16.05.2014 Views

Chapter 6 : Legal Framework - PBMR

Chapter 6 : Legal Framework - PBMR

Chapter 6 : Legal Framework - PBMR

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

CHAPTER 6: LEGAL FRAMEWORK<br />

6.1 INTERDEPARTMENTAL COLLABORATION<br />

At the outset of the EIA, the Department of Environmental Affairs and Tourism (DEAT) as<br />

the lead authority on environmental matters, and the National Nuclear Regulator (NNR)<br />

agreed to work in close collaboration regarding the assessment of nuclear related matters<br />

associated with the project. As a result, the scoping report reflects numerous issues<br />

relating to nuclear safety that were raised by interested and affected parties (I&APs).<br />

Such issues will be dealt with in terms of the National Nuclear Regulator Act (Act No. 47 of<br />

1999). The National Nuclear Regulator (NNR) nuclear installation licence process is<br />

detailed below.<br />

The National Nuclear Regulator Act (Act No. 47 of 1999) authorises the NNR to:<br />

Provide for the protection of persons, property and the environment against nuclear<br />

damage through the establishment of safety and regulatory practices.<br />

These safety standard and regulatory practices typically include risk criteria addressing risk<br />

to public and workers, radiation dose limits due to normal operation, fundamental safety<br />

principles including as-low-as-reasonably-achievable (ALARA) and defence-in-depth,<br />

general safety principles related to international standards and requirements for<br />

emergency planning.<br />

Subject to the NNR board’s approval, the Chief Executive Officer (CEO) may:<br />

refuse an application for a nuclear installation licence and must provide the applicant<br />

with the reasons for the refusal in writing; or<br />

grant an application for a nuclear installation licence, subject to such conditions.<br />

In order to give practical impetus to the process described above a cooperative<br />

governance agreement was entered into between the DEAT and the NNR. The process<br />

described in this agreement will be followed to address radiological and nuclear safety<br />

related issues during this EIA.<br />

6.2 STATUTORY FRAMEWORK<br />

Beside the normal decision-making structures for an EIA, several other acts, regulations<br />

and treaties apply to this particular proposed study. These include, inter alia:<br />

6.2.1 ACTS<br />

The Constitution of South Africa (Act 108 of 1996);<br />

National Environmental Management Act (Act 107 of 1998);<br />

National Heritage Resources Act (Act 25 of 1999);


National Roads Traffic Act (Act 93 of 1996);<br />

National Water Act (Act 36 of 1998);<br />

Occupational Health and Safety Act (Act 85 of 1993);<br />

Physical Planning Act (Act 125 of 1991);<br />

Promotion of Access to Information Act (Act 2 of 2000);<br />

The Atmospheric Pollution Prevention Act (Act 45 of 1965);<br />

The Electricity Act (Act 41 of 1987);<br />

The Environmental Conservation Act (Act 73 of 1989);<br />

The Hazardous Substances Act (Act 15 of 1973);<br />

The National Nuclear Regulator Act (Act 47 of 1999);<br />

The Nuclear Act (Act 46 of 1999);<br />

The Seashore Act (Act 21 of 1935);<br />

Dumping at Sea Control Act, 1980;<br />

Air Quality Act, 2004 (in force 11/09/05);<br />

Compensation for Occupational Injuries and Diseases Act (Act 130 of 1993);<br />

Disaster Management Act (Act 57 of 2002);<br />

National Building Regulations and Building Standards Act (Act 103 of 1977);<br />

National Key Points Act (Act 102 of 1980).<br />

6.2.2 PROVINCIAL/LOCAL LEGISLATION<br />

Land Use Planning Ordinance (Ordinance 15 of 1985);<br />

Local By-laws.<br />

6.2.3 REGULATIONS<br />

The EIA Regulations, Regulation R1182, 1183 and 1184 as published in the Government<br />

Gazette of 5 September 1997.<br />

6.2.4 TREATIES<br />

National Nuclear Non-Proliferation Treaty enacted by the Nuclear Energy Act.<br />

The Basel Convention on Transboundary Waste Transport.<br />

6.3 NUCLEAR LICENCE PROCESS<br />

In addition to the EIA process, the project proponent also needs nuclear installation<br />

licences for the proposed nuclear activities.


These licences must be obtained from the National Nuclear Regulator (NNR) and are<br />

required under the National Nuclear Regulator Act (Act 47 of 1999). The act states that no<br />

person may site, construct, operate, decontaminate or decommission a nuclear<br />

installation, except under the authority of a nuclear installation licence. Section 21 of the<br />

Act makes provision for persons wishing to engage in any of these activities to apply to the<br />

(CEO) of the NNR for such a licence. It is important to note that different requirements<br />

exist for the nuclear installation licence and the EIA process.<br />

As is the case with the EIA process, the licence process is a sequential (staged) process.<br />

Unlike the EIA process, the licence process is ongoing (i.e. throughout the life cycle of the<br />

project – planning, construction, commissioning, operation / maintenance and<br />

decommissioning).<br />

The involvement of the public in the licence process is at the discretion of the CEO of the<br />

NNR. In terms of the Act, the CEO of the NNR is obliged to direct the applicant for a<br />

nuclear installation licence to serve a copy of the application upon:<br />

every municipality affected by the application;<br />

such other body or person as the CEO determines;<br />

publish a copy of the application in the Government Gazette and two newspapers<br />

circulating in the area of every such municipality.<br />

Any person(s) who may be directly affected by the granting of a nuclear installation<br />

licence pursuant to an application, may make representation to the NNR Board on<br />

matters relating to radiological health, safety and environmental issues connected to the<br />

application, within 30 days of the date of publication in the Government Gazette.<br />

For nuclear installations and the transport of nuclear material(s), the licence process<br />

entails the setting down of standards expressed in terms of:<br />

the quality of engineering and operation required;<br />

the limitation of radiation exposure to people.<br />

The prime considerations during a good nuclear safety design are the principles of<br />

“ALARA” (As low as reasonable achievable) and “defence-in depth”.<br />

With regard to good nuclear safety design practice, of prime consideration are the<br />

principles of defence-in-depth and of ensuring that risks and radiation doses to members<br />

of the public and workers will be maintained as low as reasonably achievable (ALARA)<br />

below the stipulated radiation dose limits.<br />

The principle of “defence-in-depth” requires that there should be multiple layers<br />

(structures, components, systems, procedures or a combination thereof) with overlapping<br />

safety provisions. Accident prevention and accident mitigation are natural<br />

consequences of the defence-in-depth principle.<br />

Besides the normal decision-making structures for an EIA, several other approvals apply to<br />

this particular proposed study. These steps in the approval process include:


DEAT must approve the EIA in co-operative agreement with the relevant provincial<br />

environmental authorities.<br />

The NNR must approve the nuclear safety aspects of the design, construction and<br />

operation/maintenance of the plant(s) (electricity generation and fuel manufacture)<br />

as well as the transportation of nuclear materials.<br />

Thereafter, Cabinet must consider all of the information in the documents that result<br />

from the above studies, and approve the construction of a demonstration module<br />

<strong>PBMR</strong> to demonstrate the techno-economic feasibility of the technology.<br />

After cabinet approval of this project, various permits must be applied for and issued<br />

for land-use, emission releases, effluent disposal, conventional waste disposal and<br />

water use.<br />

6.4 ESKOM’S INTEGRATED STRATEGIC ELECTRICITY PROGRAMME<br />

(ISEP)<br />

Eskom also has responsibilities in respect of the White Paper on National Energy Policy.<br />

Eskom uses a programme called the Integrated Strategic Electricity Programme (ISEP) to<br />

guide their planning process.<br />

As stated previously, the ISEP concerns supply-side and demand-side options. The <strong>PBMR</strong> is<br />

an option for the supply-side.<br />

ISEP is the way in which Eskom assesses by how much the demand for electricity is likely to<br />

grow, and how best to meet and manage that demand. Long-term economic forecasts<br />

are made and provide the framework to investigate and implement a wide range of new<br />

supply-side and demand-side technologies.<br />

As part of the ongoing effort to evaluate the viability of all the supply-side options, a<br />

number of power generation technologies, which have not yet been implemented in<br />

South Africa on a commercial basis, are being evaluated in terms of technical, socioeconomic<br />

and environmental aspects.<br />

6.5 AUTHORISATIONS AND PERMITS TO BE OBTAINED<br />

Table 1 summarises the permits that may be required for the proposed project, their legal<br />

basis and the authorities that would be required to issue them.<br />

Table 1: Permits potentially required for the proposed project<br />

LEGAL BASIS DEPARTMENT NATURE OF PERMIT<br />

Environment Conservation Act,<br />

73/1989 (sect 21,22,26 and Sept<br />

1997 regulations)<br />

Dept of Environmental Affairs<br />

and Tourism<br />

Environmental Impact<br />

Authorisation<br />

National Environmental<br />

Management Act, 107 of 1998<br />

Dept of Environmental Affairs<br />

Environmental Impact<br />

Authorisation: New EIA


LEGAL BASIS DEPARTMENT NATURE OF PERMIT<br />

(sect 24) and Tourism regulations<br />

National Water Act, 36 of 1998<br />

Atmospheric Pollution<br />

Prevention Act 45 of 1965<br />

National Environmental<br />

Management: Air Quality Act,<br />

39 of 2004<br />

Dept. of Water Affairs and<br />

Forestry (DWAF), regional office<br />

Cape Town<br />

Dept of Environmental Affairs<br />

and Tourism<br />

Dept of Environmental Affairs<br />

and Tourism<br />

Permission to carry out “water<br />

use” – widely defined<br />

Noxious & Offensive gas permit:<br />

Scheduled process under<br />

Annexure APPA<br />

Act promulgated regulations<br />

not formulated<br />

Nuclear Regulator Act 47/1999<br />

(Sect 20(1))<br />

Nuclear Energy Act 46/1999<br />

(Sect 46)<br />

Nuclear Energy Act 46/1999<br />

(Sect 34)<br />

Land Use Planning Ordinance<br />

15/1985<br />

National Nuclear Regulator<br />

Department of Minerals and<br />

Energy<br />

Department of Minerals and<br />

Energy<br />

Western Cape Provincial Dept of<br />

Environment & Development<br />

Planning<br />

Nuclear installation licence:<br />

Authorisation for sitting,<br />

constructing, operating,<br />

decontaminating or<br />

decommissioning a nuclear<br />

installation<br />

Dealing with nuclear waste –<br />

permit requirement<br />

Identified Authorizations by the<br />

Minister<br />

Rezoning i.t.o. 14.4(a)<br />

Full Rezoning process<br />

In addition to the legislation mentioned in Table 1, the Department of Minerals and Energy<br />

has established a national policy on the management of radioactive waste, including<br />

spent fuel.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!