24.11.2014 Views

Jetty Non Technical Summary - EDF Hinkley Point

Jetty Non Technical Summary - EDF Hinkley Point

Jetty Non Technical Summary - EDF Hinkley Point

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Temporary <strong>Jetty</strong> Applications<br />

<strong>Hinkley</strong> <strong>Point</strong> C - Proposed Nuclear Development<br />

<strong>Non</strong>-<strong>Technical</strong> <strong>Summary</strong><br />

November 2010


[This page is intentionally left blank.]


CONTENTS<br />

Page<br />

1 Introduction 1<br />

2 Project Background 1<br />

2.1 <strong>Hinkley</strong> <strong>Point</strong> C 1<br />

2.2 <strong>Jetty</strong> Development 2<br />

2.3 Site Preparation Works 2<br />

3 Consenting and EIA Requirements 2<br />

4 <strong>EDF</strong> Energy and Nuclear Power 3<br />

5 Project Description 3<br />

5.1 The Application Site 3<br />

5.2 Description of the <strong>Jetty</strong> Development 5<br />

6 Environmental Impact Assessment 9<br />

6.1 Introduction 9<br />

6.2 Consultation 9<br />

6.3 EIA Methodology for the Assessment of Impacts 10<br />

6.4 Consideration of Alternatives 12<br />

6.5 The Environmental Statement 14<br />

7 Overview of Predicted Impacts on the Human and Built Environment 15<br />

7.1 Recreation and Amenity 15<br />

7.2 Transport 20<br />

7.3 Air Quality 22<br />

7.4 Noise and Vibration 24<br />

7.5 Landscape and Visual Amenity 27<br />

7.6 Historic Environment 36<br />

7.7 Socio-economics 38<br />

7.8 Navigation 41<br />

8 Overview of Predicted Impacts on the Natural and Physical Environment 44<br />

8.1 Coastal Hydrodynamics and Geomorphology 44<br />

8.2 Marine Ecology 46<br />

8.3 Terrestrial Ecology and Ornithology 48<br />

8.4 Water Quality 52<br />

8.5 Hydrology and Drainage 54<br />

8.6 Groundwater 55<br />

8.7 Soils and Land Use 57<br />

8.8 Geology and Contaminated Land 58<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development i November 2010


9 Cumulative Effects 59<br />

9.1 Introduction 59<br />

9.2 Cumulative Effects with the Site Preparation Works 59<br />

9.3 Cumulative Effects with the <strong>Hinkley</strong> <strong>Point</strong> C Project 60<br />

9.4 Cumulative Effects with Other Plans and Projects 61<br />

10 Conclusion 62<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development ii November 2010


1 INTRODUCTION<br />

1.1.1 NNB Generation Company Limited (part of <strong>EDF</strong> Energy) is seeking consent from the<br />

Marine Management Organisation (MMO) for the development of a temporary jetty and<br />

associated onshore infrastructure at <strong>Hinkley</strong> <strong>Point</strong>, Somerset (i.e. the ‘jetty<br />

development’). These works are proposed as ‘Preliminary Works’ to facilitate the<br />

construction of a new nuclear power station at <strong>Hinkley</strong> <strong>Point</strong> – <strong>Hinkley</strong> <strong>Point</strong> C.<br />

1.1.2 Consent will be sought by way of a Harbour Empowerment Order (HEO) under the<br />

Harbours Act 1964 (as amended) and licences under the Food & Environment Protection<br />

Act 1985 (i.e. FEPA licences).<br />

1.1.3 In addition to the jetty development, <strong>EDF</strong> Energy is proposing site preparation works to<br />

clear and level the site and provide the necessary infrastructure to facilitate the<br />

construction of <strong>Hinkley</strong> <strong>Point</strong> C. Key features of the site preparation works include site<br />

clearance, earthworks and drainage, which together with the jetty development form<br />

Preliminary Works to the construction of <strong>Hinkley</strong> <strong>Point</strong> C. <strong>EDF</strong> Energy is seeking consent<br />

for the site preparation works by way of grant of planning permission from West<br />

Somerset Council under the Town & Country Planning Act 1990.<br />

1.1.4 Since the jetty development and site preparation works are both Preliminary Works to the<br />

<strong>Hinkley</strong> <strong>Point</strong> C Project they are being treated as distinct but related projects.<br />

1.1.5 <strong>EDF</strong> Energy will separately be seeking a Development Consent Order (DCO) from the<br />

Infrastructure Planning Commission (IPC) to construct and operate <strong>Hinkley</strong> <strong>Point</strong> C.<br />

1.1.6 This document provides a <strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong> (NTS) of the Environmental<br />

Statement (ES) produced in support of the HEO and FEPA licences applications for the<br />

jetty development (the ES can be found in Volumes 2 to 4 inclusive of the submission).<br />

The ES is the formal report of the Environmental Impact Assessment (EIA) of the<br />

potential impacts of the jetty development’s construction, operation, dismantling and<br />

restoration phases (i.e. the phases that would occur if the DCO is granted for the <strong>Hinkley</strong><br />

<strong>Point</strong> C Project). The ES also reports on the potential impacts of the jetty development’s<br />

removal and reinstatement phase (i.e. the phase that would occur if the DCO is not<br />

granted for the <strong>Hinkley</strong> <strong>Point</strong> C Project).<br />

2 PROJECT BACKGROUND<br />

2.1 <strong>Hinkley</strong> <strong>Point</strong> C<br />

2.1.1 The <strong>Hinkley</strong> <strong>Point</strong> C site was nominated for new nuclear build by <strong>EDF</strong> Energy in 2009<br />

and is identified in the Government’s revised draft National Policy Statement (NPS) for<br />

Nuclear Power Generation as one of eight sites in England and Wales that are potentially<br />

suitable for the deployment of nuclear reactors by 2025 (Department for Energy and<br />

Climate Change, October 2010). The NPS makes it clear that all eight sites are needed,<br />

and that it is in the public interest to give priority to sites where new nuclear power<br />

stations can be developed significantly earlier than 2025. <strong>Hinkley</strong> <strong>Point</strong> C is the only site<br />

capable of being developed by 2018, which accords with Government policy on early<br />

deployment (see paragraphs 2.2.1 and 6.4.2 for further details).<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 1 November 2010


2.2 <strong>Jetty</strong> Development<br />

2.2.1 The jetty development is needed early to provide a means for delivery of bulk<br />

construction materials (principally stone, sand and cement) to the construction site at<br />

<strong>Hinkley</strong> <strong>Point</strong>. They are necessary as Preliminary Works to the <strong>Hinkley</strong> <strong>Point</strong> C Project to<br />

speed up the construction programme so that the new power station can be operational<br />

by 2018. This is in line with Government policy that encourages early development of<br />

new nuclear build to assist in meeting the UK’s carbon reduction targets (to help mitigate<br />

climate change) and improve the diversity and security of our electricity supplies.<br />

2.2.2 In addition, early construction of the temporary jetty would mean it would be available to<br />

serve the whole of the construction phase for <strong>Hinkley</strong> <strong>Point</strong> C; thus minimising HGV<br />

construction traffic on local roads.<br />

2.3 Site Preparation Works<br />

2.3.1 The proposed site preparation works involve the following activities: site clearance<br />

(including erection of fencing, vegetation removal, demolition of existing structures, and<br />

creation of alternative footpaths); earthworks (including soil stripping and storage, site<br />

levelling, soil screening / storage for subsequent re-use on site); provision of earth<br />

retaining structures; deep excavations; provision and relocation of drainage infrastructure<br />

(including culverts, outfalls, balancing ponds); the provision and operation of plant and<br />

machinery (including plant for concrete batching); site establishment works (including the<br />

provision of construction compounds and associated (including layover) facilities, car<br />

parks, haulage roads, site access points and roundabouts, and laying, replacement<br />

and/or diversion of utilities); and other associated works. In the event that <strong>Hinkley</strong> <strong>Point</strong> C<br />

is not consented, all structures would be removed and the site reinstated. Collectively<br />

these works are necessary to enable the earliest possible completion of construction of<br />

<strong>Hinkley</strong> <strong>Point</strong> C following the grant of the DCO.<br />

2.3.2 Prior to commencing the site preparation works and, where relevant, subject to obtaining<br />

separate planning permission, a small package of enabling works is also to be initiated in<br />

2010 to facilitate the site preparation works. These works would include remediation<br />

works to remove known areas of asbestos contamination within an existing spoil mound<br />

on site and in other areas of made ground located within the eastern part of the<br />

application site (see Section 8.8).<br />

3 CONSENTING AND EIA REQUIREMENTS<br />

3.1.1 As identified above, <strong>EDF</strong> Energy is seeking a HEO to authorise the jetty development<br />

and FEPA licences to authorise discrete aspects of the jetty development’s construction.<br />

Both of the consent application procedures include provisions for EIA in accordance with<br />

the requirements of European Community Directive 85/337/EEC (as amended) On the<br />

Assessment of the Effects of Certain Public and Private Projects on the Environment<br />

(herein referred to as the ‘EIA Directive’). In relation to the HEO, the EIA Directive is<br />

transposed into national law by the Harbour Works (Environmental Impact Assessment)<br />

Regulations 1999 (as amended in 2000 and 2009). In relation to FEPA licences, the EIA<br />

Directive is transposed into national law by the Marine Works (Environmental Impact<br />

Assessment) Regulations 2007.<br />

3.1.2 Through a ‘screening’ process, the MMO has confirmed that the jetty development is<br />

subject to EIA under the provisions of the EIA Directive and both of the aforementioned<br />

Regulations because it, or elements of it, would either qualify as facilitating and relating to<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 2 November 2010


a nuclear power station development, or qualify in its own right constitute a port<br />

development. Accordingly, the jetty development is subject to EIA.<br />

3.1.3 Since the jetty development would be situated within and adjacent to a number of<br />

internationally important nature conservation sites (i.e. the Severn Estuary Special Area<br />

of Conservation (SAC), Special Protection Area (SPA) and Ramsar site), it would need to<br />

comply with the measures set out in Council Directive (1992/43/EC) On the conservation<br />

of natural habitats and wild flora and fauna (herein referred to as the ‘Habitats Directive’),<br />

which is transposed into UK law through the Conservation of Habitats and Species<br />

Regulations 2010.<br />

3.1.4 In addition, the jetty development includes a number of activities that would require<br />

separate legal consents from a number of different regulatory bodies, potentially including<br />

land drainage consents, discharge consents, waste management exemptions / licences,<br />

and protected species licences. Prior to commencement of these activities, <strong>EDF</strong> Energy<br />

will ensure that it has secured the necessary consents and that any relevant works are<br />

undertaken in full compliance with legal requirements and best practice.<br />

4 <strong>EDF</strong> ENERGY AND NUCLEAR POWER<br />

4.1.1 Électricité de France (<strong>EDF</strong>) is one of the world’s largest energy companies and the<br />

world’s largest operator of nuclear power plants, with 58 operational plants in France and<br />

a further one under construction at Flamanville in Normandy. <strong>EDF</strong> has a strong safety<br />

track record in the operation of nuclear power stations and safety is at the heart of the<br />

design and operating procedures for all its nuclear plants. Within the UK, <strong>EDF</strong> operates<br />

via its UK subsidiary – <strong>EDF</strong> Energy – and currently owns and operates eight nuclear<br />

power stations, including Sizewell B in Suffolk.<br />

4.1.2 <strong>EDF</strong> Energy has indicated publicly for over three years that it would be interested in<br />

investing in a new generation of nuclear plants in the UK and that it is confident that new<br />

plants can be built and run safely and economically, without subsidy.<br />

5 PROJECT DESCRIPTION<br />

5.1 The Application Site<br />

5.1.1 This section describes the jetty development and the characteristics of the application<br />

site and surrounding area that it could affect. The application site (see Figure 1) is<br />

located on the northern coastline of West Somerset, 25km to the east of Minehead and<br />

12km to the north-west of Bridgwater, and falls within the parish of Stogursey. The<br />

onshore component of the application site falls within the land under the control of <strong>EDF</strong><br />

Energy, adjacent and to the west of the existing <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex.<br />

The offshore component of the application site extends into Bridgwater Bay, part of the<br />

Severn Estuary.<br />

5.1.2 Immediately to the east of the application site are the <strong>Hinkley</strong> <strong>Point</strong> A and <strong>Hinkley</strong> <strong>Point</strong> B<br />

nuclear power stations (i.e. the <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex). <strong>Hinkley</strong> <strong>Point</strong> A<br />

operated between 1965 and 2000 and is currently undergoing decommissioning by the<br />

Nuclear Decommissioning Authority (NDA). <strong>Hinkley</strong> <strong>Point</strong> B, owned by <strong>EDF</strong> Energy, has<br />

operated since 1976 and is scheduled to continue generating until at least 2016.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 3 November 2010


Figure 1 <strong>Jetty</strong> Development Application Site<br />

5.1.3 The topography of the application site and the surrounding land is typical of that in the<br />

wider locality, comprising mostly open, gently rolling, mixed lowland farmland with a<br />

series of east-west trending ridges. Ground elevations range from approximately 10m to<br />

35m Above Ordnance Datum (AOD). The main access road serving <strong>Hinkley</strong> <strong>Point</strong> is the<br />

C182, which is an unclassified road that runs south from <strong>Hinkley</strong> <strong>Point</strong> through the village<br />

of Cannington and then joins the A39 to the south of the village (see Figure 8). The A39<br />

is a local strategic east-west road with Bridgwater to the east and Minehead to the west.<br />

Within Bridgwater the A39 joins the A38, which is also a local strategic road that links to<br />

the M5 motorway north and south of Bridgwater at Junctions 23 and 24 respectively.<br />

5.1.4 The application site contains a network of public rights of way (PRoW). It includes a<br />

portion of the West Somerset Coast Path (Footpath WL 23/95), which is a 25km linear<br />

walk and a resource of national importance. The network of existing PRoW is shown on<br />

Figure 2. One of the main routes to south of the application site – known as Green Lane<br />

(Footpath WL 23/110) - is an east-west track that runs along a ridge with significant<br />

nature conservation, heritage and landscape value.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 4 November 2010


Figure 2 Existing Public Rights of Way<br />

5.2 Description of the <strong>Jetty</strong> Development<br />

5.2.1 The jetty development would be constructed and, assuming a DCO is granted for the<br />

<strong>Hinkley</strong> <strong>Point</strong> C Project, operated during construction of <strong>Hinkley</strong> <strong>Point</strong> C. It would then be<br />

dismantled and the site restored where it lies outside of the area of permanent works<br />

associated with <strong>Hinkley</strong> <strong>Point</strong> C. However, if a DCO is not granted for the <strong>Hinkley</strong> <strong>Point</strong><br />

C Project, the constructed jetty would not be operated, but would be removed and the<br />

land reinstated back to its current form.<br />

5.2.2 The jetty is proposed as a two-staged structure that can be constructed in a manner that<br />

accommodates the emerging transport demands of the <strong>Hinkley</strong> <strong>Point</strong> C Project, so that<br />

the first stage could operate alone without the second stage. However, it is expected that<br />

the two stages would in fact be built as one structure under one construction programme<br />

(i.e. stage two would be constructed once stage one is in place without any interval).<br />

This is reflected in the HEO application, which proposes the jetty development in its<br />

entirety, and is assessed in the ES.<br />

5.2.3 The jetty development comprises the following offshore infrastructure, as shown in<br />

Figures 3 and 4:<br />

• a jetty bridge constructed from vertical tubular piles supporting the deck;<br />

• a jetty head constructed from vertical tubular piles supporting horizontal cross-heads<br />

and a deck, and incorporating mooring infrastructure (e.g. dolphins);<br />

• a berthing pocket dredged alongside the jetty head to accommodate vessels at<br />

various states of the tide;<br />

• materials handling and conveyance equipment on the jetty head and along jetty<br />

bridge;<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 5 November 2010


• a roadway along the jetty bridge; and<br />

• aids to navigation.<br />

5.2.4 Indicative visual representations of the jetty are shown in Figure 5.<br />

Figure 3 Plan of <strong>Jetty</strong> Bridge and <strong>Jetty</strong> Head<br />

5.2.5 The jetty development comprises the following onshore infrastructure as shown in Figure<br />

6:<br />

• an aggregates storage area comprising stockpile areas for stone and sand, and silos<br />

for cement and/or cement replacement products, and including a surface water<br />

drainage system with a water management zone for the treatment and regulation of<br />

discharges;<br />

• a rock extraction area and two soil storage areas to facilitate construction of the<br />

onshore components;<br />

• a service road providing access to the aggregates storage area, the rock extraction<br />

area and, temporarily for the purposes of construction, to the foreshore; and<br />

• materials handling and conveyance equipment from the jetty bridge to the<br />

aggregates storage area.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 6 November 2010


Figure 4 Detailed Plan of <strong>Jetty</strong> Head<br />

Figure 5 Photomontages of the <strong>Jetty</strong> - Looking West (top) and Looking East<br />

(bottom)<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 7 November 2010


Figure 6 Temporary <strong>Jetty</strong> Development – Onshore Development<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works <strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 8 November 2010


6 ENVIRONMENTAL IMPACT ASSESSMENT<br />

6.1 Introduction<br />

6.1.1 Environmental impact assessment (EIA) is a process that must be followed for certain<br />

types of development before they are granted consent. In this instance, the MMO has<br />

determined that the jetty development is a project listed under Annex I to the EIA<br />

Directive, as transposed into national law by the Harbour Works (EIA) Regulations and<br />

the Marine Works (EIA) Regulations.<br />

6.1.2 The MMO’s Scoping Opinion (dated 4 June 2010) included a Screening Opinion which<br />

identified that the jetty development, or elements of it (i.e. regulated activities), would<br />

either qualify as facilitating and relate to the description of the development of a nuclear<br />

power station / nuclear reactor, or would in its own right constitute a port development<br />

itself within Annex I.<br />

6.2 Consultation<br />

6.2.1 Consultation for the jetty development has been undertaken during the consultation<br />

phase for the <strong>Hinkley</strong> <strong>Point</strong> C Project. This consultation has been with regulators,<br />

statutory government agencies, non-governmental organisations and the public<br />

throughout the EIA process for the <strong>Hinkley</strong> <strong>Point</strong> C Project and, also, specifically for the<br />

Preliminary Works, including the jetty development. <strong>EDF</strong> Energy has had ongoing<br />

informal engagement with key statutory consultees and other interested parties, which<br />

has informed the preparation of its development proposals for the <strong>Hinkley</strong> <strong>Point</strong> C<br />

Project, dating back to 2008. Key milestones include the consultation programme<br />

coordinated in the autumn and winter of 2008 in support of the EIA scoping process and,<br />

in early 2009, to assist the Government’s Strategy Siting Assessment process for new<br />

nuclear power stations. Generic consultation has included the consultation undertaken<br />

as part of the DCO application process for the <strong>Hinkley</strong> <strong>Point</strong> C Project. The primary aim<br />

of the pre-application consultation is to engage early with local authorities, statutory<br />

consultees, local communities and the general public in order to:<br />

• allow members of the local community to influence the way projects are developed<br />

by providing feedback on potential options, providing them with an opportunity to<br />

shape the way in which their community develops;<br />

• assist in a better understanding of the proposed project and the implications at a<br />

local scale and resolve misunderstandings or concerns at an early stage;<br />

• obtain important information about the economic, social and environmental impacts<br />

of a scheme from consultees, to help identify project options which are unsuitable<br />

and not worth developing further;<br />

• enable potential mitigating measures to be considered and, in some cases, built into<br />

the project before an application is submitted; and<br />

• identify ways in which the project could support wider strategic or local objectives,<br />

where appropriate.<br />

6.2.2 <strong>EDF</strong> Energy undertook the first formal stage of consultation from November 2009 to<br />

February 2010. The consultation at Stage 1 set out the initial proposals and options for<br />

the <strong>Hinkley</strong> <strong>Point</strong> C Project. These initial proposals were presented in a consultation<br />

document together with an Environmental Status Report setting out the preliminary<br />

environmental information relating to the proposed development. Stage 1 consultation<br />

provided an early opportunity for statutory and non-statutory consultees to comment on<br />

the scheme whilst development proposals were still being worked up. In addition, it also<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 9 November 2010


provided a specific opportunity for stakeholders to comment on the proposals for<br />

Preliminary Works, including the jetty development.<br />

6.2.3 <strong>EDF</strong> Energy began the second formal stage of consultation in July 2010. This stage is<br />

consulting on the preferred proposal for the <strong>Hinkley</strong> <strong>Point</strong> C Project (and this proposal<br />

includes the project’s Preliminary Works, including the jetty development). The<br />

consultation documents include a detailed Environmental Appraisal. The Environmental<br />

Appraisal was not an ES, but was designed to enable consultees to give an informed<br />

response to the likely environmental effects of the <strong>Hinkley</strong> <strong>Point</strong> C Project based on the<br />

current information compiled on the project by that stage. The consultation extended into<br />

October 2010. Further development of the detail of jetty development undertaken since<br />

July 2010 (when Stage 2 consultation began) has been progressed in consultation with<br />

key statutory consultees and local residents.<br />

6.2.4 Consultation has also been undertaken through the Marine Authorities Liaison Group<br />

(MALG). The MALG was formed in early 2009 and generally met on a monthly basis<br />

until April 2010. The MALG comprises representatives from regulators and advisory<br />

agencies with an interest in the <strong>Hinkley</strong> <strong>Point</strong> C Project, particularly from a marine and<br />

coastal perspective, including the Marine Management Organisation (MMO), the Centre<br />

for Environment, Fisheries and Aquaculture Science (Cefas), West Somerset Council,<br />

Sedgemoor District Council including the Port of Bridgwater, Somerset County Council,<br />

the Environment Agency, English Heritage, Natural England and the Countryside Council<br />

for Wales (CCW). The purpose of the MALG meetings is to advise the attendees of the<br />

latest concepts and developments associated with the <strong>Hinkley</strong> <strong>Point</strong> C Project and to<br />

receive their feedback. Many of the MALG meetings have provided attendees with<br />

information about the jetty (e.g. alternative options for the jetty’s position at <strong>Hinkley</strong> <strong>Point</strong>,<br />

alternative options for the jetty’s infrastructure design) and its potential impacts on the<br />

environment (e.g. construction noise, habitat loss, footpath closures). Comments<br />

received from attendees have been fed into the EIA process for the jetty development<br />

during scoping and impact assessment.<br />

6.2.5 Other consultation specifically for the jetty development outside of the MALG has<br />

included direct consultation with various parties and in relation to specific issues relating<br />

to the various environmental parameters of interest.<br />

6.3 EIA Methodology for the Assessment of Impacts<br />

6.3.1 At the impact assessment stage, the potentially beneficial and adverse impacts of the<br />

jetty development are identified and assessed with reference to the existing environment.<br />

Environmental impacts have been predicted with reference to definitive standards and<br />

legislation where available. Where it has not been possible to quantify impacts,<br />

qualitative assessments have been carried out based on available knowledge and<br />

professional judgement. Where uncertainties, limitations or assumptions exist, they have<br />

been noted in the ES.<br />

6.3.2 The significance of predicted impacts has been determined by reference to impact<br />

criteria for each assessment topic. Broadly, the significance of the impact gives<br />

consideration to the magnitude of the potential impact, the value and sensitivity of the<br />

receiving environment and the likelihood of the impact occurring.<br />

Impact Magnitude<br />

6.3.3 Magnitude refers to the ‘size’ or ‘amount’ of an impact. It is a function of other aspects,<br />

such as the impact’s extent (i.e. the area over which the impact occurs), duration (i.e. the<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 10 November 2010


time for which the impact is expected to last prior to recovery or replacement of the<br />

resource or feature), likelihood (i.e. the chance that the impact will occur) and reversibility<br />

(i.e. an irreversible (permanent) impact is one from which recovery is not possible within<br />

a reasonable timescale or for which there is no reasonable chance of action being taken<br />

to reverse it). Where possible, environmental impacts have been predicted with reference<br />

to quantified baseline conditions, definitive standards and legislation; where it is not<br />

possible to quantify impacts, qualitative assessments have been carried out based on<br />

available knowledge and professional judgement.<br />

Value and Sensitivity<br />

6.3.4 This is a composite criterion, where the ‘value’ of the receptor (the individual or feature<br />

that the impact could affect) will be a function of a variety of factors (e.g. biodiversity<br />

value, social/community value and economic value) and can be determined within a<br />

defined geographical context. In some instances, the inherent value of a receptor will<br />

have been recognised by the expert community and Governmental bodies by means of<br />

designation. Irrespective of recognised value, all receptors will exhibit a greater or lesser<br />

degree of ‘sensitivity’ to the changes brought about by the proposed development. The<br />

precise form which these indicators take in each case will vary according to subject<br />

matter, but by following the generic methodology adopted, assessors have ensured that<br />

these factors have been taken into account within their subject areas.<br />

Impact Assessment Matrix and Impact Significance<br />

6.3.5 Using the magnitude of the impact together with the value and sensitivity of the<br />

environmental receptor, the degree of significance of an impact can be determined. To<br />

assist this process, an impact assessment matrix (IAM) provides a mechanism for initially<br />

assessing impact significance (see Table 1).<br />

Table 1 Impact Assessment Matrix<br />

Magnitude<br />

Values and Sensitivity of Receptor<br />

Very low Low Medium High<br />

Very Low Negligible Negligible Minor Minor<br />

Low Negligible Minor Minor Moderate<br />

Medium Minor Minor Moderate Major<br />

High Minor Moderate Major Major<br />

6.3.6 It should be noted that while the matrix provides a good framework for the consistent<br />

assessment of impacts across all parameters, there is still an important role for expert<br />

judgement and further objective assessment to play in moderating the significance rating<br />

process.<br />

6.3.7 Defining the significance rating of the impact is the most important step in the EIA<br />

process since it is this rating which provides a strong indication as to whether mitigation<br />

may be required and also whether, following the use of mitigation measures, identified<br />

impacts may be reduced to environmentally acceptable levels (or not).<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 11 November 2010


Mitigation<br />

6.3.8 In this EIA, those impacts assessed as being of potentially greater than minor adverse<br />

significance (i.e. impacts of moderate and major adverse significance) are the focus of<br />

mitigation, although every attempt has been taken to avoid, reduce and mitigate impacts<br />

through design change and adoption of best practice.<br />

6.3.9 The preferred hierarchy of mitigation is prevention first, then minimisation and, only as a<br />

last resort, compensation or remediation. The definitions of these are as follows:<br />

• prevention: avoid, relocate, modify the design and / or do not carry out the<br />

development;<br />

• reduction: introduce screens / blinds, modify design, alter technology, reduce size<br />

and scale of development etc; and<br />

• compensation or remediation: compensation to provide like-for-like replacement for<br />

any lost environmental elements (e.g. open green spaces, public facilities, wildlife<br />

area etc).<br />

6.3.10 Where possible, mitigation has been built into the jetty development (e.g. through the<br />

options chosen and through its design) and may be accepted, offset by other benefits of<br />

the jetty development or managed by the imposition of conditions within the HEO and/or<br />

on any licences granted.<br />

Residual Impacts<br />

6.3.11 The final step in the EIA process is the assessment of the residual impacts (i.e. those<br />

impacts remaining after the implementation (where necessary) of the proposed mitigation<br />

measures). Residual impacts are rated in accordance with the definitions of significance<br />

provided above. In this EIA, residual impacts assessed as minor or negligible are<br />

considered to be insignificant. More significant impacts may be accepted, offset by other<br />

benefits of the jetty development, or managed by the imposition of conditions within the<br />

HEO and / or on any licences granted.<br />

Cumulative Effects Assessment<br />

6.3.12 Cumulative effects are the additive and interactive effects that can arise from the jetty<br />

development cumulatively with other plans and projects. The EIA considers the jetty<br />

development cumulatively with the site preparation works, the <strong>Hinkley</strong> <strong>Point</strong> C Project,<br />

and other plans and projects which overlap in time and space (as regards those<br />

receptors that potentially could be affected).<br />

6.4 Consideration of Alternatives<br />

6.4.1 In accordance with the EIA Directive, an ES should outline the main alternatives<br />

considered by the applicant and present the main reasons for selecting the application<br />

site and design.<br />

No Development Alternative<br />

6.4.2 Proposed as Preliminary Works, the jetty development would allow <strong>EDF</strong> Energy to meet<br />

the target date of 2018 for the start of nuclear power generation by enabling the<br />

construction of <strong>Hinkley</strong> <strong>Point</strong> C to begin as early as possible after grant of the DCO. The<br />

2018 target is clearly set out in the draft National Policy Statements related to energy and<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 12 November 2010


is designed to meet the Government’s objective of early deployment of new nuclear<br />

power stations to help provide security of electricity supplies in the period post-2015.<br />

6.4.3 If the jetty development is not undertaken in 2011-2012 as Preliminary Works to the<br />

<strong>Hinkley</strong> <strong>Point</strong> C Project, there would be a delay of approximately one year to the<br />

programme for construction and operation of <strong>Hinkley</strong> <strong>Point</strong> C. <strong>EDF</strong> Energy estimates, on<br />

a conservative basis, that the operation of <strong>Hinkley</strong> <strong>Point</strong> C would save some 12 million<br />

tonnes of CO 2 per year (in comparison with efficient fossil fuel based generation plant).<br />

This saving of CO 2 emissions would be equivalent to taking four million cars off the road.<br />

6.4.4 Proposed as Preliminary Works, the jetty development would also facilitate construction<br />

of <strong>Hinkley</strong> <strong>Point</strong> C in a way that significantly reduces the use of HGVs to import<br />

construction materials to site via the local public highway network, including the roads to<br />

<strong>Hinkley</strong> <strong>Point</strong> through Cannington and possibly through Bridgwater. Without the jetty<br />

development, a total of approximately two million tonnes of bulk construction materials for<br />

concrete production (i.e. stone, sand and cement) would have to be imported by road (or<br />

by a combination of rail and road). Based on a 15 tonnes payload, the importation of<br />

materials by road instead of via the jetty would add a total of approximately 260,000 HGV<br />

movements on the local highway network over <strong>Hinkley</strong> <strong>Point</strong> C’s construction period.<br />

Depending on the rate of demand for bulk construction materials over the course of<br />

<strong>Hinkley</strong> <strong>Point</strong> C’s construction period, the jetty development would offset between 245<br />

and 436 HGV movements per day.<br />

<strong>Jetty</strong> Location at <strong>Hinkley</strong> <strong>Point</strong><br />

6.4.5 Compared to the alternatives (i.e. the redevelopment of Combwich Wharf and possible<br />

use of facilities at Dunball Wharf), the temporary jetty option would be the most<br />

appropriate option and, therefore, the preferred option for the delivery of bulk materials<br />

because it would have least effect on local communities (particularly those along the<br />

route between Combwich Wharf and <strong>Hinkley</strong> <strong>Point</strong>).<br />

<strong>Jetty</strong> Position at <strong>Hinkley</strong> <strong>Point</strong><br />

6.4.6 Compared to the alternatives (i.e. an eastern jetty option), the western jetty option is the<br />

preferred option primarily because it has a smaller footprint and, therefore, a smaller<br />

scale of impacts on the designated sites (except the Lilstock to Blue Anchor SSSI),<br />

marine ecological receptors and archaeological receptors. In addition, it is more likely to<br />

avoid the Corallina turfs present on the foreshore. Unlike the eastern option it would, in<br />

part, cross – and partially obscure – the exposures in the Lilstock to Blue Anchor SSSI.<br />

However, the affected exposures are replicated and are accessible elsewhere in the<br />

SSSI, so there would be no physical loss of geological exposures or damage to the<br />

resource due to the works.<br />

<strong>Jetty</strong> Design<br />

6.4.7 Compared to the alternative designs, the two-staged jetty option is preferred because it<br />

offers greater operational flexibility. In terms of its environmental impact it offers the<br />

‘middle ground’. In the marine environment, its footprint is slightly larger than one option<br />

and slightly smaller than the other, but its operational flexibility offers more opportunity<br />

than the one option and a similar opportunity to another for reducing traffic, air quality<br />

and noise impacts. Overall the two-staged option is preferred on the basis of its<br />

expected operational performance and environmental impact.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 13 November 2010


Disposal of Dredged Material<br />

6.4.8 Compared to the alternatives (i.e. other offshore disposal options, beneficial use options<br />

and onshore disposal options), the disposal of dredged material at the Cardiff Grounds is<br />

the preferred option because the dredged material arising from the berthing pocket is not<br />

anticipated to be too contaminated for offshore disposal, and given the logistical<br />

difficulties and associated environmental issues, onshore disposal options were not<br />

considered viable.<br />

6.5 The Environmental Statement<br />

6.5.1 In accordance with the EIA Directive and aforementioned EIA Regulations, the ES<br />

reports on the potential environmental impacts arising during the construction, operation<br />

and dismantling / restoration phases of the jetty development. The ES also reports in the<br />

potential environmental impacts arising during the removal / reinstatement phase of the<br />

jetty development, should the DCO not be granted and, therefore, removal of the jetty<br />

development and reinstatement of the land be required.<br />

6.5.2 The ES that this NTS accompanies contains the following information:<br />

• a description of the proposed temporary jetty development and an outline of the main<br />

alternatives considered;<br />

• a description of the existing (baseline) environment that the jetty development has<br />

the potential to impact upon (both directly and indirectly);<br />

• definitions of the relevant study areas for the EIA;<br />

• prediction of potential impacts (during the jetty development’s various phases) on the<br />

existing environment and assessment of their significance;<br />

• a description of any mitigation measures proposed to avoid, reduce or off-set<br />

potential impacts; and<br />

• an indication of any difficulties (e.g. uncertainties, assumptions and limitations)<br />

encountered during the preparation of the ES.<br />

6.5.3 The ES contains the specific assessment methodologies adopted, the baseline<br />

environmental conditions, and the technical assessments of the potential impacts<br />

associated with the jetty development. Assessments have been made for the following<br />

environmental parameters:<br />

• recreation and amenity;<br />

• transport;<br />

• air quality;<br />

• noise and vibration;<br />

• landscape and visual amenity;<br />

• archaeology and cultural heritage;<br />

• socio-economics;<br />

• coastal hydrodynamics and geomorphology;<br />

• marine ecology;<br />

• terrestrial ecology and ornithology;<br />

• water quality;<br />

• hydrology and drainage;<br />

• groundwater;<br />

• soils and land use; and<br />

• geology and contaminated land.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 14 November 2010


6.5.4 The ES also contains an assessment of cumulative effects.<br />

6.5.5 An overview of the findings of the ES is provided in the subsequent sections of this NTS.<br />

These are summarised as predicted impacts on the human and built environment (e.g.<br />

recreation, noise, air quality and traffic) and then impacts on the natural environment<br />

(e.g. ecology, water quality and soils). A brief description of the existing environmental<br />

conditions is provided, followed by a summary of the main impacts that would arise from<br />

the jetty development. The key mitigation measures to avoid, reduce or off-set impacts<br />

are also summarised and the residual impacts are discussed. Where significant residual<br />

impacts are predicted, these are summarised in tables at the end of each section.<br />

7 OVERVIEW OF PREDICTED IMPACTS ON THE HUMAN AND BUILT<br />

ENVIRONMENT<br />

7.1 Recreation and Amenity<br />

Existing Environment<br />

7.1.1 The site and wider study area is well served by a network of public footpaths, including:<br />

• a portion of the West Somerset Coast Path, a resource of national importance, which<br />

links the River Parrett Trail at Steart in Bridgwater Bay with the South West Coast<br />

Path National Trail at Minehead;<br />

• a number of smaller, interconnecting footpaths across the site that are generally<br />

aligned north to south and east to west, with a length of 20km of PRoW within 1km of<br />

the site and 60km of PRoW within 3km of the site.<br />

7.1.2 Surveys have been carried out to determine the use of PRoW in and around the<br />

application site. The West Somerset Coast Path, which runs along the northern<br />

boundary of the application site, is used most often during the summer months and<br />

holiday periods. The data provides approximate visitor numbers each month along the<br />

West Somerset Coast Path between 2006 and 2009, with counts taken from the junction<br />

of PRoW WL 23/56 and WL 23/95 (see Figure 2). The highest number of users (410)<br />

was recorded in August 2008 for this stretch of path.<br />

7.1.3 In terms of the remainder of the site’s PRoW, the survey carried out in 2009 identified<br />

that the majority of users appear to be local residents (70% of those surveyed lived less<br />

than 3km from the study area). However, visitors who reside significant distances from<br />

the area (e.g. live in excess of 25km from the study area) were also recorded using the<br />

PRoW.<br />

7.1.4 There are no bridleways within the application site boundary, though a number of<br />

bridleways are located in the surrounding area. Due to the limited availability of public<br />

bridleways, the majority of this equestrian activity takes place on private land.<br />

7.1.5 Within the Severn Estuary and Bristol Channel, there are a large number of sailing,<br />

cruising, boating and yacht clubs. However, no formal boating and/or sailing activities or<br />

events are known to occur off <strong>Hinkley</strong> <strong>Point</strong> due to the insufficient depth of water at this<br />

location.<br />

7.1.6 An Excepted Area is located on the foreshore at <strong>Hinkley</strong> <strong>Point</strong>, stretching from Stolford in<br />

the east, past <strong>Hinkley</strong> <strong>Point</strong>, to the boundary of the Bridgwater Bay NNR in the west. The<br />

Excepted Area can be used for shooting by any member of the British Society for<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 15 November 2010


Shooting and Conservation (BASC). Consultation with Natural England indicates that the<br />

Excepted Area is used intermittently by between 5-10 people during the season.<br />

7.1.7 There are no existing sports and recreation facilities (including playing fields, sports clubs<br />

and stadiums) within a 1km radius of the application site boundary, although there are<br />

such facilities within the wider study area.<br />

7.1.8 In addition, there are no areas of open access land within the application site. Wick Moor<br />

Common lies to the south-east of the application site and extends eastwards. A search<br />

of Natural England’s Common Rights of Way (CRoW) database indicates that a further<br />

series of commons are located over 1km from the application site.<br />

7.1.9 There are no areas of public open space, such as formal parks and gardens, within the<br />

application site. The nearest formal areas of public open space are in excess of 4km<br />

from the application site (i.e. Combwich Village Green and Combwich Common).<br />

7.1.10 Walking, wildfowling, fishing, bird watching and horse riding are the predominant sporting<br />

and recreational activities undertaken in close proximity to or within the study area.<br />

However, given the limited use of the Common Land and foreshore by any formal and<br />

informal recreational activities, and given the availability of similar recreational resource<br />

in the surrounding area, local importance is ascribed.<br />

Main Predicted Impacts<br />

7.1.11 During the construction of the jetty development, the aggregates storage area would be<br />

enclosed by a 2.14m high chain link security fence. Hence the first phase of construction<br />

(the earthworks) would result in the obstruction, for health and safety reasons, of a<br />

number of PRoW until the works are completed, which is anticipated to be around 3 to 4<br />

months from commencement (see Figure 7). Following completion of the first phase of<br />

construction, the access road would again be passable and, consequently, certain PRoW<br />

would be re-opened while the rest would remain closed for the duration of the works<br />

(expected to 14 to 15 months). In addition, the elevated jetty would be constructed over<br />

the route of the West Somerset Coast Path and this would also be obstructed.<br />

7.1.12 Without mitigation, the obstruction of the affected PRoW is considered to represent a<br />

high magnitude disturbance because the right of passage would be removed. The<br />

affected PRoW network (excluding the section of the West Somerset Coast Path) is a<br />

resource of local importance and, consequently, an impact of moderate adverse<br />

significance is predicted.<br />

7.1.13 The obstruction of the West Somerset Coast Path (WL 23/95) is considered to represent<br />

a high magnitude effect given the loss of right of access along the coast, albeit for a<br />

reasonably short period of time. Given the national importance of this asset, without<br />

mitigation, a short- to medium-term impact of major adverse significance is assessed.<br />

7.1.14 The jetty development would also result in an increase in noise, dust and visual<br />

disturbance due to the movement and activities of construction personnel, plant and<br />

equipment; all of which could have an adverse impact on the amenity value of the PRoW<br />

close to the location of such activities and equipment for the duration of works. These<br />

impacts are considered in relevant sections on air quality, noise and vibration, and<br />

landscape and visual amenity herein.<br />

7.1.15 Impacts to other sports and recreation facilities, open access land, or public open space<br />

are not expected to be significant during the jetty development.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 16 November 2010


7.1.16 Although the foreshore is an Excepted Area where wildfowling can and does take place,<br />

its use is very low in frequency and by a small number of people, representing a locally<br />

important resource. The scale of the area obstructed in the foreshore (which would be<br />

limited to temporary obstructions to small areas) is very small (a minimum of 1.4ha to a<br />

maximum of 6ha) in comparison to the available area (the Excepted Area covers 314ha,<br />

and consequently no more than 2% would be obstructed). Consequently, a minor<br />

adverse impact is predicted.<br />

7.1.17 During any interim period between completion of the construction phase and operation of<br />

the jetty, there would be no activities on site that would result in emissions of dust or<br />

other air quality deterioration. Therefore, there would be no change in the background air<br />

quality environment and, hence, no impact is predicted to occur to users of the PRoW.<br />

7.1.18 With respect to the jetty development alone, those PRoW that would be obstructed<br />

during the latter phase of construction (i.e. following the earthworks) would continue to be<br />

obstructed during the operational phase and a moderate adverse impact would arise in<br />

the medium-term (the combined impact of the site preparation works and the jetty<br />

development is considered in Section 9 below). However, PRoW access would be<br />

available under the jetty and there would be no obstruction to the West Somerset Coast<br />

Path.<br />

7.1.19 The dismantling and restoration phases of the jetty development would result in the<br />

obstruction of the same PRoW affected during construction until the structures are taken<br />

off site. Following the dismantling and restoration works, the PRoW located within the<br />

jetty development’s application site would be re-opened.<br />

7.1.20 The removal and reinstatement of the jetty development, if required (i.e. if the DCO for<br />

the <strong>Hinkley</strong> <strong>Point</strong> C Project is not granted) would have similar impacts to those predicted<br />

for the jetty development’s dismantling and restoration phase.<br />

Mitigation<br />

7.1.21 Following discussions with local residents, equestrians and Somerset County Council<br />

regarding the Preliminary Works, it was agreed that alternative PRoW would be provided<br />

during the works to maintain the connectivity and routes of those PRoW that would be<br />

obstructed; thus maintaining a linked network of routes around the site. The alternative<br />

routes are shown in Figure 7 and would be used by those following the West Somerset<br />

Coast Path. Where alternative PRoW cross field boundaries, gates (including selfclosing<br />

pedestrian gates) would be constructed and appropriate access for disabled<br />

persons would be catered for as far as practicable.<br />

7.1.22 Mitigation measures would also be put in place to avoid or reduce the magnitude and<br />

probability of dust, noise and visual disturbance (as identified in the relevant sections on<br />

air quality, noise and vibration, and landscape and visual).<br />

7.1.23 Should the DCO not be granted for the <strong>Hinkley</strong> <strong>Point</strong> C Project, all PRoW routes<br />

disrupted by the jetty development would be reinstated and upgraded where practicable<br />

through reinstatement of the landform and landscape.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 17 November 2010


Figure 7 Public Rights of Way Closures and Alternative Routes<br />

Residual Impacts<br />

7.1.24 The magnitude of impacts on PRoW would be significantly reduced by providing users<br />

with alternative routes, thereby maintaining a right of passage as well as connectivity<br />

within the surrounding PRoW network. Specifically, the impact associated with<br />

obstruction to PRoW would be reduced to a minor level for all affected routes. Table 2<br />

below represents a summary of the potentially significant impacts on recreation and<br />

amenity that would remain after the mitigation measures discussed above have been put<br />

into practice.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 18 November 2010


Table 2 <strong>Summary</strong> Significant Impacts on Recreation and Amenity<br />

Description of Impact Impact Mitigation Measure Residual Impact<br />

Construction Phase<br />

Disturbance to<br />

users of public<br />

rights of way<br />

Minor adverse to<br />

moderate adverse<br />

(noise) temporary<br />

Negligible adverse<br />

to major adverse<br />

(visual)<br />

Adherence to best<br />

practice noise<br />

minimisation<br />

Landscaping and<br />

planting<br />

Negligible adverse<br />

to moderate<br />

adverse (noise)<br />

temporary<br />

Negligible to major<br />

adverse (visual)<br />

Negligible to major<br />

adverse (visual –<br />

during interim<br />

period)<br />

Negligible to major<br />

adverse (visual –<br />

during interim<br />

period)<br />

Disturbance to<br />

sports and<br />

recreation facilities,<br />

open access land,<br />

and public open<br />

space<br />

Minor adverse<br />

(noise) temporary<br />

Major adverse on<br />

foreshore (visual)<br />

Major adverse on<br />

foreshore (visual –<br />

during interim<br />

period)<br />

Adherence to best<br />

practice noise<br />

minimisation<br />

Landscaping and<br />

planting<br />

Negligible adverse<br />

to minor adverse<br />

(noise) temporary<br />

Major adverse on<br />

foreshore (visual)<br />

Major adverse on<br />

foreshore (visual –<br />

during interim<br />

period)<br />

Operation Phase<br />

Disturbance to<br />

users of public<br />

rights of way<br />

Minor adverse to<br />

moderate adverse<br />

(noise) temporary<br />

Adherence to best<br />

practice noise<br />

minimisation<br />

Minor adverse to<br />

moderate adverse<br />

(noise) temporary<br />

Negligible adverse<br />

to major adverse<br />

(visual)<br />

Landscaping and<br />

planting<br />

Negligible adverse<br />

to major adverse<br />

(visual)<br />

Disturbance to<br />

sports and<br />

recreation facilities,<br />

open access land,<br />

and public open<br />

space<br />

Major adverse on<br />

foreshore (visual)<br />

Landscaping and<br />

planting<br />

Major adverse on<br />

foreshore (visual)<br />

Dismantling and Restoration Phase<br />

Disturbance to<br />

users of public<br />

rights of way<br />

Minor adverse to<br />

moderate adverse<br />

(noise) temporary<br />

Adherence to best<br />

practice noise<br />

minimisation<br />

Minor adverse to<br />

moderate adverse<br />

(noise) temporary<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 19 November 2010


Description of Impact Impact Mitigation Measure Residual Impact<br />

Removal and Reinstatement Phase<br />

Disturbance to<br />

users of public<br />

rights of way<br />

Minor adverse to<br />

moderate adverse<br />

(noise) temporary<br />

Adherence to best<br />

practice noise<br />

minimisation<br />

Minor adverse to<br />

moderate adverse<br />

(noise) temporary<br />

Negligible adverse<br />

to major adverse<br />

(visual)<br />

Reinstatement of<br />

features and<br />

planting<br />

Negligible adverse<br />

to major adverse<br />

(visual)<br />

Disturbance to<br />

sports and<br />

recreation facilities,<br />

open access land,<br />

and public open<br />

space<br />

Major adverse on<br />

foreshore (visual)<br />

Reinstatement of<br />

features and<br />

planting<br />

Major adverse on<br />

foreshore (visual)<br />

7.2 Transport<br />

Existing Environment<br />

7.2.1 The transportation network surrounding the site is set in a rural location with a network of<br />

country lanes linking scattered residences; farmhouses and a number of small hamlets<br />

(see Figure 8). The settlement of Shurton lies to the south of the site; the village of<br />

Combwich lies 5km south-east on the western side of the River Parrett; and the village of<br />

Cannington lies approximately 7km to the south-east of the site.<br />

7.2.2 The main access road serving the existing <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex is the<br />

C182, which is a single carriageway road passing from <strong>Hinkley</strong> <strong>Point</strong> south-east to the<br />

village of Cannington. The C182 routes to the east of Shurton and to the west of<br />

Combwich and passes through the centre of Cannington to join the A39 to the south of<br />

the village.<br />

Main Predicted Impacts<br />

7.2.3 The jetty development’s construction is programmed in two consecutive and overlapping<br />

stages totalling seven quarters, spanning Quarter 2 2011 to Quarter 4 2012. The first<br />

stage would take place between Quarter 2 2011 and Quarter 2 2012, potentially running<br />

concurrently with the site preparation works which are due to be completed in Quarter 1<br />

2012. The second stage of would follow on directly from the first stage and is<br />

programmed to take place between Quarter 2 2012 and Quarter 4 2012.<br />

7.2.4 The jetty development’s design seeks to minimise the amount of road traffic generated.<br />

For example, rather than being imported by road, construction materials would be<br />

imported by sea where they are needed for the jetty’s offshore components and fill<br />

material for the aggregates storage area’s development platform would be sourced on<br />

site. Table 3 details the transport demand for the jetty construction works.<br />

7.2.5 For the jetty, offshore construction work would be carried out in two weekday shifts to be<br />

influenced by the tidal patterns. Onshore construction work would be carried out on<br />

weekdays (07:00 to 18:00) and Saturdays (07:00-13:00), but not on Sundays, bank<br />

holidays or public holidays.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 20 November 2010


Figure 8 Main Traffic Routes to <strong>Hinkley</strong> <strong>Point</strong><br />

7.2.6 During the jetty development’s construction phase, the peak daily staff numbers equates<br />

to 120 vehicle trips. Daily HGV traffic associated with the jetty development is estimated<br />

at 8 HGV trips per day. Base flows on Rodway for 2012 are forecast at 7672, which<br />

means that the jetty development changes flows by 1.6% over the baseline. Closer to<br />

the application site, Wick Moor Drove registered an average daily two-way flow of 1,950<br />

vehicles for a five day average during March 2010, which means that the jetty<br />

development changes flows by. 6.4% over the baseline.<br />

Table 3 <strong>Jetty</strong> Construction Material Quantities and Personnel<br />

Movements 2011 Q1 2011 Q2 2011 Q3 2011 Q4 2012 Q1<br />

a Daily HGV Deliveries<br />

(quantities)<br />

b Daily HGV Deliveries<br />

(contingency)<br />

0 2 2 2 2<br />

0 2 2 2 2<br />

c Personnel 0 60 60 60 60<br />

d Daily Two Way Trips<br />

(a+b+c)x2<br />

0 128 128 128 128<br />

7.2.7 Overall, the traffic arising from the jetty development’s construction phase is small and<br />

not significant and it is within 10% of daily traffic fluctuations. Therefore, it has been<br />

concluded that the traffic will have no discernable impact on the highway network and no<br />

further assessment of environmental impacts of the jetty development need be<br />

undertaken. The other phases of the jetty development have also been predicted to<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 21 November 2010


generate no discernable change, and impacts on transport are, therefore, assessed as<br />

being not significant.<br />

Mitigation<br />

7.2.8 Since the impacts are not significant, no mitigation measures are required.<br />

Residual Impacts<br />

7.2.9 Given that the original impacts are not significant, the residual impacts are also not<br />

significant.<br />

7.3 Air Quality<br />

Existing Environment<br />

7.3.1 In terms of air quality, the jetty development’s application site at <strong>Hinkley</strong> <strong>Point</strong> is located<br />

in a rural setting on the coastline of the Severn Estuary. This provides favourable<br />

conditions for pollutant dilution and dispersion, with an on-shore breeze dominating from<br />

the west-north-west. The topography of the region is also conducive to good pollutant<br />

dispersion, with the immediate area surrounding the site being rolling countryside.<br />

7.3.2 Within the district of West Somerset, industrial pollution sources are limited to two<br />

Pollution Prevention and Control (PPC) Part-A processes (<strong>Hinkley</strong> <strong>Point</strong> B and<br />

Wansbrough Paper Mill) and seven Part-B2 processes. The Wansbrough Paper Mill is<br />

located approximately 7km from the application site and is thus not expected to<br />

significantly impact the air quality in the locality. There are emissions to air arising from<br />

the operation of <strong>Hinkley</strong> <strong>Point</strong> B, although these are minimal and principally limited to<br />

emissions released during the periodic testing of backup diesel generators.<br />

Consequently, industrial pollutant sources to air in the site locality are few.<br />

7.3.3 West Somerset Council has identified the A39 as the most significant source of vehicle<br />

emissions to air in the West Somerset district. Within the district of Sedgemoor,<br />

Sedgemoor District Council has acknowledged that the steady increase of traffic volume<br />

on the Northern Distributor Road since it opened in 2003 is of concern with regards to air<br />

quality. The highest vehicle flows within Sedgemoor, however, result from traffic on the<br />

M5, which has Annual Average Daily Traffic (AADT) of approximately 80,000 vehicles per<br />

day.<br />

7.3.4 The baseline air quality monitoring campaign confirmed that the air quality in the<br />

immediate vicinity to <strong>Hinkley</strong> <strong>Point</strong> can be generally categorised as good, with pollutant<br />

concentrations well below the annual mean UK Air Quality Objective limits.<br />

Main Predicted Impacts<br />

7.3.5 The extent to which dust and particle generation and nuisance arising from the jetty<br />

development’s construction works might occur depends upon various factors, including<br />

the precise nature of work being undertaken, wind direction, wind speed, precipitation,<br />

type and quantity of material being handled, particle size distribution of the material being<br />

handled and moisture content of the material being handled.<br />

7.3.6 Airborne dust levels are more likely to increase during periods of prolonged warm, dry<br />

weather. During periods of wetter weather, precipitation not only minimises the amount<br />

of dust that becomes airborne, but also removes existing airborne dust from the<br />

atmosphere.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 22 November 2010


7.3.7 The distance from the source of the dust to the sensitive receptor (e.g. residential<br />

properties) is also critical. Both airborne dust and particle concentrations, and dust<br />

deposition rates, fall off rapidly on moving away from the source, due to dispersion and<br />

dilution. Large particles usually only travel 10 to 20m before being deposited where as<br />

smaller particles (e.g. PM 10 particles) are not readily deposited and can travel for longer<br />

distances, although the vast majority of small particles are deposited within 100m of the<br />

source. Hence, it is in the 100m zone where the risk from dust and particles is greatest.<br />

7.3.8 Thirty of the 32 identified human receptors are greater than 1km from the jetty<br />

development’s application site boundary. The separation distance between all human<br />

receptors and potential dust/PM 10 generating activities is greater than 750m. The nearest<br />

receptor is Doggets, located at a distance of approximately 786m from the closest point<br />

of relevant site activity.<br />

7.3.9 Given that the majority of the dust would be deposited within 100m of the source, human<br />

receptors are expected to be sufficiently far enough away from the closest point of<br />

construction activity to allow for substantial dispersion, dilution and deposition of<br />

dust/PM 10 . It is, therefore, extremely unlikely that dust would be a problem at any human<br />

receptors and the significance of this impact is assessed as minor.<br />

7.3.10 Given the relatively low numbers of diesel powered off-road construction plant and<br />

machinery required for the jetty development’s construction works, site exhaust<br />

emissions to air are predicted to be of imperceptible or small magnitude, and thus<br />

negligible in terms of their impact. Similarly, exhaust emissions from marine vessel<br />

movements associated with the jetty construction activities are also predicted to be of<br />

imperceptible, and thus negligible in terms of their impact.<br />

7.3.11 Construction of the jetty would lead to a negligible increase in the volume of road traffic.<br />

Therefore, the impact of all vehicular emissions to air (NO 2 , PM 10 and PM 2.5 ) associated<br />

with traffic generated by the jetty development is not considered to be significant.<br />

Mitigation<br />

7.3.12 All potential air quality impacts have been assessed as minor or not significant before<br />

any mitigation has been applied.<br />

7.3.13 Nevertheless, mitigation measures are proposed to control dust and particulate<br />

emissions during the jetty development works and to ensure dust nuisance is prevented<br />

in areas around the site. These measures would be included within the Dust<br />

Management Plan (DMP) which forms part of the Environmental Management and<br />

Monitoring Plan (EMMP) for the jetty development.<br />

7.3.14 In addition, a Dust Monitoring Scheme (DMS) would detail any associated monitoring<br />

responsibilities required to ensure that the DMP is being implemented successfully.<br />

Precise details of the DMP will be determined through consultation (e.g. with West<br />

Somerset Council), but should make reference to current best practice guidance and<br />

other supporting documentation.<br />

7.3.15 A comprehensive Travel Plan would also be implemented to minimise off-site vehicular<br />

movements during the jetty development’s construction works, to mitigate the associated<br />

impacts from vehicular exhaust emissions to air. Such measures would include, but by<br />

no means limited to, car sharing schemes and provision of bus transport for the<br />

workforce.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 23 November 2010


7.3.16 Given that the potential impacts during jetty development’s operation,<br />

dismantling/restoration and, if required, removal/reinstatement phases are similar to or<br />

less than those during jetty development’s construction phase, the mitigation measures<br />

for the jetty development’s construction phase could be implemented during the jetty<br />

development’s other phases.<br />

Residual Impacts<br />

7.3.17 No significant residual impacts are predicted to occur. Nevertheless, as detailed above,<br />

measures would be put in place in accordance with current good practice for construction<br />

management.<br />

7.4 Noise and Vibration<br />

Existing Environment<br />

7.4.1 Baseline noise surveys were undertaken to obtain a measure of the existing noise<br />

environment, in accordance with the relevant guidance documents. The dominant noise<br />

sources identified during the baseline noise survey included local road traffic, birdsong<br />

and surf movement (at a coastal monitoring location). The determined ambient noise<br />

levels are typical of a rural environment, dropping to low levels during the night time.<br />

Main Predicted Impacts<br />

7.4.2 Assessments of the jetty development’s construction noise impacts were undertaken for<br />

three distinct activity scenarios (i.e. points in time when multiple construction activities<br />

are expected to be ongoing). These were identified primarily to provide an assessment<br />

of the worst-case situation at each of the identified sensitive receptor locations. It is<br />

predicted that the recognised proposed noise threshold criteria would not be exceeded at<br />

any residential receptor location during the jetty development’s construction. Hence the<br />

significance of the impact is assessed as minor adverse (see Figure 9).<br />

7.4.3 At the assessed public amenity receptor location on Benhole Lane, high noise levels are<br />

predicted during specific activities associated with the jetty development’s construction<br />

works close to the site boundary. The significance of the noise impact to this location<br />

during these periods is assessed as moderate adverse (in the short term). Noise impacts<br />

on other public amenity locations (e.g. the Coast Path, Wick Moor / Pixies’ Mound) are<br />

assessed as minor adverse.<br />

7.4.4 The nature of the jetty development’s construction means that the worst-case situation<br />

would be short term and may only exist for a matter of days. There would also be regular<br />

periods, even during the course of a single day, when the assumed noise plant would not<br />

be in operation (i.e. during breaks or changes of working routine).<br />

7.4.5 The potential vibration impacts resulting from the jetty development’s construction have<br />

been assessed. Given the significant distance between areas where construction<br />

activities may cause ground borne vibration and residential properties, it is not expected<br />

that any perceptible vibration would occur within those properties and impacts are<br />

assessed as minor adverse.<br />

7.4.6 Assessments of the jetty development’s operational noise impacts were undertaken for<br />

four aggregates import scenarios (covering both day and night-time working). It is<br />

predicted that the recognised proposed noise threshold criteria would not be exceeded at<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 24 November 2010


any residential receptor location during the jetty development’s operation. Hence the<br />

significance of the impact is assessed as minor adverse.<br />

7.4.7 At the assessed public amenity receptor location on the West Somerset Coast Path at its<br />

closest point to the jetty, receptors (i.e. users of the public footpath) would be exposed to<br />

high noise levels during specific activities associated with the jetty development’s<br />

operation. However, the receptors are not considered to be permanently exposed to the<br />

operational noise (unlike a receptor living at a residential property), so the potential noise<br />

impact of cargo operations to users of the public footpath is assessed as being of minor<br />

significance.<br />

Figure 9 Noise Contour Plot (Scenario 1)<br />

7.4.8 The dismantling of the jetty development and restoration of the site is likely to involve<br />

similar activities to construction, except with reduced intensity. Therefore, it is assessed<br />

that the overall noise and vibration impacts during this phase would be minor adverse.<br />

7.4.9 The removal and reinstatement of the site is also likely to involve similar activities to<br />

construction, except with reduced intensity. Therefore, it is assessed that the overall<br />

noise impacts and vibration impacts during this phase would be minor adverse.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 25 November 2010


Mitigation<br />

7.4.10 The main mitigation to be implemented would include good construction practice and<br />

management tools for minimising nuisance from noise and vibration. For example,<br />

British Standard BS 5228: Part 1:2009 gives detailed advice on standard good<br />

construction practice for minimising nuisance from construction noise. This includes the<br />

use of electrical items of plant instead of diesel plant in especially sensitive locations,<br />

keeping internal haul roads well maintained and avoiding steep gradients where possible,<br />

avoiding unnecessary revving of engines and switching of equipment when it is not in<br />

use.<br />

7.4.11 Measures to be incorporated would be included within the EMMP for the project. As<br />

appropriate, these would include:<br />

• use of white-noise spectrum reversing alarms and/or in-cab radar systems;<br />

• soft-start piling operations; and<br />

• prior notice for noisy short-term onshore activities that are expected to exceed the<br />

respective construction noise limit (48 hours in advance).<br />

7.4.12 A formal system would be put in place which identifies the roles and responsibilities of<br />

site staff regarding the noise complaint action procedure. Site logs would be maintained,<br />

detailing all complaints received relating to noise nuisance impacts, and the<br />

corresponding response made to each complainant.<br />

7.4.13 The assessment of potential hourly road traffic noise impacts includes an assumed 2.24<br />

car share rate. This would be managed by through a Travel Plan and minimising the<br />

number of car parking spaces on site.<br />

Residual Impacts<br />

7.4.14 Table 4 presents a summary of the significant noise impacts that would remain after the<br />

measures discussed above have been put into practice. It should be noted that<br />

measures built into the jetty development’s design to minimise adverse impacts (e.g. best<br />

practice) is not considered to be mitigation.<br />

Table 4 <strong>Summary</strong> of Significant Impacts on Noise and Vibration<br />

Description of Impact Impact Mitigation Measure Residual Impact<br />

Construction Phase<br />

Onshore construction<br />

works<br />

Moderate adverse<br />

(Benhole Lane<br />

PRoW)<br />

Implementation of<br />

best practice<br />

measures<br />

Moderate adverse<br />

Receptors are<br />

transient<br />

Dismantling and Restoration Phase<br />

Onshore construction<br />

works<br />

Minor to major<br />

adverse (public<br />

footpaths and other<br />

outdoor amenities)<br />

Implementation of<br />

best practice<br />

measures<br />

Negligible to<br />

moderate adverse<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 26 November 2010


Description of Impact Impact Mitigation Measure Residual Impact<br />

Removal and Reinstatement Phase<br />

Onshore construction<br />

works<br />

Negligible to<br />

moderate adverse<br />

(public footpaths<br />

and other outdoor<br />

amenities)<br />

Implementation of<br />

best practice<br />

measures<br />

Negligible to<br />

moderate adverse<br />

7.5 Landscape and Visual Amenity<br />

Existing Environment<br />

7.5.1 For the purposes of the EIA, the Landscape and Visual Impact Assessment (LVIA) study<br />

area was determined through computer modelling, desk studies and consultation, and<br />

detailed landscape analysis was undertaken up to around 5km from the application site.<br />

7.5.2 There are no international, national, regional or local landscape designations within the<br />

application site. Exmoor National Park is located 14km to the west of the application site.<br />

Two Areas of Outstanding Natural Beauty (AONB) are located within the study area,<br />

namely Quantock Hills AONB (4km south-west of the site) and Mendip Hills AONB (18km<br />

north-east of the site).<br />

7.5.3 No county and local landscape designations exist within the application site. However,<br />

several county and local designations of relevance to the LVIA are present within the<br />

study area. They include Conservation Areas, Listed Buildings, County Wildlife Sites and<br />

local council landscape policies designating an area as a Green Wedge.<br />

7.5.4 The application site lies within the ‘Vale of Taunton and Quantock Fringes’ National<br />

Landscape Character Area and ‘Quantock Vale’ County Landscape Character Area. Five<br />

seascape character areas have also been identified within the study area using existing<br />

local landscape character area assessments.<br />

7.5.5 The application site is situated within an area of rolling farmland and does not contain<br />

any landscape elements and features of high national, regional, county or district<br />

importance. The ridge of Green Lane situated to the south of the application site is a<br />

feature of local importance. Historic field patterns, a few hedgerows and watercourses<br />

with adjacent riparian vegetation are other locally important elements and features within<br />

the application site. In the wider context, the application site lies within an intrinsically<br />

dark area; however the adjacent <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex is a significant<br />

source of existing light pollution.<br />

7.5.6 The visibility of the application site varies within the study area. Open views into the<br />

application site exist from the areas of farmland up to 3km to the west of the site and<br />

from elevated viewpoints situated within the north-eastern fringes of the Quantock Hills<br />

AONB. The application site is predominantly screened from the south by the local ridge<br />

of Green Lane. No views into the application site exist from Knighton, Shurton or Burton<br />

and glimpsed views into the application site exist from elevated areas of farmland up to<br />

5km away. The existing <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex screens the application<br />

site from the east. A few long distance views into the application site exist from the most<br />

elevated viewpoints within the study area. The visibility of the application site has been<br />

identified through a selection of 23 representative panoramic views.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 27 November 2010


Main Predicted Impacts<br />

Landscape Impacts<br />

7.5.7 This assessment takes account of the main design features of the development, such as<br />

development footprint adjustments to avoid important landscape features or minimising<br />

the size of the proposed structures, but not the advanced planting or adoption of<br />

appropriate lighting controls, which are considered mitigation.<br />

7.5.8 Before the implementation of the mitigation measures, the landscape impacts on the<br />

national, regional, county and district landscape character would be short-term, adverse<br />

and of minor significance during construction, operation, dismantling (but not restoration)<br />

and, if required, removal (but not reinstatement) of the jetty development; and long-term,<br />

neutral and of negligible significance following restoration and, if required, reinstatement.<br />

7.5.9 The local and site-specific impacts on landscape character, impacts on seascape<br />

character as well as on local and site-specific landform would be short-term, adverse and<br />

of moderate significance during construction, operation, dismantling (but not restoration)<br />

and, if required, removal (but not reinstatement) of the jetty development; and long-term,<br />

neutral and of negligible significance following restoration and, if required, reinstatement.<br />

7.5.10 The local and site-specific impacts on land use and land cover, would be short-term,<br />

adverse and of minor significance during construction, operation, dismantling (but not<br />

restoration) and, if required, removal (but not reinstatement) of the jetty development;<br />

and long-term, neutral and of negligible significance following restoration and<br />

reinstatement.<br />

Visual Impacts<br />

7.5.11 The visibility of the unmitigated jetty development would vary depending on the<br />

separation distance and elevation of viewpoints from the site. Visual impact would also<br />

be caused by the potential light pollution of the jetty development’s lighting scheme<br />

before mitigation.<br />

7.5.12 Impacts associated with construction, dismantling (but not restoration) and, if required,<br />

removal (but not reinstatement) would be short-term (0-5 years), operational impacts<br />

would be short-term to medium-term (0-15 years), and impacts associated with the<br />

restored and, if required, reinstated landscape would be long-term (over 15 years).<br />

7.5.13 It is assessed that during construction and operation of the jetty development there would<br />

be visual impacts of major adverse significance in the local area where local PRoW have<br />

views of the application site and, therefore, where the medium magnitude of visual<br />

change is combined with high sensitivity receptors. The main adverse visual impacts<br />

would occur within the Coastal Eastern Lowlands (receptors represented by PRoW WL<br />

23/95 and PRoW no. WL 24/9; see Figure 2) up to 3km to the west of the application<br />

site. All these locations would receive views of the jetty development, as well as<br />

changed topography.<br />

7.5.14 Adverse impacts of major significance would also occur on the locally important ridge to<br />

the south of the site (PRoW no. WL 23/110) (see Figure 10), which due to its elevation<br />

would receive views of the majority of the site, and at Pixies Mound (Wick Barrow). From<br />

Pixies Mound the jetty development would not be visible; however, the proximity of the<br />

eastern part of the application site would cause a medium magnitude of visual change.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 28 November 2010


7.5.15 Due to the screening provided by the Green Lane ridge and undulating topography there<br />

would be no visual impact on views from Shurton, Burton or Knighton.<br />

Figure 10 Existing View and Photomontage of the <strong>Jetty</strong> Development from<br />

Principal Viewpoint 1 (PRoW number WL 23/110, Benhole Lane)<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 29 November 2010


7.5.16 Impacts on views from the east, including farms located within the Wick Moor landscape<br />

character area would be of minor to moderate adverse significance depending on the<br />

sensitivity of the receptor. These views would be potentially affected by the light pollution<br />

associated with the (unmitigated) jetty development. The majority of views, however,<br />

would not be affected due to screening provided by the existing <strong>Hinkley</strong> <strong>Point</strong> Power<br />

Station Complex, topography and vegetation. The only visual impact of major adverse<br />

significance would occur at Pixies Mound due to the very short distance from the site and<br />

medium magnitude of impact on this highly sensitive receptor.<br />

7.5.17 The impact of the unmitigated jetty development and associated lighting on the elevated<br />

areas of the Quantock Hills AONB or Mendip Hills AONB would be of moderate adverse<br />

significance. The main source of this impact would be light pollution. A similar adverse<br />

impact could be also experienced from Brean Down, Fairfield House, Stockland Bristol<br />

and other local viewpoints up to 3km from the application site. Although the majority of<br />

these viewpoints would have limited views of the jetty development’s construction and<br />

operation, adverse impacts would occur due to potential light pollution.<br />

7.5.18 The unmitigated dismantling and restoration phase of the jetty development or, if<br />

required, removal and reinstatement phase, would include the dismantling or removal of<br />

all built elements created during the construction phase and restoration or reinstatement<br />

of the existing landform and vegetation.<br />

7.5.19 The short-term visual impacts associated with the dismantling or, if required, removal of<br />

the jetty development would be largely the same as the impacts associated with<br />

construction and operation. The impact caused by the dismantling or, if required, removal<br />

of built form, earthworks and lighting, as well as activities associated with the replanting<br />

of the vegetation lost during construction within the site, would cause the same<br />

magnitude of visual impacts and remain adverse in nature.<br />

7.5.20 Following the short-term impact associated with the dismantling or, if required, removal of<br />

the jetty, long-term impacts would occur due to the restoration or, if required,<br />

reinstatement of the existing landscape features within the application site, including<br />

topography and vegetation. The impact on all visual receptors following restoration or, if<br />

required reinstatement would be of negligible significance in the long-term.<br />

Mitigation<br />

7.5.21 Following the identification of the potential landscape and visual impacts on the receptors<br />

identified in the baseline study, measures have been proposed to mitigate these effects<br />

during construction, operation, dismantling and restoration and, if required, removal and<br />

reinstatement phases of the jetty development.<br />

7.5.22 The mitigation measures are proposed within the site boundary and, where possible,<br />

within the wider <strong>Hinkley</strong> <strong>Point</strong> C development site. To mitigate adverse impacts on the<br />

Coastal Eastern Lowlands area and Fairfield House, and to protect land on the estate<br />

(which is of outstanding scenic interest) from landscape and visual impacts during all<br />

phases of the jetty development, Fairfield Estate (supported by <strong>EDF</strong> Energy and in<br />

consultation with English Heritage and Natural England) is in the process of preparing<br />

proposals for off site planting to augment the on site mitigation (see Figure 11).<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 30 November 2010


Figure 11 Construction Mitigation Landscape Plan<br />

7.5.23 To minimise landscape and visual impact of the jetty development, the design of the silos<br />

(which are a design feature, not mitigation) was also considered. The preferred option<br />

was selected during the following process. The original engineering design included silos<br />

at 40m high located on the development platform for the aggregates storage area.<br />

Sensitivity of the location was recognised and the impacts considered unacceptable in<br />

the context of the Preliminary Works. Design options were explored to lower the height of<br />

the silos whilst still achieving the project’s storage requirements. These options included<br />

laying the silos on their sides which would result in the silos being at least 20m high due<br />

to operational requirements, and also developing the option of a storage building instead<br />

of silos. This structure would also have to be of considerable size. The preferred option is<br />

to provide a number of smaller silos at 20m high which would achieve the minimum<br />

engineering requirements. The top of the silos is comparable to the height of Green Lane<br />

which ensures that visual impacts on the land to the south of Green Lane, including the<br />

settlements of Shurton, Burton Knighton and Wick, are limited.<br />

7.5.24 The main mitigation measures proposed for construction and operation of the jetty<br />

development include seeding 8.66ha of land within the application with grass to soften<br />

views, retaining 0.03ha of broad leaved woodland and 0.31ha of improved grassland<br />

within the application site, planting 550m native species rich hedgerow along the western<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 31 November 2010


oundary to contribute to biodiversity and provide visual screening from the PRoW<br />

located on low topography to the west of the application site, and protecting boundary<br />

vegetation by appropriate fencing during construction.<br />

7.5.25 The impact of lighting during construction would be mitigated by the implementation of<br />

appropriate lighting mitigation measures. The proposed limits on intrusive light aimed at<br />

minimising problems for neighbouring areas are designed to protect the most sensitive<br />

landscapes, such as AONB, from light pollution. Other lighting mitigation objectives and<br />

measures include minimising the use of light (i.e. only in areas being actively worked),<br />

directing light downwards to minimise light pollution, avoidance of ‘over-lighting’ of the<br />

area (using correct illumination levels), avoidance of lighting close to the application site<br />

boundary, avoidance of unnecessary night time lighting and reduction of the heights of<br />

light columns to an acceptable minimum.<br />

7.5.26 The landscape proposals during the dismantling and restoration phase would be limited<br />

to the western part of the application site, to the west of the proposed <strong>Hinkley</strong> <strong>Point</strong> C<br />

Power Station. The remaining part of the application site would be occupied by the<br />

<strong>Hinkley</strong> <strong>Point</strong> C nuclear power station. The key change to the site would be the<br />

remodelled, gently undulating landform providing screening to the remaining part of the<br />

site from the adjacent landscape. The landform would be formed as a slope rather than a<br />

bund, in line with the existing local landscape character. The screening proposals would<br />

be reinforced by a narrow strip of broad-leaved woodland stretching from the coastline to<br />

the southern boundary of the application site, adjacent to the proposed <strong>Hinkley</strong> <strong>Point</strong> C.<br />

The remaining landscape would comprise restored agricultural field, including arable land<br />

and fields of semi-improved grassland divided by species-rich hedgerows on field<br />

boundaries and arable conservation headlands. All proposed planting would be of native<br />

species, selected to complement and enhance existing local landscape character and to<br />

suit site conditions. Other landscape features proposed within the western part of the<br />

application site would include a narrow strip of calcareous grassland on top of the coastal<br />

cliff and dense scrub (see Figure 12). The access would be improved by additional<br />

public footpaths to be located within the restored site.<br />

7.5.27 Should it be required, the landscape mitigation for the short period of removal (but not<br />

reinstatement) activities would be the same as for the construction phase, due to the<br />

similar nature of works and their predicted visual impact. The landscape and ecological<br />

features identified for retention and/or protection during the jetty’s construction would be<br />

also retained and/or protected during the removal and reinstatement works. It is<br />

proposed that during the removal and reinstatement phase the landscape features within<br />

the application site would be reinstated to the existing condition, including the<br />

reinstatement of the landform to resemble the existing condition (including the removal of<br />

the development platform for the aggregates storage area), and reinstatement of<br />

agricultural land and existing landscape features with no net gain or loss in biodiversity.<br />

During the reinstatement phase, the PRoW closed during the construction phase of the<br />

jetty development would be reinstated, including the coastal footpath. The reinstated<br />

footpaths would be clearly defined and signposted.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 32 November 2010


Figure 12 Landscape Restoration Plan<br />

Residual Impacts<br />

Landscape Impacts<br />

7.5.28 Following the implementation of mitigation measures, residual landscape impacts on<br />

national and regional landscape character would be of negligible significance during all<br />

phases of the jetty development.<br />

7.5.29 Residual impacts on county and district landscape character would be adverse and of<br />

minor significance during the construction, operation, dismantling (but not restoration) or,<br />

if required, removal (but not reinstatement), and of negligible neutral significance<br />

following restoration or reinstatement.<br />

7.5.30 Residual impacts on seascape character would be adverse and of moderate significance<br />

during the construction, operation, dismantling (but not restoration) or, if required,<br />

removal (but not reinstatement), and long-term, neutral and of negligible significance<br />

following restoration or reinstatement.<br />

7.5.31 During construction, operation, dismantling (but not restoration) or, if required, removal<br />

(but not reinstatement), residual impacts on local and site-specific landscape character<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 33 November 2010


and landform would be adverse and of moderate significance and impacts on local and<br />

site-specific land use and land cover would be adverse and of minor significance.<br />

7.5.32 Following restoration, the residual landscape impacts on local landscape character as<br />

well as local and site-specific land use and land cover would be long-term beneficial and<br />

of minor significance. The residual impact on local and site-specific landform during<br />

restoration would be adverse and of minor significance.<br />

7.5.33 Following reinstatement, the residual impact on local and site-specific landscape<br />

character, landform, land-use and land cover would be long-term, neutral and of<br />

negligible significance.<br />

Visual Impacts<br />

7.5.34 Following the implementation of the mitigation measures, some residual visual impact of<br />

the jetty development would be reduced in comparison to the unmitigated construction<br />

phase. The residual visual impacts on elevated viewpoints located in the vicinity of the<br />

application site (predominantly up to 3km to the west of the site) would be largely the<br />

same as during the unmitigated construction however, all visual impacts on more distant<br />

receptors would be reduced by the proposed mitigation measures, which are primarily<br />

targeted to mitigate the lighting impacts (potential light pollution) on the surrounding<br />

AONB. The additional hedgerow planting to the west of the application site would help<br />

reduce visual impacts from some PRoW located immediately to the west of the<br />

application site (see Figure 11).<br />

7.5.35 The residual visual impacts of major adverse significance would not change in<br />

comparison to the unmitigated scheme and would include PRoW no. WL 23/95, PRoW<br />

no. WL 24/9 to the west of the application site, PRoW no. WL23/110 West of Benhole<br />

Lane (see Figure 2), and at Pixies Mound (Wick Barrow). An impact of moderate<br />

adverse significance would occur at Viewpoints 8 and 9 within the Quantock Hills AONB<br />

(Beacon Hill and footpath between Woodland Hill and Dowsborough), which represent<br />

the north-eastern parts of the Quantock Hills AONB located on high topography that<br />

would receive limited views of the jetty development’s construction. The residual visual<br />

impact on the remaining viewpoints, including a number of AONB viewpoints, would be<br />

reduced to either minor adverse or negligible.<br />

7.5.36 The visibility of the mitigated jetty development during operation, dismantling (but not<br />

restoration) or, if required, removal (but not reinstatement) would be the same as the<br />

visibility during the mitigated construction phase (same visual receptors would be<br />

affected). Hence the magnitude of change and the resulting significance of impact would<br />

be the same as during construction. The nature of visual impacts during operation would<br />

change from short-term to medium-term, although the impacts would remain temporary.<br />

7.5.37 The significance of the residual visual impact of the restored landscape within the site<br />

would be largely negligible, as there would be no change in views from the majority of<br />

visual receptors. The only visual receptors which would experience visible change due to<br />

the implementation of a Landscape Restoration Plan would be Principal Viewpoints 1, 2<br />

and 3, where permanent beneficial impacts would occur due to the mitigation measures.<br />

7.5.38 Following the reinstatement phase, if required, and the maturation of landscape<br />

proposals, the significance of residual impact for all visual receptors is assessed as<br />

negligible in the long-term (15 years and beyond).<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 34 November 2010


7.5.39 Table 5 below presents a summary of the significant landscape and visual impacts that<br />

would remain after the mitigation measures discussed above have been put into practice.<br />

Table 5 <strong>Summary</strong> of Significant Residual Impacts on Landscape and Visual<br />

Amenity<br />

Receptor Impact Mitigation<br />

Measures<br />

Residual Impact<br />

Construction, Operation, Dismantling (but not Restoration) and Removal (but not<br />

Reinstatement) Phases<br />

Seascape character units<br />

Moderate,<br />

adverse,<br />

temporary<br />

Landscape and<br />

lighting mitigation<br />

Moderate,<br />

adverse,<br />

temporary<br />

Local and site-specific<br />

landscape character<br />

Moderate,<br />

adverse,<br />

temporary<br />

Landscape and<br />

lighting mitigation<br />

Moderate,<br />

adverse,<br />

temporary<br />

Local and site-specific<br />

landform<br />

Moderate,<br />

adverse,<br />

temporary<br />

N/A<br />

Moderate,<br />

adverse,<br />

temporary<br />

Principal Viewpoint 1:<br />

PRoW no. WL23/110 West<br />

of Benhole Lane<br />

Major, adverse,<br />

temporary<br />

Landscape and<br />

lighting mitigation<br />

Major, adverse,<br />

temporary<br />

Principal Viewpoint 2:<br />

Coastal Footpath PRoW<br />

no. WL 23/95<br />

Major, adverse,<br />

temporary<br />

Landscape and<br />

lighting mitigation<br />

Major, adverse,<br />

temporary<br />

Principal Viewpoint 3:<br />

Lilstock - PRoW no. WL<br />

24/9<br />

Major, adverse,<br />

temporary<br />

Lighting mitigation<br />

Major, adverse,<br />

temporary<br />

Principal Viewpoint 5:<br />

Pixies Mound (Wick<br />

Barrow)<br />

Major, adverse,<br />

temporary<br />

Landscape and<br />

lighting mitigation<br />

Major, adverse,<br />

temporary<br />

Principal Viewpoint 7:<br />

Quantock Hills AONB,<br />

Beacon Hill<br />

Moderate,<br />

adverse,<br />

temporary<br />

Lighting mitigation<br />

Moderate,<br />

adverse,<br />

temporary<br />

Principal Viewpoint 8:<br />

Quantock Hills AONB,<br />

Footpath between<br />

Woodland Hill and<br />

Dowsborough<br />

Moderate,<br />

adverse,<br />

temporary<br />

Lighting mitigation<br />

Moderate,<br />

adverse,<br />

temporary<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 35 November 2010


Receptor Impact Mitigation<br />

Measures<br />

Residual Impact<br />

Restoration Phase<br />

Principal Viewpoint 1:<br />

PRoW no. WL23/110 West<br />

of Benhole Lane<br />

Negligible, neutral,<br />

permanent<br />

Landscape<br />

Restoration Plan<br />

Moderate,<br />

beneficial,<br />

permanent<br />

Principal Viewpoint 2:<br />

Coastal Footpath PRoW<br />

no. WL 23/95<br />

Negligible, neutral,<br />

permanent<br />

Landscape<br />

Restoration Plan<br />

Moderate,<br />

beneficial,<br />

permanent<br />

7.6 Historic Environment<br />

Existing Environment<br />

7.6.1 There are no Scheduled Monuments, Listed Buildings, Conservation Areas or Registered<br />

Parks and Gardens or Registered Battlefields within the application site. The closest<br />

Scheduled Monument to the application site is Wick Barrow (also known as Pixies’<br />

Mound) (see Figure 13). It is located 50m to the east of Wick Moor Drove. Wick Barrow<br />

dates from the Neolithic and Bronze Age periods and was partially excavated in 1907.<br />

Figure 13 Locations of Historic Environment Features<br />

7.6.2 Geophysical survey and trial trenching confirmed that there are no buried archaeological<br />

remains within the application site. There are, however, a number of hedgerows within<br />

the application site that meet the archaeological and historical criteria of Important<br />

Hedgerows as defined in the Hedgerow Regulations 1997. There is one historic building,<br />

Benhole Barn, which dates from the late 18 th or early 19 th century. The barn has been<br />

extensively altered and is in a derelict state.<br />

7.6.3 Undesignated heritage assets dating from the Mesolithic (10,000–3,500 BC), Neolithic<br />

(3,500-2,000 BC), Bronze Age (2,000-700BC), Iron Age (700BC-AD43), Roman (AD43-<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 36 November 2010


AD450), Early-medieval (AD 450-AD1066), Medieval (AD1066-AD1540) and Postmedieval<br />

(AD1540 onwards) periods have been identified within the 500m study area<br />

around the application site (see Figure 13).<br />

7.6.4 A foreshore survey undertaken in June 2010 confirmed that there are no surviving<br />

archaeological remains above the Mean High Water Mark.<br />

7.6.5 Offshore, the UKHO wreck record for the study area contains 14 wreck sites. No<br />

protected wrecks were identified within the application site boundary. One apparent<br />

wreck site, located ~750m east of the application site boundary, reflected a ‘diffuser’<br />

associated with the existing <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex. Another potential<br />

wreck, identified from sidescan anomalies, lies 116m north-west of the edge of the<br />

application site boundary. It is not possible to offer a definitive interpretation of the type<br />

of wreck or wreckage that this may represent. No confirmed submerged archaeological<br />

remains have been identified in the area of the jetty development.<br />

7.6.6 Lithological and stratigraphic modelling of deposits based on survey data from core logs<br />

collected in 2009 revealed a relatively consistent sequence across the survey area; ~1-<br />

3m of surficial sands, gravels or clays, overlying a more consistent clay layer (0.5-5m<br />

thick) before reaching claystone bedrock. The discovery of peat deposits underlying the<br />

uppermost superficial deposits in 39 out of 63 vibrocores, and organic rich clays in a<br />

further 13 vibrocores, confirms the widespread presence of buried peats and other<br />

palaeo-landsurfaces, first identified in the western part of the survey area. These layers<br />

thin to the south-west of the survey area and only limited organic material has been<br />

identified in the core logs from the area of the jetty development.<br />

Main Predicted Impacts<br />

7.6.7 During the jetty development it is considered that there is potential for a number of<br />

significant impacts to the historic environment.<br />

7.6.8 The Scheduled Monument, Wick Barrow, is located to the east of the site and its setting<br />

would be partially altered during the construction phase as the area to the west would<br />

become a construction site. This would result in a moderate adverse impact.<br />

7.6.9 The historic hedgerows would experience a high magnitude of impact during<br />

construction, which is assessed to be a moderate adverse impact.<br />

7.6.10 Construction of the aggregates storage area would result in the complete removal of<br />

Benhole Barn, which would result in an overall adverse impact of moderate significance.<br />

7.6.11 The buried peat and organic horizons below the soft sediments offshore are believed to<br />

be a relict Mesolithic landscape. The peat deposits may contain palaeo-environmental<br />

data such as pollen, macrofossil, insect remains and radiocarbon datable organics.<br />

Disturbance and removal of these horizons during construction works could cause a loss<br />

of research potential, and a moderate adverse impact.<br />

7.6.12 The buried peat and organic horizons below the soft sediments offshore are believed to<br />

be a relict Mesolithic landscape. The peat deposits may contain palaeo-environmental<br />

data such as pollen, macrofossil, insect remains and radiocarbon datable organics.<br />

Disturbance and removal of these horizons during construction works could cause a loss<br />

of research potential, and a moderate adverse impact.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 37 November 2010


Mitigation<br />

7.6.13 It is proposed that a Monument Management Plan should be prepared to ensure the<br />

long-term preservation, and enhancement, of Wick Barrow (Pixies Mound) and its<br />

immediate setting.<br />

7.6.14 Due to the nature of the jetty development, the preservation in-situ of the historic<br />

hedgerows within the application site boundary would not be an option, so suitable<br />

mitigation would entail preservation by record.<br />

7.6.15 Due to the low importance of Benhole Barn, suitable mitigation would entail preservation<br />

by record.<br />

7.6.16 Preservation by record of onshore heritage assets would comprise archaeological<br />

investigation and recording in advance of construction. All investigation works would be<br />

carried out in accordance with the relevant Institute for Archaeologists standards and<br />

guidance.<br />

7.6.17 Although no heritage assets have been identified within the offshore part of the<br />

application site, the area proposed for dredging of the berthing pocket contains deposits<br />

comparable to those containing archaeological material further east. Therefore a<br />

watching brief would be undertaken during this phase.<br />

Residual Impacts<br />

7.6.18 No significant residual impacts are predicted to occur.<br />

7.7 Socio-economics<br />

Existing Environment<br />

7.7.1 Baseline data has been collected for Somerset and the key districts of Sedgemoor, West<br />

Somerset and Taunton Deane. The overall picture revealed by the baseline assessment<br />

is one of, until recently, a relatively prosperous local area, as indicated by above-average<br />

rates of population and employment growth, and relatively low levels of unemployment.<br />

However, there are other indicators, including migration flows, economic structure, skills<br />

and earnings levels, which indicate a much less resilient local economy, and with<br />

particular problem pockets of deprivation and considerable variations between the three<br />

districts.<br />

7.7.2 The combined population in the three immediate districts of West Somerset, Sedgemoor<br />

and Taunton Deane is almost 256,000 (mid-2007 population estimates). West Somerset<br />

and Sedgemoor are predominantly rural districts, with relatively low population densities.<br />

Taunton Deane is also significantly rural in nature, but has a higher proportion of its<br />

population in larger urban settlements.<br />

7.7.3 The districts do display some important socio-economic issues. Sedgemoor, for example,<br />

has overall low levels of skills in the workforce, below average educational attainment,<br />

some severe pockets of multiple deprivation and worklessness. Recent studies have<br />

highlighted weaknesses in the district’s economic resilience, linked to workforce skills<br />

issues, plus, for example, a sectoral mix limited in knowledge intensive industries.<br />

Taunton Deane is heavily dependent on public sector employment, which may face cuts<br />

in the current context of public sector activity review. West Somerset has a number of<br />

significant deprivation issues, for example in relation to affordable housing and access to<br />

services.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 38 November 2010


7.7.4 The rate of job growth, between 2001-2007, in the immediate districts (West Somerset,<br />

Sedgemoor and Taunton Deane) was broadly similar to the average for Somerset (6-<br />

7%), but slightly above the South West (5.5-5.6%) and national averages (4.6%).<br />

Tourism is a particularly important local industry. Annual Business Inquiry data show that<br />

tourism-related sectors accounted for an estimated 11,100 employee jobs in the three<br />

immediate districts. This represents approximately 10.5% of all employee jobs in the<br />

immediate districts, and compares with a national average of only 8.2%.<br />

Main Predicted Impacts<br />

7.7.5 Socio-economic impacts are the people effects of major projects. Of primary focus are<br />

the employment and expenditure associated with the works. These can result in a range<br />

of knock-on effects in the local economy, including impacts on population, local<br />

employment and unemployment levels, the local accommodation markets, and demand<br />

for local services.<br />

7.7.6 <strong>EDF</strong> Energy would seek as far as possible to provide positive socio-economic benefits to<br />

the local community; for example, through opportunities for training, employment and<br />

participation in the supply chain. More specific socio-economic objectives, which would<br />

be trialled during the jetty development (i.e. prior to the anticipated <strong>Hinkley</strong> <strong>Point</strong> C<br />

Project), would include, for example:<br />

• promote the training and recruitment of local people and support the provision of<br />

training courses and facilities in the local area (data demonstrate that the structure of<br />

the local economies in Sedgemoor and West Somerset already have a strong base<br />

in construction and skilled trades);<br />

• encourage and facilitate the involvement of local businesses in the supply chain;<br />

• make use of existing accommodation in the local area and support local businesses<br />

(e.g. owners of B&Bs and caravan parks) but without displacing the local tourist<br />

industry;<br />

• ensure that non-local workers, in all forms of accommodation, are well supported<br />

and maintain high standards of conduct, especially in their interaction with the local<br />

community; and<br />

• ensure that the impacts of the development on local communities are assessed and<br />

appropriate mitigation measures are put in place (e.g. support for local health and<br />

education facilities).<br />

7.7.7 The proposed jetty development would generate the following levels of employment:<br />

• construction phase: up to 60 jobs for up to 21 months;<br />

• operation phase: approximately 10 jobs for up to 8 years;<br />

• dismantling / restoration phase: approximately 25 jobs for approximately 1 year (for<br />

dismantling); and<br />

• removal / reinstatement phase (if required): approximately 25 jobs for approximately<br />

1 year (for removal).<br />

7.7.8 Average earnings levels on site, especially during construction, are likely to be<br />

significantly above the existing local economy average. The employment impact would<br />

be minor but generally positive even though there may be some local leakage of<br />

employment benefits because of labour supply / skills limitations and the nature / policies<br />

of contractors.<br />

7.7.9 It is anticipated that approximately 45% of the workforce might be non-local / non-home<br />

based, and would move into the area for the duration of the construction phase, thus<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 39 November 2010


equiring temporary accommodation. Since there is a very substantial supply of such<br />

accommodation within a 45 minutes commute of <strong>Hinkley</strong> <strong>Point</strong>, there is unlikely to be any<br />

significant pressure from such numbers on the capacity of the tourism accommodation to<br />

satisfy the ongoing tourism market. The demand during off-peak periods may be of<br />

some benefit to suppliers of local tourism accommodation. As such, this could provide a<br />

small scale but nevertheless useful boost to the tourist accommodation sector and the<br />

Somerset tourism industry.<br />

7.7.10 Impacts on other socio-economic parameters (i.e. other services, quality of life and the<br />

wider economy) are also predicted to not be significant.<br />

Mitigation<br />

7.7.11 A series of mitigation measures would be introduced. For example, the estimated levels<br />

of local recruitment may be boosted through a proactive recruitment and training policy.<br />

Such an approach is important to meet the objectives of both the local and regional<br />

authorities and of <strong>EDF</strong> Energy, and would utilise initiatives being developed for the<br />

<strong>Hinkley</strong> <strong>Point</strong> C Project more generally through a Construction Workforce Development<br />

Strategy. These initiatives include a range of education, training and access initiatives.<br />

The programme for the jetty development (along side that for the site preparation works)<br />

provides an important opportunity to pilot, develop and fine-tune such initiatives.<br />

7.7.12 The Construction Workforce Development Strategy would include a range of measures to<br />

create a clear pathway to local employment, and would be put in place by early 2011.<br />

These measures are described in the following paragraphs.<br />

7.7.13 A Preliminary Works Skills’ Charter would be established to maximise opportunities for<br />

local people to be employed. Furthermore, <strong>EDF</strong> Energy has indicated that it is keen to<br />

support businesses in the local area<br />

7.7.14 An Employment Brokerage would provide a local one-stop shop facility, including on-line<br />

access, dedicated for the development. The brokerage would provide access for local<br />

people to job opportunities and a place where contractors would advertise their<br />

vacancies. The facility would include resourcing, job shops, and workplace managers<br />

engaging with the growing supply chain. The provision of such a facility adjacent to the<br />

site at Sizewell B helped to place 5,500 job applicants, many of whom had been<br />

unemployed.<br />

7.7.15 A Construction Skills Centre to be brought forward by Bridgwater College would be<br />

supported by <strong>EDF</strong> Energy for the provision of early entry level skills training. The<br />

contribution would be used to establish the physical development of the Centre, at a<br />

location which is practicable for the training required to support the Preliminary Works<br />

and the main <strong>Hinkley</strong> <strong>Point</strong> C Project.<br />

7.7.16 In addition, <strong>EDF</strong> Energy would encourage contractors to support and promote local<br />

recruitment, including targeting training for and recruitment from the unemployed and<br />

others in disadvantaged groups, to bring people back into the workforce. Furthermore,<br />

there should be potential for job transition supported through the Construction Workforce<br />

Development Strategy.<br />

7.7.17 <strong>EDF</strong> Energy would also monitor and publish, on a regular basis, information on the<br />

development’s performance on recruitment and training. The contractor for the site<br />

preparation enabling works has already committed to use at least two-thirds Somerset<br />

based workers to manage, supervise and carry out the work.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 40 November 2010


Residual Impacts<br />

7.7.18 No significant residual impacts are predicted to occur.<br />

7.8 Navigation<br />

Existing Environment<br />

7.8.1 The Severn Estuary is an important shipping route, with commercial vessels navigating<br />

through the deep water approaches to several ports and harbours. Apart from the Port of<br />

Bridgwater, these ports are situated distant away from <strong>Hinkley</strong> <strong>Point</strong>, either on the south<br />

coast of Wales or at and upstream of Bristol. Databases of commercial shipping<br />

movements indicate that shipping in Bridgwater Bay is very low. As shown by two<br />

months of data from 2009, most commercial shipping movements occur on the opposite<br />

side of the Bristol Channel (see Figure 14; Note: this figure shows the proposed<br />

alignments of the cooling water structures associated with <strong>Hinkley</strong> <strong>Point</strong> C - intake in blue<br />

and outfalls in red).<br />

7.8.2 The Port of Bridgwater’s limits cover approximately 25 square nautical miles and include<br />

Combwich Wharf and Dunball Wharf on the River Parrett, but do not extend west as far<br />

as the proposed jetty development. Bridgwater Harbour Authority (part of Sedgemoor<br />

District Council) is responsible for navigation and mooring, safety, rights of access,<br />

pilotage, maintenance of channels and navigation aids oil spill contingency and port<br />

waste management. Port operations, oil spill contingency and port waste management<br />

plans are in place. Commercial vessel movements at the Port of Bridgwater totalled 41<br />

in 2007 and 37 in 2008. Most vessels were carrying aggregates and general cargo.<br />

Recreational moorings within the port limits are located mainly in the River Brue Estuary<br />

and Combwich Pill, although recreational activity tends to be focused around Burnhamon-Sea.<br />

7.8.3 As indicated on Figure 14, vessels inbound for the River Parrett and the Port of<br />

Bridgwater pass to the west and south of the Bell Gore Buoy, having due regard for the<br />

Cobblers Patch Shoal of -1.8m CD, which is located 2.5 cables south-south-west of Bell<br />

Gore. This route means vessels would pass directly north of the proposed jetty<br />

development’s location at <strong>Hinkley</strong> <strong>Point</strong>.<br />

7.8.4 The Bridgwater Bay Danger Area (D119) establishes the air space allocated for military<br />

activities and covers a circular area over land in West Somerset and sea in Bridgwater<br />

Bay. Its extent over the sea is marked on Admiralty Charts (as “Firing Practice Area<br />

D119”) and covers a partial circular area offshore that could be defined by an arc<br />

extending from <strong>Hinkley</strong> <strong>Point</strong> to beyond the 10m bathymetric contour towards Culver<br />

Sands and returning to land at Watchet. The Danger Area is a delineation of the air<br />

space above the water and does not place any restrictions on navigation and vessels<br />

have the right to transit it at any time.<br />

7.8.5 The Lilstock Range Firing Area is smaller than and is situated within D119 but only<br />

extends over the sea in Bridgwater Bay. Similar to D119, the firing area covers a partial<br />

circular area offshore that could be defined by an arc extending from east of <strong>Hinkley</strong><br />

<strong>Point</strong> and returning to land to the west of Watchet. The firing area delineates the water<br />

surface template for air to surface gunnery activities and is marked by buoys. The firing<br />

area is used primarily for military helicopter gunnery training and is operated under a<br />

clear range procedure so that exercises and training only take place when the area is<br />

clear of vessels.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 41 November 2010


Figure 14 Commercial Shipping Movements in the Bristol Channel<br />

7.8.6 According to the Port of Bridgwater’s Marine Operations Plan (2009), no commercial<br />

fishing vessels are registered at the port or on the River Parrett, although there is one<br />

vessel that can be chartered for angling. Vessel tracking and sighting by the Marine and<br />

Fisheries Agency (MFA); now part of the MMO) indicates that fishing activity in<br />

Bridgwater Bay is very limited since fishing with vessels of 15m and more is confined<br />

mainly to the west of a north to south line between Bideford (north Devon) and Swansea<br />

(south Wales), and fishing activity to the east of this line is much reduced, particularly<br />

east of a north to south line through Lynmouth (north Devon).<br />

7.8.7 Data derived from the Royal Yachting Association (RYA) and Cruising Association<br />

indicate that the water area surrounding <strong>Hinkley</strong> <strong>Point</strong> and the inner Bristol Channel as a<br />

whole is a designated sailing area for recreational craft, and the water area<br />

approximately 3.5nm to the west of <strong>Hinkley</strong> <strong>Point</strong> is used for racing. According to the<br />

Port of Bridgwater’s Marine Operations Plan (2009), there are three sailing clubs within<br />

the Port of Bridgwater. Combwich Cruising Club is based at Combwich and the Burnham<br />

Motor Boat & Sailing Club is based on the River Brue. Both clubs have afloat moorings.<br />

The Burnham Boat Owners’ Sea Angling Association has a substantial membership but<br />

only small boats, which members launch from Burnham Slipway when required. Some<br />

visiting yachts call each year. The inbound route to Burnham Motor Boat & Sailing Club<br />

passes to the north of the proposed jetty development site in a similar manner to<br />

commercial shipping.<br />

Main Predicted Impacts<br />

7.8.8 Impacts on navigation are assessed on the basis of risks of hazards to navigation.<br />

Hazards were identified during a specialist workshop with key stakeholders. Risk<br />

assessments are based on the potential consequences and likelihoods of the hazards<br />

identified on navigation receptors (i.e. commercial vessels, military vessels, fishing<br />

vessels, recreational vessels and the Port of Bridgwater’s interests).<br />

7.8.9 For the risk assessments, the potential consequences are considered to be severe for<br />

commercial vessels and the Port of Bridgwater’s interests, and minor for military, fishing<br />

and recreational vessels. The potential likelihoods are considered to be medium for<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 42 November 2010


commercial vessels and the Port of Bridgwater’s interests and very low for military,<br />

fishing and recreational vessels. The application of these hazard components means<br />

that risks to commercial vessels and the Port of Bridgwater’s interests are assessed as<br />

high and, therefore, unacceptable, and that risks to military, fishing and recreational<br />

vessels are assessed as low and, therefore, acceptable.<br />

7.8.10 The jetty development (including the presence and movement of construction plant and<br />

materials) would be constructed within Danger Area D119 and within or close to the<br />

Lilstock Range Firing Area. Although there are no restrictions on navigation within these<br />

areas, the firing range is only used when it is clear of vessels. Therefore, depending on<br />

the presence of the jetty development and construction plant in the firing area and / or the<br />

proximity of the jetty development and construction plant to the firing area, the jetty<br />

development’s construction activities could preclude the use and/or the safe use of the<br />

firing area for military training and exercises. Based on informal consultation with the<br />

MoD, it is anticipated that interference to military activities would be high / unacceptable if<br />

the jetty and/or construction plant were to be present within or directly adjacent to the<br />

firing area during construction activities.<br />

Mitigation<br />

7.8.11 A number of control measures are proposed as mitigation to reduce risks such that they<br />

are acceptable. During the jetty development’s construction, dismantling / restoration<br />

and (if required) removal / reinstatement phases, an exclusion zone of some 500m would<br />

be in place around the jetty head (see Figure 15) and it may be prudent to implement a<br />

standby vessel (small patrol vessel) during working hours.<br />

7.8.12 Control measures are also recommended to reduce the risk to navigation associated with<br />

the passage of dredging plant between the jetty and the Cardiff Grounds offshore<br />

disposal site. Dredging plant should not cross vessels that may be restricted by their<br />

draught or restricted by their ability to manoeuvre, and should, at all times, pass to the<br />

west of Bell Gore and Cobbler Patch, with due regard given to the shoal patch of 18m.<br />

7.8.13 Once constructed, the jetty would have to be marked (e.g. lights on the jetty head) for<br />

safety (e.g. to reduce the risk of passing vessels colliding with it). To reduce the risk to<br />

navigation associated with the presence and movement of the vessels using the jetty, it is<br />

recommend that navigation information be clearly documented in a Safety Management<br />

System (SMS).<br />

7.8.14 On the basis of consultation with the MoD, the following measures are proposed in<br />

relation to the Lilstock Range Firing Area:<br />

• the buoys delineating the firing area are to be moved westwards within Danger Area<br />

D119’s boundary such that the firing area is temporarily re-positioned away from the<br />

jetty development;<br />

• operational and maintenance plant, vessels and other marine equipment associated<br />

with the jetty development’s operation activities including maintenance works are to<br />

be instructed to avoid entering the firing area (even if, for example, transiting the<br />

firing area offers a more direct route to and from the jetty) by means of Notices to<br />

Mariners and other instructions from the Harbour Master; and<br />

• the proposed HEO (which is part of the application) will include provisions that will<br />

only allow the jetty development’s harbour authority (i.e. the authority that would be<br />

established by the HEO) to make by-laws affecting navigation in the authority's limits<br />

of jurisdiction around the jetty and to give general directions to vessels navigating<br />

within those limits subject in both cases to prior consultation with the MoD.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 43 November 2010


Figure 15 Proposed Exclusion Zone<br />

Residual Impacts<br />

7.8.15 With the controls in place, the residual risks to commercial vessels, the Port of<br />

Bridgwater’s interests and the MoD’s military activities are assessed as moderate and,<br />

therefore, as low as reasonably practicable (ALARP), and the residual risks to military,<br />

fishing and recreational vessels are assessed as low and, therefore, acceptable (subject<br />

to negotiation).<br />

8 OVERVIEW OF PREDICTED IMPACTS ON THE NATURAL AND PHYSICAL<br />

ENVIRONMENT<br />

8.1 Coastal Hydrodynamics and Geomorphology<br />

Existing Environment<br />

8.1.1 The wave cut platform at <strong>Hinkley</strong> <strong>Point</strong> comprises the cliff units that extend from the cliff<br />

towards the north. The units are shallow dipping and are aligned approximately parallel<br />

with the cliff. Shingle / boulders collect in the troughs behind the limestone scarp<br />

surfaces. The boulders are predominantly limestone, originating from the erosion of the<br />

limestone within the vicinity of their deposition on the foreshore. Where the shale is<br />

thicker, the ridges are larger and are often characterised by a veneer of mud and<br />

seaweed. Nearing low tide the limestone becomes increasingly heavily weathered and<br />

individual units are more difficult to trace.<br />

8.1.2 Erosion of the cliff line is influenced by storm events, and therefore the rate of recession<br />

may not be consistent from year to year. In addition to wave undercutting, it is likely that<br />

the cliffs also fail due to excess groundwater pressures behind the face of the cliff. The<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 44 November 2010


cliff at the location of the proposed jetty development contains evidence to indicate that<br />

the inter-bedded limestones and shales of the Blue Lias cliff top have retreated at around<br />

0.13m/yr since 1888, and mean high water mark by around 0.04m/yr.<br />

8.1.3 Sediment transport within the inter-tidal area comprises mud moving as suspended<br />

sediment, sand moving in suspension and as bed load, and gravel and coarser particles<br />

moving on the upper part of the rock platform as bedload. The most obvious evidence of<br />

coastal sediment transport at <strong>Hinkley</strong> <strong>Point</strong> (coarse grained sediment) is shown by the<br />

ridge of shingle and coarser particles at the crest of the beach immediately west of the<br />

existing seawall protecting the current <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex. The<br />

seawall projects out approximately 10 to 20m from the cliff line further west and it is likely<br />

that, due to the longshore drift of this coarse beach sediment, the accumulation of a<br />

wider shingle beach here compared to elsewhere has occurred. The existing seawall at<br />

<strong>Hinkley</strong> <strong>Point</strong> is not considered to be acting as a barrier to hinder shingle transport<br />

around <strong>Hinkley</strong> <strong>Point</strong>.<br />

8.1.4 Further offshore in Bridgwater Bay, there is a large variation in the type and distribution of<br />

seabed sediment along the coastline in front of <strong>Hinkley</strong> <strong>Point</strong>. Sediments generally range<br />

from finer sediment in the east (around Bridgwater Bay) to coarser material in the west.<br />

The seabed sediments immediately offshore of <strong>Hinkley</strong> <strong>Point</strong> are described as a thin<br />

muddy veneer overlaying the bedrock.<br />

8.1.5 The suspended sediment concentrations in the Severn Estuary result from the strong<br />

tidal currents and are generally exceptionally high, creating a turbid environment. A field<br />

campaign by Ravensrodd Consultants found suspended sediment concentrations within<br />

the Bristol Channel within the range of less than 100mg/l to approaching 200,000mg/l<br />

(fluid mud). This range of suspended sediment concentrations was also reported around<br />

<strong>Hinkley</strong> <strong>Point</strong> following four monitoring campaigns over the winter of 2008/2009. This<br />

monitoring recorded a maximum suspended sediment concentration of 1,795mg/l, a<br />

mean concentration of 264mg/l, and a minimum concentration of 33mg/l. Although some<br />

increase with depth was observed, the water column was well mixed. Both the values<br />

and distribution of suspended sediment concentrations show differences between spring<br />

and neap tides.<br />

8.1.6 Monitoring found tidal currents of <strong>Hinkley</strong> <strong>Point</strong> to be generally orientated along the main<br />

axis of the estuary (i.e. shore-parallel), with currents reaching a maximum velocity of<br />

1.7m/s on spring tides and 1.4m/s on neap tides at an offshore monitoring location. The<br />

inshore monitoring site showed peak currents to attain only 1.5m/s on spring tides and<br />

1.0m/s on neap tides. At all locations ebb currents were stronger than flood currents.<br />

Main Predicted Impacts<br />

8.1.7 During the jetty development’s construction, piling could disturb sediment so the chosen<br />

piling technique to be employed (specific methodologies would be confirmed by<br />

contractors) would minimise the degree of sediment disturbance, through the choice of<br />

access method and type of piling.<br />

8.1.8 In addition, the dredged berthing pocket could be subject to sediment deposition.<br />

However, the proposed design of the berthing pocket (i.e. its specific alignment relative to<br />

the tidal flows) has been chosen in order to encourage hydrodynamic conditions that<br />

promote self-scouring of this dredged area and, therefore, to reduce the requirement for<br />

frequent maintenance dredging during the jetty development’s operational phase.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 45 November 2010


8.1.9 The overall design of the jetty structure and other design elements, such as the exact<br />

positioning of the jetty, the orientation of the berthing pocket and the number of piles and<br />

uprights have been chosen to minimise environmental impacts. Nevertheless, during its<br />

operational phase, the presence of the jetty would have an effect on local hydrodynamic<br />

and sediment transport processes. The piles associated with the jetty would cause local<br />

hydraulic changes in the tidal flow around each support which have been assessed to be<br />

of negligible significance and do not require specific mitigation.<br />

8.1.10 Overall, all potential impacts on coastal hydrodynamic and geomorphology receptors<br />

during the jetty development’s construction, operation and dismantling and restoration<br />

phases and, if required, its removal and reinstatement phase have been assessed to be<br />

of minor or negligible significance prior to implementation of mitigation measures. This is<br />

primarily due to the very low or low magnitude of change predicted to occur on<br />

hydrodynamic and sediment transport processes as a result of the jetty development.<br />

Mitigation<br />

8.1.11 The overall design of the jetty’s structure and other design elements (e.g. the exact<br />

positioning of the jetty, the orientation of the berthing pocket and the number of piles and<br />

uprights0 have been chosen to minimise environmental impacts.<br />

8.1.12 Mitigation measures identified may be viewed as best practice, rather than as necessarily<br />

required. Where best practice mitigation measures can be implemented, this would<br />

further reduce the potential impact on hydrodynamic processes, sediment transport<br />

processes and geomorphological receptors.<br />

8.1.13 Where possible, the chosen piling technique to be employed (specific methodologies<br />

would be confirmed by contractors) would minimise the degree of sediment disturbance,<br />

through the choice of access method and type of piling.<br />

Residual Impacts<br />

8.1.14 No significant impacts are predicted after mitigation.<br />

8.2 Marine Ecology<br />

Existing Environment<br />

8.2.1 The application site is fronted by the rocky foreshore of the Severn Estuary. To the east<br />

are large areas of inter-tidal mudflats and saltmarsh in Bridgwater Bay and bordering the<br />

estuary of the River Parrett.<br />

8.2.2 The Severn Estuary is an important nature conservation area and supports a number of<br />

international, national and local designations for wetland habitats, bird populations and<br />

the presence of other habitats and species of conservation interest. The extreme natural<br />

environmental conditions in the estuary strongly influence the species and habitats that<br />

are present in the inter-tidal and sub-tidal zones. While these species and habitats are<br />

characteristic of other UK estuaries, they are less abundant in the Severn Estuary due to<br />

sediment surface instability and extremely high turbidity levels. The high turbidity levels<br />

also limit the densities of phytoplankton and zooplankton (i.e. micro-organisms in the<br />

water column).<br />

8.2.3 The foreshore in front of, and either side of, <strong>Hinkley</strong> <strong>Point</strong> B is dominated by a shelving<br />

rocky shore which supports relatively few marine species. The turf areas formed by the<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 46 November 2010


ed alga Corallina is the main habitat of importance. The honeycomb worm Sabellaria is<br />

also present. Aggregations of Sabellaria, forming reefs, are of importance as these<br />

provide habitat for many other organisms. In its reef form, Sabellaria is protected under<br />

the EC Habitats Directive, and some areas of reef exist approximately 200m and 300m<br />

offshore.<br />

8.2.4 The sub-tidal habitats, which are either always submerged or only briefly exposed at<br />

extremely low tides, consist of extensive areas of muddy sediments, and are dominated<br />

by a few species including bivalve molluscs, polychaete worms and crustaceans. The<br />

brown shrimp is abundant and provides an important food source for a number of fish<br />

species and birds.<br />

8.2.5 A variety of fish species live permanently within or migrate through the estuary, including<br />

some that are protected under European Directives and/or national legislation (e.g.<br />

Atlantic salmon, twaite shad, allis shad, river lamprey, sea lamprey, sea trout and eel).<br />

Bridgwater Bay is considered to be an important nursery area for juvenile fish and a<br />

number of fish species utilise the inter-tidal areas.<br />

8.2.6 There are no resident populations of marine mammals within the estuary although a<br />

number of species may feed there at different times of the year. The harbour porpoise is<br />

the most commonly recorded marine mammal species.<br />

Main Predicted Impacts<br />

8.2.7 The following potential impacts on marine ecological receptors could arise during the jetty<br />

development’s construction phase:<br />

• temporary and permanent loss of sensitive marine receptors;<br />

• physical disturbance of marine receptors due to piling activities at each jetty upright<br />

and to provide access for vehicle and plant, the delivery of materials and the<br />

workforce;<br />

• changes in cross-shore and longshore, inter-tidal drainage patterns and associated<br />

effects on Corallina;<br />

• physical disturbance due to dredging around the seaward end of the jetty (including<br />

impacts associated with the re-suspension within the water column of bottom<br />

sediments such as smothering etc.);<br />

• other water quality impacts due to run-off during construction and potentially<br />

associated with other accidents and incidents (particularly spillage and leaks of fuels<br />

and oils and possibly other chemicals, including cement and concrete if it is used in<br />

the jetty construction);<br />

• noise and vibration; and<br />

• artificial light disturbance during 24 hour construction works.<br />

8.2.8 One potentially significant adverse impact has been indentified in relation to physical<br />

disturbance caused during the jetty development’s construction phase. Piling, dredging<br />

and the use of construction plant and materials could disturb the physical environment<br />

(and its species and habitats) and drainage characteristics of the inter-tidal area in and<br />

around the site of these works. While most species of invertebrates, fish and marine<br />

mammals would not be significantly affected, the red alga species Corallina could be<br />

significantly affected by physical disturbance (i.e. interruptions) to the inter-tidal crossshore<br />

drainage channels where it is present (see Figure 16); although the jetty’s location<br />

has been chosen such that it avoids key areas of Corallina habitat (i.e. the turf areas) that<br />

occur more regularly to the east. An impact of moderate significance is predicted as a<br />

result of the medium sensitivity of Corallina and the medium magnitude of the impact.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 47 November 2010


Figure 16 Distribution of Corallina in relation to the <strong>Jetty</strong> Development<br />

8.2.9 During the jetty development’s operational phase, impacts on marine ecology could arise<br />

as a result of maintenance dredging (if required), noise and vibration, artificial light and<br />

water quality effects. No significant impacts have been identified on marine ecological<br />

receptors during this phase.<br />

8.2.10 During the jetty development’s dismantling / restoration phase, or removal / reinstatement<br />

phase (if required), impacts on marine ecology could arise from loss of and disturbance<br />

to inter-tidal and sub-tidal habitat (e.g. due to removal of each jetty upright, access for<br />

construction vehicles and plant) and water quality effects. No significant impacts have<br />

been identified on marine ecological receptors during this phase.<br />

Mitigation<br />

8.2.11 Specific mitigation measures are proposed to protect Corallina habitat and the species<br />

associated with it from physical disturbance during the construction and dismantling /<br />

restoration phases, or the removal / reinstatement phase (if required). These include<br />

establishment of a narrow working corridor across the inter-tidal area to avoid areas of<br />

Corallina where possible, and measures to ensure that the drainage environment of<br />

Corallina is not compromised by piling activities.<br />

8.2.12 All other impacts on marine ecological receptors have been assessed as being of minor<br />

or negligible significance, and hence no further specific mitigation is required. However,<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 48 November 2010


in recognition of the importance and protected status of the nearby marine environment,<br />

a number of good practice and precautionary measures are proposed to provide<br />

additional safeguards. These include the designation of “no-go” areas and associated<br />

buffer zones around all identified sensitive locations; buffer zones around construction<br />

and access sites in foreshore areas; provision of training for the construction workforce;<br />

specific accident and incident response and cleanup procedures; and implementation of<br />

a monitoring programme.<br />

Residual Impacts<br />

8.2.13 No significant impacts are predicted after mitigation.<br />

8.3 Terrestrial Ecology and Ornithology<br />

Existing Environment<br />

8.3.1 The application site has been subject to extensive vegetation survey work, together with<br />

surveys of a wide range of animal species including bats, otter, badger, reptiles,<br />

amphibians, birds and invertebrates. In addition, extensive bird survey work has been<br />

carried out on the coastal area that forms part of the Severn Estuary Special Protection<br />

Area (SPA), which is protected at the European level because of the importance of its<br />

bird populations. This coastal area is also part of the Severn Estuary Special Area of<br />

Conservation (SAC) and Ramsar site, as well as being part of several Sites of Special<br />

Scientific Interest (SSSIs) (see Figure 17).<br />

8.3.2 The land in and around the application site comprises open, gently rolling mixed lowland<br />

farmland with hedgerows, small scrubby woodlands and occasional standard trees.<br />

Although much of the area is intensively managed, small areas of species-rich limestone<br />

grassland occur along the cliff edge and the immediate vicinity of the <strong>Hinkley</strong> <strong>Point</strong> Power<br />

Station Complex. The northern site boundary lies adjacent to the Bristol Channel from<br />

which it is separated by a low cliff. The application site also includes seven hedgerows,<br />

five of which are species-rich, support at least five woody species, and are ecologically<br />

‘important’ under the Hedgerow Regulations, 1997.<br />

8.3.3 Fifteen species of wetland birds were recorded feeding or roosting in the intertidal area in<br />

the vicinity of the application site, with five of these also being recorded feeding or<br />

roosting in the fields within the site. A total of 18 species of breeding bird have been<br />

recorded on the site.<br />

8.3.4 A minimum of seven bat species have been recorded using the application site and one<br />

small roost is present in a derelict barn. Badgers are present within the application site<br />

and there is potential for otter to make very occasional use of the <strong>Hinkley</strong> <strong>Point</strong> C<br />

Drainage Ditch.<br />

Main Predicted Impacts<br />

8.3.5 Drawing upon the results of the surveys and other data gathering, and informed by<br />

consultation with Natural England, the RSPB, Somerset County Council, Somerset<br />

Wildlife Trust and West Somerset Council, the jetty development’s design has been<br />

progressively refined to minimise the adverse impacts on wildlife and, where possible, to<br />

deliver benefits. The changes to the scheme include:<br />

• avoidance of mature woodland and use of existing field accesses to avoid impacts on<br />

hedgerows;<br />

• changes to <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch being restricted to one culvert extension;<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 49 November 2010


• production of an updated <strong>Hinkley</strong> Integrated Land Management Plan (ILMP) detailing<br />

the protection and management of retained habitat features;<br />

• vegetation clearance would, where possible, take place in the period January - March<br />

(inclusive), which is outside of the core breeding season for all of the bird species that<br />

have been recorded breeding within the site - where this is not possible, clearance<br />

would only be undertaken once surveys have shown that either no active nests are<br />

present or that any breeding birds have fledged from the areas to be cleared;<br />

• implementation of best practice measures to minimise emissions and dust deposition;<br />

and<br />

• a simple jetty design that is likely to reduce the potential for bird collisions.<br />

8.3.6 Other measures are put forward as proposed mitigation. These are described and the<br />

residual impacts are assessed below.<br />

8.3.7 During the construction phase, there is the potential for birds using the inter-tidal areas<br />

close to the jetty and foreshore access location to be adversely affected by noise<br />

generated by the jetty development, changes in inter-tidal plant / animal communities<br />

caused by discharges from the site, visual disturbance caused by the workforce that<br />

undertakes the jetty development and their machinery, and lighting. However, these<br />

effects are predicted to have a very low magnitude impact on birds using inter-tidal areas<br />

and not be significant, despite the high value populations associated with the Severn<br />

Estuary SPA and Ramsar Site and the Bridgwater Bay SSSI.<br />

8.3.8 Terrestrial vegetation removal during the jetty development’s construction phase would<br />

mean that the cleared areas would no longer be likely to support any of the bird species<br />

that currently breed on the site, including skylark (eight pairs), linnet (three pairs),<br />

dunnock (five pairs) and song thrush (one pair). However, the loss of habitat for breeding<br />

birds would not have an adverse impact on the conservation status of the species<br />

concerned. On this basis, the loss of habitat and breeding birds would be a minor<br />

adverse impact.<br />

8.3.9 The jetty development’s construction phase would result in the loss of one ephemeral<br />

common pipistrelle roost located in a disused, derelict barn. Given the low status of the<br />

roost and the common species recorded using the barn, its loss is unlikely to affect the<br />

conservation status of the local bat population.<br />

8.3.10 The stripping of topsoil and the removal of hedgerows across the application site would<br />

result in the loss or reduction in size of the territories of up to three badger social groups<br />

and the destruction of one sett. In the absence of mitigation, this would result in the<br />

contravention of the law pertaining to badgers, which would cause a major adverse<br />

impact.<br />

8.3.11 No significant impacts are predicted to arise in relation to otters, reptiles and<br />

invertebrates using habitats within the study area during the jetty development.<br />

8.3.12 Losses of grassland, pond and hedgerow habitat, loss of 10% of the <strong>Hinkley</strong> County<br />

Wildlife Site and disturbance to the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch and a small area of<br />

limestone grassland are also predicted to occur. However, none of these effects are<br />

predicted to be significant.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 50 November 2010


Figure 17 Designated Nature Conservation Areas in relation to the <strong>Jetty</strong> Development’s Application Site<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works <strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 51 November 2010


8.3.13 Fewer potential impacts are predicted to arise during the jetty development’s operation<br />

and dismantling and restoration phases or, if required, its removal and reinstatement<br />

phase, namely:<br />

• adverse impacts on intertidal birds resulting from disturbance caused by ships<br />

docking to unload cargo, and from human activity, light and noise along and on route<br />

to the jetty;<br />

• disturbance to bats as a result of site lighting; and<br />

• restoration (or, if required, reinstatement) of the site, resulting in the creation of<br />

habitats which would subsequently be available for colonisation by wildlife.<br />

8.3.14 Similarly, none of these potential impacts are predicted to be significant.<br />

Mitigation<br />

8.3.15 Construction of the jetty development would be undertaken and, as appropriate,<br />

scheduled in such a way as to avoid or reduce impacts on birds using the inter-tidal<br />

areas (e.g. piling on the foreshore would be scheduled to take place over the summer<br />

period from July to September as far as possible). In addition, the construction works on<br />

the inter-tidal area would be constantly rather than intermittently lit each night through the<br />

use of directional lighting so that light spill is limited and birds can habituate to the light.<br />

8.3.16 To ensure compliance with the legal protection afforded to bats, destruction of the barn<br />

with confirmed bat interest would be undertaken in accordance with a method statement<br />

that is agreed with Natural England, in the context of a derogation licence. In addition, a<br />

strategy would be implemented to ensure that lighting is designed to have minimal<br />

impacts on bats, whilst being compliant with safety and security criteria.<br />

Residual Impacts<br />

8.3.17 No significant impacts are predicted after mitigation.<br />

8.4 Water Quality<br />

Existing Environment<br />

8.4.1 A review of literature has been used to derive an overview of the marine surface water<br />

quality conditions. In addition, the results of surface water sampling campaigns carried<br />

out in 2009 have been used to inform the baseline conditions. The two key receptors<br />

identified for potential impacts arising from the jetty development are the freshwater<br />

quality status of the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch and the marine water quality status of<br />

the Severn Estuary.<br />

8.4.2 Onshore, the jetty development’s application site includes a series of interconnecting<br />

agricultural drainage ditches that drain the land and discharge to the <strong>Hinkley</strong> <strong>Point</strong><br />

foreshore. The primary watercourse of relevance to the jetty development is known as<br />

the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch. This watercourse is supplied with water from surface<br />

drainage running off from surrounding agricultural land. Its water quality status is<br />

characterised by highly variable water quality conditions, including elevated<br />

concentrations of suspended solids. In addition, it is known to dry out during prolonged<br />

periods without rainfall.<br />

8.4.3 Offshore, the water quality status of the inter-tidal area at <strong>Hinkley</strong> <strong>Point</strong> is variable<br />

according to tidal conditions. Under high tide conditions the inter-tidal area is inundated<br />

with water that is characterised by high concentrations of suspended solids. Given the<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 52 November 2010


high tidal range, there is a large dilution capacity available to buffer other suspended<br />

solids and other potential water quality impacts during high tide periods and the overall<br />

water quality status sensitivity is low. The sensitivity of the inter-tidal water quality status<br />

is increased during low tide periods when water is retained in pools and foreshore<br />

channels that support marine ecology. During these periods there is reduced dilution<br />

capacity to potential impacts from foreshore discharges and an increased sensitivity.<br />

8.4.4 The sub-tidal areas off <strong>Hinkley</strong> <strong>Point</strong> are characterised by high suspended solids<br />

concentrations due to sediment mobilisation under high tidal flows. The tidal disturbance<br />

of the sediments would also lead to mobilisation of any associated sediment<br />

contaminants into the well-mixed water column. It has been shown that disturbance of<br />

the superficial sediments in the area around <strong>Hinkley</strong> <strong>Point</strong> has a low influence on<br />

chemical water quality status.<br />

8.4.5 In terms of sediment quality, survey data indicate the presence of elevated metal and<br />

hydrocarbon concentrations, but very few of the metal concentrations recorded would be<br />

considered to be significantly contaminated. It is suggested that elevated metal<br />

contamination in surface sediment may be representative of wider baseline<br />

concentrations and the result of contaminant redistribution from elsewhere in the Bristol<br />

Channel. Concentrations of other organic substances were found to be generally present<br />

at low concentrations.<br />

Main Predicted Impacts<br />

8.4.6 The impact assessment found that there is the potential for water quality status to be<br />

adversely affected as a result of a range of activities associated with the jetty<br />

development. The impacts that have been identified during the construction of the jetty<br />

may be broadly divided into:<br />

• disturbance of marine sediment and mobilisation of associated contaminants into the<br />

Severn Estuary (e.g. due to dredging of the berthing pocket or scouring around the<br />

jetty’s piles);<br />

• discharge of water containing sediment, hydrocarbons and/or concrete leachates into<br />

the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch and the Severn Estuary (e.g. surface water run-off<br />

from the onshore storage area);<br />

• discharge of freshwater onto the foreshore where Corallina is present in drainage<br />

channels; and<br />

• accidents and incidents.<br />

8.4.7 During construction of the jetty no significant impacts are predicted to arise in relation to<br />

water quality due to the measures that would be put in place to control the quality and<br />

volume of discharges into the surface drainage (i.e. the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch)<br />

and onto the foreshore and the waters of the Severn Estuary. In addition, the sensitivity<br />

of the local marine water quality conditions to increases in suspended solids is low given<br />

the existing high background concentrations.<br />

8.4.8 The impacts associated with the operation of the jetty are likely to arise from<br />

maintenance dredging of the berthing pocket, scouring of sediment from the seabed<br />

around the jetty’s infrastructure (e.g. piles and berthing pocket), and freshwater<br />

discharges into the marine environment from the onshore storage area. However, the<br />

impacts assessed would be of negligible or minor significance.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 53 November 2010


8.4.9 Impacts associated with dismantling and restoration phase and, if required, the removal /<br />

reinstatement phase would be in similar to those described for the construction phase,<br />

with no significant impact predicted.<br />

Mitigation<br />

8.4.10 Due in part to the design measures associated with the jetty development (e.g. oil water<br />

separator and a water management zone for the aggregates storage area), all of the<br />

identified impacts on water quality were found to be not significant (i.e. minor and<br />

negligible impacts) prior to implementation of mitigation measures. Nevertheless,<br />

mitigation measures will be adopted on the basis of a precautionary approach to<br />

protection of the environment. Mitigation measures include:<br />

• the application and accordance with discharge consent conditions for discharges to<br />

the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch and the Severn Estuary;<br />

• the adoption of the best practice guidance for works in and adjacent to<br />

watercourses, as provided in the Environment Agency’s Pollution Prevention<br />

Guidelines (PPGs);<br />

• the implementation of a surface drainage strategy for the onshore areas including<br />

measures to minimising generation of sediment-laden surface drainage water and<br />

potential impacts on the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch (e.g. settlement ponds to<br />

reduce suspended solids and oil interceptors to recover hydrocarbons); and<br />

• the implementation of a wide range of environmental protection measures and<br />

monitoring detailed in the Water and Sediment Management Plan which forms part<br />

of the EMMP.<br />

Residual Impacts<br />

8.4.11 No significant impacts are predicted after mitigation.<br />

8.5 Hydrology and Drainage<br />

Existing Environment<br />

8.5.1 There are a number of controlled waters in the <strong>Hinkley</strong> <strong>Point</strong> area; however, the only<br />

fluvial watercourse of relevance to the jetty development is the <strong>Hinkley</strong> <strong>Point</strong> C Drainage<br />

Ditch. The ditch is designated as an Ordinary Watercourse (i.e. it is not a Main River).<br />

The <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch’s contributing catchment (78.3ha) is undulating with<br />

generally shallow slopes. It runs from west to east with its source at 14.5m AOD until its<br />

alignment is rotated through 90° such that it flows from south to north where it discharges<br />

onto the foreshore. Flow in the ditch is intermittent / ephemeral (i.e. it does not flow all<br />

year round).<br />

8.5.2 There is no fluvial flooding indicated on the Environment Agency’s Flood Map; however,<br />

flooding from catchments of less than 3km 2 is not shown so it is possible that some fluvial<br />

flooding could occur along the ditch’s margins.<br />

8.5.3 A Flood Risk Assessment has been carried out in accordance with PPS25. It can be<br />

found in Appendix 13-1 in Volume 4. On the basis of the information presented in this<br />

FRA, and subject to its recommendations being implemented, it is concluded that the<br />

jetty development at <strong>Hinkley</strong> <strong>Point</strong> is appropriate on the grounds that all flooding risks<br />

and residual risks have been given due consideration and are found to be acceptable.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 54 November 2010


8.5.4 The <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch discharges to the foreshore and drains into the<br />

Severn Estuary except during very high tides when it will discharge directly into the<br />

Severn Estuary.<br />

Main Predicted Impacts<br />

8.5.5 The key impact would occur as a result of elevated surface water run-off from the jetty<br />

development’s onshore components, and particularly from the aggregates storage area<br />

and service road. It is proposed that this water would be discharged to the <strong>Hinkley</strong> <strong>Point</strong><br />

C Drainage Ditch and eventually to the foreshore and the Severn Estuary. Common<br />

types of potential hydrological and drainage impacts extend across a range of<br />

construction activities and have been grouped accordingly and include:<br />

• elevated surface water run-off;<br />

• elevated sediment delivery and deposition in watercourses; and<br />

• flooding of land off-site of the application site resulting from various sources, such as<br />

flooding as a result of elevated surface water run-off and flooding as a result of<br />

elevated sediment deposition in channels resulting in a reduced channel capacity.<br />

8.5.6 Onshore, the jetty development would have a surface water drainage system in place to<br />

control and manage surface water and sediment discharges associated with the<br />

aggregates storage area. This system would be designed to basic compliance criteria<br />

and, therefore, is not considered to be mitigation measure.<br />

8.5.7 No significant potential impacts (i.e. moderate or major impacts) were identified in<br />

relation to hydrology and drainage for the jetty development’s construction, operation and<br />

dismantling and restoration phases and, if required, its removal and reinstatement.<br />

Mitigation<br />

8.5.8 The impact assessment is based on the assumption of regulatory compliance and thus<br />

measures would be implemented to ensure regulatory compliance. These measures are<br />

presented within the Water and Sediment Management Plan, which forms part of the<br />

EMMP, and would be applied during the jetty development’s dismantling and restoration<br />

phase or, if required, its removal and reinstatement phase.<br />

8.5.9 Although the onshore aggregates storage area’s design includes for an operational<br />

drainage system, monitoring and maintenance and controls would be put in place for<br />

unusual conditions (contingency discharges and provision for emergency run-off).<br />

Residual Impacts<br />

8.5.10 No significant impacts are predicted after mitigation.<br />

8.6 Groundwater<br />

Existing Environment<br />

8.6.1 The groundwater regime at the jetty development’s application site is described as a<br />

Secondary A (Minor) aquifer (a rock formation that can bear or transmit water). Such<br />

aquifers can be “fractured or potentially fractured rocks, which do not have a high primary<br />

permeability, or other formations of variable permeability including unconsolidated<br />

deposits. Although these aquifers will seldom produce large quantities for abstraction,<br />

they are important both for local supplies and in supplying base flow to rivers”. The lower<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 55 November 2010


oundary on the active groundwater regime in the area may be the base of the Lilstock<br />

Formation of the Penarth Group, possibly less than 4m below the base of the Lower Lias.<br />

8.6.2 The groundwater is considered to be compartmentalised between the Green Lane area<br />

and the shoreline by an upfaulted inlier of low permeability Mercia Mudstones.<br />

Groundwater flow is essentially south-south-west to north-north-east discharging at some<br />

point at the foreshore or underwater up to several hundred metres offshore.<br />

8.6.3 Surveys show that the water tables rise in response to sustained rainfall during the winter<br />

months and then fall away again as recharge declines. Rainfall between spring and early<br />

autumn does not show a groundwater response, probably because available recharge is<br />

taken up by the growing soil moisture deficit and does not reach the unsaturated zone or<br />

the water table.<br />

8.6.4 It is apparent that groundwater in the application site is controlled by local rainwater<br />

recharge and topography as the groundwater contours reflect the topography. The<br />

<strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch, which flows west to east then turns north to discharge to<br />

the shoreline, receives groundwater baseflow and exerts significant control on<br />

groundwater levels.<br />

8.6.5 At high water table levels, groundwater ranges from around 20m AOD to 11m AOD from<br />

south to north across the western part of the application site. At low water table levels at<br />

the end of summer, groundwater ranges from around 14m AOD to 8m AOD in the same<br />

boreholes.<br />

8.6.6 There are no potable water abstractions and no associated Source Protection Zones<br />

within the application site. There are 17 licensed groundwater abstractions within several<br />

kilometres of the application site. All these wells and boreholes are for general farming<br />

and domestic purposes. The nearest abstraction is more than 0.5km from the western<br />

part of the application site. All the other abstractions are more than 2km from the<br />

western part of the application site.<br />

Main Predicted Impacts<br />

8.6.7 The principal activities associated with the jetty development that could affect<br />

groundwater are associated with the onshore works and particularly construction of the<br />

aggregates storage area, the soil storage areas and the rock extraction area. The<br />

anticipated impacts on groundwater receptors such as groundwater levels and resources<br />

during all phases of the jetty development have been assessed to be of negligible or<br />

minor significance.<br />

Mitigation<br />

8.6.8 Mitigation would be provided through implementation of the EMMP, which would ensure<br />

that best practice construction methods are adopted to minimise spillages and<br />

contamination. Monitoring programmes would be implemented as part of the EMMP to<br />

verify the behaviour and any movement of groundwater, in order to confirm the<br />

anticipated non-impacts.<br />

Residual Impacts<br />

8.6.9 No significant impacts are predicted after mitigation.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 56 November 2010


8.7 Soils and Land Use<br />

Existing Environment<br />

8.7.1 The topography of the application site is typical of that in the wider locality comprising<br />

mostly open, gently rolling, mixed lowland farmland with a series of east-west ridges of<br />

land. Improved grassland areas within the site are grazed annually as part of the<br />

management of the <strong>Hinkley</strong> <strong>Point</strong> County Wildlife Site, with other areas maintained in<br />

Good Agricultural and Environmental Condition (GAEC).<br />

8.7.2 The main soil type present (Evesham Soil Series) comprises soils which are slow<br />

draining and vulnerable to structural damage if worked when waterlogged. The<br />

application site and much of the surrounding area is covered by agri-environment<br />

schemes (Countryside or Environmental Stewardship Agreements).<br />

8.7.3 The application site is classified as Grade 3b (moderate quality) agricultural land, with the<br />

rock extraction area classified as non-agricultural land due to previous development<br />

associated with the <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex. The surrounding land is also<br />

predominantly Grade 3b with some Grade 3a (classified as best and most versatile land<br />

(BMVL) and some Grade 4 (poor quality agricultural land).<br />

Main Predicted Impacts<br />

8.7.4 Only the onshore elements of the jetty development are considered to have the potential<br />

to impact on soil and land use and, therefore, no assessment of the jetty’s offshore<br />

components has been made.<br />

8.7.5 Soil and land use impacts arising from the jetty development’s construction phase would<br />

primarily be associated with topsoil stripping, storage and handling, including the<br />

potential for damage to soil structure and profiles, loss of agricultural potential, loss of<br />

land for livestock and loss of land currently managed under agri-environment schemes.<br />

Since the affected soils are mainly heavy clays with relatively poor structure, soil<br />

compaction, and loss of soil structure could occur as soils are excavated, handled and<br />

stored for later re-use.<br />

8.7.6 Other jetty development activities, including construction of site access, site compound,<br />

service road to the foreshore and rock extraction would take place after topsoil stripping<br />

has occurred and, therefore, there would be no adverse impacts on soils and land use<br />

related to these activities.<br />

8.7.7 The anticipated impacts on soil quality and agricultural land use during all phases of the<br />

jetty development have been assessed to be of minor adverse significance.<br />

Mitigation<br />

8.7.8 Mitigation would be provided through implementation of the EMMP, which would ensure<br />

that best practice construction methods are adopted. As part of this, a Soil Management<br />

Plan (SMP) would be set in place to address all phases of the jetty development,<br />

containing measures for soil protection ahead of stripping, segregation and storage to<br />

protect soil quality and prevent loss of soil structure.<br />

8.7.9 These measures would also ensure appropriate biosecurity (disease and pest control),<br />

weed control, management of site run-off, erosion and dust generation to protect both on<br />

site soils and adjacent land holdings. As part of the landscape restoration and, if<br />

required, reinstatement, stockpiled soils and subsoils would be re-used to create suitable<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 57 November 2010


conditions for agricultural land and habitat creation. Appropriate reinstatement techniques<br />

would be set out in the SMP to ensure that well-managed and viable soil materials are<br />

available.<br />

Residual Impacts<br />

8.7.10 All potential impacts on soils and land use have been rated as minor before any<br />

mitigation has been applied. Nevertheless, mitigation measures are proposed to protect<br />

soil quality and prevent loss of soil structure.<br />

8.8 Geology and Contaminated Land<br />

Existing Environment<br />

8.8.1 The majority of the application site is not overlain by significant drift deposits. Intrusive<br />

investigations, have revealed that where drift deposits are present within the application<br />

site they are classified typically as slightly gravelly locally sandy silty clay to a sandy silt /<br />

clay and slightly sandy slightly gravely clay respectively. The solid geology in the locality<br />

of the application site predominantly comprises the Lower Lias of the Lias Group (Lower<br />

Jurassic) and the Triassic Penarth and Mercia Mudstone Groups.<br />

8.8.2 The Blue Anchor to Lilstock SSSI (see yellow outlined area on Figure 17) is designated<br />

for its geological and geomorphological interest. The exposed stratigraphic units along<br />

the cliff face are considered to be amongst the best examples of the Blue Lias outcrop in<br />

Europe and the SSSI’s geomorphological designation is for the exposed limestone rock<br />

pavement on the foreshore. The application site includes a small portion of the<br />

designated cliff and foreshore.<br />

8.8.3 In terms of contaminated land, while the application site has been and remains<br />

predominantly agricultural, some of its eastern part has been affected by development.<br />

Key features and potential pollution sources include the presence of historically infilled<br />

ponds, former sewage treatment works, a double mounded feature in the centre of the<br />

site containing surplus spoil from the construction of the <strong>Hinkley</strong> <strong>Point</strong> Power Station<br />

Complex, a former licensed waste management facility and the former fabrication /<br />

construction and accommodation areas with associated electrical substations and<br />

possible fuel oil storage tanks and boiler house.<br />

8.8.4 Contaminant concentrations found by intrusive investigations of shallow and deeper soils<br />

within the application site are considered to be consistent with natural background<br />

concentrations in the locality and typical UK background soil concentrations. The<br />

majority of the soils within the eastern part of the application site are considered to be<br />

suitable for the proposed end use given the incorporation of standard design mitigation<br />

measures where necessary (such as sulphate resistant concrete) and appropriate<br />

materials management and placement (e.g. not within top metre in some cases) during<br />

earthworks. The exceptions to this are the presence of asbestos containing materials<br />

(ACM) which have been identified at several locations on the eastern part of the<br />

application site. These materials have in almost all cases been identified as discrete<br />

pieces and fragments of ACM with very little evidence of any diffuse or free fibres<br />

identified in the site soils or associated with the ACM. The current risk from these ACM<br />

is considered to be low. In addition, all known areas of asbestos contamination would be<br />

removed during the enabling works prior to the commencement of the jetty development.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 58 November 2010


8.8.5 Gas monitoring data indicate that there are no significant sources of ground gas on the<br />

application site and, therefore, there is no significant risk posed to human health or<br />

buildings by ground gas given its current land use.<br />

Main Predicted Impacts<br />

8.8.6 The anticipated impacts on geological receptors have been assessed to be of negligible<br />

to minor adverse significance for all phases of the jetty development. A key impact on<br />

geology was considered in relation to the jetty development’s potential to affect the<br />

features (i.e. exposures) of the Blue Anchor to Lilstock SSSI. Only a small portion of the<br />

jetty would affect the SSSI and a geological mapping exercise has identified that the<br />

features affected by the jetty development can be observed and accessed elsewhere<br />

within the SSSI, such that there is no loss of the unique geology.<br />

8.8.7 The anticipated Impacts on contaminated land receptors (including soil, water, vegetation<br />

and human health) have been assessed to be negligible to minor adverse for all phases<br />

of the jetty development.<br />

Mitigation<br />

8.8.8 Despite no significant adverse impacts, the EMMP will include measures relating to the<br />

control of the release of potentially contaminated materials into the environment from<br />

their original source location. Certain standard control measures which are typically<br />

applied on construction sites are also effective at controlling the dispersion and creation<br />

of contamination. Typical measures will include standard measures to prevent<br />

contamination occurring from construction operations (e.g. appropriate use and storage<br />

of fuel oils and other chemicals and measures to control dust and surface run-off, etc.).<br />

8.8.9 No significant impacts to geology are predicted, however the foreshore is fossiliferous<br />

and, therefore, a pre-construction survey to identify any palaeontological finds of<br />

scientific importance would be undertaken on the area of the foreshore to be impacted by<br />

the jetty development (access road and piling).<br />

Residual Impacts<br />

8.8.10 No significant impacts are predicted after mitigation.<br />

9 CUMULATIVE EFFECTS<br />

9.1 Introduction<br />

9.1.1 The potential for cumulative impacts to occur as a result of the implementation of the jetty<br />

development with other projects is largely determined by the spatial and temporal<br />

characteristics of the works themselves and the nature of the environmental receptors<br />

that may be affected by the works. Relevant projects in this instance include the site<br />

preparation works, the proposed <strong>Hinkley</strong> <strong>Point</strong> C nuclear power station and several other<br />

plans and projects that have been scoped into the assessment process.<br />

9.2 Cumulative Effects with the Site Preparation Works<br />

9.2.1 The inclusion of the ground works for the onshore elements of the jetty development<br />

within the site preparation works effectively means that potential cumulative effects on<br />

onshore / terrestrial environmental receptors (e.g. soils and land use, terrestrial ecology,<br />

geology and contaminated land) would be, in most instances, no greater than for the site<br />

preparation works alone. With regard to the potential impact of noise generated during<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 59 November 2010


construction and changes in air quality, given the separation distance of the jetty<br />

construction works from the nearest residential properties, the cumulative effect would be<br />

no greater than that assessed solely for the site preparation works.<br />

9.2.2 For landscape and heritage issues, the addition of the land-based components of the<br />

jetty storage infrastructure and the jetty structure itself to the site preparation works has<br />

the potential to cause a cumulative effect. These structures are predicted to marginally<br />

increase the overall magnitude of change with respect to effects on local landscape<br />

character and visual sensitivity from some viewpoints. With respect to the setting of Wick<br />

Barrow, however, the combined impact magnitude is predicted to be no greater than that<br />

assessed for the site preparation works alone.<br />

9.2.3 From a recreation and amenity perspective, the coastal footpath would be obstructed and<br />

alternative routes put in place around the combined works. There would be a temporary<br />

increase in the visual impact to users of the coastal section to the west of the site as a<br />

result of the combined effect. However, views from the footpath would be limited to those<br />

that could be gained away from the immediate vicinity of the development site.<br />

9.3 Cumulative Effects with the <strong>Hinkley</strong> <strong>Point</strong> C Project<br />

During Construction of the <strong>Jetty</strong><br />

9.3.1 During construction there is only a very limited temporal overlap of approximately nine<br />

months between the jetty development’s construction phase and the <strong>Hinkley</strong> <strong>Point</strong> C<br />

construction works. This small overlap between the works effectively limits the potential<br />

for many cumulative impacts to occur. The negligible traffic volume and relevant air<br />

quality and noise effects associated with the jetty development would not be expected to<br />

represent a discernable difference from those associated with <strong>Hinkley</strong> <strong>Point</strong> C alone.<br />

9.3.2 For some receptors, such as landscape, heritage and amenity, there is the potential for<br />

the continuation or further modification of an impact due to the commencement of the<br />

<strong>Hinkley</strong> <strong>Point</strong> C construction works. However, given the short temporal overlap, the<br />

scope for any significant change is extremely limited and in reality the additional effect<br />

during this overlap period would be unlikely to lead to any greater impacts than those that<br />

could be attributed to the jetty development alone.<br />

9.3.3 For receptors within the footprint of the onshore components of the jetty development,<br />

such as terrestrial ecological interest, soils and landuse, buried archaeology, etc., there<br />

would be no cumulative impact with the commencement of the <strong>Hinkley</strong> <strong>Point</strong> C<br />

construction works. This is because these interests would be lost as a result of the jetty<br />

development’s construction and the site preparation works.<br />

During Operation of the <strong>Jetty</strong><br />

9.3.4 The overlap in time between the operational phase of the jetty and continued<br />

construction of <strong>Hinkley</strong> <strong>Point</strong> C would last approximately 7 years. The potential for<br />

cumulative impacts to arise with the jetty is significant due to the scale and complexity of<br />

the construction work for <strong>Hinkley</strong> <strong>Point</strong> C that would be undertaken during this period.<br />

However, these cumulative impacts would be temporary and would cease once the jetty<br />

had been dismantled, meaning that beyond this period the impacts would revert to those<br />

of the <strong>Hinkley</strong> <strong>Point</strong> C Project alone.<br />

9.3.5 These impacts would relate to the additive effects of the <strong>Hinkley</strong> <strong>Point</strong> C Project with<br />

regard to those environmental aspects that would either be affected outside of the<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 60 November 2010


footprint of the jetty development as this area would not be altered during by the <strong>Hinkley</strong><br />

<strong>Point</strong> C works during this phase of the jetty development, or which continue on from<br />

construction. The main aspects that fall into these categories are, in the first instance,<br />

landscape, heritage (setting) and amenity and with regard to the second category air and<br />

noise impacts.<br />

9.3.6 The building work for <strong>Hinkley</strong> <strong>Point</strong> C would significantly alter the local landscape and<br />

have wider visual impact. During the operational period for the jetty the visual impact of<br />

the jetty structure would combine with the <strong>Hinkley</strong> <strong>Point</strong> C reactor buildings to generate a<br />

greater visual impact than that of the jetty structure alone. While it could be argued that<br />

the visual and landscape impact would be due to the <strong>Hinkley</strong> <strong>Point</strong> C construction works,<br />

it would be difficult to separate out the combined elements of the jetty development and<br />

the new buildings such that specific impacts could be attributed to each. The total effect<br />

therefore has to be considered and in this context the cumulative impact would be<br />

greater than that attributable to the jetty development alone. This conclusion also applies<br />

to the setting of heritage interests where the jetty would form a significant component of<br />

the visible built form.<br />

9.3.7 Assessment of noise and air impacts for the jetty development indicates that they would<br />

be of limited significance during operation. Consequently, no greater cumulative impact is<br />

predicted with respect to these aspects during the overlap period with construction of<br />

<strong>Hinkley</strong> <strong>Point</strong> C.<br />

9.4 Cumulative Effects with Other Plans and Projects<br />

9.4.1 There are only a few projects in the wider environment that have could interact with the<br />

jetty development and potentially lead to cumulative impacts.<br />

9.4.2 At a regional level, the proposed Bristol Port Deep Sea Container Terminal project at<br />

Avonmouth is spatially so distant that cumulative effects would be confined to those that<br />

could only operate at a regional level. Apart from a negligible potential traffic / transport<br />

interaction between the jetty development / site preparation works and this project, no<br />

such effects have been identified. In proximity to the jetty development the<br />

decommissioning works for <strong>Hinkley</strong> <strong>Point</strong> A are of most relevance, while the continued<br />

operation of <strong>Hinkley</strong> <strong>Point</strong> B effectively forms part of the baseline against which impacts<br />

have been assessed for the jetty development.<br />

9.4.3 Available information for the <strong>Hinkley</strong> <strong>Point</strong> A decommissioning works shows that the<br />

majority of impacts would be confined to the footprint of the <strong>Hinkley</strong> <strong>Point</strong> A site and<br />

therefore outwith any spatial interaction with the jetty development. The cumulative<br />

socio-economic effects are considered to be no greater than the effects of jetty<br />

development / site preparation works alone since the contribution of <strong>Hinkley</strong> <strong>Point</strong> A is<br />

already included in the baseline.<br />

9.4.4 During operation of the jetty, there are a number of projects which temporally overlap. Of<br />

these, the proposed new nuclear power station at Oldbury is located at such a distance<br />

from <strong>Hinkley</strong> <strong>Point</strong> that the potential for any spatial interaction with the effects of the jetty<br />

is either non-existent or negligible. Potential overlap with the Steart Coastal Management<br />

Project would occur, but the lack of any significant spatial interaction and low magnitude<br />

effects associated with the jetty indicate that any cumulative effects would be negligible.<br />

For the transmission line upgrade into <strong>Hinkley</strong> <strong>Point</strong> C, there could be some interaction<br />

with regard to landscape and visual sensitivities however, the overall effect is unlikely to<br />

be significant. This is largely due to the fact that the combined landscape impact of the<br />

jetty and the transmission line upgrade would be significantly subsumed by the much<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 61 November 2010


greater landscape impact of the <strong>Hinkley</strong> <strong>Point</strong> C Project itself combined with the<br />

transmission line upgrade (i.e. in reality the transmission line upgrade is associated with<br />

the construction of <strong>Hinkley</strong> <strong>Point</strong> C).<br />

9.4.5 This assessment, therefore, concludes that any cumulative impacts with the potential to<br />

arise between the jetty development and other relevant projects would be negligible.<br />

10 CONCLUSION<br />

10.1.1 The majority of the impacts predicted to arise due to the jetty development are assessed<br />

to be of minor and negligible significance, particularly following mitigation. However, a<br />

few impacts are assessed to be significant (i.e. moderate or major adverse impacts).<br />

10.1.2 The key human and built environment impacts associated with the proposals for the jetty<br />

development at <strong>Hinkley</strong> <strong>Point</strong> are anticipated to arise from disturbance to users of public<br />

rights of way, changes to seascape and local and site landscape features, visual impacts<br />

along public rights of way, and effects on the setting of designated sites and features of<br />

cultural importance. These impacts are summarised in Section 7.<br />

10.1.3 The key impacts on the natural and physical environment, prior to mitigation, are<br />

summarised in Section 8, with the most significant adverse impact likely to arise from the<br />

disturbance to Corallina habitat and to badger habitat. Potential impacts on birds using<br />

inter-tidal areas are not predicted to be significant.<br />

10.1.4 As discussed in Sections 7 and 8, potentially significant effects could arise locally from<br />

the proposed development. However, care has been taken to avoid, reduce and mitigate<br />

potential adverse environmental effects as far as possible.<br />

<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />

<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />

Temporary <strong>Jetty</strong> Development 62 November 2010

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!