Stages of construction - lining the pit with bricks<br />

<strong>The</strong> size of bricks varies considerably, but about 400 -500 farm bricks are<br />

normally enough to line a pit of this size. <strong>The</strong> pit is lined so the internal<br />

diameter within the brickwork is 1.4m. This diameter is maintained for 1.5m<br />

above the base of the pit. <strong>The</strong>n the corbelling begins, with each course<br />

being stepped in by about 20 -25mm. <strong>The</strong> brickwork should rise above<br />

ground level by about 2 courses. <strong>The</strong> external diameter of the uppermost<br />

course should be slightly larger than the slab diameter of 1.2m.