March (pdf) - New York Power Authority
March (pdf) - New York Power Authority
March (pdf) - New York Power Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>March</strong> 29, 2011<br />
5. RM Flynn <strong>Power</strong> Plant 2011 Major Outage –<br />
Capital Expenditure Authorization Request<br />
SUMMARY<br />
The President and Chief Executive Officer submitted the following report:<br />
“The Trustees are requested to approve capital expenditures of $7.195 million for projects associated with<br />
the 2011 RM Flynn <strong>Power</strong> Plant’s (‘Flynn’) major outage and subsequent replacement or upgrade of critical parts<br />
for the RM Flynn gas turbine.<br />
BACKGROUND<br />
“In accordance with the <strong>Authority</strong>’s Expenditure Authorization Procedures, Trustees’ approval is required<br />
for capital expenditures in excess of $3 million.<br />
“Flynn has been in service since May 1994. The plant consists of gas turbine and steam turbine. The<br />
timing of major overhauls and large projects at the plant is based on the recommended maintenance cycles of the<br />
Siemens V84.2 gas turbine. Siemens recommends that the gas turbine be completely overhauled and upgraded<br />
approximately every 33,000 operating hours, which is once every four years. When the plant is shutdown, other<br />
projects which cannot be done while the plant is in service are completed. Flynn’s major outages were completed in<br />
1996, 1999, 2003 and 2007. The next major outage is scheduled for October and November 2011. The projects<br />
described in the discussion section below are crucial to the safe, reliable and efficient operation of the plant.<br />
DISCUSSION<br />
“The Siemens V84.2 gas turbine has two large mixing elbows that are in the hot gas path section which<br />
direct the combustion gases to the turbine section. The mixing elbows that will be removed in 2011 have been in<br />
service for approximately 100,000 hours and are the end of their useful life. <strong>New</strong> mixing elbows will be purchased<br />
for inventory.<br />
“The gas turbine industry in general and Siemens specifically, have determined that the material used to<br />
make the blade wheel in stage 4 of the turbine becomes brittle over time and may fracture under certain conditions.<br />
If the disc fails to pass Non Destructive Examinations (‘NDE’) it will be declared unusable. Published lead time for<br />
this part is over one year. Flynn staff has determined that the safe and prudent action is to replace the disc. The disc<br />
in service will have approximately 150,000 operating hours at the time of the 2011 major outage.<br />
“If compressor blades or diaphragms fail in service, it usually causes severe damage to the turbine. All of<br />
Flynn’s seventeen compressor stages are original and running well beyond the 100,000 hours, the time in which<br />
Siemens recommends replacement. Based on fleet history, Siemens has identified certain stages that are more prone<br />
to failure. Using Siemens’ recommendations, Flynn staff has selected stages 2, 4 and 7 for replacement in 2011.<br />
“Flynn’s gas turbine generator has six lead bushings which connect the generator output to the transmission<br />
system. Some have had component failures related to vibrations. Certain failures have the potential to damage the<br />
generator. Flynn staff thinks it is prudent to replace the bushings in 2011.<br />
“During the 2007 outage, divided seal rings were identified as worn; staff recommends that they be<br />
replaced in 2011.<br />
“At the 2011 major outage, the turbine’s stage 3 blades and stage 2 vanes will be at the end of their useful<br />
life. <strong>New</strong> blades and vanes will be purchased for inventory.<br />
“The Siemens V84.2 gas turbine has two distinct burner decks each of which has six burners. Each deck<br />
has four control valves for fuel gas and fuel oil. The actuators for these valves have typically required frequent<br />
maintenance and have the potential to fail in ways that damage the gas turbine. Siemens has developed actuators<br />
54