08.11.2014 Views

BRUCE HEAVY WATER PLANT DECOMMISSIONING PROJECT

BRUCE HEAVY WATER PLANT DECOMMISSIONING PROJECT

BRUCE HEAVY WATER PLANT DECOMMISSIONING PROJECT

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Bruce Heavy Water Plant Decommissioning<br />

Environmental Assessment Study Report<br />

Ontario Power Generation<br />

Final Submission to CNSC<br />

2.1.2 Option 2: Partial Decommissioning/Partial Mothballing and Selective<br />

Demolition<br />

This option involves decommissioning the Enriching Unit towers, flare stack, pipe racks and<br />

other tall structures to ground level. The other unused buildings and structures on site would be<br />

mothballed. The redundant underground services would be isolated but left in situ.<br />

Removing the tall structures and the pipe racks would reduce the potential hazards from falling<br />

objects and structural collapse. The visual environment would also be improved by the removal<br />

of these landmarks. Leaving the buildings on site and continuing care and maintenance on them<br />

would be costly and would not reduce the eventual demolition cost. This cost could be offset if<br />

the buildings were reused. Some of the buildings on site are currently being used for other<br />

purposes and it is not intended to decommission them at this stage. This option was ranked third,<br />

equal to Option 4.<br />

2.1.3 Option 3: Partial Decommissioning/Demolition to Grade – No Mothballing<br />

This option involves decommissioning the Enriching Unit towers, flare stack, pipe racks and<br />

other redundant buildings and structures to ground level. The redundant underground services<br />

would be isolated but left in situ.<br />

This option has the same safety benefits as Option 2 but with the added advantage that hazards<br />

posed by the redundant buildings would be removed. It would also improve the environment and<br />

reduce the care and maintenance costs. However, it would cost more in the short term to<br />

implement than Option 2. Additionally, the underground services, concrete foundations, etc.,<br />

which would remain after the decommissioning will eventually have to be removed. This option<br />

received the highest score.<br />

2.1.4 Option 4: Partial Decommissioning/Demolition to Grade, Excavation and<br />

Removal of Underground Services<br />

This option involves decommissioning the Enriching Unit towers, flare stack, pipe racks and<br />

other redundant buildings and structures to ground level. The redundant underground services<br />

would be excavated and removed.<br />

Removal of all the redundant services would further reduce the hazards on site and enhance the<br />

environment. This would be a lengthy task and could threaten the integrity of services that were<br />

still required such that they might have to be re-routed. The cost would be higher and the<br />

program longer than for Options 2 and 3. This option was ranked third, equal to Option 2.<br />

2.1.5 Option 5: Complete Decommissioning/Option 4 Plus Removal of Foundations<br />

and Support Piers<br />

This option involves completely decommissioning the Enriching Unit towers, flare stack, pipe<br />

racks and other redundant buildings and structures including their underground foundations and<br />

2-3 December 2002

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!