WILL COUNTY STORMWATER MANAGEMENT PLANNING COMMITTEE<br />

58 E. Clinton Street, Suite 500<br />

Joliet, IL 60432<br />

V 815.740.8140 F 815.774.6327<br />

December 2, 2009<br />

Karen L. Cotton<br />

Manager, External Affairs<br />

minois American Water<br />

123 S.W. Washington Street<br />

Peoria, IL 61602<br />

RE: <strong>Fiddyment</strong> <strong>Creek</strong> <strong>Maint</strong>enance <strong>Project</strong> Summary Report<br />

Dear Ms. Cotton:<br />

The Stormwater Committee embarked on its first stream maintenance project earlier this year. The project's<br />

plU-pose was to remove blockages within the creek's channel to help improve storrnwater conveyance and<br />

flooding. Utilizing the watershed prioritization work the Committee completed in the spring 01'2009 we were<br />

able to select <strong>Fiddyment</strong> <strong>Creek</strong> as the focus for the American Water grant. <strong>Fiddyment</strong> <strong>Creek</strong> is located in the<br />

DesPlaines River watershed Enclosed are the following:<br />

./ A map of the project area with pictures<br />

./ <strong>Project</strong> Fact Sheet<br />

./ <strong>Project</strong> Budget Sheet<br />

./ Additional Pictures<br />

Below is the summary of the project:<br />

• Participating Members:<br />

• <strong>Will</strong> <strong>County</strong> Storrnwater Management Planning Committee<br />

• <strong>Will</strong> <strong>County</strong> <strong>Land</strong> <strong>Use</strong><br />

• City of Lockport<br />

• Lockport Township Highway Dept.<br />

• Lockport Township Park District<br />

• American Water, Inc<br />

• Forest Preserve District of <strong>Will</strong> <strong>County</strong><br />

• Homer Tree, Inc. (contractor)<br />

• Dick's Towing (contractor)<br />

• June 2009 the Environmental Grant funded by American Water was applied for.<br />

• July 2009 American Water awarded $3,000 to <strong>Will</strong> COlmty for the <strong>Fiddyment</strong> <strong>Creek</strong> <strong>Maint</strong>enance <strong>Project</strong>.<br />

Chair Vice-Chair Secretary Director<br />

Scott Killinger, PE Ken Carroll, PE Thomas Pawlowicz, PE Howard Hamilton, PE, CFM<br />

District 2 Municipal District 9 <strong>County</strong> District 4 <strong>County</strong> 815.740.8140<br />

815.462.6450 815.609.9675 630.226.8851


<strong>Fiddyment</strong> Summary Report<br />

12/2/2009<br />

American Water<br />

• <strong>Project</strong> had to be completed by December 1,2009.<br />

• August 2009 a blockage inventory was conducted to identify and locate blockages (see map).<br />

• 12 blockages were identified for the project.<br />

• An action plan was developed and members were assigned to each blockage.<br />

• A survey questionnaire is sent out asking for residents' input and informing them of the work.<br />

• Action plan is executed in October and November 2009.<br />

• Material removed (see attached sample photos):<br />

• Trees and other woody materiel totaling 1100 Cubic Feet<br />

• CornEd spool for storing wire<br />

• (1) Car<br />

The cooperation alone warrants this project to be considered a success. All groups were helpful in strategizing<br />

and willing to go the extra mile to ensure a successful project. The amount of work that was done for this project<br />

would have easily been in the tens of thousands of dollars if contractors were hired for each blockage, but through<br />

this great partnership we were able to minimize the amount of dollars being spent directly from anyone's budget.<br />

The in-kind services provided for the project resulted in a great return on investment for the tax payers. We are<br />

proud to share this project with American Water and hope that any future projects will be as successful.<br />

If you should have questions please contact me at 815.740.8140 or DO'Sullivan@willcountylanduse.com<br />

Sincerely,<br />

<strong>Will</strong> <strong>County</strong> Stormwater Management Planning Committee<br />

l ./'<br />

. .'<br />

,;<br />

" ~) .'.<br />

./~'-~<br />

.,;'1 :' / i~~-<br />

;'7\ [A~{..~<br />

O&ek CYSullivan, CFM<br />

Assistant Director<br />

__


<strong>Fiddyment</strong> <strong>Creek</strong> <strong>Maint</strong>enance <strong>Project</strong><br />

PROJECT FACT SHEET<br />

Fall 2009<br />

• The <strong>Will</strong> <strong>County</strong> Stormwater Management Planning Committee initiated a stream maintenance program and<br />

chose <strong>Fiddyment</strong> <strong>Creek</strong> to be their first project. The selection of the creek was based on a series of planning and<br />

prioritizing activities the Committee conducted.<br />

• A $3,000 environmental grant was awarded to the Stormwater Committee by American Water to help offset<br />

cost of the project.<br />

• <strong>Fiddyment</strong> <strong>Creek</strong> <strong>Maint</strong>enance <strong>Project</strong> stretches from 1-355 downstream to the Southwest to IL Rte 171 in the<br />

City of Lockport.<br />

• <strong>Project</strong> scope is to remove identified blockages within the <strong>Creek</strong>'s channel to help improve floodwater<br />

conveyance and flooding of property.<br />

• A total of twelve (12) blockages were found, one of them being a car.<br />

• The project successfully brought together multiple jurisdictions to form a joint partnership. Each project partner<br />

took a defined amount of blockages that they would remove using their own resources.<br />

• This partnership not only helped bring together the local authorities in the community, but it also helped reduce<br />

the need of cash contributions and budgeted dollars.<br />

• A couple of contracting partners were indentified and used to help with some of the blockages.<br />

• <strong>Project</strong> Partners:<br />

./ American Water(environmental grant program)<br />

./ City of Lockport<br />

./ Forest Preserve District of <strong>Will</strong> <strong>County</strong><br />

./ Lockport Township Highway Department<br />

./ Lockport Township Park Districts<br />

./ <strong>Will</strong> <strong>County</strong> <strong>Land</strong> <strong>Use</strong> Department<br />

./ <strong>Will</strong> <strong>County</strong> Stormwater Management Planning Committee<br />

• Contracting Partners:<br />

./ Dick's towing Service, Inc.<br />

./ Homer tree Services, Inc.