Typical Project Schedule<br />

• Engineering & fabrication 20-24 weeks<br />

– Depending on delivery Silika<br />

• Site preparation 4-6 weeks<br />

• Demolition (3-wall block) 6-8 days<br />

• Wall re-built & heat-up 26-29 days<br />

– Wall placement in one day<br />

<strong>Oven</strong>s ~32-37 days out of service, which is a<br />

reduction of 15 days (Fused Silika) to 45 days<br />

(Silika).<br />

COMA <strong>Coke</strong> Conference March 2012