Rp of Chalk Gobindapur - LGED
Rp of Chalk Gobindapur - LGED
Rp of Chalk Gobindapur - LGED
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
epresentative inform APs <strong>of</strong> the subproject impacts, and their entitlements and rehabilitation<br />
options under the RP. Copies <strong>of</strong> the draft RP will be distributed amongst the WMCA including<br />
APs.<br />
A Grievance Redress Committee (GRC) formed by the Ministry <strong>of</strong> Local Government, Rural Development<br />
and Cooperatives (MoLGRDC) vide gazette Notification 46.068.004.00.002.2011-<br />
161 <strong>of</strong> dated10-03-2011. Any grievances submitted to the GRC will be resolved within stipulated<br />
period.<br />
Internal monitoring will be carried out by IWRMU’s Environment and Safeguards Section with<br />
support from the CRO, field staff at <strong>LGED</strong> district and upazila <strong>of</strong>fices and PIC Resettlement<br />
Specialist will establish a monthly monitoring system and prepare a Monthly Progress Report on<br />
all aspects <strong>of</strong> RP implementation. <strong>LGED</strong> will also report to ADB on land acquisition and resettlement<br />
and social development in the Quarterly Progress Report.<br />
This subproject does not have any budget for land acquisition as all the land is khas land,<br />
owned by the Government. As per Resettlement Framework the full costs <strong>of</strong> compensation will<br />
be the responsibility <strong>of</strong> the <strong>LGED</strong>. and special assistance to vulnerable AHHs502455.<br />
RESETTLEMENT PLAN FOR <strong>Chalk</strong> Gobindhapur –Aldadpur Subproject<br />
Table <strong>of</strong> Contents<br />
A. Project Background and Description .......................................................................... 1<br />
1. Background ................................................................................................ 1<br />
2. The <strong>Chalk</strong> <strong>Gobindapur</strong>-Aldadpur Subproject Description ............................ 3<br />
B.<br />
3. Area and Location ...................................................................................... 1<br />
Scope <strong>of</strong> Land Acquisition and Displacement ............................................................ 2<br />
1. Subproject Objectives ................................................................................. 2<br />
2. Construction Activities ................................................................................ 2<br />
3. Scope <strong>of</strong> Land Acquisition and Resettlement .............................................. 2<br />
4. Land Use and Settlement Pattern ............................................................... 3<br />
5. Methodology and Data Collection ............................................................... 3<br />
C.<br />
6. Socioeconomic Pr<strong>of</strong>ile <strong>of</strong> APs ..................................................................... 3<br />
Objectives, Resettlement Policy Framework and Entitlements ................................. 3<br />
1. Land Acquisition and Resettlement Principles ............................................ 3<br />
D.<br />
2. Entitlement Matrix ....................................................................................... 4<br />
Consultation and Disclosure ..................................................................................... 19<br />
1. Consultation and Stakeholders' Participation ............................................ 19<br />
2. Grievance Redress Mechanism ................................................................ 19<br />
E. Compensation and Resettlement Budget and Financing ......................................... 20<br />
F. RP Implementation ..................................................................................................... 20<br />
1. Implementation Schedule ......................................................................... 20<br />
G.<br />
2. Monitoring and Evaluation ........................................................................ 21<br />
Implementation Arrangements .................................................................................. 22<br />
1. Ministry <strong>of</strong> Local Government, Regional Development and Cooperatives<br />
(MoLGRDC) ...................................................................................................... 22<br />
2. Water Management Cooperative Association (WMCA) ............................ 22<br />
3. Resettlement Processing Committees/Teams .......................................... 23<br />
iii