National Intergrated Resource Plan 2 - PBMR
National Intergrated Resource Plan 2 - PBMR
National Intergrated Resource Plan 2 - PBMR
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Contents<br />
Page<br />
FOREWORD 2<br />
ACKNOWLEDGEMENTS 3<br />
NIRP2 Reference Case Report 4<br />
NIRP2 Stage 2: Risk and Sensitivity Analyses Report 37<br />
NIRP2 Stage 2 Appendix A:<br />
Summary of Comments on NIRP2 Reference Case 65<br />
NIRP2 Stage 2 Appendix D:<br />
Summary of ARC Comments on NIRP2 Stage 2 report 76<br />
Information provided on CD ROM<br />
inside back cover<br />
NIRP2 Reference Case Appendix 1: Supply-side data,<br />
NIRP2 Reference Case Appendix 2: Results,<br />
NIRP2 Reference Case Appendix 3: Background supply-side data.<br />
NIRP2 Stage 2 Appendix B: Summary of <strong>Plan</strong>s<br />
NIRP2 Stage 2 Appendix C: NIRP2 Stage 2 Database
Foreword<br />
Background<br />
In the light of the Energy Policy White Paper for South Africa and the recent government initiatives for<br />
restructuring of the ESI, the NER introduced the development of a <strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> (NIRP)<br />
as an independent information source to stakeholders and decision-makers for insuring security of the supply.<br />
The first <strong>National</strong> IRP (NIRP1) was completed and published in March 2002.<br />
At the beginning of the year 2003, the NER established the NIRP Advisory and Review Committee (ARC) with<br />
the function to provide wide stakeholders' guidance and contribution to the NIRP development process.<br />
Unlike its predecessor the NIRP 2003/4 (NIRP2) relies on average international data (modified to reflect South<br />
African labor and exchange rates) for the cost and performance of new generation plants. Other important<br />
change from NIRP1 is the inclusion of sensitivity analysis and scenarios to address risk factors and<br />
uncertainties. Further the NIRP2 takes into account the transmission integration costs and losses associated<br />
with the location of the new generation plants.<br />
NIRP2 Studies<br />
2<br />
The NIRP2 has been generated under the guidance of the NER NIRP Advisory and Review Committee (ARC)<br />
by a NIRP team comprising Eskom <strong>Resource</strong>s and Strategy Group, Energy Research Institute of UCT and the<br />
NER. The work carried out for NIRP2 is divided into two stages:<br />
& Stage 1: Development of a reference case<br />
& Stage 2: Development of risk and sensitivity analyses<br />
The NIRP2 reference case was completed and published on the NER Web site on 3 March 2004 while NIRP2<br />
Stage 2: Risk and Sensitivity Analysis - on 22 September 2004.<br />
This publication consists of NIRP2 Stage 1 and 2 reports. Some of the Appendices associated with the main<br />
reports are provided in an electronic format (CD).<br />
The NIRP 2 Reference Case publication contains the following parts:<br />
& NIRP2 Reference Case Report<br />
& Appendix 1: Supply-side data<br />
& Appendix 2: Results<br />
& Appendix 3: Background supply-side data.<br />
The NIRP 2 Stage 2: Risk and Sensitivity analysis includes the following five parts:<br />
& NIRP2 Stage 2 Report,<br />
& Appendix A: Summary of comments on NIRP2 Reference Case<br />
& Appendix B: Summary of <strong>Plan</strong>s<br />
& Appendix C: NIRP2 Stage 2 Data Base Summary<br />
& Appendix D: Summary of ARC Comments on NIRP2 Stage 2 report.
Acknowledgements<br />
The NER acknowledge the guidance, contribution and<br />
valuable suggestions of:<br />
NER NIRP Advisory and Review Committee (ARC):<br />
Project Team:<br />
Chairman: Prof A Eberhard, NER Board<br />
Dr Bianka Belinska, NER<br />
Members: Smunda Mokoena, CEO NER Steve McFadzean, Eskom ISEP<br />
Naresh Singh, EM NER<br />
Johan Prinsloo, Eskom ISEP<br />
Andre Otto, DME<br />
Zaheer Khan, Eskom ISEP<br />
Dr Elsa Du Toit, DME<br />
Andrew Etzinger, Eskom ISEP<br />
Robert Maake, DME<br />
Mavo Solomon, Eskom ISEP<br />
Tseliso Magubela, DME<br />
Moonlight Mbatha, Eskom ISEP<br />
Chris Gadsden, NT<br />
Mark Howells, ERI UCT<br />
Justice Mavhungu, DPE<br />
Glen Heinrich, ERI UCT<br />
Arnot Hepburn, EIUG<br />
Thomas Alfstadt, ERI UCT<br />
Piet van Staden, EIUG<br />
Andrew Kenny, ERI UCT<br />
Dick Kruger, Chamber of Mines<br />
Alison Hughes, ERI UCT<br />
Danny Vengedasamy, SACOB<br />
Rizia Buckas, NER<br />
Manfred Kuster, AMEU<br />
Willie Boeije, NER<br />
Mandla Tshabalala, AMEF<br />
Lambert du Plessis, NER<br />
Gerhard Loedolff, Eskom Generation<br />
Lynette Vajeth, Eskom Generation<br />
WEB Publisher:<br />
June Willis, Eskom Transmission<br />
Michael Barry, Eskom Transmission<br />
Correy Sutherland, NER<br />
Segomoco Scheppers, Eskom Transmission<br />
Erica Johnson, Eskom Transmission<br />
NIRP Contact Person:<br />
Jean Louis Pabot, Eskom KSACS<br />
Hermann FW Oelsner, Darling Windfarm IPP<br />
Dr Bianka Belinska, NER<br />
Robert Siemers, Kelvin IPP Tel: 012-4014650<br />
Donald Bennett, Kelvin IPP Fax: 012-4014687<br />
Prof K Bennett, ERI UCT<br />
Email: bianka.belinska@ner.org.za<br />
3<br />
ARC Management Officer:<br />
Dr Bianka Belinska, NER
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Reference Case<br />
4<br />
COMPILED BY<br />
ISEP Eskom (<strong>Resource</strong>s and Strategy)<br />
AND<br />
Energy Research Institute<br />
University Of Cape Town<br />
AND<br />
The <strong>National</strong> Electricity Regulator<br />
27 February 2004
Reference Case<br />
Executive Summary<br />
INTRODUCTION<br />
In the light of the Energy Policy White Paper for South Africa and the recent government initiatives for<br />
restructuring of the ESI, the NER introduced the development of a <strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> (NIRP)<br />
as an independent information source to stakeholders and decision-makers for insuring security of the supply.<br />
The first <strong>National</strong> IRP (NIRP1) was completed and published in March 2002.<br />
At the beginning of the year 2003, the NER established an IRP Advisory and Review Committee (ARC) to<br />
provide wide stakeholders' contribution to the NIRP process. The main functions of the ARC are to approve the<br />
primary assumptions (technical, economical, environmental and social), evaluate the supply- and demand<br />
options for inclusion in the plan and oversee the development process.<br />
This NIRP is a revision of the first NIRP issued in March 2002 and published on the NER Web site. For the<br />
purposes of these analyses the first NIRP is referred as NIRP1 and the current study as NIRP2.<br />
The NIRP2 has been generated under the guidance and approval of the NER NIRP Advisory and Review<br />
Committee (ARC) by a NIRP team comprising Eskom <strong>Resource</strong>s and Strategy Group, Energy Research<br />
Institute of UCT and the NER.<br />
Unlike its predecessor the NIRP2 relies on average international data (modified to reflect South African labor<br />
and exchange rates) for the cost and performance of new generation plants.<br />
Other important change from NIRP1 is the inclusion of sensitivity analysis and scenarios to address risk<br />
factors and uncertainties such as performance of existing generation plants (Eskom and non-Eskom),<br />
sustainability and delivery of Demand-side Management (DSM) options (including Interruptible load supplies<br />
(ILS)) and changes in the electricity demand load shape. Further the NIRP2 takes into account Transmission<br />
integration costs and credit for regional location of new capacity not included previously.<br />
5<br />
The growth in demand for electricity over the next twenty-year planning horizon is consistent with that<br />
predicted in NIRP1 and follows a moderate forecast with moderate weather conditions.<br />
OBJECTIVE AND PRIMARY ASSUMPTIONS<br />
The objective of the <strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> (NIRP) is to determine the least cost supply options to<br />
the country, provide information to market participants on opportunities for investment in new power stations<br />
and evaluate the security of the supply.<br />
The NIRP2 reference case is based on the following primary assumptions approved by the ARC:<br />
& The net discount rate (before tax) agreed for the studies is 10 % internal to South Africa;<br />
& Options are compared on the basis of 1 January 2003 prices. Foreign capital is converted to South African<br />
Rand at the exchange rate of R9/$ reflective of a long-term planning approach;<br />
& <strong>Plan</strong>t availabilities for new plants are based on the World Energy Council (WEC) best quartile results for<br />
2002. For existing plants the studies use the current targets in Eskom adjusted independently for each<br />
individual station to give a weighted average for base-load capacity of 88% EAF; (7% PCLF: 3% UCLF with a<br />
provision of 2% for OCLF to cater for risk).<br />
& The planning horizon for the study is 20 years from 2003 to 2022;<br />
& Moderate electricity consumption and demand growth;<br />
& Low DSM penetration;<br />
& Inflation for all fuels and new technologies was at South African PPI.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
CAPACITY OUTLOOK FOR NIRP2 REFERENCE PLAN<br />
The capacity outlook for the NIRP Reference plan developed in Stage 1 is illustrated graphically in Figure 1.<br />
Reference capacity plan (10% Reserve margin) 2004 to 2022<br />
Capacity (MW)<br />
58000<br />
56000<br />
54000<br />
52000<br />
50000<br />
48000<br />
46000<br />
44000<br />
42000<br />
40000<br />
38000<br />
Greenfield <strong>PBMR</strong> (Base) - Earliest end 2013<br />
Greenfield PF (Base) - Earliest end 2013<br />
Greenfield Pumped Storage - Earliest 2013<br />
FBC (Base) - Earliest end 2009<br />
CCGT (Base) - Earliest end 2008<br />
Komati PF - Earliest 2010<br />
OCGT - Earliest 2008<br />
Grootvlei PF - 2007<br />
Camden<br />
36000<br />
Eskom Existing Capacity with Decommissioning Non-Eskom Existing Capacity with Decommissioning<br />
34000<br />
Imports-Cahora Bassa Hydro<br />
Simunye Eskom mothballed plants<br />
Pumped Storage capacity<br />
Peaking capacity<br />
32000<br />
Base load capacity Peak Demand before DSM<br />
Peak Demand after DSM<br />
Required capacity<br />
30000<br />
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022<br />
6<br />
Figure 1: Capacity Outlook for NIRP2 Reference <strong>Plan</strong><br />
CONCLUSIONS<br />
The main conclusions drawn from the NIRP2 reference case study could be summarised as follows:<br />
1) Options for diversification are insufficient to meet all of the forecast demand for electricity over the next 20-<br />
year planning horizon. Coal-fired options are still required for expansion during this period. For<br />
environmental benefit it is imperative to continue with efforts to reduce the costs of implementing clean<br />
coal technologies and improve the efficiency of coal-fired plants;<br />
2) Base load plants are required for commercial operation from 2010. Base load options competing, include;<br />
Pulverised Fuel Coal-fired (PF); Fluidised Bed Combustion (FBC); Combined Cycle Gas Turbine (CCGT).<br />
Given the cost and performance data used in the plan these options are broadly comparable, at 10% net<br />
discount rate, if regional siting and transmission benefits are included;<br />
3) At the current assumed cost of capital (10% net discount rate) and after returning the Eskom mothballed<br />
plant to service, fluidised bed combustion technologies are South Africa's most economic option, followed<br />
by investment in coal-fired plant. This in turn is followed by importing gas / LNG for CCGT plant in the<br />
Cape;<br />
4) It will be difficult to justify diversification on an economic basis, unless penalties for not doing so are<br />
included in future analyses. As the cost for diversification is becoming increasingly more expensive these<br />
penalties (or opportunities for emissions trading) will need to be substantial to offset the economic benefits<br />
of remaining with coal;<br />
5) The NIRP plans are based on attainment and sustainability of the DSM targets , power plants availability,<br />
imports and interruptible loads;<br />
6) The NIRP plans indicate that 920 MW OCGT peak load plants must begin commissioning from 2008;
Reference Case<br />
7) Maintaining a higher reserve margin of 15% over the planning period will require acceleration of the RTS of<br />
the mothballed plants and coal-fired options together with commissioning of additional base load capacity<br />
(CCGT);<br />
8) Diversified options are new technologies to South Africa. If these options for whatever reason are not able<br />
to be implemented it will mean a return to a dependency on new pulverised coal-fired plants earlier than<br />
shown in these plans;<br />
9) There are supply options that have not been considered such as co-generation in industry, converting<br />
OCGT to CCGT, adding units onto existing power stations and new imports resulting from the<br />
development of Electricity Supply in the Southern African region;<br />
10) Should interruptible supply and / or OCGT capacity not be implemented this will significantly advance new<br />
base-load capacity;<br />
7
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Table of Contents<br />
EXECUTIVE SUMMARY 5<br />
TABLE OF CONTENTS 8<br />
LIST OF TABLES 9<br />
LIST OF FIGURES 9<br />
ABBREVIATIONS 10<br />
1.INTRODUCTION - THE INTEGRATED RESOURCE PLANNING PROCESS 11<br />
2.STRATEGIC FRAMEWORK AND PRIMARY ASSUMPTIONS 11<br />
2.1 STRATEGIC POSITION (DEFINED BY THE ADVISORY AND REVIEW COMMITTEE (ARC)<br />
OF THE NER) 12<br />
2.2 PRIMARY ASSUMPTIONS 12<br />
2.3 RISKS AND UNCERTAINTIES 12<br />
2.4 OPTIMISATION PARAMETERS 13<br />
2.5 CRITERIA FOR INCLUSION OF SUPPLY-SIDE AND DEMAND-SIDE OPTIONS 13<br />
8<br />
3.NATIONAL ELECTRICITY FORECAST 13<br />
3.1 ECONOMIC GROWTH 16<br />
3.2 LARGE INDUSTRIAL PROJECTS 16<br />
3.3 ELECTRIFICATION 16<br />
3.4 ELECTRICITY INTENSITY 17<br />
3.5 NATURAL GAS 17<br />
3.6 FOREIGN FORECAST COMPONENT 17<br />
3.7 DEMAND PROFILES 18<br />
4.DEMAND-SIDE OPTIONS (DSM) 18<br />
4.1 THE DEMAND SIDE PLANNING BASIS FOR NIRP2 20<br />
4.2 INTRODUCTION TO THE DEMAND-SIDE SCREENING RESULTS 20<br />
4.2.1 Residential Energy Efficiency - REE 21<br />
4.2.2 Industrial, Mining and Commercial Energy Efficiency 22<br />
4.2.3 Residential Load Management (RLM) 23<br />
4.2.4 Industrial and Mining Load Management (IMLM) 23<br />
4.3 UNCERTAINTY AND RISK ASSOCIATED WITH DSM 23<br />
4.4 PRIORITIES FOR THE DEVELOPMENT OF DEMAND-SIDE RESOURCES 24<br />
5.SUPPLY-SIDE OPTIONS 25<br />
5.1 ESKOM SYSTEM - EXISTING AND COMMITTED CAPACITY 25<br />
5.2 NON-ESKOM SYSTEM - EXISTING CAPACITY 25<br />
5.3 RETURN TO SERVICE OF ESKOM MOTHBALLED PLANT (SIMUNYE) 25
Reference Case<br />
5.4 NEW SUPPLY-SIDE OPTIONS 26<br />
5.4.1 New Pulverised Fuel (PF) Coal-Fired Stations 26<br />
5.4.2 New Gas-Fired <strong>Plan</strong>t 26<br />
5.4.3 New Pumped Storage Schemes 27<br />
5.4.4 Greenfield Fluidised Bed Combustion 27<br />
5.4.5 Conventional Nuclear (Advanced Light Water Reactor (ALWR)) 29<br />
5.4.6 Research projects/programs 29<br />
5.4.7 Imported Hydro 29<br />
5.5 SCREENING CURVES 29<br />
5.6 OTHER: ENVIRONMENTAL, EXTERNALITIES, TRANSMISSION EXPANSION 31<br />
6.INTEGRATION AND SENSITIVITY ANALYSIS 31<br />
6.1 REFERENCE PLAN 32<br />
6.2 ALTERNATIVE PLAN 1 TO REFERENCE PLAN 33<br />
6.3 ALTERNATIVE PLAN 2 (SENSITIVITY STUDY) 33<br />
6.4 ALTERNATIVE PLAN 3 (OPTIMAL RESERVE MARGIN) 34<br />
7.SYSTEM ANNUAL AVERAGE LONG RUN MARGINAL COST 35<br />
8.CONCLUSIONS 36<br />
LIST OF TABLES<br />
Table 1: Average demand growth intervals 14<br />
Table 2: DSM aggregate megawatts displaced 19<br />
Table 3: Residential Energy Efficiency 21<br />
Table 4: Commercial energy efficiency 22<br />
Table 5: Industrial and Mining Energy Efficiency 22<br />
Table 6: Residential load management programmes 23<br />
Table 7: Industrial and mining load management 23<br />
Table 8: Summary of cost and performance data of new supply-side options 28<br />
9<br />
LIST OF FIGURES<br />
Figure 1: Electricity sales forecast range - <strong>National</strong> plus foreign 14<br />
Figure 2: Increase in annual peak demand and system losses (national plus foreign) 15<br />
Figure 3: Eskom track record 16<br />
Figure 4: RSA electricity intensity 17<br />
Figure 5: Typical hourly peak demand summer profile 18<br />
Figure 6: Typical hourly peak demand winter profile 18<br />
Figure 7: Life cycle levelised costs to build and operate base load plants 30<br />
Figure 8: Life cycle levelised costs to build and operate peaking plants 30<br />
Figure 9: Reference plan (10% Reserve Margin) 32<br />
Figure 10: Alternative 1 to reference plan (15% Reserve Margin) 33<br />
Figure 11: Alternative 2 - sensitivity to reference plan (excludes interruptible supply options) 34<br />
Figure 12: Annual average long run marginal costs of plans 35<br />
APPENDIX 1: SUPPLY SIDE MODELLING DATA SUMMARY<br />
APPENDIX 2: RESULTS<br />
APPENDIX 3: BACKGROUND SUPPLY SIDE DATA
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Abbreviations<br />
10<br />
ALWR<br />
ARC<br />
CEE<br />
CCGT<br />
CF<br />
CF (DSM)<br />
CV<br />
CUE<br />
DEAT<br />
DME<br />
DSM<br />
DWAF<br />
EAF<br />
EIA<br />
EPC<br />
ESI<br />
FBC<br />
FOR<br />
GT<br />
HELM<br />
HHV<br />
HTF<br />
ICLM<br />
IMEE<br />
IMLM<br />
IEA<br />
IRP<br />
ISEP<br />
LF<br />
LOLE<br />
LOLP<br />
LNG<br />
LPG<br />
MCR<br />
MEUL<br />
NDR<br />
MOU<br />
NER<br />
O&M<br />
OCGT<br />
OCLF<br />
PCLF<br />
<strong>PBMR</strong><br />
PF<br />
POR<br />
PPI<br />
PV<br />
PWR<br />
REE<br />
Advanced Light Water Reactor<br />
Advisory Review Committee<br />
Commercial Energy Efficiency<br />
Combined Cycle Gas Turbine<br />
Coal Fired<br />
Capacity Factor for DSM<br />
Calorific Value<br />
Cost of Unserved Energy<br />
Department of Environmental Affairs and Tourism<br />
Department of Minerals and Energy<br />
Demand Side Management<br />
Department of Water Affairs and Forestry<br />
Energy Availability Factor<br />
Energy Information Administration<br />
Engineering, Procurement and Construction<br />
Electricity Supply Industry<br />
Fluidised Bed Combustion<br />
Forced Outage Rate<br />
Gas Turbine<br />
Hourly Electricity Load Model<br />
High Heating Value<br />
Heat Transfer Fluid<br />
Industrial and Commercial Load Management<br />
Industrial and Mining Energy Efficiency<br />
Industrial and Mining Load Management<br />
International Energy Agency<br />
Integrated <strong>Resource</strong> <strong>Plan</strong><br />
Integrated Strategic Electricity <strong>Plan</strong>ning<br />
Load Factor<br />
Loss of load expectation<br />
Loss of load probability<br />
Liquefied Natural Gas<br />
Liquefied Petroleum Gas<br />
Maximum Continuous Rating<br />
Minimum Energy Utilization Level<br />
Net Discount Rate<br />
Memorandum of Understanding<br />
<strong>National</strong> Electricity Regulator<br />
Operation and Maintenance<br />
Open Cycle Gas Turbine<br />
Other Capability Loss Factor<br />
<strong>Plan</strong>ned Capability Loss Factor<br />
Pebble Bed Modular Reactor<br />
Pulverised Fuel<br />
<strong>Plan</strong>ned Outage Rate<br />
Producer Price Index<br />
Present Value<br />
Pressurised Water Reactor<br />
Residential Energy Efficiency<br />
RLM<br />
ROD<br />
UE<br />
UCLF<br />
WEC<br />
Residential Load Management<br />
Record of Decision<br />
Unserved energy<br />
Unplanned Capability Loss Factor<br />
World Energy Council
Reference Case<br />
1.INTRODUCTION THE INTEGRATED RESOURCE PLANNING PROCESS<br />
The prime objective of the <strong>National</strong> Integrated <strong>Resource</strong>s <strong>Plan</strong> (NIRP) is to provide a long-term least-cost<br />
resource plan for meeting the electricity demand consistent with the reliability of the electricity supply,<br />
environmental, social and economic policies. The NIRP also serves as an information tool for potential project<br />
developers and decision-makers.<br />
The NIRP provides an assessment of the system adequacy and also addresses other public policies such as<br />
environmental impacts and Demand Side Management (DSM).<br />
The NIRP also takes into account the “The New Partnership for African Development (NEPAD)” by<br />
incorporating committed contracts for imports and exports to South Africa from neighbouring States.<br />
This is the second NIRP carried out under the auspices of the NER. The first NIRP was carried out during 2001-<br />
2002 and published on the NER Web site. For the purposes of these analyses the first NIRP is referred as<br />
NIRP1 and the current study as NIRP2. This analysis follows the steps already defined in the NIRP 1 as<br />
follows:<br />
& Develop the primary assumptions and selection criteria;<br />
& Produce an electricity consumption and demand forecasts;<br />
& Investigate a full array of demand- and supply-side options and identify those that meet the strategic<br />
selection criteria for inclusion in the plan;<br />
& Determine an optimal combination of demand- and supply-side options from those selected for inclusion in<br />
the resource plan;<br />
& Evaluate the risk factors associated with uncertainties such as load growth, plant availability, weather<br />
conditions, DSM penetration level, level of interruptible loads etc;<br />
& Analyse the environmental, external and financial consequences;<br />
& Select a preferred plan.<br />
11<br />
The IRP studies carried out in this process use several computer software models. A major model is the RP<br />
Workstation, which consists of a suite of computer software programs, developed by the American Electricity<br />
Power Research Institute (EPRI) and specifically the optimisation module, Electric Generation Expansion<br />
Analysis System (EGEAS).<br />
Due to time constraints, the work carried out for this NIRP is divided into two stages as agreed within the terms<br />
of the <strong>National</strong> Electricity Regulator (NER) Advisory and Review Committee (ARC). These two stages consist:<br />
& Stage 1: Determine a reference plan for analysis and as basis for recommendation on capacity planning<br />
issues in the short-term;<br />
& Stage 2: Develop sensitivity studies and scenarios in order to address targeted risk factors and<br />
uncertainties.<br />
The first stage is intended for completion by Feb 2004, which constitutes this report, and the second for<br />
completion by April 2004.<br />
2.STRATEGIC FRAMEWORK AND PRIMARY ASSUMPTIONS<br />
This serves as the strategic basis for the planning assumptions for the NIRP. The NIRP2 was based on the<br />
planning assumptions approved by the ARC. These studies are based on January 2003 as its primary<br />
reference date for cost parameters and for the start of the twenty- year planning horizon. The NIRP is a longterm<br />
planning process and it is undertaken on an annual basis. The assumptions defined in this document<br />
need to be considered in that context.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
2.1 Strategic position (defined by the Advisory and Review Committee (ARC) of the NER)<br />
The following key points are worth highlighting:<br />
& The aim of the modelling is to determine the long-term least-cost electricity supply options to the country,<br />
independent of ESI structure and subject to the primary assumptions and constraints;<br />
& The NIRP includes the electricity market within and external to South Africa (imports to and exports from<br />
South Africa);<br />
& The NIRP may be used as a basis for identifying investment opportunities for suppliers in the ESI;<br />
& The NIRP's objective is to optimise the supply-side and demand-side mix to keep the price of electricity to the<br />
consumers as low as possible.<br />
2.2 Primary Assumptions<br />
The NIRP2 reference case is based on the following primary assumptions approved by the ARC:<br />
12<br />
& The net discount rate (before tax) agreed for the study is 10 % internal to South Africa;<br />
& Options are compared on the basis of 1 January 2003 prices. Foreign capital is converted to South African<br />
rands at the exchange rate of R9/$ reflective of a long-term planning approach;<br />
& <strong>Plan</strong>t availabilities for new plants are based on the World Energy Council (WEC) best quartile results for<br />
2002. For existing plants the studies use the current targets in Eskom adjusted independently for each<br />
individual station to give a weighted average for base-load capacity of 88% EAF; (7% PCLF: 3% UCLF with a<br />
provision of 2% for OCLF to cater for risk).<br />
& The planning horizon for the study is 20 years, from 2003 until 2022;<br />
& <strong>National</strong> moderate electricity consumption and demand growth;<br />
& Low DSM penetration;<br />
& Inflation for O&M and fuel resources at South African PPI unless stated otherwise;<br />
& New technologies costs are adjusted for Transmission integration or where applicable the avoided<br />
Transmission costs (and losses) according to regional site selection;<br />
& The NIRP2 does not make any assumptions on the ownership of the plants.<br />
2.3 Risks and Uncertainties<br />
This Report does not address risk rigorously but rather addresses it through imposing a minimum reserve<br />
margin on the plan of 10%. Imposing a deterministic reliability index (reserve margin of 10%) as a constraint<br />
does not directly reflect specific risk factors such as FOR, generation mix and unit size. However, it does<br />
provide a reasonable estimate of reliability performance when other parameters remain constant over the<br />
planning period.<br />
Due to time constraints, it was agreed at the ARC as a first pass, to develop a reference plan using a 10%<br />
reserve margin constraint as proxy for risk. The 10% reserve margin is reflective of current inter utility<br />
agreements in the Southern African Power Pool (SAPP). In addition, a second plan is developed based on a<br />
15% reserve margin constraint reflective of international practise.<br />
There are a large number of risks confronting the ESI in the future. These risks are both short-term and longterm.<br />
For example in terms of the load forecast a short-term risk could consist of an unexpected cold weather<br />
snap, whereas a long-term risk could be unexpected sustained increase in demand for electricity. Some of<br />
these risks include:<br />
& <strong>Plan</strong>t failure leading to longer than expected plant outage;<br />
& Unavailability of municipal / Eskom / imported generating capacity;<br />
& Degree of market penetration of DSM and maintaining current level of interruptible loads;
Reference Case<br />
& Unexpected decrease / increase, spurious or sustained, of electricity demand;<br />
& Changes to the load shape associated with the forecast electricity demand;<br />
& Unexpected decommissioning / de-rating of existing generating capacity<br />
& Uncertain and prolonged lead times for building new plant;<br />
& Project slippage<br />
& Inclusion of co-generation options;<br />
& Embargoes on nuclear energy;<br />
& Shortage of skills to maintain and grow the system;<br />
& Other energy forms displacing electricity in the energy market;<br />
& Revolutionary technologies coming on the scene and stranding existing assets;<br />
& Internalisation of externalities, such as Introduction of a carbon tax and environmental levy;<br />
& <strong>Plan</strong>t life expectations not met;<br />
& Retail choice;<br />
& Deterioration in credit rating, exchange rates etc. resulting in a higher cost of capital;<br />
& Electricity supply and sales contracts (import and export contracts) being reneged upon;<br />
& Effect of AIDS on the electricity market.<br />
& Drought and Floods<br />
2.4 Optimisation parameters<br />
The basis for the optimisation of this NIRP is the least cost of electricity for the supply life cycle. This takes into<br />
consideration the cost of un-served energy (CUE) to the consumer. For this NIRP2, the CUE is assumed to be<br />
R20 666/MWh (Eskom 2003).<br />
This CUE was derived from a customer survey of the market sectors of the electricity supply industry (ESI).<br />
Because of an expected marketing drive for DSM, mainly in the residential sector, but also in the commercial<br />
and industrial sectors, the high CUE associated with the industrial sector was chosen as representative. This is<br />
because DSM initiatives that could change the load profile may become exhausted over the 20-year planning<br />
horizon. Previous NIRP1 used CUE of R 19000/MWh associated with the industrial sector.<br />
13<br />
2.5 Criteria for inclusion of Supply-side and Demand-side options<br />
The criteria listed below have been approved by the NER's Advisory and Review Committee (ARC) and are<br />
intended to give guidance in determining whether an option is formally included in the base case.<br />
Technologies that are not included in the base case will be evaluated in sensitivity studies. For technologies to<br />
be included in the reference case they should:<br />
& Be technologically feasible;<br />
& Be economically viable;<br />
& Have adequate accuracy of costs;<br />
& Be under national control either via equity participation, ownership or secure contracts;<br />
& Be socially, politically and environmentally acceptable;<br />
& Be dispatchable;<br />
& In line with World Bank emission standards.<br />
3.NATIONAL ELECTRICITY FORECAST<br />
The load forecast is the foundation upon which resources planning is based. It is an endeavour to forecast the<br />
most likely futures based on selected long-term Southern African economic forecasts. The forecast takes as its<br />
starting point the current position in the electricity supply market but in projecting the future, it excludes any<br />
further demand-side interventions.<br />
A detailed sectoral approach has been used over the last ten years to develop the long-term energy (GWh)
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
forecast. This method has been improved and refined over time. Using a sectoral approach, which considers<br />
about 110 sectors or major customers individually, is one of the ways to lower the forecast risk. The forecast<br />
has also been updated on average more than once per year during the past ten years.<br />
The national plus foreign electricity forecast used in these studies is based on an average annual economic<br />
growth rate of 2.8%, over the planning horizon and moderate temperatures throughout the year. The foreign<br />
portion includes normal sales to traditional neighbouring states plus the Scorpion zinc project in Namibia and<br />
the aluminium smelters Mozal 1 & 2 in Mozambique.<br />
To address the major inherent uncertainty in the environment, a cone of uncertainty approach is used to<br />
develop low, moderate and high-energy forecasts. The electricity database consists of the best quality of data<br />
for all the 110 individual sectors, going back as far as 1980. The load forecast has been developed by Eskom<br />
together with contributions from major sectors/customers and wide consultations inside and outside Eskom.<br />
The <strong>National</strong> forecast range is illustrated in Figure 1 below.<br />
Electricity sales forecasts - national plus foreign<br />
400000<br />
350000<br />
High<br />
Moderate<br />
Low<br />
14<br />
GWh<br />
300000<br />
250000<br />
200000<br />
150000<br />
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022<br />
Figure 1: Electricity sales forecast range - <strong>National</strong> plus foreign<br />
The average growth in energy in intervals over a five-year period within the planning horizon is given in Table 1:<br />
Table 1: Average demand growth intervals<br />
High (%) Moderate (%) Low (%)<br />
2003 - 2008 4.3 3.2 1.6<br />
2008 - 2013 3.1 2.3 1.0<br />
2013 - 2018 2.6 1.8 0.9<br />
2018 - 2022 2.5 1.8 0.8<br />
The electricity growth in the early years until 2006 is high (4% pa) due in part to cater for major expansions in<br />
platinum mining and high demand for ferrochrome as experienced in 2002 and 2003 and one further 850MW<br />
aluminium smelter at Coega. However this high growth is not sustained after 2006. Eskom sales growth has<br />
been high in 2002 and 2003 but the average sales growth is only 2.2% per annum over the last six years. The<br />
long-term forecast allows for a growth in fixed investment but there are currently no new major projects, which<br />
have been officially approved, other than the platinum mine expansions.
Reference Case<br />
An hourly electricity load model (HELM) is used to develop the maximum demand forecast where the annual<br />
energy forecast has been converted to an annual maximum demand forecast using updated sectoral<br />
customer usage profiles. It is expected that system energy utilisation with respect to annual peak demand will<br />
deteriorate slightly over time and the system annual load factor worsen from a current average of 74% to about<br />
73% by 2017.<br />
Of specific importance is the impact of system losses on the forecast demand. The Eskom system losses have<br />
been increasing over the last number of years from 5% in 1990 to 7.7% in 2002. The system losses for the<br />
<strong>National</strong> forecast are estimated to be currently 9% increasing to in excess of 10% over the planning horizon.<br />
Details of the moderate annual forecast (energy and demand) are shown in the Tables given in Appendix 2 to<br />
this report. The demand forecast is illustrated in Figure 2: Increase in annual peak demand and system losses<br />
(national plus foreign) below.<br />
Increase in forecast annual peak demand (<strong>National</strong> + Foreign) and losses<br />
12.0%<br />
10.0%<br />
(%) Increase<br />
8.0%<br />
6.0%<br />
4.0%<br />
<strong>National</strong> + Foreign annual<br />
system losses (%)<br />
Annual Increase in peak<br />
Demand (<strong>National</strong> + Foreign) (%)<br />
Forecast Annual Peak Demand in<br />
2022 = 53256MW<br />
I e. Growth from 2004 to 2022 =<br />
19611MW<br />
15<br />
2.0%<br />
Forecast Annual<br />
Peak Demand in<br />
2004 = 33645MW<br />
0.0%<br />
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022<br />
Figure 2: Increase in annual peak demand and system losses (national plus foreign)<br />
The short-term accuracy of the forecast and the track record of the long-term forecast are being monitored on<br />
an annual basis. The short-term variance is around the zero line and is not always positive or always negative.<br />
Figure 3 below tracks Eskom's (as opposed to national plus foreign) forecast predictions over the last ten years<br />
within a cone of 1.5% to 4% growth per annum. Actual sales are shown in the thick black line.<br />
Over the last few years these results show that the actual values achieved were slightly lower than the forecast<br />
values but in the last two years actual values were slightly higher. It is also important to note that the forecast<br />
value for the year 2007, as seen at this stage is very close to the value forecasted for the same year in 1996.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Eskom long term sales forecast track record<br />
GWh<br />
370000<br />
320000<br />
270000<br />
220000<br />
1994<br />
1995<br />
1996<br />
1997<br />
1998<br />
1999<br />
2000<br />
2001<br />
2002<br />
2003<br />
Actual<br />
High 4%<br />
Low 1.5%<br />
170000<br />
120000<br />
1990 1995 2000 2005 2010 2015<br />
16<br />
Figure 3: Eskom track record<br />
The following is a brief summary of the main assumptions of the long-term forecast (national plus foreign).<br />
3.1 Economic Growth<br />
Long term economic growth rate for the moderate forecast is 2.8% average annual growth over the planning<br />
horizon. This economic growth rate takes into account the impact of HIV / AIDS.<br />
3.2 Large Industrial Projects<br />
New large industrial projects, such as the proposed Pechiney aluminium smelter, Billiton Hillside aluminium<br />
smelter expansions, Columbus Stainless Steel expansions, Sasol new projects and expansions and Mozal 2,<br />
have been included in the forecast. Further expansions to ferrochrome plants are also provided for. Current<br />
platinum mining expansions have been included, with provision for limited expansions after 2007/8. It was<br />
assumed that new gold mining projects would replace old ones. Gold production in South Africa is assumed to<br />
continue to decrease slightly over the long term. With regard to the longer term, allowance had also been made<br />
in the energy forecast for unknown new projects, based on past experience. A list is regularly revised for all<br />
possible new electricity intensive projects, including projects with a very low probability of occurrence.<br />
3.3 Electrification<br />
The forecast makes provision for the electrification of homes by Eskom and the municipalities. Electrification<br />
carried out by Eskom forms the bulk of its prepaid sales category. The number of connections obtained from<br />
planners and an estimated consumption per connection are used as a guide. It is assumed that the<br />
electrification rate will level off over time. The prepaid category only formed about 2.5% of total 2002 electricity<br />
sales in the country.
Reference Case<br />
3.4 Electricity Intensity<br />
The growth in the long term forecast is high in the near term due to major expansions of some electricity<br />
intensive industries. However, the growth is expected to reduce in the latter period of the planning horizon due<br />
to the fact that the electricity intensity of the South African economy is expected to decrease over time. This is<br />
characteristic of an economy, which is moving towards a more service based structure as is the case in South<br />
Africa and implies that the GDP growth rate in future will be consistently higher on average than the electricity<br />
growth rate. This has already been experienced in South Africa during the four-year period 1998 to 2001.<br />
The electricity intensity of the South African economy is shown in Figure 4. The current major expansions of<br />
electricity intensive industries are expected to decline and platinum mining is not expected to continue to<br />
maintain the current high growth rates after 2007/8. With more beneficiation of minerals, less energy will be<br />
required per unit of production. Once there is no more excess generating capacity, electricity prices will have to<br />
increase in real terms. Although it is assumed that this increase will not be extraordinary, it is expected that it<br />
will marginally affect electricity consumption.<br />
0.35<br />
RSA electricity intensity<br />
0.30<br />
0.25<br />
kWh / rand<br />
0.20<br />
0.15<br />
17<br />
0.10<br />
0.05<br />
0.00<br />
1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000<br />
Figure 4: RSA electricity intensity<br />
3.5 Natural Gas<br />
Allowance is made for the loss in electricity sales due to consumers switching from the use of electricity to the<br />
use of natural gas.<br />
3.6 Foreign Forecast component<br />
This part of the forecast includes sales that are currently in place - mostly under contract. Also included are the<br />
Mozal aluminium smelter in Mozambique and the Skorpion zinc project in Namibia. Provision had also been<br />
made for the Corridor heavy mineral sands project in Mozambique over the longer term.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
3.7 Demand Profiles<br />
Figure 5 shows a typical demand profile for the total Eskom system for a summer week.<br />
27000<br />
25000<br />
Eskom integrated system typical summer week hourly demand profile<br />
January/February<br />
2002<br />
2001<br />
2000<br />
23000<br />
MW<br />
21000<br />
19000<br />
17000<br />
15000<br />
Mon Tue Wed Thu Fri Sat Sun<br />
Figure 5: Typical hourly peak demand summer profile<br />
Figure 6 and shows a typical demand profile for the total Eskom system for a winter week.<br />
18<br />
33000<br />
31000<br />
29000<br />
27000<br />
Eskom integrated system typical winter week hourly peak demand<br />
July<br />
2002<br />
2001<br />
2000<br />
MW<br />
25000<br />
23000<br />
21000<br />
19000<br />
17000<br />
15000<br />
Mon Tue Wed Thu Fri Sat Sun<br />
Figure 6: Typical hourly peak demand winter profile<br />
4.DEMAND-SIDE OPTIONS (DSM)<br />
This NIRP2 assumes a significantly (approximately 50%) lower penetration of DSM programmes than the<br />
previously in NIRP1. Previous estimates were based on desktop studies. Pilots and experience in the field<br />
now indicate that a more conservative approach should be followed in the estimates for DSM programmes<br />
both in terms of capacity and cost. Five DSM programmes are targeted:
Reference Case<br />
& Residential Energy Efficiency (REE)<br />
& Commercial Energy Efficiency (CEE)<br />
& Industrial and Mining Efficiency (IMEE)<br />
& Residential Load Management (RLM)<br />
& Industrial and Mining Load Management (IMLM)<br />
Each programme has been modelled on a basis that capital will be expended over a nine-year period to ensure<br />
increasing annual displacements of aggregate Megawatts will be deducted from the load associated with a<br />
specified energy usage profile as indicated in the Table 2.<br />
Table 2: DSM aggregate megawatts displaced<br />
Programme Annual MW Displacements Annual Energy Displaced GWh<br />
Residential Energy Efficiency 32 129<br />
Commercial Energy Efficiency 14 69<br />
Industrial and Mining Efficiency 16 101<br />
Residential Load Management 49<br />
Industrial and Mining Load Management 41<br />
Each aggregate annual displacement is maintained over a period of twenty years to ensure no deterioration of<br />
displacement takes place. (I.e. maintenance will continue for a further 11 years beyond the nine-year<br />
investment period).<br />
Interruptible supply options are modelled separately to the above DSM programmes. Eskom has several<br />
interruptible supply agreements with key customers. These agreements are severely energy constrained and<br />
their capacity impact in the long-term has been reduced. There have been several comments by various ARC<br />
members to consider these interruptible supply agreements as emergency capacity only. This issue will be<br />
addressed in the next round of the NIRP in terms of the uncertainty inherent in this assumption.<br />
19<br />
The DSM team of Eskom in their endeavours to continually improve decision-making on the role of DSM in<br />
resources planning have taken several actions one of which is to improve information on DSM before its<br />
inclusion.<br />
In terms of residential DSM, Eskom has good statistics on device populations and unit gains in the residential<br />
markets. The homogeneity in residential markets provides confidence in DSM planning data, because enduse<br />
devices are generally characterised within narrow ranges of diversity.<br />
The need to upgrade confidence for this NIRP was in the commercial and industrial market segments,<br />
because previously there was no sound strategy to deal with the diversity of information. Fortunately since the<br />
previous <strong>National</strong> Integrated <strong>Resource</strong>s <strong>Plan</strong>, NIRP1, the DSM team has had access to a document on market<br />
assessment for electric motors prepared for the Department of Energy (DOE) in the USA. This document<br />
clearly spells out the opportunities for energy efficiency in the majority of the commercial and industrial enduse<br />
sectors. Electric motors make up nearly 50% of Eskom's total sales, or more than 65% of the sales to<br />
industrial and commercial clients.<br />
A major task in preparation of DSM data for NIRP2 has been the mapping of the DOE information on DSM<br />
opportunities in the USA into the South African context. This has now been done, and together with other desk<br />
research it has been revealed that the situation in SA is very different to the USA. South Africa needs to devise<br />
its own strategy to contend with issues that do not exist in the case of the USA.<br />
There has been a major focus on the industrial and commercial sectors, providing a better insight into the CEE,<br />
IMEE and IMLM strategies to be adopted in the future. A further improvement in this NIRP is in the provision of
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
an aggregated summary for the ICEE and ICLM programmes compared with the previous industrial and<br />
commercial components.<br />
The NIRP1 placed more emphasis on energy efficiency as opposed to load management programmes. Better<br />
experience has now shown this emphasis to be misplaced, in that energy efficiency programmes are difficult to<br />
implement and to achieve performance targets due to the many barriers involved, and are turning out more<br />
costly than previously estimated.<br />
4.1 The Demand Side <strong>Plan</strong>ning Basis for NIRP2<br />
The basis for end-use load forecasting adopted for DSM planning in this NIRP is the “moderate forecast” as<br />
detailed above. The amount of DSM resources to be developed over a planning period is very sensitive to the<br />
load forecast. For sensitivity studies there is also the facility to use a “high load growth” and a “low load growth”<br />
forecast. A high growth forecast would imply higher targets for DSM, and a low load forecast would suggest<br />
lower targets than required for the moderate forecast. This issue will also be addressed in the next round of the<br />
NIRP in terms of the uncertainty in DSM penetration.<br />
4.2 Introduction to the Demand-Side Screening Results<br />
The following summarises the DSM resources submitted for inclusion in the NIRP2. <strong>Resource</strong>s that are not<br />
currently included may qualify for inclusion in future version if further investigation provides the information<br />
needed to obtain positive screening results. The screening results for energy efficiency options are given in<br />
Table 1 to 3 below. For comparison, separate columns give the NIRP1 and NIRP2 assumed market<br />
penetration.<br />
20<br />
In Tables 6 and 7, pertaining to the load management resources, there are high and low capacity factor (CF)<br />
resource capacities, given in MW, and the balance, which is the difference between the two.<br />
Capacity factor is defined as the percentage of time that the capacity of the load management resource can be<br />
fully utilised. “Hi CF MW” means that control algorithms are utilised to achieve a high capacity factor. There is a<br />
maximum percentage of time that the residential load management (RLM) resource can be utilised. In the<br />
maximum percentage mode the system peak MW can only be reduced by the amount reflected in the “Hi CF<br />
MW” column.<br />
The system peak can be further reduced by the amount in the “Balance of MW” column, when operated in the<br />
low capacity mode. The “Lo CF MW” column indicates the total reduction of the system peak if the entire load<br />
management resource is only operated in low capacity factor mode.
Reference Case<br />
4.2.1 Residential Energy Efficiency - REE<br />
Table 3 gives the results of screening Residential Energy Efficiency.<br />
Table 3: Residential Energy Efficiency<br />
OPTION No of units Assumed Market<br />
Penetration<br />
MW/a GWh/a IN NIRP2 NIRP1 NIRP2<br />
INTEGRAL CFL'S 25.20 91.97 YES 33% 20%<br />
HOT WATER SYS. EFFICIENCY 2.93 10.13 YES 28% 10%<br />
LOW FLOW SHOWERHEADS 2.38 8.22 YES 34% 10%<br />
HOTWATER CONSERVATION 0.47 1.63 YES 30% 10%<br />
COOKING AWARENESS 1.34 3.44 YES 30% 10%<br />
EFFICIENT COOL STORAGE NO 30% 10%<br />
THERMAL EFFICIENCY NO 30% 10%<br />
DEMARKETING TO GAS NO 30% 15%<br />
MODULAR CFL'S NO 33% 20%<br />
Total 32.39 129.0<br />
The REE resources submitted for NIRP are predominated by integral CFL's.<br />
The energy efficiency measures related to hot water systems have also been included but it was decided not to<br />
include efficient cool storage appliances, thermally efficient building practices and de-marketing to gas. Also<br />
included are integral CFL's and energy efficiency measures on storage water heaters. The integral version of<br />
the CFL costs less to sustain this technology over the planning period. The major problem associated with<br />
targeting integral CFL's for the efficient residential lighting initiatives is the risk of sustainability (i.e. conversion<br />
back to inefficient incandescent light bulbs in the future).<br />
21<br />
The strategy with respect to electrical water heating is to encourage storage water heating. Indications are that<br />
residential load management is a lower cost resource than building peaking plant. Instant water heaters have<br />
not found favour, because they do not lend themselves to load shifting. For storage water heating to hold its<br />
ground in SA it is important to demonstrate that these systems can be energy efficient, and that the per capita<br />
water consumption can be contained, especially in the event of water shortages at a future time. For waterheater<br />
system efficiency measures like hot water conservation, low flow showerheads and thermal insulation<br />
are included.<br />
Other DSM options that have been included in residential energy efficiency strategies in other countries have<br />
yet to be developed to a stage where they are mature enough to include in the REE strategy with some<br />
confidence. For example energy-efficient fridges and freezers will only be included in the strategy at a later<br />
stage when there is more clarification on appliance labelling policy. Information is required on how appliance<br />
labelling would help to create demand and to make the program economically more attractive. The strategy on<br />
fridges and freezers is therefore to closely monitor the DME initiatives regarding appliance labelling.<br />
Residential space-heating loads are not included but should be targeted as a demand-side measure, because<br />
they are one of the main reasons for poor utilization of supply capacity, and therefore not very economical to<br />
supply. Previous work by the DSM team has indicated that gas heating is likely to be more expensive to the<br />
consumer, yet electrical space heating is losing market share to gas space heating. With rising oil prices, and<br />
therefore LPG prices, it is uncertain, whether there will be a significant shift to gas for space heating. Better<br />
information is needed on how thermal efficiency measures impact on space heating demand before deciding<br />
on a relevant strategy. In particular, there is a need to know what the most marketable measures are to desensitise<br />
system space-heating demand to weather-related events like falling temperatures and cloud cover<br />
during winter months.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
4.2.2 Industrial, Mining and Commercial Energy Efficiency<br />
Table 4 gives the results of screening CEE programmes. For CEE, the assumptions on market penetration<br />
remain more or less the same as with the NIRP1<br />
Table 4: Commercial energy efficiency<br />
OPTION No of units Assumed Market<br />
Penetration<br />
MW/a GWh/a IN NIRP2 NIRP1 NIRP2<br />
SUPERVISION 2.05 10.60 YES 14.1% 15%<br />
FANS/PUMPS 0.64 4.68 YES 26.0% 26.0%<br />
COMP AIR<br />
LIGHTING 9.53 43.54 YES 27.0% 27.0%<br />
VSD's 0.26 1.90 YES 3.0% 3.0%<br />
REPLACE 0.68 3.50 YES 15.0% 10.0%<br />
UPGRADE 0.66 3.40 YES 13.0% 10.0%<br />
DOWNSIZE NO<br />
COOLING SYSTEM EFF NO<br />
HEAT RECOVERY NO<br />
INSULATION NO<br />
Total 13.82 69.38<br />
22<br />
Table 5 gives the results of screening of Industrial and Mining energy efficiency programmes<br />
Table 5: Industrial and Mining Energy Efficiency<br />
OPTION No of units Assumed Market<br />
Penetration<br />
MW/a GWh/a IN NIRP NIRP1 NIRP2<br />
SUPERVISION 2.24 15.33 YES 14.1% 2.0%<br />
FANS/PUMPS 1.31 9.26 YES 26.0% 5.0%<br />
COMP AIR 2.26 16.54 5.0%<br />
LIGHTING 3.77 23.44 YES 27.0% 10.0%<br />
VSD's 4.40 29.3 YES 3.0% 3.0%<br />
REPLACE 1.13 7.72 YES 15.0% 2.0%<br />
UPGRADE 1.06 7.02 YES 13.0% 2.0%<br />
DOWNSIZE NO<br />
COOLING SYSTEM EFF NO<br />
HEAT RECOVERY NO<br />
INSULATION NO<br />
Total 16.15 100.93<br />
These results suggest that most of the drive-power programs qualify for submission. The demand-side plan<br />
assumes that ESCO's will be enabled that specialize in the delivery of CEE and IMEE resources to the<br />
industrial market, and that they are competitive and operational in SA in the future. Under these assumptions it<br />
is possible that this target can be achieved within 10 years.<br />
This assumption assumes support from<br />
governance authorities in terms of policy.<br />
Additional energy efficiency resources would become available were commercial and industrial participants to
Reference Case<br />
focus their attention on heating and cooling systems that derive their energy from an electricity supply. These<br />
are indicated in the demand-side plan as a requirement for further investigation.<br />
The most viable area for industrial and commercial energy efficiency is motor supervision and control.<br />
Maintenance and supervision of compressed air or gas compressor systems is another area for potentially<br />
very cost-effective energy efficiency measures. Companies that employ the practice of re-winding motors<br />
rated lower than 45kW may require advice on the economics of re-winding versus replacing. In some cases it<br />
may even pay to upgrade motors to premium efficiency motors.<br />
It is most important to transform the market for new construction to energy efficient lighting, especially in<br />
commercial buildings. Lighting controls should be installed to avoid unnecessary lighting usage. Retrofits<br />
typically do not offer very short paybacks, but are in the range where respectable rates of return can be<br />
guaranteed. Lighting retrofits that would also reduce air-conditioning load should be targeted first. It is a matter<br />
of major concern that the majority of industrial and commercial lighting sales into the new construction market<br />
still conform to old and outdated standards for energy efficiency.<br />
Every effort should be made to apply best practices in the design of systems employing fluid or airflow. In<br />
particular excessive throttling of flow should give way to variable speed drives or staged switching of drives,<br />
and pipes and ducts should be sized to minimise total resource costs. Every effort should be made to promote<br />
the adherence to best practices on systems with pumps, fans and compressors. CEE and IMEE retrofits<br />
should initially target systems of large drives, i.e. 200 kW and larger.<br />
4.2.3 Residential Load Management (RLM)<br />
In the case of RLM, the screening criteria have led the DSM Team to firm conclusions on the RLM strategy. Up<br />
until now too many conflicting DSM strategies were considered. Table 6 gives the results of screening the<br />
various RLM strategies and options.<br />
23<br />
Table 6: Residential load management programmes<br />
SUMMARY OF RLM SCREENING RESULTS<br />
Options Hi CF MW/a Balance of MW/a Lo CF MW/a<br />
Ripple Control 49 49 98<br />
4.2.4 Industrial and Mining Load Management (IMLM)<br />
The pre-integration study data shows that for IMLM there is a potential 600 MW of controllable load that can be<br />
developed, assuming the resource is operated at high capacity factor.<br />
A summary of the first-round screening results for ICLM is given in Table 7<br />
Table 7: Industrial and mining load management<br />
Options Hi CF MW/a Balance of MW/a Lo CF MW/a<br />
INDUSTRIAL/ MINING LOAD 40.9 40.9 82<br />
Under system emergencies the resource can be operated at low capacity factor. The low capacity factor<br />
figures assume that the resource is required for 2 hours per day.<br />
4.3 Uncertainty and Risk Associated with DSM<br />
The DSM team has had to come to grips with the reality that it is developing DSM plans for a fast-changing<br />
energy market. Many of the decisions about the future structures of the Electricity Supply Industry (ESI) in
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
South Africa, which have yet to be made, may impact on DSM. Utilities will have no control over the way the<br />
industry will develop in future.<br />
To deal with uncertainty about the future, the DSM team has to make certain assumptions regarding the<br />
conditions for sustainable demand-side resources to exist. The DSM programmes assume that the<br />
governance authorities in consensus will set up the specified conditions for a DSM resource market with key<br />
stakeholders and energy consumers.<br />
Risk is closely linked to a lack of dependable information. The Demand-side plans make many assumptions on<br />
important factors that affect market penetration. The DSM assumptions and resource plans are based on<br />
targets that are believed to be realistic. The demand-side plan is exposed to risk if any of the assumptions are<br />
proven to be unrealistic. It is prudent to firm up on much needed information about the market potential for<br />
demand-side resources.<br />
4.4 Priorities for the Development of Demand-Side <strong>Resource</strong>s<br />
24<br />
These demand-side plans are based on the assumption that the SA market will be willing and able to transform<br />
towards a preference for the development of demand-side resources. Historically the preference has been to<br />
develop supply-side resources, so the SA market is currently not richly endowed with the resources and skills<br />
required to deliver demand-side resources on a large scale. A prime issue of concern is the fact that DSM is<br />
often seen from a utility perspective as a loss leader in that their core business is in selling electricity. This is<br />
especially relevant to energy efficiency programmes and it is imperative that policy and legislation be adopted<br />
in future to address this problem. Another major problem is in sustainability. For example in the Table View load<br />
management pilot study, previously about 8-10MW could be achieved through geyser control. Recent tests<br />
show only 4MW can currently be switched off. Customers are bypassing the system because they see no<br />
personal benefit as no time-of-use tariff is in place for individual residential customers.
Reference Case<br />
5.SUPPLY-SIDE OPTIONS<br />
Technology options are compared on the basis of discounted cash flows (total capital & operating costs) over<br />
the option lifetime using 10% net discount rate as dictated by the ARC of the NER. The levelised cost per unit<br />
output of the option is obtained by dividing the present value by the total discounted lifetime generation.<br />
Levelised costs are calculated as a function of plant load factors (screening curves) to illustrate the relation<br />
between the levelised cost and plant load factor.<br />
5.1 Eskom System - Existing and Committed Capacity<br />
The current (2003) total net base load capacity in operation of the Eskom system is given in Appendix 1 to this<br />
report and is 33 871 MWe. The total net peaking capacity in operation is 2319 MWe. This includes Acacia and<br />
Port Rex gas turbines, Drakensberg and Palmiet pumped storage, Gariep and Vanderkloof hydro plants.<br />
Eskom has a long-term contract to purchase power from Cahora Bassa hydro plant in Mozambique. Available<br />
net capacity from Cahora Bassa is at present 912 MWe (after losses). A further 369 MWe (after losses) is<br />
committed from 2004. Eskom is importing about 100 MWe of peaking capacity from Zesco (Zambia) via<br />
Zimbabwe and about 110 MWe from the DRC. These latter are excluded from the study as Eskom has been a<br />
net exporter of similar proportions to neighbouring states. (I.e. as these imports and exports are effectively<br />
equivalent the exports are not included in the load forecast nor are the imports included in the capacity plan).<br />
5.2 Non-Eskom System - Existing Capacity<br />
The following options are considered in the plan:<br />
Appendix 1 also gives the net capacity of non-Eskom generating plant. These have been aggregated into<br />
blocks of similar capacity units for modelling purposes as follows:<br />
25<br />
& Munic 1: consisting 12x60 MW sent out coal-fired capacity<br />
& Munic 2: consisting 21x30 MW sent out coal-fired capacity<br />
& Sasol: consisting 12x60 MW sent out coal-fired capacity<br />
& Steenbras pumped storage plant: 3x60 MW sent out<br />
& Mini Hydro: 1x65 MW sent out<br />
& Minic OCGT: 6x50 MW sent out<br />
The details of these plant and capacities are given in Appendix 1.<br />
In addition to the Eskom and non-Eskom supply capacity there is a total 1510 MW interruptible supply capacity<br />
included in the plan. The interruptible load accepted for inclusion in the plan, although based on current<br />
contracts, does not necessarily represent the existing contracts. It is assumed that some level of interruptible<br />
capacity, either in the form of contracts for reserve or as a demand-side bidding option, will exist in the future. In<br />
total the existing capacity assumed on the <strong>National</strong> system in 2003 amounts to 41378 MWe sent out.<br />
5.3 Return to Service of Eskom Mothballed <strong>Plan</strong>t (Simunye)<br />
These are the stations that were put into storage during the period of high excess capacity on the Eskom<br />
system: Camden (1520 MW), Grootvlei (1130 MW) and Komati (909 MW). These capacities are on a sent out<br />
basis. These stations all use PF coal. When refurbished, Camden is anticipated to run as base load, whereas<br />
Grootvlei and Komati would most probably be two-shifted i.e. operating at an annual load factor of less than<br />
30%.<br />
Results of a pre-feasibility study initiated and carried out by Eskom indicate that repowering some of Eskom's<br />
old plant with Fluidised Bed Combustion (FBC) technology (such as at Komati) could be an option in
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
comparison with other future base load plant. The remaining half of Komati (456 MW) could be re-powered<br />
with FBC technology to operate as base load.<br />
5.4 New Supply-Side Options<br />
Table 8 below summarises the data for all the new supply-side technologies considered in the plan. Detailed<br />
description of the cost and performance of the considered supply-side options is shown in Appendix 3. The<br />
ARC, applying the approved selection criteria, determined the inclusion of the supply side technologies in the<br />
plan. The capital costs are averages of the international data evaluated. Operating and Maintenance costs<br />
shown are averages from the international literature, after they have been adjusted for South African labour<br />
conditions. Appendix 3 contains additional information about the supply-side technologies, including costs,<br />
performance parameters, lead times and data statistics.<br />
A transmission benefit has been given to stations built in the Cape close to the load centres. This is to account<br />
for the line losses that occur when transmitting electricity from an equivalent station in the Highveld and for<br />
strengthening the grid along transmission lines.<br />
<strong>PBMR</strong> data is given for both the initial multi-module and, after several multi-modules have been deployed, a<br />
cheaper multi-module (costs are likely to decrease, benefiting from technology learning).<br />
Adding units to existing coal plants and co-generation options have not been considered in the plan.<br />
5.4.1 New Pulverised Fuel (PF) Coal-Fired Stations<br />
26<br />
In the absence of more cost competitive options, coal-fired plants are likely to remain the backbone of the<br />
electricity supply industry in South Africa for a long time. Their proven design, the vast operating experience<br />
gained locally, their wide availability, reliability and relatively low cost make them an attractive option for base<br />
1<br />
load generation. This is often the case in other parts of the world, such as China , where low-cost coal is<br />
available. The future stations considered consist of 6 units, each of 700 MW installed capacity, with drycooling<br />
(or hybrid) systems. Coal stations can operate with or without flue gas desulphurisation (FGD) to<br />
reduce emissions but only the option with FGD was considered for the plan because of the decision to adhere<br />
to World Bank emission standards. Detailed information on the cost and performance of the PF plants is<br />
shown in Appendix 3.4<br />
5.4.2 New Gas-Fired <strong>Plan</strong>t<br />
Potentially Namibia, Mozambique or Angola could supply Gas. New gas-fired plants considered are open<br />
cycle gas turbines (OCGT) and combined cycle gas turbines (CCGT). Open cycle gas turbines, by virtue of<br />
their low efficiencies and resultant high cost of fuel when operating at low load factors are considered for<br />
peaking options only. Combined cycle gas turbines with much improved efficiency levels are regarded as nonpeaking<br />
technologies due to the likely constraints on gas contracts (take or pay) although they could<br />
technically follow load.<br />
The OCGT stations considered have two 120 MW units. The CCGT stations considered have 5 x 400 MW<br />
units.<br />
If OCGT turbines were built, and in the future a gas network was developed, it is likely that OCGT plants would<br />
be converted to CCGT plants, which would increase the capacity and efficiency of the stations. This has not<br />
been taken into account in the plan.<br />
1 Future Implications of China’s Energy-Technology Choices, July 2001
Reference Case<br />
Fuels considered for OCGT plants are kerosene, LPG, local syngas and LNG. Fuels considered for CCGT are<br />
pipeline gas and LNG. Fuel prices for the gas options are given for all the fuels considered for each technology.<br />
Detailed information on the cost and performance of the OCGT and CCGT plants is shown in Appendix 3.2 and<br />
3.3 respectively.<br />
5.4.3 New Pumped Storage Schemes<br />
Two pumped-storage schemes have been considered in the plan. Braamhoek (which has already received a<br />
record of decision (ROD)) and a generic scheme which would follow Braamhoek. Braamhoek consists of four<br />
333 MW units, while the generic option consists of three 333 MW units. It must be noted that the costing of<br />
pumped storage schemes is site specific. Additional details on the pumped storage plants are provided in<br />
Appendix 3.8.<br />
5.4.4 Greenfield Fluidised Bed Combustion<br />
The fluidised bed combustion (FBC) stations considered have an installed capacity of 500 MW. They are<br />
comprised of two 250 MW boilers and a 500 MW turbine, and have a 35 year lifetime. The price of duff coal will<br />
have to be negotiated between the station and the mines. Additional information on the FBC is provided in<br />
Appendix 3.5.<br />
27
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
28<br />
Table 8: Summary of cost and performance data of new supply-side options
Reference Case<br />
5.4.5 Conventional Nuclear (Advanced Light Water Reactor (ALWR))<br />
The new nuclear plant considered is an advanced light water reactor. It consists of two 900 MW units and will<br />
be built at the Koeberg (existing nuclear) site near Cape Town.<br />
The ALWRs are based on existing light water reactors but are designed for simplicity and ease of construction<br />
and maintenance. They have a considerable degree of inherent safety (safety built in to the design rather than<br />
reliant on active safety mechanisms). Examples of such reactors are the Westinghouse AP1000 and the<br />
General Electric ABWR. There are currently no ALWR plants in operation. Additional information on the ALWR<br />
is provided in Appendix 3.6.<br />
5.4.6 Research projects/programs<br />
In addition to the “mainstream” supply-side options listed above, the following are amongst the technologies<br />
that are being researched and are considered in the screening curve analysis:<br />
5.4.6.1 Wind energy<br />
There are several areas in South Africa, particularly in the coastal regions, which have been identified as<br />
having good potential for wind power. The proposed wind farm consists of twenty (1 MW) wind turbines.<br />
There is little detailed data available for specific sites in South Africa. Additional details on wind turbines are<br />
provided in Appendix 3.9.<br />
5.4.6.2 Solar thermal<br />
The Solar Thermal power station would be built near Upington in the Northern Cape. It would have three 110<br />
MW units and the capacity for storage. It is therefore regarded as a dispatchable station in the plan. Additional<br />
details on solar thermal power stations are provided in Appendix 3.10.<br />
29<br />
5.4.6.3 <strong>PBMR</strong><br />
If the necessary approvals are given and a commercial decision is taken to build one, the first full-sized<br />
demonstration unit should be on line by 2008. If successful, further units will be built with the aim of producing<br />
a power station consisting of eight units, each unit with an installed capacity of 170 MW. Additional details on<br />
the <strong>PBMR</strong> plant are provided in Appendix 3.7<br />
5.4.7 Imported Hydro<br />
There is a large potential for South Africa to import hydro-electricity from the rest of Africa. A promising site is at<br />
Mepanda Uncua in Mozambique about 60 km downstream of the existing Cahora Bassa Power Station on the<br />
Zambezi River. In the first stage of this project the installed capacity at the HV terminals would be 1300 MW.<br />
The firm power capacity at 95% availability is 827 MWe. Additional details on the imported hydro option are<br />
provided in Appendix 3.11.<br />
5.5 Screening Curves<br />
To evaluate the cost of generation from new options, a screening curve analysis was undertaken. A screening<br />
curve evaluates the cost of generating electricity at different average levels of production or load factors over<br />
the life of the plant. This gives an indication of the economics of running the plant at these load factors.<br />
The following screening curves have been drawn from the levelised capital, O&M and fuel costs for the various<br />
technologies at different load factors. The analysis has been split into two sections: non-peaking stations<br />
(plants expected to run at high load factors) and peaking stations (plants expected to run at low load factors).<br />
Non-peaking plants operate as base load when their operating (including fuel) costs are lower than peaking
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
stations. There are some exceptions where stations with high operating costs are included as must run plants<br />
by virtue of fixed price contracts or technical constraints. CCGT options are examples whereby the gas<br />
contracts are placed on the basis of firm commitments to take minimum quantities by virtue of purchasing<br />
power agreements. These plants can be considered as inflexible options to system dispatch and construed as<br />
must run options.<br />
Peaking stations run at low load factors by virtue of their high operating costs generally have lower capital and<br />
fixed operating expenses than non-peaking stations. The ranges reported in the screening curves reflect the<br />
deviation in the data collected from international literature.<br />
Figure 7 illustrates the life cycle costs to build and operate the base load plants analysed in this report.<br />
1500.00<br />
1300.00<br />
1100.00<br />
R/MWh<br />
900.00<br />
700.00<br />
CF with FGD<br />
Conventional Nuclear<br />
<strong>PBMR</strong><br />
Imported Hydro<br />
Solar Thermal<br />
500.00<br />
CCGT LNG<br />
CCGT Pipe<br />
300.00<br />
30<br />
Greenfield FBC<br />
100.00<br />
30 40 50 60 70 80 90<br />
Load Factor (%)<br />
1<br />
Figure 7: Life cycle levelised costs to build and operate base load plants<br />
Figure 8 illustrates the life cycle costs to build and operate the peaking plants analysed in this report.<br />
4000<br />
3500<br />
3000<br />
2500<br />
Gas Turbine (LNG)<br />
Gas Turbine (Local Syngas)<br />
R/MWh<br />
2000<br />
1500<br />
1000<br />
Wind (Non-dispatchable)<br />
Pumped Storage (Generic)<br />
500<br />
Pumped Storage (Braamhoek)<br />
0<br />
0 5 10 15 20 25 30<br />
Load Factor (%)<br />
Figure 8: Life cycle levelised costs to build and operate peaking plants
Reference Case<br />
The open cycle gas turbine levelised cost curves cross the Braamhoek Pumped Storage scheme cost curve<br />
near 6% load factor. They cross the Generic Pumped Storage Scheme near 10% load factor. (Note: Wind<br />
turbines are considered non-dispatchable options operating at low load factor due to paucity of wind resources<br />
in South Africa).<br />
Although some of the technologies overlap in the screening curves shown above, there is a significant<br />
statistical difference between the capital costs of the various technologies at a 95 % confidence interval (see<br />
Appendix 3). The screening curves show that, once capital costs are combined with O&M and fuel costs, the<br />
differences between the total levelised costs of certain technologies are not statistically significant (they<br />
overlap) at certain load factors.<br />
5.6 Other: Environmental, Externalities, Transmission Expansion<br />
Certain sites and technologies will reduce the need to strengthen the electricity grid as they will be built close to<br />
load centres that are currently far from existing generation. This is taken into account in the levelised cost<br />
curves and is described further in the detailed descriptions of the technologies.<br />
All the new coal fired generating options considered meet World Bank emissions standards. Conventional coal<br />
stations will be equipped with flue gas desulphurisation. Due to the limited water resources all new coal<br />
stations are dry cooled.<br />
6.INTEGRATION AND SENSITIVITY ANALYSIS<br />
<strong>Resource</strong>s <strong>Plan</strong>ning has to deal with multiple conflicting objectives, a broad range of options and pervasive<br />
uncertainty. In this context it has to do with dominance and finding plans representing reasonable trade off<br />
amongst various conflicting objectives. If, for example, the objective were to minimise cost then those plans<br />
with higher cost would be considered inferior to those with lower cost. Lower cost plans would therefore<br />
dominate the higher cost plans.<br />
31<br />
The focus of the traditional resources planning approach is to provide a robust (and flexible) plan determined<br />
on the basis of an analysis of risk from either under or over investment within a range of forecast demand for<br />
electricity over a specified planning horizon. (A plan that is 100% robust is one which lies in the decision set for<br />
all futures and would lead to no regret). Flexibility is of equal importance to robustness, if not more important in<br />
the uncertain planning environment. Flexibility can be defined as the ability to modify a resource plan without<br />
significantly degrading system reliability and economics, in response to actual data that have deviated from<br />
the forecast data.<br />
The objective is therefore to provide long-term strategic projections of supply-side and demand-side options<br />
added or deducted from the system over a specified planning horizon taking into account investment risk and<br />
option lead time under a range of different planning scenarios.<br />
The risks associated with this planning process have been outlined previously but predominantly focus on<br />
those uncertainties, which will influence decisions on:<br />
& The timing for new supply-side and demand-side initiatives<br />
& The plant mix
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Due to time constraints, this round of the NIRP focuses on the development of a reference plan only. Elements<br />
of uncertainty and risk are taken into account by imposing constraints on plant operating reserve. In terms of<br />
this process two plans have been developed for this round of the NIRP, namely:<br />
& Reference <strong>Plan</strong> - constrained to 10% reserve margin<br />
& Alternative <strong>Plan</strong> 1 - constrained to 15% reserve margin<br />
& Alternative <strong>Plan</strong> 2 - sensitivity study conducted on the reference plan in order to determine the impact of<br />
excluding Interruptible supply agreements from the plan<br />
& Alternative <strong>Plan</strong> 3 (optimum reserve margin) - non-constrained plan providing as an output the optimum RM<br />
based on trade-off between the cost of reliability of supply and the cost of un-served energy to the<br />
consumer.<br />
The details of these plans are given in Appendix 2 to this report.<br />
6.1 Reference <strong>Plan</strong><br />
The reference plan has a minimum constraint of 10% on the reserve margin as proxy to take account of the risk<br />
elements detailed above. In addition to the constraint on the reserve margin, two further constraints are<br />
imposed.<br />
The first is in terms of the extent of un-served energy that would be allowed. In this case the un-served energy<br />
is constrained to a maximum of 0.011% of total energy demand in any specific year. This is reflective of<br />
historical values utilised in Eskom in previous years in order to ensure a loss of load expectation (LOLE) of 22<br />
hours is not exceeded in any given year.<br />
32<br />
The second is in terms of the number and capacities of Open Cycle Gas turbines accommodated in the plan<br />
because of perceived limitations in the gas supply and the possibility of these options becoming stranded<br />
assets in the event more interruptible supply options are implemented in the future. It was decided in this<br />
instance to consider a maximum number of 10 stations limited to 2x120 MW each could be built in the twentyyear<br />
planning horizon.<br />
The capacity outlook for this plan is illustrated in Figure 9 below and the detailed results are given in Appendix<br />
2 to this report.<br />
Mothballed Coal-Fired FBC GT Pumped Storage Demand-side Options<br />
YR Cam (PF) Gr'tvlei<br />
(PF)<br />
Kom<br />
(PF)<br />
PF (1) PF (2) Greenfield<br />
FBC<br />
OCGT PS (A) PS (B) PS (C) PS (D) CEE IMEE IMLM REE RLM Syst Res<br />
Committed Committed CommittedCommittedCommittedCommittedCommitted<br />
2003 Decide 14 16 41 32 49 24%<br />
2004 Decide Decide 14 16 41 32 49 21%<br />
2005 380 Decide Decide 14 16 41 32 49 18%<br />
2006 380 Decide 14 16 41 32 49 15%<br />
2007 380 Decide Decide 14 16 41 32 49 14%<br />
2008 380 Decide 240 14 16 41 32 49 12%<br />
2009 377 480 14 16 41 32 49 12%<br />
2010 377 303 480 14 16 41 32 49 12%<br />
2011 377 303 480 14 16 41 32 49 10%<br />
2012 303 466 480 333 11%<br />
2013 240 999 11%<br />
2014 466 666 11%<br />
2015 333 333 10%<br />
2016 466 666 11%<br />
2017 932 333 11%<br />
2018 466 333 11%<br />
2019 642 10%<br />
2020 642 1284 12%<br />
2021 1284 1284 12%<br />
2022 1284 1284 11%<br />
TOTAL 1520 1130 909 3852 3852 2796 2400 1332 999 999 666 124 145 368 292 441<br />
Figure 9: Reference plan (10% Reserve Margin)
Reference Case<br />
These results indicate a commitment to ensuring the immediate return to service of Camden power station in<br />
the suite of Eskom Simunye mothballed plants. In addition an immediate decision is required to build at least<br />
720 MW of OCGT plant for commissioning and commercial service by 2009. Furthermore, activities<br />
(monitoring and evaluation) need to be implemented immediately to ensure Braamhoek pumped storage<br />
remains on track for commercial service in 2012, and also that the DSM programmes achieve their targets over<br />
the ensuing years.<br />
6.2 Alternative <strong>Plan</strong> 1 to Reference <strong>Plan</strong><br />
There is a concern that carrying a 10% reserve margin on the moderate national forecast is too conservative in<br />
the light that most international utilities are reluctant to carry a RM below 15%. An additional plan has been<br />
developed which is constrained to a reserve margin of 15%. This plan is detailed in Figure 10 below.<br />
Mothballed Coal-Fired FBC GAS Pumped Storage Demand-side Options<br />
YR<br />
Cam (PF) Gr'tvle<br />
i (PF)<br />
Kom<br />
(PF)<br />
PF (1) PF (2) Greenfield<br />
FBC<br />
CCGT<br />
(1)<br />
CCGT (2) OCGT PS (A) PS (B) PS (C) PS (D) CEE IMEE IMLM REE RLM Syst<br />
Res<br />
Committed Decide Committed Committed Committed Committed CommittedCommitted<br />
2003 Decide Decide Decide Decide 14 16 41 32 49 24%<br />
2004 Decide Decide Decide 14 16 41 32 49 21%<br />
2005 380 14 16 41 32 49 18%<br />
2006 380 Decide 14 16 41 32 49 15%<br />
2007 380 188 Decide 14 16 41 32 49 14%<br />
2008 380 377 202 Decide 480 14 16 41 32 49 15%<br />
2009 377 303 480 14 16 41 32 49 15%<br />
2010 202 466 387 240 14 16 41 32 49 15%<br />
2011 466 774 14 16 41 32 49 14%<br />
2012 188 1161 333 15%<br />
2013 202 999 15%<br />
2014 932 333 15%<br />
2015 666 14%<br />
2016 642 333 15%<br />
2017 466 666 333 15%<br />
2018 642 466 15%<br />
2019 333 13%<br />
2020 1284 333 15%<br />
2021 1284 1284 15%<br />
2022 1284 1284 387 14%<br />
TOTAL 1520 1130 909 3852 3852 2796 1935 774 1200 1332 999 999 999 124 145 368 292 441<br />
33<br />
Figure 10: Alternative <strong>Plan</strong> 1 to reference plan (15% Reserve Margin)<br />
Alternative 1 requires additional capacity of 1842 MW over the planning horizon, at the additional cost of 15<br />
552 million Rand, in order to maintain the higher RM of 15%. The plan also requires acceleration of the return to<br />
service of the mothballed plants and base load PF plant.<br />
6.3 Alternative <strong>Plan</strong> 2 (Sensitivity Study)<br />
A prime concern of ARC members is the uncertainty surrounding the sustainability of interruptible supply<br />
options. In order to determine the impact of interruptible supply options, a further plan (Alternative <strong>Plan</strong> 2) was<br />
developed based on the primary assumptions and constraints used to develop the reference plan but<br />
excluding all interruptible supply options from the plan. This plan is detailed in Figure 11 below.<br />
This plan requires significant acceleration of the return to service programme of the mothballed plants in the<br />
near term. In this, the plan is at risk, because the return to service programme of the Simunye plant, even with<br />
the best endeavours, might be unable to be accelerated sufficiently to meet the demand in the near term<br />
(2006).<br />
There is a PV increase in costs of this plan when compared to the reference plan of 2 997 Million Rand. The<br />
higher cost of this plan is largely due to the fact that there is a penalty paid in interrupting customers in the early<br />
years at a high cost of un-served energy of 20 660 R/MWh.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Mothballed Coal-Fired FBC Gas Pumped Storage Demand-side Options<br />
YR Cam (PF) Gr'tvlei<br />
(PF)<br />
Kom (PF) PF (1) PF (2) Greenfield<br />
FBC<br />
OCGT PS (A) PS (B) PS (C) PS (D) CEE IMEE IMLM REE RLM Syst<br />
Res<br />
Committed Committed Committed Committed Committed Committed Committed<br />
2003 Decide Decide Decide Decide 14 16 41 32 49 19%<br />
2004 Decide Decide 14 16 41 32 49 16%<br />
2005 380 14 16 41 32 49 13%<br />
2006 380 Decide Decide 14 16 41 32 49 10%<br />
2007 380 377 101 14 16 41 32 49 10%<br />
2008 380 101 Decide 480 14 16 41 32 49 11%<br />
2009 377 202 480 14 16 41 32 49 11%<br />
2010 377 303 480 14 16 41 32 49 12%<br />
2011 202 466 480 14 16 41 32 49 11%<br />
2012 466 480 333 11%<br />
2013 999 11%<br />
2014 999 333 11%<br />
2015 333 10%<br />
2016 466 333 333 10%<br />
2017 932 333 11%<br />
2018 642 333 11%<br />
2019 466 10%<br />
2020 642 1284 11%<br />
2021 1284 1284 11%<br />
2022 1284 1284 11%<br />
TOTAL 1520 1130 909 3852 3852 2796 2400 1332 999 999 999 124 145 368 292 441<br />
Figure 11: Alternative <strong>Plan</strong> 2 - sensitivity to reference plan (excludes interruptible supply options)<br />
6.4 Alternative <strong>Plan</strong> 3 (Optimal reserve margin)<br />
The issue of determining an optimal reserve margin for electricity generation in South Africa has not been<br />
addressed formally in any forum in the country to date. In optimal integrated resources planning studies, the<br />
calculation of the reserve margin is an outcome, based on the primary assumptions underpinning the<br />
development of the plan.<br />
34<br />
It is therefore expedient to determine a reserve margin based on the outcome of the optimisation process, but<br />
taking into account specified risk(s) associated with key uncertainties in the primary planning assumptions.<br />
Such a plan will result in a different mix and timing of new plant options compared to one developed to meet a<br />
deterministic reliability index.<br />
The development of such a plan is intended as the outcome of the next round of studies aimed at producing a<br />
recommended set of strategies (plan) for NIRP2 based on an analysis of risk factors associated with the<br />
primary assumptions.<br />
As a starting point to this exercise, an optimal plan has been developed, based on the primary assumptions<br />
listed above without imposing any constraints and in particular on the reserve margin, un-served energy and<br />
number of peaking (OCGT) plants.<br />
This plan is detailed in the Appendix 2 to this report. It is intended that this plan will serve as the basis for the<br />
next round of studies where several different plans will be developed on the basis of meeting a number of risk<br />
scenarios associated with the uncertainties surrounding several of the key assumptions. In each of the plans,<br />
the reserve margin will be an outcome as a function of the risk associated with specified uncertainties.<br />
It is important to state that given certainty in the current primary assumptions, the reserve margin required<br />
would be of the order 4% in the long-term. This plan would however not be sufficiently flexible to meet any of<br />
the short or long-term risks detailed above.
Reference Case<br />
7.SYSTEM ANNUAL AVERAGE LONG RUN MARGINAL COST<br />
In this report, the terms Long Run Marginal Cost (LRMC) and Long Run Incremental Cost (LRIC) are used<br />
interchangeably. Theoretically the LRMC refers to the incremental cost of providing one additional unit of<br />
energy to supply the increase in demand; whereas the LRIC refers to the incremental cost of providing an<br />
additional increment of energy.<br />
The LRMC curve is calculated by determining the difference in costs between two generation expansion plans<br />
developed over the twenty-year planning horizon:<br />
(1) Base case: to meet the forecast demand in electricity and,<br />
(2) Marginal case: the forecast demand increased by an increment (500 MW in this case)<br />
The annual difference in optimal cost for building and operating plant to meet these two plans is divided by the<br />
difference in energy associated with each of these annual forecast demands. (I.e. the base demand and the<br />
demand increased by the increment of 500 MW at the system annual average load factor).<br />
The LRMC has been developed using this methodology, for the reference plan and each of the alternative<br />
plans to the reference plan. The detailed results are given in Appendix 2 attached to this report and illustrated<br />
graphically in Figure 12.<br />
280.0<br />
260.0<br />
System Marginal Cost of NIRP Ref <strong>Plan</strong> at 2003 prices (10% NDR)<br />
240.0<br />
220.0<br />
35<br />
LRMC in R/MWh<br />
200.0<br />
180.0<br />
160.0<br />
140.0<br />
120.0<br />
100.0<br />
80.0<br />
Alt <strong>Plan</strong> 2 (Ref excluding interruptible loads , (R/MWh)<br />
Alt <strong>Plan</strong> 1 (15% RM) (R/MWh)<br />
Ref <strong>Plan</strong> (R/MWh)<br />
60.0<br />
40.0<br />
20.0<br />
0.0<br />
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022<br />
Years<br />
Figure 12: Annual average long run marginal costs of plans<br />
Of particular significance in these results are the high values of the LRMC in the early years associated with the<br />
Alternative 2 excluding interruptible supply options. This is because the Simunye mothballed plant cannot be<br />
returned to service in time to avoid interrupting customers at a high cost to the economy.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
8.CONCLUSIONS<br />
The main conclusions drawn from the NIRP2 reference case study could be summarised as follows:<br />
36<br />
1) Options for diversification are insufficient to meet all of the forecast demand for electricity over the next 20-<br />
year planning horizon. Coal-fired options are still required for expansion during this period. For<br />
environmental benefit it is imperative to continue with efforts to reduce the costs of implementing clean<br />
coal technologies and improve the efficiency of coal-fired plants;<br />
2) Base load plants are required for commercial operation from 2010. Base load options competing, include;<br />
Pulverised Fuel Coal-fired (PF); Fluidised Bed Combustion (FBC); Combined Cycle Gas Turbine (CCGT).<br />
Given the cost and performance data used in the plan these options are broadly comparable, at 10% net<br />
discount rate, if regional siting and transmission benefits are included.<br />
3) At the current assumed cost of capital (10% net discount rate) and after returning the Eskom mothballed<br />
plant to service, fluidised bed combustion technologies are South Africa's most economic option, followed<br />
by investment in coal-fired plant. This in turn is followed by importing gas / LNG for CCGT plant in the<br />
Cape. The studies also show that after taking the avoided cost of transmission into account (including<br />
losses) that is not sufficient to make the CCGT plant competitive with coal;<br />
4) It will be difficult to justify diversification on an economic basis, unless penalties for not doing so are<br />
included in future analyses. As the cost for diversification is becoming increasingly more expensive these<br />
penalties (or opportunities for emissions trading) will need to be substantial to offset the economic benefits<br />
of remaining with coal;<br />
5) The NIRP plans are based on attainment and sustainability of the DSM targets , power plants availability,<br />
imports and interruptible loads;<br />
6) The NIRP plans indicate that 920 MW OCGT peak load plants must begin commissioning from 2008;<br />
7) Maintaining a higher reserve margin of 15% over the planning period will require acceleration of the RTS of<br />
the mothballed plants and coal-fired options together with commissioning of additional base load capacity<br />
(CCGT);<br />
8) Diversified options are new technologies to South Africa. If these options for whatever reason are not able<br />
to be implemented it will mean a return to a dependency on new pulverised coal-fired plants earlier than<br />
shown in these plans;<br />
9) There are supply options that have not been considered such as co-generation in industry, converting<br />
OCGT to CCGT, adding units onto existing power stations and new imports resulting from the<br />
development of Electricity Supply in the Southern African region;<br />
10) Should interruptible supply and / or OCGT capacity not be implemented this will significantly advance<br />
new base-load capacity;
Risk & Sensitivity Analysis<br />
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Stage 2<br />
Risk & Sensitivity Analysis<br />
37<br />
COMPILED BY<br />
The <strong>National</strong> Electricity Regulator<br />
ISEP Eskom (<strong>Resource</strong>s and Strategy)<br />
Energy Research Institute<br />
University Of Cape Town
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
NIRP 2 STAGE 2:<br />
RISK AND UNCERTAINTY ANALYSIS<br />
TABLE OF CONTENTS<br />
1 INTRODUCTION 40<br />
2 SCOPE OF STUDY 40<br />
2.1 APPROPRIATE RESERVE MARGIN 40<br />
2.2 IDENTIFIED RISKS AND UNCERTAINTIES 41<br />
2.3 IMPACT OF THE SELECTED RISK PORTFOLIOS 42<br />
38<br />
3 MODELED UNCERTAINTIES 43<br />
3.1 FORECAST 43<br />
3.1.1 Background 43<br />
3.1.2 Compilation of the energy component of the higher forecast 43<br />
3.1.3 Compilation of the demand component of the higher forecast 44<br />
3.1.4 Forecast Data 46<br />
3.2 AVAILABILITY OF PLANT 47<br />
3.3 SUSTAINABILITY OF EXISTING INTERRUPTIBLE LOADS 48<br />
3.4 SUSTAINABILITY OF EXISTING CAPACITY 48<br />
4 SCENARIO DEVELOPMENT 49<br />
5 RANKING OF PLANS/CANDIDATE PLANS 51<br />
5.1 METHODOLOGY 51<br />
5.2 TOTAL PROBABILITY-WEIGHTED COST 52<br />
5.3 RELIABILITY ASSESSMENT 53<br />
5.4 EMISSIONS AND DIVERSIFICATION ASSESSMENT 54<br />
6 PREFERRED RESOURCE PLAN 56<br />
6.1 PREFERRED PLAN 14 56<br />
7 SENSITIVITY ANALYSIS 57<br />
7.1 COMPARISON OF DATA CHANGES TO NIRP2 REFERENCE PLAN 57<br />
7.2 THE IMPACT OF NET DISCOUNT RATE ON OPTIMUM CHOICE OF TECHNOLOGY 59<br />
7.3 RENEWABLE ENERGY TECHNOLOGIES 62<br />
8 CONCLUSIONS 64<br />
9 APPENDICES 64
Risk & Sensitivity Analysis<br />
LIST OF FIGURES<br />
Figure 1. Impact of Modelled Uncertainties 43<br />
Figure 2. Energy Forecasts 44<br />
Figure 3. Maximum Demand Forecasts 45<br />
Figure 4. The proportion of consumption increases over the reference case. 47<br />
Figure 5. Variability of total cost. 53<br />
Figure 6. Reserve Margin under own future. 53<br />
Figure 7. Reserve Margin under A1 future. 54<br />
Figure 8. Ranking of <strong>Plan</strong>s 56<br />
Figure 9. Capex Costs for Base Options 58<br />
Figure 10. O&M Costs for NIRP 2 Reference <strong>Plan</strong> and NIRP 2 Risk & Sensitivity <strong>Plan</strong> 58<br />
Figure 11. Fuel Costs for NIRP 2 Reference <strong>Plan</strong> and NIRP 2 Risk & Sensitivity <strong>Plan</strong> 59<br />
Figure 12. Levelised costs of base-load plants versus Net Discount Rate for the<br />
NIRP 2 Reference <strong>Plan</strong> 61<br />
Figure 13. Levelised costs of base-load plants versus Net Discount Rate for the<br />
NIRP 2 Risk & Sensitivity analysis 61<br />
Figure 14. Preferred <strong>Plan</strong> 14 with Renewables 63<br />
Figure 15. Reduction in environment emissions in preferred <strong>Plan</strong> 14 with renewables. 63<br />
LIST OF TABLES<br />
Table 1. Forecasting Data 46<br />
Table 2. Electricity demand in the high growth scenario (GWh) 47<br />
Table 3. Availabilities of new plant. 48<br />
Table 4. Probabilities associated with primary assumptions. 49<br />
Table 5. Scenarios and their probabilities. 50<br />
Table 6. PWC Ranking of the <strong>Plan</strong>s 52<br />
Table 7. Comparison of Candidate <strong>Plan</strong>s 55<br />
Table 8. Preferred <strong>Plan</strong> 14. 57<br />
Table 9. Levelised costs of candidates for selection in the NIRP2 Reference <strong>Plan</strong> 60<br />
Table 10. Levelised costs of candidates for selection for the NIRP2 Risk and Sensitivity<br />
analysis 60<br />
Table 11. Additional Cost of Renewable Technologies 62<br />
39
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
1.Introduction<br />
This Report is an update of the NIRP2 Reference <strong>Plan</strong>. This work was commissioned following comments<br />
received from both the Public and the NER Advisory Review Committee (ARC) after the publication of the<br />
NIRP2 Reference <strong>Plan</strong>.<br />
This Report should be read in conjunction with that of the NIRP2 Reference <strong>Plan</strong> since it uses as basis the<br />
primary planning assumptions (including the data base) of the reference plan unless stated otherwise. Where<br />
data revisions have been made to the reference data, these are explained in the Report. The list of<br />
abbreviations and bibliography of the NIRP2 Reference <strong>Plan</strong> apply to this Report.<br />
The objective of this study is to provide a robust plan for NIRP2 based on an appropriate net reserve margin<br />
above the expected annual maximum demand for electricity assumed in the Reference plan. This reserve<br />
margin is calculated as an outcome based on an analysis of specified probability weighted risk portfolios.<br />
A complete listing of comments from the Advisory Review Committee (ARC) of the NER plus comments from<br />
individual members of the Public concerning the NIRP2 Reference <strong>Plan</strong> are contained in Appendix A attached<br />
to this Report. The most important aspects leading to the need to carry out a risk and sensitivity analysis are<br />
summarized below:<br />
& The use of deterministic reserve capacity margin as a substitute for risks, without explicitly identifying the<br />
mitigated risks associated with the planning uncertainties (plant availability, load forecast deviations, fuel<br />
availability, interruptible supplies etc), is not ideal planning method;<br />
40<br />
& The appropriate reserve margin should be an outcome of a risk and uncertainty analyses, characteristics of<br />
the existing and future plants and costs. The reserve margin should be an outcome of the modeling process<br />
based on sets of defined assumptions for different scenarios;<br />
& The impact of the discount rate on the optimum choice of technology should be considered in the analyses;<br />
& Considerations regarding resource alternatives under high growth scenarios should be included;<br />
& The costs of some generation sources such as FBC and imported hydro, as well as the cost of the coal are<br />
underestimated;<br />
& The Inclusion of Government renewable energy targets.<br />
2.Scope of study<br />
The major concern expressed by the ARC and members of the Public were expressed in the many comments<br />
regarding an appropriate reserve margin to cater for risk. This report therefore focuses on developing a robust<br />
plan with an appropriate reserve margin accounting for risk. It also takes into account as far as possible<br />
attributes other than least cost such as environmental emissions, flexibility and a diversified portfolio of<br />
options.<br />
2.1 Appropriate Reserve Margin<br />
The reference plan used two levels of deterministic net reserve margin (10% and 15%) to take account of risk.<br />
The use of a deterministic net reserve margin to address risk, without explicitly identifying and quantifying the<br />
risks associated with the primary planning uncertainties (e.g. plant availability, load forecast deviations, fuel<br />
availability, interruptible supplies etc), is not an ideal planning method.
Risk & Sensitivity Analysis<br />
An appropriate net reserve margin should consist of a plant mix which matches the risk impacting the capacity<br />
shortage; E.g. If Cahora Bassa units became unavailable , base-load capacity would be required to meet the<br />
shortfall. If interruptible capacity became unavailable, peaking plant would be required.<br />
Following discussions at the Advisory Review Committee and resulting from the various comments received, it<br />
was decided to adopt the following approach to determine a appropriate net reserve margin for stage2 of<br />
NIRP2.<br />
& Develop scenarios and assign probabilities<br />
& Develop plans for each scenario<br />
& Carry out trade-off analyses (I.e. Test each plan under each scenario and calculate the total probability<br />
weighted cost (cost of supply plus cost of non-supply) of each plan multiplied by the probability of<br />
occurrence of the scenario<br />
& Select the most robust (flexible) plan under agreed attributes<br />
Evaluate the net reserve margin of this plan in respect of the expected forecast<br />
2.2 Identified risks and uncertainties<br />
Following the NIRP2 Reference plan, the following short-term and long-term risks and uncertainties were<br />
identified for inclusion in the risk and uncertainty analysis.<br />
& <strong>Plan</strong>t failure leading to longer than expected plant outage;<br />
& Unavailability of municipal / Eskom / imported generating capacity;<br />
& Degree of market penetration of DSM and maintaining current level of interruptible loads;<br />
& Unexpected decrease / increase, spurious or sustained, of electricity demand;<br />
& Changes to the load shape associated with the forecast electricity demand;<br />
& Unexpected decommissioning / de-rating of existing generating capacity<br />
& Uncertain and prolonged lead times for building new plant;<br />
& Project slippage<br />
& Inclusion of co-generation options;<br />
& Embargoes on nuclear energy;<br />
& Shortage of skills to maintain and grow the system;<br />
& Other energy forms displacing electricity in the energy market;<br />
& Revolutionary technologies coming on the scene and stranding existing assets;<br />
& Internalisation of externalities, such as introduction of a carbon tax and environmental levy;<br />
& <strong>Plan</strong>t life expectations not met;<br />
& Deterioration in credit rating, exchange rates etc. resulting in a higher cost of capital;<br />
& Electricity supply and sales contracts (import and export contracts) being reneged upon;<br />
& Effect of AIDS on the electricity market.<br />
& Drought and Floods<br />
41<br />
Many of these risks and uncertainties are inter-dependent. By aggregating some risk events into independent<br />
risk portfolios it is possible to provide a net reserve margin to cater for a number of risk events under the<br />
umbrella of one independent risk portfolio. This can best be illustrated by the following examples:<br />
Drought: The impact of drought on Hydro imports (Cahora Bassa) can be taken into account by reducing the<br />
capacity of this option. The level of capacity reduction from Cahora Bassa can also be increased to cater for<br />
reduced imports due to increasing capacity withdrawals to neighbouring states (notwithstanding current<br />
agreements) in the future. Although strictly speaking these two events can be construed as separate events<br />
each with their own probability of occurrence, for the purposes of this report the level of capacity reduction is<br />
set to accommodate both with the same probability.<br />
No account is taken of the impact of drought on existing Hydro capacity because the amount of such Hydro in
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
this country is very low. Drought also impacts both cooling water supplies of existing and new coal-fired plants.<br />
This is mitigated to some extent by the fact that all new inland base plants are considered to be dry-cooled (or in<br />
the least dry-cooled with wet assistance at high ambient temperatures). Those located at the coast use once<br />
through sea water cooling.<br />
Flood: This impacts the availability of fuel supplies to the coal-fired plants, mitigated to some extent by those<br />
stations with open cast mines (these are more likely to be impacted) carrying higher stock levels. From the<br />
point of view of imported Hydro, a substantial energy loss could be averted in times of flood, through<br />
implementing a SAPP Zambesi River Authority to ensure for example that where possible water is not let out of<br />
higher altitude dams (Kafua) whilst lower altitude dams (Cahora Bassa) are spilling.<br />
Impact of fuel cost / price: The South African Electricity Supply is heavily dependent on coal as feedstock. In<br />
the event that there was a major price increase in the cost of coal, the economy would be at risk. There are<br />
proponents to providing a diversified approach to building new generating options which may also be more<br />
favorable in reducing environmental and greenhouse gas emissions. This aspect is addressed in that three<br />
new base technologies other than conventional coal-fired plants are considered: Fluidised Bed Combustion<br />
(FBC), Nuclear Pebble Bed Modular Reactors, Gas Combined Cycle (CCGT) options.<br />
Following discussions with various experts in their specific fields, it was decided to address the following four<br />
risk portfolios, considered to be largely independent of each other and as having a major impact on the plant<br />
mix, timing and requirement for carrying reserve, namely:<br />
42<br />
& Level of risk associated with the moderate national forecast being higher and particularly in the near-term to<br />
medium-term;<br />
& Level of risk associated with Eskom and non-Eskom generators being able to sustain high levels of plant<br />
availability once the system becomes stressed and the plants age;<br />
& Level of risk of Non-Eskom and Import capacity becoming unavailable or unreliable (i.e. being de-rated) and<br />
particularly in the near-term;<br />
& Availability of interruptible supply options continuing to serve as reserve capacity. Already these options are<br />
severely energy constrained and their capacity impact has been reduced.<br />
2.3 Impact of the selected risk portfolios<br />
Following discussions with respective experts the following levels of risk were identified for each of the risk<br />
portfolios:<br />
& <strong>National</strong> moderate Load forecast increased by 2570MW in 2007 to 5078MW in 2022 to account for higher<br />
GDP growth and colder weather (Base-load to Peaking)<br />
& <strong>Plan</strong>t availability reduced from 88% to 85% due to poorer FOR (Base-load).<br />
& Contracted Interruptible Supply Excluded:<br />
> Mozal, Alusaf, Ferrochrome and other industries (Peaking)<br />
& Capacity Reductions:<br />
> Cahora Bassa capacity reduced from 1281MW by 250MW in 2004 and 500MW thereafter (Base-load)<br />
> Non-Eskom OCGT capacity (180MW of 270MW) assumed unavailable over the planning horizon<br />
(Peaking)<br />
> Non-Eskom coal-fired capacity (600MW of 1920MW) assumed unavailable over the planning horizon<br />
(Base-load)
Risk & Sensitivity Analysis<br />
The impact of these levels of uncertainty over the planning horizon is illustrated graphically in Figure 1 below.<br />
Impact of Modelled Uncertainties<br />
10000<br />
9000<br />
8000<br />
7000<br />
Capacity (MW)<br />
6000<br />
5000<br />
4000<br />
3000<br />
Capacity impact of excluding Import and Munic capacity (MW)<br />
Capacity Impact of excluding DSM Interruptible load (MW)<br />
Capacity impact of increased load forecast (MW)<br />
Capacity impact of reduced plant availability (89% to 85%) (MW)<br />
2000<br />
1000<br />
0<br />
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022<br />
Years<br />
Figure 1: Impact of Modelled Uncertainties<br />
3.Modelled Uncertainties<br />
These risk portfolios were generated on the basis of the comments made on the primary assumptions by the<br />
ARC and in consultations with various experts. Following is a description of the levels or risk associated with<br />
the primary assumptions as detailed in the NIRP2 Reference <strong>Plan</strong>.<br />
43<br />
3.1 Forecast<br />
3.1.1 Background<br />
The NIRP2 reference plan is based on a moderate demand for electricity developed by Eskom. This forecast<br />
used moderate GDP growth and moderate weather conditions. It was recommended by the ARC to also<br />
develop a forecast of accelerated demand growth for the risk and uncertainty analysis, reflecting colder<br />
weather conditions and higher GDP growth (especially in the near-term). It was not considered necessary by<br />
the ARC to use a lower forecast than the moderate, the moderate being considered to be already reflective of a<br />
lower than expected scenario. It was agreed that the Energy Research Centre (ERC) would develop the high<br />
growth forecast independent of Eskom. Eskom resources would be used to transform the energy forecast into<br />
hourly annual demand values according to Eskom sector profiles.<br />
3.1.2 Compilation of the energy component of the higher forecast<br />
The higher energy forecast in demand for electricity was developed by ERC based on energy forecasting<br />
techniques incorporated in the LEAP model (SEIB 2002; Howells et al 2002; and Hughes et al, 2003), and the<br />
Integrated <strong>Resource</strong> <strong>Plan</strong>ning manual of the United Nations Environment Program (UNEP 1998). It considers<br />
a relatively detailed breakdown of electricity consuming sectors. For example, the mining sector was divided<br />
into nine different sub-sectors, as was the industrial sector. Added to this was the commercial, transport,<br />
agricultural and residential sectors. A relationship was developed between the outputs of these sectors and the<br />
future Gross Domestic Product (GDP) (with the exception of the residential sector) as a basis for future<br />
electricity demand. The relationship between GDP and sector output is time dependant with the proportional<br />
contribution of each sector changing over time. The sector outputs considered was either value added, or<br />
physical output.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
In line with the assumptions approved by ARC, the ERC developed a high forecast which used higher than<br />
expected growth in the near- to medium-term in specific sectors. The growth associated with this forecast is<br />
higher than that of the moderate forecast of the NIRP2 Reference plan by an estimated half a percentage point<br />
in the short to medium term.<br />
When the results of the ERC energy forecast are compared to that of the Eskom model they will differ in certain<br />
respects. A forecast with a higher growth rate will automatically imply a different sectoral energy mix.<br />
Furthermore, the energy model used by the ERC makes use of sectoral data of a more aggregated nature than<br />
the Eskom sectoral model.<br />
A comparison of the energy forecasts for the previous NIRP1, NIRP2 reference case and this analysis is<br />
shown in the Figure 2 below.<br />
Energy sent out<br />
400000<br />
44<br />
Annual energy sent out [GWh]<br />
350000<br />
300000<br />
250000<br />
200000<br />
NIRP1 Moderate growth and moderate weather<br />
NIRP2 Moderate growth and moderate weather<br />
NIRP2 High growth and cold weather<br />
150000<br />
2001<br />
2003<br />
2005<br />
2007<br />
2009<br />
2011<br />
2013<br />
2015<br />
2017<br />
2019<br />
2021<br />
2023<br />
2025<br />
Year<br />
Figure 2:. Energy Forecasts<br />
3.1.3 Compilation of the demand component of the higher forecast<br />
The energy forecast is transformed into an hourly demand forecast (instantaneous demands averaged over<br />
each hour) with the HELM (Hourly Electric Load Model) computer model. The model uses:<br />
& Detailed sectoral load profiles developed by Eskom<br />
& Energy sales forecast and losses as inputs<br />
& Temperature as an input where the impact is determined through pre-determined formulae (E.g. for<br />
extremely cold weather).<br />
& Output is hourly maximum demands in each year over the whole planning horizon<br />
The following assumptions were used in developing this demand forecast:<br />
& The ERC energy sales forecast as described above;<br />
& Updated sectoral demand profiles, which were obtained from recent load research carried out by Eskom<br />
consultants in 2003;<br />
& The system load factor was constrained to deteriorate within a narrowband (from 72% in 2004 to 70% in<br />
2022).
Risk & Sensitivity Analysis<br />
& Based on 1996 weather conditions which is recorded as the coldest weather <strong>National</strong>ly over the last 12 years<br />
& No new demand side management initiatives are included in the forecast from 2003 (I.e. from the beginning<br />
of the planning horizon)<br />
It is pertinent to note that the system losses as calculated by the ERC and used in this analysis are marginally<br />
different to those calculated by Eskom. The annual maximum demands for the various NIRP studies are<br />
compared in Figure 3below.<br />
65000<br />
Maximum demand<br />
60000<br />
Maximum demand [MW]<br />
55000<br />
50000<br />
45000<br />
40000<br />
35000<br />
30000<br />
25000<br />
NIRP1 Moderate growth with moderate weather<br />
NIRP2 Moderate growth with moderate weather<br />
NIRP2 High growth with cold weather<br />
2001<br />
2003<br />
2005<br />
2007<br />
2009<br />
2011<br />
2013<br />
2015<br />
2017<br />
2019<br />
2021<br />
2023<br />
2025<br />
Year<br />
45<br />
Figure 3:. Maximum Demand Forecasts<br />
3.1.3.1.1 Weather<br />
The 1996 <strong>National</strong> weather pattern was used to estimate weather impact because statistically it was found to<br />
be the coldest over the last twelve years. The impact of this colder weather is to increase the annual peak<br />
demand of the moderate forecast by approximately 3% in 1996 and extrapolated for the other years in the<br />
planning horizon.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
3.1.4 Forecast Data<br />
The relevant data supporting the Figures illustrated above are given in the Table 1 below.<br />
NIRP1 (Moderate) NIRP2 (Moderate) NIRP2 (High)<br />
Moderate Growth and moderate<br />
weather (Forecast energy and losses<br />
determined by Eskom)<br />
Moderate Growth and moderate<br />
weather (Forecast energy and losses<br />
determined by Eskom)<br />
Higher Growth and cold weather<br />
(Forecast energy and losses<br />
determined by ERC)<br />
Year<br />
NIRP1 MW<br />
Moderate Increase<br />
per<br />
Year<br />
(MW)<br />
Sales<br />
GWh<br />
Losses<br />
%<br />
Annual<br />
Energy<br />
(GWh)<br />
NIRP2<br />
Moderate<br />
Demand<br />
(MW)<br />
MW<br />
Increase<br />
per<br />
Year<br />
(MW)<br />
Sales<br />
GWh<br />
Losses<br />
%<br />
Annual<br />
Energy<br />
(GWh)<br />
NIRP2 MW<br />
High Increase<br />
Demand per<br />
(MW) Year<br />
(MW)<br />
Sales<br />
GWh<br />
Losses<br />
%<br />
Annual<br />
Energy<br />
(GWh)<br />
46<br />
1999 177689<br />
2000 181908<br />
2001 32316 185171 9.88 205476<br />
2002 33283 967 188747 10.83 211665<br />
2003 34499 1216 194240 11.63 219794 33645 197189 9.15 217044 34624 197401 9.21 217426<br />
2004 35684 1185 202858 10.81 227439 34914 1269 205159 9.15 225824 36817 1274 209722 9.33 231303<br />
2005 36784 1100 212559 9.19 234066 36146 1232 212415 9.15 233805 38394 1238 218274 9.45 241054<br />
2006 37867 1083 220649 8.24 240457 37632 1486 221593 9.27 244242 39931 1466 227001 9.57 251024<br />
2007 38811 944 225444 8.22 245623 38528 896 226305 9.27 249423 41098 902 232602 9.69 257560<br />
2008 39798 987 230669 8.15 251128 39440 912 231064 9.26 254657 42166 919 237671 9.81 263523<br />
2009 40784 986 235125 8.51 256984 40377 937 236245 9.33 260559 43387 930 243686 9.93 270552<br />
2010 41835 1051 239711 8.84 262952 41389 1012 241799 9.33 266681 44574 1018 249547 10.05 277429<br />
2011 42864 1029 244139 9.26 269068 42342 953 247295 9.34 272762 45777 961 255450 10.17 284370<br />
2012 43894 1030 248886 9.53 275118 43389 1047 253220 9.41 279513 47091 1039 262064 10.29 292123<br />
2013 44893 999 253810 9.64 280896 44343 954 258581 9.41 285448 48275 962 267718 10.42 298859<br />
2014 45922 1029 258683 9.83 286883 45271 928 263829 9.42 291258 49423 936 273173 10.54 305358<br />
2015 46971 1049 263584 10.04 292993 46198 927 268355 9.55 296678 50520 903 278263 10.66 311465<br />
2016 47980 1009 268586 10.22 299148 47034 836 273055 9.56 301910 51597 844 283176 10.78 317391<br />
2017 49068 1088 273812 10.37 305500 47939 905 277825 9.56 307194 52692 913 288139 10.90 323388<br />
2018 50199 1131 278976 10.64 312198 48901 962 282731 9.63 312847 53839 954 293445 11.02 329788<br />
2019 51350 1151 284268 10.88 318978 49841 940 287716 9.63 318375 54976 948 298636 11.14 336075<br />
2020 52507 1157 289652 11.10 325802 50790 949 292725 9.63 323929 56118 958 303850 11.26 342405<br />
2021 53739 1232 295143 11.32 332817 52249 1459 297965 10.64 333445 57101 1072 308905 11.38 348572<br />
2022 54936 1197 300639 11.55 339879 53256 1007 303304 10.64 339407 58334 1013 314602 11.50 355483<br />
2023 56182 1246 306176 11.74 346911<br />
2024 57400 1218 311731 11.96 354066<br />
2025 58673 1273 317332 12.16 361269<br />
Average 1098 1032 1013<br />
Table 1: Forecasting Data<br />
3.1.4.1 Changes in higher forecast from reference case<br />
The difference between the NIRP2 Reference case forecast and this high growth forecast is due mostly to an<br />
increase in industrial demand. This is illustrated in a breakdown of differences in consumption for the year<br />
2013 as shown in Figure 4.
Risk & Sensitivity Analysis<br />
Transport<br />
Residential<br />
Mining<br />
Agriculture<br />
Commerce<br />
Industry<br />
Figure 4: The proportion of consumption increases over the reference case.<br />
A detailed breakdown in GWh of demand consumption for the high growth case is given in Table 2 below.<br />
Table 2: Electricity demand in the high growth scenario (GWh)<br />
Sector/Year 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013<br />
Transport 3432 3569 3656 3752 3782 3807 3847 3886 3930 3987 4029<br />
Mining 31923 33204 34079 34987 35228 35326 35528 35678 35966 36398 36694<br />
Total Industry 91658 97999 101415 105855 108896 111698 115107 118308 121313 124531 127563<br />
Commerce 18360 19537 20450 21449 22058 22633 23317 23968 24660 25457 26161<br />
Agriculture 6310 6728 7055 7408 7621 7819 8052 8267 8493 8755 8985<br />
Residential 32884 34866 36325 37431 38882 40202 41596 42944 44296 45650 46982<br />
Total domestic<br />
ex own<br />
generation 184568 195903 202981 210881 216468 221484 227446 233052 238659 244779 250414<br />
47<br />
3.2 Availability of plant<br />
The plant availabilities of new plants for the NIRP2 Reference <strong>Plan</strong> are based on the World Energy Council<br />
(WEC) best quartile results for 2002. For existing plants the NIRP2 Reference <strong>Plan</strong> uses the current targets in<br />
Eskom adjusted independently for each individual station to give a weighted average for base-load capacity of<br />
88% EAF; (7% PCLF: 3% UCLF with a provision of 2% for OCLF to cater for risk).<br />
The above availability levels were considered too optimistic by the ARC. It was decided to use average results<br />
rather than best quartile taken from the WEC Report 2001 as being reflective of a lower level of plant<br />
availability. (Note: Later editions of WEC Reports do not accurately reflect global plant availability levels<br />
because fewer and fewer utilities are providing input to the WEC database as competition in the Electricity<br />
Supply Industry increases. Figures are now biased towards a few remaining large utility players still<br />
contributing). For existing plants this study uses lower Eskom targets adjusted independently for each<br />
individual station to give a weighted average for base-load capacity of 85% EAF; (7% PCLF: 6% UCLF with a<br />
provision of 2% for OCLF).<br />
A comparison of plant availability levels for this analysis as compared to the NIRP2 Reference <strong>Plan</strong> is given in<br />
Table 3 below for all new plant options.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Table 3: Availabilities of new plant.<br />
48<br />
Option Expected Low Option Expected Low<br />
New Coal with FGD<br />
New Gt Open Cycle (LNG)<br />
PORg 7.20% 7.20% PORg 7.08% 7.08%<br />
FORg 5.17% 7.97% FORg 7.31% 13.90%<br />
Availability 88.00% 85.40% Availability 86.13% 80.00%<br />
New Coal without FGD<br />
New Gt Open Cycle (Kerosene)<br />
PORg 7.20% 7.20% PORg 7.08% 7.08%<br />
FORg 5.17% 7.97% FORg 7.31% 13.90%<br />
Availability 88.00% 85.40% Availability 86.13% 80.00%<br />
New Pumped Storage<br />
Renewables (CSP)<br />
PORg 1.66% 1.66% PORg 3.85%<br />
FORg 1.26% 4.82% FORg 1.98%<br />
Availability 97.10% 93.60% Availability 94.25%<br />
New Fluidised Bed<br />
Renewables (Wind)<br />
PORg 10.20% 7.69% PORg 2.00% 2.00%<br />
FORg 4.57% 8.89% FORg 1.02% 8.16%<br />
Availability 85.70% 84.10% Availability 97.00% 90.00%<br />
CCGT Pipeline Excl Trans<br />
Public <strong>PBMR</strong> (1st MM) Excl Tran<br />
PORg 8.73% 8.73% PORg 4.04% 4.04%<br />
FORg 6.46% 9.61% FORg 4.13% 8.29%<br />
Availability 85.37% 82.50% Availability 92.00% 88.00%<br />
CCGT LNG Exc Trans<br />
Public <strong>PBMR</strong> (1st MM) Inc Tran<br />
PORg 8.73% 8.73% PORg 4.04% 4.04%<br />
FORg 6.46% 9.61% FORg 4.13% 8.29%<br />
Availability 85.37% 82.50% Availability 92.00% 88.00%<br />
CCGT LNG Inc Trans<br />
Public <strong>PBMR</strong> Series No Trans<br />
PORg 8.73% 8.73% PORg 4.04% 4.04%<br />
FORg 6.46% 9.61% FORg 2.04% 6.21%<br />
Availability 85.37% 82.50% Availability 94.00% 90.00%<br />
New Gt Open Cycle (Local Syngas) Nuclear<br />
PORg 7.08% 7.08% PORg 15.00%<br />
FORg 7.31% 13.90% FORg 7.65%<br />
Availability 86.13% 80.00% Availability 78.50%<br />
3.3 Sustainability of existing interruptible loads<br />
The current contracts entered between customers and Eskom concerning interruptible supply are severely<br />
constrained in terms of their usage requirements. Studies carried out in Eskom comparing these options with<br />
equivalent OCGT capacity showed that they should be de-rated to obtain equivalence. In anticipation of future<br />
Demand Market Participation or other Demand Response mechanisms becoming available, it was considered<br />
prudent by the ARC to consider the possibility that current interruptible supply contracts may be re-negotiated<br />
in the future. As such some plans should be developed on the basis of excluding them from the planning base<br />
in the risk analysis.<br />
3.4 Sustainability of existing capacity<br />
As stated previously, some risk events are aggregated into independent risk portfolios. The aggregated<br />
options in each portfolio are assigned the same probability of occurrence for purposes of this Report.<br />
The following capacity reductions are included as aggregated options in this analysis. The levels of capacity<br />
reductions are based on either ARC recommendations or expert opinion:
Risk & Sensitivity Analysis<br />
& Cahora Bassa capacity is reduced by 250MW (from 1281MW) in 2004 and by 500MW thereafter. This is a<br />
base-load capacity reduction;<br />
& Non-Eskom OCGT capacity is reduced by 180MW (from 270MW) and assumed unavailable over the<br />
planning horizon. This is a Peaking capacity reduction;<br />
& Non-Eskom coal-fired capacity is reduced by 600MW (from 1920MW) and assumed unavailable over the<br />
planning horizon. This is a base-load capacity reduction. In addition, this latter option targets Municipal<br />
capacity destined for decommissioning from 2011.<br />
4.Scenario Development<br />
It was agreed by the ARC to carry out the risk and uncertainty analysis to develop an appropriate net reserve<br />
margin using a <strong>Resource</strong>s <strong>Plan</strong>ning approach. The focus of this approach is to provide a best (robust and<br />
flexible) plan developed from an analysis of the risk portfolios and then compare the capacity of the selected<br />
plan with the expected demand to establish an appropriate net reserve margin.<br />
(Note: A plan that is 100% robust is one, which lies in the decision set for all futures and would lead to no regret<br />
whereas flexibility is the ability to modify a resource plan without significantly degrading system reliability and<br />
economics, in response to actual data that have deviated from the forecast data).<br />
There are four risk portfolios defined each consisting two alternatives. This results in sixteen scenarios<br />
incorporating the alternative risk events from each risk portfolio. Optimal plans are then developed for each of<br />
the sixteen scenarios where the basis for the optimisation is the least cost of electricity for the supply life cycle.<br />
This considers the least cost of each plan in terms of the cost of supply and the cost of non-supply (CUE) to the<br />
consumer. For this NIRP2 as explained in the NIRP2 Reference <strong>Plan</strong>, the CUE is assumed to be<br />
R20 666/MWh.<br />
Probabilities were assigned to each of the risk portfolios using a Delphi approach in consultation with the<br />
various experts in the field associated with developing the portfolios.<br />
49<br />
Table 4 below details the probabilities assigned to each of the risk portfolios.<br />
Table 4: Probabilities associated with primary assumptions.<br />
Uncertainties: Probability Probability<br />
Load Forecast Expected (Moderate) (ED) 0.6 High (HD) 0.4<br />
<strong>Plan</strong>t outage Expected (EF) 0.4 High (HF) 0.6<br />
Capacity availability Expected (EC) 0.3 Low (LC) 0.7<br />
DSM Interruptible Load Expected (EI) 0.4 Low (LI) 0.6<br />
Table 5 below details the sixteen scenarios incorporating the alternative risk events from each risk portfolio<br />
with the resultant probabilities assigned to each scenario.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Table 5: Scenarios and their probabilities.<br />
Futures <strong>Plan</strong> A-1 / Scenario 1 <strong>Plan</strong> A-2 / Scenario 2<br />
Load Forecast Expected (ED) High (HD)<br />
<strong>Plan</strong>t outage Expected (EF) High (HF)<br />
Capacity availability Expected (EC) Low (LC)<br />
DSM Interruptible Supply Expected (EI) Low (LI)<br />
Probability 0.0288 0.1008<br />
Futures <strong>Plan</strong> A-3 / Scenario 3 <strong>Plan</strong> A-4 / Scenario 4<br />
Load Forecast Expected (ED) High (HD)<br />
<strong>Plan</strong>t outage High (HF) Expected (EF)<br />
Capacity availability Low (LC) Expected (EC)<br />
DSM Interruptible Supply Low (LI) Expected (EI)<br />
Probability 0.1512 0.0192<br />
Futures <strong>Plan</strong> A-5 / Scenario 5 <strong>Plan</strong> A-6 / Scenario 6<br />
Load Forecast Expected (ED) High (HD)<br />
<strong>Plan</strong>t outage High (HF) High (HF)<br />
Capacity availability Expected (EC) Low (LC)<br />
DSM Interruptible Supply Low (LI) Expected (EI)<br />
Probability 0.0648 0.0672<br />
50<br />
Futures <strong>Plan</strong> A-7 / Scenario 7 <strong>Plan</strong> A-8 / Scenario 8<br />
Load Forecast Expected (ED) High (HD)<br />
<strong>Plan</strong>t outage Expected (EF) High (HF)<br />
Capacity availability Low (LC) Expected (EC)<br />
DSM Interruptible Supply Low (LI) Expected (EI)<br />
Probability 0.1008 0.0288<br />
Futures <strong>Plan</strong> A-9 / Scenario 9 <strong>Plan</strong> A-10 / Scenario 10<br />
Load Forecast Expected (ED) High (HD)<br />
<strong>Plan</strong>t outage Expected (EF) Expected (EF)<br />
Capacity availability Expected (EC) Expected (EC)<br />
DSM Interruptible Supply Low (LI) Low (LI)<br />
Probability 0.0432 0.0288<br />
Futures <strong>Plan</strong> A-11 / Scenario 11 <strong>Plan</strong> A-12 / Scenario 12<br />
Load Forecast Expected (ED) High (HD)<br />
<strong>Plan</strong>t outage High (HF) Expected (EF)<br />
Capacity availability Expected (EC) Low (LC)<br />
DSM Interruptible Supply Expected (EI) Expected (EI)<br />
Probability 0.0432 0.0448<br />
Futures <strong>Plan</strong> A-13 / Scenario 13 <strong>Plan</strong> A-14/ Scenario 14<br />
Load Forecast Expected (ED) High (HD)<br />
<strong>Plan</strong>t outage High (HF) Expected (EF)<br />
Capacity availability Low (LC) Low (LC)<br />
DSM Interruptible Supply Expected (EI) Low (LI)<br />
Probability 0.1008 0.0672<br />
Futures <strong>Plan</strong> A-15 / Scenario 15 <strong>Plan</strong> A-16/ Scenario 16<br />
Load Forecast Expected (ED) High (HD)<br />
<strong>Plan</strong>t outage Expected (EF) High (HF)<br />
Capacity availability Low (LC) Expected (EC)<br />
DSM Interruptible Supply Expected (EI) Low (LI)<br />
Probability 0.0672 0.0432
Risk & Sensitivity Analysis<br />
It is necessary to state that after consultation with the various experts in their fields, that some of the expected<br />
events (used as basis for developing the NIRP2 Reference <strong>Plan</strong>) were in fact less realistic than originally<br />
thought. This resulted in some cases, higher probabilities being assigned to the alternative case than the<br />
expected case.<br />
5.Ranking of <strong>Plan</strong>s/Candidate <strong>Plan</strong>s<br />
The assessment of the plans/scenarios includes the following steps:<br />
& Development of optimal resource plan for each of the 16 scenarios;<br />
& Testing each of the plans under the assumptions of the remaining scenarios;<br />
& Calculation of the total probability weighted cost (PWC) of each plan;<br />
& Ranking of the plans in terms of the attributes<br />
& Selection of the most robust plan<br />
The output of the trade-off analyses would be the most robust optimum plan/strategy for capacity development<br />
over the planning period.<br />
The selected attributes (measures of goodness) for evaluation of the plans are:<br />
& Total probability weighted cost<br />
& Reliability<br />
& Emissions;<br />
& Diversity of fuel sources.<br />
5.1 Methodology<br />
51<br />
The main criteria for measuring the performance of the plans is the total probability-weighted cost (PWC). The<br />
probability-weighted cost is calculated as the sum of the total cost of the plan for each of the 16 scenarios<br />
multiplied by the probability of occurrence of the corresponding scenario.<br />
The 16 plans are ranked in ascending order (minimum cost) in terms of total probability-weighted cost (PWC).<br />
The first three plans with the lowest probability-weighted total cost are then selected as candidates for the<br />
preferred plan.<br />
In order to test the sensitivity of the probability-weighted cost to the length of planning period, these analyses<br />
were conducted for planning horizon of 8, 12, 16 and 20 years.<br />
To test the sensitivity of the probability weighted cost to the probability assigned to each of the primary<br />
uncertainties, i.e. the analyses were conducted for equal probability of each of the primary uncertainties (50%<br />
probability of occurrence of each of the primary uncertainties), as well as for 60% probability of occurrence of<br />
the expected uncertainties.<br />
The second attribute considered is the reliability of the plans measured as the level of the reserve margin<br />
provided by the plan over the planning horizon. Higher reserve margin will provide higher system adequacy<br />
and reliability. The candidate plans are ranked in descending order according to the RM they provide.<br />
The evaluation of the plans in terms of the emissions is conducted by comparing the total emission level (CO2,<br />
SO2, NO2 and particulate emissions) of the three candidate plans over the planning horizon.<br />
The fourth attribute for comparison is the diversity of the plans. The diversity of the plans is measured as the<br />
ratio of non-coal and coal based generation resources.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
5.2 Total Probability-Weighted Cost<br />
The ranking of the plans is conducted in terms of the attribute total probability weighted cost. The first three<br />
plans are selected as candidates for the most robust plan/strategy for implementation.<br />
The ranking of the 16 plans and their associated expectation cost over the whole planning period (20 years), 16<br />
years, 12 years and 8 years is illustrated in Table 6 below. While under the assumed probabilities of the<br />
primary uncertainties <strong>Plan</strong> 14 enjoys the least cost or most robust position, <strong>Plan</strong> 8 and <strong>Plan</strong> 16 follow closely its<br />
performance. The ranking of these three plans remains unchanged within a range of planning period from 12 to<br />
20 years.<br />
The ranking of the plans for the first 8 years indicates that the <strong>Plan</strong> 14 and <strong>Plan</strong> 08 maintain their position as the<br />
best performers while <strong>Plan</strong> 3 emerges as the second most robust plan for the first 8 years of the resource plan<br />
study period.<br />
Table 6: PWC Ranking of the <strong>Plan</strong>s<br />
Ranking of Expectation over<br />
<strong>Plan</strong>s over 8 8 years, mR<br />
years<br />
Ranking of <strong>Plan</strong>s<br />
over 12 years<br />
Expectation over<br />
12 years, mR<br />
Ranking of<br />
<strong>Plan</strong>s over 16<br />
years<br />
Expectation<br />
over 16 years,<br />
mR<br />
Ranking of<br />
<strong>Plan</strong>s over<br />
20 years<br />
Expectation<br />
over 20 years,<br />
mR<br />
52<br />
Assumed probabilities<br />
<strong>Plan</strong>14 102 651 <strong>Plan</strong>14 145 335 <strong>Plan</strong>14 181 830 <strong>Plan</strong>14 212 601<br />
<strong>Plan</strong>03 102 790 <strong>Plan</strong>08 145 712 <strong>Plan</strong>08 182 547 <strong>Plan</strong>08 214 053<br />
<strong>Plan</strong>08 102 872 <strong>Plan</strong>16 146 098 <strong>Plan</strong>16 183 084 <strong>Plan</strong>16 214 546<br />
50% Probabilities of primary uncertainties (Each plan has an equal probabilty of 6.25%)<br />
<strong>Plan</strong>14 102 267 <strong>Plan</strong>14 144 854 <strong>Plan</strong>14 181 364 <strong>Plan</strong>14 212 175<br />
<strong>Plan</strong>03 102 361 <strong>Plan</strong>08 145 250 <strong>Plan</strong>08 182 154 <strong>Plan</strong>08 213 722<br />
<strong>Plan</strong>08 102 379 <strong>Plan</strong>16 146 046 <strong>Plan</strong>12 183 077 <strong>Plan</strong>12 213 968<br />
60% Probablities of expected primary uncertainties (<strong>Plan</strong> A1 has the highest probability of 12.96%)<br />
<strong>Plan</strong>10 100 341 <strong>Plan</strong>10 141 587 <strong>Plan</strong>12 177 074 <strong>Plan</strong>12 207 187<br />
<strong>Plan</strong>12 100 341 <strong>Plan</strong>12 141 633 <strong>Plan</strong>10 177 122 <strong>Plan</strong>10 207 203<br />
<strong>Plan</strong>05 100 456 <strong>Plan</strong>14 141 780 <strong>Plan</strong>14 177 241 <strong>Plan</strong>14 207 444<br />
The above results show that the ranking of <strong>Plan</strong> 14 is not sensitive to small changes in the assigned<br />
probabilities and the length of the planning period.<br />
The difference in the PWC of the first three plans is marginal and less than 1%.<br />
The actual variability of the plans PV cost under the modeled future conditions is illustrated in Figure 5 below.<br />
For a comparison the graph also includes plan A2 which is developed for the most pessimistic conditions<br />
(highest capacity requirements) and therefore carries the least variability of the costs under the remaining 15<br />
more favorable futures.<br />
The performance of the first three plans, <strong>Plan</strong> 14, 08 and 16 is further evaluated in terms of the attributes<br />
reliability, emissions and diversity.
Risk & Sensitivity Analysis<br />
310 000<br />
290 000<br />
<strong>Plan</strong> 2 NPV 20<br />
<strong>Plan</strong> 3 NPV 20<br />
<strong>Plan</strong> 8 NPV 20<br />
<strong>Plan</strong> 14 NPV 20<br />
<strong>Plan</strong> 16 NPV 20<br />
Total cost, mR<br />
270 000<br />
250 000<br />
230 000<br />
210 000<br />
190 000<br />
S01 S02 S03 S04 S05 S06 S07 S08 S09 S10 S11 S12 S13 S14 S15 S16<br />
Scenario<br />
Figure 5: Variability of total cost.<br />
5.3 Reliability Assessment<br />
The reliability assessment is conducted in terms of the reserve margin carried by the plans under the future<br />
scenario they were developed for and the reserve margin that the plans would carry had the expected<br />
conditions (business as usual) prevailed over the planning period. The reserve margin under own future and<br />
under the expected (A1) future are shown in Figure 6 and Figure 7, respectively.<br />
25.00%<br />
53<br />
RM, %<br />
20.00%<br />
15.00%<br />
A3<br />
A14<br />
A16<br />
A8<br />
10.00%<br />
5.00%<br />
0.00%<br />
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022<br />
Year<br />
Figure 6: Reserve Margin under own future.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
25.00%<br />
20.00%<br />
A3<br />
A14<br />
A16<br />
A8<br />
RM, %<br />
15.00%<br />
10.00%<br />
5.00%<br />
0.00%<br />
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022<br />
Year<br />
Figure 7: Reserve Margin under A1 future.<br />
<strong>Plan</strong> 14 carries a higher than 10% reserve margin (RM) under its own future from 2008 to 2022 and 12% % RM<br />
under expected future (A1). In comparison <strong>Plan</strong> 16 carries a better RM under A1 future but under its own future<br />
scenario its RM is relatively low.<br />
5.4 Emissions and Diversification Assessment<br />
54<br />
A summary of the comparison of the plans in terms of diversity of resources, emissions as well as costs and<br />
reliability parameters is provided in Table 7 overleaf.<br />
In terms of emissions the least-cost candidate plans have quite similar performance. This is a result of the large<br />
share of the coal-fired generation in all 16 plans. For the same reason the diversification of the plans is also low<br />
and varies between 9 and 12%. However, regardless of the close performance of the plans in terms of<br />
emissions, <strong>Plan</strong> 3 ranks marginally as the plan with the lowest emissions level, followed by the remaining three<br />
plans with almost equal pollution level.<br />
Higher diversification of resource is achieved in the alternative of the <strong>Plan</strong> 14, presented hereafter, which<br />
factors the Government renewable energy (RE) target of 10 000 GWh by 2012 in the capacity mix.
Risk & Sensitivity Analysis<br />
Table 7: Comparison of Candidate <strong>Plan</strong>s<br />
NIRP 2 STAGE 2 COMPARISON OF CANDIDATE PLANS<br />
<strong>Plan</strong> A14 A8 A16 A3<br />
Probability 0.0672 0.0288 0.0432 0.1512<br />
Demand High High High E<br />
FOR E High High high<br />
Capacity Avail Low E E Low<br />
DSM IL Low E Low Low<br />
RM(weighted average 2006-2022) 10.61% 6.85% 6.23% 8.90%<br />
RM(weighted average 2006-2022) under Ref<br />
case A1 14.53% 16.57% 17.70% 12.80%<br />
LOLP (average over 20 yrs) 0.00514 0.0054066 0.007379 0.00568<br />
USE (over 20yrs), GWh 919 940 1307 888<br />
Probability weighted PV cost over 20yrs, mR 212 601 214 053 214 546 216 969<br />
Probability weighted PV cost over 20yrs, % 100.00% 100.68% 100.91% 102.05%<br />
PV System Cost, mR 209 169 221 189 230 200 202 638<br />
PV of Capex, mR 61 009 69 261 70 534 58553<br />
PV of Energy Prod (20 yrs) GWh 2 455 643 2 545 521 2 545 268 2 455 613<br />
Constant cost, R/KWh 0.0852 0.0869 0.0904 0.0825<br />
Constant pobability weighted cost, R/KWh 0.0866 0.0841 0.0843 0.0884<br />
New capacity, MW<br />
Mothballed plants, MW 3559 3559 3559 3559<br />
First unit year 2005 2005 2005 2005<br />
OCGT(peak), MW 2880 2880 3360 1920<br />
First unit year 2 006 2 006 2 006 2006<br />
Pump Storage (peak), MW 3330 3330 3330 3330<br />
First unit year 2 012 2 012 2 012 2012<br />
CCGT (base load), MW - - - -<br />
First unit year - - - -<br />
PF(base load), MW 9630 10914 11556 10272<br />
First unit year 2016 2015 2015 2015<br />
FBC (base load), MW 2330 2796 2330 1398<br />
First unit year 2012 2010 2010 2010<br />
Total capacity MW 21 729 23 479 24 135 20 479<br />
PV of Capex, mR 61 009 69 261 70 534 58553<br />
Coal based, % 86.75% 87.73% 86.08% 90.62%<br />
Diversity (non-coal), % 13.25% 12.27% 13.92% 9.38%<br />
55<br />
CO2 Emissions (Mt) 5397 5340 5336 5180<br />
SO2 Emissions (Mt) 47 47 46 44<br />
NO2 Emissions (Mt) 20 20 20 19<br />
Particulate Emissions (Mt) 1 1 1 1<br />
Water Usage (Mcub m) 7232 7028 7034 6951<br />
Total emissions, Mt 5464 5407 5402 5243
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
6.Preferred <strong>Resource</strong> <strong>Plan</strong><br />
The overall ranking of the plans is conducted in terms of the attributes PWC, RM own, diversity and emissions<br />
with a weighting of 40, 40, 10 and 10% respectively. Sensitivity analyses are performed with weightings of<br />
30/30/20/20 and 50/30/10/10. The results of the ranking of the plans are illustrated in Figure 8 below.<br />
1.100<br />
1.000<br />
0.900<br />
Best plan =1<br />
A14<br />
A3<br />
A8<br />
A16<br />
0.800<br />
0.700<br />
0.600<br />
0.500<br />
0.400<br />
RM own Prob Weighted PV Emmissions Diversity Weight 40/40/10/10 Weight 30/30/20/20 Weight 50/30/10/10<br />
Figure 8: Ranking of <strong>Plan</strong>s<br />
56<br />
<strong>Plan</strong> 14 remains the most robust plan, followed by <strong>Plan</strong> 3, plan 8 and <strong>Plan</strong> 16. Therefore in terms of the<br />
attributes <strong>Plan</strong> 14 should be selected as the optimum most robust plan/strategy for implementation. It has to be<br />
highlighted that the four candidate plans are very similar regarding the capacity mix and timing. All plans,<br />
except <strong>Plan</strong> 3 are developed for high growth scenario which is the planning uncertainty with the highest impact<br />
on the future capacity requirements, timing and capacity mix.<br />
The preferred <strong>Plan</strong> 14 is developed under high growth demand forecast, expected plant outage rate, low<br />
import and municipal capacity availability and no interruptible loads.<br />
6.1 Preferred <strong>Plan</strong> 14<br />
The capacity mix and timing of <strong>Plan</strong> 14 are shown in Table 8. Details about <strong>Plan</strong> 14 attributes are illustrated in<br />
Table 5.2.<br />
Similarly to the remaining 15 plans, <strong>Plan</strong> 14 is also based on RTS of all mothballed plants by the year 2011.<br />
In terms of peaking plants, the plan requires construction of 2880 MW of OCGTs starting from the year 2006 to<br />
meet the medium term requirements for peaking capacity. The peaking requirements in the second half of the<br />
planning period are satisfied by the commissioning of 3330 MW of pump-storage plants starting from the year<br />
2012.<br />
The first FBC base-load capacity is required in 2012 while the first PF coal-fired unit must be commissioned in<br />
2016.<br />
The plan provides certain degree of flexibility regarding modification of the timing of the required capacity.<br />
Depending on deviations of the actual demand from the forecasted, the decisions for resource commissioning<br />
could be accelerated or delayed.
Risk & Sensitivity Analysis<br />
Table 8: Preferred <strong>Plan</strong> 14.<br />
Mothballed Coal-Fired FBC Gas Pumped Storage DSM<br />
YR Cam (PF) Gr'tvlei<br />
(PF)<br />
Kom (PF) PF (1) PF (2) PF (3) Green-field<br />
FBC<br />
OCGT PS (A) PS (B) PS (C) CEE IMEE<br />
IMLM REE<br />
RLM<br />
Reserve on<br />
moderate<br />
forecast<br />
Committed Committed Committed<br />
2003 Committed Committed Decide 152 24%<br />
2004 Decide Decide 152 21%<br />
2005 380 Decide 152 18%<br />
2006 380 720 152 17%<br />
2007 570 188 152 16%<br />
2008 190 377 101 Decide 480 152 16%<br />
2009 565 202 Decide 720 Decide 152 17%<br />
2010 303 720 152 17%<br />
2011 303 152 13%<br />
2012 932 333 13%<br />
2013 466 999 13%<br />
2014 932 999 15%<br />
2015 13%<br />
2016 1284 13%<br />
2017 1284 14%<br />
2018 1284 14%<br />
2019 999 14%<br />
2020 1284 15%<br />
2021 1284 642 14%<br />
2022 1284 1284 240 13%<br />
TOTAL 1520 1130 909 3852 3852 1926 2330 2880 1332 999 999 1370<br />
7.Sensitivity Analysis<br />
The ARC requested the following sensitivities be investigated:<br />
& The impact of the net discount rate on the optimum choice of technology;<br />
& The impact of Renewable Energy Technologies on the preferred (robust) plan;<br />
57<br />
These sensitivity studies were considered necessary to test the robustness of the conclusions and<br />
recommendations emanating from the NIRP2 Reference <strong>Plan</strong>, and their impact on important energy policy<br />
issues.<br />
Before discussing the sensitivity analysis it is necessary to highlight data changes made to the demand- and<br />
supply-side data base of the NIRP2 Reference <strong>Plan</strong> in this study.<br />
A summary of the complete data base of new plant capital, O&M, Fuel costs and performance parameters is<br />
given in Appendix C of this Report<br />
7.1 Comparison of Data changes to NIRP2 Reference <strong>Plan</strong><br />
No data changes were made to any existing plant options or new demand-side initiatives from the NIRP2<br />
Reference <strong>Plan</strong>. Marginal changes were made to some specific new supply-side options. To highlight these<br />
changes more effectively, the candidate plants are separated into Peaking and Base Load options.<br />
These options are compared in terms of their levelised costs at their maximum production levels and<br />
separated into O&M, Fuel and Capex components. It is important to note that the CCGT option in the Cape<br />
using natural gas was excluded from the analysis in this Report. However this was replaced with a CCGT plant<br />
(located in Namibia) using natural gas from the Kudu field.<br />
The results in Figure 9, Figure 10 and Figure 11 below, show that the most significant changes were made to<br />
the cost of coal. There is an increase in coal costs in the case of the PF plants and an increase in O&M cost for<br />
new FBC options to account for an increased requirement for sorbent.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Comparison of Change in Cost at 10% NDR between the Reference NIRP2 <strong>Plan</strong> and the<br />
Risk & Sensitivity <strong>Plan</strong><br />
400.00<br />
Reference <strong>Plan</strong> <strong>Plan</strong>t Capex<br />
Risk & Sensitivity <strong>Plan</strong>t Capex<br />
360.00<br />
320.00<br />
CAPEX R /MWh<br />
280.00<br />
240.00<br />
200.00<br />
160.00<br />
120.00<br />
80.00<br />
40.00<br />
0.00<br />
CF with FGD<br />
Greenfield FBC<br />
with FGD<br />
CCGT Incl Trans<br />
(LNG)<br />
CCGT Kudu<br />
(Offshore nat gas)<br />
CCGT Incl Trans<br />
(pipe)<br />
Mepanda Uncua<br />
<strong>PBMR</strong> (1st MM<br />
Incl trans)<br />
PWR (Incl trans<br />
benefits)<br />
Figure 9: Capex Costs for Base Options<br />
58<br />
Comparison of Change in Cost at 10% NDR between the Reference NIRP2 <strong>Plan</strong> and the<br />
Risk & Sensitivity <strong>Plan</strong><br />
Reference O & M Cost<br />
60.00<br />
Risk & Sensitivity O & M Cost<br />
CAPEX R /MWh<br />
40.00<br />
20.00<br />
0.00<br />
CF with FGD<br />
Greenfield FBC<br />
with FGD<br />
CCGT Incl Trans<br />
(LNG)<br />
CCGT Kudu<br />
(Offshore nat gas)<br />
CCGT Incl Trans<br />
(pipe)<br />
Mepanda Uncua<br />
<strong>PBMR</strong> (1st MM<br />
Incl trans)<br />
PWR (Incl trans<br />
benefits)<br />
Figure 10: O&M Costs for NIRP 2 Reference <strong>Plan</strong> and NIRP 2 Risk & Sensitivity <strong>Plan</strong>
Risk & Sensitivity Analysis<br />
Comparison of Change in Cost at 10% NDR between the Reference NIRP2 <strong>Plan</strong> and the<br />
Risk & Sensitivity <strong>Plan</strong><br />
Reference Fuel Working Cost<br />
Risk & Sensitivity Fuel Working Cost<br />
200.00<br />
CAPEX R /MWh<br />
150.00<br />
100.00<br />
50.00<br />
0.00<br />
CF with FGD<br />
Greenfield FBC<br />
with FGD<br />
CCGT Incl Trans<br />
(LNG)<br />
CCGT Kudu<br />
(Offshore nat gas)<br />
CCGT Incl Trans<br />
(pipe)<br />
Mepanda Uncua<br />
<strong>PBMR</strong> (1st MM<br />
Incl trans)<br />
PWR (Incl trans<br />
benefits)<br />
Figure 11: Fuel Costs for NIRP 2 Reference <strong>Plan</strong> and NIRP 2 Risk & Sensitivity <strong>Plan</strong><br />
7.2 The impact of net discount rate on optimum choice of technology<br />
59<br />
The timing of building new plant options will not be impacted to any great extent by small changes to the net<br />
discount rate. However changes to the net discount rate will impact on which base-load and peaking<br />
technologies are selected in the plant mix.<br />
Due to time constraints required to prepare sets of plans for different net discount rates, it was agreed by the<br />
ARC to carry out this analysis, external to the computer modelling process, by studying the impact of different<br />
net discount rates on the life-cycle levelised costs of building and operating the specific plant options.<br />
The analysis is carried out on both the data as detailed in the NIRP2 Reference <strong>Plan</strong> database as well as for the<br />
updated costs as applied in the database for this study. Where applicable, differences between the two sets of<br />
data are highlighted.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
Table 9 below shows the impact of changes in the net discount rate on the life-cycle levelised costs of all the<br />
options available to the NIRP2 Reference <strong>Plan</strong> at their maximum operating levels.<br />
Table 9: Levelised costs of candidates for selection in the NIRP2 Reference <strong>Plan</strong><br />
NIRP 2 Reference <strong>Plan</strong> Options Load Factor<br />
Net Discount Rate<br />
4.0% 6.0% 8.0% 10.0% 12.0% 14.0% 16.0%<br />
PF with FGD 88% 137.4 160.1 185.6 214.0 244.7 277.7 312.7<br />
PF without FGD 88% 127.5 148.3 171.7 197.6 225.8 256.0 288.1<br />
Greenfield FBC without FGD 86% 131.7 153.0 176.9 202.9 230.8 260.5 291.5<br />
Greenfield FBC with FGD 86% 134.2 155.3 179.0 205.0 232.9 262.5 293.5<br />
CCGT Incl Trans (LNG) 85% 310.7 318.7 327.6 337.1 347.2 357.8 368.7<br />
CCGT Excl Trans (LNG) 85% 328.1 337.4 347.6 358.6 370.3 382.5 395.0<br />
Single cycle GT (kerosine) 13% 1158.3 1199.8 1244.3 1291.3 1340.0 1389.8 1440.2<br />
Single cycle GT (LNG) 13% 706.9 749.5 795.1 843.0 892.5 943.0 994.2<br />
Single cycle GT (local syngas) 13% 663.3 706.3 752.3 800.6 850.5 901.4 952.9<br />
Single cycle GT (LPG) 13% 1005.8 1047.7 1092.6 1139.9 1188.8 1238.9 1289.5<br />
CCGT Incl Trans (pipe) 85% 219.5 227.7 236.7 246.4 256.5 267.2 278.1<br />
CCGT Excl Trans (pipe) 85% 234.8 244.3 254.7 265.8 277.5 289.8 302.4<br />
PS (based on Braamhoek public data) 23% 185.2 225.3 275.2 335.4 406.6 489.5 585.4<br />
PS (generic) 20% 269.1 348.9 448.2 568.1 710.0 875.5 1066.8<br />
Mepanda Uncua 58% 242.3 303.9 375.4 456.5 547.4 647.8 758.0<br />
Wind 33% 256.0 292.6 331.9 373.8 417.9 463.9 511.4<br />
Concentrating Solar Power 70% 336.6 409.2 486.3 566.0 646.9 728.0 808.3<br />
<strong>PBMR</strong> (1st MM incl. trans) 86% 187.7 220.6 258.3 299.9 344.9 392.8 443.4<br />
<strong>PBMR</strong> (1st MM excl. trans) 86% 206.6 244.0 286.7 334.0 385.0 439.4 496.7<br />
<strong>PBMR</strong> (Series MM excl. trans) 88% 154.7 174.7 197.7 223.1 250.5 279.7 310.4<br />
PWR (inc trans benefits) 79% 236.9 268.4 303.5 341.2 380.8 421.9 464.1<br />
PWR (exc trans benefits) 79% 248.6 280.4 315.7 353.8 393.8 435.3 477.9<br />
60<br />
Table 10 below shows the impact of changes in the net discount rate on the life-cycle levelised costs of all the<br />
options available in this study also at their maximum operating levels.<br />
Table 10: Levelised costs of candidates for selection for the NIRP2 Risk and Sensitivity Analysis<br />
NIRP 2 Risk and Sensitivity <strong>Plan</strong> Options Load Factor<br />
Net Discount Rate<br />
4.0% 6.0% 8.0% 10.0% 12.0% 14.0% 16.0%<br />
PF with FGD 88% 145.6 167.9 193.2 221.1 251.5 284.1 318.7<br />
PF without FGD 88% 136.0 156.4 179.6 205.1 233.0 262.8 294.5<br />
Greenfield FBC without FGD 86% 134.8 156.1 179.9 206.0 233.9 263.6 294.7<br />
Greenfield FBC with FGD 86% 150.2 171.8 195.9 222.1 250.2 279.9 311.1<br />
CCGT Incl Trans (LNG) 85% 308.0 315.9 324.6 334.0 343.9 354.3 365.1<br />
CCGT Excl Trans (LNG) 85% 320.4 329.5 339.5 350.3 361.7 373.6 385.9<br />
Single cycle GT (kerosine) 13% 1158.3 1199.8 1244.3 1291.3 1340.0 1389.8 1440.2<br />
Single cycle GT (LNG) 13% 706.9 749.5 795.1 843.0 892.5 943.0 994.2<br />
Single cycle GT (local syngas) 13% 663.3 706.3 752.3 800.6 850.5 901.4 952.9<br />
Single cycle GT (LPG) 13% 1005.8 1047.7 1092.6 1139.9 1188.8 1238.9 1289.5<br />
CCGT Kudu (Offshore nat gas) 85% 228.8 238.4 249.0 260.4 272.5 285.1 298.2<br />
PS (based on Braamhoek public data) 23% 193.7 233.8 283.7 343.8 415.0 498.0 593.8<br />
PS (generic) 20% 277.6 357.4 456.7 576.6 718.5 884.0 1075.2<br />
Mepanda Uncua 58% 216.0 280.6 355.8 440.8 535.1 638.5 751.1<br />
Wind 33% 251.1 281.9 314.3 347.7 381.9 416.5 451.3<br />
Concentrating Solar Power 70% 492.6 565.2 642.3 722.1 803.1 884.2 964.5<br />
<strong>PBMR</strong> (1st MM incl. trans) 92% 168.6 199.3 233.7 271.0 310.4 351.6 394.2<br />
<strong>PBMR</strong> (1st MM excl. trans) 92% 183.8 218.7 257.7 299.9 344.7 391.4 439.7<br />
<strong>PBMR</strong> (Series MM excl. trans) 94% 124.3 143.0 163.9 186.7 210.8 235.9 261.8<br />
PWR (inc trans benefits) 79% 239.3 270.8 305.8 343.6 383.2 424.3 466.4<br />
PWR (exc trans benefits) 79% 255.4 287.1 322.5 360.6 400.6 442.1 484.6<br />
Due to the levelised cost being sensitive to the load factor applied, the following analyses focus on the<br />
candidate base-load technologies taken at their maximum operating levels.
Risk & Sensitivity Analysis<br />
Selected plots for the various options based on type can be revealing. The base-load options with transmission<br />
credits, referenced against a coal-fired plant are illustrated in Figure 12 and Figure 13 below for both the NIRP2<br />
Reference <strong>Plan</strong> and this study. Options with a high capital component become less attractive with the increase<br />
in net discount rate. The reverse is true at lower discount rates.<br />
Life cycle levelised cost (R/MWh) to build and operate new plant - NIRP2 Reference plan<br />
Cost of Supply (R/MWh)<br />
500.0<br />
450.0<br />
400.0<br />
350.0<br />
300.0<br />
250.0<br />
200.0<br />
150.0<br />
PWR (inc trans benefits)<br />
CCGT Incl Trans (LNG)<br />
<strong>PBMR</strong> (1st MM incl. trans)<br />
CCGT Incl Trans (pipe)<br />
PF with FGD<br />
Greenfield FBC with FGD<br />
100.0<br />
50.0<br />
0.0<br />
4.0% 6.0% 8.0% 10.0% 12.0% 14.0% 16.0%<br />
Real Discount Rate (%)<br />
Figure 12: Levelised costs of base-load plants vs Net Discount Rate for the NIRP 2 Reference <strong>Plan</strong><br />
61<br />
Sensitivity of Levelised Lifecycle costs of <strong>Plan</strong>t to Net Discount Rate - NIRP2 Risk & Sensitivity<br />
Analysis<br />
Cost of Supply (R/MWh)<br />
500.0<br />
450.0<br />
400.0<br />
350.0<br />
300.0<br />
250.0<br />
200.0<br />
150.0<br />
PWR (inc trans benefits)<br />
CCGT Incl Trans (LNG)<br />
<strong>PBMR</strong> (1st MM incl. trans)<br />
CCGT Kudu (Offshore nat gas)<br />
PF with FGD<br />
Greenfield FBC with FGD<br />
100.0<br />
50.0<br />
0.0<br />
4.0% 6.0% 8.0% 10.0% 12.0% 14.0% 16.0%<br />
Real Discount Rate (%)<br />
Figure 13: Levelised costs of base-load plants vs Net Discount Rate for the NIRP 2 Risk &<br />
Sensitivity Analysis
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
7.3 Renewable Energy Technologies<br />
The levelised costs of renewable technologies (wind and concentrating solar power) are relatively high when<br />
compared to other equivalent supply options operating at similar levels of production. Because of this high cost<br />
in building renewable energy technologies, the computed economic least cost optimisation process excludes<br />
these options from the planning base.<br />
However, it is difficult to assess the externality benefits of these options in a purely economic comparison and it<br />
is stated Government policy to introduce some amount of renewable technologies in the Electricity Supply<br />
planning base.<br />
For purposes of this study, and to try and meet the aspirations of Government policy (10000GWh cumulative<br />
energy supplied by renewable energy sources (RES) wind, solar, biomass, small-scale hydro by 2013), two of<br />
the technologies; wind and concentrating solar power (CSP), are considered in this analysis only due to the<br />
lack of reliable data for other RES. It has to be underlined that the selected RES mix is not the least cost mix. A<br />
number of lower cost RES options have been identified by the White Paper on Renewable Energy (WPRE)<br />
and currently under investigation for implementation.<br />
The lead-time required to engineer, design and build these options is stated as 2 years for wind, and 3 years for<br />
CSP. This excludes EIA's, licensing, financing and other issues. For the purpose of this study and to be able to<br />
meet Government aspirations, wind turbines (20MW total) are brought into commercial service in 2007,<br />
expected to achieve a maximum load factor of at least 30% annually. CSP (300MW total), is anticipated to<br />
operate at a load factor of at least 70% (with battery assistance) are introduced from 2008.<br />
62<br />
The additional cost of imposing renewable technologies on the system and the cumulative energy contribution<br />
can be seen in Table 11 below.<br />
Table 11: Additional Cost of Renewable Technologies<br />
Capex (Rm)<br />
O & M Costs<br />
Total<br />
PV Cost (Rm)<br />
Total Energy SO<br />
(Rm)<br />
cost of<br />
of<br />
(GWh)<br />
Wind &<br />
Renewables<br />
Solar<br />
Year Wind Solar Wind Solar (Rm) Total Cum. Annual Cum.<br />
2003<br />
2004<br />
2005<br />
2006<br />
2007 155 4 159 109 109 57 57<br />
2008 10377 4 337 10717 6655 6763 1935 1992<br />
2009 4 337 341 192 6955 1935 3927<br />
2010 4 337 341 175 7130 1935 5862<br />
2011 4 337 341 159 7289 1935 7797<br />
2012 4 337 341 144 7434 1935 9732<br />
2013 4 337 341 131 7565 1935 11667<br />
2014 4 337 341 119 7684 1935 13602<br />
2015 4 337 341 109 7793 1935 15537<br />
2016 4 337 341 99 7892 1935 17472<br />
2017 4 337 341 90 7981 1935 19407<br />
2018 4 337 341 82 8063 1935 21342<br />
2019 4 337 341 74 8137 1935 23277<br />
2020 4 337 341 67 8204 1935 25212<br />
2021 4 337 341 61 8266 1935 27147<br />
2022 4 337 341 56 8321 1935 29082<br />
These results show the high cost of the solar contribution to the total additional cost of these two renewable<br />
technologies. The overall increase in cost to the system from implementing these options is estimated by<br />
carrying out a detailed computational analysis on the preferred plan 14.
Risk & Sensitivity Analysis<br />
The power supply profiles of these options will not always be consistent with the system demand profile. These<br />
options are therefore modelled as non-dispatchable technologies. A power demand profile for the wind option<br />
was supplied by ERC in consultation and assistance from the Darling Wind Farm IPP in the Western Cape, to<br />
yield a load factor of 33%.<br />
The profile for the CSP was assumed to be similar to that of the commercial and industrial energy efficiency<br />
programmes yielding a load factor of 71%. These profiles were used to simulate the required load factor<br />
expectations of these renewable options.<br />
The results of the computational analysis show an increase in PV cost of R4773 Million cumulative over the<br />
planning horizon compared to the preferred <strong>Plan</strong> 14 without renewables, as illustrated in Figure 14 below.<br />
Mothballed Coal-Fired FBC Gas Pumped Storage Renewables DSM<br />
YR Cam (PF) Gr'tvlei<br />
(PF)<br />
Kom (PF) PF (1) PF (2) PF (3) Green-field<br />
FBC<br />
OCGT PS (A) PS (B) PS (C) Conc.<br />
Solar<br />
Panels<br />
(CSP)<br />
Wind<br />
Turbines<br />
CEE IMEE<br />
IMLM REE<br />
RLM<br />
Committed Committed Committed<br />
2003 Committed Committed Decide 152<br />
2004 Decide Decide Decide Decide 152<br />
2005 380 Decide 152<br />
2006 380 720 152<br />
2007 570 188 20 152<br />
2008 190 377 101 Decide 240 300 152<br />
2009 565 202 720 152<br />
2010 303 Decide 720 152<br />
2011 303 240 Decide 152<br />
2012 932 333<br />
2013 999<br />
2014 932 999<br />
2015 466<br />
2016 1284<br />
2017 1284<br />
2018 1284<br />
2019<br />
2020 1284<br />
2021 1284 466 999<br />
2022 1284 1284<br />
TOTAL 1520 1130 909 3852 3852 1284 2796 2640 1332 999 999 300 20 1370<br />
63<br />
Figure 14: Preferred <strong>Plan</strong> 14 with Renewables<br />
The renewable options will reduce environmental emissions and water consumption of the preferred <strong>Plan</strong>14.<br />
The extent to which the renewables reduce the environmental emissions is illustrated in Figure 15 below.<br />
CO 2 MTons<br />
30<br />
25<br />
20<br />
Cum CO2 Reduced Emissions<br />
Cum SO2 Reduced Emissions<br />
Cum Reduced NO2 Emissions<br />
Cum Reduced Part Emissions<br />
MTons { SO 2 , Particulates<br />
& NO 2 Emmisions}<br />
0.3<br />
0.25<br />
0.2<br />
15<br />
0.15<br />
10<br />
0.1<br />
5<br />
0.05<br />
0<br />
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022<br />
Years<br />
Figure 15: Reduction in environment emissions in preferred <strong>Plan</strong> 14 with renewables.<br />
0
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2<br />
The cumulative total emission reduction of CO2 over the planning horizon is 28.2 Million Tons whereas the<br />
cumulative constant rand increase in the cost of the plan is R13547 Million. This represents a cost of R481/Ton<br />
of CO2 saved at 1 January 2003 prices.<br />
8.Conclusions<br />
The main conclusions of these studies in comparison with the NIRP2 reference are summarised as follows:<br />
64<br />
1) The preferred plan has been developed on the basis of an evaluation of risk profiles and the reserve<br />
margin is an outcome of the optimisation process.<br />
2) The reserve margin of the preferred plan is higher than the 10% reserve margin used as a deterministic<br />
reliability criteria in the reference plan;<br />
3) The studies show that immediate decisions are required for peaking and base load plants from 2006 and<br />
2012 respectively;<br />
4) The base load plants competing for commercial operation from 2012 competing, include; Pulverised Fuel<br />
Coal-fired (PF); Fluidised Bed Combustion (FBC); Combined Cycle Gas Turbine (CCGT)<br />
5) In order to meet Government RES targets by 2013 immediate decisions are also required for renewable<br />
energy options;<br />
6) Options for diversification are still insufficient to meet all of the forecast demand for electricity over the next<br />
20-year planning horizon. Coal-fired options are still predominating the capacity during the 20-year<br />
planning horizon. For environmental benefit it is imperative to continue with efforts to reduce the costs of<br />
implementing clean coal technologies and improve the efficiency of coal-fired plants;<br />
7) At the current assumed cost of capital (10% net discount rate before tax) and after returning the Eskom<br />
mothballed plant to service, fluidised bed combustion technologies are South Africa's most economic<br />
option, followed by investment in coal-fired plant. This in turn is followed by importing gas / LNG for CCGT<br />
plant in the Cape;<br />
8) It will be difficult to justify diversification on an economic basis, unless penalties for not doing so are<br />
included in future analyses. As the cost for diversification is becoming increasingly more expensive these<br />
penalties (or opportunities for emissions trading) will need to be substantial to offset the economic benefits<br />
of remaining with coal;<br />
9) The NIRP2 Stage 2 plans are based on the accepted RTS program of the mothballed plants;<br />
10) The preferred plan indicates that 2880 MW OCGT peaking plants are required in the planning horizon in<br />
service from 2006;<br />
11) There are supply options that have not been considered such as co-generation in industry, converting<br />
OCGT to CCGT, adding units onto existing power stations and new imports resulting from the<br />
development of Electricity Supply in the Southern African region;<br />
12) The RES scenario is not fully reflective of the least cost RES mix currently investigated for implementation<br />
of the WPRE. This will be included in the next round of the NIRP update.<br />
13) Should interruptible supply and / or OCGT capacity not be implemented this will significantly advance new<br />
base-load capacity;<br />
9.Appendices<br />
Appendix A: Summary of comments on reference case report<br />
Appendix B: Detailed <strong>Plan</strong>s<br />
Appendix C: Data Base
ARC and Public Comments on NIRP2 Reference Case<br />
Appendix A<br />
ARC AND PUBLIC COMMENTS ON THE NIRP2 REFERENCE CASE<br />
I. ESKOM SYSTEM OPERATION COMMENTS 66<br />
II. ESKOM KSACS COMMENT 67<br />
III. EIUG COMMENT ON NIRP 2003/4 REFERENCE CASE VERSION 18 DECEMBER 2003 70<br />
IV. ESKOM GENERATION COMMENTS ON NIRP 2003/4 REFERENCE CASE<br />
VERSION 18 DECEMBER 2003 72<br />
V. COMMENTS FROM DARLING IPP 74<br />
VI. COMMENTS FROM KELVIN IPP 75<br />
65
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix A<br />
I<br />
I. ESKOM SYSTEM OPERATION COMMENTS<br />
Provided by Mr. Michael Barry<br />
1. The method to use pre-defined reserve margins and then derive the generation expansion plan is not<br />
ideal. As mentioned in the ARC meetings, I believe a set of data assumptions should be defined and used<br />
in the modeling. The reserve margin is then an outcome of the modeling process. Using this approach,<br />
one can relate each generation expansion plan to a set of assumptions, for example with x% reduction in<br />
generation performance, the expansion plan is advanced by y years. This set of assumptions is changed<br />
for the various sensitivity studies/scenarios.<br />
2. The NIRP Reference <strong>Plan</strong> is for the forecast moderate load growth. (The documentation makes mention of<br />
robust plans, no regret and flexibility, but from my understanding these are not specifically considered in<br />
deriving the reference plan). The Reference <strong>Plan</strong> then gives a conservative picture (building too late)<br />
when one considers the load growth uncertainty and the cost of supplied vs unsupplied electricty. The<br />
Reference <strong>Plan</strong> should, as part of the set of assumptions, include an additional plant margin for load<br />
growth uncertainty.<br />
3. The NIRP Reference <strong>Plan</strong> does not make provision for the inherent inertia in changing the "direction" of a<br />
"ship" the size of the electricity industry in South Africa. The country is used to many years of no significant<br />
generation capacity expansion. The Reference <strong>Plan</strong> should, as part of the set of assumptions, include an<br />
additional plant margin for this inertia.<br />
66<br />
4. The Conclusions contain a number of "immediately implement" statements when referring to specific<br />
capacity additions. Is the NIRP saying a period of capacity shortages is forthcoming (and even more so<br />
considering the comments above)? If this is the case, should the NIRP not make some clear statement<br />
about the desirability of any capacity expansion or demand management in the next few years.<br />
5. From a strategic perspective, I believe a NIRP resulting in a reserve margin of anything less than 12% will<br />
harm the economy of South Africa. Potential international investors in the industrial arena might think<br />
"electricity interruptions" when seeing future reserve margins of less than 12%. Should the strategy not<br />
rather be to establish the capacity thereby stimulating highe growth?<br />
6. The reserve margin is calculated after the peak demand is reduced by the interruptible load. This implies a<br />
NIRP planning to interrupt customers. Is this the correct message?
ARC and Public Comments on NIRP2 Reference Case<br />
II<br />
II.ESKOM KSACS COMMENT<br />
Provided by Dr. Jean Pabot<br />
With respect to SAPP, I did not find this word in your report, though you mention briefly an option for imported<br />
hydro (Table 6). This option is not even discussed in the text (e.g. in Section 5). I assume you included the<br />
transmission costs from the foreign plant to the Eskom network into your capital cost. However this option<br />
appears not to have been considered in your simulations? If true, why?<br />
I accept that there are no good recent reliable data for SAPP hydro plants, except maybe for Mepanda Uncua,<br />
which may be the option mentioned inTable 6. If this is the case, it should be stated.<br />
You might consider a scenario where both Mepanda Uncua and Inga 3 are built, e.g. in 2014, irrespective of<br />
their costs, and study the impact thereof on your NIERP.<br />
There is some confusing wording and apparently an inconsistency about imports-exports in Section 3.6 and<br />
Section 5.1 (last 3 lines). Were exports included in the load forecast or not?<br />
It would be useful to include a table showing the MW exports included in the load forecast. It might already be in<br />
the appendices, but I did not see it.<br />
With respect to the reserve margins used in the SAPP studies, these are:<br />
We use:<br />
& 7,6 % for hydro units,<br />
& 10,6 % for thermal units,<br />
67<br />
There is a problem, even in Eskom, to justify a 10 % capacity reserve criterion to auditors, when many<br />
utilities have reserve criteria ranging from 15 % to 25 %.<br />
The minimum (or optimal) reserve margin is utility dependent. It depends on:<br />
& The risks which the utiity wants to mitigate by adding reserve capacity, e.g risks associated with uncertainties<br />
on plant availability, load forecast, fuel availability, etc.<br />
& The characteristics of the existing and future plants, e.g. unit size, plant availability, etc.<br />
& The costs involved, e.g. plant cost, cost of un-served energy, etc.<br />
Eskom is a SAPP member. A few years ago, the SAPP reduced its minimum installed capacity reserve<br />
requirements (not the operating reserve requirements) to about 10 %, based on the results of a simple<br />
optimization study. The methodology and assumptions are auditable, though auditors might disagree with all.<br />
With hindsight, I now believe that one of the drought related assumptions is not valid, but this would have little<br />
impact on thermal plant based utilities.<br />
Additional minor comments on your report:<br />
1. Interruptible supplies:<br />
& In section 5.2, the report states: there is a total 1510 MW interruptible supply capacity included in the plan.<br />
Does this mean that you have 1510 MW of interruptible load/supplies assumed to be equivalent to 1510 MW
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix A<br />
of supply capacity? or is this 2500 MW or 3000 MW of interruptible load/supplies assumed to be equivalent<br />
to 1510 MW of supply capacity? Table 1 in Appendix 1 mentions it is derated capacity. This should be<br />
explained in the text.<br />
& Table 2 in Appendix 2 shows that the existing interruptible load (IL) decreases from 1510 MW to 500 MW in<br />
2012 and 384 MW and that it is not replaced by new IL. This does not make much sense.<br />
& IL is a very cost effective way to provide reserve to a system, and if Eskom's IL contracts come to an end,<br />
Eskom would surely seek new IL contracts.<br />
2. LRMC<br />
Table 12 in Appendix 12 shows that the LRMC does not vary significantly with the reserve margin (i.e. with the<br />
alternative plan) beyond 2015.<br />
With the methodology presented in Section 7, the LRMC should depend on<br />
the amount of plant to be built to meet a 500 MW load increase, which depends on the reserve margin criterion.<br />
3. Wind generator<br />
Section 9, in Appendix 3, should indicate the fuel/wind availability: when is it available during the day and with<br />
what probability?<br />
What capacity credit do you give the wind generator for reserve margin calculations?<br />
68<br />
4. Imported hydro<br />
& The capital cost of imported hydro differs in Table 6 of the main report ( Rm 17044) and in Table 3 of Appendix<br />
1 (Rm 19366).<br />
& The life of the imported hydro plant is given as 30 years, much lower that the life of a pumped storage plant or<br />
a <strong>PBMR</strong> (40 years). This is not realistic. A dam can last 100 years, and a hydro generating unit 40 or 50 years.<br />
NIRP2 Reference Case Handling of Risks<br />
I noticed in your executive summary (Section 6) and in the main report (section 2.3) the way you handle risk:<br />
"The reference plan uses a constraint of 10% on the reserve margin. In addition the un-served energy is<br />
constrained to a maximum of 0.11% of total energy demand in any specific year.<br />
In order to address some risks to some extent and to determine reserve margin exposure to lead time, four<br />
alternative plans to the NIRP Reference plan were developed for increasing levels of constraint on the reserve<br />
margin<br />
As explained previously this Report does not address risk rigorously in this round but rather addresses it<br />
through imposing a minimum reserve margin on the plan of 10%."<br />
& Where did you get the 10% on the reserve margin criterion from and the 0.11 % UE criterion from?<br />
& Why do you need these criteria for planning? Theoretically, your optimization method should yield a plan,<br />
from which you could derive the planned reserve margin and UE.
ARC and Public Comments on NIRP2 Reference Case<br />
& Why do you need to have plans for various reserve margins, from 10 % to 17 %. This is not a random choice.<br />
Which on is the best and why?<br />
& The above points should be explained in the report.<br />
& SAPP uses a reserve margin criterion because this was the only way acceptable to all members to agree on<br />
what capacity each member should provide. However the reserve margin criterion itself was selected with a<br />
specific auditable process (see my previous message and attached paper) and was not arbitrary (though<br />
debatable).<br />
I just have a few additional theoretical comments. You could find the same comments and additional /better<br />
ones in the numerous articles available in the literature on this topic.<br />
& In a generation planning problem, the planner has to handle risk (associated with uncertainties), i.e. he has<br />
to have a base/reference plan (e.g. over 10 years) and to define risk handling strategies to deviate from the<br />
plan if uncertainties are realized in a way or another (e.g. if the load forecast increases or decreases, if<br />
nuclear energy is phased out or encouraged, or if gas becomes very cheap or expensive, or if wind energy<br />
becomes a must have option).<br />
& Long ago (20 or 30 or 50 years ago), the planners identified their planning risks, determined a reserve margin<br />
criterion (e.g peak load + 20 %), planned accordingly, and would revise their plans regularly as uncertainties<br />
become realized, and new ones develop.<br />
The problem is that a reserve margin criterion becomes invalid if the load shape changes, or the<br />
reliability changes, or uncertainties change.<br />
& Later (25-35 years ago) the planners moved to a reliability criterion (e.g. 1 days in 10 years loss of load, or<br />
LOLE = 20 hours per year, or UE = .1 % or any similar one).<br />
69<br />
& This is better than a reserve margin criterion, but how do you select the reliability criterion?<br />
& Later (20-30 years ago) the planners moved to a minimum cost to society approach (using the cost of unserved<br />
energy)<br />
& Eskom generation planners moved from a reserve margin criterion (long ago, before my time) to a reliability<br />
criterion (10 % LOLP at the peak of the year) around 1979, but the reliability criterion was derived from the<br />
minimum cost to society approach (using a 0.5 R/kWh cost of un-served energy).<br />
& Later around 1995 Eskom generation planners moved to a pure minimum cost to society approach, mainly<br />
because of the availability of more modern computing tools.<br />
& I am not involved in Eskom ISEP, and I have not seen the plans ISEP9 and/or 9A. I understand that the<br />
Eskom ISEP planners are now also using a reserve margin criterion in addition to the minimum cost to<br />
society approach.<br />
& I saw various Eskom documents where various people compared the reserve margin in Eskom with the<br />
reserve margin in other utilities. This is not very meaningful, unless you know well what risks each utility is<br />
exposed to (i.e. their associated uncertainties), and which risks are mitigated by a reserve margin (i.e.<br />
building reserve plant) and which risks are mitigated by additional strategies (e.g. plant mix, flexibility, etc),<br />
strategies which might be cheaper than building additional reserve plant.<br />
& The problem with handling risk in planning, is that it changes from year to year in future (uncertainties<br />
increase as you look further in the future), therefore the reserve margin criterion should change every year in
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix A<br />
your planning process (e.g. 8 % in 2004, 9 % in 2005, 10 % in 2006, etc...) but there is a limit in future, where it<br />
is not meaningful to plan to build additional reserve, since there would be time to change the plans (e.g. in<br />
SAPP, the reserve margin criterion is optimized to mitigate risk over 4 years, e.g. if one notices a load<br />
forecast increase in year 1, the utility can do something about it in year 4, e.g. install a GT or contract for<br />
interruptible load).<br />
III. EIUG COMMENT ON NIRP 2003/4 REFERENCE CASE VERSION 18 DECEMBER 2003<br />
Provided by Mr Arnot Hepburn, EIUG Sectretariat<br />
Impressions<br />
1. The Eskom / ERI-UCT / NER team are to be congratulated on developing the NIRP document from what<br />
was previously a high level comparison of planning scenario options to a study report making specific<br />
project recommendations.<br />
70<br />
2. EIUG Members welcome the publication of a significantly more comprehensive NIRP than previously<br />
issued which provides information that is essential to the business planning of energy intensive users.<br />
3. Although the NER was under the impression that they had given 4 weeks for comment the fact that the<br />
document was released just before the Christmas recess meant that most recipients were afforded less<br />
than 2 weeks to review and comment on this critical document. This has negatively impacted on the<br />
review and comments received.<br />
General Comments<br />
4. It is important to note that the optimum choice of technology is very dependent on the selected discount<br />
rate, with higher discount rates favouring less capital-intensive plant with shorter lead times. This mirrors<br />
the international trend towards more flexible technology options and away from traditional coal-fired and<br />
hydro stations.<br />
5. Due to the high regulatory uncertainty, independent power producers may well require rates of return<br />
higher than 10%, thereby affecting the appropriate technology choice. This effect should be taken<br />
into consideration.<br />
6. It is noted that although a range of demand projections are presented, the alternatives are only considered<br />
against a single demand forecast. There needs to be consideration of the course of action under the<br />
high demand scenario at least, or at the very least a qualitative description of the response to that<br />
scenario.<br />
7. A load duration curve and a forecast for its evolution over time should be included, so as to provide the<br />
minimum required information for attracting independent power producers into the ESI in the medium to<br />
long term.<br />
8. The full impact of the appropriate reserve margin should be considered - 10% appears low by
ARC and Public Comments on NIRP2 Reference Case<br />
1<br />
international norms, which are around 20% for long-term planning purposes . While the<br />
appropriate reserve margin differs from market to market, and should be a result of a thorough<br />
LOLP and VOLL analysis, the specific characteristics of the South African system, i.e. a high<br />
degree of uncertainty on demand forecasts and the inflexible and long lead-time technologies<br />
used in SA (coal PF, pump storage) would indicate the need for a higher rather than lower reserve<br />
margin.<br />
9. The EIUG have stated at IRP ARC meetings and would again like to place on record that we do not<br />
agree with interruptible load being considered as 'firm capacity' as this capacity can only be used in<br />
an emergency and is only 'firm' for a contractually limited time period each week.<br />
10. We are surprised to find that media sources, such as the Engineering News, serve as references for cost<br />
estimations (Appendix 3 footnote 64, p25). This creates doubt over the reliability of this information and<br />
should be avoided in future.<br />
11. The report has been enhanced by the addition of the appendices however there is very limited reference to<br />
specific sections in the appendices within the text of the report negating the effective transfer of<br />
information to the reader. This should be addressed in editing the report.<br />
12. The opening paragraph of the report mentions taking into account committed contracts for imports and<br />
exports to South Africa from neighbouring states which is tie-line trading. The NEPAD initiative would<br />
require South Africa to be the anchor customer for bulk import of new hydropower as envisaged from the<br />
so-called Western Corridor (DRCANSA Interconnection). Lack of comment on the impact of such<br />
regional initiates on the NIRP appears to be an omission.<br />
Specific Comments<br />
71<br />
13. In Table 6 of the main report (p18) entitled 'Summary Table of New Supply Side Options Data', the<br />
efficiency ascribed to the CCGT's appears low. A figure of 50% is routinely quoted in international papers.<br />
14. In Table 8 of Appendix 1, no fuel costs have been allocated to the pumped storage units i.e. off-peak<br />
electricity purchases for pumping. It is important to know whether, in the evaluation of the viability of<br />
pumped storage units, the cost of the additional coal that has to be burnt for the pumping cycle was<br />
included as a variable pumped storage cost. Table 8 implies that this has not been done and if so, should<br />
be rectified.<br />
15. Table 2 of Appendix 2 (p3) shows that 2,400 MW of new build SCGT is to be fired on local syngas. The<br />
assumption that as much as 2,400 MW of local syngas will actually be available seems quite optimistic.<br />
The other SCGT fuel source is Kerosene as it is currently cheaper than diesel, although kerosene is a<br />
government subsidised fuel and it is not certain if it would be appropriate to subsidise a peak power<br />
station's fuel source.<br />
16. In paragraph 5 of Appendix 3 the Fluidised Bed Coal Fired <strong>Plan</strong>t is discussed. The lower firing<br />
temperatures in a fluidised bed boiler certainly limits the formations of NOX's. However the SOX's are<br />
dependent on the coal characteristics and presumably limestone will be required. It appears as if<br />
limestone costs are not included in the variable costs of this technology. In addition, the coal<br />
costs appear to be low and should be confirmed with the owners of the reserves.<br />
17. The efficiency range quoted (in note 51) of 35.2 to 42.1 presumably refers to pressurised and other<br />
advanced fluidised bed technologies. We assume that the technology in the NIRP is basic fluidised<br />
combustion. For this technology an efficiency of 37.36% seems to be very optimistic.<br />
1 <strong>National</strong> Grid Company of the UK “Seven Year Statement” www.nationalgrid.com
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix A<br />
18. Points 4 to 7 in the Conclusions of the Executive Summary and the Report are welcomed as they are clear<br />
recommendations to implement specific projects but these should all have the required commissioning<br />
date (or first to last unit commissioning dates) as has been done with point 5 to stress the need.<br />
19. The Conclusions need to make a clear statement regarding why the import of bulk hydropower is<br />
not considered in the report.<br />
20. The Conclusions need to make a clear statement as to whether the studies identified any<br />
inadequacies or constraints in the transmission system that could impact on the quality of supply.<br />
21. Question - are the amounts of dispatched imbedded generation (municipal and industrial)<br />
included in the load forecast (fig 1 page 5) to give the total consumption since imbedded<br />
generation is included in the supply side availability figures.<br />
22. Executive summary text editing:<br />
Page I para 1 line 4 : ensuring not insuring<br />
Page IV section 5 line 2 : as dictated by the ARC of the NER<br />
Page VII fig 5 title : NIRP reference plan and alternatives at<br />
Page VII conclusion 1 last sentence : (including losses) it is not sufficient.<br />
Report text editing :<br />
Page 14 last line : time-of use tariff is available.<br />
72<br />
IV<br />
IV. ESKOM GENERATION COMMENTS ON NIRP 2003/4 REFERENCE CASE VERSION 18 DECEMBER<br />
2003<br />
Provided by Mr. Gerhard Loedolff<br />
1) Is this a report by Eskom, ERI and NER, or is it a report by Eskom & ERI for NER, or is it a report by NER,<br />
drafted by Eskom and ERI. Depending on the answer, the text needs to be reflective of the position the<br />
report is written from.<br />
2) In the Introduction, it is referred in par 1 that the study is conducted to provide information on the<br />
economics of new electrical generation. Is this really so, or is objective more fold, and directed at<br />
identifying the appropriate level of new capacity additions to meet future supply; assess the<br />
appropriateness of various solutions and reflect on the economic outcome of such solutions?<br />
3) Also in the Introduction, a number of bullets is listed as steps defined and carried forward from NIRP1.<br />
However, on many of them the objective (to achieve what?) is not specified. Therefore, as an example,<br />
you are 'Selecting a preferred <strong>Plan</strong>' to achieve what?; or you are analyzing financial consequences of<br />
What?<br />
4) At the top of page 2, the report refers to the "NER agreeing to...." . Surely the NER appointed ARC to<br />
develop the planning assumptions.<br />
5) Especially on DSM, the report contains a huge amount of debate and policy and management suggestions<br />
to NER. To my knowledge this is outside of the scope of this report. I would have expected a good review of<br />
assumptions, with possible implications of deviation on the study outcomes. Refer pages 14- 16
ARC and Public Comments on NIRP2 Reference Case<br />
6) Paragraph 3.3: 2% to 3% represents a movement of 50%. can you not<br />
7) close the gap somewhat?<br />
8) Par 3.5: Surely such a statement needs some explanation?<br />
9) Par 3.7: No indication is provided on the relevance of this information<br />
10) Par 3.7.2: No indication as to why sales growth is assumed to be higher in earlier than later years. Also<br />
impact of TOU based WEPS rates not referred to.<br />
11) Who is DOE?<br />
12) Wording around Eskom's plant performance is again confusing. Suggest it reflects that it is based on<br />
90:7:3, with an average long term EAF of 88%, as also discussed at the last ARC meeting, and as used.<br />
(p27)<br />
13) In a number of places in the report, restructuring of the text to bullet format will substantially ease reading.<br />
14) Par 5.4: New Supply Side Options were recognized, BUT not included. Why?<br />
15) R60/ton for coal to the 6-pack appears underestimated by around R20/ton, while overnight capital appears<br />
about R100/kW higher that latest used in ISEP<br />
16) Suggest that the screening curves should focus only on proven technologies, and not on the speculative /<br />
developing ones in the main report. Can include an annex to give relative position to adopted supply side<br />
options<br />
73<br />
17) Section 6 deals with some issues around reliability of supply. Rather than opening a debate here, which<br />
could also be based on invalid assumptions like Cost of non supply, should the current regulatory standard<br />
w.r.t. QoS criteria as applied via licenses not rather serve as the basis?<br />
18) The plan on p29 indicates OCGT's being decided upon ahead of Komati and Grootvlei. From the<br />
discussion at the ARC meeting this appears to be the result of artificially constraining the return of<br />
Grootvlei and Komati. Is this still so; If so, Please correct!
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix A<br />
V<br />
V. COMMENTS FROM DARLING IPP<br />
Provided by Mr. Herman Oelsner<br />
I would like to put on record our disappointment that input given in our E-mail dated 2nd of December (copied<br />
below) has not found its way into the modelling.<br />
The committee could find itself soon in a very embarrassing situation since Renewable Energy Sources and<br />
Technologies have largely been ignored. This despite clear government (RE White Paper) policy and targets<br />
and numerous country-wide spread activities in this sector.<br />
From the Renewable Sector's view it appears to be "business as usual".<br />
In order to enable a more valuable contribution from the Renewable Energy Service sector, I would like to<br />
propose the co-option of two new additional members from RES to the committee which can assist me in<br />
effectively contributing to the process.<br />
Since there was only short time to look at the documentation you distributed, I had no opportunity to query<br />
certain figures in the modelling results.<br />
For example:<br />
74<br />
The lead times for wind are much shorter and should be recorded as:<br />
a Concept Phase<br />
one year<br />
b Feasibility phase<br />
two years (Darling as first-off is a bad example/ see<br />
Klipheuwel EIA took less a year)<br />
c Investment and construction one year maximum for 20 MW<br />
Extremely short lead times and the possibility of small decentralized plants which can integrate into existing<br />
national grid are the outstanding advantages of wind electricity generation.<br />
a.Life (yrs) 25 (not 20)<br />
b.Maximum Capacity factor 35% (not 19.27)<br />
c.Minimum Capacity factor 20 %(not 4,85)<br />
d.Operational Mode is not in base load but generation takes place dominantly during peak and standard times.<br />
e.Energy Limit per station of 20 MW is 54 GWh/a not 33.5<br />
There are several abbreviations in the documentation, which I do not recognize. A key would be of great help.<br />
Renewable Energy generation, solar / wind does not appear at all in the NIRP <strong>Plan</strong>s for Publication projecting<br />
plans until 2022.<br />
At last weeks World Wind Energy Conference Honourable Minister Ms Phumzile Mlambo-Ngcuka announced<br />
that the government will ratify in Cabinet on Wednesday the 3rd of December the Renewable Energy White<br />
Paper.<br />
The White Paper sets a 10-years target of 10 000 GWh renewable energy contribution to final energy<br />
consumption by 2013, from wind, biomass, solar and small hydro. Since wind is arguably at present the most<br />
economic mode of electricity generation and a well developed technology, wind will play a dominant role in new<br />
generation plant in South Africa in the near future. Assuming that wind will contribute at least half for this target,
ARC and Public Comments on NIRP2 Reference Case<br />
would translate into 10 off 20 MW wind farms, which is very realistic and rather conservative.<br />
The implementation progress will be evaluated mid-term in order to find out whether it will be necessary to<br />
revise the White paper.<br />
Based on the White Paper, the first draft renewable energy strategy is expected to be published in February<br />
2004.<br />
I respectfully submit that RE must be included in the NIRP Reference <strong>Plan</strong>.<br />
VI<br />
75<br />
VI. COMMENTS FROM KELVIN IPP<br />
Provided by Mr. Donald Bennett<br />
I have been through the document and do not have any major comments about it in general. The only point<br />
that I would like to make is that the reference to Kelvin Power Station is incorrect (Appendix 1 page 3 table 2).<br />
Kelvin (A & B) is grouped with the “Munics 1 & 2”. Kelvin was in fact privatized in November 2001 and operates<br />
as an IPP (although only serving the City of Johannesburg under a Long Term Agreement at this point in time).<br />
Reference is also made in point 5.2 (Non-Eskom System Existing Capacity) page 15 of the main document to<br />
the fact that Kelvin generation is included in the “Munic 1 & 2” blocks.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix D<br />
Appendix D<br />
NIRP ARC COMMENTS ON THE NIRP2 STAGE 2 REPORT<br />
I. ESKOM KSACS COMMENT 77<br />
Concept of expectation / Definition of the word “expected” 77<br />
Uncertainties considered (Section 4) 77<br />
Range of values for uncertain parameters (Section 4) 77<br />
Definition of scenarios (futures) (Section 4) 78<br />
Simulation of plans , and cost estimates (Sections 4 and 5) 79<br />
Renewable technologies (Section 7.3) 80<br />
Conclusion 80<br />
II. EIUG COMMENT ON NIRP2 STAGE 2 REPORT 80<br />
III. DEPARTMENT OF MINERALS AND ENERGY COMMENTS<br />
ON RENEWABLE ENERGY SCENARIO 81<br />
76
NIRP ARC Comments on NIRP2 Stage 2 Report<br />
I<br />
I. ESKOM KSACS COMMENT 22 August, 2004<br />
COMMENTS ON NIRP 2003/4 STAGE 2 REPORT<br />
Personal comments by JL Pabot<br />
The principle of the methodology used in the report to develop an optimal plan seems reasonable, but I have<br />
serious doubts on the implementation techniques applied with this methodology to derive the recommended<br />
plan, which in my opinion invalidates the results.<br />
Therefore I cannot determine from the report if the recommended plan is truly the best plan.<br />
Concept of expectation / Definition of the word “expected”<br />
The word “expected” is mentioned at many places in the document, but It does not seem to have the usual<br />
meaning, which is confusing for the reader.<br />
For me, when a parameter (e.g. availability of plant) has a statistical distribution of values over a range (low,<br />
median, high), the expected value is the probability weighted average over the range, usually close to the<br />
median value.<br />
In the whole report, the expected value of a parameter seems to always be at one end of the range, always the<br />
least favourable (i.e. the best) end for capacity investment (the side requiring the least capacity installed). All<br />
other values are worse, i.e. lead to higher capacity investment.<br />
77<br />
Uncertainties considered (Section 4)<br />
The report addresses only uncertainties that have a direct impact on the load/capacity balance.<br />
Other uncertainties that might have a significant impact on the plan, are not considered, e.g. fuel cost or fuel<br />
availability (except for imported hydro).<br />
Range of values for uncertain parameters (section 4)<br />
As mentioned in comment 1 above, the range of values selected for the analysis for the uncertain parameters<br />
is systematically biased towards the worst end of the range (i.e. the values requiring the highest capacity<br />
installed). The expected value being the lowest value considered.<br />
This obviously will lead to an optimal plan requiring more capacity than truly required.<br />
Examples of parameters that could have more favourable values than expected, i.e. outside the range<br />
considered in the study:<br />
& Load growth forecast: Surely there is some probability that there might be an economic crisis due to some<br />
international event (high petrol price, financial crisis, war in the middle, crisis in a neighbouring country,<br />
impact of AIDS, etc) which might lead to lower energy consumption growth. Export sales to SAPP might also<br />
decrease if new stations are built in SAPP.
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix D<br />
& Imported energy: Surely there is some probability that Eskom could import more power from SAPP, e.g. from<br />
Inga 1-2 after refurbishment, from ZESCO in Zambia, when they have finished refurbishing their plant, from<br />
Kafue Gorge lower, from Kudu in Namibia, if the plant is built primarily for supplying Nampower, and if Eskom<br />
buys the balance of energy generated, etc…<br />
& Interruptible load (IL) and DSM: it is quite likely that in future Eskom may contract for more IL capacity,<br />
possibly with less usage constraints, and for more demand management programmes (DMP) or DSM<br />
programmes.<br />
The probabilities allocated to the parameters values on the worst (for MW to be built) end of the range seem<br />
excessive, e.g. 70 % for available capacity<br />
Definition of scenarios (futures) (Section 4)<br />
There is an implicit (not discussed in the text) assumption in the scenarios: the 4 uncertain parameters are of a<br />
random nature, and are independent.<br />
At least one parameter, the existing IL MW capacity, is not a random parameter. The IL contracts are to a large<br />
extent under Eskom's control, i.e. their continued existence cannot be used in a probabilistic analysis.<br />
The 4 parameters are not independent in the long term, and a few of them are also not independent in the short<br />
term.<br />
78<br />
& IL MW capacity is not independent of the other parameters. Eskom is unlikely to cancel (or renegotiate)<br />
these contracts if there is a shortage of capacity to replace them (e.g. if there is some indication of a high load<br />
growth, or if imports are curtailed).<br />
& The same can be said of the municipal generation (it will not be retired if its capacity is needed) and of the<br />
plant availability (if low, Eskom will strive to improve it if there is a shortage of capacity, at least within a year or<br />
two).<br />
& The MW capacity of DSM programmes contracted by Eskom is not independent of the other parameters:<br />
Escom will invest more resources in developing these programmes if there is more need for them (e.g. for<br />
high load growth)<br />
& The MW capacity of imports is also not independent of the other parameters: Eskom will not give up part of its<br />
contractual MW allocation form Cahora Bassa at Songo if this capacity is needed in South Africa. Also<br />
Eskom will import more energy form SAPP if there is a need for it, mainly because Eskom can then offer a<br />
higher price.<br />
& The load forecast includes the energy exported to SAPP (about 2100 MW peak power in 2004). Most of<br />
Eskom's export contracts are expiring soon, part of the existing contract are non-firm (Eskom can decline to<br />
sell energy at 1 day notice). In future Eskom will reduce exports if there is a prospect of capacity shortage.<br />
Therefore the definition of the scenarios (by combining all the values of the uncertain parameters), and the<br />
derivation of their probabilities (by multiplication of the individual probabilities), is not appropriate for this<br />
expansion planning exercise.<br />
It would be more appropriate to define a set of 3 values for the uncertain parameters (low, medium, high),<br />
assess their interdependence, and derive by judgement a set of 4 or 5 realistic futures.<br />
With reference to my comment 1, it is very odd that the future (scenario 1) with all parameters having their<br />
expected values has a probability of 3 % and that all the other futures (with a combined probability of 97 %) are
NIRP ARC Comments on NIRP2 Stage 2 Report<br />
all worse (in terms of capacity requirements), even much worse for many of them.<br />
This reflects a bias in the study towards the worst cases, requiring higher installed capacity.<br />
Simulation of plans , and cost estimates (sections 4 and 5)<br />
The NIERP planners (the authors of the study) design 16 plans for the 16 futures. They then simulate each plan<br />
for each future, over the study period (8 to 20 years) assuming that the plans remain as designed for the whole<br />
duration of the study period.<br />
This does not make sense: a plan designed for a low load growth forecast would not remain unchanged if a<br />
higher load forecast would occur. Eskom would surely take some action within a year or two, e.g. order OCGTs<br />
(lead time = 1 or 2 years), contract more IL, etc…The simulation should make some provision for the<br />
adaptability of the plans to the future under which they are simulated.<br />
The consequence of this methodology implementation technique is to derive very high costs for the plans<br />
designed for favourable (i.e. good, as defined in Comment 1) futures when run under unfavourable (bad)<br />
futures.<br />
Example: The table below shows the PV cost of plans 1 (designed for future 1, the best) and 2 (designed for<br />
future 2, the worst) when run under futures 1 and 2. It shows also the expected cost (probability weighted cost,<br />
PWC) of the plans over the 16 scenarios. These costs were provided by the NIERP planners in a spreadsheet.<br />
Simulation Scenario Scenario PWC<br />
20 years future 1 future 2 cost<br />
79<br />
<strong>Plan</strong> 1, cost Rm 182427 746958 403520<br />
<strong>Plan</strong> 2, cost Rm 215676 240722 222918<br />
The high cost of plan 1 (low capacity installed) for future 2 is due to the high amount of unserved energy<br />
calculated for that case, and to the high cost of unserved energy (20 R/kWh).<br />
& The cost of unserved energy is unrealistic for that case. This is an outage cost, not a shortage cost. As<br />
mentioned extensively in the literature, outage costs are incurred by consumers when unexpected outages<br />
occur, and shortage costs are incurred when outages are expected (e.g. when there is a shortage of capacity<br />
over long periods, e.g. 6 months). Shortage costs are much lower that the outage costs. Obviously in the<br />
case of plan 1 run under future 2, outages would be expected, and a shortage cost should have been used<br />
for unserved energy, not an outage cost.<br />
& The high amount of unserved energy of plan 1 for future 2 is totally unrealistic. <strong>Plan</strong> 1 would not remained<br />
unchanged over 20 years for future 2, nor for any future worst than future 1 (i.e. for all other futures) over 20<br />
years, nor over 8 years, nor over 4 years.<br />
The impact of this invalid methodology implementation technique is to weigh all plans designed for the most<br />
favourable futures with very high unserved energy costs, which leads to very high probability weighted costs<br />
for these plans, and to their elimination on the basis of high PWC.<br />
In effect the study is seriously biased towards plans designed for bad futres, i.e. with high capacity installed.<br />
The study would be more valid if the plans were simulated as adaptable, i.e. if additional gas turbines could be<br />
installed at short notice when needed, or if plant commissioning could be delayed at short notice (with
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix D<br />
additional costs) to cope with changing futures.<br />
Renewable technologies (Section 7.3)<br />
<strong>Plan</strong> 14 with 320 MW of renewable capacity installed over the nest 20 years only pays lip service to the<br />
government's desire to introduce renewable energy in the generation of electricity. I did not check the white<br />
paper on energy policy, so maybe the study is realistic in this respect.<br />
A more visionary scenario would consider a more commendable goal, e.g. 5 % or 10 % of all new installed<br />
capacity to be based on renewable energy.<br />
If in future South Africa moves to gas fired plants with expensive gas fuel (e.g. LNG) for electricity generation,<br />
wind power plants may become economical because of their associated fuel savings, even if they receive no<br />
capacity credit to meet the peak load:<br />
Conclusion<br />
The principle of the methodology used in the report to develop an optimal plan seems reasonable, but the<br />
planning techniques used in this study for the implementation of this methodology, are in my opinion invalid.<br />
In my opinion, the shortcomings identified in the above comments invalidate the results, i.e. I cannot determine<br />
from the report if the recommended plan 14 is truly the best.<br />
I also cannot determine if the recommendation to build 720 MW of Open cycle gas turbines in 2006 is<br />
reasonable.<br />
80<br />
However since the DME representatives stated at a recent meting at the NER that Eskom and the DME had<br />
already agreed that these 720 MW of OCGT would be built in 2006, this capacity is in effect committed, and my<br />
opinion on this point is irrelevant.<br />
II<br />
II.EIUG COMMENT ON NIRP2 STAGE 2 REPORT<br />
Provided by Mr Arnot Hepburn, EIUG Sectretariat<br />
EIUG members in their review of the NIRP2 Stage 2 report are in agreement that the comments submitted<br />
previously and the EIUG concerns raised again at the last NIRP ARC meeting are all that need be given for the<br />
current report. As stated by the EIUG at the last NIRP ARC meeting it is imperative that the release of the report<br />
should not be delayed in any way as the information is urgently needed by decision makers. It is appreciated<br />
that it will never be possible to achieve 100% projections but what is known must be published.<br />
The EIUG gives it's assurance that it will give what ever support possible to future NIRP studies and reports<br />
and submit to you the following comments for consideration in the preparation of NIRP3:<br />
Demand- and consumption growth forecasting<br />
1. There appears to be uncertainty and a lack of agreement on the actual figures in the baselines as used,<br />
and on the expected demand growth in future. For example, in table 1 in the NIRP HIGH column, the sales
NIRP ARC Comments on NIRP2 Stage 2 Report<br />
in 2003 is shown as 197 401 GWh. From the Eskom annual report the actual Eskom sales was 196 980<br />
GWh. The Eskom figures excludes the energy sent out from non-Eskom generation, and therefore it<br />
appears that we are projecting future demand and consumption figures from a too low base. This may<br />
have a significant effect on the actual reserve situation in future.<br />
Further to the above, the 0,5% increase (on top of the NIRP 2 base case) in the demand growth from the<br />
ERC study to arrive at the high growth scenario, seems modest compared to the actual year on year<br />
growth of 5% over the last few years, even if we know of large new industrial loads that came on line<br />
recently. It the actual rate of growth does not taper off to 3% during the remaining months of 2004, we<br />
should consider another upward adjustment to the forecast next year.<br />
2. In table 4, the probabilities assigned to the different primary assumptions seem debatable. A probability of<br />
0.4 is assigned to the high load forecast, while recent history and the current economic outlook seem to<br />
support a higher probability. Similarly, the 0.6 probability that plant outages will be higher implies that<br />
Eskom will not be able to maintain their equipment availability, against a history that they never dropped<br />
below 88%, even in a bad year like 2003. Given the fact that the impact of higher load growth is more<br />
severe than the rest (figure 1), these assumptions greatly influence the results in the 16 scenarios. If a 0.6<br />
probability is assigned to the high load growth assumption it will result in lower reserve margins and higher<br />
PWC in scenarios 2, 6, 8 and 16. If such a relative modest change in a primary assumption can lead to a<br />
scenario of zero reserve margin, the report should point that out, assign a probability to it and sensitize<br />
government to such a possible eventuality.<br />
3. The report is silent on brown fields CF base load options, while it is common knowledge that these<br />
possibilities have shorter lead times and are cheaper than green fields options.<br />
4. The inclusion of 300 MW CSP, at R10bn capital does not seem to be well researched. It is unclear why<br />
wind power cannot contribute more to the 10 000 GWh target of Government.<br />
81<br />
III<br />
III. DEPARTMENT OF MINERALS AND ENERGY COMMENTS ON RENEWABLE ENERGY SCENARIO<br />
Provided by Mr. Andre Otto<br />
The levelised cost for wind is for all discount rates as indicated in table 9 lower than that for CSP wind, what was<br />
then the decision rationale and calculation used to "choose" the significant 300 MW CSP vs only 20 MW wind?<br />
The GEF South African Wind Energy Programme (GEF council approval of full size project in progress) aimed<br />
at an installed wind farm capacity of up to 50 MW (5 MW Darling + 45 MW through SAWEP) by December<br />
2009. 50 MW is regarded as the minimum installed wind farm capacity to attract investment and to start up a<br />
local manufacturing and exporting capability which should lower further wind farm investment in SA.<br />
The Eskom CSP demo plant (as far as I know) is based on 100 MW which still have to secure the necessary<br />
financing and authorisation.<br />
A macro-economic analysis (see attached) done (in cooperation with <strong>National</strong> Treasury) in motivating for
<strong>National</strong> Integrated <strong>Resource</strong> <strong>Plan</strong> 2 - Appendix D<br />
Cabinet approval of the White Paper on Renewable Energy (RE WP) and forming the basis of the RE Strategy<br />
(in progress), indicates a least cost based approached to be followed in implementing the RE WP target of 10<br />
000 GWh RE contribution to energy consumption by 2013.<br />
The Renewable Energy Market Transformation project (REMT) which is approved and financed by the SA<br />
Government, GEF and PCF via the World Bank, investment will start in 2005, aimed at establishing RE<br />
capacity to produce the 1st 1000 GWh of the 10 000 GWh target by 2008. Pending the success, the project will<br />
be expanded to an additional 3000 GWh to be introduced the following 4 years. The REMT is based on the<br />
macro-economic least cost approached of introducing the RE WP. The following RE technologies and<br />
applications (see table below) have been identified through a DME and World Bank economic and financial<br />
due diligence of the REMT.<br />
Recommendation<br />
The NER NIRP be updated with the RE technologies and applications as identified through the DME and<br />
World Bank economic and financial due diligence of the REMT, including CSP and wind energy as indicated in<br />
the attached table.<br />
Please take note: The REMT envisaged to introduce 744 MW RE capacity over the 1st 8 years of the RE target<br />
period which is already in excess of 320 MW.<br />
Footnote in RE WP published in Government Gazette vol 466, 14 May 2004, No 26169:<br />
82<br />
"It is estimated that if the cumulative renewable energy capacity by end of 2013 is<br />
approximately 1667 MW, then 10 000 GWh renewable energy would have been consumed over<br />
the 10 year period"<br />
Dec 03 Jan 07<br />
to Jan to Dec<br />
07 GWh 11<br />
GWh<br />
REMT Phase 1 Phase 2<br />
Sugar sugar mills spare<br />
capacity<br />
reduced process<br />
MW<br />
Annual<br />
load<br />
factor<br />
%<br />
55 55 12 52<br />
109 109 24 52<br />
steam<br />
full scale cogen 551 157 40<br />
SWH 175 1,000 190 60<br />
Pulp Ngodwana 65 65 8 90<br />
&Paper<br />
Additional projects 20 170 21 90<br />
Hydro Identified projects 210 210 63 38<br />
Additional projects 75 1,000 300 38<br />
LFG Identified projects 240 240 34 80.8<br />
Additional projects 51 600 85 80.8<br />
GEF<br />
SAWEP<br />
Wind 120 50 28<br />
Eskom<br />
CSP 613 100 70<br />
Total 1000 4733 894<br />
Total 5733 GWh (57% of 10 000 GWh target)<br />
Balance 4267 GWh most probably taken up by biofuel
Notes<br />
83