<strong>Estate</strong> <strong>Strategy</strong><br />

<strong>2011–2015</strong>


Document title<br />

<strong>Estate</strong> <strong>Strategy</strong><br />

<strong>2011–2015</strong><br />

Document author and department Responsible person and department<br />

Andrew Cardy,<br />

Director <strong>of</strong> <strong>Estate</strong>s<br />

Approving body<br />

Pr<strong>of</strong>essor John Turner,<br />

Pro Vice-Chancellor,<br />

Directorate<br />

Date <strong>of</strong> approval<br />

Board <strong>of</strong> Governors 16 June 2010, Min 80.2<br />

Review date Edition no. ID code<br />

June 2015<br />

EITHER<br />

For public access online (internet)?<br />

Tick as appropriate<br />

4 54<br />

OR<br />

For staff access only (intranet)?<br />

Tick as appropriate<br />

Yes<br />

3<br />

Yes<br />

For public access on request copy<br />

to be mailed<br />

Tick as appropriate<br />

Password protected<br />

Tick as appropriate<br />

Yes<br />

3<br />

No Yes No<br />

3<br />

External queries relating to the document to be referred in the first instance to the <strong>University</strong> Secretary:<br />

telephone +44 (0)23 9284 3195 or email university.secretary@port.ac.uk


Contents<br />

Page no.<br />

1. Introduction and overview<br />

1.1 Introduction and history . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4<br />

1.2 Planning and future purchases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4<br />

1.3 Aspirations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4<br />

2. <strong>Estate</strong> data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5<br />

2.1 Areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5<br />

2.2 Age . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5<br />

2.3 Ownership . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5<br />

2.4 Condition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5<br />

2.5 Space utilisation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6<br />

2.6 Running costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6<br />

2.7 Functional suitability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6<br />

2.8 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6<br />

3. Out-turn from the 2006–2010 <strong>Estate</strong> <strong>Strategy</strong> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6<br />

4. Overview <strong>of</strong> requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6<br />

5. Planning the future estate<br />

5.1 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7<br />

5.2 Overview <strong>of</strong> future development opportunities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7<br />

5.3 Planning studies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8<br />

5.4 Other development opportunities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8<br />

5.5 Future needs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9<br />

5.6 Other considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9<br />

5.7 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9<br />

6. <strong>Estate</strong> maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9<br />

7. Health and safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10<br />

8. Environmental management<br />

8.1 Policy and legislation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10<br />

8.2 Carbon reduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10<br />

8.3 Sustainable construction and refurbishment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11<br />

9. Funding the <strong>Estate</strong> <strong>Strategy</strong> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11<br />

10. Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11<br />

Appendix 1 Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13<br />

Appendix 2 Maps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15<br />

Appendix 3 Out-turn from the 2006–2010 <strong>Estate</strong> <strong>Strategy</strong> . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17<br />

UNIVERSITY OF PORTSMOUTH ESTATE STRATEGY <strong>2011–2015</strong> 3


1. Introduction and overview<br />

1.1 Introduction and history<br />

The <strong>University</strong> Strategic Plan 2007–2012 identifies<br />

four headline aims:<br />

a) To give an excellent student experience focused<br />

on knowledge and skills essential for roles in the<br />

global workforce.<br />

b) To raise aspirations and to promote access to the<br />

<strong>University</strong>.<br />

c) To promote the discovery, development and<br />

application <strong>of</strong> knowledge through high quality<br />

research.<br />

d) To contribute to sustainable economic, social,<br />

cultural and community regeneration and<br />

development.<br />

The aim <strong>of</strong> this <strong>Estate</strong> <strong>Strategy</strong> is to facilitate delivery<br />

<strong>of</strong> these Aims. Providing excellent buildings (and<br />

removing the remaining poor-quality estate) makes<br />

a major contribution to improving the student<br />

experience. Student recruitment benefits substantially<br />

from the fact that our estate is accessible and <strong>of</strong><br />

high and improving quality. Research and knowledge<br />

transfer also benefits from fit-for-purpose facilities.<br />

The <strong>University</strong> has, through its own efforts,<br />

regenerated a large part <strong>of</strong> the city (now known as<br />

the <strong>University</strong> Quarter). The City Council recognises<br />

this gain and is generally supportive <strong>of</strong> our planning<br />

applications. The <strong>Portsmouth</strong> Society and others<br />

have recognised the <strong>University</strong>’s contribution to<br />

regenerating the city by several awards, including<br />

the <strong>University</strong> Library (Best New Building 2007),<br />

the Students’ Union (Best New Building 2003),<br />

and the Portland Building (Best New Building<br />

1997). In 2007 Ravelin Park won five awards in the<br />

‘<strong>Portsmouth</strong> in Bloom’ competition 1 . The <strong>University</strong><br />

Library and Dennis Sciama buildings were awarded<br />

a Commendation in the 2009 and 2010 Civic Trust<br />

Awards respectively.<br />

The last decade has seen big improvements in the<br />

<strong>University</strong> estate. Several new buildings have been<br />

constructed, including a major enlargement <strong>of</strong> the<br />

<strong>University</strong> Library, a new Student Centre and the<br />

Dennis Sciama Building. Significant additional student<br />

residences have also been provided and extensive<br />

refurbishment undertaken in most other buildings.<br />

With the disposal <strong>of</strong> the former Milton Campus and<br />

consequent re-housing <strong>of</strong> the Business School,<br />

the <strong>University</strong> has now achieved spatial coherence<br />

with most academic and support facilities located<br />

on a single campus. The remaining ‘outliers’ are<br />

the Eastney marine laboratory, a small facility at<br />

Petersfield for environmental technology, Sigma<br />

Research in south London, and the Langstone sports<br />

facilities, none <strong>of</strong> which can or should be moved to<br />

the main campus.<br />

The co-location <strong>of</strong> almost all academic activities within<br />

a relatively small area has improved efficiency and<br />

has led to improved interaction between previously<br />

dispersed parts <strong>of</strong> the <strong>University</strong>. With the exception<br />

<strong>of</strong> the outlying sites discussed in the previous<br />

paragraph, when planning future development the<br />

<strong>University</strong> should aim to preserve this geographical<br />

focus and resist any temptation to move to areas<br />

outside the ‘<strong>University</strong> Quarter’.<br />

The success <strong>of</strong> all this activity is demonstrated by the<br />

assessment <strong>of</strong> estate quality derived as part <strong>of</strong> the<br />

annual <strong>Estate</strong>s Management Statistics (EMS) return<br />

to HEFCE. <strong>Portsmouth</strong>’s estate was last assessed in<br />

2009 and 92% <strong>of</strong> it was found to be in either category<br />

A or B condition 2 . The remaining 8% largely consists<br />

<strong>of</strong> the Wiltshire Building, Mercantile House and<br />

Burrell House. Remedial action for these buildings is<br />

proposed in the current Capital Plan.<br />

1.2 Planning and future purchases<br />

Student numbers are unlikely to increase significantly<br />

during the life <strong>of</strong> this <strong>Strategy</strong>. Individual Faculties<br />

have, however, experienced changes in recruitment<br />

patterns, giving rise to accommodation pressures in<br />

some areas. In many cases the solution lies in better<br />

use <strong>of</strong> our teaching space, including greater flexibility<br />

on the part <strong>of</strong> Faculties regarding the time and<br />

location <strong>of</strong> teaching, rather than new building projects.<br />

Even though the campus is fairly compact, Faculties<br />

are <strong>of</strong>ten reluctant to disperse activities beyond their<br />

‘core’ buildings.<br />

As noted earlier the <strong>University</strong>’s strategy should be to<br />

preserve the current geographical focus and resist any<br />

temptation to move to areas outside the ‘<strong>University</strong><br />

Quarter’.<br />

There are a number <strong>of</strong> sites within the ‘<strong>University</strong><br />

Quarter’ that may become available, and the<br />

<strong>University</strong> should always be prepared to consider<br />

acquiring sites <strong>of</strong> strategic importance within or<br />

adjacent to the campus.<br />

Our strategy should continue to be that we will<br />

investigate and consider site acquisitions within the<br />

<strong>University</strong> Quarter as possibilities arise and in the light<br />

<strong>of</strong> <strong>University</strong> needs and finances at the time.<br />

1.3 Aspirations<br />

Most <strong>of</strong> our estate is in category A or B condition as<br />

noted earlier. Our aim is to have all <strong>of</strong> our facilities in at<br />

least the B category.<br />

The cost <strong>of</strong> energy continues to rise and is now a very<br />

significant part <strong>of</strong> the <strong>Estate</strong>s budget. A further<br />

1 Community and Neighbourhood Award. Best Environmental Project. Best Historic Garden. Best Newcomer. Best Environment Project for Wildlife<br />

Conservation.<br />

2 EMS Condition measures A to D; A = being as new, B = sound, operationally safe and exhibiting only minor deterioration, C = in need <strong>of</strong> significant<br />

refurbishment and D = unserviceable.<br />

4 ESTATE STRATEGY <strong>2011–2015</strong> UNIVERSITY OF PORTSMOUTH


aspiration therefore is to ensure that all buildings<br />

are as energy-efficient as possible. For all new<br />

construction we will specify a ‘BREEAM 3 excellent’<br />

rating when tendering.<br />

We will also follow current best practice for<br />

sustainable construction and refurbishment work.<br />

Finally, we will continue to undertake sufficient<br />

preventive work to avoid creating problems for the<br />

future (‘long term maintenance’). Our strategy will<br />

be to ensure that a sufficient and adequate annual<br />

budget is allocated for long-term maintenance.<br />

2. <strong>Estate</strong> data<br />

This section looks in some detail at the estate and provides<br />

key data upon which decisions for the future can be made.<br />

The original data from which this information is obtained<br />

can be found in the appendices and is taken from the<br />

institutional return to HEFCE for the EMS relating to 2009.<br />

2.1 Areas<br />

2.3 Ownership<br />

At 79% the majority <strong>of</strong> the <strong>University</strong>’s property is<br />

held under freehold ownership. The remaining 21%<br />

is split between leasehold (2%) and long leasehold,<br />

exceeding 25 years (19%).<br />

The leasehold properties are a mix <strong>of</strong> academic,<br />

research and pr<strong>of</strong>essional services use. Of the long<br />

leasehold properties the majority are residential<br />

buildings on the Guildhall Campus which provide<br />

approximately 45% <strong>of</strong> the overall study bedrooms<br />

managed by the <strong>University</strong>.<br />

2.4 Condition<br />

The condition <strong>of</strong> the estate is assessed internally<br />

as part <strong>of</strong> the annual EMS return to HEFCE with<br />

properties placed in one <strong>of</strong> four condition categories,<br />

A to D (refer to paragraph 1.1, footnote 2).<br />

The <strong>University</strong> has a rolling five year planned<br />

preventative maintenance strategy which is further<br />

explained in paragraph 6.<br />

The overall <strong>University</strong> estate amounts to a little under<br />

26 hectares. Of this total approximately 10.5 hectares<br />

are playing fields at the Langstone Campus and just<br />

over four hectares are parkland at Ravelin Park on the<br />

Guildhall Campus.<br />

The estate comprises 91 buildings <strong>of</strong> which 23 are<br />

halls <strong>of</strong> residence providing c3,000 bedspaces. The<br />

gross internal area <strong>of</strong> these buildings equates to<br />

207,000m 2 with c137,000m 2 <strong>of</strong> this being academic<br />

and support facilities and the remaining 70,000m 2<br />

residential.<br />

2.2 Age<br />

The buildings which make up the <strong>University</strong>’s estate<br />

vary in age from the mid 1800s through to buildings<br />

still under construction with just over half <strong>of</strong> the total<br />

area being constructed since 1980. The percentage<br />

distribution is shown in Figure 1 below.<br />

Figure 2. Condition <strong>of</strong> the estate (2009)<br />

100%<br />

B – 65%<br />

A – 27%<br />

C –<br />

8%<br />

D – 0%<br />

60<br />

80%<br />

D<br />

% <strong>of</strong> estate<br />

50<br />

40<br />

30<br />

20<br />

60%<br />

40%<br />

20%<br />

0%<br />

Non-residential<br />

Residential<br />

C<br />

B<br />

A<br />

10<br />

0<br />

Pre<br />

1914<br />

1915–<br />

1939<br />

1940–<br />

1959<br />

1960–<br />

1979<br />

1980<br />

on<br />

Figure 3. Condition <strong>of</strong> the estate by function<br />

Figure 1. Age <strong>of</strong> buildings<br />

3 BREEAM (Building Research Establishment Environmental Assessment Method) is an environmental assessment method for buildings. It sets the<br />

standard for best practice in sustainable design and has become the de facto measure used to describe a building’s environmental performance.<br />

UNIVERSITY OF PORTSMOUTH ESTATE STRATEGY <strong>2011–2015</strong> 5


2.5 Space utilisation<br />

The <strong>University</strong> aims to use teaching space as<br />

efficiently as possible, whilst <strong>of</strong>fering students<br />

convenient, reasonably spacious and fit for purpose<br />

facilities. There is, <strong>of</strong> course, a conflict between these<br />

two aims: raising utilisation (defined as the product<br />

<strong>of</strong> frequency <strong>of</strong> use and room occupancy) inevitably<br />

generates complaints <strong>of</strong> overcrowding and less than<br />

convenient timetables. Therefore, applying too much<br />

pressure on space utilisation can have undesirable<br />

consequences.<br />

During 2008–09 the <strong>University</strong> appointed SUMS 4 to<br />

review its timetabling processes, which are <strong>of</strong> course<br />

closely related to space utilisation. In their report<br />

SUMS notes that ‘space utilisation [at <strong>Portsmouth</strong>] is<br />

so good that it can be compared with the best [in the<br />

sector]’.<br />

These Key Performance Indicators are in line with the<br />

<strong>University</strong>’s EMS Peer Group.<br />

2.7 Functional suitability<br />

The functional suitability <strong>of</strong> each building is also<br />

assessed as part <strong>of</strong> the annual EMS return to HEFCE<br />

using four categories from excellent through to poor.<br />

The majority <strong>of</strong> the estate achieves an excellent<br />

rating which, together with the results achieved<br />

under the assessment <strong>of</strong> condition, reflect the level<br />

<strong>of</strong> investment the <strong>University</strong> has made in the estate<br />

and the level <strong>of</strong> importance it places on having a good<br />

quality learning and working environment.<br />

General teaching space is categorised as either<br />

pooled or dedicated, pooled space being generally<br />

managed and timetabled centrally and dedicated<br />

space being departmentally managed and timetabled.<br />

However, the final timetable coordination is<br />

undertaken centrally by the Central Timetabling Unit.<br />

Excellent<br />

79%<br />

Good<br />

20%<br />

Fair<br />

1%<br />

Utilisation statistics are produced each semester, the<br />

average results for the first semester 2008–09 are<br />

given in the table below.<br />

Poor 0%<br />

Table 1. Space utilisation summary<br />

Pooled<br />

space<br />

Dedicated<br />

space<br />

Frequency Occupancy Utilisation<br />

79% 55% 44%<br />

68% 50% 37%<br />

Overall occupancy rates for the halls <strong>of</strong> residence are<br />

monitored on a regular basis and consistently report<br />

high levels <strong>of</strong> space efficiency. Average occupancy<br />

levels across all halls for the 2008/2009 academic<br />

year is reported as 98.76%<br />

2.6 Running costs<br />

As previously mentioned, the <strong>University</strong> submits data<br />

to the HEFCE backed EMS data collection exercise.<br />

Key outcomes from the 2009 submission are noted<br />

below.<br />

• Total property costs<br />

per m 2 (NIA) – £95<br />

per student head – £782<br />

• Maintenance costs<br />

per m 2 (GIA) – £21<br />

• Energy costs<br />

per m 2 (GIA) – £9.74<br />

Gas as a percentage <strong>of</strong> total energy costs – 29%<br />

Electricity as a percentage <strong>of</strong> total energy costs –<br />

71%<br />

• Energy consumption<br />

kW/h per m 2 (GIA) – 192<br />

kW/h per student FTE – 2518<br />

Figure 4. Functional suitability <strong>of</strong> the built estate<br />

2.8 Summary<br />

During the course <strong>of</strong> the outgoing Plan the <strong>University</strong><br />

has been able to maintain its estate at an overall<br />

good standard and achieve space utilisation levels<br />

in line with the best in the sector. Projects currently<br />

underway or scheduled for this plan period should<br />

see an end to the poorer quality estate either by<br />

refurbishment or replacement.<br />

3. Out-turn from the 2006–2010<br />

<strong>Estate</strong> <strong>Strategy</strong><br />

The outgoing <strong>Estate</strong> <strong>Strategy</strong> set the <strong>University</strong> some key<br />

goals in terms <strong>of</strong> improvements to the estate, many <strong>of</strong><br />

which have been achieved. These goals and their outcomes<br />

are highlighted in Appendix 3.<br />

4. Overview <strong>of</strong> requirements<br />

Through the implementation <strong>of</strong> its previous Capital Plan and<br />

<strong>Estate</strong> <strong>Strategy</strong> the <strong>University</strong> has made good progress<br />

towards the strategic objectives <strong>of</strong> replacing poor quality<br />

space, refurbishing existing buildings, ensuring that learning<br />

spaces are fit for purpose, meeting the needs <strong>of</strong> new<br />

subject areas (e.g. Dentistry and Law), and providing new<br />

student accommodation.<br />

We still have some poor quality space which it is<br />

uneconomic or impractical to refurbish (particularly the<br />

Wiltshire Building and Eldon West). We also have two<br />

4 Southern Universities Management Services.<br />

6 ESTATE STRATEGY <strong>2011–2015</strong> UNIVERSITY OF PORTSMOUTH


uildings that require extensive refurbishment if we are to<br />

retain them for the medium to long term (Mercantile House<br />

and St. George’s). Finally, we have one student hall which is<br />

outdated and cannot easily be updated (Burrell Hall). There<br />

is a significant and persistent unmet demand for student<br />

housing.<br />

The <strong>University</strong>’s home/EU student numbers are likely to<br />

remain fixed for the next few years. There may be some<br />

growth in international student numbers (for example from<br />

ICP), and this may have implications for student housing<br />

needs. However, it does not seem likely that any major<br />

expansion <strong>of</strong> the <strong>University</strong>’s academic space will be<br />

needed during the lifetime <strong>of</strong> this <strong>Strategy</strong>.<br />

Two Faculties (CCi and HSS) suffer from having their<br />

activities dispersed across more than one separated site.<br />

An aim <strong>of</strong> this <strong>Strategy</strong> is to co-locate Faculties as far as<br />

possible. This aim will be largely met by moving the School<br />

<strong>of</strong> Architecture and SCAFM to the proposed Eldon West<br />

and NTR buildings (see later), and also by moving SECS<br />

and ICJS to the new Victoria Building (again see later).<br />

Thus, the <strong>University</strong>’s likely space requirements and strategy<br />

can be summarised as follows:<br />

• We need to provide space for academic activities (i.e.<br />

teaching and research) at about the current level.<br />

• We must work to ensure that our teaching and research<br />

spaces (laboratories, lecture theatres, seminar rooms<br />

etc) meet current and future Faculty requirements for<br />

size, configuration, facilities and equipment. This may<br />

mean re-configuration <strong>of</strong> room sizes and layouts has to<br />

take place as teaching/research needs change.<br />

• There is a continuing demand from academic staff for<br />

individual cellular <strong>of</strong>fice space. However, this demand<br />

is unsustainable in terms <strong>of</strong> general provision for<br />

academic and support staff. The design <strong>of</strong> any new<br />

build or major refurbishment project will be based on<br />

sensitively designed shared <strong>of</strong>fice areas accompanied<br />

by adequate and appropriate provision <strong>of</strong> private<br />

interview rooms. This should lead to a more cost<br />

effective and efficient use <strong>of</strong> space resources. Where<br />

it is considered there is supportable justification<br />

to deviate from this policy this will require the prior<br />

approval <strong>of</strong> the Directorate.<br />

• Our aim is to maintain the quality <strong>of</strong> our existing stock<br />

<strong>of</strong> student accommodation, and as finances and<br />

opportunities permit make available further student<br />

bedrooms. As a very rough estimate we may need<br />

another 1500 bedrooms in addition to the number<br />

available in 2009/10. We should not necessarily aim<br />

to own or lease additional student housing – seeking<br />

development partners may be a more effective way<br />

to secure additional student housing and reduces the<br />

financial risk to the <strong>University</strong>.<br />

• The <strong>University</strong>’s Pr<strong>of</strong>essional Services and Support<br />

Departments are dispersed across a number <strong>of</strong><br />

buildings, some <strong>of</strong> which are not well optimised for<br />

their current use. As opportunities arise we should<br />

consider co-locating Pr<strong>of</strong>essional Services and Support<br />

Departments in larger, more energy-efficient and betterquality<br />

buildings – especially where this allows us to<br />

dispose <strong>of</strong> or terminate leases on some <strong>of</strong> our smaller<br />

and less desirable properties.<br />

5. Planning the future estate<br />

5.1 Background<br />

Recent years has seen the <strong>University</strong> invest heavily in<br />

its estate with transformational results. The estate has<br />

been transformed from one with a disparate collection<br />

<strong>of</strong> buildings spread across a number <strong>of</strong> areas <strong>of</strong><br />

the city in varying states <strong>of</strong> condition and functional<br />

suitability to one predominantly located in the heart<br />

<strong>of</strong> the city comprising buildings in good condition<br />

and providing a high level <strong>of</strong> functional suitability. This<br />

has been achieved by a mix <strong>of</strong> property acquisitions,<br />

disposals, refurbishments and a number <strong>of</strong> new<br />

purpose-built buildings.<br />

This process has been guided by previous <strong>Estate</strong>s<br />

Strategies building on an initial framework set out in<br />

1992, updated in 1999/2000 and a master plan which<br />

set out a vision for the future <strong>of</strong> the <strong>University</strong> in 1992.<br />

Most <strong>of</strong> the aspirations <strong>of</strong> that plan have now been<br />

achieved.<br />

In 1995 a detailed planning study <strong>of</strong> Ravelin Park was<br />

undertaken to inform possible future developments in<br />

that location as it was clear that the available land for<br />

future development was limited. The amenity value <strong>of</strong><br />

the park was recognised and therefore the resultant<br />

plan was landscape driven which maintained the<br />

amenity value whilst identifying a number <strong>of</strong> sites,<br />

predominantly to the north <strong>of</strong> the park, which could<br />

be developed. The plan was formally adopted by<br />

<strong>Portsmouth</strong> City Council as planning guidance for<br />

future planning decisions.<br />

Langstone Campus had the benefit <strong>of</strong> a planning<br />

consent for a further 680 study bedrooms, however,<br />

the decision was taken in 2002 not to pursue a<br />

renewal due to the strengthening <strong>of</strong> planning policy<br />

relating to open spaces, playing fields and housing,<br />

coupled with the difficult planning history <strong>of</strong> the site.<br />

5.2 Overview <strong>of</strong> future development<br />

opportunities<br />

As intimated previously in this document the<br />

<strong>University</strong> has limited opportunities for undertaking<br />

developments on land in its existing freehold<br />

ownership. Where such opportunities do exist they<br />

generally require demolition <strong>of</strong> existing building stock<br />

as part <strong>of</strong> the development. There are however a<br />

small number <strong>of</strong> possibilities for such developments<br />

which are expanded upon later in this <strong>Strategy</strong> but in<br />

summary they are:<br />

• Anglesea-Burnaby area on land released as a<br />

result <strong>of</strong> previous or future demolition <strong>of</strong> poorer<br />

quality buildings.<br />

• The remaining undeveloped sites identified in<br />

the Ravelin Park development plan referred to in<br />

paragraph 5.1 above and consisting mainly <strong>of</strong><br />

the site <strong>of</strong> the previous Student Union building,<br />

Alexandra House.<br />

• Wiltshire Building site.<br />

UNIVERSITY OF PORTSMOUTH ESTATE STRATEGY <strong>2011–2015</strong> 7


Two other possibilities which were not in <strong>University</strong><br />

ownership were identified in the previous <strong>Estate</strong><br />

<strong>Strategy</strong>, namely the site <strong>of</strong> the Tennis Dome in<br />

Cambridge Road (currently in MOD ownership<br />

and leased to <strong>Portsmouth</strong> City Council) and the<br />

site <strong>of</strong> the Swimming Pool in Victoria Park (owned<br />

by <strong>Portsmouth</strong> City Council). Whilst the former <strong>of</strong><br />

these two remains a possibility in the future, at the<br />

time <strong>of</strong> drafting this <strong>Strategy</strong> the <strong>University</strong> is in the<br />

final stages <strong>of</strong> negotiations to acquire the site <strong>of</strong> the<br />

swimming pool in Victoria Park for a mixed student<br />

residential and academic space development.<br />

In addition to these two sites, land to the rear <strong>of</strong> and<br />

in the ownership <strong>of</strong> the New Theatre Royal (NTR) has<br />

also been identified as a possible future development<br />

site for the location <strong>of</strong> certain aspects <strong>of</strong> the various<br />

performing arts departments.<br />

5.3 Planning studies<br />

In order to provide a realistic basis for the satisfaction<br />

<strong>of</strong> future development needs the <strong>University</strong><br />

commissioned studies <strong>of</strong> the North Campus,<br />

the southern end <strong>of</strong> Ravelin Park and the site at<br />

Eastney in an effort to establish acceptable levels <strong>of</strong><br />

development in these areas.<br />

5.3.1 North Campus<br />

The removal <strong>of</strong> temporary buildings at the<br />

rear <strong>of</strong> the Anglesea and Burnaby Buildings<br />

was undertaken using HEFCE Poor <strong>Estate</strong>s<br />

Initiative funding from 1999 onwards. This led<br />

to the creation <strong>of</strong> a number <strong>of</strong> development<br />

opportunities in this area, and architects<br />

Stubbs Rich were commissioned to examine<br />

the options for its future and that <strong>of</strong> the North<br />

Campus more generally.<br />

The study concluded that it would be possible<br />

to undertake a phased redevelopment <strong>of</strong> five<br />

buildings on the area between Anglesea and<br />

Burnaby buildings which when completed<br />

would provide over 15,800m 2 <strong>of</strong> new space<br />

whilst demolishing approximately 8,350m 2<br />

resulting in a net addition <strong>of</strong> approximately<br />

7,450m 2 . These proposals were supported by<br />

the local planning authority and approved by<br />

the Board <strong>of</strong> Governors as the preferred route<br />

for future development <strong>of</strong> the North Campus.<br />

The Dennis Sciama Building is the first building<br />

<strong>of</strong> this plan, possible without significant<br />

demolition, and was completed and opened<br />

for use in January 2009 and provided a new<br />

home for the Institute <strong>of</strong> Cosmology and<br />

Gravitation, a variety <strong>of</strong> general purpose<br />

teaching spaces and new staff and student<br />

catering facilities.<br />

5.3.2 Ravelin Park South<br />

The Ravelin Park plan previously mentioned<br />

established the principle that developments<br />

could be undertaken on the site <strong>of</strong> a<br />

demolished building. This principle has been<br />

adopted for the Student Centre building and<br />

the Dental Outreach Centre. The previous<br />

Students’ Union building, Alexandra House,<br />

was located in the south west corner <strong>of</strong><br />

the Park and this site, together with the<br />

adjacent Rotunda building site were reviewed<br />

to establish the scale <strong>of</strong> buildings that<br />

would be acceptable to the local planning<br />

authority. This review, supported by the local<br />

planning authority, concluded that buildings<br />

<strong>of</strong> approximately 3,350m 2 and 1,750m 2<br />

respectively were likely to be acceptable. The<br />

Alexandra House building site is currently<br />

being utilised as a car park under a temporary<br />

planning permission.<br />

5.3.3 Institute <strong>of</strong> Marine Sciences, Eastney<br />

The site at Eastney was acquired from<br />

the MOD in the mid 1990s and consists<br />

<strong>of</strong> a collection <strong>of</strong> separate buildings on an<br />

exposed site on a spit <strong>of</strong> land in Langstone<br />

Harbour. Whilst the buildings provide adequate<br />

accommodation in most respects there is<br />

a need for additional space and the ability<br />

to move between facilities in comfort when<br />

the weather is inclement would be a distinct<br />

advantage. A basic development plan was<br />

produced in 2004 in order to demonstrate<br />

how the site could be developed on a phased<br />

basis whilst remaining operational. This was<br />

undertaken to inform the location etc. <strong>of</strong> a<br />

new building which has subsequently been<br />

constructed and which effectively forms the<br />

first phase <strong>of</strong> a development plan.<br />

In 2009 architects were appointed to produce<br />

a more detailed development plan which<br />

satisfied the local planning authority and<br />

enabled the <strong>University</strong> to progress the next<br />

phase. The resulting document proposes<br />

a further three phases <strong>of</strong> development<br />

comprising individual buildings linked by a<br />

common atrium/link which will enable users<br />

to move between facilities in comfort. These<br />

three phases provide a total <strong>of</strong> 2,231m 2<br />

(GEA) <strong>of</strong> new space whilst demolishing some<br />

1,107m 2 (GEA) <strong>of</strong> existing accommodation<br />

thus providing a net additional 1,124m 2 (GEA)<br />

<strong>of</strong> space. It is anticipated that the first <strong>of</strong> these<br />

three phases will commence on site in 2010.<br />

5.4 Other development opportunities<br />

5.4.1 Wiltshire Building<br />

The Wiltshire Building currently houses<br />

performing arts and music activities and is<br />

in many ways less than ideal. Should the<br />

joint development with the NTR referred to<br />

in paragraph 5.3 above come to fruition this<br />

site is likely to be disposed <strong>of</strong>. However,<br />

should this not turn out to be the case the<br />

site provides a possible opportunity for<br />

development in the future, ideally in connection<br />

with the acquisition <strong>of</strong> adjacent properties to<br />

create a more rational footprint. Initial thoughts<br />

are that a development <strong>of</strong> approximately<br />

3,500–4,500m 2 would be possible on the<br />

rationalised site.<br />

8 ESTATE STRATEGY <strong>2011–2015</strong> UNIVERSITY OF PORTSMOUTH


5.4.2 Swimming Pool Site, Victoria Park<br />

The <strong>University</strong> is currently working with<br />

a development partner to acquire and<br />

develop this site to provide approximately<br />

600 bedrooms <strong>of</strong> student residential<br />

accommodation together with approximately<br />

4,300m 2 <strong>of</strong> academic space. This will assist<br />

with the shortfall <strong>of</strong> student bedrooms<br />

identified in paragraph 4 and enable the<br />

potential disposal <strong>of</strong> the St George’s Building<br />

and Burrell House located on the southern<br />

edge <strong>of</strong> the Guildhall Campus.<br />

5.4.3 Tennis Dome Site<br />

An initial assessment is that this site, located<br />

adjacent to the Nuffield Sports Hall and<br />

Spinnaker buildings could accommodate a<br />

building <strong>of</strong> approximately 4,000m 2 . Due to<br />

the current ownership status <strong>of</strong> the site any<br />

potential acquisition is likely to be a lengthy<br />

process and is also unlikely to become<br />

available in the near future. At this stage it has<br />

been considered for completeness sake but<br />

has not been taken into account in current<br />

plans.<br />

5.4.4 New Theatre Royal back lot<br />

At the time <strong>of</strong> drafting this <strong>Strategy</strong> the<br />

<strong>University</strong> is working with the NTR to jointly<br />

develop this site for both <strong>University</strong> activities<br />

and much needed additional facilities for the<br />

theatre which they lost in a fire in 1972. This<br />

development will enable the co-location <strong>of</strong><br />

performing arts and music with a working<br />

theatre and the probable disposal <strong>of</strong> the<br />

Wiltshire Building where these activities are<br />

currently based.<br />

5.4.5 Milldam House<br />

Milldam house is an in-lier in the <strong>University</strong>’s<br />

property portfolio which is currently owned<br />

by <strong>Portsmouth</strong> City Council. It is unlikely to<br />

<strong>of</strong>fer a future development opportunity, but<br />

its acquisition could provide an additional<br />

250m 2 <strong>of</strong> space and rationalise the <strong>University</strong>’s<br />

boundary in this part <strong>of</strong> the North Campus.<br />

5.5 Future needs<br />

It is not anticipated that the <strong>University</strong> will grow<br />

significantly either in terms <strong>of</strong> student numbers or<br />

overall size <strong>of</strong> estate during the period <strong>of</strong> this <strong>Estate</strong><br />

<strong>Strategy</strong>. It will therefore more likely be a period <strong>of</strong><br />

consolidation and rationalisation as opportunities arise<br />

rather than expansion. However, should expansion<br />

become necessary it would be possible to build<br />

additional facilities on existing <strong>University</strong> sites.<br />

5.6 Other considerations<br />

As mentioned in paragraph 1.1 Mercantile House<br />

falls within the small percentage <strong>of</strong> the estate<br />

that is considered to be in condition category C.<br />

The completion <strong>of</strong> the Eldon, NTR and Victoria<br />

developments and the subsequent vacation <strong>of</strong> St<br />

George’s Building will provide decant space for the<br />

activities remaining in Mercantile House. This will<br />

enable Mercantile House to be refurbished thereby<br />

removing a significant portion <strong>of</strong> the category C space.<br />

Three sites currently have temporary planning<br />

consents, Milldam Nursery, Ravelin Car Park and<br />

Montgomery Building at Eastney. The Nursery,<br />

currently housed in a temporary building in the<br />

Milldam Courtyard, is due to move into new facilities<br />

in LA Block at Milldam following its refurbishment and<br />

conversion. The temporary nursery building will then<br />

be removed.<br />

The Ravelin Car Park consent has been renewed for<br />

a further three years expiring in 2010. This is proving<br />

to be a beneficial asset to the <strong>University</strong>, and the City<br />

who make use <strong>of</strong> it at weekends, and attempts will<br />

be made to secure a permanent consent if possible.<br />

However, this will not be a straightforward exercise<br />

due to the City’s transport policies. The site does,<br />

<strong>of</strong> course, remain as one <strong>of</strong> the <strong>University</strong>’s possible<br />

development sites.<br />

The Montgomery Building at Eastney will be removed<br />

as part <strong>of</strong> the last phase <strong>of</strong> development on this site<br />

(see paragraph 5.4.3 above) and until such time as<br />

this is instigated further renewals will be required.<br />

5.7 Summary<br />

The various planning studies that have been<br />

undertaken have identified a number <strong>of</strong> development<br />

opportunities on sites currently in <strong>University</strong><br />

ownership. There are also two site acquisitions, NTR<br />

and Victoria Pool, which are currently being pursued.<br />

Due to the anticipation that the <strong>University</strong> will not grow<br />

significantly during this plan period it is believed that<br />

further site acquisitions will not be necessary to meet<br />

the <strong>University</strong>’s strategic aims. However, the exception<br />

to this would be if opportunities arise to acquire sites<br />

that would be <strong>of</strong> strategic importance in terms <strong>of</strong><br />

their location or if such an acquisition would enable<br />

further consolidation and rationalisation <strong>of</strong> activities,<br />

particularly in terms <strong>of</strong> the Pr<strong>of</strong>essional Services<br />

departments.<br />

6. <strong>Estate</strong> maintenance<br />

One <strong>of</strong> the strategic aims <strong>of</strong> the <strong>University</strong> is to give an<br />

excellent student experience. There are many things that<br />

combine to provide this but one essential ingredient is to<br />

<strong>of</strong>fer a well maintained estate in good condition and fit for<br />

the purpose. As has been mentioned previously the majority<br />

<strong>of</strong> the estate falls with condition categories A or B but to<br />

achieve and maintain this level <strong>of</strong> quality requires a pro<br />

active maintenance programme which is adequately funded.<br />

The day-to-day maintenance <strong>of</strong> the estate can be<br />

subdivided into reactive and planned preventative activities.<br />

Reactive maintenance is reported through the <strong>Estate</strong>s<br />

Helpdesk and formally logged into the works order<br />

management system. The aim is to increase the level<br />

<strong>of</strong> planned preventative maintenance and, as a result,<br />

reduce the level <strong>of</strong> reactive activities required by the early<br />

identification and rectification <strong>of</strong> problems.<br />

UNIVERSITY OF PORTSMOUTH ESTATE STRATEGY <strong>2011–2015</strong> 9


A programme <strong>of</strong> annual condition surveys is used to inform<br />

a rolling five year Long Term Maintenance (LTM) plan<br />

which identifies and schedules the more major items <strong>of</strong><br />

expenditure as opposed to the day-to-day maintenance<br />

referred to above. The LTM is reviewed on a regular basis<br />

and revised in accordance with the surveys and available<br />

budgets.<br />

7. Health and safety<br />

The <strong>University</strong>’s central Health and Safety Office has overall<br />

responsibility for ensuring the activities <strong>of</strong> the <strong>University</strong><br />

are carried out in accordance with relevant legislation etc.<br />

Management <strong>of</strong> the estate in general clearly falls within this<br />

overall remit but there are specific, and increasingly more,<br />

sections <strong>of</strong> legislation which relate to the wide range <strong>of</strong><br />

activities that constitute estate management. The <strong>University</strong><br />

will integrate Health and Safety into all <strong>of</strong> these activities,<br />

taking all reasonable and practical steps to ensure the<br />

health and safety <strong>of</strong> all persons affected by them.<br />

The <strong>University</strong> uses s<strong>of</strong>tware to manage many <strong>of</strong> its estate<br />

related activities and will work towards incorporating the<br />

management and coordination <strong>of</strong> health and safety into the<br />

existing s<strong>of</strong>tware systems to ensure compliant safe systems<br />

<strong>of</strong> work are used for all <strong>of</strong> its activities and the activities <strong>of</strong><br />

third parties employed to undertake estate management<br />

tasks on its behalf.<br />

8. Environmental management<br />

8.1 Policy and legislation<br />

Continuing to improve the overall environmental<br />

management and performance <strong>of</strong> the estate is key to<br />

achieving standards and reducing operational costs.<br />

To support this, the <strong>University</strong> has created a policy<br />

structure which includes controls on the impacts <strong>of</strong><br />

the buildings, starting with the environmental policy<br />

and concluding with codes <strong>of</strong> practice for sustainable<br />

construction, and energy and carbon reduction.<br />

Within this policy context it is expected that design<br />

teams will consistently use the BREEAM approach to<br />

sustainable building design in order to drive the need<br />

for energy efficient buildings which are cheaper to run.<br />

HEFCE has introduced carbon management<br />

policy which expects Universities to have carbon<br />

management plans in place and to report annually<br />

on carbon reductions in order to satisfy CIF2.<br />

From a legislation perspective there are increasing<br />

demands on the estate to be publicly accountable<br />

for energy consumption and associated carbon<br />

emissions. The introduction in 2008 <strong>of</strong> Display Energy<br />

Certificates (DEC) for existing larger buildings, Energy<br />

Performance Certificates (EPC) for new, sold or rented<br />

buildings and the introduction <strong>of</strong> the CRC Energy<br />

Efficiency Scheme are pressing the <strong>University</strong> to<br />

acknowledge and reduce its carbon emissions.<br />

The estate also has to simplify its approach to the<br />

management <strong>of</strong> new waste management legislation<br />

that covers site waste management plans for<br />

construction/refurbishment projects over a certain<br />

value and disposal controls on waste electrical and<br />

electronic equipment (WEEE) and batteries.<br />

Ultimately, to install safeguards and proper controls,<br />

accreditation to the international standard for<br />

environmental management systems (ISO14001) by<br />

2013 is essential as it will provide external scrutiny <strong>of</strong><br />

our compliance with environmental policy, legislation<br />

and procedures. The first stages <strong>of</strong> accreditation<br />

are being implemented by a joint Health, Safety and<br />

Environment project board which is aiming to expand<br />

the use <strong>of</strong> the existing estate management s<strong>of</strong>tware,<br />

Maximo, to host system records.<br />

8.2 Carbon reduction<br />

The CRC Energy Efficiency Scheme is a compelling<br />

reason to reduce carbon emissions from energy<br />

consumption as the <strong>University</strong> is subject to full<br />

compliance and is having to carefully manage its<br />

participation and performance within the scheme.<br />

From April 2011 carbon allowances will have to be<br />

purchased for the year ahead with some return <strong>of</strong><br />

this expenditure depending upon performance in the<br />

annual league tables.<br />

In recognition <strong>of</strong> the carbon reduction obligations<br />

there are already in place schemes to reduce carbon<br />

emissions from energy use. The <strong>University</strong>’s success<br />

in obtaining funding from the HEFCE/Salix Revolving<br />

Green Fund has enabled the creation <strong>of</strong> a fund for<br />

energy efficiency projects which is now saving up<br />

to 400t CO2 per annum and producing significant<br />

reductions to energy bills. The fund is continually<br />

topped up from energy savings and will be used to<br />

drive carbon emissions down. In addition the whole<br />

estate has been covered by a radio-based energy use<br />

monitoring system which can in most cases monitor<br />

and record gas and electricity consumption per<br />

building each half hour <strong>of</strong> every day. This automatic<br />

monitoring and targeting system (AM&T) will be used<br />

to identify where energy usage can be reduced.<br />

Participation in the Carbon Trust’s HE Carbon<br />

Management Programme will culminate in a detailed<br />

carbon management plan being available in the first<br />

half <strong>of</strong> 2011. The plan will provide a long-term carbon<br />

reduction strategy from energy use but will also cover<br />

carbon emissions from fleet vehicles, recycling and<br />

waste, water consumption and commuting, all areas<br />

influenced by management <strong>of</strong> the estate. It is likely<br />

that a strategic rethink <strong>of</strong> energy supply to buildings<br />

will be required in order to meet long-term carbon<br />

reduction targets.<br />

Reliable data collection systems are proving vital in<br />

the reporting <strong>of</strong> carbon emissions and in improving<br />

environmental performance generally. Systems will be<br />

extended to cover all scopes <strong>of</strong> carbon emission and<br />

existing relationships maintained to monitor water use<br />

and provide monthly weight data for recycling and<br />

general waste. Carbon reduction will be overseen by<br />

the work <strong>of</strong> the Carbon Management Group chaired<br />

by a Pro Vice-Chancellor which will continue to<br />

guide the <strong>University</strong> through its carbon management<br />

obligations.<br />

10 ESTATE STRATEGY <strong>2011–2015</strong> UNIVERSITY OF PORTSMOUTH


8.3 Sustainable construction and<br />

refurbishment<br />

The <strong>University</strong> has successfully achieved an<br />

‘Excellent’ BREEAM rating for the library extension<br />

in the past and this approach will be included in the<br />

specification for all new buildings. To compliment<br />

this approach use <strong>of</strong> the BRE Green Guide to<br />

Specification will be used as a valuable asset in the<br />

selection <strong>of</strong> materials with low environmental impact.<br />

Ideally a standard specification for sustainable<br />

construction will be developed for use in tendering<br />

which will ensure in particular the procurement <strong>of</strong> low<br />

energy use buildings. The specification could be used<br />

for the refurbishment <strong>of</strong> buildings too.<br />

Waste weight data from construction and<br />

refurbishment projects will be collected from<br />

contractors site waste management plans (SWMP)<br />

and incorporated within annual statistics.<br />

The estate needs to recognise its role in adapting<br />

to climate change. Over the course <strong>of</strong> this <strong>Strategy</strong><br />

a climate change risk assessment needs to be<br />

undertaken and a plan put in place which influences<br />

a range <strong>of</strong> services including building design to cope<br />

with changes in our climate.<br />

9. Funding the <strong>Estate</strong> <strong>Strategy</strong><br />

Since 1999 the <strong>University</strong> has produced a Capital Plan<br />

which is updated every 4–5 years. The Capital Plan runs<br />

in parallel with the <strong>Estate</strong>s <strong>Strategy</strong> and is intended to<br />

demonstrate that the <strong>University</strong>’s capital expenditure<br />

ambitions are achievable.<br />

The current Capital Plan covers the period from 2009–2014.<br />

The detailed Plan was presented and discussed at the<br />

meeting <strong>of</strong> <strong>Estate</strong>s and IT Committee held on 26 May<br />

2009. The total expenditure proposed (including 10% for<br />

contingencies and an allowance for inflation over the life <strong>of</strong><br />

the Plan) is £64m. This expenditure is partially funded by a<br />

number <strong>of</strong> planned property disposals.<br />

The Capital Plan is focussed almost entirely on<br />

improvements to the <strong>University</strong> <strong>Estate</strong>. New and refurbished<br />

academic buildings and the provision <strong>of</strong> additional student<br />

accommodation are planned. A key aim is to improve the<br />

student experience by eliminating the remaining poorerquality<br />

accommodation. Funding is drawn from a variety <strong>of</strong><br />

sources, including:<br />

• Disposals (Wiltshire, Burrell, Halpern, St George’s,<br />

Guildhall Walk)<br />

• HEFCE Teaching and Learning Capital Funding<br />

• HEFCE Strategic Development fund<br />

• NHS (for Dental Outreach)<br />

• the <strong>University</strong>’s own resources.<br />

The 2009 Capital Plan was written during 2008–9 and<br />

property prices have changed substantially in the last 18<br />

months. The outlook for HEFCE (and other public sector)<br />

funding is far more uncertain than was the case at the time<br />

the Plan was drafted. Nevertheless, work has continued on<br />

most <strong>of</strong> the projects reported in the Plan. In most cases<br />

substantial progress has been made with planning and<br />

design, and in some cases site work is underway or has<br />

been completed.<br />

A refurbishment <strong>of</strong> Mercantile House (estimated cost around<br />

£10m) has been deferred until other major projects (Eldon<br />

and Victoria) are complete. Mercantile is a stand alone<br />

project and is one where deferral due to funding delays<br />

would impact least severely on student experience <strong>of</strong> the<br />

three main projects in the Plan. A structural survey has been<br />

undertaken to confirm that this building requires no urgent<br />

remedial action.<br />

For similar reasons the planned refurbishment <strong>of</strong> the St<br />

George’s Building has also been deferred.<br />

The major building projects included in the Plan are:<br />

• development <strong>of</strong> the Victoria Pool site;<br />

• development <strong>of</strong> the Eldon West site and a linked<br />

development on the New Theatre Royal ‘back lot’;<br />

• replacement <strong>of</strong> marine science laboratories at Eastney;<br />

• construction <strong>of</strong> a security lodge and refurbishment <strong>of</strong><br />

the changing rooms at Langstone;<br />

• conversion <strong>of</strong> the Students’ Union nightclub into a<br />

social learning area;<br />

• conversion <strong>of</strong> the former refectory in Anglesea into<br />

facilities for the School <strong>of</strong> Law.<br />

The current Capital Plan does not envisage any<br />

further building in Ravelin Park. No other development<br />

opportunities are currently being considered (as discussed<br />

in section 5). However, as discussed in section 5.7 the<br />

<strong>University</strong> will consider and investigate any sites that may<br />

become available within the ‘<strong>University</strong> Quarter’ on a caseby-case<br />

basis.<br />

The Victoria Pool site development involves a partner who<br />

is co-funding much <strong>of</strong> the building work. This approach<br />

is likely to be used again should further residential<br />

development opportunities arise.<br />

10. Conclusion<br />

• The <strong>University</strong> is committed to delivering the <strong>Estate</strong><br />

<strong>Strategy</strong> against the current background <strong>of</strong> financial<br />

and academic uncertainty.<br />

• It is not anticipated that the <strong>University</strong> will grow<br />

significantly during the period <strong>of</strong> this <strong>Estate</strong> <strong>Strategy</strong>.<br />

It will therefore more likely be a period <strong>of</strong> consolidation<br />

and rationalisation as opportunities arise rather than<br />

expansion. However, should expansion become<br />

necessary it would be possible to build additional<br />

facilities on existing <strong>University</strong> sites.<br />

• The <strong>University</strong>’s strategy is to preserve the existing<br />

geographical focus and resist any temptation to move<br />

outside the ‘<strong>University</strong> Quarter’.<br />

• There are a number <strong>of</strong> sites within the ‘<strong>University</strong><br />

Quarter’ that may become available, and the <strong>University</strong><br />

should always be prepared to consider acquiring<br />

sites <strong>of</strong> strategic importance within or adjacent to the<br />

campus.<br />

UNIVERSITY OF PORTSMOUTH ESTATE STRATEGY <strong>2011–2015</strong> 11


• The majority <strong>of</strong> the estate is in condition category A<br />

or B and our aim is to maintain this level <strong>of</strong> quality<br />

and have all <strong>of</strong> our facilities in at least category B. The<br />

completion <strong>of</strong> the developments and refurbishment<br />

projects identified in this <strong>Estate</strong> <strong>Strategy</strong> should achieve<br />

this aim.<br />

• The co-location <strong>of</strong> dispersed activities will be pursued<br />

as far as possible/practical. Academically this will be<br />

achieved with the completion <strong>of</strong> the Victoria, Eldon and<br />

NTR developments.<br />

• There is a continuing demand from academic staff for<br />

individual <strong>of</strong>fice space. However, this demand may be<br />

unsustainable and serious consideration should be<br />

given to increasing the amount <strong>of</strong> shared or open-plan<br />

<strong>of</strong>fice space in any new or reconfigured buildings.<br />

• There is a significant and persistent unmet demand<br />

for student residential accommodation. The current<br />

Victoria development will meet a proportion <strong>of</strong> this<br />

demand but the <strong>University</strong> will be open to the provision<br />

<strong>of</strong> further bedrooms through partnership arrangements.<br />

• The <strong>University</strong> will continue to undertake sufficient<br />

preventive work to avoid creating problems for the<br />

future. Our strategy will be to ensure that a sufficient<br />

and adequate annual budget is allocated for long-term<br />

maintenance.<br />

• There is a significant challenge to be met in terms <strong>of</strong> the<br />

reduction in energy use and carbon emissions which<br />

the <strong>University</strong> is committed to meeting.<br />

• Finally, this <strong>Strategy</strong> is being drafted at a time <strong>of</strong><br />

economic and, to an extent, academic uncertainty.<br />

Therefore the <strong>Strategy</strong> set out may need to be revised<br />

to take account <strong>of</strong> events that may unfold as a result <strong>of</strong><br />

this uncertainty.<br />

12 ESTATE STRATEGY <strong>2011–2015</strong> UNIVERSITY OF PORTSMOUTH


Appendix 1<br />

Data<br />

Building Gross Condition Main Tenure<br />

area (m 2 ) category use<br />

Guildhall Campus<br />

Anglesea Building (+ Lodge) 9,656 B Ac FH<br />

Buckingham Building 4,118 B Ac FH<br />

Burnaby Building 5,612 C Ac FH<br />

Burnaby Building Huts 216 B Ac FH<br />

Burnaby Terrace 812 B Ac FH<br />

Dennis Sciama 3,280 A Ac/Re/Pr FH<br />

Durham Street 181 B Pr LH<br />

Eldon Building (incl ext) 9,979 B Ac FH<br />

Guildhall Walk 1,076 B Pr FH<br />

Halpern House 954 B Pr FH<br />

Hampshire Terrace 1,107 B Pr LH<br />

James Watson – Ground Floor 2,424 A Pr/Ac LH<br />

King Henry Building 6,278 B Ac/Re FH<br />

Lion Gate Building 2,708 B Ac FH<br />

Mercantile House 4,848 C Pr/Ac FH<br />

Middle Street (36–40) 624 B Ac LH<br />

Middle Street (56) 506 B Pr LH<br />

Milldam Site 3,651 B Ac FH<br />

Nuffield Centre 3,881 B Pr FH<br />

Nuffield Sports Hall 1,625 A Pr FH<br />

Park Building (+ Annexe) 8,863 B Ac FH<br />

Port Royal Street 642 B Pr LH<br />

Portland Building 6,715 B Ac FH<br />

Ravelin House (+ Annexes) 824 B Ac FH<br />

Richmond Building 6,799 A Ac FH<br />

Rotunda 314 C Pr FH<br />

Spinnaker Building 1,805 A Ac/Re FH<br />

St George’s Building 5,360 B Ac FH<br />

St Andrew’s Court 462 A Pr LH<br />

St Michael’s Building 5,822 B Ac/Re FH<br />

St Michael’s Building Extn 6,697 B Ac/Re FH<br />

St Paul’s Road 1,801 B Pr FH<br />

Student Centre (Gun House) 779 B Pr FH<br />

Student Centre (Main) 3,576 B Pr FH<br />

<strong>University</strong> House (+ Lodge) 3,102 B Pr FH<br />

<strong>University</strong> Library 10,373 A Pr FH<br />

William Beatty 1,223 A Ac FH<br />

Wiltshire Building 1,901 C Ac FH<br />

Langstone<br />

Amenities Block and Sick Bay 1,232 B Pr FH<br />

Changing Rooms 401 B Pr FH<br />

Langstone 2,124 B Pr FH<br />

Service Buildings 226 C Pr FH<br />

Sundry Other Buildings<br />

Eastney 1,303 B/C Ac/Re FH<br />

Montgomery Building 113 B Ac FH<br />

Petersfield 313 B Re LH<br />

Tradescant 223 C Re LH<br />

Key: Ac – Academic; Re – Research; Pr – Pr<strong>of</strong>essional Services; Res – Residential.<br />

UNIVERSITY OF PORTSMOUTH ESTATE STRATEGY <strong>2011–2015</strong> 13


Building Gross Condition Main Tenure<br />

area (m 2 ) category use<br />

Halls <strong>of</strong> Residence<br />

Barnard Tower 2,317 B Res FH<br />

Bateson Hall 5,343 B Res FH<br />

Burrell House 2,437 C Res FH<br />

Harry Law Hall 7,719 B Res FH<br />

James Watson Hall 17,942 A Res LH<br />

Langstone Flats 3,973 B Res FH<br />

Margaret Rule Hall 8,820 B Res LH<br />

Rees Hall 6,422 B Res FH<br />

Trafalgar Hall 9,985 A Res LH<br />

Trust Block 1,586 B Res FH<br />

QEQM – A/B 681 B Res FH<br />

QEQM – C/D 681 B Res FH<br />

QEQM – E/F 808 B Res FH<br />

QEQM – G/H 680 B Res FH<br />

QEQM – White/Dymond 705 B Res FH<br />

QEQM – Bungalows & Lodge 369 C Res FH<br />

QEQM – Ker/St James 495 B Res FH<br />

Key: Ac – Academic; Re – Research; Pr – Pr<strong>of</strong>essional Services; Res – Residential.<br />

14 ESTATE STRATEGY <strong>2011–2015</strong> UNIVERSITY OF PORTSMOUTH


Appendix 2<br />

Maps<br />

<strong>Portsmouth</strong><br />

UNIVERSITY OF PORTSMOUTH ESTATE STRATEGY <strong>2011–2015</strong> 15


<strong>University</strong> Quarter (Guildhall)<br />

16 ESTATE STRATEGY <strong>2011–2015</strong> UNIVERSITY OF PORTSMOUTH


Appendix 3<br />

Out-turn from the 2006–2010 <strong>Estate</strong> <strong>Strategy</strong><br />

(only applicable paragraphs have been included)<br />

Paragraph<br />

reference<br />

Item<br />

Brief resume<br />

2.6 Running costs • Through use <strong>of</strong> the HEFCE/Salix Revolving Green Fund it has been possible<br />

to invest in a number <strong>of</strong> energy efficiency projects.<br />

• A Carbon Management Group has been formed to steer the institution’s<br />

activities relating to the Carbon Reduction agenda.<br />

4.1 Academic space requirements • Joint project with the New Theatre Royal being progressed to provide<br />

replacement accommodation for the Wiltshire Building.<br />

4.3 Support accommodation • Requirement has not been as great as anticipated but a small amount <strong>of</strong><br />

replacement/additional space has been acquired at St Andrew’s Court.<br />

4.4 Residential accommodation • Applications for halls places have exceeded available places in recent years<br />

and therefore additional spaces are being progressed in conjunction with<br />

third party providers.<br />

• When developments referred to above come online serious consideration<br />

will be given to the disposal <strong>of</strong> Burrell House.<br />

5.3 An overview <strong>of</strong> future development<br />

opportunities<br />

• Negotiations are currently ongoing regarding the acquisition and<br />

development <strong>of</strong> the site <strong>of</strong> the former swimming pool in Victoria Park.<br />

5.4 Recent planning studies • Dennis Sciama Building on the North Campus was opened in January<br />

2009.<br />

5.5 Other development opportunities • See resume for 5.3 above.<br />

5.7 Other considerations • Redevelopment <strong>of</strong> existing space in Milldam to provide permanent nursery<br />

facility currently nearing completion.<br />

• Renewed temporary planning consent for the car park in Ravelin Park<br />

obtained.<br />

6 <strong>Estate</strong> maintenance • PPM system using Maximo s<strong>of</strong>tware in place.<br />

• Maximo upgraded to latest version in 2009 and Archibus currently being<br />

reviewed.<br />

• 8% <strong>of</strong> all buildings fall below condition category B.<br />

• Not all <strong>Estate</strong> record drawing yet in electronic format.<br />

7.1 Funding the <strong>Strategy</strong> • All major building projects identified in the second phase capital plan have<br />

been completed.<br />

UNIVERSITY OF PORTSMOUTH ESTATE STRATEGY <strong>2011–2015</strong> 17


<strong>University</strong> <strong>of</strong> <strong>Portsmouth</strong><br />

<strong>Estate</strong>s Department<br />

1 Guildhall Walk<br />

<strong>Portsmouth</strong> PO1 2RY<br />

United Kingdom<br />

T: +44 (0)23 9284 2679<br />

F: +44 (0)23 9284 2742<br />

E: estates@port.ac.uk<br />

W: www.port.ac.uk<br />

MD5730 0910