1.4<br />

14.6<br />

50% 19.1 5.0 3.9<br />

Standard Passenger lane with AIT 45% 17.2 2.4 7.2<br />

Special Assistance/Family Passenger<br />

Lane<br />

DRAFT<br />

5% 2 1.5 1.4<br />

12.5<br />

Source:<br />

Ross & Baruzzini<br />

In order to meet the requirements for the current expected peak hour, the quantity<br />

of lanes range from 16 lanes assuming only a ten-percent Pre✓ enrollment down to<br />

approximately 13 SSCPs lanes assuming a 50 percent Pre✓ enrollment. If the<br />

allowable processing time for the peak hour is allowed to be extended to<br />

70 minutes, which will allow a queue line to form, then the quantity of lanes would<br />

be as shown in Table 3.2-7, Lane Requirements for Peak Hour Load<br />

Processed in 70 Minutes – 2012; Table 3.2-8, Lane Requirements for Peak<br />

Hour Load Processed in 70 Minutes – 2025; and Table 3.2-9, Lane<br />

Requirements for Peak Hour Load Processed in 70 Minutes – 2030.<br />

Landrum & Brown Page 62<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 3.2-7<br />

LANE REQUIREMENTS FOR PEAK HOUR LOAD PROCESSED IN 70 MINUTES -<br />

2012<br />

Expected Lane Requirements – 2012<br />

Percentage<br />

Total<br />

Passengers<br />

Expected<br />

Throughput<br />

Total<br />

Lanes<br />

Population in TSA Pre✓/Trusted Traveler 10% 3.3 5.0 0.7<br />

Standard Passenger lane with AIT 85% 27.9 2.4 11.7<br />

Special Assistance/Family Passenger<br />

Lane<br />

Expected lane Requirements – 2012<br />

5% 1.7 1.5 1.2<br />

Population in TSA Pre✓/Trusted Traveler 25% 8.2 5.0 1.7<br />

Standard Passenger<br />

DRAFT<br />

lane with AIT 70% 23 2.4 9.6<br />

Special Assistance/Family Passenger<br />

5% 17 1.5 1.2<br />

Lane<br />

12.5<br />

Expected lane Requirements – 2012<br />

Population in TSA Pre✓/Trusted Traveler 50% 16.4 5.0 3.3<br />

Standard Passenger lane with AIT 45% 14.8 2.4 6.2<br />

Special Assistance/Family Passenger<br />

5% 1.7 1.5 1.2<br />

Lane<br />

10.7<br />

Source: Ross & Baruzzini<br />

In order to meet the adjusted processing time for peak hour, allowing for the peak<br />

hour passengers to be processed in approximately 70 minutes, the quantity of<br />

SSCP lanes would range from 14 lanes, assuming only a ten percent Pre✓<br />

enrollment, down to approximately 11 lanes, assuming a 50 percent Pre✓<br />

enrollment.<br />

13.6<br />

Landrum & Brown Page 63<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 3.2-8<br />

LANE REQUIREMENTS FOR PEAK HOUR LOAD PROCESSED IN 70 MINUTES –<br />

2025<br />

Expected Lane Requirements -2025<br />

Percentage<br />

Total<br />

Passengers<br />

Expected<br />

Throughput<br />

Total<br />

Lanes<br />

Population in Pre✓/Trusted Traveler 10% 34.2 5.0 0.9<br />

Standard Passenger lane with AIT 85% 35.7 2.4 14.9<br />

Special Assistance/Family Passenger Lane 5% 2.1 1.5 1.4<br />

Expected lane Requirements – 2012<br />

Population in Pre✓/Trusted Traveler 25% 10.5 5.0 2.1<br />

Standard Passenger lane with AIT 70% 29.4 2.4 12.3<br />

Special Assistance/Family Passenger Lane 5% 2.1 1.5 1.4<br />

Expected lane Requirements – 2012<br />

Population in Pre✓/Trusted Traveler 50% 21 5.0 4.2<br />

Standard Passenger lane with AIT 45% 18.9 2.4 7.9<br />

Special Assistance/Family Passenger Lane 5% 2.1 1.5 1.4<br />

Source:<br />

Ross & Baruzzini<br />

17.2<br />

15.8<br />

13.5<br />

Table 3.2-9<br />

LANE REQUIREMENTS FOR PEAK HOUR LOAD PROCESSED IN 70 MINUTES –<br />

2030<br />

Expected Lane Requirements -2030<br />

DRAFT<br />

Percentage<br />

Total<br />

Passengers<br />

Expected<br />

Throughput<br />

Population in Pre✓/Trusted Traveler 10% 4.6 5.0 1<br />

Total<br />

Lanes<br />

Standard Passenger lane with AIT 85% 39.1 2.4 16.3<br />

Special Assistance/Family Passenger Lane 5% 2.3 1.5 1.6<br />

Expected lane Requirements – 2012<br />

Population in Pre✓/Trusted Traveler 25% 11.5 5.0 2.3<br />

Standard Passenger lane with AIT 70% 32.2 2.4 13.5<br />

Special Assistance/Family Passenger Lane 5% 2.3 1.5 1.6<br />

Expected lane Requirements – 2012<br />

Population in Pre✓/Trusted Traveler 50% 23 5.0 4.6<br />

Standard Passenger lane with AIT 45% 20.7 2.4 8.7<br />

Special Assistance/Family Passenger Lane 5% 2.3 1.5 1.6<br />

18.9<br />

17.4<br />

14.9<br />

Source:<br />

Ross & Baruzzini<br />

Landrum & Brown Page 64<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Based upon the calculations, it is apparent that the quantity of SSCP lanes required<br />

can vary widely. However, looking at the 2012 Total Lane requirements (using the<br />

adjusted throughput as a basis) for a ten percent Pre✓ population and the 2030<br />

Total Lane Requirements for a 50-percent Pre✓ population, it is expected that the<br />

SSCP lane quantities would be close to being the same. Based upon the<br />

calculations, approximately 15 lanes would be required at peak times if the overall<br />

processing of the peak hour is allowed to extend to approximately 70 minutes.<br />

The current recommendation of 16 lanes allows a buffer for equipment maintenance<br />

and failure, unscheduled excess traffic, and other unforeseen circumstances.<br />

Another aspect to consider is the advancement of technology and passenger<br />

familiarity with the process for that equipment. While the AIT units have been in<br />

use for several years as specific facilities, the implementation of these units at all<br />

airports is still on-going. The metrics used in this calculation are based upon<br />

observed passenger throughputs on the existing equipment at the existing facilities.<br />

Over time, it would be expected that the screening time per passenger would go<br />

down based upon familiarity with the process, allowing for a higher PPM metric for<br />

the standard passenger screening. Also, the advancement in screening equipment<br />

such as LED could also negate the requirement to remove liquids, aerosols, and<br />

gels from baggage for screening, reducing the time required for screening.<br />

These factors, in conjunction with customer service metrics for allowable screening<br />

wait times, should be considered when determining the total quantity of SSCP lanes<br />

required.<br />

3.2.4.4 Employee Screening<br />

DRAFT<br />

All of the discussion above was based upon loadings for screening of passengers<br />

only. Another factor to consider is the screening of employees including airline<br />

ramp workers, airline customer service representatives, flight crews, and tenant<br />

and concession personnel. At the present time, the screening of employees that<br />

have Secure Identification Display Area (SIDA) or Secure Area badges through<br />

security screening checkpoint type of equipment is not mandated. There has been<br />

much discussion of implementing requirements of this type, so this should be<br />

considered as part of the overall exercise.<br />

For purposes of this document, the overall population will be considered to be<br />

approximately ten percent of the passenger load. Based upon practices at other<br />

airports, there are several different scenarios that can be considered. Many of<br />

these scenarios will need to be vetted against the staffing plan for the TSA or<br />

checkpoint screening company to compare the impact that each scenario would<br />

have on the overall staffing requirements.<br />

Remote Employee Screening: Several airports such as Denver International Airport<br />

or Atlanta Hartsfield (ATL) have remote employee entry points in remote parking<br />

areas. The employee is vetted upon entry into the parking area. At DIA, the<br />

employee enters a building in the parking area and gains entry to a bus<br />

transportation area by use of the Access Control System that includes biometric<br />

verification. This facility also has SSCP lanes, and random employees are selected<br />

for screening. However, if full employee screening were mandated, this facility<br />

Landrum & Brown Page 65<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

could be used to screen all employees prior to allowing them to board a bus that<br />

drops the employees on the airside of the airport. This process allows for the<br />

employees to be screened in a separate area from the traveling public, but does not<br />

allow for the easy sharing of screening personnel between the employee SSCP and<br />

the traveling public SSCP.<br />

Separate Employee Screening: Airports such as Chicago O’Hare Airport (ORD)<br />

utilizes employee SSCPs that are located between the traveling public checkpoints.<br />

These allow for employees or goods to be screened, but not in a shared<br />

environment as the traveling public. However, as these SSCPs are in close<br />

proximity to the traveling public SSCPs, the sharing of screening personnel is easily<br />

accomplished. Also, as this configuration is usually from public to sterile, all<br />

badged employees including sterile area personnel or airline crews would be able to<br />

be processed through this SSCP. This would remove the common disruption caused<br />

by these personnel passing through the traveling public SSCP.<br />

Screening of employees through the traveling public SSCPs: At many airports,<br />

employees that need to pass from public to sterile are required to be screened<br />

through a traveling public SSCP. While this does maximize the efficiency of the<br />

screening staff, it is not ideal from a customer service point of view and can be<br />

disruptive to the passenger screening process.<br />

In order to maximize the efficiency of the screening staff utilization and also<br />

maintain high service levels for the traveling public, it is recommended that the<br />

process for screening employees and goods be planned and space allocated for<br />

screening locations separate from the primary passenger SSCPs, even if these are<br />

not implemented on day one. (See Table 3.2-10, Employee/Crew Screening).<br />

Table 3.2-10<br />

EMPLOYEE/CREW SCREENING<br />

DRAFT<br />

Employee Crew Quantities Year 2012 Year 2025 Year 2030<br />

10% of Passenger Loading – Peak Hour 228.4 292.3 320.1<br />

Employee/Crew Per Minute 3.8 4.9 5.3<br />

Source:<br />

Ross & Baruzzini<br />

Based on using a ten percent of passenger loading factor, and assuming that the<br />

employee/crew screening process will be similar to the Trusted Traveler and Known<br />

Crewmember process, the recommendation is to provide two SSCP lanes. For the<br />

initial build-out, only one SSCP lane may be required to be staffed. However, for<br />

redundancy of equipment, having two SSCP lanes would ensure that a single<br />

equipment failure would not shut down the employee screening area.<br />

Goods Screening: In order to make the best use of personnel, it would be<br />

recommended that the design include provisions for goods screening at the<br />

employee/crew area or in an area adjacent to this SSCP. Goods screening usually<br />

entails a large, pallet style screening device to check for contraband or weapons in<br />

goods being delivered for concessions. In many cases, personnel are required to<br />

Landrum & Brown Page 66<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

pass from public to sterile as part of the screening, which can require the screening<br />

of employees as part of the goods screening process. In some cases, the screening<br />

is conducted by the screening personnel and goods are stored in locked areas on<br />

both sides. If this is the case, the plan would require the implementation of locked<br />

areas on the public side and sterile side for storage of the goods. Also, as many<br />

items are refrigerated or frozen, these storage areas would require refrigerated or<br />

frozen storage areas.<br />

The screening personnel are used not only for the traveling public SSCP, they are<br />

also utilized in the Check Baggage Screening areas to perform ETD and searches in<br />

the Level 3 screening areas as well as possibly staff employee, crew, and goods<br />

screening areas. Accounting for these functions as part of the initial design and<br />

providing a means for these personnel to transit directly from the various areas to<br />

other areas will significantly increase the efficiency and utilization of the screening<br />

personnel. In some newer facilities, these types of areas have been stacked<br />

vertically and dedicated stairs have been provided to allow direct access between<br />

these areas. Inclusion of these vertical circulation routes in the initial design and<br />

accounting for any access control or other surveillance required as part of these<br />

elements will simplify any future implementations or changes in security for the life<br />

of the facility.<br />

3.2.4.5 Conclusion<br />

In order to ensure long-term viability of the SSCP space or spaces, it is important<br />

to plan sufficient space for not only upcoming equipment, but also for a sufficient<br />

quantity of SSCP lanes. Other facilities that have been constructed or renovated<br />

since the creation of the TSA have provided screening spaces that included space<br />

for future SSCP lanes. While not all of the SSCP lanes may be implemented on day<br />

one, allocating the space to add SSCP lanes facilitates future expansion, as well as<br />

allowing for the implementation of newer generations of screening equipment,<br />

without necessarily requiring the removal of the existing equipment. This flexibility<br />

will serve the Airport well and allow for a more seamless operation in the future.<br />

DRAFT<br />

3.2.5 SUMMARY OF TERMINAL BUILDING REQUIREMENTS<br />

KCI’s <strong>Terminal</strong> Improvement <strong>Program</strong> (TIP), which was completed in 2004,<br />

renovated and added holdroom space, restrooms within the secured holdrooms,<br />

and included all new mechanical and electrical systems. Even after the program<br />

was completed, merging airlines, reduced flight schedules, and inefficient<br />

operations and aging infrastructure make interoperation between the three<br />

terminals increasingly difficult. A replacement terminal is necessary to supplant the<br />

aging infrastructure of the three terminals and their increasing functional<br />

obsolescence. It should be noted that the future program assumes greater<br />

efficiencies through consolidation of the functions into one terminal that are<br />

replicated in the current operational layouts of the three terminals. This reduces<br />

the overall gross terminal area need.<br />

Landrum & Brown Page 67<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

KCI currently has a gross terminal area of approximately 1,105,100 square<br />

feet. The existing recommended facilities for 2012 require a gross terminal area of<br />

864,400 square feet indicating the current facilities are oversized for the current<br />

level of peak hour activity. There are exceptions to this assessment. Certain areas<br />

of the terminals require additional space to meet demand requirements, such as<br />

the operational layouts of the holdroom areas, security, secure concessions and<br />

circulation areas, baggage claim circulation, integration of checked baggage<br />

screening into the baggage handling system, and some individual airline operations<br />

space.<br />

The new terminal program is split into two planning implementation levels for 2025<br />

and 2030 as seen in Table 3.2-11.<br />

Table 3.2-11<br />

SUMMARY OF THE TERMINAL AREA PROGRAM<br />

Aircraft Parking Positions<br />

Forecast Year<br />

2025 2030<br />

Total Functional <strong>Terminal</strong> Area 791,270 884,470<br />

Total Gross <strong>Terminal</strong> Area 912,470 1,020,870<br />

Sources:<br />

<strong>Terminal</strong> Area <strong>Program</strong> / Landrum & Brown<br />

The future program requirements have been shown to be less than the current<br />

aggregated terminal area of the existing three terminals, indicating an excess of<br />

throughout the projected future. Since that the gross terminal area of the existing<br />

facilities is spread over three separate terminals, many of the future program<br />

requirement improvements cannot be easily met through expansion or contractions<br />

of the current terminal design with its concrete structure and narrow width hemmed<br />

in on the airside by existing gates and on the landside by existing curb, roadways<br />

and structured parking. Many factors, including airline consolidation, aging<br />

facilities, and difficulties in interoperability among multiple processors, have led to<br />

the recommendation that a new single consolidated terminal with expansion<br />

capabilities is the preferred choice to meet the <strong>Advance</strong> <strong>Terminal</strong> <strong>Planning</strong> project<br />

goals.<br />

DRAFT<br />

3.3 Concessions Requirements<br />

This section highlights current features of the concession program at the Airport<br />

which will be beneficial to the Airport operators when the time comes to develop a<br />

thriving concessions program in the New <strong>Terminal</strong>. Also discussed are some of the<br />

features that should be included in the future concessions program.<br />

Landrum & Brown Page 68<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.3.1 EXISTING AIRPORT RETAIL PROGRAM REVIEW<br />

The historical financial performance of the concession program at KCI was reviewed<br />

for the past two fiscal years. Although the future concession program will be<br />

substantially different, it is important to consider the performance of the existing<br />

concessions as indicators of consumer preferences and behavior that may affect<br />

future development. Table 3.3-1, Airport Space by Location, presents a<br />

summary of the existing concession space in the three terminals at the Airport by<br />

type and location.<br />

Table 3.3-1<br />

AIRPORT CONCESSION SPACE BY LOCATION (SQ. FT.)<br />

Food Service<br />

Retail<br />

<strong>Terminal</strong> A <strong>Terminal</strong> B <strong>Terminal</strong> C Total Airport<br />

Space<br />

% of<br />

Total<br />

Space<br />

% of<br />

Total<br />

Space<br />

% of<br />

Total<br />

Space<br />

% of<br />

Total<br />

Airside 72 1% 408 2% 172 3% 652 2%<br />

Landside 4,720 75% 14,998 75% 4,234 71% 23,952 75%<br />

Total Food<br />

Service<br />

4,792 76% 15,406 78% 4,406 74% 24,604 77%<br />

Airside - 0% - 0% 82 1% 82 0%<br />

Landside 1,498 24% 4,469 22% 1,489 25% 7,456 23%<br />

Total Retail 1,498 24% 4,469 22% 1,571 26% 7,538 23%<br />

Total<br />

Concession<br />

Space<br />

Source:<br />

DRAFT<br />

6,290 100% 19,875 100% 5,977 100% 32,142 100%<br />

Kansas City Aviation Department<br />

The concessions area in the three terminals currently includes over 32,000 square<br />

feet. Approximately 730 square feet is allocated to concessions in the post-security<br />

areas of the terminals. Pre-security concessions account for 98 percent of the<br />

concession space, which is unusual in comparison with other U.S. airports.<br />

Over 60 percent of the concession space at KCI is located in <strong>Terminal</strong> B. In each of<br />

the three terminals, nearly three-fourths of the concession space is allocated to<br />

food service concessions. The remaining concession space is primarily allocated to<br />

convenience retail stores, with three exceptions on Concourse B: PGA Tour Shop;<br />

Babies on the Go, that offers diapers, baby wipes, snacks and other products<br />

targeted towards parents with infants; and a shoeshine stand and Shine on the Go.<br />

Figure 3.3-1, Food Service Concession Space And Gross Sales, FY 2011, and<br />

Figure 3.3-2, Retail Concession Space And Gross Sales, FY 2011, show the<br />

concession space allocated and the gross sales generated, by concession type.<br />

Generally, concession space and gross sales are closely correlated, although the<br />

<strong>Terminal</strong> C concessions produce a higher percentage of both food service and retail<br />

sales than the percentage of space allocated for each category.<br />

Landrum & Brown Page 69<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 3.3-1<br />

FOOD SERVICE CONCESSION SPACE AND GROSS SALES, FY 2011<br />

70%<br />

60%<br />

50%<br />

40%<br />

63%<br />

59%<br />

30%<br />

20%<br />

19%<br />

18%<br />

18%<br />

24%<br />

10%<br />

0%<br />

Note:<br />

Source:<br />

Fiscal year sales are estimates based on CY10 and CY11 data.<br />

Kansas City Aviation Department; HMSHost<br />

Figure 3.3-2<br />

RETAIL CONCESSION SPACE AND GROSS SALES, FY 2011<br />

70%<br />

60%<br />

50%<br />

<strong>Terminal</strong> A <strong>Terminal</strong> B <strong>Terminal</strong> C<br />

% of Total Concession Space % of Total Sales<br />

DRAFT<br />

59%<br />

52%<br />

40%<br />

30%<br />

20%<br />

20%<br />

16%<br />

21%<br />

32%<br />

10%<br />

0%<br />

<strong>Terminal</strong> A <strong>Terminal</strong> B <strong>Terminal</strong> C<br />

% of Total Concession Space % of Total Sales<br />

Source:<br />

Kansas City Aviation Department; The Paradies Shops<br />

Landrum & Brown Page 70<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 3.3-2, Concession Productivity, Fiscal Years 2010-2011, lists a<br />

summary of food service and retail concession sales, and productivity statistics for<br />

fiscal years 2010 and 2011. Table 3.3-3, Revenue to KCAD, Years Ending<br />

April 30, presents a summary of revenue for years 2010 and 2011.<br />

Table 3.3-2<br />

CONCESSION PRODUCTIVITY, FISCAL YEARS 2010-2011<br />

Food Service<br />

Source:<br />

Sales<br />

Sales/<br />

Enplanement<br />

Square<br />

Feet<br />

Kansas City Aviation Department; HMSHost; The Paradies Shops<br />

Table 3.3-3<br />

REVENUE TO KCAD, YEARS ENDING APRIL 30<br />

Square Feet/<br />

Thousand<br />

Enplanements<br />

Note: Concession sales estimates are by fiscal year (ending June 30)<br />

Source: Kansas City Aviation Department; HMSHost; The Paradies Shops<br />

Sales/<br />

Square Foot<br />

2011 $ 18,525,769 $ 3.71 24,604 4.92 $ 753<br />

2010 $ 17,717,169 $ 3.58 24,604 4.97 $ 720<br />

Total Retail<br />

2011 $ 6,163,465 $ 1.23 7,538 1.51 $ 818<br />

2010 $ 5,917,456 $ 1.20 7,538 1.52 $ 785<br />

Total<br />

2011 $ 24,689,234 $ 4.94 32,142 6.43 $ 768<br />

2010 $ 23,634,625 $ 4.78 32,142 6.50 $ 735<br />

Food Service<br />

Retail<br />

DRAFT<br />

2010 2011<br />

Sales $ 18,345,719 $ 19,248,041<br />

Revenue to the KCAD $ 1,625,321 $ 1,763,036<br />

Effective Rent Percentage 8.9% 9.2%<br />

Sales $ 5,529,380 $ 6,472,213<br />

Revenue to the KCAD $ 777,780 $ 963,758<br />

Effective Rent Percentage 14.1% 14.9%<br />

Landrum & Brown Page 71<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.3.2 COMPARABLE AIRPORT CONCESSION PERFORMANCE<br />

In order to gauge the general performance of KCI’s concession program, the<br />

concession performance was examined at ten airports of similar size to KCI as listed<br />

in Table 3.3-4, Comparable Airports.<br />

Table 3.3-4<br />

COMPARABLE AIRPORTS<br />

IATA Code<br />

Source:<br />

SMF<br />

BNA<br />

OAK<br />

MKE<br />

MEM<br />

YYC<br />

STL<br />

PDX<br />

SAN<br />

YUL<br />

AirProjects, Inc.<br />

Airport Name<br />

Sacramento International<br />

Nashville International<br />

Oakland International<br />

General Mitchell International (Milwaukee)<br />

Memphis International<br />

Calgary International<br />

Lambert-St. Louis International<br />

Portland International<br />

San Diego International<br />

Montreal-Trudeau International<br />

Figure 3.3-3, Concession Space by Type, 2010, shows a comparison of the<br />

total food service and retail concession space for each airport listed in Table 3.3-4.<br />

DRAFT<br />

Figure 3.3-3<br />

CONCESSION SPACE BY TYPE, 2010<br />

Source:<br />

Airport Revenue News Fact Book 2011; compiled by AirProjects, Inc.<br />

Landrum & Brown Page 72<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

KCI has approximately 24,600 square feet of food service concession space, which<br />

is the second lowest amount among the comparable airports and well below the<br />

37,700-square foot average. The food service space allocated at KCI is<br />

approximately 4.9 square feet per 1,000 enplaning passengers, which is well below<br />

the average of 6.6 square feet per 1,000 enplaning passengers at the comparable<br />

airports. The total retail concession space allocated at KCI is approximately<br />

7,500 square feet, which is the least of any of the comparable airports. This retail<br />

space allocation is approximately 1.5 square feet of space per 1,000 enplaning<br />

passengers. This per-passenger space allocation for retail is well below the average<br />

for the comparable airports of 3.9 square feet per 1,000 enplaning passengers.<br />

Table 3.3-5, Food Service Concession Productivity, 2010, and Table 3.3-6,<br />

Retail Concession Productivity, 2010, summarize the productivity of the food<br />

service and retail concessions among the comparable airports by comparing the<br />

sales per enplanement and sales per square foot.<br />

Table 3.3-5<br />

FOOD SERVICE CONCESSION PRODUCTIVITY, 2010<br />

Airport Sales/Epax Sales/SqFt<br />

Kansas City International $ 3.71 $ 753<br />

Oakland International $ 4.57 $ 1,099<br />

General Mitchell International $ 4.66 $ 649<br />

Lambert-St. Louis International $ 4.72 $ 581<br />

DRAFT<br />

Sacramento International $ 4.77 $ 792<br />

Nashville International $ 4.95 $ 816<br />

San Diego International $ 5.29 $ 1,288<br />

Memphis International $ 5.59 $ 627<br />

Portland International $ 5.76 $ 746<br />

Montreal-Trudeau International $ 6.95 $ 835<br />

Calgary International $ 7.15 $ 1,027<br />

Note: Kansas City International productivity data is for FY 2011.<br />

Source: Airport Revenue News Fact Book 2011; compiled by AirProjects, Inc.<br />

Landrum & Brown Page 73<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 3.3-6<br />

RETAIL CONCESSION PRODUCTIVITY, 2010<br />

Airport Sales/Epax Sales/SqFt<br />

Kansas City International $ 1.23 $ 818<br />

Oakland International $ 2.10 $ 431<br />

General Mitchell International $ 2.19 $ 1,351<br />

Lambert-St. Louis International $ 2.36 $ 780<br />

Sacramento International $ 2.44 $ 896<br />

Nashville International $ 2.76 $ 1,614<br />

San Diego International $ 3.01 $ 730<br />

Memphis International $ 3.05 $ 741<br />

Portland International $ 4.36 $ 498<br />

Montreal-Trudeau International $ 4.79 $ 851<br />

Calgary International $ 5.00 $ 1,158<br />

Note: Kansas City International productivity data is for FY 2011.<br />

Source: Airport Revenue News Fact Book 2011; compiled by AirProjects, Inc.<br />

For both food service and retail concessions, KCI lags behind the comparable<br />

airports in terms of productivity as measured by sales per enplanement. Sales per<br />

square foot at the Airport are slightly below the average for the comparable airports<br />

for food service, but slightly above the average for retail productivity. High sales<br />

per square foot do not necessarily imply a successful concession program. It may<br />

also suggest that there is inadequate concession space, which negatively impacts<br />

customer service, product variety, and concession sales and revenue.<br />

DRAFT<br />

Figure 3.3-4, Total Revenue Versus Enplaned Passengers, 2010, shows a<br />

comparison of total concession rental revenue earned by each of the comparable<br />

airport operators versus the number of enplaned passengers at that airport for<br />

2010.<br />

Landrum & Brown Page 74<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 3.3-4<br />

TOTAL REVENUE VERSUS ENPLANED PASSENGERS, 2010<br />

$10,000,000<br />

SAN<br />

Total Rent Revenue<br />

$9,000,000<br />

$8,000,000<br />

$7,000,000<br />

$6,000,000<br />

$5,000,000<br />

$4,000,000<br />

SMF<br />

MKE<br />

OAK<br />

YYC<br />

PDX<br />

Note:<br />

Source:<br />

$3,000,000<br />

MCI<br />

$2,000,000<br />

4,000,000 6,000,000 8,000,000<br />

Enplanements<br />

KCI data is for FY 2011; revenue data for BNA, MEM, STL and YUL were unavailable.<br />

Airport Revenue News Fact Book 2011; compiled by AirProjects, Inc.<br />

Among the comparable airports, the concessions at KCI produce significantly less<br />

revenue. This may be explained, at least in part, by the fact that the Airport has<br />

the lowest percentage rent for its concessions among those airports for which data<br />

was available (rent revenue data was not available for all comparable airport<br />

concession programs). Table 3.3-7, Total Concession Sales and Effective<br />

Percentage Rent, 2010, shows the food service, retail concessions, and total<br />

concession sales combined effective percentage rent at the comparable airports.<br />

DRAFT<br />

Table 3.3-7<br />

TOTAL CONCESSION SALES AND EFFECTIVE PERCENTAGE RENT, 2010<br />

Airport Total Sales ($m) Effective %<br />

Kansas City International $ 24.7 11.0%<br />

Sacramento International $ 34.5 14.5%<br />

Nashville International $ 36.2 NA<br />

Oakland International $ 32.2 13.7%<br />

General Mitchell International $ 34.5 15.0%<br />

Memphis International $ 38.0 NA<br />

Calgary International $ 75.4 11.6%<br />

Lambert-St. Louis International $ 46.8 NA<br />

Portland International $ 70.9 12.6%<br />

San Diego International $ 68.1 14.4%<br />

Montreal-Trudeau International $ 73.0 NA<br />

Note: Kansas City International data is for FY 2011.<br />

Source: Airport Revenue News Fact Book 2011; compiled by AirProjects, Inc.<br />

Landrum & Brown Page 75<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Although the total effective concession rent is not significantly below those at the<br />

comparable airports, the food service effective rent is quite a bit lower. In FY 2011,<br />

the food service effective percentage rent at KCI was 9.1 percent, which was<br />

approximately 3.3 percent less than the average food service effective rent for the<br />

comparable airports. Conversely, the 15.6 percent, effective rent for the retail<br />

concessions at the Airport is higher than the 13.8 percent average among the<br />

comparable airports.<br />

3.3.3 MARKET RESEARCH<br />

3.3.3.1 Market Overview<br />

The Kansas City metropolitan statistical area (MSA), as defined by the U.S. Census<br />

Bureau, is a fifteen-county metropolitan area, anchored by Kansas City, Missouri,<br />

that spans the border between Missouri and Kansas. The MSA population was<br />

estimated at 2,487,526 in 2011. It is the second largest metropolitan area in<br />

Missouri after Greater St. Louis and is the largest MSA in Kansas. The MSA includes<br />

a number of suburbs, including Independence, Missouri; Kansas City, Kansas;<br />

Olathe, Kansas; and Overland Park, Kansas. The median household income for the<br />

Kansas City MSA in 2011 was estimated at $51,095 and the average household<br />

income in 2011 was $66,296. Figure 3.3-5, Kansas City MSA Current<br />

Population by Age, shows that almost 50 percent of the population is under the<br />

age of 34.<br />

Figure 3.3-5<br />

KANSAS CITY MSA CURRENT POPULATION BY AGE<br />

DRAFT<br />

Age 55-64,<br />

11.5%<br />

Over 65,<br />

12.3%<br />

Under 18,<br />

24.9%<br />

Age 45-54,<br />

14.4%<br />

Age 35-44,<br />

13.4%<br />

Age 25-34,<br />

13.9%<br />

Age 18-24,<br />

9.5%<br />

Source: Nielsen Pop-Facts Demographics, 2011<br />

Landrum & Brown Page 76<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Per capita income in the Kansas City MSA rose sharply in the early 2000’s, peaked<br />

in 2008, fell during the 2008-2009 recession, and has since started to recover, as<br />

shown in Figure 3.3-6, Kansas City MSA Per Capita Income Since 2000.<br />

Figure 3.3-6<br />

KANSAS CITY MSA PER CAPITA INCOME SINCE 2000<br />

Source:<br />

DRAFT<br />

U.S. Department of Commerce; Bureau of Economic Analysis<br />

Landrum & Brown Page 77<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The population of the Kansas City MSA over the age of 25 tends to achieve a higher<br />

level of education than that of the entire U.S., as shown in Figure 3.3-7,<br />

Educational attainment, Kansas City MSA.<br />

Figure 3.3-7<br />

EDUCATIONAL ATTAINMENT, KANSAS CITY MSA<br />

50.0%<br />

45.0%<br />

40.0%<br />

35.0%<br />

30.0%<br />

25.0%<br />

20.0%<br />

15.0%<br />

10.0%<br />

5.0%<br />

0.0%<br />

Source:<br />

High School<br />

Diploma or<br />

less<br />

Some<br />

College<br />

U.S. Census Bureau<br />

Figure 3.3-8, Cost of Living Index, displays the cost of living in major<br />

metropolitan areas in the U.S. for the second quarter of 2011. The cost of living in<br />

the Kansas City region is slightly below the national average, which adds to its<br />

attractiveness as a place to live.<br />

Figure 3.3-8<br />

COST OF LIVING INDEX<br />

180<br />

160<br />

140<br />

120<br />

100<br />

80<br />

60<br />

40<br />

20<br />

0<br />

College<br />

Degree<br />

Graduate or<br />

Professional<br />

Degree<br />

KC MSA<br />

DRAFT<br />

US<br />

Source:<br />

The Council for Community and Economic Research<br />

Landrum & Brown Page 78<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Per capita retail sales in Kansas City are well above the U.S. average, better than<br />

many major metropolitan areas, as shown in Figure 3.3-9, Per Capita Retail<br />

Sales. This sales statistic is an indicator that KCI travelers may have a strong<br />

propensity to dine and shop at the Airport if an appealing concession program were<br />

available.<br />

Figure 3.3-9<br />

PER CAPITA RETAIL SALES<br />

$16,000<br />

$14,000<br />

$12,000<br />

$10,000<br />

$8,000<br />

$6,000<br />

$4,000<br />

$2,000<br />

Source:<br />

www.kcmo.org<br />

3.3.3.2 Population Characteristics<br />

Because approximately 62 percent of the passengers using the Airport are Kansas<br />

City residents, local population characteristics and lifestyle trends were researched<br />

to gain insights into the retail preferences and purchasing patterns of the Airport’s<br />

passenger base. The following are some of the more pertinent results of this<br />

research.<br />

Compared to the U.S. population, Kansas City residents are:<br />

<br />

<br />

<br />

<br />

<br />

<br />

$0<br />

DRAFT<br />

slightly less likely to eat gourmet foods whenever possible, try new food<br />

products, or eat healthy<br />

slightly more likely to drink micro-brewed beer or light beer<br />

seven percent less likely to drink low or non-alcoholic beer<br />

between six and seven percent less likely to drink upscale alcoholic<br />

beverages, such as cognac, brandy, Armagnac, or Scotch whiskey<br />

more likely to drink domestic wine and beer than imported wine and beer<br />

slightly less likely to have a budget that allows for the purchase of designer<br />

clothes, or to keep up with the latest fashions<br />

Landrum & Brown Page 79<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

more likely to spend over $400 per year on children’s clothing<br />

slightly more likely to own multiple personal computers and Apple personal<br />

computers<br />

slightly less likely to be the first to have new electronic equipment<br />

slightly more likely to have gone on-line in the last month to make a<br />

purchase or gather shopping information<br />

slightly less likely to state that the Internet is their primary entertainment<br />

source or to play online games<br />

more likely to include power boating (five percent greater), bowling (two<br />

percent greater), and weight training (two percent greater) activities<br />

slightly less likely to belong to an environmental organization<br />

slightly less likely to be willing to pay higher prices for environmentallyfriendly<br />

products<br />

The overall implications of this data are that the Kansas City area residents are<br />

fairly conservative regarding the adoption of fashion and food trends and do not<br />

travel frequently. It should be noted, though, that Kansas City is known for its<br />

barbeque, and is the home of many renowned restaurants. Residents enjoy good,<br />

freshly-prepared food, and high-quality food that may not be widely considered<br />

“gourmet” or “healthy.” The research suggests that restaurants that focus on<br />

familiar foods and domestic beverages would tend to be more successful.<br />

3.3.3.3 Possible Concessions at the Airport<br />

The Kansas City area is home to numerous shopping venues, ranging from upscale,<br />

boutique-focused venues to those that cater to big-box and discount operations.<br />

Some of the area’s significant shopping destinations are:<br />

<br />

<br />

<br />

DRAFT<br />

Country Club Plaza - A shopping, dining, and entertainment district<br />

encompassing a 15-block area and encompasses over 150 shops and dozens<br />

of restaurants. Shops range from nationally-known high fashion retailers to<br />

local favorites. Food offerings range from sports bars to upscale fine local<br />

dining to nationally known chain restaurants. The venue also features a wide<br />

variety of specialty food offerings, including coffee, chocolate, and cupcakes.<br />

Oak Park Mall - one of the region’s largest indoor shopping centers, featuring<br />

a wide variety of over 170 specialty shops as well as department store<br />

anchor tenants located in Overland Park.<br />

Zona Rosa - one of the region’s premier outdoor shopping, dining, and<br />

entertainment destinations, featuring both nationally- and locally-owned<br />

venues, offering patrons a superb variety of shopping and dining<br />

experiences.<br />

Landrum & Brown Page 80<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The Kansas Legends Outlet Center - offers both shopping and educational /<br />

entertainment options honoring famous Kansans in athletics, music,<br />

exploration, science, technology, politics, art, and much more, recognizing<br />

the men and women who truly make the state unique. The Center features a<br />

diverse mix of outlet-type stores and is also home to some unique offerings.<br />

<br />

<br />

Crown Center - often called a city within a city, located in the heart of<br />

downtown Kansas City, with three levels of great shopping and dining that<br />

complement two luxury hotels, multiple office buildings, a residential<br />

community, and several entertainment attractions. It surrounds the<br />

worldwide headquarters of Hallmark Cards, Inc. and also offers unique<br />

shopping opportunities.<br />

Brookside - A destination venue for people seeking unique dining and unique<br />

and ethnic shopping experiences, located just south of Country Club Plaza.<br />

The diversity and creativity of the Kansas City region’s shopping and dining venues<br />

provide substantial opportunities from which to acquire and adapt ideas for<br />

developing a unique concession experience in the new <strong>Terminal</strong> at KCI. Many of<br />

these venues have unique products and would allow for significant participation by<br />

local business owners. Incorporating such ideas into the Airport’s concession<br />

program could allow the Airport to showcase local businesses and significantly<br />

increase its non-aviation revenue, which, in turn, would be a support to the<br />

community.<br />

The following businesses are headquartered in the Kansas City region or have<br />

significant ties to the area. The businesses presented highlight some locally-based<br />

or known vendors that could enhance the concession program and provide a deeper<br />

awareness and appreciation of Kansas City region. Some of these businesses<br />

already operate retail concepts, while others would need to develop a retail<br />

concept, if interested.<br />

<br />

<br />

<br />

<br />

<br />

<br />

DRAFT<br />

AMC Theaters - the second largest movie theater chain in North America<br />

Applebee’s Restaurants - which already has an airport operation at Richmond<br />

International Airport<br />

Garmin - the world’s largest manufacturer of GPS devices and headquartered<br />

in Olathe<br />

Hallmark Cards - the largest producer of greeting cards in the U.S., also has<br />

a retail business under the Hallmark Crown brand<br />

National Association of Intercollegiate Athletics (NAIA) - an athletic<br />

association that organizes college and university-level athletic programs<br />

(membership includes smaller colleges and universities across the U.S. and<br />

Canada)<br />

Russell Stover Candies - a family-owned confectionary company that owns<br />

both its own and the Whitman’s brand, and operates over 40 retail stores,<br />

besides wholesaling its products to a multitude of shops and stores.<br />

Landrum & Brown Page 81<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

Sprint-Nextel Corporation - operates the third-largest wireless telecommunications<br />

network in the U.S and also operates the Sprint Prepaid<br />

Group, which includes Boost Mobile and the Virgin Mobile USA brands.<br />

Wolferman’s Bakery - founded in Kansas City, but is now operated by Harry<br />

& David’s and offers a wide variety of baked goods, primarily through the<br />

Internet and catalogue retail outlets.<br />

One of the strongest ways to bring a local feel to an airport is to offer the brands<br />

and types of food for which the region is famous. Kansas City is most closely<br />

identified with barbeque. Currently, there are over 100 restaurants in the Kansas<br />

City area that specialize in this style of cooking, ranging from roadside stands to<br />

full-service establishments. The following list includes some of more widely-known<br />

brands that might be appropriate for the Airport.<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Fiorella’s Jack Stack Barbeque - has four locations in the Kansas City area<br />

Jack Stack’s - an upscale dining experience featuring all varieties of Kansas<br />

City barbeque and a wide variety of side dishes<br />

Zagat’s - at one point named Jack Stack’s the best barbeque in the U.S.<br />

Arthur Bryant’s Barbeque - Possibly the best known, using a combination of<br />

hickory and oak to achieve a unique flavor<br />

Gates Bar-B-Q – the sauce is not sweetened with molasses, unlike other<br />

Kansas City-style barbeque sauces<br />

Woodyard Bar-B-Que - is a working lumberyard and roadside barbecue amid<br />

storage complexes on the Kansas/Missouri border that uses a variety of<br />

different woods to achieve their unique flavor and is especially known for its<br />

“burnt end chili”<br />

Oklahoma Joe's Barbecue and Catering - received top honors at national<br />

barbeque contests as part of the Slaughterhouse Five pit master team and<br />

features antibiotic-free meats slow-cooked over white oak.<br />

Kansas City offers far more than great barbeque. There are a number of other<br />

well-known and well-respected local restaurants, such as:<br />

<br />

<br />

<br />

<br />

Bread and Butter Concepts<br />

Eggtc<br />

Chip’s Chocolate Factory<br />

The Roasterie<br />

There are a number of products that could be considered typical of the region, and<br />

could be favored by travelers seeking souvenirs of their visit. As the new terminal<br />

is developed, the possibility of establishing individual stores or retail merchandise<br />

units around one or more of these themes could be considered.<br />

<br />

<br />

DRAFT<br />

Wizard of Oz-themed merchandise<br />

Barbeque sauces, rubs, and accessories, featuring the products of Kansas<br />

City’s noted barbeque purveyors<br />

Landrum & Brown Page 82<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

<br />

<br />

<br />

Memorabilia from Kansas City’s professional sports teams<br />

Logo merchandise from the many universities in and around the Kansas City<br />

area<br />

Merchandise celebrating Kansas City’s noted and historic music culture and<br />

the American Jazz Museum<br />

Memorabilia based on the displays and the history of Kansas City’s Negro<br />

Leagues Baseball Museum<br />

A “legends” of Kansas City themed offering, building on the diverse collection<br />

of notable residents of the region and their contributions to all aspects of<br />

modern American culture and life<br />

In addition to the large corporations in the region that may offer opportunities for<br />

locally-branded operations at the Airport, there are many smaller, locally-known<br />

retailers that could help make the Airport’s concession program unique.<br />

<br />

<br />

<br />

<br />

<br />

Stuff<br />

The Vintage Market<br />

The (NEW) Dime Store<br />

Gifted Hands Gift Shop<br />

Indigo Wild<br />

3.4 Specialty Systems and New Technology<br />

DRAFT<br />

3.4.1 GENERAL REQUIREMENTS<br />

The New <strong>Terminal</strong> should be built based upon the objective of creating a modern,<br />

secure, and efficient airport terminal environment. Today’s Information and<br />

Communication Technology (ICT) has become one of the most valuable business<br />

enablers to create such environment. ICT permeates every aspect of<br />

communications, operations, and security. A properly planned technology<br />

environment provides reliable systems that reduce costs and provide enhanced<br />

services to airlines and passengers as well as operational efficiency and enhanced<br />

safety and security.<br />

The New <strong>Terminal</strong> systems should be designed to adapt to the ever-changing<br />

aviation operations and passenger requirements. The intent is to create systems<br />

that are capable of adapting to change with minimal disruption during transition<br />

from existing to new facilities. The overall concept is to standardize the equipment<br />

to the greatest extent possible; thus simplifying long-term support, maintenance,<br />

and operations. The infrastructure should provide fiber optic cabling throughout the<br />

New <strong>Terminal</strong> and associated facilities to allow for day one connectivity and<br />

sufficient extra capacity for future expansion.<br />

Landrum & Brown Page 83<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.4.1.1 Introduction<br />

Figure 3.4-1, <strong>Terminal</strong> Area Phasing Plan 2025, depicts the New <strong>Terminal</strong><br />

Concept Design.<br />

Figure 3.4-1<br />

TERMINAL AREA PHASING PLAN 2025<br />

DRAFT<br />

Source:<br />

Landrum & Brown<br />

One of the primary purposes for the infrastructure is to provide a redundant,<br />

available, and expandable communication backbone, both active and passive to<br />

support the Airport, key business partners, and tenants. The new passenger<br />

terminal building should include significant communications infrastructure including<br />

two properly sized Main Equipment Rooms (MERs) that will act as the terminal main<br />

equipment rooms and main connection points to airport-wide systems, which are<br />

presumed to be located in the two existing data centers on campus outside the new<br />

terminal project limits. The MERs should house all electronic equipment for ICT<br />

systems and should act as the main distribution facility to the various internal<br />

Telecommunication Rooms (TRs) within the PTB and its associated facilities.<br />

Landrum & Brown Page 84<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The New <strong>Terminal</strong> should also contain numerous safety and security systems.<br />

Safety systems should include a fire alarm and its associated voice evacuation.<br />

Security systems should include:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Access Control, to provide secured facilities as well as segregation and<br />

tracking of access activities<br />

Identity Management that is compatible with the overall airport-wide security<br />

system<br />

Video Surveillance System (VSS)<br />

Storage Area Network (SAN) for the storage of video to provide surveillance<br />

of the New <strong>Terminal</strong><br />

Passenger and hand luggage screening equipment at Security Screening<br />

Checkpoints (SSCP)<br />

Customs screening equipment within the Customs and Border Protection<br />

(CBP) area<br />

Hold Baggage Screening (HBS) equipment<br />

Several communication systems should be provided for the New <strong>Terminal</strong><br />

operations. A Voice over IP (VoIP) telephone system for telecommunications using<br />

telephony devices located at all applicable spaces within the New <strong>Terminal</strong>.<br />

A Public Address system will provide specific zone paging, courtesy announcements,<br />

emergency evacuation, and overall mass notification. A Master Cable or<br />

alternatively an Internet Protocol Television (IPTV) distribution system to provide<br />

general TV programs throughout the PTB. Infrastructure should be required to<br />

support other applications such as CNN, interactive systems, control, management,<br />

scheduling, mapping, wayfinding, and messaging.<br />

DRAFT<br />

Audio Visual systems should be provided in the conference rooms, operation center<br />

facilities, and other locations within the PTB. The systems should include all<br />

display, input, and control equipment for each local space. A Distributed Antenna<br />

System should be provided to amplify radio signals for assured reception of public<br />

safety 800MHz Trunk radio, very-high frequency (VHF) radio, ultra-high frequency<br />

(UHF) radio, and cellular telephone signals inside the PTB.<br />

Various Airport Operation Systems should be provided including passenger<br />

processing, resources management, and common use systems. In addition, an<br />

airport operations database and systems integration should be provided to ensure<br />

state of the art operations and common use functionality for the New <strong>Terminal</strong>.<br />

Lastly, in order to support green initiatives, all technology equipment should be<br />

Energy Star 4.0 certified products, as applicable. All products should also bear the<br />

Restriction of Hazardous Substances Directive (ROHS), as applicable. All servers,<br />

desktop computers, and storage equipment should be virtualized to maximize the<br />

use of available assets without wasting energy for duplicative storage and<br />

processing equipment. Likewise, monitors should utilize LED backlit technology<br />

instead of cold-cathode fluorescent to reduce energy consumption, as applicable.<br />

Landrum & Brown Page 85<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.4.2 OVERALL ICT DESIGN GOALS<br />

The design of the ICT systems should be made with a clear understanding of the<br />

future of each technology. Infrastructure (pathways and spaces) should be<br />

designed for the latest technology in fiber optics and copper media with<br />

consideration for future technology additions. Systems should be scalable and<br />

ready for anticipated growth and interface with disparate systems.<br />

Only technologies that make sense, based on the typical size and anticipated KCI<br />

environment, should be considered for use. For example, systems that require<br />

huge upfront capital investments or most applicable to large international hubs,<br />

should not be considered.<br />

Topologies and infrastructure components within a passenger terminal facility must<br />

be reliable. Careful consideration should be given to the redundancies and<br />

expected end of life cycles of all technology components.<br />

Systems should be designed with information and physical security in mind.<br />

Careful considerations should be given to human and system interaction and<br />

potential inherent vulnerabilities.<br />

Various ICT Systems and infrastructure components that should be utilized in the<br />

New <strong>Terminal</strong> are discussed in Appendix X, Specialty Systems and New Technology.<br />

3.4.3 CODES AND STANDARDS<br />

DRAFT<br />

Systems should be implemented in accordance with best practices, standards as<br />

well as local codes and requirements of authorities and organizations having<br />

jurisdiction. A list is included in Appendix X, Specialty Systems and New<br />

Technology.<br />

3.4.4 PASSIVE/ACTIVE INFRASTRUCTURE<br />

3.4.4.1 Wide Area Network (WAN) / Campus Area Network (CAN)<br />

/ Local Area Network (LAN)<br />

The Wide Area Network (WAN) is assumed to be associated with off-campus<br />

headquarter systems such as Kansas City city-wide systems, and Federal<br />

Government DHS, Federal Bureau of Investigation (FBI) National Crime Information<br />

Center (NCIC), TSA, CBP systems. The equipment and systems associated with<br />

these WAN should be provided by either the City or respective Government agency<br />

and should be installed and connected as part of the new <strong>Terminal</strong> project, if<br />

required.<br />

It is assumed that the existing Campus Area Network (CAN) should be upgraded, if<br />

needed, and extended as part of this project. The CAN consists of existing<br />

terminals and facilities located within the Airport especially during transitioning<br />

phases. The Mechanical Equipment Rooms (MERs) of the New <strong>Terminal</strong> should be<br />

considered a branch of hierarchical star network topology for the overall airport.<br />

Landrum & Brown Page 86<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The CAN infrastructure should include single mode (nine-micron) optical fiber cables<br />

routed in a redundant fashion to two data centers / distribution facilities on the<br />

Airport. This should include two points of entry into the New <strong>Terminal</strong>. Redundant<br />

CAN connections should be designed to minimize single points of failure between<br />

the New <strong>Terminal</strong> and the existing Airport data network. CAN hardware located<br />

within the MERs should consist of distribution level switches connected to redundant<br />

infrastructures for fiber and electrical power.<br />

The Local Area Network (LAN) will consist of the local data network, infrastructure,<br />

and connections within the New <strong>Terminal</strong> and associated new facilities.<br />

LAN infrastructures include fiber optics backbone and horizontal copper and fiber<br />

media installations and supporting hardware (conduit, racks, and equipment).<br />

All IP-based devices should share the common physical LAN infrastructure and<br />

should include video, voice, and data services; wireless networks; building<br />

automation; overhead paging; intercom; and airport operating systems. Virtual<br />

LANs (VLANs) should be created to segregate network traffic for each system.<br />

The New <strong>Terminal</strong> should feature a redundant backbone topology within each<br />

Telecommunications Room (TR) connected to both MERs by fiber optic cables.<br />

Distribution Layer routing and switching should be provided by communications<br />

devices located within the MER. Access Layer switching should be provided by<br />

48-port power-over-Ethernet (POE) switches, where applicable, configured in a<br />

stack-topology with two connections to the MERs distribution layer switches via the<br />

redundant backbone topology.<br />

The New <strong>Terminal</strong> is planned as a converged network environment of which a<br />

dedicated security LAN for the use of security systems such as Video Surveillance<br />

and Access Control should not be required. The idea is to logically segregate and<br />

secure security systems with duplicating network infrastructure, management, and<br />

support.<br />

DRAFT<br />

Other LANs should also be present inside the New <strong>Terminal</strong> such as the law<br />

enforcement NCIC, CBP, and TSA, as well as airline-based circuits for connectivity<br />

to host systems via dedicated circuits for common use systems airlines.<br />

It is highly recommended that the Data Center network be fully virtualized using<br />

unified fabric architecture with fully redundant distribution/aggregation levels.<br />

This should support new technologies such as Fiber Channel over Ethernet and<br />

provide ten Gigabyte per second (GB/s) or multiples of ten GB/s speeds with near<br />

zero latency, high quality of service (QoS), and sufficient redundancy to prevent<br />

outages of service to the Airport. Likewise, for data security the KCI LAN should<br />

provide 802.1x security and Network administration control.<br />

The LANs should provide full coverage for all required IP data connectivity inside<br />

the New <strong>Terminal</strong>. At least 50 percent of all passive data outlets should be fully<br />

activated by being fully patched to the network, the rest of the data outlets should<br />

be provided only as spares and only terminated at the TR patch panel. Likewise,<br />

each network switch should not be utilized beyond 75 percent of the total ports<br />

capacity (e.g. 36 ports of a 48-port switch); the other 25 percent of the ports<br />

Landrum & Brown Page 87<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

should be reserved as spares for future use. Similar reserved capacity should be<br />

provided in the Distribution and Core levels of the network, with a minimum of<br />

25 percent capacity left in the form of available ports on the provided modules.<br />

The network over subscription ration general rule should be as follows:<br />

• Access to Distribution 20:1<br />

• Distribution to Core 4:1<br />

• Core to Core 1:1<br />

All Access Switches should be Layer 3/Layer 2 switches. All LAN equipment should<br />

be provided with redundant power supplies and redundant fans. For the chassisbased<br />

Distribution and Core switches, the power supplies and the processing cards<br />

should be fully redundant to provide a fully fault tolerant unit.<br />

3.4.4.2 Outside Plant “OSP” and Backbone Cabling<br />

The Airport-wide backbone and intra-building backbone cabling infrastructures<br />

should consist of high strand count Single Mode fiber optic cabling Single Mode<br />

cables. Overall, the fiber cables infrastructure should be provided with a minimum<br />

of 100 percent spare capacity in all runs after the ICT systems are implemented.<br />

All fiber should be run in a manner to minimize fiber splices, and no run from end to<br />

end should contain more than two fusion splices unless noted otherwise.<br />

Alternative pathway distribution techniques such as air-blown fiber should also be<br />

considered to maximize outside plant flexibility. Connectivity to the airport should<br />

be via two diversified routes. Within the New <strong>Terminal</strong> a hybrid Single Mode/Multi<br />

Mode (50 Micron Laser optimized) and 100 pair copper should be provided from<br />

MER to each TR.<br />

DRAFT<br />

3.4.4.3 Horizontal Structured Cabling<br />

Voice, data, and networked video requirements should be supported using<br />

Category 6a Foiled/Unshielded Twisted Pair (F/UTP) cables (or future Category 8<br />

when standard becomes available), extending from each TR to each Work Area<br />

Outlet (WAO). Outlets should be configured with a quantity of cables appropriate<br />

for the location, and should conform to ANSI/TIA-569 recommended densities.<br />

Rooms designated with low density should contain two ports, medium density<br />

should contain six to 14 ports, and high density should contain more than 14 ports.<br />

The cabling should be planned to accommodate future equipment needs, diverse<br />

and increasing user applications, ongoing maintenance, relocation, sustainability,<br />

flexibility, and service changes. In the TRs, all cables should be terminated on<br />

rack-mounted modular terminating patch panels according to American National<br />

Standards Institute / Telecommunications Industry Association (ANSI/TIA) 568-A or<br />

B depending on KCI approved standards.<br />

The maximum horizontal cable length should not exceed 90 meters for Category 6a<br />

cables. The additional length of patch cords should not cause the total channel<br />

length to be more than 100 meters. As a rule, horizontal Work Area Outlet<br />

connections should start and finish on the same floor with no cross-floor<br />

Landrum & Brown Page 88<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

connections. Occasionally, in areas where no space is available for TRs due to large<br />

open-span environment (e.g. baggage hall or departure hall), cross-floor<br />

connections may be employed. It is important that all security system field devices<br />

be installed completely in secure conduits and boxes (i.e. not utilizing open cable<br />

trays or unprotected data outlets).<br />

Horizontal cabling should be supported within each telecommunications room by<br />

cable ladder rack, wire basket, ladder rack supports, 'waterfalls', and Velcro straps<br />

(not cable ties). With the exception of Fire Alarm panels and Access Control Panels,<br />

no infrastructure attachment should be permitted to attach directly to the TR wall.<br />

All attachments must be placed on fire-retardant painted AC grade plywood.<br />

Cabling should be placed in wall mounted slack-loop supported by D-rings after<br />

entering room and prior to terminating on equipment rack.<br />

3.4.4.4 Telecommunication Spaces<br />

Telecommunication spaces should consist of spaces, cable tray, ladder rack,<br />

conduit, back boxes, and cabinets that carry, house, and transport voice and data<br />

traffic from the point of origin to the point of use. This infrastructure should be<br />

designed to support secure and reliable wired and wireless communications for all<br />

systems throughout the PTB and its supporting facilities, as required. Room size<br />

and systems should be properly sized, taking into account potential for future<br />

expansion and limits on spaces above ceilings and inter-floor service requirements,<br />

where it exists.<br />

Work area outlet components consist of the faceplate or housing, cable<br />

terminations, and patch cords for connecting the end user devices to the horizontal<br />

cable link from the local TR. Outlets should be coordinated with or built-into<br />

furniture, as appropriate.<br />

DRAFT<br />

The structured cabling infrastructure design should be provided with a reference<br />

signal grounding in the MERs and bonding system, designed and installed in<br />

accordance with the Telecommunications Industry Association/Energy Information<br />

Administration (TIA/EIA) 607-A Grounding & Bonding and/or local codes and<br />

standards documents in all TR spaces. The primary purpose of the equipment<br />

grounding system is to ensure personnel safety and reduce the likelihood of a fire<br />

hazard by facilitating the operation of over current within devices.<br />

An effective administration and labeling system is crucial for the efficient operation<br />

and maintenance of the converged network infrastructure and connectivity system<br />

and all its components, particularly within a multiple building, large campus<br />

environment. The existing Airport identification standards should be utilized to<br />

identify each pathway segment, technology space, cabinet or rack, patch panel,<br />

cable, and network device installed within the Airport technology system.<br />

All active and associated equipment should be housed in equipment cabinets within<br />

the MERs, Service Entrances, and TRs. Equipment cabinets should be lockable<br />

approximately 29 inches wide x 36 inches deep x 84 inches high to support at least<br />

45 rack unit 19-inch rack mount width conforming to TIA standards. The cabinets<br />

Landrum & Brown Page 89<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

should be oriented with front to back perforated ventilation to establish hot aisles<br />

and cold aisles in the rooms, coordinated with cooling equipment. All equipment<br />

cabinets should be equipped with seismic protection relevant to Kansas City seismic<br />

zone designation. Cabinets should also be equipped with vertical and horizontal<br />

cable management and dual power distribution strips.<br />

Two MERs should be located in the New <strong>Terminal</strong> building. They should contain the<br />

primary and backup distribution layer equipment of the LAN topology and should<br />

connect the terminal to the airport-wide LAN core. The MERs should house terminal<br />

specific head-end equipment such as PA system, and LAN/CAN communications<br />

hardware. Each TR within the terminal should connect to both MERs using fiber<br />

optic and copper backbone cables. The building power feed to the MERs should be<br />

backed up by emergency standby power. A central UPS system should be used to<br />

provide standby power to MERs equipment rather than individual rack-mounted<br />

UPS devices. The MERs should interconnect with the new parking garage main<br />

telecommunication rooms for distribution network connectivity.<br />

Two Building Entrance Rooms (BERs) should be provided to serve the New <strong>Terminal</strong><br />

by providing redundancy of services. It is strongly recommended that the New<br />

<strong>Terminal</strong> contain both Building Entrance Rooms on the building lowest level.<br />

These rooms should be located at the perimeter of the building and have direct<br />

access to the telecommunications ductbanks. The BERs should contain transition<br />

wall space for outdoor gel filled cables, splice boxes, fiber splice and terminations,<br />

transition surge protection for outside copper cables, and should provide<br />

connectivity to the New <strong>Terminal</strong> MERs. Each BER should be 20 square meters<br />

minimum, and may be co-located with the MER room if the room size takes into<br />

account requirements for both functions.<br />

DRAFT<br />

A Telecommunications Utility room should be located on the lowest level to house<br />

the termination points for the Telcos and cellular provider service cables and<br />

equipment. The room should adhere to the following requirements:<br />

• The Standard Telephone Company (STC) Room should be 12 feet x 15 feet,<br />

and must be separate from the MER and BERs. The room must be accessible<br />

from the terminal exterior or landside.<br />

• Door should be solid (no glass) that is aluminum or steel and should have<br />

access control.<br />

• A raised floor of at least 12 inches is preferred. The floor should be rated for<br />

at least 400 pounds per square foot. The raised floor should be<br />

accomplished via a depressed slab to avoid access ramps.<br />

• Ceiling height should be a minimum of nine feet.<br />

• At least two four-inch conduits should be provided to exterior communication<br />

manhole<br />

• The room should not be located near electrical distribution equipment or<br />

transformers to prevent Electromagnetic Interference/Radio Frequency<br />

Interference (EMI/RFI).<br />

Landrum & Brown Page 90<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The PTB should contain multiple TRs located in a direct riser topology, with at least<br />

one TR per floor, where possible. The quantity of TRs per floor should be<br />

determined by the floor size and geometry, and spaced so that work area outlets<br />

should be within approximately 60 meters of a TR. Maximum Horizontal cable<br />

length should not exceed 90 meters between the telecom outlet and the TR patch<br />

panel port. Horizontal cabling for voice, data, wireless, IPTV, audio/visual (A/V)<br />

elements, security systems, and other low voltage technologies should terminate in<br />

TRs. An equipment room space on the Top level should be designated as the Point<br />

of Presence (POP) for roof-top antenna system services. Communication backbone<br />

cables should connect the TRs to the MERs. Each TR should be approximately 150<br />

to 180 square feet to account for both wall-mounted and rack-mounted equipment.<br />

TRs should be designed and coordinated to accommodate systems and equipment<br />

that include but are not limited to:<br />

• Termination and patching facilities for the horizontal cabling<br />

• Termination and patching facilities for the fiber optic backbone cabling<br />

• Termination and patching facilities for the copper backbone cabling<br />

• Hardware and racking for Network Access devices<br />

• Converged/Common Network Access devices<br />

• A/V equipment<br />

• Wireless LAN networking equipment<br />

• Building Management Systems<br />

• Security Systems<br />

• Fire Alarm panel<br />

• Distributed Antenna System (DAS) provided by a Global System for Mobile<br />

(GSM) and public safety radio provider<br />

• Vertical riser pathways<br />

DRAFT<br />

3.4.5 AIRPORT OPERATION SYSTEMS<br />

3.4.5.1 Common Use Systems<br />

Common Use Systems (CUS) are integrated systems for sharing of passenger<br />

processing systems to maximize Passenger <strong>Terminal</strong> Building (PTB) facility access<br />

and allocation through non-dedicated resources. It is a viable alternative to the<br />

traditional approach, which uses proprietary/exclusive-use models. CUSs are<br />

airport-operator provided hardware and software systems that provide an interface<br />

through which airline-host systems as well as common resources can operate with<br />

increased facility utilization and flexibility.<br />

In the context of KCI, Common Use Passenger Processing System (CUPPS), which<br />

is an overhaul of the former Common Use <strong>Terminal</strong> Equipment (CUTE) standard, is<br />

the generic term applied to standardized system platforms for agent-facing<br />

common-use systems at pre-equipped, designated locations only. CUSs encompass<br />

Landrum & Brown Page 91<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

CUTE, Common Use Self Service (CUSS), and Resources Management System<br />

(RMS). The system should be based on the latest International Air Transport<br />

Association (IATA) standards.<br />

3.4.5.2 CUPPS Concept of Operation<br />

CUPPS allows airlines to share PTB resources such as gate counters and ticket<br />

counters to provide efficient passenger services. Benefits to utilizing CUPPS<br />

include:<br />

• Efficient use of PTB real estate by allowing airlines to utilize common use<br />

facilities to handle operations as needed.<br />

• Allows the airport to rapidly offer facilities to new entrant airlines as well as<br />

to carriers with small number of flights without having to dedicate gates,<br />

counters, or other facilities on a full time basis. Likewise, airlines gain the<br />

benefit of decreased equipment mobilization costs.<br />

CUPPS utilizes common workstations and peripherals among the various<br />

participating airlines of which, upon authentication, the system connects the airline<br />

agent to requested airline host system. The system provides full access to airline<br />

host applications (or local departure control for non-hosted or charter carriers)<br />

including searching flight information and passenger records, updating travel<br />

information, and printing documents, which includes boarding passes, baggage<br />

tags, and flight manifests.<br />

3.4.5.3 CUSS Concept of Operation<br />

DRAFT<br />

CUSS enables airlines to provide passengers with self check-in services at common<br />

kiosks. There are a number of benefits to utilizing CUSS including:<br />

• Standardized approach for customer interaction with self check-in<br />

applications at a single point of contact.<br />

• Allows the Airport to offer common self check-in space to all carriers, which<br />

enhances efficiencies and minimizes queuing time compared to airlinesupplied<br />

dedicated systems.<br />

CUSS kiosks display a list of airline icons, which upon selection of a specific icon<br />

automatically launches the requested airline's application. The main touch screen<br />

interface usually lists all airlines that participate in the CUSS kiosk. Passengers<br />

may use a credit card, passport, or simply utilize the touch screen keyboard to<br />

input information. Upon completion of the check-in process, passengers receive a<br />

printed boarding pass (based on International Air Transport Association (IATA) 2D<br />

barcode) and, once implemented in the U.S., may print self-adhesive bag tags for<br />

tagging their checked in luggage.<br />

Landrum & Brown Page 92<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.4.5.4 Resource Management System (RMS) Concept of Operation<br />

The basic idea of RMS is a two-step process: resource planning and real-time<br />

resource management. A resource assignment schedule is typically created and<br />

issued in advance in order to facilitate planning by various airport and airline<br />

personnel. Due to various factors (i.e., flight delay, ground handling equipment<br />

failure, etc.) resource assignments may have to be altered. The resource<br />

assignments are then reassigned as required, on a real-time basis, with the goal of<br />

minimizing impact on both passengers and airport personnel.<br />

Various constraints or “rules” come into play in resource allocation, including<br />

physical limitations of a gate (e.g., cannot support widebody aircraft), convenience,<br />

carrier preferred gates, etc. These various rules form a rule-based database for the<br />

system. An expert system with easy-to-define rules is utilized as part of RMS core<br />

functions to facilitate configuration of the airport constraints. The New <strong>Terminal</strong><br />

should include full development of RMS operational rules for all new gates as well<br />

as development of any special operations required during transitioning.<br />

For the system to properly allocate resources in a real-time operating environment,<br />

it needs up-to-date flight information. This requires integration with the Airport<br />

Operational Database (AODB), which provides all necessary operational flight data<br />

for real-time allocation of seasonal schedules, Flight Information Display System<br />

(FIDS) data (e.g., flight arrival time change), and/or FAA or third party aircraft or<br />

flight actual data (e.g. Passur’s real time monitoring of air traffic).<br />

3.4.6 SYSTEM DESIGN CONCEPTS<br />

DRAFT<br />

A new system should be deployed for the designated common use areas within the<br />

new PTB. This will include head-end equipment, hardware for field devices at gates<br />

and counters, as well as participating airline gateways, and local departure control<br />

for airlines with no host-based system.<br />

Equipment should be required at all common-use gates, check-in counters, CUSS<br />

pods, remote gate holdrooms, participating airline/operations back-offices and<br />

baggage service office. The exact locations and quantities as well as coordination<br />

with architectural millwork should be carefully planned during the design of the New<br />

<strong>Terminal</strong>. All head-end hardware, including the associated servers, should be<br />

located in lockable cabinets within the <strong>Terminal</strong> MERs.<br />

Airport structured cable system and the common LAN should be utilized for<br />

communication of the Common Use system between servers and field equipment.<br />

Dedicated VLANs should be used for Common Use system communications.<br />

3.4.6.1 Hardware Configurations<br />

CUPPS workstations to be provided require components as a minimum are listed in<br />

Appendix X, Specialty Systems and New Technology.<br />

Landrum & Brown Page 93<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

CUSS kiosks to be provided require components as a minimum are listed in<br />

Appendix X, Specialty Systems and New Technology.<br />

RMS stations to be provided require components as a minimum as discussed in<br />

Appendix X, Specialty Systems and New Technology.<br />

3.4.6.2 General Requirements<br />

General rules to be used for the operation of the CUPPS/CUSS system:<br />

• No data should be maintained at public kiosks.<br />

• No data should be retained by the vendor.<br />

• No Application Provider’s (i.e. Airlines) proprietary data should be accessed<br />

by or made available to any other airline unless agreement for such use is in<br />

place.<br />

• All interfaces should be tested and certified as per CUPSS latest standards<br />

and AODB requirements.<br />

3.4.7 FLIGHT INFORMATION SYSTEMS<br />

3.4.7.1 System Overview<br />

Flight Information Systems (FIS) are client-server or web-based applications that<br />

manage and disseminate flight-oriented information such as flight times, gate, and<br />

baggage information to the traveling public, operational personnel, and airport<br />

administration. In the context of this project, FIS encompasses a number of subsystems<br />

including:<br />

DRAFT<br />

• Electronic Visual Information Display Systems (EVIDS)<br />

• Flight Information Display System (FIDS)<br />

• Baggage Information Display System (BIDS) including operational areas<br />

• Gate Information Display System (GIDS)<br />

• Counter Information Display System (CIDS)<br />

• Passport Control Dynamic Signage (PCDS) where applicable<br />

• Airport Information Management System (AIMS)<br />

• Interface to existing Airport Operations Database (AODB)<br />

The system provides a consistent source of information to the public based on data<br />

collected from automated airline interfaces, manual updates, and third-party<br />

sources. Information is typically displayed to passengers and the public throughout<br />

the airport using either banks of FIDS screens or stand-alone displays. Operational<br />

personnel may access flight information in airline offices and ramp operation spaces<br />

using public displays or workstations connected directly to the airport network.<br />

Landrum & Brown Page 94<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Personnel typically update flight data when necessary from a few authorized AIMS<br />

workstations. Airport administration personnel should be able to use the<br />

information within the system databases to monitor flight and operational statistics.<br />

The flight information can also be displayed on the airport’s web site and other<br />

remote locations as desired.<br />

General FIDS banks in the ticketing area are used by passengers to obtain initial<br />

flight information and to determine which common-use check-in counters, where<br />

applicable, are associated with their flights. FIDS banks in the concourses are used<br />

by passengers to obtain current flight information and gate assignments as they<br />

proceed to their gate or to visit concession areas. FIDS displays in the baggage<br />

claim area are used by arriving passengers to determine the correct baggage<br />

allocated carousel. No FIDS should be presented in secured arriving corridors as<br />

passengers should be directed by static signs to CPB passport and customs control<br />

area.<br />

BIDS screens at each baggage claim carousel should provide visual indication to<br />

arriving passengers when the first bag and last bag of a flight are unloaded.<br />

Baggage Information Display Systems (BIDS) should also be made available for<br />

operational staff at the unloading belt area. Counter Information Display System<br />

(CIDS) screens above check-in counters should typically display an airline logo or<br />

other image so that the traveling public proceeds to appropriate processing queue.<br />

Gate Information Display System (GIDS) screens at each gate holdroom area and<br />

counter podium back wall are used by the passengers as they approach in the<br />

holdroom to obtain updated flight status information, in a format customizable per<br />

each operating airline. GIDS screens should also be used to display boarding<br />

information if each airline chooses to integrate their boarding status information<br />

with the FIS (e.g. boarding by groups).<br />

DRAFT<br />

The FIS should be utilized by several entities at KCI to display and manage the New<br />

<strong>Terminal</strong> flight information as well as all terminals flights during transitioning<br />

phases. The quantity of displayed flights and display screens required within the<br />

terminal expansion area should be determined during design phases and should be<br />

adequate for displaying flight activity within peak operation hour sorted by flight<br />

time or by City depending on the Airport’s final determination. However, the<br />

system administrator should have the capability of defining maximum flight window<br />

times with scrolling options.<br />

The FIS will require a new AODB for all data entry and as the central storehouse of<br />

flight information and main input platform for all flight updates. The airport<br />

operational database (AODB) should provide a platform for high-level integration of<br />

airport operational systems. Bi-directional interfaces should be established<br />

between the New <strong>Terminal</strong> and the existing AODB during transition phases to<br />

receive updated data from automated airline data feeds, and to send current<br />

database information. Data from external sources should be utilized to provide<br />

updated seasonal schedule and code share information directly to the new<br />

Resources Management System (RMS), which in turn should update FIS via the<br />

AODB.<br />

Landrum & Brown Page 95<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

FIS hardware should be based on modern highly integrated ad virtualized devices<br />

(e.g. flat screens based on LED technology and integrated digital controllers).<br />

The application software should be scalable and can be easily expanded to meet the<br />

requirements of the new PTB, transitioning phases, and future expansion.<br />

3.4.7.2 Hardware Configurations<br />

In general, screen orientation and quantities should vary by location. The use of<br />

46-inch screens is the typical standard used in modern airports to accommodate<br />

landscape flight listing. Each gate podium back-wall should be provided with a<br />

46-inch LED backlit flat panel screen (GIDS) oriented in a landscape mode. Each<br />

baggage claim carousel should be provided with two back-to-back 46-inch LED<br />

backlit flat panel screens oriented in a landscape mode. All FIDS banks should be<br />

provided with multiple 46-inch LED backlit flat panel screens oriented in portrait<br />

mode to accommodate up to 120 departure/arrival flights during peak hour.<br />

Additional screens can be added if desired to expand the window for listed flights.<br />

Each LED backlit flat panel screen should be controlled by a dedicated video output<br />

from a Display Device Controller (DDC), which is module board built into each<br />

display (i.e. using a single 120V outlet for both screen and DDC). An AODB<br />

interface with CUSs should be implemented to automatically update flight listings<br />

above check-in counters upon agent sign in. Each inbound baggage unloading belt<br />

should contain an input device for use by the tug driver to indicate that bags for the<br />

flight are being unloaded (i.e. first bag and last bag). All baggage belts allocation<br />

should be completed automatically by the RMS without manual intervention by the<br />

tug drivers. Workstations should be provided in selected operational areas for<br />

manual updates of flight information.<br />

DRAFT<br />

3.4.7.3 General Requirements<br />

All FIS hardware and interfaces should be procured and implemented specifically for<br />

the New <strong>Terminal</strong> and eventually for the entire airport operations. Casework design<br />

and associated millwork requirements should be coordinated with the New <strong>Terminal</strong><br />

Architect.<br />

At FIS equipment locations, at least a duplex of 120 volts alternating current (VAC)<br />

receptacles is required to support display devices and any other ancillary<br />

equipment. Rack mounted equipment should utilize equipment rack power.<br />

The FIS system servers should be housed within the Data Center and/or MERs,<br />

which should be equipped with temperature and humidity control. Display devices<br />

should be equipped with integrated cooling systems and should be rated for<br />

continuous operations.<br />

Access to the FIS system should be restricted to authorized users via<br />

login/password authentication. The system should partition access to the flight<br />

information database such that airline personnel should have access to view and<br />

Landrum & Brown Page 96<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

edit only information associated with their airline. Airport administrators should<br />

establish access rights for all users. Lastly, the FIS system should operate on a<br />

secure partition of the LAN (i.e. VLAN).<br />

The FIS system field equipment and device quantities should be designed and sized<br />

to provide for system expansion to 300 percent of projected flight schedule without<br />

hardware/software upgrade.<br />

Backups of flight record databases should be executed on a regular basis per the<br />

airport maintenance/backup schedule.<br />

3.4.8 SECURITY SYSTEMS<br />

3.4.8.1 Access Control System<br />

An Access Control System (ACS) provides positive electronic control and monitoring<br />

of secure areas throughout the airport. The ACS for this project should be required<br />

to electronically control and monitor access between all restricted areas in addition<br />

to specially designated areas (i.e. communication rooms, utility areas, critical<br />

infrastructure areas, administration spaces, and other spaces identified by the<br />

airport) and vehicle access points to the airside areas. The system should also<br />

provide Guard Tour functionality using card readers and input points located at<br />

various points in PTB. The Access Control System (ACS) should be used in<br />

conjunction with the VSS/CCTV system to provide security control center with the<br />

information needed to monitor safety, enforce airport regulations and security, and<br />

general operations of the airport.<br />

The ACS should be designed to provide positive control of the New <strong>Terminal</strong>.<br />

This should include control of the main facility entrances, loading dock areas, staff<br />

entrances, control of public access into various areas of the facility, and should<br />

include all vertical circulation within the facility including elevators and stairways.<br />

Airport security zones called out within this narrative and other project documents<br />

are based on the following definitions:<br />

<br />

<br />

DRAFT<br />

Airport Operational Area (AOA): The area specified in the Airport Security<br />

<strong>Program</strong> (ASP) in which security measures specified in the ASP are carried<br />

out. This area includes aircraft movement areas, aircraft parking areas,<br />

loading ramps, and safety areas, for use by aircraft regulated under 49 CFR<br />

part 1544 or 1546, and any adjacent areas (such as general aviation areas)<br />

that are not separated by adequate security systems, measures, or<br />

procedures. This area does not include the secured area.<br />

Secured Area: The area of the airport utilized for the loading and unloading<br />

of commercial aviation aircraft within which certain security measures<br />

specified in 49 CFR part 1542 are carried out. This area is where aircraft<br />

operators and foreign air carriers that have a security program under part<br />

1544 or 1546 of this chapter enplane and deplane passengers, sort, load<br />

baggage, and any adjacent areas that are not separated by adequate<br />

security measures. This is the highest security area of the airport.<br />

Landrum & Brown Page 97<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

Security Identification Area (SIDA): This area encompasses both the AOA<br />

and Secured Area and is the area in which Identification must be displayed<br />

including the portion of the airport, specified in the ASP, in which security<br />

measures are carried out.<br />

Public area: Any portion of the airport in which the visiting or traveling<br />

public can freely enter without screening of person or property.<br />

Sterile area: A portion of the airport defined in the ASP that provides<br />

passengers access to boarding aircraft and to which the access is generally<br />

controlled through the screening of persons and property<br />

Non-public area: A portion of the airport in which the owner or tenants<br />

conduct business where the traveling public does not require regular access.<br />

Non-public sterile area: A portion of the airport that the public does not<br />

require regular access and the access for employees is controlled through the<br />

screening of persons and property.<br />

<br />

<br />

Customs area: A portion of the airport operated by the CBP including the<br />

CBP Office spaces, CBP Booths, processing area, and secondary screening<br />

area, and the Secure Corridor System (SCS) from the aircraft to the CBP<br />

processing area. This area includes international arrivals.<br />

Transition/Swing: A portion of the airport that transitions between multiple<br />

security zones. International flight Jet-bridges and the associated vestibules<br />

are examples of these areas.<br />

The ACS should use a combination of access media such as smart cards, card<br />

readers, guard tour input points, door hardware, door position monitoring<br />

equipment, and access control components to fully monitor and control access<br />

throughout the facility. The ACS should control access and provide tracking of all<br />

access and attempted access events as well as log and enunciate all alarms on the<br />

system at the alarm monitoring workstation. The ACS should be used to segregate<br />

employees and visitors to specific areas or zones, allowing or denying access based<br />

upon user rights, time schedules, programmed rules, or any combination of the<br />

above.<br />

DRAFT<br />

The New <strong>Terminal</strong> and associated facilities should operate under a new ACS that is<br />

separate from any existing access control systems associated with other existing<br />

airport facilities. However, the rest of the airport should transition to the new<br />

system to minimize duplicative badges and information. A new Identity<br />

Management System and associated smart cards should be provided as part of the<br />

new system. This means that employees that work in both existing and proposed<br />

facilities should require separate and unique identification badges for overall access<br />

during transition phases.<br />

All cards should be contactless Smart cards with 32Kbit of memory. All card<br />

readers should be contactless type readers with keypads and should be equipped<br />

with a Light Emitting Diode (LED) display and an audible device to provide visual<br />

and audible feedback to the user for access granted and denied. All cards should<br />

Landrum & Brown Page 98<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

be provided with keypads to allow the reader to be able to read contactless smart<br />

cards in addition to requiring the use of a Personal Identification Number (PIN) for<br />

heightened security.<br />

All Card Readers used for access to critical areas such as access to the Customs<br />

area, terminal MER, Sterile or Secure from Public, critical infrastructure areas, and<br />

other sensitive and critical areas of the terminal should be equipped with card<br />

readers with biometric readers and keypads that can provide three factor<br />

authentication of the card holder.<br />

All MERs, TRs, and designated critical infrastructure room doors should be accesscontrolled<br />

with contactless card readers with biometrics and keypads. Electrical<br />

and Mechanical room doors and emergency building exits should be monitored by<br />

door position switches at a minimum to report entries and door status.<br />

The ACS should consist of IP-based, redundant, real-time host processors/servers,<br />

multiple workstations and terminals, and a hierarchy of IP based intelligent field<br />

panels that provide connections for specified readers, portal input devices, portal<br />

output devices, monitor and control devices. The system should be capable of<br />

routing individual alarms to specific workstations.<br />

The ACS will include equipment to enforce rules and regulations at the Airport.<br />

The ACS hardware should include devices at specific portals to prevent<br />

unauthorized tailgating/piggybacking or unauthorized escorting through the portal.<br />

The ACS should include equipment to detect possible wrong-way entry through exit<br />

Lane corridors and provide alarms upon these events to prevent a breach condition<br />

from occurring.<br />

DRAFT<br />

The ACS should incorporate the monitoring of other alarms types such as duress<br />

alarms, Automatic External Defibrillator (AED) cabinet opening, and Intrusion<br />

Detection. Upon activation of duress buttons, additional actions or responses<br />

should be provided such as disallowing extended hold functions on Passenger<br />

Boarding Bridges, the activation of audible/visual devices within the sterile area,<br />

and the pre-positioning and call-up of cameras within the affected area. Detection<br />

of an AED cabinet being opened should allow for the activation of audible/visual<br />

devices adjacent to the cabinet and the call-up and pre-position of cameras in the<br />

area of the cabinet. An Intrusion Detection alarm should allow for the activation of<br />

audible/visual devices in the area of the alarm and the call-up and pre-position of<br />

cameras in the area.<br />

The ACS should be interfaced with the Video Surveillance System (VSS) to provide<br />

camera call-up and Dome fixed and Pan-Tilt Zoom (PTZ) pre-position upon ACS<br />

alarm. The ACS should be interfaced with the Fire Alarm System to provide release<br />

of doors in the path of egress as required by the Authority Having Jurisdiction and<br />

as required to meet Code.<br />

The ACS should include a separate Identity Management sub-system, which allows<br />

for the enrollment of personnel, storage of information, capture of biometric<br />

templates, and the production of Identification Badges for use by the staff for<br />

Landrum & Brown Page 99<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

access to and within the facility. The ACS should provide high security printing<br />

capabilities including security overlays and holograms. The system should include a<br />

minimum of four Identity Management Workstations with full data entry, photo<br />

capture capability, and card printing. The card printers should be capable of<br />

printing cards on both sides and should be able to produce a double sided, full color<br />

encoded card in less than 60 seconds.<br />

The ACS should include a minimum of 10,000 smart cards along with sufficient<br />

printer supplies such as printing ribbons and holographic overlays to print all of the<br />

cards in a double-sided printing configuration. Location of Identity Management<br />

Workstations and access to the public should be determined during subsequent<br />

design.<br />

The ACS should utilize numerous technologies including card readers, door position<br />

sensors, audible/visual devices, locking equipment, and other devices to control<br />

and monitor the portal operation throughout the facility. The access control is<br />

capable of utilizing card readers, card readers with PIN pads, and card readers with<br />

PIN pads and biometrics. Project door hardware should be concealed/flushmounted<br />

where possible and should be coordinated with the architect. Door<br />

functionality should be defined based on the usage requirement for each door type.<br />

Typical Airport ACS control points include:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Telecommunication room doors<br />

Utility Room doors (mechanical, electrical, etc)<br />

Man-trap doors<br />

Overhead doors<br />

Baggage claim chop doors<br />

Oversized baggage claim doors<br />

Check-in counters baggage doors<br />

Oversized check-in baggage doors<br />

Access hatch openings<br />

Operational doors<br />

Egress doors<br />

Elevator Cab Floor control/Elevator call control<br />

Emergency exit only doors<br />

Ground Boarding doors<br />

Passenger Boarding Bridge doors (Extended Hold Functions)<br />

Security equipment/screening checkpoint shut down gate control<br />

Airfield Gates<br />

DRAFT<br />

Landrum & Brown Page 100<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

Guard Tour input points. The ACS should support guard tour management<br />

allowing the configuration of card readers and inputs to be used as guard<br />

tour points. The system should generate alarms and reports to indicate the<br />

status of each tour.<br />

Silent alarm/Duress Button locations (security checkpoints, information<br />

counters, CBP Booths, CBP Interview Rooms, and CBP Coordination Center,<br />

KCAD Airport Police Division publicly accessible counter locations)<br />

General Requirements<br />

<br />

<br />

<br />

<br />

<br />

Software: licenses for equipment added as part of the PTB Project should be<br />

provided including all servers, workstations, and reader ports.<br />

Space and Mounting Requirements: All controllers should be mounted within<br />

secured, monitored, wall-mounted panels inside the communication rooms.<br />

ACS servers should be housed in lockable cabinets inside the terminal MER.<br />

Spares: At least five percent of all field components should be provided.<br />

Power: Servers/Workstations – 120 VAC plug in inside cabinets fed by UPS.<br />

Servers should also have generator back-up in addition to UPS. Controllers,<br />

modules, and door devices should be fed from a wall mounted 120 VAC to<br />

12/24 volts direct current (VDC) power supply with a minimum of 4-hour<br />

battery or UPS back up unit that is hardwired to a generator backed-up<br />

emergency circuit.<br />

Environmental: All servers should be housed within the terminal MERs which<br />

should be equipped with temperature and humidity control.<br />

Typical system integration/interface requirements for this system are indicated<br />

below.<br />

VSS System: To provide automatic alarm call up and pre-positioning of<br />

camera views associated with ACS alarms to provide live viewing of areas<br />

surrounding the ACS alarm. To provide alarm ‘flagging’ of associated video<br />

for quick recall and ease of incident review. This interface should be<br />

accomplished using manufacturer’s standard IP/Ethernet software<br />

communication.<br />

<br />

<br />

DRAFT<br />

Fire Alarm System (FAS): To provide fire alarm release of any ”means of<br />

egress” doors that are located within the fire alarm zone that is in alarm for<br />

evacuation purposes. This interface should be accomplished using dry<br />

contacts from Fire Alarm system within the Communications Rooms to drop<br />

power to the magnetic lock power supplies or provide a fail-safe signal to<br />

mortise type locks for portals that are required for emergency egress.<br />

Elevator Interface: To provide elevator control to restrict secure floor access<br />

to authorized personnel only. This interface should be accomplished using<br />

dry contacts from the ACS system into the elevator controller to control the<br />

appropriate floor selection buttons.<br />

Landrum & Brown Page 101<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

Baggage Handling System (BHS): To provide control of the baggage chop<br />

doors and bag belt activation that occur on the public to secure security lines<br />

for authorized personnel only. This interface should be accomplished using<br />

dry contacts from the ACS system into the baggage system control panel to<br />

control baggage activation only after a valid card read and monitor baggage<br />

run and parallel chop door contacts.<br />

Building Management System: The ACS should interface with the Building<br />

Management System to provide any required system operation status for<br />

overall maintenance and automatic work order dispatch.<br />

3.4.8.2 Video Surveillance System (VSS)<br />

The VSS (aka Closed Circuit TV or CCTV) should be designed to provide general<br />

video surveillance of the terminal, adjacent airfield, outbuildings, and vehicle gates<br />

associated with this project. Coverage should include public entrances and exits,<br />

staff entry and exits, exterior perimeter areas, loading dock areas, passenger<br />

screening areas and checkpoints, elevator lobbies, elevators and public areas on<br />

the various terminal floors. The intent is to provide identification and recognition<br />

level video in these areas to allow for the tracking of people within the facility.<br />

In addition, the VSS should support the ACS system by providing coverage of all<br />

Access Controlled portals to allow for assessment of alarms from a central<br />

monitoring point.<br />

The proposed VSS should not be based on reusing the existing security camera<br />

monitoring systems currently in operation at the existing airport facilities. Instead,<br />

it should be a new and separate head-end server system provided along with<br />

separate video storage components as part of new PTB.<br />

The VSS should be comprised of IP type cameras, the transport of digital video<br />

signals over the LAN to the digital video management system, the display of live<br />

camera video, and the archiving of all camera video onto long term enterprise-class<br />

storage facilities.<br />

The VSS should be required to monitor and record activities throughout the New<br />

<strong>Terminal</strong>. All cameras should be recorded on a continuous basis. Increased<br />

recording frame rate or resolution should be either manually triggered by the<br />

operators or automatically triggered by access control alarms and/or motion<br />

detection technology. The following areas should, but are not limited to, require<br />

cameras:<br />

<br />

<br />

<br />

<br />

<br />

<br />

DRAFT<br />

Portals between public and sterile areas of the airport<br />

Portals between public and secure areas of the airport<br />

Portals between sterile and secure areas of the airport<br />

General ramp and roadway areas<br />

General Sterile Area coverage<br />

General Public Area coverage<br />

Landrum & Brown Page 102<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

<br />

<br />

<br />

Security Screening Checkpoints<br />

Customs and Passport Control areas<br />

Hold Baggage screening areas<br />

Bag Claim Areas<br />

Curbsides<br />

The VSS should be based on IT standards to allow for the use of open architecture<br />

equipment and other standards such as Open Network Video Interface Format<br />

(ONVIF) for video transport, processing, and storage. The VSS should be a<br />

software-based system that should allow for the simultaneous viewing, recording,<br />

and review of recorded video. The Graphical User Interface (GUI) should include a<br />

map-based interface to allow for the selection of a camera based on location.<br />

The system should also include a video surround feature that should allow for the<br />

cameras that are adjacent to the current camera being viewed to be viewed and<br />

selected to allow for the following of a person. Upon selecting a new camera as the<br />

primary view, that camera should move to the center panel and the adjacent<br />

cameras should be repopulated around the primary camera automatically.<br />

The VSS should be fully redundant such that the loss of any individual system<br />

component (excluding actual camera loss) should not degrade video performance or<br />

prevent recording to or retrieval of video from the Storage Area Network (SAN).<br />

All video should be stored on the SAN provided as part of this project. The SAN<br />

capacity should be provided to allow all cameras to be stored at their native<br />

resolution, full color, at 15 fps during motion in the camera field of view or based<br />

upon alarms and at 7.5 fps during periods of inactivity. All video should be stored<br />

for a minimum of thirty days. It is anticipated that cameras should view motion for<br />

50 percent of the time in a typical 24-hour period. A smaller capacity (i.e. seven<br />

days storage) should be provided in the Secondary MER to maintain operations in<br />

case of loss of the Primary MER.<br />

DRAFT<br />

The system should also include video analytics as required to provide perimeter<br />

detection of the facility and in remote areas of the facility.<br />

The VSS system should be utilized for security surveillance, operational monitoring,<br />

and forensic analysis of events or alarms via recorded video. The system should be<br />

used by all security and law enforcement agencies including the KCAD Airport Police<br />

Division, TSA, CBP, and other Government authorized agencies. Monitoring<br />

workstation locations should be coordinated with stakeholders during the design<br />

phase. Hardware for the VSS system is discussed in Appendix X, Specialty Systems<br />

and New Technology.<br />

Landrum & Brown Page 103<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.4.8.3 Security Checkpoint Screening Systems<br />

The main function of security screening at airports is to screen people and goods to<br />

ensure that weapons, contraband, or dangerous items are prevented from being<br />

introduced onto an aircraft or entering the country. Security screening functions in<br />

the U.S. are currently performed by the TSA, and all equipment at the SSCP is<br />

provided by the TSA. The typical screening locations include the following<br />

locations.<br />

Passenger Security Screening Checkpoint: Per TSA regulations, all passengers,<br />

people, and goods/baggage entering the Sterile Area must be screened. This will<br />

typically include a mixture of Walk Through Metal Detectors (WTMD), <strong>Advance</strong>d<br />

Imaging Technology (AIT) scanners, Hand-held metal detectors, Explosive Trace<br />

Detection (ETD) equipment, and Hand Baggage X-Ray Equipment.<br />

Employee/goods Security Screening Checkpoint: The provision of a dedicated<br />

Employee or Goods Screening checkpoint varies from airport to airport. Some<br />

facilities allow employees to use Access Control as the primary control, while other<br />

facilities require screening of all personnel. At some facilities, all personnel are<br />

required to go through the public SSCP, while other facilities provide separate<br />

facilities. Likewise, the screening of goods varies from facility to facility. Some<br />

facilities use a separate goods screening area, while others use the public SSCP but<br />

prohibit goods screening during busy or peak times. For this facility, we<br />

recommend the implementation of a separate goods/employee screening area.<br />

This will facilitate a more efficient flow and prevent the mixing of the two separate<br />

populations.<br />

Security Check Point Configuration Considerations<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

DRAFT<br />

Queuing Space: The queue is where passengers stand in line at the front of<br />

the checkpoint on the public side. Depending on the architectural layout, the<br />

queue should be bounded by double strap stanchions along the perimeter<br />

with single strap stanchions defining the various lanes from the queue<br />

entrance including separated men from women lanes.<br />

Baggage X-Ray Machine (by TSA)<br />

Trays holder (Manual tray return) (by TSA)<br />

Loading Table/Entrance Roller Conveyor (by TSA)<br />

In-feed Tunnel (by TSA)<br />

Scanning Belt (continuous from In-feed to Out-feed Tunnel) (by TSA)<br />

X-ray Dome (dual axis / multi view x-ray) (by TSA)<br />

Built in Liquid Scanner (as per latest standards) (by TSA)<br />

Out-feed Tunnel including alarm bag cut-out (by TSA)<br />

High Speed Conveyor & Tunnel (by TSA)<br />

Extension Rollers and/or Exit Roller (by TSA)<br />

Landrum & Brown Page 104<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

<br />

<br />

Walk Through Metal Detector (WTMD): The WTMD is an electronic archway<br />

used to detect metallic weapons and/or metal contraband concealed on a<br />

person. (by TSA)<br />

Barriers & Wheelchair Gates (by TSA)<br />

In order to prevent passengers and/or items from passing into the sterile<br />

area from the non-sterile area without being screened, barriers and/or<br />

wheelchair gates should be installed to close all gaps exceeding 300mm<br />

across the front width or façade of the checkpoint. (by TSA)<br />

<strong>Advance</strong>d Imaging Technology (AIT) (by TSA)<br />

Holding Stations: A holding station holds passengers temporarily until<br />

screeners are available to escort them to the proper area to conduct<br />

secondary screening using hand held metal detection wands. The holding<br />

station should be positioned so passengers can be diverted directly into the<br />

area without obstructing the path of non-alarming passengers, and should<br />

prevent the passing of prohibited items to sterile passengers. (by TSA)<br />

• Explosives Trace Detection (ETD): Secondary baggage screening areas are<br />

required for clearing passenger carry-on items when the primary screening at<br />

the X-ray indicates suspect items. Secondary baggage screening areas<br />

should include Explosives Trace Detection (ETD) device. (by TSA)<br />

<br />

<br />

<br />

Private Search Area: Private screening rooms should be located at the back<br />

end of the checkpoint in the sterile area. The area should be available to<br />

accommodate passengers who request private screening instead of being out<br />

in the open. The private screening room should be opaque. (by TSA)<br />

Egress Seating Area: Egress seating at the sterile side of the checkpoint is<br />

used for passengers to sit down and compose themselves with their personal<br />

belongings after completing the screening process. This area is usually out<br />

of the main passenger flow.<br />

Supervisory Podium: A podium should be located on the sterile side near the<br />

checkpoint exit to provide the screening supervisor with adequate viewing of<br />

the overall operation. This podium will typically be provided with an<br />

ACS/VSS workstation to allow for duress alarm reporting and viewing of<br />

CCTV images from the SSCP.<br />

Adjacent Walls & Boundaries: All walls adjacent to the non-sterile side<br />

should be at least ten feet high to prevent the passage of prohibited items<br />

from the non-sterile area to the sterile area.<br />

General Requirements<br />

DRAFT<br />

<br />

Space and Mounting Requirements: Space allocation requirements for SSCP<br />

equipment should be closely coordinated with the Architect for appropriate<br />

passenger flow. Quantities of SSCP equipment at each specific screening<br />

location should be dependent upon overall operational requirements and<br />

should be closely coordinated with the Architect for appropriate passenger<br />

flow.<br />

Landrum & Brown Page 105<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

Power: Servers/Workstations – 120 VAC plug in inside cabinets fed by UPS.<br />

Servers should also have generator back-up in addition to UPS. Equipment<br />

should be fed from 120 VAC receptacles that may have UPS back up unit that<br />

is hardwired to a generator backed-up emergency circuit. Design of SSCP<br />

equipment floor power locations should be closely coordinated with the<br />

electrical designer.<br />

Data: The WTMD, X-Ray, AIT, and ETD equipment have data connection<br />

requirements. Provide data outlets for this equipment. Coordinate<br />

requirements with TSA.<br />

Environmental: All servers (as required) should be housed within the<br />

terminal MER, which should be equipped with temperature and humidity<br />

control.<br />

3.4.8.4 CHECKED BAGGAGE SCREENING<br />

The Hold Baggage Screening System (HBS) provides screening of all checked bags<br />

prior to the baggage being loaded onto aircraft. Per the scope of work, the Hold<br />

Baggage Screening is required to meet all TSA standards. Currently, there are no<br />

in-line TSA certified Explosive Detection System (EDS) machines available for Outof-Gauge<br />

(OOG) baggage due to tunnel dimension limitations; as such, TSA<br />

requires manual processing of all OOG baggage through Explosive Trace Detection<br />

(ETD) machines.<br />

Hold Baggage Screening: Hold Baggage Screening is required for all baggage that<br />

is checked and will be transported on commercial passenger aircraft. There are<br />

typically three stages to this screening which includes the use of Explosive<br />

Detection System (EDS) equipment, a Stage 2 screening involving on-screen<br />

resolution, and finally a Stage 3 that involves manual search and ETD verification.<br />

Bags that pass at any stage will be routed for loading onto the aircraft; bags that<br />

fail will be sent for disposal. Ultimate disposal of suspect bags would be via bomb<br />

disposal equipment.<br />

DRAFT<br />

3.4.9 TELECOMMUNICATION SYSTEMS<br />

3.4.9.1 Voice Communication Systems – Telephone<br />

Telephone service should be provided based on Voice over Internet Protocol (VoIP)<br />

solution. Telephone service to the desktop work areas should be provided by<br />

common data network infrastructure enabling a data information sharing platform<br />

over the telephone. A call processor unit with backup unit should be located in<br />

MERs.<br />

The system should interface with various audio video conference systems. Subject<br />

to final calculations for the New <strong>Terminal</strong> and other new facilities, the system<br />

should be provided to serve approximately 1,500 to 3,000 endpoints initially and<br />

should be capable of serving ultimately 5,000 endpoints. The system should allow<br />

initial endpoints installed with Direct Dial Inwards (DDI) telephone numbers as<br />

needed.<br />

Landrum & Brown Page 106<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Gateways should be provided to serve a trunk line capacity of 300 trunk lines<br />

initially using PRI digital trunk technology and SIP protocol as coordinated with the<br />

new terminal and Telcos. The external lines should be distributed between the<br />

primary and secondary service providers’ entrances.<br />

As a minimum, but not limited to, the VoIP devices/server, software and handsets<br />

should be required to support industry based, standard protocols, and specifications<br />

as discussed in Appendix X, Specialty Systems and New Technology.<br />

Interactive Voice Response (IVR) with speech recognition capabilities should be<br />

provided to provide callers the ability to navigate to destinations after being<br />

presented audible menu options. Voice Mail & Unified Messaging should be part of<br />

the system. All lines, subject to activation of service, should be provided with Voice<br />

Mail capability.<br />

3.4.9.2 Wireless Data/Voice<br />

A building wireless LAN system should be provided; it is recommended that the<br />

system use discrete access points. Access points should be considered "light<br />

weight” and should be controlled via a backend engine. Wireless networks should<br />

be designed to carry wireless traffic for voice and data systems. The General data<br />

network should be used for all public WiFi services including billing and charging<br />

modules for pay per use service, if desired. Standards, certifications, and<br />

requirements for the WLAN are listed in Appendix X, Specialty Systems and New<br />

Technology.<br />

3.4.9.3 Distributed Antenna System<br />

Like all large steel and glass buildings, the New <strong>Terminal</strong> building structure should<br />

significantly weaken the propagation of externally-generated wireless signals inside<br />

the terminal building. Due to this, a wireless distribution system should be installed<br />

to provide uniform radio coverage throughout the new terminal. The main function<br />

of the system, which should be referred to as the Distributed Antenna System<br />

(DAS), is to receive, amplify, and distribute public safety radio and cellular phone<br />

signals as-is. The DAS should be state-of-the art in design and function, and<br />

should provide excellent coverage to commercial and non-commercial portable<br />

radio devices used within the new terminal. The DAS should provide ubiquitous<br />

coverage for all trunked radio, public safety frequencies, ground to air radio and<br />

VHF/UHF radio systems. The system should be comprised of the following<br />

components:<br />

<br />

<br />

<br />

Antennas<br />

DRAFT<br />

Digital signal distribution system<br />

RF signal radiating elements<br />

Landrum & Brown Page 107<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

All antennas used by the airport, airlines, and tenants for wide-area radio<br />

communications should be located at the antenna farm, a high and visually discrete<br />

rooftop area on the New <strong>Terminal</strong>. All DAS equipment including transceivers and<br />

amplifiers required by the airport or service providers should be located in the<br />

MERs, which should have direct pathways to the antenna farm.<br />

The active components of the DAS should convert radio frequency signals from the<br />

transmitters and amplifiers to loss-free signals for distribution throughout the<br />

terminal interiors and back to the wide-area radio network. The distribution system<br />

should be comprised of a mixture of fiber, CAT-6a, solid coaxial cabling and interior<br />

antennas.<br />

Dedicated Radio Dispatch Consoles for radio communications and radio paging<br />

should be provided in all Airport Security, Operations, and Emergency Centers.<br />

However, the type and configuration of the console should be dependent on<br />

used/planned frequencies (e.g. 700/800MHz, UHF, VHF, paging tones, etc.).<br />

3.4.9.4 Intercom<br />

Intercom systems are fixed point-to-point communications devices that allow for<br />

ease of communication between geographically separated locations. However,<br />

recently, intercom systems have been usurped in favor of using existing telephone<br />

lines and VoIP wireless telephones. This type of system should not be provided in<br />

any of the proposed facilities and instead its functionality should be provided by the<br />

proposed VOIP telephone system using call boxes that mimic intercom functions.<br />

3.4.9.5 Audio/Visual & Teleconferencing<br />

The PTB should contain spaces dedicated for conferences and training; these areas<br />

should be used for general meetings or presentations. A/V requirements should be<br />

customized to the spaces that house them, depending on use, room size, and<br />

ancillary requirements. Design consideration for each space should be defined<br />

based on best practices to provide users with needed features and flexibility.<br />

Typical small conference rooms could consist of a wall mounted flat panel display<br />

screen. More complex systems found in large conference rooms and board rooms<br />

could include large flat screens, motorized projectors, and speakers, sound<br />

reinforcement, discrete microphone placement, and smart boards with integrated<br />

video conference capabilities. A list of A/V systems and devices that should be<br />

included is in Appendix X, Specialty Systems and New Technology.<br />

Preliminary Room types and examples of A/V equipment in each room type is as<br />

follows:<br />

<br />

DRAFT<br />

Large Conference Rooms should support Executive meetings at the PTB. It is<br />

expected that these spaces should vary in architectural fit and finish but<br />

should incorporate similar technologies. A/V equipment should include front<br />

projection display, integrated supplemental flat panel displays in custom<br />

furniture, video teleconferencing, DVD, IPTV, robotic cameras, low profile<br />

table microphones, integrated control touch screen, etc.<br />

Landrum & Brown Page 108<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

Multipurpose rooms are typically large spaces that can be subdivided into<br />

smaller rooms for different uses. Due to the nature of these environments,<br />

the audio systems and front projection systems are typically the only<br />

components permanently installed into the space. When divided, the<br />

segments' audiovisual systems are fully self-contained and function<br />

independently. When combined, the segments' audiovisual systems combine<br />

to function as a single entity. Laptop, video, audio, power and network<br />

connections should be provided in floor boxes throughout. Furniture should<br />

be furnished with table-top flip-up panels containing power, network, laptop,<br />

and A/V connections. Control over the rooms should be via wall-mounted<br />

control in each segment and a wireless touch screen for use either at the<br />

lectern or table top. The control system programming should feature<br />

automated setup macros for different room configurations via single button<br />

presses.<br />

Staff meeting rooms and small conference rooms should have technologies<br />

present to allow for presentations and curriculum development. Typically,<br />

they should have a wall mounted flat panel display and a resident personal<br />

computer (PC) along with a laptop plug-in point at the table. <strong>Program</strong> audio<br />

should come from the flat panel’s internal speakers and a conference phone<br />

is typically available on the table. Control is handled via the flat panel<br />

infrared handheld remote. In addition to audiovisual equipment supporting<br />

computer display, staff’s meeting rooms are typically outfitted with<br />

whiteboards and tack surfaces.<br />

The Central Systems Management and Software system should be wired<br />

digital system or a client/server network based system to provide network<br />

based remote room control, resource management, monitoring, and<br />

scheduling capabilities in support of audiovisual systems that have integrated<br />

networked control systems across the campus. It should also serve as the<br />

core system for audio visual help desk support across the campus. Touch<br />

screen controllers should be provided outside of each audiovisual enabled<br />

space where room schedule information can be displayed and edited.<br />

3.4.9.6 Master Cable / IPTV System<br />

<br />

<br />

DRAFT<br />

A master Cable or Internet Protocol TV (IPTV) system should be provided in<br />

the new terminal. The system should allow TV signal distribution, digital<br />

signage, dynamic advertisement, and auxiliary visual paging. Either a<br />

traditional fiber/coaxial based Cable TV distribution or a separate IPTV TV<br />

signal modulators, streaming servers, and middleware servers should be<br />

provided to distribute signals throughout the PTB.<br />

If IPTV is utilized, the data network should be configured for QoS parameters<br />

to achieve video streaming without disruption the user experience. Exact<br />

values should be set the Final Specifications. Likewise, IP Set-Top Box<br />

(STB), which is a digital system designed and built to receive interaction with<br />

the unlimited world of IP services including TV Channels, Audio programs,<br />

Music, Widgets, Games and much more. With applications in the broadband<br />

environment, the HD IP Set-Top Box has multicast or Internet Group<br />

Management Protocol (IPTV) support (IGMP), Video-On-Demand, Audio-On-<br />

Landrum & Brown Page 109<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Demand, EPG, CA support (if required), and digital stereo audio support. All<br />

provided through the HD IP Set-Top Box’s powerful hardware platform,<br />

strong multi-audio/video H.264, MPEG-2, MPEG-4 decoding support. STBs<br />

should be employed for each TV location to receive IPTV signals. Standard<br />

data outlets should be utilized for horizontal cabling connectivity.<br />

TV signals should be distributed in the following areas:<br />

Departure Lounges<br />

VIP waiting areas<br />

Meeting and greeting areas<br />

Pay-per-use for tenants and concessionaires<br />

Digital Advertisement: Provisioned areas for advertisement video walls are<br />

as follows:<br />

Departure and Arrival Corridors<br />

Dedicated screens should be used for digital signage, electronic way finding<br />

guidance, and people flow to direct passengers to various services and<br />

events within the terminal.<br />

The overall system should be specified for Day 1 provision with additional<br />

100 percent without the need for Expansion hardware and software license.<br />

3.4.9.7 Public Address System (Overhead Paging)<br />

The Public Address (PA) System should provide the ability to distribute intelligible,<br />

loud, and uniform audio signals to set groups of speakers or zones in corridors and<br />

waiting rooms. The PA system should include field equipment including speakers,<br />

cabling, and paging microphones as well as the head-end equipment including the<br />

overall paging control system, digital signal processor, and amplifiers.<br />

DRAFT<br />

The PA system should be an IP based system that utilizes the network for<br />

distribution of audio programming from the head-end to the distributed PA<br />

amplifiers and field equipment. The ability to page from individual<br />

microphones/paging stations or the delivery of automated messages to specific<br />

zones should be fully programmable. The system should provide for the ability to<br />

page from the phone system by authorized users as required.<br />

The system should provide “zoned” and “all call” paging as required. Amplifiers<br />

should be distributed throughout the TRs. This system should allow for preprogrammed<br />

messages, integration into the Building Automation System, Fire<br />

Alarm System, and Building Security System. The system should have the<br />

capability of playing Azan for prayer times and other type of messages as needed in<br />

selected areas.<br />

The Public Address system should be zoned and programmable to distribute specific<br />

messages to specific zones while excluding other specific areas.<br />

Landrum & Brown Page 110<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

PA Zoning should be defined according to functional space. Zones should be<br />

organized so that a terminal area is contained in a zone and zones should not<br />

generally cover more than one area. All locations should be equipped with at least<br />

one general announcement zone that may be comprised of smaller sub-zones as<br />

required by the functional operation of the <strong>Terminal</strong>.<br />

IP based Paging stations should be provided in all Operations/Security Centers, and<br />

main public paging information desks.<br />

In large voids that have acoustically challenging environment, such as building<br />

entrances and baggage hall, line array type speakers should be utilized to achieve<br />

the required level of intelligibility and loudness. The contractor should be required<br />

to validate the speakers’ layout design with appropriate electro acoustical study.<br />

3.4.9.8 Data Storage<br />

A new Storage Area Network (SAN) should be provided within the campus wide<br />

data centers as part of this project. The SAN should utilize Fiber Channel or Fiber<br />

Channel over Ethernet (FCOE). FCOE is the preferred option due to elimination of<br />

dedicated fiber channel components and direct utilization of a unified fabric based<br />

network. The Storage Area Network (SAN) should provide storage for, but not<br />

limited to, digital video storage for the VSS, storage to multimedia systems,<br />

storage for Audio/Visual, backup of operating system, and support for servers and<br />

desktop virtualization as needed. The SAN should be comprised of modular storage<br />

arrays, should be expandable, and should have sufficient size and speed to assure<br />

consistent storage.<br />

DRAFT<br />

The SAN can be expanded to serve all personal storage, server storage, databases<br />

to support the airport operation systems, general storage, and special systems<br />

storage. The SAN should be fully redundant and the storage arrays should be<br />

configured in a redundant array of independent disks (RAID) 6 configuration with<br />

redundant striping of data and error codes hot standby drives ready in case of a<br />

failure. The SAN should be of sufficient speed to be able to rebuild the failed disk<br />

while still providing full operation without degradation in the overall performance of<br />

the SAN. The SAN should also be capable of performing all diagnostics and utilities<br />

required for Preventative Maintenance without degrading performance of the<br />

system.<br />

The size of the primary SAN should not be less than 500 Terabytes (TB) with the<br />

capability to expand up to a total size of no less than 1 Petabyte. Final capacity<br />

should be determined during design phases. All SAN controllers provided should be<br />

fully redundant and capable of accepting the expansion noted above without<br />

requiring any changes or upgrades. SAN on-line storage (i.e. Tier 1 high speed<br />

Fiber Channel or serial attached small computer system interface (SAS) drives)<br />

should be at least 50 percent of total capacity to support low latency transactional<br />

applications. Near-line storage (i.e. Lower speed serial advanced technology<br />

attachment (SATA) II drives) should be used for higher latency applications such as<br />

reference applications, archival and backup data. The SAN should provide<br />

automatic backup by taking periodic snapshots of active data in order to provide a<br />

Landrum & Brown Page 111<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

method of recovering records that have been deleted or destroyed. It is assumed<br />

that off-site data archival should be provided by others as part of existing Operation<br />

and Maintenance procedures of the Airport.<br />

3.4.10 OPERATION CENTERS<br />

3.4.10.1 Existing Communication Center and Emergency<br />

Operations Center<br />

The current Communications Center and Emergency Operations Center (EOC) are<br />

located on the third floor of the Airport Police Building. It has not yet been fully<br />

determined if the Police Building will remain as part of the PTB project. However,<br />

regardless of whether the building is maintained, the current available space is not<br />

sufficient to allow growth of the Communications Center or the EOC.<br />

The Communications Center functions as the Security Operations Center for the<br />

existing airport facilities. All Access Control alarms are monitored and dispatch<br />

occurs from this location. The CCTV cameras are also displayed on a video wall<br />

within the Communications Center, and the Communication Center operators<br />

monitor the CCTV cameras throughout the facility when not responding to other<br />

alarms or events. Directly across the hall from the Communications Center is the<br />

EOC. The existing EOC is conference room with Audio/Visual capability. Overall,<br />

these two spaces and the functions performed should be reconsidered in the<br />

context of the new PTB project, and the functions expanded to meet the operational<br />

needs of the new facility.<br />

DRAFT<br />

The trend in airports is to combine more functions into a single operations center,<br />

referred to as an Airport Operations Center (AOC). Depending upon the Airport<br />

business model, it is becoming more common that the AOC perform overall Airport<br />

Operations as well as Security Operations. One of the main business drivers for<br />

this model is to leverage the work force required for Operations Centers, as well as<br />

providing a single point of contact and dispatch for the overall facility.<br />

This improves the overall Airport Situational Awareness, improving function, safety,<br />

and security by allowing more concise response to incidents and events that is<br />

possible with split Operations and Security Centers.<br />

3.4.10.2 Airport Operations Center<br />

The Airport Operations Center (AOC) is the focal point for command and control of<br />

KCI operations; communications; security monitoring and operations; specialized<br />

technologies; and information collections, assessment, analysis, and dissemination<br />

for all resources under non-emergency and emergency conditions to support a<br />

common operating picture. It is assumed that an AOC should be developed to<br />

support the new <strong>Terminal</strong> expanded operational requirements.<br />

The primary responsibility of an AOC is the safe, efficient, and secure movement of<br />

passengers, employees, aircraft, and vehicles within the new terminal and, if<br />

desired, for the entire airport complex. The AOC should monitor the entire PTB<br />

operations and respond to issues to resolve situations affecting security, life safety,<br />

Landrum & Brown Page 112<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

as well as passenger, aircraft and vehicular flows. This responsibility includes<br />

coordination across different agencies and departments. The AOC should have<br />

overall responsibility of ensuring smooth functioning and availability of all PTB<br />

facilities and services.<br />

Functions that could be housed under the AOC include Resources Allocation, PA<br />

paging, FIDS update, CCTV monitoring and control, and all access control and<br />

security monitoring, control, and dispatch. The AOC should include or be adjacent<br />

to an Emergency Operations Center (EOC), which should be staffed on as<br />

as-needed basis to allow decision makers to respond to emergencies affecting the<br />

<strong>Terminal</strong> in specific or the Airport campus in general.<br />

There are a number of operational concepts for a typical AOC that assist in refining<br />

systems that are overseen from this location and the type of personnel that are<br />

utilized for staffing positions. These concepts have been taken into consideration<br />

for the general layout of the operations center:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

The AOC should require feeds from all major systems. Particularly in the<br />

event of emergency or incident, the adjacent EOC should rely on the AOC to<br />

be the central receiving, processing and dissemination point for all Airport-<br />

Wide related information.<br />

The AOC require feeds from all security and life safety systems. The AOC<br />

should be responsible for dispatch of personnel for all security related alarms<br />

and issues.<br />

Airport-Wide passenger/customer service-related calls should be maintained<br />

by current operations located elsewhere on the site.<br />

DRAFT<br />

The AOC should not be utilized for fixing or servicing field equipment. Airport<br />

janitorial functions should not be managed out of the AOC. Likewise, all<br />

tenant operations is considered an administrative function and as such be<br />

managed elsewhere.<br />

The AOC should assist with fielding emergencies and directing overall<br />

security and emergency response teams.<br />

The Air Traffic Control Tower should maintain responsibility for all functions<br />

pertaining to the runways and taxiways; therefore, the AOC should not<br />

require positions for areas such as Airfield Lighting, Runway and Taxiway<br />

inspections, etc.<br />

All rescue efforts should be managed by the Airport Fire & Rescue<br />

department and should not require a standalone position within the AOC.<br />

In the event of emergencies, existing staff within the AOC may have<br />

emergency response duties but should utilize their existing<br />

consoles/workstations.<br />

The programmatic detail of each of these key operation centers such as key<br />

function, headcount, and schematic layout should be developed during<br />

design phases.<br />

Landrum & Brown Page 113<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Potential functions of the AOC include:<br />

PTB Security:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

­ Responsible for monitoring PTB security systems including Access Control<br />

and Video Surveillance<br />

Airport Security:<br />

­ Responsible for monitoring Airport-wide, Roadways, Tenant and perimeter<br />

security.<br />

Life Safety:<br />

­ Responsible for monitoring Fire Alarm and Life Safety Systems<br />

Special Security:<br />

­ Responsible for coordination and arrangement of VIP and special events<br />

security<br />

Flight Operations:<br />

­ Flight Data Operations: Responsible for flight data handling on the<br />

operational day.<br />

­ Flight Data Monitoring: Responsible for monitoring flight data and<br />

operation systems.<br />

Resources Management:<br />

Stands Allocation: Responsible for aircraft stands allocation and adjustments.<br />

Gates & Check-in Allocation: Responsible for gates and check-in allocation<br />

and adjustments.<br />

Baggage Belts Allocation: Responsible for allocating flights to Inbound and<br />

outbound baggage chutes/reclaim belts.<br />

Performance Management:<br />

­ <strong>Terminal</strong> Operations: Responsible for managing and coordinating terminal<br />

operations.<br />

­ Minimum Connection Time and Online Performance: Responsible for<br />

maintaining operation performance and minimizing disruption to<br />

schedules.<br />

<strong>Planning</strong>:<br />

­ Allocation <strong>Planning</strong>: Manages resources planning and leveling<br />

­ Capacity <strong>Planning</strong>: Manages capacity planning and simulation<br />

­ Statistical Analysis: Manages historical data, trends and analysis<br />

Call Center:<br />

DRAFT<br />

­ Telecommunications: Responsible for handling normal and emergency<br />

voice and data communications with the public, staff, and systems.<br />

­ Public Announcement: Responsible for handling all flight and courtesy<br />

announcements.<br />

Landrum & Brown Page 114<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

Airport-wide Operations<br />

Landside/Airside Operations<br />

­ Landside: Responsible for handling landside and Construction coordination<br />

operations<br />

­ Airside: Responsible for handling Airside and NOTAMS Operations<br />

3.4.10.3 Emergency Operations Center<br />

The EOC should support the incident management team responsible for handling a<br />

crisis or emergency in PTB or at the airport at large. The EOC should include the<br />

following functions:<br />

<br />

<br />

<br />

<br />

Main Crisis Management Room for the Incident Management Team who is<br />

responsible for managing the crisis and coordinating activities among the<br />

various operation sections.<br />

Break out room for small group meetings, caucusing<br />

Policy Room for executive level and VIP decision meetings.<br />

Technical Resource for preparing and managing the EOC facility and<br />

controlling technical communication and Audio-visual equipment during<br />

crises.<br />

3.5 Utilities, Infrastructure and MEP Requirements<br />

3.5.1 PROJECTED NEW TERMINAL UTILITY REQUIREMENTS:<br />

Peak estimated demands of Mechanical Electrical & Plumbing (MEP) systems are<br />

listed below for the New <strong>Terminal</strong>. Exception, <strong>Terminal</strong> C peak cooling will be<br />

added to the Central Plant capacity. Refer to Appendix X for new <strong>Terminal</strong> Utilities<br />

demands estimate calculations.<br />

<br />

Peak Cooling:<br />

DRAFT<br />

o New <strong>Terminal</strong> 3,293 Tons<br />

o Existing <strong>Terminal</strong> B 1,500 Tons<br />

(Initially <strong>Terminal</strong> B will be served until such time as it is demolished.)<br />

o Existing <strong>Terminal</strong> C 1,500 Tons<br />

Subtotal<br />

6,293 Tons<br />

Peak Heating:<br />

o New <strong>Terminal</strong> 32,050 mbh<br />

o <strong>Terminal</strong> C NA (Use existing Boilers in Term C)<br />

Domestic Water: 500 gpm<br />

Fire Protection: 2,000 gpm<br />

Domestic Hot Water: 150 gpm<br />

Landrum & Brown Page 115<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Sanitary Sewer: 1,840 Sewer Fixture Units<br />

Peak Natural Gas: 109,840 CFH<br />

Roof Storm Water: 16,360 gpm<br />

Electrical Connected Load: 21.5MW<br />

Exhibit M-8, New <strong>Terminal</strong> Estimated Peak Utilities Demand in Appendix X, outlines<br />

the peak demand of the building utilities and the equipment and piping required to<br />

serve the needs.<br />

3.5.2 NEW TERMINAL MECHANICAL AND ELECTRICAL SYSTEM<br />

DESCRIPTIONS<br />

3.5.2.1 Heating Equipment<br />

KCI has an existing Central Utility Plant (CUP) in a building with the airport Data<br />

Center and Police Facility. The site layout is shown in Exhibit M-1, Existing<br />

Conditions (in Appendix X). The CUP used to include steam boilers, distributing<br />

steam to hot water heat exchangers located in <strong>Terminal</strong>s A, B, and C. Due to high<br />

operating and maintenance costs the steam boilers were removed from the CUP<br />

and hot water boilers were installed in each terminal building. KCI’s preference is<br />

to maintain this approach with the New <strong>Terminal</strong>, i.e., provide mechanical space in<br />

the New <strong>Terminal</strong> to install hot water heating equipment.<br />

3.5.2.2 COOLING EQUIPMENT<br />

The existing CUP is located landside, adjacent to airport surface parking, and near<br />

the ATCT. It includes three York Millennium centrifugal chillers rated at 1,500 tons<br />

apiece. An induced draft cooling tower is located to the east of the CUP, and chilled<br />

water distribution piping runs from the CUP to <strong>Terminal</strong>s A, B, and C.<br />

See Exhibit M-9, CUP Enlarged Plan – Existing Chiller Plant in Appendix X, for<br />

existing equipment layout and Exhibit M-2, <strong>Terminal</strong> B and C Chilled Water<br />

Distribution Phasing Plan in Appendix X, for routing of piping during construction of<br />

New <strong>Terminal</strong>. KCI used a trenchless, underground pipe lining (In-situ Pipe Repair)<br />

method to rehabilitate the below grade segments of the distribution piping when<br />

leaks developed. For future buried chilled water distribution piping, a utility tunnel<br />

or a prefabricated, pre-insulated piping system should be included if leaks develop.<br />

3.5.2.3 Mechanical Plant<br />

DRAFT<br />

The Mechanical Equipment serving the New <strong>Terminal</strong> will consist of a Boiler Plant<br />

located in the New <strong>Terminal</strong> and a Chilled Water Plant located in the existing CUP or<br />

a new CUP. The existing boiler plant, in <strong>Terminal</strong> C, will be maintained.<br />

Landrum & Brown Page 116<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.5.2.4 HVAC Systems<br />

Table 3.5-1, New <strong>Terminal</strong> HVAC Requirements, shows the HVAC loads (space<br />

cooling and heating) that are estimated for the New <strong>Terminal</strong> based on a break out<br />

of terminal square footage per function.<br />

Table 3.5-1<br />

NEW TERMINAL HVAC REQUIREMENTS<br />

Area Schedule Area Airflow Supply Total Heating Total<br />

Per<br />

area Airflow<br />

Clg<br />

Load Per Area<br />

Htg<br />

Load<br />

‘by function<br />

SF<br />

cfm/S<br />

F cfm mbh Btuh/SF mbh<br />

Aircraft Gates 85,772 1.0 85,770 3,512 35 3,000<br />

Airline Clubs 4,251 1.0 4,250 174 35 150<br />

Airline Operations 95,922 1.0 95,920 3,928 35 3,360<br />

Airline Ticket Office 9,886 1.0 9,890 405 35 350<br />

Baggage Handling 96,957 0.53 51,720 2,729 19.7 1,810<br />

Circulation 242,871 1.00 242,870 9,946 35 8,500<br />

Concession Support 17,987 1.00 1,7990 737 35 630<br />

Domestic Baggage<br />

Claim 59,280 1.0 59,280 2,428 35 2,070<br />

Domestic Ticket<br />

Counter 17,676 1.0 17,680 724 35 620<br />

International<br />

Ticketing 2,867 1.0 2,870 118 35 100<br />

Miscellaneous<br />

Tenants 5,883 1.0 5,880 241 35 200<br />

Non-Airline Tenants 11,699 1.0 11,700 479 35 410<br />

Other Space 57,986 1.0 57,990 2,375 35 2,030<br />

Public Restrooms 18,154 1.0 18,160 1,414 35 630<br />

Retail 85,280 1.0 85,280 3,492 35 2,990<br />

Security 40,483 1.0 40,480 1,658 35 1,420<br />

<strong>Terminal</strong> Function 129,324 0.58 74,910 3,802 20.3 2,620<br />

US Customs 33,182 1.0 33,180 1,359 35 1,160<br />

<strong>Terminal</strong> C 300,000 NA NA 12,000 NA NA<br />

New Term Sub-<br />

Total<br />

DRAFT<br />

1,015,46<br />

0<br />

Term C Sub-Total 462,500 18,000<br />

New + Term C Total<br />

1,477,96<br />

0 57,518<br />

4,793<br />

Tons<br />

915,82<br />

0 39,518 32,050<br />

Source:<br />

HNTB Corporation Analysis based on ASHRAE Pocket Guide for Air-Conditioning, Heating, Ventilation<br />

and Refrigeration, 7 th Ed.<br />

Landrum & Brown Page 117<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Existing <strong>Terminal</strong> A, B, and C HVAC Systems<br />

<strong>Terminal</strong>s A, B, and C are currently served by a mix of HVAC systems including<br />

some dual duct, multi-zone, and single duct Variable Air Volume (VAV) air<br />

distribution systems. Air Handling Units (AHUs) are located in Mechanical Rooms<br />

that are spaced throughout the all three terminals. Perimeter spaces are<br />

conditioned by forced air type systems and perimeter finned tube radiation.<br />

All restroom spaces are exhausted.<br />

The Chiller Plant is not run year round and chilled water is not available to provide<br />

cooling for computer equipment. Separate Direct Expansion (DX) Air Conditioning<br />

split systems cool these spaces.<br />

Bag makeup and tug area and truck receiving dock areas are exhausted with a<br />

ducted system. Hot water (HW) unit heaters provide heating. Concession Food<br />

Prep areas are limited in <strong>Terminal</strong>s A, B, and C.<br />

3.5.2.5 Aircraft Specialty Equipment<br />

Currently <strong>Terminal</strong>s A, B, and C use point-of-use preconditioned air and 400 hertz<br />

motor generator units at each gate. These systems are preferred by KCI and the<br />

Airlines. If a single unit fails it does not impact the rest of the gates. Point of Use<br />

(POU) technology also makes it easier to assign costs given that each loading<br />

bridge is self-sufficient. Ground Support Equipment (GSE) Quick Charging Stations<br />

are not used.<br />

3.5.2.6 Plumbing Items<br />

DRAFT<br />

Water Service is currently provided to <strong>Terminal</strong>s A, B, and C from a KCMO Water<br />

Service 12-inch diameter water main located landside. Water enters the buildings<br />

in the mechanical rooms through a backflow preventer and a pipe splits it into cold<br />

water (CW) and HW mains. The HW main is heated by the HW boilers (described<br />

previously). Water softeners for the HW system are provided in the boiler room.<br />

The three existing terminals are protected with a fire sprinkler system and<br />

standpipes per National Fire Prevention Administration (NFPA) 13, Installation of<br />

Sprinkler Systems. Only one airside fire hydrant exists near the terminals and is<br />

located near on the southeast side of <strong>Terminal</strong> C. See Exhibit FP-1, Fire Protection<br />

Existing Conditions (in Appendix X). <strong>Terminal</strong> sanitary sewers drain by gravity to<br />

the sewer mains. Individual grease traps are used in food preparation areas for<br />

grease waste from the concessions, where needed.<br />

Natural Gas serves the HW boilers, domestic hot water boilers, and concessions in<br />

each terminal. The gas is piped to the Boiler Room from a 10-inch diameter main<br />

from Missouri Gas & Energy. The gas pressure in the main is 25 pound-force per<br />

square inch psig.<br />

Landrum & Brown Page 118<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Roof drains and emergency overflow roof drains are spaced as needed on the<br />

terminal roofs for stormwater. Stormwater leaders are sized per the plumbing code<br />

and run down the interior of a building to the stormwater system.<br />

3.5.2.7 Electrical Items<br />

A total connected load of 15.76MW will be required to service the New 1.015M SF<br />

<strong>Terminal</strong> based on a break out of the New <strong>Terminal</strong> square footage per function as<br />

shown in Table 3.5-2, New <strong>Terminal</strong> Power Requirements.<br />

Table 3.5-2<br />

NEW TERMINAL POWER REQUIREMENTS<br />

Area<br />

Schedule<br />

SF<br />

Lighting<br />

W/SF<br />

Power<br />

W/SF<br />

HVAC<br />

W/SF<br />

IT/COMM<br />

W/SF<br />

Security<br />

W/SF<br />

Total<br />

Aircraft Gates 85,772 3.50 4.00 6.50 4.00 4.00 1,886,984.00<br />

Airline Clubs 4,251 2.00 1.00 6.50 1.00 2.00 53,137.50<br />

Airline<br />

Operations<br />

Airline Ticket<br />

Office<br />

Baggage<br />

Handling<br />

95,922 3.50 1.00 6.50 2.00 2.00 1,438,830.00<br />

9,886 3.50 1.00 6.50 2.00 2.00 148,290.00<br />

96,957 2.00 8.00 6.50 1.00 2.00 1,890,661.50<br />

Circulation 242,871 1.00 0.50 6.50 0.25 0.50 2,125,121.25<br />

Concession<br />

Support<br />

Domestic<br />

Baggage<br />

Claim<br />

Domestic<br />

Ticket<br />

Counter<br />

International<br />

Ticketing<br />

Miscellaneous<br />

Tenants<br />

Non-Airline<br />

Tenants<br />

17,987 1.00 1.00 6.50 1.00 0.50 179,870.00<br />

59,280 3.00 8.00 6.50 1.00 1.00 1,155,960.00<br />

17,676 3.50 1.00 6.50 2.00 1.00 247,464.00<br />

2,867 3.50 1.00 6.50 2.00 1.00 40,138.00<br />

5,883 3.50 1.00 6.50 2.00 1.00 82,362.00<br />

11,699 3.50 1.00 6.50 2.00 1.00 163,786.00<br />

Other Space 57,986 3.50 1.00 6.50 1.00 1.00 753,818.00<br />

Public<br />

Restrooms<br />

18,154 2.00 0.50 6.50 0.25 0.50 177,001.50<br />

Retail 85,280 3.00 1.00 6.50 2.00 1.00 1,151,280.00<br />

Security 40,483 3.50 4.00 6.50 4.00 4.00 890,626.00<br />

<strong>Terminal</strong><br />

Function<br />

DRAFT<br />

129,324 2.00 8.00 6.50 2.00 2.00 2,651,142.00<br />

US Customs 33,182 3.50 4.00 6.50 4.00 4.00 730,004.00<br />

<strong>Terminal</strong><br />

Sub-Total 1,015,460 15,766,475.75<br />

Source:<br />

HNTB Corporation Analysis based on 2012 RS MEANS DIVISION 26 and historical data.<br />

Landrum & Brown Page 119<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Per KCP&L meter readings, the existing Peak kW demand between the months of<br />

June and August 2012, for the three terminals are:<br />

<br />

<br />

<br />

<strong>Terminal</strong> A - 1240.2kW<br />

<strong>Terminal</strong> B - 2138.9kW<br />

<strong>Terminal</strong> C - 1359kW<br />

The 2138.9kW peak at <strong>Terminal</strong> B is due to higher levels of passenger traffic at<br />

<strong>Terminal</strong> B. However, it is assumed that during construction, once <strong>Terminal</strong> A has<br />

been demolished and the passenger traffic has been diverted to <strong>Terminal</strong>s C and B,<br />

both terminals will see an increase in load. See below for estimated loads on<br />

<strong>Terminal</strong>s B and C during construction, assuming an even distribution of passenger<br />

traffic: <strong>Terminal</strong> B, 2400kW and <strong>Terminal</strong> C, 2400kW.<br />

3.5.2.8 Gate Power Requirements<br />

Using a function per gate approach to calculate the load at the gates, a total<br />

connected load of 8.4MW will be required to service the proposed 41 gates. Power<br />

to these gates will be fed via adjacent gate sub-electrical rooms. This calculation<br />

includes Rapid Recharge Stations at 75 percent of the gates, as well as point of use<br />

400Hz service and pre-conditioned air, as shown on Table 3.5-3, Gate<br />

Requirements.<br />

Table 3.5-3<br />

GATE REQUIREMENTS<br />

Gate Requirements<br />

DRAFT<br />

Watts per Gate<br />

400Hz Power 100,000<br />

AHU 50,000<br />

Rapid Recharge 40,000<br />

Lighting 10,000<br />

PWC 5,000<br />

41 Gates Sub-Total 8,405,000<br />

Source:<br />

HNTB Corporation<br />

Despite the fact that only 37 gates will be installed under the Phase 1 build out of<br />

<strong>Terminal</strong> A, the infrastructure for the additional four gates will need to be<br />

considered in the planning process.<br />

3.5.2.9 CUP Power Requirements<br />

In addition to providing Chilled Water to the existing terminals, the existing CUP is<br />

currently the KCP&L central hub for electrical distribution to the existing terminals<br />

and ancillary buildings, including the Airfield Lighting Vault, ATCT, and Data Center.<br />

This type of consolidated power distribution leaves the Airport vulnerable to<br />

Landrum & Brown Page 120<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

campus-wide outages due to a single point of failure. In addition, demolition and<br />

relocation of the existing CUP would require a cut-over of electrical power for the<br />

entire Airport.<br />

The Base Case approach to the New <strong>Terminal</strong> allows the existing CUP to remain in<br />

place and provides for two new feeders from KCP&L directly to a distribution point<br />

within the New <strong>Terminal</strong>, bypassing the existing CUP. The Preferred Alternative,<br />

discussed later in the PCD, will require the relocation of the existing CUP but<br />

isolates the new Data Center and COP shop on independent feeders.<br />

Despite the independent feeders to the New <strong>Terminal</strong> and the Data Center, this is<br />

not a redundant installation since, for all scenarios power comes from an existing<br />

KCP&L Substation – KCI. In order to provide a truly redundant power system,<br />

additional feeders would have to be picked up from one of the other two adjacent<br />

KCP&L substations: Tiffany Springs Substation and Overhaul Base Substation.<br />

This is discussed later in this document.<br />

The new CUP, providing chilled water only to the terminals and ancillary buildings<br />

will require a total connected load of 5.5MW, and the renovated CUP will require a<br />

total connected load of 3.6MW as shown in Table 3.5-4, CUP Requirements.<br />

Table 3.5-4<br />

CUP REQUIREMENTS<br />

New CUP<br />

Qty.<br />

Unit<br />

Amps Volts Unit Watts<br />

Total<br />

Watts<br />

1500Ton Chillers 3.00 176.95 4160.00 1275000.00 3825000.00<br />

DRAFT<br />

150HP Primary Pumps 3.00 180.00 480.00 149649.19 448947.57<br />

150HP Secondary Pumps 3.00 180.00 480.00 149649.19 448947.57<br />

1500Ton Cooling Towers 3.00 20.82 4160.00 150000.00 450000.00<br />

100HP Condenser Water Pumps 3.00 125.00 480.00 103923.05 311769.15<br />

Power 24000.00 2.50 60000.00<br />

Lighting 24000.00 1.50 36000.00<br />

IT/Security/COMM 24000.00 0.50 12000.00<br />

Total CUP Mechanical<br />

Load 5,592,664<br />

CUP Renovation Qty. Unit A V Unit W Total W<br />

1500Ton Chillers 2.00 176.95 4160.00 1275000.00 2550000.00<br />

150HP Primary Pumps 2.00 180.00 480.00 149649.19 299298.38<br />

150HP Secondary Pumps 2.00 180.00 480.00 149649.19 299298.38<br />

1500Ton Cooling Towers 2.00 20.82 4160.00 150000.00 300000.00<br />

100HP Condenser Water Pumps 2.00 125.00 480.00 103923.05 207846.10<br />

Total CUP Mechanical<br />

Load 3,656,443<br />

Source:<br />

HNTB Corporation<br />

Landrum & Brown Page 121<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.5.2.10 Total Power Requirements<br />

The total connected power at the New <strong>Terminal</strong> including gates and a new CUP will<br />

be 29.6MW. The total connected power at the New <strong>Terminal</strong> including gates and a<br />

renovated CUP will be 27.7MW. With a demand of 40 percent on the terminal<br />

based on historical comparisons, the New <strong>Terminal</strong> and gates will have a total<br />

demand load of 11.84MW, and the new CUP, 2.5MW.<br />

3.5.2.11 Emergency and Stand-by Power Requirements<br />

Basic code required Emergency Egress and Fire Life Safety requirements include:<br />

smoke control, elevator return, egress lighting requirements, and terminal<br />

evacuation to dedicated evacuation sites. This can be facilitated by local individual<br />

battery units, at each light fixture and smoke control unit, or as central power unit<br />

that can consist of emergency generators or battery backed-up UPS systems.<br />

Additional stand-by, non-code required back-up power can be provided for freeze<br />

protection, additional elevator functionality, additional lighting, emergency powered<br />

gate systems that allow for the controlled egress from aircraft at designated gates,<br />

and other systems that allow for a more coordinated, public friendly terminal<br />

evacuation.<br />

3.5.2.12 Fire Alarm System Requirements<br />

A new fully addressable Fire Alarm System will need to be incorporated into the<br />

New <strong>Terminal</strong>. This system will have to be tied back into a main Fire Alarm control<br />

panel room, in accordance with the local Fire Department, within the <strong>Terminal</strong> as<br />

well as back to the main emergency response center at the Airport Rescue and<br />

Firefighting facility (ARFF) and/or Police shop. These new systems will have to be<br />

capable of interfacing with the existing Fire Alarm systems within existing <strong>Terminal</strong>s<br />

B and C, as well as other existing ancillary buildings to remain. Additional<br />

migrating hardware and or software may be required in order to fully integrate the<br />

different systems.<br />

DRAFT<br />

3.5.2.13 Fire Alarm System Requirements<br />

A new fully addressable Fire Alarm System will need to be incorporated into the<br />

New <strong>Terminal</strong>. This system will have to be tied back into a main Fire Alarm control<br />

panel room, in accordance with the local Fire Department, within the <strong>Terminal</strong> as<br />

well as back to the main emergency response center at the Airport Rescue and<br />

Firefighting facility (ARFF) and/or Police shop. These new systems will have to be<br />

capable of interfacing with the existing Fire Alarm systems within existing <strong>Terminal</strong>s<br />

B and C, as well as other existing ancillary buildings to remain. Additional<br />

migrating hardware and or software may be required in order to fully integrate the<br />

different systems.<br />

Landrum & Brown Page 122<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3.5.2.14 IT Requirements<br />

A portion of the existing Fiber Optic Loop System will have to be re-routed in order<br />

to maintain the double ended feed to existing <strong>Terminal</strong>s B and C through the ACC in<br />

the existing CUP, during the demolition and construction of <strong>Terminal</strong> A. In addition,<br />

final connections will have to be made from the Central Communications Hub, the<br />

<strong>Terminal</strong>, and the existing Fiber Optic Loop system. These cut-overs will have to be<br />

strategically coordinated in order to avoid shutdowns of any secure or mission<br />

critical systems.<br />

The Fiber Optic Loop System will need to be extended into the New <strong>Terminal</strong><br />

through a Main Point of Entrance (MPOE) room or Main Distribution Frame (MDF)<br />

Room. The MPOE/MDF room will also be a central connection point for all telephone<br />

and cable TV connections, including Fiber Optic Converters, Cisco type routers and<br />

switches, centralized telephone and Fire Alarm interface for the PA system, head<br />

units for Electronic Visual Information Display System (eVIDS), Common Use<br />

<strong>Terminal</strong>s, as well as Automated Critical Asset Management System (ACAMS) and<br />

Closed Circuit TV (CCTV).<br />

Intermediate Distribution Frame (IDF) rooms will be required on the apron level to<br />

house routers for connections to local airline Gate Information Display System<br />

(GIDS); connections to airline and passenger WIFI routers; local eVIDS systems;<br />

amplifiers, noise sensors and network switches for local Public Address (PA)<br />

systems; ACAMS security panels for local doors; CCTV network hubs for signal<br />

consolidation and local viewing if required by individual airlines; local Fire Alarm<br />

sub-panels and UPS units to maintain system power during brown outs or during<br />

generator start-up. In addition each IDF and MPOE/MDF will be required to have a<br />

dedicated UPS powered air-conditioning unit separate from the <strong>Terminal</strong> cooling<br />

system.<br />

DRAFT<br />

The existing Data Center and the Airport Communications Center (ACC) in the<br />

existing CUP were renovated in 2011. Although both of these centers are in likenew<br />

condition with upgraded IT systems, modifications will have to be made in<br />

order to support the New <strong>Terminal</strong>.<br />

Landrum & Brown Page 123<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4. LANDSIDE REQUIREMENTS<br />

The 2008 MP identified a new terminal south of Runway 9/27, and a new terminal<br />

curb-front and loop roadway system. The new roadway system was to consist of a<br />

new south access roadway from Missouri Route 152 (M-152), and an upgrade of<br />

I-435 and I-29 ramps connecting to M-152. These changes would affect regional<br />

transportation patterns, which are traditionally considered within a 20-year time<br />

frame. Because new airport access would have a permanent impact on regional<br />

transportation in the Northland as well as the entire metropolitan area, a Regional<br />

Travel <strong>Study</strong> was conducted as an early part of the <strong>Advance</strong> <strong>Terminal</strong> <strong>Planning</strong><br />

<strong>Study</strong> in order to provide an evaluation of providing access to a new airport<br />

terminal on M-152 instead of the existing Cookingham Drive access. Following a<br />

capital cost assessment of a new terminal south of Runway 9/27, it was determined<br />

that this southern terminal was beyond the financial affordability threshold so more<br />

economical sites near the existing terminals were subsequently explored.<br />

The requirements in this section focus on the new terminal in the selected<br />

<strong>Terminal</strong> A site.<br />

DRAFT<br />

Landrum & Brown Page 124<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4.1 Regional Access<br />

KCI is located directly adjacent to the regional highways I-29 and I-435, and<br />

approximately 15 miles northwest of downtown Kansas City, located in Platte<br />

County. Figure 4.1-1, Regional <strong>Study</strong> Area, shows the location of the Airport<br />

from a regional perspective.<br />

Figure 4.1-1<br />

REGIONAL STUDY AREA<br />

DRAFT<br />

Source:<br />

HNTB Corporation<br />

Landrum & Brown Page 125<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

As shown in Figure 4.1-2, Airport Access, the Airport is surrounded by I-435 on<br />

the west, I-29/US 71 on the north and east, and M-152 on the south. Both local<br />

service interchanges and regional system interchanges are shown with a blue dot.<br />

It is assumed that since the new terminal will be located in the existing <strong>Terminal</strong> A<br />

site, access would remain from the existing Cookingham interchange. Analysis took<br />

into account the 2020 and 2040 future land development as presented in the<br />

Mid-America Regional Council (MARC) regional Long-Range Transportation Plan.<br />

Figure 4.1-2<br />

AIRPORT ACCESS<br />

DRAFT<br />

Source:<br />

HNTB Corporation<br />

Landrum & Brown Page 126<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4.1.1 AIRPORT TRAVEL MARKET<br />

Understanding where airport users (passengers and employees) are traveling to<br />

and from in the Kansas City metropolitan area helps to identify target any issues<br />

with the regional network and necessary transportation improvements. The MARC<br />

regional travel demand model was used to analyze existing and future travel<br />

markets to and from KCI (as shaded in Figure 4.1-2) for trips originating or<br />

terminating in the metropolitan area. The regional travel market assessment used<br />

a six step process, as listed below.<br />

1. Airport zone land use assumptions were reviewed.<br />

2. Regional model traffic analysis zones (TAZs), or travel markets, were<br />

aggregated into super TAZs, as shown in Figure 4.1-3, Travel Demand<br />

Model Traffic Analysis Zones (TAZs).<br />

3. Auto and transit trip origins and destinations were reviewed between travel<br />

markets.<br />

4. Vehicle trips were analyzed for Existing (2010) conditions based on MARC’s<br />

travel demand model.<br />

5. Vehicle trips were analyzed for the MP (2020 and 2040). KCI vehicle trips<br />

were coded in the MARC model as special generator trips. The MARC travel<br />

demand model typically utilizes a gravity model which gives priority to trips<br />

that are close in proximity to other zones. However, special generators, such<br />

as the Airport, assign vehicle trips based on other factors such as household<br />

income. The KCI passenger trips were not assigned based on any passenger<br />

surveys performed at the airport.<br />

DRAFT<br />

6. The Airport Passenger Survey data was used to compare to the regional<br />

model.<br />

Landrum & Brown Page 127<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 4.1-3<br />

TRAVEL DEMAND MODEL TRAFFIC ANALYSIS ZONES (TAZS)<br />

DRAFT<br />

Source:<br />

MARC Regional Model<br />

Landrum & Brown Page 128<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4.1.2 TRAVEL MARKET PASSENGER SURVEY<br />

In March 2012 a KCI passenger intercept survey was conducted in the gate<br />

holdrooms prior to flight departure. Twenty-one hundred surveys were properly<br />

completed and data summarized for use in this analysis.. Details and conclusions<br />

of the Passenger Survey are discussed in Section 1.2, Passenger Surveys, of this<br />

document. The passenger survey results regarding travel mode choice and regional<br />

access are presented in Table 4.1-1, Passenger Survey Mode Choice and<br />

Regional Access. These survey results only include airport passengers and do not<br />

represent airport employees.<br />

Table 4.1-1<br />

PASSENGER SURVEY MODE CHOICE AND REGIONAL ACCESS<br />

KCI Passenger Survey Response<br />

62 percent are local metro area residents<br />

38 percent are visitors<br />

85 percent come in a privately-owned car.<br />

85 percent come in a privately-owned car<br />

and 67 percent park at the airport<br />

Most passengers use I-29 and I-435 to<br />

access the Airport<br />

Privately-owned cars (68 percent) and<br />

rental cars (18 percent) are the primary<br />

modes of transportation<br />

Passenger travel times<br />

Effect on Regional Travel<br />

Visitors are more likely to arrive at the<br />

Airport via a mode different than a<br />

privately-owned vehicle such as rental car,<br />

transit, or drop-off.<br />

This could be a privately-owned car or rental<br />

car. This increases the number of trips<br />

attracted to the airport.<br />

The difference represents the curbside<br />

drop-offs.<br />

This does not include other users such as<br />

employees.<br />

Transit was not included in the mode share<br />

data. There is currently transit service to<br />

<strong>Terminal</strong> C.<br />

DRAFT<br />

Some peak airport times are off-peak of<br />

background regional roadway traffic.<br />

A detailed regional traffic study looks at the<br />

peak of the total regional roadway traffic<br />

which includes the background traffic and<br />

airport traffic.<br />

Source:<br />

Kansas City International Airport New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong>, Passenger Survey<br />

Landrum & Brown Page 129<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4.1.3 MARC MODEL ASSESSMENT<br />

To plan for the transportation infrastructure needs, it is important to understand<br />

the travel markets served by the Airport. These markets are served by a regional<br />

transportation network that serves both “trips to work” and passengers or airport<br />

travelers.<br />

KCI serves workers and passengers from all over the metropolitan area and outside<br />

the metropolitan area. Table 4.1-2, Summary of Total User Markets Served<br />

To and From the KCI Airport – By Zone, lists the local markets served in the<br />

metropolitan area both today and in the future based on MARC’s regional travel<br />

model. Figure 4.1-3 in Section 4.1.1 shows all the traffic analysis zones (TAZs).<br />

Table 4.1-2<br />

SUMMARY OF TOTAL USER MARKETS SERVED TO AND FROM THE KCI<br />

AIRPORT – BY ZONE<br />

Zone<br />

Description<br />

2010 2020 2040<br />

A Local KCI Area 11% 10% 8%<br />

B North I-29 6% 10% 16%<br />

C North I-435 10% 8% 6%<br />

D South I-435 From Northwest 3% 3% 2%<br />

E South I-435 From I-70 1% 1% 1%<br />

F South I-435 From Southwest 13% 13% 13%<br />

DRAFT<br />

G South I-29 From I-635 4% 4% 3%<br />

H South I-29 13% 12% 10%<br />

I South I-29 From I-70 9% 8% 7%<br />

J South I-29 From Southeast 8% 7% 7%<br />

K East M-152 From Northeast 22% 24% 27%<br />

Total 100% 100% 100%<br />

Note:<br />

Source:<br />

Largest travel markets by zone are shaded.<br />

MARC Regional Model<br />

Landrum & Brown Page 130<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

As shown in Table 4.1-3, the largest travel markets by zone today and in the future<br />

are zones F, H, and K, respectively. These markets provide the largest interaction<br />

with the Airport because of proximity and number of trips to and from the Airport.<br />

Table 4.1-3, Summary of Total User Markets Served To and From KCI – By<br />

District, shows the markets served in the metropolitan area both today and in the<br />

future based on MARC’s regional travel model by aggregated district. Figure 4.1-6<br />

in Section 4.1.1 shows the zones. Today, an estimated 16 percent of the total<br />

vehicle trips (passengers and employees) to and from the Airport are from the<br />

North, 21 percent are from the Southwest (Kansas), and 63 percent are from the<br />

southeast (Missouri).<br />

Table 4.1-3<br />

SUMMARY OF TOTAL USER MARKETS SERVED TO AND FROM KCI - BY<br />

DISTRICT<br />

District<br />

North<br />

S.W.<br />

S.E.<br />

Note:<br />

Source:<br />

1<br />

Description<br />

North of KCI<br />

(Missouri)<br />

Johnson and<br />

Wyandotte Counties<br />

(Kansas)<br />

2010 2020 2040<br />

Passengers<br />

Only<br />

Existing<br />

Total 1<br />

3% 16% 18% 22%<br />

35% 21% 20% 19%<br />

Jackson, Clay,<br />

Platte and Cass<br />

south and east of<br />

62% 63% 62% 59%<br />

KCI. (Missouri)<br />

Total 100% 100% 100% 100%<br />

DRAFT<br />

Passengers and employees<br />

MARC Regional Model<br />

Previous data has indicated a travel market share to and from the Airport as much<br />

as 45 percent from Johnson County. However, this number was based on a license<br />

plate survey of the long-term parking lot and does not reflect all trips to the Airport<br />

including transit trips, drop-offs, and employees.<br />

Historically, one to three percent of the region’s travel trips to and from KCI are by<br />

Kansas City Area Transportation Authority (KCATA) transit bus service. This<br />

percentage is higher if other high-occupant modes, such as shared-ride vans, are<br />

included. KCATA currently operates the 129 and 129X routes to the Airport which<br />

carry 543 people per day on over 21 round trips as shown in Figure 4.1-4, KCI<br />

Transit Service.<br />

Landrum & Brown Page 131<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 4.1-3<br />

KCI TRANSIT SERVICE<br />

DRAFT<br />

Source:<br />

KCATA<br />

Landrum & Brown Page 132<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The MARC regional model was used to determine what roadways KCI users take to<br />

and from the Airport today and in the future. Figure 4.1-5, Existing (2010)<br />

Daily Travel Patterns To/From KCI – Example, shows what routes KCI users<br />

travel today. Figures future travel patterns are provided in the <strong>Terminal</strong> Area<br />

Master Plan.<br />

Figure 4.1-5<br />

EXISTING (2010) DAILY TRAVEL PATTERNS TO/FROM KCI – EXAMPLE<br />

DRAFT<br />

Source:<br />

MARC Regional Model<br />

Landrum & Brown Page 133<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The Existing and Future Access average daily traffic (ADT) volumes, as reported by<br />

MoDOT in 2010 and projected for 20040 by MARC are shown in Figure 4.1-6,<br />

Existing and Future Two-Way Daily Traffic Volumes. Traffic volumes are<br />

depicted are the total for both directions.<br />

Figure 4.1-6<br />

EXISTING AND FUTURE TWO-WAY DAILY TRAFFIC VOLUMES<br />

DRAFT<br />

Source:<br />

MoDOT Count Map and MARC Regional Model<br />

Landrum & Brown Page 134<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4.1.4 REGIONAL ACCESS<br />

Table 4.1-4, Regional Transportation Airport Access Routes, summarizes the<br />

percentage of airport trips using the each access route in 2010 and 2040.<br />

Table 4.1-5, Future Regional Access Route Traffic Volumes shows the total<br />

volume of traffic along these routes in 2020 and 2040. The number of KCI trips<br />

increased 1.2 percent from 2010 to 2020 and 4.4 percent from 2010 to 2040.<br />

However, route distribution to and from KCI does not change significantly from<br />

existing access to future existing access conditions. Primarily due to increased<br />

development east and north of KCI and freeway congestion affecting route choice.<br />

Table 4.1-4<br />

REGIONAL TRANSPORTATION AIRPORT ACCESS ROUTES<br />

Roadway 2010 2040<br />

I-29 north of KCI 9% 11%<br />

I-29 south to/from KCMO 23% 16%<br />

I-635 south to/from Kansas 17% 14%<br />

I-435 south to/from Kansas 5% 7%<br />

I-435 east of KCI 19% 26%<br />

M-152 east of KCI 5% 8%<br />

all other routes 22% 18%<br />

Source:<br />

MARC Regional Model<br />

DRAFT<br />

Table 4.1-5<br />

FUTURE REGIONAL ACCESS ROUTE TRAFFIC VOLUMES<br />

Roadway 2020 2040<br />

I-29 north of I-435/I-29 Split 55,473 73,807<br />

I-29 south of M-152 96,110 121,751<br />

I-29 south of Cookingham 70,875 85,755<br />

I-435 east of I-29 30,849 43,712<br />

M-152 west of Hampton Rd. 17,094 28,057<br />

M-152 west of Congress Ave. 19,045 58,121<br />

M-152 connection to KCI N/A N/A<br />

I-435 south of I-29 (west of KCI) 8,284 12,884<br />

Note:<br />

Source:<br />

These values are directly from the MARC model and may not compare well to the adjusted<br />

volumes.<br />

HNTB Corporation<br />

Landrum & Brown Page 135<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Today, the Kansas City metropolitan area freeway network is relatively free of<br />

congestion with only 8.6 percent of the regional freeways and expressways<br />

currently operating above their capacity. However, by 2040 the region is expected<br />

to have 18.2 percent of its freeways and expressways operate over capacity, as<br />

shown in Table 4.1-6, Percent of Regional Freeway Congested.<br />

Table 4.1-6<br />

PERCENT OF REGIONAL FREEWAYS CONGESTED<br />

Scenario<br />

Percent Congested<br />

Freeways<br />

Existing Access (2010) 8.6%<br />

Existing Access (2040) 18.2%<br />

M-152 Access (2040) 18.2%<br />

Note:<br />

Source:<br />

Congested freeways are defined as interstates and state highways that have volume to<br />

capacity ratio greater than 1.0. The MARC 2040 Model includes all of the fiscally constrained<br />

Long-Range Transportation Plan Projects identified for the region.<br />

MARC Regional Model.<br />

In 2010, there were several existing freeway bottlenecks that played affected<br />

access to/from KCI. According to the MARC travel demand model, I-29, north of<br />

downtown, was one of the worst bottlenecks in the region (as shown in Appendix X,<br />

Figure X-6). However, this location was improved in 2011 when MoDOT widened<br />

the corridor from four lanes to six lanes, plus auxiliary lanes from the northeast<br />

corner of the downtown loop to the I-29/I-35 split. Other congested corridors<br />

according to the MARC travel demand model include:<br />

<br />

<br />

<br />

<br />

I-35 in Johnson County<br />

I-435 in southern Johnson and Jackson counties<br />

I-70 east of downtown Kansas City, Missouri<br />

US-71 south of downtown Kansas City, Missouri<br />

The corridors that are congested in 2010 also are congested in 2040 (as shown in<br />

Appendix X, Figure X-7). Additional bottlenecks that will cause airport travelers<br />

delays in 2040 include:<br />

<br />

<br />

<br />

U.S. 169 north of downtown<br />

I-29 north of the I-29 central business district<br />

I-635 over the Missouri River<br />

M-152 east of I-29<br />

DRAFT<br />

Table 4.1-7, Existing and Forecast Cookingham Drive Traffic Generation,<br />

shows existing and forecast passenger enplanements, average daily vehicle trips<br />

(ADT), and peak hour roadway capacity. In order to validate the model output<br />

showing adequate operations of Cookingham Drive in the future, a non-model<br />

technique was utilized. It was assumed that all of the daily traffic using<br />

Cookingham Drive today is tied to Airport demand. Therefore, the current ADT<br />

Landrum & Brown Page 136<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

divided by enplaned passengers was used as the existing and future traffic<br />

generation rate. Airport employee growth is also tied to passenger growth and the<br />

projected increase in passengers would account for the associated increase in<br />

employee trips along Cookingham Drive. To show the future ADT on Cookingham<br />

Drive in Table 4.1-7, a volume to capacity ratio was developed using the 2010 HCM<br />

threshold of 58,000 vehicles per day, which is projected to be 0.75 in 2030.<br />

This means that through the design year, the two lane ramps to and from I-29 are<br />

expected to be sufficient to meet the traffic demand. However, as peak hour<br />

volume to capacity increase approaches 0.85, planning for transportation<br />

enhancements to accommodate increased demand should be considered.<br />

Table 4.1-7<br />

EXISTING AND FORECAST COOKINGHAM DRIVE TRAFFIC GENERATION<br />

Time<br />

Frame<br />

Daily<br />

Passenger<br />

Enplanemets<br />

ADT<br />

Daily<br />

Trips/Passenger<br />

Enplanement<br />

Peak Hour<br />

Volume/Capacity<br />

Existing 17,100 30,709 1.80 0.53<br />

Future<br />

(2030)<br />

24,100 43,380 1.80 0.75<br />

Note: Existing ADT, directional split and PHF from KCMO 2011/12 count. Capacity based on 2010<br />

LOS D/E capacity threshold.<br />

Source: HNTB Corporation<br />

4.1.5 AIRPORT TRAVEL TIMES<br />

Motorists’ travel time to and from the Airport is an excellent measure for evaluating<br />

regional transportation quality of service for Airport passengers and employees.<br />

To analyze current and historical airport travel time, two data sets from MARC were<br />

used.<br />

<br />

<br />

DRAFT<br />

2005/06 Travel Time Data - 2005/06 travel time data was collected by<br />

MARC staff on more than 1,600 miles of roadway in the metropolitan area.<br />

The study logged 70 routes throughout Kansas City metro area, including a<br />

cross-section of road types.<br />

2010 INRIX Travel Time Data – MARC recently purchased 2010 INRIX<br />

data. INRIX is a private provider of traffic information, directions, and driver<br />

services.<br />

Travel times to the Airport are shown in Figure 4.1-7, 2010 AM Peak Period<br />

Travel Time Intervals To KCI Airport, and regional activity centers are<br />

summarized in Table 4.1-8, 2010 AM Peak Period Travel Times To KCI<br />

Airport. Travel times from the Airport are shown in Figure 4.1-8, 2010 PM Peak<br />

Period Travel Time Intervals to KCI Airport, and regional activity centers are<br />

summarized in Table 4.1-9, 2010 PM Peak Period Travel Times To KCI<br />

Airport.<br />

Landrum & Brown Page 137<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 4.1-7<br />

2010 AM PEAK PERIOD TRAVEL TIME INTERVALS TO KCI AIRPORT<br />

Source:<br />

MARC, 2010 INRIX Data<br />

DRAFT<br />

Table 4.1-8<br />

2010 AM PEAK PERIOD TRAVEL TIMES TO KCI AIRPORT<br />

Activity Center<br />

Downtown<br />

Lee’s Summit (I-470/US 50)<br />

Johnson County (I-435/US 69)<br />

Travel Time<br />

19 minutes<br />

41 minutes<br />

33 minutes<br />

Source:<br />

INRIX 2010 Data<br />

Landrum & Brown Page 138<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 4.1-8<br />

2010 PM PEAK PERIOD TRAVEL TIMES INTERVALS FROM KCI AIRPORT<br />

DRAFT<br />

Source:<br />

MARC, 2010 INRIX Data<br />

Table 4.1-9<br />

2010 PM PEAK PERIOD TRAVEL TIMES FROM KCI AIRPORT<br />

Activity Center<br />

Downtown<br />

Lee’s Summit (I-470/US 50)<br />

Johnson County (I-435/US 69)<br />

Travel Time<br />

19 minutes<br />

38 minutes<br />

35 minutes<br />

Source:<br />

INRIX 2010 Data<br />

Landrum & Brown Page 139<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

When you compare 2010 travel time data to 2005/06 travel time data, trends can<br />

be identified. Figure 4.1-9, AM Peak Period Travel Times to KCI Airport<br />

(Change from 2005 to 2010), shows the changes in travel time to the Airport.<br />

As shown in the figures, AM peak hour travel times between the Airport and<br />

downtown slightly increased, AM peak hour travel times between the Airport and<br />

Lee’s Summit decreased, and AM peak hour travel times between the Airport and<br />

Johnson County decreased.<br />

Figure 4.1-9<br />

AM PEAK PERIOD TRAVEL TIMES TO KCI AIRPORT<br />

(Change from 2005 to 2010)<br />

DRAFT<br />

Source:<br />

INRIX 2010 Data<br />

Landrum & Brown Page 140<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

As shown in Figure 4.1-10, PM Peak Period Travel Times from KCI Airport<br />

(Change from 2005 to 2010), the PM peak hour travel times between the Airport<br />

and downtown increased, PM peak hour travel times between the Airport and Lee’s<br />

Summit decreased, and PM peak hour travel times between the Airport and Johnson<br />

County decreased.<br />

Figure 4.1-10<br />

PM PEAK PERIOD TRAVEL TIMES FROM KCI AIRPORT<br />

(Change from 2005 to 2010)<br />

DRAFT<br />

Source:<br />

INRIX 2010 Data<br />

Landrum & Brown Page 141<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4.1.6 SUMMARY<br />

The regional transportation infrastructure is anticipated to be sufficient to serve the<br />

airport’s needs through the planning period. Regional congestion identified by<br />

MARC will continue to exist until but will not prohibit access and the interchange at<br />

Cookingham Drive is sufficient to accommodate airport traffic through 2030. In the<br />

future, traffic along Cookingham Drive should be monitored and when the volume<br />

to capacity ratio beyond 2030 begins to approach 0.85 enhancements to the<br />

interchange should be considered to facilitate traffic access.<br />

4.2 <strong>Terminal</strong> Area Landside Requirements<br />

In this section, the methodology and summary of landside requirements are<br />

presented. Requirements are based on data presented in the 2008 Master Plan and<br />

additional data collected 2012 at the onset of this study. A comprehensive data<br />

collection effort was initiated in March 2012 corresponding to the passenger surveys<br />

and traffic counts, vehicle classification, dwell time observations and pedestrian<br />

crosswalk counts were collected and used to develop requirements for:<br />

<br />

<br />

<br />

<br />

<strong>Terminal</strong> Roadways<br />

Curbside Areas<br />

Vehicular Parking<br />

Commercial Vehicle Staging Area<br />

4.2.1 TERMINAL ROADWAYS<br />

DRAFT<br />

The peak hour traffic volumes collected on the International Circle entrance<br />

roadways were adjusted to account for the difference between a peak day in March<br />

and an average peak day in July (the design day). Volumes for courtesy shuttles<br />

were not increased as these shuttles would typically operate on similar schedules<br />

while carrying more passengers; however, all volumes attributable to demand<br />

driven vehicle modes (e.g. private vehicles [curbside and parking], taxicabs and<br />

limousines). A five percent adjustment was applied based on historic passenger<br />

volumes and characteristics of the peak day of March versus an average peak day<br />

in July. The volumes were projected to future years based on the forecast increase<br />

in O&D passengers and are presented in Table 4.2-1, Forecast Peak Hour<br />

Traffic Volumes. The capacity of the inbound and outbound roadways is assumed<br />

to be 900 vehicles per hour per lane, reflecting slowing speeds as vehicles approach<br />

the terminal area. <strong>Terminal</strong> arrivals and departures curbside roadway capacity is<br />

based on the decreasing capacity of each lane toward the terminal with the lane<br />

adjacent to the curbside drop-off / pick-up areas not accommodating any vehicle<br />

throughput. Associated lane requirements are shown in Table 4.2-2, Lane<br />

Requirements. As shown, the inbound and outbound roadways will require a<br />

minimum of two lanes in each direction this accommodates all traffic associated<br />

with the future terminal development plan.<br />

Landrum & Brown Page 142<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The forecast traffic volumes and lane requirements for the terminal curbsides are<br />

also shown in Tables 4.2-1 and 4.2-2, respectively. Arrivals and Departures<br />

roadway volumes were increased as described above to account for the design day<br />

in July and then adjusted based on the combined traffic volumes at the existing<br />

terminals to reflect a single terminal with separate arrivals and departures levels.<br />

Vehicle trips associated with the inter-terminal Red Bus were removed and volumes<br />

were adjusted to account for commercial vehicles stopping only once at the new<br />

single terminal. The volumes and associated lane requirements shown in Tables<br />

4.2-1 and 4.2-2 assume a separate commercial vehicle curb serving both arriving<br />

and departing passengers. As a result, the departures curb requirement only<br />

reflects private vehicle, taxicab, and limousine drop-off, while the arrivals curb only<br />

reflects private vehicle pick-up. All other activity is assumed to be accommodated<br />

on the commercial vehicle curb.<br />

Table 4.2-1<br />

FORECAST PEAK HOUR TRAFFIC VOLUMES<br />

Location Existing 2015 2020 2025 2030<br />

Entrance International Circle 1 1,200 1,300 1,420 1,555 1,700<br />

Exit International Circle 1 1,200 1,300 1,420 1,555 1,700<br />

<strong>Terminal</strong> Arrivals Roadway 835 905 985 1,080 1,180<br />

<strong>Terminal</strong> Departures Roadway 730 790 865 945 1,035<br />

<strong>Terminal</strong> Commercial Vehicles<br />

Roadway<br />

185 190 205 225 245<br />

Note: 1 Volume will vary based on number of parking spaces and other uses provided within<br />

the terminal area. Specific requirement will be defined during concept development<br />

and refinement.<br />

Source: March 2012 Traffic Surveys and HNTB analysis based on forecast passenger growth.<br />

Table 4.2-2<br />

LANE REQUIREMENTS<br />

DRAFT<br />

Location Existing 2015 2020 2025 2030<br />

Entrance International Circle 1 2 2 2 2 2<br />

Exit International Circle 1 2 2 2 2 2<br />

<strong>Terminal</strong> Arrivals 3 3 4 4 4<br />

<strong>Terminal</strong> Departures 3 3 3 4 4<br />

<strong>Terminal</strong> Commercial Vehicles N/A N/A N/A N/A N/A<br />

Note: 1 Volume will vary based on number of parking spaces and other uses provided within<br />

the terminal area. Specific requirement will be defined during concept development<br />

and refinement.<br />

Source: HNTB analysis based on forecast peak hour traffic volumes.<br />

Landrum & Brown Page 143<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4.2.2 CURBSIDES<br />

Curbside length requirements were calculated for private vehicle arrivals, private<br />

vehicle departures, and commercial vehicles, assuming a consolidated multi-level<br />

terminal building. The specific layout of the terminal building and curbsides may<br />

result in adjustments to the curbside requirements.<br />

Traffic volumes presented in Table 4.2-1 in the previous section were used to<br />

calculate curbside length requirements. The future overall airport peak hour<br />

arrivals, departures, and curbside volumes were developed by applying the vehicle<br />

classification percentages collected during the survey. Then future private vehicle,<br />

taxicab, and limousine volumes, which are demand driven; and single party vehicle<br />

modes, were estimated assuming that that the volumes would increase in direct<br />

proportion to the forecast increases in O&D airline passenger activity.<br />

This assumes no significant change in the proportion of connecting passengers,<br />

travel mode choice patterns, or the use of public parking (versus curbside pick-up<br />

or drop-off). Commercial courtesy vehicles serving multiple parties, such as<br />

parking, rental car, and hotel shuttles, were assumed to grow at half the rate of<br />

O&D passengers since these vehicles will typically increase passenger occupancy<br />

prior to adding shuttles during peak periods. Some growth will still occur as a<br />

result of new entrants serving the Airport, such as new off-airport hotels, and this<br />

growth is accounted for in the reduced growth rate.<br />

Curbside requirements were developed for each vehicle type by calculating the<br />

linear length required to accommodate vehicle loading and unloading activity using<br />

vehicle volumes, vehicle parking stall lengths, and proposed dwell time data<br />

presented in Table 4.2-4. Vehicle parking lengths are based on actual vehicle<br />

lengths plus an additional length to allow for space to maneuver in and out of<br />

curbside parking spaces. A Poisson distribution, a discrete probability distribution<br />

that identifies the probability of a given number of events occurring in a fixed<br />

interval of time, was applied to account for the randomness of vehicles arriving at<br />

the curbside and associated peaking within the peak hour. The curbside length<br />

requirement presented in Table 4.2-3, Required Departures Los C Curb Length<br />

(Feet), for the departures curb assumes only private vehicle, taxicab, and<br />

limousine activity will occur on the departures curbside. The arrivals curbside<br />

length requirement presented in Table 4.2-4, Required Private Vehicles Los C<br />

Arrivals Curb Length (Feet), assumes only private vehicles will use the curbside<br />

and the requirements for all other commercial vehicle activity is shown in<br />

Table 4.2-5, Required Commercial Vehicles Curb Length (Feet), and is<br />

assumed to occur on a commercial curbside.<br />

DRAFT<br />

Landrum & Brown Page 144<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 4.2-3<br />

REQUIRED DEPARTURES LOS C CURB LENGTH (FEET)<br />

Private vehicle<br />

Taxicab<br />

Limousine<br />

Classification Existing 2015 2020 2025 2030<br />

500 545 580 630 690<br />

Source:<br />

HNTB analysis based on forecast peak hour traffic volumes and March 2012 survey data.<br />

Table 4.2-4<br />

REQUIRED PRIVATE VEHICLES LOS C ARRIVALS CURB LENGTH (FEET)<br />

Classification Existing 2015 2020 2025 2030<br />

Private vehicle 660 695 770 820 890<br />

Source:<br />

HNTB analysis based on forecast peak hour traffic volumes and March 2012 survey data.<br />

Table 4.2-5<br />

REQUIRED COMMERCIAL VEHICLES CURB LENGTH (FEET)<br />

Classification Existing 2015 2020 2025 2030<br />

Taxicab 100 100 125 125 125<br />

Limousine 120 120 120 120 150<br />

DRAFT<br />

For-hire shuttle 70 70 70 105 105<br />

Rental car shuttle 110 110 110 110 110<br />

Hotel shuttle 70 105 105 105 105<br />

Blue bus (economy parking) 55 55 110 110 110<br />

Park-Air Express 35 70 70 70 70<br />

Off-Airport parking shuttle 80 120 120 120 120<br />

Charter bus 60 60 60 60 60<br />

Metro (public bus) 60 60 60 60 60<br />

Other 25 25 25 25 25<br />

Total 785 895 975 1,010 1,040<br />

Source:<br />

HNTB analysis based on forecast peak hour traffic volumes and March 2012 survey data.<br />

Landrum & Brown Page 145<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Departures and arrivals curb requirements are adjusted to reflect double parking up<br />

to 40 percent of the curb during the peak period, representing LOS C operations.<br />

The commercial curb requirements do not assume double parking due to<br />

operational and safety considerations for commercial vehicle shuttles.<br />

Commercial curbside requirements assume combined drop-off and pick-up activity<br />

for courtesy shuttles (e.g. hotel, parking, and rental car shuttles). If separate<br />

pick-up / drop-off areas are designated the requirements should be adjusted<br />

accordingly using the observed dwell times collected in the March survey. Curbside<br />

allocation plans and associated requirements for both scenarios are depicted in the<br />

recommended transit plaza plans.<br />

Scheduled services, such as the public buses, were assumed to maintain their<br />

current level of service in the future and not increase frequency, however, space for<br />

a dedicated stop was assumed for the public bus. A dedicated four-space taxicab<br />

queue, increasing to five in 2020, was assumed for pick-up activity on the<br />

commercial curb.<br />

4.3 Vehicular Parking<br />

4.3.1 PUBLIC PARKING<br />

Public parking requirements were determined by analyzing the capacity,<br />

transactions, and occupancies of all the Airport-operated public parking facilities.<br />

Overnight facility occupancies, and entry and exit volumes (transactions) were<br />

provided by KCAD staff for March 2012 to coincide with the month originating<br />

passenger surveys were conducted. Transactions were estimated by duration<br />

category (e.g. 30 minutes, 30 minutes – 1 hour, etc.) and the number of spaces<br />

required for each duration category was calculated by applying a turn factor<br />

(an estimate of the number of times a parking space is “turned over” or utilized<br />

each day in the respective duration category). The number of turns per day was<br />

estimated based on industry observations and calibrated to overnight counts and an<br />

estimate of peak hour occupancy. March transactions were then adjusted based on<br />

the actual increase in 2011 monthly transactions during the peak parking month<br />

(July for the terminal garages and October for the Circle and Economy Lots)<br />

compared to March, and a peak month, average day parking demand was<br />

calculated.<br />

DRAFT<br />

Table 4.3-1, Public Parking Requirements, presents terminal area and remote<br />

economy parking with the terminal area divided into two categories (close-in and<br />

long-term), based on the division of usage in the current close-in garages and circle<br />

lot. The circle lot patrons represent both overflow from the <strong>Terminal</strong> B garage,<br />

which is constrained at peak times and parkers who are generally more price<br />

sensitive and may be less inclined to pay an increased rate at the terminal garages.<br />

As selected concepts are refined, this requirement will be reviewed to determine<br />

how the number of spaces available within the terminal area garages and surface<br />

lot affect the breakdown of close-in and long-term parking and the potential pricing<br />

structure.<br />

Landrum & Brown Page 146<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Requirements include a search factor, as is typical in the industry, to account for<br />

the required surplus that will allow vehicles entering the facility to find an open<br />

parking space within a reasonable amount of time. A search factor of ten percent<br />

was applied to garage spaces and five percent to long-term terminal area and<br />

economy parking. Future year requirements were developed based on the growth<br />

in daily originating passengers as presented in the aviation forecasts.<br />

Table 4.3-1<br />

PUBLIC PARKING REQUIREMENTS<br />

Facility Existing 2015 2020 2025 2030<br />

Annual Originating<br />

Passengers<br />

4,646,770 5,040,400 5,501,400 6,017,300 6,590,700<br />

Close-in (Garage) 4,720 5,090 5,520 6,085 6,615<br />

Long-term (Surface) 1,655 1,720 1,935 2,150 2,335<br />

Total <strong>Terminal</strong> Area 6,375 6,810 7,455 8,235 8,950<br />

Remote Economy 11,300 12,300 13,400 14,700 16,000<br />

Total 17,675 19,110 20,855 22,935 24,950<br />

Source:<br />

HNTB analysis based on existing parking data provided by KCAD and forecast growth in passengers.<br />

Parking Design Considerations<br />

Current terminal parking facilities are configured with 63-foot bays and 8.5-foot<br />

wide stalls. Future parking facilities should maintain a minimum of 63-foot parking<br />

bays and 8.5-foot stalls with a preference toward 9-foot wide parking stalls.<br />

4.3.2 EMPLOYEE PARKING<br />

DRAFT<br />

Employee parking is provided primarily in a 1,500-space remote parking area on<br />

Mexico Avenue. Employee parking requirements were determined based on peak<br />

85-percent occupancy reported in the MP and adjusted to existing conditions based<br />

on actual passenger growth. The future requirements shown in Table 4.3-2,<br />

Employee Parking Requirements, were based on the forecast growth in overall<br />

airport passengers.<br />

Table 4.3-2<br />

EMPLOYEE PARKING REQUIREMENTS<br />

Facility Existing 2015 2020 2025 2030<br />

Employee 11,800 12,800 14,000 15,300 16,800<br />

Source:<br />

HNTB analysis based on existing parking data provided by KCAD and forecast growth in passengers.<br />

Landrum & Brown Page 147<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

4.3.3 COMMERCIAL VEHICLE STAGING AREA<br />

Currently, staging for taxicabs, limousines, and for-hire shuttles is provided in two<br />

lots within International Circle while they wait to pick-up arriving passengers.<br />

The first is a 3.5-acre multi-purpose lot south of the ATCT which is used for for-hire<br />

shuttles, charter bus, and some limousine staging. The second is a 0.5-acre taxi<br />

hold lot located east of the ATCT. Estimated requirements for for-hire shuttles,<br />

limousines, and taxicabs staging were developed based on an estimate of peak<br />

hour volumes for each vehicle type gathered during the traffic surveys and curbside<br />

observations. For the purpose of sizing a staging area, it was assumed that<br />

sufficient space be provided to accommodate a two-hour supply of for-hire shuttles<br />

and limousines, and a three-hour supply of taxicabs. This would provide sufficient<br />

space for vehicles arriving to pick up passengers during the peak periods to remain<br />

in the staging areas for up to two and three hours, which is common for taxi<br />

drivers. The rolling peak periods were determined by analyzing the adjusted<br />

terminal area arrivals traffic volumes with the applied vehicle classification<br />

breakdown. The peak periods were determined to be Fridays from 5:00 PM to<br />

8:00 PM for for-hire shuttles and 7:00 PM to 10:00 PM for taxicabs and limousines.<br />

A 10-percent surplus was applied to account for vehicle surges during the time<br />

period and delayed flights that would result in vehicles remaining in the hold lot<br />

longer than anticipated.<br />

Table 4.3-3, Commercial Vehicle Staging Requirement, lists the requirements<br />

for each vehicle. In addition, equivalent area requirements were calculated<br />

assuming 380 square feet per space for shuttles, 330 square feet per space for<br />

limousines, and 200 square feet per space for taxicabs (assuming a nose-to-tail<br />

parking configuration, with taxicabs being dispatched to the terminal in the order<br />

they arrive). The area requirements are also summarized in Table 4.3-3.<br />

Table 4.3-3<br />

COMMERCIAL VEHICLE STAGING REQUIREMENT<br />

Staging Space Requirement<br />

Vehicle Existing 2015 2020 2025 2030<br />

For-hire shuttles 22 24 26 29 31<br />

Limousines 61 66 72 78 86<br />

Taxicabs 50 54 58 64 70<br />

Total 133 144 156 171 187<br />

Staging Area Requirement (acres)<br />

DRAFT<br />

For-hire shuttles 0.19 0.20 0.22 0.25 0.26<br />

Limousines 0.46 0.50 0.55 0.59 0.65<br />

Taxicabs 0.23 0.25 0.27 0.29 0.32<br />

Total 0.88 0.95 1.03 1.13 1.24<br />

Source:<br />

HNTB analysis based on 2012 Traffic Survey data.<br />

Landrum & Brown Page 148<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

5. TERMINAL SUPPORT REQUIREMENTS<br />

The 2008 MP presented requirements for airport and airline support facilities based<br />

on the forecast developed at that time. Since this past MP was completed aircraft<br />

operations and passenger volumes have declined and an updated operations and<br />

passenger forecasts have been developed as part of the New <strong>Terminal</strong> <strong>Advance</strong><br />

<strong>Planning</strong> <strong>Study</strong>. With this decrease in demand the terminal support facilities were<br />

re-evaluated in this <strong>Study</strong> to determine if the future requirements prepared in 2008<br />

would change based on the updated forecast.<br />

It was determined that the airport administration building, Aircraft Rescue and<br />

Firefighting (ARFF) facility, field maintenance facilities, aircraft maintenance<br />

facilities, the service station, the Federal Aviation Administration (FAA) Air Traffic<br />

Control Tower (ATCT), and the FAA <strong>Terminal</strong> Radar Approach Control Facility<br />

(TRACON) do not require expansion (beyond any expansion plans that are already<br />

in place). Because the updated forecast has lower demand than the MP forecast,<br />

the MP conclusions for these facilities will not change and therefore, revised facility<br />

requirements were not developed.<br />

The 2008 MP identified a need to expand the following facilities based on forecast<br />

demand: fleet maintenance facilities; fuel/wash facility; aviation facilities<br />

maintenance; airport police department; flight kitchens; and airport hotel.<br />

The requirements for these facilities were re-calculated based on the updated<br />

forecast in order to determine the appropriate size of these facilities. In addition,<br />

while the MP did not evaluate ground service equipment (GSE) maintenance and<br />

storage area requirements, these areas were also evaluated as part of this analysis.<br />

The KCI support facilities are shown on Figure 5-1, Support Facilities.<br />

DRAFT<br />

Landrum & Brown Page 149<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 5-1<br />

SUPPORT FACILITIES<br />

Source:<br />

Airport Layout Plan; Landrum & Brown<br />

DRAFT<br />

5.1 FLEET MAINTENANCE<br />

The fleet maintenance facility is located at the west end of Paris Street along<br />

Taxiway B. According to the MP, the fleet maintenance building encompasses<br />

34,345 square feet and is located on a 202,337-square foot parcel. The MP<br />

identified a need for an additional 85,363 square feet of land area for fleet<br />

maintenance by 2025. This requirement was based on a 2007 ratio of building area<br />

per commercial operation of 0.23 and a 2007 land to building ratio of 5.9.<br />

These ratios were applied to the updated forecast to determine the revised<br />

requirement. Based on the MP ratios and the updated forecast, an additional<br />

17,063 square feet of land area will be needed by 2030 (see Table 5.1-1, Fleet<br />

Maintenance Requirements).<br />

Landrum & Brown Page 150<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 5.1-1<br />

FLEET MAINTENANCE REQUIREMENTS (IN SQUARE FEET)<br />

YEAR<br />

2007<br />

COMMERCIAL BLDG 2007 LAND<br />

LAND/<br />

REQUIREMENT<br />

SURPLUS/<br />

BLDG<br />

(DEFICIT)<br />

OPERATIONS 1 SF/OP. AREA<br />

BLDG<br />

SIZE<br />

RATIO BLDG LAND BLDG LAND<br />

Actual<br />

2007 34,435 149,770 0.23 202,337 5.9 34,435 202,337 - -<br />

Forecast<br />

2015 34,435 133,247 0.23 202,337 5.9 30,636 180,000 3,799 22,337<br />

2020 34,435 142,028 0.23 202,337 5.9 32,655 191,900 1,780 10,437<br />

2025 34,435 151,644 0.23 202,337 5.9 34,866 204,900 (431) (2,563)<br />

2030 34,435 162,367 0.23 202,337 5.9 37,331 219,400 (2,896) (17,063)<br />

Note: 1 Commercial operations do not include non-commercial air taxi, general aviation or<br />

military operations. SF=square feet<br />

Sources: 2008 Kansas City International Airport Master Plan; New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong> forecast; Landrum<br />

& Brown<br />

5.2 FUEL/WASH FACILITY<br />

The KCI fuel/wash area is located at 194 Bogota Street and is approximately<br />

43,655 square feet. It serves as the fuel/wash facility for airport parking buses,<br />

police vehicles, and airport maintenance vehicles. According to the MP,<br />

maintenance personnel have expressed a need for replacement of the wash area<br />

facilities. The MP analysis showed a need for an additional 29,600 square feet of<br />

fuel/wash facilities by 2025 based on a 2006 ratio of 0.008 square feet of land area<br />

per enplaned passenger. This ratio was applied to the revised forecast to<br />

determine an updated fuel/wash facility requirement (see Table 5.2-1,<br />

Fuel/Wash Facility Requirement). Based on the MP ratios and the updated<br />

forecast, there is a need to provide an additional 14,100 square feet of fuel/wash<br />

land area by 2030.<br />

Table 5.2-1<br />

FUEL/WASH FACILITY REQUIREMENTS (IN SQUARE FEET)<br />

YEAR<br />

2006 LAND<br />

DRAFT<br />

ENPLANED<br />

PASSENGER<br />

SF PER<br />

ENPL.<br />

AREA<br />

REQ'D<br />

SURPLUS/<br />

(DEFICIT)<br />

AREA<br />

Actual<br />

2006 43,655 5,471,339 0.008 43,655 -<br />

Forecast<br />

2015 43,655 5,536,000 0.008 44,200 (500)<br />

2020 43,655 6,042,000 0.008 48,200 (4,500)<br />

2025 43,655 6,608,500 0.008 52,700 (9,000)<br />

2030 43,655 7,237,900 0.008 57,800 (14,100)<br />

Note:<br />

Sources:<br />

SF=square feet<br />

2008 Kansas City International Airport Master Plan; New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong> forecast; Landrum<br />

& Brown<br />

Landrum & Brown Page 151<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

5.3 AVIATION FACILITIES MAINTENANCE<br />

The aviation maintenance facilities are located at 711 Mexico City Avenue.<br />

The building is 10,000 square feet and is located on a 40,091-square foot parcel.<br />

The MP facility requirements were calculated based on a 2006 ratio of building<br />

square feet per commercial operation of 0.07 and a land to building ratio of 4.0.<br />

The MP determined there was a need for an additional 24,209 square feet of land<br />

area for aviation facilities maintenance by 2025. Based on the MP ratios and the<br />

updated forecast, there is a need for an additional 3,409 square feet of land area by<br />

2030 (see Table 5.3-1, Aviation Facilities Maintenance).<br />

Table 5.3-1<br />

AVIATION FACILITIES MAINTENANCE REQUIREMENTS (IN SQUARE FEET)<br />

YEAR<br />

2006<br />

BLDG COMMERCIAL 2006 LAND<br />

LAND/<br />

REQUIREMENT<br />

SURPLUS/<br />

BLDG<br />

SF/OP.<br />

(DEFICIT)<br />

OPERATIONS 1 AREA<br />

BUILDING<br />

AREA<br />

RATIO BLDG LAND BLDG LAND<br />

Actual<br />

2006 10,000 0.07 149,770 40,091 4.0 10,000 40,091 - -<br />

Forecast<br />

2015 10,000 0.07 133,247 40,091 4.0 8,897 35,700 1,103 4,391<br />

2020 10,000 0.07 142,028 40,091 4.0 9,483 38,000 517 2,091<br />

2025 10,000 0.07 151,644 40,091 4.0 10,125 40,600 (125) (509)<br />

2030 10,000 0.07 162,367 40,091 4.0 10,841 43,500 (841) (3,409)<br />

Note:<br />

Sources:<br />

SF=square feet<br />

1 Commercial operations do not include non-commercial air taxi, general aviation or<br />

military operations.<br />

2008 Kansas City International Airport Master Plan; New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong> forecast; Landrum<br />

& Brown analysis.<br />

DRAFT<br />

5.4 AIRPORT POLICE DEPARTMENT<br />

The KCI police department is located in the center of the terminal area. It is a<br />

44,381-square foot building on a 115,000-square foot parcel that supports the<br />

police and security functions at the Airport and the communications center and<br />

Sprint telecommunications. The MP identified a need for 78,100 square feet of<br />

additional land area by 2025, based on a 2006 ratio of building square feet per<br />

enplaned passenger of 0.008 and a 2006 land area per enplaned passenger ratio of<br />

0.021. These ratios were applied to the updated forecast to determine revised<br />

police department requirements (see Table 5.4-1, Police Department<br />

Requirements). The updated forecast yields a requirement for 37,100 additional<br />

square feet of land area by 2030 for the police department.<br />

Landrum & Brown Page 152<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 5.4-1<br />

POLICE DEPARTMENT REQUIREMENTS (IN SQUARE FEET)<br />

YEAR<br />

2006<br />

BLDG. SF<br />

LAND<br />

SURPLUS/<br />

ENPLANED<br />

LAND<br />

REQUIREMENT<br />

BLDG<br />

PER<br />

AREA/<br />

(DEFICIT)<br />

PASSENGERS<br />

AREA<br />

AREA<br />

ENPL.<br />

ENPL. BLDG LAND BLDG LAND<br />

Actual<br />

2006 44,381 5,471,339 0.008 115,000 0.021 44,381 115,000 - -<br />

Forecast<br />

2015 44,381 5,536,000 0.008 115,000 0.021 44,900 116,400 (519) (1,400)<br />

2020 44,381 6,042,000 0.008 115,000 0.021 49,000 127,000 (4,619) (12,000)<br />

2025 44,381 6,608,500 0.008 115,000 0.021 53,600 138,900 (9,219) (23,900)<br />

2030 44,381 7,237,900 0.008 115,000 0.021 58,700 152,100 (14,319) (37,100)<br />

Note:<br />

Sources:<br />

SF=square feet<br />

2008 Kansas City International Airport Master Plan; New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong> forecast; Landrum<br />

& Brown<br />

5.5 FLIGHT KITCHENS<br />

There are two flight kitchen facilities at KCI: LSG Sky Chefs and Midwest Airlines<br />

Commissary. LSG Sky Chefs has a 42,000-square foot facility located at<br />

566 Brasilia Avenue. Midwest Airlines Commissary is a 20,808-square foot building<br />

located at 241 Paris Street. Combined, the two facilities are located on<br />

181,713 square feet of land area.<br />

According to the MP, the Sky Chefs facility size is sufficient but the Midwest Airlines<br />

Commissary facility will need an additional 12,487 square feet of land area by<br />

2025. The MP requirement was calculated based on a 2006 meals-per-passenger<br />

ratio of 0.06, 2006 meals-per-total square feet ratio of 0.03, and a 2006 ratio of<br />

land area per commercial operation of 0.8. The 2006 ratios were calculated based<br />

on actual building usage information provided by Sky Chefs and Midwest Airlines<br />

commissary personnel. Based on these ratios and the updated forecast, no<br />

expansion of the flight kitchen facilities is required during the planning period<br />

(see Table 5.5-1, Flight Kitchen Requirements).<br />

DRAFT<br />

Table 5.5-1<br />

FLIGHT KITCHEN REQUIREMENTS (IN SQUARE FEET)<br />

YEAR<br />

2006 2006<br />

DAILY<br />

SURPLUS/<br />

PMAD<br />

COMMERCIAL REQUIREMENT<br />

BLDG LAND<br />

MEALS<br />

(DEFICIT)<br />

PASS.<br />

OPERATIONS 1<br />

AREA AREA<br />

REQ'D<br />

BLDG LAND BLDG LAND<br />

Actual<br />

2006 57,140 181,713 15,857 1,026 149,770 36,140 121,077 21,000 60,636<br />

Forecast<br />

2015 57,140 181,713 18,600 1,203 133,247 42,391 107,719 14,749 73,994<br />

2020 57,140 181,713 20,300 1,313 142,028 46,266 114,818 10,874 66,895<br />

2025 57,140 181,713 22,200 1,436 151,644 50,596 122,592 6,544 59,121<br />

2025 57,140 181,713 24,100 1,559 162,367 54,926 131,261 2,214 50,452<br />

Notes: 1 SF=square feet<br />

Commercial operations do not include non-commercial air taxi, general aviation or<br />

military operations.<br />

Sources: 2008 Kansas City International Airport Master Plan; New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong> forecast; Landrum<br />

& Brown<br />

Landrum & Brown Page 153<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

5.6 AIRPORT HOTEL<br />

Currently there is a single hotel located on Airport property which is the Marriott<br />

Hotel at 775 Brasilia Avenue. This existing hotel has 382 rooms and a<br />

conference/banquet center. According to the MP, the occupancy rate in 2006 was<br />

82 percent, resulting in a 2006 ratio of 17,467 enplanements per room. Based on<br />

this ratio by 2025 there is only a need for 378 rooms and the existing Marriot has<br />

382 rooms which is a surplus of 4 rooms. In 2030 however the revised forecast<br />

based on this historic ratio of passenger enplanements to rooms shows the need for<br />

32 additional rooms over the current capacity of the Marriott Hotel.<br />

(See Table 5.6-1, Airport Hotel Requirements)<br />

Table 5.6-1<br />

AIRPORT HOTEL REQUIREMENTS<br />

YEAR<br />

2006 ANNUAL ENPL/ ROOMS SURPLUS/<br />

ROOMS ENPL. ROOM REQUIRED (DEFICIT)<br />

Actual<br />

2006 382 5,471,339 17,467 313 69<br />

Forecast<br />

2015 382 5,536,000 17,467 317 65<br />

2020 382 6,042,000 17,467 346 36<br />

2025 382 6,608,500 17,467 378 4<br />

2030 382 7,237,900 17,467 414 (32)<br />

Sources:<br />

2008 Kansas City International Airport Master Plan; New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong> forecast; Landrum<br />

& Brown<br />

DRAFT<br />

5.7 GROUND SERVICE EQUIPMENT (GSE) FACILITIES<br />

The GSE are stationed at and around the terminal gates for the servicing of<br />

passenger aircraft and are stored in the vicinity of the aircraft gates at the<br />

terminals when in regular use. GSE fuel facilities are located between the terminals<br />

on the aircraft ramp so that equipment can be fueled near the gates via hydrant<br />

system, similar to the aircraft hydrant fueling system. There are three fueling<br />

facilities for GSE equipment on the terminal ramp: one between <strong>Terminal</strong>s A and B,<br />

one between <strong>Terminal</strong>s B and C, and one to the north of <strong>Terminal</strong> C. There is<br />

sufficient area around the gates to accommodate the GSE that is in regular use.<br />

According to Airport officials, GSE is stored in the buildings along Cargo Row<br />

(both on the ramp and in the buildings) when not in use. The airlines perform light<br />

maintenance on their GSE in their leased terminal areas. Heavy mechanical<br />

maintenance is performed along Cargo Row. The MP did not evaluate sizing<br />

requirements for GSE maintenance and storage areas. Airport officials have<br />

advised that GSE maintenance/storage is not a critical issue and that additional<br />

space will not be needed. As a result, no additional land should be set aside for<br />

additional GSE maintenance and storage facilities.<br />

Landrum & Brown Page 154<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

5.8 AIRSIDE SNOW STORAGE AND MELTING AREAS<br />

KCI’s Snow and Ice Control Plan 2 was reviewed and Airport personnel were<br />

interviewed to determine current snow clearing procedures for the airfield.<br />

KCI’s Priority 1 3 areas include primary runways with their respective entry and exit<br />

taxiway connectors, two high-speed taxiways on primary arrival runways, an<br />

associated parallel taxiway, and access taxiways to the terminal ramps.<br />

The remaining taxiways and terminal aprons are cleared as conditions allow.<br />

There are no formal designated “snow dump” areas for the terminals.<br />

Snow removal procedures for the terminal apron include plowing out from the<br />

terminal to the taxiways while working around parked aircraft, and setting up rows<br />

of plowed snow (referred to as “windrows”) at the apron’s edge to blow snow into<br />

the grass infields. The snow is ultimately stored in the field surrounding the ARFF<br />

building (see Figure 5.8-1, <strong>Terminal</strong> Area). The snow that builds in the alleys<br />

between <strong>Terminal</strong>s A and B and between <strong>Terminal</strong>s B and C is usually plowed<br />

straight out toward the infield and blown into the grass infields at Taxiway M1 and<br />

Taxiways C6/C7/C8. KCI has looked into the possibility of closing Taxiway C7<br />

during the winter to expedite the removal of snow from the <strong>Terminal</strong> B and C alley.<br />

According to Airport personnel, the addition of the Remain Overnight (RON) parking<br />

pad, located off the <strong>Terminal</strong> B apron, has resulted in crews plowing almost double<br />

the volume of snow on several occasions. This results in large piles of snow<br />

accumulating until enough equipment is committed to plow and blow the<br />

accumulated snow into the field surrounding the ARFF facility. There have been<br />

instances years ago when snow accumulations were so great that the operation<br />

could not be set up properly and snow was plowed into the alleys to be removed by<br />

loader and dump truck at the first opportunity. Elimination of the grass infields as<br />

part of the terminal program will cause KCI to have to move snow even further<br />

across live pavement (as in the case of the RON apron) and possibly cause the<br />

apron to become impassable during a snow event.<br />

DRAFT<br />

With the expansion of the terminal, the need for snow storage and melting areas<br />

must be taken into consideration. Four potential areas for snow storage and<br />

melting were identified: (1) the first is to the Northeast of existing Taxiway G;<br />

(2) the second is located Northeast of the existing ARFF; (3) the third is East of<br />

<strong>Terminal</strong> C; and (4) the fourth is between the proposed deicing pads East of<br />

Taxiway B. (See Figure 5.8-2, Potential Future Areas for Snow<br />

Storage/Melting In <strong>Terminal</strong> Area)<br />

2<br />

3<br />

Snow and Ice Control Plan , Kansas City International Airport, May 12, 2012<br />

According to FAA Advisory Circular 150/5200-30C, Airport Winter Safety and Operations, airport<br />

operators can limit interruption of service as much as possible during snow events by classifying<br />

the most critical portions of the aircraft movement area and supporting facilities as Priority 1 and<br />

then taking care of other areas in their order of importance. KCI must clear one inch of snow from<br />

its Priority 1 areas within a one-half hour.<br />

Landrum & Brown Page 155<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 5.8-1<br />

TERMINAL AREA<br />

Sources:<br />

Airport Layout Plan; airport personnel; Snow and Ice Control Plan, Kansas City International Airport,<br />

dated May 12, 2012; and Landrum & Brown<br />

DRAFT<br />

Landrum & Brown Page 156<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 5.8-2<br />

POTENTIAL FUTURE AREAS FOR SNOW STORAGE/MELTING IN TERMINAL<br />

AREA<br />

Sources:<br />

DRAFT<br />

Airport Layout Plan and Landrum & Brown<br />

5.9 RAMP CONTROL TOWER<br />

Currently, there is not a ramp control tower at the KCI terminal. Aircraft that push<br />

back from the gates onto movement areas are under the control of the ATCT.<br />

The ATCT acts in an advisory capacity only for aircraft that do not push back onto<br />

movement areas.<br />

If a ramp control tower is needed with the proposed terminal expansion, it would<br />

likely be located on top of the terminal building. The maximum elevations of the<br />

terminal building/ramp tower were determined based on an ATCT line-of-sight<br />

analysis and FAA Federal Aviation Regulation (FAR) Part 77, Objects Affecting<br />

Navigable Airspace. These maximum elevations are shown on Figure 5.9-1,<br />

Maximum <strong>Terminal</strong> Building Elevations.<br />

Landrum & Brown Page 157<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 5.9-1<br />

MAXIMUM TERMINAL BUILDING ELEVATIONS<br />

Notes: NAVD-88 = North American Vertical Datum of 1988<br />

AGL = Above Ground Level<br />

Sources: FAA Federal Aviation Regulation (FAR) Part 77, Objects Affecting Navigable Airspace; Landrum & Brown<br />

analysis<br />

The size of a ramp tower at KCI would be based on who controls the tower<br />

(the airport, a single airline, or multiple airlines), the number of work stations, and<br />

how many gates would be under the control of the ramp tower. To give an idea of<br />

possible facility size at KCI, ramp control towers at several airports were surveyed:<br />

<br />

<br />

DRAFT<br />

McCarran International Airport (LAS): The D-Gates ramp control tower<br />

at LAS was built in 2005. The facility handles 45 gates and its observation<br />

area is 50 feet in diameter. 4<br />

Philadelphia International Airport (PHL): PHL, which has 130 gates,<br />

has coordinated ramp control towers at the eastern and western ends of the<br />

terminal area. The newest tower, which was constructed in 2002 as part of<br />

the new International <strong>Terminal</strong>, has a 60-foot diameter cab and was<br />

designed to accommodate 25 staffed ramp and operations agent positions.<br />

This tower is run by US Airways which represents just less than half of the<br />

operations at PHL. The second tower cab has a 45-foot diameter. It is run<br />

by the airport and is near <strong>Terminal</strong> F. 5<br />

4<br />

5<br />

http://www.emporis.com/building/mccarraninternationalairportdgatesrampcontroltower-lasvegasnv-usa<br />

Google Earth; www.phl.org gate layout and February 1, 2002 press release; www.pgal.com<br />

Landrum & Brown Page 158<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Orlando International Airport (MCO): Wings 10, 11, and 12<br />

(Gates 60-99) at MCO’s <strong>Terminal</strong> B consist of 32 gates. Its ramp control<br />

tower has a cab radius of 45 feet. 6<br />

Hartsfield-Jackson Atlanta International Airport (ATL): Concourse C<br />

at ATL has 48 gates. It has a ramp control tower with a cab that is 60 feet<br />

by 30 feet. 7<br />

<br />

<br />

Dallas/Fort Worth International Airport (DFW): DFW’s <strong>Terminal</strong> E has<br />

28 gates. Its ramp control tower has a 30-foot by 30-foot cab. 8<br />

Chicago O’Hare International Airport (ORD): ORD has a ramp control<br />

tower that serves Concourses B and C. Its cab is 40 feet by 30 feet.<br />

The average ratio of cab area per gate for all of these airports is 38 square feet per<br />

gate (see Table 5.9-1, Ramp Control Tower Ratios).<br />

Table 5.9-1<br />

RAMP CONTROL TOWER RATIOS<br />

AIRPORT<br />

TERMINAL<br />

CAB<br />

DIMENSIONS<br />

CAB<br />

AREA<br />

(SF)<br />

NO. OF<br />

GATES<br />

CAB<br />

AREA/<br />

GATE<br />

LAS D-Gates 50' diameter 1,963 45 44<br />

PHL 1 Eastern End of <strong>Terminal</strong> Area 60' diameter 2,826 65 43<br />

Western End of <strong>Terminal</strong> Area 45' diameter 1,590 65 24<br />

MCO <strong>Terminal</strong> B, Wings 10-12 45' diameter 1,590 32 50<br />

ATL Concourse C 60x30' 1,800 48 38<br />

DFW <strong>Terminal</strong> E 30x30' 900 28 32<br />

ORD Concourses B and C 40'x30' 1,200 32 38<br />

Average: 1,778 45 38<br />

DRAFT<br />

Note: 1 Number of gates for PHL assumes ramp tower controls half the airport's gates.<br />

Sources: Google Earth; airport websites; www.pgal.com;<br />

http://www.emporis.com/building/mccarraninternational airportdgatesrampcontroltower-lasvegas-nvusa<br />

The proposed terminal for KCI has 41 gates. The application of the 38 square feet<br />

per gate ratio to the KCI terminal results is the need for a cab area of 1,600 square<br />

feet (see Table 5.9-2, Ramp Tower Requirements). A circular ramp control<br />

tower cab at KCI would need to have a diameter of 45 feet. A square shaped tower<br />

would need to be 40 feet by 40 feet in size.<br />

6<br />

7<br />

8<br />

Google Earth and www.orlandoairports.net<br />

Google Earth and www.atlanta-airport.com<br />

Google Earth and www.dfwairport.com<br />

Landrum & Brown Page 159<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 5.9-2<br />

RAMP TOWER REQUIREMENTS<br />

Average Cab Area/Gate (square feet) 38<br />

No. of Gates 41<br />

Required Cab Area (in square feet) 1,600<br />

Circular Cab Diameter 45'<br />

Square Cab Dimensions<br />

40'x40'<br />

Source:<br />

Landrum & Brown analysis<br />

5.10 REMAIN OVERNIGHT (RON) PARKING<br />

The 2008 MP identified five current hardstand positions for RON aircraft during the<br />

base year (2007) and a need for one additional hardstand position by 2025.<br />

This requirement was based on the peak month average day (PMAD) departures<br />

per gate method that accounts for current and anticipated airline utilizations and<br />

fleet mix parameters.<br />

An alternate methodology was applied to the updated forecast to determine the<br />

revised RON parking requirements through 2030 using the updated forecast.<br />

Existing 2012 and future 2030 RON parking requirements were derived from the<br />

2012 and 2030 design day flight schedules developed as part of the terminal<br />

analysis. The 2025 requirement was interpolated.<br />

There are 53 aircraft that RON at KCI in the 2012 schedule and 69 in the<br />

2030 schedule. Subtracting the number of gates from the number of RON aircraft<br />

yields the hardstand requirement for each year (see Table 5.10-1,<br />

Recommended Additional RON Parking Positions). Based on this<br />

methodology, an expansion to the existing terminal apron will be needed to<br />

accommodate 27 hardstand positions by 2025 and 28 hardstand positions by 2030.<br />

The RON parking positions need to be sized to accommodate ADG-III aircraft in<br />

both 2025 and 2030.<br />

DRAFT<br />

Table 5.10-1<br />

RECOMMENDED ADDITIONAL RON PARKING POSITIONS<br />

2012<br />

EXISTING<br />

2025<br />

REQUIREMENT<br />

2030<br />

REQUIREMENT<br />

Total RON Aircraft 53 64 69<br />

Contact Gates 50 37 41<br />

Hardstand Positions 3 27 28<br />

Sources:<br />

2012 and 2030 design day flight schedules; Landrum & Brown analysis<br />

Landrum & Brown Page 160<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6. REFINE CONCEPTUAL TERMINAL COMPLEX SITE PLAN<br />

6.1 Airside Site Plan<br />

As discussed previously, the proposed New <strong>Terminal</strong> at KCI is to be constructed at<br />

the existing <strong>Terminal</strong> A location. Three airfield pavement configurations were<br />

evaluated to support the initial 37-gate terminal construction. Each alternative had<br />

to meet the requirements for the New <strong>Terminal</strong> apron and supporting<br />

infrastructure, summarized below and detailed in prior sections of this document.<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Maintain constant apron elevation around the perimeter of the New <strong>Terminal</strong><br />

building<br />

Meet minimum 1 percent pavement grade adjacent to the New <strong>Terminal</strong> to<br />

satisfy NFPA codes<br />

Do not exceed maximum 1 percent pavement grades on airfield pavements<br />

to meet FAA criteria<br />

Meet ADG III design criteria for taxilanes on the apron, yet allow a single<br />

ADG V operation when necessary<br />

Provide dual taxilanes around the perimeter of the New <strong>Terminal</strong> to allow<br />

simultaneous aircraft operations in opposite directions to all terminal gates<br />

Implement triple taxilanes in areas between parallel concourses to allow push<br />

back from a gate while maintaining dual aircraft taxiing operations<br />

Meet ADG V design criteria for taxiway improvements adjacent to the<br />

terminal apron<br />

DRAFT<br />

Construct centralized deicing pads to meet the projected aircraft fleet mix<br />

Provide a centralized deicing operations administration and maintenance<br />

complex<br />

Provide 28 RON aircraft parking positions<br />

Provide a dedicated collection system of centralized deicing pads to separate<br />

glycol-contaminated runoff from stormwater runoff<br />

Meet MDNR requirements of discharges from the Airport<br />

Landrum & Brown Page 161<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.1-1, Apron Configuration-Alternative 1, depicts the first apron<br />

configuration alternative. Alternative 1 assumes that <strong>Terminal</strong> B will remain in<br />

place after completion of the New <strong>Terminal</strong>. Two dedicated taxilanes will be<br />

developed east of the southern deicing pads to connect Taxiway D to the proposed<br />

terminal complex.<br />

A condensed triple taxilane configuration can be developed in the southern gate<br />

area, but the proximity of the New <strong>Terminal</strong> to <strong>Terminal</strong> B will only provide a single<br />

taxilane from the southern gate areas.<br />

Figure 6.1-1<br />

APRON CONFIGURATION-ALTERNATIVE 1<br />

Source: HNTB<br />

DRAFT<br />

Landrum & Brown Page 162<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.1-2, Apron Configuration-Alternative 2, depicts the second apron<br />

configuration alternative. Alternative 2, similar to Alternative 1, assumes that<br />

<strong>Terminal</strong> B will remain in place after completion of the New <strong>Terminal</strong>, but only a<br />

single access taxilane east of the southern deicing pads to connect Taxiway D and<br />

the proposed terminal will be provided.<br />

A condensed triple taxilane configuration can be developed in the southern gate<br />

area, but the proximity of the New <strong>Terminal</strong> to <strong>Terminal</strong> B will only provide a single<br />

taxilane from the southern gate areas.<br />

Figure 6.1-2<br />

APRON CONFIGURATION-ALTERNATIVE 2<br />

Source: HNTB<br />

DRAFT<br />

Landrum & Brown Page 163<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The third alternative is depicted in Figure 6.1-3, Apron Configuration-<br />

Alternative 3. Alternative 3 assumes that <strong>Terminal</strong> B will be demolished after<br />

completion of the New <strong>Terminal</strong>. It provides triple access taxilanes east of the<br />

southern deicing pads to connect Taxiway D and the New <strong>Terminal</strong>.<br />

Figure 6.1-3<br />

APRON CONFIGURATION-ALTERNATIVE 3<br />

Source:<br />

HNTB<br />

DRAFT<br />

Alternative three was chosen as the Preferred Alternative, which requires the<br />

removal of <strong>Terminal</strong> B to provide the optimum apron transition from the southeast<br />

gates of the New <strong>Terminal</strong>.<br />

The following sections detail recommended airside configuration.<br />

6.1.1 APRON AND TAXILANES<br />

The apron in the Preferred Alternative will interface with the New <strong>Terminal</strong> building<br />

to meet aircraft parking and ground servicing needs. Fueling, maintenance, and<br />

baggage handling are typical services that will be provided at each gate and require<br />

direct access from the terminal building. The apron will be sized to provide proper<br />

wingtip clearance between aircraft parking positions and additional area for ground<br />

service operations at the aircraft parking positions.<br />

Landrum & Brown Page 164<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Push-back zones are areas that must remain clear to push aircraft from a parking<br />

position at a terminal gate for taxi exit to the movement area. A dedicated taxilane<br />

will be located behind each terminal gate to allow aircraft to be pushed back.<br />

A parallel taxilane will also be provided to allow aircraft movements to be<br />

maintained without interruption during push-back operations. In the areas between<br />

two parallel concourses, triple taxilanes will be necessary to allow simultaneous<br />

push-back from each concourse and allow aircraft operations within the concourses.<br />

Figure 6.1-4, Apron Configuration-Alternative 3, depicts the dual and triple<br />

taxilane layouts that will provide push-back zones and maintain aircraft ground<br />

movements.<br />

Figure 6.1-4<br />

APRON CONFIGURATION-ALTERNATIVE 3<br />

DRAFT<br />

Source:<br />

HNTB<br />

The centerline of taxilanes closest to the aircraft parking positions will be located<br />

81 feet from the outer edge of the service road to meet ADG III standards for the<br />

distance from taxilane centerline to a fixed or movable object. Associated parallel<br />

taxilanes will be offset 140 feet to meet ADG III separation standards for parallel<br />

taxilanes.<br />

Landrum & Brown Page 165<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The edge of outboard taxilanes is located 25 feet from the taxilane centerline to<br />

provide the 50-foot taxilane width for ADG III design standards.<br />

ADG V aircraft movements will utilize the center taxilane in areas with triple<br />

taxilanes. No other aircraft operations will be permitted to/from the gates during a<br />

ADG V aircraft ground movement. In areas with only dual taxilanes, the ADG V<br />

aircraft will taxi parallel, and in the middle of the two parallel ADG III taxilanes.<br />

Paved shoulders will be constructed to be 25 feet wide.<br />

6.1.2 TAXIWAYS<br />

The delineation between movement and non-movement areas will be located at the<br />

east edge of the Taxiway B OFA and at the north edge of the Taxiway D OFA as<br />

shown in Figure 6.1-5, TAXIWAY RECONSTRUCTION LIMITS. Therefore,<br />

aircraft movements on the apron area and associated taxilanes will be controlled by<br />

the terminal apron control tower. Aircraft movements onto Taxiways B and D will<br />

be controlled by the FAA ATCT. A non-movement area marking will be located<br />

along the OFA of the adjacent taxiways at a distance of 160 feet from the centerline<br />

of Taxiways B and D.<br />

The elevation of the east edge of Taxiway B drops 8 feet from the south edge of the<br />

New <strong>Terminal</strong> apron to the north edge. With the objective to maintain a constant<br />

elevation at the interface of the apron and meet FAA-grading criteria, it is<br />

necessary to raise the elevation of Taxiway B to allow for a constant apron<br />

elevation at the New <strong>Terminal</strong> apron/building interface.<br />

DRAFT<br />

The reconstruction of Taxiway B adjacent to the proposed apron will impact<br />

Taxiway A and the connecting taxiways to meet the grade criteria. To meet the<br />

required pavement elevations on Taxiway B and construct transitions to meet<br />

FAA-grading criteria, Taxiways A and B will be reconstructed from the ARFF access<br />

road on the south to Taxiway B4 on the north.<br />

Figure 6.1-5<br />

TAXIWAY RECONSTRUCTION LIMITS<br />

Source:<br />

HNTB<br />

Landrum & Brown Page 166<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Connecting Taxiways A9 and G will remain in their existing location to match<br />

proposed taxilane centerlines from the apron. Taxiway M will be reconstructed in a<br />

new location directly east of Taxiway A10. A new connecting taxiway will be<br />

constructed by extending the southern-most taxilane on the apron to Taxiway A.<br />

6.1.3 SERVICE ROADS<br />

The distance of the service road behind the terminal gates is typically located<br />

180 feet from the face of the terminal building. The service road around the<br />

terminal gate will be marked to lead to the make-up areas located on the apron<br />

level of the New <strong>Terminal</strong> building.<br />

As shown in Figure 6.1-6, PROPOSED NEW SERVICE ROADS, the terminal<br />

service road will also extend north in two locations to connect to a proposed new<br />

service road constructed north of the terminal apron. The new northern service<br />

road will extend west to intersect Ottawa Avenue, the existing service road that<br />

parallels Taxiway B on the east side. An additional service road will extend south<br />

from Ottawa Avenue to access the centralized deicing pads. All service roads are<br />

two lanes with each lane being 12.5 feet wide.<br />

Figure 6.1-6<br />

PROPOSED NEW SERVICE ROADS<br />

DRAFT<br />

Source:<br />

L&B<br />

6.1.4 REMOTE OVER NIGHT (RON) PARKING POSITIONS<br />

In addition to the aircraft positions at the terminal gates, there will be 28 remote<br />

overnight (RON) aircraft parking positions designated to temporarily store aircraft<br />

that cannot be accommodated at the terminal gates. Figure 6.1-7, Remote Over<br />

Night Parking Positions, identifies the RON parking positions, denoted by boxes.<br />

Each box is 150 feet x 150 feet to accommodate ADG III aircraft.<br />

Landrum & Brown Page 167<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.1-7<br />

REMOTE OVER NIGHT PARKING POSITIONS<br />

Source:<br />

L&B<br />

DRAFT<br />

6.1.5 CENTRALIZED DEICING PADS<br />

Centralized deicing pads will be established on the terminal apron in three different<br />

areas. Dividing the twelve required deicing pads into three areas reduces<br />

congestion, provides proximity to all terminal gates, and allows deicing pads to be<br />

isolated for snow removal operations or deactivated if the operational need for all<br />

twelve pads is not necessary.<br />

Figure 6.1-8, West Deicing Pads, depicts nine of the twelve deicing pads located<br />

on the west side of the New <strong>Terminal</strong>. Due to the proximity of the New <strong>Terminal</strong> to<br />

Taxiway B, each of these pads is sized to accommodate ADG III aircraft. A deicing<br />

pad to accommodate ADG V aircraft will not work on the west side of the terminal<br />

area.<br />

Landrum & Brown Page 168<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.1-8<br />

WEST DEICING PADS<br />

Source:<br />

HNTB<br />

The deicing pads will be located to allow the dual taxilanes on the north and south<br />

side of the New <strong>Terminal</strong> to remain in operation during deicing conditions.<br />

In addition, two taxilanes separate the two groups of deicing pads to provide direct<br />

access from the terminal gates located in the center of the west side of the terminal<br />

complex.<br />

DRAFT<br />

Deicing pads on the north side of the apron will not be constructed due to the<br />

proximity to existing infrastructure that will remain in place after the initial phase of<br />

the New <strong>Terminal</strong> construction is completed. Locating five deicing pads north of the<br />

center taxilanes will provide direct access from the north gates to more deicing<br />

pads.<br />

A pavement area outside the center taxilane OFA or the deicing pad VSZ will be<br />

constructed adjacent to the northern deicing pads as shown in Figure 6.1-9, Snow<br />

Dump Plan. This area can be used to store snow that is pushed from the terminal<br />

gates or stage snow removal equipment.<br />

South of the center taxilanes, four additional deicing pads can serve ADG III<br />

aircraft.<br />

Landrum & Brown Page 169<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.1-9<br />

SNOW DUMP PLAN<br />

DRAFT<br />

Source:<br />

L&B<br />

Landrum & Brown Page 170<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.1-10, South Deicing Pads, depicts three deicing pads that will be<br />

constructed south of the New <strong>Terminal</strong>, adjacent to Taxiway D. The western two<br />

pads are sized to serve ADG III aircraft and the eastern pad is sized to<br />

accommodate an ADG Group VBoeing 787-8 aircraft. When not in use as an ADG<br />

Group V pad, the large size of this deicing pad allows the flexibility to deice two<br />

ADG II aircraft simultaneously.<br />

Dual taxilanes designed to bypass the deicing pads are located east of the deicing<br />

pads. A single taxilane is utilized to access the three new southern deicing pads<br />

and is sized to accommodate ADG V aircraft. Additional taxilanes branch from the<br />

ADG V taxilane to access the additional deicing pads or direct ADG II aircraft to<br />

deicing positions within the larger pad.<br />

Figure 6.1-10<br />

SOUTH DEICING PADS<br />

DRAFT<br />

Source:<br />

HNTB<br />

Gate deicing operations will not be permitted once the New <strong>Terminal</strong> is in operation.<br />

If airlines are permitted to perform spot deicing of aircraft near the terminal gate,<br />

glycol recovery vehicles will be used to collect the small amount of glycol fluids<br />

applied before aircraft taxi to centralized deicing pads.<br />

Landrum & Brown Page 171<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.1.6 AIRSIDE SECURITY<br />

Access to the Airside from the landside will be provided by a security gate on the<br />

west end of Paris Street. After entering the secure area through the gate, a vehicle<br />

operator will utilize Ottawa Avenue and the proposed new service roads to access<br />

the New <strong>Terminal</strong> gates and centralized deicing pads.<br />

Apron floodlighting is required for contact gates, RON positions, and deicing pads.<br />

Floodlighting provides visibility for pilots operating aircraft and sufficient<br />

illumination for safe and efficient aircraft servicing.<br />

Floodlighting adjacent to the New <strong>Terminal</strong> should be building mounted.<br />

Where feasible, RON positions should be provided with pole-mounted floodlighting<br />

located along the rear of the parking positions to avoid interference with aircraft<br />

movements. Existing floodlights on <strong>Terminal</strong> C can be used to illuminate RON<br />

positions in this area. In no case can poles or fixtures penetrate Part 77 surfaces.<br />

Floodlighting of centralized deicing pads is more challenging. Additional studies to<br />

understand the impacts of glare on the FAA ATCT and the potential height and<br />

hazards obstructions will be necessary to determine the optimum lighting of the<br />

centralized deicing pads.<br />

Floodlights should be provided with connections to emergency lighting circuits.<br />

Servicing of floodlights is expected to be completed by utilizing equipment currently<br />

owned by the airport.<br />

DRAFT<br />

6.1.7 AIRFIELD CONSTRUCTION SEQUENCING<br />

The construction sequencing for the airfield pavement requires multiple phases to<br />

minimize the impact on aircraft operations on the airfield and at the <strong>Terminal</strong> B<br />

gates. Four phases are anticipated to construct the airfield pavements. They are<br />

shown in Figure 6.1.11, Overall Airfield Phasing Diagram, and summarized<br />

below.<br />

1. Phase 1-Construct airfield pavements outside the OFA of the taxilanes<br />

accessing <strong>Terminal</strong> B.<br />

2. Phase 2-Close <strong>Terminal</strong> B Gates 31-36. Construct airfield to access southern<br />

gates of new terminal.<br />

3. Phase 3-Close <strong>Terminal</strong> B. Construct airfield to provide a single taxilane<br />

south from new terminal to Taxiway D.<br />

4. Phase 4-Demolish <strong>Terminal</strong> B. Construct remaining airfield pavement to<br />

provide triple taxilane access south from the new terminal.<br />

Landrum & Brown Page 172<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.1.11<br />

OVERALL AIRFIELD PHASING DIAGRAM<br />

Source:<br />

HNTB<br />

DRAFT<br />

6.1.7.1 Airfield Construction-Phase 1<br />

Phase 1 includes the reconstruction of Taxiways A and B for the purpose of raising<br />

the elevation of the north side of the apron to ultimately provide a consistent apron<br />

elevation around the perimeter of the terminal. Taxiways A and B cannot be closed<br />

simultaneously. <strong>Terminal</strong> B gates will not be impacted during this phase of<br />

construction either. Figure 6.1-12, Airfield Phasing Diagram-Phase 1, shows<br />

this area.<br />

Phase 1 construction operations should consider the following sequence.<br />

1. Perform demolition and construction operations on Taxiway A and connecting<br />

taxiways from the east edge of the Runway 1L-19R RSA to the west edge of<br />

the Taxiway A RSA. Aircraft operations will be maintained on Taxiway B, the<br />

existing terminal aprons and Runway 1L-19R. All connecting taxiways south<br />

of Taxiway B4 shall remain closed after the completion of Taxiway A<br />

construction due to the elevation changes.<br />

Landrum & Brown Page 173<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

2. Perform demolition operations on Taxiway B and connecting taxiways from<br />

the east edge of the Taxiway A RSA to the east edge of Taxiway B. Aircraft<br />

operations will be maintained on Taxiway A and Runway 1L-19R.<br />

All connecting taxiways south of Taxiway B4 can re-open after the<br />

construction operations within the Taxiway B safety area are completed.<br />

3. Simultaneously with the Taxiway B construction, <strong>Terminal</strong> A can be<br />

demolished.<br />

4. Remove enough <strong>Terminal</strong> A apron pavement to construct the foundation and<br />

walls of the new terminal. Leave as much of the existing pavement to serve<br />

as a staging area for terminal construction.<br />

5. Constructing the west deicing pads and associated drainage network after<br />

the Taxiway B construction will allow the deicing pads to be commissioned as<br />

soon as possible. Remove only enough apron pavement as necessary to<br />

maintain as much of the existing pavement for terminal construction staging<br />

operations.<br />

6. Remove additional <strong>Terminal</strong> A apron pavement to construct taxilanes from<br />

<strong>Terminal</strong> B to the deicing pads. Aircraft can begin deicing operations at the<br />

new deicing pads upon completion of the access to the deicing pads.<br />

7. Construct the remainder of Phase 1 pavement upon completion of the<br />

construction of the exterior walls of the terminal.<br />

Figure 6.1-12<br />

AIRFIELD PHASING DIAGRAM-PHASE 1<br />

DRAFT<br />

Source:<br />

HNTB<br />

Landrum & Brown Page 174<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.1.7.2 Airfield Construction-Phase 2A<br />

Upon completion the Phase 1 pavement, it will be necessary to close Gates 31-35 in<br />

<strong>Terminal</strong> B to construct the Phase 2A pavement to allow access to the south interior<br />

gates. It will take approximately three months to complete the Phase 2A pavement<br />

construction. The construction of the pavement area depicted in Figure 6.1-13,<br />

Airfield Phasing Diagram-Phase 2A, should occur simultaneously with the last<br />

three months of the terminal construction.<br />

Figure 6.1-13<br />

AIRFIELD PHASING DIAGRAM-PHASE 2A<br />

Source:<br />

HNTB<br />

DRAFT<br />

Four gates currently utilized by Southwest Airlines will not be accessible during the<br />

construction of the Phase 2A apron pavement. The KCAD shall coordinate with the<br />

impacted airline to maintain the airline’s operations. Options to consider include.<br />

1. Close Gates 31-35 and Southwest Airlines operates from fewer gates for<br />

three months. This is likely not possible as they are the busiest carrier at<br />

KCI.<br />

2. During the shift of airlines when <strong>Terminal</strong> A closes, move Delta to <strong>Terminal</strong> C<br />

and provide an additional four gates for Southwest on the east side of their<br />

current gates. Move a smaller airline from <strong>Terminal</strong> A or C into the area<br />

vacated by Delta.<br />

3. Prior to Phase 2A paving, construct the majority of the new terminal to allow<br />

<strong>Terminal</strong> B tenants to vacate their current space and occupy the northern<br />

and western gates of the new terminal.<br />

Landrum & Brown Page 175<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Upon completion of Phase 2A, only a single taxilane from the south gates is<br />

constructed. Ground movements into the southern gates will have to be<br />

coordinated with departures from the southern gates as there will be a bottleneck<br />

until Phase 2B is constructed.<br />

6.1.7.3 Airfield Construction-Phase 2B<br />

Figure 6.1-14, Airfield Phasing Diagram-Phase 2B, depicts the paving limits of<br />

this Phase. This paving will require the closure of many <strong>Terminal</strong> B gates andwill<br />

occur after <strong>Terminal</strong> B airlines have moved to the new terminal. This phase<br />

includes the construction of the south deicing pads. Phase 2B will provide a second<br />

taxilane from the southern terminal gates, but also a single taxilane south to<br />

Taxiway D.<br />

Phase 2B can be constructed without <strong>Terminal</strong> B being demolished but many of the<br />

gates at <strong>Terminal</strong> B will require closure.<br />

Figure 6.1-14<br />

AIRFIELD PHASING DIAGRAM-PHASE 2B<br />

DRAFT<br />

Source:<br />

HNTB<br />

Landrum & Brown Page 176<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.1.7.4 Airfield Construction-Phase 2C<br />

Once <strong>Terminal</strong> B is demolished, Phase 2C can be constructed. Phase 2C may be<br />

constructed simultaneously with Phases 2A and/or 2B depending on when <strong>Terminal</strong><br />

B is vacated and if <strong>Terminal</strong> B will be demolished after the airlines shift to the new<br />

terminal.<br />

As shown in Figure 6.1-15, Airfield Phasing Diagram-Phase 2C, this pavement<br />

provides dual taxilanes around the south deicing pads and provides triple taxilane<br />

capabilities from the southern terminal gates.<br />

Figure 6.1-15<br />

AIRFIELD PHASING DIAGRAM-PHASE 2C<br />

Source: HNTB<br />

DRAFT<br />

Landrum & Brown Page 177<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.2 Ground Access Site Plan for the New <strong>Terminal</strong><br />

The recommended New <strong>Terminal</strong> ground access site plan provides the following<br />

features:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

A two-level curb roadway adjacent to the New <strong>Terminal</strong> building<br />

Reconfiguration of the existing terminal loop roadway utilizing Bonn Circle<br />

and including relocation of the existing return-to-terminal roadway<br />

A six-level parking structure<br />

A commercial vehicle plaza within the parking structure<br />

A surface parking lot behind the new parking structure and within the new<br />

terminal loop roadway<br />

Consolidated entry and exit plazas for the garage and surface parking areas<br />

Connections to the existing <strong>Terminal</strong> B and <strong>Terminal</strong> C garages<br />

Relocation of the taxi and commercial vehicle staging areas<br />

Opportunity to maintain existing Central Utility Plant (CUP) and Police<br />

Building<br />

Figure 6.2-1, Ground Access Site Plan, shows the recommended overall<br />

landside concept features that preserve the existing airfield lighting vault and FAA<br />

ATCT. The concept also allows the existing CUP to be retained, as shown, during<br />

construction and as part of the final build out, if warranted.<br />

DRAFT<br />

Landrum & Brown Page 178<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 179<br />

April 2013<br />

Figure 6.2-1<br />

GROUND ACCESS SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.2.1 ROADWAYS<br />

As shown in Figure 6.2-1, Ground Access Site Plan, the recommended roadway<br />

concept will provide a reconstruction of the terminal loop roadway to align with<br />

Bonn Circle, relocated return-to-terminal roadway, two-level curbside adjacent to<br />

the New <strong>Terminal</strong>, separate access for commercial vehicles to a dedicated<br />

commercial vehicle plaza, terminal loading dock with separate access, and modified<br />

access to the FAA ATCT.<br />

6.2.1.1 <strong>Terminal</strong> Loop Roadway<br />

The New <strong>Terminal</strong> loop roadway will diverge from the existing Cookingham Drive<br />

alignment immediately south of the Paris Street overpass to access the New<br />

<strong>Terminal</strong>. Access to the parking garage and surface lot entrances will be provided<br />

from the left side of the terminal loop roadway before the main<br />

The primary terminal complex entrance along Cookingham Drive would remain two<br />

lanes until splitting to provide two access lanes, each to the upper (departures) and<br />

lower (arrivals) level curbside roadways (four lanes total). South of the New<br />

<strong>Terminal</strong>, the loop roadway will follow the Bonn Circle alignment to allow sufficient<br />

space for the upper and lower roadways to merge and to maximize the area<br />

available for surface parking within the loop roadway. The upper and lower<br />

roadways are two lanes each merging to two outbound lanes east of <strong>Terminal</strong> B.<br />

The outbound roadway returns to the existing International Circle/Cookingham<br />

Drive alignment north of <strong>Terminal</strong> C where both the parking exit and commercial<br />

vehicle roadway merge with the outbound roadway.<br />

6.2.1.2 Return-To-<strong>Terminal</strong> Roadway<br />

The return-to-terminal roadway will be relocated beyond the Paris Street overpass<br />

to accommodate for maneuvering vehicles as they approach the New <strong>Terminal</strong>.<br />

This roadway should be a minimum of one lane with a shoulder, and provide an<br />

additional storage lane along Cookingham Drive in both the northbound and<br />

southbound directions to allow sufficient time for vehicles to reduce speed for the<br />

turn and merge with traffic after the turn.<br />

6.2.1.3 Curbsides<br />

DRAFT<br />

As part of the New <strong>Terminal</strong> design, curbs and separate private vehicle arrivals and<br />

departures curbs will be provided. Zero clearance - or soft curbs - are proposed to<br />

minimize passenger tripping hazards. Sloping pavement will be used for the curbs<br />

and/or different pavement material or colors will be used for the roadway to help<br />

differentiate between the pedestrian and vehicle areas. Bollards will be provided<br />

along the curb to protect waiting passengers from vehicles.<br />

A maximum grade of 6 percent will be used on the curbside approach roadway and<br />

4.3 percent on the departure roadway.<br />

Landrum & Brown Page 180<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

As shown on Figure 6.2-2, Departures Level, the departures roadway will be<br />

four lanes, comprised of one 20-foot wide parking lane and three 11-foot wide<br />

travel lanes. The 20-foot wide parking lane will allow vehicles to double park as<br />

necessary to unload passengers during the peak periods without blocking the travel<br />

lanes. The lane adjacent to the parking lane will accommodate vehicle<br />

maneuvering and, as a result, will have a lower vehicle throughput than the outer<br />

travel lanes.<br />

The departures curbside length will be 790 feet, meeting the requirement for<br />

providing LOS C operations during peak periods. LOS C operations will allow double<br />

parking on up to 40 percent of the curb. The required curb length assumes only<br />

private vehicle, taxicab, and for-hire shuttle and limousine passenger drop-off, and<br />

all other commercial vehicle drop-off will occur at the commercial vehicle plaza.<br />

A 20-foot sidewalk/curb will be provided for passenger loading between the<br />

roadway and terminal building.<br />

Figure 6.2-2<br />

DEPARTURES LEVEL<br />

DRAFT<br />

Source:<br />

HNTB<br />

Landrum & Brown Page 181<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The arrivals curb is located on the lower level adjacent to baggage claim and is<br />

depressed 10 feet below grade adjacent to the new terminal building. As shown on<br />

Figure 6.2-3, Arrivals Level, the arrivals roadway will be four lanes comprised of<br />

one 20-foot wide parking lane and three 11-foot wide travel lanes. The 20-foot<br />

parking lane will allow vehicles to double-park as necessary to load passengers<br />

during the peak periods without blocking the travel lanes. The lane adjacent to the<br />

parking lane will accommodate vehicle maneuvering and, as a result, will have a<br />

lower vehicle throughput than the outer travel lanes. Two additional bypass lanes<br />

are provided east of the curbside roadway. These lanes are separated by a 10 foot<br />

median serving as a landing for the upper level roadway columns.<br />

The arrivals curbside length will be 895 feet, meeting the requirement for providing<br />

LOS C operations during peak periods. LOS C operations will allow double parking<br />

on up to 40 percent of the curb. The required curb length assumes only private<br />

vehicle passenger pick-up and all commercial vehicle pick-up will occur at the<br />

commercial vehicle plaza. A 20-foot sidewalk/curb for passenger waiting and<br />

loading will be provided between the roadway and terminal building.<br />

Figure 6.2-3<br />

ARRIVALS LEVEL<br />

DRAFT<br />

Source:<br />

HNTB<br />

Landrum & Brown Page 182<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.2.1.4 Commercial Vehicle Access Roadway<br />

A dedicated commercial vehicle access roadway will be provided on the east side of<br />

the site with direct access to the commercial plaza within the garage. This roadway<br />

will be two lanes in each direction to provide sufficient capacity and prevent slower<br />

moving buses from blocking other vehicles. The entrance to the commercial<br />

roadway is off Cookingham Drive immediately prior to the parking entrance and<br />

would be restricted to commercial vehicles and FAA traffic only. The inbound and<br />

outbound lanes will traverse the FAA ATCT parking areas with the outbound lanes<br />

connecting to the terminal outbound roadway just past the parking exit plaza.<br />

To maintain the CUP and Police Building, the commercial roadway would be located<br />

17.4 feet onto the south side of the FAA ATCT parking area. This offset would allow<br />

an 8-foot walkway on the north side of the Police Building to be maintained along<br />

with a new exit from the FAA ATCT parking area between the building and<br />

Commercial Roadway.<br />

The commercial plaza will have a maximum 5 percent embankment to allow buses<br />

to make the ascent/descent in snow and icy conditions, and allow snow removal<br />

equipment to clear snow.<br />

6.2.1.5 Loading Docks<br />

A primary loading dock will be provided on the north side of the New <strong>Terminal</strong> for<br />

concessions delivery and trash collection. Dedicated access to this dock will be<br />

provided from Paris Street along Athens Avenue, which would be upgraded and<br />

extend to the New <strong>Terminal</strong>. It is assumed that concession deliveries would be<br />

made to a central receiving location and then brought to the New <strong>Terminal</strong> loading<br />

dock in box trucks. However, space will be provided north of the dock to allow a<br />

53-foot tractor-trailer to turn and back into the dock or turn to leave if necessary.<br />

DRAFT<br />

A secondary loading area will be provided on the south side of the building and<br />

accessed from the south end of the lower level roadway but would be restricted to<br />

parking for authorized employees or deliveries by small vehicles.<br />

Truck loading/unloading could not occur here due to having to traverse the lower<br />

level curbside roadway and make a tight 180-degree turn to access the<br />

dock/parking area.<br />

6.2.1.6 FAA Air Traffic Control Tower Access<br />

Access for vehicular traffic will be provided to the FAA ATCT site along the<br />

commercial vehicle roadway. Direct access into the site will be provided from the<br />

inbound commercial vehicle lanes with an entrance on the northeast end of the site.<br />

Egress will be provided from the west end of the site with an exit lane connecting to<br />

the southwest corner, traversing under the commercial roadway adjacent to the<br />

surface parking access roadway and connecting to the south side of the outbound<br />

commercial lanes when the vehicles reach ground level. This allows FAA employees<br />

and visitors direct ingress and egress to the site without going through the public<br />

Landrum & Brown Page 183<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

parking entry or exit plazas. As described in Section 6.2.1.4, to maintain the CUP<br />

and Police Building, the commercial roadway would be located 17.4 feet on the<br />

south side of the FAA ATCT parking area.<br />

6.2.1.7 Roadway Phasing<br />

The interim roadway phasing, as depicted in Figure 6.2-4, Roadway Phasing,<br />

will provide a contiguous area for terminal, garage, and utility construction to occur<br />

for as long as possible while maintaining operations and vehicle access at<br />

<strong>Terminal</strong>s B and C. It is expected that the major vehicle movements remain freeflow<br />

with limited stop control on the minor movements. As depicted, inbound traffic<br />

flow will be provided along the east portion of International Circle with a temporary<br />

connection from Cookingham Drive to International Circle. Direct access for<br />

vehicles to <strong>Terminal</strong>s B and C from International Circle will be provided via the<br />

existing bridges. These movements would be free flow with no crossing traffic.<br />

Outbound traffic from <strong>Terminal</strong> B would follow International Circle but ramp down,<br />

traverse the edge of the Circle Lot connecting to Bonn Circle, pass under the<br />

<strong>Terminal</strong> C access bridges, and merge with Cookingham Drive along the planned<br />

terminal exit roadway. In order to maintain free-flow operations from <strong>Terminal</strong> C,<br />

the outbound <strong>Terminal</strong> C traffic would use International Circle in the opposite<br />

direction of the inbound traffic with a barrier dividing the traffic flows.<br />

A roadway connection between <strong>Terminal</strong> B and C will be provided along<br />

International Circle in the north direction to allow commercial vehicles to drop-off<br />

and pick-up at both terminals.<br />

DRAFT<br />

In order to maintain access to <strong>Terminal</strong> B during construction, the south wing of the<br />

parking garage would be phased last and completed once <strong>Terminal</strong> B operations are<br />

moved.<br />

As terminal parking will be limited during construction, every effort should be made<br />

to keep the Circle Lot, between <strong>Terminal</strong>s B and C and north of <strong>Terminal</strong> C,<br />

operational through construction. There would be no connection between parking<br />

lots due to the outbound <strong>Terminal</strong> B traffic flow and the new parking exit, would<br />

need to be provided in the portion adjacent to <strong>Terminal</strong> C. Access to the portion of<br />

the Circle Lot between <strong>Terminal</strong>s B and C will be provided via a ramp from the<br />

<strong>Terminal</strong> B access. Access to the portion of the Circle Lot adjacent to <strong>Terminal</strong> C<br />

will be provided from the curbside exit.<br />

During construction, return-to-terminal traffic will use the Paris Street overpass or<br />

the newly constructed return-to-terminal roadway beyond the terminal complex.<br />

FAA traffic has direct ingress from International Circle, but during construction<br />

would also exit to International Circle in the south flow direction, and use the<br />

connector prior to the <strong>Terminal</strong> B curb entrance to turn and merge with the<br />

<strong>Terminal</strong> B exiting traffic.<br />

Landrum & Brown Page 184<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.2-4<br />

ROADWAY PHASING<br />

Source:<br />

HNTB<br />

6.2.2 PARKING<br />

The recommended landside concept includes a six level parking structure and an<br />

approximately 2,400 space surface parking area east of the garage. The plan<br />

maintains the existing airfield lighting vault and FAA ATCT facility, provides space<br />

for a new central utility plant adjacent to the exit plaza, maintains the existing<br />

<strong>Terminal</strong> B and C garages, and allows the existing CUP and Police Building to be<br />

maintained during construction and beyond if desired. Specific components of the<br />

plan are described below.<br />

6.2.2.1 Garage<br />

DRAFT<br />

The proposed new garage footprint has been planned to preserve the airfield<br />

lighting vault and FAA ATCT facility sites, and would be constructed 39 feet west of<br />

the existing police building allowing it to be maintained during construction.<br />

The offset will provide a 7.5-foot walkway to maintain access to the west side of the<br />

police building and an access roadway for the surface parking area between the<br />

Landrum & Brown Page 185<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

walkway and garage. Sufficient space will be provided to allow excavation during<br />

construction of the lower levels of the garage while maintaining the police building<br />

using standard construction practices of excavation slopes.<br />

The garage will be six-levels, two levels below-grade, one at-grade, and three<br />

above-grade to maintain views over the garage from the arrivals level of the<br />

terminal building. There will be three main sections to conform to the circular<br />

alignment of the terminal and roadway system; however, each of these sections<br />

would connect and vehicles would circulate seamlessly between them. The garage<br />

will be 350 feet deep with the north wing 468 feet long, the central section 588 feet<br />

long, and the south wing 468 feet long. Area is available for expanding the north<br />

and south wings on either side of the garage.<br />

Vehicles would enter the garage at the third floor and circulate either up or down to<br />

find parking. External helices will be provided for primary entry and exit flows with<br />

the entry flow through the north helix and exit flow through the south helix.<br />

Internal ramps will be provided in each wing to allow circulation between floors and<br />

a simplified search pattern. Direct access from the entry plaza to the ground level<br />

third floor will also be provided.<br />

A typical floor plan is depicted on Figure 6.2-5, Typical Garage Floor Plate,<br />

representing levels one through four that will provide 1,336 parking spaces per<br />

level. Parking aisles will follow an east-west configuration with the pedestrian flow<br />

toward a center circulation core and then east-west toward the building.<br />

The proposed floor plan for Level 5 is depicted on Figure 6.2-6, Garage Level 5<br />

Commercial Vehicle Floor Plate. Level 5 will serve as the commercial vehicle<br />

plaza and will also accommodate 1,016 parking spaces with 509 on each side of the<br />

commercial plaza. In order to maintain uninterrupted commercial vehicle flow, no<br />

connection between the north and south sides of the garage will be provided on<br />

Level 5. Vehicles would use the internal ramping system to access Level 4 or<br />

Level 6 to connect to the opposite side of the garage. Level 5 will serve as the<br />

primary pedestrian circulation to and from the terminal and provide moving<br />

walkways on either side of the commercial plaza to facilitate pedestrian movement<br />

through the garage.<br />

DRAFT<br />

The proposed floor plan for Level 6 is depicted on Figure 6.2-7, Garage Level 6<br />

Upper Floor Plate. Level 6 will be the top floor of the garage and provide<br />

1,206 parking spaces with an open area above the commercial plaza to allow<br />

sunlight to reach the plaza and exhaust fumes to escape. The opening will provide<br />

added height to the commercial plaza preventing it from feeling constricted.<br />

A connection between the north and south sides of the garage will be provided on<br />

both the east and west ends allowing vehicles to circulate between areas.<br />

Landrum & Brown Page 186<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 187<br />

April 2013<br />

Figure 6.2-5<br />

TYPICAL GARAGE FLOOR PLATE<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 188<br />

April 2013<br />

Figure 6.2-6<br />

GARAGE LEVEL 5 COMMERCIAL VEHICLE FLOOR PLATE<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 189<br />

April 2013<br />

Figure 6.2-7<br />

GARAGE LEVEL 6 UPPER FLOOR PLATE<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The space counts for each floor of the garage, as depicted on Figures 6.2-5, 6.2-6,<br />

and 6.2-7, are summarized on Table 6.2-1, New Garage Parking Space<br />

Summary. A total of 7,566 parking spaces are depicted; however, this number<br />

will reduce slightly as handicap parking spaces are added.<br />

Table 6.2-1<br />

NEW GARAGE PARKING SPACE SUMMARY<br />

FLOOR<br />

SPACE COUNT<br />

First 1,336<br />

Second (Tunnel Connection) 1,336<br />

Third (Ground) 1,336<br />

Fourth 1,336<br />

Fifth (Commercial Plaza, Bridge Connection) 1,016<br />

Sixth 1,206<br />

Total 7,566<br />

Note:<br />

Based on typical floor plans shown in Figures 6.2-5, 6.2-6, and 6.2-7 and does not count<br />

lost space for ADA parking stalls.<br />

The Americans with Disabilities Act (ADA) defines a minimum required number of<br />

handicap accessible parking spaces based on the size of the parking facility.<br />

The minimum requirement per the ADA Accessibility Guidelines, as amended in<br />

September 2002, is provided in Table 6.2-2, Minimum Accessible Parking<br />

Space Requirement. To meet ADA requirements, one of every eight accessible<br />

spaces, but not less than one must be van accessible with an adjacent access aisle.<br />

In accordance with these requirements the depicted parking garage would require<br />

86 accessible parking spaces with 11 of these being van accessible. Accessible<br />

parking stalls should be provided in each parking facility available to ensure equal<br />

access to all parking rates and types of parking offered at the airport.<br />

DRAFT<br />

Table 6.2-2<br />

MINIMUM ACCESSIBLE PARKING SPACE REQUIREMENT<br />

TOTAL PARKING SPACES IN MINIMUM REQUIRED NUMBER OF ACCESSIBLE<br />

LOT OR GARAGE<br />

SPACES<br />

0-25 1<br />

26-50 2<br />

51-75 3<br />

76-100 4<br />

101-150 5<br />

151-200 6<br />

201-300 7<br />

301-400 8<br />

401-500 9<br />

501-1,000 2% of total<br />

1,001 and over 20 plus 1 for every 100 or fraction of 100 over 1,000<br />

Source: Americans with Disabilities Act Accessibility Guidelines as amended September 2002.<br />

Landrum & Brown Page 190<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The primary pedestrian route to the New <strong>Terminal</strong> will be on Level 5 of the garage.<br />

Moving walkways will be provided on either side of the commercial vehicle plaza to<br />

aid pedestrian movement between the backs of the garage and two pedestrian<br />

bridges connecting to the terminal on either side of the commercial vehicle plaza.<br />

Pedestrians at all levels of the garage will be directed to this level to access the<br />

pedestrian bridges. A secondary terminal connection will also be provided via two<br />

tunnels located on Level 2 of the garage for those parking in the front (west)<br />

portion of lower levels.<br />

Three primary vertical circulation cores will be provided and located at the front,<br />

center, and back of the garage. The back circulation core is on the south end of the<br />

central portion of the garage providing vertical access to the pedestrian walkways<br />

on Level 5 for those parking in the surface lot. Two central circulation cores, one<br />

on each side of the commercial plaza will provide primary vertical access to Level 5<br />

for those parking in the central or back portions of the garage. Each circulation<br />

core will consist of two elevators and a stairwell. Vertical circulation will also be<br />

provided at the front of the garage adjacent to the pedestrian bridges and tunnels<br />

on either side of the commercial vehicle plaza. A set of up/down escalators<br />

between each floor of the garage and three elevators will be provided on each side<br />

of the plaza. The tunnels on Level 2 and bridges on Level 5 will allow passengers to<br />

walk between the garage and terminal with a minimum of one level change.<br />

Table 6.2-3, Parking Design <strong>Criteria</strong>, lists the criteria used for the garage floor<br />

plans. Parking bays are depicted at a minimum of 62 feet, to match existing<br />

facilities at KCI, with a desired stall width of 9 feet to allow sufficient room to<br />

unload passengers and baggage from vehicles (8.5 feet is the minimum allowable<br />

stall width for this facility to maintain acceptable level of service). The column grid<br />

depicted is 63 feet by 27 feet allowing structural columns to be located between<br />

parking spaces without compromising the parking space depth. The column<br />

spacing would remain the same beneath the commercial plaza but the floor slab<br />

depth would increase from 30 inches to 36 inches. The floor-to-floor height is also<br />

shown as 12 feet on a typical level with 14 feet provided on the commercial vehicle<br />

level to allow extra clearance for commercial vehicles. Emergency vehicles would<br />

be restricted to the commercial plaza on the fifth floor of the garage and snow<br />

removal vehicles are also only assumed to be required on the fifth floor and roof, as<br />

necessary. Access would be provided for trucks to conduct maintenance and<br />

repairs.<br />

DRAFT<br />

An area may be reserved for priority parking near the terminal walkways on Level 5<br />

and if desired, higher fees could be charged for these spaces. This would provide a<br />

direct connection to the terminals and access to the passenger check-in and<br />

baggage check facilities at the commercial vehicle plaza. Spaces near the bridges<br />

on Level 5 and tunnels on Level 2 could be utilized for handicap accessible parking.<br />

Landrum & Brown Page 191<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 6.2-3<br />

PARKING DESIGN CRITERIA<br />

Parking bay<br />

PARAMETER<br />

Parking space width (recommended shown)<br />

Parking space width (minimum)<br />

Parking garage column grid depicted<br />

Emergency vehicle access<br />

Snow removal vehicle access<br />

Typical floor-to-floor height depicted<br />

Commercial plaza level floor-to-floor height<br />

depicted<br />

CRITERIA<br />

62 feet<br />

9 feet<br />

8.5 feet<br />

63 feet by 27 feet<br />

Only Level 5 (commercial plaza)<br />

Only Level 5 (commercial plaza);<br />

Level 6 (roof) if covering not provided<br />

12 feet<br />

14 feet<br />

Source:<br />

Team recommendation with input from KCAD.<br />

6.2.2.2 Surface Parking<br />

Surface parking is provided in the area east of the garage and south of the FAA<br />

ATCT providing approximately 2,462 parking spaces with removal of the existing<br />

CUP/Police Building and 2,360 parking spaces if the building remains. Within this<br />

lot a minimum of 35 handicap accessible spaces and five van accessible spaces<br />

must be provided. Pedestrian access to the terminal is provided through level 5 of<br />

the parking garage with elevators on the back and center of the garage to provide<br />

vertical circulation to reach level 5 from the surface lot. Parking bays are depicted<br />

at a minimum of 62 feet to match existing facilities at KCI. A desired width of<br />

9 feet (8.5 feet is considered the minimum allowable width) will allow sufficient<br />

room to unload passengers and baggage from vehicles.<br />

DRAFT<br />

6.2.2.3 Entry and Exit Plazas<br />

The primary entrance to the parking garage and surface lot is provided from the left<br />

side of the terminal entrance roadway before the new terminal and parking garage.<br />

After branching off the main terminal access roadway the parking entry splits to<br />

separate entrances for the garage and surface lot. The entrance plaza queue area<br />

would also serve as a screening area for vehicles entering the parking garage<br />

during high threat levels and a connection back to the terminal access roadway will<br />

be provided for vehicles that do not wish to be searched.<br />

A secondary dual lane access to the garage will be provided after the departures<br />

curbside to serve those that want to enter the parking garage after dropping-off<br />

passengers or those that might access the terminal roadway from Paris Street<br />

ramp, which merges with the terminal access roadway beyond the main parking<br />

entrance.<br />

Landrum & Brown Page 192<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Plaza sizing was based on a projected hourly design volume and estimated service<br />

rate for each entry/exit lane. The hourly design volume was determined by<br />

reviewing the March 2012 peak hour parking entry and exit volumes for each<br />

facility. The combined hourly volumes for the existing <strong>Terminal</strong>s A, B, and C<br />

garages were used for the New <strong>Terminal</strong> garage entry and the Circle Lot volumes<br />

were used for the surface lot entry. Combined terminal garages and Circle Lot peak<br />

hour exit volumes were used for a combined exit plaza. The March 2012 peak hour<br />

entry/exit volumes for each facility were adjusted to represent the peak transaction<br />

month of July for the garages and October for the Circle Lot. These adjusted<br />

volumes were projected to 2030 based on the forecast growth in origin and<br />

destination passengers. The volumes were then increased relative to the difference<br />

in the required parking spaces and the number of parking spaces to be provided in<br />

the proposed facilities to represent the maximum volume for the initial build.<br />

This volume was then divided by a service rate of 0.85 to account for surges within<br />

the peak hour resulting in the peak hour design volume reported in Table 6.2-4,<br />

Parking Plaza Sizing.<br />

The number of entry and exit lanes shown in Table 6.2-4, Parking Plaza Sizing, was<br />

determined by the number of lanes required to accommodate the peak hour design<br />

volume with the design throughput for each lane. The design throughput assumes<br />

a capacity associated with unfamiliar drivers to represent the portion of airport<br />

parking users who are infrequent and have slower processing times than frequent<br />

users such as employees or frequent travelers. The entry lanes assume a push<br />

button ticket dispenser with unfamiliar user capacity of 250 vehicles per hour. Use<br />

of alternate equipment could result in different throughput capacity. Four entry<br />

lanes are required for the garage and two for the surface parking lot. Five garage<br />

entry lanes are recommended to provide for the reduction of one lane taken out of<br />

service for repairs.<br />

DRAFT<br />

The exit plaza will be sized to accommodate both the garage and surface parkers<br />

and a gate would be provided between the lots allowing garage patrons to exit<br />

through the surface lot but prevent surface parkers from trying to park in the<br />

garage. The number of exit lanes was calculated for 100 percent pay-on-foot with<br />

an unfamiliar user service rate of 200 vehicles per hour and 100 percent manned<br />

cashier stations with an unfamiliar user service rate of 100 vehicles per hour.<br />

Six lanes would be required if parking is 100 percent pay-on-foot while twelve lanes<br />

would be required if all exit booths are staffed with cashiers. Pay-on-foot has the<br />

fastest transaction time because the ticket is coded at a pay station within the<br />

parking area and entered into the machine at the exit lane raising the gate arm<br />

when the ticket is processed requiring no additional interaction. Alternate<br />

automated transaction options such as machine read credit-card transactions or<br />

credit card in/out may be used and would have a service rate/throughput capacity<br />

between pay-on-foot and cashier. A combination of both automated and cashier<br />

booths at the exits is recommended to allow flexibility in the future (cashier booths<br />

can be equipped for automated use when not staffed). The ground access site plan<br />

depicts the maximum 12 lanes to reserve space for maximum flexibility during<br />

design. When a parking revenue control system vendor is chosen, specific design<br />

capacities will be provided for their specific equipment and the recommended<br />

number of lanes can be refined as necessary.<br />

Landrum & Brown Page 193<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Table 6.2-4<br />

PARKING PLAZA SIZING<br />

TYPE<br />

Entry Garage<br />

Push Button<br />

Dispenser<br />

Entry Surface Lot<br />

DESIGN<br />

THROUGHPUT<br />

PER LANE<br />

PEAK HOUR<br />

DESIGN VOLUME<br />

(WITH 0.85<br />

SERVICE RATE)<br />

REQUIRED<br />

NUMBER OF<br />

LANES<br />

RECOMMENDED<br />

NUMBER OF<br />

LANES<br />

250 veh/hr 830 veh/hr 4 lanes 5 lanes<br />

Push Button<br />

250 veh/hr 255 veh/hr 2 lanes 2 lanes<br />

Dispenser<br />

Exit Garage and Surface<br />

Note:<br />

Sources:<br />

Pay-on-foot 200 veh/hr 1,115 veh/hr 6 lanes<br />

Cashier<br />

(variable<br />

fee)<br />

100 veh/hr 1,115 veh/hr 12 lanes 12 lanes<br />

Veh/hr = vehicles per hour<br />

Design throughput capacity, Institute of Transportation Engineers, Traffic Engineering Handbook<br />

sourcing Weant and Levinson, Parking; peak hour volumes and lane requirements, HNTB analysis based<br />

on KCAD parking data.<br />

6.2.2.4 Existing Garages B and C<br />

The existing <strong>Terminal</strong> B and C garages would be maintained with connections to the<br />

New <strong>Terminal</strong> loop roadway. The existing <strong>Terminal</strong> B garage, which provides<br />

2,006 parking spaces, would serve as a self-park public garage with a walkway to<br />

the New <strong>Terminal</strong>. The existing <strong>Terminal</strong> C garage which provides 2,258 parking<br />

spaces is envisioned to serve as space for valet parking services, such as vehicle<br />

storage, or employee parking.<br />

6.2.3 COMMERCIAL VEHICLES<br />

Taxis, limos, and for-hire shuttles (such as SuperShuttle) would be allowed to<br />

drop-off passengers on the departures curb. All commercial vehicles including taxi,<br />

limo, and for-hire shuttles passenger pick-up would occur at the commercial vehicle<br />

plaza described below. Access to the plaza would be provided by a dedicated<br />

commercial vehicle roadway described previously in Section 6.2.1, Roadways.<br />

6.2.3.1 Plaza<br />

DRAFT<br />

The commercial vehicle plaza will be 220 feet wide with four 260-foot long<br />

curbsides: one on each side and two island curbs. The outer curb lanes are 36 feet<br />

or three lanes wide and are reserved for bus and shuttle loading/unloading.<br />

The two island curb lanes are 24 feet or two lanes wide and would serve taxis,<br />

limos, and for-hire shuttles. A 20-foot sidewalk curb passenger loading/unloading<br />

area is provided on each side of the roadway and the island curbs are each 23 feet<br />

wide. Vehicle flow-through is inbound on the north side toward outer and inner<br />

north curbs and outbound on the south side through the inner and outer south<br />

Landrum & Brown Page 194<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

curbs. Vehicles can stop on either the north or south curbs, depending on the<br />

selected allocation plan, with vehicle loading/unloading from the right side of the<br />

vehicle at each curb. The plaza is designed to accommodate the turn radius of a<br />

45-foot bus along the outer curb lanes.<br />

Two potential allocation plans were developed to ensure adequate space and<br />

commercial vehicle operations. The commercial vehicle requirements were adapted<br />

for the operations associated with each allocation plan as shown in Table 6.2-5,<br />

Commercial Vehicle Plaza Sizing. Initial requirements were developed based on<br />

pick-up and drop-off activity for courtesy shuttles occurring at a single stop.<br />

However, the second allocation plan provides a separate area for courtesy shuttles<br />

to drop-off passengers reducing the dwell time required for picking-up passengers<br />

and changing the required curb length.<br />

Table 6.2-5<br />

COMMERCIAL<br />

DRAFT<br />

VEHICLE PLAZA SIZING (FEET)<br />

PROPOSED PROPOSED<br />

2030<br />

2030 ALLOCATION ALLOCATION<br />

REQUIREMENT REQUIREMENT DESIGNATED COMBINED<br />

VEHICLE (INDEPENDENT (COMBINED AREAS<br />

AREAS<br />

CLASSIFICATION OPERATIONS) OPERATIONS) (FIGURE 6.2-8) (FIGURE 6.2-9)<br />

Taxicab 125 125 160 160<br />

Limousine 150 150 200 200<br />

For-Hire Shuttle 105 105 160 160<br />

Rental Car Shuttle 110 110 120 100<br />

Hotel Shuttle 105<br />

120<br />

160<br />

140<br />

Off-Airport Parking 1 160<br />

(combined<br />

160<br />

(combined<br />

Blue Bus/ Economy<br />

110 pick-up)<br />

80<br />

pick-up)<br />

Park<br />

Charter Bus 60 60 Departures curbside<br />

Metro (public bus) 60 60 Departures curbside<br />

Combined Courtesy<br />

N/A 210 N/A 240<br />

Shuttle Drop-off<br />

Total 1,015 980 1,000 1,000<br />

Notes: 1 Off-Airport parking includes Park Air Express<br />

N/A = Not applicable<br />

Source: HNTB Analysis.<br />

Landrum & Brown Page 195<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The first allocation plan, Figure 6.2-8, Designated Drop-off/Pick-up Area,<br />

provides a designated area for type of shuttle (rental car, off-Airport parking, KCI<br />

economy parking, and hotel) where both passenger drop-off and pick-up activities<br />

occur. The taxis, limos, and for-hire shuttles would pick up passengers on the<br />

north and south inner islands in both plans.<br />

Figure 6.2-8<br />

DESIGNATED DROP-OFF/PICK-UP AREA<br />

Source: HNTB<br />

DRAFT<br />

Landrum & Brown Page 196<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The second allocation plan, Figure 6.2-9, Combined Drop-off Area, provides a<br />

combined passenger drop-off for rental car, off-Airport parking, KCI Economy<br />

Parking, and hotel/motel shuttles on the outer north curb. Passenger pick-up for<br />

these modes is provided on the south curb with rental cars on the west end of the<br />

curb and hotels/parking shuttles on the east end of the curb.<br />

Figure 6.2-9<br />

COMBINED DROP-OFF AREA<br />

Source:<br />

HNTB<br />

DRAFT<br />

6.2.3.2 Staging Area<br />

The commercial vehicle and taxi staging areas will be displaced by the surface<br />

parking area and relocated outside of the terminal area. An area within the existing<br />

surface lot on the south side of Paris Street near London Avenue could potentially<br />

be used for taxi, limo, for-hire shuttle, and charter bus staging with easy access to<br />

the commercial vehicle roadway entrance. An area of 0.32 acres are required for<br />

taxi parking in a traditional nose-to-tail configuration for dispatch to the terminal in<br />

addition to 0.92 acres for limousine and for-hire shuttle staging resulting in a total<br />

requirement of 1.24 acres for commercial vehicle staging.<br />

Landrum & Brown Page 197<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.3 <strong>Terminal</strong> Support and Collateral Development Site<br />

Plan<br />

6.3.1 AVIATION FUELING<br />

The purpose of the aviation fueling system is to supply fuel from the Tank Farm into<br />

the aircraft through an underground piping system. The piping system serves<br />

hydrant pits located at each aircraft parking position. Existing <strong>Terminal</strong>s A, B, and<br />

C include 90 gates. The New <strong>Terminal</strong> will have 37 narrowbody gates.<br />

6.3.1.1 Fuel Pipeline – Magellan - Bridging Concept Analysis<br />

The existing six-inch fuel supply pipeline is adequate to meet the New <strong>Terminal</strong> fuel<br />

demands. At the current delivery rate (22,000 gph), KCI fuel consumption could<br />

increase to 300,000 gallons per day (GDP) and still be below a 14-hour batch<br />

delivery. The coalescer filters and clay treater flow rates are rated for 800 gpm<br />

which exceeds the current delivery rate (367 gpm).<br />

6.3.2 HYDRANT FUELING BRIDGING CONCEPT ANALYSIS<br />

No new hydrant distribution mains are needed to meet the estimated peak flow rate<br />

for the New <strong>Terminal</strong>. Figure 6.3-1, Existing Fuel Site Plan, shows the existing<br />

fuel distribution mains. However, alterations to the existing mains will be needed<br />

for the proposed New <strong>Terminal</strong>.<br />

Phasing Plan for Construction: A fuel system phasing plan will need to be prepared<br />

to maintain airport operations during construction of the proposed New <strong>Terminal</strong>.<br />

DRAFT<br />

Fuel Back Feed: During construction of the New <strong>Terminal</strong>, one 18-inch hydrant<br />

main line will need to be installed on “landside,” out of the New <strong>Terminal</strong> work area<br />

as shown in Figure 6.3-2, Hydrant Distribution Plan Temporary <strong>Terminal</strong> B<br />

and C Fueling, to maintain fuel supply to <strong>Terminal</strong>s B and C and provide an<br />

independent supply to the south end of the New <strong>Terminal</strong> to improve system<br />

reliability. In addition, two new 16-inch hydrant lines will need to be installed to<br />

the north side of the new terminal. The 18-inch and two 16-inch lines will provide<br />

peak flow in two separate directions, meet the fuel demands of the new terminal,<br />

and provide back feed capability. Refer to Figure 6.3-3, Hydrant Distribution<br />

Plan – New <strong>Terminal</strong> Fueling, for more information. High-point vent (HPV) and<br />

low-point drain (LPD) pits will be installed throughout the system. It is assumed<br />

that Cathodic protection will be the sacrificial anode type and leak detection will be<br />

provided with the Hansa Consult portable type system which is currently in use.<br />

Landrum & Brown Page 198<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 199<br />

April 2013<br />

Figure 6.3-1<br />

EXISTING FUEL SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 200<br />

April 2013<br />

Figure 6.3-2<br />

HYDRANT DISTRIBUTION PLAN TEMPORARY TERMINAL B AND C FUELING<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 201<br />

April 2013<br />

Figure 6.3-3<br />

HYDRANT DISTRIBUTION PLAN – NEW TERMINAL FUELING<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

New Hydrant Distribution: The ADG III gates will include one hydrant pit located<br />

within 10 feet of the right aircraft wing fuel tank and behind the engine. ADG V flex<br />

gates will include one hydrant pit under each aircraft wing within ten feet of the fuel<br />

tank point of connection and behind the engine. Hydrant pit branch lines will<br />

alternate connections between the two 16-inch mains. Isolation valve vaults will be<br />

located to segregate the fuel pits into four main groups. Each vault will contain<br />

motor operated (MOV) double-block and bleed valves that are tied into the<br />

Emergency Fuel Shut-Off (EFSO) system. Upon activation of an EFSO button, the<br />

respective valves will isolate fuel to that group of hydrant pits. Exhibit F-3, Hydrant<br />

Distribution Plan – New <strong>Terminal</strong> Fueling, shows the locations of the new hydrant<br />

pits and valve vaults.<br />

6.3.1.1 Truck Fueling/Staging Facility Needs<br />

The fuel farm consists of one tanker truck/refueler load/offload position with a fuel<br />

flow rate equal to 1600 to 2000 gpm. Space and pipe connections are available to<br />

install one airport refueler load/offload station. No additional truck fueling or<br />

staging facility requirements is needed. Figure 6.3-4, Plan-Fuel Storage<br />

Expansion, shows the fuel farm layout with provisions for the future truck<br />

transportation refueler load/offload station and fuel tanks.<br />

Figure 6.3-4<br />

PLAN-FUEL STORAGE EXPANSION<br />

DRAFT<br />

Source:<br />

HNTB<br />

Landrum & Brown Page 202<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.3.1.2 Commercial Vehicle Staging and Delivery Layout<br />

The fuel farm is located to the north of the airport on Brasilia Avenue and Bern<br />

Street. The fuel farm control building has a parking lot capacity for 35 vehicles.<br />

Commercial vehicles stage at the fuel farm to make deliveries. No additional<br />

commercial vehicle staging is needed.<br />

6.3.1.3 Aviation Fueling Power and Communications<br />

Control valve vaults will be equipped with motor-operated double block and bleed<br />

plug valves, vault float switch for water/hydrocarbon detection, low and high flow<br />

terminal control valves, and fuel shutoff capability. This protocol will be followed<br />

for each of the new control valve vaults installed on the KCI airfield.<br />

The permanent valve control connectivity and power for all vault electrical<br />

equipment will be supplied from two dedicated Fuel Control Rooms at ramp level in<br />

the New <strong>Terminal</strong>. Each control valve vault will receive 208V power from the<br />

nearby apron level electrical rooms within the terminal. See Figure 6.3-5,<br />

<strong>Terminal</strong> Electrical & Telecomm Room Floor Plan, for locations. The alarm<br />

and controls for the valve vaults will connect back to the MDF through EFSO Control<br />

Panels via nearby apron level IDF rooms. See Figure 6.3-5, <strong>Terminal</strong> Electrical &<br />

Telecomm Room Floor Plan, for IDF and MDF room locations. In addition,<br />

connections will be made for full system monitoring at the Airport Fuel Farm.<br />

Emergency fuel shutoff pushbutton stations will be located in the vicinity of each<br />

aircraft gate. When activated, the EFSO station will stop the flow of fuel on that<br />

group of hydrant pits. Fuel flow shutdown will be accomplished by closing<br />

motor-operated valves in the associated control valve vault. Each EFSO pushbutton<br />

station will receive 120V power from the nearby apron level electrical rooms within<br />

the terminal. See Figure 6.3-5, <strong>Terminal</strong> Electrical & Telecomm Room Floor Plan,<br />

for locations. The alarm and controls for the various EFSO push button stations will<br />

connect from the EFSO push button station through a zone monitor card, located<br />

within three different EFSO control panels. The control panels will then<br />

communicate to their respective control valve vaults via an EFSO surge suppressor<br />

panel. The EFSO Control panels will be located on the exterior of the New <strong>Terminal</strong>,<br />

on the north, south and west. EFSO push button stations will be located at each<br />

gate.<br />

DRAFT<br />

Landrum & Brown Page 203<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.3-5<br />

TERMINAL ELECTRICAL & TELECOMM ROOM FLOOR PLAN<br />

Source:<br />

HNTB<br />

6.3.2 AIRFIELD DRAINAGE<br />

DRAFT<br />

The purpose of the apron drainage system is to capture stormwater runoff from the<br />

entire apron area, as well as intercept existing storm drainage pipes within the new<br />

apron limits, and convey it to the existing drainage basins.<br />

Any glycol-contaminated runoff will be collected and diverted to above ground<br />

storage tanks.<br />

The proposed terminal apron and associated taxilanes will drain by sheet flow to<br />

drainage structures constructed with the apron pavement. The New <strong>Terminal</strong><br />

configuration will result in a swale between the concourses and area inlets will be<br />

installed in the swales. The apron will also be graded in such a manner to isolate<br />

the centralized deicing pads and reduce the drainage area required to capture the<br />

glycol-contaminated runoff.<br />

The stormwater collection system for the terminal apron is designed for two<br />

separate systems: “clean” and “glycol contaminated” runoff. The “clean” runoff<br />

collection system is designed to intercept flows from normal rainfall events.<br />

This storm water is routed to the existing detention basin south of the Berlin<br />

Reservoir. The “clean” runoff collection system is denoted in Figure 6.3-6, Storm<br />

Drainage System.<br />

Landrum & Brown Page 204<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.3-6<br />

STORM DRAINAGE SYSTEM<br />

Source:<br />

HNTB<br />

DRAFT<br />

New trench drains located behind the aircraft parking positions at the terminal will<br />

collect stormwater runoff from areas where aircraft fueling operations are<br />

conducted and minimal gate deicing operations may occur. This is a high risk area<br />

for grease and oil pollutants.<br />

In an effort to improve water quality, the first flush (0.2 inch/hour rainfall) from the<br />

contamination high risk areas, those areas between the terminal and the trench<br />

drain, will be routed through oil/water separation devices prior to discharge into the<br />

storm sewer collection trunk lines. The oil/water separators are designed to reduce<br />

the grease and oil pollutant load to meet the permit requirements for the Kansas<br />

City International Airport.<br />

Periodic maintenance is required for the oil/water separators. As the oil level<br />

increases, the oil must be removed, typically with a vacuum truck. If the oil is not<br />

removed, the separation function will cease. Since the separators are located<br />

within the secure area, their maintenance will have to be coordinated with KCAD<br />

operations and maintenance personnel.<br />

Landrum & Brown Page 205<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Runoff from the taxilane portions of the apron, as well as from the centralized<br />

deicing pad, is not considered to be at high risk of containing grease and oil<br />

pollutants and will not pass through any oil water separation devices. Stormwater<br />

runoff in these areas is collected by a series of area inlets. The area inlets are<br />

connected by a series of pipes. The “clean” runoff may be conveyed in reinforced<br />

concrete pipes or other structures designed to withstand aircraft loadings.<br />

The “clean” runoff collected around the terminal will be conveyed to a trunk line<br />

located on the north side of the terminal. This trunk line will ultimately convey all<br />

“clean” storm water runoff to the existing detention basin and ultimately to the<br />

Berlin Reservoir.<br />

At this time all pipes are anticipated to gravity flow.<br />

6.3.3 GLYCOL COLLECTION AND STORAGE<br />

Collection of glycol-contaminated runoff begins with reducing the area of the<br />

application of deicing fluids, grading the area to collect the entirety of the deicing<br />

pad(s) and incorporating collection areas and pipe networks to convey the<br />

contaminated runoff to a retention facility for ultimate treatment or disposal.<br />

Figure 6.3-7, Glycol Collection System depicts the glycol-contaminated runoff<br />

collection and storage system.<br />

Figure 6.3-7<br />

GLYCOL COLLECTION SYSTEM<br />

DRAFT<br />

Source:<br />

HNTB<br />

Landrum & Brown Page 206<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Area inlets will be installed within the centralized deicing area to collect runoff.<br />

The inlets will be connected by HDPE (or similar) pipes and flow to the glycol trunk<br />

line. A diversion manhole will be installed at the beginning of each pipe located<br />

within a deicing pas. During deicing conditions, the runoff will flow to the glycol<br />

collection trunk line. During normal rainfall events, the runoff will be diverted to<br />

the “clean” runoff pipes.<br />

The pipes conveying runoff contaminated with deicing fluids should be high density<br />

polyethylene (HDPE) pipes (or similar materials) to avoid damage caused by the<br />

corrosive properties of the glycol fluids. Valves and manholes that are not<br />

susceptible to damage by glycol fluids shall be specified as well.<br />

Glycol-contaminated runoff will flow from the deicing pads to a dedicated glycol<br />

trunk line to above ground storage tanks located north of the terminal apron along<br />

Mexico City Avenue. The existing above ground storage tank adjacent to Paris<br />

Street may remain during the initial construction. This tank collects the<br />

glycol-contaminated runoff from the cargo and general aviation aprons. Once the<br />

ultimate apron is constructed, this tank will require relocation to the proposed tank<br />

location.<br />

It has not been determined how to dispose of the highly concentrated glycol runoff<br />

once they have been conveyed to the storage tanks. Runoff with high<br />

concentrations of glycols has been shipped to the wastewater treatment facility via<br />

truck for disposal, but there are more alternatives to repurpose the glycol fluids<br />

that could be a benefit to the environment, but also provide economic advantages<br />

to the KCAD.<br />

DRAFT<br />

Landrum & Brown Page 207<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 6.3-8, Combined Drainage Infrastructure, provides an overview of the<br />

combined drainage systems to understand how the two systems will operate.<br />

The glycol collection system will only be operable when the diversion manholes<br />

within a set of deicing pads are set to allow discharge to the glycol collection<br />

system.<br />

Figure 6.3-8<br />

COMBINED DRAINAGE INFRASTRUCTURE<br />

Source: HNTB<br />

DRAFT<br />

Landrum & Brown Page 208<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.3.4 DEICING SUPPORT FACILITIES<br />

Aircraft deicing will be conducted by a third party vendor once the new terminal is<br />

in operation. The development of a centralized location for management of the<br />

deicing operations is proposed north of the terminal apron, yet within close<br />

proximity to the deicing pads. The proposed location is shown in Figure 6.3-9,<br />

Glycol Support Facilities.<br />

Figure 6.3-9<br />

GLYCOL SUPPORT FACILITIES<br />

Source: HNTB<br />

DRAFT<br />

Landrum & Brown Page 209<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

This location shown in Figure 6.3-9, Glycol Support Facilities, is west of Mexico City<br />

Avenue. The facility should be centered on the existing AOA security fence to<br />

minimize unwarranted access to the AOA. At this location glycol vehicles will be<br />

maintained and loaded with deicing fluids. The support facilities include an<br />

administration building for management of the glycol operations and driver training.<br />

Parking for employees is located east of the security fence.<br />

Also on the landside is an access road for the delivery of glycol fluids. Delivery<br />

vehicles will remain outside the fence. Glycol fluids will be unloaded into storage<br />

tanks located within the AOA security fence. In addition to the glycol storage<br />

tanks, water hydrants will be installed to complete the glycol blending process prior<br />

to aircraft deicing application.<br />

A staging area for loading water and glycol fluid onto the deicing vehicles is<br />

depicted within the security fence so these vehicles are not required to leave the<br />

AOA at any time. Within the fence is a maintenance facility to repair and store<br />

deicing vehicles.<br />

Deicing vehicles will access the deicing pads via the proposed new service road.<br />

The service road will extend west from the staging area to Ottawa Avenue.<br />

6.3.5 AIRFIELD LIGHTING<br />

The proposed lighting system is based on the current apron and taxiway<br />

configuration described in Section 6.1. A detailed signage and lighting plan will be<br />

developed during the final design phase of the project.<br />

DRAFT<br />

The taxiway lighting system should provide a centerline lighting layout and circuitry<br />

to connect into the existing Taxiway A and Taxiway B centerline lights. Taxiway<br />

centerline lights should emit a steady burning green light with applicable variable<br />

intensity to match the existing taxiway centerline lighting system.<br />

Elevated taxiway edge lights will be installed in the paved shoulders adjacent to the<br />

terminal apron and Taxiways A and B. Taxiway edge lights should emit a steady<br />

burning blue light with applicable variable intensity to match the existing taxiway<br />

centerline lighting system.<br />

The current terminal aprons do not have centerline lighting. A taxilane centerline<br />

lighting layout and circuitry to delineate the taxilanes on the apron should be<br />

installed.<br />

Landrum & Brown Page 210<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

6.3.6 AIRFIELD LIGHTING VAULT<br />

The Existing Airfield Lighting Vault, and adjacent Airfield Lighting Power and<br />

Communications Manholes 1, 2, 3, and 4 will be left in place and protected. The<br />

Airfield Lighting Power and Communications Manholes and duct bank serving the<br />

North Airfield between existing manholes AP-1/AC-1 and AP-4/AC-4 will have to be<br />

relocated prior to demolition. A new 9w4-inch power duct bank and 2w4-inch<br />

communications duct bank will be installed around the new terminal and parking<br />

garage construction area. Refer to Figure 6.3-10, Proposed Electrical Site<br />

Plan, Figure 6.3-11, Existing Airfield Electrical Site Plan, and Figure 6.3-12,<br />

Proposed Airfield Electrical Site Plan, for proposed design details.<br />

Figure 6.3-10<br />

PROPOSED ELECTRICAL SITE PLAN<br />

Source: HNTB<br />

DRAFT<br />

Landrum & Brown Page 211<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 212<br />

April 2013<br />

Figure 6.3-11<br />

EXISTING AIRFIELD ELECTRICAL SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 213<br />

April 2013<br />

Figure 6.3-12<br />

PROPOSED AIRFIELD ELECTRICAL SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Cut-overs for all airfield lighting circuits will be done during airfield operations<br />

off-hours between the hours of 1:00 a.m. and 5:00 am, or in conjunction with<br />

scheduled Airfield Operations and maintenance shutdowns.<br />

For the Preferred Alternative, the existing (2) 1.5MW emergency generators in the<br />

CUP maintenance yard, will be relocated just North of the existing airfield electrical<br />

vault. All power feeds will be reconnected to existing 2000KVA, 4.16kV – 480/277V<br />

Stand-by Service Transformer, located at the southeast corner of the existing<br />

airfield lighting vault. In addition the KCP&L service transformer for the airfield<br />

lighting vault will have to be relocated as shown in Figure 6.3-13, Electrical<br />

Lighting Vault Plan, and Figure 6.3-14, Proposed Airfield Electrical Site<br />

Plan.<br />

Figure 6.3-13<br />

ELECTRICAL LIGHTING VAULT PLAN<br />

DRAFT<br />

Source:<br />

HNTB<br />

6.4 FAA Navigational Aids<br />

The existing navigational aids at KCI will not be impacted by the construction of the<br />

new terminal and associated airfield pavements. During design, a study will be<br />

conducted to determine the location of buried cables, within the construction limits,<br />

that must be protected to maintain the operation of all navigational aids.<br />

Landrum & Brown Page 214<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 215<br />

April 2013<br />

Figure 6.3-14<br />

PROPOSED AIRFIELD ELECTRICAL SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7. REFINE CONCEPTUAL TERMINAL BUILDING PLANS<br />

7.1 Conceptual <strong>Terminal</strong> and Concourse Plans<br />

7.1.1 CONCEPTUAL ALTERNATIVES AND OPTIONS<br />

The following three alternatives were developed for the <strong>Terminal</strong> A site, each of<br />

which are different in the way vehicles would approach and use the new terminal.<br />

Passenger experience is also unique in each alternative by requiring different levels<br />

of navigation from the drop-off curb to the security screening checkpoint.<br />

<br />

<br />

<br />

Alternative 1a and 1b: This alternative provides a traditional approach to the<br />

new terminal with the curbside drop-off and pick-up lanes of arriving and<br />

departing passengers have been separated on an upper and lower deck. The<br />

curbside lanes would run along the length of the main terminal entrance. To<br />

reduce congestion at the curbside lanes, commercial vehicles would use a<br />

separate route which is located in the parking garage structure and is aligned<br />

with the main gate level of the terminal. With this arrangement all<br />

passengers using the surface parking lot within International Circle, the<br />

parking garage, and commercial vehicle plaza would consolidate at the plaza<br />

in a conditioned space and enter the terminal at the gate level which would<br />

be located between the arriving and departing vehicular traffic.<br />

Whereas most terminals are arranged with departing passengers on the top<br />

level and arriving passengers at the bottom, Alternative 1a reverses this<br />

trend and has placed the arriving passengers at the top level. This<br />

arrangement would welcome all arriving passengers to Kansas City as they<br />

proceed from the gate level up to a grandiose baggage claim hall flooded<br />

with natural light and views out to the landscape of the Kansas City area. As<br />

a matter of concern, the traditional arrangement of arriving passengers<br />

located on the bottom level has been examined in Alternative 1b.<br />

DRAFT<br />

Alternative 2: This alternative would divide the main terminal processor into<br />

two terminals, which would allow a major airline to use as an exclusive<br />

terminal, if desired. The two terminals would share a common commercial<br />

vehicle plaza, but parking garages would have to be separated in this<br />

configuration. This arrangement of roadways and a commercial vehicle plaza<br />

would allow the main terminal processor to be two levels instead of three.<br />

Alternative 3: This alternative, while similar to Alternative 1a, would move<br />

the commercial vehicle plaza from the parking structure to the back side of<br />

the terminal processor. The major advantage to this alternative is that it<br />

places commercial traffic closer to the main terminal entrance.<br />

Landrum & Brown Page 216<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The layout of the conceptual terminal building at KCI is driven by airside and<br />

landside activities on a variety of levels. The airside activities (concourse,<br />

holdroom/gates) generally occur within the <strong>Terminal</strong> Concourse and landside<br />

activities (ticketing, security screening, and baggage claim) generally occur within<br />

the <strong>Terminal</strong> Processor as shown in Figure 7.1-1, Concept Diagram: <strong>Terminal</strong><br />

Processor and <strong>Terminal</strong> Concourse).<br />

Figure 7.1-1<br />

CONCEPT DIAGRAM: TERMINAL PROCESSOR AND TERMINAL CONCOURSE<br />

Source:<br />

L&B and Wellner Architects<br />

DRAFT<br />

Within the boundaries of the airfield and based on required setbacks and efficient<br />

aircraft circulation, the concourse layout has been defined as a bent ‘H’<br />

configuration. This configuration was defined early on in the study and was refined<br />

only slightly as the plans developed. Each of the terminal processor alternatives<br />

were combined with the typical ‘H’ configuration concourse layout and then<br />

modified as needed to meet the program requirements.<br />

When considering the layout of the terminal and site-wide components including<br />

vehicular traffic patterns and public parking, passenger convenience is important.<br />

Convenience factors include reducing passenger travel distance/time (from vehicle<br />

to departure gate), safety from other vehicles (cross traffic flows), protection from<br />

weather (rain, snow, etc.), and ease of navigation (traffic patterns and signage).<br />

Landrum & Brown Page 217<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7.1.2 CONCEPTUAL CONCOURSE SPACE ALLOCATION<br />

Apron Level 01<br />

The conceptual concourse consists of two levels, an Apron Level and a Gate Level.<br />

A partial third level is required for the U.S. Customs and Border Patrol (CBP)<br />

services and other functions that would be located adjacent to the Baggage Claim<br />

Hall on a third level of the <strong>Terminal</strong> Processor. An example of general space<br />

allocation can be seen in Figure 7.1-2, Conceptual Apron Level – <strong>Terminal</strong><br />

Concourse.<br />

Figure 7.1-2<br />

CONCEPTUAL APRON LEVEL – TERMINAL CONCOURSE<br />

DRAFT<br />

Source:<br />

L&B and Wellner Architects<br />

The conceptual terminal Apron Level is similar in function to the existing terminals<br />

at KCI. Space on the Apron Level would include non-public functions such as<br />

baggage handling; airline operation; concession support; security; and mechanical,<br />

electrical, and trash collection/disposal rooms. The Apron Level would be served by<br />

a central circulation corridor, approximately eleven feet wide, which is sufficient to<br />

handle pedestrian traffic and delivery or service vehicles such as electric powered<br />

utility carts. The Apron level would be intersected by three apron cross-through<br />

drives, each 20 feet wide, that are required for efficient operation of tugs and other<br />

support vehicles which utilize the apron.<br />

Landrum & Brown Page 218<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Vertical circulation cores have been placed along the main service corridor at<br />

locations that would allow back-of-house service to most of the retail spaces on the<br />

Gate Level. The circulation cores would also serve as public egress paths from the<br />

Gate Level above for both fire and hazardous weather events. Adjacent to each<br />

vertical circulation core would be retail support storage rooms where goods will be<br />

delivered and stored until the vendors move up to the Gate level.<br />

Outbound baggage handling rooms are central to the Apron Level layout. Bags are<br />

received from the TSA checked baggage screening room which is also located on<br />

the apron level within the boundaries of the terminal processor. The inbound<br />

baggage handling rooms are located closer to the terminal processor to minimize<br />

belt runs to the baggage claim hall.<br />

Mechanical rooms, which serve all levels of the terminal, are distributed throughout<br />

the Apron Level of the concourse. The balance of space is utilized for Airline<br />

Operations along with approximately 6,000 square feet to be used for Airport<br />

Operations<br />

Gate Level 02<br />

Located 13.5 feet above the Apron Level, the Gate Level of the concourse would<br />

provide passenger holdroom space for each gate, food and retail concessions,<br />

public restrooms, vertical circulation cores, and other airport function spaces.<br />

These other airport function spaces would be located along the perimeter of the<br />

concourse and would typically be contained within a thirty-foot deep structural bay<br />

module. All of these spaces would be served by a central circulation spine with<br />

moving walkways. As illustrated in Figure 7.1-3, Typical Gate Level – <strong>Terminal</strong><br />

Concourse, the corridors would be double loaded along the main concourse which<br />

would run in an east-west direction and along the north and south wings of the<br />

west corridor. The main corridor width would be sixty feet wide and the west<br />

corridor would be forty-five feet wide. The north and south wings of the east<br />

corridor would be single loaded and thirty feet wide.<br />

DRAFT<br />

The general layout of spaces within the Gate Level of the concourse is defined by<br />

the aircraft parking and the nodular concept of the concessions space. Food and<br />

retail concessions create a synergy of activity when they are grouped together in<br />

nodes instead of being sporadically distributed throughout the terminal. First and<br />

foremost, aircraft parking drives the location of the passenger boarding bridges.<br />

Off of each boarding bridge a holdroom of approximately 2,200 square feet would<br />

be provided. The aircraft parking layout and the resulting gate locations reinforce<br />

the main retail nodes at the intersections of the concourse. Secondary and tertiary<br />

nodes for concessions would be provided further down each concourse wing.<br />

Public restrooms modules that are 900 square feet each would be distributed<br />

throughout the concourse. Maximum passenger travel distance would be no more<br />

than two gate lengths, or approximately 150 feet.<br />

Landrum & Brown Page 219<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.1-3<br />

TYPICAL GATE LEVEL – TERMINAL CONCOURSE<br />

Source:<br />

L&B and Wellner Architects<br />

Arrival level 03<br />

CBP<br />

DRAFT<br />

The new terminal study requires planning for four international gates and each gate<br />

designated as international must provide sterile corridor access to the CBP services<br />

area. Connecting the gates to the CBP area would be accomplished by access to<br />

the third level shown in Figure 7.1-4, Arrival Level. Each international gate<br />

would contain a vertical circulation core consisting of an elevator and a staircase<br />

leading up to Level 3. The CBP would be located adjacent to the “ Sky Lobby “ hall<br />

and therefore, would provide a direct link for international passengers to exit the<br />

terminal while utilizing the same directional signage for transportation and lodging<br />

services. International passengers with connecting flights would return to the<br />

security screening checkpoint and then proceed to their connecting gate. The<br />

location of the CBP would also be in relatively close proximity to baggage conveyor<br />

systems needed to support the CBP.<br />

Landrum & Brown Page 220<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.1-4<br />

ARRIVAL LEVEL<br />

This illustration is a preliminary concept drawing and indicates sterile corridors for two international<br />

gates. Refer to Section 7.2 for developed plan showing four international gates.<br />

Source:<br />

L&B and Wellner Architects<br />

Baggage Claim Support<br />

DRAFT<br />

The opposite side of Level 3 would provide space within the concourse but it would<br />

be accessed from the Baggage Claim Hall. This area would include space for retail,<br />

baggage service offices, public restrooms, miscellaneous tenants, and facility<br />

support.<br />

7.1.3 CONCEPTUAL ALTERNATIVES 1A AND 1B<br />

A traditional vehicular approach was considered for this alternative. Traditional, in<br />

this definition, would require splitting the arrival and departure vehicular traffic<br />

onto separate levels, one on top of the other, in a counter-clockwise flow.<br />

In Alternative 1a the arrivals traffic is on top and the departures traffic is<br />

underneath. Conversely, in Alternative 1b, the Departures traffic is on top and the<br />

Arrivals traffic is underneath. It was further defined, that Commercial vehicular<br />

traffic would be separated to help relieve congestion at the curbside.<br />

All Commercial traffic except departure taxis and limousines would flow through the<br />

Landrum & Brown Page 221<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Level 5 of the parking garage which would be located midway between the Arrival<br />

and Departures level of the <strong>Terminal</strong> Building. Pedestrian traffic from the<br />

commercial vehicles and the parking garage would be consolidated at Level 5 of the<br />

parking garage and then proceed in an enclosed and air conditioned and heated<br />

walkway across the roadway and into the terminal on the main gate level of the<br />

terminal. See Figure 7.1-5, Alternative 1A, Level 01 – Departures.<br />

Figure 7.1-5<br />

ALTERNATIVE 1A, LEVEL 01 – DEPARTURES<br />

Source:<br />

L&B and Wellner Architects<br />

DRAFT<br />

Departing passengers that are being dropped off in private vehicles will enter the<br />

terminal at this level which is ten feet lower than the concourse apron level.<br />

Four curbside baggage check positions will be distributed along the entrance.<br />

Passengers can either check their bags or enter into the terminal and then proceed<br />

up one level to the Gate Level. Besides public restrooms, this is the only public<br />

function of the Apron Level. Behind the public circulation corridor is space for nonairline<br />

tenants. Entrance for these tenants is from the public circulation corridor.<br />

All other functions within the terminal processor except the central mechanical<br />

space will be elevated 10 feet to match up the concourse apron level.<br />

Delivery support for concessions will be located on the right side of the floor plan.<br />

The space includes a dock for deliveries and a temporary processing and storage<br />

area that will be located adjacent to the main circulation of the apron concourse<br />

level. On the opposite (left side of the plan) will be delivery and access for building<br />

support services such as maintenance, shop, and storage as needed for terminal<br />

functions. In the center will be TSA space for checked baggage screening, office,<br />

and break room.<br />

Landrum & Brown Page 222<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Entrance to the Gate level will be from conditioned bridges that span over the<br />

departure traffic below and will be connected to the parking garage at the<br />

commercial vehicle plaza level (Level 5). Passengers will also access the Gate level<br />

from the upper departures level lobby using stairs, escalators, or elevators.<br />

As shown in Figure 7.1-6, Alternative 1a, Level 02 – Gates, the lobby of the<br />

gate level will include vertical circulation connecting the levels above and below,<br />

ticketing for domestic and international flights, public restrooms, retail, and a main<br />

entrance into the security screening checkpoint queuing area.<br />

Figure 7.1-6<br />

ALTERNATIVE 1A, LEVEL 02 – GATES<br />

Source:<br />

L&B and Wellner Architects<br />

DRAFT<br />

This up-front approach for the security screening checkpoint will allow passengers<br />

with boarding passes to have quick and direct access from the terminal entrance.<br />

From that point, screened passengers will proceed directly into the main node of<br />

the terminal concourse. Working outwards from the security checkpoint entrance<br />

will be retail space so that all passengers have close visual contact with some retail<br />

before entering the checkpoint. Next will be public restrooms and then ticketing<br />

which will include a 45-foot deep space for kiosks banks and ticket queuing space.<br />

The security screening checkpoint will be flanked on both sides with an exit corridor<br />

for arriving passengers that do not have baggage to claim on the level above.<br />

Those passengers will be able to proceed across the bridge to the parking garage or<br />

go up a level for curbside pick-up.<br />

Behind the ticket counters will be space for Airline Ticket Offices. Other space on<br />

this level will include shafts for baggage conveyors systems that feed the baggage<br />

claim devices, the CBP space, and other support space for terminal functions.<br />

Landrum & Brown Page 223<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

As shown in Figure 7.1-7, Alternative 1a, Level 03 – Arrival / Baggage<br />

Claim, arriving passengers needing to claim baggage will proceed from the Gate<br />

Level up the vertical circulation (elevators, stairs, and escalators) to the Baggage<br />

Claim Hall located on the third level. There, passengers will pass the<br />

meeter/greeter area before moving to the baggage claim devices. The claim hall<br />

will include concessions, public restrooms, baggage service offices, and space for<br />

other tenants. All of these support spaces will be distributed along the back<br />

concourse which allows an open view to the curbside. Arriving passengers will then<br />

exit the terminal for curbside pick-up or proceed down to Level 2 and across the<br />

bridge for all other transportation options.<br />

Figure 7.1-7<br />

ALTERNATIVE 1A, LEVEL 03 – ARRIVAL / BAGGAGE CLAIM<br />

Source:<br />

L&B and Wellner Architects<br />

DRAFT<br />

Landrum & Brown Page 224<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The conceptual section will be cut through the middle of the building spline, starting<br />

at the parking structure shown on the left side, through the roadways, into the<br />

terminal processor, and then terminating at the beginning of the main concourse.<br />

The section illustrates that 23.5 feet will be needed between the departure curb and<br />

the gate level bridge leading to the garage in order to accommodate vehicular<br />

traffic, pedestrian bridge structure, and depth within the bridge structure needed to<br />

contain baggage conveyance systems. The distance between the apron and gate<br />

level of 13.5 feet will be determined by the greatest dimension allowed such that<br />

the slope of the boarding bridges when docked with aircrafts does not exceed the<br />

ADA ramp standards. The distance between the Apron and Gate level at the<br />

existing KCI terminal is 13.0 feet. See Figure 7.1-8, Alternative 1a, Conceptual<br />

Section Through Parking Garage, Roadway, Processor And Concourse.<br />

An optional tunnel from Level 2 of the parking garage leading to the departure<br />

lobby is shown in this illustration but has not been developed or included in refined<br />

building plans.<br />

Figure 7.1-8<br />

ALTERNATIVE 1A, CONCEPTUAL SECTION THROUGH PARKING GARAGE,<br />

ROADWAY, PROCESSOR AND CONCOURSE<br />

DRAFT<br />

Source:<br />

L&B and Wellner Architects<br />

Landrum & Brown Page 225<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Alternative 1b<br />

Alternative 1b is the converse of Alternate 1a. In this scheme the Arriving<br />

passenger pick-up and Bag Claim is on the lower level and the Departing<br />

Passengers are dropped off on the upper level. See Figure 7.1-9, Alternative 1b,<br />

Level 01 – Arrival / Baggage Claim.<br />

Arriving passengers needing to claim baggage will proceed from the Gate Level<br />

down the vertical circulation (elevators, stairs, and escalators) to the Baggage<br />

Claim Hall located on the lowest level, 10 feet below the concourse Apron level.<br />

There, passengers will pass the meeter/greeter area before moving to the baggage<br />

claim devices. The claim hall includes concessions, public restrooms, baggage<br />

service offices, and space for other tenants. The loading dock for retail deliveries is<br />

also on this level but is a back-of-house function. All of these support spaces will<br />

be distributed along the back concourse side which allows an open view to the<br />

curbside. Arriving passengers will then exit the terminal for curbside pick-up or<br />

proceed up to Level 2 and across the bridge for all other transportation options.<br />

This layout is very similar to Alternative 1a but with a different structural grid<br />

geometry. Entrance to the Gate level will be from conditioned bridges which span<br />

over the arrival traffic below and connected to the parking garage at the<br />

commercial vehicle plaza level (Level 5). Passengers will also come down from the<br />

departure level (above) using stairs, escalators, or elevators.<br />

Figure 7.1-9<br />

ALTERNATIVE 1B, LEVEL 01 – ARRIVAL / BAGGAGE CLAIM<br />

DRAFT<br />

Source:<br />

L&B and Wellner Architects<br />

Landrum & Brown Page 226<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The entrance lobby of the gate level will include vertical circulation connecting the<br />

levels above (departure drop-off) and below (arrivals), ticketing for domestic and<br />

international flights, public restrooms, retail, and a prominent entrance into the<br />

security screening checkpoint queuing area.<br />

This up-front approach for the security screening checkpoint will allow passengers<br />

with boarding passes to have quick and direct access from the terminal entrance.<br />

From that point, screened passengers will proceed directly into the main node of<br />

the terminal concourse. Working outwards from the security checkpoint entrance<br />

will be retail space so that all passengers have close visual contact with some retail<br />

before entering the checkpoint. Next will be public restrooms and then ticketing<br />

which will include a 45-foot deep space for kiosks banks, and ticket queuing space.<br />

The security screening checkpoint will be flanked on both sides with an exit corridor<br />

for arriving passengers that do not have baggage to claim on the level below.<br />

Those passengers will either proceed across the bridge to the parking garage or go<br />

down to the level below for curbside pick-up.<br />

Behind the ticket counters will be space for Airline Ticket Offices. Other space on<br />

this level will include shafts for baggage conveyor systems which will feed the<br />

baggage claim devices, the CBP space, and other support space for terminal<br />

functions. See Figure 7.1-10, Alternative 1b, Level 02 – Gates.<br />

Figure 7.1-10<br />

ALTERNATIVE 1B, LEVEL 02 – GATES<br />

DRAFT<br />

Source:<br />

L&B and Wellner Architects<br />

Landrum & Brown Page 227<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

As shown in Figure 7.1-11, Alternative 1b, Level 03 – Departure Level,<br />

departing passengers that are being dropped off in private vehicles will enter the<br />

terminal at this level. Three main entrances will be spaced along the front of the<br />

terminal. Passengers will enter into the main lobby and can either check bags at<br />

this location or proceed down to the gate level below. Walkways at each of the<br />

main entrances will span through the main lobby and lead to space for non-airline<br />

tenants. The center will contain TSA space for checked baggage screening, office,<br />

and break room.<br />

Figure 7.1-11<br />

ALTERNATIVE 1B, LEVEL 03 – DEPARTURE LEVEL<br />

Source:<br />

L&B and Wellner Architects<br />

DRAFT<br />

Landrum & Brown Page 228<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The conceptual section is similar to Alternative 1a and will cut through the middle of<br />

the building spline, starting at the parking structure shown on the left side, through<br />

the roadways, into the terminal processor, and then will terminate at the beginning<br />

of the main concourse. The section illustrates that 23.5 feet will be needed<br />

between the arrival curb and the gate level bridge leading to the garage to<br />

accommodate vehicular traffic, pedestrian bridge structure, and depth within the<br />

bridge structure needed to contain baggage conveyance systems. The distance<br />

between the apron and gate level of 13.5 feet will be determined by the greatest<br />

dimension allowed such that the slope of the boarding bridges when docked with<br />

aircrafts do not exceed the ADA ramp standards. See Figure 7.1-12, Alternative<br />

1b, Conceptual Section Through Parking Garage, Roadway, Processor, And<br />

Concourse.<br />

Figure 7.1-12<br />

ALTERNATIVE 1B, CONCEPTUAL SECTION THROUGH PARKING GARAGE,<br />

ROADWAY, PROCESSOR, AND CONCOURSE<br />

Source:<br />

L&B and Wellner Architects<br />

DRAFT<br />

Landrum & Brown Page 229<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7.1.4 CONCEPTUAL ALTERNATIVE 2<br />

Another way to approach the terminal processor is to split arrival and departure<br />

vehicular traffic into two separate wings, depending on the airline being used.<br />

In Alternative 2 the commercial vehicles will be separated and utilize a commercial<br />

plaza that is centered between the two-winged processor. This plaza will allow<br />

direct access into the terminal security screening checkpoint without having to<br />

cross roadways or travel through ticketing lobbies if passengers have boarding<br />

passes in hand and will eliminate the “bridge” level shown in Alternative 1.<br />

Departing passengers will be dropped off along two curbside lanes depending on<br />

the airline being used. This level will contain two separate lobby wings containing<br />

the ticket counters, kiosks, public restrooms and retail, and airline ticket offices.<br />

Between the two public lobbies will be space designated for mechanical systems,<br />

baggage handling, and checked baggage screening. Directly above the mechanical<br />

and baggage handling rooms will be the commercial vehicle plaza. Commercial<br />

vehicle passengers that need to use the ticket counter will determine which<br />

terminal wing to enter and then proceed down to the Apron level. Upon entering<br />

either lobby, passengers will check their bags and then proceed towards the<br />

concourse at which point they will circulate up to the gate level and arrive at the<br />

security screening checkpoint. See Figure 7.1-13, Alternative 2, Level 01 –<br />

Departures.<br />

Figure 7.1-13<br />

ALTERNATIVE 2, LEVEL 01 – DEPARTURES<br />

DRAFT<br />

Source:<br />

L&B and Wellner Architects<br />

Landrum & Brown Page 230<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Passengers coming up from the departure level below will be at the entrance to the<br />

security screening checkpoint. This is the same location where commercial vehicle<br />

passengers can enter the terminal if they do not need to go to the ticket counter.<br />

Passengers will proceed through the screening checkpoint and on to their assigned<br />

gate.<br />

Arriving passengers will flow through the exit corridors that are flanked on each<br />

side of the security screening checkpoint and then into the Baggage Claim Hall.<br />

From that point the passenger’s baggage will be claimed, if needed, and then will<br />

go on to passenger curbside pickup or the central commercial vehicle plaza located<br />

between the two terminal processor wings. See Figure 7.1-14, Alternative 2,<br />

Level 02 – Arrivals.<br />

Figure 7.1-14<br />

ALTERNATIVE 2, LEVEL 02 – ARRIVALS<br />

DRAFT<br />

Source:<br />

L&B and Wellner Architects<br />

7.1.5 CONCEPTUAL ALTERNATIVE 3<br />

The vehicular approach in Alternative 3 is similar to Alternative 1a. The departure<br />

drop-off traffic will be at the lowest level. The Gate level will be the next level and<br />

enclosed bridges will connect the gate level to the parking garage located across<br />

the roadway. Vehicles will pick up arriving passengers on the third level. The main<br />

difference in this alternative is the <strong>Terminal</strong> Processor will be separated from the<br />

<strong>Terminal</strong> Concourse and all commercial vehicles will drive between the Processor<br />

and Concourse at the arriving passenger (third) level. Departing commercial<br />

Landrum & Brown Page 231<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

vehicle passengers will enter the terminal and go down to the gate level and then<br />

to the security screening checkpoint, or they can continue down to the departure<br />

level and to the ticket counter. This is the only alternative where the commercial<br />

vehicle lane is not part of a plaza within the parking structure. See Figure 7.1-15,<br />

Alternative 3, Level 01 – Departures / Ticketing.<br />

Figure 7.1-15<br />

ALTERNATIVE 3, LEVEL 01 – DEPARTURES / TICKETING<br />

Source:<br />

L&B and Wellner Architects<br />

DRAFT<br />

Departing passengers that are being dropped off in private vehicles will enter the<br />

terminal at this level. Four curbside baggage check positions will be distributed<br />

along the entrance. Passengers can either check their bags at curbside or enter<br />

into the terminal lobby. At this level the terminal lobby will include ticket counters<br />

and kiosks, retail, public restrooms, and vertical circulation cores serving the levels<br />

above. Behind the ticket counters will be space for airline ticket offices.<br />

The interstitial space between the processor and the concourse will contain the<br />

main mechanical room. It will also contain delivery support for retail which is<br />

located on the right side of the floor plan. The space will include a dock for<br />

deliveries and a temporary processing and storage area that will be located<br />

adjacent to the main circulation of the apron concourse level. On the opposite side<br />

will be delivery and access for building support services such as maintenance, shop,<br />

and storage as needed for terminal functions.<br />

In this alternative shown in Figure 7.1-16, Alternative 2, Level 02 –<br />

Security/Gates, the TSA space for checked baggage screening, office, and break<br />

room will be pushed further into the terminal concourse.<br />

Landrum & Brown Page 232<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.1-16<br />

ALTERNATIVE 2, LEVEL 02 – SECURITY/GATES<br />

Source:<br />

L&B and Wellner Architects<br />

The entrance to the Gate level will be from conditioned bridges which span over the<br />

departure traffic below, and connected to the parking garage at the commercial<br />

vehicle plaza level (Level 05). Passengers will also access the Gate level from the<br />

lower departure level using stairs, escalators, or elevators.<br />

DRAFT<br />

The entrance lobby of the gate level will include vertical circulation connecting the<br />

levels above (baggage claim) and below (departure drop-off). Adjacent to this<br />

lobby will be the non-airline tenant space. Departing passengers will feed towards<br />

the concourse and directly into the security screening checkpoint. Arriving<br />

passengers will exit the concourse on each side of the screening checkpoint where<br />

they can proceed directly to the parking garage or up to the third level to claim<br />

baggage or use transportation services.<br />

Arriving passengers that come up to Level 3 will do so after passing underneath the<br />

commercial vehicle drive located on the back side of the terminal processor. Upon<br />

entering the third level at the meeter/greeter lobby, arriving passengers can exit to<br />

the commercial vehicle curbside, enter the baggage claim hall, or exit at the<br />

opposite side of the claim hall for non-commercial curbside pick-up.<br />

See Figure 7.1-17, Alternative 3, Level 03 – Arrival / Baggage Claim.<br />

This level will contain commercial vehicle curbside baggage check-in. It will also<br />

contain a baggage service office, retail, public restrooms, and terminal function<br />

space. Although the CBP facility will also be on this level, arriving international<br />

passengers would exit the facility by proceeding down to the gate level and then<br />

exit with other arriving passengers. See Figure 7.1-18, Alternative 3, Section<br />

Diagrams.<br />

Landrum & Brown Page 233<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.1-17<br />

ALTERNATIVE 3, LEVEL 03 – ARRIVAL / BAGGAGE CLAIM<br />

Source:<br />

L&B and Wellner Architects<br />

Figure 7.1-18<br />

ALTERNATIVE 3, SECTION DIAGRAMS<br />

DRAFT<br />

Source:<br />

L&B and Wellner Architects<br />

Landrum & Brown Page 234<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7.2 Refined Alternative 1B Building Plans<br />

Throughout the course of this study the alternatives described in Section 7.1 were<br />

analyzed and ranked against each other. The results led to the decision to refine<br />

Alternative 1B.<br />

7.2.1 LEVEL O1 DEPARTURE<br />

Refinement of the Apron Level Concourse:<br />

During Refinement, an adjustment was made to the aircraft parking layout, which<br />

included among other things, allocation for four international gates shown in<br />

Figure 7.2-1, Refined Alternative 1B Apron Level. Conflicts with aircraft<br />

taxiing at the existing KCI <strong>Terminal</strong> B then led to a slight adjustment in the lengths<br />

of the concourse wings. The south end of the east wing was shortened while the<br />

north end of the east wing was lengthened. The main circulation corridor has been<br />

maintained and the vertical circulation cores which include a stairwell and an<br />

elevator coordinate with the back-of-house retail spaces above.<br />

Space allocated for outbound baggage operations was reduced providing more<br />

space for mechanical rooms and Airport and airline operations. The distribution of<br />

mechanical rooms was reviewed and resized. There are a total of nine mechanical<br />

rooms which each containing two air handling units, chilled water pumps, exhaust<br />

fans, water heater, and air compressor. Vertical shafts from each mechanical room<br />

will be approximately 80 square feet each. The Emergency and Standby Generator<br />

Plant and the Domestic Hot Water Plant are placed at the south end of the east<br />

wing. Approximately 11,000 square feet is occupied by these functions.<br />

DRAFT<br />

Behind the public space of the departure lobby the TSA screening room was reoriented<br />

to accommodate equipment and baggage belt runs required for in-line<br />

baggage screening. TSA space has been provided adjacent to the screening facility<br />

and dedicated vertical circulation feeds into the security screening checkpoint<br />

located on the level above.<br />

Refinement of the Apron Level ”Sky Lobby”:<br />

Escalators, elevators, and stairs within the Sky Lobby of the departures level have<br />

been coordinated with the placement of the entrance vestibules and curbside<br />

baggage check-in podiums. Design Details can be seen in Figure 7.2-2, Refined<br />

Departure Level ”Sky Lobby”.<br />

Landrum & Brown Page 235<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 236<br />

April 2013<br />

Figure 7.2-1<br />

REFINED ALTERNATIVE 1B APRON LEVEL<br />

DRAFT<br />

Source: L&B and Wellner Architects


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.2-2<br />

REFINED DEPARTURE LEVEL ”Sky Lobby”<br />

Source: L&B and Wellner Architects<br />

7.2.2 LEVEL 02 GATES<br />

Refinement of the Gate Level Concourse:<br />

DRAFT<br />

As shown in Figure 7.2-3, Refined Alternate 1B Gate Level, the refinement of<br />

the aircraft parking layout resulted in a slight shortening of the main concourse.<br />

In addition, the south end of the east wing was shortened while the north end of<br />

the east wing was lengthened. The number of moving walkways in the main<br />

corridor was reduced and moved to the center of the spine. Not only does this<br />

allow for better pedestrian flow within the concourse but it moves the walkway pits<br />

out of the outbound baggage handling rooms below and into the ceiling space of<br />

the apron corridor. Vertical circulation down to the baggage claim hall has been<br />

enhanced with the addition of a grand staircase and elevators to supplement the<br />

escalators.<br />

Refinement of the Gate Level Ticket Lobby:<br />

Configuration of the ticket lobby did not change from the preliminary concepts.<br />

Vertical circulation cores were refined and coordinated with the levels above and<br />

below. Behind the ticket counters, shaft space was added for check-in bag belts<br />

that would turn back into the ticket counter back wall and then decline to the ceiling<br />

space of the Apron level. Airline Ticket Office space was adjusted to meet the<br />

program requirements. Design details can be seen in Figure 7.2-4, Refined Gate<br />

Level Ticket Lobby.<br />

Landrum & Brown Page 237<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 238<br />

April 2013<br />

Figure 7.2-3<br />

REFINED ALTERNATE 1B GATE LEVEL<br />

DRAFT<br />

Source: L&B and Wellner Architects


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.2-4<br />

REFINED GATE LEVEL TICKET LOBBY<br />

Source:<br />

L&B and Wellner Architects<br />

DRAFT<br />

Landrum & Brown Page 239<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Refinement of the Gate Level Screening Checkpoint Lobby:<br />

Boundaries of the Security Screening Checkpoint were increased slightly and the<br />

configuration of the checkpoint lanes changed slightly. A central passenger exit<br />

corridor was introduced to simplify wayfinding for arriving passengers. Mechanical<br />

shafts from the mechanical room below which are used to feed air to the lobby and<br />

spaces above have been added and are adjacent to the retail space at the entrance<br />

to the security checkpoint. Vertical circulation within the main lobby is refined and<br />

coordinated with the levels above and below. Design details can be seen in<br />

Figure 7.2-5, Refined Gate Level Screening Checkpoint Lobby.<br />

7.2.3 LEVEL 01 APRON/BAGGAGE CLAIM<br />

Refinement of the Apron Level:<br />

As shown in Figure 7.2-6, Refined Apron Level, many of the operational<br />

functions and building systems are housed in the apron level of the building.<br />

The layout of the apron level is similar to the conceptual layout. These functions<br />

include secure circulation, inbound baggage processing and claim, outbound<br />

baggage processing and screening, concessions storage and screening, airline<br />

operations and storage, and mechanicals for the building (i.e. HVAC, backup<br />

generators, trash, etc.). Publicly accessible support functions, such as bag claim,<br />

baggage service offices, and USO offices are also housed within the apron level.<br />

Refinement of the Apron Level Baggage Claim Hall:<br />

A total of six domestic baggage claim devices are needed for the Baggage Claim<br />

Hall. Passenger circulation flows from the bottom of the escalator/stairs, through a<br />

space for meters/greeters, and into the public circulation areas along the frontage<br />

of the facility. Other support spaces adjacent to the Claim Hall remain unchanged<br />

from the conceptual stage. The preferred layout is shown in Figure 7.2-7,<br />

Refined Apron Level Baggage Claim Hall.<br />

7.2.4 LEVEL 03 U.S. CBP<br />

DRAFT<br />

Refinement of the Arrival Level U.S. CBP:<br />

The refined plan for International flights shown in Figure 7.2-8, Refined Arrival<br />

Level U.S. CBP, includes up to four gates for arriving aircraft and an arrivals hall<br />

designed to maintain a high level of service while processing the arriving<br />

passengers. Immigration, Customs, Bag Claim and restrooms are all provided in<br />

one central area at the upper “Sky Lobby” level. In this concept, international<br />

passengers that are exiting the CBP would use stairs or elevators down to the<br />

Baggage Claim Hall, and then exit the terminal or return to the security screening<br />

checkpoint entrance for connecting flights.<br />

Landrum & Brown Page 240<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 241<br />

April 2013<br />

Figure 7.2-5<br />

REFINED GATE LEVEL SCREENING CHECKPOINT LOBBY<br />

DRAFT<br />

Source: L&B and Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 242<br />

April 2013<br />

Figure 7.2-6<br />

REFINED APRON LEVEL<br />

DRAFT<br />

Source: L&B and Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 243<br />

April 2013<br />

Figure 7.2-7<br />

REFINED APRON LEVEL BAGGAGE CLAIM HALL<br />

DRAFT<br />

Source: L&B and Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 244<br />

April 2013<br />

Figure 7.2-8<br />

REFINED ARRIVAL LEVEL U.S. CBP<br />

DRAFT<br />

Source: L&B and Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 245<br />

April 2013<br />

7.3 Conceptual <strong>Terminal</strong> Building Cross-Sections<br />

7.3.1 LONGITUDINAL SECTIONS<br />

DRAFT<br />

Figure 7.3-1<br />

SECTION THROUGH SPINE OF TERMINAL, LOOKING NORTH<br />

Source: Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 246<br />

April 2013<br />

Figure 7.3-2<br />

ENLARGED SECTION THROUGH SPINE OF TERMINAL, PROCESSOR<br />

DRAFT<br />

Source: Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 247<br />

April 2013<br />

Figure 7.3-3<br />

ENLARGED SECTION THROUGH SPINE OF TERMINAL<br />

DRAFT<br />

Source: Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 248<br />

April 2013<br />

Figure 7.3-4<br />

END OF CONCOURSE AT RETAIL NODE<br />

DRAFT<br />

Source: Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 249<br />

April 2013<br />

Figure 7.3-5<br />

SECTION THROUGH CONCOURSE<br />

DRAFT<br />

Source: Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 250<br />

April 2013<br />

7.3.2 TRANSVERSE SECTIONS<br />

Figure 7.3-6<br />

LOOKING BACK TO SECURITY SCREENING CHECKPOINT<br />

DRAFT<br />

Source: Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 251<br />

April 2013<br />

Figure 7.3-7<br />

SECTION THROUGH SINGLE LOADED CORRIDOR LOOKING BACK TO TERMINAL PROCESSOR<br />

DRAFT<br />

Source: Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 252<br />

April 2013<br />

7.4 Conceptual Building Mass Elevations<br />

7.4.1 TERMINAL ELEVATIONS<br />

DRAFT<br />

Figure 7.4-1<br />

SECTION THROUGH SINGLE LOADED CORRIDOR LOOKING BACK TO TERMINAL PROCESSOR<br />

Source: Wellner Architects


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 253<br />

April 2013<br />

7.5 Conceptual Illustrations<br />

7.5.1 EXTERIOR ILLUSTRATIONS<br />

DRAFT<br />

Figure 7.5-1<br />

EXTERIOR ILLUSTRATION – CONCEPTUAL TERMINAL AND PARKING STRUCTURE<br />

Source: L&B


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Figure 7.5-2<br />

EXTERIOR ILLUSTRATION – CONCEPTUAL PARKING STRUCTURE AND COMMERCIAL PLAZA ROOF<br />

Landrum & Brown Page 254<br />

April 2013<br />

DRAFT<br />

Source: L&B


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Figure 7.5-3<br />

EXTERIOR ILLUSTRATION – CONCEPTUAL PARKING STRUCTURE AND COMMERCIAL PLAZA - CUTAWAY<br />

Landrum & Brown Page 255<br />

April 2013<br />

DRAFT<br />

Source: L&B


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 256<br />

April 2013<br />

Figure 7.5-4<br />

EXTERIOR ILLUSTRATION – CONCEPTUAL APPROACH AT THE DEPARTURES LEVEL<br />

DRAFT<br />

Source: L&B


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Figure 7.5-5<br />

INTERIOR ILLUSTRATION – CONCEPTUAL MAIN CONCOURSE LOOKING TOWARD CONCESSIONS NODE<br />

Landrum & Brown Page 257<br />

April 2013<br />

7.5.2 INTERIOR ILLUSTRATIONS<br />

DRAFT<br />

Source: L&B


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 258<br />

April 2013<br />

Figure 7.5-6<br />

INTERIOR ILLUSTRATION – CONCEPTUAL TICKETING LEVEL - CUTAWAY<br />

DRAFT<br />

Source: L&B


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Figure 7.5-7<br />

INTERIOR ILLUSTRATION – CONCEPTUAL CONCOURSE AND CONCESSIONS NODE - CUTAWAY<br />

Landrum & Brown Page 259<br />

April 2013<br />

DRAFT<br />

Source: L&B


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7.6 New <strong>Terminal</strong> Mechanical & Electrical<br />

Improvements/Alternatives<br />

7.6.1 PROJECTED NEW TERMINAL IMPROVEMENTS/<br />

ALTERNATIVES:<br />

7.6.1.1 Heating Equipment<br />

The New <strong>Terminal</strong> will include a mechanical space for a hot water (HW) heating<br />

system as follows:<br />

<br />

HW Space Heating System: 600 horsepower (20,085 MBTU) natural<br />

gas-fired hot water boilers with 10:1 turn down burner ratio.<br />

HW Distribution: Primary-Secondary Flow HW distribution for space heating.<br />

HW<br />

DRAFT<br />

Supply and Return Temperatures: Supply temperature equals<br />

190 degrees Fahrenheit and Return equals 150 degrees fahrenheit at less<br />

than 60 psig pressure.<br />

Ancillary HW equipment: Water softener, chemical tanks (corrosion<br />

inhibitors), air separator, mixing valve and 5 psig natural gas supply to each<br />

boiler pressure regulating station.<br />

Domestic Hot Water (DHW) system: Natural gas-fired condensing boilers for<br />

large HW demands by restaurants and concessions. Electric unit heaters to<br />

be used for restrooms and miscellaneous demands.<br />

DHW recirculation system will be included for condenser boiler system.<br />

DHW supply temperature equal to 125 degrees fahrenheit.<br />

Water Softeners: All heated water to be softened.<br />

Figure 7.6-1, Boiler/Domestic Hot Water Plant, shows the layout of the New<br />

<strong>Terminal</strong> Boiler Room.<br />

Landrum & Brown Page 260<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.6-1<br />

BOILER/DOMESTIC HOT WATER PLANT<br />

Source:<br />

HNTB<br />

7.6.1.2 Cooling Equipment<br />

The existing CUP will be used for cooling the New <strong>Terminal</strong>. The alternative to<br />

install cooling equipment in the New <strong>Terminal</strong> was not considered because terminal<br />

space is reserved for revenue generating opportunities and there was no good<br />

landside location for the cooling towers. The following cooling system will be<br />

provided.<br />

<br />

<br />

<br />

<br />

<br />

<br />

DRAFT<br />

Chillers: 1500 Ton, centrifugal, refrigerant type R123 or 134A, with<br />

4160 volt motors. Pipe chillers in parallel.<br />

Chilled Water Supply (CWS) and Chilled Water Return (CWR) Temperatures:<br />

CWS temperature to equal 40 degrees Fahrenheit as it leaves the chiller<br />

plant. Assume 42 degrees Fahrenheit as it enters the AHUs in the New<br />

<strong>Terminal</strong>. CWR temperature to equal 58 degrees Fahrenheit back at the CUP<br />

at less than 60 psig pressure.<br />

CWS distribution type: Variable Primary Flow.<br />

Cooling Towers: Induced draft type, six Cells; induced draft; no anti-plume;<br />

two speed fans; three single-speed condenser water (CHW) pumps – 480V.<br />

Cooling Tower Water Design: Condenser Water Temperature differential<br />

design criteria equal to 90 degrees Fahrenheit in and 80 degrees Fahrenheit<br />

out with Air Wet Bulb temperature equal to 72 degrees Fahrenheit.<br />

Plate Frame Exchangers for Economizer Cooling in winter: Will not be used.<br />

Landrum & Brown Page 261<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7.6.1.3 Mechanical Plant<br />

Central Utility Plant (CUP)<br />

In addition to using the existing CUP Site, five alternative sites were investigated as<br />

a new CUP location. The Alternative 4 site was selected as the Prefered Alternative<br />

if the existing CUP site was not used. The preferred Alternative 4 CUP is located<br />

northwest of the existing plant. See Figure 7.6-2, CUP Site Plan-Base Case, for<br />

the existing CUP site location and new CHW piping to the New <strong>Terminal</strong> and<br />

Figure 7.6-3, CUP Site Plan Alternatives and Utility Corridors. The base case<br />

and the preferred Alternative 4 CUPs are planned to include the following:<br />

<br />

<br />

<br />

<br />

<br />

<br />

Chillers:<br />

Primary-Variable Flow Chilled Water PumpsMotor Control Center for chilled<br />

water equipment.<br />

Appropriate chilled water system chemical treatment, corrosion inhibiters,<br />

and expansion tanks.<br />

Kansas City Power & Light (KCP&L) Switchgear Room located on one end of<br />

the CUP with code required egress.<br />

Cooling Towers: Match the chillers, with space to add a future cooling tower.<br />

Distribution Piping: 15 parking spaces outside of the CUP for plant operators.<br />

7.6.1.4 HVAC Systems<br />

<strong>Terminal</strong> HVAC<br />

DRAFT<br />

The New <strong>Terminal</strong> HVAC is planned to be a Single-Duct Variable Air Volume (VAV)<br />

air distribution system for the majority of the spaces. Air Handling Units (AHUs)<br />

will be located in Mechanical Rooms that are spaced throughout the New <strong>Terminal</strong>.<br />

See Figure 7.6-4, Mechanical Room Locations (Appendix A), for mechanical<br />

room locations in the New <strong>Terminal</strong> as well as a typical mechanical room layout.<br />

The AHUs will consist of a plug-type supply fan, chilled water cooling coil, heating<br />

water pre heat coil, plug-type return fan, and pre filters and final filters.<br />

Sufficient outside air is introduced at the AHUs to meet the requirements of<br />

ASHRAE 62.1, Ventilation for Acceptable Indoor Air Quality. A 100 percent Outside<br />

Air Economizer will provide “free cooling” when outdoor air conditions permit.<br />

No humidification will be provided in AHUs. Radiant or HTHW unit heaters will be<br />

used.<br />

The air supply temperature will equal 55 degrees Fahrenheit and return air<br />

temperatures will be at 78 degrees Fahrenheit. Conditioned air is ducted to VAV<br />

boxes with HW coils for additional heating to meet the space requirements.<br />

Perimeter spaces will use a forced air type system and/or perimeter finned tube<br />

radiation depending on the architecture. All restroom spaces will be exhausted.<br />

Landrum & Brown Page 262<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 263<br />

April 2013<br />

Figure 7.6-2<br />

CUP SITE PLAN-BASE CASE<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 264<br />

April 2013<br />

Figure 7.6-3<br />

CUP SITE PLAN ALTERNATIVES AND UTILITY CORRIDORS<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 265<br />

April 2013<br />

Figure 7.6-4<br />

MECHANICAL ROOM LOCATIONS<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The Chiller Plant is not run year round and chilled water is not available to provide<br />

cooling for computer equipment. Separate Direct Expansion (DX) Air Conditioning<br />

split systems will serve the larger computer rooms. This involves an indoor Fan Coil<br />

unit, with a refrigerant DX coil to cool the air. The refrigerant is piped to an<br />

outdoor air cooled condensing unit to complete the split system. Smaller IT<br />

Equipment Rooms will use Through-the-Wall DX air conditioning systems.<br />

Bag makeup, tug area, and truck receiving dock areas will be exhausted with a<br />

ducted system and HW unit heaters will provide heating. CO sensors will be<br />

provided for diesel and some gasoline Ground Support Equipment (GSE). Outside<br />

air will come from roof top intakes and will include two-inch pleated paper filters as<br />

minimum. Air Curtains are planned at baggage doors and large support area<br />

openings.<br />

Concession Food Prep areas will be exhausted. Heat Recovery will be investigated<br />

as the design progresses. Kitchen exhaust hoods and gas-fired makeup air units<br />

will be provided for restaurant grease hoods.<br />

7.6.1.5 Aircraft Specialty Equipment<br />

Point-of-Use (POU) systems are preferred by KCI and the Airlines. New <strong>Terminal</strong><br />

gates are planned to have loading bridges with a POU Pre-conditioned Air unit<br />

(PCA) and a 400 Hz unit. Central or zone type PCA and 400 Hz systems were<br />

considered because they save energy and require less maintenance than the POU<br />

type. However, if a chiller or motor generator set fails, the entire system is<br />

impacted. In addition, the capital cost of these systems are high and aircraft<br />

diversity must be significant in order to realize increased savings from reduced<br />

energy usage and reduced maintenance costs to justify these investments. Finally,<br />

central and zone type systems are difficult to modify. For example, at Hobby<br />

International Airport, they want to add Group V aircraft to the terminal but the<br />

existing zone PCA system was designed for Group III aircraft. Pipe size is fixed and<br />

consequently they will likely install a POU type for the larger gates.<br />

DRAFT<br />

GSE Quick Charging Stations are a great technology to help reduce fossil fuel<br />

emissions at the Airport and reduce undesirable emissions from fossil fuel GSE.<br />

The New <strong>Terminal</strong> is planned to include electric GSE and quick charging stations.<br />

Adequate power for electric GSE recharging equipment is planned. For example,<br />

Bob Hope Airport in Burbank, California, was the first in the U.S. to convert to an<br />

“all-electric” GSE fleet model. At Bob Hope Airport, they were able to come to<br />

agreement with the airlines to convert the GSE fleet to electric if the airport<br />

provided the rapid charger infrastructure. Many U.S. airports now operate at least<br />

one electric fast charge system.. Major international airports that have rapid<br />

charging stations include Boston Logan, Charlotte, Chicago O’Hare, Dallas Fort<br />

Worth, Dulles, George Bush, John F. Kennedy, La Guardia, Los Angeles, Miami,<br />

Newark, Philadelphia, and San Francisco. These airports have replaced thousands<br />

of their fossil-fueled GSE vehicles with cleaner, more efficient electric-powered<br />

alternatives<br />

Landrum & Brown Page 266<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Recommended Aircraft Specialty Equipment for the New <strong>Terminal</strong> is POU<br />

Preconditioned Air and 400 Hz motor generator units on each loading bridge and<br />

GSE Quick Charging Stations, not the conventional eight-hour chargers. Rapid<br />

chargers provide up to one hour 80 percent equipment charges and are convenient<br />

but come with higher first costs.<br />

7.6.1.6 PLUMBING ITEMS<br />

Water Service<br />

Water Service is planned to come from the KCMO Water Service 12-inch diameter<br />

water main located landside of the existing terminals. Water will enter the building<br />

at the Boiler/Domestic Hot Water Plant through a backflow preventer. The pipe<br />

splits into cold water (CW) and hot water (HW) mains, heated by the HW boilers<br />

(described previously). Water softeners for the HW system will be provided for in<br />

the boiler room.<br />

Sprinkler System<br />

The New <strong>Terminal</strong> will have a complete sprinkler system to meet the requirements<br />

of National Fire Protection Administration (NFPA) 13, Installation of Sprinkler<br />

Systems. No fire pumps are anticipated. Water flow will be provided per the 2012<br />

IFC unless the KCI fire insurance carrier requirements are more conservative.<br />

The water flow rate will be assumed to be 2,000 gallons per minute (gpm) for a<br />

four-hour duration unless otherwise directed. (2012 IFC minimum water flow for<br />

Class IIIA construction over 166,501 square feet is 1,500 gpm for four hours).<br />

Two fire hydrants are planned for airside installation. Figure 7.6-5, Fire<br />

Protection Existing Conditions, shows the existing fire protection mains.<br />

Figure 7.6-6, <strong>Terminal</strong> B and C Fire Protection Phasing Plan, indicates a new<br />

12-inch diameter water line to re-feed the mains for <strong>Terminal</strong>s B and C, as well as<br />

demolition for the existing <strong>Terminal</strong> A mains. Figure 7.6-7, Fire Protection<br />

Routing-New <strong>Terminal</strong>, shows the routes of the fire mains around the New<br />

<strong>Terminal</strong>. In addition, it shows a distribution of fire sprinkler risers and standpipes<br />

in the New <strong>Terminal</strong> and Parking Garage.<br />

Sewer<br />

DRAFT<br />

The New <strong>Terminal</strong> sewer will drain by gravity to the sewer main. The plan is to<br />

have two minimum main eight-inch diameter sewer connections from the New<br />

<strong>Terminal</strong>, one from the north half and one from the south. Lift station<br />

requirements will be determined based on elevations and sanitary outfall.<br />

Individual grease traps will be provided in every food prep area. KCI is very spread<br />

out which makes a centralized grease waste system not practical. If a central<br />

grease vault is located on airside within 100 feet of the main restaurant /<br />

concessions area, it may be considered.<br />

Landrum & Brown Page 267<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 268<br />

April 2013<br />

Figure 7.6-5<br />

FIRE PROTECTION EXISTING CONDITIONS<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 269<br />

April 2013<br />

Figure 7.6-6<br />

TERMINAL B AND C FIRE PROTECTION PHASING PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 270<br />

April 2013<br />

Figure 7.6-7<br />

FIRE PROTECTION ROUTING-NEW TERMINAL<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Natural Gas<br />

Natural gas serves the HTHW boilers, domestic hot water boilers, and concessions.<br />

Natural gas is piped to the Boiler Room from a 10-inch diameter main from Missouri<br />

Gas & Energy. The gas pressure in the main is 25 psig. The gas will be regulated<br />

down to 5.0 psig at the boiler plant. This will provide the gas pressure of 2.8 psig<br />

required at the boiler plus additional pressure for good regulator operation. Natural<br />

gas for concessions will enter the New <strong>Terminal</strong> separately and be regulated down<br />

to seven-inch w.g. to serve the food service equipment.<br />

Roof Drainage<br />

Roof drains and emergency overflow roof drains are spaced as needed to cover all<br />

New <strong>Terminal</strong> roofs. Stormwater leaders are sized per the plumbing code and run<br />

down the interior of the building to the stormwater system. Stormwater runoff<br />

onto apron pavement should be avoided. Roof drains and leaders should not<br />

contribute to build up of ice sheets.<br />

7.6.1.7 Electrical Items<br />

<strong>Terminal</strong> Power Requirements<br />

In order to distribute power throughout the New <strong>Terminal</strong> without extensive voltage<br />

drop, 12.5kV, 3-phase power will be distributed around the New <strong>Terminal</strong>, from the<br />

main KCP&L Switchgear room, to four main KCI substation and switchgear rooms.<br />

It is recommended that this 12.5kV distribution be done in the apron so as to<br />

increase ease of access, and reduce risk of personal injury and vandalism in the<br />

case of a fault. See Figure 7.6-8, KCI <strong>Terminal</strong> 12.5kv Ductbank Site Plan,<br />

for the approximate size and location of the KCP&L Switchgear room and the<br />

locations of the four KCI switchgear rooms. The KCP&L 15kV switchgear will feed<br />

four double-ended unit substations. Each of these four unit substations will consist<br />

of two 2500kVA, 12.5kV – 277/480V transformers and a secondary 4000A maintie-main<br />

switchgear. Each substation will distribute power to 21 100-square foot<br />

sub-electrical rooms located throughout the New <strong>Terminal</strong> for power to adjacent<br />

gates, and low voltage terminal loads. See Figure 7.6-9, Electrical Single Line<br />

Diagram, and Figure 7.6-10, <strong>Terminal</strong> Electrical and Telecomm Room Floor<br />

Plan. Each of the 21 sub-electrical rooms will have 277/480V distribution boards,<br />

480/120/208V transformers, 120/208V distribution boards, and lighting control<br />

panels.<br />

DRAFT<br />

Landrum & Brown Page 271<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 272<br />

April 2013<br />

Figure 7.6-8<br />

KCI TERMINAL 12.5KV DUCTBANK SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 273<br />

April 2013<br />

Figure 7.6-9<br />

ELECTRICAL SINGLE LINE DIAGRAM<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 274<br />

April 2013<br />

Figure 7.6-10<br />

TERMINAL ELECTRICAL AND TELECOMM ROOM FLOOR PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Each of the four KCI Switchgear rooms will have KCP&L meters that tie back to a<br />

centralized metering point in the main <strong>Terminal</strong> KCP&L Electrical room. The main<br />

<strong>Terminal</strong> electrical room including emergency and stand-by generators as well as<br />

the KCI Switchgear Room A, will require a minimum of 6,500 square feet of space.<br />

The four main KCI substations A, B, C, and D can be fed as shown on Figure 7.6-9,<br />

Electrical Single Line Diagram, or as part of a loop system. The advantages of a<br />

loop system is that fewer, if not larger feeder cables would be required to maintain<br />

power to the four substations as well as allowing additional substations to be added<br />

without interruption. However, source switching equipment would be required in<br />

order to remove and maintain any single substation from the loop without<br />

disrupting power to the entire terminal. It is recommended that the New <strong>Terminal</strong><br />

distribution system be installed as shown on Figure 7.6-9, Electrical Single Line<br />

Diagram, as it requires less equipment and no additional terminal loads are<br />

anticipated. This proposed <strong>Terminal</strong> distribution will be the same for the Base Case<br />

and all alternatives.<br />

CUP<br />

In the proposed Base Case, the existing CUP will remain protected in place.<br />

See Exhibit E-4, KCI <strong>Terminal</strong> 12.5kv Ductbank Site Plan-Base Case. This includes<br />

all the existing 15kV KCP&L switchgear. In addition, new chillers and MCC<br />

equipment will be required in the existing CUP in order to support the New<br />

<strong>Terminal</strong>. To support this new equipment, the existing 15kV KCP&L switchgear,<br />

used for existing <strong>Terminal</strong> A, will be cut over to support the new CUP equipment,<br />

thus avoiding the need for any major overhaul of the existing KCP&L switchgear in<br />

the existing CUP. See Figure 7.6-11, Base Case-Upgraded Cup First Floor<br />

Plan, for power requirements needed to support the new mechanical equipment.<br />

DRAFT<br />

Figure 7.6-11<br />

BASE CASE-UPGRADED CUP FIRST FLOOR PLAN<br />

Source:<br />

HNTB<br />

Landrum & Brown Page 275<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

KCP&L Distribution Power<br />

In anticipation of the construction, and in order to maintain power to the existing<br />

CUP and <strong>Terminal</strong>s B and C, the existing 15kV distribution ductbanks and manholes<br />

from the KCP&L – KCI Substation 270 will have to be rerouted between existing<br />

MH-PA-10 to existing MH-PA-16. See Figure 7.6-12, 12.5kV Electrical Site<br />

Plan, for proposed re-route.<br />

KCP&L <strong>Terminal</strong> Power<br />

At least two 10MVA feeders are recommended for the New <strong>Terminal</strong>, with each<br />

feeding opposing ends of a 15kV KCP&L double ended switchboard. These new<br />

feeders will enter the New <strong>Terminal</strong> main electrical room directly from the KCP&L –<br />

KCI Substation 270. The New <strong>Terminal</strong> main switchboard will require a space that<br />

is approximately 30 feet x 75 feet, and can be co-located with the KCI Switchgear<br />

Room A within the New <strong>Terminal</strong>. See Figure 7.6-13, KCI <strong>Terminal</strong> 12.5kV<br />

Ductbank Site Plan (Appendix A), for Base Case 12.5kV <strong>Terminal</strong> Power.<br />

The existing KCP&L – KCI Substation 270 has a 50MVA capacity and only 15MVA is<br />

currently utilized. The existing substation is serviced by two transformers, which<br />

allows extending one new feeder from each transformer, providing adequate<br />

capacity, in case one of the transformers fails. KCP&L will own and operate all<br />

15kV distribution lines and associated 15kV equipment. In order to support the<br />

new distribution cables, concrete encased conduit and manholes will have to be<br />

provided to the New <strong>Terminal</strong> Main Electrical Room.<br />

In order to have a truly redundant system, 10MVA of power would have to be<br />

provided from one of the two local KCP&L adjacent substations: Tiffany Springs<br />

Substation or Overhaul Base Substation.<br />

DRAFT<br />

Although the Overhaul base substation is the closer of the two alternative locations<br />

(8,000 linear feet away), it was not originally constructed as a standard substation.<br />

In addition the new feeders from Overhaul Base would have to cross the entire East<br />

Airfield, including Runway 19L-1R and Taxiways E and F. Also, this substation does<br />

not have the ability to provide enough power to feed the entire terminal.<br />

With $500,000 improvements, it could provide one feeder to serve part of the<br />

required load. The cost for such a run could be as high as $3MIL for a single<br />

10MVA feeder and $6MIL for two feeders for materials alone, not counting the cost<br />

associated with jack and boring under the existing airfield and apron or unforeseen<br />

site conditions over the approximate 1.5 mile run. These upgrades would have to<br />

be confirmed with KCP&L prior to any final decision being made.<br />

Landrum & Brown Page 276<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 277<br />

April 2013<br />

Figure 7.6-12<br />

12.5KV ELECTRICAL SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 278<br />

April 2013<br />

Figure 7.6-13<br />

KCI TERMINAL 12.5KV DUCTBANK SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Tiffany Springs Substation is the newest substation and can provide service to the<br />

New <strong>Terminal</strong>. It has 50 MVA capacity and three transformers, two of which are<br />

new. However, Tiffany Springs is the furthest substation from the New <strong>Terminal</strong><br />

(approximately 27,000 linear feet), and would have to cross the south or east<br />

airfield. The cost for such a run could be as high as $8MIL for a single 10MVA<br />

feeder and $16MIL for two feeders for materials alone, not counting the cost<br />

associated with jack and boring under the existing airfield and apron or unforeseen<br />

site conditions over the approximate five-mile run. These upgrades would have to<br />

be confirmed with KCP&L prior to any final decision being made.<br />

Given the unknown condition of the existing Overhaul Base substation, the long<br />

distance associated with connecting to the Tiffany Springs substation as well as the<br />

cost and potential disruptions to aircraft movements, it is recommended at this<br />

time that all connections for the New <strong>Terminal</strong>, CUP, and new Data Center be made<br />

from the existing KCP&L KCI substation to the north. However, if in the future it is<br />

determined that the existing KCP&L KCI substation is prone to failure and outages,<br />

intercept manholes, as well as space for connections to additional feeders will be<br />

provided at the New <strong>Terminal</strong>, CUP, and Data Center, in order to facilitate a new<br />

feeder from either the Overhaul Base or Tiffany Springs Substation. The manholes<br />

and additional switchgear will be located in such a manner that no disruptions to<br />

the terminal or terminal activities will be experienced during the cut-over.<br />

Emergency and Stand-by Power<br />

The Basic code required Emergency Egress and Fire Life Safety requirements can be<br />

facilitated by two 1 MW Emergency Generators provided in the main <strong>Terminal</strong><br />

electrical room. This will allow for basic smoke control, elevator return, egress<br />

lighting requirements, and airplane and terminal evacuation to dedicated<br />

evacuation sites. See Figure 7.6-14, Emergency and Standby Generator<br />

Plant, and Figure 7.6-15, KCI <strong>Terminal</strong> 12.5kv Ductbank Site Plan-Base<br />

Case.<br />

DRAFT<br />

Additional stand-by, non-code required back-up power can be provided for freeze<br />

protection, additional elevator functionality, additional lighting, emergency powered<br />

gate systems that allow for the controlled egress from aircraft at designated gates<br />

and other systems that allow for a more coordinated, public friendly terminal<br />

evacuation. This additional level of stand-by power can be facilitated by two<br />

1.5 MW stand-by generators in the main terminal electrical room.<br />

See Figure 7.6-14, Emergency and Standby Generator Plant.<br />

The entire generator system should be consolidated and located as close as possible<br />

to a KCI switchgear room. This will allow the emergency power to be controlled,<br />

monitored, and fed from a single point of distribution. Per Figure 7.6-15, KCI<br />

<strong>Terminal</strong> 12.5kv Ductbank Site Plan-Base Case, the preferred location is in the<br />

South East corner of the new <strong>Terminal</strong>. In addition to being located near an easily<br />

accessible landside access point, it is also near the main mechanical boiler room<br />

and MDF room, allowing for an inexpensive connection to the standby generator<br />

system.<br />

Landrum & Brown Page 279<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.6-14<br />

EMERGENCY AND STANDBY GENERATOR PLANT<br />

Source:<br />

HNTB<br />

DRAFT<br />

Locating the emergency and stand-by generators in the new CUP was not<br />

addressed because power for the New <strong>Terminal</strong> would be provided directly from the<br />

existing KCP&L substation, and not routed through the new CUP in order to reduce<br />

the risk of a single point of failure. Locating the generators in the new CUP with<br />

normal power going directly to the New <strong>Terminal</strong> would require that the ATS be<br />

located in the New <strong>Terminal</strong> Electrical room well over 2,000 feet away.<br />

This distance would mean significant voltage drop and added cost due to additional<br />

feeder size and length. The current location for the generator room at the far south<br />

end of the New <strong>Terminal</strong> puts them well out of the way of public traffic, and can be<br />

easily insulated to reduce noise.<br />

Landrum & Brown Page 280<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.6-15<br />

KCI TERMINAL 12.5KV DUCTBANK SITE PLAN-BASE CASE<br />

Source: HNTB<br />

Fire Alarm System<br />

DRAFT<br />

The New <strong>Terminal</strong> Fire Alarm System will need to have a main Fire Alarm Control<br />

Room located within the New <strong>Terminal</strong>, located on the ground floor adjacent to the<br />

front lobby, and approximately 10 feet x 20 feet in size. This room will house the<br />

main Fire Alarm Control Panel, as well smoke evacuation control system and<br />

emergency generator controls, in accordance with the local Fire Department.<br />

This system will have to be tied back into the main emergency response center at<br />

the Airport Rescue and Fire Fighting (ARFF) and/or Police shop, with remote<br />

annunciators at both locations. This new system will have to be capable of<br />

interfacing with the existing Fire Alarm systems within the existing <strong>Terminal</strong>s B and<br />

C, as well as other existing ancillary buildings to remain. Additional migrating<br />

hardware and or software may be required in order to fully integrate the different<br />

systems.<br />

Coordination with the Kansas City Fire Department (KCFD) should be completed<br />

early on, in order to coordinate the exact location of the New <strong>Terminal</strong> Fire Alarm<br />

Control Room, as well as determining if a second staging area at the COP Shop, or<br />

some other more desirable location is preferred.<br />

Landrum & Brown Page 281<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Fiber Optic Site<br />

To accommodate the demolition of <strong>Terminal</strong> A, and maintain the connectivity of the<br />

existing Fiber optic loop, a portion of the existing Fiber Optic Loop System will have<br />

to be re-routed in order to maintain the double-ended feed to existing <strong>Terminal</strong>s B<br />

and C. In addition, final connections will have to be made at the New <strong>Terminal</strong>.<br />

These cut-overs will have to be strategically coordinated in order to avoid<br />

shutdowns of any secure or mission critical systems. See Figure 7.6-16, Fiber<br />

Optic Communications Site Plan.<br />

The existing Data Center and Airport Communications Center (ACC) in the CUP will<br />

continue to be the central hub for the fiber optic loop system. Once the <strong>Terminal</strong><br />

has been completed, the Fiber Optic Loop System will be extended into the new<br />

<strong>Terminal</strong> through a Main Point of Entrance (MPOE) Room or Main Distribution Frame<br />

(MDF) Room.<br />

<strong>Terminal</strong> IT System<br />

With a basic level of service required for the base line operation of the New<br />

<strong>Terminal</strong>, the MPOE/MDF room should be no less than 800 square feet, and located<br />

at the first point of entrance into the New <strong>Terminal</strong> for all communications systems.<br />

The MPOE/MDF room will provide a central hub for communications distribution to<br />

14 smaller telecommunications rooms or Intermediate Distribution Frames (IDFs)<br />

located throughout the New <strong>Terminal</strong>. See Figure 7.6-17, <strong>Terminal</strong> Electrical<br />

and Telecomm Room Floor Plan. The MPOE/MDF room will have all systems<br />

backed up with a UPS to maintain system power during brown outs or during<br />

generator start-up.<br />

DRAFT<br />

The six smaller IDFs will be no less than 150 square feet, and will house routers for<br />

connections to local airline GIDS; connections to airline and passenger WIFI<br />

routers; local eVIDS systems; amplifiers, noise sensors, and network switches for<br />

local Public Address systems; ACAMS security panels for local doors; closed circuit<br />

TV (CCTV) network hubs for signal consolidation and local viewing if required by<br />

individual airlines; local Fire Alarm sub-panels and UPS units to maintain system<br />

power during brown outs or during generator start-up. The IDFs should not be<br />

located any more than 300 feet apart, taking into account structural features such<br />

as stairwells and elevator shafts, which may require the rooms to be located closer<br />

together in order to maintain a 300 feet maximum cable run length between them.<br />

In addition to the IDFs IT closets no less than 8 feet x 10 feet shall be located at<br />

each gate, for ramp services monitoring systems, and local airline IT equipment. In<br />

addition, each IDF, IT closet, and MPOE/MDF will have a dedicated UPS powered<br />

air-conditioning unit separate from the New <strong>Terminal</strong> cooling system.<br />

Landrum & Brown Page 282<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 283<br />

April 2013<br />

Figure 7.6-16<br />

FIBER OPTIC COMMUNICATIONS SITE PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY PROGRAM CRITERIA DOCUMENT<br />

ADVANCE TERMINAL PLANNING STUDY DRAFT<br />

Landrum & Brown Page 284<br />

April 2013<br />

Figure 7.6-17<br />

TERMINAL ELECTRICAL AND TELECOMM ROOM FLOOR PLAN<br />

DRAFT<br />

Source: HNTB


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

IT<br />

The existing Data Center and ACC will be maintained. However, because of the<br />

New <strong>Terminal</strong> systems that will be installed, modifications will have to be made to<br />

both centers. The preferred option is to utilize existing adjacent support space for<br />

expanded systems. By utilizing adjacent rooms, existing systems to <strong>Terminal</strong>s B<br />

and C can be maintained during construction without interruption while the New<br />

<strong>Terminal</strong> systems are installed in the adjacent space. See Figure 7.6-18,<br />

Existing CUP First Floor Plan, for the existing Data Center room location and<br />

layout, and Figure 7.6-19, Existing CUP Third Floor Plan, for the existing ACC<br />

room location and layout. For the expanded Data Center requirements see<br />

Figure 7.6-20, Upgraded CUP First Floor Plan, and Figure 7.6-21, Upgraded<br />

CUP Third Floor Plan, for the ACC requirements.<br />

Figure 7.6-18<br />

EXISTING<br />

DRAFT<br />

CUP FIRST FLOOR PLAN<br />

Source: HNTB<br />

Landrum & Brown Page 285<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.6-19<br />

EXISTING CUP THIRD FLOOR PLAN<br />

Source:<br />

HNTB<br />

DRAFT<br />

Figure 7.6-20<br />

UPGRADED CUP FIRST FLOOR PLAN<br />

Source: HNTB<br />

Landrum & Brown Page 286<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.6-21<br />

UPGRADED CUP THIRD FLOOR PLAN<br />

Source: HNTB<br />

DRAFT<br />

Landrum & Brown Page 287<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7.7 Baggage Handling System (BHS)<br />

7.7.1 OUTBOUND BHS<br />

The conceptual Checked Baggage Inspection System (CBIS) for Kansas City<br />

International Airport (MCI) consists of 15 total induction points which feed baggage<br />

to four inline screening devices (ISD) and sort to eight slope plate devicesshown in<br />

Figure 7.7-1, Overall BHS System.<br />

Figure 7.7-1<br />

OVERALL BHS SYSTEM<br />

Source: Vic Thompson Co.<br />

DRAFT<br />

Landrum & Brown Page 288<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7.7.2 BAGGAGE INDUCTION POINTS<br />

There are four ticket counter baggage induction points on the north end of the<br />

terminal, and four ticket counter induction points on the south end of the terminal.<br />

Additionally, there are two curbside baggage induction points, four self-tagging<br />

baggage induction points (garage) and one international re-check induction point.<br />

These 15 induction points are collected by two main security feed lines; one for the<br />

north ticket counters and one for the south ticket counters, curbsides and<br />

international re-check. The two security feed lines merge together before entering<br />

the matrix screening area , shown in Figure 7.7-2, Level 2 BHS.<br />

Figure 7.7-2<br />

LEVEL 2 BHS<br />

DRAFT<br />

Source:<br />

Vic Thompson Co.<br />

Landrum & Brown Page 289<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Oversize is handled separately from the CBIS. There is an oversize baggage<br />

induction point for each side of the terminal. These two lines merge together<br />

before entering the Checked Baggage Resolution Area (CBRA) for manual<br />

screening.<br />

7.7.3 SCREENING MATRIX<br />

After the two security feed lines merge together, baggage is sized using a bag<br />

measuring array (BMA). Bags that are too large to fit into the ISD will be<br />

considered out-of-gauge (OOG) and will divert to a screening machine bypass line<br />

that leads directly to CBRA for manual screening. The single security feed main line<br />

will divert all in-gauge baggage to one of four CTX9800 screening machines. After<br />

the level 1 screening decision is made by the ISD, clear bags merge onto a main<br />

clear line. Alarmed bags will merge on to an on-screen resolution (OSR) line while<br />

the level 2 decision is pending. Bags which have been cleared by the level 2 OSR<br />

operator will<br />

DRAFT<br />

then be diverted from the OSR line onto the main clear line. Bags that<br />

remain alarmed will continue on to the CBRA for a level 3 inspection by TSA.<br />

Once the baggage is cleared by TSA, it will be placed on the CBRA clear line and<br />

merge onto the main clear line.<br />

7.7.4 BAGGAGE SORTATION<br />

Baggage on the main clear line is then processed through an automatic tag reader<br />

(ATR) for bag sorting. Bags that fail to be read are diverted to a manual encode<br />

station for manual scanning. The main clear line splits into two separate lines, one<br />

for the carriers on the north end and one for the carriers on the south end. Each of<br />

these clear lines feeds four slope plate devices. Any bags that fail to divert will end<br />

up on the most downstream slope plate device.<br />

There is a dedicated oversize clear line in CBRA that carries the cleared oversize<br />

baggage directly to the outbound bag room for make-up. The carriers will need to<br />

collect their oversized items from this single run-out belt for oversized baggage.<br />

7.7.5 INBOUND BHS<br />

The inbound will consist of six inbound load belts that feed six inbound claim units<br />

shown in Figure 7.7-3, Level 1 BHS. Each load belt feeds one claim unit without<br />

crossover capabilities.<br />

Landrum & Brown Page 290<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 7.7-3<br />

LEVEL 1 BHS<br />

Source:<br />

Vic Thompson Co.<br />

DRAFT<br />

Landrum & Brown Page 291<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

7.7.6 FIS<br />

International inbound bags are loaded onto a dedicated FIS inbound load belt in the<br />

south inbound bag room. These bags are read by an ATR and sorted to one of two<br />

FIS claim units shown in Figure 7.7-4, Level 3 BHS.<br />

Figure 7.7-4<br />

LEVEL 3 BHS<br />

Source: Vic Thompson Co.<br />

DRAFT<br />

Landrum & Brown Page 292<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

8. ENVIRONMENTAL CONSIDERATIONS<br />

8.1 Alternative Evaluation - Environmental Resources<br />

Initial alternatives during the Master <strong>Planning</strong> process were examined in compliance<br />

with the operational planning criteria found in the FAA Advisory Circular<br />

150/5300-13, Airport Design. KCI has a relatively large amount of land that is<br />

currently undeveloped. KCI’s property boundary includes 11,000 acres of open<br />

land with varying terrain providing various site selection possibilities. This uniquely<br />

positive attribute led to the selection of three initial terminal complex site envelopes<br />

in the Master Plan. The three initial options included development in the central<br />

terminal area, development in the west open area between existing Runway 1L/19R<br />

and Interstate 435, and development in the south between existing Runway 9/27<br />

and State Highway 152.<br />

8.1.1 ADVANCED PLANNING/PURPOSE AND NEED<br />

Since the Master Plan, KCAD has identified specific goals, objectives, and passenger<br />

demand characteristics that guided the further development of alternatives.<br />

The purpose of the terminal development project would be to reduce operating<br />

costs and enhance revenues for KCAD while improving passenger processing and<br />

efficiency within the terminal and provide convenient roadways, parking lots, and<br />

traffic flow for Airport users and vehicles. It is KCAD’s goal to provide a high level<br />

of air service, as well as a source of community pride for Kansas City and the Metro<br />

Region in a cost effective and affordable manner. The new terminal would need to<br />

incorporate the latest in passenger processing technology and achieve a balanced<br />

capacity of gates, terminal processing, and landside facilities.<br />

DRAFT<br />

8.1.2 PREFERRED ALTERNATIVE<br />

Based on KCAD’s specific goals, FAA operational requirements, and criteria<br />

including affordability, airside, terminal, and landside characteristics, support<br />

facilities, availability of utilities, environmental pro and cons, implementation, and<br />

other strategic considerations, KCAD has selected a preferred alternative.<br />

8.2 Implementation <strong>Planning</strong> – Environmental<br />

Considerations<br />

The FAA is responsible for complying with both the procedures and policies of the<br />

National Environmental Policy Act (NEPA) 1 and other related environmental laws,<br />

regulations, and orders applicable to FAA actions. FAA Order 1050.1E states that,<br />

“Unless otherwise exempted by the Council on Environmental Quality (CEQ)<br />

regulations, all formal actions taken by FAA officials are subject to NEPA review<br />

unless statutory law applicable to the FAA's operations expressly prohibits or makes<br />

compliance impossible. Actions covered by NEPA review include grants, loans,<br />

1<br />

42 U.S.C. 4321-4347.<br />

Landrum & Brown Page 293<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

contracts, leases, construction, research activities, rulemaking and regulatory<br />

actions, certifications, licensing, permits, plans submitted to the FAA which require<br />

FAA approval, and legislation proposed by the FAA.” 2<br />

8.2.1 POTENTIAL NEPA PROCESSING REQUIREMENTS<br />

Federal regulations outline three major levels of NEPA review relevant to proposed<br />

airport development projects – Categorical Exclusion, Environmental Assessment,<br />

and Environmental Impact Statement.<br />

Categorical Exclusion (CATEX) – applies to those actions that have been found<br />

(under normal circumstances) to have no potential for significant environmental<br />

impact. Actions that are eligible for a CATEX are listed in Chapter Three of FAA<br />

Order 1050.1E. CATEX documents can take up to three months to prepare and FAA<br />

review time may take 45 to 60 days. A CATEX generally does not require<br />

coordination with regulatory agencies and does not require public notice of the<br />

project.<br />

Environmental Assessment (EA) – applies to those actions that have been found by<br />

experience to sometimes have significant environmental impacts. The list of<br />

actions normally requiring an EA can be found in Chapter Four of FAA Order<br />

1050.1E. The purpose of an EA is to determine whether the proposed project will<br />

have significant impacts. Upon review of the EA findings, the FAA either issues<br />

project approval in the form of a Finding of No Significant Impact (FONSI) or directs<br />

the preparation of an Environmental Impact Statement (EIS) to investigate further<br />

the potential environmental impacts in detail before project approval can be<br />

granted. An EA typically takes between 6 and 24 months to prepare and obtain an<br />

FAA decision. A public hearing is not required but may be recommended by the<br />

FAA.<br />

DRAFT<br />

Environmental Impact Statement (EIS) – applies to those actions that have been<br />

found by experience to usually have significant environmental impacts. An EIS is<br />

the most intense level of environmental review and may take two to four years to<br />

complete. The FAA manages the preparation of the EIS and may issue a Record of<br />

Decision (ROD) after the Final EIS has been released.<br />

To determine if NEPA documentation for the proposed terminal project would be<br />

required, each element of KCAD’s Preferred Alternative and the other improvements<br />

listed on KCAD’s 5-year Capital Improvement Plan was reviewed to determine if a<br />

Federal Action would occur and then the project was appraised to determine the<br />

level of NEPA review that may be required.<br />

2<br />

FAA Order 1050.1E Environmental Impacts: Policies and Procedures. Chapter 2 NEPA <strong>Planning</strong> and<br />

Integration, 200e Applicability of NEPA Procedures to FAA Actions, (3) FAA Actions Subject to<br />

NEPA Review. March 20, 2006.<br />

Landrum & Brown Page 294<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

For most of the proposed developments projects, there is an associated Federal<br />

action, such as allocation of Federal funds or FAA approval of changes to the Airport<br />

Layout Plan (ALP) to reflect new development; therefore, NEPA would apply.<br />

Based on the type of projects and the anticipated impacts, it is recommended that<br />

an Environmental Assessment be pursued for this project.<br />

8.2.2 ALTERNATIVES TO BE CONSIDERED FOR FURTHER DETAILED<br />

ENVIRONMENTAL ANALYSIS<br />

Federal and state guidelines concerning the environmental review process require<br />

that all prudent, feasible, reasonable, and practicable alternatives that might<br />

accomplish the objectives of a project be identified and evaluated. Federal<br />

agencies may consider the applicant's purposes, needs, and common sense realities<br />

of a given situation in the development of alternatives. 3 Federal agencies may also<br />

afford substantial weight to the alternative preferred by the applicant, provided<br />

there is no substantially superior alternative from an environmental standpoint.<br />

While all the alternatives developed in the Master <strong>Planning</strong> process and advanced<br />

terminal planning process will be disclosed, it is anticipated that only two<br />

alternatives will be carried forward for detailed analysis of environmental impacts,<br />

the No Action and the Proposed Action/Preferred Alternative.<br />

8.3 Sustainability <strong>Planning</strong><br />

8.3.1 LOCAL SUSTAINABILITY INITIATIVES / ENVIRONMENTAL<br />

CONTEXT<br />

The City of Kansas City, Missouri is strongly committed to enhancing sustainability<br />

and the quality of life for its residents and visitors, as evidenced by development of<br />

the following initiatives and documents:<br />

<br />

<br />

DRAFT<br />

Climate Protection Plan: The City released its Climate Protection Plan in July<br />

2008 driven by the belief that greenhouse gas emissions can be reduced at<br />

the same time as the economy and quality of life are improved for businesses<br />

and citizens. The plan includes recommended goals for community-wide<br />

greenhouse gas reductions and actions to achieve the goals, as well as<br />

recommendations affecting the City’s climate protection planning process.<br />

Citywide Green Solutions Policies: In laying the groundwork for the Climate<br />

Protection Plan, the Kansas City Council adopted Resolution #070830,<br />

establishing the policy of the City to integrate green solutions in City<br />

planning and development processes. In addition, the City Manager adopted<br />

the Green Solutions Administrative Regulation (A.R. 5-5) to incorporate<br />

green solutions into City policies, projects, and programs.<br />

3<br />

Guidance Regarding NEPA Regulations, CEQ, 48 Federal Register 34263 (July 28, 1983).<br />

Landrum & Brown Page 295<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

Sustainability in Kansas City Brochure: As a complement to the City’s Green<br />

Solutions Policy and the Climate Protection Plan, which provide a roadmap for<br />

making the City’s vision of being a “certifiable green city” a reality, this<br />

brochure identified the City and regional initiatives designed to help achieve<br />

that goal.<br />

Green Building Ordinance No. 110235: It is the policy of the City that the<br />

design, construction, and operation of new facilities of any size and<br />

renovations in which the facility affected has at least 5,000 square feet of<br />

space, for which the City issues a request for qualifications for design<br />

services, design-build services, or conducts such services itself, shall conform<br />

to the LEED Gold rating or higher.<br />

Transportation Outlook 2040: Metropolitan Kansas City's long-range<br />

transportation plan, developed by the Mid America Regional Council (MARC)<br />

and adopted in June 2010, outlines a vision for the future relationship<br />

between transportation investments and land use in the region. The plan<br />

established a broad set of goals that cover areas ranging from<br />

transportation’s impacts on climate change and energy, to place-making, to<br />

the condition of existing transportation systems. While the plan focuses on<br />

surface transportation for the region, it acknowledges the importance of<br />

aviation and the region’s airports, stating that the Plan’s proper consideration<br />

of aviation planning activities will facilitate and achieve coordinated and<br />

comprehensive transportation planning within the region, thereby further<br />

supporting the overall transportation system goals of accessibility and<br />

economic vitality.<br />

<br />

<br />

Environmental Management System and Green Solutions Annual Report:<br />

The City’s Environmental Management System (EMS) was developed through<br />

a work group involving City employees from 12 departments. The EMS<br />

describes the structure of the City's internal environmental management<br />

program and specifies the best management practices to be followed by City<br />

employees in handling most commonly encountered environmentally<br />

sensitive tasks. The EMS is the focus of environmental orientation training<br />

received by every City employee, and is the standard used for the annual<br />

environmental audit of every City facility. The annual evaluation of each<br />

department’s progress in meeting environmental goals and the City’s efforts<br />

to incorporate green solutions into its programs, projects, and policies is<br />

reported in the EMS and Green Solutions Annual Report.<br />

DRAFT<br />

EnergyWorks KC Initiative: This initiative is designed to inform home and<br />

business owners of ways to reduce energy waste, increase comfort, and<br />

make a healthier live-work space. Through the web site<br />

www.EnergyWorksKC.org a variety of services are available to support home<br />

and business owners in the pursuit of reduced energy waste and increased<br />

energy efficiency. The initiative also includes development of<br />

recommendations for local and state policy changes in support of energy<br />

efficiency, creation of job opportunities, and public education and outreach.<br />

Landrum & Brown Page 296<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

<br />

<br />

<br />

Things We Can Do as Individuals to Reduce Greenhouse Gas Emissions:<br />

This brochure describes several quick and easy things that individuals can do<br />

in their homes and throughout their daily routines to do their part in reducing<br />

the amount of greenhouse gas emissions in the Kansas City area.<br />

A Million Lights Initiative: Kansas City was the first city in the nation to set<br />

the goal of changing one million light bulbs from traditional incandescent to<br />

energy-efficient compact fluorescent lights (CFLs), as part of the ENERGY<br />

STAR® national campaign to help consumers save money and energy<br />

through the switch. In 2008, the program reported that throughout the<br />

Kansas City metro area, over 1.6 million CFLs were purchased and/or<br />

distributed by the City and its partners. The program remains in effect today<br />

and continues to encourage residents and businesses to switch from<br />

incandescent to CFLs.<br />

City Environmental Improvement Goals: Each fiscal year, the City adopts<br />

environmental improvement goals for departmental implementation.<br />

The goals are administered in their respective departments by Environmental<br />

Coordinating Managers with progress towards attaining these goals reported<br />

in the City’s annual report to the City Manager at the end of the fiscal year.<br />

The goals are also stated on the City’s public web site.<br />

Sustainable Skylines <strong>Program</strong>: The U.S. EPA Region 7 has recognized<br />

Kansas City as a Sustainable Skylines Partner in its locally-led program to<br />

reduce air emissions and promote sustainability in urban environments.<br />

Greater Kansas City was chosen as one of the first pilot communities to<br />

implement this program, which provides a flexible framework for partners to<br />

integrate transportation, energy, land use, and air quality planning; yield<br />

measurable air quality benefits; promote collaboration among multiple<br />

stakeholders; and identify and leverage resources among partners.<br />

The specific projects under this program in the Kansas City area include:<br />

o<br />

o<br />

o<br />

o<br />

o<br />

o<br />

DRAFT<br />

KC Idle-Free – An idle-reduction campaign, working with public and<br />

private fleets to establish idle-free zones and assist the Kansas City<br />

metropolitan area in maintaining the national air quality standard for<br />

ozone.<br />

Be Water Wi$e – Water conservation and strategic landscaping projects<br />

with parks and homeowners associations to use less water and promote<br />

native plant species.<br />

Parking Lots to Parks – Curbing the urban heat island effect and reducing<br />

storm water runoff through sustainable parking lot design.<br />

Solar KC – Solar demonstration projects at schools and city-owned<br />

buildings to promote renewable, clean energy.<br />

Kansas City Future Forum – Action by individuals, businesses, and civic<br />

groups to reduce our environmental impact and become a green region.<br />

“Constructing” Clean Air – A diesel engine retrofits partnership with the<br />

heavy construction industry in Kansas City to reduce air pollution from<br />

construction equipment.<br />

Landrum & Brown Page 297<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

8.3.2 RELEVANT REGULATIONS / GUIDANCE<br />

The Leadership in Energy and Environmental Design (LEED ® ) Rating System,<br />

developed (in 2000) and administered by the U.S. Green Building Council (USGBC),<br />

is an internationally recognized mark of excellence for occupied buildings. LEED<br />

provides a framework to building owners and operators for identifying and<br />

implementing practical and measurable green building design, construction,<br />

operations, and maintenance solutions. Working throughout a building’s life cycle,<br />

LEED certification provides independent, third-party verification that the building<br />

was designed and built using strategies aimed at achieving high performance in key<br />

areas of human and environmental health: sustainable site development, water<br />

savings, energy efficiency, materials selection, and indoor environmental quality.<br />

Chicago Department of Aviation Sustainable Airport Manual<br />

The Chicago Department of Aviation (CDA) is embracing the best possible<br />

environmental, social, and fiscally responsible practices to enhance the quality of<br />

life and complement the overall mission and goals of the City of Chicago. In so<br />

doing, the CDA has developed the Sustainable Airport Manual (SAM), with a vision<br />

that it will become the global industry standard for sustainability planning,<br />

development, and everyday functions at airports around the world.<br />

When the original edition of the SAM was unveiled as the Sustainable Design<br />

Manual (SDM) in December of 2003, Chicago was the first in the nation to develop<br />

sustainability guidance specifically for airports. Numerous, wide-ranging projects<br />

have since been reviewed and rated according to the standards established by the<br />

SDM and SAM, resulting in the evolution of a unique process and many industry<br />

firsts:<br />

<br />

<br />

<br />

DRAFT<br />

Development of a rating system,<br />

Development of a green airplane certification award system, and<br />

Recognition of designers and contractors for sustainable accomplishments.<br />

The Sustainable Airport Manual (SAM) is an integral part of Chicago’s ongoing<br />

efforts toward implementing more environmentally sustainable buildings and civil<br />

infrastructure, incorporating best practice guidance for planning, operations and<br />

maintenance of all City airport facilities and functions, and those of its tenants.<br />

The purpose of the SAM is to integrate airport-specific sustainable planning and<br />

practices early in the design process, through planning, construction, operations,<br />

maintenance and all airport functions with minimal impact to schedule or budget.<br />

To achieve greater success, the SAM should be considered in every step of a<br />

project.<br />

Landrum & Brown Page 298<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

While certain elements of the SAM are specific to the CDA, they can easily be<br />

customized and interpreted for any airport’s unique environment. The vast<br />

majority of SAM’s guidance is already applicable to any airport. The SAM provides<br />

direction and is a guideline for incorporation of as many sustainable elements into a<br />

project as are feasible, beyond those elements that are required through an<br />

individual project’s contract specifications and design standards.<br />

The SAM has been drawn in large part from the LEED Green Building Rating<br />

System and the CDA strongly encourages all applicable airport projects to seek<br />

individual LEED certification in addition to incorporating sustainable elements to the<br />

greatest extent possible and practicable. The SAM is also based on existing federal,<br />

state, and local regulatory requirements with additional sustainable and best<br />

practice environmental strategies and considerations. The guidance provided does<br />

not supersede, but is intended to supplement such regulatory requirements.<br />

Los Angeles World Airports (LAWA) Sustainable Airport <strong>Planning</strong> Design<br />

and Construction Guidelines<br />

Los Angeles World Airports (LAWA) has developed sustainable practices that move<br />

beyond environmental stewardship and integrate economic growth (e.g. use of local<br />

contractors and suppliers) and social responsibility (e.g. implementing fair labor<br />

practices) in their operations. LAWA’s multi-level embrace of sustainability is<br />

enhanced by its use of the Triple Bottom Line philosophy, recognizing that in order<br />

to be sustainable, LAWA’s success should not only be measured by the traditional<br />

bottom line of financial performance but also by its impact on the local, regional<br />

and global economy, environment, and society. LAWA’s sustainability commitment<br />

not only shapes its internal business practices, but also its external relationships<br />

with its tenants, contractors, passengers, suppliers, peers and neighboring<br />

communities.<br />

DRAFT<br />

With the development of the Sustainable Airport <strong>Planning</strong>, Design and Construction<br />

Guidelines (LSAG), LAWA intends to meet its commitment to become the global<br />

leader in airport sustainability through building green infrastructure and being held<br />

to the highest sustainability standards. LSAG is included in all LAWA’s big<br />

documents, design specification and construction contracts. LSAG goes beyond<br />

LEED and provides a set of performance standards and a rating system for both<br />

horizontal and vertical airport projects. LSAG is a compilation of sustainable<br />

planning, design and construction practices that meet the unique circumstances and<br />

needs of an airport. LSAG builds upon the LEED rating systems for buildings.<br />

Because of this overlap between LSAG and LEED, LAWA recommends LEED silver<br />

certification for all building projects.<br />

8.3.3 EXAMPLES OF AIRPORT TERMINAL SUSTAINABLE DESIGN<br />

PROJECTS<br />

This section contains a review of sustainability programs at a selected set of other<br />

major U.S. airports that resulted in sustainable design, construction, and<br />

operation/maintenance of terminal buildings.<br />

Landrum & Brown Page 299<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

San Francisco International Airport (SFO) <strong>Terminal</strong> 2<br />

SFO’s mission is to be the airport of choice for passengers, the airlines, and for the<br />

industry; and they recognize the importance that environmental sustainability plays<br />

in helping achieve this goal. The Airport is committed to drastically reducing its<br />

environmental impact over the next decade by working to reduce contributions to<br />

global warming, improve air and water quality, reduce noise impacts, and preserve<br />

natural resources. During the past several years SFO has met many milestones in<br />

environmental achievements and resource conservation including the initiatives<br />

listed in this section.<br />

In November 2010, SFO announced that the designed renovation of the Airport’s<br />

<strong>Terminal</strong> 2 (SFO T2) is the first LEED Gold-registered airport terminal in the<br />

United States. The 640,000 square-foot terminal opened in April 2011 and features<br />

progressive sustainability measures that aim to inspire people to live more<br />

sustainably, as summarized below:<br />

<br />

<br />

<br />

Hydration Stations will enable flyers to fill reusable water bottles once past<br />

security, reducing the significant volume of waste created by single-use<br />

water bottles. While native San Francisco travelers will soon adapt to this<br />

amenity, travelers from other cities will also see these stations, triggering<br />

their awareness of the possibility of traveling with reusable water bottles.<br />

Designed to be a teaching tool, creative signage engages travelers and<br />

educates T2's more than 6 million visitors on the terminal's sustainable<br />

features.<br />

Local food: The terminal will feature local-organic food vendors, offering<br />

wholesome food grown and prepared in a healthful manner.<br />

Removing complexity: Three double-height, naturally illuminated spaces<br />

greet passengers, intuitively guiding them at key decision-making points,<br />

such as post-security, pre-baggage claim and the departure lounge.<br />

The natural daylight makes the terminal easier for travelers to navigate,<br />

creates a more healthy environment in which to travel, and helps save<br />

electricity used for lighting during the day.<br />

Building Materials Savings: By reusing a substantial portion of the<br />

infrastructure of the existing building in the renovated T2, SFO generated<br />

cost savings and reduced the global warming impact of the new terminal.<br />

<br />

The incorporation of energy efficient lighting and efficient machinery will<br />

reduce electrical energy consumption by 2.9 gigawatt hours per year, and<br />

natural gas consumption by 116,000 therms per year, resulting in a<br />

reduction of 1,640 tons of CO 2 emissions per year.<br />

Employees at SFO T2 also benefit from sustainable design elements that create a<br />

more sustainable and healthful workplace:<br />

<br />

DRAFT<br />

Take a Deep Breath: SFO’s innovative displacement ventilation system will<br />

use filtered air to improve indoor air quality, while using 20 percent less<br />

energy. The effect will be a more healthy work environment for terminal<br />

employees.<br />

Landrum & Brown Page 300<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

Completing a Multi-Modal Hub: The renovation will connect T2 to BART via<br />

SFO's AirTrain people mover system, so that employees and travelers alike<br />

can easily go from airport to city on mass transit.<br />

Abundant natural light: Skylights and clerestories bring daylight into the<br />

ticketing lobby and retail areas, providing a healthier working environment<br />

while significantly reducing electricity requirements during daylight hours.<br />

<br />

Educating the workforce: In addition to the multiple education and signage<br />

programs throughout the terminal, airport employees will have access to<br />

composting guides at all waste stations that explain the airport’s compost<br />

program, and how, as employees, they can contribute to the airport’s zero<br />

waste goal.<br />

In addition, as with other tenants, SFO’s concession tenants are encouraged to use<br />

green building materials for their facilities and will be required to recycle and<br />

compost.<br />

Los Angeles International Airport (LAX) Tom Bradley International<br />

<strong>Terminal</strong><br />

The rehabilitation of the 1 million-square-foot terminal completed in May 2010<br />

created new concourses and 2 boarding gates to accommodate larger aircraft such<br />

as the Boeing 787 and Airbus A380. At LAX, recycled content was used in glass<br />

walls, metal ceilings, and the carpet (backed with low-VOC adhesives).<br />

Additionally, more than 75 percent of the construction and demolition waste was<br />

recycled or salvaged. New, efficient HVAC and lighting systems were installed—and<br />

green power will came from photovoltaic arrays and from the Los Angeles<br />

Department of Water and Power, which provided 100 percent of the airport’s<br />

electricity from renewable sources.<br />

DRAFT<br />

The Airport is currently increasing the capacity of the west side of the terminal<br />

under the Bradley West Project. This project will add additional gates 18 roomier<br />

boarding gates/waiting areas with 9 able to accommodate new generation aircraft<br />

(Boeing 787 and Airbus A380) in addition to a Great Hall for dining, retail shopping<br />

and passenger amenities beyond passenger security screening.<br />

In accordance with LAWA’s LSAG, the Bradley West Project will optimize the use of<br />

recycles building materials, minimize the amount of energy used in construction<br />

and optimize energy efficiency. In an effort to minimize adverse environmental<br />

impacts from this project on surrounding areas, LAWA will; recycle construction<br />

materials, place concrete mixers and other equipment on site to reduce the number<br />

of trips construction vehicles must take, designate specific routes that construction<br />

vehicles must use, retrofit construction equipment with emission and noise<br />

reduction devices, and control dust.<br />

Landrum & Brown Page 301<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Boston Logan International Airport <strong>Terminal</strong> A<br />

<strong>Terminal</strong> A at Boston Logan International Airport is the world's first air terminal to<br />

earn LEED certification. The terminal was designed with Massport’s Sustainable<br />

Design Goals, in mind, including:<br />

<br />

Asset Management – Increase value and revenue generating potential of<br />

projects<br />

Environmental Benefits/Permitting Strategy – Reduced impacts and<br />

permitting time/costs<br />

<br />

<br />

Citizenship – Positive community impact<br />

Design Excellence – Innovative, aesthetic and responsible design<br />

Sustainable elements incorporated into the design of <strong>Terminal</strong> A include:<br />

<br />

<br />

<br />

<br />

<br />

<br />

Sustainable sites ‐ Curb design promotes HOV access, including bus and<br />

subway; bicycle racks installed near bus and subway stops.<br />

Energy conservation ‐ roofing and paving materials that reflect solar<br />

radiation, master lighting control systems and photo sensors; windows that<br />

maximize natural lighting; low E glass that reduces heat load<br />

Water conservation ‐ low‐flow toilets, waterless urinals, and drip irrigation.<br />

Materials and resources conservation ‐ >10 percent from recycled sources.<br />

Atmosphere protection ‐ no CFC‐based, HCFC‐based, or halon refrigerants.<br />

Enhanced indoor environmental air quality ‐ low and VOC‐free adhesives,<br />

sealants, paints, and carpets; smoking is prohibited inside the terminal<br />

building.<br />

Sustainable elements incorporated into the daily operation of <strong>Terminal</strong> A include:<br />

<br />

<br />

<br />

<br />

<br />

400‐MHz Power/Preconditioned Air at all contact gates<br />

High Occupancy Vehicle (HOV) Promotion<br />

Recycling <strong>Program</strong><br />

DRAFT<br />

Ground Service Equipment (GSE) Conversion<br />

Assist tenants to meet sustainable goals<br />

Landrum & Brown Page 302<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Atlanta Hartsfield-Jackson International Airport, Maynard H. Jackson Jr.<br />

International <strong>Terminal</strong><br />

Opened in May 2012, the 1.2 mil square-foot Maynard H. Jackson Jr. International<br />

<strong>Terminal</strong> has a goal of achieving LEED Silver certification. The City of Atlanta has<br />

planned, designed, and is constructing the terminal in such a way to reflect its<br />

ongoing commitment to sustainability, including the following major elements:<br />

<br />

<br />

<br />

<br />

<br />

<br />

Construction: Contractors were required to use recycled and/or regionally<br />

produced construction materials and sustainable-certified wood products.<br />

Construction waste management programs diverted as much as 75 percent<br />

from disposal.<br />

Water reclamation: One of the most impressive sustainability features of the<br />

international terminal project is a 25,000-cubic-foot “water box.”<br />

The structure collects rainwater from the roof and cleanses it through a<br />

series of filters before releasing it back into the environment. The process<br />

greatly reduces the building’s environmental impact on surrounding<br />

groundwater.<br />

Recycling: The Airport’s recycling program is being extended to the<br />

international terminal and Concourse F. The program will include<br />

source-separated recycling, organics and composting containers.<br />

Water conservation: Low-flow restroom fixtures throughout the facility,<br />

along with highly efficient cooling and heating systems, will cut water usage,<br />

saving more than 40,000 gallons annually.<br />

Carbon footprint reduction: Several sustainable-design features of the project<br />

will limit the overall greenhouse gases emitted as a result of international<br />

terminal operations.<br />

Energy conservation: Environmental conservation played a role in the<br />

selection of finishes and building elements, such as insulated glass for the<br />

front façade and throughout the building. Energy-efficient lighting and<br />

equipment also greatly will reduce the use of electricity and natural gas.<br />

Gate facilities: All Concourse F gates provide preconditioned air and 400<br />

hertz power supplies for aircraft. This cuts jet fuel use dramatically, because<br />

aircraft auxiliary power units are not required to power or cool aircraft at the<br />

gates.<br />

<br />

DRAFT<br />

Plug-in electrical chargers for ground services equipment: These chargers<br />

will be available at all Concourse F gates, saving fuel and reducing<br />

greenhouse gas emissions.<br />

Preferential parking for alternative fuel vehicles: The international hourly<br />

parking deck will feature 14 close-in parking spaces for alternative fuel<br />

vehicles as well as 14 parking spaces for vanpools and carpools.<br />

Indoor air quality: To ensure the quality of indoor air, the international<br />

terminal project incorporates low-chemical-emitting paints, sealants,<br />

carpeting and adhesives as well as environmentally friendly cleaning products<br />

and techniques. Increased ventilation and monitoring of incoming outdoor<br />

air also will enhance air quality.<br />

Landrum & Brown Page 303<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

<br />

Educational outreach: Quick Read (QR) codes, which passengers can scan<br />

with their smartphones, will link to web-based information about<br />

sustainability initiatives.<br />

8.3.4 PARTNERING OPPORTUNITIES<br />

There are many opportunities for grants, rebates, incentives and credits available<br />

from Federal, State and private sources, for which units of local government can<br />

apply. Resources to research such programs include the following:<br />

<br />

www.dsireusa.org is a comprehensive source of information on state, local,<br />

utility and federal incentives and policies that promote renewable energy and<br />

energy efficiency.<br />

eCivis ® Grants Network (www.ecivis.com) provides grants management<br />

software for accurate grants information, reporting, and management used<br />

by governments and community organizations.<br />

<br />

ACRP Synthesis 24: Strategies and Financing Opportunities for Airport<br />

Environmental <strong>Program</strong>s (http://onlinepubs.trb.org/onlinepubs/acrp/<br />

acrp_syn_024.pdf). The purpose of this ACRP synthesis is to provide a<br />

comprehensive summary of those funding opportunities, programs, and<br />

strategies available to airports to assist them in meeting their environmental<br />

responsibilities or undertaking environmental initiatives.<br />

Depending on the technology/initiative under consideration, there may also be<br />

funding available for participation in a test or demonstration program.<br />

8.3.5 DEVELOPMENT OF PROGRAM SUSTAINABILITY GOALS<br />

Sustainability has been at the forefront during the New <strong>Terminal</strong> <strong>Advance</strong> <strong>Planning</strong><br />

<strong>Study</strong>. One of the criteria in the selection of the central terminal core location for<br />

the terminal development as opposed to the south site included efforts to try and<br />

take advantage of existing infrastructure. This would result in less of an<br />

environmental impact as opposed to building on a green site which would cause<br />

destruction of natural resources including wetlands, streams, and natural vegetated<br />

habitat. A sustainable approach was also considered for the specific site of the<br />

terminal development within the central terminal core.<br />

Next Steps<br />

DRAFT<br />

The City has adopted environmental improvement goals as listed below. As the<br />

planning and design continue, a sustainability policy or mission statement specific<br />

to the terminal development project should be developed with KCAD.<br />

Goal 1 – Improve energy management by increasing energy efficiency in production<br />

processes, incorporating energy conservation into facility operations and designs, and<br />

using more renewable or sustainable energy resources.<br />

Goal 2 – Demonstrate improvements in preservation and restoration of natural<br />

resources and habitats such as wetlands, forests, water bodies and prairies, as well as<br />

manage facility properties and buildings to reduce environmental impacts.<br />

Landrum & Brown Page 304<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Goal 3 – Reduce air emissions from facilities through pollution prevention initiatives<br />

and emission control strategies. Reduce air emissions from mobile sources by reducing<br />

environmental impacts of shipping and receiving, fleet operations and employee<br />

commuting.<br />

Goal 4 – Incorporate green solutions, whenever possible and appropriate, during the<br />

planning process into City policies, projects and programs.<br />

Goal 5 – Protect employee health and the environment by ensuring that training<br />

requirements for individuals are identified; that training opportunities are made<br />

available and are carried out; that training is recorded and tracked; and that training<br />

requirements are monitored, revised, and refresher training provided, as appropriate,<br />

to maintain competence.<br />

Goal 6 – Create a cleaner City by implementing actions that reduce illegal dumping<br />

and improve the City's response to illegal dumping.<br />

In discussion with KCAD preliminary goals include LEED certification, a potential<br />

green roof on top of the proposed new six level parking garage and the desire to<br />

construct a more efficient stormwater and glycol collection system for the new<br />

terminal. A baseline inventory should be conducted for defined sustainability<br />

categories in order to set targets for future performance. Several of the<br />

Sustainability categories are listed below.<br />

<br />

<br />

<br />

<br />

<br />

<br />

Air Emissions Reductions<br />

Materials Management<br />

Energy Initiatives<br />

Water Quality<br />

Construction Practices<br />

DRAFT<br />

Community Outreach and stakeholder relationships<br />

Further the Airport could take this opportunity to develop a sustainable plan not<br />

just for the new terminal development project but for all airport activities.<br />

Landrum & Brown Page 305<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

9. PROGRAM IMPLEMENTATION<br />

9.1 Introduction<br />

The preceding chapters presented a description of the development projects<br />

associated with the construction of a new 42 gate terminal to accommodate the<br />

projected aviation needs at Kansas City International Airport (KCI) over the next<br />

20 years (2032). This chapter presents a description of the projects associated<br />

with the new terminal program and each development phase along with a<br />

preliminary timeline for implementing the new terminal program. Also included is<br />

an order-of-magnitude cost estimate for the proposed new terminal program<br />

projects.<br />

9.2 <strong>Terminal</strong> Development Phasing Summary<br />

In practice, airport projects will be undertaken only when demand warrants, rather<br />

than in accordance with a projected schedule developed in advance. Factors that<br />

can trigger the need to proceed with a particular airport development project can<br />

range from tenant demands for landside and support facilities, to airside and<br />

terminal capacity requirements, to renewing and replacing aging and inefficient<br />

infrastructure. The need for each development project will materialize as the<br />

associated demand level that triggers the need for expansion increases. However,<br />

in the case of the new terminal program most of the associated projects will need<br />

to be implemented in a very short and sequenced timeframe. As such, the<br />

proposed new terminal projects have been divided into three phases with the<br />

beginning of ground breaking activities to opening day, along with a post opening<br />

day set of projects.<br />

9.2.1 PHASE 1 TERMINAL DEVELOPMENT PROJECTS<br />

The Phase 1 projects are those associated with pre-construction activities and<br />

implementation of temporary construction works needed to open up the existing<br />

<strong>Terminal</strong> A site for development of the new terminal development program. These<br />

projects include the following:<br />

<br />

<br />

<br />

DRAFT<br />

Consolidation of remaining airlines to <strong>Terminal</strong> C<br />

Construction of temporary roads to maintain access to <strong>Terminal</strong>s B and C<br />

Construction of temporary utility connections to maintain utility access to<br />

<strong>Terminal</strong>s A and C<br />

Landrum & Brown Page 306<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

9.2.2 PHASE 2 TERMINAL DEVELOPMENT PROJECTS<br />

The Phase 2 projects are the projects associated with construction of the initial<br />

opening phase of the new terminal and parking garage. These projects include the<br />

following:<br />

<br />

<br />

<br />

Construction of a new 37 gate terminal facility and associated roadways<br />

Construction of the first phase of a new 7,500 space parking garage with<br />

a commercial vehicle plaza and associated access roadways<br />

Construction of a new aircraft apron and taxiway/taxilane system (Phase<br />

1A, 1B and 1D)<br />

Construction of a new common use aircraft deicing ramp area (Phase 1C)<br />

and storage facility<br />

<br />

Construction of a new two-level terminal curbfront and loop roadway<br />

9.2.3 PHASE 3 TERMINAL DEVELOPMENT PROJECTS<br />

The Phase 3 projects are projects that must be completed after all airlines are<br />

relocated from <strong>Terminal</strong> B to the new terminal. These projects include the<br />

following:<br />

<br />

<br />

Construction of the second phase of the new parking garage (south wing)<br />

Construction of the new aircraft apron and taxiway/taxilane system (Phase<br />

2A and 2C)<br />

Construct a new common use aircraft deicing ramp area (Phase 2B)<br />

<br />

Construction of the final tie-ins of the upper-level terminal curbfront and loop<br />

roadway<br />

9.2.4 POST OPENING DAY (2025) and BEYOND TERMINAL<br />

DEVELOPMENT PROJECTS<br />

The post opening day projects are not anticipated to be needed as a part of the<br />

initial build (2025). The post opening day terminal development projects include<br />

the following:<br />

<br />

DRAFT<br />

Expansion (as needed) of the terminal to 42 gates<br />

Landrum & Brown Page 307<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

9.3 Capital Costs of the New <strong>Terminal</strong> <strong>Program</strong><br />

Table 9.3-1, <strong>Terminal</strong> Development <strong>Program</strong> Capital Costs, presents a<br />

summary of capital costs for the new terminal program. Estimated construction<br />

costs are in 2013 dollars and include “soft” costs associated with services for design<br />

and program/construction management. A 15 percent estimating contingency has<br />

been added to the construction costs, along with a five percent owner’s<br />

contingency, seven percent design/engineering, ten percent program/construction<br />

management, and one percent for permits, testing, and inspection. When a<br />

construction time period is determined, it is suggested that the costs be inflated to<br />

the proposed construction year of a project.<br />

Table 9.3-1<br />

TERMINAL DEVELOPMENT PROGRAM CAPITAL COSTS<br />

DEVELOPMENT PHASE COST ($2013)<br />

<strong>Terminal</strong> $680,740,825<br />

Landside 319,761,975<br />

Civil Airside $203,235,630<br />

CUP Modifications $19,609,043<br />

TOTAL $1,223,347,473<br />

9.4 Enabling Projects<br />

DRAFT<br />

This section of the PCD describes the projects that will help facilitate the<br />

development of the new terminal at Site A. Enabling projects identified include<br />

temporary access roadways, temporary and relocated utility lines, and other<br />

enabling projects and are described above as Phase 1 <strong>Terminal</strong> Development<br />

Projects.<br />

9.4.1 TEMPORARY ACCESS ROADWAYS<br />

In order to isolate the existing <strong>Terminal</strong> A site for construction of the new terminal<br />

while maintaining access to <strong>Terminal</strong>s B and C a series of temporary roadway<br />

connections need to be constructed. These temporary roadways are depicted in<br />

Figure 9.4-1, Temporary Access Roadways, below.<br />

Landrum & Brown Page 308<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Figure 9.4-1<br />

TEMPORARY ACCESS ROADWAYS<br />

Parking traffic crosses outbound<br />

<strong>Terminal</strong> B flow<br />

Commercial access to <strong>Terminal</strong> C –<br />

reverse flow<br />

Temporary connectors from Cookingham Drive to International Circle and<br />

International Circle to both the <strong>Terminal</strong> B and <strong>Terminal</strong> C access ramps would be<br />

constructed to route inbound traffic to <strong>Terminal</strong>s B and C without having to travel<br />

through the new terminal construction site. Likewise, temporary connectors from<br />

<strong>Terminal</strong>s B and C access ramps to a new temporary exit roadway system would be<br />

constructed ass shown in Exhibit 9.4-1. Once complete these temporary roadways<br />

would allow for unencumbered access to <strong>Terminal</strong>s B and C during the construction<br />

of the new terminal and its associated infrastructure improvements. Once the new<br />

terminal is open for operations it is anticipated that the temporary roadways would<br />

be removed.<br />

9.4.2 TEMPORARY AND RELOCATED UTILITY LINES<br />

Parking traffic crosses outbound<br />

<strong>Terminal</strong> C flow<br />

DRAFT<br />

In order to maintain access to <strong>Terminal</strong>s B and C to critical utility infrastructure<br />

during construction, a number of utility systems will need to be temporarily<br />

rerouted during construction. These systems include a temporary or secondary<br />

connection of the aircraft hydrant fueling system bypassing the <strong>Terminal</strong> A site, a<br />

new connector from the chilled water plant to <strong>Terminal</strong>s B and C, and new<br />

connectors for the of the 12.5 KV duct bank and airfield lighting systems.<br />

These new and/or temporary infrastructure systems are necessary to facilitate<br />

Landrum & Brown Page 309<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

unencumbered connection to critical utility systems necessary to maintain full<br />

operations at <strong>Terminal</strong>s B and C during the construction of the new terminal and<br />

parking garage.<br />

9.4.3 OTHER ENABLING PROJECTS<br />

One of the first projects needed to allow for the new terminal program to move<br />

forward is the relocation of existing airlines on <strong>Terminal</strong> A to <strong>Terminal</strong> C. These<br />

airlines include United Airlines and US Airways. United and US Airways are<br />

currently operating in <strong>Terminal</strong> A and plans are under development to consolidate<br />

these airlines with the other airlines already operating on <strong>Terminal</strong> C today. It has<br />

been determined that there is adequate space on <strong>Terminal</strong> C to accommodate the<br />

United and US Air operations without any operational impacts to the other airlines.<br />

It is anticipated that these move would take place well in advance of start of<br />

construction of the new terminal in order to not have a negative effect on airline<br />

operations.<br />

9.5 LEED Gold Certification<br />

The City of Kansas City, Missouri currently has a requirement that all new public<br />

projects built in their jurisdiction achieve a LEED Gold Rating from the U.S. Green<br />

Building Council. Although a terminal building may be designed in a manner to<br />

meet LEED Gold standards, there are many factors that need to be taken into<br />

consideration as to which level of LEED certification is appropriate and/or should be<br />

achieved. However, in order to plan for the potential to include LEED Gold design<br />

elements in the new terminal, the program capital cost estimate includes a three<br />

percent contingency factor for incorporating LEED Gold elements in to the terminal<br />

building design.<br />

DRAFT<br />

The following list contains items for consideration with the goal of reaching LEED<br />

Gold. Each item needs to be evaluated to determine the potential of saving energy<br />

and/or resources versus the project cost (additional expense, schedule delay,<br />

technical feasibility, etc.).<br />

1. Compare Point of Use (POU) Pre-Conditioned Air (PCA) and Central<br />

PCA: PCA is used to provide air conditioning and heating inside aircraft while<br />

parked at the gate. This provides passenger comfort and allows the aircraft<br />

to turn off its auxiliary power unit, thereby saving jet fuel and the associated<br />

emissions. Analysis is required to determine if a centralized PCA system is<br />

cost effective over Ground Power Units. Items to consider include first costs,<br />

operation and maintenance, system diversity, space requirements and<br />

flexibility for the various aircraft planned at KCI airport.<br />

2. Rain Harvesting: Collect rainwater to use for irrigation and other nonpotable<br />

water uses. Evaluate rainwater collection system cost and space<br />

required versus amount of treated water savings.<br />

Landrum & Brown Page 310<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

3. Grey Water for Restroom Use: Use pipe water from grey water storage to<br />

use for flushing bathroom fixtures. Evaluate system capacity and feasibility<br />

for the New <strong>Terminal</strong> and investigate the type of filtration system needed.<br />

Determine code restrictions for this type of project<br />

4. Ground Source Equipment (GSE) Electrification: Provide the ability for<br />

KCI to use electric GSE rather than those with internal combustion engines.<br />

Electric GSE will eliminate the need for diesel fuel and the associated<br />

greenhouse gas emissions. It has been estimated that electric GSE are<br />

90 percent cleaner and 75 percent less expensive to operate — even after<br />

taking power plant emissions into account. These savings need to be<br />

weighed against the additional electrical service needed and space required<br />

for GSE chargers.<br />

5. Day Lighting and Lighting Controls: Work with project architects to<br />

evaluate day lighting potential with the building envelope design.<br />

Investigate appropriate lighting controls balancing energy savings with the<br />

Airport’s light requirements, as public safety is an issue.<br />

6. Energy Management Control System (EMCS) Energy Reduction<br />

Strategies: Propose strategies to be programmed into the EMCS that will<br />

save energy while maintaining the Airport’s fundamental mission.<br />

7. Monitoring and Verification Strategies (M&V): Consider appropriate<br />

energy measurement instrumentation and software with the goal of<br />

maintaining energy and water savings into future years.<br />

8. Biofuels & CNG for Vehicles: It is highly probable that GSE electrification<br />

will not be 100 percent and consequently will need some fuels. Look at<br />

options and feasibility for alternative fuels for Airport vehicles.<br />

DRAFT<br />

9. Recycling <strong>Program</strong>: Outline a recycling program for the demolished<br />

pavement and construction materials. Develop a second recycling program<br />

for the long term regarding airport waste, i.e., sorting facility for carbon<br />

waste streams to go to composting, metals for potential sale, and deicing<br />

fluid for sale in secondary markets.<br />

10.Solar PV: This was discussed at a previous meeting with KCP&L. KCP&L<br />

resource management group provided the following “ballpark” information for<br />

renewable energy incentives regarding a renewable energy system size<br />

range equal to 500 to 1000 kW:<br />

­ Any renewable - $30-$35/MWh<br />

­ Solar RECs would be another $8 to $10/MWh in addition to the<br />

renewable energy<br />

11.Cogeneration: The price of electricity is too low to justify. KCP&L resource<br />

management group provided the following “ballpark” information for<br />

renewable energy incentives regarding a renewable energy system size<br />

range equal to 500 to 1000 kW:<br />

­ Co-Gen: $25-$35 / MWh<br />

12.Thermal Energy Storage (TES): There is no “on-peak” or time of day<br />

demand shift opportunity and no up-front incentive for TES by KCP&L.<br />

Landrum & Brown Page 311<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

9.6 Implementation Timeline<br />

There are several elements needed to implement the development of the new<br />

terminal and its associated projects. Figure 9.6-1, Preliminary <strong>Program</strong><br />

Implementation Timeline presents an early schedule for implementing actions<br />

required to develop the new terminal program. These elements include completing<br />

an environmental assessment in accordance with NEPA, selecting a program<br />

manager, the construction tender process, and the overall construction process. It<br />

is anticipated that the projected opening day of the first phase (Phase 1 and 2<br />

projects) of the new terminal would be 1-February-2019 with subsequent phases<br />

(Phase 3 projects) opening later that same year. Additional phases of the terminal<br />

program beyond the 2025 requirements would be developed as needed and when<br />

demand warrants their construction.<br />

Figure 9.6-1<br />

PRELIMINARY PROGRAM IMPLEMENTATION TIMELINE<br />

NEW TERMINAL - PRELIMINARY PROGRAM SCHEDULE<br />

Duration<br />

Estimated Estimated<br />

(Calendar<br />

Start Date End Date<br />

Days)<br />

Description<br />

Environmental Assessment<br />

29-May-13 12-Jul-13 45 Publish Draft EA/Public Comment Period<br />

27-Jun-13 27-Jun-13 1 Public Workshop/ Public Hearing<br />

30-Aug-13 30-Aug-13 1 Publish Final EA<br />

30-Aug-13 30-Sep-13 10-30 FAA prepares FONSI<br />

Project <strong>Program</strong> Management<br />

3-Jun-13 10-Mar-14 280 Select <strong>Program</strong> Manager<br />

17-Mar-14 13-Oct-14 210 Select Design Architect/Engineers<br />

17-Mar-14 28-Jan-19 1,778 <strong>Program</strong> Management/Construction Management<br />

20-Oct-14 16-May-16 574 <strong>Terminal</strong> Design<br />

20-Oct-14 12-Oct-15 357 Parking Structure Design<br />

20-Oct-14 5-Oct-15 350 Civil Airside Design<br />

20-Oct-14 18-Jan-16 455<br />

Landside Roadway Design - Multiple Bid<br />

Packages/Phases<br />

20-Oct-14 19-Oct-15 364 Utilities Design - Multiple Bid Packages/Phases<br />

Construction Tender Process<br />

12-Oct-15 11-Apr-16 182<br />

Civil Airside Construction Tender Process - D-B-B FAA<br />

Grant Eligible<br />

25-Jan-16 25-Jul-16 182<br />

Landside Roadways Construction Tender Process - D-<br />

B-B Multiple Phases/Packages<br />

26-Oct-15 2-May-16 189<br />

Utilities Construction Tender Process - D-B-B Multiple<br />

Phases/Packages<br />

14-Sep-15 27-Jun-16 287 <strong>Terminal</strong> Construction Tender Process - CM @ Risk<br />

8-Jun-15 8-Feb-16 245<br />

Parking Structure Construction Tender Process - CM<br />

@ Risk or Design/Build or D-B-B<br />

Construction Process<br />

28-Jun-16 12-Dec-18 897 <strong>Terminal</strong> Construction<br />

18-Apr-16 12-Mar-18 693 Apron/Airfield Construction<br />

15-Feb-16 12-Feb-18 728 Parking Structure Construction<br />

19-Oct-15 19-Sep-18 1,066 Landside Roadways Construction - Multiple Phases<br />

19-Oct-15 19-Sep-18 1,066 Utilities Construction - Multiple Phases<br />

1-Feb-19 1-Feb-19 1 <strong>Terminal</strong> Opening Day<br />

DRAFT<br />

Landrum & Brown Page 312<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

9.7 <strong>Program</strong> Delivery Methods<br />

There are several methodologies that could be employed to implement the new<br />

terminal development program. The program delivery methods are generally<br />

divided in to traditional and non-traditional concepts. Examples of traditional<br />

delivery methods include a design-bid-build methodology and a design-build<br />

methodology. An example of a non-traditional delivery method would be to find an<br />

entity that would finance, design, construct, operate and maintain the new terminal<br />

under a long-term operating and lease agreement with the City.<br />

Below is a brief description of each of these methods of delivery contrasting their<br />

advantages and disadvantages to the KCAD.<br />

9.7.1 DESIGN-BID-BUILD<br />

Design-Bid-Build is the most common form of project delivery. It is typically<br />

executed in three phases with three prime players. Many times an owner would<br />

need to also hire a <strong>Program</strong> Manager/Construction Manager to augment their staff<br />

to assist in overseeing the management and implementation of the construction<br />

program. Some features of the methodology include:<br />

Independent contracts between the owner and the architect and the owner<br />

and the contractor<br />

Results in a linear sequence of work<br />

Common with public owners with requirements to select low bid<br />

Below are listed some of the advantages<br />

and disadvantages of this delivery method.<br />

Advantages<br />

Widespread use in industry<br />

Familiarity among owners<br />

Clear roles assigned to each party<br />

Design complete prior to construction<br />

Linear process<br />

Disadvantages<br />

DRAFT<br />

Relatively lengthy process<br />

Multiple contracts to manage<br />

Lacks single point of responsibility<br />

Owner at-risk for detecting design/ construction errors<br />

Construction costs unknown until contract award<br />

Change orders and delay claims are more likely<br />

Landrum & Brown Page 313<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

9.7.2 DESIGN-BUILD<br />

Design-Build is also a fairly common form of project delivery in today’s construction<br />

industry. In this case, an owner contracts with a single entity that would be<br />

responsible for delivery of both design and construction services. With this delivery<br />

method a contractor is usually in the lead with a design team as a sub-contractor.<br />

Similar to the Design-Bid-Build process, many times an owner would need to also<br />

hire a <strong>Program</strong> Manager/Construction Manager to augment their staff to assist in<br />

overseeing the management and implementation of the construction program.<br />

Some features of the methodology include:<br />

Single point of responsibility<br />

Results in a shorter delivery period work<br />

Becoming increasingly more common with public owners looking to minimize<br />

risk<br />

The process for implementing this method of<br />

project delivery would include:<br />

Two step process: design and<br />

construction<br />

Design is completed by<br />

architect/engineer<br />

Construction is completed by<br />

contractor<br />

Early cost commitment is made<br />

Below are listed some of the advantages<br />

and disadvantages of this delivery method.<br />

Advantages<br />

Single point of responsibility<br />

Minimizes owner’s risks<br />

Shortened project delivery time (varies)<br />

Guaranteed pricing on a project<br />

Reduces change orders<br />

Minimized claims and damage<br />

Better design control<br />

Disadvantages<br />

DRAFT<br />

Complex delivery method<br />

Lack of direct communication between owner/architect and owner/contractor<br />

Potential for compromises in quality to meet budget<br />

Landrum & Brown Page 314<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

The figure below graphically depicts the timing differences in the two previously<br />

describe delivery methods.<br />

9.7.3 FINANCE, DESIGN, CONSTRUCT, OPERATE AND MAINTAIN<br />

This delivery method is very similar to the Design-Build delivery method in terms of<br />

the overall timing of the design and construction process. Where it differs is where<br />

the contracted entity also brings the necessary financing to develop the terminal<br />

program in exchange for a long-term lease to operate and maintain the terminal<br />

facilities. The term on the lease is usually tied to the amount of time needed to<br />

recoup the initial investment made by the contracted entity. This methodology is<br />

used in many markets around the world and is increasingly becoming a viable<br />

option for airport owners in this country that have difficulties in financing large<br />

development programs. The advantages to this methodology are that the owner<br />

would not need to arrange for financing of the terminals program and would only<br />

coordinate with one management entity. Disadvantages to this delivery method<br />

are that the owner would lose some level of control during the design and<br />

construction process and would lose the management of the terminal asset for the<br />

duration of the lease period.<br />

DRAFT<br />

It is recommended that KCAD continue to keep their options open and continue to<br />

explore both traditional and non-traditional project delivery methods.<br />

Landrum & Brown Page 315<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

10. FINANCIAL IMPLEMENTATION PLAN<br />

Objective: Draft a document that defines the key inputs, assumptions, and<br />

conclusions of the financial analysis.<br />

Description: The final draft working paper will present the results of the preceding<br />

analyses by outlining the overall KCI terminal development plan and the<br />

recommended refinements to the new South <strong>Terminal</strong> Complex Plan based on<br />

financial feasibility.<br />

Deliverables: Copies of the draft terminal development financial plan working<br />

paper will be prepared for distribution to the KCAD management for their review<br />

and comment. In addition, after review and revision an Executive Summary of the<br />

working paper, approximately six (6) to eight (8) pages in size, will be developed at<br />

a high quality, suitable for officials, that addresses the key issues and findings of<br />

the working paper.<br />

10.1 Cost and Affordability of New Replacement <strong>Terminal</strong><br />

10.1.1 PROJECT OVERVIEW<br />

The Kansas City International Airport (KCI) has commissioned a financial analysis<br />

and review of the construction of a new single terminal complex to replace the<br />

airport’s antiquated three terminal complex. The new terminal is projected to open<br />

for operations in the 1 st quarter of fiscal year (FY) 2019 with construction beginning<br />

in FY2016. This section of the report presents a summary of the estimated project<br />

costs, the assumed sources of project funding, and the analysis and findings of a<br />

financial affordability model.<br />

DRAFT<br />

10.1.2 PROJECT COST SUMMARY<br />

Project costs are currently estimated to be approximately $1.2 billion including<br />

design, project and construction management, and contingency costs. The total is<br />

in 2013 USD and does not include project financing or bond issuance costs that will<br />

be discussed separately. The general project scope includes the demolition of the<br />

existing building and apron, roads and other structures necessary to construct the<br />

first phase of a replacement terminal on the site of the existing <strong>Terminal</strong> A.<br />

The project components are allocated into four major areas: <strong>Terminal</strong>; Landside;<br />

Airside; and Central Utility Plant Modifications.<br />

<strong>Terminal</strong> $680,740,825<br />

Landside 319,761,975<br />

Civil Airside 203,235,630<br />

CUP Modifications 19,609,043<br />

Total $1,223,347,473<br />

Landrum & Brown Page 316<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

10.1.3 SOURCES OF FUNDING<br />

KCI is not in the position to self-fund a project of this scale and will rely on multiple<br />

sources to fund the costs associated with the new terminal project. The airport will<br />

provide some available cash to initially fund preliminary and reimbursable portions<br />

of the overall project. It is anticipated that a percentage of the project will be<br />

eligible for FAA Airport Improvement <strong>Program</strong> (AIP) grants. The two main areas of<br />

source funds will be through the collection of Passenger Facility Charges (PFCs) and<br />

through the issuance of new airport debt in the form of General Airport Revenue<br />

Bonds (GARBs). The debt service on these bonds will be allocated to airport cost<br />

centers and recovered through rates and charges. The financial affordability model<br />

created for KCI incorporates the necessary bond issuance and funding<br />

requirements.<br />

Airport Cash<br />

It is assumed that KCI will have approximately $60 million in cash reserve funds to<br />

initially cover expected reimbursable expenses associated with the terminal project.<br />

These funds are not intended to reduce the amount that will need to be borrowed<br />

through the issuance of GARBs but will be necessary to guarantee preliminary work.<br />

All cash paid out from available cash reserves is expected to be repaid to the fund<br />

upon issuance of new debt.<br />

AIP Grant Money<br />

The airport will be eligible for FAA AIP grant money for select portions of the total<br />

project that relate predominately to increasing capacity, improving safety and<br />

security, and addressing environmental concerns. The AIP grants are allocated to<br />

qualifying airport capital projects on a yearly basis and are dependent, in part,<br />

upon how much money is available in the FAA region’s annual budget. Eligible<br />

projects can receive grants for up to 75 percent of the estimated cost. The model<br />

makes the very conservative assumption of the receipt of $30 million of AIP grant<br />

monies.<br />

PFC Collections<br />

DRAFT<br />

The airlines currently collect a PFC of $4.50 per eligible enplaned passenger at KCI.<br />

It is assumed that there is currently a reserve of nearly $40 million which should<br />

grow to $46 million by the proposed start of the construction process in FY2016.<br />

Future PFC collections to be applied to the new terminal project were estimated at<br />

$250 million based on continuing PFC based terminal capital spending and debt<br />

obligations. The $250 million is reduced by the available $46 million to a total of<br />

$204 million that would be funded through the issuance of new PFC backed bonds.<br />

Throughout the repayment period of 30 years it is assumed that the PFC collection<br />

rate will remain constant at $4.50.<br />

Landrum & Brown Page 317<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

GARB Debt<br />

After considering the available funds from Airport cash, AIP Grants and PFC<br />

Collections, the remainder of the funding will need to come from GARBs.<br />

The GARBs are assumed to be issued in three separate tranches, one each year<br />

during the projected construction phase of FY2016 to FY2018. During these three<br />

phases, interest on the expensed capital will be capitalized and accrued for the<br />

bond issuances. In total, GARBs will be issued for approximately $1.2 billion in<br />

order to cover all of the expected costs after applying the available AIP and PFC<br />

funds. The conservative assumption for cost of capital is between 6.0 and 6.5<br />

percent.<br />

10.1.4 FINANCIAL MODEL METHODOLOGY AND ASSUMPTIONS<br />

The general concepts used in this affordability model assume that the airport will<br />

first replace the existing rates and charges agreement at KCI with a system residual<br />

model that recovers all net airport operational expenses and capital improvement<br />

expenses through landing fees, terminal rents and facility charges. The model<br />

assumes that the new terminal will be constructed by the end of FY2018 and be<br />

operational at the beginning of FY2019. The majority of financing will come from<br />

GARB and PFC bond offerings that will begin in FY2016. GARB offerings are<br />

projected to be done in three tranches (annually from FY2016-2018) with interest<br />

capitalized until FY2019 when the new terminal opens. New PFC debt service<br />

payments are scheduled to begin in FY2017, and the residual funds in the existing<br />

PFC reserve fund will be used first in the construction process to meet early<br />

planning and design financial requirements.<br />

DRAFT<br />

The model assumes a continuation of existing revenue and expense streams that<br />

are both scheduled to grow at a modest rate of 3 percent annually. Capital<br />

improvement projects currently scheduled in the 5 Year capital improvement<br />

program (CIP) to maintain the existing airfield and terminals are incorporated into<br />

the model and future baseline expenditure levels are assumed for the new terminal<br />

beginning in FY2019. CIP expenditures of the new terminal are set to increase at<br />

the same 3 percent growth rate beginning in FY2020. Starting in FY2019, terminal<br />

concession revenues are assumed to increase 200 percent because of the improved<br />

terminal concession layout. Operating and maintenance (O&M) expenses are<br />

expected to be reduced by approximately 15 percent with a new and more efficient<br />

terminal design.<br />

The airline cost per enplanement (CPE) calculation includes landing fees, terminal<br />

rents, boarding bridge fees, and airline prepaid expenses. Annual landed weight<br />

and enplanement figures are provided in the 2012 Kansas City International Airport<br />

Master Plan Forecast update. The CPE was used as the barometer for affordability<br />

and compared to other medium hub airports CPE levels.<br />

Landrum & Brown Page 318<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Affordability Model Assumptions<br />

General<br />

• Baseline Project Costing equal to $1.2 billion<br />

• Airport will open for operations at the beginning of 2019<br />

• Base Cost Center allocations are 83.4% <strong>Terminal</strong> & Landside and 16.6%<br />

Airfield<br />

• New System Residual Lease Agreement to begin in FY2015<br />

• All Costs, Revenues and Expenses grown at the same inflation growth rates<br />

(2% in 2012-2013, 3% annually thereafter)<br />

• 2012 Airport Cash Reserve estimated at $60 million for modeling purposes<br />

• 2012 PFC reserves estimated at $40 million or modeling purposes<br />

• Operations and Passengers forecasts will be adequately realized<br />

• PFC collection rate held constant at $4.50 per enplanement<br />

Financing<br />

• Three annual capital expenditure phases (2016, 2017, 2018)<br />

• Capital Expenditures will be nearly equal during each year<br />

• Capitalized Interest will accrue during each year<br />

• Cost of Capital will increase during construction (6.0% in FY2016, 6.25% in<br />

FY2017 and 6.5% in FY2018)<br />

• Bond durations for each issuance amortized over 29, 28 and 27 years<br />

• Projected PFC bond proceeds equal to approximately $204 million<br />

• PFC Cash Reserves will be used in the first year of Capital Expenses to reduce<br />

required PFC Bond amount<br />

• $30 million in AIP grant monies expected from FAA<br />

• PFC bond proceeds and AIP grant monies reduce total GARB requirement<br />

Revenues<br />

• 200% increase in terminal concession revenues when new <strong>Terminal</strong> opens<br />

O&M Expenses<br />

DRAFT<br />

• 15% reduction in terminal O&M costs when new <strong>Terminal</strong> opens<br />

• MCI 5 year capital improvement plan estimated outlays incorporated into the<br />

model<br />

• CIP beginning in FY2017 starts at $12 million and increases annually at 3%<br />

• Capital improvement totals allocated at 50% each to the Airfield and<br />

<strong>Terminal</strong> cost centers<br />

Landrum & Brown Page 319<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

10.2 Determinations of Affordability<br />

10.2.1 DEBT PAYMENTS<br />

The annual debt service payments in the model are a combination of the PFC bonds<br />

and GARBs. The annual PFC debt service payment is projected to increase from<br />

$10 million in FY2016 to approximately $25 million in FY2017 after the issuance of<br />

$204 million in PFC backed public bonds. The annual GARB debt service payment is<br />

projected to increase from $22 million in FY2018 to $109 million in 2019 with the<br />

beginning of payments on the new GARB debt (including capitalized interest) of<br />

approximately $1.2 billion. The total outstanding debt for the Kansas City<br />

International Airport in 2019 is expected to reach nearly $1.55 billion.<br />

10.2.2 CPE COMPARISON<br />

Cost per enplanement (CPE) is a common measure of costs to the airlines and thus<br />

relevant to the determination of affordability for a large scale project such as the<br />

construction of new terminal and associated facilities. In 2010, CPE at the Airport<br />

was $4.96 and was near the bottom in cost comparison to other medium hub<br />

airports. The low average cost can be attributed mainly to the age of the existing<br />

terminals and the current rates and charges agreement. In contrast, airports with<br />

newly renovated or newly built terminals are situated toward the right of the<br />

following comparison chart.<br />

Airline Cost per Enplanement<br />

$20.00<br />

$18.00<br />

$16.00<br />

$14.00<br />

$12.00<br />

$10.00<br />

$8.00<br />

$6.00<br />

2010 Medium Hub CPE<br />

(derived from FAA CATS Form 127)<br />

DRAFT<br />

$4.00<br />

$2.00<br />

$-<br />

Sources:<br />

FAA CATS Form 127, Landrum & Brown analysis<br />

Landrum & Brown Page 320<br />

April 2013


KANSAS CITY NEW TERMINAL STUDY<br />

ADVANCE TERMINAL PLANNING STUDY<br />

PROGRAM CRITERIA DOCUMENT<br />

DRAFT<br />

Recent examples of large scale terminal projects have been constructed at<br />

Indianapolis International Airport (IND), San Jose International Airport (SJC) and<br />

Sacramento International Airport (SMF). Each of these airports with new terminals<br />

has an average CPE value of between $11 and $12. The next chart presents the<br />

expected CPE range for the same group of medium hub airports for 2019.<br />

The same new terminal airports are expected to show increasing CPE into the $14<br />

range; and MCI is projected to jump up to nearly $19 with the construction of the<br />

planned $1.2 billion terminal project using the conservative assumptions discussed<br />

above.<br />

$25.00<br />

Projected 2019 Medium Hub CPE<br />

(derived from 2010 FAA CATS Form 127, + 3% AAGR)<br />

Airline Cost per Enplanement<br />

$20.00<br />

$15.00<br />

$10.00<br />

Sources:<br />

$5.00<br />

$-<br />

Medium Hub<br />

Average CPE = $11.72<br />

DRAFT<br />

FAA CATS Form 127, Landrum & Brown analysis<br />

Landrum & Brown Page 321<br />

April 2013


DRAFT

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!