Jetty Non Technical Summary - EDF Hinkley Point
Jetty Non Technical Summary - EDF Hinkley Point
Jetty Non Technical Summary - EDF Hinkley Point
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Temporary <strong>Jetty</strong> Applications<br />
<strong>Hinkley</strong> <strong>Point</strong> C - Proposed Nuclear Development<br />
<strong>Non</strong>-<strong>Technical</strong> <strong>Summary</strong><br />
November 2010
[This page is intentionally left blank.]
CONTENTS<br />
Page<br />
1 Introduction 1<br />
2 Project Background 1<br />
2.1 <strong>Hinkley</strong> <strong>Point</strong> C 1<br />
2.2 <strong>Jetty</strong> Development 2<br />
2.3 Site Preparation Works 2<br />
3 Consenting and EIA Requirements 2<br />
4 <strong>EDF</strong> Energy and Nuclear Power 3<br />
5 Project Description 3<br />
5.1 The Application Site 3<br />
5.2 Description of the <strong>Jetty</strong> Development 5<br />
6 Environmental Impact Assessment 9<br />
6.1 Introduction 9<br />
6.2 Consultation 9<br />
6.3 EIA Methodology for the Assessment of Impacts 10<br />
6.4 Consideration of Alternatives 12<br />
6.5 The Environmental Statement 14<br />
7 Overview of Predicted Impacts on the Human and Built Environment 15<br />
7.1 Recreation and Amenity 15<br />
7.2 Transport 20<br />
7.3 Air Quality 22<br />
7.4 Noise and Vibration 24<br />
7.5 Landscape and Visual Amenity 27<br />
7.6 Historic Environment 36<br />
7.7 Socio-economics 38<br />
7.8 Navigation 41<br />
8 Overview of Predicted Impacts on the Natural and Physical Environment 44<br />
8.1 Coastal Hydrodynamics and Geomorphology 44<br />
8.2 Marine Ecology 46<br />
8.3 Terrestrial Ecology and Ornithology 48<br />
8.4 Water Quality 52<br />
8.5 Hydrology and Drainage 54<br />
8.6 Groundwater 55<br />
8.7 Soils and Land Use 57<br />
8.8 Geology and Contaminated Land 58<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development i November 2010
9 Cumulative Effects 59<br />
9.1 Introduction 59<br />
9.2 Cumulative Effects with the Site Preparation Works 59<br />
9.3 Cumulative Effects with the <strong>Hinkley</strong> <strong>Point</strong> C Project 60<br />
9.4 Cumulative Effects with Other Plans and Projects 61<br />
10 Conclusion 62<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development ii November 2010
1 INTRODUCTION<br />
1.1.1 NNB Generation Company Limited (part of <strong>EDF</strong> Energy) is seeking consent from the<br />
Marine Management Organisation (MMO) for the development of a temporary jetty and<br />
associated onshore infrastructure at <strong>Hinkley</strong> <strong>Point</strong>, Somerset (i.e. the ‘jetty<br />
development’). These works are proposed as ‘Preliminary Works’ to facilitate the<br />
construction of a new nuclear power station at <strong>Hinkley</strong> <strong>Point</strong> – <strong>Hinkley</strong> <strong>Point</strong> C.<br />
1.1.2 Consent will be sought by way of a Harbour Empowerment Order (HEO) under the<br />
Harbours Act 1964 (as amended) and licences under the Food & Environment Protection<br />
Act 1985 (i.e. FEPA licences).<br />
1.1.3 In addition to the jetty development, <strong>EDF</strong> Energy is proposing site preparation works to<br />
clear and level the site and provide the necessary infrastructure to facilitate the<br />
construction of <strong>Hinkley</strong> <strong>Point</strong> C. Key features of the site preparation works include site<br />
clearance, earthworks and drainage, which together with the jetty development form<br />
Preliminary Works to the construction of <strong>Hinkley</strong> <strong>Point</strong> C. <strong>EDF</strong> Energy is seeking consent<br />
for the site preparation works by way of grant of planning permission from West<br />
Somerset Council under the Town & Country Planning Act 1990.<br />
1.1.4 Since the jetty development and site preparation works are both Preliminary Works to the<br />
<strong>Hinkley</strong> <strong>Point</strong> C Project they are being treated as distinct but related projects.<br />
1.1.5 <strong>EDF</strong> Energy will separately be seeking a Development Consent Order (DCO) from the<br />
Infrastructure Planning Commission (IPC) to construct and operate <strong>Hinkley</strong> <strong>Point</strong> C.<br />
1.1.6 This document provides a <strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong> (NTS) of the Environmental<br />
Statement (ES) produced in support of the HEO and FEPA licences applications for the<br />
jetty development (the ES can be found in Volumes 2 to 4 inclusive of the submission).<br />
The ES is the formal report of the Environmental Impact Assessment (EIA) of the<br />
potential impacts of the jetty development’s construction, operation, dismantling and<br />
restoration phases (i.e. the phases that would occur if the DCO is granted for the <strong>Hinkley</strong><br />
<strong>Point</strong> C Project). The ES also reports on the potential impacts of the jetty development’s<br />
removal and reinstatement phase (i.e. the phase that would occur if the DCO is not<br />
granted for the <strong>Hinkley</strong> <strong>Point</strong> C Project).<br />
2 PROJECT BACKGROUND<br />
2.1 <strong>Hinkley</strong> <strong>Point</strong> C<br />
2.1.1 The <strong>Hinkley</strong> <strong>Point</strong> C site was nominated for new nuclear build by <strong>EDF</strong> Energy in 2009<br />
and is identified in the Government’s revised draft National Policy Statement (NPS) for<br />
Nuclear Power Generation as one of eight sites in England and Wales that are potentially<br />
suitable for the deployment of nuclear reactors by 2025 (Department for Energy and<br />
Climate Change, October 2010). The NPS makes it clear that all eight sites are needed,<br />
and that it is in the public interest to give priority to sites where new nuclear power<br />
stations can be developed significantly earlier than 2025. <strong>Hinkley</strong> <strong>Point</strong> C is the only site<br />
capable of being developed by 2018, which accords with Government policy on early<br />
deployment (see paragraphs 2.2.1 and 6.4.2 for further details).<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 1 November 2010
2.2 <strong>Jetty</strong> Development<br />
2.2.1 The jetty development is needed early to provide a means for delivery of bulk<br />
construction materials (principally stone, sand and cement) to the construction site at<br />
<strong>Hinkley</strong> <strong>Point</strong>. They are necessary as Preliminary Works to the <strong>Hinkley</strong> <strong>Point</strong> C Project to<br />
speed up the construction programme so that the new power station can be operational<br />
by 2018. This is in line with Government policy that encourages early development of<br />
new nuclear build to assist in meeting the UK’s carbon reduction targets (to help mitigate<br />
climate change) and improve the diversity and security of our electricity supplies.<br />
2.2.2 In addition, early construction of the temporary jetty would mean it would be available to<br />
serve the whole of the construction phase for <strong>Hinkley</strong> <strong>Point</strong> C; thus minimising HGV<br />
construction traffic on local roads.<br />
2.3 Site Preparation Works<br />
2.3.1 The proposed site preparation works involve the following activities: site clearance<br />
(including erection of fencing, vegetation removal, demolition of existing structures, and<br />
creation of alternative footpaths); earthworks (including soil stripping and storage, site<br />
levelling, soil screening / storage for subsequent re-use on site); provision of earth<br />
retaining structures; deep excavations; provision and relocation of drainage infrastructure<br />
(including culverts, outfalls, balancing ponds); the provision and operation of plant and<br />
machinery (including plant for concrete batching); site establishment works (including the<br />
provision of construction compounds and associated (including layover) facilities, car<br />
parks, haulage roads, site access points and roundabouts, and laying, replacement<br />
and/or diversion of utilities); and other associated works. In the event that <strong>Hinkley</strong> <strong>Point</strong> C<br />
is not consented, all structures would be removed and the site reinstated. Collectively<br />
these works are necessary to enable the earliest possible completion of construction of<br />
<strong>Hinkley</strong> <strong>Point</strong> C following the grant of the DCO.<br />
2.3.2 Prior to commencing the site preparation works and, where relevant, subject to obtaining<br />
separate planning permission, a small package of enabling works is also to be initiated in<br />
2010 to facilitate the site preparation works. These works would include remediation<br />
works to remove known areas of asbestos contamination within an existing spoil mound<br />
on site and in other areas of made ground located within the eastern part of the<br />
application site (see Section 8.8).<br />
3 CONSENTING AND EIA REQUIREMENTS<br />
3.1.1 As identified above, <strong>EDF</strong> Energy is seeking a HEO to authorise the jetty development<br />
and FEPA licences to authorise discrete aspects of the jetty development’s construction.<br />
Both of the consent application procedures include provisions for EIA in accordance with<br />
the requirements of European Community Directive 85/337/EEC (as amended) On the<br />
Assessment of the Effects of Certain Public and Private Projects on the Environment<br />
(herein referred to as the ‘EIA Directive’). In relation to the HEO, the EIA Directive is<br />
transposed into national law by the Harbour Works (Environmental Impact Assessment)<br />
Regulations 1999 (as amended in 2000 and 2009). In relation to FEPA licences, the EIA<br />
Directive is transposed into national law by the Marine Works (Environmental Impact<br />
Assessment) Regulations 2007.<br />
3.1.2 Through a ‘screening’ process, the MMO has confirmed that the jetty development is<br />
subject to EIA under the provisions of the EIA Directive and both of the aforementioned<br />
Regulations because it, or elements of it, would either qualify as facilitating and relating to<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 2 November 2010
a nuclear power station development, or qualify in its own right constitute a port<br />
development. Accordingly, the jetty development is subject to EIA.<br />
3.1.3 Since the jetty development would be situated within and adjacent to a number of<br />
internationally important nature conservation sites (i.e. the Severn Estuary Special Area<br />
of Conservation (SAC), Special Protection Area (SPA) and Ramsar site), it would need to<br />
comply with the measures set out in Council Directive (1992/43/EC) On the conservation<br />
of natural habitats and wild flora and fauna (herein referred to as the ‘Habitats Directive’),<br />
which is transposed into UK law through the Conservation of Habitats and Species<br />
Regulations 2010.<br />
3.1.4 In addition, the jetty development includes a number of activities that would require<br />
separate legal consents from a number of different regulatory bodies, potentially including<br />
land drainage consents, discharge consents, waste management exemptions / licences,<br />
and protected species licences. Prior to commencement of these activities, <strong>EDF</strong> Energy<br />
will ensure that it has secured the necessary consents and that any relevant works are<br />
undertaken in full compliance with legal requirements and best practice.<br />
4 <strong>EDF</strong> ENERGY AND NUCLEAR POWER<br />
4.1.1 Électricité de France (<strong>EDF</strong>) is one of the world’s largest energy companies and the<br />
world’s largest operator of nuclear power plants, with 58 operational plants in France and<br />
a further one under construction at Flamanville in Normandy. <strong>EDF</strong> has a strong safety<br />
track record in the operation of nuclear power stations and safety is at the heart of the<br />
design and operating procedures for all its nuclear plants. Within the UK, <strong>EDF</strong> operates<br />
via its UK subsidiary – <strong>EDF</strong> Energy – and currently owns and operates eight nuclear<br />
power stations, including Sizewell B in Suffolk.<br />
4.1.2 <strong>EDF</strong> Energy has indicated publicly for over three years that it would be interested in<br />
investing in a new generation of nuclear plants in the UK and that it is confident that new<br />
plants can be built and run safely and economically, without subsidy.<br />
5 PROJECT DESCRIPTION<br />
5.1 The Application Site<br />
5.1.1 This section describes the jetty development and the characteristics of the application<br />
site and surrounding area that it could affect. The application site (see Figure 1) is<br />
located on the northern coastline of West Somerset, 25km to the east of Minehead and<br />
12km to the north-west of Bridgwater, and falls within the parish of Stogursey. The<br />
onshore component of the application site falls within the land under the control of <strong>EDF</strong><br />
Energy, adjacent and to the west of the existing <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex.<br />
The offshore component of the application site extends into Bridgwater Bay, part of the<br />
Severn Estuary.<br />
5.1.2 Immediately to the east of the application site are the <strong>Hinkley</strong> <strong>Point</strong> A and <strong>Hinkley</strong> <strong>Point</strong> B<br />
nuclear power stations (i.e. the <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex). <strong>Hinkley</strong> <strong>Point</strong> A<br />
operated between 1965 and 2000 and is currently undergoing decommissioning by the<br />
Nuclear Decommissioning Authority (NDA). <strong>Hinkley</strong> <strong>Point</strong> B, owned by <strong>EDF</strong> Energy, has<br />
operated since 1976 and is scheduled to continue generating until at least 2016.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 3 November 2010
Figure 1 <strong>Jetty</strong> Development Application Site<br />
5.1.3 The topography of the application site and the surrounding land is typical of that in the<br />
wider locality, comprising mostly open, gently rolling, mixed lowland farmland with a<br />
series of east-west trending ridges. Ground elevations range from approximately 10m to<br />
35m Above Ordnance Datum (AOD). The main access road serving <strong>Hinkley</strong> <strong>Point</strong> is the<br />
C182, which is an unclassified road that runs south from <strong>Hinkley</strong> <strong>Point</strong> through the village<br />
of Cannington and then joins the A39 to the south of the village (see Figure 8). The A39<br />
is a local strategic east-west road with Bridgwater to the east and Minehead to the west.<br />
Within Bridgwater the A39 joins the A38, which is also a local strategic road that links to<br />
the M5 motorway north and south of Bridgwater at Junctions 23 and 24 respectively.<br />
5.1.4 The application site contains a network of public rights of way (PRoW). It includes a<br />
portion of the West Somerset Coast Path (Footpath WL 23/95), which is a 25km linear<br />
walk and a resource of national importance. The network of existing PRoW is shown on<br />
Figure 2. One of the main routes to south of the application site – known as Green Lane<br />
(Footpath WL 23/110) - is an east-west track that runs along a ridge with significant<br />
nature conservation, heritage and landscape value.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 4 November 2010
Figure 2 Existing Public Rights of Way<br />
5.2 Description of the <strong>Jetty</strong> Development<br />
5.2.1 The jetty development would be constructed and, assuming a DCO is granted for the<br />
<strong>Hinkley</strong> <strong>Point</strong> C Project, operated during construction of <strong>Hinkley</strong> <strong>Point</strong> C. It would then be<br />
dismantled and the site restored where it lies outside of the area of permanent works<br />
associated with <strong>Hinkley</strong> <strong>Point</strong> C. However, if a DCO is not granted for the <strong>Hinkley</strong> <strong>Point</strong><br />
C Project, the constructed jetty would not be operated, but would be removed and the<br />
land reinstated back to its current form.<br />
5.2.2 The jetty is proposed as a two-staged structure that can be constructed in a manner that<br />
accommodates the emerging transport demands of the <strong>Hinkley</strong> <strong>Point</strong> C Project, so that<br />
the first stage could operate alone without the second stage. However, it is expected that<br />
the two stages would in fact be built as one structure under one construction programme<br />
(i.e. stage two would be constructed once stage one is in place without any interval).<br />
This is reflected in the HEO application, which proposes the jetty development in its<br />
entirety, and is assessed in the ES.<br />
5.2.3 The jetty development comprises the following offshore infrastructure, as shown in<br />
Figures 3 and 4:<br />
• a jetty bridge constructed from vertical tubular piles supporting the deck;<br />
• a jetty head constructed from vertical tubular piles supporting horizontal cross-heads<br />
and a deck, and incorporating mooring infrastructure (e.g. dolphins);<br />
• a berthing pocket dredged alongside the jetty head to accommodate vessels at<br />
various states of the tide;<br />
• materials handling and conveyance equipment on the jetty head and along jetty<br />
bridge;<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 5 November 2010
• a roadway along the jetty bridge; and<br />
• aids to navigation.<br />
5.2.4 Indicative visual representations of the jetty are shown in Figure 5.<br />
Figure 3 Plan of <strong>Jetty</strong> Bridge and <strong>Jetty</strong> Head<br />
5.2.5 The jetty development comprises the following onshore infrastructure as shown in Figure<br />
6:<br />
• an aggregates storage area comprising stockpile areas for stone and sand, and silos<br />
for cement and/or cement replacement products, and including a surface water<br />
drainage system with a water management zone for the treatment and regulation of<br />
discharges;<br />
• a rock extraction area and two soil storage areas to facilitate construction of the<br />
onshore components;<br />
• a service road providing access to the aggregates storage area, the rock extraction<br />
area and, temporarily for the purposes of construction, to the foreshore; and<br />
• materials handling and conveyance equipment from the jetty bridge to the<br />
aggregates storage area.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 6 November 2010
Figure 4 Detailed Plan of <strong>Jetty</strong> Head<br />
Figure 5 Photomontages of the <strong>Jetty</strong> - Looking West (top) and Looking East<br />
(bottom)<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 7 November 2010
Figure 6 Temporary <strong>Jetty</strong> Development – Onshore Development<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works <strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 8 November 2010
6 ENVIRONMENTAL IMPACT ASSESSMENT<br />
6.1 Introduction<br />
6.1.1 Environmental impact assessment (EIA) is a process that must be followed for certain<br />
types of development before they are granted consent. In this instance, the MMO has<br />
determined that the jetty development is a project listed under Annex I to the EIA<br />
Directive, as transposed into national law by the Harbour Works (EIA) Regulations and<br />
the Marine Works (EIA) Regulations.<br />
6.1.2 The MMO’s Scoping Opinion (dated 4 June 2010) included a Screening Opinion which<br />
identified that the jetty development, or elements of it (i.e. regulated activities), would<br />
either qualify as facilitating and relate to the description of the development of a nuclear<br />
power station / nuclear reactor, or would in its own right constitute a port development<br />
itself within Annex I.<br />
6.2 Consultation<br />
6.2.1 Consultation for the jetty development has been undertaken during the consultation<br />
phase for the <strong>Hinkley</strong> <strong>Point</strong> C Project. This consultation has been with regulators,<br />
statutory government agencies, non-governmental organisations and the public<br />
throughout the EIA process for the <strong>Hinkley</strong> <strong>Point</strong> C Project and, also, specifically for the<br />
Preliminary Works, including the jetty development. <strong>EDF</strong> Energy has had ongoing<br />
informal engagement with key statutory consultees and other interested parties, which<br />
has informed the preparation of its development proposals for the <strong>Hinkley</strong> <strong>Point</strong> C<br />
Project, dating back to 2008. Key milestones include the consultation programme<br />
coordinated in the autumn and winter of 2008 in support of the EIA scoping process and,<br />
in early 2009, to assist the Government’s Strategy Siting Assessment process for new<br />
nuclear power stations. Generic consultation has included the consultation undertaken<br />
as part of the DCO application process for the <strong>Hinkley</strong> <strong>Point</strong> C Project. The primary aim<br />
of the pre-application consultation is to engage early with local authorities, statutory<br />
consultees, local communities and the general public in order to:<br />
• allow members of the local community to influence the way projects are developed<br />
by providing feedback on potential options, providing them with an opportunity to<br />
shape the way in which their community develops;<br />
• assist in a better understanding of the proposed project and the implications at a<br />
local scale and resolve misunderstandings or concerns at an early stage;<br />
• obtain important information about the economic, social and environmental impacts<br />
of a scheme from consultees, to help identify project options which are unsuitable<br />
and not worth developing further;<br />
• enable potential mitigating measures to be considered and, in some cases, built into<br />
the project before an application is submitted; and<br />
• identify ways in which the project could support wider strategic or local objectives,<br />
where appropriate.<br />
6.2.2 <strong>EDF</strong> Energy undertook the first formal stage of consultation from November 2009 to<br />
February 2010. The consultation at Stage 1 set out the initial proposals and options for<br />
the <strong>Hinkley</strong> <strong>Point</strong> C Project. These initial proposals were presented in a consultation<br />
document together with an Environmental Status Report setting out the preliminary<br />
environmental information relating to the proposed development. Stage 1 consultation<br />
provided an early opportunity for statutory and non-statutory consultees to comment on<br />
the scheme whilst development proposals were still being worked up. In addition, it also<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 9 November 2010
provided a specific opportunity for stakeholders to comment on the proposals for<br />
Preliminary Works, including the jetty development.<br />
6.2.3 <strong>EDF</strong> Energy began the second formal stage of consultation in July 2010. This stage is<br />
consulting on the preferred proposal for the <strong>Hinkley</strong> <strong>Point</strong> C Project (and this proposal<br />
includes the project’s Preliminary Works, including the jetty development). The<br />
consultation documents include a detailed Environmental Appraisal. The Environmental<br />
Appraisal was not an ES, but was designed to enable consultees to give an informed<br />
response to the likely environmental effects of the <strong>Hinkley</strong> <strong>Point</strong> C Project based on the<br />
current information compiled on the project by that stage. The consultation extended into<br />
October 2010. Further development of the detail of jetty development undertaken since<br />
July 2010 (when Stage 2 consultation began) has been progressed in consultation with<br />
key statutory consultees and local residents.<br />
6.2.4 Consultation has also been undertaken through the Marine Authorities Liaison Group<br />
(MALG). The MALG was formed in early 2009 and generally met on a monthly basis<br />
until April 2010. The MALG comprises representatives from regulators and advisory<br />
agencies with an interest in the <strong>Hinkley</strong> <strong>Point</strong> C Project, particularly from a marine and<br />
coastal perspective, including the Marine Management Organisation (MMO), the Centre<br />
for Environment, Fisheries and Aquaculture Science (Cefas), West Somerset Council,<br />
Sedgemoor District Council including the Port of Bridgwater, Somerset County Council,<br />
the Environment Agency, English Heritage, Natural England and the Countryside Council<br />
for Wales (CCW). The purpose of the MALG meetings is to advise the attendees of the<br />
latest concepts and developments associated with the <strong>Hinkley</strong> <strong>Point</strong> C Project and to<br />
receive their feedback. Many of the MALG meetings have provided attendees with<br />
information about the jetty (e.g. alternative options for the jetty’s position at <strong>Hinkley</strong> <strong>Point</strong>,<br />
alternative options for the jetty’s infrastructure design) and its potential impacts on the<br />
environment (e.g. construction noise, habitat loss, footpath closures). Comments<br />
received from attendees have been fed into the EIA process for the jetty development<br />
during scoping and impact assessment.<br />
6.2.5 Other consultation specifically for the jetty development outside of the MALG has<br />
included direct consultation with various parties and in relation to specific issues relating<br />
to the various environmental parameters of interest.<br />
6.3 EIA Methodology for the Assessment of Impacts<br />
6.3.1 At the impact assessment stage, the potentially beneficial and adverse impacts of the<br />
jetty development are identified and assessed with reference to the existing environment.<br />
Environmental impacts have been predicted with reference to definitive standards and<br />
legislation where available. Where it has not been possible to quantify impacts,<br />
qualitative assessments have been carried out based on available knowledge and<br />
professional judgement. Where uncertainties, limitations or assumptions exist, they have<br />
been noted in the ES.<br />
6.3.2 The significance of predicted impacts has been determined by reference to impact<br />
criteria for each assessment topic. Broadly, the significance of the impact gives<br />
consideration to the magnitude of the potential impact, the value and sensitivity of the<br />
receiving environment and the likelihood of the impact occurring.<br />
Impact Magnitude<br />
6.3.3 Magnitude refers to the ‘size’ or ‘amount’ of an impact. It is a function of other aspects,<br />
such as the impact’s extent (i.e. the area over which the impact occurs), duration (i.e. the<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 10 November 2010
time for which the impact is expected to last prior to recovery or replacement of the<br />
resource or feature), likelihood (i.e. the chance that the impact will occur) and reversibility<br />
(i.e. an irreversible (permanent) impact is one from which recovery is not possible within<br />
a reasonable timescale or for which there is no reasonable chance of action being taken<br />
to reverse it). Where possible, environmental impacts have been predicted with reference<br />
to quantified baseline conditions, definitive standards and legislation; where it is not<br />
possible to quantify impacts, qualitative assessments have been carried out based on<br />
available knowledge and professional judgement.<br />
Value and Sensitivity<br />
6.3.4 This is a composite criterion, where the ‘value’ of the receptor (the individual or feature<br />
that the impact could affect) will be a function of a variety of factors (e.g. biodiversity<br />
value, social/community value and economic value) and can be determined within a<br />
defined geographical context. In some instances, the inherent value of a receptor will<br />
have been recognised by the expert community and Governmental bodies by means of<br />
designation. Irrespective of recognised value, all receptors will exhibit a greater or lesser<br />
degree of ‘sensitivity’ to the changes brought about by the proposed development. The<br />
precise form which these indicators take in each case will vary according to subject<br />
matter, but by following the generic methodology adopted, assessors have ensured that<br />
these factors have been taken into account within their subject areas.<br />
Impact Assessment Matrix and Impact Significance<br />
6.3.5 Using the magnitude of the impact together with the value and sensitivity of the<br />
environmental receptor, the degree of significance of an impact can be determined. To<br />
assist this process, an impact assessment matrix (IAM) provides a mechanism for initially<br />
assessing impact significance (see Table 1).<br />
Table 1 Impact Assessment Matrix<br />
Magnitude<br />
Values and Sensitivity of Receptor<br />
Very low Low Medium High<br />
Very Low Negligible Negligible Minor Minor<br />
Low Negligible Minor Minor Moderate<br />
Medium Minor Minor Moderate Major<br />
High Minor Moderate Major Major<br />
6.3.6 It should be noted that while the matrix provides a good framework for the consistent<br />
assessment of impacts across all parameters, there is still an important role for expert<br />
judgement and further objective assessment to play in moderating the significance rating<br />
process.<br />
6.3.7 Defining the significance rating of the impact is the most important step in the EIA<br />
process since it is this rating which provides a strong indication as to whether mitigation<br />
may be required and also whether, following the use of mitigation measures, identified<br />
impacts may be reduced to environmentally acceptable levels (or not).<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 11 November 2010
Mitigation<br />
6.3.8 In this EIA, those impacts assessed as being of potentially greater than minor adverse<br />
significance (i.e. impacts of moderate and major adverse significance) are the focus of<br />
mitigation, although every attempt has been taken to avoid, reduce and mitigate impacts<br />
through design change and adoption of best practice.<br />
6.3.9 The preferred hierarchy of mitigation is prevention first, then minimisation and, only as a<br />
last resort, compensation or remediation. The definitions of these are as follows:<br />
• prevention: avoid, relocate, modify the design and / or do not carry out the<br />
development;<br />
• reduction: introduce screens / blinds, modify design, alter technology, reduce size<br />
and scale of development etc; and<br />
• compensation or remediation: compensation to provide like-for-like replacement for<br />
any lost environmental elements (e.g. open green spaces, public facilities, wildlife<br />
area etc).<br />
6.3.10 Where possible, mitigation has been built into the jetty development (e.g. through the<br />
options chosen and through its design) and may be accepted, offset by other benefits of<br />
the jetty development or managed by the imposition of conditions within the HEO and/or<br />
on any licences granted.<br />
Residual Impacts<br />
6.3.11 The final step in the EIA process is the assessment of the residual impacts (i.e. those<br />
impacts remaining after the implementation (where necessary) of the proposed mitigation<br />
measures). Residual impacts are rated in accordance with the definitions of significance<br />
provided above. In this EIA, residual impacts assessed as minor or negligible are<br />
considered to be insignificant. More significant impacts may be accepted, offset by other<br />
benefits of the jetty development, or managed by the imposition of conditions within the<br />
HEO and / or on any licences granted.<br />
Cumulative Effects Assessment<br />
6.3.12 Cumulative effects are the additive and interactive effects that can arise from the jetty<br />
development cumulatively with other plans and projects. The EIA considers the jetty<br />
development cumulatively with the site preparation works, the <strong>Hinkley</strong> <strong>Point</strong> C Project,<br />
and other plans and projects which overlap in time and space (as regards those<br />
receptors that potentially could be affected).<br />
6.4 Consideration of Alternatives<br />
6.4.1 In accordance with the EIA Directive, an ES should outline the main alternatives<br />
considered by the applicant and present the main reasons for selecting the application<br />
site and design.<br />
No Development Alternative<br />
6.4.2 Proposed as Preliminary Works, the jetty development would allow <strong>EDF</strong> Energy to meet<br />
the target date of 2018 for the start of nuclear power generation by enabling the<br />
construction of <strong>Hinkley</strong> <strong>Point</strong> C to begin as early as possible after grant of the DCO. The<br />
2018 target is clearly set out in the draft National Policy Statements related to energy and<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 12 November 2010
is designed to meet the Government’s objective of early deployment of new nuclear<br />
power stations to help provide security of electricity supplies in the period post-2015.<br />
6.4.3 If the jetty development is not undertaken in 2011-2012 as Preliminary Works to the<br />
<strong>Hinkley</strong> <strong>Point</strong> C Project, there would be a delay of approximately one year to the<br />
programme for construction and operation of <strong>Hinkley</strong> <strong>Point</strong> C. <strong>EDF</strong> Energy estimates, on<br />
a conservative basis, that the operation of <strong>Hinkley</strong> <strong>Point</strong> C would save some 12 million<br />
tonnes of CO 2 per year (in comparison with efficient fossil fuel based generation plant).<br />
This saving of CO 2 emissions would be equivalent to taking four million cars off the road.<br />
6.4.4 Proposed as Preliminary Works, the jetty development would also facilitate construction<br />
of <strong>Hinkley</strong> <strong>Point</strong> C in a way that significantly reduces the use of HGVs to import<br />
construction materials to site via the local public highway network, including the roads to<br />
<strong>Hinkley</strong> <strong>Point</strong> through Cannington and possibly through Bridgwater. Without the jetty<br />
development, a total of approximately two million tonnes of bulk construction materials for<br />
concrete production (i.e. stone, sand and cement) would have to be imported by road (or<br />
by a combination of rail and road). Based on a 15 tonnes payload, the importation of<br />
materials by road instead of via the jetty would add a total of approximately 260,000 HGV<br />
movements on the local highway network over <strong>Hinkley</strong> <strong>Point</strong> C’s construction period.<br />
Depending on the rate of demand for bulk construction materials over the course of<br />
<strong>Hinkley</strong> <strong>Point</strong> C’s construction period, the jetty development would offset between 245<br />
and 436 HGV movements per day.<br />
<strong>Jetty</strong> Location at <strong>Hinkley</strong> <strong>Point</strong><br />
6.4.5 Compared to the alternatives (i.e. the redevelopment of Combwich Wharf and possible<br />
use of facilities at Dunball Wharf), the temporary jetty option would be the most<br />
appropriate option and, therefore, the preferred option for the delivery of bulk materials<br />
because it would have least effect on local communities (particularly those along the<br />
route between Combwich Wharf and <strong>Hinkley</strong> <strong>Point</strong>).<br />
<strong>Jetty</strong> Position at <strong>Hinkley</strong> <strong>Point</strong><br />
6.4.6 Compared to the alternatives (i.e. an eastern jetty option), the western jetty option is the<br />
preferred option primarily because it has a smaller footprint and, therefore, a smaller<br />
scale of impacts on the designated sites (except the Lilstock to Blue Anchor SSSI),<br />
marine ecological receptors and archaeological receptors. In addition, it is more likely to<br />
avoid the Corallina turfs present on the foreshore. Unlike the eastern option it would, in<br />
part, cross – and partially obscure – the exposures in the Lilstock to Blue Anchor SSSI.<br />
However, the affected exposures are replicated and are accessible elsewhere in the<br />
SSSI, so there would be no physical loss of geological exposures or damage to the<br />
resource due to the works.<br />
<strong>Jetty</strong> Design<br />
6.4.7 Compared to the alternative designs, the two-staged jetty option is preferred because it<br />
offers greater operational flexibility. In terms of its environmental impact it offers the<br />
‘middle ground’. In the marine environment, its footprint is slightly larger than one option<br />
and slightly smaller than the other, but its operational flexibility offers more opportunity<br />
than the one option and a similar opportunity to another for reducing traffic, air quality<br />
and noise impacts. Overall the two-staged option is preferred on the basis of its<br />
expected operational performance and environmental impact.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 13 November 2010
Disposal of Dredged Material<br />
6.4.8 Compared to the alternatives (i.e. other offshore disposal options, beneficial use options<br />
and onshore disposal options), the disposal of dredged material at the Cardiff Grounds is<br />
the preferred option because the dredged material arising from the berthing pocket is not<br />
anticipated to be too contaminated for offshore disposal, and given the logistical<br />
difficulties and associated environmental issues, onshore disposal options were not<br />
considered viable.<br />
6.5 The Environmental Statement<br />
6.5.1 In accordance with the EIA Directive and aforementioned EIA Regulations, the ES<br />
reports on the potential environmental impacts arising during the construction, operation<br />
and dismantling / restoration phases of the jetty development. The ES also reports in the<br />
potential environmental impacts arising during the removal / reinstatement phase of the<br />
jetty development, should the DCO not be granted and, therefore, removal of the jetty<br />
development and reinstatement of the land be required.<br />
6.5.2 The ES that this NTS accompanies contains the following information:<br />
• a description of the proposed temporary jetty development and an outline of the main<br />
alternatives considered;<br />
• a description of the existing (baseline) environment that the jetty development has<br />
the potential to impact upon (both directly and indirectly);<br />
• definitions of the relevant study areas for the EIA;<br />
• prediction of potential impacts (during the jetty development’s various phases) on the<br />
existing environment and assessment of their significance;<br />
• a description of any mitigation measures proposed to avoid, reduce or off-set<br />
potential impacts; and<br />
• an indication of any difficulties (e.g. uncertainties, assumptions and limitations)<br />
encountered during the preparation of the ES.<br />
6.5.3 The ES contains the specific assessment methodologies adopted, the baseline<br />
environmental conditions, and the technical assessments of the potential impacts<br />
associated with the jetty development. Assessments have been made for the following<br />
environmental parameters:<br />
• recreation and amenity;<br />
• transport;<br />
• air quality;<br />
• noise and vibration;<br />
• landscape and visual amenity;<br />
• archaeology and cultural heritage;<br />
• socio-economics;<br />
• coastal hydrodynamics and geomorphology;<br />
• marine ecology;<br />
• terrestrial ecology and ornithology;<br />
• water quality;<br />
• hydrology and drainage;<br />
• groundwater;<br />
• soils and land use; and<br />
• geology and contaminated land.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 14 November 2010
6.5.4 The ES also contains an assessment of cumulative effects.<br />
6.5.5 An overview of the findings of the ES is provided in the subsequent sections of this NTS.<br />
These are summarised as predicted impacts on the human and built environment (e.g.<br />
recreation, noise, air quality and traffic) and then impacts on the natural environment<br />
(e.g. ecology, water quality and soils). A brief description of the existing environmental<br />
conditions is provided, followed by a summary of the main impacts that would arise from<br />
the jetty development. The key mitigation measures to avoid, reduce or off-set impacts<br />
are also summarised and the residual impacts are discussed. Where significant residual<br />
impacts are predicted, these are summarised in tables at the end of each section.<br />
7 OVERVIEW OF PREDICTED IMPACTS ON THE HUMAN AND BUILT<br />
ENVIRONMENT<br />
7.1 Recreation and Amenity<br />
Existing Environment<br />
7.1.1 The site and wider study area is well served by a network of public footpaths, including:<br />
• a portion of the West Somerset Coast Path, a resource of national importance, which<br />
links the River Parrett Trail at Steart in Bridgwater Bay with the South West Coast<br />
Path National Trail at Minehead;<br />
• a number of smaller, interconnecting footpaths across the site that are generally<br />
aligned north to south and east to west, with a length of 20km of PRoW within 1km of<br />
the site and 60km of PRoW within 3km of the site.<br />
7.1.2 Surveys have been carried out to determine the use of PRoW in and around the<br />
application site. The West Somerset Coast Path, which runs along the northern<br />
boundary of the application site, is used most often during the summer months and<br />
holiday periods. The data provides approximate visitor numbers each month along the<br />
West Somerset Coast Path between 2006 and 2009, with counts taken from the junction<br />
of PRoW WL 23/56 and WL 23/95 (see Figure 2). The highest number of users (410)<br />
was recorded in August 2008 for this stretch of path.<br />
7.1.3 In terms of the remainder of the site’s PRoW, the survey carried out in 2009 identified<br />
that the majority of users appear to be local residents (70% of those surveyed lived less<br />
than 3km from the study area). However, visitors who reside significant distances from<br />
the area (e.g. live in excess of 25km from the study area) were also recorded using the<br />
PRoW.<br />
7.1.4 There are no bridleways within the application site boundary, though a number of<br />
bridleways are located in the surrounding area. Due to the limited availability of public<br />
bridleways, the majority of this equestrian activity takes place on private land.<br />
7.1.5 Within the Severn Estuary and Bristol Channel, there are a large number of sailing,<br />
cruising, boating and yacht clubs. However, no formal boating and/or sailing activities or<br />
events are known to occur off <strong>Hinkley</strong> <strong>Point</strong> due to the insufficient depth of water at this<br />
location.<br />
7.1.6 An Excepted Area is located on the foreshore at <strong>Hinkley</strong> <strong>Point</strong>, stretching from Stolford in<br />
the east, past <strong>Hinkley</strong> <strong>Point</strong>, to the boundary of the Bridgwater Bay NNR in the west. The<br />
Excepted Area can be used for shooting by any member of the British Society for<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 15 November 2010
Shooting and Conservation (BASC). Consultation with Natural England indicates that the<br />
Excepted Area is used intermittently by between 5-10 people during the season.<br />
7.1.7 There are no existing sports and recreation facilities (including playing fields, sports clubs<br />
and stadiums) within a 1km radius of the application site boundary, although there are<br />
such facilities within the wider study area.<br />
7.1.8 In addition, there are no areas of open access land within the application site. Wick Moor<br />
Common lies to the south-east of the application site and extends eastwards. A search<br />
of Natural England’s Common Rights of Way (CRoW) database indicates that a further<br />
series of commons are located over 1km from the application site.<br />
7.1.9 There are no areas of public open space, such as formal parks and gardens, within the<br />
application site. The nearest formal areas of public open space are in excess of 4km<br />
from the application site (i.e. Combwich Village Green and Combwich Common).<br />
7.1.10 Walking, wildfowling, fishing, bird watching and horse riding are the predominant sporting<br />
and recreational activities undertaken in close proximity to or within the study area.<br />
However, given the limited use of the Common Land and foreshore by any formal and<br />
informal recreational activities, and given the availability of similar recreational resource<br />
in the surrounding area, local importance is ascribed.<br />
Main Predicted Impacts<br />
7.1.11 During the construction of the jetty development, the aggregates storage area would be<br />
enclosed by a 2.14m high chain link security fence. Hence the first phase of construction<br />
(the earthworks) would result in the obstruction, for health and safety reasons, of a<br />
number of PRoW until the works are completed, which is anticipated to be around 3 to 4<br />
months from commencement (see Figure 7). Following completion of the first phase of<br />
construction, the access road would again be passable and, consequently, certain PRoW<br />
would be re-opened while the rest would remain closed for the duration of the works<br />
(expected to 14 to 15 months). In addition, the elevated jetty would be constructed over<br />
the route of the West Somerset Coast Path and this would also be obstructed.<br />
7.1.12 Without mitigation, the obstruction of the affected PRoW is considered to represent a<br />
high magnitude disturbance because the right of passage would be removed. The<br />
affected PRoW network (excluding the section of the West Somerset Coast Path) is a<br />
resource of local importance and, consequently, an impact of moderate adverse<br />
significance is predicted.<br />
7.1.13 The obstruction of the West Somerset Coast Path (WL 23/95) is considered to represent<br />
a high magnitude effect given the loss of right of access along the coast, albeit for a<br />
reasonably short period of time. Given the national importance of this asset, without<br />
mitigation, a short- to medium-term impact of major adverse significance is assessed.<br />
7.1.14 The jetty development would also result in an increase in noise, dust and visual<br />
disturbance due to the movement and activities of construction personnel, plant and<br />
equipment; all of which could have an adverse impact on the amenity value of the PRoW<br />
close to the location of such activities and equipment for the duration of works. These<br />
impacts are considered in relevant sections on air quality, noise and vibration, and<br />
landscape and visual amenity herein.<br />
7.1.15 Impacts to other sports and recreation facilities, open access land, or public open space<br />
are not expected to be significant during the jetty development.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 16 November 2010
7.1.16 Although the foreshore is an Excepted Area where wildfowling can and does take place,<br />
its use is very low in frequency and by a small number of people, representing a locally<br />
important resource. The scale of the area obstructed in the foreshore (which would be<br />
limited to temporary obstructions to small areas) is very small (a minimum of 1.4ha to a<br />
maximum of 6ha) in comparison to the available area (the Excepted Area covers 314ha,<br />
and consequently no more than 2% would be obstructed). Consequently, a minor<br />
adverse impact is predicted.<br />
7.1.17 During any interim period between completion of the construction phase and operation of<br />
the jetty, there would be no activities on site that would result in emissions of dust or<br />
other air quality deterioration. Therefore, there would be no change in the background air<br />
quality environment and, hence, no impact is predicted to occur to users of the PRoW.<br />
7.1.18 With respect to the jetty development alone, those PRoW that would be obstructed<br />
during the latter phase of construction (i.e. following the earthworks) would continue to be<br />
obstructed during the operational phase and a moderate adverse impact would arise in<br />
the medium-term (the combined impact of the site preparation works and the jetty<br />
development is considered in Section 9 below). However, PRoW access would be<br />
available under the jetty and there would be no obstruction to the West Somerset Coast<br />
Path.<br />
7.1.19 The dismantling and restoration phases of the jetty development would result in the<br />
obstruction of the same PRoW affected during construction until the structures are taken<br />
off site. Following the dismantling and restoration works, the PRoW located within the<br />
jetty development’s application site would be re-opened.<br />
7.1.20 The removal and reinstatement of the jetty development, if required (i.e. if the DCO for<br />
the <strong>Hinkley</strong> <strong>Point</strong> C Project is not granted) would have similar impacts to those predicted<br />
for the jetty development’s dismantling and restoration phase.<br />
Mitigation<br />
7.1.21 Following discussions with local residents, equestrians and Somerset County Council<br />
regarding the Preliminary Works, it was agreed that alternative PRoW would be provided<br />
during the works to maintain the connectivity and routes of those PRoW that would be<br />
obstructed; thus maintaining a linked network of routes around the site. The alternative<br />
routes are shown in Figure 7 and would be used by those following the West Somerset<br />
Coast Path. Where alternative PRoW cross field boundaries, gates (including selfclosing<br />
pedestrian gates) would be constructed and appropriate access for disabled<br />
persons would be catered for as far as practicable.<br />
7.1.22 Mitigation measures would also be put in place to avoid or reduce the magnitude and<br />
probability of dust, noise and visual disturbance (as identified in the relevant sections on<br />
air quality, noise and vibration, and landscape and visual).<br />
7.1.23 Should the DCO not be granted for the <strong>Hinkley</strong> <strong>Point</strong> C Project, all PRoW routes<br />
disrupted by the jetty development would be reinstated and upgraded where practicable<br />
through reinstatement of the landform and landscape.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 17 November 2010
Figure 7 Public Rights of Way Closures and Alternative Routes<br />
Residual Impacts<br />
7.1.24 The magnitude of impacts on PRoW would be significantly reduced by providing users<br />
with alternative routes, thereby maintaining a right of passage as well as connectivity<br />
within the surrounding PRoW network. Specifically, the impact associated with<br />
obstruction to PRoW would be reduced to a minor level for all affected routes. Table 2<br />
below represents a summary of the potentially significant impacts on recreation and<br />
amenity that would remain after the mitigation measures discussed above have been put<br />
into practice.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 18 November 2010
Table 2 <strong>Summary</strong> Significant Impacts on Recreation and Amenity<br />
Description of Impact Impact Mitigation Measure Residual Impact<br />
Construction Phase<br />
Disturbance to<br />
users of public<br />
rights of way<br />
Minor adverse to<br />
moderate adverse<br />
(noise) temporary<br />
Negligible adverse<br />
to major adverse<br />
(visual)<br />
Adherence to best<br />
practice noise<br />
minimisation<br />
Landscaping and<br />
planting<br />
Negligible adverse<br />
to moderate<br />
adverse (noise)<br />
temporary<br />
Negligible to major<br />
adverse (visual)<br />
Negligible to major<br />
adverse (visual –<br />
during interim<br />
period)<br />
Negligible to major<br />
adverse (visual –<br />
during interim<br />
period)<br />
Disturbance to<br />
sports and<br />
recreation facilities,<br />
open access land,<br />
and public open<br />
space<br />
Minor adverse<br />
(noise) temporary<br />
Major adverse on<br />
foreshore (visual)<br />
Major adverse on<br />
foreshore (visual –<br />
during interim<br />
period)<br />
Adherence to best<br />
practice noise<br />
minimisation<br />
Landscaping and<br />
planting<br />
Negligible adverse<br />
to minor adverse<br />
(noise) temporary<br />
Major adverse on<br />
foreshore (visual)<br />
Major adverse on<br />
foreshore (visual –<br />
during interim<br />
period)<br />
Operation Phase<br />
Disturbance to<br />
users of public<br />
rights of way<br />
Minor adverse to<br />
moderate adverse<br />
(noise) temporary<br />
Adherence to best<br />
practice noise<br />
minimisation<br />
Minor adverse to<br />
moderate adverse<br />
(noise) temporary<br />
Negligible adverse<br />
to major adverse<br />
(visual)<br />
Landscaping and<br />
planting<br />
Negligible adverse<br />
to major adverse<br />
(visual)<br />
Disturbance to<br />
sports and<br />
recreation facilities,<br />
open access land,<br />
and public open<br />
space<br />
Major adverse on<br />
foreshore (visual)<br />
Landscaping and<br />
planting<br />
Major adverse on<br />
foreshore (visual)<br />
Dismantling and Restoration Phase<br />
Disturbance to<br />
users of public<br />
rights of way<br />
Minor adverse to<br />
moderate adverse<br />
(noise) temporary<br />
Adherence to best<br />
practice noise<br />
minimisation<br />
Minor adverse to<br />
moderate adverse<br />
(noise) temporary<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 19 November 2010
Description of Impact Impact Mitigation Measure Residual Impact<br />
Removal and Reinstatement Phase<br />
Disturbance to<br />
users of public<br />
rights of way<br />
Minor adverse to<br />
moderate adverse<br />
(noise) temporary<br />
Adherence to best<br />
practice noise<br />
minimisation<br />
Minor adverse to<br />
moderate adverse<br />
(noise) temporary<br />
Negligible adverse<br />
to major adverse<br />
(visual)<br />
Reinstatement of<br />
features and<br />
planting<br />
Negligible adverse<br />
to major adverse<br />
(visual)<br />
Disturbance to<br />
sports and<br />
recreation facilities,<br />
open access land,<br />
and public open<br />
space<br />
Major adverse on<br />
foreshore (visual)<br />
Reinstatement of<br />
features and<br />
planting<br />
Major adverse on<br />
foreshore (visual)<br />
7.2 Transport<br />
Existing Environment<br />
7.2.1 The transportation network surrounding the site is set in a rural location with a network of<br />
country lanes linking scattered residences; farmhouses and a number of small hamlets<br />
(see Figure 8). The settlement of Shurton lies to the south of the site; the village of<br />
Combwich lies 5km south-east on the western side of the River Parrett; and the village of<br />
Cannington lies approximately 7km to the south-east of the site.<br />
7.2.2 The main access road serving the existing <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex is the<br />
C182, which is a single carriageway road passing from <strong>Hinkley</strong> <strong>Point</strong> south-east to the<br />
village of Cannington. The C182 routes to the east of Shurton and to the west of<br />
Combwich and passes through the centre of Cannington to join the A39 to the south of<br />
the village.<br />
Main Predicted Impacts<br />
7.2.3 The jetty development’s construction is programmed in two consecutive and overlapping<br />
stages totalling seven quarters, spanning Quarter 2 2011 to Quarter 4 2012. The first<br />
stage would take place between Quarter 2 2011 and Quarter 2 2012, potentially running<br />
concurrently with the site preparation works which are due to be completed in Quarter 1<br />
2012. The second stage of would follow on directly from the first stage and is<br />
programmed to take place between Quarter 2 2012 and Quarter 4 2012.<br />
7.2.4 The jetty development’s design seeks to minimise the amount of road traffic generated.<br />
For example, rather than being imported by road, construction materials would be<br />
imported by sea where they are needed for the jetty’s offshore components and fill<br />
material for the aggregates storage area’s development platform would be sourced on<br />
site. Table 3 details the transport demand for the jetty construction works.<br />
7.2.5 For the jetty, offshore construction work would be carried out in two weekday shifts to be<br />
influenced by the tidal patterns. Onshore construction work would be carried out on<br />
weekdays (07:00 to 18:00) and Saturdays (07:00-13:00), but not on Sundays, bank<br />
holidays or public holidays.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 20 November 2010
Figure 8 Main Traffic Routes to <strong>Hinkley</strong> <strong>Point</strong><br />
7.2.6 During the jetty development’s construction phase, the peak daily staff numbers equates<br />
to 120 vehicle trips. Daily HGV traffic associated with the jetty development is estimated<br />
at 8 HGV trips per day. Base flows on Rodway for 2012 are forecast at 7672, which<br />
means that the jetty development changes flows by 1.6% over the baseline. Closer to<br />
the application site, Wick Moor Drove registered an average daily two-way flow of 1,950<br />
vehicles for a five day average during March 2010, which means that the jetty<br />
development changes flows by. 6.4% over the baseline.<br />
Table 3 <strong>Jetty</strong> Construction Material Quantities and Personnel<br />
Movements 2011 Q1 2011 Q2 2011 Q3 2011 Q4 2012 Q1<br />
a Daily HGV Deliveries<br />
(quantities)<br />
b Daily HGV Deliveries<br />
(contingency)<br />
0 2 2 2 2<br />
0 2 2 2 2<br />
c Personnel 0 60 60 60 60<br />
d Daily Two Way Trips<br />
(a+b+c)x2<br />
0 128 128 128 128<br />
7.2.7 Overall, the traffic arising from the jetty development’s construction phase is small and<br />
not significant and it is within 10% of daily traffic fluctuations. Therefore, it has been<br />
concluded that the traffic will have no discernable impact on the highway network and no<br />
further assessment of environmental impacts of the jetty development need be<br />
undertaken. The other phases of the jetty development have also been predicted to<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 21 November 2010
generate no discernable change, and impacts on transport are, therefore, assessed as<br />
being not significant.<br />
Mitigation<br />
7.2.8 Since the impacts are not significant, no mitigation measures are required.<br />
Residual Impacts<br />
7.2.9 Given that the original impacts are not significant, the residual impacts are also not<br />
significant.<br />
7.3 Air Quality<br />
Existing Environment<br />
7.3.1 In terms of air quality, the jetty development’s application site at <strong>Hinkley</strong> <strong>Point</strong> is located<br />
in a rural setting on the coastline of the Severn Estuary. This provides favourable<br />
conditions for pollutant dilution and dispersion, with an on-shore breeze dominating from<br />
the west-north-west. The topography of the region is also conducive to good pollutant<br />
dispersion, with the immediate area surrounding the site being rolling countryside.<br />
7.3.2 Within the district of West Somerset, industrial pollution sources are limited to two<br />
Pollution Prevention and Control (PPC) Part-A processes (<strong>Hinkley</strong> <strong>Point</strong> B and<br />
Wansbrough Paper Mill) and seven Part-B2 processes. The Wansbrough Paper Mill is<br />
located approximately 7km from the application site and is thus not expected to<br />
significantly impact the air quality in the locality. There are emissions to air arising from<br />
the operation of <strong>Hinkley</strong> <strong>Point</strong> B, although these are minimal and principally limited to<br />
emissions released during the periodic testing of backup diesel generators.<br />
Consequently, industrial pollutant sources to air in the site locality are few.<br />
7.3.3 West Somerset Council has identified the A39 as the most significant source of vehicle<br />
emissions to air in the West Somerset district. Within the district of Sedgemoor,<br />
Sedgemoor District Council has acknowledged that the steady increase of traffic volume<br />
on the Northern Distributor Road since it opened in 2003 is of concern with regards to air<br />
quality. The highest vehicle flows within Sedgemoor, however, result from traffic on the<br />
M5, which has Annual Average Daily Traffic (AADT) of approximately 80,000 vehicles per<br />
day.<br />
7.3.4 The baseline air quality monitoring campaign confirmed that the air quality in the<br />
immediate vicinity to <strong>Hinkley</strong> <strong>Point</strong> can be generally categorised as good, with pollutant<br />
concentrations well below the annual mean UK Air Quality Objective limits.<br />
Main Predicted Impacts<br />
7.3.5 The extent to which dust and particle generation and nuisance arising from the jetty<br />
development’s construction works might occur depends upon various factors, including<br />
the precise nature of work being undertaken, wind direction, wind speed, precipitation,<br />
type and quantity of material being handled, particle size distribution of the material being<br />
handled and moisture content of the material being handled.<br />
7.3.6 Airborne dust levels are more likely to increase during periods of prolonged warm, dry<br />
weather. During periods of wetter weather, precipitation not only minimises the amount<br />
of dust that becomes airborne, but also removes existing airborne dust from the<br />
atmosphere.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 22 November 2010
7.3.7 The distance from the source of the dust to the sensitive receptor (e.g. residential<br />
properties) is also critical. Both airborne dust and particle concentrations, and dust<br />
deposition rates, fall off rapidly on moving away from the source, due to dispersion and<br />
dilution. Large particles usually only travel 10 to 20m before being deposited where as<br />
smaller particles (e.g. PM 10 particles) are not readily deposited and can travel for longer<br />
distances, although the vast majority of small particles are deposited within 100m of the<br />
source. Hence, it is in the 100m zone where the risk from dust and particles is greatest.<br />
7.3.8 Thirty of the 32 identified human receptors are greater than 1km from the jetty<br />
development’s application site boundary. The separation distance between all human<br />
receptors and potential dust/PM 10 generating activities is greater than 750m. The nearest<br />
receptor is Doggets, located at a distance of approximately 786m from the closest point<br />
of relevant site activity.<br />
7.3.9 Given that the majority of the dust would be deposited within 100m of the source, human<br />
receptors are expected to be sufficiently far enough away from the closest point of<br />
construction activity to allow for substantial dispersion, dilution and deposition of<br />
dust/PM 10 . It is, therefore, extremely unlikely that dust would be a problem at any human<br />
receptors and the significance of this impact is assessed as minor.<br />
7.3.10 Given the relatively low numbers of diesel powered off-road construction plant and<br />
machinery required for the jetty development’s construction works, site exhaust<br />
emissions to air are predicted to be of imperceptible or small magnitude, and thus<br />
negligible in terms of their impact. Similarly, exhaust emissions from marine vessel<br />
movements associated with the jetty construction activities are also predicted to be of<br />
imperceptible, and thus negligible in terms of their impact.<br />
7.3.11 Construction of the jetty would lead to a negligible increase in the volume of road traffic.<br />
Therefore, the impact of all vehicular emissions to air (NO 2 , PM 10 and PM 2.5 ) associated<br />
with traffic generated by the jetty development is not considered to be significant.<br />
Mitigation<br />
7.3.12 All potential air quality impacts have been assessed as minor or not significant before<br />
any mitigation has been applied.<br />
7.3.13 Nevertheless, mitigation measures are proposed to control dust and particulate<br />
emissions during the jetty development works and to ensure dust nuisance is prevented<br />
in areas around the site. These measures would be included within the Dust<br />
Management Plan (DMP) which forms part of the Environmental Management and<br />
Monitoring Plan (EMMP) for the jetty development.<br />
7.3.14 In addition, a Dust Monitoring Scheme (DMS) would detail any associated monitoring<br />
responsibilities required to ensure that the DMP is being implemented successfully.<br />
Precise details of the DMP will be determined through consultation (e.g. with West<br />
Somerset Council), but should make reference to current best practice guidance and<br />
other supporting documentation.<br />
7.3.15 A comprehensive Travel Plan would also be implemented to minimise off-site vehicular<br />
movements during the jetty development’s construction works, to mitigate the associated<br />
impacts from vehicular exhaust emissions to air. Such measures would include, but by<br />
no means limited to, car sharing schemes and provision of bus transport for the<br />
workforce.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 23 November 2010
7.3.16 Given that the potential impacts during jetty development’s operation,<br />
dismantling/restoration and, if required, removal/reinstatement phases are similar to or<br />
less than those during jetty development’s construction phase, the mitigation measures<br />
for the jetty development’s construction phase could be implemented during the jetty<br />
development’s other phases.<br />
Residual Impacts<br />
7.3.17 No significant residual impacts are predicted to occur. Nevertheless, as detailed above,<br />
measures would be put in place in accordance with current good practice for construction<br />
management.<br />
7.4 Noise and Vibration<br />
Existing Environment<br />
7.4.1 Baseline noise surveys were undertaken to obtain a measure of the existing noise<br />
environment, in accordance with the relevant guidance documents. The dominant noise<br />
sources identified during the baseline noise survey included local road traffic, birdsong<br />
and surf movement (at a coastal monitoring location). The determined ambient noise<br />
levels are typical of a rural environment, dropping to low levels during the night time.<br />
Main Predicted Impacts<br />
7.4.2 Assessments of the jetty development’s construction noise impacts were undertaken for<br />
three distinct activity scenarios (i.e. points in time when multiple construction activities<br />
are expected to be ongoing). These were identified primarily to provide an assessment<br />
of the worst-case situation at each of the identified sensitive receptor locations. It is<br />
predicted that the recognised proposed noise threshold criteria would not be exceeded at<br />
any residential receptor location during the jetty development’s construction. Hence the<br />
significance of the impact is assessed as minor adverse (see Figure 9).<br />
7.4.3 At the assessed public amenity receptor location on Benhole Lane, high noise levels are<br />
predicted during specific activities associated with the jetty development’s construction<br />
works close to the site boundary. The significance of the noise impact to this location<br />
during these periods is assessed as moderate adverse (in the short term). Noise impacts<br />
on other public amenity locations (e.g. the Coast Path, Wick Moor / Pixies’ Mound) are<br />
assessed as minor adverse.<br />
7.4.4 The nature of the jetty development’s construction means that the worst-case situation<br />
would be short term and may only exist for a matter of days. There would also be regular<br />
periods, even during the course of a single day, when the assumed noise plant would not<br />
be in operation (i.e. during breaks or changes of working routine).<br />
7.4.5 The potential vibration impacts resulting from the jetty development’s construction have<br />
been assessed. Given the significant distance between areas where construction<br />
activities may cause ground borne vibration and residential properties, it is not expected<br />
that any perceptible vibration would occur within those properties and impacts are<br />
assessed as minor adverse.<br />
7.4.6 Assessments of the jetty development’s operational noise impacts were undertaken for<br />
four aggregates import scenarios (covering both day and night-time working). It is<br />
predicted that the recognised proposed noise threshold criteria would not be exceeded at<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 24 November 2010
any residential receptor location during the jetty development’s operation. Hence the<br />
significance of the impact is assessed as minor adverse.<br />
7.4.7 At the assessed public amenity receptor location on the West Somerset Coast Path at its<br />
closest point to the jetty, receptors (i.e. users of the public footpath) would be exposed to<br />
high noise levels during specific activities associated with the jetty development’s<br />
operation. However, the receptors are not considered to be permanently exposed to the<br />
operational noise (unlike a receptor living at a residential property), so the potential noise<br />
impact of cargo operations to users of the public footpath is assessed as being of minor<br />
significance.<br />
Figure 9 Noise Contour Plot (Scenario 1)<br />
7.4.8 The dismantling of the jetty development and restoration of the site is likely to involve<br />
similar activities to construction, except with reduced intensity. Therefore, it is assessed<br />
that the overall noise and vibration impacts during this phase would be minor adverse.<br />
7.4.9 The removal and reinstatement of the site is also likely to involve similar activities to<br />
construction, except with reduced intensity. Therefore, it is assessed that the overall<br />
noise impacts and vibration impacts during this phase would be minor adverse.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 25 November 2010
Mitigation<br />
7.4.10 The main mitigation to be implemented would include good construction practice and<br />
management tools for minimising nuisance from noise and vibration. For example,<br />
British Standard BS 5228: Part 1:2009 gives detailed advice on standard good<br />
construction practice for minimising nuisance from construction noise. This includes the<br />
use of electrical items of plant instead of diesel plant in especially sensitive locations,<br />
keeping internal haul roads well maintained and avoiding steep gradients where possible,<br />
avoiding unnecessary revving of engines and switching of equipment when it is not in<br />
use.<br />
7.4.11 Measures to be incorporated would be included within the EMMP for the project. As<br />
appropriate, these would include:<br />
• use of white-noise spectrum reversing alarms and/or in-cab radar systems;<br />
• soft-start piling operations; and<br />
• prior notice for noisy short-term onshore activities that are expected to exceed the<br />
respective construction noise limit (48 hours in advance).<br />
7.4.12 A formal system would be put in place which identifies the roles and responsibilities of<br />
site staff regarding the noise complaint action procedure. Site logs would be maintained,<br />
detailing all complaints received relating to noise nuisance impacts, and the<br />
corresponding response made to each complainant.<br />
7.4.13 The assessment of potential hourly road traffic noise impacts includes an assumed 2.24<br />
car share rate. This would be managed by through a Travel Plan and minimising the<br />
number of car parking spaces on site.<br />
Residual Impacts<br />
7.4.14 Table 4 presents a summary of the significant noise impacts that would remain after the<br />
measures discussed above have been put into practice. It should be noted that<br />
measures built into the jetty development’s design to minimise adverse impacts (e.g. best<br />
practice) is not considered to be mitigation.<br />
Table 4 <strong>Summary</strong> of Significant Impacts on Noise and Vibration<br />
Description of Impact Impact Mitigation Measure Residual Impact<br />
Construction Phase<br />
Onshore construction<br />
works<br />
Moderate adverse<br />
(Benhole Lane<br />
PRoW)<br />
Implementation of<br />
best practice<br />
measures<br />
Moderate adverse<br />
Receptors are<br />
transient<br />
Dismantling and Restoration Phase<br />
Onshore construction<br />
works<br />
Minor to major<br />
adverse (public<br />
footpaths and other<br />
outdoor amenities)<br />
Implementation of<br />
best practice<br />
measures<br />
Negligible to<br />
moderate adverse<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 26 November 2010
Description of Impact Impact Mitigation Measure Residual Impact<br />
Removal and Reinstatement Phase<br />
Onshore construction<br />
works<br />
Negligible to<br />
moderate adverse<br />
(public footpaths<br />
and other outdoor<br />
amenities)<br />
Implementation of<br />
best practice<br />
measures<br />
Negligible to<br />
moderate adverse<br />
7.5 Landscape and Visual Amenity<br />
Existing Environment<br />
7.5.1 For the purposes of the EIA, the Landscape and Visual Impact Assessment (LVIA) study<br />
area was determined through computer modelling, desk studies and consultation, and<br />
detailed landscape analysis was undertaken up to around 5km from the application site.<br />
7.5.2 There are no international, national, regional or local landscape designations within the<br />
application site. Exmoor National Park is located 14km to the west of the application site.<br />
Two Areas of Outstanding Natural Beauty (AONB) are located within the study area,<br />
namely Quantock Hills AONB (4km south-west of the site) and Mendip Hills AONB (18km<br />
north-east of the site).<br />
7.5.3 No county and local landscape designations exist within the application site. However,<br />
several county and local designations of relevance to the LVIA are present within the<br />
study area. They include Conservation Areas, Listed Buildings, County Wildlife Sites and<br />
local council landscape policies designating an area as a Green Wedge.<br />
7.5.4 The application site lies within the ‘Vale of Taunton and Quantock Fringes’ National<br />
Landscape Character Area and ‘Quantock Vale’ County Landscape Character Area. Five<br />
seascape character areas have also been identified within the study area using existing<br />
local landscape character area assessments.<br />
7.5.5 The application site is situated within an area of rolling farmland and does not contain<br />
any landscape elements and features of high national, regional, county or district<br />
importance. The ridge of Green Lane situated to the south of the application site is a<br />
feature of local importance. Historic field patterns, a few hedgerows and watercourses<br />
with adjacent riparian vegetation are other locally important elements and features within<br />
the application site. In the wider context, the application site lies within an intrinsically<br />
dark area; however the adjacent <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex is a significant<br />
source of existing light pollution.<br />
7.5.6 The visibility of the application site varies within the study area. Open views into the<br />
application site exist from the areas of farmland up to 3km to the west of the site and<br />
from elevated viewpoints situated within the north-eastern fringes of the Quantock Hills<br />
AONB. The application site is predominantly screened from the south by the local ridge<br />
of Green Lane. No views into the application site exist from Knighton, Shurton or Burton<br />
and glimpsed views into the application site exist from elevated areas of farmland up to<br />
5km away. The existing <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex screens the application<br />
site from the east. A few long distance views into the application site exist from the most<br />
elevated viewpoints within the study area. The visibility of the application site has been<br />
identified through a selection of 23 representative panoramic views.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 27 November 2010
Main Predicted Impacts<br />
Landscape Impacts<br />
7.5.7 This assessment takes account of the main design features of the development, such as<br />
development footprint adjustments to avoid important landscape features or minimising<br />
the size of the proposed structures, but not the advanced planting or adoption of<br />
appropriate lighting controls, which are considered mitigation.<br />
7.5.8 Before the implementation of the mitigation measures, the landscape impacts on the<br />
national, regional, county and district landscape character would be short-term, adverse<br />
and of minor significance during construction, operation, dismantling (but not restoration)<br />
and, if required, removal (but not reinstatement) of the jetty development; and long-term,<br />
neutral and of negligible significance following restoration and, if required, reinstatement.<br />
7.5.9 The local and site-specific impacts on landscape character, impacts on seascape<br />
character as well as on local and site-specific landform would be short-term, adverse and<br />
of moderate significance during construction, operation, dismantling (but not restoration)<br />
and, if required, removal (but not reinstatement) of the jetty development; and long-term,<br />
neutral and of negligible significance following restoration and, if required, reinstatement.<br />
7.5.10 The local and site-specific impacts on land use and land cover, would be short-term,<br />
adverse and of minor significance during construction, operation, dismantling (but not<br />
restoration) and, if required, removal (but not reinstatement) of the jetty development;<br />
and long-term, neutral and of negligible significance following restoration and<br />
reinstatement.<br />
Visual Impacts<br />
7.5.11 The visibility of the unmitigated jetty development would vary depending on the<br />
separation distance and elevation of viewpoints from the site. Visual impact would also<br />
be caused by the potential light pollution of the jetty development’s lighting scheme<br />
before mitigation.<br />
7.5.12 Impacts associated with construction, dismantling (but not restoration) and, if required,<br />
removal (but not reinstatement) would be short-term (0-5 years), operational impacts<br />
would be short-term to medium-term (0-15 years), and impacts associated with the<br />
restored and, if required, reinstated landscape would be long-term (over 15 years).<br />
7.5.13 It is assessed that during construction and operation of the jetty development there would<br />
be visual impacts of major adverse significance in the local area where local PRoW have<br />
views of the application site and, therefore, where the medium magnitude of visual<br />
change is combined with high sensitivity receptors. The main adverse visual impacts<br />
would occur within the Coastal Eastern Lowlands (receptors represented by PRoW WL<br />
23/95 and PRoW no. WL 24/9; see Figure 2) up to 3km to the west of the application<br />
site. All these locations would receive views of the jetty development, as well as<br />
changed topography.<br />
7.5.14 Adverse impacts of major significance would also occur on the locally important ridge to<br />
the south of the site (PRoW no. WL 23/110) (see Figure 10), which due to its elevation<br />
would receive views of the majority of the site, and at Pixies Mound (Wick Barrow). From<br />
Pixies Mound the jetty development would not be visible; however, the proximity of the<br />
eastern part of the application site would cause a medium magnitude of visual change.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 28 November 2010
7.5.15 Due to the screening provided by the Green Lane ridge and undulating topography there<br />
would be no visual impact on views from Shurton, Burton or Knighton.<br />
Figure 10 Existing View and Photomontage of the <strong>Jetty</strong> Development from<br />
Principal Viewpoint 1 (PRoW number WL 23/110, Benhole Lane)<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 29 November 2010
7.5.16 Impacts on views from the east, including farms located within the Wick Moor landscape<br />
character area would be of minor to moderate adverse significance depending on the<br />
sensitivity of the receptor. These views would be potentially affected by the light pollution<br />
associated with the (unmitigated) jetty development. The majority of views, however,<br />
would not be affected due to screening provided by the existing <strong>Hinkley</strong> <strong>Point</strong> Power<br />
Station Complex, topography and vegetation. The only visual impact of major adverse<br />
significance would occur at Pixies Mound due to the very short distance from the site and<br />
medium magnitude of impact on this highly sensitive receptor.<br />
7.5.17 The impact of the unmitigated jetty development and associated lighting on the elevated<br />
areas of the Quantock Hills AONB or Mendip Hills AONB would be of moderate adverse<br />
significance. The main source of this impact would be light pollution. A similar adverse<br />
impact could be also experienced from Brean Down, Fairfield House, Stockland Bristol<br />
and other local viewpoints up to 3km from the application site. Although the majority of<br />
these viewpoints would have limited views of the jetty development’s construction and<br />
operation, adverse impacts would occur due to potential light pollution.<br />
7.5.18 The unmitigated dismantling and restoration phase of the jetty development or, if<br />
required, removal and reinstatement phase, would include the dismantling or removal of<br />
all built elements created during the construction phase and restoration or reinstatement<br />
of the existing landform and vegetation.<br />
7.5.19 The short-term visual impacts associated with the dismantling or, if required, removal of<br />
the jetty development would be largely the same as the impacts associated with<br />
construction and operation. The impact caused by the dismantling or, if required, removal<br />
of built form, earthworks and lighting, as well as activities associated with the replanting<br />
of the vegetation lost during construction within the site, would cause the same<br />
magnitude of visual impacts and remain adverse in nature.<br />
7.5.20 Following the short-term impact associated with the dismantling or, if required, removal of<br />
the jetty, long-term impacts would occur due to the restoration or, if required,<br />
reinstatement of the existing landscape features within the application site, including<br />
topography and vegetation. The impact on all visual receptors following restoration or, if<br />
required reinstatement would be of negligible significance in the long-term.<br />
Mitigation<br />
7.5.21 Following the identification of the potential landscape and visual impacts on the receptors<br />
identified in the baseline study, measures have been proposed to mitigate these effects<br />
during construction, operation, dismantling and restoration and, if required, removal and<br />
reinstatement phases of the jetty development.<br />
7.5.22 The mitigation measures are proposed within the site boundary and, where possible,<br />
within the wider <strong>Hinkley</strong> <strong>Point</strong> C development site. To mitigate adverse impacts on the<br />
Coastal Eastern Lowlands area and Fairfield House, and to protect land on the estate<br />
(which is of outstanding scenic interest) from landscape and visual impacts during all<br />
phases of the jetty development, Fairfield Estate (supported by <strong>EDF</strong> Energy and in<br />
consultation with English Heritage and Natural England) is in the process of preparing<br />
proposals for off site planting to augment the on site mitigation (see Figure 11).<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 30 November 2010
Figure 11 Construction Mitigation Landscape Plan<br />
7.5.23 To minimise landscape and visual impact of the jetty development, the design of the silos<br />
(which are a design feature, not mitigation) was also considered. The preferred option<br />
was selected during the following process. The original engineering design included silos<br />
at 40m high located on the development platform for the aggregates storage area.<br />
Sensitivity of the location was recognised and the impacts considered unacceptable in<br />
the context of the Preliminary Works. Design options were explored to lower the height of<br />
the silos whilst still achieving the project’s storage requirements. These options included<br />
laying the silos on their sides which would result in the silos being at least 20m high due<br />
to operational requirements, and also developing the option of a storage building instead<br />
of silos. This structure would also have to be of considerable size. The preferred option is<br />
to provide a number of smaller silos at 20m high which would achieve the minimum<br />
engineering requirements. The top of the silos is comparable to the height of Green Lane<br />
which ensures that visual impacts on the land to the south of Green Lane, including the<br />
settlements of Shurton, Burton Knighton and Wick, are limited.<br />
7.5.24 The main mitigation measures proposed for construction and operation of the jetty<br />
development include seeding 8.66ha of land within the application with grass to soften<br />
views, retaining 0.03ha of broad leaved woodland and 0.31ha of improved grassland<br />
within the application site, planting 550m native species rich hedgerow along the western<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 31 November 2010
oundary to contribute to biodiversity and provide visual screening from the PRoW<br />
located on low topography to the west of the application site, and protecting boundary<br />
vegetation by appropriate fencing during construction.<br />
7.5.25 The impact of lighting during construction would be mitigated by the implementation of<br />
appropriate lighting mitigation measures. The proposed limits on intrusive light aimed at<br />
minimising problems for neighbouring areas are designed to protect the most sensitive<br />
landscapes, such as AONB, from light pollution. Other lighting mitigation objectives and<br />
measures include minimising the use of light (i.e. only in areas being actively worked),<br />
directing light downwards to minimise light pollution, avoidance of ‘over-lighting’ of the<br />
area (using correct illumination levels), avoidance of lighting close to the application site<br />
boundary, avoidance of unnecessary night time lighting and reduction of the heights of<br />
light columns to an acceptable minimum.<br />
7.5.26 The landscape proposals during the dismantling and restoration phase would be limited<br />
to the western part of the application site, to the west of the proposed <strong>Hinkley</strong> <strong>Point</strong> C<br />
Power Station. The remaining part of the application site would be occupied by the<br />
<strong>Hinkley</strong> <strong>Point</strong> C nuclear power station. The key change to the site would be the<br />
remodelled, gently undulating landform providing screening to the remaining part of the<br />
site from the adjacent landscape. The landform would be formed as a slope rather than a<br />
bund, in line with the existing local landscape character. The screening proposals would<br />
be reinforced by a narrow strip of broad-leaved woodland stretching from the coastline to<br />
the southern boundary of the application site, adjacent to the proposed <strong>Hinkley</strong> <strong>Point</strong> C.<br />
The remaining landscape would comprise restored agricultural field, including arable land<br />
and fields of semi-improved grassland divided by species-rich hedgerows on field<br />
boundaries and arable conservation headlands. All proposed planting would be of native<br />
species, selected to complement and enhance existing local landscape character and to<br />
suit site conditions. Other landscape features proposed within the western part of the<br />
application site would include a narrow strip of calcareous grassland on top of the coastal<br />
cliff and dense scrub (see Figure 12). The access would be improved by additional<br />
public footpaths to be located within the restored site.<br />
7.5.27 Should it be required, the landscape mitigation for the short period of removal (but not<br />
reinstatement) activities would be the same as for the construction phase, due to the<br />
similar nature of works and their predicted visual impact. The landscape and ecological<br />
features identified for retention and/or protection during the jetty’s construction would be<br />
also retained and/or protected during the removal and reinstatement works. It is<br />
proposed that during the removal and reinstatement phase the landscape features within<br />
the application site would be reinstated to the existing condition, including the<br />
reinstatement of the landform to resemble the existing condition (including the removal of<br />
the development platform for the aggregates storage area), and reinstatement of<br />
agricultural land and existing landscape features with no net gain or loss in biodiversity.<br />
During the reinstatement phase, the PRoW closed during the construction phase of the<br />
jetty development would be reinstated, including the coastal footpath. The reinstated<br />
footpaths would be clearly defined and signposted.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 32 November 2010
Figure 12 Landscape Restoration Plan<br />
Residual Impacts<br />
Landscape Impacts<br />
7.5.28 Following the implementation of mitigation measures, residual landscape impacts on<br />
national and regional landscape character would be of negligible significance during all<br />
phases of the jetty development.<br />
7.5.29 Residual impacts on county and district landscape character would be adverse and of<br />
minor significance during the construction, operation, dismantling (but not restoration) or,<br />
if required, removal (but not reinstatement), and of negligible neutral significance<br />
following restoration or reinstatement.<br />
7.5.30 Residual impacts on seascape character would be adverse and of moderate significance<br />
during the construction, operation, dismantling (but not restoration) or, if required,<br />
removal (but not reinstatement), and long-term, neutral and of negligible significance<br />
following restoration or reinstatement.<br />
7.5.31 During construction, operation, dismantling (but not restoration) or, if required, removal<br />
(but not reinstatement), residual impacts on local and site-specific landscape character<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 33 November 2010
and landform would be adverse and of moderate significance and impacts on local and<br />
site-specific land use and land cover would be adverse and of minor significance.<br />
7.5.32 Following restoration, the residual landscape impacts on local landscape character as<br />
well as local and site-specific land use and land cover would be long-term beneficial and<br />
of minor significance. The residual impact on local and site-specific landform during<br />
restoration would be adverse and of minor significance.<br />
7.5.33 Following reinstatement, the residual impact on local and site-specific landscape<br />
character, landform, land-use and land cover would be long-term, neutral and of<br />
negligible significance.<br />
Visual Impacts<br />
7.5.34 Following the implementation of the mitigation measures, some residual visual impact of<br />
the jetty development would be reduced in comparison to the unmitigated construction<br />
phase. The residual visual impacts on elevated viewpoints located in the vicinity of the<br />
application site (predominantly up to 3km to the west of the site) would be largely the<br />
same as during the unmitigated construction however, all visual impacts on more distant<br />
receptors would be reduced by the proposed mitigation measures, which are primarily<br />
targeted to mitigate the lighting impacts (potential light pollution) on the surrounding<br />
AONB. The additional hedgerow planting to the west of the application site would help<br />
reduce visual impacts from some PRoW located immediately to the west of the<br />
application site (see Figure 11).<br />
7.5.35 The residual visual impacts of major adverse significance would not change in<br />
comparison to the unmitigated scheme and would include PRoW no. WL 23/95, PRoW<br />
no. WL 24/9 to the west of the application site, PRoW no. WL23/110 West of Benhole<br />
Lane (see Figure 2), and at Pixies Mound (Wick Barrow). An impact of moderate<br />
adverse significance would occur at Viewpoints 8 and 9 within the Quantock Hills AONB<br />
(Beacon Hill and footpath between Woodland Hill and Dowsborough), which represent<br />
the north-eastern parts of the Quantock Hills AONB located on high topography that<br />
would receive limited views of the jetty development’s construction. The residual visual<br />
impact on the remaining viewpoints, including a number of AONB viewpoints, would be<br />
reduced to either minor adverse or negligible.<br />
7.5.36 The visibility of the mitigated jetty development during operation, dismantling (but not<br />
restoration) or, if required, removal (but not reinstatement) would be the same as the<br />
visibility during the mitigated construction phase (same visual receptors would be<br />
affected). Hence the magnitude of change and the resulting significance of impact would<br />
be the same as during construction. The nature of visual impacts during operation would<br />
change from short-term to medium-term, although the impacts would remain temporary.<br />
7.5.37 The significance of the residual visual impact of the restored landscape within the site<br />
would be largely negligible, as there would be no change in views from the majority of<br />
visual receptors. The only visual receptors which would experience visible change due to<br />
the implementation of a Landscape Restoration Plan would be Principal Viewpoints 1, 2<br />
and 3, where permanent beneficial impacts would occur due to the mitigation measures.<br />
7.5.38 Following the reinstatement phase, if required, and the maturation of landscape<br />
proposals, the significance of residual impact for all visual receptors is assessed as<br />
negligible in the long-term (15 years and beyond).<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 34 November 2010
7.5.39 Table 5 below presents a summary of the significant landscape and visual impacts that<br />
would remain after the mitigation measures discussed above have been put into practice.<br />
Table 5 <strong>Summary</strong> of Significant Residual Impacts on Landscape and Visual<br />
Amenity<br />
Receptor Impact Mitigation<br />
Measures<br />
Residual Impact<br />
Construction, Operation, Dismantling (but not Restoration) and Removal (but not<br />
Reinstatement) Phases<br />
Seascape character units<br />
Moderate,<br />
adverse,<br />
temporary<br />
Landscape and<br />
lighting mitigation<br />
Moderate,<br />
adverse,<br />
temporary<br />
Local and site-specific<br />
landscape character<br />
Moderate,<br />
adverse,<br />
temporary<br />
Landscape and<br />
lighting mitigation<br />
Moderate,<br />
adverse,<br />
temporary<br />
Local and site-specific<br />
landform<br />
Moderate,<br />
adverse,<br />
temporary<br />
N/A<br />
Moderate,<br />
adverse,<br />
temporary<br />
Principal Viewpoint 1:<br />
PRoW no. WL23/110 West<br />
of Benhole Lane<br />
Major, adverse,<br />
temporary<br />
Landscape and<br />
lighting mitigation<br />
Major, adverse,<br />
temporary<br />
Principal Viewpoint 2:<br />
Coastal Footpath PRoW<br />
no. WL 23/95<br />
Major, adverse,<br />
temporary<br />
Landscape and<br />
lighting mitigation<br />
Major, adverse,<br />
temporary<br />
Principal Viewpoint 3:<br />
Lilstock - PRoW no. WL<br />
24/9<br />
Major, adverse,<br />
temporary<br />
Lighting mitigation<br />
Major, adverse,<br />
temporary<br />
Principal Viewpoint 5:<br />
Pixies Mound (Wick<br />
Barrow)<br />
Major, adverse,<br />
temporary<br />
Landscape and<br />
lighting mitigation<br />
Major, adverse,<br />
temporary<br />
Principal Viewpoint 7:<br />
Quantock Hills AONB,<br />
Beacon Hill<br />
Moderate,<br />
adverse,<br />
temporary<br />
Lighting mitigation<br />
Moderate,<br />
adverse,<br />
temporary<br />
Principal Viewpoint 8:<br />
Quantock Hills AONB,<br />
Footpath between<br />
Woodland Hill and<br />
Dowsborough<br />
Moderate,<br />
adverse,<br />
temporary<br />
Lighting mitigation<br />
Moderate,<br />
adverse,<br />
temporary<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 35 November 2010
Receptor Impact Mitigation<br />
Measures<br />
Residual Impact<br />
Restoration Phase<br />
Principal Viewpoint 1:<br />
PRoW no. WL23/110 West<br />
of Benhole Lane<br />
Negligible, neutral,<br />
permanent<br />
Landscape<br />
Restoration Plan<br />
Moderate,<br />
beneficial,<br />
permanent<br />
Principal Viewpoint 2:<br />
Coastal Footpath PRoW<br />
no. WL 23/95<br />
Negligible, neutral,<br />
permanent<br />
Landscape<br />
Restoration Plan<br />
Moderate,<br />
beneficial,<br />
permanent<br />
7.6 Historic Environment<br />
Existing Environment<br />
7.6.1 There are no Scheduled Monuments, Listed Buildings, Conservation Areas or Registered<br />
Parks and Gardens or Registered Battlefields within the application site. The closest<br />
Scheduled Monument to the application site is Wick Barrow (also known as Pixies’<br />
Mound) (see Figure 13). It is located 50m to the east of Wick Moor Drove. Wick Barrow<br />
dates from the Neolithic and Bronze Age periods and was partially excavated in 1907.<br />
Figure 13 Locations of Historic Environment Features<br />
7.6.2 Geophysical survey and trial trenching confirmed that there are no buried archaeological<br />
remains within the application site. There are, however, a number of hedgerows within<br />
the application site that meet the archaeological and historical criteria of Important<br />
Hedgerows as defined in the Hedgerow Regulations 1997. There is one historic building,<br />
Benhole Barn, which dates from the late 18 th or early 19 th century. The barn has been<br />
extensively altered and is in a derelict state.<br />
7.6.3 Undesignated heritage assets dating from the Mesolithic (10,000–3,500 BC), Neolithic<br />
(3,500-2,000 BC), Bronze Age (2,000-700BC), Iron Age (700BC-AD43), Roman (AD43-<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 36 November 2010
AD450), Early-medieval (AD 450-AD1066), Medieval (AD1066-AD1540) and Postmedieval<br />
(AD1540 onwards) periods have been identified within the 500m study area<br />
around the application site (see Figure 13).<br />
7.6.4 A foreshore survey undertaken in June 2010 confirmed that there are no surviving<br />
archaeological remains above the Mean High Water Mark.<br />
7.6.5 Offshore, the UKHO wreck record for the study area contains 14 wreck sites. No<br />
protected wrecks were identified within the application site boundary. One apparent<br />
wreck site, located ~750m east of the application site boundary, reflected a ‘diffuser’<br />
associated with the existing <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex. Another potential<br />
wreck, identified from sidescan anomalies, lies 116m north-west of the edge of the<br />
application site boundary. It is not possible to offer a definitive interpretation of the type<br />
of wreck or wreckage that this may represent. No confirmed submerged archaeological<br />
remains have been identified in the area of the jetty development.<br />
7.6.6 Lithological and stratigraphic modelling of deposits based on survey data from core logs<br />
collected in 2009 revealed a relatively consistent sequence across the survey area; ~1-<br />
3m of surficial sands, gravels or clays, overlying a more consistent clay layer (0.5-5m<br />
thick) before reaching claystone bedrock. The discovery of peat deposits underlying the<br />
uppermost superficial deposits in 39 out of 63 vibrocores, and organic rich clays in a<br />
further 13 vibrocores, confirms the widespread presence of buried peats and other<br />
palaeo-landsurfaces, first identified in the western part of the survey area. These layers<br />
thin to the south-west of the survey area and only limited organic material has been<br />
identified in the core logs from the area of the jetty development.<br />
Main Predicted Impacts<br />
7.6.7 During the jetty development it is considered that there is potential for a number of<br />
significant impacts to the historic environment.<br />
7.6.8 The Scheduled Monument, Wick Barrow, is located to the east of the site and its setting<br />
would be partially altered during the construction phase as the area to the west would<br />
become a construction site. This would result in a moderate adverse impact.<br />
7.6.9 The historic hedgerows would experience a high magnitude of impact during<br />
construction, which is assessed to be a moderate adverse impact.<br />
7.6.10 Construction of the aggregates storage area would result in the complete removal of<br />
Benhole Barn, which would result in an overall adverse impact of moderate significance.<br />
7.6.11 The buried peat and organic horizons below the soft sediments offshore are believed to<br />
be a relict Mesolithic landscape. The peat deposits may contain palaeo-environmental<br />
data such as pollen, macrofossil, insect remains and radiocarbon datable organics.<br />
Disturbance and removal of these horizons during construction works could cause a loss<br />
of research potential, and a moderate adverse impact.<br />
7.6.12 The buried peat and organic horizons below the soft sediments offshore are believed to<br />
be a relict Mesolithic landscape. The peat deposits may contain palaeo-environmental<br />
data such as pollen, macrofossil, insect remains and radiocarbon datable organics.<br />
Disturbance and removal of these horizons during construction works could cause a loss<br />
of research potential, and a moderate adverse impact.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 37 November 2010
Mitigation<br />
7.6.13 It is proposed that a Monument Management Plan should be prepared to ensure the<br />
long-term preservation, and enhancement, of Wick Barrow (Pixies Mound) and its<br />
immediate setting.<br />
7.6.14 Due to the nature of the jetty development, the preservation in-situ of the historic<br />
hedgerows within the application site boundary would not be an option, so suitable<br />
mitigation would entail preservation by record.<br />
7.6.15 Due to the low importance of Benhole Barn, suitable mitigation would entail preservation<br />
by record.<br />
7.6.16 Preservation by record of onshore heritage assets would comprise archaeological<br />
investigation and recording in advance of construction. All investigation works would be<br />
carried out in accordance with the relevant Institute for Archaeologists standards and<br />
guidance.<br />
7.6.17 Although no heritage assets have been identified within the offshore part of the<br />
application site, the area proposed for dredging of the berthing pocket contains deposits<br />
comparable to those containing archaeological material further east. Therefore a<br />
watching brief would be undertaken during this phase.<br />
Residual Impacts<br />
7.6.18 No significant residual impacts are predicted to occur.<br />
7.7 Socio-economics<br />
Existing Environment<br />
7.7.1 Baseline data has been collected for Somerset and the key districts of Sedgemoor, West<br />
Somerset and Taunton Deane. The overall picture revealed by the baseline assessment<br />
is one of, until recently, a relatively prosperous local area, as indicated by above-average<br />
rates of population and employment growth, and relatively low levels of unemployment.<br />
However, there are other indicators, including migration flows, economic structure, skills<br />
and earnings levels, which indicate a much less resilient local economy, and with<br />
particular problem pockets of deprivation and considerable variations between the three<br />
districts.<br />
7.7.2 The combined population in the three immediate districts of West Somerset, Sedgemoor<br />
and Taunton Deane is almost 256,000 (mid-2007 population estimates). West Somerset<br />
and Sedgemoor are predominantly rural districts, with relatively low population densities.<br />
Taunton Deane is also significantly rural in nature, but has a higher proportion of its<br />
population in larger urban settlements.<br />
7.7.3 The districts do display some important socio-economic issues. Sedgemoor, for example,<br />
has overall low levels of skills in the workforce, below average educational attainment,<br />
some severe pockets of multiple deprivation and worklessness. Recent studies have<br />
highlighted weaknesses in the district’s economic resilience, linked to workforce skills<br />
issues, plus, for example, a sectoral mix limited in knowledge intensive industries.<br />
Taunton Deane is heavily dependent on public sector employment, which may face cuts<br />
in the current context of public sector activity review. West Somerset has a number of<br />
significant deprivation issues, for example in relation to affordable housing and access to<br />
services.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 38 November 2010
7.7.4 The rate of job growth, between 2001-2007, in the immediate districts (West Somerset,<br />
Sedgemoor and Taunton Deane) was broadly similar to the average for Somerset (6-<br />
7%), but slightly above the South West (5.5-5.6%) and national averages (4.6%).<br />
Tourism is a particularly important local industry. Annual Business Inquiry data show that<br />
tourism-related sectors accounted for an estimated 11,100 employee jobs in the three<br />
immediate districts. This represents approximately 10.5% of all employee jobs in the<br />
immediate districts, and compares with a national average of only 8.2%.<br />
Main Predicted Impacts<br />
7.7.5 Socio-economic impacts are the people effects of major projects. Of primary focus are<br />
the employment and expenditure associated with the works. These can result in a range<br />
of knock-on effects in the local economy, including impacts on population, local<br />
employment and unemployment levels, the local accommodation markets, and demand<br />
for local services.<br />
7.7.6 <strong>EDF</strong> Energy would seek as far as possible to provide positive socio-economic benefits to<br />
the local community; for example, through opportunities for training, employment and<br />
participation in the supply chain. More specific socio-economic objectives, which would<br />
be trialled during the jetty development (i.e. prior to the anticipated <strong>Hinkley</strong> <strong>Point</strong> C<br />
Project), would include, for example:<br />
• promote the training and recruitment of local people and support the provision of<br />
training courses and facilities in the local area (data demonstrate that the structure of<br />
the local economies in Sedgemoor and West Somerset already have a strong base<br />
in construction and skilled trades);<br />
• encourage and facilitate the involvement of local businesses in the supply chain;<br />
• make use of existing accommodation in the local area and support local businesses<br />
(e.g. owners of B&Bs and caravan parks) but without displacing the local tourist<br />
industry;<br />
• ensure that non-local workers, in all forms of accommodation, are well supported<br />
and maintain high standards of conduct, especially in their interaction with the local<br />
community; and<br />
• ensure that the impacts of the development on local communities are assessed and<br />
appropriate mitigation measures are put in place (e.g. support for local health and<br />
education facilities).<br />
7.7.7 The proposed jetty development would generate the following levels of employment:<br />
• construction phase: up to 60 jobs for up to 21 months;<br />
• operation phase: approximately 10 jobs for up to 8 years;<br />
• dismantling / restoration phase: approximately 25 jobs for approximately 1 year (for<br />
dismantling); and<br />
• removal / reinstatement phase (if required): approximately 25 jobs for approximately<br />
1 year (for removal).<br />
7.7.8 Average earnings levels on site, especially during construction, are likely to be<br />
significantly above the existing local economy average. The employment impact would<br />
be minor but generally positive even though there may be some local leakage of<br />
employment benefits because of labour supply / skills limitations and the nature / policies<br />
of contractors.<br />
7.7.9 It is anticipated that approximately 45% of the workforce might be non-local / non-home<br />
based, and would move into the area for the duration of the construction phase, thus<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 39 November 2010
equiring temporary accommodation. Since there is a very substantial supply of such<br />
accommodation within a 45 minutes commute of <strong>Hinkley</strong> <strong>Point</strong>, there is unlikely to be any<br />
significant pressure from such numbers on the capacity of the tourism accommodation to<br />
satisfy the ongoing tourism market. The demand during off-peak periods may be of<br />
some benefit to suppliers of local tourism accommodation. As such, this could provide a<br />
small scale but nevertheless useful boost to the tourist accommodation sector and the<br />
Somerset tourism industry.<br />
7.7.10 Impacts on other socio-economic parameters (i.e. other services, quality of life and the<br />
wider economy) are also predicted to not be significant.<br />
Mitigation<br />
7.7.11 A series of mitigation measures would be introduced. For example, the estimated levels<br />
of local recruitment may be boosted through a proactive recruitment and training policy.<br />
Such an approach is important to meet the objectives of both the local and regional<br />
authorities and of <strong>EDF</strong> Energy, and would utilise initiatives being developed for the<br />
<strong>Hinkley</strong> <strong>Point</strong> C Project more generally through a Construction Workforce Development<br />
Strategy. These initiatives include a range of education, training and access initiatives.<br />
The programme for the jetty development (along side that for the site preparation works)<br />
provides an important opportunity to pilot, develop and fine-tune such initiatives.<br />
7.7.12 The Construction Workforce Development Strategy would include a range of measures to<br />
create a clear pathway to local employment, and would be put in place by early 2011.<br />
These measures are described in the following paragraphs.<br />
7.7.13 A Preliminary Works Skills’ Charter would be established to maximise opportunities for<br />
local people to be employed. Furthermore, <strong>EDF</strong> Energy has indicated that it is keen to<br />
support businesses in the local area<br />
7.7.14 An Employment Brokerage would provide a local one-stop shop facility, including on-line<br />
access, dedicated for the development. The brokerage would provide access for local<br />
people to job opportunities and a place where contractors would advertise their<br />
vacancies. The facility would include resourcing, job shops, and workplace managers<br />
engaging with the growing supply chain. The provision of such a facility adjacent to the<br />
site at Sizewell B helped to place 5,500 job applicants, many of whom had been<br />
unemployed.<br />
7.7.15 A Construction Skills Centre to be brought forward by Bridgwater College would be<br />
supported by <strong>EDF</strong> Energy for the provision of early entry level skills training. The<br />
contribution would be used to establish the physical development of the Centre, at a<br />
location which is practicable for the training required to support the Preliminary Works<br />
and the main <strong>Hinkley</strong> <strong>Point</strong> C Project.<br />
7.7.16 In addition, <strong>EDF</strong> Energy would encourage contractors to support and promote local<br />
recruitment, including targeting training for and recruitment from the unemployed and<br />
others in disadvantaged groups, to bring people back into the workforce. Furthermore,<br />
there should be potential for job transition supported through the Construction Workforce<br />
Development Strategy.<br />
7.7.17 <strong>EDF</strong> Energy would also monitor and publish, on a regular basis, information on the<br />
development’s performance on recruitment and training. The contractor for the site<br />
preparation enabling works has already committed to use at least two-thirds Somerset<br />
based workers to manage, supervise and carry out the work.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 40 November 2010
Residual Impacts<br />
7.7.18 No significant residual impacts are predicted to occur.<br />
7.8 Navigation<br />
Existing Environment<br />
7.8.1 The Severn Estuary is an important shipping route, with commercial vessels navigating<br />
through the deep water approaches to several ports and harbours. Apart from the Port of<br />
Bridgwater, these ports are situated distant away from <strong>Hinkley</strong> <strong>Point</strong>, either on the south<br />
coast of Wales or at and upstream of Bristol. Databases of commercial shipping<br />
movements indicate that shipping in Bridgwater Bay is very low. As shown by two<br />
months of data from 2009, most commercial shipping movements occur on the opposite<br />
side of the Bristol Channel (see Figure 14; Note: this figure shows the proposed<br />
alignments of the cooling water structures associated with <strong>Hinkley</strong> <strong>Point</strong> C - intake in blue<br />
and outfalls in red).<br />
7.8.2 The Port of Bridgwater’s limits cover approximately 25 square nautical miles and include<br />
Combwich Wharf and Dunball Wharf on the River Parrett, but do not extend west as far<br />
as the proposed jetty development. Bridgwater Harbour Authority (part of Sedgemoor<br />
District Council) is responsible for navigation and mooring, safety, rights of access,<br />
pilotage, maintenance of channels and navigation aids oil spill contingency and port<br />
waste management. Port operations, oil spill contingency and port waste management<br />
plans are in place. Commercial vessel movements at the Port of Bridgwater totalled 41<br />
in 2007 and 37 in 2008. Most vessels were carrying aggregates and general cargo.<br />
Recreational moorings within the port limits are located mainly in the River Brue Estuary<br />
and Combwich Pill, although recreational activity tends to be focused around Burnhamon-Sea.<br />
7.8.3 As indicated on Figure 14, vessels inbound for the River Parrett and the Port of<br />
Bridgwater pass to the west and south of the Bell Gore Buoy, having due regard for the<br />
Cobblers Patch Shoal of -1.8m CD, which is located 2.5 cables south-south-west of Bell<br />
Gore. This route means vessels would pass directly north of the proposed jetty<br />
development’s location at <strong>Hinkley</strong> <strong>Point</strong>.<br />
7.8.4 The Bridgwater Bay Danger Area (D119) establishes the air space allocated for military<br />
activities and covers a circular area over land in West Somerset and sea in Bridgwater<br />
Bay. Its extent over the sea is marked on Admiralty Charts (as “Firing Practice Area<br />
D119”) and covers a partial circular area offshore that could be defined by an arc<br />
extending from <strong>Hinkley</strong> <strong>Point</strong> to beyond the 10m bathymetric contour towards Culver<br />
Sands and returning to land at Watchet. The Danger Area is a delineation of the air<br />
space above the water and does not place any restrictions on navigation and vessels<br />
have the right to transit it at any time.<br />
7.8.5 The Lilstock Range Firing Area is smaller than and is situated within D119 but only<br />
extends over the sea in Bridgwater Bay. Similar to D119, the firing area covers a partial<br />
circular area offshore that could be defined by an arc extending from east of <strong>Hinkley</strong><br />
<strong>Point</strong> and returning to land to the west of Watchet. The firing area delineates the water<br />
surface template for air to surface gunnery activities and is marked by buoys. The firing<br />
area is used primarily for military helicopter gunnery training and is operated under a<br />
clear range procedure so that exercises and training only take place when the area is<br />
clear of vessels.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 41 November 2010
Figure 14 Commercial Shipping Movements in the Bristol Channel<br />
7.8.6 According to the Port of Bridgwater’s Marine Operations Plan (2009), no commercial<br />
fishing vessels are registered at the port or on the River Parrett, although there is one<br />
vessel that can be chartered for angling. Vessel tracking and sighting by the Marine and<br />
Fisheries Agency (MFA); now part of the MMO) indicates that fishing activity in<br />
Bridgwater Bay is very limited since fishing with vessels of 15m and more is confined<br />
mainly to the west of a north to south line between Bideford (north Devon) and Swansea<br />
(south Wales), and fishing activity to the east of this line is much reduced, particularly<br />
east of a north to south line through Lynmouth (north Devon).<br />
7.8.7 Data derived from the Royal Yachting Association (RYA) and Cruising Association<br />
indicate that the water area surrounding <strong>Hinkley</strong> <strong>Point</strong> and the inner Bristol Channel as a<br />
whole is a designated sailing area for recreational craft, and the water area<br />
approximately 3.5nm to the west of <strong>Hinkley</strong> <strong>Point</strong> is used for racing. According to the<br />
Port of Bridgwater’s Marine Operations Plan (2009), there are three sailing clubs within<br />
the Port of Bridgwater. Combwich Cruising Club is based at Combwich and the Burnham<br />
Motor Boat & Sailing Club is based on the River Brue. Both clubs have afloat moorings.<br />
The Burnham Boat Owners’ Sea Angling Association has a substantial membership but<br />
only small boats, which members launch from Burnham Slipway when required. Some<br />
visiting yachts call each year. The inbound route to Burnham Motor Boat & Sailing Club<br />
passes to the north of the proposed jetty development site in a similar manner to<br />
commercial shipping.<br />
Main Predicted Impacts<br />
7.8.8 Impacts on navigation are assessed on the basis of risks of hazards to navigation.<br />
Hazards were identified during a specialist workshop with key stakeholders. Risk<br />
assessments are based on the potential consequences and likelihoods of the hazards<br />
identified on navigation receptors (i.e. commercial vessels, military vessels, fishing<br />
vessels, recreational vessels and the Port of Bridgwater’s interests).<br />
7.8.9 For the risk assessments, the potential consequences are considered to be severe for<br />
commercial vessels and the Port of Bridgwater’s interests, and minor for military, fishing<br />
and recreational vessels. The potential likelihoods are considered to be medium for<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 42 November 2010
commercial vessels and the Port of Bridgwater’s interests and very low for military,<br />
fishing and recreational vessels. The application of these hazard components means<br />
that risks to commercial vessels and the Port of Bridgwater’s interests are assessed as<br />
high and, therefore, unacceptable, and that risks to military, fishing and recreational<br />
vessels are assessed as low and, therefore, acceptable.<br />
7.8.10 The jetty development (including the presence and movement of construction plant and<br />
materials) would be constructed within Danger Area D119 and within or close to the<br />
Lilstock Range Firing Area. Although there are no restrictions on navigation within these<br />
areas, the firing range is only used when it is clear of vessels. Therefore, depending on<br />
the presence of the jetty development and construction plant in the firing area and / or the<br />
proximity of the jetty development and construction plant to the firing area, the jetty<br />
development’s construction activities could preclude the use and/or the safe use of the<br />
firing area for military training and exercises. Based on informal consultation with the<br />
MoD, it is anticipated that interference to military activities would be high / unacceptable if<br />
the jetty and/or construction plant were to be present within or directly adjacent to the<br />
firing area during construction activities.<br />
Mitigation<br />
7.8.11 A number of control measures are proposed as mitigation to reduce risks such that they<br />
are acceptable. During the jetty development’s construction, dismantling / restoration<br />
and (if required) removal / reinstatement phases, an exclusion zone of some 500m would<br />
be in place around the jetty head (see Figure 15) and it may be prudent to implement a<br />
standby vessel (small patrol vessel) during working hours.<br />
7.8.12 Control measures are also recommended to reduce the risk to navigation associated with<br />
the passage of dredging plant between the jetty and the Cardiff Grounds offshore<br />
disposal site. Dredging plant should not cross vessels that may be restricted by their<br />
draught or restricted by their ability to manoeuvre, and should, at all times, pass to the<br />
west of Bell Gore and Cobbler Patch, with due regard given to the shoal patch of 18m.<br />
7.8.13 Once constructed, the jetty would have to be marked (e.g. lights on the jetty head) for<br />
safety (e.g. to reduce the risk of passing vessels colliding with it). To reduce the risk to<br />
navigation associated with the presence and movement of the vessels using the jetty, it is<br />
recommend that navigation information be clearly documented in a Safety Management<br />
System (SMS).<br />
7.8.14 On the basis of consultation with the MoD, the following measures are proposed in<br />
relation to the Lilstock Range Firing Area:<br />
• the buoys delineating the firing area are to be moved westwards within Danger Area<br />
D119’s boundary such that the firing area is temporarily re-positioned away from the<br />
jetty development;<br />
• operational and maintenance plant, vessels and other marine equipment associated<br />
with the jetty development’s operation activities including maintenance works are to<br />
be instructed to avoid entering the firing area (even if, for example, transiting the<br />
firing area offers a more direct route to and from the jetty) by means of Notices to<br />
Mariners and other instructions from the Harbour Master; and<br />
• the proposed HEO (which is part of the application) will include provisions that will<br />
only allow the jetty development’s harbour authority (i.e. the authority that would be<br />
established by the HEO) to make by-laws affecting navigation in the authority's limits<br />
of jurisdiction around the jetty and to give general directions to vessels navigating<br />
within those limits subject in both cases to prior consultation with the MoD.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 43 November 2010
Figure 15 Proposed Exclusion Zone<br />
Residual Impacts<br />
7.8.15 With the controls in place, the residual risks to commercial vessels, the Port of<br />
Bridgwater’s interests and the MoD’s military activities are assessed as moderate and,<br />
therefore, as low as reasonably practicable (ALARP), and the residual risks to military,<br />
fishing and recreational vessels are assessed as low and, therefore, acceptable (subject<br />
to negotiation).<br />
8 OVERVIEW OF PREDICTED IMPACTS ON THE NATURAL AND PHYSICAL<br />
ENVIRONMENT<br />
8.1 Coastal Hydrodynamics and Geomorphology<br />
Existing Environment<br />
8.1.1 The wave cut platform at <strong>Hinkley</strong> <strong>Point</strong> comprises the cliff units that extend from the cliff<br />
towards the north. The units are shallow dipping and are aligned approximately parallel<br />
with the cliff. Shingle / boulders collect in the troughs behind the limestone scarp<br />
surfaces. The boulders are predominantly limestone, originating from the erosion of the<br />
limestone within the vicinity of their deposition on the foreshore. Where the shale is<br />
thicker, the ridges are larger and are often characterised by a veneer of mud and<br />
seaweed. Nearing low tide the limestone becomes increasingly heavily weathered and<br />
individual units are more difficult to trace.<br />
8.1.2 Erosion of the cliff line is influenced by storm events, and therefore the rate of recession<br />
may not be consistent from year to year. In addition to wave undercutting, it is likely that<br />
the cliffs also fail due to excess groundwater pressures behind the face of the cliff. The<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 44 November 2010
cliff at the location of the proposed jetty development contains evidence to indicate that<br />
the inter-bedded limestones and shales of the Blue Lias cliff top have retreated at around<br />
0.13m/yr since 1888, and mean high water mark by around 0.04m/yr.<br />
8.1.3 Sediment transport within the inter-tidal area comprises mud moving as suspended<br />
sediment, sand moving in suspension and as bed load, and gravel and coarser particles<br />
moving on the upper part of the rock platform as bedload. The most obvious evidence of<br />
coastal sediment transport at <strong>Hinkley</strong> <strong>Point</strong> (coarse grained sediment) is shown by the<br />
ridge of shingle and coarser particles at the crest of the beach immediately west of the<br />
existing seawall protecting the current <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex. The<br />
seawall projects out approximately 10 to 20m from the cliff line further west and it is likely<br />
that, due to the longshore drift of this coarse beach sediment, the accumulation of a<br />
wider shingle beach here compared to elsewhere has occurred. The existing seawall at<br />
<strong>Hinkley</strong> <strong>Point</strong> is not considered to be acting as a barrier to hinder shingle transport<br />
around <strong>Hinkley</strong> <strong>Point</strong>.<br />
8.1.4 Further offshore in Bridgwater Bay, there is a large variation in the type and distribution of<br />
seabed sediment along the coastline in front of <strong>Hinkley</strong> <strong>Point</strong>. Sediments generally range<br />
from finer sediment in the east (around Bridgwater Bay) to coarser material in the west.<br />
The seabed sediments immediately offshore of <strong>Hinkley</strong> <strong>Point</strong> are described as a thin<br />
muddy veneer overlaying the bedrock.<br />
8.1.5 The suspended sediment concentrations in the Severn Estuary result from the strong<br />
tidal currents and are generally exceptionally high, creating a turbid environment. A field<br />
campaign by Ravensrodd Consultants found suspended sediment concentrations within<br />
the Bristol Channel within the range of less than 100mg/l to approaching 200,000mg/l<br />
(fluid mud). This range of suspended sediment concentrations was also reported around<br />
<strong>Hinkley</strong> <strong>Point</strong> following four monitoring campaigns over the winter of 2008/2009. This<br />
monitoring recorded a maximum suspended sediment concentration of 1,795mg/l, a<br />
mean concentration of 264mg/l, and a minimum concentration of 33mg/l. Although some<br />
increase with depth was observed, the water column was well mixed. Both the values<br />
and distribution of suspended sediment concentrations show differences between spring<br />
and neap tides.<br />
8.1.6 Monitoring found tidal currents of <strong>Hinkley</strong> <strong>Point</strong> to be generally orientated along the main<br />
axis of the estuary (i.e. shore-parallel), with currents reaching a maximum velocity of<br />
1.7m/s on spring tides and 1.4m/s on neap tides at an offshore monitoring location. The<br />
inshore monitoring site showed peak currents to attain only 1.5m/s on spring tides and<br />
1.0m/s on neap tides. At all locations ebb currents were stronger than flood currents.<br />
Main Predicted Impacts<br />
8.1.7 During the jetty development’s construction, piling could disturb sediment so the chosen<br />
piling technique to be employed (specific methodologies would be confirmed by<br />
contractors) would minimise the degree of sediment disturbance, through the choice of<br />
access method and type of piling.<br />
8.1.8 In addition, the dredged berthing pocket could be subject to sediment deposition.<br />
However, the proposed design of the berthing pocket (i.e. its specific alignment relative to<br />
the tidal flows) has been chosen in order to encourage hydrodynamic conditions that<br />
promote self-scouring of this dredged area and, therefore, to reduce the requirement for<br />
frequent maintenance dredging during the jetty development’s operational phase.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 45 November 2010
8.1.9 The overall design of the jetty structure and other design elements, such as the exact<br />
positioning of the jetty, the orientation of the berthing pocket and the number of piles and<br />
uprights have been chosen to minimise environmental impacts. Nevertheless, during its<br />
operational phase, the presence of the jetty would have an effect on local hydrodynamic<br />
and sediment transport processes. The piles associated with the jetty would cause local<br />
hydraulic changes in the tidal flow around each support which have been assessed to be<br />
of negligible significance and do not require specific mitigation.<br />
8.1.10 Overall, all potential impacts on coastal hydrodynamic and geomorphology receptors<br />
during the jetty development’s construction, operation and dismantling and restoration<br />
phases and, if required, its removal and reinstatement phase have been assessed to be<br />
of minor or negligible significance prior to implementation of mitigation measures. This is<br />
primarily due to the very low or low magnitude of change predicted to occur on<br />
hydrodynamic and sediment transport processes as a result of the jetty development.<br />
Mitigation<br />
8.1.11 The overall design of the jetty’s structure and other design elements (e.g. the exact<br />
positioning of the jetty, the orientation of the berthing pocket and the number of piles and<br />
uprights0 have been chosen to minimise environmental impacts.<br />
8.1.12 Mitigation measures identified may be viewed as best practice, rather than as necessarily<br />
required. Where best practice mitigation measures can be implemented, this would<br />
further reduce the potential impact on hydrodynamic processes, sediment transport<br />
processes and geomorphological receptors.<br />
8.1.13 Where possible, the chosen piling technique to be employed (specific methodologies<br />
would be confirmed by contractors) would minimise the degree of sediment disturbance,<br />
through the choice of access method and type of piling.<br />
Residual Impacts<br />
8.1.14 No significant impacts are predicted after mitigation.<br />
8.2 Marine Ecology<br />
Existing Environment<br />
8.2.1 The application site is fronted by the rocky foreshore of the Severn Estuary. To the east<br />
are large areas of inter-tidal mudflats and saltmarsh in Bridgwater Bay and bordering the<br />
estuary of the River Parrett.<br />
8.2.2 The Severn Estuary is an important nature conservation area and supports a number of<br />
international, national and local designations for wetland habitats, bird populations and<br />
the presence of other habitats and species of conservation interest. The extreme natural<br />
environmental conditions in the estuary strongly influence the species and habitats that<br />
are present in the inter-tidal and sub-tidal zones. While these species and habitats are<br />
characteristic of other UK estuaries, they are less abundant in the Severn Estuary due to<br />
sediment surface instability and extremely high turbidity levels. The high turbidity levels<br />
also limit the densities of phytoplankton and zooplankton (i.e. micro-organisms in the<br />
water column).<br />
8.2.3 The foreshore in front of, and either side of, <strong>Hinkley</strong> <strong>Point</strong> B is dominated by a shelving<br />
rocky shore which supports relatively few marine species. The turf areas formed by the<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 46 November 2010
ed alga Corallina is the main habitat of importance. The honeycomb worm Sabellaria is<br />
also present. Aggregations of Sabellaria, forming reefs, are of importance as these<br />
provide habitat for many other organisms. In its reef form, Sabellaria is protected under<br />
the EC Habitats Directive, and some areas of reef exist approximately 200m and 300m<br />
offshore.<br />
8.2.4 The sub-tidal habitats, which are either always submerged or only briefly exposed at<br />
extremely low tides, consist of extensive areas of muddy sediments, and are dominated<br />
by a few species including bivalve molluscs, polychaete worms and crustaceans. The<br />
brown shrimp is abundant and provides an important food source for a number of fish<br />
species and birds.<br />
8.2.5 A variety of fish species live permanently within or migrate through the estuary, including<br />
some that are protected under European Directives and/or national legislation (e.g.<br />
Atlantic salmon, twaite shad, allis shad, river lamprey, sea lamprey, sea trout and eel).<br />
Bridgwater Bay is considered to be an important nursery area for juvenile fish and a<br />
number of fish species utilise the inter-tidal areas.<br />
8.2.6 There are no resident populations of marine mammals within the estuary although a<br />
number of species may feed there at different times of the year. The harbour porpoise is<br />
the most commonly recorded marine mammal species.<br />
Main Predicted Impacts<br />
8.2.7 The following potential impacts on marine ecological receptors could arise during the jetty<br />
development’s construction phase:<br />
• temporary and permanent loss of sensitive marine receptors;<br />
• physical disturbance of marine receptors due to piling activities at each jetty upright<br />
and to provide access for vehicle and plant, the delivery of materials and the<br />
workforce;<br />
• changes in cross-shore and longshore, inter-tidal drainage patterns and associated<br />
effects on Corallina;<br />
• physical disturbance due to dredging around the seaward end of the jetty (including<br />
impacts associated with the re-suspension within the water column of bottom<br />
sediments such as smothering etc.);<br />
• other water quality impacts due to run-off during construction and potentially<br />
associated with other accidents and incidents (particularly spillage and leaks of fuels<br />
and oils and possibly other chemicals, including cement and concrete if it is used in<br />
the jetty construction);<br />
• noise and vibration; and<br />
• artificial light disturbance during 24 hour construction works.<br />
8.2.8 One potentially significant adverse impact has been indentified in relation to physical<br />
disturbance caused during the jetty development’s construction phase. Piling, dredging<br />
and the use of construction plant and materials could disturb the physical environment<br />
(and its species and habitats) and drainage characteristics of the inter-tidal area in and<br />
around the site of these works. While most species of invertebrates, fish and marine<br />
mammals would not be significantly affected, the red alga species Corallina could be<br />
significantly affected by physical disturbance (i.e. interruptions) to the inter-tidal crossshore<br />
drainage channels where it is present (see Figure 16); although the jetty’s location<br />
has been chosen such that it avoids key areas of Corallina habitat (i.e. the turf areas) that<br />
occur more regularly to the east. An impact of moderate significance is predicted as a<br />
result of the medium sensitivity of Corallina and the medium magnitude of the impact.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 47 November 2010
Figure 16 Distribution of Corallina in relation to the <strong>Jetty</strong> Development<br />
8.2.9 During the jetty development’s operational phase, impacts on marine ecology could arise<br />
as a result of maintenance dredging (if required), noise and vibration, artificial light and<br />
water quality effects. No significant impacts have been identified on marine ecological<br />
receptors during this phase.<br />
8.2.10 During the jetty development’s dismantling / restoration phase, or removal / reinstatement<br />
phase (if required), impacts on marine ecology could arise from loss of and disturbance<br />
to inter-tidal and sub-tidal habitat (e.g. due to removal of each jetty upright, access for<br />
construction vehicles and plant) and water quality effects. No significant impacts have<br />
been identified on marine ecological receptors during this phase.<br />
Mitigation<br />
8.2.11 Specific mitigation measures are proposed to protect Corallina habitat and the species<br />
associated with it from physical disturbance during the construction and dismantling /<br />
restoration phases, or the removal / reinstatement phase (if required). These include<br />
establishment of a narrow working corridor across the inter-tidal area to avoid areas of<br />
Corallina where possible, and measures to ensure that the drainage environment of<br />
Corallina is not compromised by piling activities.<br />
8.2.12 All other impacts on marine ecological receptors have been assessed as being of minor<br />
or negligible significance, and hence no further specific mitigation is required. However,<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 48 November 2010
in recognition of the importance and protected status of the nearby marine environment,<br />
a number of good practice and precautionary measures are proposed to provide<br />
additional safeguards. These include the designation of “no-go” areas and associated<br />
buffer zones around all identified sensitive locations; buffer zones around construction<br />
and access sites in foreshore areas; provision of training for the construction workforce;<br />
specific accident and incident response and cleanup procedures; and implementation of<br />
a monitoring programme.<br />
Residual Impacts<br />
8.2.13 No significant impacts are predicted after mitigation.<br />
8.3 Terrestrial Ecology and Ornithology<br />
Existing Environment<br />
8.3.1 The application site has been subject to extensive vegetation survey work, together with<br />
surveys of a wide range of animal species including bats, otter, badger, reptiles,<br />
amphibians, birds and invertebrates. In addition, extensive bird survey work has been<br />
carried out on the coastal area that forms part of the Severn Estuary Special Protection<br />
Area (SPA), which is protected at the European level because of the importance of its<br />
bird populations. This coastal area is also part of the Severn Estuary Special Area of<br />
Conservation (SAC) and Ramsar site, as well as being part of several Sites of Special<br />
Scientific Interest (SSSIs) (see Figure 17).<br />
8.3.2 The land in and around the application site comprises open, gently rolling mixed lowland<br />
farmland with hedgerows, small scrubby woodlands and occasional standard trees.<br />
Although much of the area is intensively managed, small areas of species-rich limestone<br />
grassland occur along the cliff edge and the immediate vicinity of the <strong>Hinkley</strong> <strong>Point</strong> Power<br />
Station Complex. The northern site boundary lies adjacent to the Bristol Channel from<br />
which it is separated by a low cliff. The application site also includes seven hedgerows,<br />
five of which are species-rich, support at least five woody species, and are ecologically<br />
‘important’ under the Hedgerow Regulations, 1997.<br />
8.3.3 Fifteen species of wetland birds were recorded feeding or roosting in the intertidal area in<br />
the vicinity of the application site, with five of these also being recorded feeding or<br />
roosting in the fields within the site. A total of 18 species of breeding bird have been<br />
recorded on the site.<br />
8.3.4 A minimum of seven bat species have been recorded using the application site and one<br />
small roost is present in a derelict barn. Badgers are present within the application site<br />
and there is potential for otter to make very occasional use of the <strong>Hinkley</strong> <strong>Point</strong> C<br />
Drainage Ditch.<br />
Main Predicted Impacts<br />
8.3.5 Drawing upon the results of the surveys and other data gathering, and informed by<br />
consultation with Natural England, the RSPB, Somerset County Council, Somerset<br />
Wildlife Trust and West Somerset Council, the jetty development’s design has been<br />
progressively refined to minimise the adverse impacts on wildlife and, where possible, to<br />
deliver benefits. The changes to the scheme include:<br />
• avoidance of mature woodland and use of existing field accesses to avoid impacts on<br />
hedgerows;<br />
• changes to <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch being restricted to one culvert extension;<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 49 November 2010
• production of an updated <strong>Hinkley</strong> Integrated Land Management Plan (ILMP) detailing<br />
the protection and management of retained habitat features;<br />
• vegetation clearance would, where possible, take place in the period January - March<br />
(inclusive), which is outside of the core breeding season for all of the bird species that<br />
have been recorded breeding within the site - where this is not possible, clearance<br />
would only be undertaken once surveys have shown that either no active nests are<br />
present or that any breeding birds have fledged from the areas to be cleared;<br />
• implementation of best practice measures to minimise emissions and dust deposition;<br />
and<br />
• a simple jetty design that is likely to reduce the potential for bird collisions.<br />
8.3.6 Other measures are put forward as proposed mitigation. These are described and the<br />
residual impacts are assessed below.<br />
8.3.7 During the construction phase, there is the potential for birds using the inter-tidal areas<br />
close to the jetty and foreshore access location to be adversely affected by noise<br />
generated by the jetty development, changes in inter-tidal plant / animal communities<br />
caused by discharges from the site, visual disturbance caused by the workforce that<br />
undertakes the jetty development and their machinery, and lighting. However, these<br />
effects are predicted to have a very low magnitude impact on birds using inter-tidal areas<br />
and not be significant, despite the high value populations associated with the Severn<br />
Estuary SPA and Ramsar Site and the Bridgwater Bay SSSI.<br />
8.3.8 Terrestrial vegetation removal during the jetty development’s construction phase would<br />
mean that the cleared areas would no longer be likely to support any of the bird species<br />
that currently breed on the site, including skylark (eight pairs), linnet (three pairs),<br />
dunnock (five pairs) and song thrush (one pair). However, the loss of habitat for breeding<br />
birds would not have an adverse impact on the conservation status of the species<br />
concerned. On this basis, the loss of habitat and breeding birds would be a minor<br />
adverse impact.<br />
8.3.9 The jetty development’s construction phase would result in the loss of one ephemeral<br />
common pipistrelle roost located in a disused, derelict barn. Given the low status of the<br />
roost and the common species recorded using the barn, its loss is unlikely to affect the<br />
conservation status of the local bat population.<br />
8.3.10 The stripping of topsoil and the removal of hedgerows across the application site would<br />
result in the loss or reduction in size of the territories of up to three badger social groups<br />
and the destruction of one sett. In the absence of mitigation, this would result in the<br />
contravention of the law pertaining to badgers, which would cause a major adverse<br />
impact.<br />
8.3.11 No significant impacts are predicted to arise in relation to otters, reptiles and<br />
invertebrates using habitats within the study area during the jetty development.<br />
8.3.12 Losses of grassland, pond and hedgerow habitat, loss of 10% of the <strong>Hinkley</strong> County<br />
Wildlife Site and disturbance to the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch and a small area of<br />
limestone grassland are also predicted to occur. However, none of these effects are<br />
predicted to be significant.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 50 November 2010
Figure 17 Designated Nature Conservation Areas in relation to the <strong>Jetty</strong> Development’s Application Site<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works <strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 51 November 2010
8.3.13 Fewer potential impacts are predicted to arise during the jetty development’s operation<br />
and dismantling and restoration phases or, if required, its removal and reinstatement<br />
phase, namely:<br />
• adverse impacts on intertidal birds resulting from disturbance caused by ships<br />
docking to unload cargo, and from human activity, light and noise along and on route<br />
to the jetty;<br />
• disturbance to bats as a result of site lighting; and<br />
• restoration (or, if required, reinstatement) of the site, resulting in the creation of<br />
habitats which would subsequently be available for colonisation by wildlife.<br />
8.3.14 Similarly, none of these potential impacts are predicted to be significant.<br />
Mitigation<br />
8.3.15 Construction of the jetty development would be undertaken and, as appropriate,<br />
scheduled in such a way as to avoid or reduce impacts on birds using the inter-tidal<br />
areas (e.g. piling on the foreshore would be scheduled to take place over the summer<br />
period from July to September as far as possible). In addition, the construction works on<br />
the inter-tidal area would be constantly rather than intermittently lit each night through the<br />
use of directional lighting so that light spill is limited and birds can habituate to the light.<br />
8.3.16 To ensure compliance with the legal protection afforded to bats, destruction of the barn<br />
with confirmed bat interest would be undertaken in accordance with a method statement<br />
that is agreed with Natural England, in the context of a derogation licence. In addition, a<br />
strategy would be implemented to ensure that lighting is designed to have minimal<br />
impacts on bats, whilst being compliant with safety and security criteria.<br />
Residual Impacts<br />
8.3.17 No significant impacts are predicted after mitigation.<br />
8.4 Water Quality<br />
Existing Environment<br />
8.4.1 A review of literature has been used to derive an overview of the marine surface water<br />
quality conditions. In addition, the results of surface water sampling campaigns carried<br />
out in 2009 have been used to inform the baseline conditions. The two key receptors<br />
identified for potential impacts arising from the jetty development are the freshwater<br />
quality status of the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch and the marine water quality status of<br />
the Severn Estuary.<br />
8.4.2 Onshore, the jetty development’s application site includes a series of interconnecting<br />
agricultural drainage ditches that drain the land and discharge to the <strong>Hinkley</strong> <strong>Point</strong><br />
foreshore. The primary watercourse of relevance to the jetty development is known as<br />
the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch. This watercourse is supplied with water from surface<br />
drainage running off from surrounding agricultural land. Its water quality status is<br />
characterised by highly variable water quality conditions, including elevated<br />
concentrations of suspended solids. In addition, it is known to dry out during prolonged<br />
periods without rainfall.<br />
8.4.3 Offshore, the water quality status of the inter-tidal area at <strong>Hinkley</strong> <strong>Point</strong> is variable<br />
according to tidal conditions. Under high tide conditions the inter-tidal area is inundated<br />
with water that is characterised by high concentrations of suspended solids. Given the<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 52 November 2010
high tidal range, there is a large dilution capacity available to buffer other suspended<br />
solids and other potential water quality impacts during high tide periods and the overall<br />
water quality status sensitivity is low. The sensitivity of the inter-tidal water quality status<br />
is increased during low tide periods when water is retained in pools and foreshore<br />
channels that support marine ecology. During these periods there is reduced dilution<br />
capacity to potential impacts from foreshore discharges and an increased sensitivity.<br />
8.4.4 The sub-tidal areas off <strong>Hinkley</strong> <strong>Point</strong> are characterised by high suspended solids<br />
concentrations due to sediment mobilisation under high tidal flows. The tidal disturbance<br />
of the sediments would also lead to mobilisation of any associated sediment<br />
contaminants into the well-mixed water column. It has been shown that disturbance of<br />
the superficial sediments in the area around <strong>Hinkley</strong> <strong>Point</strong> has a low influence on<br />
chemical water quality status.<br />
8.4.5 In terms of sediment quality, survey data indicate the presence of elevated metal and<br />
hydrocarbon concentrations, but very few of the metal concentrations recorded would be<br />
considered to be significantly contaminated. It is suggested that elevated metal<br />
contamination in surface sediment may be representative of wider baseline<br />
concentrations and the result of contaminant redistribution from elsewhere in the Bristol<br />
Channel. Concentrations of other organic substances were found to be generally present<br />
at low concentrations.<br />
Main Predicted Impacts<br />
8.4.6 The impact assessment found that there is the potential for water quality status to be<br />
adversely affected as a result of a range of activities associated with the jetty<br />
development. The impacts that have been identified during the construction of the jetty<br />
may be broadly divided into:<br />
• disturbance of marine sediment and mobilisation of associated contaminants into the<br />
Severn Estuary (e.g. due to dredging of the berthing pocket or scouring around the<br />
jetty’s piles);<br />
• discharge of water containing sediment, hydrocarbons and/or concrete leachates into<br />
the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch and the Severn Estuary (e.g. surface water run-off<br />
from the onshore storage area);<br />
• discharge of freshwater onto the foreshore where Corallina is present in drainage<br />
channels; and<br />
• accidents and incidents.<br />
8.4.7 During construction of the jetty no significant impacts are predicted to arise in relation to<br />
water quality due to the measures that would be put in place to control the quality and<br />
volume of discharges into the surface drainage (i.e. the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch)<br />
and onto the foreshore and the waters of the Severn Estuary. In addition, the sensitivity<br />
of the local marine water quality conditions to increases in suspended solids is low given<br />
the existing high background concentrations.<br />
8.4.8 The impacts associated with the operation of the jetty are likely to arise from<br />
maintenance dredging of the berthing pocket, scouring of sediment from the seabed<br />
around the jetty’s infrastructure (e.g. piles and berthing pocket), and freshwater<br />
discharges into the marine environment from the onshore storage area. However, the<br />
impacts assessed would be of negligible or minor significance.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 53 November 2010
8.4.9 Impacts associated with dismantling and restoration phase and, if required, the removal /<br />
reinstatement phase would be in similar to those described for the construction phase,<br />
with no significant impact predicted.<br />
Mitigation<br />
8.4.10 Due in part to the design measures associated with the jetty development (e.g. oil water<br />
separator and a water management zone for the aggregates storage area), all of the<br />
identified impacts on water quality were found to be not significant (i.e. minor and<br />
negligible impacts) prior to implementation of mitigation measures. Nevertheless,<br />
mitigation measures will be adopted on the basis of a precautionary approach to<br />
protection of the environment. Mitigation measures include:<br />
• the application and accordance with discharge consent conditions for discharges to<br />
the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch and the Severn Estuary;<br />
• the adoption of the best practice guidance for works in and adjacent to<br />
watercourses, as provided in the Environment Agency’s Pollution Prevention<br />
Guidelines (PPGs);<br />
• the implementation of a surface drainage strategy for the onshore areas including<br />
measures to minimising generation of sediment-laden surface drainage water and<br />
potential impacts on the <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch (e.g. settlement ponds to<br />
reduce suspended solids and oil interceptors to recover hydrocarbons); and<br />
• the implementation of a wide range of environmental protection measures and<br />
monitoring detailed in the Water and Sediment Management Plan which forms part<br />
of the EMMP.<br />
Residual Impacts<br />
8.4.11 No significant impacts are predicted after mitigation.<br />
8.5 Hydrology and Drainage<br />
Existing Environment<br />
8.5.1 There are a number of controlled waters in the <strong>Hinkley</strong> <strong>Point</strong> area; however, the only<br />
fluvial watercourse of relevance to the jetty development is the <strong>Hinkley</strong> <strong>Point</strong> C Drainage<br />
Ditch. The ditch is designated as an Ordinary Watercourse (i.e. it is not a Main River).<br />
The <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch’s contributing catchment (78.3ha) is undulating with<br />
generally shallow slopes. It runs from west to east with its source at 14.5m AOD until its<br />
alignment is rotated through 90° such that it flows from south to north where it discharges<br />
onto the foreshore. Flow in the ditch is intermittent / ephemeral (i.e. it does not flow all<br />
year round).<br />
8.5.2 There is no fluvial flooding indicated on the Environment Agency’s Flood Map; however,<br />
flooding from catchments of less than 3km 2 is not shown so it is possible that some fluvial<br />
flooding could occur along the ditch’s margins.<br />
8.5.3 A Flood Risk Assessment has been carried out in accordance with PPS25. It can be<br />
found in Appendix 13-1 in Volume 4. On the basis of the information presented in this<br />
FRA, and subject to its recommendations being implemented, it is concluded that the<br />
jetty development at <strong>Hinkley</strong> <strong>Point</strong> is appropriate on the grounds that all flooding risks<br />
and residual risks have been given due consideration and are found to be acceptable.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 54 November 2010
8.5.4 The <strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch discharges to the foreshore and drains into the<br />
Severn Estuary except during very high tides when it will discharge directly into the<br />
Severn Estuary.<br />
Main Predicted Impacts<br />
8.5.5 The key impact would occur as a result of elevated surface water run-off from the jetty<br />
development’s onshore components, and particularly from the aggregates storage area<br />
and service road. It is proposed that this water would be discharged to the <strong>Hinkley</strong> <strong>Point</strong><br />
C Drainage Ditch and eventually to the foreshore and the Severn Estuary. Common<br />
types of potential hydrological and drainage impacts extend across a range of<br />
construction activities and have been grouped accordingly and include:<br />
• elevated surface water run-off;<br />
• elevated sediment delivery and deposition in watercourses; and<br />
• flooding of land off-site of the application site resulting from various sources, such as<br />
flooding as a result of elevated surface water run-off and flooding as a result of<br />
elevated sediment deposition in channels resulting in a reduced channel capacity.<br />
8.5.6 Onshore, the jetty development would have a surface water drainage system in place to<br />
control and manage surface water and sediment discharges associated with the<br />
aggregates storage area. This system would be designed to basic compliance criteria<br />
and, therefore, is not considered to be mitigation measure.<br />
8.5.7 No significant potential impacts (i.e. moderate or major impacts) were identified in<br />
relation to hydrology and drainage for the jetty development’s construction, operation and<br />
dismantling and restoration phases and, if required, its removal and reinstatement.<br />
Mitigation<br />
8.5.8 The impact assessment is based on the assumption of regulatory compliance and thus<br />
measures would be implemented to ensure regulatory compliance. These measures are<br />
presented within the Water and Sediment Management Plan, which forms part of the<br />
EMMP, and would be applied during the jetty development’s dismantling and restoration<br />
phase or, if required, its removal and reinstatement phase.<br />
8.5.9 Although the onshore aggregates storage area’s design includes for an operational<br />
drainage system, monitoring and maintenance and controls would be put in place for<br />
unusual conditions (contingency discharges and provision for emergency run-off).<br />
Residual Impacts<br />
8.5.10 No significant impacts are predicted after mitigation.<br />
8.6 Groundwater<br />
Existing Environment<br />
8.6.1 The groundwater regime at the jetty development’s application site is described as a<br />
Secondary A (Minor) aquifer (a rock formation that can bear or transmit water). Such<br />
aquifers can be “fractured or potentially fractured rocks, which do not have a high primary<br />
permeability, or other formations of variable permeability including unconsolidated<br />
deposits. Although these aquifers will seldom produce large quantities for abstraction,<br />
they are important both for local supplies and in supplying base flow to rivers”. The lower<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 55 November 2010
oundary on the active groundwater regime in the area may be the base of the Lilstock<br />
Formation of the Penarth Group, possibly less than 4m below the base of the Lower Lias.<br />
8.6.2 The groundwater is considered to be compartmentalised between the Green Lane area<br />
and the shoreline by an upfaulted inlier of low permeability Mercia Mudstones.<br />
Groundwater flow is essentially south-south-west to north-north-east discharging at some<br />
point at the foreshore or underwater up to several hundred metres offshore.<br />
8.6.3 Surveys show that the water tables rise in response to sustained rainfall during the winter<br />
months and then fall away again as recharge declines. Rainfall between spring and early<br />
autumn does not show a groundwater response, probably because available recharge is<br />
taken up by the growing soil moisture deficit and does not reach the unsaturated zone or<br />
the water table.<br />
8.6.4 It is apparent that groundwater in the application site is controlled by local rainwater<br />
recharge and topography as the groundwater contours reflect the topography. The<br />
<strong>Hinkley</strong> <strong>Point</strong> C Drainage Ditch, which flows west to east then turns north to discharge to<br />
the shoreline, receives groundwater baseflow and exerts significant control on<br />
groundwater levels.<br />
8.6.5 At high water table levels, groundwater ranges from around 20m AOD to 11m AOD from<br />
south to north across the western part of the application site. At low water table levels at<br />
the end of summer, groundwater ranges from around 14m AOD to 8m AOD in the same<br />
boreholes.<br />
8.6.6 There are no potable water abstractions and no associated Source Protection Zones<br />
within the application site. There are 17 licensed groundwater abstractions within several<br />
kilometres of the application site. All these wells and boreholes are for general farming<br />
and domestic purposes. The nearest abstraction is more than 0.5km from the western<br />
part of the application site. All the other abstractions are more than 2km from the<br />
western part of the application site.<br />
Main Predicted Impacts<br />
8.6.7 The principal activities associated with the jetty development that could affect<br />
groundwater are associated with the onshore works and particularly construction of the<br />
aggregates storage area, the soil storage areas and the rock extraction area. The<br />
anticipated impacts on groundwater receptors such as groundwater levels and resources<br />
during all phases of the jetty development have been assessed to be of negligible or<br />
minor significance.<br />
Mitigation<br />
8.6.8 Mitigation would be provided through implementation of the EMMP, which would ensure<br />
that best practice construction methods are adopted to minimise spillages and<br />
contamination. Monitoring programmes would be implemented as part of the EMMP to<br />
verify the behaviour and any movement of groundwater, in order to confirm the<br />
anticipated non-impacts.<br />
Residual Impacts<br />
8.6.9 No significant impacts are predicted after mitigation.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 56 November 2010
8.7 Soils and Land Use<br />
Existing Environment<br />
8.7.1 The topography of the application site is typical of that in the wider locality comprising<br />
mostly open, gently rolling, mixed lowland farmland with a series of east-west ridges of<br />
land. Improved grassland areas within the site are grazed annually as part of the<br />
management of the <strong>Hinkley</strong> <strong>Point</strong> County Wildlife Site, with other areas maintained in<br />
Good Agricultural and Environmental Condition (GAEC).<br />
8.7.2 The main soil type present (Evesham Soil Series) comprises soils which are slow<br />
draining and vulnerable to structural damage if worked when waterlogged. The<br />
application site and much of the surrounding area is covered by agri-environment<br />
schemes (Countryside or Environmental Stewardship Agreements).<br />
8.7.3 The application site is classified as Grade 3b (moderate quality) agricultural land, with the<br />
rock extraction area classified as non-agricultural land due to previous development<br />
associated with the <strong>Hinkley</strong> <strong>Point</strong> Power Station Complex. The surrounding land is also<br />
predominantly Grade 3b with some Grade 3a (classified as best and most versatile land<br />
(BMVL) and some Grade 4 (poor quality agricultural land).<br />
Main Predicted Impacts<br />
8.7.4 Only the onshore elements of the jetty development are considered to have the potential<br />
to impact on soil and land use and, therefore, no assessment of the jetty’s offshore<br />
components has been made.<br />
8.7.5 Soil and land use impacts arising from the jetty development’s construction phase would<br />
primarily be associated with topsoil stripping, storage and handling, including the<br />
potential for damage to soil structure and profiles, loss of agricultural potential, loss of<br />
land for livestock and loss of land currently managed under agri-environment schemes.<br />
Since the affected soils are mainly heavy clays with relatively poor structure, soil<br />
compaction, and loss of soil structure could occur as soils are excavated, handled and<br />
stored for later re-use.<br />
8.7.6 Other jetty development activities, including construction of site access, site compound,<br />
service road to the foreshore and rock extraction would take place after topsoil stripping<br />
has occurred and, therefore, there would be no adverse impacts on soils and land use<br />
related to these activities.<br />
8.7.7 The anticipated impacts on soil quality and agricultural land use during all phases of the<br />
jetty development have been assessed to be of minor adverse significance.<br />
Mitigation<br />
8.7.8 Mitigation would be provided through implementation of the EMMP, which would ensure<br />
that best practice construction methods are adopted. As part of this, a Soil Management<br />
Plan (SMP) would be set in place to address all phases of the jetty development,<br />
containing measures for soil protection ahead of stripping, segregation and storage to<br />
protect soil quality and prevent loss of soil structure.<br />
8.7.9 These measures would also ensure appropriate biosecurity (disease and pest control),<br />
weed control, management of site run-off, erosion and dust generation to protect both on<br />
site soils and adjacent land holdings. As part of the landscape restoration and, if<br />
required, reinstatement, stockpiled soils and subsoils would be re-used to create suitable<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 57 November 2010
conditions for agricultural land and habitat creation. Appropriate reinstatement techniques<br />
would be set out in the SMP to ensure that well-managed and viable soil materials are<br />
available.<br />
Residual Impacts<br />
8.7.10 All potential impacts on soils and land use have been rated as minor before any<br />
mitigation has been applied. Nevertheless, mitigation measures are proposed to protect<br />
soil quality and prevent loss of soil structure.<br />
8.8 Geology and Contaminated Land<br />
Existing Environment<br />
8.8.1 The majority of the application site is not overlain by significant drift deposits. Intrusive<br />
investigations, have revealed that where drift deposits are present within the application<br />
site they are classified typically as slightly gravelly locally sandy silty clay to a sandy silt /<br />
clay and slightly sandy slightly gravely clay respectively. The solid geology in the locality<br />
of the application site predominantly comprises the Lower Lias of the Lias Group (Lower<br />
Jurassic) and the Triassic Penarth and Mercia Mudstone Groups.<br />
8.8.2 The Blue Anchor to Lilstock SSSI (see yellow outlined area on Figure 17) is designated<br />
for its geological and geomorphological interest. The exposed stratigraphic units along<br />
the cliff face are considered to be amongst the best examples of the Blue Lias outcrop in<br />
Europe and the SSSI’s geomorphological designation is for the exposed limestone rock<br />
pavement on the foreshore. The application site includes a small portion of the<br />
designated cliff and foreshore.<br />
8.8.3 In terms of contaminated land, while the application site has been and remains<br />
predominantly agricultural, some of its eastern part has been affected by development.<br />
Key features and potential pollution sources include the presence of historically infilled<br />
ponds, former sewage treatment works, a double mounded feature in the centre of the<br />
site containing surplus spoil from the construction of the <strong>Hinkley</strong> <strong>Point</strong> Power Station<br />
Complex, a former licensed waste management facility and the former fabrication /<br />
construction and accommodation areas with associated electrical substations and<br />
possible fuel oil storage tanks and boiler house.<br />
8.8.4 Contaminant concentrations found by intrusive investigations of shallow and deeper soils<br />
within the application site are considered to be consistent with natural background<br />
concentrations in the locality and typical UK background soil concentrations. The<br />
majority of the soils within the eastern part of the application site are considered to be<br />
suitable for the proposed end use given the incorporation of standard design mitigation<br />
measures where necessary (such as sulphate resistant concrete) and appropriate<br />
materials management and placement (e.g. not within top metre in some cases) during<br />
earthworks. The exceptions to this are the presence of asbestos containing materials<br />
(ACM) which have been identified at several locations on the eastern part of the<br />
application site. These materials have in almost all cases been identified as discrete<br />
pieces and fragments of ACM with very little evidence of any diffuse or free fibres<br />
identified in the site soils or associated with the ACM. The current risk from these ACM<br />
is considered to be low. In addition, all known areas of asbestos contamination would be<br />
removed during the enabling works prior to the commencement of the jetty development.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 58 November 2010
8.8.5 Gas monitoring data indicate that there are no significant sources of ground gas on the<br />
application site and, therefore, there is no significant risk posed to human health or<br />
buildings by ground gas given its current land use.<br />
Main Predicted Impacts<br />
8.8.6 The anticipated impacts on geological receptors have been assessed to be of negligible<br />
to minor adverse significance for all phases of the jetty development. A key impact on<br />
geology was considered in relation to the jetty development’s potential to affect the<br />
features (i.e. exposures) of the Blue Anchor to Lilstock SSSI. Only a small portion of the<br />
jetty would affect the SSSI and a geological mapping exercise has identified that the<br />
features affected by the jetty development can be observed and accessed elsewhere<br />
within the SSSI, such that there is no loss of the unique geology.<br />
8.8.7 The anticipated Impacts on contaminated land receptors (including soil, water, vegetation<br />
and human health) have been assessed to be negligible to minor adverse for all phases<br />
of the jetty development.<br />
Mitigation<br />
8.8.8 Despite no significant adverse impacts, the EMMP will include measures relating to the<br />
control of the release of potentially contaminated materials into the environment from<br />
their original source location. Certain standard control measures which are typically<br />
applied on construction sites are also effective at controlling the dispersion and creation<br />
of contamination. Typical measures will include standard measures to prevent<br />
contamination occurring from construction operations (e.g. appropriate use and storage<br />
of fuel oils and other chemicals and measures to control dust and surface run-off, etc.).<br />
8.8.9 No significant impacts to geology are predicted, however the foreshore is fossiliferous<br />
and, therefore, a pre-construction survey to identify any palaeontological finds of<br />
scientific importance would be undertaken on the area of the foreshore to be impacted by<br />
the jetty development (access road and piling).<br />
Residual Impacts<br />
8.8.10 No significant impacts are predicted after mitigation.<br />
9 CUMULATIVE EFFECTS<br />
9.1 Introduction<br />
9.1.1 The potential for cumulative impacts to occur as a result of the implementation of the jetty<br />
development with other projects is largely determined by the spatial and temporal<br />
characteristics of the works themselves and the nature of the environmental receptors<br />
that may be affected by the works. Relevant projects in this instance include the site<br />
preparation works, the proposed <strong>Hinkley</strong> <strong>Point</strong> C nuclear power station and several other<br />
plans and projects that have been scoped into the assessment process.<br />
9.2 Cumulative Effects with the Site Preparation Works<br />
9.2.1 The inclusion of the ground works for the onshore elements of the jetty development<br />
within the site preparation works effectively means that potential cumulative effects on<br />
onshore / terrestrial environmental receptors (e.g. soils and land use, terrestrial ecology,<br />
geology and contaminated land) would be, in most instances, no greater than for the site<br />
preparation works alone. With regard to the potential impact of noise generated during<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 59 November 2010
construction and changes in air quality, given the separation distance of the jetty<br />
construction works from the nearest residential properties, the cumulative effect would be<br />
no greater than that assessed solely for the site preparation works.<br />
9.2.2 For landscape and heritage issues, the addition of the land-based components of the<br />
jetty storage infrastructure and the jetty structure itself to the site preparation works has<br />
the potential to cause a cumulative effect. These structures are predicted to marginally<br />
increase the overall magnitude of change with respect to effects on local landscape<br />
character and visual sensitivity from some viewpoints. With respect to the setting of Wick<br />
Barrow, however, the combined impact magnitude is predicted to be no greater than that<br />
assessed for the site preparation works alone.<br />
9.2.3 From a recreation and amenity perspective, the coastal footpath would be obstructed and<br />
alternative routes put in place around the combined works. There would be a temporary<br />
increase in the visual impact to users of the coastal section to the west of the site as a<br />
result of the combined effect. However, views from the footpath would be limited to those<br />
that could be gained away from the immediate vicinity of the development site.<br />
9.3 Cumulative Effects with the <strong>Hinkley</strong> <strong>Point</strong> C Project<br />
During Construction of the <strong>Jetty</strong><br />
9.3.1 During construction there is only a very limited temporal overlap of approximately nine<br />
months between the jetty development’s construction phase and the <strong>Hinkley</strong> <strong>Point</strong> C<br />
construction works. This small overlap between the works effectively limits the potential<br />
for many cumulative impacts to occur. The negligible traffic volume and relevant air<br />
quality and noise effects associated with the jetty development would not be expected to<br />
represent a discernable difference from those associated with <strong>Hinkley</strong> <strong>Point</strong> C alone.<br />
9.3.2 For some receptors, such as landscape, heritage and amenity, there is the potential for<br />
the continuation or further modification of an impact due to the commencement of the<br />
<strong>Hinkley</strong> <strong>Point</strong> C construction works. However, given the short temporal overlap, the<br />
scope for any significant change is extremely limited and in reality the additional effect<br />
during this overlap period would be unlikely to lead to any greater impacts than those that<br />
could be attributed to the jetty development alone.<br />
9.3.3 For receptors within the footprint of the onshore components of the jetty development,<br />
such as terrestrial ecological interest, soils and landuse, buried archaeology, etc., there<br />
would be no cumulative impact with the commencement of the <strong>Hinkley</strong> <strong>Point</strong> C<br />
construction works. This is because these interests would be lost as a result of the jetty<br />
development’s construction and the site preparation works.<br />
During Operation of the <strong>Jetty</strong><br />
9.3.4 The overlap in time between the operational phase of the jetty and continued<br />
construction of <strong>Hinkley</strong> <strong>Point</strong> C would last approximately 7 years. The potential for<br />
cumulative impacts to arise with the jetty is significant due to the scale and complexity of<br />
the construction work for <strong>Hinkley</strong> <strong>Point</strong> C that would be undertaken during this period.<br />
However, these cumulative impacts would be temporary and would cease once the jetty<br />
had been dismantled, meaning that beyond this period the impacts would revert to those<br />
of the <strong>Hinkley</strong> <strong>Point</strong> C Project alone.<br />
9.3.5 These impacts would relate to the additive effects of the <strong>Hinkley</strong> <strong>Point</strong> C Project with<br />
regard to those environmental aspects that would either be affected outside of the<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 60 November 2010
footprint of the jetty development as this area would not be altered during by the <strong>Hinkley</strong><br />
<strong>Point</strong> C works during this phase of the jetty development, or which continue on from<br />
construction. The main aspects that fall into these categories are, in the first instance,<br />
landscape, heritage (setting) and amenity and with regard to the second category air and<br />
noise impacts.<br />
9.3.6 The building work for <strong>Hinkley</strong> <strong>Point</strong> C would significantly alter the local landscape and<br />
have wider visual impact. During the operational period for the jetty the visual impact of<br />
the jetty structure would combine with the <strong>Hinkley</strong> <strong>Point</strong> C reactor buildings to generate a<br />
greater visual impact than that of the jetty structure alone. While it could be argued that<br />
the visual and landscape impact would be due to the <strong>Hinkley</strong> <strong>Point</strong> C construction works,<br />
it would be difficult to separate out the combined elements of the jetty development and<br />
the new buildings such that specific impacts could be attributed to each. The total effect<br />
therefore has to be considered and in this context the cumulative impact would be<br />
greater than that attributable to the jetty development alone. This conclusion also applies<br />
to the setting of heritage interests where the jetty would form a significant component of<br />
the visible built form.<br />
9.3.7 Assessment of noise and air impacts for the jetty development indicates that they would<br />
be of limited significance during operation. Consequently, no greater cumulative impact is<br />
predicted with respect to these aspects during the overlap period with construction of<br />
<strong>Hinkley</strong> <strong>Point</strong> C.<br />
9.4 Cumulative Effects with Other Plans and Projects<br />
9.4.1 There are only a few projects in the wider environment that have could interact with the<br />
jetty development and potentially lead to cumulative impacts.<br />
9.4.2 At a regional level, the proposed Bristol Port Deep Sea Container Terminal project at<br />
Avonmouth is spatially so distant that cumulative effects would be confined to those that<br />
could only operate at a regional level. Apart from a negligible potential traffic / transport<br />
interaction between the jetty development / site preparation works and this project, no<br />
such effects have been identified. In proximity to the jetty development the<br />
decommissioning works for <strong>Hinkley</strong> <strong>Point</strong> A are of most relevance, while the continued<br />
operation of <strong>Hinkley</strong> <strong>Point</strong> B effectively forms part of the baseline against which impacts<br />
have been assessed for the jetty development.<br />
9.4.3 Available information for the <strong>Hinkley</strong> <strong>Point</strong> A decommissioning works shows that the<br />
majority of impacts would be confined to the footprint of the <strong>Hinkley</strong> <strong>Point</strong> A site and<br />
therefore outwith any spatial interaction with the jetty development. The cumulative<br />
socio-economic effects are considered to be no greater than the effects of jetty<br />
development / site preparation works alone since the contribution of <strong>Hinkley</strong> <strong>Point</strong> A is<br />
already included in the baseline.<br />
9.4.4 During operation of the jetty, there are a number of projects which temporally overlap. Of<br />
these, the proposed new nuclear power station at Oldbury is located at such a distance<br />
from <strong>Hinkley</strong> <strong>Point</strong> that the potential for any spatial interaction with the effects of the jetty<br />
is either non-existent or negligible. Potential overlap with the Steart Coastal Management<br />
Project would occur, but the lack of any significant spatial interaction and low magnitude<br />
effects associated with the jetty indicate that any cumulative effects would be negligible.<br />
For the transmission line upgrade into <strong>Hinkley</strong> <strong>Point</strong> C, there could be some interaction<br />
with regard to landscape and visual sensitivities however, the overall effect is unlikely to<br />
be significant. This is largely due to the fact that the combined landscape impact of the<br />
jetty and the transmission line upgrade would be significantly subsumed by the much<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 61 November 2010
greater landscape impact of the <strong>Hinkley</strong> <strong>Point</strong> C Project itself combined with the<br />
transmission line upgrade (i.e. in reality the transmission line upgrade is associated with<br />
the construction of <strong>Hinkley</strong> <strong>Point</strong> C).<br />
9.4.5 This assessment, therefore, concludes that any cumulative impacts with the potential to<br />
arise between the jetty development and other relevant projects would be negligible.<br />
10 CONCLUSION<br />
10.1.1 The majority of the impacts predicted to arise due to the jetty development are assessed<br />
to be of minor and negligible significance, particularly following mitigation. However, a<br />
few impacts are assessed to be significant (i.e. moderate or major adverse impacts).<br />
10.1.2 The key human and built environment impacts associated with the proposals for the jetty<br />
development at <strong>Hinkley</strong> <strong>Point</strong> are anticipated to arise from disturbance to users of public<br />
rights of way, changes to seascape and local and site landscape features, visual impacts<br />
along public rights of way, and effects on the setting of designated sites and features of<br />
cultural importance. These impacts are summarised in Section 7.<br />
10.1.3 The key impacts on the natural and physical environment, prior to mitigation, are<br />
summarised in Section 8, with the most significant adverse impact likely to arise from the<br />
disturbance to Corallina habitat and to badger habitat. Potential impacts on birds using<br />
inter-tidal areas are not predicted to be significant.<br />
10.1.4 As discussed in Sections 7 and 8, potentially significant effects could arise locally from<br />
the proposed development. However, care has been taken to avoid, reduce and mitigate<br />
potential adverse environmental effects as far as possible.<br />
<strong>Hinkley</strong> <strong>Point</strong> C Preliminary Works<br />
<strong>Non</strong> <strong>Technical</strong> <strong>Summary</strong><br />
Temporary <strong>Jetty</strong> Development 62 November 2010