Khandwa – Dedhtalai – Burhanpur <strong>road</strong><br />
(Schedule-K)<br />
REPAIR/RECTIFICATION OF DEFECTS AND DEFICIENCIES<br />
Annex-I<br />
The Concessionaire shall repair and rectify the defects and deficiencies specified in<br />
this Annex-I of Schedule-K within the time limit set forth herein<br />
Nature of defect or deficiency Time limit for Repair/rectification<br />
ROADS<br />
(a) Carriageway and paved shoulders<br />
(i) Breach or blockade - Temporary restoration of<br />
Traffic within 24 hours; permanent<br />
restoration within 15 days<br />
(ii) Roughness value exceeding 3000 - 180 days<br />
mm in a stretch of 1km (as measured<br />
by a standardized Vehicle mounted<br />
ROMDAS system Rougho meter/Bump<br />
Integrator)<br />
(iii) Characteristic deflection as per IRC-81-1997- Every year after<br />
rainy season<br />
(iv) Pot holes - 48 hours<br />
(v) Cracking in more than 5% of <strong>road</strong> - 30 days<br />
Surface in a stretch of 1 km<br />
(vi) Rutting 10mm in more than 2% of - 30 days<br />
<strong>road</strong> surface in a stretch of 1 km<br />
(measured with 3 m straight edge)<br />
(vii) Bleeding/skidding - 7 days<br />
(viii) Raveling/Stripping of bitumen - 15 days<br />
Surface Exceeding 10 sq m<br />
(ix) Damage to pavement edges - 15 days<br />
exceeding 10 cm<br />
(x) Removal of debris - 6 hours<br />
(b) Hard/earth shoulders, side slopes, drains and culverts<br />
(i) Variation by more than 2% in - 30 days<br />
prescribed slope of camber/cross fall<br />
(ii) Edge drop at shoulders exceeding - 7 days<br />
40 mm<br />
(iii) Variation by more than 15% - 30 days<br />
in the prescribed side (embankment)<br />
slopes<br />
(iv) Rain cuts/gullies in slope - 7 days<br />
(v) Damage to or silting of culverts and - 7 days<br />
Side drains during and immediately<br />
Preceding the rainy season<br />
(vi) Desilting of drains in - 48 hours<br />
urban/semi-urban areas<br />
(c) <strong>Road</strong> side furniture including <strong>road</strong> signs and pavement marking<br />
(i) Damage to shape or position; - 48 hours<br />
poor visibility or loss of retro-reflectivity<br />
______________________________________________________________________<br />
MPRDC-Bhopal December, 2010