For an all-inclusive impact summary refer to Appendix G for the I-95, Section 200 Wetland<br />
Impact Matrix that identifies permanent and temporary impacts for all wetland systems<br />
identified within the study area.<br />
Express Toll Lanes Alternative<br />
This alternative (including MD 152 Option 4A, MD 24 Option 2, MD 543 Option 7, and<br />
MD 22 Option 1) would permanently impact 1.3 acres of wetlands and temporarily impact 1<br />
acre of wetlands. All temporary impacts are associated with the construction of the<br />
alternative, and were determined using a 25 foot buffer from the proposed LOD for this<br />
alternative. Please refer to Appendix B, Plates 33-65 for the locations of the wetlands in<br />
association with the Express Toll Lanes Alternative. Impacts to wetlands for each<br />
interchange option are listed in Table III-12.<br />
The following summarizes some of the impacts to wetlands associated with the Express Toll<br />
Lanes Alternative:<br />
• All 0.368 acres of wetlands within the current I-95/MD 152 Interchange would be<br />
filled due to the interchange enhancements (Appendix B, Plate 41).<br />
• All WET-18B (0.068 acres) would be impacted as a result of upgrades to the MD 152<br />
exit ramp from I-95 southbound (Appendix B, Plate 42).<br />
• Construction of interchange ramps would permanently impact wetlands within the<br />
immediate vicinity of the I-95/MD 24 Interchange. A total of 0.072 acres would be<br />
impacted at the following wetlands: WP024, WP001, WP002, WP003, WP004,<br />
WP004A, WP004B, and WET-25B. (Appendix B, Plates 44-46)<br />
• Roadway widening would necessitate all 0.177 acres of WET-6C to be filled<br />
(Appendix B, Plate 50).<br />
• In addition to 0.042 acres of temporary construction impacts, WET-7C (0.030 acres)<br />
would be permanently impacted due to the roadway expansion (Appendix B, Plate<br />
50).<br />
• WET-3D and WET-4D would be impacted due to roadway widening. The impacts<br />
will total 0.053 acres (Appendix B, Plates 53). Also, both WET-5D and WET-18D<br />
Section 200 Draft <strong>Environmental</strong> <strong>Assessment</strong><br />
III-63