<strong>The</strong> <strong>Marmaray</strong> <strong>Project</strong><br />

<br />

BC1 Contract<br />

Engineering/design, procurement and construction of<br />

a 13.6 km railway and related structures, which<br />

comprise of :<br />

approximately 1.4 km immersed tunnel,<br />

9.4 km twin-bore tunnel<br />

NATM Tunnel (Sirkeci(<br />

Deep Station with 250 mt<br />

platform and Uskudar Crossover Tunnel)<br />

Cut-and<br />

and-Cover Tunnels (Yenikapi(<br />

(760 mt) ) and<br />

Uskudar (310 mt) ) Deep Stations)