2.1.2. PROFESSIONAL FEE AND PAYMENT SCHEDULE<br />
The fee may be quoted on the basis <strong>of</strong> cost <strong>of</strong> the project. The<br />
payment schedule for the services in the scope <strong>of</strong> work, shall be as<br />
per following stages consistent with the work done plus<br />
reimbursable expenses as agreed upon. Any past payments made to<br />
the Consultants for particular project shall be adjusted against the<br />
final amount payable for that project.<br />
2.1.2.1 Payment upto stage-6 shall be made on the Total estimated<br />
cost prepared on the basis <strong>of</strong> BSR in the initial phase <strong>and</strong><br />
final payment be paid as per the actual project cost on<br />
execution including cost <strong>of</strong> all infrastructure other than<br />
l<strong>and</strong> cost<br />
2.1.2.2 Final payment <strong>of</strong> stage-7 be made upon completion <strong>of</strong> the<br />
project<br />
Stage Description Fees Payable<br />
1. On the date <strong>of</strong> signing <strong>of</strong> 5% <strong>of</strong> the total fee payable.<br />
Agreement.<br />
(As mobilisation advance)<br />
2. On submission <strong>of</strong> preliminary 10% <strong>of</strong> the total fee<br />
drawings/designs along with the payable, less payment<br />
estimates based on area basis <strong>and</strong> already made.<br />
acceptance <strong>of</strong> the same by the local<br />
body.<br />
3. (a) On submission <strong>of</strong> final architectural<br />
drawings.<br />
3. (b) During preparation <strong>of</strong> basic<br />
working drawing <strong>and</strong> details<br />
sufficient for preparing item wise<br />
estimate.<br />
3. (c) On submission <strong>of</strong> all the drawing<br />
mentioned in stage 3(a) <strong>and</strong> (b)<br />
above <strong>and</strong> on acceptance <strong>of</strong> the<br />
same by the local body.<br />
4 On submitting detailed<br />
specifications, schedule <strong>of</strong><br />
quantities, detailed design <strong>of</strong><br />
structure <strong>and</strong> services <strong>and</strong> Estimate<br />
<strong>of</strong> costs <strong>and</strong> draft Tender documents<br />
sufficient to invite tender.<br />
5 On submission <strong>of</strong> complete set <strong>of</strong><br />
drawings <strong>and</strong> details sufficient for<br />
the work to commence at site.<br />
20% <strong>of</strong> the total fee<br />
payable, less payment<br />
already made.<br />
25% <strong>of</strong> the total fee<br />
payable, less payment<br />
already made.<br />
30% <strong>of</strong> the total fees<br />
payable, less payment<br />
already made.<br />
50% <strong>of</strong> the total fees<br />
payable, less payment<br />
already made.<br />
60% <strong>of</strong> the total fees<br />
payable, less payment<br />
already made.<br />
17