Lahore Manufacturing<br />

Works<br />

By Haseeb Malik<br />

client. This project was awarded to <strong>Descon</strong> by Turbomach –<br />

Switzerland, who were EPC contractor & supplier of gas<br />

turbine to Saudi Paper Mills. The project has been<br />

commissioned to utmost satisfaction of EPC Contractor &<br />

end user and all the performance guarantees & parameters<br />

have been met.<br />

Water Tube boiler for Packages Kasur Factory<br />

The 200 TPH Water tube boiler for Packages Kasur Factory<br />

has been commissioned. It is a power boiler with 03 stage<br />

super heater steam & a steam flow of 200 Tons per hour, at a<br />

pressure of 96 Barg & temperature of 535°C. It is aligned with<br />

a 41 MW Condensing Extraction type steam turbine provided<br />

by Siemens. The boiler is in operation & generating steam &<br />

power as per client's requirement.<br />

HRSG for Engro Chemicals, Daharki,<br />

under mechanical erection<br />

Supply of Direct Fired Boilers for Bosicor Oil<br />

Pakistan Limited<br />

Bosicor Oil Pakistan Limited have shown their confidence in<br />

<strong>Descon</strong> LMW by placing the order of 3 x 50 TPH Direct Fired<br />

Boilers for their Hub, Balochistan plant. LMW will act as a one<br />

window supplier for these boilers in co-ordination with<br />

<strong>Descon</strong> PC & S, which will be responsible for erection and<br />

installation of boilers. The first boiler will be commissioned by<br />

April, 2010, the second boiler by July, 2010 and the 3rd boiler by<br />

March, 2011.<br />

Boilers Projects underway…<br />

01 x 150 TPH, 48 kg/cm2, 350ºC Heat Recovery Steam<br />

Generator (HRSG) for Engro Chemicals Pakistan Urea<br />

Expansion project is under final erection stages & pre<br />

commissioning activities will commence shortly.<br />

01 x 46 TPH HRSG for Dawood Hercules Chemicals.<br />

Hydotest of boiler block is completed & ready for<br />

shipment.<br />

1 x 145000 lbs/hr, 70 Psi, Water Tube Boiler for OGDCL<br />

at UCH site, is under final stages of mechanical erection<br />

Fresh air firing for 01 x 46 TPH HRSG for<br />

Dawood Hercules Chemicals Limited (DHCL)<br />

DHCL has awarded LMW with additional work for existing<br />

order of 01 x 46 TPH, HRSG. The additional scope includes<br />

Fresh Air Firing System including 02 Ducts, FD Fan with Motor,<br />

FD Fan Damper, Burner, Additional Stop valves (Solenoid),<br />

cable trays & instruments.<br />

Fire Tube Boiler for Proctor & Gamble (P & G)<br />

Pakistan<br />

The project for 1 x 1.5 TPH, 10 Barg, Wet Back, 03 pass, Fire<br />

Tube Boiler has been awarded to LMW by Proctor & Gamble<br />

Pakistan. The scope includes design, fabrication, supply, erection<br />

& commissioning of the boiler. The project is expected to be<br />

completed by October 2009.<br />

HRSG for Saudi Paper Mill<br />

01 x 25 TPH, 16 Barg, Fire tube type HRSG behind a TITAN 130<br />

gas turbine from Turbomach, for Saudi Paper mills, Damam,<br />

KSA has been successfully commissioned and handed over to<br />

HRSG for Saudi Paper Mill, Damam, KSA<br />

Boiler projects completed…<br />

The 08 TPH Boiler for Lahore Plant of Coca Cola has been<br />

successfully commissioned & handed over to client.<br />

Supply of membrane wall for 30 TPH boiler for Vimpex Syria<br />

Supply of Flue gas boiler element for SABIC Hadeed<br />