Charter Court Reception <strong>Refurbishment</strong> Apr 09<br />
A35<br />
SPECIFIC LIMITATIONS ON METHOD/ SEQUENCE/ TIMING<br />
110 SCOPE<br />
General: The limitations described in this section are supplementary to limitations described or<br />
implicit in information given in other sections or on the drawings.<br />
130 METHOD/ SEQUENCE OF WORK<br />
Specific Limitations: Include the following in the programme:<br />
- A fully functioning temporary reception desk must be installed; all existing reception desk<br />
services must be redirected and maintained during the works..<br />
140 SCAFFOLDING<br />
Standing scaffolding: Make available to subcontractors at all times.<br />
160 USE OR DISPOSAL OF MATERIALS<br />
Specific limitations: See site rules.<br />
170 WORKING HOURS<br />
Specific limitations: see site rules.<br />