2.5 Space utilisation<br />

The <strong>University</strong> aims to use teaching space as<br />

efficiently as possible, whilst <strong>of</strong>fering students<br />

convenient, reasonably spacious and fit for purpose<br />

facilities. There is, <strong>of</strong> course, a conflict between these<br />

two aims: raising utilisation (defined as the product<br />

<strong>of</strong> frequency <strong>of</strong> use and room occupancy) inevitably<br />

generates complaints <strong>of</strong> overcrowding and less than<br />

convenient timetables. Therefore, applying too much<br />

pressure on space utilisation can have undesirable<br />

consequences.<br />

During 2008–09 the <strong>University</strong> appointed SUMS 4 to<br />

review its timetabling processes, which are <strong>of</strong> course<br />

closely related to space utilisation. In their report<br />

SUMS notes that ‘space utilisation [at <strong>Portsmouth</strong>] is<br />

so good that it can be compared with the best [in the<br />

sector]’.<br />

These Key Performance Indicators are in line with the<br />

<strong>University</strong>’s EMS Peer Group.<br />

2.7 Functional suitability<br />

The functional suitability <strong>of</strong> each building is also<br />

assessed as part <strong>of</strong> the annual EMS return to HEFCE<br />

using four categories from excellent through to poor.<br />

The majority <strong>of</strong> the estate achieves an excellent<br />

rating which, together with the results achieved<br />

under the assessment <strong>of</strong> condition, reflect the level<br />

<strong>of</strong> investment the <strong>University</strong> has made in the estate<br />

and the level <strong>of</strong> importance it places on having a good<br />

quality learning and working environment.<br />

General teaching space is categorised as either<br />

pooled or dedicated, pooled space being generally<br />

managed and timetabled centrally and dedicated<br />

space being departmentally managed and timetabled.<br />

However, the final timetable coordination is<br />

undertaken centrally by the Central Timetabling Unit.<br />

Excellent<br />

79%<br />

Good<br />

20%<br />

Fair<br />

1%<br />

Utilisation statistics are produced each semester, the<br />

average results for the first semester 2008–09 are<br />

given in the table below.<br />

Poor 0%<br />

Table 1. Space utilisation summary<br />

Pooled<br />

space<br />

Dedicated<br />

space<br />

Frequency Occupancy Utilisation<br />

79% 55% 44%<br />

68% 50% 37%<br />

Overall occupancy rates for the halls <strong>of</strong> residence are<br />

monitored on a regular basis and consistently report<br />

high levels <strong>of</strong> space efficiency. Average occupancy<br />

levels across all halls for the 2008/2009 academic<br />

year is reported as 98.76%<br />

2.6 Running costs<br />

As previously mentioned, the <strong>University</strong> submits data<br />

to the HEFCE backed EMS data collection exercise.<br />

Key outcomes from the 2009 submission are noted<br />

below.<br />

• Total property costs<br />

per m 2 (NIA) – £95<br />

per student head – £782<br />

• Maintenance costs<br />

per m 2 (GIA) – £21<br />

• Energy costs<br />

per m 2 (GIA) – £9.74<br />

Gas as a percentage <strong>of</strong> total energy costs – 29%<br />

Electricity as a percentage <strong>of</strong> total energy costs –<br />

71%<br />

• Energy consumption<br />

kW/h per m 2 (GIA) – 192<br />

kW/h per student FTE – 2518<br />

Figure 4. Functional suitability <strong>of</strong> the built estate<br />

2.8 Summary<br />

During the course <strong>of</strong> the outgoing Plan the <strong>University</strong><br />

has been able to maintain its estate at an overall<br />

good standard and achieve space utilisation levels<br />

in line with the best in the sector. Projects currently<br />

underway or scheduled for this plan period should<br />

see an end to the poorer quality estate either by<br />

refurbishment or replacement.<br />

3. Out-turn from the 2006–2010<br />

<strong>Estate</strong> <strong>Strategy</strong><br />

The outgoing <strong>Estate</strong> <strong>Strategy</strong> set the <strong>University</strong> some key<br />

goals in terms <strong>of</strong> improvements to the estate, many <strong>of</strong><br />

which have been achieved. These goals and their outcomes<br />

are highlighted in Appendix 3.<br />

4. Overview <strong>of</strong> requirements<br />

Through the implementation <strong>of</strong> its previous Capital Plan and<br />

<strong>Estate</strong> <strong>Strategy</strong> the <strong>University</strong> has made good progress<br />

towards the strategic objectives <strong>of</strong> replacing poor quality<br />

space, refurbishing existing buildings, ensuring that learning<br />

spaces are fit for purpose, meeting the needs <strong>of</strong> new<br />

subject areas (e.g. Dentistry and Law), and providing new<br />

student accommodation.<br />

We still have some poor quality space which it is<br />

uneconomic or impractical to refurbish (particularly the<br />

Wiltshire Building and Eldon West). We also have two<br />

4 Southern Universities Management Services.<br />

6 ESTATE STRATEGY <strong>2011–2015</strong> UNIVERSITY OF PORTSMOUTH

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!