Khandwa – Dedhtalai – Burhanpur <strong>road</strong><br />

(Schedule-K)<br />

REPAIR/RECTIFICATION OF DEFECTS AND DEFICIENCIES<br />

Annex-I<br />

The Concessionaire shall repair and rectify the defects and deficiencies specified in<br />

this Annex-I of Schedule-K within the time limit set forth herein<br />

Nature of defect or deficiency Time limit for Repair/rectification<br />

ROADS<br />

(a) Carriageway and paved shoulders<br />

(i) Breach or blockade - Temporary restoration of<br />

Traffic within 24 hours; permanent<br />

restoration within 15 days<br />

(ii) Roughness value exceeding 3000 - 180 days<br />

mm in a stretch of 1km (as measured<br />

by a standardized Vehicle mounted<br />

ROMDAS system Rougho meter/Bump<br />

Integrator)<br />

(iii) Characteristic deflection as per IRC-81-1997- Every year after<br />

rainy season<br />

(iv) Pot holes - 48 hours<br />

(v) Cracking in more than 5% of <strong>road</strong> - 30 days<br />

Surface in a stretch of 1 km<br />

(vi) Rutting 10mm in more than 2% of - 30 days<br />

<strong>road</strong> surface in a stretch of 1 km<br />

(measured with 3 m straight edge)<br />

(vii) Bleeding/skidding - 7 days<br />

(viii) Raveling/Stripping of bitumen - 15 days<br />

Surface Exceeding 10 sq m<br />

(ix) Damage to pavement edges - 15 days<br />

exceeding 10 cm<br />

(x) Removal of debris - 6 hours<br />

(b) Hard/earth shoulders, side slopes, drains and culverts<br />

(i) Variation by more than 2% in - 30 days<br />

prescribed slope of camber/cross fall<br />

(ii) Edge drop at shoulders exceeding - 7 days<br />

40 mm<br />

(iii) Variation by more than 15% - 30 days<br />

in the prescribed side (embankment)<br />

slopes<br />

(iv) Rain cuts/gullies in slope - 7 days<br />

(v) Damage to or silting of culverts and - 7 days<br />

Side drains during and immediately<br />

Preceding the rainy season<br />

(vi) Desilting of drains in - 48 hours<br />

urban/semi-urban areas<br />

(c) <strong>Road</strong> side furniture including <strong>road</strong> signs and pavement marking<br />

(i) Damage to shape or position; - 48 hours<br />

poor visibility or loss of retro-reflectivity<br />

______________________________________________________________________<br />

MPRDC-Bhopal December, 2010