2.4 Payload Fabrication and Pre-Integration Testing<br />
New mechanical and electrical hardware is fabricated in the shop facilities at WFF. Payload<br />
specific hardware is fabricated and assembled at WFF, with the exception of standard flight<br />
systems such as ignition/despin/separation systems, attitude control/boost guidance systems,<br />
recovery systems, and nose cones. Mechanical hardware is assembled and fit-checked prior<br />
to integration with scientific instrumentation provided by the customer. Electrical and<br />
telemetry instrumentation wiring and components are assembled and tested prior to<br />
integration with the customer's electrical/data systems to facilitate a smooth, trouble-free<br />
integration effort. Special pre-integration design qualification tests are often performed for<br />
new separation/ejection/deployment mechanisms, vacuum doors, and other devices. These<br />
special tests are in addition to the total payload post-integration testing that must be<br />
successfully completed before flight.<br />
Figure 2.4.1 The Very Complex Pfaff Payload Used<br />
Extended Booms to Investigate Sporadic E Events<br />
in the Ionosphere; Pfaff 21.126 Launched<br />
on 26 June 2001.<br />
Figure 2.4-2 Mentored by NSROC Staff,<br />
UVA Students begin Electrical Wiring of the<br />
Laufer 30.046 payload for the University’s<br />
“first ever” launch, 27 April 2001.<br />
2.5 Pre-Integration Review (PIR)<br />
A PIR by the project team (Mission Manager, subsystem disciplines and science) occurs prior<br />
to payload testing and integration. The purpose of this meeting is to assess the Mission<br />
Team’s readiness to support payload integration activities prior to authorizing travel by the<br />
customer or his staff. This serves to insure that the customer is not inconvenienced in having<br />