FastWall System - Coke Oven Managers Association
FastWall System - Coke Oven Managers Association
FastWall System - Coke Oven Managers Association
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Typical Project Schedule<br />
• Engineering & fabrication 20-24 weeks<br />
– Depending on delivery Silika<br />
• Site preparation 4-6 weeks<br />
• Demolition (3-wall block) 6-8 days<br />
• Wall re-built & heat-up 26-29 days<br />
– Wall placement in one day<br />
<strong>Oven</strong>s ~32-37 days out of service, which is a<br />
reduction of 15 days (Fused Silika) to 45 days<br />
(Silika).<br />
COMA <strong>Coke</strong> Conference March 2012