J - HKU Libraries
J - HKU Libraries
J - HKU Libraries
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
TERRITORY DEVELOPMENT DEPARTMENT<br />
SOUTH EAST NEW TERRITORIES DEVELOPMENT OFFICE<br />
Agreement No. CE 59/90<br />
ENGINEERING FEASIBILITY STUDY<br />
OF DEVELOPMENT OF<br />
TSEUNG KWAN O AREA 137<br />
Final Report<br />
EXECUTIVE SUMMARY<br />
MAIN REPORT<br />
DRAWINGS<br />
March 1993<br />
APH CONSULTANTS<br />
Acer Consultants (Far East) Ltd.<br />
Au Posford Consultants Ltd.<br />
Frederick R. Harris (Far East) Ltd.<br />
in association with<br />
UrbisTravers Morgan Ltd.<br />
MVA Asia Ltd.
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
ENGINEERING FEASIBILITY STUDY OF DEVELOPMENT OF<br />
TSEUNG KWAN O AREA 137<br />
MAIN REPORT<br />
CONTENTS<br />
Section<br />
Page<br />
INTRODUCTION<br />
1.1 Background<br />
1.2 Study Objectives<br />
1.3 Study Stages<br />
1.4 Report Structure<br />
1 . 5 Acknowledgement<br />
PLANNING BASE<br />
2.1 The Study Area<br />
2.2 Planning Context of Study Area<br />
2.3 Interfaces and Constraints<br />
THE PREFERRED CONCEPT<br />
3.1 Planning Background<br />
3.2 Alternative Concepts<br />
3.3 Risk Assessment of PHI Industries<br />
3.4 Preferred Concept<br />
LAND USE PLANNING<br />
4.1 Detailed Planning Layouts<br />
4.2 PHI and PHI Related Development<br />
4.3 DWI Development<br />
4.4 Supporting Development and Facilities<br />
4.5 Provision of Berthing Facilities<br />
4.6 Landscaping<br />
M<br />
1-1<br />
1-2<br />
1-2<br />
1-3<br />
2-1<br />
2-1<br />
2-3<br />
3-1<br />
3-1<br />
3-3<br />
3-7<br />
4-1<br />
4-1<br />
4-3<br />
4-4<br />
4-6<br />
AfH Consultants Page 1
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
5 ENGINEERING STUDIES<br />
5.1 Engineering Investigations<br />
5.2 Land Formation.<br />
5.3 Edge Structures<br />
5.4 Fill Requirements and Sources<br />
5.5 Dredging Requirements and Disposal<br />
5.6 Cavern Development<br />
5.7 Highways and Roads<br />
5.8 Stormwater Drainage<br />
5.9 Water Supply<br />
5.10 Sewerage<br />
5.11 Public Utilities<br />
6 MARINE STUDY<br />
6.1 Introduction<br />
6.2 Marine Traffic<br />
6.3 Ship Handling Operations<br />
6.4 Interaction Effects of Passing Ships<br />
6.5 Downtime Considerations<br />
6.6 Pilotage and Aids to Navigation<br />
6.7 Anchorages<br />
6.8 Navigational Risk and Vessel Traffic Control<br />
7 TRAFFIC AND TRANSPORT STUDY<br />
7.1 Traffic Forecasts<br />
7.2 The External Network<br />
7.3 Internal Road Network<br />
7.4 Public Transport Requirements<br />
8 WESTERN COAST ROAD<br />
8.1 Introduction<br />
8.2 Western Coast Road Connections<br />
8.3 Evaluation of Options<br />
8.4 Traffic and Roads<br />
8.5 Land Use Impacts<br />
8.6 Environmental Impacts<br />
8.7 Cost Comparison<br />
8.8 Evaluation Summary<br />
5-1<br />
5-5<br />
5-7<br />
5-10<br />
5-10<br />
5-11<br />
5-11<br />
5-12<br />
5-13<br />
5-15<br />
5-17<br />
6-1<br />
6-1<br />
6-3<br />
6-5<br />
6-6<br />
6-9<br />
6-9<br />
6-10<br />
7-1<br />
7-6<br />
7-17<br />
7-22<br />
8-1<br />
8-1<br />
8-2<br />
8-2<br />
8-3<br />
8-7<br />
8-13<br />
8- 15<br />
APH Consultants 2
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
9 ENVIRONMENTAL ASSESSMENT<br />
9.1 Introduction<br />
9.2 Key Impact Sources and Sensitive Receivers<br />
9.3 Water Quality<br />
9.4 Air Quality<br />
9.5 Noise<br />
9.6 Waste Management<br />
9.7 Visual Impact and Glare Nuisance<br />
9.8 Environmental Monitoring and Audit Schedules<br />
10 IMPLEMENTATION<br />
10.1 Introduction<br />
10.2 Preliminaries<br />
10.3 Implementation Schedule<br />
10.4 Capital Expenditure and Revenue Streams<br />
10.5 Study Implications<br />
10.6 Study Findings<br />
9-1<br />
9-1<br />
9-2<br />
9-7<br />
9-10<br />
9-13<br />
9-13<br />
9-18<br />
10-1<br />
10-1<br />
10-2<br />
10-5<br />
10-8<br />
10-9<br />
APPENDIX A STUDY REPORTS AND WORKING PAPERS<br />
APPENDIX B WRITTEN STATEMENTS<br />
APPENDIX C SUGGESTED MODIFICATIONS TO TSEUNG KWAN O ODP<br />
APPENDIX D DRAFT FINAL REPORT COMMENTS AND RESPONSES<br />
APH. Consultants Page 3
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
SECTION 1<br />
INTRODUCTION<br />
1.1 BACKGROUND<br />
The Port and Airport Development Strategy (PADS), October 1989, provides for future growth of port<br />
and air traffic up to 2011 and beyond. The strategy sets out in broad terms development proposals to<br />
support port and airport development as well as to satisfy the forecast strategic demands for industrial<br />
land. Within the PADS context, Area 137, to the south of Tseung Kwan 0 on the eastern side of the bay,<br />
is to be developed for port facilities supporting Deep Waterfront Industries (DWIs) and Potentially<br />
Hazardous Installations (PHIs).<br />
The Final Report of the Tseung Kwan O Feasibility Study of Opportunities for Further Development<br />
outlined two possible links from the proposed Western Coast Road to East Kowloon. It was agreed that<br />
the need for additional transport links for Tseung Kwan O would be considered in the context of the<br />
feasibility study for the proposed development of Areas 131 and 137. In October 1991, the Port Progress<br />
Committee decided that only the Area 137 study should proceed but that the possible future development<br />
of Area 131 should be taken into consideration in the study.<br />
Accordingly, APH Consultants were commissioned in February 1992 to investigate the feasibility of<br />
developing Area 137 forDWI and PHI industries, to assess the likely impacts of such a development and<br />
to produce an outline engineering design and land use plan for the site. The assessments were required<br />
to take into consideration the possible development of Area 131 as a dockyard facility and particular<br />
attention was required to be given to the selection of the Western Coast Road connections.<br />
This Final Report gives details of the recommended development layout and the outline engineering<br />
design. The Report documents the findings of the Study and describes the analysis and considerations<br />
which support the findings. The Final Report consists of three documents, an Executive Summary of the<br />
Study, the Main Report, containing the text of the analysis and the Drawings document, containing the<br />
land use and outline engineering design drawings.<br />
1.2 STUDY OBJECTIVES<br />
The prime objective of the Study is to produce an outline engineering design of the recommended layout<br />
for Area 137 in sufficient detail to allow progression to detailed planning and design of the development.<br />
Major issues required to be examined under the Brief include:<br />
> an assessment of land use demand and constraints and the development of a land use plan,<br />
together with infrastructure requirements;<br />
* engineering solutions for the reclamation of the site and determination of a berth layout*<br />
compatible with user demand and providing safe and efficient marine traffic arrangements;<br />
> assessment of traffic and transport impacts and the provision of transport infrastructure, both<br />
within and outside the area of development;<br />
> marine and environmental impacts of the development;<br />
* outline design for the provision of services and utilities to the site;<br />
APH Consultants Page 1-
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
> preparation of a development programme together with revenue and expenditure forecasts.<br />
Of particular concern is the interface with the SENT Landfill and the Tseung Kwan O Industrial Estate<br />
(TKOEE) to the north of the Site. The development of Area 137 also has to be incorporated into the<br />
framework of overall strategic development and planning requirements of the area.<br />
1.3 STUDY STAGES<br />
The Study has been carried out in three main stages:<br />
The Alternative Concepts Stage, reviewed the existing background data and determined the level of<br />
potential interest in the site to enable the first conceptual plans to be drawn up. These were then evaluated<br />
and two alternatives selected for development and refinement within the next stage.<br />
The Preferred Concept Stage, the selected''layouts were subjected to detailed assessments including<br />
WAHMO and ship manoeuvring modelling and environmental assessments of the impacts associated with<br />
the development. On the basis of this, the Preferred Concept was identified.<br />
The Final Stage, completed all required evaluations and studies and defined the Recommended<br />
Development Layout including implementation programming.<br />
Each of the above stages was completed with the preparation of a Report, with the last stage being covered<br />
by this Final Report for the Study. In addition a total of nine working papers have been produced during<br />
the course of the Study covering the major issues and a schedule of these documents is provided in<br />
Appendix A.<br />
1.4 REPORT STRUCTURE<br />
This document presents the recommended development layout for Area 137 together with the findings of<br />
the Study in support of its selection. In so doing, the Report draws on the detailed information and<br />
assessments contained in the previous Study Reports as well as in the Discussion and Working Papers<br />
produced under the Study.<br />
Section 2, Planning Base, describes the Study Area and provides the planning context within which the<br />
proposed development has been accommodated. Constraints which affect the development of the site are<br />
also established.<br />
Section 3, the Preferred Concept, describes the stages leading up to the selection of the Recommended<br />
Development Layout. The rationale behind the selection of this layout is given together with the<br />
engineering and planning issues and constraints which underlie the concept.<br />
The subsequent Sections (4 to 9) give details of the studies that have been undertaken for the proposed<br />
development. These studies are:<br />
> Land Use Study, detailing the envisaged DWI and PHI industries and supporting facilities, risk<br />
assessment and landscaping proposals;<br />
+ Engineering Considerations, including land formation, marine structures, site road network and<br />
provision of services and utilities;<br />
APH Conmitaats
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
final Report - Main Report<br />
> Marine Study, in which the suitability of the berthing arrangements and marine traffic safety<br />
issues are addressed;<br />
> Traffic and Transport Study, which assesses the internal and external road network and traffic<br />
impacts on these roads;<br />
> The Western Coast Road connection;<br />
> Environmental Aspects which considers the relevant issues arising from the environmental<br />
assessment, including impacts and mitigation measures as well as monitoring and audit<br />
requirements.<br />
Finally, in Section 10, the development phasing and implementation issues are discussed and revenues and<br />
cash flows estimated.<br />
1.5 ACKNOWLEDGEMENT<br />
The Study Team wish to express their gratitude to all in Government and the private sector who have<br />
provided assistance or advice during the course of the Study. Thanks are especially due to the members<br />
of the Steering and Working Groups, PM SENT and the staff of the Territory Development Department,<br />
South East New Territories Development Office. All have assisted the Team in a supportive and positive<br />
manner which has made a major contribution to the Study work and progress.<br />
APH Consultants Pag* 1-
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
SECTION 2<br />
PLANNING BASE<br />
2.1 THE STUDY AREA<br />
Area 137 is located almost 8 km southeast ofTseung Kwan O New Town, at the entrance to the Tseung<br />
Kwan O bay. Figure 2.1 indicates the Study Area and land use as covered by the Tseung Kwan O ODP,<br />
The implementation of Area 137 will require the reclamation of an area of open sea between Fat Tong<br />
Chau (Junk Island) and Tit Cham Chau. Once formed, the site will abut the Clearwater Bay Country Park<br />
to the east. The Park is a designated country park which is governed by a series of regulations structured<br />
to conserve its natural features and amenity. To the north of the site, Fat Tong Chau is being partially<br />
excavated to provide reclamation material for the Tseung Kwan O Industrial Estate (TKOIE). The<br />
proposed SENT Landfill site, to the southeast of the TKOIE, demarcates the northeast boundary of Area<br />
137.<br />
To the west of the site, the Tathong Channel separates Area 137 from Hong Kong Island and Chai Wan.<br />
This channel, which has a Traffic Separation Scheme, provides access to Victoria Harbour from the east.<br />
2.2 PLANNING CONTEXT OF STUDY AREA<br />
2.2.1 Tseung Kwan O Outline Development Plan (ODP)<br />
Subsequent to the endorsement of the Tseung Kwan O New Town Study by the Land Development Policy<br />
Committee (LDPC) in July 1982, the Executive Council approved in principle the development ofTseung<br />
Kwan O into a New Town. The Tseung Kwan O New Town Outline Development Plan (ODP) was<br />
approved by LDPC in August 1983 as a basis for the overall development.<br />
Throughout the 1980*s several revised OOP's were prepared and approved to reflect and encompass the<br />
findings of various studies which were undertaken in relation to specific aspects of the New Town<br />
Development and with respect to physical changes which had an impact on planning intentions for the<br />
area.<br />
The latest ODP was approved by the Development Progress Committee (DPC) in November 1990 and<br />
provides the planning context for the present Study area.<br />
The ODP proposes that residential and town centre development will be concentrated on existing and<br />
reclaimed land at the head of the Tseung Kwan O bay. Almost 20% of the total land use budget is given<br />
to residential and commercial/residential development. The achievement of the target population of<br />
440,000 is largely dependent on the upgrading of transport links to the N"ew Town. These include the<br />
construction of the Western Coast Road and the development of a MTR link. Anticipated population<br />
thresholds may not therefore be achieved within the timescale anticipated by the ODP if transport<br />
connections are not upgraded when and as expected. Furthermore, the absence of new transport links may<br />
constrain the efficient passage of products from Area 137.<br />
The ODP proposes that industrial development will comprise almost 22% of the total land use budget and<br />
will be confined to sites south east of the New Town, separated from residential development by the<br />
Tseung Kwan O Stage 1 Landfill.<br />
APH Consultants Page 2-1
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
Industrial development I(A) (high density high intensity commonly associated with flatted factory type<br />
development) is proposed immediately south of the Stage I Landfill. Adjacent to this area is the Tseung<br />
Kwan O Sewage Treatment Works. An interim upgrading of the plant is scheduled to commence in late<br />
1993. On completion in mid 1995, the additional facilities will be able to cope with the effluent generated<br />
by the TKOEE. Additional effluent generated by development in Tseung Kwan O will require further<br />
upgrading of the plant. Further south, reclamation is underway for the TKOIE. The site is being<br />
developed in two phases and will provide for I(B) class industries. Inland from the TKOIE is the site of<br />
the SENT Landfill, for which marine access is provided from the south, through Area 137.<br />
Further to the findings of PADS, the ODP incorporated a recommendation that Area 137 be reserved for<br />
DWI including a site amounting to almost 20 ha reserved for the estimated demand for PHIs. The<br />
relatively isolated location of the site and the availability of deep water, renders the site well suited to<br />
DWI and PHI use. The site will not only provide new industrial lots but will also provide for the removal<br />
of existing installations which, by virtue of the processes they utilise, are incompatible with adjacent land<br />
uses in existing Urban Areas. Area 137 is zoned for I(B) (typically low density land extensive industries<br />
which normally have special site and technological requirements) and I(C) (industries normally comprising<br />
warehousing, bulk storage and dangerous goods storage developments) purposes under the operative ODP<br />
which will allow for the development of land extensive industry and premises for warehousing or storage.<br />
2.2.2 The Port and Airport Development Strategy (PADS)<br />
The PADS Development Statement No.5 'Tseung Kwan O Port Development" sets out the requirements<br />
which are to be met by the proposed port facilities in Tseung Kwan O. The Development Statement was<br />
endorsed by the LDPC in August 1990 as a basis for detailed development study.<br />
An implementation programme for the site was defined which proposed that site formation works in Area<br />
137 should commence in late 1993 to allow availability of sites for Pffl's in early 1995. The PADS<br />
development programme is summarised in Table 2.1.<br />
TABLE 2.1 : PADS DEVELOPMENT PROGRAMME : AREA 137<br />
Development Phase<br />
Potentially Hazardous Installations<br />
Phase 1<br />
Phase 2<br />
Phase 3<br />
Gross Area (ha)<br />
20<br />
30<br />
30<br />
40<br />
Proposed Availability<br />
early 1995<br />
7/1995<br />
4/1996<br />
1/1997<br />
120<br />
Source: PADS Development Statement No.5<br />
The total site area given to Area 137 was subsequently reduced to 108 ha to cater for the southward<br />
expansion of the proposed SENT Landfill.<br />
2.2.3 Planning Issues<br />
The Hong Kong Planning Standards and Guidelines (HKPSG) provide for a maximum average plot ratio<br />
for I(C) industries in New Towns of 5.0. Nevertheless, the range of plot ratios permitted for this category<br />
APH Consultants Page 2-2
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
extends from 3.5 to 9.5. A maximum plot ratio of 2.5 is suggested for I(B) industries in New Towns with<br />
scope for lower plot ratios to be employed as appropriate.<br />
The ODP proposes that plot ratios applied to I(B) and I(C) industrial sites should be 2.5 and 5.0<br />
respectively. The Written Statement does recognize that there may be a need for higher or lower plot<br />
ratios "depending on local circumstances' 1 . In Area 137, where industrial site requirements are likely to<br />
be land extensive, fairly nominal plot ratios may be appropriate due to risk consideration and the nature<br />
of operations which may be undertaken.<br />
The construction of lower density, high technology industries accords well, not only with the provisions<br />
of the HKPSG, but also with Planning Department's recently published Metropolitan Development<br />
Strategy (Metroplan: The Selected Strategy, October 1991). However, low density DWI and PHI<br />
development may have to be encouraged by lower premiums being levied on lease agreements. Without<br />
this incentive it is likely that potential operators would want to locate outside the Territory where land<br />
acquisition costs and development conditions are comparatively less restrictive.<br />
An Outline Zoning Plan (OZP) covering the subject area was gazetted on 11 December 1992. The OZP<br />
will give statutory effect to the land use proposals for the area.<br />
23 INTERFACES AND CONSTRAINTS<br />
23.1 The Tseung Kwan O Industrial Estate (TKOIE)<br />
The TKOIE is being developed in two phases in Area 87, north of Fat Tong Chau. The estate will<br />
ultimately provide for 75 ha of industrial lots on reclaimed land. The first phase is anticipated to be<br />
completed by 1993/94 and the Phase II reclamation by 1995.<br />
Reclamation material within the TKOIE will be retained by rubble revetments. No vertical seawalls are<br />
being constructed, although provision exists for the construction of mooring facilities to be undertaken by<br />
a private developer if required. However, the Hong Kong Industrial Estates Corporation (HKIEC) would<br />
regard this as a private initiative and would not wish to become involved in the management of marine<br />
related facilities.<br />
While the provision of berthing facilities could conceivably put the TKOIE in direct competition with<br />
envisaged DWI lots in Area 137, it is likely that the TKOIE development will be confined to medium<br />
density, high to medium technology, industries. HKIEC specifically prohibits the establishment of any<br />
operation which confines itself to storage or godown operations. Furthermore, lot sizes within the TKOIE<br />
are unlikely to be sufficiently large to meet DWI or PHI spatial requirements. It is considered more likely<br />
that industrial development within TKOIE is likely to be compatible with that on Area 137.<br />
HKIEC have indicated that they are concerned at the interface between industrial sites on the TKOIE and<br />
PHI development on Area 137. The Corporation would be strongly opposed to the construction of any<br />
PHI or dangerous goods facility immediately adjacent to their site, as this may have a significant impact<br />
on the site's viability.<br />
23.2 SENT Landfill<br />
The SENT Landfill is located to the north east of Area 137. The Advance Works Contract is currently<br />
underway and the Landfill is due to be implemented in 1993 with the first waste material being received<br />
in 1994. Twenty percent of all material will be delivered by sea with the balance being delivered by road.<br />
Material to be deposited will include construction waste and treated sludge from Drainage Services<br />
Department's Stonecutters Treatment facility. The latter will be delivered to site by barge. The life of<br />
APH Consultants ~~ r rage 2-
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
the Landfill is dependent on the volume of waste likely to be generated in the Territory and availability<br />
of other landfill sites. Current estimates envisage the Landfill having a minimum life of 8 years and a<br />
maximum life of 20 years, with a probable life of 13 years. During the 30 year aftercare period there will<br />
be ongoing site maintenance and landscaping work as well as collection and treatment of leachate and<br />
landfill gas. The SENT Landfill Contract is programmed to be completed by approximately 2038.<br />
The Advance Works Contract will provide basic site works including a 100 metre quay wall along the<br />
southern perimeter of the landfill site and a seawall extending south from the eastern tip of Fat Tong<br />
Chau. A works area is to be established behind the seawall to provide for the supervision, construction<br />
and maintenance of the Landfill. The alignment of the seawall running south from Fat Tong Chau<br />
coincides with the proposed alignment of Road D6 which is required to provide access to Area 137.<br />
Furthermore, 150 m of quay wall will be required along the seawall to provide moorings for barges<br />
delivering waste and treated sludge to site upon implementation of the Landfill.<br />
The SENT Landfill Contract requires marine access to be maintained throughout the duration of the<br />
Contract, ie until approximately 2038. Reclamation of Area 137 will therefore require the reprovisioning<br />
of the access facilities to a suitable alternative location. Whilst it has been agreed that the SENT Landfill<br />
marine access will be incorporated within Area 137 in the planning of the development, the relocation of<br />
the access outside Area 137 should also be considered in the light of the constraint imposed.<br />
2*33 Physical Constraints<br />
An important element of the planning Brief is that the integrity of existing physical features should be<br />
preserved as far as practicable. The adjacent islands and Clearwater Bay Country Park are important<br />
features or areas of recreational amenity. Careful consideration is therefore required that the character<br />
of these features is not substantially undermined.<br />
This requires appropriate attention to be given to interface treatments which are capable of mitigating both<br />
physical and visual impacts. These aspects have been considered in the preparation of landscape proposals<br />
for the development, particularly at interfaces with sensitive or important landmark features.<br />
Urban design considerations are of similar significance. Defined parameters are required to ensure that<br />
the density, height and composition of industrial development on Area 137 is assembled in a manner<br />
complementary to its surroundings and that on-site industrial interfaces are mutually compatible.<br />
It is important also that the development of the site is undertaken with sensitivity to ensure, as far as<br />
practicable, that visual impacts are attenuated. Of particular concern are the likely visual impacts to<br />
existing and proposed residential development in Chai Wan. Again these can only be reduced through<br />
the application of specific design controls and with the utilisation of appropriate design and landscape<br />
measures.<br />
Finally, a further constraint to the development results from land drainage measures required by the SENT<br />
Landfill, At least two major culverts will discharge initially from the seawall constructed to the south of<br />
the landfill site. These will subsequently require extension through Area 137. Under Drainage Service<br />
Department requirements, no development is permitted on or over culvert reserves.<br />
2.3,4 Access Constraints<br />
Access to Area 137 will be provided via a new district distributor, Road D6, which will function as a<br />
southerly extension of Road PI, serving, in addition to Area 137, Industrial Area 86, TKOIE and the<br />
SENT Landfill site.<br />
APH Consultants Page 2-4
Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
Road PI presently consists of a single carriageway from its junction with Chiu Shun Road (Road D4) to<br />
Area 86. By 1994 it is expected that this route will be extended southwards (as Road D6) to serve<br />
TKOIE. Although D6 will be constructed initially as a single carriageway, a dual 2 lane carriageway is<br />
envisaged with estimated capacity of 6300 pcu^hr. The second carriageway to Road PI is expected to be<br />
constructed by the year 2001.<br />
Road D6 will be constructed initially to a roundabout in the north of the TKOIE to provide access to the<br />
industrial estate. A stub will be provided from which temporary access to the adjacent SENT Landfill site<br />
will be provided. The present proposals as regards the southern extension of D6 are that the section of<br />
road reserve between TKOIE and SENT Landfill up to and including the tip of Fat Tong Chau will be<br />
handed over to the SENT Landfill contractor as a working area once the TKOIE contract works in the area<br />
are complete, anticipated to be mid 1995. The landfill contractor will then complete the formation of this<br />
section of Road D6 and hand the area back to Territory Development Department for the construction of<br />
the road within 12 months of receipt of notice. Completion of the D6 extension to the south of Area 137<br />
would therefore be anticipated by mid 1997.<br />
This Study gives further consideration to the need for junction improvements along route D6/P1 which<br />
is seen as one of the key access routes to Area 137 as it links directly to Tseung Kwan 0 Tunnel and<br />
thence to East Kowloon. In the Tseung Kwan 0 Feasibility Study of Opportunities for Further<br />
Development (TKOFSOFD) the question of access to Tseung Kwan O from the urban area was examined.<br />
Options to provide additional road capacity were evaluated, and as a result a recommendation was made<br />
that a Western Coast Road link should be provided. For Area 137 the Western Coast Road combined with<br />
the proposed Cross-Bay Bridge (Road D9), is seen as the other key access route to East Kowloon,<br />
particularly if the Western Coast Road links up with the Kai Tak Connector. The nature of traffic<br />
generated by the proposed DWIs and Pffls within Area 137 is such that it is desirable to confine this<br />
traffic to high standard expressway routes. These routes, which will include the Western Coast Road and<br />
the Cross Bay Bridge, will be separated from the residential and commercial areas in Tseung Kwan 0 and<br />
ensure that environmental impacts are minimised.<br />
The development of Area 137 will be dependent on the successful and expeditious resolution of access<br />
constraints. Potential operators have expressed a view that Area 137 is required urgently and that demand<br />
will tail off dramatically if the site is not formed promptly and suitable access arrangements provided.<br />
APH Consultants ' ' '<br />
:<br />
' ' '• • '. ': • ,<br />
!<br />
~ ' ~ —;<br />
Page 2-5
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
SECTION 3<br />
THE PREFERRED CONCEPT<br />
3.1 PLANNING BACKGROUND<br />
The planning for a marine related industrial development must cater for the needs of the identified<br />
industrial land demand together with the provision of safe and efficient port facilities. Within the area<br />
designated for development, land uses and berth configurations need to be integrated to form an efficient<br />
and cost effective unit.<br />
The initial planning for Area 137, for the definition of land use requirements, focused on identifying<br />
potential operators and the likely split in demand between DWIs and Pffls. The split between DWI and<br />
PHI was determined by surveys which indicated that the demand for PHI sites may be stronger than<br />
originally envisaged under PADS. Therefore, for planning purposes, an allocation of 50 ha for PHI was<br />
recommended with the remaining 60 ha allocated to DWI as well as site services, roads, quay working<br />
areas, etc. It was recognised that flexibility would need to be inherent in any land use proposals in order<br />
that the final layout could be responsive to future changes in demand.<br />
Several key PHI developments were identified for potential location in Area 137, These included:<br />
+ a bulk chemical storage facility;<br />
> fuel storage facility;<br />
> a naphtha storage and gas production facility;<br />
*• an LPG storage and bottling facility.<br />
The PHI related activities included chemical processing and dangerous goods godowns. Based on research<br />
undertaken, the demand for DWI did not appear as robust as that for PHI, although it was felt that the<br />
site provided considerable opportunities which could generate strong demand over time. Possible DWI<br />
facilities included concrete batching and precasting works as well as warehousing.<br />
The PHI development was located to the south of Area 137 to avoid interface problems with adjacent land<br />
uses, in particular the TKOIE. The balance of the site was allocated to DWI development, other industrial<br />
uses, and identified supporting land uses such as:<br />
* public transport interchange;<br />
> truck/container storage area;<br />
* service centre accommodating administration offices, food stalls, banks etc;<br />
* pipeline and drainage reserves;<br />
> possible water treatment plant;<br />
> saltwater pumping station to provide water for flushing;<br />
* open space;<br />
+ reserves for other infrastructure including sewerage pumping stations, electricity substations etc.<br />
3.2 ALTERNATIVE CONCEPTS<br />
The findings of the initial planning studies enabled the preparation of a series of conceptual layouts<br />
incorporating several port berthing configurations, with each providing marine facilities of varying degrees<br />
of protection, efficiency and ship utility. Seven alternative layout options were presented in the<br />
Alternative Concepts Report based on planning, demand, engineering, marine and environmental<br />
APH Consultants Pag* 3~1
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
considerations. The layouts produced were conceptual in nature and did not preclude detail changes in<br />
later stages of the Study. All Options, bar one, provided for the reprovisioning of marine access to the<br />
SENT Landfill with a 250 m berthing facility and a 50 m wide working area behind the quay for back up<br />
facilities.<br />
Each Option produced a varying extent of DWI and PHI provision dependent on the land provided behind<br />
the seawall and the configuration of the seawall itself. The extent of land provided was also, to some<br />
degree, governed by the alignment of the proposed extension to Distributor Road D6. In all instances a<br />
landscape buffer was maintained around the perimeters of Area 137 to provide a reasonable interface<br />
between industrial development on the site and the rural hinterland, and to maintain the integrity of key<br />
physical features.<br />
The quay wall alignments and berthing layouts were determined primarily in relation to marine constraints.<br />
In the initial assessment, the predominant wave direction was assumed to be parallel to the Tathong<br />
Channel fairway orientation. A similar orientation was therefore assumed for the quay wall to reduce<br />
downtime due to wave action.<br />
Other constraints which affected the berth layouts related to navigational manoeuvring in cross currents,<br />
provision of re-entrants and basins for more sheltered berthing facilities, separation from shipping lanes<br />
and interaction with other ships.<br />
A comprehensive evaluation was undertaken to select the options for further refinement, namely Option<br />
B(i) and Option D (Figures 3.1 and 3.2). These layouts allowed for flexibility in later planning in the<br />
balance of provision of DWI and PHI land and in the nature of marine facilities required. Option B(i)<br />
maximised land for development with lesser emphasis on sheltered berthing for smaller vessels. The land<br />
provided was suited to the spatial requirements of PHI development. Option D placed emphasis on the<br />
provision of protected berthing facilities with the land provided being suited to greater DWI development.<br />
Land allocation and lengths of berths provided by these two options are shown in Table 3.1.<br />
TABLE 3.1 :<br />
LAND AREAS AND BERTH LENGTHS OF SELECTED ALTERNATIVE CONCEPTS<br />
Gross site area (ha)<br />
PHI site area (ha)<br />
DWI site area (ha)<br />
Deepwater berth length (m)<br />
Protected berth length (m)<br />
OPTION B(i)<br />
111<br />
51<br />
38<br />
2020<br />
550<br />
OPTION D<br />
39<br />
51<br />
20<br />
2470<br />
1350<br />
In addition, consideration was given to the proposed dockyaid development in Area 131. An assessment<br />
was carried out to determine the preferred layout of dockyard fecilities in terms of the wave climate and<br />
tidal flow, based on information available at the time. A recommended layout, Figure 3.3, was selected<br />
for use in die tidal flow and water quality modelling required for the Study.<br />
Implementation of the recommended dockyard arrangement would require the realignment of Road D9<br />
at its junction with Road P2. Although mis would appear to introduce no additional technical problems,<br />
a modification of the ODP would be required.<br />
'<br />
APH Consultants ' ~ " ; — —~<br />
Page 3-2
Figure 3.1<br />
SENT Landfill<br />
FAT TONG CHAU<br />
( Junk Island )<br />
SENT Landfill Access<br />
c.'.spaca-.v,<br />
and services<br />
Clearwater Bay<br />
Country Park<br />
Passible future<br />
extension of 06<br />
„ Bulk chemical storage<br />
X * X * X * " '<br />
LEGEND<br />
Potentially hazardous installations<br />
Deep water frontage industry<br />
CHAM<br />
HAU<br />
Open soace and services<br />
[' ..... " | Boundary of Area 137<br />
Interface landscaping<br />
Proposed dredged level<br />
Scale 1:10.000<br />
n 100 200 300 400 500<br />
ALTERNATIVE CONCEPTS, OPTION B(i)<br />
APH CONSULTANTS
Figure 3.2<br />
FAT TONG CHAU<br />
( Junk Island )<br />
SENT Landfill Access -,_<br />
Jv:>\ .' ; 0p«n spact..','<br />
pSv^VV'."
Figure 3.3<br />
INDUSTRIAL<br />
DEVELOPMENT<br />
APCAC<br />
AREA 131 RECOMMENDED DOCKYARD LAYOUT<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
33 RISK ASSESSMENT OF Pffl INDUSTRIES<br />
3.3,1 Overview<br />
An assessment of the risks associated with the PHIs on Area 137 has been carried out. In essence, this<br />
work provided a basis against which to consider the following questions:<br />
* Is Area 137 suitable for the location of PHIs<br />
>> What restrictions, if any, should be placed on the nature of such PHIs<br />
* Given the presence of PHIs, what planning controls would be appropriate in the vicinity<br />
Three separate reports were prepared in relation to:<br />
> risks associated with land-based operations at each of the PHI sites;<br />
> risks associated with a "worst-case analysis" of marine incidents at or close to, the jetties; and<br />
> risks associated with both land-based operations and marine incidents at or close to, the jetties.<br />
These reports have been presented and discussed at CCPffl meetings held on 24 November 1992 and 3<br />
February 1993. The following sections summarise the endorsed results of the latter report; namely the<br />
risks associated with both land-based operations and marine incidents at or close to the jetty.<br />
33*2 Risks and Risk Assessment<br />
Modern facilities which handle hazardous materials including gases, oil products and chemicals, are<br />
designed, constructed and operated to ensure that the chances of a major incident are very low.<br />
Nevertheless, there remains the possibility that a major incident could occur which represents a risk to<br />
people beyond the boundary fence.<br />
Such risks are differentiated between individual and societal risks. Individual risk represents the chances<br />
of being killed at a particular location from the effects of a number of different postulated accidents. A<br />
complementary method is to summate the likelihoods of the various accidents with their associated<br />
consequences, in terms of the numbers of fatalities, to give a picture of the overall risk to people nearby.<br />
This is referred to as the societal risk.<br />
3.3.3 The Pffls<br />
In order to provide a basis for the risk assessment, it was assumed that the following Pffls would be<br />
located on Area 137:<br />
> an oil product terminal;<br />
* a bulk chemical storage facility (BCSF);<br />
» an LPG (liquefied petroleum gas) terminal;<br />
* a gas production facility.<br />
Further assumptions were then made as to the likely throughput of materials, the transport of materials<br />
to and from the sites and the storage/processing fecilities as shown in Table 3.2 below.<br />
APH Consultants "~ ""<br />
Page J- 3
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 3.2 :<br />
BASELINE ASSUMPTIONS USED IN THE ANALYSIS<br />
PHI:<br />
OIL TERMINAL<br />
BCSF<br />
LPG TERMINAL<br />
GAS<br />
FACILITY<br />
Throughput<br />
(raVyr)<br />
1,000,000<br />
500,000<br />
100,000<br />
500,000<br />
(naphtha)<br />
Vessel Size<br />
(imports)<br />
30-45,OOQdwt<br />
40,000
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Operations at, or close to, the jetty were determined to be the major contributors to the overall risks. The<br />
risks were derived for a spectrum of accidents ranging from the more likely but less serious incidents to<br />
very remote, but credible, and severe incidents. In particular, large and unignited, spills of several<br />
hundred tonnes of the more hazardous materials could lead to the generation of significant quantities of<br />
toxic fumes. Depending on the prevailing weather conditions, such events could result in 100 or more<br />
fatalities amongst those on Area 137. In the extreme, it was possible to identify a sequence of events<br />
which could lead to fatalities in Siu Sai Wan; a residential area of Chai Wan some 1.5 km to the west of<br />
the proposed jetties.<br />
More likely but less severe incidents with the potential for off-site fatalities, included flash fires in the<br />
vicinity of the jetty and a major explosion involving highly reactive chemicals which would have serious<br />
consequences in the immediate area.<br />
3.3.6 LPG Terminal<br />
The LPG is assumed to arrive in small coastal tankers and be transferred to horizontal pressure vessels,<br />
bullets. The bullets would be of the latest semi-mounded design with additional protection to prevent any<br />
damage associated with nearby fires or explosions. There would also be LPG bottling/storage/dispatch<br />
facilities.<br />
Incidents involving multi-tonne releases of LPG at the jetty, from the storage area or during the loading<br />
of bulk road tankers could aU lead to off-site fatalities. The most severe events identified were vapour<br />
cloud explosions which could lead to 100 or more fatalities amongst those on Area 137, and, in the worst<br />
case, a large vapour cloud could be ignited near the Siu Sai Wan shore-line.<br />
33.7 Gas Production Facility<br />
This facility was be assumed to be broadly similar to the existing Tai Po plant. Naphtha would arrive in<br />
tankers and be stored in three large tanks located at the southern edge of Area 137. There would be<br />
processing units to convert the naphtha to town gas and gas export facilities via pipeline.<br />
The risks were dominated by those associated with large releases of naphtha at the jetty which could lead<br />
to off-site fatalities. In the worst cases, a flash fire could result in 20 or more fatalities in Area 137 and,<br />
in the extreme, the Siu Sai Wan area could be affected.<br />
33.8 Risk Results and Risk Criteria<br />
Individual Risks<br />
In accord with the recommendations of the CCPffl, the assessed individual risks for each Pffl were<br />
compared to the Individual Risk Guideline which suggests that the off-site individual risk should not<br />
exceed 1 chance in 100,000 per year of becoming a fatality.<br />
The results of the risk assessment indicate that there would be negligible individual risks to people outside<br />
Area 137. With regard to workers on Area 137, the individual risks associated with each of the Pffls<br />
were below the Guideline value of 1 in 100,000 per year,<br />
Societal Risks<br />
The results of the risk assessment were also evaluated in respect of societal risks The Societal Risk<br />
Guideline is more complex than that for individual risk, but, in essence, comprises three regions:<br />
* a region within which the risks may be regarded as unacceptable;<br />
APH Consultants "~~ —:<br />
Page Jo
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
> a region within which the risks may be regarded as acceptable; and<br />
> a region between the two in which measures should be taken to ensure that the risks are "as low<br />
as reasonably practicable" (ALARP).<br />
Numerically, the upper bound of the ALARP region and hence the borderline of "unacceptabiiity", can<br />
be summarised as:<br />
> 1 chance in 1,0(30 per year of an incident resulting in 1 or more fatalities;<br />
+ 1 chance in 10,000 per year of an incident resulting in 10 or more fatalities;<br />
> 1 chance in 100,000 per year of an incident resulting in 100 or more fatalities; and<br />
> not more than 1,000 fatalities at a frequency of greater than 1 chance in a billion (1,000,000,000)<br />
per year.<br />
For three of the sites, the BCSF, the LPG Terminal and the Gas Production Facility, the societal risk<br />
results may be summarised as follows:<br />
>•<br />
a region associated with incidents which could result in a few off-site fatalities. In broad terms,<br />
the societal risks were close to the Societal Risk Guideline. In one case, the LPG Terminal, the<br />
Guideline was very slightly exceeded. It is considered that this was due to a combination of the<br />
pessimistic assumptions made and the nature of the calculation methods used. On this basis, it<br />
is not considered that these assessed risks should be deemed "unacceptable" at this stage.<br />
Furthermore, should the outline development plans proceed to firm detailed proposals, the<br />
operators should be able to demonstrate compliance with this part of the Societal Risk Guideline<br />
in due course;<br />
> a region associated with less likely but more serious incidents which could lead to tens, or more,<br />
of fatalities amongst people on other facilities on Area 137. Such incidents, as would be<br />
expected, were found to be very unlikely, typically less than 1 chance in 100,000 per year and<br />
the associated societal risks fell within the ALARP region of this part of the Societal Risk<br />
Guideline; and<br />
> a region associated with extremely remote incidents but with potentially severe consequences<br />
including fatalities in the Chai Wan area under the worst conditions. At this low frequency/high<br />
consequence end of the societal risk spectrum, the calculations are uncertain and, as a result, the<br />
Consultants cannot guarantee that, at this conceptual stage, the three PHIs will be able to<br />
demonstrate compliance with the Guideline in this region should detailed proposals be put<br />
forward, particularly in respect of the Bulk Chemical Storage Facility.<br />
Due to the limited hazards associated with the fourth site, the Oil Terminal, the associated societal risks<br />
were well within the ALARP/acceptafale regions of the Societal Risk Guideline - particularly since no<br />
event was identified which could lead to ten or more fatalities.<br />
3.3.9 Key Findings<br />
Is Area 137 Suitable for PHIs<br />
There are no areas of significant residential population within 1 km of Area 137 and, as such, the risks<br />
associated with the proposed PHIs would be expected to be tolerable. In broad terms, this view was<br />
reinforced by the results of the risk assessment which generally comply with the Risk Guidelines adopted<br />
by the Hong Kong Government (through the CCPHI). As such, it is considered that Area 137 is a suitable<br />
site for the development of PHIs. Nevertheless, there remains a possibility that the Societal Risk<br />
Guideline will be exceeded in relation to extremely remote, but credible, events associated with marine<br />
incidents at, or close to, the jetties.<br />
APH Consultants Pag* 3-6
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
final Report - Main Report<br />
Restrictions on ihe Nature ofPHIs<br />
Apart from a BCSF, there is practical operational experience and associated risk assessments in Hong<br />
Kong of the PHIs considered. There is little to suggest either from this experience or from the results of<br />
this assessment that any restrictions should be placed upon the nature of the PHIs which could be located<br />
on Area 137.<br />
Nevertheless, there are three broad principles which apply to any PHI development:<br />
> quantities of hazardous materials to be stored (and handled) should be minimised;<br />
> practical measures should be taken to minimise both on and off site risks where practicable;<br />
> the development of a particular PHI would normally be subject to a further and more detailed risk<br />
assessment.<br />
Planning Controls<br />
As already indicated, within the scope of the work undertaken, the results suggest that no specific planning<br />
controls need to be exercised on risk grounds for areas outside Area 137. In other words, the presence<br />
of PHIs on Area 137 should not impose restrictions, on risk grounds, on the TKOIE and the SENT<br />
Landfill sites immediately to the north, nor would planning controls for the Chai Wan area be appropriate.<br />
Within Area 137, it would be prudent to limit the worker densities to those used as a basis for the<br />
analysis, namely 20/ha on the PHI sites, and 30/ha on other sites within Area 137.<br />
Finally, there is an annual festival at nearby Tai Miu Wan (Joss House Bay) which attracts thousands of<br />
visitors. Although the level of individual risk in this area will be minimal, the presence of so many people<br />
close to Area 137 introduces the remote possibility of a major multi-fatality accident. Given that the risks<br />
are dominated by incidents at the jetties, it is suggested that it would be prudent to suspend all jetty<br />
operations for the day.<br />
3.4 PREFERRED CONCEPT<br />
Additional detailed studies have been undertaken in the refinement and selection of the Preferred Planning<br />
Concept. These included:<br />
* planning issues;<br />
* wave modelling;<br />
> tidal flow and sUtation modelling;<br />
> water quality modelling;<br />
> air quality measurement;<br />
+ geotechnical and geophysical site investigation;<br />
> marine and navigational assessment study;<br />
> assessment of alternative quay structures;<br />
> dredging and reclamation issues;<br />
> traffic and transport issues.<br />
The planning research indicated interest in the site by the bulk chemical storage industry and the Hong<br />
Kong China Gas Company (HKCGC). The latter are currently undertaking a detailed study into future<br />
gas requirements in the Territory, the findings of which will be incorporated into their 5 year<br />
Development Plan. The HKCGC regard Area 137 as a potential site for a gas production facility.<br />
APH Consultants "" ' ~~ T ~TI<br />
Page 3-7
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
The interest in the site has been matched by an overwhelming concern expressed with regard to the likely<br />
site implementation schedule. The view has been repeatedly stressed that if Hong Kong is to remain<br />
competitive as a port then new deep water berthing and industrial facilities are urgently required. This<br />
is particularly the case with regard to the storage and distribution of chemicals which have a high value<br />
added component. Operators have stressed that if provision of such facilities is not implemented soon then<br />
they will divert investment elsewhere. In addition to timing considerations, a number of operators have<br />
cited the absence of a railway connection as being a constraint to successful implementation. It is more<br />
likely, however, that timing considerations will weigh more heavily than the provision of rail links to the<br />
site.<br />
A major influence on the planning and layout of the development resulted from the risk assessment and<br />
the findings were considered to be a pre-requisite to the further refinement of planning layouts for the site.<br />
Further, the basic planning premise was adopted that PHI layouts similar to those used in the risk<br />
assessment should be utilised to maintain the validity of the results and recommendations of the risk<br />
assessment study.<br />
The selected alternative Options B(i) and D were further developed as Options 1 and 2 respectively and<br />
were refined to incorporate the results of the additional studies outlined above. The refinement of options<br />
also incorporated the addition of a provisional road network together with the subdivision of the site into<br />
notional industrial lots. Both options incorporated worker densities of 20 persons per ha for PHI lots and<br />
30 persons per ha for DWI lots. In conformity with Government Planning Standards and to avoid<br />
exceedence of the recommended worker densities, it was recommended that the plot ratio applied to the<br />
site should not exceed 2.5.<br />
3.4.1 Option 1 (Figure 3.4)<br />
The detailed wave modelling and analysis revealed that the predominant residual swell direction is not<br />
parallel to the traffic separation fairways, as previously assumed, but in fact lies further to the west, thus<br />
negating the benefits of the initially proposed quay orientation. In addition, the setback in the quay wall<br />
was shown to introduce added complexity to the departure manoeuvre requiring good vessel and tug<br />
control to bring the vessel off the southern berth and swing it onto the required departure alignment. The<br />
setback was also shown to be undesirable in the event that a berthing manoeuvre needed to be aborted.<br />
Taking into account the results of both the wave modelling and marine study, the quay wall alignment was<br />
modified in order to provide a more desirable berthing layout, both improving navigational aspects and<br />
minimising downtime due to wave action. The principle of the straight line seawall was retained, with<br />
a small basin in the north, primarily for the provision of the SENT Landfill marine access.<br />
A possible extension of Road D6 through Area 137 providing future access to Joss House Bay was allowed<br />
for on the revised layout. Access to and within Area 137 was proposed via a spine road. It was<br />
envisaged that the road would access the site from a proposed roundabout located on Road D6 south of<br />
the SENT Landfill and extend southward through the project area. Secondary site access was provided<br />
off the spine road. An access road to the SENT Landfill was provided to the north of the site.<br />
The land use layout within the site was maintained in accordance with the findings of the risk assessment.<br />
This required that naphtha storage and gas production facilities are located at the south of the site with<br />
LPG bottling and storage, bulk chemical storage and fuel storage further north. Site configuration was<br />
governed to some extent by berthing requirements related to each of the PHI sites and to the spatial<br />
requirements of each operation to reduce industrial risks to a minimum. An emergency vehicle access<br />
(EVA) was provided to the PHI sites along the edge of the development. This area would also act as a<br />
drainage reserve behind the seawall to cater for overtopping drainage in extreme storm conditions. In all,<br />
some 50 ha net of land for PHI development was provided which accounted for almost 48% of the total<br />
available site area.<br />
APH Consultants Page 3-8
Figure 3.4<br />
TONG CHAU<br />
To Taaung Kwan O<br />
f<br />
SENT Landfill<br />
TKOIE<br />
SENT Landfill<br />
marine<br />
50m general<br />
working area<br />
Ciearwater Bay<br />
Country Park<br />
Qhemical storage<br />
Possible extension of 06<br />
to Joss House Say<br />
3*w«raa« Pumping<br />
Station<br />
27.3m EVA and<br />
no build area<br />
EVA reserve {7.3m<br />
LEGEND<br />
TIT CHAM<br />
CHAU<br />
Potentially hazardous installations<br />
:::;;::: 1 Deep water frontage industry<br />
PH.! related Industry<br />
Open space and Interfaca landscaping<br />
Services<br />
EVA i Emergency vehicle access<br />
OPTION 1 CONCEPTUAL LAYOUT<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
To complement PHI development, a number of sites were zoned for PHI related development. These were<br />
located east of the north-south spine road and accounted for about 4 ha or approximately 4.0% of the total<br />
land use budget.<br />
Some 28 ha of land was allocated to DWI development in the northern portion of the site. Marine access<br />
to these sites was provided via a General Working Area adjacent to the marginal quays. This included<br />
a 50 m reserve behind the quay for marine related and cargo working activities.<br />
Remaining land uses included roads and road reserves, a reservation for the SENT Landfill marine access<br />
and backup site, on-site services designated to include commercial retail provision and some 5 ha allocated<br />
to open space and interface landscaping reserves. Landscape buffers were maintained at the fringes of the<br />
site to preserve the integrity of the adjacent Country Park, Fat Tong Chau and Tit Cham Chau.<br />
The total site area comprised some 105 ha which provided adequately for the PHI and DWI development<br />
requirements identified. The land use budget for Option 1 is summarised below in Table 3.3.<br />
3.4.2 Option 2 (Figure 3.5)<br />
The results of the marine and wave studies outlined in Option 1 above dictated similar modifications to<br />
the quay wall alignment to give a more efficient berthing and land use layout. The outer berths were<br />
modified to provide a straight line quay wall along the same alignment as that of the Option 1, while<br />
retaining the basin protected by a finger pier.<br />
The road network for Option 2 comprised a centrally located reservation for Road D6 with the primary<br />
site access road looping around the east of the site. Access to the external road network was again from<br />
a roundabout on Road D6 at the south of the SENT Landfill. Secondary access within the site was<br />
provided, as in Option 1, off the main road.<br />
In order to maintain the site layout in accordance with the assumptions and results of the risk assessment,<br />
it was not possible to provide for all identified Pffls due to the limited land area available under the<br />
Option. Provision for a naphtha plant, LPG bottling and storage plant and a chemical storage facility were<br />
made in the southern portion of the site. An EVA and drainage reserve was again provided along the edge<br />
of the development.<br />
A total of some 31 ha, or 32% of total site, was provided for PHI development. DWI development<br />
accounted for 33 ha or 35% of total site area. PHI related sites (4.10 ha) were provided to the east of<br />
Road D6 reserve. A 50 m General Working Area was provided adjacent to the marginal quay walls. The<br />
greater area of marine related working space provided under this Option would prove advantageous if<br />
emphasis was placed on the provision of DWI industries.<br />
The total land area provided under Option 2 comprised some 95 ha. The land use budget for Option 2<br />
is summarised in Table 3.3 below.<br />
Each Option allowed for a phased development. Moreover, the initial phasing envisaged under both<br />
Options specifically did not preclude the realization of one or other Option at the full development stage.<br />
This flexibility would allow the development to be responsive to changing industrial demand.<br />
APH Consultants Page 3-9
Figure 3.5<br />
To Tseung Kwan 0<br />
SENT Landfill<br />
~ Reserve for<br />
| possible<br />
alignment of 06<br />
Clearwater Bay<br />
Country Park<br />
50m general<br />
working area<br />
Possible extension of D6<br />
to Joss House Bay<br />
LEGEND<br />
Potentially hazardous installations<br />
JnllSlJI Deep water frontage industry<br />
PHI related industry<br />
Open space and Jnterface landscaping<br />
Services<br />
27.3m HVA and<br />
no build area<br />
•V- '•"• *•"'.*•*."• *•"-.'•'V'. 4 - '•"•."•'•/• '.'•/••<br />
/>;. •.••.• *. •:» *.••,•'. •;* *. • \^z^s.<br />
EVA reserve (7.3m<br />
TIT CHAM<br />
CHAU<br />
£VA 1 Hniergency vehicle access<br />
OPTION 2 CONCEPTUAL LAYOUT<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 3.3 :<br />
LAND USE BUDGET BY OPTION<br />
LAND USE OPTION 1<br />
Area % of total<br />
PHI<br />
49.95<br />
47.6<br />
DWI<br />
2S.10<br />
26.8<br />
PHI Related Industry<br />
4.05<br />
3.9<br />
Open Space<br />
4.98<br />
4.7<br />
Services<br />
2.30<br />
2 2<br />
SENT Access<br />
2.25<br />
2.1<br />
General Working Area<br />
3.65<br />
3.5<br />
Roads & Road Reserves<br />
9.72<br />
9.3<br />
OPTION 2<br />
Area % of total<br />
30.80 32.4<br />
33.00 34.7<br />
4.10 4.3<br />
6.57 6.9<br />
1.60 1.7<br />
2.30 2.4<br />
7.10 7.5<br />
9.53 10.0<br />
105.00<br />
100<br />
95.00<br />
100<br />
3*4.3 Selection of Preferred Concept<br />
Option 1 and Option 2 were evaluated in terms of engineering and marine, land planning, traffic and<br />
transport and environmental criteria. In most respects, both options were found to be similar in provision<br />
of facilities and impacts of the development. The main difference between the two lay in their ability to<br />
meet industrial land demand.<br />
Option 1 provided adequately for identified PHI demand whereas Option 2 fell short of target spatial<br />
requirements. Conversely, Option 2 provided more DWI sites and would, therefore, be a more viable<br />
option if, over time, DWI site demand and requirement for greater cargo working areas were found to be<br />
stronger than is presently the case.<br />
Cost estimates were carried out for the two options for the construction of the reclamation, edge structures<br />
and roads, and the provision of services and drainage to the individual site entrances. The order of capital<br />
cost estimates were:<br />
Option 1<br />
Option 2<br />
HKS 2,067M<br />
HK$ 2,190M<br />
Through the process of optimisation of the layouts there had been a considerable convergence of the two<br />
Options, with effectively equivalent developments in the south. In the selection of the Preferred Concept,<br />
therefore, considerable weight was attached towards the balance of the split between DWI and PHI<br />
requirements. The land use demand surveys indicated a very positive interest in PHI development and<br />
related industries and it is considered that the balance should be directed towards these industries. Area<br />
137 is, possibly, one of the few remaining sites suitable for PHI development in Hong Kong whereas<br />
DWI, involving non-PHI activities, could be accommodated at alternative sites recently considered but<br />
found unsuitable for PHI.<br />
In terms of the full development, the preference must therefore lie with the greater provision for PHI<br />
activities. As such, Option I was recommended as the Preferred Concept, It has therefore been agreed<br />
that outline engineering design will be carried out for this concept with the proposed implementation based<br />
on a rolling programme of development with the PHI sites in the south developed first.<br />
APH Consultants Page 3-10
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
SECTION 4<br />
LAND USE PLANNING<br />
4,1 DETAILED PLANNING LAYOUTS<br />
The planning process outlined in the foregoing Sections has involved the progressive refinement of initial<br />
planning concepts into more detailed planning layouts. This Section concludes the land use planning<br />
process with the presentation of the Recommended Development Layout.<br />
The size and configuration of the site required the preparation of three layout plans at the prescribed scale<br />
of 1:1000 to adequately cover the entire planning area as presented in the accompanying Drawings. The<br />
Written Statements are included as Appendix B. Figure 4.1 provides an overall presentation of the<br />
proposed land uses.<br />
Accompanying the land use proposals is a Landscape Master Plan at scale 1:2500 which depicts landscape<br />
proposals for the site. Details of the landscaping measures proposed are provided within this Section and<br />
within the Written Statements for each of the planning layouts.<br />
The Recommended Development Layout encompasses new information which has become available since<br />
the submission of the Preferred Concept Report and the refinements to the layout in response to comments<br />
received from Government Departments. The proposed road network has been revised to accord with<br />
planning intentions for the area. Road alignments, radii and widths fully accord with current highway<br />
standards. Infrastructural provision has now been extensively revised to accommodate current planning<br />
proposals, Storm water culvert alignments have been shown where they exert an influence or constraint<br />
on proposed land use or landscaping measures. Finally, berthing arrangements and site configurations<br />
have been jointly refined to ensure that an efficient marine to land use relationship is achieved.<br />
4.2 PHI AND Pffl RELATED DEVELOPMENT<br />
Four sites comprising a total area of 41.37 ha have been specifically reserved for PHI development and<br />
are zoned Industry Group B (I(B)) and Industry Group C (I(C)). Three sites adjacent to the Clearwater<br />
Bay Peninsula have been reserved for PHI related industrial activities. Spatial provision and allocation<br />
per site has been determined with reference to the findings of the previous land planning studies, ongoing<br />
contacts with interested operators and with particular cognisance of the findings of the risk assessment.<br />
Nevertheless, lot boundaries have been indicated with a broken line to provide flexibility and to allow for<br />
any alteration in spatial requirements related to specific sites.<br />
Site 1, comprising a total area of 10.95 ha and zoned I(B), has been allocated for gas production purposes.<br />
In conformity with the HKPSG a minimum building setback of 6.0 m has been applied to the northern<br />
boundary of the site. A 15.0 m setback has been proposed along the eastern boundary adjacent to Road<br />
Rl in order to effectively set development well back from a public thoroughfare. Along the southern and<br />
western boundaries there is a 20 m Emergency Vehicle Access (EVA) and seawall maintenance reserve.<br />
A plot ratio of 1.25 is suggested for the site which produces 4 Gross Floor Area (GFA) amounting to<br />
136,900 nr. In accordance with the findings of the risk assessment worker density has been fixed at 20<br />
workers per ha. This density produces a total site workforce of 219 workers.<br />
A dolphin berth suitable for the offloading of naphtha to the proposed gas production plant has been<br />
provided adjacent to the seawall. The design of the berth is sufficient to accommodate classes of vessels<br />
which are likely to off-load at the gas production facility. It is envisaged that no major structure, except<br />
APH Consultants Page 4~l
Figure 4.1<br />
OEARWATER 3AY<br />
COUNTRY PARK<br />
TATHONO CHANNEL<br />
LEGEND;<br />
Potentially hazardous installation<br />
0««p waterfront industry<br />
TA1 UU! WAN<br />
PHI related industry<br />
Open 3pac« and interface landscaping<br />
Services<br />
TSEUNG KWAN 0 AREA 137<br />
RECOMMENDED PLANNING LAYOUT<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
for stacks or flues, will be constructed to height exceeding 30 m. The positioning, design, and massing<br />
of the required stacks and flues should be subject to a visual and environmental assessment when firm<br />
development proposals are known.<br />
Site 2 has been allocated to an LPG storage and bottling facility and comprises a total of 9.61 ha, zoned<br />
I(C). A plot ratio of 1.25 is recommended which produces a GFA amounting to 120,100 m 2 . Berthing<br />
arrangements of this and adjacent sites along the seawall have determined the H L" shaped site<br />
configuration.<br />
Worker density on the site is recommended not to exceed 20 workers per ha. This density results in a<br />
total estimated site workforce of 192 persons. A 6.0 m setback is maintained along the northern and<br />
southern boundaries for emergency and fire fighting purposes. A 15.0 m setback reserve is proposed<br />
adjacent to Road Rl. Access to the site will be achieved via two access points from Road Rl located at<br />
the eastern boundary of the site.<br />
As for Site 1, the height of development should not exceed 30.0 m. Stacks and flues may be permitted<br />
in exceedence of this height subject to an appropriate visual and environmental study. A jetty berth has<br />
been provided for the importation of LPG.<br />
Site 3 has an "L" shaped configuration with a site area of 10.72 ha and is zoned I(C). The site is<br />
proposed for chemical storage purposes. Two dolphin berths will be required for the bulk import of<br />
chemicals and transhipment to regional markets. A plot ratio of 1.25 is suggested for the site which<br />
produces an estimated GFA amounting to 134,000 m 2 . Worker density will be restricted to 20 workers<br />
per ha producing a maximum on-site workforce of 214. Height restrictions and conditions appertaining<br />
to flues and stacks will apply to the site development as for Sites 1 and 2.<br />
Site 4, with a total site area of 10,09 ha, zoned I(C), is reserved for the bulk storage of oil and petroleum<br />
products. Again a plot ratio of 1.25 is suggested resulting in a GFA amounting to 126,100 m 2 . A<br />
building setback of 6,0 m is proposed adjacent to the northern and southern boundaries of the site while<br />
a 15.0 m setback is recommended adjacent to Road Rl. Conditions regarding height, massing, and the<br />
installation of flues and stacks should be applied as above.<br />
A 20 m EVA and seawall maintenance reserve is proposed to the west of the PHI sites adjacent to the<br />
seawall and is included within the curtilage of the adjacent lots. The EVA will require to be kept clear<br />
at all times to allow for the passage of emergency vehicles.<br />
The Study has identified a likely requirement for industrial sites with a direct product relationship to the<br />
PHI sites, for operations such as high value added (HVA) chemical processing. There is a potential<br />
demand for three sites for such purposes with a spatial allocation of around 3.0 ha per site. Three sites<br />
zoned I(B) have been reserved for PHI related industries to the east of the PHI sites. However, due to<br />
planning and site layout constraints, only 7.18 ha has been allocated to the PHI related industrial activities.<br />
From the recommendations of the risk assessment, worker density in the PHI related sites is 30 workers<br />
per ha. This results in a total worker density for the three sites estimated at 193 workers. Reduced risk<br />
operations which are likely to be undertaken on these sites allows for the application of a higher plot ratio.<br />
A plot ratio of 2,5 is. therefore, recommended which produces a total GFA across the three sites<br />
amounting to 179,500 m 2 . Building height will be restricted to 30 m and applications for stacks or flues<br />
exceeding this limitation should be considered on a site by site basis and with regard to visual and<br />
aesthetic considerations. On a broad basis, given the interface with the adjacent Country Park, it is not<br />
generally recommended that the 30.0 m height restriction be breached.<br />
It is proposed that a 10.0 m building setback be applied to each site adjacent to the Road R2/D6 reserve,<br />
a 6.0 m setback on the northern and southern boundaries and a 15,0 m setback on the boundaries abutting<br />
APR Consultants Page 4-2
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
Road Rl. This will ensure adequate access in the event of an emergency, secure the safe disposition of<br />
buildings and allow for a desirable blocking and massing of buildings. All loading and unloading of<br />
vehicles will be undertaken within the curtilage of each site and appropriate provision should be made in<br />
this regard. Similarly, parking provision in conformity to the HKPSG should be made on each site. No<br />
parking or loading and off-loading operations should be permitted on estate roads. No access to any lot<br />
shall be permitted from Road R2.<br />
To ensure that the development and layout of buildings and storage facilities on PHI sites satisfies current<br />
practices and standards, the operators should make an appropriate submission to CCPHI and comply with<br />
the requirements of EPD Advice Note 2/92 with regard to the presentation of on-site environmental<br />
safeguards which will be applied to each site. An application to the Town Planning Board may also be<br />
required. It is suggested, however, that a means be found to expedite the application process in order to<br />
avoid discouragement of investors.<br />
4.3 DWI DEVELOPMENT<br />
A total of 22 sites have been allocated to DWI development. In broad conformity with the provisions of<br />
the HKPSG, 20% of the sites have been zoned for I(C) purposes and the balance allocated to I(B) purposes<br />
which accords with the intentions of the OOP. By definition DWI development comprises industrial or<br />
warehousing operations which, by virtue of their nature require access to deep water berths. Activities<br />
which cannot prove such a requirement will be precluded from the DWI lots. Operators who have shown<br />
an interest in this regard include the bulk heavy oil storage and packing industry, the break bulk chemical<br />
industry and the concrete batching and prefabrication industry. Other activities which could be allowed<br />
would include dangerous goods godowns. Government is currently seeking the removal of such facilities<br />
from the existing urban areas and the provision of alternative sites would aid the realisation of this<br />
objective. Site boundaries have been indicated with broken lines to render the plan flexible and to provide<br />
for further consolidation or subdivision of lots.<br />
Because of risk and visual considerations the density of development in DWI areas has been limited. A<br />
mean lot size of 1 ha has been assumed. Nevertheless, this would not preclude the subdivision or<br />
consolidation of lots in relation to demand where this is physically practicable. A plot ratio of 2.5 is<br />
suggested which results in a total GFA for the 22 sites amounting to 557,300 nor. In accordance with the<br />
findings of the risk assessment worker density has been maintained at 30 workers per Ha. This results<br />
in a total projected DWI workforce amounting to 668 workers. Building height in DWI areas will be<br />
restricted to 30 m in order to limit visual impacts and to maintain the backdrop and integrity of the<br />
Country Park.<br />
Proposed access points to each site are indicated in the detailed layout plans. No access to DWI sites will<br />
be obtained from Road D6 or Road R2/D6 reserve. The SENT Landfill operation requires a private road<br />
for access to the barge berth which precludes use of this road for the Area 137 development. This reduces<br />
the planning efficiency of the DWI sites. Should this limitation be removed, it is recommended that<br />
affected lots be replanned to form more efficient configurations.<br />
A 9.1 m EVA access is provided to the rear of lots 12 to 16. Elsewhere, emergency access on more than<br />
one side of each lot can be obtained via public roads or cargo working areas. Access arrangements would<br />
have to be reviewed if several lots are consolidated. A 9.1 m EVA reserve should will be established<br />
along the working area fronting lots 25 to 30 to ensure through passage for emergency vehicles in the<br />
event of an incident. To aid emergency access and to produce a satisfactory arrangement of buildings on<br />
site, building setbacks have been proposed. These comprise a 6.0 m setback around the lots except at the<br />
sides where one lot abuts another, where a 4.5 m setback should be applied.<br />
APH Consultants<br />
page
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
A 50 m marine working area has been provided to service all DWI lots. It is not intended that there<br />
should be any exclusivity of use or access. Lots 25 to 30 inclusive which front the working area have,<br />
however, an advantageous location when compared to other DWI lots. It is suggested that this<br />
consideration is reflected in the premium levied on these sites.<br />
Although no firm commitment has been expressed with regard to DWI take up, the general view among<br />
operators is that, as deep water moorings are at such a premium in Hong Kong, DWI sites in Tseung<br />
Kwan O would be well received by the market.<br />
4.4 SUPPORTING DEVELOPMENT AND FACILITIES<br />
Road RIO provides access to the SENT Landfill marine access facility and working area. A marginal<br />
quay of 250 m has been reserved for SENT Landfill use with a 50 m working area provided to the rear<br />
of the quaywaiL Once SENT Landfill operations are complete, the site could be handed over to another<br />
user for industrial development.<br />
Site 8 has been reserved for service and recreational facilities. The HKPSG requires the allocation of<br />
0.5m 2 of open space per industrial worker (5 ha per 10,000 svorkers). As this standard would only<br />
produce nominal open space, additional recreational facilities have been provided given the relatively<br />
isolated location of Area 137. Details of open space facilities are given in Section 4.6 below. Site 8 will<br />
also provide for offices and small scale commercial premises. It is not, however, anticipated that these<br />
will need to be large scale facilities and only two to three storey structures should be permitted.<br />
Two sewage pumping stations are provided on the site. A 225 m 2 reserve is provided adjacent to Site 3<br />
to accommodate the full development of Area 137 and a 100 nr site reserve is provided adjacent to Road<br />
RIO for a temporary pumping station for the SENT Landfill marine facility. A 2,400 m : reserve has been<br />
provided in the southern portion of the site for an electrical sub-station.<br />
Several storm water culverts dissect the planning area. Drainage reserves are demarcated on the planning<br />
layout plans. No development or hard planting will be permitted on or over these reserves.<br />
Areas on the periphery of the site have been maintained as buffer areas. The treatment of these areas and<br />
roadside planting measures are described in Section 4.6 which describes the landscape master plan.<br />
Table 4.1, overleaf, provides a breakdown of development and land use by site. The site numbers used<br />
in the Table correspond to the site numbers depicted in Figure 4.1.<br />
4.5 PROVISION OF BERTHING FACILITIES<br />
Some 1000 m of deepwater frontage has been provided for the PHI sites. The berths as indicated in<br />
Figure 4.1 should be regarded as indicative, based on potential user requirements. These may be modified<br />
with regard to ultimate user requirements.<br />
Multi-user marginal quays have been provided to serve the PHI related and DWI sites. These consist of<br />
200 m of aeepwater outer marginal quay wall and 800 m of basin marginal quay wall (including SENT<br />
Landfill access berths).<br />
The outer deepwater berths will be dredged to -14 mPD, while the basin will be dredged to -10 rnPD.<br />
APH Consultants Page 4-4
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 4.1 :<br />
AREA 137 LAND USE, GROSS FLOOR AREA & WORKER<br />
DENSITY BY SITE<br />
SITE No.<br />
LAND USE<br />
SITE AREA<br />
(ha)<br />
PLOT<br />
RATIO<br />
GFA<br />
(m : )<br />
No.<br />
WORKERS<br />
1<br />
PHI (gas)<br />
10.95<br />
1.25<br />
136900<br />
219<br />
2<br />
PHI (LPG)<br />
9.61<br />
1.25<br />
120100<br />
192<br />
3<br />
PHI (chem)<br />
10.72<br />
1.25<br />
134000<br />
214<br />
4<br />
PHI (oil)<br />
10.09<br />
1.25<br />
126100<br />
202<br />
Sub Total<br />
41.37<br />
517100<br />
827<br />
5<br />
PHI related<br />
2.82<br />
2.5<br />
70500<br />
85<br />
6<br />
PHI related<br />
2.10<br />
2.5<br />
52500<br />
63<br />
7<br />
PHI related<br />
2.26<br />
2.5<br />
56500<br />
45<br />
Sub Total<br />
7.18<br />
179500<br />
193<br />
8<br />
Services<br />
1.00<br />
9<br />
DWI<br />
0.93<br />
2.5<br />
23300<br />
28<br />
10<br />
DWI<br />
0.75<br />
2.5<br />
18800<br />
22<br />
11<br />
DWI<br />
1.70<br />
2.5<br />
42500<br />
51<br />
12<br />
DWI<br />
0.60<br />
2.5<br />
15000<br />
18<br />
13<br />
DWI<br />
0.45<br />
2.5<br />
11300<br />
13<br />
14<br />
DWI<br />
0.50<br />
2.5<br />
12500<br />
15<br />
15<br />
DWI<br />
0.48<br />
2.5<br />
12000<br />
14<br />
16<br />
DWI<br />
0.44<br />
2.5<br />
11000<br />
13<br />
17<br />
DWI<br />
0.70<br />
2.5<br />
17500<br />
21<br />
18<br />
19<br />
DWI<br />
DWI<br />
0.82<br />
0.93<br />
2.5<br />
2.5<br />
20500<br />
23300<br />
25<br />
28<br />
20<br />
21<br />
T><br />
23<br />
24<br />
25<br />
26<br />
27<br />
23<br />
29<br />
30<br />
Sub Total<br />
DWI<br />
DWI<br />
DWI<br />
DWI<br />
DWI<br />
DWI<br />
DWI<br />
DWI<br />
DWI<br />
DWI<br />
DWI<br />
1.36<br />
1.57<br />
1.13<br />
1.05<br />
0,71<br />
0.57<br />
1.05<br />
LOO<br />
1.01<br />
2.32<br />
1 T><br />
22 ^9<br />
2.5<br />
2.5<br />
2.5<br />
2.5<br />
2.5<br />
2.5<br />
2.5<br />
2.5<br />
2.5<br />
2.5<br />
2.5<br />
34000<br />
39300<br />
28300<br />
26300<br />
17800<br />
14300<br />
26300<br />
25000<br />
25300<br />
58000<br />
55500<br />
557800<br />
41<br />
47<br />
34<br />
31<br />
21<br />
17<br />
32<br />
30<br />
30<br />
70<br />
67<br />
668<br />
Page 4-5
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
TABLE 4.1 (CONTINUED)<br />
SITE No.<br />
LAND USE<br />
31 FatTongChau<br />
Buffer (a)<br />
32 Fat Tong Chau<br />
Buffer (b)<br />
33 Tit Cham Chau<br />
Buffer t- EVA<br />
34 Clearwater Buffer<br />
Sub Total<br />
35 SPS<br />
38 SENT Working<br />
Area<br />
39 DWI Working<br />
Area -r EVA<br />
36 SPS<br />
37 ESS<br />
Sub Total<br />
Road and Footpaths<br />
SITE AREA PLOT GFA No.<br />
(ha) RATIO (or) WORKERS<br />
0.89<br />
2.12<br />
1.41<br />
4.18<br />
8.60<br />
0.01<br />
1.25<br />
3.58<br />
0.02<br />
0.24<br />
5.10<br />
16.24<br />
Total<br />
101.78 1254400 1688<br />
4,6 LANDSCAPING<br />
4,6.1 Introduction<br />
The landscape proposals are illustrated in the Landscape Master Plan contained in the Drawings document.<br />
The primary aims of the landscape proposals are:<br />
* to ameliorate the assessed visual impact of the industrial development views from Rennies Mill<br />
and Hong Kong Island to the west and from the Clearwater Bay Country Park to the east;<br />
> to create an appropriate landscape setting for the development within the context of the<br />
surrounding coastal landscape;<br />
+ to enhance the quality of the environment within the development itself,<br />
The landscape proposals seek to fulfil these aims through a comprehensive framework of woodland<br />
structure planting. Larger blocks of woodland around the perimeter of the site and along the new<br />
waterfront will help to provide a buffer screen at ground level and to tie into the pockets of existing<br />
vegetation on adjacent hill slopes. Planting strips along individual lot boundaries and along road corridors<br />
will help break up the visual extent of the development and create a more attractive setting within.<br />
APH Consultants Page 4-6
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
No specific landscape treatment has been indicated within the lots as this will be developed, as<br />
appropriate, within the detailed design of the individual plots.<br />
4.6.2 Landscape Framework<br />
Structure Planting<br />
The structure planting will be composed of broad swathes of woodland type planting, using tree and shrub<br />
species that will be tolerant of the anticipated exposed conditions, high air borne pollution levels and low<br />
maintenance regimes.<br />
Perimeter Planting<br />
The planting around the site perimeter will flank the development and act as an interface between it and<br />
Clearwater Bay Country Park, Tit Cham Chau and Fat Tong Chau. The planting can be used as a visual<br />
extension of the country park, thus avoiding the abrupt change from countryside to industry, by extending<br />
fingers of vegetation into the development. The integrity of the islands can be maintained by using planting<br />
to reinforce the existing vegetation.<br />
Along the waterfront zones, intermittent planting will be used to break up the impact of the industrial<br />
buildings from the distant views across the bay. This will help to create a gradual transition from the sea<br />
to the backdrop of the hills.<br />
Internal Planting<br />
Within the body of the site, the internal structure planting will be implemented along landscape belts<br />
between the major access roads and industrial plots. These "fingers" of vegetation will be important in<br />
maintaining visual and physical connections with the scenic backdrop of the hills of Clearwater Bay<br />
Peninsula to the east, Fat Tong Chau to the north and Tit Cham Chau to the south.<br />
The planting will also act as an extension of the perimeter structure planting, breaking up the scale of the<br />
development and reducing the effects of abrupt changes in land use. The planting will be similar in<br />
composition to the external structure planting but will include some less proven species to increase the<br />
options to create more interest and identity at the detailed design stage.<br />
The landscape belts will also give some opportunity to introduce low mounding into the development,<br />
which will contribute towards ameliorating visual conflict between adjacent land uses.<br />
Roadside Planting<br />
The road network has a strong influence on the physical structure of the development and the landscape<br />
treatment will play an important role in creating a "green" framework for the development. The physical<br />
quality of the road system will, to an extent, dictate the quality of the environment within the<br />
development. Typical examples of roadside planting are shown in Figure 4.2.<br />
Tree and shrub planting is proposed along all the major access roads within the site. The planting will<br />
be used to define route ways as well as acting as visual barriers. Tree planting along the roads wiE<br />
provide shade to pedestrians and reduce glare from hard surfaces. It will help to provide visual relief<br />
from the extent of the roads and the adjacent industry.<br />
Trees and shrubs will be planted at ground level alongside the road with a high kerb to act as a physical<br />
barrier to deter casual parking and to protect the planting from splash back. A minimum width of 2.0 in<br />
service free zone will be allowed for the planters to enable uninterrupted root development.<br />
APH Consultants
Figure 4.2<br />
FOOTPATH<br />
PRIMARY<br />
STRUCTURE ORNAMENTAL<br />
ROADSIDE<br />
EXISTING HILLSIDE A VEGETATION , PLANTING SHRUBS |<br />
PLANTER<br />
t ACCESS ROAD<br />
VARIES 3M 2.SM<br />
GROUND COVER<br />
ORNAMEHTA1 SHRUBS<br />
ORNAMENTAL SHRUBS<br />
ROADSIDE TREE<br />
DEEP WATEH INDUSTRY<br />
FOOTPATH<br />
WTEBFACEZONE<br />
SECONDARY STRUCTURE PLANTING<br />
ROADSIDE<br />
PLANTER<br />
1 I<br />
i SM 3M ' 2.5M<br />
TYPICAL LANDSCAPE PLANTING<br />
APH CONSULTANTS
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
A number of more ornamental tree and shrub species have been included in the list to allow the planting<br />
design to be accentuated in the open space area and at traffic islands and roundabouts,<br />
Plant Speties<br />
Table 4.2 lists suggested plant species for the woodland structure planting, roadside planting, open space<br />
and roundabout areas. The use of individual species will be determined at the detailed design stage.<br />
All plant species have been chosen on the basis of being tolerant of the expected site climatic and substrate<br />
conditions and the anticipated low maintenance regimes.<br />
TABLE 4.2 :<br />
SUGGESTED SPECIES FOR LANDSCAPE PLANTING<br />
Location Trees Shrubs<br />
Structure Planting<br />
Acacia auricuiiformis<br />
A confusa<br />
Castanopsis fissa<br />
Eucalyptus torelliana<br />
Ficus microcarpa<br />
Hibiscus tiliaceus<br />
Litsea glutinosa<br />
Litsea raonopetala<br />
Leucanea leucaccphala<br />
Macaranga tanarius<br />
Melaleuca leucadendron<br />
Tristania conferta<br />
Duranta repens<br />
Gordonia axillaris<br />
Hibiscus schizopetalus<br />
Jasminum mesnyi<br />
Callistemon rigidus<br />
Pittosporum revoiutum<br />
Tamarix chinensis<br />
Roadside Planting and Amenity<br />
Planting<br />
Aleurites moluccana<br />
Casuarina equisetifolia<br />
Cinnamonum camphora<br />
Dracontomelon dao<br />
Erythrina crista-galli<br />
Eucalyptus citriadora<br />
Grevillea banksii<br />
Melia azedarach<br />
Pongamia pinnata<br />
Reevesia thrysoidea<br />
Thespesia populunea<br />
Schefflera octophyila<br />
Stercuiia lanceolata<br />
Rhododendron spp<br />
Gardenia jasminoides<br />
Ficus microcarpa "Golden Lear<br />
Schefflera arboricola<br />
Hamelia patens<br />
Lagerstroemia speciosa<br />
Rosa multiflora<br />
Parthenocissus himalayana<br />
Livistonia chinensis<br />
APH Consultants<br />
Page 4-8
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
SECTION 5<br />
ENGINEERING STUDIES<br />
5.1 ENGINEERING INVESTIGATIONS<br />
5.1.1 Introduction<br />
Site investigations and mathematical modelling have been carried out to establish the engineering and<br />
marine parameters needed for the planning and outline design of the development. These include:<br />
> Geophysical and geotechnical site surveys<br />
> Wave modelling<br />
> Tidal flow modelling<br />
+ Siltation modelling<br />
5.1.2 Geotechnical Data<br />
A geophysical survey was carried out in June 1992, from which the contoured seabed levels and contoured<br />
levels of the underlying soil strata, together with isopaches of dumped material, have been obtained. A<br />
borehole survey was completed in July 1992 which provided a visual identification of the soil strata<br />
supported by in-situ and laboratory tests.<br />
An assessment of the site investigation data indicates the general lithological sequence from the seabed as<br />
being fill (previously dumped material), manne deposits, alluvium, completely decomposed volcanic tuff<br />
and bedrock of moderately to slightly decomposed tuff. The following levels and thicknesses can be<br />
expected:<br />
Seabed level<br />
Fill (dumped material):<br />
Marine Deposits<br />
Alluvium<br />
Rock<br />
generally -3 mPD to -12 mPD, with high seabed levels occurring<br />
towards the north of the site in the dumping ground area.<br />
fill of unknown sources occurs over a large area of the northern site, up<br />
to 10 m thick and comprising poorly sorted clayey silt, sand, gravel and<br />
cobbles.<br />
generally 11 m to 15 rn thick, reducing to zero at the edges of the site<br />
where the bedrock nses to the adjacent peninsula and island cliffs. The<br />
marine deposits are classified as slightly sandy clayey silt. The base of<br />
the marine deposits is at approximately -26 mPD.<br />
17 to 30 m thick, generally 26 m thick over the western half of the site,<br />
reducing to zero towards the eastern (peninsula) edge and along the<br />
northern and southern (island) edges. The alluvium is classified as a<br />
sandy very clayey silt.<br />
the bedrock comprises a moderately to slightly decomposed volcanic tuff<br />
at levels -55 mPD to -60 mPD along the western edge (berthing line) of<br />
the site, rising towards the eastern, northern and southern cliff edges of<br />
the site. Overlying the bedrock is a layer of highly decomposed<br />
volcanic tuff, varying in thickness between 1 m and 8 m but generally<br />
about 3 m to 4 m thick.<br />
APH Consultants<br />
Page
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Typical geological cross-sections through the site and borehole locations are shown in Figures 5.1 and 5,2.<br />
The geophysical survey included a localised, close-spaced seismic survey giving full coverage over an area<br />
of the dumped fill material. While there was some evidence of magnetic anomalies in this layer, the<br />
survey revealed no evidence of obstructions. Although this is not conclusive evidence that the entire site<br />
is free of obstructions in the fill layer, it would appear unlikely that operations such as the installation of<br />
wick drains will prove problematical.<br />
It should be noted that only a limited borehole investigation has been carried out for this Study and<br />
further, more detailed site investigation will be required for the detailed design stage of the development.<br />
5.1.3 Tidal Flow Modelling<br />
Modelling Computations<br />
Tidal flow simulations have been performed for the dry season with the well mixed water condition and<br />
for the wet season with the stratified condition. Only spring tides have been considered, as it is adjudged<br />
that these tides will produce the highest and most critical flow conditions. The simulations were<br />
performed with a 100 m grid model of the Study Area and were carried out for the following cases:<br />
* the baseline condition, without any development in Area 137 but including all planned and<br />
committed projects in the model's area of influence (included in all subsequent development<br />
simulations);<br />
* the Area 137 development;<br />
* Area 137 and the proposed Area 131 developments;<br />
> an initial development in the south of Area 137;<br />
> an initial development of Area 137, with the proposed Area 131 development.<br />
Flow Modelling Results<br />
Figures 5.3 to 5.5 detail the vector plots for the dry season peak tidal currents in the upper layer for the<br />
baseline condition, for the Area 137 development and Area 131 development,<br />
A detailed assessment of the changes in the flow condition between the baseline and the development<br />
scenarios has been derived by analysis of the current velocity time histories. The assessment analysed<br />
changes in flow conditions at Lei Yue Mun, within Tseung Kwan O, in the Tathong Channel opposite<br />
Area 137, at the fishculture zone to the north of Tung Lung Chau and in the south Tathong Channel.<br />
GeneraEy, the Area 137 development will have little if any effect on the overall tidal flow conditions in<br />
the area. An initial development in the south of Area 137 would have virtually the same effect on the flow<br />
conditions as the full development.<br />
The main effect of the Area 131 development is on the flow conditions inside Tseun* Kwan O. Whilst<br />
resulting in lower velocities at the entrance to the bay, the configuration of the breakwater results in the<br />
diversion of flow deeper into the northern areas of the bay.<br />
5,1*4 SHtation Modelling<br />
SUtation simulations have been performed by means of a 250 m grid mud flow model The cases<br />
considered are the same as those simulated with the tidal flow model. As siltation occurs mainly during<br />
the wet season and changes in siltation will be largest with spring tides, the simulations have been carried<br />
out for these conditions. Ills approach is considered sufficient to determine the -eneral impact oa<br />
siltation of the development of Area 137. *<br />
APH Consultants "~ — TT<br />
Page >2
Figure 5.3<br />
SPRING TIDE<br />
Peak abb currants<br />
SPRING TIDE<br />
0 !<br />
Peak flood currants<br />
DRY SEASON PEAK TIDAL CURRENTS<br />
BASELINE CONDITION<br />
APH CONSULTANTS
Figure 5.4<br />
SPAING TIDE<br />
Peak abb currants<br />
SPRING TIDE<br />
Peak Hood currants<br />
DRY SEASON PEAK TIDAL CURRENTS<br />
WITH AREA 137<br />
253 APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
The results show low suspended sediment concentrations in the Study Area. At the modelled output<br />
stations the concentrations in the upper layer are generally less than 5 ppm. The same applies to the lower<br />
layer with the exception of the mid-Tathong Channel where the concentration increases to 8 ppm during<br />
peak flood conditions and the south Tathong Channel where the concentration is about 10 ppm during the<br />
full tidal cycle. Changes in the concentration with all the development scenarios compared to the baseline<br />
are very small.<br />
With all the modelled cases, the suspended sediment concentrations are very low by most estuarine<br />
standards. Because of this limited natural sediment supply, siltation rates in the area susceptible to<br />
deposition of fine sediments will be low, which is confirmed by the simulation results. Figure 5.6<br />
presents the mud deposition contour plot for the baseline simulation. As the Figure indicates, in most of<br />
the Tseung Kwan O area the deposition rate is in the range of 0.0 to 0.05 kg/nr per tide. This rate<br />
corresponds to a siltation in the order of 1 cm per year. In the area northwest and south of Tung Lung<br />
Chau the deposition rate is 0.05 to 0.10 kg/m 2 per tide, corresponding to a siltation in the order of 2.5<br />
cm per year.<br />
The mud deposition contour plot for the case with Area 137 development is presented in Figure 5.7.<br />
Compared to the baseline, there is a limited increase of deposition rate west of Tung Lung Chau and a<br />
decrease of the deposition rate in the area west of Area 137. These changes are relatively small, the more<br />
so in view of the generally very low deposition rates in the area. The cases with an initial development<br />
and with Area 131 showed almost identical deposition rate patterns as above.<br />
It is therefore concluded that the Area 137 and Area 131 developments will have a very limited impact<br />
on sediment movement and siltation. In the overall area the changes in siltation rate will be effectively<br />
negligible.<br />
5.1.5 Wave Modelling<br />
Mean. Annual Wave Climate Analysis<br />
The offshore mean annual wave climate is based on VOS data for the area off Hong Kong covering the<br />
period from 1949 to 1991.<br />
When propagating from deep water to Area 137, the wave heights will reduce, mainly by refraction and<br />
the sheltering effects of the offshore islands and headlands. Other phenomena which will affect the wave<br />
height are dissipation by bottom friction and wave generation by wind.<br />
The refraction and the sheltering effects have been established by means of the OUTDJF model. Results<br />
from the computations were obtained for locations adjacent to the Area 137 quay wall. Effects of bottom<br />
friction on the wave height have been established by means of the ENDEC wave model. Computations<br />
were performed for inshore wave heights from Hs=0.5 up to 4 m. The bottom friction effects were found<br />
to be small as the water depth in the Tathong Channel is relatively deep in relation to the mean annual<br />
waves. Wave generation by wind was analysed by means of the JONRAY model.<br />
By use of the results of the OUTDDF, ENDEC and JONRAY modelling the offshore mean annual wave<br />
climate was transformed to the local wave climate adjacent to the Area 137 quay wall as given in Table<br />
5J. Wave directions will range between 160 and 195 degrees N. The local generated wave climate at<br />
Area 137, based on the wind climate and the results of the JONRAY computations is presented in the<br />
Table 5.2. Periods of the local generated waves will be less than 5.0 s.<br />
APH Consultants<br />
fagg
Figure 5.6<br />
HO<br />
Tung Lung j —<br />
oo<br />
0.00 to 0.05 !cg/m**2 / el da<br />
-/o o o ao o<br />
0.05 to 0,10 kg/m**2 /<br />
00<br />
OO<br />
O O<br />
O O 0-15 to 0.20 kg/m**2 /<br />
aa<br />
a<br />
0-20 to 0.25 kg/m^2 / tide<br />
O O 0 O O<br />
00-^0000^0<br />
oooooooooo<br />
oooooooo<br />
MUD DEPOSITION CONTOUR PLOT<br />
BASELINE CONDITION<br />
APH CONSULTANTS
Figure 5.7<br />
< 0.00 kg/n»**2 / tld*<br />
0,00 kg/»**2 /tide<br />
0,00 to 0.05 kg/»**2 / eld»<br />
0,05 to O.JO kg/m**2 / crd«<br />
0.10 to 0.15 Seg/flM>*2 / tick<br />
0,15 to 0.20 kg/»**2 / trd-<br />
0*20 to 0.25 kg/m**2 / tfd«<br />
> 0.25 kg/»**2 / «ld«<br />
00000<br />
^OOOO<br />
O<br />
MUD DEPOSITION CONTOUR PLOT<br />
WITH AREA 137<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 5.1 : MEAN ANNUAL WAVE CLIMATE AT AREA 137<br />
Exceedence of wave height in percentage of time<br />
Hs(m)<br />
0.10<br />
0.20<br />
0.30<br />
0.40<br />
Tp>0s<br />
29.80<br />
21.42<br />
14.71<br />
8.48<br />
Tp>5s<br />
15.92<br />
12.92<br />
962<br />
5.95<br />
Tp>7s<br />
5.83<br />
5.04<br />
4.13<br />
3.06<br />
Tp>9$<br />
1.64<br />
1.49<br />
1.28<br />
1.06<br />
Tp>13s<br />
0.22<br />
0.18<br />
0.13<br />
0.10<br />
0.50<br />
5.62<br />
4.24<br />
2.21<br />
0.74<br />
0.08<br />
0.60<br />
3.64<br />
2.87<br />
1.60<br />
0.58<br />
0.07<br />
0.70<br />
1.82<br />
1.50<br />
0.99<br />
0.40<br />
0.06<br />
O.SO<br />
1.37<br />
1.08<br />
0.82<br />
0.31<br />
0.03<br />
0.90<br />
0.83<br />
0.71<br />
0.51<br />
0.21<br />
0.03<br />
1.00<br />
0.63<br />
0.55<br />
0.42<br />
0.16<br />
0.03<br />
1.25<br />
0.24<br />
0.21<br />
0.19<br />
0.10<br />
0.02<br />
1.50<br />
0.06<br />
0.05<br />
0.04<br />
0.02<br />
0.00<br />
1.75<br />
0.01<br />
0.01<br />
0.00<br />
0.00<br />
0.00<br />
200<br />
0.00<br />
0.00<br />
0.00<br />
0.00<br />
0.00<br />
TABLE 5.2 :<br />
LOCAL GENERATED WAVE CLIMATE<br />
Exceedence of wave height in percentage of time<br />
Hs(m)<br />
Direction<br />
SE<br />
S<br />
NW<br />
0.1<br />
6.0<br />
2.7<br />
1.2<br />
0.2<br />
0.9<br />
0.6<br />
0.4<br />
0.3<br />
0.2<br />
0.1<br />
0.1<br />
0.4<br />
-<br />
-<br />
-<br />
Extreme Wave Climate Analysis<br />
The offshore extreme wave climate was derived from a hindcast study undertaken by the Hong Kong<br />
Polytechnic through the use of a parametric wave prediction tnodei with input data from 14 selected<br />
typhoons which have occurred during the last 42 years.<br />
Table 5.3 presents the resulting extreme wave climate at Area 137. The direction of these extreme waves<br />
will be between 170 degrees N and 190 degrees N. Wave periods will range from 10 s to 16 s.<br />
APH Consultants Page 5-4
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 5 J :<br />
INSHORE EXTREME WAVE CLIMATE<br />
Return Period<br />
(jrs)<br />
1<br />
10<br />
20<br />
50<br />
100<br />
200<br />
Hs<br />
(m)<br />
1.8<br />
2.7<br />
3.2<br />
3.7<br />
4.0<br />
4.3<br />
The local generated wave climate, established from the extreme wind climate and the JONRAY results<br />
is presented below in Table 5.4. Periods of these local generated waves will range between 3 s and 6 s,<br />
TABLE 5.4 :<br />
EXTREME LOCAL GENERATED WAVE CLIMATE<br />
Significant Wave Height Hs (m)<br />
Return Period<br />
Direction<br />
(yrs)<br />
SE<br />
S<br />
SW<br />
1<br />
0.5<br />
0.5<br />
0.4<br />
10<br />
0.8<br />
1.2<br />
0.7<br />
20<br />
1.0<br />
1.5<br />
0.8<br />
50<br />
1.2<br />
1.9<br />
0.9<br />
100<br />
1.3<br />
2.1<br />
1.0<br />
200<br />
1.4<br />
2.4<br />
1.1<br />
5.2 LAND FORMATION<br />
5.2.1 Method of Site Reclamation<br />
The site reclamation can be undertaken with or without the removal of the soft marine deposits. Removal<br />
of this layer and replacement with a granular fill would give a reclamation base with stronger and more<br />
certain engineering properties and reduce considerably the time required for consolidation. This method<br />
would, however, involve the dredging and disposal of a large volume (some 10 to 15 Mm 3 ) of the soft<br />
marine deposits, with associated environmental impacts. The dredged material would then require<br />
replacement by additional fill.<br />
It is proposed that the site reclamation should be undertaken with the minimum removal of the marine<br />
deposit layer, thus reducing the environmental impacts, fill requirements and minimising the extent of mud<br />
disposal.<br />
APR Consultants Page 5-5
Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
The placement of fill material over the marine deposit and underlying alluvium will result in the<br />
consolidation of these materials and the consequential settlement of the reclamation. This consolidation<br />
would normally take place over a very long period of time and accelerated consolidation will therefore<br />
be required in order to complete the reclamation within an acceptable timescale.<br />
5.2,2 Settlement and Consolidation Time<br />
The settlement of the underlying layers has been calculated using geotechnical data determined from the<br />
site investigation. For a finished reclamation level of -1-5.0 mPD, total settlement has been estimated to<br />
range from 1.8 m in the north of the site to 3.1 m in the south, with consolidation in both the marine<br />
deposit and alluvium layers. The difference in settlement is due to the varying thickness of marine<br />
deposits and because the dumped material in the north of the site has already induced a certain amount<br />
of consolidation in the underlying soft layers.<br />
The rate of consolidation of the soft cohesive'material is dictated primarily by the rate of drainage within<br />
the layer ie the rate at which excess pore water pressures can dissipate. In order to accelerate the<br />
consolidation process, it is proposed that vertical (wick) drains be installed in the soft material. The<br />
spacing of these drains together with the weight of the fill will determine the rate of consolidation.<br />
Using a preload surcharge of 1.5 m and with vertical drains installed to -24 mPD, spaced at 1.7 m in a<br />
triangular pattern, full primary consolidation could be achieved within 6 months of completion of the<br />
reclamation construction. The small amount of the remaining secondary compression will occur over an<br />
indefinite period of time and would not normally present any significant design or construction problems.<br />
In the north of the site where some consolidation of the marine deposits has already taken place, full<br />
primary consolidation could be achieved within 2 years without the installation of wick drains or<br />
accelerated through the introduction of vertical drains as outlined above.<br />
The design should be confirmed by further site investigation during the detailed design stage of the<br />
project. In addition, when installing the drains, the spacing should be checked and optimised during the<br />
first phase of the installation by adopting different wick drain spacings and monitoring the consolidation<br />
results.<br />
5.2*3 Construction Methodology<br />
The primary constraint when filling on top of the marine deposit is the low shear strength. In order to<br />
avoid instability and mixing of mud and fill material it is necessary to ensure that:<br />
+ the fill is placed in layers of uniform thickness;<br />
* the leading edge of the fill forms a shallow slope, typically 1:6 or less.<br />
Water depths in the general fill area are insufficient to permit access by loaded trailer dredgers and it is<br />
therefore envisaged that the base sand fill layers would be placed by using a spreader barge supplied by<br />
a cutter suction dredger or a trailer dredger with a self unloading facility. These base layers should be<br />
built up to provide a 2 m thick sand blanket.<br />
Once die base layers have been placed, the bulk filling can commence. The fill should be placed in<br />
relatively low lifts (2 to 3 m) to an initial level of -f 2.0 mPD, which is considered high enough for the<br />
installation of vertical drains and placing of the surcharge fill. For the staged construction of the site a<br />
50 m wide embankment, with temporary bund walls if necessary and a flat 1:6 (minimum) fill slope, is<br />
placed along the edges of the reclamation area, where not contained by permanent edge structures.<br />
Construction of the embankment around die reclamation area should be completed first, or ahead of the<br />
reclamation between the embankments. Installation of vertical drains and subsequent placing of the<br />
APH Consultants Page 5*6
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
surcharge fill should start at the embankments and continue into the reclamation area. Figure 5.8 indicates<br />
such a construction sequence.<br />
After raising the reclamation level from 4-2.0 mPD to 4-5.0 mPD, a surcharge fill is placed which<br />
incorporates the 3,1 m fill required to take up the predicted settlement and a 1.5 m preload fill. The total<br />
(theoretical) height of the finished elevation of the surcharge would then be 4-9.6 mPD.<br />
In view of the restrictions of water depth, it is likely that most of the bulk fill would be placed either by<br />
a cutter suction dredger pumping ashore from a rehandling basin supplied by barges or trailers or by<br />
trailer dredgers pumping ashore through floating pipelines.<br />
In the event that a land sourced fill material is utilised, or where the reclamation site is used for public<br />
dumping, the first layers over the sand blanket would need to be placed by careful bottom dumping from<br />
barges so as to build up a layer with minimal disturbance to the previously placed sand or fill. Once this<br />
barge-dumped material has reached a level of -2.0 mPD, end tipping from land can commence.<br />
Installation of vertical drains is assumed to take place in the dry, after the initial fill has reached a level<br />
of -f 2.0 mPD. This presumes that the fill material is either sand, or, if land sourced material is used,<br />
that the maximum particle size is less than 50 mm. For fill materials which do not meet the above stated<br />
requirements, the vertical drains will have to be installed by marine based equipment after the 2 m sand<br />
blanket has been placed.<br />
5.3 EDGE STRUCTURES<br />
53.1 Method of Construction<br />
Removal of the marine deposits from beneath the seawalls has been considered necessary at this stage.<br />
The reasons for this are twofold:<br />
*• from a structural point of view, removal of the soft marine deposit layer eliminates the uncertainty<br />
associated with the use of this material as a foundation layer - settlement of the quay structure<br />
could be critical to its performance;<br />
+ in comparing the construction of gravity structures, retaining structures and open piled structures,<br />
removal of the marine deposits has been found to be more cost effective.<br />
However, it is possible that during the detailed design stage, a more thorough site investigation of the<br />
seawall alignment could indicate that the marine deposits may have a higher strength than normally<br />
associated with this material, and time and cost effective retention could be considered.<br />
The construction methodology for removal of marine deposits involves dredging a trench along the line<br />
of the edge structure and replacing the marine deposits with a granular fill. The site characteristics<br />
suggest that most of the dredging is likely to be undertaken using grab dredgers, possibly supplemented<br />
by trailers in those areas where access permits.<br />
The method which is employed to backfill trenches will largely depend on the nature of the material used<br />
as backfill. In the case of rock, it is likely that the fill would be delivered in conventional dump barges<br />
or on pontoons. Backfilling would be achieved by dumping from the barge or by bulldozing the fill off<br />
the pontoon. In the case of sand backfill, filling would be carried out by controlled bottom dumping from<br />
barges, or trailers where there are no access constraints, or by direct delivery to the bottom of the trench<br />
using downpipes.<br />
APH Consultants<br />
p ^
Figure 5.8<br />
TEMPORARY -~v<br />
8UNDWA1LS \ SO PD<br />
A \J^<br />
-^^i^1<br />
wrWSnWG Sg'A BOTTOM i<br />
i<br />
VERTICAL NICK 1<br />
DRAINS {<br />
_ — . , — — !„<br />
50m CM8ANKWENT ARQUNO<br />
RECLAMATION SECTIONS<br />
4-2.0 mP.O.<br />
i i qftmru<br />
in:::<br />
—uu I Iiii<br />
H-hfHHH-H<br />
f4- ill ii —^s^--<br />
}<br />
i<br />
I<br />
!1<br />
iiii<br />
Mi!<br />
Mil<br />
iiil<br />
1111<br />
Mi!<br />
HIM<br />
illll<br />
Iiii!<br />
11 1 !! EMBANXilENT J<br />
Hi |f SLOPE<br />
Hill<br />
lit! ill!<br />
1M1 LLLJJ<br />
1MM<br />
LUU<br />
{Hi!<br />
LLLLJ ,<br />
STAGE 1 • PLACING FILL FOR EMBANKMENT AND INSTALLATION OF WICK DRAIN<br />
STAGE 2 - RECLAMATION BET\VEEN EMBANKMENT AND INSTALLATION OF WICK DRAINS<br />
50m EMBANKMENT AROUND<br />
RECLAMATION SECTIONS<br />
TEWPOARAY -v<br />
BUNOWAU.S \<br />
\ * 5 0 mP 0<br />
+• 9 8 mP O<br />
. ,r-r- "^ l<br />
£ +ZO mP.O. ^V<br />
, \ _^^ffi^MHiffmin<br />
^sfr^"*^7^i-rcji'^i*m<br />
v - 1 — ii i f i —:i i<br />
•>• ISs**."" TITT^ "~ T ,.""<br />
{• ' !f] j^*^15^1^-----<br />
__ r«Tvv "..T~-~^^ . ^f^lSTWC SE4_30nQH.J_ LJ _LJ LI^ LLLL Li_Ll<br />
«"' r i i ^*~i-**.<br />
-i - — 1 1 j jj. . .. _ i<br />
! i MM! (Hi {(lit Mi ii EW8ANKMEKT J<br />
VERTICAL -WICK 1 I I I i 1 1 II I I Mill ill!! SLOP^<br />
MAINS ! I Hill 111! HIM II! ii<br />
I i iiiii Hi!<br />
i M i M 1 1 1 m i<br />
iim<br />
mil<br />
Ml ii<br />
nin<br />
STAGE 3A -<br />
PLACING PRELOAD FILL ON EMBANKMENT AND SUBSEQUENTLY<br />
ON RECLAMATION AREAS<br />
TEMPORARY RETENTION —-v<br />
EMBANKMENT / SEAWAUL \<br />
—- ORIGINAL SURFACE FROM WHICH TMCX<br />
ORAJNS MERE tNSTAUJEO<br />
+ S.OmPD. HNISHED SURFACE AFTER<br />
REMOVAL OF EXCESS SURCHACE HLL<br />
i-SETTLED PROFILES<br />
i—SETTLEMENT<br />
STAGE 38 - SETTLED PROFILE / SURFACE AFTER PRELOADING<br />
RECLAMATION WITHOUT REMOVAL OF MARINE DEPOSITS<br />
993 APH CONSULTANTS
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Thereafter, for revetment structures, a bund wall is constructed and the bulk filling behind the edge<br />
structure is undertaken in low lifts of 2 to 3 m. The increased stability afforded by the greater shear<br />
strength of the granular trench material means that the edge bund can be constructed to the required design<br />
slope (1:2). Wick draining and surcharging behind the edge structure are the same as previously<br />
described. The quay structure is constructed on completion of the filling operation. For sheet pile walls,<br />
the rock bund is not required and after construction of the sheet piling the landward fill is placed up<br />
against the wall, together with installation of anchors.<br />
5*3.2 Selection of Edge Structure<br />
There is a wide range of structural concepts available for the provision of the quay structures, which can<br />
be divided broadly into gravity structures, anchored retaining structures and open piled structures. The<br />
suitability of each type will vary as a function of the design requirements and the physical and<br />
environmental characteristics at the site. In general, the least cost alternative types of edge structures have<br />
been selected where these are technically appropriate. The selection and design of these edge structures<br />
will be subject to further analysis in the detailed design stage when more information with respect to soils<br />
properties and design loadings is available.<br />
Seawalls<br />
The type of seawall proposed for locations where no berthing structure is required is a revetted slope with<br />
rock armour. This is the normal type of seawall construction in the Territory for locations exposed to<br />
moderate wave action, since the wave run-up, overtopping and reflection is reduced from that associated<br />
with a vertical faced structure. It is also proposed that the seawall behind the dolphin berths along the<br />
PHI frontage should be a revetted slope with rock armour.<br />
The crest level of the seawall is 4-6.5 mPD, to prevent overtopping for the mean annual wave conditions.<br />
Any overtopping that may occur due to runup during extreme storm events will be contained in a drainage<br />
catchment behind the wall crest. At the more exposed southern corner of the site, off Tit Cham Chau,<br />
the crest level is raised to 4-7.5 mPD.<br />
Details of the seawalls are shown in Figure 5.9.<br />
Dolphin Berths<br />
It is proposed that the deep water bulk liquid berths (chemical, LPG, fuel and naphtha) should be dolphin<br />
berths, situated in front of a revetted slope seawall (Figure 5.9). It is normal practice to provide dolphin<br />
berths for bulk liquid vessels, since the pipe manifolds are located amidships, and the loading/unloading<br />
platforms can therefore be of limited length. Breasting dolphins with appropriate fendering are located<br />
on either of the loading platform and are set slightly seaward of it, so that the berthed vessel is kept clear<br />
of the loading platform. Mooring dolphins are also provided on either side of the berth, set back 30 m<br />
behind the berthing line, to take the breast, head and stern lines from the berthed ship. Catwalks are<br />
provided for access to the breasting and mooring dolphins.<br />
limited vehicle access to the loading platform would be provided by a short access bridge, which would<br />
also carry the pipelines to the shore. The level of the deck of the loading platform and access bridge<br />
would be 4-6.5 mPD to avoid excessive overtopping under extreme conditions and to reduce wave forces<br />
on the underside of the structures.<br />
The loading platform, breasting dolphins and mooring dolphins would all be piled structures. Most of the<br />
reinforced concrete work would be tn-situ, but there is some scope for precasting beams and slab soffits.<br />
There is no need for the removal of marine deposits under the piled structures.<br />
APH Consultants<br />
pag€
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
The dredged level of these berths would be -14 mPD.<br />
The berth layouts have been based on utilisation by the following "design" ships:<br />
Berth No.l - Naptha tankers, LOA 200 m 30,000 DWT<br />
Berth No.2 - LPG tankers, LOA 80 m 1,200 DWT<br />
Berth No.3 - Chemical transhipment tankers, LOA 120 m 8,000 DWT<br />
Berth No.4 - Chemical parcel tankers, LOA 185 m 40,000 DWT<br />
Berth No.5 - Fuel oil tankers, LOA 225 m 45,000 DWT<br />
Outer Marginal Berths<br />
A deep water marginal berth is proposed for the northernmost 200 m of the outer berthing line. The<br />
dredged level at this berth would be -14 mPD. The berth would be used by ocean-going vessels serving<br />
the DWFs at Area 137, or by smaller coastal and river trade vessels. Since the import, transhipment or<br />
export cargoes handled at these berths will be break-bulk general cargo, or possibly small quantities of<br />
dry bulk cargo, there is a need for a wide apron immediately behind the berthing face on which mobile<br />
cranes, forklift trucks, tractors and trailers and lorries may operate. No requirement is envisaged for fixed<br />
or travelling cranes to serve this multi-user berth.<br />
The type of quay proposed is an open deck on piles with a rock armoured revetted slope (see Figure<br />
5.10). The location is exposed to some wave action and a sloping revetment with open-piled structure is<br />
therefore preferred to a vertical faced structure. In addition, wave conditions during construction may,<br />
on occasions, make it difficult to construct alternative forms of quay such as sheet piling at this location.<br />
The reinforced concrete deck could be cast in situ; again there is scope for precasting the beams, slab<br />
soffits, fender and rear downstands.<br />
Basin Marginal Berths<br />
The basin berths in the north of the site would be used for transhipment and export of PHI related<br />
products in containers, and for the import, transhipment and export of DWI goods. The SENT Landfill<br />
marine access berth would be dedicated to the unloading of the SENT Landfill. The basin would be<br />
dredged to -10 mPD.<br />
A large degree of protection from wave action is afforded by the configuration of the basin. There is<br />
therefore not the same need to ensure minimal wave reflections at the berths as at the outer berthing line.<br />
In addition, conditions during construction will be calmer.<br />
An anchored steel sheet piled retaining wall, with removal of marine deposits, has been found to be more<br />
economical than other forms of marginal quay wall construction. It is therefore proposed that the basin<br />
marginal quays should be constructed with steel sheet piles anchored to suitable anchorages set back<br />
behind the quay (see Figure 5.11).<br />
A 50 m wide apron behind the berthing fece is required for the operation of cargo handling equipment<br />
and lorries. Again, no requirement for fixed or travelling cranes to serve the berths is envisaged.<br />
The cope level would be 4-5.0 mPD. The limited wave action in the basin reduces the likelihood of runup<br />
and overtopping.<br />
APH Consultants Page 5-9
5.9<br />
QUAY STRUCTURES<br />
SECTION THROUGH DOLPHIN BERTH JETTY AND REVETMENT<br />
APH CONSULTANTS
Figure 5.11<br />
QUAY STRUCTURES<br />
SECTION THROUGH SHEET PILE WALL<br />
APH CONSULTANTS
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
5.4 FILL REQUIREMENTS AND SOURCES<br />
Estimates of fill requirements for the proposed development in Area 137 indicate a total requirement for<br />
approximately 15 Mm 3 , based on the assumption that the marine deposits will be left in place in the<br />
general fill areas.<br />
Whilst no allocation of marine fill has yet been made for Area 137, it is possible that fill may be available<br />
in the borrow areas of North, Mid and South Tathong and East Tung Lung Chau. These borrow areas<br />
are already allocated to projects which are either in progress or about to commence and it is therefore not<br />
possible to identify at this stage those parts of the borrow areas which will still contain economic resources<br />
when they are handed back and become available for Area 137 and other projects. In the event that<br />
insufficient marine fill is available, land sourced fill would need to be used. Land sourced fill may be<br />
available from Anderson Road Quarry, where some 6.7 Mm 3 of overburden will need to be disposed of<br />
from 1994 onwards. However, it is not certain at this stage whether this material would be available for<br />
the Area 137 development. The formal allocation of fill for Area 137 would be made by FMC at the<br />
detailed design stage.<br />
An alternative source of fill material is screened construction waste, or public dumping. The use of this<br />
material is attractive not only because it would be a very low cost fill but it also saves valuable landfill<br />
space. Whilst the volume of construction waste material produced in the Territory is not sufficient to meet<br />
the demands of a fast track construction programme, this would be a useful source of fill for on-going<br />
reclamation after, for example, the early establishment of an initial development.<br />
5.5 DREDGING REQUIREMENTS AND DISPOSAL<br />
Dredging in Area 137 will be required to deepen the berthing areas and approach channels and to remove<br />
unsuitable material from beneath the seawalls and quay structures. The total volume to be dredged has<br />
been estimated to be around 2.9 Mm 3 for the construction of the full development. This is made up of<br />
0,5 Mm 3 to be dredged from berthing areas and approach channels and 2.4 Mm 3 from seawall trenches.<br />
The disposal of unsuitable materials which will be dredged in the Territory in the coming years is<br />
becoming a matter of increasing concern. The FMC Database of Fill Requirements and Surpluses (March<br />
1992) estimates the volume of mud which will arise from dredging and reclamation projects during the<br />
period 1992 to 2000 to be 330 Mm 3 . Set against this volume, the disposal of 2.9 Mm 3 of dredged material<br />
from Area 137 should not present any particular difficulty. The material may be disposed of in redundant<br />
borrow pits that are expected to be available at the time; alternately, the material may have to be disposed<br />
of at gazetted dumping grounds.<br />
Dredging of Contaminated Sediments<br />
From sampling and testing in this area prior to this Study and from testing carried out as part of the Area<br />
137 site investigation, it is apparent that some sediments to be dredged from Area 137 are likely to contain<br />
significant concentrations of trace elements.<br />
Given this conclusion, the dredging and disposal of these sediments requires particular care to minimise<br />
the release and resuspension of contaminated materials. Suitable dredging procedures would include fitting<br />
grab dredgers with closed grabs and operating grabs within silt curtains.<br />
The disposal of contaminated material would depend on the availability of disposal sites for contaminated<br />
material at the time. Capping the contaminated material with non-contaminated spoil is the most likely<br />
solution to disposal problems but this will depend to a large extent on the release of suitable allocations<br />
for spoil disposal and the comparative timing of the various projects producing spoil.<br />
APH Consultants<br />
Page >lti
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
5.6 CAVERN DEVELOPMENT<br />
The feasibility of rock cavern development in the vicinity of Area 137 has been examined for storage of<br />
dangerous goods.<br />
GEO have carried out a preliminary study of the geological potential for cavern development in the<br />
vicinity of Area 137. Three sites have been identified of which the closest and most suitable is within the<br />
Clearwater Bay Country Park adjacent to the site. Four caverns could be constructed at this location,<br />
generating a storage area of some 1.6 ha and producing some 325,000 m 3 of rockfill for use within the<br />
reclamation.<br />
The approach to the minimisation of risks for each PHI site, as discussed in Section 3, has been to<br />
concentrate the high risk activities and storage in one area and use lower risk activities as buffers on the<br />
boundaries between each site. The marine related import/export of materials has, naturally, lead to the<br />
location of the higher risk activities in close proximity to the berths. The adoption of further removed<br />
cavern storage would significantly increase' the land transfer distances and hence, spread the area of<br />
potentially high risk activities. This could move the boundary of acceptable risk further north and possibly<br />
into the TKOEE and SENT Landfill areas. Moreover, material import and export from the storage tanks<br />
would be effectively continuous. This may well be a departure from the more conventional use of caverns<br />
for the long term storage of potentially hazardous products, often in small unitised volumes.<br />
The total quantity of excavated material from the caverns is small in relation to the site reclamation<br />
requirements and would not form a significant contribution. The cost of formation of the caverns would<br />
depend upon the nature of the lining and tunnel support requirements, but is likely to be an order of<br />
magnitude higher than that associated with conventional reclamation.<br />
It is therefore considered that the relative remoteness of the potential sites for cavern development, as well<br />
as cost considerations, effectively rules out the adoption of caverns for storage in this instance.<br />
5.7 HIGHWAYS AND ROADS<br />
5.7.1 Site Access<br />
External road access to Area 137 will be from the proposed Road D6, which will run southwards between<br />
the TKOIE and the SENT Landfill boundaries to Area 137. The proposed cross-section of D6 comprises<br />
a 7.3 m dual two lane carriageway with wide verges incorporating 3.5 m footpaths, 3.0 m planting areas<br />
and a 3.5 m cycle track. Initially, only one carriageway will be constructed to provide access to Area<br />
137. This road will be extended into Area 137 to a roundabout in the north of the site.<br />
Provision has been made in the Area 137 planning for an extension of D6 to the south of the site, along<br />
the edge of the Clearwater Bay Peninsula. Access to the south of the site is proposed by constructing the<br />
southbound carriageway of this road, ie a 7.3 m two way single carriageway road, to the southern<br />
roundabout.<br />
5.7.2 Internal Road Network<br />
Road Hierarchy<br />
The internal road network in Area 137 consists of a 13,5 m single carriageway principal access road and<br />
10.3 m (two way) and 7.3 m (one way) single carriageway secondary access roads. For all roads, verges<br />
incorporating 3,5 m footpaths and 2.0 m planting areas are provided on both sides of the road. Design<br />
APR Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
speeds adopted for the internal road network are 70 kph and 50 kph for the principal and secondary access<br />
roads respectively.<br />
Principal Access Road<br />
The 13.5 m single carriageway principal access is the main arterial road for the proposed development.<br />
It runs some 800 m from the northern roundabout intersection to the roundabout at the south of the<br />
development. The secondary access roads feed off this road to serve the individual sites.<br />
Secondary Access Roads<br />
The 10.3 m and 7.3 m (one way) secondary access roads feed off both the principal access road and the<br />
northern roundabout. Junction spacings in the north of the site are close due to the constraints of the<br />
planning layout but nevertheless maintain the standards laid down in the Transport Planning and Design<br />
Manual. Turning circles are provided at the ends of cul-de sacs. Along the northern site boundary, an<br />
access road to the SENT Landfill marine access facility is provided off Road D6.<br />
Emergency Vehicle Access (EVA)<br />
Additional reserves for Emergency Vehicle Access are provided, in particular along the seawalls. These<br />
would be paved areas which must be kept clear at ail times in the event of emergencies; they do not form<br />
part of the road network.<br />
5.8 STORMWATER DRAINAGE<br />
5.8.1 Existing Catchment Areas<br />
The study area contains two catchment types :<br />
*> areas on the south side of Fat Tong Chau and south of Tin Ha Village, consist of short steep<br />
catchments falling directly to the reclamation area;<br />
> the area around Tin Ha Village will be recontoured as part of the SENT Landfill and will<br />
discharge to Area 137 at two locations.<br />
5.3.2 Existing Drainage<br />
Two drainage culverts discharging surface water from the SENT Landfill will traverse Area 137. Flow<br />
from these culverts will be incorporated as part of the surface water drainage system for Area 137.<br />
Leachate from the SENT Landfill is collected separately and directed to the sewage treatment works.<br />
5.3.3 Drainage Requirements<br />
The following specific requirements represent a summary of the objectives for the drainage system in Area<br />
137:<br />
> security from flooding by heavy rainfall and typhoon surge with a freeboard allowance to<br />
accommodate settlement and wave action;<br />
» mitigation or at least maintaining status quo of flooding conditions in existing undeveloped areas;<br />
*• the provision of adequate surface water drainage to avoid ponding of water;<br />
* reclamation works and stoonwater outfall to be designed for 1 in 200 year storm recurrence<br />
interval;<br />
APR Consultants Page 5-12
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
+ appropriate allowance for deterioration of system performance of 10 to 15% of design discharge<br />
capacity;<br />
* no overtopping of road kerbs;<br />
> trunk drainage systems to accommodate flows from 1 in 200 year storm recurrence intervals with<br />
subsidiary drainage designed for 1 in 50 years.<br />
5.8*4 Proposed Drainage<br />
Stormwater runoff will be collected by a system of channels at the interface with undeveloped land and<br />
by box culverts discharging to sea at specific drainage outfalls constructed in the seawall. Several<br />
subcatchments are combined to minimise the requirement for drainage reserves across developable land<br />
and box culverts are located along roads wherever possible. Drainage outfalls and box culverts are<br />
designed to maintain a freeboard above high tide level (2.25 mPD) of 500 mm for large culverts and 300<br />
mm for small culverts. Figure 5.12 shows the proposed drainage layout of the site together with the<br />
catchment areas.<br />
To minimise pollutants in stormwater runoff discharging to sea in the vicinity of the development, runoff<br />
from PHI and related industry will be controlled by on-site treatment facilities. Stormwater runoff from<br />
existing undeveloped slopes will be intercepted by a system of *U* channels and silt traps, so that the<br />
initial flows from any storm will discharge only minimal accumulated debris from the road network.<br />
Significant areas of the PHI sites will be bunded and after suitable treatment, stormwater runoff from these<br />
areas will be discharged from each site to the sea by surface drainage outlets through the sea wall.<br />
5.9 WATER SUPPLY<br />
5*9.1 Existing Fresh Water Supply System<br />
An existing 150mm diameter freshwater main, along the Tai Miu Tsiu Road, serves villages on the<br />
Clearwater Bay Peninsula. Villages adjacent to the Study Area obtain their supply from this source but<br />
will be cleared under the SENT Landfill project. The existing water supply system which will supply new<br />
development on reclamation areas has been extended along Road D6 only as far as the Tseung Kwan 0<br />
Sewage Treatment Works in Area 85.<br />
5.9.2 Future Fresh Water Supply Distribution<br />
It is anticipated that the fresh water supply facilities which are proposed as part of the development of the<br />
TKODE in Area 87 will be extended south to also service Area 137. Water Services Department have<br />
advised that although initial stages of TKOIE will be supplied from existing service reservoirs, water<br />
supply to Area 137 will be made available via the principal distribution main along Road D6, from the<br />
proposed Tseung Kwan O East Low Level Service reservoir to be located in Area 106.<br />
According to the WSD programme, the service reservoir should be completed by early 1996, which is<br />
consistent with the anticipated requirements of the initial PHI development on Area 137.<br />
Fresh water-supply requirements for Area 137 have been estimated with factors used by WSD, as given<br />
in Table 5.5. Consumption rates for DWIs and PHI Related Industries are based on comparative rates<br />
for I(B) Industry. General working areas are considered low water consumers and an equivalent I(C)<br />
Industry consumption rate has been adopted in this instance.<br />
APfl Consultants<br />
p
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
TABLE 5.5 :<br />
ESTIMATED FRESH WATER USAGE<br />
Development Type<br />
Gross<br />
Area (ha)<br />
Net Area<br />
(ha)<br />
Consumption<br />
(m 3 /ha/day)<br />
Daily<br />
Usage<br />
Potentially Hazardous Industry I(C) (storage of<br />
chemicals, oil, LPG)<br />
Potentially Hazardous Industry (naptha and gas<br />
production plant)<br />
30-42<br />
10.95<br />
19.77<br />
-<br />
30<br />
•<br />
601<br />
2500<br />
Deep Water Industry I(B)<br />
22.29<br />
14.49<br />
110<br />
1594<br />
PHI Related Industry I(B)<br />
7.18<br />
4.67<br />
110<br />
514<br />
Services<br />
1.00<br />
0.65<br />
30<br />
20<br />
General Working Areas<br />
4.83<br />
3.14<br />
30<br />
94<br />
5323<br />
PHI areas will be predominantly (75%) used for storage of chemicals, oil and LPG, which are considered<br />
to have low water consumption. These industries use extensive dedicated tanking and distribution piping<br />
to minimise their water requirements for cleaning purposes.<br />
A gas production plant is proposed for the remaining PHI area. For planning purposes it has been<br />
assumed that the water consumption of such a plant will be similar to that of the existing facility at Tai<br />
Po which has a daily fresh water consumption of approximately 2,500 m 3 .<br />
The estimated fresh water consumption of 5,323 nrVday for Area 137 is greater than the present WSD<br />
allowance of 4,700 m 3 /day for this area. Although the planned 600 mm diameter trunk main along Road<br />
D6 is likely to be adequate, a further review of the adequacy of the system is appropriate when major<br />
water consumers in Area 137 and the adjacent TKOIE have been identified.<br />
Moreover, the Hong Kong and China Gas Co Ltd have advised that should a more extensive gas<br />
production facility be constructed in Area 137, overall water consumption by the gas production plant<br />
could be of the order of 8,000 m 3 /day, which would require WSD to reassess the supply provisions in this<br />
area especially with respect to the capacity of the proposed fresh water service reservoir at Tseung Kwan<br />
O East. A review of the system, including the water main feeding the service reservoir, the capacity of<br />
the service reservoir and the 600 mm diameter main leading to Area 137, will be necessary,<br />
5.9.3 Proposed Salt Water Supply<br />
Supply of salt water for flushing purposes wfll be provided to all low level areas from the fixture Tseung<br />
Kwan O East salt water pumping station located in Area 86. Further extension of these facilities is<br />
required to provide supply to both the TKOBE and Area 137. A provision for future salt water flushing<br />
has been made as part of the development of the TKOIE by a proposed 500 mm diameter main to be<br />
located in Road D6.<br />
WSD advise that the proposed salt water supply system in the area will cater for the estimated flushing<br />
water demand in Area 137.<br />
APH Consultants Page 5-14
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
5.9.4 Firefighting Water Supply<br />
WSD advise that under abnormal operation mode, the principal main on Road D6 can deliver FSD<br />
requirement of 33,000 m 3 /day for fire fighting purposes. This may, however, result in temporary inability<br />
of the distribution mains in the area to meet other water supply requirements at the same time.<br />
5.10 SEWERAGE<br />
5.10.1 Existing Sewerage Facilities<br />
No existing sewerage facilities are located within close proximity to the Study Area.<br />
The Tseung Kwan O Sewage Treatment Works is located some two kilometres north of Area 137. This<br />
plant accepts sewage from the developing Tseung Kwan O New Town. Phase I of the Tseung Kwan O<br />
Sewage Treatment Works was commissioned in 1989 and it is understood that the plant is presently<br />
operating at approximately 60% of its capacity.<br />
5.10.2 Future Sewerage Facilities<br />
A Revised Design Statement for Tseung Kwan 0 Sewage Treatment and Disposal has recently been<br />
documented. This review outlines proposed strategies for construction of the Sewage Treatment Works<br />
which are required to meet the projected New Town growth and the development of the TKOEE and other<br />
industrial developments.<br />
From the Design Statement, full development of Phase II Stage 1 of the Sewage Treatment Works will<br />
provide for 88,000 mVday in 1998. Phase n Stage 2 of the Sewage Treatment Works (2001) should<br />
provide a further increase in capacity of 50%, to around 120,000 nrVday. The ultimate planning for the<br />
Sewage Treatment Works (2011) provides for a total capacity of 192,000 m 3 /day. It is probable that the<br />
timing of the next phase of the Sewage Treatment Works will be determined by the rate of development<br />
of the Tseung Kwan 0 New Town and the TKOEE and is unlikely to be affected by the rate of<br />
development of Area 137. Variations in flows from Area 137 represent only a minor proportion of the<br />
total flow at the Sewage Treatment Works.<br />
Provision has been made for sewage flows from the Area 137 development in the Revised Design<br />
Statement. An allowance of 3,125 nrVday has been made within the design of Phase H Stage 1, increasing<br />
to 4,500 nrVday, for Phase H Stage 2 in 2001 when the full development can be expected to become<br />
operational. This is in line with WSD's estimated water supply provision for Area 137. Further, for the<br />
ultimate planning horizon, an allowance of some 36,000 nrVday from Area 137 has been made, based on<br />
the assumption of a change of land use from that currently under study to a high density industrial<br />
development such as the TKOIE.<br />
Sewage flows from the development are based on site areas as given Section 4 (Table 4J). Using the<br />
ultimate per capita daily water demand and industrial water usage rates from the Civil Engineering Manual<br />
for the various classes of consumers, dry weather sewage flows (DWF) from Area 137 have been<br />
estimated as shown in Table 5.6.<br />
APH Cojtsutiants Page 5-15
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
final Report - Main Report<br />
TABLE 5.6 :<br />
ESTIMATED SEWAGE FLOWS<br />
Land Use<br />
Gross Site Area<br />
(ha)<br />
Net Site Area<br />
(65% of Gross)<br />
(ha)<br />
Water Consumption<br />
per hectare<br />
(m 3 /day)<br />
Sewage Flows<br />
(m 3 /day)<br />
(DWF)<br />
PHI (gas)<br />
10.95<br />
7.12<br />
112.0<br />
797.44<br />
PHI (LPG/chcm/oil)<br />
30.42<br />
19.77<br />
112.0<br />
2214.24<br />
PHI related<br />
7. IS<br />
4.67<br />
112.0<br />
523.04<br />
DWI<br />
22.29<br />
14.50<br />
112.0<br />
1624.00<br />
Services<br />
LOO<br />
0.65<br />
0.08<br />
0.05<br />
Total<br />
say<br />
5,156 rrrVday<br />
5,200 mVday<br />
Should the gas production facility be more extensive than planned, Hong Kong and China Gas Co Ltd<br />
have advised that additional waste water discharge from the ultimate plant could be in the order of 2,000<br />
mVday (DWF). Together with the other planned facilities this would require that an allowance of about<br />
7,200 arVday DWF be made in the design of the Sewage Treatment Works for flows from Area 137.<br />
Advice from the consultants for the Sewage Treatment Works indicates that this increase is not expected<br />
to present any difficulties as these flows form a very small proportion of the total design flows and can<br />
be easily accommodated.<br />
In the event of a future change of land use for Area 137, there may be a significant increase of sewage<br />
flow volumes; however, adequate provision has been made in the ultimate planned capacity of the Sewage<br />
Treatment Works.<br />
No provision has been made within proposed gravity sewers in the TKOIE for flows from Area 137,<br />
which will therefore need to discharge to the treatment plant by separate sewer.<br />
5.10*3 Sewerage Network<br />
Area 137 is remote from the Tseung Kwan 0 Sewage Treatment Works, therefore sewage will be directed<br />
to a centrally located pumping station and then discharged to the Sewage Treatment Works via a rising<br />
main located within the services reserve of Road D6. To enable relocation of the SENT Landfill marine<br />
access facilities, temporary pumping of flows from these facilities into the TKOIE sewers is envisaged.<br />
Alternately, it may be possible to utilise self-contained (chemical) units, which would eliminate these<br />
sewage flows. A review of the proposed sewerage system wiU be necessary once specific operators for<br />
the development have been identified.<br />
The anticipated PHI development in Area 137 may require the inclusion of on-site treatment facilities, the<br />
extent of which can only be assessed on an individual industry needs basis.<br />
5.10.4 Sewage Disposal<br />
Initially sewage flows from the Study Area will undergo preliminary treatment at the Tseung Kwan 0<br />
Sewage Treatment Works and will then be discharged via the existing Tseung Kwan 0 submarine outfall<br />
into the Tathong Channel, Options exist for future upgrading of the Sewage Treatment Works to<br />
secondary treatment or alternatively discharging directly to the Strategic Sewage Disposal Scheme interim<br />
outfall.<br />
APH Consultants Page 5-16
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
5.11 PUBLIC UTILITIES<br />
China Light and Power Company propose to supply Tseung Kwan O from a major 400 kV substation to<br />
be established near Tseung Kwan O Town Centre. A feeder network of 132 kV circuits will then supply<br />
primary substations to be located in areas of new development. Extension of electricity services will occur<br />
as part of the staged development of the new TKOIE. Supply to Area 137 will be an extension of these<br />
facilities.<br />
Hong Kong Telephone Company intends to extend its services to areas of development as demand<br />
requires. It is intended that the regional telephone exchange is located in the Tseung Kwan 0 New Town<br />
Centre and that extension to the TKOIE and to SENT Landfill areas occurs progressively. It is understood<br />
that sufficient capacity exists within the present network for the requirements of the development in Area<br />
137.<br />
Two gas connections to the Tseung Kwan O New Town are currently available. One extends from<br />
Kowloon via Po Lam Road and the other proceeds via Clear Water Bay Road and provides for<br />
development in Area 31. A new supply via the Tseung Kwan O Tunnel is anticipated to ensure sufficient<br />
capacity for future development of the New Town. Utilisation of gas production from SENT Landfill and<br />
gas supply from the proposed gas production facility in Area 137 may also be possible.<br />
Adequate service reserves will need to be provided in road D6 for the provision of these utilities.<br />
APH Consultants Page 5-17
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
SECTION 6<br />
MARINE STUDY<br />
6.1 INTRODUCTION<br />
The recommended development layout has been studied in relation to the marine operational requirements<br />
of the development itself as well as its interaction with the other marine operations in the area. This<br />
includes the impact of shipping generated by the proposed development on the shipping in the Tathong<br />
channel; likewise the effects of passing vessels and the effects of the marine climate conditions on ships<br />
berthed at Area 137. An investigation has been carried out on the feasibility of safe arrival and departure<br />
manoeuvres under various environmental conditions, including typhoon evacuation. Navigational safety<br />
is assessed together with the requirements for existing and new anchorage facilities.<br />
During detailed design, discussions with the Hong Kong Pilots Association will be necessary to establish<br />
berthing procedures and criteria for the specific berths dependent on the type and size of vessels using<br />
such facilities.<br />
6.2 MARINE TRAFFIC<br />
6.2.1 Present Situation<br />
The present volume of ocean going traffic using the Tathong Channel is relatively small, at some 12%<br />
of the current level of arrivals in Hong Kong. This corresponds to some 2,500 arrivals per year.<br />
A traffic count was carried out to establish the movements of vessels through Lei Yue Mun and Tathong<br />
Channel. The results of this counting are summarised in Table 6.1.<br />
TABLE 6.1 :<br />
DAILY VESSEL MOVEMENTS TATHONG CHANNEL<br />
(as recorded on 14 April 1992, 06.00 - 18.00 hrs)<br />
Vessel Type<br />
East Bound<br />
West Bound<br />
Total<br />
Percentage<br />
Ocean going<br />
3<br />
3<br />
6<br />
1.2<br />
River trade<br />
16<br />
21<br />
37<br />
7.3<br />
Towed barge<br />
16<br />
13<br />
29<br />
5.7<br />
Femes<br />
1<br />
1<br />
2<br />
0.4<br />
Fishing boats<br />
64<br />
124<br />
188<br />
37.1<br />
Small craft<br />
114<br />
85<br />
199<br />
393<br />
Dredgers<br />
10<br />
8<br />
IS<br />
3.6<br />
Speed boats<br />
14<br />
14<br />
28<br />
5.5<br />
Totals<br />
238<br />
269<br />
507<br />
100.0<br />
The survey showed that vessel movements are generally constant throughout the day apart from fishing<br />
boat movements, which peak during the morning with the return of the fishing fleet. The predominant<br />
APH Consultants<br />
Page
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Find Report - Main Report<br />
traffic through the Tathong Channel is fishing boats and small vessels, which account for over 75% of the<br />
total daily vessel movements.<br />
The survey also showed that the fishing boats and small craft tend to use the Inshore Traffic Zone past<br />
Chai Wan, while the other vessels use the main Tathong Channel. The number of vessel movements<br />
within the Traffic Separation Scheme (TSS) of the Tathong Channel at present amounts to some 240 per<br />
day. The present ocean going traffic accounts for some 15 vessel movements per day.<br />
6.2.2 Future Situation<br />
The marine traffic through the Tathong Channel will increase due to the expected growth of the total<br />
traffic calling at Hong Kong and due to Vessel Traffic Management regulations and guidelines. An<br />
assumed 20% traffic share for the Tathong Channel in 2011, will result in some 7,500 arrivals or 15,000<br />
ocean going vessel movements per year (ref. Lantau Port and Western Harbour Development Study,<br />
Working Paper No. 9). This would correspond to some 40 ocean going vessel movements per day.<br />
The Area 137 development will generate additional shipping traffic in the waters to the East of Hong Kong<br />
Island. The fleet mix calling at Area 137 has been estimated based on the identified industry/land use<br />
allocation and the expected marine traffic is presented in Table 6.2. The number of river trade vessels<br />
is based on a ratio of (arbitrarily) 5 times the number of ocean going traffic.<br />
TABLE 62 : ESTIMATED MARINE TRAFFIC FOR AREA 137<br />
Ship Type Ship Size (DWT) Number of Vessel Calls Number of Vessel<br />
Per Year<br />
Movements per Year<br />
Naphtha tanker<br />
30,000<br />
12<br />
24<br />
LPG tanker<br />
1,200<br />
50<br />
100<br />
Product tanker<br />
3,000<br />
50<br />
100<br />
Product tanker<br />
30-45,000<br />
100<br />
200<br />
Chemical tanker<br />
30-45,000<br />
100<br />
200<br />
Miscellaneous<br />
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
The total marine traffic (i.e. ocean going, river trade, barges) related to the development of Area 137 will<br />
result in an increase of some 30 to 35 vessel movements per day, which is also considered to be a<br />
relatively small increase compared to present traffic intensities (240 movements per day).<br />
The river trade traffic for Area 137 and the SENT Landfill barges will be handled in the northern basin<br />
berths and will therefore have limited interaction with the ocean going traffic destined for the deep water<br />
berths in the south of Area 137. Similarly, the proposed development at Area 131 will generate, typically,<br />
one to two ocean going vessel movements per day and can be effectively discounted in terms of the overall<br />
future movement patterns of the area.<br />
6.3 SHIP HANDLING OPERATIONS<br />
6*3.1 Introduction<br />
Ship manoeuvring simulations have been carried out to assess the manoeuvring behaviour of ships when<br />
arriving and departing from the proposed berths. The input to the simulations comprises an intended track<br />
to be followed by the vessel under specified wind, wave and current conditions. Further, the use of<br />
engine and scope of tug assistance is specified. During the simulations the vessel is controlled by an<br />
autopilot which calculates required rudder angles, engine settings and tug forces in order to follow the<br />
intended track as closely as possible.<br />
6.3.2 Input Conditions<br />
Arrivals and departures are presented for Berth 4 (parcel tanker berth), which is typical of the tanker<br />
berths, with a loaded and a ballasted 37,500 DWT tanker. Principal dimensions of the simulated tanker<br />
are indicated in Table 6.3.<br />
TABLE 6.3 :<br />
PRINCIPAL SHIP DIMENSIONS<br />
Dimension<br />
Unit<br />
Loaded<br />
Ballasted<br />
Length Overall<br />
Length P'ends<br />
Beam<br />
Draft<br />
m<br />
m<br />
m<br />
m<br />
180<br />
171<br />
25.5<br />
10.4<br />
180<br />
171<br />
25.5<br />
5.4 (tnmmed)<br />
The ocean going vessels for Area 137 will carry potentially hazardous cargoes and will require sufficient<br />
tugs when approaching or leaving the berths to effectively guarantee safe manoeuvres. Tankers for Berths<br />
1, 4 and 5 will require at least 3 tugs upon arrival and 2 tugs when departing. The smaller LPG carriers<br />
and chemical transhipment tankers (Berths 2 and 3) will need the assistance of 2 tugs and 1 tug for arrivals<br />
and departures respectively. In the simulations a maximum tug force of 40 tons has been assumed to be<br />
available at the bow as well as at the stem of the tankers for arrival and departure manoeuvres.<br />
Arrival manoeuvres commence in the centre of the Inbound Traffic Lane of the Tathong Channel abeam<br />
of Nga Ying Pai with starting speeds of 6 to 8 ktn depending on the weather conditions. Tankers proceed<br />
through the Tathong Channel and make a 30 degree starboard turn, followed almost immediately by a port<br />
turn for lining up for the final approach to the berths. The manoeuvre simulation was terminated once<br />
the tanker is stopped and well under control in front of the berth. It is assumed that tankers will berth<br />
bow in as is common practice in Hong Kong.<br />
APH Consultants Page 6-3
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Departing tankers will be cleared off the berths with tugs and swung over some 30 to 50 degrees to port<br />
in order to line up for departure. Simulations were commenced at this position and continued with a large<br />
port turn towards the Outbound Traffic Lane of the TSS in the Tathong Channel. The manoeuvre<br />
simulation was terminated once passage in the Tathong Channel had been achieved.<br />
Manoeuvres were studied under normal operating wind conditions of 20 ktn from the prevailing directions,<br />
north, east and southwest. Emergency departures were simulated under northwesterly and northeasterly<br />
winds of 30 ktn.<br />
Local generated waves in the Study Area are generally less than 0.3m with periods below 5 sec and will<br />
therefore not affect manoeuvring tankers. Residual swells come from a southerly direction and a typical<br />
wave height of 0.5 m was selected for this navigation study.<br />
Current speeds at the present pilot boarding station are generally 0.6 ktn for ebb and flood tides.<br />
However, during the wet season with spring ebb conditions the current speeds can be as high as 1.2 ktn.<br />
For the simulations 0.6 ktn flood and ebb currents were used as well as a L2 ktn ebb current.<br />
6.33 Ship Manoeuvres<br />
Operating Conditions<br />
Safe arrivals are considered practicable with loaded and ballasted tankers during any stage of the tide and<br />
under normal operating conditions.<br />
An arrival manoeuvre for a loaded tanker is made with moderate use of engine and rudder. After a<br />
smooth approach manoeuvre the tanker is lined up for a final approach to the berth and is stopped well<br />
in time with half astern engine power. When arriving during (strong) ebb tide conditions more engine<br />
power is required to counteract winds and currents. The tanker could be stopped in time and kept under<br />
control with limited tug assistance. For arrivals on a flood tide and in southerly winds, the speeds should<br />
be taken off well before the final approach to the berth. Sufficient tug assistance is required (30 tons at<br />
bow and stern) to counteract the starboard swing of the tanker when half (and occasionally full) astern<br />
power is given.<br />
A ballasted arrival in calm weather is shown in Figure 6.1. The arrival track is closely followed with<br />
engine at half and slow ahead and moderate rudder angles are required to make the starboard and port turn<br />
respectively. Slow astern power is applied to stop the ship. Safe arrivals at ebb tides in northerly or<br />
easterly winds can also be made with moderate tug assistance (e.g. 30 tons tug at bow and stern) during<br />
the final stage of the manoeuvre to keep the tankers under control.<br />
Ballasted arrivals in flood tides and southerly winds should be undertaken with care. When approaching<br />
the berth and slowing down, the ballasted tankers will swing to starboard due to the wind and tide. To<br />
keep the tanker under control at least two 30 tons tugs at the stern and one at the bow are needed. Under<br />
such conditions, some vessels may find berthing "portside to" more practicable.<br />
Safe departures from the berth with ballasted tankers are practicable under normal wind conditions at any<br />
stage of the tide. Ballasted departure manoeuvres from Berth No.4 commenced with the tankers well<br />
cleared from the berth and lined up for departure by the assisting tugs. The engine was put at dead slow<br />
ahead.<br />
The port turn towards the Tathong Channel was made with moderate rudder angles between 10 and 15<br />
degrees with the engine at dead slow and slow ahead. The speed during this turn amounted to some 4 ktn.<br />
No tug assistance was required under this condition following the initial berth clearance.<br />
APH ComuItaMs<br />
f
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
When departing on an ebb tide and in a northerly wind the departing tanker should be lined up heading<br />
into the wind and current. During the first phase of the manoeuvre the speed is approx 2 ktn and<br />
moderate tug forces are required to keep the vessel under control. The port turn is made with the engine<br />
on slow ahead and with rudder angles between 10 and 20 degrees.<br />
During the first phase of departure for manoeuvres at flood tides and south-westerly winds, tugs are<br />
required to keep the tankers under control by pulling to port with some 8 to 10 tonne at bow and stern.<br />
During the turn to port only limited tug assistance is required.<br />
The crossing time of departing vessels of the Inbound Traffic Lane of the TSS is restricted to some 5<br />
minutes.<br />
Emergency Departures (typhoon evacuation)<br />
The more critical ballasted departures from the berths are safe and practicable, provided that sufficient<br />
tugs (2 tugs of 30 tonnes each) are available to pull the vessel from the berth and align the vessel for<br />
departure. The tankers should be lined up in such a way that they stay well clear of any berth structure<br />
and other moored ships when they commence their departure manoeuvres and port swings.<br />
Figure 6.2 shows a departure at spring flood in a 30 ktn northwesterly wind. A safe departure manoeuvre<br />
is possible provided that the vessel is well cleared of the berth and lined up for departure. At the initial<br />
stage of the manoeuvre up to 10 tonne of tug assistance to port side at bow and stern is required to<br />
counteract wind and current.<br />
Under conditions of wet season spring ebb tides the tankers need to be lined up with the currents prior<br />
to commencing the departure manoeuvres. The port turn is made with engine on (dead) slow ahead and<br />
with rudder angles of approx 15 degrees. Tug boat forces at bow and stern amounted to 20 tonne.<br />
6.4 INTERACTION EFFECTS OF PASSING SHIPS<br />
Ships moored at berths may be subjected to interaction effects caused by passing ships. These interaction<br />
effects are experienced as longitudinal and transverse forces combined with a yaw movement and are most<br />
pronounced in shallow water with the passing ships in close proximity of the moored ship and moving at<br />
speed. Interaction forces combined with other external forces acting on the moored ship may cause the<br />
moored ship to range on its moorings, with the possibility of mooring lines parting.<br />
The governing parameters affecting the interaction of passing ships are the ship sizes, separation distances<br />
between moored and passing ships and the sailing speeds.<br />
> Ship Sizes; the largest tankers moored at the outer berths of Area 137 are expected to range from<br />
30,000 up to 45,000 DWT. Ships sailing in the Inbound Traffic Lane and passing the Area 137<br />
port facilities are assessed to be typically 30,000 to 40,000 DWT. Maximum ship sizes are<br />
determined by the allowable draught in the Victoria Harbour area, which amounts to 11.0 m. The<br />
maximum ship size passing Area 137 is selected at 65,000 DWT.<br />
> Separation Distances; for the determination of the separation distances it is assumed that, on<br />
average, the inbound passing ships will sail in the centre of the Inbound Traffic Lane. The<br />
calculation assumes a separation distance between the passing and moored ships of 600 m.<br />
»* Sailing Speeds; the maximum speed of inbound vessels when passing Area 137 is taken at 10 ktn.<br />
Actual sailing speeds are most probably lower considering the fact that these vessels will be under<br />
pilotage at this location.<br />
APH Consultants<br />
P&g*
Figure 6.1<br />
SHIP MANOEUVRES -<br />
BALLASTED ARRIVAL<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
The mean longitudinal and transverse interaction forces on the moored tankers, for the above conditions,<br />
are given in Table 6.4.<br />
TABLE 6.4 :<br />
MEAN INTERACTION FORCES ON MOORED TANKERS<br />
Passing Ships<br />
30,000-40,000 DWT<br />
65,000 DWT<br />
Longitudinal<br />
Transverse<br />
Longitudinal<br />
Transverse<br />
Interaction Forces (tf)<br />
(Separation Distance 600m)<br />
1.6<br />
7.0<br />
4.5<br />
20.0<br />
In addition to the interaction forces the moored tankers may be subjected to wind, wave and current forces<br />
which may amount to 7.0 to 15 tonnes depending upon wind direction.<br />
The mooring restraint forces are defined as the maximum allowable forces acting on a moored ship before<br />
mooring lines break. These forces are dependent on the type and number of mooring lines used as well<br />
as on the mooring arrangement but are assessed at 47 tonnes longitudinal and 300 tonnes transverse force<br />
for the moored tanker.<br />
The mooring restraint safety factor is defined as the mooring restraint forces divided by the total mean<br />
disturbing force on the moored ship. It is considered that this factor of safety should be at least 4 to allow<br />
for dynamic and other effects. The mooring restraint safety factors are calculated for the various<br />
conditions and are presented in Table 6.5.<br />
TABLE 6.5 :<br />
MOORING RESTRAINT SAFETY FACTOR<br />
(Separation Distance 600 m)<br />
Passing Ships<br />
30,000-40,000 DWT<br />
65,000 DWT<br />
Interaction Forces<br />
Longitudinal<br />
Transverse<br />
Longitudinal<br />
Transverse<br />
Safety Factor<br />
5.5<br />
13.6<br />
4.1<br />
8.6<br />
With the given 600 m separation distance, adequate safety margins are present for passing ships of typical<br />
size 30,000 to 40,000 DWT. For maximum ship sizes of up to 65,000 DWT passing Area 137, the safety<br />
margin is also satisfactory.<br />
6.5 DOWNTIME CONSIDERATIONS<br />
6*5,1 Introduction<br />
Vessels moored at the berths are exposed to locally generated waves and residual waves and swells coming<br />
from southerly directions. When wave induced ship motions are too large, cargo handling operations will<br />
APH Consultants Page 6-6
Figure 6.2<br />
SHIP MANOEUVRES - TYPHOON DEPARTURE<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
have to slow down or even cease, resulting in operational downtime. Acceptable ship motions are,<br />
amongst others, dependent on the ship types and sizes, type of cargoes handled and cargo handling<br />
equipment. Mainly oil and gas tankers are to be expected at the deep water berths of Area 137 and their<br />
products will be handled by loading arms.<br />
At the most northern berths general cargo vessels and small coasters can be expected. Cargo is anticipated<br />
to be handled using cranes, either onshore or onboard.<br />
6.5.2 Wave Conditions<br />
Local generated waves come from northeasterly, southeasterly and southerly directions with wave heights<br />
below 0.5 m. Residual ocean waves and swells enter through the Tathong Channel and come from a<br />
southerly direction. With the berth orientation of SSE/NNW these wave directions result in (port) stern<br />
quartering seas on the moored ships. It is assumed that vessels will be berthed bow inwards (northerly<br />
heading) as discussed in Section 6.3.<br />
The exceedence frequencies of the residual waves and swell are indicated in Table 6.6.<br />
TABLE 6.6 : WAVE EXCEEDENCE FREQUENCIES (%)<br />
Wave<br />
Height Hs<br />
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
final Report - Main Report<br />
6.5.4 Operational Downtime<br />
The operational downtime for the various vessels expected to call at Area 137, based on the above wave<br />
conditions and downtime criteria, are presented in Table 6.8.<br />
TABLE 6.8 : OPERATIONAL DOWNTIME AREA 137<br />
Vessel Type<br />
Tanker<br />
LPG Carrier<br />
General Cargo Vessel<br />
Coaster<br />
Vessel Size (DWT)<br />
30,000 - 45,000<br />
8,000 - 10,000<br />
1,200<br />
5,000 - 8,000<br />
2,000<br />
Downtime (%)<br />
0.35<br />
1.2<br />
3.4<br />
1.2<br />
3.4<br />
The operational downtimes for the various ships are all below 5%. The highest downtimes occur for the<br />
small LPG tankers and coasters. Considering the frequency of vessel calls at the port facilities (see Table<br />
6.2) the actual downtimes for all vessels will be very limited.<br />
SENT Landfill Barges<br />
The wave conditions at the Sent Landfill quays have been analysed to determine what change in<br />
operational conditions would occur in relocating the marine access from the present planned location to<br />
the proposed location at the north of the Area 137 development.<br />
The wave exceedence frequencies of the residual waves and swell, calculated at the present SENT Landfill<br />
location and at the reprovisioned location during both an initial development and for the full development,<br />
are indicated in Table 6.9.<br />
TABLE 6.9 : WAVE EXCEEDENCE FREQUENCIES AT SENT LANDFILL QUAYS (%)<br />
Wave Height<br />
Hs(m)<br />
Landfill<br />
5 sec<br />
Location<br />
7 sec<br />
Area 137 Initial<br />
Wave Period Tp<br />
5 sec 7 sec<br />
Area 137 Final<br />
5 sec 7 sec<br />
0.5<br />
0.55<br />
0.42<br />
0.21<br />
0.19<br />
0.60<br />
0.42<br />
0.7<br />
0.05<br />
0.04<br />
0.01<br />
.<br />
0.06<br />
0.05<br />
1.0<br />
~<br />
,<br />
-<br />
.<br />
,<br />
.<br />
There will be minimal change in wave conditions between the alternative quay locations. In all cases, the<br />
frequency of the critical wave heights and periods is less than 1 %, and downtime for the SENT Landfill<br />
barges will be very limited and effectively unchanged.<br />
APH Consultants<br />
fage
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
6.6 PILOTAGE AND AIDS TO NAVIGATION<br />
6.6.1 Pilotage<br />
The pilot station for shipping traffic using the Tathong Channel is at present located approximately<br />
between Hak Kok Tan and Tit Cham Chau. With the development of Area 137, and possibly also Area<br />
131, this pilot boarding station will need to be relocated to a position off Tai Long PaL<br />
This relocation would result in an additional sailing distance of some 1.75 nm for the pilot cutter.<br />
Considering the marine traffic intensity in the Tathong Channel in 2011 and the number of vessels<br />
requiring a pilot (over 1,000 GRT for vessels with dangerous cargoes), this additional sailing distance<br />
appears acceptable for a high speed pilot cutter.<br />
Wave and weather conditions at the proposed site are only slightly more onerous than at the present<br />
location and it is not expected that pilot boatding operations would be significantly affected by relocating<br />
the boarding station.<br />
6.6*2 Aids to Navigation<br />
The approach routes to the new port facilities are all located in deep water and no specific aids to<br />
navigation to mark these routes are required.<br />
The port facilities will be marked by shore based beacons as indicated on Figure 6,3.<br />
6.63 Tathong Channel Traffic Separation System (TSS)<br />
In order to maintain the 600 m separation distance between passing ships in the Inbound Traffic Lane of<br />
the TSS and vessels berthed at Area 137, and to separate as much as possible passing ships from ships<br />
manoeuvring for the berths, a realignment of the TSS off the berthing face is required. This involves<br />
easing the present course change of some 35° by "cutting the corner 11 and reducing the present course<br />
change to two smaller course changes, about 0.8 run apart. Figure 6.3 indicates the nature of this<br />
realignment, together with the aids to navigation requirements. IMO approval will be required for this<br />
revised channel alignment.<br />
6,7 ANCHORAGES<br />
6.7.1 Tseung Kwan O Mooring Buoys<br />
The Study is required to consider the continued use of the three mooring buoys (A60, A61 and A62) in<br />
Tseung Kwan O in conjunction with the development of Area 137 facilities.<br />
The PHI development and operation of the Area 137 port facilities will not require the use of these<br />
mooring buoys, since the handling of hazardous cargoes at the mooring buoys would be inappropriate and<br />
not permitted under the existing ordinances, The lack of definition of the requirements for DWI<br />
operations do not permit recommendations to be made upon the suitability of retaining these buoys in<br />
relation to these operations.<br />
6*7*2 Dangerous Goods Anchorage<br />
The dangerous goods anchorage in Tseung Kwan O is presently used by a limited number of vessels:<br />
approximately one to two vessels per week. The vessels utilising the proposed Area 137 facilities will<br />
be carrying potentially hazardous cargoes. It is considered that the use of the existing dangerous goods<br />
APH Consultants Page 6*9
Figure 6.3<br />
TSEUNG<br />
(Junk Bay)<br />
KWAN<br />
r» Long Wan M<br />
Wave Bay}<br />
PROPOSED FAIRWAY REALIGNMENT<br />
AND AIDS TO NAVIGATION<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
anchorage would introduce unnecessary risks and in the occasional circumstances when a waiting<br />
anchorage is required then the vessel should utilise the existing dangerous goods anchorage to the south<br />
of Lamma Island. The frequency of this usage should, however, be monitored and, if required, a new<br />
dangerous goods anchorage could be established nearer Area 137, possibly between Tung Lung Chau and<br />
the Ninepins.<br />
6*7*3 Quarantine and Immigration<br />
The existing quarantine and immigration anchorage for vessels approaching from the east is located in<br />
Kowloon Bay off Kai Tak. Any requirement for vessels carrying dangerous goods or potentially<br />
hazardous cargoes to utilise this anchorage would again introduce unnecessary risks. The designation of<br />
an alternative anchorage seaward of the proposed development would be equally inappropriate given the<br />
nature of the current method of clearance.<br />
It therefore recommended that pre-entry clearance should be granted wherever possible and failing this,<br />
clearance should be granted when the vessel is on the berth as is the current practice in many international<br />
ports. This is not currently done in Hong Kong and Immigration Department's resources may therefore<br />
be limited for such duties.<br />
6.8 NAVIGATIONAL RISK AND VESSEL TRAFFIC CONTROL<br />
6.8.1 Introduction<br />
The development of Area 137 port facilities will generate additional marine traffic in the Tathong Channel.<br />
Ocean going vessels will arrive from the south and river trade vessels and barges will pass through Lei<br />
Yue Mun.<br />
In addition, the marine traffic in this area will increase due to the expected growth of the total marine<br />
traffic calling at Hong Kong and due to Vessel Traffic Management regulations (as discussed in Section<br />
6.2).<br />
6.8.2 Navigation Risks<br />
Arriving ocean going vessels for Area 137 have minimal interference with other marine traffic. Pilots will<br />
board in the approaches and follow the Inbound Traffic Lane of the Tathong Channel. After passing Tung<br />
Lung Chau they make their approach to the berths of Area 137, The number of vessels within the TSS<br />
and in the Eastern Inshore Traffic Zone is very low and the risk of collision with these vessels is equally<br />
low.<br />
During the final approaches to the berths, it is considered that safe arrival and berthing manoeuvres can<br />
be made when sufficient tug assistance and clear aids to navigation (on the quays) are provided.<br />
Ships should be unberthed with sufficient tug assistance and should be well lined up for departure.<br />
Departing ships have to cross the Inbound Traffic Lane to join other marine traffic in the Outbound Traffic<br />
Lane of the TSS in the Tathong Channel. As is discussed in Section 6.3 the time required to cross the<br />
Inbound Traffic Lane is short and amounts to some 5 minutes.<br />
During these departure manoeuvres there is a potential risk of collision with inbound or outbound traffic<br />
in the Tathong Channel and a proper timing and monitoring procedure will be essential. The probabilities<br />
of collision are very low in view of the traffic intensities in the Tathong Channel and frequency of<br />
departure manoeuvres from Area 137. Nevertheless, unberthing and departure manoeuvres should not<br />
commence prior to receiving advice from the VTS on committed vessel movements in the Tathong<br />
APH Consultants Page 6-10
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
Channel. In particular during typhoon evacuations the departure manoeuvres should be closely monitored<br />
by VTS.<br />
River trade vessels and barges destined for Area 137 will all be handled at the northern basin and there<br />
will therefore be little interference with the ocean going ships for Area 137.<br />
Vessels destined for Area 137 and coming through Lei Yue Mun, sailing in the Outbound Traffic Lane,<br />
have to cross the Inbound Traffic Land when entering the northern basin. During these crossings potential<br />
collisions with other traffic is present. A proper timing of manoeuvres, monitored by the VTS, is hence<br />
required.<br />
6.8.3 Marine Support<br />
The requirements for tug assistance for the different classes of vessels utilising the proposed facility have<br />
been discussed in Section 6.3.2. Tugs are presently based in the vicinity of Tsing Yi and there are<br />
proposals for relocating their base to Lantau Port. Thus there is a response time for the tugs of the order<br />
of 1 hr, which would be acceptable under normal operating conditions. However, in an emergency<br />
involving the need for immediate departure or fire fighting assistance then a more rapid response would<br />
be required.<br />
It is recommended that a minimum of 2 tugs, with fire fighting capabilities, should be stationed at the<br />
proposed facility and provision should be made for quayside support and a berth allocation of some 30m.<br />
6.8.4 Vessel Traffic Control<br />
All vessel traffic movements to and particularly from the planned port facilities of Area 137 should be<br />
monitored by the VTS. A good radar coverage of the approach routes is hence required. The present<br />
Vessel Traffic Services system and location of radar sites in Hong Kong is indicated in Figure 6.4.<br />
It is understood that the proposed berthing line of Area 137 is located just inside the blind sector of the<br />
Waglan radar coverage. However discussions with the Marine Department have indicated that this minor<br />
limitation would be acceptable and that no additional radar locations would be required.<br />
Recent developments have, however, indicated that Marine Department may lose the facilities currently<br />
provided by the ASDE radar at Kai Tak. The establishment of a replacement and the timing and siting<br />
of the new facility have yet to be finalised; further consultation will therefore be necessary with Marine<br />
Department to determine the future marine traffic levels and capability of the VTS at the time the Area<br />
137 development is scheduled to be implemented.<br />
APH Consultants<br />
Page
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
SECTION 7<br />
TRAFFIC AND TRANSPORT STUDY<br />
7.1 TRAFFIC FORECASTS<br />
7.1.1 Development Assumptions<br />
Traffic forecasts in Hong Kong are generally made within the context of the Comprehensive Transport<br />
Study (CTS-2) model, which enables the forecasts to be placed within an agreed framework of assumptions<br />
which are consistent between studies. This Study has made use of the CTS-2 forecasts provided by<br />
Government. The population and employment levels underlying the forecasts are summarised in Tables<br />
7.1 and 7.2.<br />
The implied development assumptions are consistent with Metroplan objectives and represent the<br />
assumptions in general use for transport planning studies in Hong Kong at the time of the current Study.<br />
The figures are under review, partly as a result of the 1991 Census showing lower population figures than<br />
had been expected, with the implication of lower population growth rates. There is also the possibility that<br />
Phase 3 of Tseung Kwan 0 could be developed to a higher level leading to a population of the order of<br />
440,000 by 2011. Sensitivity tests have investigated the impact on the Study findings of changes in the<br />
population assumptions.<br />
TABLE 7.1 :<br />
POPULATION DISTRIBUTION UNDERLYING THE FORECASTS<br />
(Units; OWs)<br />
Year<br />
Area<br />
1991 1996 2001 2006 2011<br />
Tseung Kwan 0<br />
Sai Kung<br />
Clear Water Bay<br />
New Territories<br />
Hong Kong Island<br />
Kowloon<br />
84<br />
30<br />
3<br />
2250<br />
1295<br />
2144<br />
153<br />
34<br />
19<br />
2581<br />
1359<br />
1955<br />
241<br />
26<br />
12<br />
2641<br />
1316<br />
2099<br />
243<br />
25<br />
12<br />
2701<br />
1362<br />
2160<br />
333<br />
24<br />
11<br />
2746<br />
1362<br />
2151<br />
Total 5811 6101 6335 6503 6627<br />
APH Consultants Page 7-1
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 72 :<br />
EMPLOYMENT DISTRIBUTION UNDERLYING THE FORECASTS<br />
(Units; OOO's)<br />
Area<br />
1991<br />
1996<br />
Year<br />
2001<br />
2006<br />
2011<br />
Tseung Kwan 0<br />
34<br />
38<br />
57<br />
76<br />
85<br />
Sai Kung<br />
13<br />
7<br />
5<br />
5<br />
5<br />
Clear Water Bay<br />
4<br />
9<br />
11<br />
10<br />
11<br />
New Territories<br />
95S<br />
991<br />
1051<br />
1092<br />
1130<br />
Hong Kong Island<br />
781<br />
922<br />
916<br />
931<br />
893<br />
Kowloon<br />
1030<br />
1042<br />
1091<br />
1092<br />
1123<br />
Total<br />
2820<br />
3009<br />
3131<br />
3206<br />
3247<br />
The Metroplan based assumptions indicate that Tseung Kwan O is expected to quadruple in size between<br />
1991 and 2011 in terms of population, with the major growth between 1991 and 2001, and then between<br />
2006 to 2011. The employment figures suggest about 30,000 jobs were planned to be located there by<br />
1991; recent results from the Travel Characteristics Survey indicate this may be on the high side with the<br />
current figure of around 10,000 reflecting the reluctance of employers to relocate to the New Towns<br />
unless there are specific opportunities associated with the move. The Metroplan assumptions indicate<br />
about 85,000 jobs by 2011 would be located in Tseung Kwan O.<br />
The forecast of population in Tseung Kwan O is largely based on Housing Department plans as the<br />
Housing Programme is well defined; although there is the potential for a major variation in the extent of<br />
completion of Phase 3, and the implications of this have been examined. A minor variation could occur<br />
in the degree of vacancy and take-up of flats, but this is expected to be small and well within the limits<br />
of accuracy in forecasting. It should also be noted that the population forecast for 1991 was similar to<br />
what was recorded in the 1991 Census and the 1992 Travel Characteristics Survey. The population<br />
forecast can therefore be viewed as firm and reliable.<br />
As discussed above, the forecasts of employment are less definitive. There is no corresponding control<br />
on employment location other than planning permission on land use. This cannot specify the number or<br />
detailed type of jobs, or encourage employment to be relocated to areas such as Tseung Kwan O, The<br />
forecast of about 30,000 jobs to be located in Tseung Kwan O by 1991 has not been met. The target of<br />
85,000 jobs by 2011 excludes the industrial developments considered in this Study. There must be some<br />
doubt as to whether or not this target will be met, although the Area 137 and TKOIE developments may<br />
be the necessary stimulus to achieve this figure.<br />
7*1.2 Infrastructure Assumptions<br />
The major infrastructure development over the next fifteen to twenty years is likely to concentrate on<br />
improving access through West Kowloon for the Airport related projects and also providing access to areas<br />
of new reclamation. The items of highway construction which most effect Tseung Kwan O are as follows:<br />
* completion of Lung Cheung Road Improvements (by 2001);<br />
* Hung Horn Bypass and Princess Margaret Road Link (by 2001);<br />
> Kai Tak Connector between Kai Tak and Kwun Tong (by 2006);<br />
» Kowloon Bay Reclamation Roads (by 2011).<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
It should be noted that the Kai Tak Connector as currently proposed is planned to terminate at the junction<br />
with Cha Kwo Ling Road.<br />
Assumptions for the phasing of the future year networks for the New Town are based on information from<br />
Plan TK2019C - Road Completion Dates, Tseung Kwan 0 (dated 23.3.92), supplied by TDD's SENT<br />
Development Office. The current programme of road development is illustrated in Figure 7.1.<br />
Area 137 would be connected by a single road, proposed as Road D6, which is scheduled to be completed<br />
by 1999. However, in accordance with the development programme for Area 137, the completion date<br />
for Road D6 is required to be brought forward to 1997.<br />
By 2011, all the major roads connecting external accesses to Road D6 would be completed. These include<br />
the following:<br />
> Cross Bay Bridge Road D9 (Dual-2 lane)<br />
> Road PI, North of D6 (Dual-2 lane)<br />
> Easterly Link Road connecting PI and D3 (Single lane)<br />
The Cross Bay Bridge Road is indicated on plan TK2019C as constructed by 2003-2004; for the purposes<br />
of network testing it is assumed to be completed by 2006, The Western Coast Road is shown on the plan<br />
as having the first carriageway completed by 2000 and the second carriageway completed by 2002. This<br />
is in accordance with the findings of the TKOFSOFD which identified a need for this road by 2001.<br />
However, for the purposes of critically examining the implications of the timing of the provision of the<br />
Western Coast Road it has been assumed to be deferred until 2006.<br />
Road PI between Tl and D4, programmed for completion by 2001, wouid need to be brought forward<br />
in line with the industrial developments in TKO if industrial traffic is to avoid the Hang Hau area.<br />
The proposed MTR extension to Tseung Kwan O is assumed to be open by 2006 and to be operated by<br />
means of split working of the Kwun Tong line service between the Tseung Kwan O line and the Eastern<br />
Harbour Crossing to Quarry Bay. There would be four stations at Tiu Keng Leng, Tseung Kwan 0 Town<br />
Centre, Hang Hau and Po Lam, Whilst the opening of the MTR extension by 2006 comes from the<br />
assumptions for the CTS-2 Update Study, and confirmed by the provisional findings of the Rail<br />
Development Study, there is as yet no firm commitment that it will be constructed,<br />
7.1.3 Industrial Development<br />
The CTS-2 forecasts do not make any allowance for travel associated with the following specific sites.<br />
These are;<br />
* Planning Area 87; this site is planned as the location of the TKOIE<br />
> Planning Area 101; this has been identified as a landfill site<br />
* Planning Area 137; this is the subject of the Study<br />
> Planning Area 131; this has been proposed for dockyard development<br />
»• Planning Area 86; assumed light industry<br />
It is estimated that about 1,700 jobs are associated with Area 137, while the TKOIE would provide of the<br />
order of 10,000 to 15,000 jobs. With the Metroplan employment levels this would give a total of some<br />
100,000 jobs in Tseung Kwan 0 in 2011.<br />
The traffic forecasts include the trips generated and attracted by each of these sites. These have been<br />
forecast by applying trip rates to the estimates of development at each of the sites. Area 137 was<br />
disaggregated into 18 detailed zones prior to estimating the trip making in order to provide sufficient detail<br />
APH Consultants Page 7-3
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
final Report - Main Report<br />
in the traffic analysis to plan the detailed network serving the area. The trip rates were derived from<br />
observation of trip making elsewhere in Hong Kong at locations of similar land use to that planned in<br />
Tseung Kwan 0. The sites surveyed include the Tai Po Industrial Estate and the Tsing Yi Oil Depot Area<br />
22; trip rates have also been abstracted from the SENT Landfill Study, NWNT Open Storage Areas<br />
Traffic Impact Study and surveys of container storage areas in the Castle Peak Road Corridor Study. Trip<br />
rates are summarised in Table 7.3 below.<br />
The trip rates relate the volume of goods vehicle traffic generated and attracted to a site to the extent of<br />
development expressed per 100 square metres of development area. The volume of private vehicles is<br />
related to the number of workers and represents the journey to work by car and business travel.<br />
TABLE 7.3 :<br />
TRIP RATES FOR PEAK PERIODS (pcus per hour)<br />
Land Use<br />
Goods Vehicle Rates per 100m 3<br />
Potential Hazardous Industry<br />
Deep Water Industry<br />
Private Vehicle Rates per Worker<br />
Average Industry<br />
AM Peak<br />
Attraction Generation<br />
0.042 0.071<br />
0.270 0.270<br />
0.114 0.066<br />
PMPeak<br />
Attraction Generation<br />
0.023 0.032<br />
0.270 0.270<br />
0.057 0.127<br />
The land use pattern assumed for Area 137 is summarised in Table 7.4 below by the 18 traffic zones,<br />
together with the number of trips generated by the development. The full development is expected to<br />
increase traffic volumes in the AM peak by about 900 pcu's per direction.<br />
Figure 7.2 illustrates the travel patterns for Area 137 trips in the AM and PM peaks. These have been<br />
estimated by assigning the forecast travel to and from Area 137 to the highway networks.<br />
The total generation and attractions produced by all the industrial developments on the peninsula are<br />
summarised in Table 7.5 below. The increase in traffic is about 3,100 pcus in the peak direction; goods<br />
vehicles form about 56% of the traffic, a proportion which is similar to other industrial areas. The<br />
majority of this traffic is expected to travel to or from areas outside of Tseung Kwan O, rather than be<br />
short intra New Town trips. The goods vehicles are likely to be distributing or carrying loads to all parts<br />
of the Territory, whilst the car trips are typically in-course-of-work trips by senior managers; many of<br />
these trips will also be external. Of the extra 3,100 pcus in the AM peak direction, 80% are expected to<br />
be external trips.<br />
The impact of the industrial areas on the total travel demand from Tseung Kwan O in 2011 is shown in<br />
Table 7.6 below by internal/external movements. The developments increase the extent of internal trips,<br />
but by a small proportion. Total external travel increases by 23%. Goods vehicles form the majority of<br />
the traffic stream.<br />
There is more travel associated with the industrial developments in the PM peak, but travel volumes for<br />
Tseung Kwan O, as a whole, are highest in the morning, with journeys to and from work. The majority<br />
of the subsequent traffic analysis therefore concentrates on the AM peak.<br />
APH Consultants Page 7-4
Figure 7.2<br />
NENT<br />
AM PEAK<br />
TRAVEL PATTERN<br />
W/NWNT<br />
& Lantau<br />
TKO<br />
Rest of<br />
Kowloon<br />
Hong Kong<br />
Island<br />
W/NW NT<br />
NENT<br />
PM PEAK<br />
TRAVEL PATTERN<br />
Rast of<br />
Kowloon<br />
Hong Kong<br />
Island<br />
LEGEND:<br />
36 PCUS FROM AREA 137<br />
(28) PCUS TO AREA 137<br />
TRAVEL PATTERN OF TRIPS FOR AREA 137<br />
APH CONSULTANTS
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
TABLE 7.4 :<br />
DEVELOPMENT OF TRAVEL DEMANDS FOR AREA 137 {pcus per hour)<br />
Zone* Land Use<br />
1 Fuel Storage<br />
Area (m 2 )<br />
100900<br />
Gen.<br />
87<br />
AM Peak<br />
Att.<br />
69<br />
PM Peak<br />
Gen. Att.<br />
62<br />
36<br />
2 Chemical Storage<br />
107200<br />
92<br />
73<br />
65<br />
39<br />
3 LPG<br />
96100<br />
83<br />
65<br />
59<br />
35<br />
4 Gas<br />
109500<br />
95<br />
75<br />
67<br />
39<br />
5 PHI-Related<br />
49200<br />
43<br />
34<br />
30<br />
17<br />
6 PHI-Rckted<br />
22600<br />
19<br />
15<br />
14<br />
8<br />
7 DWI<br />
17000<br />
34<br />
35<br />
36<br />
33<br />
8 DWI<br />
9500<br />
18<br />
20<br />
20<br />
18<br />
9 DWI<br />
15200<br />
29<br />
31<br />
31<br />
29<br />
10 DWI<br />
24500<br />
48<br />
50<br />
51<br />
47<br />
11 DWI<br />
13600<br />
26<br />
23<br />
28<br />
26<br />
12 DWI<br />
50300<br />
99<br />
104<br />
106<br />
98<br />
13 DWI<br />
30600<br />
60<br />
63<br />
64<br />
59<br />
14 DWI<br />
23200<br />
46<br />
48<br />
49<br />
45<br />
15 DWI<br />
22200<br />
43<br />
46<br />
47<br />
43<br />
16 SENT Landfill Access<br />
12500<br />
27<br />
28<br />
29<br />
27<br />
17 Services<br />
10000<br />
22<br />
23<br />
23<br />
21<br />
IS<br />
DWI<br />
16800<br />
33<br />
34<br />
35<br />
32<br />
Total<br />
730900<br />
904<br />
841<br />
816<br />
652<br />
* Locations of zones are shown in Figure 7 5<br />
TABLE 7.5 :<br />
ADDITIONAL TRAVEL FROM THE INDUSTRIAL DEVELOPMENT (pcus per hour)<br />
AM Peak<br />
PMPeak<br />
Planning Area<br />
Gen.<br />
Att<br />
Gen.<br />
Att.<br />
87<br />
764<br />
1226<br />
750<br />
432<br />
137<br />
904<br />
841<br />
816<br />
652<br />
101<br />
138<br />
151<br />
390<br />
377<br />
131<br />
297<br />
342<br />
345<br />
296<br />
36<br />
372<br />
550<br />
569<br />
372<br />
Total<br />
2475<br />
3110<br />
2870<br />
2129<br />
APH Consultants Page 7-5
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report • Main Report<br />
TABLE 7.6 :<br />
COMPOSITION OF TSEUNG KWAN O TRAFFIC, 2011 (pcus per hour)<br />
External<br />
Total<br />
Percent<br />
Internal<br />
Outbound<br />
Inbound<br />
Internal<br />
Without Industrial<br />
Development<br />
AM Private<br />
AM Goods<br />
AM Total<br />
1958<br />
1298<br />
3256<br />
2260<br />
5223<br />
7483<br />
2184<br />
4992<br />
7176<br />
6402<br />
11613<br />
17915<br />
31%<br />
11%<br />
18%<br />
PM Private<br />
256<br />
1900<br />
847<br />
3003<br />
9%<br />
PM Goods<br />
1106<br />
4524<br />
4199<br />
9829<br />
11%<br />
PM Total<br />
1362<br />
6424<br />
5046<br />
12832<br />
11%<br />
With Industrial<br />
Development<br />
AM Private<br />
3654<br />
2655<br />
3358<br />
9667<br />
38%<br />
AM Goods<br />
2061<br />
7472<br />
7031<br />
16564<br />
12%<br />
AM Total<br />
5715<br />
10127<br />
10389<br />
26231<br />
22%<br />
PM Private<br />
529<br />
2807<br />
1086<br />
44°2<br />
12%<br />
PM Goods<br />
1876<br />
6581<br />
6158<br />
14615<br />
13%<br />
PM Total<br />
2405<br />
9388<br />
7244<br />
19037<br />
13%<br />
Note:<br />
Private vehicles include taxis, cars and special purpose buses. Fixed route public transport services are omitted.<br />
7.1.4 Framework of the Analysis<br />
The traffic flows have been analysed at three levels of detail. The territory-wide flows have been analysed<br />
to set the boundary volumes for the Kowloon network, including Tseung Kwan O. The Kowioon network<br />
has been used to examine the strategic flows. This has then been followed by a more detailed analysis<br />
of the traffic flow within Tseung Kwan 0 to examine the movements at individual junctions, and<br />
determine the impact of the development on the road system .<br />
7.2 THE EXTERNAL NETWORK<br />
7,2.1 External Links<br />
The three existing links which provide access between Tseung Kwan O and Kowloon are Po Lam Road,<br />
Tseung Kwan O Tunnel and Hung Hau Road. Hung Hau Road provides access to Tseung Kwan 0 in the<br />
east from Clear Water Bay Road and carries traffic from the Sai Kung area. While Hang Hau Road is<br />
planned to be improved to a dual two lane standard by 2011, its capacity is limited by the roundabouts<br />
at Road D3 and Clearwater Bay Road. The proposed Western Coast Road will provide an additional<br />
access route across the western screenline.<br />
APH Consultants Page 7-6
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
The performance of the western external links are shown in Table 7.7 in terms of their peak hour<br />
voiume-to-capacity ratio (v/c ratio). A v/c ratio of 1.0 indicates the threshold of overloading, and<br />
corresponds to a level of service for operation of D. This is characterised as high density but stable flow;<br />
small increases will cause operational problems. Links can generally function up to a v/c ratio of about<br />
1.2, but with likelihood of increasing congestion and unstable flow. The capacity used is the minimum<br />
of mid-block and junction capacity.<br />
7.2.2 Improvements in Yau Tong Area<br />
The initial traffic forecasts assumed that there were no improvements to the road network in the Yau Tong<br />
area to carry the increased traffic volumes resulting from the construction of the Western Coast Road.<br />
This would lead to serious congestion in the Yau Tong area and the Western Coast Road not being fully<br />
utilised whilst the Tseung Kwan O tunnel would be seriously overloaded. Clearly there would need to<br />
be improvements in capacity in the Yau Tong area to match the increased through traffic.<br />
Table 7.7 also shows the travel demand and v/c ratios for the major links in the AM peak when Lei Yue<br />
Mun Road is assumed to be upgraded to dual 3-lane for the section between Western Coast Road and<br />
Kwun Tong Road, and Cha Kwo Ling Road is assumed to be upgraded to dual 2-lane for the section<br />
between Western Coast Road and Kwun Tong Bypass. With these improvements the flows across the<br />
screenline (Western Coast Road, Po Lam Road, TKO Tunnel and Hang Hau Road) are better balanced<br />
and the Western Coast Road is better utilised. These upgradings are illustrative of the scale and type of<br />
improvements which would be required in order to ensure that the capacity offered by the Western Coast<br />
Road is used to its full. Further detailed examination of these improvements will be required.<br />
TABLE 7.7 :<br />
2011 TRAFFIC FLOWS, AM PEAK, WITH AND WITHOUT IMPROVEMENTS IN YAU TONG<br />
(pcus per hour, v/c ratio in brackets)<br />
Link<br />
Practical Link<br />
Capacity<br />
Direction<br />
Not Improved<br />
Improved<br />
Cha Kwo Ling Road/WCR<br />
Connector<br />
3600<br />
3600<br />
W<br />
E<br />
1550(0.43)<br />
1400(0.39)<br />
1800(0.50)<br />
2000(0.56)<br />
Lei Yue Mun Road/<br />
WCR Connector<br />
3600<br />
3600<br />
W<br />
E<br />
2250(0.63)<br />
2350(0.65)<br />
2850(0.79)<br />
2600(0.72)<br />
Western Coast Road<br />
5400<br />
5400<br />
W<br />
E<br />
3750(0.69)<br />
3750(0.69)<br />
4650(0.86)<br />
4600(0.85)<br />
Po Lam Road<br />
1500<br />
1300<br />
W<br />
E<br />
1050(0.70)<br />
1200(0.92)<br />
1000(0.67)<br />
1000(0.77)<br />
Tseung Kwan O Tunnel<br />
3600<br />
3600<br />
W<br />
E<br />
4850(1.35)<br />
4800(1.33)<br />
4050(1.13)<br />
4250(1.18)<br />
Hang Hau Road<br />
2200<br />
1600<br />
N<br />
S<br />
1900(0.86)<br />
1650(1.03)<br />
1850(0.84)<br />
1550(0.97)<br />
7.2.3 External Access<br />
Tables 7.8 and 7.9 summarise forecast traffic demand on external access links for AM peak and PM peak<br />
respectively. The major underlying assumptions in the analysis are:<br />
> population of 333,000 and 85,000 jobs in Tseung Kwan O by 2011;<br />
*• inclusion of traffic from ail the industrial developments;<br />
APH Consultants Page 7*7
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
improvements in road capacity in the Yau Tong area as discussed above in Section 7.2.2;<br />
dangerous goods vehicles will use Po Lam Road prior to the opening of the Western Coast Road;<br />
the Western Coast Road is assumed to be delayed until 2006.<br />
TABLE 7.8 :<br />
AM PEAK TRAFFIC VOLUMES ON EXTERNAL ACCESS<br />
(We ratio in brackets)<br />
External Access<br />
Dir<br />
Practical<br />
Capacity<br />
1996<br />
2001<br />
Volume (pcu)<br />
2006<br />
2011<br />
Po Lam Road<br />
W<br />
E<br />
1500<br />
1300<br />
950
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
southern Tseung Kwan 0. This clearly points to the need for the Western Coast Road to be in operation<br />
by 2001.<br />
Traffic flows across the external screenline in 2001 with and without the Western Coast Road are shown<br />
in Table 7.10. The opening of the Western Coast Road in 2001 provides the required relief to the<br />
overloaded external links, with the v/c ratio for the screenline as a whole in the AM peak of around 0.65<br />
and all links on the screenline within capacity. Flow across this western screenline now also attracts an<br />
additional 400 pcus thereby providing relief to Hang Hau Road and Clearwater Bay Road.<br />
TABLE 7 JO :<br />
TRAFFIC VOLUMES IN 2001 WITH AND WITHOUT THE WESTERN COAST ROAD<br />
(pcus per hour)<br />
External Access<br />
Without WCR<br />
With WCR<br />
AM<br />
PM<br />
AM<br />
PM<br />
Po Lam Road<br />
W<br />
E<br />
1600(1.07)<br />
1450(1.12)<br />
1350(0.90)<br />
900(0.69)<br />
1100(0.73)<br />
1100(0.85)<br />
1100(0.73)<br />
700(0.54)<br />
TKO Tunnel<br />
W<br />
E<br />
4700(1.31)<br />
5000(1.39)<br />
4450(1.24)<br />
4150(1.15)<br />
2650(0.74)<br />
3250(0.90)<br />
2600(0.72)<br />
2600(0.72)<br />
WCR<br />
W<br />
E<br />
-<br />
-<br />
2950(0.55)<br />
2550(0.48)<br />
2350(0.44)<br />
2000(0.37)<br />
Screenline Total<br />
W<br />
E<br />
6300(1.24)<br />
6450(1.32)<br />
5800(1.14)<br />
5050(1.03)<br />
6700(0.64)<br />
6900(0.66)<br />
6050(0.53)<br />
5300(0.51)<br />
Subsequent traffic analyses assumes that the Western Coast Road will be provided by 2001, in line with<br />
the recommended road development programme.<br />
Road D9, the Cross Bay Bridge Road, is currently programmed for construction at 2003-2004. The<br />
impact of bringing forward this link to 2001 has also been examined. Table 7.11 shows that in overall<br />
terms, its construction has marginal impact on total traffic volume using the western external access links.<br />
However, the balance of flows between the Western Coast Road and the TKO Tunnel is changed, with<br />
between 400 and 600 additional pcus now using the Western Coast Road.<br />
TABLE 7.11 :<br />
TRAFFIC VOLUMES IN 2001 WITH AND WITHOUT THE CROSS BAY BRIDGE ROAD<br />
(ROAD D9) (pcus per hour)<br />
External Access<br />
Without Road D9<br />
With Road D9<br />
AM<br />
PM<br />
AM<br />
PM<br />
Po Lam Road<br />
W<br />
E<br />
1100(0.73)<br />
1100(0.85)<br />
1100(0.73)<br />
700(0.54)<br />
1100(0.73)<br />
1050(0.31)<br />
1100(0.73)<br />
750(0.58)<br />
TKO Tunnel<br />
W<br />
E<br />
2650(0.74)<br />
3250(0.90)<br />
2600(0,72)<br />
2600(0.72)<br />
2250(0.63)<br />
3000(0.83)<br />
2000(0.56)<br />
2000(0.56)<br />
WCR<br />
W<br />
E<br />
2950(0.55)<br />
2550(0.48)<br />
2350(0.44)<br />
2000(0.37)<br />
3350(0.62)<br />
3000(0.33)<br />
3000(0.85)<br />
2600(0.72)<br />
Screeniine Total<br />
W<br />
E<br />
6700(0.64)<br />
6900(0.66)<br />
6050(0.58)<br />
5300(0.51)<br />
6700(0.64)<br />
7050(0.67)<br />
6100(0.58)<br />
5350(0.51)<br />
AfH Consultants Page 7-9
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
A proportion of the external traffic uses Hang Hau Road, including travellers to Sai Kung and to parts of<br />
the North East New Territories via Hiram's Highway. There is also a small amount of through traffic<br />
from these areas, amounting to some 700 pcus, which uses Hang Hau Road and either TKO Tunnel or<br />
Western Coast Road. Traffic on Hang Hau Road by 2011 is of the order of 1600 to 1900 pcus per<br />
direction, which is close to its practical capacity at that time.<br />
Traffic volumes along the Clearwater Bay Road are forecast to be some 1600 to 2500 pcus depending on<br />
the section. This is made up of Tseung Kwan O traffic to Sai Kung and North East New Territories and<br />
non-Tseung Kwan O traffic from Sai Kung and North East New Territories heading for the urban area.<br />
The major movements are to and from Sai Kung and vehicles using Hiram's Highway. Higher traffic<br />
volumes than forecast may occur along this corridor as the pressure for additional residential development<br />
in its catchment area is not reflected in the planning inputs.<br />
7*2.4 Sensitivity Test for 2011 Network on Reduced Level of Self-Containment<br />
Self-containment is an indicator of the ability of a town or city to cater for the needs of its residents. The<br />
planning of a New Town strives for a high level of self-containment, but in Hong Kong the competition<br />
from other urban attractors tends to reduce this, and there are generally significant movements between<br />
the New Towns and the urban area.<br />
The main series of traffic analyses have used the amount of self-containment implied for Tseung Kwan<br />
O by the CTS-2 forecasts. However, if self-containment is over-estimated, an under-provision of transport<br />
capacity may result. An analysis of the CTS-2 travel demands indicated that in the forecasts of private<br />
vehicles the self-containment for Tseung Kwan O was somewhat higher than for other areas such as<br />
Shatin, Kwun Tong and Aberdeen/Wong Chuk Hang. Whilst there may well be good reasons why this<br />
could come about, a sensitivity test was undertaken to demonstrate the impact of reduced self-containment<br />
for private vehicles on traffic volumes.<br />
The test was carried out by reducing the level of self-containment by 20%. The most significant impact<br />
of the change in self-containment is on the external access to Tseung Kwan O. Table 7.12 shows the<br />
resultant traffic demand volumes for 2011 network for the AM peak. The additional external traffic puts<br />
marginally more pressure on the external links with total external travel increasing by 6%. The screenline<br />
as a whole is at capacity in the AM peak, but the imbalances within the screenline make the TKO Tunnel<br />
more overloaded than for the base condition, further strengthening the need for measures such as increased<br />
tolls to encourage diversion to the Western Coast Road.<br />
TABLE 7.12 :<br />
IMPACT OF REDUCED SELF-CONTAINMENT, 2011 AM PEAK (flows in pens per hour)<br />
External Access<br />
Dir<br />
Practical<br />
Capacity<br />
Ftow<br />
Base Case<br />
v/c<br />
Reduced<br />
Self- Containment<br />
Flow<br />
V/C<br />
Pa Lam Road<br />
W<br />
E<br />
1500<br />
1300<br />
1000<br />
1000<br />
0.67<br />
0.77<br />
1150<br />
1100<br />
0.77<br />
0.88<br />
TKO Tminci<br />
WCR<br />
W<br />
E<br />
W<br />
E<br />
3600<br />
3600<br />
5400<br />
5400<br />
4050<br />
4250<br />
4650<br />
4600<br />
1.13<br />
1.1S<br />
0.86<br />
0.85<br />
4150<br />
4400<br />
5000<br />
4950<br />
1.15<br />
1.22<br />
0.93<br />
0.92<br />
Screenline<br />
Total<br />
W<br />
E<br />
10500<br />
10300<br />
9700<br />
9S50<br />
0,92<br />
0.96<br />
10300<br />
10450<br />
0.98<br />
1.01<br />
APH Consultants Page 7-10
Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
7.2.5 The MTR Tseung Kwan O Extension<br />
The traffic analysis has assumed the construction of the MTR and its opening by 2006. The implication<br />
for external links if there is no MTR Extension is shown in Table 7.13. It is assumed that most of the<br />
would-be MTR passengers would switch to the bus service.<br />
In this scenario, some 600 extra pcus would cross the external screenline in the AM peak. In 2006 the<br />
external screenline operates at a v/c ratio of 0.73 overall and can therefore accommodate the extra traffic.<br />
For 2011, the additional traffic would cause the total screenline to operate at a v/c ratio of 1.02, but TKO<br />
Tunnel would be heavily overloaded.<br />
It must be noted that there would be many other difficulties associated with this scenario: interchange at<br />
Lam Tin with MTR, bus congestion in TKO and Kwun Tong, and internal implications for TKO with<br />
regard to provision of bus termini, bus stops, walkways, and other pedestrian facilities etc. The majority<br />
of planning for the New Town has been undertaken on the assumption that the MTR Extension would be<br />
constructed.<br />
TABLE 7.13 :<br />
IMPACT OF MTR EXTENSION<br />
AM Peak East Bound Flows (pcus), 2011<br />
Corridor/Link<br />
Base (with MTR)<br />
Volume V/C<br />
No MTR<br />
Extra Buses<br />
Traffic<br />
v/c<br />
Po Lam Road<br />
1000<br />
0.77<br />
200<br />
1200<br />
0.92<br />
TKO Tunnel<br />
4250<br />
1.18<br />
250<br />
4500<br />
1.25<br />
WCR<br />
4600<br />
0.85<br />
150<br />
4750<br />
088<br />
Total Screenline<br />
9850<br />
0.96<br />
600<br />
10450<br />
1.02<br />
7.2*6 Impact of Development Area 131 and Development Area 137<br />
The capacity offered by the three direct links between Tseung Kwan O and Kwun Tong is 10500 pcus per<br />
hour. The demand in 2011 for westbound travel in the AM peak is 9700 pcus in totaL Therefore the<br />
screeniine as a whole can function at just under capacity. Area 131 only contributes about 1.5% of the<br />
external westbound traffic in the AM peak, whilst Area 137 contributes about 6.6%. Areas 131 and 137<br />
are clearly attracted to the Western Coast Road but are not the dominant users of the facility. The results<br />
are summarised in Table 7.14. Area 131 would make minimal use of the TKO Tunnel About one third<br />
of Area 137 traffic would use the tunnel, contributing about 6% of the total tunnel volume.<br />
TABLE 7,14 :<br />
IMPACT OF LANDUSE DEVELOPMENT AREAS 131,137 (2011 Flows, AM Peak Westbound)<br />
Corridor Base Traffic from Area 131 Traffic from Area 137<br />
(pens) Volume Percent Volume Percent<br />
Pa Lara Road<br />
1000<br />
0<br />
0<br />
0<br />
0<br />
TKO Tunnel<br />
4050<br />
0<br />
0<br />
250<br />
6.2%<br />
WCR<br />
4650<br />
150<br />
32%<br />
400<br />
3.6%<br />
Total Screenline<br />
9700<br />
150<br />
1.5%<br />
650<br />
6.7%<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
7.2.7 Sensitivity Test on Ultimate Level of Population Forecasts<br />
The Draft 1992 Tseung Kwan 0 Development Programme implies an ultimate population figure in 2011<br />
of 440,000 whereas the corresponding population assumed in CTS-2 (Metroplan) is 333,000.<br />
It should be noted that the population figures quoted in the Development Programme are basically the<br />
design population capacity. This is the theoretical population if all apartments at any time are occupied<br />
with average family sizes. In normal circumstances, this would rarely happen and a 5% vacancy rate is<br />
considered appropriate for Tseung Kwan O. However the impact on 2011 network for an active<br />
population of 440,000 has been assessed. No extra employment has been assumed, as the industrial<br />
developments have already added about 15,000 jobs to the base figure.<br />
Table 7.15 gives 2011 AM peak demand traffic volume and volume/capacity ratio for external access<br />
links. The demand flow on the TKO Tunnel would exceed maximum capacity (V/C = L26) whilst the<br />
demand flow on the Western Coast Road is still within the limit of ultimate capacity (V/C = 1.01).<br />
TABLE 7.15 :<br />
2011 DEMAiND TRAFFIC VOLUMES WITH HIGH POPULATION, AM PEAK<br />
BASE (Metroplan Forecast)<br />
SENT Forecast<br />
External Access Direction Flow (pcu) V/C Flow(pcu) V/C<br />
Po Lam Rd<br />
TKO Tunnel<br />
WCR<br />
Screeniine<br />
Total<br />
W<br />
E<br />
W<br />
E<br />
W<br />
E<br />
W<br />
E<br />
1000<br />
1000<br />
4050<br />
4250<br />
4650<br />
4600<br />
9700<br />
9850<br />
0.67<br />
0.77<br />
1.13<br />
1.18<br />
0.86<br />
0.85<br />
0.92<br />
0.96<br />
1200<br />
1100<br />
4550<br />
4550<br />
5050<br />
4800<br />
10800<br />
10450<br />
0.80<br />
0.85<br />
1.26<br />
1.26<br />
0.94<br />
0.89<br />
1.03<br />
1.01<br />
The morning peak demand in the westbound direction would be in excess of the screenline capacity for<br />
2011 as residents leave for work. The increase in population from 333,000 to 440,000 will add about<br />
11.3% of extra traffic and load the screenline to 3% above practical capacity. The source of the<br />
screeniine traffic is as follows for the westbound AM peak:<br />
Source<br />
AM Peak Westbound<br />
Traffic from 333,000 population and 85,000 jobs 7,100<br />
Traffic from SENT Landfill and TKOIE 1,800<br />
Traffic from Areas 137 and 131 800<br />
Extra traffic from increase from 333,000 to 440,000 population 1,100<br />
As a guiding principle the screeniine covering the access to Tseung Kwan O from the west should not<br />
exceed practical capacity; improved balance within the screeniine can be achieved through toll adjustments<br />
on TKO Tunnel. The critical period in respect of increasing population is the AM peak in the westbound<br />
direction. The v/c ratio for the screeniine increases from 0.92 to 1.03 which indicates that, in terms of<br />
practical capacity of the screenline, the increase in population level should be limited to around 78,000<br />
giving a theoretical total of 411,000. However, by inclusion of an assumed 5% vacancy rate, a design<br />
population of around 432,000 could be achieved.<br />
APR Consultants Page 7
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Alternative access to Tseung Kwan O could be provided by Clear Water Bay Road and either Hang Hau<br />
Road or a new northern access such as a route from Road D2 via Tseung Lan Shue, although it is<br />
understood that the latter gives problems in alignment and may give downstream problems on Clear Water<br />
Bay Road. The Hang Hau Road capacity is limited by its north and south junctions. It is also an indirect<br />
route for much of the traffic to and from Tseung Kwan O, As a result only some 2,000 pcu's are<br />
expected to use this link in the peak hour, mainly for trips to Sai Kung. Improvements to the junctions<br />
would provide a more attractive alternative if the congestion on the western access reaches a high level.<br />
There is also a possible provision of direct access to Hong Kong Island via a vehicle ferry between Area<br />
131 and Sai Wan Ho. The availability of this link has not been included in the traffic forecasts; a practical<br />
traffic volume could be between 100 to 200 pcus in the peak hour and this would make the screenline<br />
function within capacity.<br />
It is proposed that the design population is not lowered, rather that the options of providing the vehicle<br />
ferry link and the improvements to the Hang Hau access are safeguarded, as these could accommodate<br />
the excess 300 pcus required to place the western screenline in balance.<br />
7,2.8 Traffic Impact in Area of Influence<br />
Traffic impact caused by Area 137 is mostly concentrated on two major connecting routes, route<br />
D6/P1/T1 leading to Tseung Kwan O Tunnel and the Cross Bay Bridge/Western Coast Road route to East<br />
Kowloon. From these routes the traffic dissipates rapidly through the Kowloon road network. Figure 7.3<br />
illustrates the dissipation of the Area 137 traffic. Table 7.16 summarises the traffic impact within the<br />
Area of Influence for year 2011 in the morning peak.<br />
TABLE 7.16 :<br />
TRAFFIC IMPACT AT STRATEGIC LOCATIONS<br />
1.<br />
2.<br />
3.<br />
4.<br />
5.<br />
6.<br />
7.<br />
8.<br />
9.<br />
10.<br />
11.<br />
Road<br />
Junk Bay Road<br />
Wai Yi Street<br />
Cha Kwo Ling Road<br />
Lei Yue Mun Road<br />
Eastern Harbour Crossing<br />
Kwun Tong Road<br />
Lung Cheung Road<br />
New Clear Water Bay Road<br />
Clear Water Bay Road<br />
(becwm Han* HMI fci art Uwvwwiy Rd)<br />
Hiram's Highway<br />
Kai Tak Connector<br />
Dir<br />
W<br />
E<br />
W<br />
E<br />
W<br />
E<br />
W<br />
E<br />
N<br />
S<br />
N<br />
S<br />
W<br />
E<br />
W<br />
E<br />
W<br />
E<br />
N<br />
S<br />
W<br />
E<br />
Total<br />
(pcu)<br />
6100<br />
6300<br />
2000<br />
3400<br />
2300<br />
1800<br />
3700<br />
5200<br />
5400<br />
5700<br />
3900<br />
4800<br />
4700<br />
4800<br />
3400<br />
3400<br />
1900<br />
2000<br />
1000<br />
1200<br />
2700<br />
3600<br />
V/C<br />
Ratio<br />
1.13<br />
1.16<br />
0.76<br />
1.32<br />
o.so<br />
0.63<br />
0.94<br />
1.31<br />
1.49<br />
1.59<br />
0.73<br />
0.88<br />
1.30<br />
1.33<br />
1.12<br />
1.13<br />
0.71<br />
0.50<br />
0.34<br />
0.41<br />
0.75<br />
0.99<br />
Area 137<br />
Traffic<br />
160<br />
180<br />
20<br />
30<br />
100<br />
110<br />
190<br />
160<br />
80<br />
90<br />
60<br />
40<br />
30<br />
40<br />
30<br />
30<br />
40<br />
70<br />
20<br />
20<br />
170<br />
130<br />
% Trips<br />
2.6<br />
2.9<br />
1.0<br />
0.9<br />
4.3<br />
6.1<br />
5.1<br />
3.1<br />
1.5<br />
1.6<br />
1.5<br />
0.8<br />
0.6<br />
08<br />
0.9<br />
0.9<br />
2.1<br />
3.5<br />
2.0<br />
1.7<br />
6.3<br />
3.6<br />
APH Consultants
Figure 7.3<br />
BANDWIDTH SCALE:<br />
1 OOOPCU3<br />
IMPACT OF AREA 137 TRIPS<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Find Report - Main Report<br />
There are some impacts on strategic locations outside Tseung Kwan O. The flow contribution from Area<br />
137 at these locations is small, with maximum 6% of the total traffic. The more significant contributions<br />
to overloading as a result of Area 137 are Junk Bay Road (2.9%) and Lei Yue Mun Road (3.1%).<br />
The Study has been consistent with the TKOFSOFD in assuming that improvements to Clearwater Bay<br />
Road will be made during the period 2006 to 2011. The traffic volumes are well within the capacity of<br />
the improved Clearwater Bay Road, although there is some concern that the traffic in this area may<br />
develop faster than currently forecast.<br />
7.2.9 Delays in Construction of Western Coast Road<br />
Consideration has been given to the consequences of delaying the construction of the Western Coast Road<br />
in terms of the planned forecast for population and employment build up. The analysis of permissible<br />
development levels is, however, more approximate as there will be a radical change in the type of<br />
development associated with Tseung Kwan O. Rather than striving to attract development, constraints will<br />
need to be placed on the extent of development for the New Town.<br />
The discussion of alternative scenarios is presented from the traffic planning point of view. Planning<br />
assumptions which affect traffic and transport demand are primarily population levels and employment.<br />
The external travel demand arising from these will need to be accommodated on the existing access routes<br />
between Tseung Kwan O and East Kowloon. In developing alternative scenarios, it is assumed that traffic<br />
demand needs to be maintained below the capacity of the western screenline. The absence of any other<br />
transport mode, in this case the MTR extension, will also increase traffic volumes and thereby reduce<br />
access road capacity. Table 7.17 lists the planning assumptions and the forecast travel demand for Tseung<br />
Kwan 0, together with the limitations on screenline capacity.<br />
TABLE 7.17 :<br />
FORECAST TRAVEL DEMAND AND ASSUMPTIONS<br />
ITEM<br />
YEAR<br />
2001<br />
2006<br />
2011<br />
Population (Metropian)<br />
241,000<br />
243,000<br />
333,000<br />
Employment (Metropian)<br />
57,000<br />
76,000<br />
85,000<br />
Extra Industrial Employment (approx.)<br />
20,000<br />
20,000<br />
20,000<br />
Tseung Kwan 0 Traffic (Metropian) (pcus)<br />
3,700<br />
4,700<br />
7,100<br />
TKO Area 137/131 Traffic (pcus)<br />
800<br />
800<br />
800<br />
TKO Other Industrial Traffic (pcus)<br />
1,800<br />
1,300<br />
1,800<br />
Total Traffic - MTR open in 2006<br />
Total Traffic - MTR not open<br />
6,300<br />
7,300<br />
7,900<br />
9,700<br />
10,300<br />
Capacity - Without WCR<br />
Capacity - With WCR<br />
5,100<br />
10,500<br />
5,100<br />
10,500<br />
5,100<br />
10,500<br />
To meet the forecast traffic demand for the planned population and employment, the Western Coast Road<br />
would be required in 2001 to give sufficient screenline capacity. If the Western Coast Road is delayed<br />
until 2006, constraints on population, employment or industrial growth would need to be imposed.<br />
Consideration has been given to different scenarios by which this can be achieved.<br />
APH Consultants<br />
Pa s e 7 ~ 14
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
The choice between scenarios must bear in mind that the planning forecasts implicit in Metroplan represent<br />
desirable targets rather than the output of a detailed plan; this is especially the case for employment figures<br />
which are essentially non-specific. The inherent problem in planning for non-specific employment<br />
developments is whether they would be implemented and how this would occur. In contrast, the industrial<br />
developments proposed for Tseung Kwan O are already planned and fulfil an identified need. Therefore,<br />
when reducing employment levels, alternatives which permit the proposed industrial developments and cut<br />
back on other employment must be preferred.<br />
The range of scenarios considered for the delay of the Western Coast Road to 2006 and 2011, are given<br />
in Table 7.18 and 7,19 respectively.<br />
TABLE 7.18 : SCENARIOS FOR DELAY OF WESTERN COAST ROAD TO 2006<br />
Scenarios for 2006 are:<br />
MTR<br />
Present<br />
Metroplan<br />
Population<br />
Metroplaa<br />
Employment<br />
A137<br />
A131<br />
Empl.<br />
Other<br />
Industrial<br />
Employment<br />
Bl<br />
Full Metroplan<br />
2006<br />
Yes<br />
243,000<br />
76,000<br />
50%<br />
None<br />
B2<br />
Half Metroplan<br />
2006<br />
Yes<br />
120,000<br />
43,000<br />
100%<br />
100%<br />
S3<br />
Full Metroplan<br />
2006<br />
Yes<br />
243,000<br />
28,000<br />
100%<br />
100%<br />
B4<br />
75% Population<br />
2006<br />
Yes<br />
180,000<br />
36,000<br />
100%<br />
100%<br />
B5<br />
Full Metroplan<br />
2006<br />
No<br />
243,000<br />
72,000<br />
None<br />
None<br />
B6<br />
Half Metroplan<br />
2006<br />
No<br />
120,000<br />
30,000<br />
100%<br />
100%<br />
B7<br />
Full Metroplan<br />
2006<br />
No<br />
243,000<br />
15,000<br />
100%<br />
100%<br />
B8<br />
75% Population<br />
2006<br />
No<br />
180,000<br />
23,000<br />
100%<br />
100%<br />
TABLE 7.19 : SCENARIOS FOR DELAY OF WESTERN COAST ROAD TO 2011<br />
Additional Scenarios for 2011:<br />
MTR<br />
Present<br />
Metroplan<br />
Population<br />
Metroplan<br />
Employment<br />
A137<br />
A131<br />
Other<br />
B9<br />
Full Metroplan Population<br />
Yes<br />
333,000<br />
40,000<br />
None<br />
None<br />
BIO<br />
Full Metroplan Population<br />
Yes<br />
333,000<br />
20,000<br />
100%<br />
None<br />
Bll<br />
Full Metroplan Population<br />
No<br />
333,000<br />
27,000<br />
None<br />
None<br />
B12<br />
Full Metroplan Population<br />
No<br />
333,000<br />
7,000<br />
100%<br />
None<br />
To some extent the scenarios at 2006 and 2011 are mutually exclusive, in that permitting industrial<br />
employment at 2006 would exclude the deletion of this demand at 2011. In determining the preferred long<br />
term approach a view needs to be taken at the outset on the strategy to be adopted. If the ultimate<br />
objective is to provide for the Metroplan population of 333,000 and it is considered realistic that the<br />
Western Coast Road will not be implemented even by the 2011, then no industrial development should<br />
be permitted from the outset. Clearly this will be in direct contravention of the ongoing development of<br />
TKODE and eliminate the proposed Area 137 development. Alternatively these developments could be<br />
permitted, provided the population growth was constrained to its 2006 level. This approach effectively<br />
draws the decision point back to the 2006 scenarios and consideration of the implications of the delay of<br />
construction of the Western Coast Road to 2006.<br />
APH Consultants Page 7-15
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
In endorsing any recommendations on the preferred scenario to be adopted, Government will be required<br />
to take a view on the priority attached to the three main components; should industrial and other<br />
employment be promoted in preference in population growth, for instance.<br />
There is clearly a balance to be struck between population and employment. The extent of employment<br />
(other than industrial) which can be attributed to the New Town development is less definitive than the<br />
population forecasts. Current experience would appear to indicate that, with the increasing switch in<br />
employment to the financial and service sectors and the preference for these jobs to be located in CBD<br />
areas, the take up of development opportunities for manufacturing and commercial activities may not<br />
achieve its forecast levels. Thus in striking the balance between population and employment, it is<br />
considered that the preference should lie with permitting the population build up in accordance with the<br />
development planning if possible, albeit at the same time making a reasonable provision for employment.<br />
The recommended population threshold levels for differing levels of infrastructure provision as derived<br />
from the above sensitivity analysis are summarised in Table 7.20. In presenting this data, a ratio of<br />
population to total employment in the range of 4:1 to 8:1 has been adopted. The employment levels given<br />
include both industrial (TKOIE, Area 137 and 131) and general Metroplan employment.<br />
TABLE 7.20 :<br />
POPULATION THRESHOLD LEVELS<br />
External Infrastructure<br />
Population Threshold<br />
Employment Level<br />
Comments<br />
Existing<br />
243,000<br />
30,000<br />
B7 from Table 7.18<br />
Existing 4- MTR<br />
243,000<br />
43,000<br />
B3 from Table 7. 18<br />
Existing i- WCR<br />
380,000<br />
90,000<br />
Existing •f MTR -f WCR<br />
411,000<br />
100,000<br />
Section 7.2.7<br />
As discussed, the above thresholds have recognised the advanced and more definitive nature of the<br />
population planning for the developments in TKO and have used employment levels as the main variable.<br />
If, however for the existing situation, a more balanced relationship between population and employment<br />
at around 4:1 was considered desirable for planning purposes, then the population level would need to be<br />
reduced to around 180,000 (employment 38,000) as covered by scenario B8 of Table 7,18,<br />
It should be noted that the analysis is for sensitivity purposes and as such is indicative only. However,<br />
it does indicate that if no further external links are provided then the population level would need to be<br />
constrained. It is concluded that the recommended approach is B3/B7, namely, to encourage the full 2006<br />
population of 243,000 together with the development of the industrial areas including TKOIE and Area<br />
137, while limiting other employment. A ceiling of 28,000 (against a planned level of 76,000) on other<br />
employment would be required if the MTR were constructed. No MTR would reduce the employment<br />
figure'to 15,000.<br />
The combination of MTR and no Western Coast Road would seem an unusual transport investment<br />
strategy as generally the MTR is provided for areas of high growth rather than those where growth is<br />
being deliberately constrained. The strategy of mo Western Coast Road would therefore be expected to<br />
parallel a strategy of no MTR. Therefore, it (B7) must be considered that the lower Metroplan<br />
employment level of 15,000 would be the most realistic of the two.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
7.2.10 Summary of findings<br />
The construction of the Western Coast Road is critical to the future development of Tseung Kwan 0.<br />
Without this route not only will access to the proposed industrial developments be restricted, but the<br />
development of the New Town will be severely constrained. The traffic study is therefore based on the<br />
assumption that the Western Coast Road will be constructed to meet infrastructure and traffic demand.<br />
The main findings of the traffic study are:<br />
> The Western Coast Road is required by 2001 to serve Tseung Kwan O and to relieve the<br />
overloaded TKO Tunnel, for a New Town population of 241,000 and if all proposed industrial<br />
developments are implemented. It is essential that the Western Coast Road has high capacity and<br />
effective connections in Yau Tong in order to promote its use.<br />
» The present toll level on the TKO Tunnel of S3 should be increased to encourage a better balance<br />
of traffic across the western screenline.<br />
* A change in level of self-containment, i.e. more outcommuting, would require the timing of the<br />
provision of the Western Coast Road to be brought forward marginally. It would have no major<br />
impact on internal roads.<br />
*> Without the MTR Extension there would be additional congestion at the TKO Tunnel which<br />
would be heavily overloaded in the AM peak, although the screenline as a whole would operate<br />
at capacity.<br />
> The development of Area 137 increases the screenline flows by about 6%. The Area 131<br />
development increases screenline flows by about 1.5%. For the 333,000 population level and<br />
with the developments in Areas 137 and 131, the screenline will operate below capacity.<br />
* A design population of 440,000 for Tseung Kwan 0 would overload external links by 3% overall<br />
in the morning peak if the industrial developments are present. However, a vehicle ferry service<br />
and improvements to the Hang Hau corridor would provide sufficient additional capacity to allow<br />
the design population of 440,000 to be retained.<br />
* If the Western Coast Road has to be delayed beyond 2001, it is recommended that the target<br />
population figure for 2006 should be maintained together with the industrial developments at<br />
TKOIE and Area 137 whilst limiting other Metroplan employment to 15,000 against a planned<br />
level of 76,000, This level of employment would increase to 28,000 if the MTR was constructed.<br />
The latter situation is considered to be unlikely given that the development is being deliberately<br />
constrained.<br />
73 INTERNAL ROAD NETWORK<br />
7.3,1 Tseung Kwan O Area 137<br />
Area 137 is planned to be developed as a rolling programme with the first release of sites mid 1996 to<br />
1997. With due allowance for operator development of the sites, it is considered that traffic generation<br />
will commence in 1999 and progressively build up to a maximum around 2001. This has therefore been<br />
adopted as the first horizon year for the assessment of traffic from Area 137.<br />
It is estimated that some 70-80% of the development traffic will be heavy goods vehicles. Subject to the<br />
detailed use and operation of the PHI sites, the likely maximum volumes of vehicles carrying dangerous<br />
APH Consultants<br />
Page 7^
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
final Report - Main Report<br />
goods of Categories 1, 2 and 5 are expected to be some 500 pcus/hr 2-way and 250 pcus/hr 2-way in the<br />
AM and PM peak respectively. These vehicles are restricted from passing through Tseung Kwan 0<br />
Tunnel under the current Government tunnel regulations for safety reasons.<br />
The road network within Area 137 is shown in Figure 7.4. Access to the site is via Road D6, planned<br />
as a dual 2-lane but constructed initially as a 7.3 m single carriageway.<br />
Figure 7.5 shows the traffic assignments within Area 137 on completion of the full development in 2001.<br />
Highest link flows occur on the section of Road D6 immediately north of Area 137 as it is the only<br />
vehicular entry and exit. From there, development traffic is distributed throughout the internal road<br />
network.<br />
A roundabout is provided at the intersection of Road D6 and the site distributor roads to handle the major<br />
turning movement flows. The volume/capacity ratios at the roundabout are 0.52 and 0.40 during the AM<br />
and PM peak hours respectively. Other junctions have lower flows and therefore priority control is<br />
considered appropriate.<br />
7.3.2 Road Network within Tseung Kwan O<br />
Traffic forecasts were prepared for all the major links and junctions within TKO for years 2001, 2006 and<br />
2011, in order to assess the traffic impact of the proposed development. The Western Coast Road is<br />
assumed to be present from 2001, in accordance with the external access requirements.<br />
The critical elements of the highway network are generally the junctions and the traffic analysis has<br />
concentrated on examining the operation of the junctions on the major roads in Tseung Kwan 0. The link<br />
volumes have also been examined to establish whether there are elements of the strategic and primary<br />
network with insufficient capacity. For 2001 and 2006, with the Western Coast Road in place by 2001,<br />
the traffic volumes on all such links are below their design capacity. However, as noted earlier, by 2011<br />
the TKO Tunnel and Road Tl between the Tunnel and the junction with P2/P1 would be overloaded unless<br />
measures were taken to make the Western Coast Road relatively more attractive. The volume capacity<br />
ratio for Tl would be highest in the eastbound direction in the AM peak with a value of 1.26.<br />
By Year 2001<br />
Figure 7.6 shows the road network within TKO in 2001 and the affected junctions. The 2001 traffic<br />
forecasts are shown in Figure 7.7. The development in Area 137 will be fully completed in 2001 which<br />
gives maximum development traffic generations.<br />
Capacity calculations for the affected junctions were made and the results are summarised in Table 7.21.<br />
The calculations were based on the detailed junction layouts.<br />
APH Consultants<br />
Fa S e 7 ~ 18
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 121 :<br />
CAPACITIES OF AFFECTED JUNCTIONS IN TSEUNG KWAN 0 IN 2001<br />
Signalised Junctions<br />
SI Road D6/Road L373<br />
S2 Road D6/Road L371<br />
S3 Road D6/Road D9<br />
S4 Road D6/Road L9<br />
S6 Po Lam Road/Road L2<br />
S7 Po Lam Road/Po Fung Road<br />
S8 Po Lam Road/Po Hong Road<br />
Roundabouts<br />
Rl Road D9/Arca 86 Eastern Access<br />
R4 Road Pi/Road D4<br />
R5 Road D4/Road D3<br />
R6 Road D3/Road L30<br />
R7 Road P2/Road D2/Road D3<br />
With TKO 137<br />
AM Peak<br />
Reserve Capacity (%)<br />
+ 67<br />
+ 5<br />
+ 47<br />
+ 9<br />
4-32<br />
-f 67<br />
+ 30<br />
Volume/Capacity Ratio<br />
0.068<br />
0.979<br />
0.392<br />
0.841<br />
0.885<br />
PMPeak<br />
4-137<br />
+ 19<br />
+ 43<br />
+ 58<br />
+ 74<br />
+ 103<br />
+ 76<br />
0.043<br />
0.959<br />
0.368<br />
0.620<br />
0.605<br />
It can be seen that all the affected junctions are expected to operate within capacity level in 2001.<br />
By Year 2006<br />
Figure 7.8 shows the road network within TKO in 2006 and the affected junctions. The 2006 traffic<br />
forecasts are shown in Figure 7.9. As development in Area 137 have been completed in 2001, traffic<br />
growth in TKO is mainly due to the development in the rest of TKO.<br />
Capacity calculations for the affected junctions were made and the results are summarised in Table 7.22,<br />
APH Consultants Page 7-19
o<br />
"0<br />
*<br />
O<br />
c<br />
33<br />
Tl<br />
r*<br />
O
Figure 7.8<br />
S1<br />
SIGNALISED JUNCTION KEY JUNCTIONS<br />
AFFECTED 8Y AREA 137<br />
ROUNDABOUT KEY JUNCTIONS<br />
AFFECTED 3Y AREA 137<br />
31 JUNCTION NUMBER<br />
2006 TSEUNG KWAN 0 AND AREA 137 HIGHWAY NETWORK<br />
APH CONSULTANTS
Figure 7.9<br />
960 AM PEAK<br />
«00) PM PEAK<br />
2006 PEAK HOUR LINK FLOWS<br />
993 APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
TABLE 722 : CAPACITIES OF AFFECTED JUNCTIONS IN TSEUNG KWAN 0 IN 2006<br />
With TKO 137<br />
Signalised Junctions<br />
SI Road D6/Road L373<br />
S2 Road D6/Road L371<br />
S3 Road D6/Road D9<br />
S4 Road D6/Road L9<br />
$6 Po Lam Road/Road L2<br />
S7 Po Lam Road/Po Fung Road<br />
S8 Po Lam Road/Po Hong Road<br />
Roundabouts<br />
Rl Road D9/Area 86 Eastern Access<br />
R2 Road D9/Area 86 Western Access<br />
R3 Road D9/Road P2<br />
R4 Road Pi/Road D4<br />
R5 Road D4/Road D3<br />
R6 Road D3/Road L30<br />
R7 Road P2/Road D2/Road D3<br />
AM Peak<br />
Reserre Capacity (%)<br />
-*• 71<br />
4- 7<br />
-11(4-6)<br />
4* 17<br />
4* 22<br />
x 72<br />
T 26<br />
Volume/Capacity Ratio<br />
0.616<br />
0.699<br />
0.677<br />
0.735<br />
0.422<br />
0.780<br />
0.780<br />
PMPeak<br />
M37<br />
4- 20<br />
- 15 (4-3)<br />
4- 73<br />
4- 60<br />
4-118<br />
4- 80<br />
0.691<br />
0.647<br />
0.644<br />
0.603<br />
0.419<br />
0.618<br />
0.589<br />
Note:<br />
Figures in brackets assume junction improvements.<br />
The calculations suggest that the junction of Road D6/Road D9 (Junction S3) will be overloaded in 2006,<br />
assuming the current junction design, at -11 % and -15% during the AM and PM peak respectively. It is<br />
proposed that the Road D6 northbound approach be widened to 3 lanes. This will increase junction<br />
reserve capacity to 4-6% and 4*3% during the AM and PM peaks.<br />
By Year 2011<br />
Figure 7.10 shows the road network within TKO in 2011 and the affected junction. The 2011 traffic<br />
forecasts are given in Figure 7.11. The results of the junction capacity assessment are summarised in<br />
Table 7.23,<br />
APH Consultants Page 7-20
Figure 7.10<br />
PO LAMft<br />
SIGNALISED JUNCTION KEY JUNCTIONS<br />
AFFECTED BY AREA 137<br />
ROUNDABOUT KEY JUNCTIONS<br />
AFFECTED BY AREA 137<br />
31 JUNCTION NUMBER<br />
2011 TSEUNG KWAN 0 AND AREA 137 HIGHWAY NETWORK<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 7.23:<br />
CAPACITIES OF AFFECTED JUNCTIONS IN TSEUNG KWAN 0 IN 2011<br />
Signalised Junctions<br />
SI Road D6/Road LS73<br />
S2 Road D6/Road L871<br />
S3 Road D6/Road D9<br />
S4 Road D6/Road L9<br />
S5 Road D6/Road PI<br />
S6 Po Lam Road/Road L2<br />
37 Po Lam Road/Po Fung Road<br />
S8 Po Lam Road/Po Hong Road<br />
Roundabouts<br />
Rl Road D9/Area 86 Eastern Access<br />
R2 Road D9/Area 86 Western Access<br />
R3 Road D9/Road P2<br />
R4 Road Pi/Road D4<br />
R5 Road D4/Road D3<br />
R6 Road D3/Road L30<br />
R7 Road P2/Road D2/Road D3<br />
With TKO 137<br />
AM Peak<br />
Reserve Capacity (%)<br />
-r66<br />
+ 4<br />
-K+23)<br />
4-29<br />
+ 6<br />
+35<br />
•r44<br />
4-26<br />
Volume/Capacity Ratio<br />
0.532<br />
0.705<br />
0.709<br />
1.257(0.860)<br />
0.713<br />
0.821<br />
0.948<br />
PMPeak<br />
4-137<br />
4- 19<br />
-l(+26)<br />
4- 87<br />
4-56<br />
-*-39<br />
4-113<br />
4- 68<br />
0.589<br />
0.582<br />
0.603<br />
0.527(0.447)<br />
0.567<br />
0.693<br />
0.859<br />
Note:<br />
Figures in brackets assume junction improvements.<br />
The roundabout at Road Pi/Road D4 (Roundabout R4) is forecast to have capacity shortfall in 2011. It<br />
is proposed to widen the PI southbound approach to 3 lanes to bring the V/C ratios to below 1.0. All<br />
other junctions are expected to operate within capacity with the current junction design.<br />
The junctions T1/P1/P2 and P2/D1 are both grade separated junctions. The link flows as shown in<br />
Figures 7.7, 7.9 and 7.11 are within the link capacities.<br />
The Transport Planning Design Manual principles suggest that the hourly v/c ratio for roundabouts should<br />
be less than 0.35. V/C ratios have been examined for all years on an hourly basis for the roundabouts<br />
which are approaching capacity. The results are indicated in Table 7.24. V/C ratios for Roundabout R4<br />
in 2011 assumes that the improvements suggested above have been implemented.<br />
APH Consultants Page 7-21
Figure 7.11<br />
750 AM PEAK<br />
(460) PM PEAK<br />
2011 PEAK HOUR LINK FLOWS<br />
APH CONSULTANTS
Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
TABLE 7JA :<br />
HOURLY V/C RATIOS FOR ROUNDABOUTS<br />
Volume/Capacity Ratio<br />
2001<br />
2006<br />
2011<br />
Roundabout<br />
AM<br />
PM<br />
AM<br />
PM<br />
AM<br />
PM<br />
R4<br />
R6<br />
R7<br />
0.826<br />
0.682<br />
0.791<br />
0.850<br />
0.562<br />
0.545<br />
0.659<br />
0.637<br />
0.698<br />
0.536<br />
0.560<br />
0.530<br />
0.765<br />
0.746<br />
0.845<br />
0.461<br />
0.630<br />
0.771<br />
7*4 PUBLIC TRANSPORT REQUIREMENTS<br />
Although Area 137 is only anticipated to support approximately 1,700 jobs by 2011, it will be at the<br />
southern end of a peninsula of development forecast to contain almost 50,000 jobs. At the north of this<br />
industrial corridor will be a residential area (Area 78) with a forecast population of 27,000, and a small<br />
bus terminus (in Area 86).<br />
The peninsula will attract heavy public transport demand at shift change times, sufficient to justify<br />
provision of ftanchised services. A bus terminus in Area 137 should be provided to cater for routes<br />
servicing the peninsula as a whole. This should be sited near the southern end of the peninsula.<br />
The Final Report of TKOFSOFD proposed such a terminus to cater for two internal routes (from Area<br />
3/4 and Area 38) and three external routes (from Wan Chai Ferry, Ngau Tau Kok and Tsz Wan Shan).<br />
This appears to be a reasonable planning assumption. Most of these routes would not be justified for all<br />
day operation; possibly only the internal routes, or none at all if local GMB service is provided.<br />
Consideration should be given to extending proposed route 95K (from China Ferry Terminal to Area 86),<br />
to Area 137 at peak periods.<br />
Figure 7.12 shows the suggested arrangements for routing and terminal location for the proposed bus<br />
service.<br />
APH Consultants P&S* 7-22
Figure 7.12<br />
CLEARWATCR SAY<br />
COUNTRY PARK<br />
TATHOHC CHANNEL<br />
UUI WAN<br />
BUS ROUTES AND TERMINAL IN AREA 137<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
final Report - Main Report<br />
SECTION 8<br />
WESTERN COAST ROAD<br />
8.1 INTRODUCTION<br />
The analysis in Section 7 has identified that the existing access to Tseung Kwan O would have insufficient<br />
capacity to cater for the projected external traffic flows by 2001 and that the Western Coast Road will<br />
need to be constructed by that date in order to avoid any constraints being imposed on the level of<br />
development of Tseung Kwan O.<br />
It has been proposed that the Western Coast Road will connect to both the existing Lei Yue Mun Road<br />
and Cha Kwo Ling Road in Yau Tong. Two alternatives were put forward in the TKOFSQFD for the<br />
alignment of the Western Coast Road through Yau Tong for these connections :<br />
*•<br />
Option A, the direct connection to Lei Yue Mun Road and Cha Kwo Ling Road;<br />
> Option B, connection to Lei Yue Mun Road via Yau Tong Road.<br />
Under this Study, a comparative assessment of these two alternative connections was required, leading to<br />
the identification of the most suitable option and the finalisation of a road reserve.<br />
As part of the strategic highway network, the Western Coast Road will link Roads P2 and D9 in Tseung<br />
Kwan 0 with the Kai Tak Connector, the Kwun Tong Expressway and the Eastern Harbour Crossing in<br />
East Kowloon. The provision of the Western Coast Road complements the Tseung Kwan O external<br />
routes by providing an alternative for traffic generated by the industrial developments in Tseung Kwan<br />
O. This will be of particular benefit to dangerous goods traffic from the potentially hazardous installations<br />
of Area 137 which will not be able to use the TKO Tunnel. This latter requirement only serves to<br />
reinforce the need for the early provision of the Western Coast Road to ensure that any risks associated<br />
with such traffic using the Po T>Tfr Road in the interim, are minimised.<br />
8.2 WESTERN COAST ROAD CONNECTIONS<br />
8.2.1 Option A, Direct Connection to Lei Yue Mun Road (Figure 8.1).<br />
The Western Coast Road divides into two, 2-lane, dual carriageways south of the village of Sam Ka Tsuen<br />
on the Lei Yue Mun headland. The Cha Kwo Ling Road Link follows the alignment of Cha Kwo Ling<br />
Road at an elevated level before joining the existing carriageway north of Yau Tong Bay. From this point<br />
the road will eventually connect to the Kai Tak Connector.<br />
The Lei Yue Mun Road Link passes over a new roundabout intersection on Ko Chiu Road and Yan Wing<br />
Street, before joining the existing 2-lane dual carriageway of Lei Yue Mun Road between the Ko Chiu<br />
Road and Yau Tong Estates.<br />
The existing at-grade Cha Kwo Ling Road will require re-alignment throughout to accommodate the<br />
location of the supports for the elevated structure. Realignment will be possible by the construction of<br />
retaining structures along the route, which will then allow for the provision of two at-grade traffic lanes<br />
in each direction.<br />
APH Consultants<br />
Page
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
8.2.2 Option B, Connection to Lei Yue Mun Road via Yau Tong Road (Figure 8.2).<br />
In Option B, the Western Coast Road does not divide at Sam Ka Tsuen village, but instead follows the<br />
alignment of Cha Kwo Ling Road, at an elevated level, as in Option A. After Sze Shan Street, the route<br />
divides and a connection to Yau Tong Road is made by elevated slip roads. From the point of diversion<br />
of the slip roads, the elevated Cha Kwo Ling Road continues as a 2-lane dual carriageway until it joins<br />
the existing at-grade dual 2-lane carriageway to the north of Yau Tong Bay.<br />
The existing, single carriageway, Yau Tong Road will be reconstructed as a 2-lane dual carriageway along<br />
the same alignment as the existing road until it joins Lei Yue Mun Road just north of the Yau Tong<br />
playground. The intersection of these roads, including the re-aligned link to the Eastern Harbour<br />
Crossing, is catered for by provision of an at-grade roundabout.<br />
As for Option A, the existing at-grade Cha Kwo Ling Road will require realignment throughout to<br />
accommodate the location of the supports for the elevated structure. In so doing, two traffic lanes in each<br />
direction will be provided.<br />
8.3 EVALUATION OF OPTIONS<br />
The Western Coast Road Options will have significant impacts on existing land uses in the Lei Yue Mun<br />
and Yau Tong areas in East Kowloon. The increased volume of traffic anticipated under each Option will<br />
exert significant environmental impacts along the road alignment and the structure, form and width of each<br />
road alignment will have major physical and visual implications. Numerous Government, Institutional and<br />
Community (GIC) facilities are located along each alignment together with a number of recreational and<br />
residential land uses. Mitigation measures will be required wherever development is adversely affected<br />
by the new road development.<br />
In order to select the preferred Option, the two alternatives have been evaluated against a number of<br />
criteria. These are grouped under the following key categories:<br />
* Traffic and Roads<br />
> Land Use Impacts<br />
> Environmental impacts<br />
> Cost comparison<br />
In a number of cases the performance of the Options or the magnitude of their impacts are similar and<br />
these criteria do not provide a clear basis for selection of a preferred Option. The selection is therefore<br />
based on an evaluation of those criteria which do indicate sufficiently clearly a preferred alignment for<br />
the connection.<br />
8.4 TRAFFIC AND ROADS<br />
The traffic evaluation relating to the requirement for the Western Coast Road as part of the strategic road<br />
network has been reported in Section 7, along with various sensitivity tests to examine the impacts of f<br />
among others, the Area 137 and Area 131 developments, the construction of the MTR Extension,<br />
increases of population levels and delays in the construction of the Western Coast Road, The effects on<br />
traffic flows of improvements downstream of the connections were also examined.<br />
The traffic analysis found that it is essential that the Western Coast Road has high capacity and effective<br />
connections in Yau Tong in order to promote its use. This requires improvements in the Yau Tong area<br />
which include the upgrading of the Lei Yue Mun Road to dual 3 lane for the section between Western<br />
APH Consultants P
Figure 8.2<br />
"\ *•->*" "V .<br />
- "Via >.-L 5 »'^<br />
«« _*»:;,... P. —.<br />
jr...- T. -. • •^•^•sM<br />
WESTERN COAST ROAD CONNECTION - OPTION B<br />
APH CONSULTANTS
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Coast Road and Kwun Tong Road and upgrading of the Cha Kwo Ling Road between the Western Coast<br />
Road and Kwun Tong Bypass. Table 8.1 shows the demand flows and volume/capacity ratios for major<br />
links in the AM peak with these improvements to Lei Yue Mun Road and Cha Kwo Ling Road.<br />
TABLE 8.1 :<br />
2011 DEMAND FLOWS ON IMPROVED NETWORKS FULL DEVELOPMENT (PCU/HOUR)<br />
Link<br />
Practical Link<br />
Capacity<br />
Direction<br />
Option A<br />
AM Peak<br />
Option B<br />
Cha Kwo Ling Road/<br />
WCR Connector<br />
3600<br />
3600<br />
W<br />
E<br />
2050(0.57)<br />
2200(0.61)<br />
1800(0.50)<br />
2000(0.56)<br />
Lei Yue Mun Road<br />
WCR Connector<br />
3600<br />
3600<br />
W<br />
E<br />
2500(0.69)<br />
2100(0.58)<br />
2850(0.79)<br />
2600(0.72)<br />
Western Coast Road<br />
5400<br />
5400<br />
W<br />
E<br />
4550(0.33)<br />
4300(0.80)<br />
4650(0.86)<br />
4600(0.85)<br />
Po Lam Road<br />
1500<br />
1300<br />
W<br />
E<br />
1050(0.70)<br />
1000(0.77)<br />
1000(0.67)<br />
1000(0.77)<br />
Tseung Kwan 0 Tunnel<br />
3600<br />
3600<br />
W<br />
E<br />
4150(1.15)<br />
4500(1.25)<br />
4050(1.13)<br />
4250(1.18)<br />
Hang Hau Road<br />
2200<br />
1600<br />
N<br />
S<br />
1800(0.82)<br />
1550(0.97)<br />
1850(0.34)<br />
1550(0.97)<br />
Note : Volume/Capacity ratio in brackets<br />
Option B provides a better connection of the Western Coast Road to East Kowloon than Option A in terms<br />
of traffic flows on the network. In so doing, Option B attracts a greater volume of traffic and thereby<br />
relieves congestion at the TKO Tunnel to a greater extent. Whilst this improvement is only marginal, it<br />
does indicate a preference for Option B.<br />
8.5 LAiND USE IMPACTS<br />
8.5.1 Land Requirements<br />
The construction of the Western Coast Road through Yau Tong and Lei Yue Mun will require<br />
considerable land take with associated impacts on both existing developments and planned land uses. Both<br />
Options encroach on adjacent land uses along Cha Kwo Ling Road. Existing embankments need to be<br />
cut back for road widening, requiring retaining walls and slope stability works. Option A requires<br />
additional land from the Ko Chiu Road and Yau Tong Estates as well as utilising land reserved for the<br />
proposed Lei Yue Mun Supplementary Housing Scheme, while the widening of Yau Tong Road for Option<br />
B encroaches on land to the north side of the existing road.<br />
8.5.2 Implications of Option A on Existing and Planned Land Use<br />
Cha Kwo Ling Road Link<br />
The construction of an elevated carriageway through the built up residential, commercial and industrial<br />
area along Cha Kwo Ling Road will result in severe environmental impact intrusions. Noise and air<br />
impacts will impinge on the utility of a proposed District Open Space east of the road alignment, the<br />
APH Consultants Page 8-3
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
adjacent 1C reserve within which is included a Roman Catholic Church and a kindergarten as well as the<br />
Sam Ka Tsuen Recreation ground on the west of Cha Kwo Ling Road.<br />
The Yau Tong Commercial Centre adjacent to the Roman Catholic Church reserve comprises commercial<br />
and recreational (cinema) provision. The ODP depicts the site developed for R(l) residential development;<br />
the proposed road will impact heavily on residential development on this site and noise mitigation<br />
measures will be required. Likewise, environmental impacts will affect the redevelopment proposals for<br />
Yau Tong Public Housing Estate.<br />
St Antonius Primary School abuts the Estate while Po CMu College is located west of Yau Tong Road.<br />
Both facilities have low levels of noise tolerance and will be adversely affected by the alignment of the<br />
Western Coast Road along Cha Kwo Ling Road. Noise impacts will be significant for each school and<br />
Po CMu College will suffer significant visual impacts. Traffic safety measures would be necessary to<br />
ensure the safe passage of children to and from each school.<br />
Noise and air quality impacts on the industrial buildings to the west of Cha Kwo Ling Road will also be<br />
particularly severe, particularly as in this case noise mitigation measures would not be required.<br />
Similarly, the utility of the Yau Tong Marine Lots sites would be contingent on a satisfactory air quality<br />
environment.<br />
The proposed Western Coast Road will also result in physical intrusions into adjacent properties. The Cha<br />
Kwo Ling Road link passes through an area of development whose tenure is largely served by short term<br />
tenancy arrangements. A number of these short term tenancies will be affected but there should be no<br />
resumption implications as they can all be terminated prior to the commencement of the site investigation<br />
or construction.<br />
The Cha Kwo Ling Road link then proceeds northwards encroaching on the USD Sain Ka Tsuen Complex.<br />
This development comprises a proposed combined market, indoor recreation centre and library complex.<br />
The proposed development will be physically constrained by the road alignment and noise and air quality<br />
impacts will require appropriate measures to be taken.<br />
Adjacent to the USD site is a *G* reserve for a proposed multi-storey car park. The carriageway passes<br />
over this site requiring a modification of development proposals.<br />
The Sam Ka Tsuen Recreation ground currently under construction to the west of the alignment will lose<br />
a marginal strip along the Cha Kwo Ling Road.<br />
On the west side of Cha Kwo Ling Road there is insufficient clearance between the Sunray Industrial<br />
Centre and Yau Tong Industrial Building Block 3 and the proposed elevated roadway. Clearances would<br />
vary between 4 m and 1 m, while Fire Services Department require a 5m clear access. This will<br />
necessitate the demolition of these buildings, with resultant loss of workspace. Resumption costs will be<br />
high, estimated to be in the order of HKS 250M (excluding any incentive payments),<br />
Another serious land take implication resulting from the alignment of Option A relates to the present<br />
configuration of the Yau Tong Marine Lots. 18 Lots will be affected by the encroachment of the new<br />
roads into their lots. This would necessarily result in a cost to Government if property is adversely<br />
affected by the road alignment. There is a proposal to rezone the Yau Tong Bay Area and a surrender<br />
of the existing lots and a new lot with revised boundaries could be granted if the registered lot owners<br />
wished to proceed with redevelopment. Although resumption costs may not then be payable, the use of<br />
land for road construction would result in a reduction of premiums accruabie to Government. Air quality<br />
set backs may effect the operation and utility of each site. Excepting these concerns, note should also be<br />
made of the loss of livelihood that would be incurred due to the alignment of the road through the Lots.<br />
APH Consultants<br />
p age
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
Lei Yue Mun Road Link<br />
Along the Lei Yue Mun branch of Option A, there would be severe impacts on proposed and existing land<br />
uses. Development of the proposed Lei Yue Mun Supplementary Housing Site would be largely blighted<br />
by the road alignment. The proposed alignment dissects the site creating two land parcels. Development<br />
of the resultant sites would be difficult due to the physical and environmental impacts. A reduction of the<br />
environmental impacts could be made by road enclosures and the construction of adjacent housing on<br />
podium development, although this would bring with it problems relating to ventilation of the enclosures,<br />
traffic management and road maintenance; in addition, Highways Department would be reluctant to allow<br />
the construction of an enclosure over an operating road.<br />
The proposed Option A alignment will also impact on the northern portion of Yau Tong Estate and the<br />
southern portion of Ko Chiu Road Estate. Again these are public housing estates and would require noise<br />
mitigation methods together with the use of mitigation measures at source and receiver. The physical<br />
intrusion of the road into proposed estate boundaries will not be as significant as in the Supplementary<br />
Housing Site. Nevertheless, the proposed residential layout may require revision due to the proximity of<br />
residential blocks to the road alignment. Similarly optimal building orientation would be required to<br />
afford maximum protection from noise impacts.<br />
A preliminary estimate by Housing Department indicates a loss of some 4,500 flats if Option A is adopted.<br />
This assumes that the Lei Yue Mun Supplementary Housing Site is totally undevelopable and part of Ko<br />
Chiu Road and Yau Tong Estates will be affected. The social costs of the construction of this link should<br />
also be borne in mind; these relate to the delay to the redevelopment of Yau Tong Estate, the inability to<br />
rehouse the affected tenants locally and the delay to HD's Comprehensive Redevelopment Programme.<br />
North of these estates is an open space reserve granted to USD for a rest garden and recreational<br />
purposes. Noise and air quality impacts may impinge upon the utility of the site. The Yau Tong Road<br />
Playground will be similarly affected. Physical encroachment into the site is not anticipated but access<br />
to the site may be constrained through the upgrading of the road network and additional pedestrian<br />
crossings may have to be provided.<br />
8.53 Implications of Option B on Existing and Planned Land Use<br />
Cha Kwo Ling Road Link<br />
The alignment of Option B is largely concentrated along Cha Kwo Ling Road. A connection to Lei Yue<br />
Mun Road is made along the alignment at the junction of Cha Kwo Ling Road and Yau Tong Road.<br />
Elevated road links will provide free flow access from Cha Kwo Ling Road to Yau Tong Road, The<br />
consequence of this Option will be that noise and air impacts will be more extensively concentrated along<br />
Cha Kwo Ling Road and there will be greater physical intrusion into adjacent properties.<br />
In addition to the land use impacts that Option A would have, as described in the Section above, the<br />
following further impacts will arise as a consequence of Option B.<br />
The new Cha Kwo Ling Road alignment will intrude further into the Sam Ka Tsuen Recreation ground,<br />
disrupting the proposed facilities and requiring their replanning.<br />
The north bound slip road at the junction of Cha Kwo Ling Road and Yau Tong Road will encroach into<br />
the area occupied by the Sunray Industrial Centre and Yau Tong Industrial Building Block 3 requiring,<br />
as for Option A, their demolition. The slip road will also severely encroach into the Po Chiu College site.<br />
Whilst no physical effect on existing buildings is anticipated, noise impacts are likely to be profound and<br />
part of the college playground will be lost. Substantial environmental mitigation measures will be required<br />
APH Consultants<br />
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
to ensure that a satisfactory environment can be obtained. Detailed assessment will be required for a<br />
decision on whether or not the college should remain at its present location.<br />
The northern section of the Cha Kwo Ling Road link of Option B will result in similar impacts to the Yau<br />
Tong Marine Lots as outlined above in the context of Option A, and will also impinge on the Cha Kwo<br />
Ling Road fire station.<br />
Yau Tong Road Link to Lei Yue Mun Road<br />
A site north west of the Po Chiu College has been reserved for open space purposes and has been<br />
allocated to Government. No planning has yet been undertaken for the site but its use would be in some<br />
doubt if the Yau Tong link of Option B were constructed.<br />
Further north along Yau Tong Road is a site reserved for the proposed East Kowloon Hospital. The<br />
design of the hospital would have to adopt self protective design measures in the vicinity of the Western<br />
Coast Road. A low noise open textured road surface and other 4 at source* mitigation measures would also<br />
be required if the proposed hospital were to be implemented.<br />
8.5.4 Land Use Impacts Summary<br />
A major advantage of Option B is that the sphere of influence and therefore the concomitant impact on<br />
existing and future land use will more limited than that of Option A. Option B would not, for example,<br />
preclude the development of Lei Yue Mun Supplementary Housing Site, Both Options will require the<br />
demolition of two industrial buildings.<br />
In terms of a comparative evaluation of the two Options the following assessment is made:<br />
> for existing land uses, including housing developments, public facilities etc, Option A is<br />
considered to have marginally less impact. Option B encroaches further into the Sam Ka Tsuen<br />
Recreation Ground (under construction) and impinges on the Po Chiu College and the Cha Kwo<br />
Ling Road fire station. Option A encroaches on the grounds of the Yau Tong and Ko Chiu Road<br />
Estates. Both Options encroach on the existing Yau Tong Marine Lots, Option B slightly more<br />
so;<br />
* for planned land uses, both Options encroach on the proposed Sam Ka Tsuen Complex and multistorey<br />
car park, as well as the proposed Yau Tong Bay Redevelopment. Option B will encroach<br />
on the proposed hospital site along Yau Tong Road. However, the major impact is that of Option<br />
A passing through the planned Lei Yue Mun Supplementary Housing Site, which would be<br />
severely disrupted if not rendered unsuitable due to the proposed road alignment, with significant<br />
loss (4,500) of flat production;<br />
> for industrial land uses, both Options have similar impacts with the required demolition of two<br />
industrial buildings.<br />
Options A and B are road options which, regardless of which is implemented, will have a major impact<br />
on an existing urban area- As has been shown, the utility of existing and planned development will be<br />
substantially affected by physical and environmental impacts. Valuable open space and public facilities<br />
will be lost or at least encroached upon and much needed housing development and upgrading proposals<br />
will be constrained by the loss of land and the need to provide environmental mitigation measures. From<br />
a land use planning perspective the selection of a link should not simply be cost driven. Substantial<br />
consideration should be given to the impact on people's livelihood and on the impact on the environment<br />
in which people live, work and relax.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
8.6 EN^VIRONSVIENTAL IMPACTS<br />
8.6.1 Noise Impacts<br />
The routes for each Option have been divided into segments for which noise levels were predicted in<br />
accordance with forecast peak traffic flows. Traffic flow forecasts used in this assessment are for morning<br />
peak flow in year 2011. Road traffic noise levels were calculated in terms of the L 10 (1-hr) in dB(A),<br />
using the U.K. Department of Transport procedures "Calculation of Road Traffic Noise" (CRTN), 1988.<br />
The maximum permissible road traffic noise level at the facade of domestic premises is 70 dB(A) L, 0 (1-<br />
hr). For educational institutions the suggested maximum noise level is 65 dB(A) L 10 (1-hr). Both<br />
domestic premises and educational institutions are considered to be noise sensitive receivers (NSRs). Of<br />
the many NSRs potentially affected by either Option, those likely to receive the greatest impact or those<br />
representative of a class of receiver were selected for impact modelling. Predicted noise levels were<br />
calculated based on the assumption that the road surface is of impervious concrete. Results of the<br />
modelling are shown below in Tables 8.2 and 8.3.<br />
TABLE 8.2 :<br />
OPTION A - PROJECTED TRAFFIC NOISE LEVELS AT MODELLED NSRs<br />
Major NSRs<br />
Major Separation from Predicted facade<br />
Traffic Noise the road kerb LlO(l-hr) dB(A)<br />
Contributor<br />
(m)<br />
Yau Tong Centre (West) (R1A)<br />
Yau Tong Estate (Block 17) (R2A)<br />
St. Antonius Primary School (R3A)<br />
Po Chiu College (R4A)<br />
Ko Chiu Road Estate (Block 1) (R5A)<br />
Yau Tong Est (Block 24) (R6A)<br />
Yau Tong Estate (Block 21) (R7A)<br />
20<br />
Cha Kwo<br />
Ling Road 26<br />
30<br />
16<br />
24<br />
Lei Yuc<br />
Mun Road 16<br />
42<br />
30<br />
79<br />
78<br />
SI<br />
35<br />
36<br />
80<br />
TABLE 8.3 :<br />
OPTION B - PROJECTED TRAFFIC NOISE LEVELS AT MODELLED NSRs<br />
Major NSRs<br />
Major<br />
Traffic Noise<br />
Contributor<br />
Separation from the<br />
road kerb<br />
(m)<br />
Predicted facade<br />
LlO(l-hr) dB(A)<br />
Yau Tong Centre (West) (RIB)<br />
Yau Tong Estate (Block 17) (R2B)<br />
Cha Kwo<br />
Ling Road<br />
26<br />
33<br />
84<br />
82<br />
St. Antonius Primary School (R3B)<br />
9<br />
36<br />
Po Chiu College (R4B)<br />
North bound slip<br />
road to Yau Tong<br />
Road<br />
15<br />
34<br />
Yau Tong Estate (Block 1) (R5B)<br />
Yau Tong Road<br />
3<br />
87<br />
APH Consultants Page 8-7
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
All predicted L 10 (1-hr) noise levels shown in the above tables exceed the 70 dB(A) limit recommended<br />
in HKPSG. In Option A, Ko Chiu Road Estate and Yau long Estate are the worst affected NSRs with<br />
predicted L 10 (1-hr) levels as high as 86 dB(A). In Option B, the worst affected NSRs are Yau long<br />
Estate (Block 1) and St. Antonius Primary School on Cha Kwo Ling Road, where the L 10 (1-hr) level is<br />
predicted to reach 87 dB(A) and 86 dB(A) respectively.<br />
Noise contours of typical sections of the roads for both Options have been defined. In all noise contour<br />
plots the 70 dB(A) contour was predicted to be at least 100 m from the centre line of the road. In the<br />
absence of noise control or mitigation measures, excessive noise levels within the 70 dB(A) contour<br />
distance of the roadway would preclude educational and/or residential development, thereby exerting a<br />
severe constraint on land use.<br />
Noise Mitigation Measures<br />
The use of pervious macadam road surface, rather than the concrete used in the generation of predicted<br />
noise levels, would reduce traffic noise by up to 3 dB(A), depending on traffic volume, speed and mix<br />
of light and heavy vehicles. Although attenuation of 3 dB(A) would not reduce the very high predicted<br />
noise levels to the limit set by HKPSG, use of pervious macadam would still be required on either Option<br />
A or B as an initial mitigation measure. However, additional measures would be required to achieve<br />
HKPSG limits.<br />
Road realignment to increase the setback distance of NSRs would be desirable, but not possible in either<br />
option due to space limitations. Distance separations shown in Tables 8.2 and 8.3 would need to be<br />
increased from their current range of between 8 m to 42 m, to over 120 m to achieve acceptable noise<br />
levels. Realignment to mitigate impacts to existing NSRs would also cause previously unaffected NSRs<br />
to be affected.<br />
Because limited space availability precludes adequate set backs, reduction of noise levels has been<br />
considered for a variety of mitigation measures at the noise source:<br />
> Roadside Barrier (4 m).<br />
+ Semi Enclosure, single carriageway.<br />
> Semi Enclosure, both carriageways.<br />
* Complete Road Enclosure (NSRs on both sides).<br />
Roadside barriers offer protection to low level receivers. The alignment and proximity of high rise<br />
residential development renders this kind of barrier ineffective. Use of semi-enclosure is considered to<br />
be a minimum requirement for noise reduction and can involve coverage of either a single or both<br />
carriageways. Single carriageway semi-enclosures are only effective when NSRs are on one side of the<br />
road and less than 20 m above the road surface. For receivers which are located more than 20 m above<br />
the road surface a noise reduction of only 2-3 dB(A) can be attained. Combining a pervious macadam<br />
surface with semi-enclosure yields a total noise reduction in the order of 5-6 dB(A) for receivers more<br />
than 20 m above road surface. A noise reduction of 5-6 dB(A) is however inadequate for both Options<br />
as NSRs require noise attenuation of more than 6 dB(A) to meet HKPSG limits. Where single<br />
carriageway semi-enclosures are ineffective but where NSRs are sited on one side of the alignment only,<br />
a semi-enclosure over both carriageways offers the protection of a total enclosure whilst allowing free<br />
venting of pollutants. Where high level NSRs are sited on either side of the alignment, complete road<br />
enclosure should be provided.<br />
Figures 8.3 and 8.4 show the locations of principal NSRs and the proposed noise enclosures. Breaks or<br />
openings have been introduced wherever the enclosures are not required for noise mitigation purposes.<br />
The minimum opening between the full enclosures is 10 m, for Option A.<br />
APH Consultants p e 8-3
Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
Fire regulations dictate that for any enclosure in excess of 230 metres forced ventilation is required to<br />
ensure that smoke generated in a fire is removed. For enclosures in excess of 450 metres full provision<br />
of fire safety equipment is required. The maximum length of enclosure, at 175 m (Option B), is less than<br />
these requirements and therefore would not be classed as a tunnel.<br />
Double glazing combined with air-conditioning for NSRs is an alternative noise mitigation measure.<br />
Provision of Type n glazing could reduce noise levels by 10-15 dB(A) according to HKPSG. For NSRs<br />
protected by semi-enclosures and higher than 20 m above road surfaces Type II glazing would achieve<br />
compliance with HKPSG noise standards and would obviate the need for total road enclosure. However,<br />
current Government policy is to undertake mitigation measures at source only.<br />
Construction Phase<br />
The Noise Control Ordinance (NCO) provides for control of noise from general construction work during<br />
evenings (1900-2300 hrs), night-time hours (2300 to 0700 hrs) and public holidays. Noise control<br />
regulations do not apply to non-holiday, daytime hours (0700-1900 hrs). Therefore, noise impacts can<br />
only be assessed with reference to a construction management plan and schedule. Because such details<br />
will not be available until the time of implementation, the construction impacts and mitigation measures<br />
are discussed in general terms only.<br />
For both Options A and B there are many NSRs which could be subjected to excessive noise levels during<br />
road construction. Of particular importance are the two educational institutions along Cha Kwo Ling Road<br />
(St Antonius Primary School and Po Chiu College). Construction methods and activities will require<br />
careful planning and execution to minimise disturbance to these establishments. Because both of the<br />
Options also require construction in the immediate vicinity of numerous residential blocks, construction<br />
methods and activities will also require careful coordination in these areas.<br />
Noise control methods which limit effects on NSRs include:<br />
* use of silenced equipment<br />
» siting equipment as far as possible from NSRs<br />
> use of temporary moveable acoustic barriers and machinery enclosures<br />
> proper maintenance and operation of plant<br />
> scheduling of works<br />
If piling is required, the use of percussive piling would give rise to excessive noise impacts particularly<br />
given the proximity of the NSRs. Consideration should be given to the use of bored piles which provide<br />
less of a noise impact.<br />
8,6*2 Air Quality Impacts<br />
As discussed in Section 8,6.2, total enclosures have been proposed to ameliorate the road traffic noise.<br />
In so doing, concern has turned to the likely air quality impact in the vicinity of the portals of these<br />
enclosures.<br />
For Option A t the worst case will be from the two enclosed sections and two separate modelling cases<br />
have been investigated. For end portal emissions the pollution is assumed to be generated within the two<br />
enclosures. For the 10 metre central opening, between the enclosures, a second exercise has been carried<br />
out which assumes that 33 % of pollutant generated within the two enclosures escapes through the opening.<br />
In summary this means that for portal emissions the SR at Yau Tong Estate (Block 24) will be subjected<br />
to 50% of the pollutants generated within the two enclosures and for the vent opening a separate "worst<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
case" is used which results in SR at Ko Chiu Road Estate (Block 1A) being subjected to 33% of the<br />
pollutants from the two enclosed sections.<br />
For Option B, it is the 175 m length of dual enclosure which has been identified as critical. To model<br />
the worst case it has been necessary to take account of carry over of pollutants from adjacent enclosed<br />
sections. At Yau Tong Estate (Block 2) it is assumed that 50% of the 175 m enclosure and 30% of the<br />
115 m enclosure contribute to the portal emission. At Po Chiu College 50% of the 175 m and 70% of<br />
the 115 m enclosures are assumed. For St. Antonius' Primary School 100% of the 110 m enclosure is<br />
assumed.<br />
In order to predict potential impacts, critical sensitive receptors have been identified for the two options<br />
and modelling has been carried out to quantify the air pollution condition at the receptor. Nine existing<br />
receptors have been identified which are likely to be affected by the portal emissions as indicated on<br />
Figures 8.4 and 8.5.<br />
The pollutant levels derived from the modelling exercise have been compared against the Hong Kong Air<br />
Quality Objectives (HKAQO). The HKAQO sets hourly concentrations of 30,000 jig/m 3 for carbon<br />
monoxide and 300 /ig/m 3 for nitrogen dioxide which shall not be exceeded on more than three occasions<br />
per annum.<br />
For emissions of Carbon Monoxide (CO) the worst case condition has been identified at Yau Tong Estate<br />
(Option B). The predicted CO level is 2,888 /ig/m 3 which is within the AQO requirement. It is therefore<br />
assumed that CO concentrations will not be critical for this assessment. For NO 2 , exceedences have been<br />
identified and the full results of the modelling exercise are reproduced in Tables 8.4 and 8.5 below.<br />
Generally, the SRs for Option A are sited close to the proposed roadway and experience air quality<br />
exceedences at the portal areas, Ko Chiu Road Estate (Block 1) and Yau Tong Estate (Block 24). In<br />
Option B the more substantial setbacks, for the majority of the receptors, allows compliance with the<br />
AQO, with the exception of a major exceedence at the Yau Tong Estate (Block 2).<br />
Since the road and SRs are fixed, for both Options, mitigation must involve removal of the pollution<br />
source. Two methods of mitigation have been identified. The first involves extending enclosures, to<br />
move the pollution away from the SRs, and the second involves venting the enclosure along its length<br />
while retaining the noise attenuation characteristics.<br />
TABLE 8.4 :<br />
NO 3 CONCENTRATIONS AT RECEPTORS IN OPTION A<br />
NO 2 Concentration, /ig/m 3 due to<br />
Receptors<br />
Road Emissioin<br />
Portal Emissioii<br />
Total Emission<br />
Ko Chiu Road Estate Block 1A<br />
66<br />
173<br />
239<br />
Ko Chiu Road Estate Block 1<br />
164<br />
156<br />
320 #<br />
Yau Tong Estate Block 24<br />
1S6<br />
205<br />
391 #<br />
Yau Tong Estate Block 21<br />
53<br />
131<br />
134<br />
# denotes an exceedence of the AQO<br />
APH Consultants p ag€ s-10
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
TABLE 8.5 :<br />
NO 3 CONCENTRATIONS AT RECEPTORS IN OPTION B<br />
NQ 2 Concentration, /ig/m 3 , due to<br />
Receptors<br />
Road Emission<br />
Portal Emissk3ti<br />
Total Emission<br />
Yau Tong Estate Block 2<br />
257<br />
200<br />
457 #<br />
Yau Tong Estate Block 11<br />
33<br />
147<br />
235<br />
Po Chiu College<br />
100<br />
154<br />
254<br />
St. Antonius" Primary School - EB<br />
110<br />
111<br />
221<br />
St. Antonius' Primary School - WB<br />
141<br />
114<br />
255<br />
# denotes an exceedence of the AQO<br />
Mitigation for Option A<br />
Ko Chiu Road Estate Block 1<br />
At this location, the predicted total NO 2 concentration is 32Qjig/m 3 and exceeds HKAQO. This worst case<br />
condition assumes that all pollutants generated within the enclosure escape from the portal. There is no<br />
allowance for venting through the 10 metre opening at the mid point. There is no proven modelling<br />
technique to confinn the loss at this point but it seems likely that the actual NO 2 level will be less than<br />
predicted and it is stressed that this is a worst case.<br />
A practical mitigation to remove the NQ 2 impact is to extend the northern end of the 130 m enclosure by<br />
20 m. The increased path distance would reduce the NQ 2 level at the SR to 272 jig/m 3 which is within<br />
the AQO.<br />
Yau Tong Estate Block 24<br />
This receptor is predicted to be exposed to NCk levels of 391 /xg/m 3 . This does not take into effect the<br />
presence of the semi enclosure between the source and receptor. The additional path distance is predicted<br />
to reduce the pollutant level at the receptor to 336 /ig/m 3 , though this still exceeds the AQO. Again, a<br />
portion of pollutants will escape through the opening between the two enclosures and the NO 2 level at this<br />
receptor would be further reduced.<br />
In order to produce AQO compliance, increasing the width of the semi-enclosure across the full width of<br />
Lei Yue Mun Road would increase path distance, increase separation and reduce NO 2 concentration to 277<br />
/ig/m 3 , which is within the AQO.<br />
Mitigation for Option B<br />
There is a single exceedence of the AQO for NO 2 at Yau Tong Estate (Block 2). This particular SR<br />
experiences a major exceedence at 457 /ig/m 3 . The following mitigation has been identified to overcome<br />
this impact.<br />
> extension of the enclosure by 40m will increase the path distance to a point where air quality<br />
impact on the identified SR is acceptable. However, the emission will then impact on the Yau<br />
Tong Playground and will cause exceedence of the AQO.<br />
Consultants<br />
Page
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
> use of semi-enclosure to allow free venting of traffic generated pollutants and remove the<br />
concentration effect at the portal. Though overcoming the air quality impact this could,<br />
potentially, expose the Po Chiu College and the proposed hospital to noise levels in excess of the<br />
HKPSG. It should be possible to remove the potential noise impact on the new hospital through<br />
its design, ie present a non-sensitive facade to the road. However, in the case of the existing Po<br />
Chiu College, the use of sealed windows and air conditioning systems should be considered. A<br />
similar alternative would be to design a noise cover which allows free venting of air pollutants<br />
while retaining noise integrity. Louvre noise protection systems are designed to allow free<br />
venting above the roadway but conventional designs produce protected and non protected "sides"<br />
for high level noise sensitive receivers (NSRs). The louvre system offers good protection but<br />
would have to be considered in the light of the hospital design. It is believed that a design could<br />
also be produced which provides the required venting and noise integrity requirement.<br />
Mitigation by employing semi-enclosure or enclosure with free venting louvres would require an<br />
extension of the northern end of the 175 m enclosure by 20 m. With this extension, the NO 2 level<br />
would be reduced to 250 /xg/m 3 for enclosure with free venting louvres while that for semi<br />
enclosure would be expected to be lower than 250 /ig/m 3 .<br />
Air Quality within Enclosures<br />
An assessment of the air quality impacts within the enclosed sections was made by comparison with a<br />
study of the air quality in a proposed enclosed section of Route 5 in Tsuen Wan. This assessment was<br />
carried out using the most critical working conditions. The nominal dimensions of vehicles were estimated<br />
based on the traffic mix. Using these and the road details, the vehicle emissions within the enclosure were<br />
calculated using the procedures as outlined in the Road Tunnels Report (1987) by the Permanent<br />
International Association of Road Congresses (PIARC). The conversion of NO to NO> was assumed to<br />
be 10%.<br />
The resultant concentrations of CO, NO 2 and NO were less than one-third of the air quality limits as<br />
stipulated by EPD for the design of tunnels. The 200 m enclosure of Route 5 is expected to carry 3,444<br />
veh/hr with 68% of heavy vehicles. On the other hand, both the 130 m and 135 m long enclosures in<br />
Option A will have a traffic flow of 3,036 veh/hr with 62% of heavy vehicles. By comparison, it is<br />
unlikely that the air quality within the proposed enclosures will exceed EPD's criteria. Similarly, in<br />
Option B, the air quality within the 115 m and 110 m long enclosures should meet the above criteria.<br />
Construction Phase<br />
The major air quality impact during the construction of the Western Coast Road and the associated<br />
connecting road network will result from dust emissions measurable as total suspended particulates (TSP)<br />
and respirable suspended particulates (RSP). Major dust sources are likely to be:<br />
> site preparation;<br />
> excavation;<br />
+ wind erosion of stockpiled materials and working areas;<br />
* material transfer to and from trucks/barges;<br />
» vehicle/plant movements on unpaved roads and over the sites;<br />
* concrete batching; and<br />
> concrete finishing.<br />
Because construction schedules and equipment usage data are not available, dust levels arising from<br />
construction work cannot be quantified at this stage of evaluation. However, construction dust can be<br />
significantly reduced through appropriate site practices. The two Options are expected to be<br />
approximately comparable in terms of dust emission during the construction phase.<br />
APH Consultants p age #.£2
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
8.6.3 Visual Impacts<br />
An assessment of visual impacts includes the following aspects:<br />
> the apparent size of the development from selected viewpoints<br />
> distances from the development to the sensitive receivers<br />
> the number of sensitive receivers affected<br />
» the change in the visual amenity of the area<br />
The consideration of these visual aspects involves essentially a subjective assessment. Given the elevated<br />
nature of certain sections of the roads, the close proximity of the roads to sensitive receivers, the large<br />
numbers of sensitive receivers affected and the likely change in the visual amenity, it is considered that<br />
the visual impacts will be very significant and in some cases severe for both Options A and B.<br />
8.6.4 Environmental Impacts Summary<br />
For noise impacts, both Options would require extensive construction of semi or total road enclosures to<br />
reduce the noise levels to within the HKPSG limits. This is due to the existence of many noise sensitive<br />
receivers in the immediate proximity of both proposed alignments.<br />
In terms of a comparative evaluation, the two Options are considered with their required noise mitigation<br />
measures in place. The assessment is therefore based on residual noise effects as compared with the<br />
existing situation. In this respect, Option B is considered more suitable, as the residual traffic noise<br />
occurs over an area where traffic is already present, while Option A will generate traffic noise over a<br />
wider area, including where little or no traffic occurs at present.<br />
The assessment has identified exceedences of the Air Quality Objectives (AQO) for both Options and<br />
mitigation has been proposed to overcome the exceedence. In Option A the receptors are, generally, closer<br />
to the WCR and mitigation has involved extension of enclosure and semi enclosure to increase path<br />
distance to receptors and reduce pollutant concentrations to levels which do not exceed the AQO. In<br />
Option B there is a single, major, AQO exceedence at a single receptor. Mitigation to protect the affected<br />
receptor would require an integrated design approach and involves the layout and design of the hospital<br />
to the west of Yau Tong Road, It is proposed that the main enclosure is designed to be free venting<br />
through louvres which allow a measure of noise protection to elevated noise sensitive receivers.<br />
Significant permanent visual impacts will be generated by the construction of both Options, The<br />
installation of noise mitigation measures, in the form of road enclosures, will exacerbate the significant<br />
visual impacts of elevated major roadways.<br />
8.7 COST COMPARISON<br />
Indicative construction costs for the Western Coast Road, Options A and B, have been estimated for the<br />
comparative assessment of these Options. The estimated costs include the noise mitigation measures<br />
recommended in Section 8.6.1. Summaries of these costs are shown in Table 8.6 below.<br />
APH Consultants
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
TABLE 8.6 :<br />
CONSTRUCTION COSTS<br />
PRELIMINARIES<br />
EARTHWORKS<br />
Rock Excavation<br />
Soft Excavation<br />
Fill Material<br />
ROADWORKS<br />
Site Clearance<br />
Drainage<br />
Roads & Paving<br />
Footways & Kerbing<br />
STRUCTURES<br />
Elevated<br />
Retaining Walls<br />
SLOPE PROTECTION WORKS<br />
MITIGATION MEASURES<br />
SUB TOTAL<br />
ADD 10% CONTINGENCIES<br />
TOTAL ESTIMATE<br />
OPTION A<br />
HKS (MILLIONS)<br />
66.1<br />
11.6<br />
3.2<br />
9.2<br />
0.1<br />
7.4<br />
36.0<br />
2.0<br />
345.0<br />
28.0<br />
2.0<br />
217.0<br />
727.6<br />
72.8<br />
8004<br />
OPTION B<br />
HK$ (MILLIONS)<br />
68.4<br />
10.0<br />
2.0<br />
0.0<br />
0.1<br />
8.0<br />
31.0<br />
2.0<br />
383.0<br />
10.0<br />
4.0<br />
234.0<br />
752.5<br />
75.3<br />
827.8<br />
The construction cost of Option B is therefore about 3% more than that of Option A. For both Options,<br />
the cost of noise mitigation measures accounts for nearly 30% of the total construction cost.<br />
Resumption costs represent a significant addition to the total project costs. Major resumption costs<br />
applicable to both Options A and B are those relating to the demolition of the Sunray Industrial Centre<br />
and the Yau Tong Industrial Building Block 3. These have been estimated as being about HKS 250M,<br />
excluding any incentive payments,<br />
"Lost opportunity costs" have also been considered. Relevant Government Departments have been<br />
requested to supply the estimated abottive/reprovisioning/lost opportunity costs that would arise from the<br />
construction of either Option A or Option B.<br />
Urban Services Department have estimated these costs to be:<br />
> HKS 1.2M for the Sam Ka Tsuen Complex, This cost would be applicable to Option A and<br />
Option B as they both impinge on this site.<br />
> HKS 3.0M for the Sam Ka Tsuen Recreation Ground. This cost would be applicable to Option<br />
B. Option A encroaches only slightly and would not cause excessive disruption.<br />
Housing Department have estimated their reprovisioning costs to be:<br />
* HKS 260M for the reprovisioning of the Lei Yue Mun Supplementary Housing Site. This cost<br />
would be applicable to Option A. Option B does not affect this site.<br />
AfH Consultants<br />
p ag€
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
Project costs for the two schemes, based upon the above additions, are therefore estimated to be of the<br />
order of:<br />
> Option A: HK$ 1.311M<br />
* OptionB : HK$ 1,082M<br />
Option B is thus shown to be the more cost effective option,<br />
8.8 EVALUATION SUMMARY<br />
The above discussion of the two connections under the main criteria permits the following conclusions to<br />
be drawn:<br />
> Traffic and Roads: Option B is shown to have a marginal benefit in terms of traffic flow.<br />
+ Land Use Impacts: Both Options have severe impacts.<br />
Existing Land Use; Option A is considered to have marginally less impact.<br />
Planned Land Use; Option B, in avoiding the major impact to the Lei Yue Mun Supplementary<br />
Housing Estate, is considered have less impact.<br />
Industrial Land Use; both options have similar impacts.<br />
> Environmental Impacts: Both Options have severe impacts.<br />
Noise; Option B is considered more suitable on the basis of the residual impacts.<br />
Air Quality; Option B is considered to be more suitable in view of the limited number of receivers<br />
effected.<br />
Visual; both options have similar and severe impacts.<br />
» Cost Comparison: Option B has been shown to be the most cost effective.<br />
In all instances, bar the marginal additional effects upon existing land uses, Option B has been adjudged<br />
to have a lesser impact and is the most cost effective in project cost terms. It should be noted that both<br />
Options have extensive impacts and this preference must be measured in terms of a reduction in the<br />
severity of the impact rather than the identification of a optimum solution.<br />
Notwithstanding, Option B is recommended as the preferred alignment of the two required to be studied<br />
under the Brief. However, to establish as to whether this alignment does in fact represent the optimum<br />
for the connection of the Western Coast Road to East Kowloon, further study would be required over a<br />
wider area.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
SECTION 9<br />
ENVIRONMENTAL ASSESSMENT<br />
9.1 INTRODUCTION<br />
This assessment evaluates the environmental impacts associated with the construction and operation of<br />
Area 137. For significant impacts, mitigation measures are identified and, in addition, environmental<br />
monitoring and audit schedules are recommended. The potential impacts and mitigation are discussed<br />
under the following environmental indicator categories :<br />
+ Water quality;<br />
> Air quality;<br />
> Noise;<br />
> Waste Management; and<br />
> Visual Impact and Glare Nuisance<br />
9,2 KEY IMPACT SOURCES AND SENSITIVE RECEIVERS<br />
In the baseline studies the key impacts and existing and committed sensitive receivers (SRs) were<br />
identified. In this report only sources which have potential to create impact and potentially impacted users<br />
are identified.<br />
9*2-1 Impact Sources<br />
The development of Area 137 will, inevitably, create new environmental impact sources. Most<br />
construction phase impacts can be broadly defined, including the likely dredging and reclamation<br />
techniques. The impact of the operation phase is less well defined and potential impacts are less clear.<br />
As part of the Study, potential users of Area 137 have been identified and these are broadly split into two<br />
types of use. Both rely on the need for berthing facilities, but one use, by nature of the products to be<br />
handled is identified as PHI.<br />
In addition to the construction and operation impacts of Area 137 existing and known committed<br />
developments within Tseung Kwan O and adjacent areas have been assessed for significance. Of the<br />
numerous potential impact sources identified only four are believed to have a potentially significant<br />
bearing on the development and operation of Area 137. The location of the key impact sources are shown<br />
in Figure 9.1. The specific impact sources are :<br />
Tseung Kwan O Industrial Estate which is sited immediately to the north of Area 137. It is predicted<br />
that the operation of industry on the TKOIE site will generate noise, air quality, water quality and solid<br />
waste impacts though the impact on Area 137 is anticipated to be minimal.<br />
SENT Landfill is sited immediately to the north and east of the Area 137 development. During the<br />
construction and operation phases of Area 137 it is a requirement that road access to a sea berth, provided<br />
for the delivery of solid waste is maintained through the site. There are potential impacts on the noise,<br />
air and water environments.<br />
APH Consultants<br />
Page
Figure 9.1<br />
:-\'y ; u 6 V^A;*3<br />
TKOIE<br />
Junk Bay Landfill<br />
SENT Landfill<br />
Spoil Ground<br />
1 • •' v ' '•iLr'- •<br />
*\ ^/rx::-<br />
,xvm ; >..<br />
11 -* « ..'y«^Hrtiw»w<br />
KEY IMPACT SOURCES<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Find Report - Main Report<br />
Tseung Kwan O (Junk Bay) Landfill is sited to the north of Area 137 beyond the TKOIE site. The<br />
landfill is split into three phases with Phases I and II completed and Phase HI scheduled for completion<br />
in early 1994. Shortage of landfill space has dictated that the Phase I/H landfill will be reopened to accept<br />
a limited further input of waste. The landfills have potential impacts oa water quality from seepage of<br />
leachate into the receiving waterbody.<br />
Spoil Ground Beneath Area 137 represents, potentially, the most significant impact area. The spoil<br />
ground lies under part of the Area 137 development and may be affected by dredging and reclamation.<br />
Impact on water quality by disturbance of material and disposal of any contaminated material represent<br />
potential impact areas. The location of the spoil ground is shown in Figure 9.2.<br />
9.2.2 Sensitive Receivers<br />
As part of the environmental baseline study all potential sensitive receivers (SRs) within the Study Area<br />
were identified. Of these SRs only a limited number were identified as having potential to suffer impact<br />
from the construction and operation of Area 137, some were too remote from the impact sources others,<br />
though identified as sensitive were found to have been relocated or were in the process of relocation. The<br />
location of the sensitive receivers are set out in Figure 9.3. The potentially significant SRs are identified<br />
and described in the following paragraphs.<br />
Tung Lung Chau Fish Culture Zone (FCZ). A fish culture zone operates off the north western coast<br />
of Tung Lung Chau. Fish culture requires good water quality and is susceptible to impact at both the<br />
construction and operation phases of the project. This sensitive receiver is sited 2 km to the south east<br />
of Area 137.<br />
Siu Sai Wan and Chai Wan* The closest residential areas to Area 137 are sited to the south west across<br />
the Tathong Channel on Hong Kong Island. Residential areas are defined as SRs susceptible to both noise<br />
and air quality impact in the Hong Kong Planning Standards and Guidelines (HKPSG); in addition visual<br />
impacts will be significant. In order to allow predictions of impact to be made, two locations were<br />
identified at residential properties, Siu Sai Wan and Heng Fa Chuen. SRs are approximately 1.5 Km from<br />
Area 137.<br />
Tseung Kwan O New Town. The new residential areas to the north, within Tseung Kwan O, represent<br />
a significant grouping of SRs. The significance of Area 137 is diminished by the distance to SRs and the<br />
location of the TKOIE site, and established industry, between Area 137 and the SRs.<br />
93 WATER QUALITY<br />
93.1 Background<br />
Tseung Kwan O exhibits water quality conditions which reflect its geographical location as an embayed<br />
area close to Victoria harbour and also the effects of significant local effluent loadings. The water is<br />
organically enriched, and has relatively high levels of nitrogenous compounds and bacterial concentrations<br />
which are confirmed by the ongoing EPD water quality monitoring programme. Traditionally Tseung<br />
Kwan O has suffered significant effluent loadings and linked to the poor water exchange capacity, has<br />
experienced poor water quality. Junk Bay was declared a Water Control Zone (WCZ) in 1989. Following<br />
declaration of a WCZ effluent discharges require licensing to standards which are set out in the Technical<br />
Memorandum, An outfall from the sewage treatment works was constructed into the Tathong Channel<br />
to remove nutrient loading from Tseung Kwan O and this has resulted in improvements to the water<br />
quality. However, water quality conditions remain poor and are exacerbated by the additional loadings<br />
of leachate from the Junk Bay landfills and industrial discharges from Rennies Mill.<br />
APH Consultants Pag* 9-2
Figure 9.2<br />
Study Area<br />
Spoil Ground<br />
SPOIL GROUND BENEATH STUDY AREA<br />
APH CONSULTANTS
Figure 9.3<br />
ra yjMt. i \<br />
'/'£*.'. %'W|^<br />
^r^N^-.i^/' Mtt»<br />
»..V.«_v*AT.' J.. ,< Urwirwwo<br />
t>
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
The organic enrichment of the bay gives rise to elevated levels of chlorophyll-a, and blooms of toxic<br />
dinoflageiiates have been recorded in the past, the so called "red tides". Detailed reviews of water quality<br />
in Tseung Kwan O have been carried out in other studies, most notably the EA for the Tseung Kwan 0<br />
Development Sewage Treatment and Disposal Study. For this Study, water quality has been fully<br />
documented in the Environmental Background Paper and the Preferred Concept Report and is not detailed<br />
here, except in areas which have a direct bearing on Area 137.<br />
9.3.2 WAHMO Modelling<br />
The modelling evaluated the effects of the Area 137 reclamation on water quality in Tseung Kwan 0. In<br />
addition, several model runs were employed to provide data on the impacts of an additional reclamation,<br />
off Area 131 to the southwest of the bay.<br />
Previous studies of other developments in this area, using models from the WAHMO suite, have shown<br />
that worst case water quality conditions generally occur in predictions for the wet season and spring tides.<br />
However, due to other considerations, the water quality modelling included additional simulations for dry<br />
seasons/spring tides.<br />
The scenarios modelled were as follows:<br />
> Existing Conditions: based on present reclamations within the modelled area using estimated<br />
pollution loads for 1996.<br />
> Baseline: composing all committed reclamations within the modelled area.<br />
> Scenario 1: overlaying the baseline with the Area 137 reclamation.<br />
> Scenario 2: overlaying the baseline with the Area 137 development and Area 131.<br />
> Scenario 3: overlaying the baseline with an initial development of Area 137.<br />
» Scenario 4: overlaying the baseline with an initial development of Area 137 and Area 131.<br />
To assist interpretation of the water quality data from the modelling, 12 reference stations were set up as<br />
shown on Figure 9.4. These serve as reference sites for the production of water quality data in the form<br />
of CVT (concentration versus time) plots, which may then be employed to permit comparisons between<br />
the predictions for the existing situation and those for baseline conditions and for the various development<br />
scenarios.<br />
Water quality predictions are presented for existing conditions compared to those for the other scenarios<br />
under the worst case conditions of wet season spring tides. The parameters included are dissolved oxygen;<br />
BOD 5 ; various chemical species of nitrogen; chlorophyll-a; and £. colL<br />
Dissolved Oxygen<br />
Significant changes to dissolved oxygen levels were predicted for the baseline conditions and all<br />
development scenarios compared to existing conditions. However, there were essentially no differences<br />
between the model output for the baseline conditions and any of the development scenarios. In each of<br />
these cases, dissolved oxygen levels were predicted to increase significantly over those modelled for<br />
existing conditions at all reference sites other than numbers 1 and 11. These increases were most marked<br />
at reference sites 5 to 10, which are generally located in Tseung Kwan O and the Tathong Channel area.<br />
Evidence of supersaturation of oxygen was produced at reference sites 6 to 10 and 12, indicating the<br />
existence of significant algal growth (see the discussion of chlorophyil-a levels below).<br />
BOD 3<br />
Again, differences between the predictions for the baseline conditions and those for the development<br />
scenarios were minor and generally insignificant. However, the model output for each of these exhibited<br />
APH Consultants p age $-3
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Fined Report - Main Report<br />
significant differences from the predictions for existing conditions. Thus, BOD 5 levels were modelled to<br />
increase at most reference sites by comparison to the levels predicted for existing conditions. These<br />
changes were less marked at reference sites 1, 10 and 12 and were generally absent or very minor at<br />
reference site 11, whilst they were most evident at reference sites 6 and 7. For example, average BOD 5<br />
levels at reference site 6 increased from about 4 mg/1 in predictions for existing conditions to about 5 mg/1<br />
in output for the baseline conditions or the various development scenarios. It is notable that the increases<br />
in BOD 5 levels recorded here for wet season/spring tide conditions contrast markedly to the decreases in<br />
such levels noted for dry season/spring tide simulations.<br />
Nitrogenous Species<br />
Differences between the wet season/spring tide and dry season/spring tide simulations were again apparent.<br />
In the case of the wet season/spring tide output, concentrations of total nitrogen predicted for the baseline<br />
conditions or the various development scenarios increased at most reference sites by comparison to those<br />
predicted for existing conditions. These increases in inorganic nitrogen were accompanied by comparable<br />
elevations in levels of organic nitrogen and oxidised nitrogen, whereas predicted concentrations of<br />
ammoniacal nitrogen decreased in the baseline conditions and the development scenarios by comparison<br />
to existing conditions. These changes in the predicted concentrations and speciation of nitrogenous<br />
compounds were no doubt a contributory factor to the general increases in chlorophyll-a predicted for the<br />
development scenarios compared to existing conditions.<br />
Chlorophyll-a<br />
There were no significant differences between the predicted chlorophyil-a levels for the baseline conditions<br />
and the various development scenarios. However, each of these differed from predictions for existing<br />
conditions, most reference sites exhibiting increases in chlorophyll-a levels. Only reference site 11 was<br />
unaffected by these changes, although sites 10 and 12 to the south of Tathong Channel exhibited minor<br />
changes rather than the more marked alterations observed elsewhere. It may be noted here that WAHMObased<br />
studies on other developments have suggested that chlorophyll-a predictions are highly sensitive to<br />
small changes in the other parameters modelled. Nevertheless, the prediction that chlorophyll-a levels are<br />
likely to increase substantially in the eastern reaches of Victoria Harbour and in northern Tathong Channel<br />
consequent to the construction of the baseline reclamations is of some concern.<br />
E. coli<br />
By contrast to the other parameters modelled, very few changes were predicted for levels of E. coll in the<br />
Study Area, either for the baseline conditions or the various development scenarios. The only alterations<br />
of note occurred at reference sites 6 and 7, and these constituted small increases (less than one log value)<br />
in E. coli numbers over those predicted for existing conditions.<br />
These results give rise to several important conclusions concerning the options for the development of<br />
Tseung Kwan 0 as a whole. These are as follows:<br />
» Predicted water quality for the baseline conditions differed substantially from that for existing<br />
conditions. In the wet season/spring tide simulations in particular, the addition of the baseline<br />
reclamations (without altering assumed pollutant loads) created a significant reduction in water<br />
quality, with marked increases in several species of nitrogen and in predicted chlorophyll-a levels.<br />
These changes gave rise to increases in dissolved oxygen in the Study Area, reaching<br />
supersaturation levels in reference sites in Tseung Kwan O and Tathong Channel.<br />
* Such changes in predicted water quality are of considerable concern, as it would appear likely that<br />
the committed reclamations could lead to non-compliance with Water Quality Objectives in the<br />
Study Area, even in the absence of increased pollutant loadings. It should be re-stated that the<br />
APH Consultants p a g$
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report • Main Report<br />
reclamations giving rise to these predicted effects are the committed projects, and not those<br />
associated with either the Area 137 or the Area 131 developments.<br />
The differences between the predictions for the various future development options for Areas 137<br />
and 131 (and between these and baseline conditions) were ail minor. This implies that the<br />
alteration in shape of the Area 137 reclamation (involving either its phasing or its detailed design)<br />
has no material effect on water quality in the Study Area. The same is seen to be the case for<br />
the Area 131 reclamation, when this is present in combination with the Area 137 development.<br />
Thus, the various development scenarios were modelled to exhibit very similar water quality to<br />
the baseline scenario.<br />
9.3.3 Dredging and Disposal of Sediments<br />
Background<br />
It is known that the sediments within Junk Bay are contaminated due to historical industrial practises and<br />
the influence of contaminants from Victoria Harbour. Potentially more significant is the fact that Area<br />
137 will be sited on a former spoil ground. The information relating to the types of material which were<br />
dumped is not well documented. A limited sampling and testing programme has been carried out as part<br />
of this Study and, together with, results from other studies, has been used to identify potential impacts.<br />
The dredging for Area 137 is likely to be carried out by grab dredgers and will involve the removal of<br />
some 2.9 Mm 3 from the area to form the berthing areas, approach channels and the seawall trenches. It<br />
will be necessary to ensure that any grab dredgers used are fitted with tightly closing grabs in a well<br />
maintained condition, all dredging occurs within silt curtains and that ao overflowing of the barges is<br />
allowed. Water quality schedules and action plans are provided in Section 9.8.<br />
It is believed that more intensive survey work will be necessary in the detailed design phases of the project<br />
implementation to investigate the contaminated aspect further. The closest SR to Area 137 is the fish<br />
culture zone sited off the north western coast of Tung Lung Island section.<br />
Contaminated Sediments<br />
The marine sediments at Tseung Kwan 0 are routinely monitored by the Environmental Protection<br />
Department and show significant metal contamination. However, the EPD sampling does not cover the<br />
Area 137 site. As part of the Contaminated Spoil Management Study (CSM) sampling on the old spoil<br />
ground beneath Area 137 was carried out and testing showed elevated levels of lead and zinc and excessive<br />
mercury contamination. The location of CSM sampling sites in relation to area 137 are shown in Figure<br />
9.5 and results of the testing programme are reproduced in Table 9.1.<br />
TABLE 9.1 :<br />
CSM STUDY ANALYTICAL RESULTS OF SEDIMENT SAMPLES FROM THE STUDY AREA<br />
Cu Cr Cd Pb Zn Ni Hg<br />
Site bulk
Figure 9.5<br />
0 Study Sample Point<br />
CSM Sample Point<br />
SEDIMENT SAMPLING POINTS<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
As part of this Study additional sampling and testing was carried out and this confirmed the elevated levels<br />
of metal contamination, particularly lead. The sampling results are reproduced as Table 9.2.<br />
TABLE 9.2 :<br />
AREA 137 STUDY ANALYTICAL RESULTS OF SEDIMENT SAMPLES<br />
Site<br />
Metal<br />
Cd<br />
Pb<br />
Ni<br />
Zn<br />
Cr<br />
Hg<br />
Cu<br />
Jltop<br />
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Impact on Tung Lung Chau FCZ<br />
In determining the impact of dredging on marine ecology at Tung Lung Chau a worst case situation is<br />
assumed. The seawall trench is assumed to be formed by a grab dredger of 10 m 3 capacity working at<br />
a production rate of 50,000 m 3 /week in a 10 m water depth with maximum currents of 0.6 m/s.<br />
Dredging without the use of silt curtains and using an open grab will result in a loss of sediment, (the S-<br />
factor), of 10-15 kg/m 3 of mud dredged. Assuming 130 operational hours, the rate of sediment release<br />
will be 4,800 kg/hr. At a maximum current speed of 0.6 m/s, 2.2 kg of sediment will be injected into<br />
the plume per metre. The initial plume width is assumed to be approximately 50 m at a distance of 50 m<br />
from the dredger. If the current velocity and direction remains constant, sediment would reach the FCZ<br />
in approximately 55 minutes.<br />
Diffusion of the plume is inevitable and at 2 km distance the plume is assumed to have increased its initial<br />
width by a factor of 3 giving a worst case scenario of, at most, a suspended solids concentration of 1.6<br />
ing/l above the background at the FCZ.<br />
In addition, Work by Yagi et al., 1976 and Harris et al., 1988, has demonstrated the decline in suspended<br />
solids concentration downstream of a grab dredger. Typically, suspended solids values will fall by as<br />
much as 80% over a distance of 100 metres. This would support the above as a worst case, and therefore<br />
it is most unlikely that suspended solids will have an effect at the FCZ.<br />
Despite this, it is recommended that the following mitigation measures are adopted to minimise the<br />
potential dredging impacts, since incorporation of specific requirements within contract conditions offer<br />
an effective method of controlling impact, if strictly enforced :<br />
* utilising a grab which closes tightly preventing sediment loss as it ascends;<br />
> avoiding sediment overflow from die barge where possible; and<br />
* using a slower hoisting speed, (research by Yagi et al., has shown that a hoisting speed of 0.85<br />
m/s as opposed to 1.25 m/s, can reduce the suspended solids in the upper water column by 20<br />
to 30%.<br />
9,4 AIR QUALITY<br />
9.4.1 Background<br />
Area 137 is situated on the southern fringe of the Tseung Kwan O confined airshed. Confined airsheds<br />
have limited potential to disperse pollutants generated within the airshed. The reclamation work,<br />
construction and operation of Area 137 have the potential to introduce pollutants into the airshed and<br />
therefore impact on air quality. In addition there are also potential impacts on closer SRs at Chai Wan,<br />
across the Tathong Channel, to the south west.<br />
The meteorological characteristics of the southern fringe of the TKO confined airshed, and therefore Area<br />
137, had not been investigated in any detail prior to this Study. In order to determine if Area 137 was<br />
withui the confined airshed and therefore if pollutants generated by Area 137 would influence air quality,<br />
a limited air monitoring programme was carried out and compared with the results from EPD's Junk Bay<br />
monitoring station. It is recorded in the EPD publication Environment Hong Kong 1992 ttiat annual<br />
average and maximum daily pollutant concentrations recorded at the Junk Bay air quality monitoring<br />
station did not exceed the Air Quality Objective (AQO) in 1991.<br />
APS Consultants p age 9.7
Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
9.4.2 Monitoring<br />
A monitoring station was set up and operated at Tin Ha, immediately to the north of area 137 on the<br />
Clearwater Bay Peninsula, for the period 10 to 27 July 1992. The data obtained was compered to that<br />
recorded at the EPD monitoring station situated at the head of Junk Bay at the Haven of Hope Sanatorium.<br />
It is appreciated that such a short monitoring period does not allow definitive conclusions to be drawn<br />
though there appeared to be general correlation between the air quality data recorded at each of the<br />
monitoring stations. The results of the survey suggested that air quality was similar at both stations and<br />
it was therefore concluded that emissions from Area 137 would enter the TKO airshed. However, it was<br />
noted that there was a difference between the results for S0 2 pollutant levels, which were higher at the<br />
EPD station.<br />
Meteorological conditions were monitored at both stations and here there was very significant variance.<br />
Although the information was of interest, it did not influence the outcome of the assessment but confirmed<br />
that meteorological monitoring for Area 137 would have to be carried out at the site, over water, to<br />
remove the effect of local irregularities in air movements. The location of the EPD monitoring station<br />
and the Study monitoring station are shown in Figure 9.6.<br />
9.4.3 Assessment<br />
Air quality impacts will be generated during both the construction and operating phases of the project.<br />
Three distinct impact areas have been identified, two during operation and one during construction<br />
> road traffic accessing the Area 137;<br />
* potential emissions from industry;<br />
> dust from construction.<br />
Since the actual details of end users at Area 137 are undefined, the air quality assessment has involved<br />
a number of assumptions which will need to be confirmed fay specific assessment work as users come<br />
forward with development proposals. Generally the industry to be located here is unlikely to be air<br />
polluting, or, in the case of most PHIs, will be specified processes which are subject to controls set out<br />
in the Air Pollution Control Ordinance. A special case, which has been assessed as an indicator of<br />
significance, is town gas manufacture from naphtha. This process has potentially significant air quality<br />
impacts relating to SO 2 and NO 2 emissions. Port related industry is unlikely to involve manufacturing<br />
processes and is more likely to be involved in the receipt and packing / unpacking of material received<br />
/ dispatched by road or sea which will not impact on air quality.<br />
9.4.4 Road Traffic<br />
For air pollution initiated by road vehicles the vehicles numbers have been obtained from the Traffic and<br />
Transport Assessment carried out as part of the Study. Vehicle movements are relatively low but with<br />
a high proportion of heavy vehicles, which make up 74-78% of the traffic flow. Nitrogen oxide (NO),<br />
carbon dioxide (COn) and particulates are the main air pollutants arising from heavy vehicle movements.<br />
HKPSG notes that the buffer distance required for active and passive recreational uses is 20 metres from<br />
the kerb of either Trunk or Primary Distributor Roads. The closest SRs are located at Stu Sai Wan and<br />
Heng Fa Chuen which are over 1.5 km from Area 137 and will not be adversely affected by gaseous<br />
pollution generated by road traffic.<br />
9.4.5 Industry<br />
DWI uses have not been finalised but given the distance to SRs and the types of activities, these industries<br />
are unlikely to cause impact. In the case of PHI certain facilities have been identified for planning<br />
purposes and these include:<br />
APH Consultants Page 9-8
Figure 9.6<br />
EPD Monitoring Station<br />
Havea of Hope Sanitorium<br />
^""^s4"f$ ''fa<br />
mt*$Mw<br />
' • - » l .\TX I '\ J *»*<br />
Study Monitoring Station<br />
Tin Ha Village<br />
•^Y;-i^.,; N v:Rdl<br />
AIR QUALITY MONITORING STATIONS<br />
APH CONSULTANTS
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
» fuel storage;<br />
> bulk chemical storage;<br />
> Liquified Petroleum Gas storage<br />
> naphtha storage and gas production facility<br />
Of these identified developments the significant air polluting source is taken to be from the naphtha<br />
processing plant. This is designated as a Specified Processes under the Air Pollution Control Ordinance<br />
(APCO), which require the best practicable means to prevent emission of pollutants and to render such<br />
emissions harmless and inoffensive. The other facilities are unlikely to include combustion equipment and<br />
therefore no emissions of S0 2 or NO X are anticipated. Should these land uses be replaced by fiiel intensive<br />
industries, at a later stage, additional air quality assessment will be required.<br />
Sulphur Dioxide (SO^ and Nitrogen Dioxide Q^O^) are the major air pollutants arising from the town gas<br />
manufacture from naphtha and have been chosen as air quality indicators in this assessment. The scale<br />
and layout of the gas production plant has not yet been finalised, thus a typical S0 2 emission rate from this<br />
proposed plant is assumed as 10 g/m 2 /day. The emission rate corresponds to 18.5 g/s of SO 2 generated<br />
from a 16 ha area. For comparison the existing Ma Tau Kok gas production plant capacity is 3,0 x 10 5<br />
m 3 /day which corresponds to a maximum S0 2 emission rate of 3.9 g/s. Hence the assumed emission rate<br />
of 10 g/mVday for the Area 137 site corresponds to a cyclic catalytic gas production facility of about five<br />
times the capacity of Ma Tau Kok.<br />
For N0 2 , a typical emission rate of 15 g/nr/day has been derived, based on the existing Ma Tau Kok gas<br />
production plant. This assumed emission rate also corresponds to a cyclic catalytic gas production facility<br />
of about five times the capacity of Ma Tau Kok.<br />
The Industrial Source Complex Short Term Model (ISCST), has been used in the assessment with the<br />
following parameters:<br />
Emission Strength (SOJ 10 g/m 2 /day<br />
Emission Strength (NO 2 ) 15 g/mr/day<br />
Emission Height<br />
10 m<br />
Area<br />
16 ha<br />
Working Hours<br />
24 hrs/day<br />
Wind Speed<br />
2 m/s<br />
Wind Direction<br />
Downwind<br />
Atmospheric Stability 4 (D)<br />
Mixing Height<br />
500 m<br />
Temperature 25°C<br />
SRs at Tseung Kwan O New Town within the confined airshed have been identified in this assessment as<br />
being potentially critical. SRs are approximately 4 km north west of Area 137.<br />
Results and Implications<br />
The results show that the SO-, concentrations which SRs at Tseung Kwan O New Town could experience<br />
due to emissions from the activities of Area 137 would be 22/ig/in 3 (24 hour average), whilst the NO 2<br />
concentrations would reach 32 /ig/m 3 (24 hour average). The final report on TKOFSOFD predicted<br />
maximum S0 2 concentrations of 220 /ig/m 3 (after relocation of Shiu Wing) plus Ig/m 2 /day at the southeast<br />
corner of the Tseung Kwan O New Town. The corresponding maximum NO 2 concentration wouid^S<br />
/ig/m 3 (24 hour average) with the assumption of fuel oil (0.5% sulphur content). The AQO^s of 350<br />
/ig/mVday for SO 2 and 150 /ig/m 3 /day for NO 2 can therefore be achieved andit is therefore predicted chat<br />
town gas production at Area 137 will not impact on SRs.<br />
APR Consultants
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
9*4.6 Construction<br />
No detailed construction plans have been formulated, but it is assumed that dust would arise from the<br />
following activities:<br />
* general construction operations;<br />
> truck movements on unpaved roads;<br />
* aggregate storage piles; and<br />
* concrete batching.<br />
The Industrial Source Complex (ISC2) short-term model has been used to predict dust concentration from<br />
sources associated with these operations. Analysis carried out for the Preferred Concept identified the<br />
likely processes and predicted highest hourly concentrations for TSP at different distances from the source<br />
boundary, assuming worst-case meteorological conditions. There are no statutory criteria for construction<br />
dust, but a maximum hourly TSP concentration of 500 jig/m3 is generally adopted as a guideline for<br />
assessment. The closest SRs are located beyond the Tathong Channel at Siu Sai Wan and Heng Fa Cheun.<br />
Analysis suggests that SRs could be exposed to a dust level of up to 240 /ig/m 3 TSP due to vehicles<br />
operating on unpaved roads and this was identified as being the activity which would generate worst case<br />
conditions. This level is well within the advisory guideline of 500 pg/w for TSP from construction<br />
activity.<br />
Though identified SRs are not directly affected, simple dust mitigation methods can reduce impact further<br />
in the interests of the health and safety of workers on site, efficiency and visual impact. This mitigation<br />
can include imposition of speed limits, covering stockpiles/aggregates, providing water spraying and wheel<br />
washing facilities, and locating dust producing plant as far away from SRs as practicable. All mitigation<br />
measures can be implemented without significant cost implications and would in fact be normal practise<br />
on a well run construction site.<br />
9.4,7 Odour<br />
Potential odour sources may include aliphatic and aromatic hydrocarbons, sulphides and mixed chemical<br />
vapours. Given the distance to SRs odour nuisance is not anticipated to be a problem.<br />
9.4.$ Summary<br />
It is concluded that the air quality in Tseung Kwan 0 New Town will not change significantly due to the<br />
construction and operation of Area 137, and will continue to meet the AQO. However, due to the<br />
confined nature of the airshed individual air quality impact studies are recommended for major industrial<br />
developments when specific details are known. It is considered that any such study should include a<br />
period of background monitoring at or near the development site and not merely rely on the EPD Junk<br />
Bay Air Quality Monitoring Station data.<br />
9.5 iNOISE<br />
9.5.1 Background<br />
The characteristics of the site will be subject to dramatic change as new reclamations are created and<br />
development opportunities offered. This is particularly relevant to the TKODE industrial area immediately<br />
to the north of Area 137. Hie aoise assessment is limited due to the lack of specific details of end users<br />
for area 137. An assessment has therefore been made based on assumptions of probable end uses<br />
identified during discussions with Government and the private sector. In the future it will be necessary<br />
to carry out further assessments to confirm that developments comply with the requirements of HKPSG.<br />
APS Consultants<br />
p ag€
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Noise may impact on sensitive uses within Tseung Kwan O, however, the closest sensitive receivers are<br />
beyond the TKODE and of more immediate concern are the sensitive receivers to the south west of Area<br />
137, across the Tathong Channel, at Chai Wan. In line with the air quality study the assessment has<br />
considered both the construction and operation phases of the project and considered noise from road<br />
traffic, industry and construction as potentially the most significant impact areas.<br />
9*5.2 Road Traffic<br />
Traffic data for the year 2011 has been used in this assessment and is set out in Table 9.3. The high<br />
proportion of heavy vehicles should be noted reflecting the industrial nature of the area.<br />
TABLE 9.3 :<br />
FORECAST PEAK TRAFFIC FLOWS<br />
Options<br />
Good Vehicle<br />
(vch/hr)<br />
Private Vehicle<br />
(veh/hr)<br />
% Heavy Vehicle<br />
AM Peak<br />
1202<br />
303<br />
80<br />
PM Peak<br />
1194<br />
303<br />
SO<br />
Notes:<br />
1 goods vehicle (GV) equals 1.75 passenger car units (PCU)<br />
average speed, 30 kph<br />
normal road surface<br />
4-2.5 dB(A) correction for facade effect<br />
90° angle of view<br />
The SR at Siu Sai Wan is approximately 2 km from the noise source and Hang Fa Chuen is approximately<br />
3 km from the noise source.<br />
The predicted noise levels are between 55 and 57 dB(A). These values are well below the HKPSG of 70<br />
dB(A) at the facade of new dwellings, and 65 dB(A) at the facade of new schools.<br />
9.5.3 Industry<br />
The worst affected SRs are located at Siu Sai Wan, about L5 km away from the boundary of Area 137.<br />
According to HKPSG the day time and night time criteria for operational noise are 60 dB(A) and 50 dB(A)<br />
respectively. To achieve this level at the SRs at Siu Sai Wan the Area 137 boundary sound power levels<br />
for all of the noise sources should not exceed 129 dB(A) (day time) and 119 dB(A) (night time).<br />
Whilst land-uses for Area 137 are still largely undecided and detailed assessments will be required when<br />
developments are confirmed, it is considered that these site boundary sound power levels would not be<br />
exceeded by the operation of the development. Simple measures such as factory and building orientation,<br />
etc should be used to minimise noise levels at the site boundary.<br />
9.5 % 4 Construction<br />
In the Preferred Concept Report construction activities associated with Area 137 reclamation were<br />
identified, The numbers and items of machinery were quantified and the level of noise predicted for<br />
particular construction activities. The sound power levels for Powered Mechanical Equipment (PME)<br />
were derived from the Technical Memorandum (TM2) on Noise from Construction Works other than<br />
Percussive Piling, or from BS5228, Noise Control on Construction and Open sues.<br />
APE Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Noise levels at the representative NSRs for non-piling construction activities comply with the day-time<br />
criteria of 65 dB(A) set in TM2, as shown in Table 9.4. For these same activities during the hours 2300 -<br />
0700 hr, some exceedence of the night-time criteria of 50 dB(A) at the representative SR would occur.<br />
If night time construction work is necessary, suitable mitigation measures will need to be adopted or some<br />
activities restricted. Night work requires that a Construction Noise Permit (CNP) be issued.<br />
TABLE M :<br />
CORRECTED NOISE LEVELS DUE TO NON-PILING CONSTRUCTION<br />
NOISE LEVEL AT SENSITIVE USE<br />
Activity Description SIU SAI WAN HENG FA CHUEN<br />
1. Channel and Trench Dredging<br />
2. Trench Filling<br />
3. Wick Drains- Berth<br />
4. Berth Rock Bunds and Armour<br />
5. Marine Fill Reclamation<br />
6. Construction Waste Reclamation<br />
7. Quay Wall Construction<br />
S. Works Area<br />
9. Road Construction<br />
S. Infra-Structure<br />
44<br />
43<br />
46<br />
45<br />
62#<br />
61#<br />
63#<br />
54#<br />
54#<br />
58#<br />
40<br />
39<br />
42<br />
41<br />
58#<br />
58#<br />
59#<br />
50<br />
5i#<br />
54#<br />
exceeding the criteria of 50 dB(A) for night-time penod (2300-0700 hours)<br />
Based on the worst-affected NSRs at Siu Sai Wan, the recommended maximum sound power levels arising<br />
from the construction activities at the site boundary are:<br />
> all daytime (0700 to 1900 hours) of normal working day, 144 dB(A);<br />
> all days during the evening (1900 to 2300 hours), and general holidays (including Sundays) during<br />
the day time and evening (0700 to 2300 hours), 134 dB(A);<br />
> all days during the night time (2300 to 0700 hours), 119 dB(A).<br />
The above sound power levels should not be exceeded during construction operations and may be used<br />
as a guideline when selecting types and numbers of PME plant during later design stages.<br />
Percussive piling is restricted fay the Noise Control Ordinance and requires issue of a CNP.<br />
percussive piling the results show no exceedence of the noise standard of 85 dB(A) at any NSR.<br />
For<br />
Although there is compliance with HKPSG for daytime activities, to minimise potential for impact and<br />
to reduce night time impact to acceptable levels, the following procedures are proposed:<br />
* the construction programme should be carefully planned to minimise the accumulative noise<br />
impact;<br />
* noisy equipment should be located as far from Siu Sai Wan as possible;<br />
* use should be made of acoustic enclosures, silencers or noise barriers, where appropriate;<br />
> quiet items of equipment should be employed;<br />
APH Consultants<br />
p ag€
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
during the contract tender stage, specific construction method proposals should be made by the<br />
Contractors which will be examined for compliance of noise levels;<br />
a general day time noise limit of 75 dB(A) L^ (30 min) at SRs is recommended.<br />
9.6 WASTE MANAGEMENT<br />
9.6.1 General<br />
The quantities of waste arisings are anticipated to be relatively small (4 tonnes/day or 1,500 tonnes/annum)<br />
and can be disposed of at the existing or committed disposal facilities, i.e. SENT Landfill and the<br />
Chemical Waste Treatment Centre on Tsing Yi. This is in accordance with the Waste Disposal Plan for<br />
Hong Kong (1989). Environmental impacts are not anticipated provided that good operational standards<br />
and legislative requirements are adhered to.<br />
9.6.2 Marpol Wastes<br />
Until such time as the specific industries present their proposals, it is not possible to specify the waste<br />
storage and treatment facilities required. The potential environmental impacts associated with Annex I<br />
(Oily Residues) and Annex II (Noxious Liquids) will relate to:<br />
> spillages;<br />
> inadequate storage;<br />
> treatment processes;<br />
> transportation.<br />
Where possible, storage and treatment facilities should be shared between a number of operators,<br />
particularly for Annex I wastes.<br />
9.7 VISUAL IMPACT AND GLARE NUISANCE<br />
9.7,1 Introduction<br />
Area 137 is located on the south eastern tip of Tseung Kwan 0, on the west side of the Clear Water Bay<br />
peninsula. This is an extremely attractive area of the New Territories which is well used for recreational<br />
pursuits. The rocky coastline and high peaks create a spectacular landscape and overall the area is<br />
generally of a rural nature.<br />
To the north, east and west, the area is surrounded by high steep sided hills, which form an almost<br />
continuous ridgeline providing a dramatic backdrop to the Study Area. The hill sides are well vegetated<br />
with scrub and some localized wooded areas. The land to the east of Area 137 forms part of the<br />
extensively used Clear Water Bay Country Park.<br />
Looking southwards, from Area 137, towards Hong Kong Island, across the Tathong Channel, various<br />
residential developments are visible including the high rise areas of Chai Wan and Hang Fa Cheun and<br />
the low rise developed areas of Cape D* Aguilar.<br />
The proposed development within Area 137 includes a bottling and storage facility for LPG canisters, a<br />
storage area for chemicals, a naphtha plant and a number of godown facilities. Due to the nature of these<br />
facilities it is likely that much of Area 137 will be well lit on a 24 hour a day basis.<br />
APH Consultants<br />
p &g* 9-13
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
The major visual impacts are expected to be nuisance created by the glare of flood lighting and also the<br />
effect of placing an industrial development in what is currently a rural area.<br />
9.7.2 Methodology<br />
This sub-section examines the visual impact of the development of Area 137 on the main visual receivers.<br />
There is no recognised quantitative methodology for assessing visual impacts and, therefore, the<br />
assessment is largely subjective. Area 137 will be visible from a number of different viewpoints, detailed<br />
in the next sub-section. The visual impact from each of the major viewpoints will be assessed and where<br />
practicable appropriate mitigation measures described and proposed.<br />
9.7 J Sensitive Receivers<br />
Areas from which the development at Area 137 would be readily visible have been identified as being the<br />
sensitive receivers (SRs). These SRs can be divided into three main visual categories;<br />
*> Distant/long views; these include views from Cape D'Aguilar and Shek O;<br />
» Approaching views; views from the many passing ships and recreational and pleasure craft; and<br />
» Near views; views from the residential developments of eastern Hong Kong Island and the Clear<br />
Water Bay Country Park.<br />
The locations of the major land based SRs are given in Figure 9.7.<br />
Distant/Long Views<br />
Long views towards the Study Area will be possible from Shek O and Cape D* Aguilar. At present open<br />
seascape and the relatively undeveloped Clear Water Bay peninsula are seen from these viewpoints.<br />
Approaching Views<br />
Area 137 is visible from any vessels -approaching along the Tathong Channel. The current view from<br />
these points is essentially rural in character and the ridge of the Clear Water Bay peninsula slopes down<br />
to the coastline.<br />
Near Views<br />
The major sensitive receivers are on Hong Kong Island and include the Chai Wan and Heng Fa Cheun<br />
residential areas. Approximately 2 to 3 km from the Study Area, these areas will be susceptible to visual<br />
impacts and nuisance from glare.<br />
Views from the Clear Water Bay Country Park, which is extensively used by the general public for<br />
recreational activities such as hill walking, will also be affected by the development of Area 137.<br />
Potential sensitive receivers exist in Tseung Kwan O, these include the Haven of Hope Hospital, Tiu Keng<br />
Leng (Kennies Mill) and the existing and proposed residential developments of Tseung Kwan 0 New<br />
Town.<br />
9.7.4 Visual Impacts<br />
The proposed development within Area 137 is of low to medium rise in nature being generally limited to<br />
a maximum of 30 m in height. It is intended that any requirements to exceed this height will be<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
final Report * Main Report<br />
considered on an individual basis. As such the proposed development should not significantly affect the<br />
overall view towards the Tseung Kwan 0 area which is dominated by steep sided and relatively high hills<br />
which are typically between 80 m and 105 m high.<br />
An impression of the visual effect from a typical sensitive receivers viewpoint is given in Figure 9.8.<br />
This viewpoint is taken to be the 20th floor of a residential block in Chai Wan.<br />
Distant/Long viewpoints<br />
The Study Area is positioned such that there are a limited number of distant/long viewpoints which would<br />
be affected by the development, and the area is often obscured by mist and cloud for much of the year.<br />
However, on clear days it is possible to see that the area is largely undeveloped and distinctly different<br />
from the urban areas of Hong Kong and Kowloon. Long views towards the Study Area will be possible<br />
from Shek 0 and Cape D'Aguilar. The existing view from these areas is of an open seascape and the<br />
relatively undeveloped and scenic Clear Water Bay peninsula. It should be noted that planned<br />
development for Tseung Kwan 0 new town the Tseung Kwan O Industrial Estate and the SENT landfill<br />
will alter the rural nature of the area to urban.<br />
The proposed development at Area 137 is low to medium rise with extensive landscaping intended to<br />
create integration with the existing environment. These characteristics, coupled with the 5.5 to 8 km<br />
distance between these viewers and Area 137, mean impacts to distant/long viewpoints will be minimised.<br />
Approaching Viewpoints<br />
Pleasure craft and ships navigating the Tathong Channel will frequently pass the Study Area and the Area<br />
137 development will have an effect on the view of this section of coastline. Adoption of careful design<br />
in layout, contouring and landscaping will be used to mitigate the visual impact of the development in<br />
order to blend in with the rural background. The rural nature of the area will be altered significantly with<br />
the overall development of Tseung Kwan 0, thus the lower rise, landscaped nature of Area 137 will have<br />
comparably less impact in the future.<br />
Near Viewpoints<br />
A series of local views of the development at Area 137 can be obtained from the residential developments<br />
at Chai Wan and Heng Fa Cheun on Hong Kong Island. Generally the views from these areas are of high<br />
visual quality, mainly comprising of open seascapes and the undeveloped and scenic Clear Water Bay<br />
peninsula- These views and those from viewpoints in Clear Water Bay Country Park will be undesirably<br />
affected by the visual impact of development in Area 137.<br />
These impacts will be mitigated by careful and sympathetic design and landscape design. Use of<br />
contoured landscaping and structure planting using height variation and mounding within the development<br />
will be implemented to create a gradual and integrated transition from the sea to the backdrop of hills.<br />
It is intended that the incorporation of these measures will alleviate visual impact to sensitive receivers<br />
across the bay. Impacts to viewpoints on the Clear Water Bay peninsula will be mitigated by the<br />
incorporation of the integrated design theme. In addition this will include breaking up' within the<br />
development, introducing contoured green areas more in keeping with the surrounding area.<br />
There may be visual impact to potential sensitive receivers in Tseung Kwan O. However the majority of<br />
these are shielded from Area 137 by Fat Tong Chau (Junk Island), which is in direct line of sight, and<br />
any impacts on the developments within this area are not expected to be significant. It is understood that<br />
proposals are being considered for the further removal of Fat Tong Chau as a part of the Territories land<br />
formation activities and careful consideration will need to be given to the extent of removal if the benefits<br />
of this natural screening are not to be lost.<br />
APH Consultants pae 9-15
I—<br />
Figure 9.8<br />
PERSPECTIVE VIEW<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
9.7.5 Glare Impacts<br />
The quantitative assessment of glare from industrial developments is not meaningful at the feasibility and<br />
outline design stage when the required details are not available. The assessment is therefore of a<br />
subjective nature. Previous attempts to semi quantify glare have been made using the British Glare Index<br />
however this is only of use in operational circumstances.<br />
To represent a 'worst* case scenario it has been assumed that Area 137 will be in operation 24 hours a<br />
day and consequently the majority of the area will be flood-lit during the night. Impacts from lighting will<br />
be visible for a much larger area than the visual impacts, this is due to reflection off the sea and "lighting'<br />
of the cloud base.<br />
Impacts on Hong Kong Island<br />
Area 137 is in line of sight from the residential areas of Chai Wan and Heng Fa Cheun. At present the<br />
Study Area has no significant light sources' and consequently the presence of a brightly lit area on the<br />
horizon win significantly alter the night-time views currently enjoyed by these areas. In addition to these<br />
areas, other parts of eastern Hong Kong Island will, on cloudy nights, be affected by the reflected light<br />
from the cloud base.<br />
Impacts on Tseung Kwan O<br />
Although the majority of the existing and proposed developments in Tseung Kwan O are not in direct line<br />
of sight of Area 137, due to Fat Tong Chau blocking the view, the developments will be affected fay the<br />
light reflected down from the cloud base. This will add to the high night sky light levels already produced<br />
by the urban areas of Kowloon and Hong Kong Island and those that will arise from new developments<br />
in the area.<br />
Impacts on other areas<br />
As already stated before there are currently no significant light sources in the vicinity of Area 137, the<br />
presence of a flood-lit area and associated 'cloud lighting* could potentially alter the night time views<br />
currently enjoyed from areas such as Shek O and Lei Yue Mun.<br />
9.7.6 Mitigation of Impacts<br />
Mitigation of Visual Impacts<br />
The existing rural and scenic nature of the Study Area warrants the implementation of measures to mitigate<br />
the visual impact of the proposed development. It would not be practicable to hide the development behind<br />
bunding or screening but the visual severity of the development can be reduced with the incorporation of<br />
trees placed around the edges of the facilities of Area 137.<br />
Height variation, using mounding within the development and intermittent structure planting is proposed<br />
to break up impact of industrial buildings from distant views across the bay. Primary Structure planting<br />
will also reduce visual impacts and is discussed in Section 4.6 landscaping.<br />
New safety measures have introduced a design shape for liquefied petroleum gas which is lower in height<br />
than traditional round pressure vessels. The new horizontal pressure vessels or 'bullets' sit lower into the<br />
landscape which, in conjunction with landscaping features mentioned earlier, will encourage integration<br />
into the existing landscape. Creation of a gradual transition from the sea to the backdrop of hills is<br />
suggested to mitigate the visual impact of the industrial development both from long and short range view<br />
points.<br />
APH Consultants<br />
p age
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Mitigation of Clare Impacts<br />
Although it is difficult to assess the impact of glare from Area 137 the proposals are such that the lighting<br />
would be directly visible from a number of locations on Hong Kong Island and Kowloon and indirectly<br />
visible, through cloud reflection, from Tseung Kwan O and other areas of the Territory.<br />
It is possible to calculate a Glare Rating when the details of lighting requirements are available (these<br />
include type, location and number of light sources, intensities, direction the lights will face etc). However<br />
the best way to minimise (and in some cases eliminate) glare is by careful design of the lighting system<br />
for each site. In this way it is possible to achieve acceptable glare ratings for sensitive receivers located<br />
outside of the site boundaries.<br />
General recommendations for the enforcement of mitigation of glare include:<br />
> the use of low level lighting wherever possible;<br />
» the design and location of lighting should ensure that light is directed only where needed and<br />
generally facing east; and<br />
» the strength of light should be kept to a minimum level, at which the facilities can operate safely.<br />
The proposed intermittent structure planting would, when the trees reach sufficient height and maturity,<br />
help reduce the impact especially from low level sources.<br />
9,7.7 Conclusions<br />
The nature of the Area 137 development contrasts significantly with the surrounding environment. The<br />
development which is essentially industrial in nature is proposed for an area which is at present rural in<br />
nature. Views from areas on Hong Kong island in particular Chai Wan and Hang Fa Cheun, will be<br />
subject to the most significant visual impacts due to the development and potential glare from operational<br />
lighting.<br />
Distant/long views will also be affected but SRs are fewer and at a distance 5 to 8 km away. Views from<br />
vessels navigating the Tathong Channel will also be subject to detrimental visual impact, however, the<br />
exposure of such receivers is transient.<br />
The visual impact of the development can be mitigated by the use of building height restriction, layout<br />
and landscape measures to screen integrate the development.<br />
Careful design of floodlighting to minimise the amount of glare produced should be incorporated and<br />
specified during the detailed design stage. Landscape contouring by mounding and intermittent structure<br />
planting, buffer and screen planting, will promote integration into the existing landscape and alleviate the<br />
visual impact of the industrial development both from long and short range viewpoints, by creating a<br />
gradual transition from the sea to the backdrop of hills. These landscape measures plus careful positioning<br />
and design of lighting can mitigate to some extent the impact from the night lighting.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
9.8 ENVIIIONMENTAL MONITORING AND AUDIT SCHEDULES<br />
9.8.1 Introduction<br />
Environmental monitoring schedules and audit procedures are essential in order to:<br />
> ensure that any environmental impacts resulting from the construction and operation of the Area<br />
137 development are minimised or kept to * acceptable' levels at all times;<br />
+ establish procedures for checking that mitigation measures have been applied and are effective,<br />
and that the appropriate corrective action is undertaken if and when required; and<br />
* provide a means of checking compliance with environmental objectives, recording anomalies and<br />
documenting corrective action.<br />
This sub-section outlines monitoring and audit requirements for the construction and operation of the<br />
development in relation to air quality, noise and water quality, the details of which may be referred to in<br />
the appropriate sub-sections. Monitoring and audit activities for both construction and operation should<br />
be consistent and complimentary.<br />
Monitoring schedules have been provided for the necessary environmental parameters (Table 9.5 to 9.8),<br />
however at this stage it is only possible to provide outline schedules as guidance. Detailed monitoring<br />
schedule and audit requirements should be incorporated into the construction contract(s) and lease<br />
conditions for the Axea 137 development in the form of environmental clauses which should be prepared<br />
at the detailed design stage. These clauses should be agreed in consultation with EPD before being<br />
finalised.<br />
9.8.2 Technical/Personnel Requirements<br />
Responsibilities<br />
Ensuring that the environmental monitoring and audit requirements are met during the construction and<br />
operation of the development is the responsibility of the developer and operator(s) respectively.<br />
As the various facilities will inevitably be operated by a number of organisations, it is suggested that a<br />
body be established to oversee and co-ordinate monitoring and audit requirements and activities. This<br />
would help with consistency, reduce duplication and costs and be more likely to address cumulative<br />
impacts.<br />
Staff Organisation and Structure<br />
The monitoring and audit work should be carried out by suitably qualified and experienced personnel.<br />
This should be contracted to an independent organisation. The personnel would need to include a<br />
supervisor {who reports directly to nominated senior member(s) of the developer/operator's management),<br />
and include sufficient support staff to carry out the tasks. The supervisor will need to liaise with the<br />
resident site engineer (RE) during construction and the general site managers during operation.<br />
While the monitoring and audit personnel will be required to possess appropriate technical knowledge and<br />
training to carry out Hie tasks, they should also have access to a specialist advisor for each main aspect<br />
(Le aoise, air quality, water quality). It would be advisable for details such as qualifications and<br />
experience of these personnel to be sent to EPD for information/comment.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
Equipment<br />
The developer/operator should be responsible for providing appropriate monitoring and sampling<br />
equipment and facilities immediately upon award of the construction contracts to enable the monitoring<br />
to be carried out. The equipment should be approved in advance by EPD.<br />
Monitoring and Audit Manual<br />
The developer/operator should be required to prepare an environmental monitoring and audit (EM & A)<br />
manual, the content of the manual will have to be agreed with EPD prior to the start of the construction<br />
works, but it should include the following:<br />
> the construction programme and the required EM & A programmes to assess the environmental<br />
impacts due to the development with time;<br />
> the location, frequency and type of environmental monitoring and audit requirements to assess the<br />
environmental impacts of the construction:<br />
* the form/content of event/action plans (including any emergency plans) for air, water and noise<br />
impacts;<br />
> review of pollution sources and working practices/procedures required in the event of<br />
environmental pollution levels being exceeded;<br />
* the content/presentation of monitoring data, their audit and the actions taken with respect to noncompliance<br />
with environmental pollution levels;<br />
> appropriate report formats/frequency of submission/special event reports, etc.;<br />
> complaints/consultation procedures ;<br />
* equipment service records and calibration requirements; and<br />
> the locations of sensitive receivers.<br />
EPD also require that the EM & A should also provide for site management, project programme and<br />
environmental protection requirements in contract documents, land lease and engineering conditions.<br />
9.8.3 Reporting<br />
A monthly monitoring and audit report should be prepared by the monitoring and audit personnel within<br />
7 days of the end of each month and commencing 1 month after the commencement of construction.<br />
Copies of the report should be submitted to the senior management representative and simultaneously sent<br />
to EPD.<br />
The report should be a relatively brief and concise account of the environmental monitoring during the<br />
previous month and should include a summary of:<br />
*•<br />
Project Data - A synopsis of the project organisation; project programme; management liaison<br />
structure;<br />
+ Monitoring/Audit Requirements - Summary of monitoring parameters; Trigger/Action/Target<br />
Levels; Action Plans; environmental protection requirements in contract documents; land lease<br />
and engineering conditions;<br />
> Monitoring Methodology - Monitoring equipment used; locations; duration/frequency; standards<br />
to which the methodology refers;<br />
* Monitoring Results - Parameter; date; time; environmental and weather conditions; location;<br />
equipment calibration date; activities being carried out on site; etc.;<br />
APH Consultants fa& 9-19
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
> Audit Results - Review of pollution sources, working procedures in the event of non-compliance<br />
with environmental monitoring levels; action taken in the event of non-compliance; follow-up<br />
procedures related to earlier non-compliance actions;<br />
» Complaints - Liaison and consultation undertaken; subsequent action; database of telephone<br />
/written complaints, location of complaints; action plan and follow-up procedures etc.; and<br />
> Appendices - Appropriate drawings/tables of monitoring locations, sensitive receiver locations,<br />
environmental monitoring and audit requirements etc..<br />
The monthly monitoring and audit reports should be supported by submission of a six monthly and annual<br />
summary.<br />
9.8.4 Environmental Monitoring Schedules<br />
General<br />
Environmental monitoring falls broadly into two categories: firstly baseline monitoring which should be<br />
undertaken to establish or update/confirm the existing conditions in the Study Area (this makes it possible<br />
to set limits for the construction and operational phases); and secondly compliance monitoring, which<br />
should be carried out during both the construction and operational phases of the development to achieve<br />
the following 'general* objectives:<br />
» to assess the performance of construction/operation activities in environmental terms;<br />
> to obtain early warning of potential problem areas, permit timely remedial action and identify any<br />
environmental impacts;<br />
* to comply with appropriate standards and environmental objectives; and<br />
> to provide reassurance to local communities.<br />
As part of the monitoring schedules three levels have been devised to monitor compliance with<br />
environmental objectives and to provide early warning of potential problem areas, thus stimulating the<br />
implementation of mitigation before the regulatory standards are reached. The three levels are described<br />
below:<br />
> the Target Level is the maximum permissible level which will achieve compliance with the<br />
appropriate regulatory standards, and is therefore the upper boundary/limit which is acceptable<br />
in terms of environmental quality. Consequently, achievement of this level is undesirable and may<br />
lead to the cessation of activities. Compliance monitoring schedules are therefore devised such<br />
that remedial action is taken to prevent this level being attained.<br />
+ the Trigger Level is a reference value to be used as an 'early warning 7 of a deterioration in<br />
environmental quality. Achievement of this level may stimulate increasing the frequency of<br />
monitoring and undertaking preliminary investigation (for example to identify any obvious causes)<br />
and possibly remedial action if appropriate; and<br />
> the Action level indicates that deterioration is significant and that urgent corrective action is<br />
required.<br />
Monitoring will be required to measure noise levels, particulate levels (for air quality), total suspended<br />
solids and dissolved oxygen (for water quality). In addition, monitoring will involve checking on general<br />
working practices and compliance with the various control and mitigation measures. Results should be<br />
reported to the developer/operator and EPD, and reviewed on a regular basis.<br />
APH Consultants<br />
p age
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
The requirements for each of the environmental parameters are different, and therefore it is not possible<br />
to propose a single monitoring programme for all aspects. Requirements for individual parameters are<br />
summarized below, and where appropriate outline schedules are presented in Tables 9.5 to 9.8.<br />
Construction<br />
Environmental monitoring during construction will be the responsibility of the developer. For each<br />
construction site a check list should be prepared relating to each of the environmental issues as identified<br />
in the EIA. Together with environmental clauses in the contract documents, this check list will form the<br />
basis of a proforma for the environmental monitoring programme; these are sometimes collectively<br />
referred to as the EM & A.<br />
Air Quality Monitoring<br />
A programme of particulate monitoring should be developed to ensure both the effectiveness of dust<br />
control measures and to highlight any associated deterioration of air quality during the construction phases.<br />
This will necessarily involve simultaneous wind direction and wind speed monitoring. Baseline monitoring<br />
will need to be undertaken at the appropriate SRs prior to commencing construction. Compliance<br />
monitoring will subsequently be undertaken during dust generating construction activities to check that<br />
appropriate air quality standards are maintained.<br />
An outline ak quality monitoring schedule is presented in Table 9.5. The Target Level comprises the<br />
accepted TSP limits for construction sites, of 500ptg/m 3 (1 hr average) and 260/ig/m 3 (24 hr average).<br />
Definitions of Trigger and Action levels are given by the exceedence of the sample in relation to the<br />
baseline for the Study Area plus 30%, thereby allowing for fluctuating ambient levels. The Action Level<br />
is defined by the average of the Trigger and Target values. On breaching any of these warning levels,<br />
action should be taken as described in an outline action plan (Table 9.9).<br />
It is recommended that the baseline should consist of data from 12 months monitoring in the Study Area<br />
prior to commencing construction activities.<br />
Compliance monitoring should be carried out at the construction site boundary, with samplers located<br />
down wind of active working areas. Location of samplers should be remote from influencing factors such<br />
as roads, local obstructions, etc. As a minimum, 24 hr samples should be taken at each monitoring<br />
location once every six days and hourly samples should be taken at least three times every six days. The<br />
frequency and location of monitoring may alter in accordance with local meteorological conditions and<br />
the nature of construction activities.<br />
In addition, it will also be necessary to monitor and check the effectiveness of mitigation measures, this<br />
will involve monitoring the efficiency, maintenance and use of:<br />
> wheel washers;<br />
+ water sprays;<br />
> dust covers;<br />
> plant with filtration equipment; and<br />
* barriers and enclosures.<br />
Regular checks should be made to ensure:<br />
* enforcement of speed limits;<br />
> regular servicing of plant and site vehicles;<br />
+ appropriate construction methods are being utilised and work sites are located away from SRs;<br />
* site cleanliness and the implementation of good site practice.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Noise Monitoring<br />
Noise monitoring will be required to verify compliance with the guidelines for construction noise and with<br />
requirements of any construction noise permits (CNP) and criteria contained in the contract documents.<br />
In the absence of statutory controls relevant to unrestricted day-time hours (0700-2300hrs Monday to<br />
Saturday inclusive), it is generally accepted that a limit of 75 dB(A) 1^(30 min) should be used as a<br />
guideline. Consequently, for daytime noise, the Target, Trigger and Action Levels have been devised<br />
such that the Target is 75 dB(A) 1^(30 min). Trigger and Target Levels should be 65 dB(A) and 70<br />
dB(A) L^(30 min) respectively.<br />
Due to the inevitable and gradual transition of parts of the Study Area from a rural to an urban/industrial<br />
environment, these levels may need to be adjusted in accordance with EPD requirements. In such<br />
circumstances the Trigger and Action levels would be defined according to the occurrence and frequency<br />
of complaints (Table 9.6).<br />
Construction noise during restricted hours i.e. night-time (2300-0700hrs), public holidays and Sundays<br />
will be controlled under the provisions of a CNP. The Target is therefore the relevant ANL in the Noise<br />
Control Ordinance. Where a CNP is in force, monitoring results should be submitted to the developer<br />
and EPD immediately they are available. On breaching the permit, action should be taken as described<br />
in an outline action plan (Table 9.10).<br />
Day-time compliance monitoring should be undertaken, three times per week and involve measurement<br />
of 30 minute time periods during typical activity. Periods of high ambient noise, such as during peak<br />
traffic flows should be avoided. Restricted hour monitoring should be undertaken at least twice during<br />
the restricted hours, (per 24hr period, once in the evening and once in the night-time), for a 5 minute time<br />
period, in accordance with the Technical Memorandum on Noise From Construction Work, Other Than<br />
Percussive Piling. Measurements should be taken (1 m from the external facade) at the worst affected<br />
NSRs.<br />
Regular checks will also be required to establish the implementation and effectiveness of mitigation<br />
measures. This will require checking and monitoring on a regular basis of:<br />
> the use, maintenance and efficiency of silenced construction equipment;<br />
> the appropriate location of noisy plant/equipment;<br />
* the hours of operation;<br />
> the use and effectiveness of noise enclosures and barriers; and<br />
> the implementation of good site practice.<br />
Water Quality Monitoring<br />
The objective of water quality monitoring is to minimise adverse impacts on water quality which may<br />
result from construction activities. Monitoring is required to check the impacts resulting from dredging<br />
and will involve measurement of dissolved oxygen and suspended solids and turbidity.<br />
In addition to EPD's water quality monitoring programme, ambient levels will be determined by baseline<br />
monitoring at two locations close to the areas to be dredged.<br />
Compliance monitoring will be undertaken to establish compliance with the water quality objectives<br />
(WQOs). Target, Trigger and Action Levels have been defined according to the WQOs for Junk Bay and<br />
Eastern Buffer WCZ such that for both parameters (dissolved oxygen and suspended solids) the Target<br />
is the appropriate WQO.<br />
APH Consultants<br />
p ag€
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
In order to account for the significant seasonal variations in water quality, Trigger and Action Levels have<br />
been defined according to background levels as monitored at a number of representative control stations.<br />
The Trigger Level is 20% above the running background for suspended solids and 20% below the running<br />
background for dissolved oxygen. The running background is derived from the mean of monitored data<br />
taken at the control stations. The Action Level is the average of the Trigger and Target values.<br />
As a minimum, 2-3 designated monitoring stations should be established 100 m from the active<br />
dredging/reclamation areas, 1-2 control monitoring stations should be established at appropriate locations<br />
which will not be influenced by the project or any other development activities. Samples should be taken<br />
at both the control and designated monitoring stations at least 3 times per week.<br />
In order to check the effectiveness of mitigation measures it will be necessary to ensure:<br />
* drainage channels, settlement tanks and other construction phase water pollution control measures<br />
are being used and maintained;<br />
* the effectiveness and maintenance of oil/grease interceptors;<br />
» the use of equipment for removing floatabies; and<br />
> the use and adequacy of any waste reception facilities.<br />
Operation<br />
Environmental monitoring during the operation of the Area 137 development is necessary to verify the<br />
findings of the EIA, and is the responsibility of the Operator(s) in accordance with the lease conditions.<br />
An outline monitoring schedule for air, noise and water quality is presented in Table 9.8. In addition to<br />
the operational monitoring requirements presented in this table and described below, it will be necessary<br />
for the port operator to continue monitoring working practices, plant efficiency and site cleanliness, to<br />
ensure that mitigation measures are in place and are effective.<br />
Air Quality Monitoring<br />
In order to assess the long term air quality impacts resulting from the operations, it is necessary to<br />
undertake air quality monitoring during the early years of operation. To effectively monitor these impacts<br />
it is necessary to supplement existing air quality data with additional air quality monitoring (to include<br />
wind speed and direction, NO 2 , SO 2 , TSP and RSP as a minimum).<br />
Noise Monitoring<br />
Operational noise monitoring should be undertaken by the operators to ensure compliance with the relevant<br />
NCO requirements. It is proposed that extensive noise monitoring be carried out during the early years<br />
of operation. Monitoring should also be carried out in response to complaints where appropriate.<br />
Water Quality<br />
It is envisaged that other than EPD's regular monitoring programme, minimal water quality monitoring<br />
will be required during the operation of the development. However, in the event of a major spillage or<br />
pollution incident, it is proposed that a pre-detennined monitoring programme (devised by the operator)<br />
be implemented with the necessary adjustments to suit the requirements of individual cases*<br />
Action Plans<br />
Action Plans should be devised to facilitate the appropriate and immediate response by relevant personnel,<br />
in the event that the Target, Action and Trigger Levels are either attained or exceeded. The appropriate<br />
action is determined by the frequency of exceedence of the compliance monitoring levels.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
The requirement for action plans should be contained in the contract and lease conditions and suitable<br />
plans should subsequently be submitted by the developer/operator to EPD. Examples of appropriate Action<br />
Plans for the development are outlined in Table 9.9 to 9.1 L<br />
9.8.5 Environmental Auditing<br />
General<br />
The purpose of environmental auditing is to review the effectiveness of the overall environmental<br />
protection programme (both construction and operation) in terms of monitoring, mitigation and corrective<br />
action. The audit process should not be divorced from general management activities, and should promote<br />
a pro-active approach to environmental protection.<br />
Construction Phase Auditing<br />
Construction phase auditing should be carried out in conjunction with the construction monitoring<br />
programme.<br />
The audits should be conducted monthly during the development. It is also considered prudent to conduct<br />
some audits to coincide with major construction activities.<br />
Records of environmental monitoring should be maintained by the developer, and the environmental audit<br />
should seek to check:<br />
* records of environmental monitoring procedures;<br />
+ records of environmental monitoring results;<br />
» records of exceedence of any regulatory requirements;<br />
» details of control and mitigation action taken in response to unacceptable environmental impacts;<br />
* records of any complaints from residents/SRs in the Study Area.<br />
Assessment of monitoring records will ensure that any unanticipated impacts are being addressed and that<br />
any improvements required for future monitoring programmes are identified.<br />
A monthly Monitoring and Audit Report should be compiled and submitted to the developer and EPD,<br />
These monthly reports should be supported by six monthly and annual summaries.<br />
Operational/Post-Project Auditing<br />
A post-project audit should be carried out after completion of the development.<br />
The post-project audit should be undertaken after a sufficient time period from the development becoming<br />
operational (e.g. 12 months), such that any findings are representative of the development's activities.<br />
Post project auditing should verify the findings of the EIA and provide a mechanism for:<br />
> reviewing the effectiveness of, and requirement for on-going monitoring programmes;<br />
> reviewing environmental management practices in terms of achieving environmental objectives;<br />
> reviewing the effectiveness of environmental mitigation; and<br />
* recommending improvements in environmental controls and operations in the event that<br />
environmental objectives are not achieved and environmental impacts are unacceptable.<br />
A post- project audit report and executive summary should be submitted to EPD and the operator(s) within<br />
5 weeks of completing the audit.<br />
APR Consultants p age 9-24
TABLE 9.5 I<br />
PARAMETER<br />
Particulutes<br />
AIR QUALITY MONITORING SCHEDULE (CONSTRUCTION)<br />
OBJECTIVE TRIGGER LEVEL ACTION LEVEL<br />
'Baseline N/A N/A<br />
assessment<br />
TARGET LEVEL<br />
N/A<br />
SRs<br />
LOCATION<br />
FREQUENCY/TIMING<br />
One year prior to<br />
commencing construction<br />
activities. **24hr samples<br />
every 6 days.<br />
|l<br />
f I<br />
^ s<br />
"**<br />
t<br />
1*<br />
Partieulates<br />
***Wind speed<br />
Compliance Ihr TSP, 24hr TSP Average of Trigger<br />
monitoring ^ """baseline 4-30% and Target Levels<br />
Assessment N/A N/A<br />
parameter/<br />
compliance<br />
monitoring<br />
SOOjig/m*<br />
Monitoring stations at Site<br />
Ihr average Boundary in line with nearest<br />
260/j g/in* SKb, locations to be reviewed<br />
24hr average monthly to take account of dust<br />
generating activities<br />
N/A<br />
Air Quality Monitoring Station<br />
and where necessary to account<br />
for wind direction with respect<br />
to SRs<br />
One 24hr sample once every<br />
6 days, hourly samples 3<br />
limes every 6 days or more<br />
frequently depending on site<br />
and wind conditions<br />
Continuous<br />
^£3<br />
<<br />
J-<br />
I<br />
g.<br />
^<br />
£*l<br />
1<br />
***Wind direction<br />
Note : *<br />
»+<br />
SRs<br />
N/A<br />
Assessment N/A N/A<br />
parameter/<br />
compliance<br />
monitoring<br />
N/A<br />
Air Quality Monitoring Station<br />
and where necessary to account<br />
for wind dttccUon with respect<br />
to SRs<br />
Continuous<br />
In the event that a permanent monitoring station is established in the Study Area, this will form part of the baseline assessment. As a minimum the baseline should comprise<br />
data taken from 12 months monitoring in the Study Area,<br />
US EPA Ambient Air Quality Surveillance Regulations<br />
No values recommended, potential impacts are dependant on the nature of the construction activity. High wind speeds during dusty activities and/or wind direction towards<br />
an SR should act as u trigger<br />
Sensitive Receivers<br />
Not Applicable<br />
$<br />
g<br />
**<br />
o<br />
1<br />
^»
TABLE 9.6 t<br />
NOISE MONITORING SCHEDULE (CONSTRUCTION)<br />
PARAMETER OBJECTIVE "TRIGGER 'ACTION<br />
LEVEL LEVEL<br />
TARGET<br />
LEVEL<br />
LOCATION<br />
FREQUENCY/TIMING<br />
*f<br />
L l(|l Baseline Assessment N/A<br />
N/A<br />
N/A<br />
NSRs<br />
One 24hr period during a normal working day<br />
LI«» L^j LyQ,<br />
^Ae<br />
Check Baseline<br />
N/A<br />
N/A<br />
N/A<br />
NSRs<br />
Every 3 months or as near as possible. When<br />
construction activities are not taking place<br />
££'<br />
I<br />
Spot Cheek<br />
65dB(A)<br />
70dB(A)<br />
75dB(A)<br />
NSRs<br />
Minimum of once per week for each NSR during<br />
construction activities<br />
tJO naid<br />
Compliance monitoring<br />
(non-restncied daytime<br />
hours)<br />
65dB(A)<br />
70dB(A)<br />
75dB(A)<br />
NSRs<br />
Minimum of 3 times per week between 0700 and<br />
1900hrs during general construction work;<br />
as appropriate during noisy activities<br />
(5 MM*<br />
Compliance monitoring CNP (ANL) CNP (ANL)<br />
(restricted hours)<br />
CNP (ANL)<br />
NSRs<br />
Minimum of twice per 24-hour period (continuous),<br />
(evening and nighUtnie)<br />
Response to complaints 65dB(A) 70dB(A)<br />
(non-restricted daytime<br />
hours)<br />
75dB(A) Complainant As appropriate<br />
o<br />
4s „„„><br />
Response to complaints CNP (ANL) CNP (ANL)<br />
(restricted hours)<br />
CNP (ANL) Complainant As appropriate<br />
^§<br />
Note ; NSRs<br />
N/A<br />
Noise Sensitive Receivers<br />
Not Applicable<br />
In light of creeping ambient levels resulting from the transition of a rural to an urban environment, it may be necessary to introduce Trigger and Action Levels<br />
which are defined according to the frequency of complaints such that the Trigger Level = 1 complaint (either directly to the developer or via EPD), and the<br />
Action Level = 2 independent complaints (either directly to tiie developer or via EPD). An independent complaint is defined such that only one complaint is<br />
allowed trom a single address<br />
Is*
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
Z<br />
O<br />
C<br />
CJ<br />
at<br />
55<br />
1<br />
a^><br />
FVI<br />
Ml<br />
3<br />
C/5<br />
'CUING<br />
Z<br />
55<br />
-><br />
>t<br />
, .1 ••*<br />
«$<br />
o»<br />
* il<br />
i<br />
•*<br />
l><br />
ax<br />
a<br />
*•*<br />
Q<br />
H<br />
i i<br />
1a<br />
1o<br />
M-V<br />
H*4<br />
*" -<br />
U t)<br />
a) VI 2 5<br />
J3 3<br />
o *o "3<br />
2<<br />
'is is<br />
91 « J2 Q O -3 g 0 0 —<br />
- "J3 O U 3 '- O S><br />
.2 .2 -5 3-3 -<br />
S T3 5 T3<br />
|<br />
0 T3 * -J2 -2<br />
l ! J 3 3 ^ ^ 3 g<br />
ja 3 ^ «3 2 -3 «» j» c "3 " «•<br />
OJO ^>— «D afl »-• > ^^ O<br />
*- SP-S*<br />
-g a -5 5<br />
0 ^3 0 T3 QSu^^-g Qau^^l<br />
*c .2 "1 J cn .2 oi s .3 q cn .2 c^4 s 3<br />
o -° o - 0<br />
ff<br />
So s: a<br />
,3.^5- «^.5s^<br />
Ml !*• «*><br />
«4<br />
^1<br />
^a < j<br />
&4 "**<br />
Z<br />
J<br />
U<br />
w<br />
^<br />
z<br />
o<br />
a «*f* **c<br />
1<br />
s<br />
»J<br />
AS<br />
r£<br />
X<br />
X<br />
&a ><br />
j<br />
£2}<br />
MM<br />
5 ««4<br />
/•^<br />
W<br />
2C<br />
ii<br />
d<br />
2 •< i^X<br />
^f2<br />
I«4 M<br />
,2 a<br />
s a<br />
J « -2 -<br />
o o "o "i><br />
S I 2 |<br />
s8.<br />
gȤ.<br />
ts > ^ > •a J -a 3<br />
C ^ C TC<br />
g M 3 3D 1 i 1 If<br />
ao .2 ao -S<br />
.s § .s g<br />
o S ^ S<br />
C '3 C »«3<br />
5 X li X<br />
e 2 s s<br />
53 C. P d,<br />
Q 3» «*> Q «t »»<br />
§ | § |<br />
o * o *•<br />
A tJ *% "9<br />
2 o 3 o<br />
u *C u 'u<br />
I 8 --! 8 0U as CU ca-<br />
1 §<br />
01 OS<br />
O O<br />
< ^S<br />
*<br />
Z<br />
i s<br />
z z<br />
< <<br />
z z<br />
c c<br />
g s H S<br />
13 35 •"» 33<br />
i> U 2<br />
«" ^ « ^<br />
^-H .2 >».«<br />
S-3 § 13 g<br />
P cn S<br />
Q cn S<br />
^<br />
C r<br />
^> •"•<br />
"C "C<br />
•3 1 1 2 § •§ 1 1 s s<br />
Cl »a — ' * i i \ Ol aS — » i i i<br />
g<br />
§ gO'<br />
* £<br />
u. u<br />
•U y*<br />
ad — 2<br />
3 ^<br />
*J !rt<br />
-a J3<br />
S S s w r i s3<br />
i<br />
•y»<br />
3<br />
S— .<br />
^<br />
> s "i<br />
S | i<br />
w» X 2<br />
w<br />
OS X<br />
CA X<br />
:l 1 If<br />
> o -r g<br />
•*3 3 .is<br />
|l *!<br />
1 8 -si<br />
11 *<br />
•si 1 £<br />
2 ^ Z *<br />
0 00 0 30<br />
§ * s *»<br />
.2 cx<br />
* £<br />
U V*<br />
O M<br />
an —<br />
*-> -J*<br />
5ii ^2<br />
.3 § . g<br />
'""• S *-* o<br />
H j H j<br />
'*- _•<br />
f ~* «j<br />
O 'J<br />
O U<br />
a 2 * £<br />
£ S2<br />
u, c* u r*<br />
5J 3<br />
< 5<br />
2 < 3<br />
aO 54}<br />
^ wi C yj<br />
s "o<br />
'S U<br />
S > G ><br />
2 -H S 3<br />
i 3 * 3<br />
li ii<br />
•^ afl * 50<br />
g "y ^ IS<br />
O =J O sa<br />
<br />
•S S<br />
-II<br />
o — | H "<br />
£ §* sa I S* «<br />
•" O «<br />
•** 3 M<br />
§ ° "a § ' J "g<br />
a "3 i 0-33<br />
— 2 'S ^ .2 's<br />
«** '—• »«J<br />
3 5 2<br />
•" *W ~\<br />
o *j 2<br />
^^ <br />
"£s<br />
J<br />
*2<br />
0<br />
1<br />
§2<br />
"f<br />
"•3<br />
37S<br />
•<br />
.•i<br />
•3 g J<br />
« ^ ^><br />
"^3 3 S<br />
-8 ^ 7 .2 ~ .—<br />
i. 8 s<br />
3 § §<br />
aj •"• J3<br />
.2 -H<br />
| 1 1<br />
J<br />
'***'<br />
"ah ^<br />
>M g<br />
"ajj Tf CM<br />
C u u<br />
> 01 va<br />
X<br />
•Sail<br />
-> 3 J J<br />
O ^ 75 Tt<br />
s -3 i i<br />
'•3 ^ ^3 S<br />
,, !! § a, H o H<br />
o<br />
u - « r5<br />
-3 S . -<br />
^ •— Q O<br />
a ° aa<br />
a > ><br />
•^ 3 > ><br />
tS "^ > *<br />
^ 2 J-2<br />
S 5 -3 j<br />
S3 «• ^^<br />
x g .22 .2<br />
^ lo o<br />
^ 1 Q a<br />
G ""* T3 "3<br />
i*l|<br />
o o i 2<br />
^ cn so ^0<br />
«i "«^ «i 2 ^<br />
-O _4 -s —<br />
Q — . — M<br />
^ x§ 1 I<br />
1 '1 '•§ 5 5<br />
-H 3 S<br />
•^ 0» *<br />
— 1 1 S^f<br />
II<br />
ilieS<br />
^ o<br />
< a><br />
z> *<br />
APS Consultants Page 9-27<br />
**<br />
3i<br />
Z<br />
^
TABLE 9.8 i<br />
ENVIRONMENTAL MONITORING SCHEDULE (OPERATION)<br />
PARAMETER OBJECTIVE STANDARD LOCATION<br />
* AIR QUALITY<br />
NO 2 Establish baseline data and trends AQOs Near to Site<br />
SO 2<br />
ISP<br />
RSP<br />
FREQUENCY/TIMING<br />
Continuously for gaseous Every 6 days<br />
for particulates<br />
Requirement for on going monitoring to be<br />
assessed in the audit procc;ss<br />
-<br />
NOISE<br />
WATER QUALITY<br />
Compliance with NCO Appropriate AN Li Worst NSRi **Over a 24hr period approximately every<br />
month Requirement for on going<br />
monitoring to be assessed in the audit<br />
process<br />
1<br />
dn»:»olvcd oxygen<br />
Monitor the eHeUb of maintenance<br />
dredging, compliance with WQOb<br />
WQOs<br />
Designated monitoring stations<br />
near to the area to be dredged<br />
Duiing maintenance dredging<br />
Note : * NO 2 » SO 2 , TSP and RSP should represent the minimum parameters to be sampled<br />
frequency of momlormg should d^erease it NCO standards are consistently niu, or increasing in frequency if the NCO maxima is exceeded<br />
N/A Not appropriate<br />
I he water quality monitoring requirements during maintenance dredging will be similar to those m Table 9 7<br />
f<br />
o
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
1<br />
.s%i<br />
i<br />
i<br />
J<br />
*<br />
5. .1<br />
1<br />
3<br />
1<br />
3<br />
«<br />
o<br />
•>. O '£*<br />
1 C ^<br />
lg S .1<br />
8 1 '= 1<br />
1 ^ § ^<br />
* Q- a o<br />
H ! 1<br />
Jo 0 a<br />
.H^ 5 H<br />
» -a 1 3<br />
afi 3 c3 5<br />
<br />
" S<br />
*<br />
s.<br />
"13!, M •€ S "3<br />
••a 3 i •« 3 s-ll^i<br />
M-- 11 ^ M 1<br />
ill II- fri i= 1<br />
S.isll 'JgrSll<br />
- o<br />
2 g 1<br />
1 - ^ 1 1<br />
1 12 1 1<br />
> 3 CL O<br />
S a f 1 3* a.<br />
^1 5 j] 1 i,<br />
-— y •— • Q > 3<br />
5<br />
2,<br />
1<br />
1 2<br />
i .;<br />
d O s<br />
« i<br />
r<br />
«<br />
* jo<br />
n<br />
i<br />
-;<br />
53 § § S^ ^<br />
5 S 3 2^ S<br />
a I - - * - i-<br />
5 S | " -2 § a«<br />
a. i- .- ao * 2 aa<br />
y s ^ £ 2" s^<br />
^ 3 - 3 « C .S * -s a<br />
5 = * " i § 5 2 2 £<br />
•* -i 1 § *5 « § r=<br />
i S ! 1 1 11 ,<br />
1 1 ! I S! !! !<br />
at<br />
JU<br />
s s<br />
«\ *J><br />
-= = ><br />
f<br />
J i<br />
S<br />
I<br />
•a<br />
S<br />
2 3<br />
II<br />
O\<br />
3d<br />
5<br />
^<br />
fi«<br />
M>*H<br />
S<br />
^<br />
g<br />
15<br />
11<br />
« ><br />
1<br />
**M<br />
O<br />
1 i £. »<br />
ca ^<br />
APff Consultants Page 9-29<br />
1<br />
£ o<br />
f*<br />
n<br />
O3 .T<br />
i*4 «
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
2<br />
S<br />
5<br />
z<br />
0 "**•<br />
33<br />
^^ •2<br />
2<br />
2<br />
SN<br />
55<br />
jpjcr<br />
ACTION<br />
s*<br />
i<br />
£3<br />
1.<br />
1 t<br />
Monitor big Pen&ntwl<br />
HSmSite Open<br />
cu<br />
a<br />
'j0,<br />
"a<br />
'j<br />
3<br />
O<br />
«££<br />
1<br />
G jt *\<br />
f J<br />
= f -<br />
III<br />
a -3:-<br />
us eiO<br />
1<br />
i •§<br />
| S<br />
*i s<br />
"3 J<br />
a £<br />
1 "8<br />
*n o<br />
r 4 P*<br />
1 &<br />
33<br />
1 | | s<br />
»H<br />
o<br />
1 o<br />
o 2<br />
33 U<br />
CM O V*<br />
i |i<br />
•1 o 1<br />
1 2^<br />
Check working<br />
identify causes,<br />
remedial action<br />
I<br />
S S<br />
«3 <br />
§ J<br />
o .<br />
2 «2<br />
c£ o<br />
CO -«=<br />
* 1<br />
1 §<br />
ll<br />
g ||<br />
.333<br />
ill<br />
ill<br />
.2^<br />
J <<br />
"•5 — s<br />
> 3<br />
55 o<br />
3fi JS<br />
ll n<br />
1 «<br />
21 o 4 S ^<br />
|3M a i -9 ><br />
s<br />
M<br />
cS<br />
"3<br />
1<br />
u<br />
O<br />
1<br />
S<br />
ts<br />
||<br />
"Submit report to EPD within two weeks of receipt of<br />
complaint should the measured noise level exceed the Ta<br />
proposals to reduce noise should be recommended in the<br />
_<br />
J2<br />
!<br />
g<br />
VI<br />
T3 1<br />
si<br />
a 2<br />
fl<br />
"3* QA<br />
"T3<br />
j» *<br />
if<br />
a §.<br />
> 3<br />
S 1<br />
aa<br />
1<br />
><br />
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
!X<br />
«<br />
"c —<br />
| .2<br />
1 «<br />
Sf «l .3 **<br />
3" a<br />
1 1 =<br />
§ 3 2<br />
2 li<br />
t> 2 —<br />
05 0, £<br />
inform developer RSE, EPD<br />
U9<br />
^ 2<br />
C 3<br />
3 3 -1 H §<br />
!i«s s = B<br />
f .S x.S 2f» §<br />
M S "7 J2 .5 -Si<br />
Confirm monitoring result and<br />
measurement for a further 15 i<br />
min) and 30 minutes respectivt<br />
exceedeiice of Target level wit<br />
outside restricted hours follow!<br />
implementation of noise reduct<br />
"3 i><br />
.H<br />
*u*<br />
1 u*<br />
f 3<br />
i §<br />
ll<br />
i-<br />
c; H 2<br />
^ ^3<br />
_ O i«<br />
1 il<br />
u -u -5<br />
a -31<br />
^<br />
s<br />
Increase frequency of monitori<br />
&o<br />
•g 2<br />
4> *3<br />
.2 a<br />
11 i<br />
il <<br />
S 8L 3<br />
H 1<br />
11 1<br />
tl §<br />
'i-l s<br />
5 1 S .5<br />
u 2 I 5<br />
.1 | 50<br />
1.1 •§<br />
- •= 2.<br />
S =<br />
g'5<br />
§ 1 1 i<br />
a t 8 .S<br />
It<br />
11 §.!<br />
*y >«<br />
|<br />
2 x<br />
«<br />
75<br />
1<br />
ca r:<br />
1 |<br />
u,<br />
3 .2 « o «<br />
Vj CU «. > v»<br />
§ S .2 " 5 on<br />
u<br />
s*<br />
**"' t: .2 c<br />
il 1 Jit<br />
i 2<br />
Q*<br />
J2 S<br />
Ji ! Ill<br />
Ji<br />
s<br />
"J3<br />
OI<br />
i<br />
II<br />
o<br />
.2 "o<<br />
"S,<br />
s<br />
il<br />
3 o<br />
0 J»<br />
1 §<br />
3 |<br />
*ua u<br />
|1<br />
51<br />
*-l<br />
II S *<br />
1 I<br />
APH Consultants Page 9-31<br />
tM ^<br />
*<br />
* *<br />
JJ<br />
^
TABLE 9. Hi<br />
WATEU QUALITY ACTION FLAN - SUSPENDED SOLIDS AND DISSOLVED OXYGEN<br />
EVENT<br />
Bieach of Trigger<br />
Value<br />
FREQUENCY<br />
One sample<br />
MonUoilng<br />
inform developer £. RSE<br />
fano/i/wl<br />
ACTION<br />
kSK/SUe Operator<br />
Developer<br />
ffs * §•<br />
Two consecutive<br />
samples<br />
Inform EPD, developer and RSE; resample to<br />
confirm result<br />
Check working methods/practices to identify any<br />
immediate causes, take apptopriate remedial action if<br />
necessary<br />
Bieach of Action<br />
level<br />
Due sample<br />
samples<br />
Inform EPD, developer and RSE; tesample to<br />
confum result<br />
Inform EPD, developer and RSE; resample to<br />
confirm rebutt<br />
Increase frequency of monitoring<br />
Check working methods/practices to identify any<br />
immediate causes; take appiopriate remedial action if<br />
necessary<br />
Undertake detailed check of working methods and<br />
practices<br />
Review plant, equipment<br />
and working piocedures<br />
I<br />
Biea Ji of Target Level One sample<br />
Propose remedial action<br />
Continue monitoring after completion of<br />
remedial auion to contain action is effective<br />
Record event in monitoring report for<br />
submission to developer and I<br />
Inform EPD, developer and RSE;<br />
Confirm result £ increase monitoring frequency<br />
Propose remedial action<br />
Undertake monitoring at nearest water quality<br />
SR<br />
Continue monitoring after completion of<br />
remedial action to contain action is ettecttve<br />
Carry out appropriate remedial action as<br />
recommended by environmental monitoring team<br />
Ensuie coneuive action has been undertaken and is<br />
eifective<br />
Amend method statement, if appropriate<br />
Under take immediate check of activities and employ<br />
any appropriate mitigation.<br />
In extteme casea cease activities<br />
Ensure corrective action has been undertaken as<br />
proposed by (monitoring team) and is effective<br />
Amend method statement, it appropriate<br />
Ensure implementation of remedial<br />
action<br />
Inform EPD of remedial action<br />
Review plant, equipment and working<br />
procedures<br />
Ensure immediate implementation of<br />
remedial action<br />
inform EPD of remedial action<br />
§<br />
o<br />
Complete Monitoring Report and submit to<br />
developer and EPD
Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
SECTION 10<br />
IMPLEMENTATION<br />
10.1 INTRODUCTION<br />
This Section discusses the implementation of the development covering the activities from the completion<br />
of this Report to the point at which the various areas are released to operators for the further development<br />
of their sites. As such, it addresses the following topics:<br />
> preliminaries which have to be allowed for in order to carry the findings of this Report through<br />
planning and design to construction;<br />
» a review of the likely arrangements required for implementation;<br />
> implementation scheduling including the key demand horizons, constraints upon the development<br />
and phasing potential;<br />
> capital expenditure and revenue streams for the development.<br />
10.2 PRELIMINARIES<br />
Scheduling for the implementation of the works must allow for Government approval and sanctioning<br />
procedures. The steps that the these procedures entail will vary as a function of the way in which the<br />
various developments will be realised, thus, for example, whether the works are actually executed under<br />
direct Government control or entrusted to a private sector developer.<br />
The preliminaries under Government funding cover the following activities:<br />
+ DPC, PPC and LDPC endorsement;<br />
> Public Works Sub-Committee and Finance Committee sanctions for the undertaking of the detailed<br />
design and construction;<br />
> consultant selection;<br />
» detailed planning and final design;<br />
and under private sector funding:<br />
* DPC, PPC and LDPC endorsement;<br />
> Public works Sub-Committee and Finance Committee sanctions for undertaking technical<br />
assessments;<br />
+ consultant selection;<br />
* technical assessments;<br />
»• preparation of lease conditions;<br />
+ ExCO endorsement of privatisation proposals;<br />
* processing and award of development rights and land sales.<br />
Gazetting under the various Ordinances will be required for the development. In addition, the<br />
development involves the adjustment of the existing traffic separation scheme within the Tathong Channel<br />
and early application to the IMO for the proposed amendment will be required.<br />
Consultants<br />
Fa S e 10 ' 1
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
These procedures, apart from the time needed to undertake the detailed design and site investigations, can<br />
be protracted and a high degree of priority will be required to achieve a start to construction in accordance<br />
with the requirements discussed in the following sections.<br />
10.3 IMPLEMENTATION SCHEDULE<br />
10.3.1 Facility Requirements<br />
The discussion of the identified demand for facilities in Section 3 has indicated that there is considerable<br />
pressure for the provision of a site to accommodate PHI activities. These include naphtha import and gas<br />
production, LPG import and bottling and a bulk chemical storage facility. Associated with the latter<br />
facility in particular, is a requirement to provide PHI related facilities. The demand for DWI has been<br />
shown to be less forthcoming.<br />
The three main PHI sites have therefore been adopted as the core demand requiring early provision with<br />
the remaining facilities being made available on a rolling programme basis.<br />
In view of the PHI nature of the core demand it has been located in the south of Area 137 to maximise<br />
the separation distance from the TKOIE and SENT Landfill sites. As such the early provision of these<br />
sites will require the creation of land access via a coastal causeway. In addition, and irrespective of this<br />
approach, the proposed marine access to the SENT Landfill site would be affected by the commencement<br />
of the development and reprovisioning of these facilities would be required.<br />
The Master Layout Plan for the proposed development is presented in Figure 10.1.<br />
10.3.2 Implementation Constraints<br />
The main implementation constraints are the need for the reprovisioning of the SENT Landfill marine<br />
access and those associated with the provision of the main land access along Road D6.<br />
The reprovisioning of the marine access represents a significant financial burden for the early stages of<br />
development. Alternative means by which marine access can be maintained until a later stage have been<br />
discussed with the appropriate Government Departments, including the provision of a temporary road<br />
access to Area 137 through the SENT Landfill site and initial construction of the marine access outside<br />
the development area. It was concluded that a separate study should be undertaken to examine alternative<br />
sites for the location or reprovisioning of the marine access to the SENT Landfill site, taking into account<br />
transportation and development cost as well as the environmental implications. However, for the purposes<br />
of this Study it is assumed that the marine access will be retained at its proposed location and that<br />
reprovisioning will be within Area 137.<br />
The current programme for the provision of road D6 involves the following steps:<br />
» reclamation of the road reserve by SENT Landfill contractor from mid 1995;<br />
> one year notice to SENT Landfill contractor for release of the road reserve;<br />
> release of the reserve to TDD by mid 1996 for the construction of the road.<br />
The above sequence of events has the potential to impose a constraint upon the early development of the<br />
main core sites.<br />
APH Consultants p age 10-2
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
10,3.3 Phasing Potential<br />
The implementation of the development is characterised by the need for the early provision for the core<br />
demand followed by a slower release of land to meet the remaining PHI and DWI requirements. It is<br />
considered that this need lends itself to the adoption of appropriate construction techniques rather than the<br />
definition of discrete phases.<br />
For planning purposes the initial construction element, or development, is assumed to relate to the<br />
provision of land for the identified core demand at the earliest opportunity. As such the Initial<br />
Development provides for:<br />
> Site 1, Naphtha import and gas production;<br />
> Site 2, LPG import and bottling facilities;<br />
> Site 3, Bulk Chemical Storage Facility;<br />
* Sites 5 and 6, PHI related activities.<br />
Access to the site would be obtained through the reclamation of a coastal margin to provide a platform<br />
for a single lane road and services corridor. The reclamation of the site has been based upon the use of<br />
dredged marine sand in order to achieve the earliest possible hand over of the plots.<br />
Through the adoption of an effectively continuous development programme, it is considered that no<br />
provision needs to be made for armouring the temporary face of the reclamation following the completion<br />
of the initial reclamation works, although a return to the seawall revetment will be required in the north<br />
to limit local scour.<br />
The Initial Development, as outlined, will provide a total site operating area of some 36 ha with a further<br />
4.3 ha associated with the provision of access as shown on Figure 10.2.<br />
It is proposed that the creation of the remaining land area would be centred around the use of public<br />
dumping or overburden material from the Anderson Road quarry. The timing of the commencement of<br />
the dumping is variable, with an early start as soon as the initial filling is completed in any particular area.<br />
It is, however, recommended that the start should not be delayed beyond the completion of the Initial<br />
Development. This would ensure that the existence of an embayment in the north of the site is limited<br />
to that of a construction sequence within an overall implementation programme rather than a permanent<br />
or semi-permanent feature.<br />
All seabed and preparatory works would be completed prior to the commencement of the dumping<br />
operations. A barge dumping operation would be required to raise the level of the seabed in a uniform<br />
manner which would be followed by end tipping as a shore based operation. It is proposed that the<br />
sequence of plot creation would work progressively northwards.<br />
Temporary provision will be required for the extension of the proposed SENT Landfill drainage during<br />
the dumping operations. It is considered that this can best be achieved by permitting open ditch flow as<br />
the filling progresses with the permanent works constructed upon completion of the filling. Similarly, the<br />
provision of roads and services would commence upon the completion of filling or sequentially if the<br />
demand dictates.<br />
APR Cowutomte<br />
p age
Figure 10.2<br />
TKOIE<br />
39 , V'5^r^" ltltt N<br />
1<br />
27 M 18 v 12 \|<br />
tl 14 i - p " * 9 "<br />
^, •r^-""i\ 8 " I<br />
CUURWA7ER 3AY<br />
COUNTRY PARK<br />
TATHONG CHANNEL<br />
V<br />
£><br />
TA1 MUI WAN<br />
KEY:<br />
Extent of Initial Development<br />
AREA 137 INITIAL DEVELOPMENT<br />
APH CONSULTANTS
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
10.3.4 Implementation Arrangements<br />
Government has not generally shown favour towards private land reclamations as, theoretically, this would<br />
give the developer control over the land he has created. This would be contrary to the historic practice<br />
in Hong Kong where land, inclusive of reclaimed land, is vested under the authority of the Crown.<br />
In some instances, it can be suggested that a developer could form land as entrusted works for subsequent<br />
handover to Government. However, the core PHI demand amounts to some 30 ha with each individual<br />
facility allocated approximately 10 ha, being some 10% of the total site area. As such it is questionable<br />
as to whether one of the interested operators would take on the role of developer involving entrustment<br />
of their non-allocated areas unless there is a substantial increase in the land requirement for a single<br />
operator. It is possible that, subject to review, one of the identified operators may well indeed amend<br />
their indicated land requirements and this could alter the perception of the viability of operator<br />
development involving entrustment.<br />
It is considered that time frame and practicability effectively rules out the formation of an equivalent to<br />
the Hong Kong Industrial Estates Corporation or the amalgamation of a number of operators to take on<br />
the role of developer.<br />
Reclamation by Government would appear to be the most attractive and least complicated way forward.<br />
Land disposal is conventionally the responsibility of Buildings and Lands Department (BLD). BLD would<br />
determine the level of premium appropriate to individual lots and would be responsible for the preparation<br />
of lease conditions restricting land use and operation. BLD also have the option of disposing of land by<br />
competitive tender or auction.<br />
Notwithstanding, it is recommended that Government invite expressions of interest to be registered for<br />
the whole or partial development of the site. It is further recommended that this call for interest should<br />
be run in parallel with the progression of the development on a Government funded basis.<br />
10.3.5 Implementation Programme<br />
The proposed implementation programme is shown on Figure 10.3 and is generated around the release<br />
of road D6 reserve to TDD by mid 1996 requiring notice to be issued to the SENT Landfill contractor<br />
immediately after receipt of the reserve from TKOIE and allows the release of the main core PHI sites<br />
by mid 1997.<br />
The key elements this programme are:<br />
Preliminaries<br />
Appointment of Consultants is required in third quarter of 1993 to enable the<br />
detailed design to commence upon approval of design/investigation expenditure.<br />
Within the design/investigations, initial priority will have to be given to<br />
reprovisioning of the SENT Landfill marine access.<br />
SENT Marine Access<br />
The key target within this element of the programme is the completion of the<br />
reprovisioning prior to the release of road D6 reserve under the Initial<br />
Development programme when marine access to the proposed facilities would be<br />
lost. A float of three months has been built into the programme for the<br />
completion of the SENT Landfill marine access reprovisioning prior to the<br />
commencement of the site roads and paving under the Initial Development<br />
programme.<br />
APH Consultants p ag€ 10-4
Figure 10.3<br />
ii<br />
'.ii<br />
i<br />
II<br />
! Ill<br />
S5li<br />
ii! hi<br />
I | i<br />
'II<br />
II<br />
IMPLEMENTATION PROGRAMME<br />
333 APH CONSULTANTS
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Initial Development<br />
Site Completion<br />
Tender Documents would be issued early 1995 with an award of Contract some<br />
4 months later. Release of the main core sites to operators is programmed for<br />
early to mid 1997.<br />
The award of the Site Completion works is programmed to coincide with the end<br />
of the Initial Development. As discussed above, the commencement of the<br />
associated public dumping could commence earlier, if disposal or site demand<br />
justified. The programme has been developed for an assumed rate of supply of<br />
public dumping material at 1 MmVyr. Clearly, works could be completed,<br />
either earlier or later, depending upon the actual rate of supply achieved.<br />
10*3.6 Employment Build Up<br />
No specific consolidation period has been indicated within this phase of work due<br />
to the slower rate of filling as well as the fact that this site is centred on the old<br />
dump ground and the preliminary boreholes have indicated that partial<br />
consolidation has already occurred.<br />
The risk assessment for the site has recommended the adoption of a worker density within the development<br />
of 20 per ha and 30 per ha for PHI and DWI facilities respectively. These densities have been used to<br />
generate the maximum theoretical employment levels. The employment build up, assuming that the labour<br />
force is brought onto the sites 2 years after site formation, is detailed in Table 10.1.<br />
TABLE 10.1 :<br />
EMPLOYMENT BUILD UP<br />
Year<br />
Employment<br />
1988<br />
1999 773<br />
2000<br />
2001 247<br />
2002 334<br />
2003 334<br />
TOTAL 1688<br />
10.4 CAPITAL EXPENDITURE AND REVENUE STREAMS<br />
10.4.1 Capital Expenditure<br />
Cost estimates have been prepared for the various work packages covering the main construction elements.<br />
These include engineering, investigations, preliminaries, dredging, site formation, revetted seawalls,<br />
common user berth facilities, roads, services, drainage, GIC facilities and contingencies. The costs of the<br />
specific user berthing facilities have been excluded on the basis that they are user defined and would be<br />
undertaken by the operators as part of the development of the sites. The cost estimates have been<br />
prepared at March 1992 prices and are summarised*in Table 10.2,<br />
APH Consultants p age 20-5
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
TABLE 10.2 :<br />
SUMMARY OF CAPITAL COSTS<br />
(March 1992 prices, HK$ millions)<br />
Item<br />
SENT Landfill<br />
Access<br />
Initial Development<br />
Site Completion<br />
Investigatiort/Prelims/Contingencies<br />
Dredging<br />
Filling and Associated Works for<br />
Reclamation<br />
40<br />
.<br />
48<br />
263<br />
-<br />
4SS<br />
175<br />
12<br />
93<br />
Revetted Edge Structures<br />
-<br />
132<br />
33<br />
Quaywalls<br />
42<br />
-<br />
206<br />
Roads, Services, Drainage<br />
Landscaping<br />
30<br />
.<br />
132<br />
-<br />
120<br />
36<br />
TOTAL<br />
160<br />
1015<br />
675<br />
These costs have been converted into capital expenditure streams for the proposed implementation<br />
programme as shown in Table 10.3.<br />
TABLE 10.3 :<br />
CAPITAL EXPENDITURE STREAMS (HKS millions)<br />
YEAR<br />
1993<br />
1994<br />
1995<br />
1996<br />
1997<br />
1998<br />
1999<br />
2000<br />
TOTAL<br />
INITIAL DEVELOPMENT *<br />
30<br />
72<br />
385<br />
500<br />
188<br />
1173<br />
SITE COMPLETION<br />
103<br />
202<br />
202<br />
168<br />
675<br />
* Includes reprovisioning of SENT Landfill Marine Access<br />
The Present Day Value of the expenditure has been discounted at 4.0% to give PD values of HKS 1,493M<br />
with an annual allowance for maintenance expenditure of HKS 2M between completion and 2011.<br />
10.4.2 Revenues<br />
The Government would expect to receive revenues or premiums from the sale of land or grants of<br />
development rights associated with the development. In addition, the development will give rise to a<br />
marginal increase in the number of vessels visiting the Port of Hong Kong from which Government will<br />
receive Port Facility and Light dues.<br />
The levels of premium that Government may expect to receive could be assessed on the basis of operator<br />
profitability or current market levels. The diversity and undefined scale of the proposed operations,<br />
AfH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
however, effectively rules out the operator profitability approach. As a result a review has been made<br />
of the current premiums for serviced land with appropriate allowance for plot ratio and nature of use.<br />
The premiums are based on March 1992 values and are presented purely for illustrative purposes:<br />
For serviced land<br />
» PHI sites HK$ 30M per ha<br />
> PHI related sites HK$ 50M per ha<br />
> DWI sites HK$ 50M per ha<br />
The results of applying the premiums to the proposed implementation programme with the assumption that<br />
the premium is received within 1 year of the creation of serviced land for PHI's and 1 to 2 years for the<br />
main DWI sites, is given in Table 10.4.<br />
TABLE 10,4 :<br />
REVENUE STREAMS (HKS millions)<br />
Year<br />
Revenue<br />
1996<br />
1997<br />
1998 1134<br />
1999<br />
2000 415<br />
2001 557<br />
2002 557<br />
The equivalent Present Day Value (at a discount rate of 4.0 %) of the revenues is HKS 1,929M.<br />
10.4,3 Viability<br />
On the basis of the estimated serviced land premiums it is evident that the proposed development has a<br />
good rate of return with an IRR of 13.4% or 17.8% excluding the reprovisioning of the SENT Landfill<br />
marine access. The project could withstand further delayed premium payments or a reduction in premium<br />
levels of some 22% and show a positive net present value at a discount rate of 4%. However, this relates<br />
to the full development of the site and it is considered more appropriate to examine the viability of the<br />
Initial Development and also the minimum level of interest required to establish viability.<br />
Any initial development would involve the construction of a coastal road to the site and the reprovisioning<br />
of the SENT Landfill as currently envisaged. The results of this evaluation, assuming no net cost to<br />
Government (discount rate 4%) are as follows:<br />
> an 11 ha operational site would require a premium of HKS 65M per ha.<br />
> a 21 ha operational site would require a premium of HKS 43M per ha.<br />
> the Initial Development as outlined in Section 10.3.3 involving 31 ha of PHI and 5 ha of PHI<br />
related operational area would require an area averaged premium of HKS 36M per ha.<br />
The above premium values could be reduced to HKS 49M, HKS 35M and HKS 31M per ha, if the<br />
provisioning of the SENT Landfill marine access could be avoided through its relocation to a nonconstraining<br />
site.<br />
APH Consultants p ae 1Q-7
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Find Report - Main Report<br />
From the above analysis and assumed premium levels, it would appear that the minimum initial<br />
development would need to be of the order of the proposed 36 ha, if it is to be realised at no net cost to<br />
Government.<br />
10.5 STUDY IMPLICATIONS<br />
The previous Sections of this Report contain a number of related recommendations and action<br />
requirements which should be recognised in the further implementation of the development. These are<br />
listed below, by Section, for ease of reference:<br />
> Implementation of the recommended layout for Area 131 would require the realignment of Road<br />
D9 at its junction with Road P2; modification of the ODP would be required.<br />
Within Area 137 it would be prudent to limit worker densities to 20 per ha and 30 per ha for PHI<br />
and DWI sites respectively and marine operations should be suspended for the day of the festival<br />
at Tai Miu Wan. The development of a particular PHI should be subject to the results of a<br />
farther and operator specific risk assessment.<br />
> The positioning and design of the site specific facilities should be subjected to further visual and<br />
environmental assessments.<br />
* A comprehensive site investigation will be required for the detailed design of the development and<br />
early commencement of the survey would ease the design programme. Further definition is<br />
required for the sources of fill and dredge disposal including contaminated material.<br />
A reassessment of water supplies would be required if HK&CG should implement a more<br />
extensive gas plant than currently envisaged.<br />
Adequate services reserves will need to be provided in the design of Road D6 to accommodate<br />
the development requirements in addition to TKOIE.<br />
> A relocation of the pilotage boarding point will be required to serve the development and IMO<br />
approval of the proposed modification to the Traffic Separation Scheme should be sought.<br />
Pre-entry clearance for quarantine and immigration is recommended for vessels carrying<br />
hazardous materials to Area 137.<br />
fr-<br />
it is recommended that the Western Coast Road should be implemented by 2001 and this should<br />
be accompanied by improvements in the Yau Tong area.<br />
If the Western Coast Road has to be delayed beyond 2001, it is recommended that the target<br />
population figure for 2006 should be maintained together with the industrial developments at<br />
TKOEE and Area 137 whilst constraining the Metroplan forecast for employment to around<br />
15,000.<br />
The contribution of Area 137 to traffic flows within the area of influence is small, with the most<br />
significant contributions to overloading being Junk Bay Road (2.9%) and Lei Yue Mun Road<br />
(3.1%). The internal TKO network will require improvements to the Road D6/Road D9 junction<br />
in 2006 and improvements to the roundabout at Road Pi/Road D4 by 201L<br />
AfH Consultants<br />
Pa & 10 ~ 8
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Both of the proposed Western Coast Road connections have been found to have severe<br />
environmental impacts. Whilst Option B is recommended as the preferred alignment of the two,<br />
further study would be required to establish the optimum solution.<br />
Further survey work is required to establish the extent of contaminated mud removal required in<br />
relation to the Recommended Development Layout.<br />
Air quality impact studies are recommended for major industrial developments when specific<br />
details are known.<br />
Further discussions should be held with the Government Department responsible for the SENT<br />
Landfill to ascertain if the release of the Road D6 reserve can be brought forward and if the<br />
marine access could be relocated to avoid reprovisioning almost immediately after its construction.<br />
Expressions of interest for the partial or total development of the site should be called at the<br />
earliest opportunity.<br />
10.6 STUDY FINDINGS<br />
The Study has demonstrated that the proposed development is both feasible and viable in terms of land<br />
use planning, engineering and marine operations. A risk assessment for the assumed land use has been<br />
presented to the CCPffl for information purposes. Whilst it is acknowledged that further risk analyses<br />
will be required for the detailed proposals of the operators f the acceptability of this more generalised<br />
approach provides a sound basis for the generation of interest for the site.<br />
The evaluation has identified no major environmental concerns as regards the development of Area 137<br />
save the visual intrusion of an industrial development upon an otherwise generally rural area. Mitigating<br />
measures and landscaping have been introduced, which will soften to some extent the intrusion.<br />
The Study has confirmed the need for the provision of the Western Coast Road by 2001 to avoid<br />
constraining the development of Tseung Kwan O as a whole. It is recommended that a high priority is<br />
attached to the confirmation of proposals and routing for the Western Coast Road and that detailed design<br />
should be commenced to ensure the timely provision of this critical element in the external links to Tseung<br />
Kwan 0.<br />
The Study has identified positive demand for early provision for a bulk chemical storage facility and it<br />
is known that the Hong Kong and China Gas Co. are considering the potential of the site within their<br />
current planning exercise. The combination of these two requirements, possibly including an increased<br />
provision for gas production, would approach the minimum viable development referred to in Section<br />
10.4, Equally, the relocation of existing PHI activities, including LPG and fuel oil, to a lower risk area<br />
must be considered within the overall planning context of Hong Kong. The site provides for these<br />
opportunities and it is considered that the development should be progressed as a priority to ensure that<br />
they are realised in the general interest of Hong Kong.<br />
APS Consultants<br />
p ag€
,&&£ ^ • • ' • • / ^fc'SS^>/'^' S^%;.^<br />
Study Reports and<br />
Working Papers
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
final Report - Main Report<br />
APPENDIX A<br />
STUDY REPORTS AND WORKING PAPERS<br />
Study Reports, Working Papers and Discussion Papers which have been completed prior to this Final<br />
Report and upon which it is based are:<br />
Study Reports:<br />
* Inception Report.<br />
» Alternative Concepts Report.<br />
> Preferred Concept Report.<br />
Working Papers:<br />
» Working Paper No. 1 - Wave Modelling Requirements, which sets out the required wave<br />
modelling to be undertaken in the evaluation of the selected concepts.<br />
> Working Paper No. 2 - WAHMO Modelling Requirements, which sets out the mathematical<br />
modelling required for the evaluation of the hydraulic flow, siltation and with particular emphasis<br />
on water quality modelling.<br />
* Working Paper No. 3 - Environmental Background, which discusses the extent of the existing<br />
baseline data for the area and highlights the need for additional baseline surveys as necessary,<br />
> Working Paper No. 4 - Opportunities and Constraints, which presents an inventory of the existing<br />
marine and land uses, the findings of the review of potential land use demand and constraints and<br />
sets out the basis for the land use planning of Area 137.<br />
> Working Paper No. 5 - Transport Modelling Approach, which defines the modelling approach<br />
to be adopted, together with the revised input assumptions including Territory land use and<br />
network data and other model parameters.<br />
> Working Paper No. 6 * Marine Structures, Dredging and Reclamation, which discusses<br />
geotechnical, dredging and reclamation issues and assesses possible edge structures for<br />
incorporation in the outline design.<br />
+ Working Paper No. 7 - Risk Assessment, which studies the risks, both societal and individual,<br />
arising from the possible PHI development in terms of the CCPffl Guidelines.<br />
* Working Paper No. 8 - Strategic Network Forecasts, which assesses the levels of traffic and<br />
impact on the strategic road network for the design horizon years of the Study.<br />
> Working Paper No. 9 - Western Coast Road Connection, which compares the two proposed<br />
connections of the Western Coast Road to East Kowloon for the selection of a preferred route.<br />
APH Consultants<br />
Appendix A-l
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
Discussion Papers:<br />
> Discussion Paper No. la - Site Investigations, which identifies and examines geotechnical data<br />
for Tseung Kwan O Area 137, and makes recommendations regarding further site investigations<br />
that are required for the Study.<br />
APS Consultants — . , , .. _—, ; —__. -—<br />
Appendix A-2
CD 12.<br />
CD
Engineering Feasibility Study of Development o/Tseung Kvan 0 Area 137<br />
Final Report - Main Report<br />
APPENDIX B<br />
WRITTEN STATEMENTS<br />
Bl LAYOUT PLAN 1<br />
B1.1 INTRODUCTION<br />
Layout Plan 1 forms a composite part of the overall planning for Area 137 which has been undertaken<br />
under the Study. Following submission of the Preferred Concepts Report which identified a preferred land<br />
use layout for Area 137, layout plans at scale 1:1000 have been produced to reflect the Study findings.<br />
Area 137 is covered by 3 layout plans which comprehensively define land use for the proposed<br />
development.<br />
BL2<br />
OBJECTIVES OF THE PLAN<br />
Layout Plan 1 predominantly provides for Potentially Hazardous Installations (PHI) and PHI related<br />
industrial land use. The main objective of the plan is to depict land use proposals defined in the Study<br />
and to provide a formal basis for land disposal.<br />
BL3<br />
THE PLANNING AREA<br />
Area 137 is located to the southeast of Tsuen Kwan 0 New Town and is located between Fat Tong Chau<br />
and Tit Tarn Chau. The total planning area amounts to 101.78 hectares which will be composed of<br />
reclaimed land with a mean formation level of 4-5 mPD. Layout Plan 1 is located in the southern portion<br />
of the proposed reclamation. The total land area covered by the subject plan amounts to 29.60 hectares.<br />
The boundaries of the area covered by the plan are defined by the proposed new seawall to the west,<br />
Clearwater Bay Country Park to the east, Tit Tarn Chau to the south and the northern boundary of<br />
proposed lots 2/1 and 3/1 to the north.<br />
BL4<br />
LAND USE PROPOSALS<br />
To avoid confusion all layouts are numbered according to a common format. Site 3/2 refers to Site 3 on<br />
layout plan 2; similarly Site 8/3, refers to Site 8 on layout plan 3. The numbering system is intended to<br />
aid the identification of specific lots on a given layout plan without cumbersome cross referencing,<br />
Bl.4.1 Industry I(B) (13.77 Hectares)<br />
Site 1/2 with a total area of 10.95 hectares has been allocated for industry Class B use. It is intended that<br />
the site will be developed for PHI purposes. The site, subsequent to the findings of the Study, has been<br />
tentatively earmarked as a gas production facility to be operated by the Hong Kong and China Gas<br />
Company (HKCGC).<br />
The site area allocated has been determined with regard to discussions held with the HKCGC. The site<br />
has not, however, been formally allocated to the gas company who are currently undertaking a study of<br />
APR Consultants<br />
a « e
Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />
final Report - Main Report<br />
future gas production requirements in Hong Kong. As the precise land area required has not been<br />
formally confirmed, site boundaries have been indicated with a strong broken line to allow flexibility in<br />
future planning.<br />
In conformity with the Hong Kong Planning Standards and Guidelines (HKPSG) a minimum building set<br />
back of 6.0 metres has been applied to the northern boundary of the site. A 15.0 metre set back has been,<br />
proposed adjacent to road Rl to effectively set development back from the road and to enhance emergency<br />
vehicle circulation and access. No development will be permitted within 20 metres of the seawall to the<br />
west of the site. The reserve is required for emergency vehicle access purposes and as a seawall<br />
maintenance reserve. No formal set backs are applied along the southern boundary of the site which is<br />
abutted by a 7.3 emergency vehicle access (EVA) and a landscape buffer. The EVA has been provided<br />
to allow emergency vehicle access in the event of an incident. The EVA provides direct access to the<br />
seawall which will allow emergency vehicles access to berthing areas if required.<br />
Typical mooring arrangements sufficient to the requirements of a Naphtha Plant have been depicted on<br />
the plan for indicative purposes. Given the anticipated frequency of vessel arrivals, a single dolphin berth<br />
is considered adequate. The length of marine frontage has been determined by the anticipated length of<br />
vessels which are likely to service the Naphtha Plant.<br />
A plot ratio of 1.25 is suggested for the site which produces a GFA amounting to 136,875 m : . In<br />
accordance with the findings of the risk assessment worker density, should not exceed 20 workers per<br />
hectare. This density provides a total site workforce amounting to 219 workers. Maximum building<br />
height should not exceed 30 metres. Applications for stacks, flues or other structures in exceedence of<br />
this height will be subject to visual and environmental impact assessments. It is recommended that the<br />
maximum building height recommendation is rigorously applied. Everyday access to the site will be<br />
obtained from Road Rl.<br />
Site 3/1 comprises a total area of 2.82 hectares. A plot ratio of 2,5 will apply resulting in GFA of 70,500<br />
m 2 . Due to the reduced risk implications related to the processes envisaged on PHI related sites, worker<br />
density is recommended at 30 workers per hectare maximum. A 10.0 metre building setback is<br />
recommended adjacent to road R2, a 15.0 metre setback adjacent to road Rl, and a 6.0 metre setback<br />
elsewhere. The setbacks are intended to enhance traffic visibility and for safety and other considerations<br />
cited in connection with I(C) class industries. Building height will be limited to 30 metres maximum to<br />
correspond with adjacent PHI sites. No access to the site will be permitted from road R2 as this may be<br />
widened in the future to form a portion of district distributor D6. Access to the site will, therefore, be<br />
confined to Road Rl as indicated.<br />
To ensure that the development and layout of buildings and storage facilities on PHI and PHI related sites<br />
is satisfactory to prevailing practices and standards, it is recommended that individual developers seek<br />
CCPHI approval and conform to the requirements of EPD Advice Note 2/92.<br />
BL4.2 Industry I(Q (9.61 Hectares)<br />
A single reserve has been made for I(C) class industry. Site 2/1 comprises a total area of 9.61 hectares<br />
and has been reserved for Industry Class C use. In accordance with the findings of the Study, Site 2/1<br />
is envisaged to be allocated to a LPG storage and bottling facility. The facility will only require a single<br />
berth. This requirement combined with the berthing adjacent sites has dictated the *L* shaped site<br />
configuration.<br />
A plot ratio of 1.25 is recommended which results in a GFA amounting to 120,100 m 2 . On site worker<br />
density is recommended not to exceed 20 workers per hectare. This results in a total estimated workforce<br />
of 192 persons. A 6.0 metres set back is maintained along the northern and southern boundaries for the<br />
purpose of emergency vehicle access. Set backs employed behind the seawall and adjacent to road Rl are<br />
APH Consultants<br />
p age
Engineering Feasibility Study of Dwtlopmtnt of Tstung Kwan O Ana 137<br />
Find Report - Main Report<br />
identical to those described in the context of Site I/I. Access to the site will be obtained from road Rl<br />
located to the east of the site. Height limitations and conditions described in the context of Site 1/1 should<br />
be similarity applied to Site 2/1. Site boundaries have been indicated with a strong broken line to allow<br />
future flexibility should revision be required to the planning layout.<br />
B1.43 Government Institutional and Community Provision (0,24 Hectares)<br />
A single 1C reserve has been provided within the layout. The reserve comprises a 0,24 hectare lot for<br />
the construction of an electricity substation. The substation is required to ensure adequate power<br />
reticulation within Area 137.<br />
Bl.4,4 Open Space and Amenity (235 Hectares)<br />
A single amenity reserve amounting to 2.35 ha has been provided adjacent to Cleaiwater Bay Country<br />
Park and Tit Cham Chau. The reserve will permit adjacent buffer planting to ensure that the integrity of<br />
existing natural features is maintained.<br />
B1.5 ACCESS AiND CIRCULATION (3.63 Hectares)<br />
Access to Area 137 will initially be achieved by an extension of road D6, which will be extended as road<br />
R2. In the subject planning area R2 will connect to road Rl via a roundabout in the southern area of the<br />
layout. No site access will be permitted from road R2. AH road and footpath reserves have been<br />
indicated on Layout Plan L No parking will be permitted along site primary and secondary roads.<br />
Loading and unloading facilities and parking provision sufficient to the requirements of the HKPSG should<br />
be provided on each site. A bus terminus has been indicated adjacent to the eastern boundary of Site 2/1<br />
which is intended to service site employers.<br />
B1.6 IMPLEMENTATION<br />
BL6.1 Site Formation<br />
Area 137 is proposed to be constructed as part of a roiling programme. Land formation will commence<br />
in the area covered by LP1 and commence northward. Under current planning the first parcels of land<br />
could be formed by 1996. No firm date has yet been decided.<br />
Bl*6,2 Stormwater Drainage and Services<br />
Stonnwater culverts and their respective reserves have been indicated on LPL The culverts will collect<br />
run-off from Clearwater Bay Country Park and Tit Cham Chau Respectively and discharge into the sea,<br />
Mains service reticulation will be provided incrementally upon the adequate consolidation of die<br />
reclamation.<br />
Consultant*<br />
Pag *
Engineering Feasibility Study of Development of Tseiwg Kwax 0 Area 137<br />
Final Report - Main Report<br />
B1.7 LANDSCAPE PROPOSALS<br />
Layout Plan 1 covers the southern portion of Area 137 from mid site to Tit Cham Chau Island in the<br />
south, Clearwater Bay Country Park to the east, and Clearwater Bay to the West*<br />
The area covered is proposed for gas production and LPG industry, and smaller PHI related units. Both<br />
zones are served by Road Rl.<br />
Road Rl has a 15 m interface along both sides of its length. Mounding up to 2.5m and dense planting<br />
will be incorporated to reduce the scale of the development both on and off site by creating a significant<br />
green corridor.<br />
The area abutting Tit Cham Chau and Clearwater Bay Country Park will allow opportunities for extensive<br />
structure planting, buffering and development containment. An Emergency Vehicle Access runs through<br />
the buffer zone. Where feasible, grass block paving (Grass Crete) should be used to minimise the expanse<br />
of hard surface on the site.<br />
Along the water front some intermittent structure planting will be incorporated to help the development<br />
merge against the hill side. The interface at the boundaries is 4.5m for each zone resulting in a 9m strip.<br />
A 1.5m high bund will be incorporated with structure planting. These will form fingers of vegetation<br />
maintaining a visual and physical connection with the hill side.<br />
A detailed schedule of land use by site, area plot ratio and GFA is provided on Attachment 1 following.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
ATTACHMENT 1, LAYOUT 1<br />
AREA 137 LAND USE, PLOT RATIO AND GROSS FLOOR AREA<br />
Site No.<br />
Land Use<br />
1/1 I(B)<br />
2/1 KC)<br />
3/1 I(B)<br />
4/1 IC(ESS)<br />
5/1 A<br />
Roads and<br />
Footpaths<br />
Total<br />
Site Area<br />
(Hectares)<br />
10.95<br />
9.61<br />
2.82<br />
0.24<br />
2.35<br />
3.63<br />
29.60<br />
PR<br />
GFA (ra2)<br />
1.25 136,900<br />
1.25 120,100<br />
2.50 70,500<br />
-<br />
-<br />
-<br />
327.500<br />
APH Consultants<br />
Page *" 5
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
B2 LAYOUT PLAN 2<br />
B2.1 INTRODUCTION<br />
Layout Plan 2 (LP2) forms a composite part of the overall planning for Area 137 which has been<br />
undertaken under the Study. Following submission of the Preferred Concepts Report which identified a<br />
preferred land use layout and transport network for Area 137 layout plans at scale 1:1000 have been<br />
produced to reflect study findings.<br />
Area 137 is covered by 3 layout plans which comprehensively define land use for the proposed<br />
reclamation. The subject layout plan (LP2) depicts land use proposals for the central portion of the<br />
proposed Area 137 development.<br />
B2.2 OBJECTIVES OF THE PLAN<br />
Layout Plan 2 provides sites for Potentially Hazardous Installations (PHI's), PHI related industry, Industry<br />
Class B and amenity reserves. The main objective of the plan is to depict land use proposals defined in<br />
the Study and to provide a formal basis for land disposal.<br />
B23<br />
THE PLANNING AREA<br />
Area 137 is located to the southeast of Tsueng Kwan O New Town and is located between Fat Tong Chau<br />
and Tit Cham Chau. The total planning area amounts to 101.78 hectares which will be composed of<br />
reclaimed land with a mean formation level of -r5 mPD. Layout Plan 2 is located in the central portion<br />
of the proposed reclamation. The total land area covered by the subject plan amounts to 35.05 hectares.<br />
The boundaries of the area covered by the plan are defined by the proposed new seawall to the west,<br />
Clearwater Bay Country Park to the east, the southern boundaries of Site 1/2 and 8/2 to the south and the<br />
northern boundaries of Sites 3/2, 4/2, 5/2 and 6/2 to the north.<br />
B2.4 LAND USE PROPOSALS<br />
To avoid confusion all layouts are numbered according to a common format. Site 3/2 refers to Site 3 on<br />
Layout Plan 2; similarly Site 8/3, refers to Site 8 on Layout Plan 3. The numbering system is intended<br />
to aid the identification of specific lots on a given layout plan without cumbersome cross referencing.<br />
B2.4.1 Industry I(Q (20,31 Hectares)<br />
Lot 1/2 with a total area of 10,72 hectares has been allocated for Industry Class C use. It is intended that<br />
the site will be developed for PHI purposes. The site, subsequent to the findings of the Study, has been<br />
tentatively earmarked for chemical storage purposes to be operated by a private developer. The need for<br />
bulk chemical storage sites has been highlighted by the Industry Department. It is intended that the<br />
chemicals stored will be used by industries in Hong Kong and within the region.<br />
In conformity with the Hong Kong Planning Standards and Guidelines (HKPSG), a minimum building<br />
setback of 6.0 metres has been applied to the northern and southern boundaries. A 15.0 metre setback<br />
has been proposed adjacent to road Rl to effectively set development back from the road and to enhance<br />
emergency vehicle access and circulation. No development will be permitted to the west of the site within<br />
20 metres of the seawall. This reserve is required for emergency vehicle access purposes and as a seawall<br />
APH Consultants<br />
p age
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
maintenance access reserve. The EVA adjacent to the seawall will allow emergency access to berthing<br />
areas if required.<br />
Indicative typical mooring arrangements sufficient to the requirements of the envisaged chemical storage<br />
facility have been shown on the plan. The operation of a chemical storage facility requires two berths,<br />
hence two dolphin berths with sufficient mooring separation have been shown. The length of the site<br />
marine frontage has been determined by the estimated length of vessels likely to service the storage<br />
facility.<br />
A plot ratio of 1.25 is suggested for the site which produces a GFA amounting to 134,000 m 2 . In<br />
accordance with the findings of the Study risk assessment worker density will not exceed 20 workers per<br />
hectare. This density provides for a total site workforce of 214 workers. Maximum building height will<br />
not exceed 30 metres. Applications for stacks, flues or other structures in exceedence of this height will<br />
be subject to visual and environmental impact assessments. It is recommended that the maximum building<br />
height recommendation is rigorously applied. Access to the site will be obtained from roads Rl and R4.<br />
Suggested access points are depicted on Layout Pfan 2.<br />
Site 3/2 comprises a total area of 10.09 hectares and has been reserved for Industry Class C use. In<br />
accordance with the findings of the Study, Site 3/2 is envisaged to be allocated to a bulk oil storage<br />
facility. The facility will only require a single berth and a typical mooring arrangement has been depicted<br />
on Layout Plan 2.<br />
A plot ratio of 1.25 is recommended which results in a GFA amounting to 126,100 m 2 . On site worker<br />
density is recommended not to exceed 20 workers per hectare. This results in a total estimated workforce<br />
of 202 persons. A 6.0 metre set back is maintained along the northern and southern boundaries for the<br />
purpose of emergency vehicle access. Set backs employed behind the seawall and adjacent to road Rl are<br />
identical to those described in the context of Site 1/2, Access to the site will be obtained from road R4<br />
located to the south of the site. Height limitations and conditions described in the context of Site 1/2<br />
should be similarly applied to Site 3/2. Site boundaries have been indicated with a strong broken line to<br />
allow future flexibility should revision be required to the planning layout.<br />
B2.4.2 Industry I(B) PHI Related Industry (4.36 Hectares)<br />
Two PHI Related I(B) industry reserves have been made for I(B) class industry allocated for PHI related<br />
industrial purposes. It is intended that such operations will be mutually linked to adjacent PHI sites and<br />
utilise PHI products in production.<br />
Site 7/2 comprises a total area of 2.26 hectares. A plot ratio of 2.5 will apply resulting in GFA of 56,500<br />
or. The remaining I(B) Site (8/2) comprises a total area of 2.10 hectares with a resultant GFA of 52,500<br />
m 2 . Due to the reduced risk implications related to the processes envisaged on PHI related sites, worker<br />
density is recommended at 30 workers per hectare maximum. This results in a workforce of 45 for Site<br />
7/2 and 63 workers for Site 8/2. For each site a 10.0 metre building setback is recommended adjacent<br />
to road R2, a 15.0 metre setback adjacent to road Rl, and a 6.0 metre setback elsewhere. The setbacks<br />
are intended to enhance traffic visibility and for safety and other considerations cited in connection with<br />
I(C) class industries. Building height should be limited to 30 metres maximum to correspond with<br />
adjacent PHI sites. No access to the site will be permitted from road R2 as this may be widened In the<br />
future to form a portion of district distributor D6, Access to the site will, therefore, be confined to Road<br />
Rl as indicated.<br />
To ensure that the development and layout of buildings and storage facilities on PHI and PHI related sites<br />
conform to prevailing practices and standards, it is recommended that individual developers seek CCPffl<br />
approval and conform to the requirements of EPD Advice Note 2/92.<br />
APH Consultants
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
B2.4.3 I(B) Deep Water Industry (DWI) Related Sites (1.68 Hectares)<br />
Sites 5/2 and 6/2 have been allocated to DWI purposes. By definition DWI development comprises<br />
industrial or warehousing operations which, by virtue of their nature require deep water berths. Activities<br />
which cannot prove such a requirement may be precluded from the acquisition of DWI lots. Facilities<br />
falling into this category include the bulk heavy oil storage and packing industry, the break bulk chemical<br />
industry, and the concrete batching and prefabrication industry.<br />
Each I(B) site is ascribed a plot ratio of 2,5 which results in a GFA of 23,300 m 2 and 18,800 or for lots<br />
5/2 and 6/2 respectively. Worker density should not exceed 30 persons per hectare according to the<br />
recommendations of the Study risk assessment. This will result in a total workforce of 50 persons for the<br />
two sites. The same height conditions applied to I(C) and PHI related sites are also recommended for the<br />
I(B) sites. Building setbacks of 6.0 metres have been applied to roadside lot frontages and 4.5 metres on<br />
all other boundaries. This has been undertaken to ensure adequate emergency vehicle access and to create<br />
adequate separation between buildings. A detailed site schedule is shown on Attachment 2.<br />
B2.4.4 Government Institutional and Community Provision (0*02 Hectares)<br />
A 225 m 2 4 G* reserve is provided on Site 2/2 and is intended for the construction of a sewage pumping<br />
facility. This is required to pump sewage for treatment at the Tseung Kwan 0 Treatment works.<br />
Site 4/2 is a combined reserve (G and LO) providing site servicing and recreational facilities. Details of<br />
open space provision are provided below. Services anticipated would comprise estate related offices and<br />
small scale commercial premises. It is not, however anticipated that these will be large scale facilities and<br />
only two to three storey structures wiU be permitted. A suggested treatment is provided in the landscape<br />
master plan accompanying the Study Final Report. No GFA is suggested as this should be decided with<br />
respect to demand upon the implementation of Area 137.<br />
B2.4.5 Open Space and Amenity (1.0 Hectares)<br />
A single amenity reserve amounting to 2.03 ha has been provided adjacent to Clearwater Bay Country<br />
Park. The reserve will permit adjacent buffer planting to ensure that the integrity of existing natural<br />
features is maintained.<br />
The HKPSG requires the allocation of 0.5 m 2 of open space per industrial worker (5 ha per 10,000<br />
workers). As this standard would only provide nominal open space generous provision is made on Site<br />
4/2 given the relatively isolated location of Area 137. The open space will be highly compatible to the<br />
service centre anticipated on the same site.<br />
B2.S<br />
ACCESS AND CIRCULATION (5,15 Hectares)<br />
Access to Area 137 will initially be achieved by an extension of Road D6 which will be extended as road<br />
R2. A reserve for D6 has been indicated on the plan. In the subject planning area, R2 will connect to<br />
road Rl via a roundabout in the southern area of the layout. No site access will be permitted from road<br />
R2. All road and footpath reserves have been indicated on Layout Plan 2. No parking will be permitted<br />
along site primary and secondary roads. Loading and unloading facilities and parking provision sufficient<br />
to the requirements of the HKPSG should be provided on each site. In order to avoid vehicular conflicts,<br />
road R5 will be limited to west-east one way traffic flow providing access to adjacent sites. Road R4 will<br />
culminate in a turning circle and will provide access to Sites 1/2 and 3/2.<br />
APH Consultants p age B~8
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
B2.6 IMPLE3VIENTATION<br />
B2.6.1 Site Formation<br />
Area 137 is proposed to be constructed as part of a rolling development programme. Land formation will<br />
commence in the area covered by LP1 and commence north via the area occupied by Layout Plan 2.<br />
Under current planning the first parcels of land could be formed by 1996. No firm date has yet been<br />
decided.<br />
B2*6.2 Stormwater Drainage and Services<br />
Stormwater culverts and their respective reserves have been indicated on LP2. The culverts will collect<br />
run-off from Clearwater Bay Country Park and site roads and discharge into the sea.<br />
Mains service reticulation will be provided incrementally upon the adequate consolidation of the<br />
reclamation.<br />
B2.7 LANDSCAPE PROPOSALS<br />
Layout Plan 2 provided for PHI and PHI related industry in the central section of the site. Within this<br />
section is a services reserve and smaller industrial units served by roads Rl, R4, R5 and R2 located at<br />
the foot of the Clearwater Bay Country Park.<br />
R2 and R4 have a 6m interface between the footpath and the developments allowing dense tree and shrub<br />
planting to be implemented. This will act in conjunction with planting immediately alongside the road to<br />
create smaller green fingers linking into to the main vegetation infrastructure.<br />
The service area will be primarily used for recreation although buildings will be incorporated for support<br />
facilities. A grassed area with seating will be incorporated to form a green pocket within the site, with<br />
space for some ball court facility to be developed at a later date.<br />
APH Consultants Page B-9
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
ATTACHMENT 2, LAYOUT 2<br />
AREA 137 LAND USE, PLOT RATIO AND GROSS FLOOR AREA<br />
Site No.<br />
1/2<br />
2/2<br />
3/2<br />
4/2<br />
5/2<br />
6/2<br />
7/2<br />
8/2<br />
9/2<br />
Roads and<br />
Footpaths<br />
Total<br />
Land Use<br />
Site Area<br />
(Hectares)<br />
I(C) 10.72<br />
G(Pumping 0.02<br />
Station<br />
Reserve)<br />
I(C) 10.09<br />
LO+G 1.00<br />
I(B) • 0.93<br />
I(B) 0.75<br />
I(B) 2.26<br />
I(B) 2.10<br />
A 2.03<br />
5.15<br />
35.05<br />
PR GFA<br />
1.25 134,000<br />
-<br />
1.25 126,100<br />
-<br />
2.50 23,300<br />
2.50 18,800<br />
2.50 56,500<br />
2.50 52,500<br />
-<br />
411.200<br />
APH Consultants Page B-10
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Find Report - Main, Report<br />
B3 LAYOUT PLAN 3<br />
B3J<br />
INTRODUCTION<br />
Layout Plan 3 (LP3) forms a composite part of the overall planting for Area 137 which has been<br />
undertaken under the Study. Following submission of the Preferred Concepts Report which identified a<br />
preferred land use layout for Area 137, layout plans at scale 1:1000 have been produced to reflect the<br />
Study findings.<br />
Area 137 is covered by 3 layout plans which comprehensively define land use for the proposed<br />
reclamation. The subject Layout Plan (LP3) depicts land use proposals for the northern portion of the<br />
proposed Area 137 development.<br />
B3.2 OBJECTIVES OF THE PLAN<br />
Layout Plan 3 provides for Deep Water Industry (DWI), reprovisioning of the SENT Landfill marine<br />
access, and areas of amenity. The main objective of the plan is to depict land use proposals defined in<br />
the Study and to provide a formal basis for land disposal.<br />
B33<br />
THE PLANNING AREA<br />
Area 137 is located to the south east of Tseung Kwan 0 New Town and is located between Fat Tong Chau<br />
and Tit Cham Chau. The total planning area amounts to 101.78 hectares which will be composed of<br />
reclaimed land with a mean formation level of -f 5 mPD. Layout Plan 3 is located in the northern portion<br />
of the proposed reclamation. The total land area covered by the subject plan amounts to 37.13 hectares.<br />
The boundaries of the area covered by the plan are defined by the proposed new seawall to the west,<br />
Clearwater Bay Country Park to the east, Road R6 to the south and Fat Tong Chau, TKOEE and the SENT<br />
Landfill to the north.<br />
B3.4 LAND USE PROPOSALS<br />
To avoid confusion all layouts are numbered according to a common format. Site 3/2 refers to Site 3 on<br />
Layout Plan 2; similarly Site 8/3, refers to Site 8 on Layout Plan 3. The numbering system is intended<br />
to aid the identification of specific lots on a given layout plan without cumbersome cross referencing.<br />
B3.4.1 I(B) Deep Water Industry (DWD Sites (15.85 Hectares)<br />
A total of 15 sites have been allocated to DWI purposes by definition. DWI development comprises<br />
industrial or warehousing operations which, by virtue of their nature require deep water berths. Activities<br />
which cannot prove such a requirement may be precluded from the acquisition of DWI lots. Facilities<br />
falling into this category include the bulk heavy oil storage and packing Industry the break bulk chemical<br />
industry, and the concrete batching and prefabrication industry.<br />
All 15 I(B) sites have been ascribed a plot ratio of 2.5 which results in a total GFA amounting to 396,600<br />
m 2 (See Attachment 3 for breakdown). Worker density will not exceed 30 persons per hectare in<br />
accordance with the recommendations of the Study risk assessment. Maximum building height should not<br />
exceed 30 metres. Applications for stacks, flues or other structure in exceedence of this height will be<br />
Consultants<br />
Pa % e B ' L1
Engineering Feasibility Study of Development of Tseung Kwan O Arm 137<br />
Final Report - Main Report<br />
subject to visual and environmental impact assessments. It is recommended that the maximum building<br />
height recommendation is rigorously applied.<br />
Proposed access arrangements to each I(B) site have been depicted on Layout Plan 3. Although mean lot<br />
size amounts to 1.0 hectare, the boundaries of each site have been demarcated with a strong broken line.<br />
This prescribes an indicative lot boundary and provides flexibility to future planning by permitting the<br />
consolidation or subdivision of lots.<br />
A 6.0 metre building set back has been applied along front and rear boundaries and 4.5 metres along other<br />
boundaries. Set backs will ensure emergency vehicle access, provide adequate building separation and<br />
provide important breezeways.<br />
B3.4.2 I(Q Deep Water Industry (DWI) Sites (4.76 Hectares)<br />
Almost 20% of all deep water industry sites have been allocated to Industry Class (C) purposes. It is<br />
intended that these be reserved for storage purposes with the particular objective of realising Government's<br />
policy to remove existing dangerous goods godowns from the urban area.<br />
It is intended that 5 sites amounting to a total site area of 4.76 hectares be designated for I(C) DWI<br />
purposes. A plot ratio of 2.5 will apply which will generate a total GFA amounting to 119,000 nr.<br />
Building height restrictions and building set back recommendations applicable to I(B) DWI sites should<br />
also be applied to I(C) DWI sites.<br />
It is intended that all sites will have access to the 50 metre multi-user berth working area abutting the sea<br />
wall to the west of the site. The working area will be administered by Government to ensure that<br />
equitable access to the seawall is obtained. Emergency Vehicle Access to the Working Area will be<br />
provided from road R6 to the south of the layout and roads R9 and RIO to the north of the layout.<br />
B3.43 Government, Institutional and Community Provisions (3.59 Hectares)<br />
Two Government reservations have been provided an Layout Plan 3. An 100 m 2 reserve has been made<br />
for a sewage pumping station on lot 9/3 adjacent to Road RIO, The pumping station is required to provide<br />
a temporary facility for the SENT Landfill marine facility.<br />
A 3,58 hectare reservation has been provided adjacent to the seawall to provide for a multi-user berth<br />
working area. This will be used by lots which require access to deep water berths. It is anticipated that<br />
the facility will be administered by the Marine Department.<br />
B3.4.4 Open Space and Amenity (4.22 Hectares)<br />
Two amenity reserves of area 4.22 hectares have been provided adjacent to Clearwater Bay Country Park<br />
and Fat Tong Chau. The reserve will permit adjacent buffer planting to ensure that the integrity of<br />
existing natural features is maintained.<br />
B3.4.5 Other Specified Use (1.25 Hectares)<br />
A L25 hectare reserve has been reserved for the reprovisioning of SENT Landfill marine access which<br />
is required upon implementation of Area 137. The reserve comprises a 250 metre marginal quay with a<br />
50 metre working area provided to the rear of the quaywaE, Once SENT Landfill operations are complete<br />
the site could be handed over to another user for industrial development. Access to the site wiE be<br />
obtained from road RIO which will be maintained as a private road for the life of the landfill.<br />
APH Consultants Page 3*12
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
B3.5 ACCESS AND CIRCULATION (7.46 Hectares)<br />
Access to Area 137 will initially be achieved by an extension of Road D6 which will be extended as Road<br />
R2. In the subject planning area R2 will connect to road Rl via a roundabout located to the east of the<br />
layout. No site access will be permitted from roads R2 and RIO. Road RIO win be maintained as a<br />
private road for the life of the SENT Landfill. All road and footpath reserves have been indicated on<br />
Layout Plan 3. No parking will be permitted along site primary and secondary roads indicated on the<br />
plan. Loading and unloading facilities and paiidng provision sufficient to the requirements of the HKPSG<br />
should be provided on each site. Recommended points of access to each site have been indicated on<br />
Layout Plan 3.<br />
B3*6 IMPLEMENTATION<br />
B3.IJ.1 Site Formation<br />
Area 137 is proposed to be constructed as part of a rolling development programme. Land formation will<br />
commence in the area covered by LP1 and commence northwards to sites depicted on Layout Plan 3.<br />
Under current planning the first parcels of land could be formed by 1996. No firm date has yet been<br />
decided.<br />
83.6,2 Stormwater Drainage and Services<br />
Stormwater culverts and their respective reserves have been indicated on LP3. The culverts will collect<br />
run-off from SENT Landfill, Clearwater Bay Country Park and Fat Tong Chau respectively and discharge<br />
into the sea.<br />
Mains service reticulation will be provided incrementally upon the adequate consolidation of the<br />
reclamation.<br />
B3.7 LANDSCAPE TREATMENT<br />
Layout Plan 3 covers the northern section of the site adjacent to Fat Tong Chau and the SENT Landfill.<br />
This area incorporates Deep Water Industries and a 50 metre wide working area. The area is served by<br />
feeder roads R6, R7, R9 leading from a major roundabout on road D6. The roundabout and planters will<br />
be provided with ornamental shrub treatment.<br />
An extensive area of buffer planting will be implemented at the base of Fat Tong Chau and along a 7m<br />
strip at the interface to the SENT Landfill site. A 6m wide planting zone has been allocated along the<br />
working area, but planting will be intermittent to allow for access and to form a gentle merger with the<br />
hilly backdrop.<br />
Consultants Page 3-13
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
ATTACHMENT 3, LAYOUT 3<br />
AREA 137 LAND USE, PLOT RATIO AND GROSS FLOOR AREA<br />
Site No.<br />
1/3<br />
2/3<br />
3/3<br />
4/3<br />
5/3<br />
6/3<br />
7/3<br />
8/3<br />
9/3<br />
10/3<br />
11/3<br />
12/3<br />
13/3<br />
14/3<br />
15/3<br />
16/3<br />
17/3<br />
18/3<br />
19/3<br />
20/3<br />
21/3<br />
22/3<br />
23/3<br />
24/3<br />
25/3<br />
26/3<br />
Road and Footpaths<br />
Total<br />
Land Use<br />
G(Multi-User<br />
Berth Working<br />
Area)<br />
KB)<br />
I(C)<br />
KQ<br />
KB)<br />
I(B)<br />
ou'<br />
A<br />
G{Pumping<br />
Station<br />
Reserve)<br />
A<br />
I(B)<br />
KB)<br />
I(B)<br />
I(B)<br />
KB)<br />
KB)<br />
I(B)<br />
KB)<br />
KB)<br />
KB)<br />
KQ<br />
I(C)<br />
I(C)<br />
I(B)<br />
A<br />
1(B)<br />
-<br />
Site Area<br />
(Hectares)<br />
3.58<br />
2.22<br />
2.32<br />
1.01<br />
1.00<br />
1.05<br />
1.25<br />
2.12<br />
0.01<br />
0.89<br />
0.57<br />
0.71<br />
1.05<br />
1.13<br />
1.57<br />
1.36<br />
0.93<br />
0.82<br />
0.70<br />
0.44<br />
0.48<br />
0.50<br />
0.45<br />
0.60<br />
1.21<br />
1.70<br />
7.46<br />
37.13<br />
PR<br />
-<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
-<br />
-<br />
-<br />
-<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
2.50<br />
-<br />
2.50<br />
-<br />
GFA<br />
(m2)<br />
«.<br />
55,500<br />
58,000<br />
25,300<br />
25,000<br />
26,300<br />
-<br />
.<br />
_<br />
-<br />
14,300<br />
17,800<br />
26,300<br />
28,300<br />
39,300<br />
34,000<br />
23,300<br />
20,500<br />
17,500<br />
11,000<br />
12,000<br />
12,500<br />
11,300<br />
15,000<br />
.<br />
42,500<br />
-<br />
515,700<br />
APE Consultants<br />
Page B-14
Suggested Modifications<br />
to Tseung Kwan 0 OOP
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
final Report - Main Report<br />
APPENDIX C<br />
SUGGESTED MODIFICATIONS TO TSEUNG KWAN O ODP<br />
Cl<br />
IMPLICATIONS FOR THE CURRENT ODP<br />
The planning brief requires that impacts on the current ODP which arise during the course of the Area<br />
137 Study should be highlighted in the Final Report. The impacts identified may have a corresponding<br />
impact on the approved Outline Zoning Plan (QZP), The main planning impacts are listed below.<br />
The extent of land formally allocated to PHI development amounted to 20 hectares. The Study has<br />
established that the demand for PHI sites may be substantially stronger than that originally identified. The<br />
outcome of this is that the land use budget outlined in the ODP is significantly different from that<br />
recommended by the Consultants, Similarly, the findings of the Risk Assessment undertaken under the<br />
Study, have suggested that worker densities are restricted to 20 workers per hectare for PHI development<br />
and 30 workers per hectare for DWI development. Modification to the employment assumptions made<br />
in the ODP are therefore required.<br />
Upon acceptance of the Consultants layout plans, the ODP can be modified to reflect the disposition and<br />
composition of land uses. The preferred seawall alignment should also be depicted.<br />
The proposed road alignment depicted in the preferred layout plans should be incorporated on the ODP.<br />
Road details should include the proposed extension of distributor road D6 through Area 137.<br />
Work undertaken with regard to the Western Coast Road has indicated that population thresholds assumed<br />
in the ODP may not be achieved if improvements of the existing external road network, including the<br />
Western Coast Road, are not promptly implemented. It has also transpired that capacity of current road<br />
links has been based not on the ODP population, but that derived by the Metro Planning Group. This<br />
implies that the ODP target population may not be achievable within the time period envisaged and with<br />
regard to the currently planned transport links. Review of the ODP in this respect is therefore, required<br />
and planning assumptions should be modified as appropriate.<br />
The Study has provided an indicative layout for Area 13 L The layout, subject to further study, should<br />
be incorporated on the ODP. The layout requires the realignment of road D9.<br />
Finally, all of the above should be reflected in modification and amendment of the ODP written statement.<br />
APH Consultants
m<br />
•"<br />
Draft Final Report<br />
Comments & Responses
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
CIVIL ENGINEERING DEPARTMPvr<br />
Your response to my previous comment on providing<br />
more reference for the downtime criteria is not<br />
satisfactory. More specific source for establishing<br />
the downtime criteria should be given. It is not clear<br />
whether the excess of both the critical Hs and Tp is<br />
required for causing suspension of operation.<br />
I would like to reiterate that access for future<br />
maintenance of the seawall underneath the quay<br />
structures should be taken into account in the design<br />
of these structures.<br />
The report should address if land resumption and<br />
clearance would be required for the proposed<br />
developments in Area 137.<br />
Please assess the possibility to open a public dump in<br />
area 137 and indicate the timing in the<br />
implementation programme as appropriate (Figure<br />
10.2 & 10.3 refer).<br />
It is understood that Director of Planning has written<br />
to PM/SENT recently, raising the issue of the<br />
possibility of rock caverns behind Area 137.<br />
The definition of operational downtime criteria is highly site<br />
specific and there are no general sources of information.<br />
The values as presented are based on APH experience and if<br />
required could only be refined by detailed physical model<br />
tests. Generally, it may be anticipated that Tp is more<br />
critical in the suspension of operations than Hs.<br />
Noted.<br />
No land resumption or clearance would be required for the<br />
development of Area 137.<br />
As discussed in Section 10, Public dumping Is proposed for<br />
the completion stage of the project commencing late 1997.<br />
A comment on the possible use of caverns behind Ami 137<br />
will be included in the text.<br />
ii) Section 2.2.1<br />
"OPD" in para. 2 and 4 should read "OOP".<br />
Text will be amended.<br />
Figure 3.3<br />
The report should address if typhoon moorings would<br />
need to be planned in conjunction with the proposed<br />
floating docks facilities in Area 131.<br />
Section 5.2.1<br />
I fully support the proposal to adopt the reclamation<br />
methods within minimum removal of the marine mud<br />
at the site.<br />
The Area 131 layout was developed for hydraulic modelling<br />
purposes only. Consideration of typhoon moorings is not a<br />
requirement of the Brief or the additional work performed<br />
for Area 131.<br />
Noted.<br />
Section 5,2.2<br />
The assessment of total consolidation settlement of up<br />
to 3.1 m and the design of vertical drains to<br />
accelerate the settlement are based on limited ground<br />
investigation data. I concur with your<br />
recommendation that the design (settlement and<br />
vertical drain design) should be confirmed/reassessed<br />
by further ground investigation at the detailed design<br />
stage and also during the first phase of vertical dram<br />
installation.<br />
Noted.<br />
There Is a major natural slope, with cliff, to the east<br />
of the proposed internal access road, R2, which runs<br />
along the edge of the Clearwater Bay Peninsula. The<br />
stability of this slope should be investigated, with<br />
remedial works proposed as necessary, at the detailed<br />
design stage.<br />
APH Consultants<br />
Appendix D-J
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Section 53.1<br />
The two reasons stated in the report to justify the<br />
removal of marine deposits along the edge structures<br />
are superficial. This has been commented upon at<br />
the Preferred Concept Plan Report, and I suggested<br />
that the alternative of founding the edge structures on<br />
the marine mud by pretreatment of the foundation<br />
with deep chemical mixing should be kept open.<br />
You responded that this would be reviewed in the<br />
light of the site investigation laboratory results.<br />
Perhaps, you should carry out the review before<br />
finalising the Final Report.<br />
The possibility of marine deposit being stronger than<br />
normal has been noted in the Draft Executive<br />
Summary (DES, page 5) but this has not been noted<br />
in the report. The alternative construction method,<br />
as noted above, should also be highlighted in the<br />
Draft Executive Summary.<br />
Please note that under WBTC Nos. 6/92 and 22/92,<br />
the need to dredge OJ Mm* of uncontaminated mud<br />
or any qualities of contaminated mud should be<br />
justified and agreed by the FMC.<br />
The preliminary site investigations have indicated a marine<br />
deposit layer thickness on the proposed seawall alignment of<br />
11 to 15m, with an average of 12m. Farther, it would not be<br />
necessary to remove more than this layer to provide adequate<br />
seawall stability. As such the findings of WP6 remain valid;<br />
the more so if fun depth removal due to higher strengths is<br />
not confirmed as being necessary.<br />
Equally, the possible retention and drainage of the layer<br />
should be kept open at the detailed design stage.<br />
Noted. Text will be amended.<br />
Noted.<br />
Section 533,<br />
Anchored steel sheet piled retaining wall Is proposed<br />
for seawall construction inside basin. Please clarify<br />
if the maintenance cost has been compared with other<br />
types of seawall construction.<br />
Recognition has been given to the potentially higher<br />
maintenance costs associated with a sheet piled solution. The<br />
adoption of a lower maintenance solution if required<br />
(blockwork) would have a 1% effect on project costs.<br />
In adopting an anchored sheet pile retaining wall as<br />
the edge structure for the basin berths, particular<br />
attention should be given to corrosion protection<br />
under the marine environment.<br />
Section 5.4<br />
The report states (also on page 5 of DES) that 9 Mm 3<br />
of marine fill has been provisionally allocated to<br />
Area 137 by the FMC and that the shortfall (6 Mm 3<br />
out of 15 Mm 3 ) could be made up with a larger<br />
allocation. This is not correct, as advised before at<br />
ihe Prelerred Concept Report Plan report stage. The<br />
FMC has not yet allocated or reserved any marine<br />
borrow areas for Area 137 and the allocation would<br />
likely be made at the tender document stage. The<br />
report should be amended to reflect the actual<br />
situation.<br />
A misunderstanding has arisen over the information given at<br />
our earlier discussions with FMC. Hence the earlier<br />
comment on the Preferred Concept Report was equally<br />
misinterpreted. FMC have been contacted and the position<br />
clarified. The text will be amended to eliminate reference to<br />
the preliminary allocation.<br />
Section 5.5<br />
It :s not possible to identify 4 dumping ground for<br />
the dredged material at this feasibility study stage.<br />
It is possible that the dredged material may be<br />
disposed of in redundant marine borrow pits, as<br />
suggested in the report, but it is also possible that the<br />
material may have to be disposed of to gazetted<br />
dumping grounds.<br />
Text win be amended to include reference to gazetted<br />
dumping grounds.<br />
APH Consultants Appendix D-2
Engineering FeasMity Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Section 5.7 J<br />
It is understood that Area 137 will be reclaimed<br />
generally to 4-0.5mPD with crest of the seawall at<br />
4-6.5 or 4-7.5 mPD and may lead to ponding of<br />
water. The report should address the provision of<br />
adequate surface drainage to avoid ponding of water.<br />
Text will b« amended to include avoidance of ponding as an<br />
objective. The preliminary design has taken this into<br />
account where appropriate.<br />
DRAINAGE SERVICES DEPARTMENT • MAINXANB SOUTH DrVTSTOIV<br />
(a)<br />
(b)<br />
(c)<br />
As indicated in paragraph 3 of Section 5.9.2, the<br />
sewage flows from Area 137 could be increased by<br />
2000 cum/d, which is over 60% of the estimated<br />
total flow from Area 137, should the gas production<br />
facility be more extensive than planned. Please<br />
advise what allowance or contingency will be made<br />
in the sewerage design of Area 137, and accordingly<br />
the capacity of the Treatment Works, to account for<br />
the capacity of the Treatment Works, to account for<br />
variations of such kind in development and future<br />
land use.<br />
The detailed design of interim works and outline<br />
design of Phase II Works for Tseung Kwan 0<br />
Sewage Treatment Works will be commenced<br />
shortly. Please urgently confirm the quantity of<br />
sewage flow from Area 137 to be allowed within the<br />
said designs. Perhaps, PM/SENT, as the client<br />
department for both the subject study and the said<br />
designs, may wish to pursue further.<br />
It appears that the unit tlow rates adopted in Table<br />
5.6 do not conform with those recommended in Civil<br />
Engineering Manual or Sewage Strategy Study.<br />
Your elaboration will be appreciated.<br />
rVefiminary sewerage design for Area 137 is based on the<br />
provisions contained in the land use plan. Final sewerage<br />
design will be based on firm proposals for the planned<br />
facilities. It is considered that adequate allowance in the<br />
design statement for TKO sewage treatment plant has been<br />
made as noted below.<br />
Adequate allowance has been made in the design statement<br />
for TKO sewage treatment plant Phase II for anticipated<br />
flows from Area 137. The allowance is 4,500 nrVday in 2001<br />
''Stage 11" and 6 J50 m 3 /day in 2011.<br />
Unit flow rates are based on Sewage Strategy Study except<br />
for gas production where the rate is based on equivalent<br />
existing facilities. Estimated Sewage flows (Table 5.61 have<br />
been derived for year 2011 by interpolation from the Sewage<br />
Strategy Study as shown below:<br />
WIT FLOW FACTORS * SSS<br />
TKO AREA 137 -<br />
DRAFT FINAL<br />
REPORT<br />
FlowTyp*<br />
Unit<br />
l»*<br />
(mtfday)<br />
2021<br />
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(d)<br />
However, it is worth noting that unit flow factors as<br />
suggested in SSS are apparently for global<br />
consideration and it may not be appropriate for using<br />
them for detailed design in a local area such as Area<br />
137 development.<br />
It is suggested in para 2 of Section 5.9.3 that flows<br />
from Area 137 will be temporarily pumped into the<br />
sewer system of Tseung Kwan O Industrial Estate.<br />
As there is no provision made within the sewers of<br />
TKODB for flows from Area 137, please clarify how<br />
this temporary arrangement can be done without<br />
causing adverse consequence.<br />
Noted: In this case, it is considered most appropriate to use<br />
these factors for outline design of Area 137 development,<br />
until specific (and more exact) information is available about<br />
the actual industry which will use Area 137.<br />
Temporary pumped flows from the SENT landfill marine<br />
access in Area 137 to TKO sewers will less than 1% of<br />
capacity and therefore insignificant. Alternatively, it may be<br />
possible to utilize self-contained (chemical) units which would<br />
eliminate these sewage flows.<br />
ENVIRONMENTAL PROTECTION DEPARTMENT<br />
(I)<br />
AIR QUALITY IMPACTS<br />
Section 8 - Western Coast Road<br />
(1) Section 8.6.2<br />
The results of air quality impact assessment for both<br />
options in Tables S.4 & 8.5 are consistent with the<br />
data previously presented and the modelling<br />
methodology agreed with EPD.<br />
For mitigation for both options by extension of<br />
enclosure, would the Consultants please confirm that<br />
the methodology used tor the assessment of the<br />
residue air quality impact is the same as the<br />
methodology previously agreed with EPD and advise<br />
on the length of extension required For mitigation<br />
by employing semi-enclosure or enclosure with free<br />
venting louvres, would the Consultants please<br />
provide us with further details in respect of the<br />
mitigation measures, the assessment methodology of<br />
the residue air quality impact and the predicted value<br />
of the residue air pollution level at the sensitive<br />
receptions upon the implementation of the mitigation<br />
Regarding the air quality inside the enclosure, would<br />
the Consultants please confirm that the air quality<br />
within the road enclosure would comply meet with<br />
the EPD 1 Tunnel Air quality guidelines which are as<br />
follows :<br />
Pollutant<br />
CO<br />
N
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Both 13Cm and 135m enclosures for Option A will carry<br />
3036 vebkle/hr with 62% of heavy vehicles while Route 5<br />
extension (200m tunnel) is expected to carry 3444 vehicle/hr<br />
with 68% of heavy vehicle. By comparison, it is expected that<br />
it is unlikely to violate the EPD's Tunnel Air Quality<br />
Guidelines for 130m and 135m enclosures in Option A.<br />
In Option B, the predkted air quality values for the 115m<br />
enclosure are 12 ppm (CO), 0.15 ppm (N0 2 ), and 1.5 ppm<br />
(NO). Since the 110m enclosure is expected to operate under<br />
similar traffic condition, both of them will comply with the<br />
EPD's Tunnel Air Quality Guidelines for 115m enclosure.<br />
Section 9 - Environmental Assessment<br />
(2)<br />
Section 9.4.3<br />
The main air pollutants emitted from the town gas<br />
manufacture from naphtha is Nitrogen Oxides. The<br />
maximum emission rate from the plant is merely<br />
about 3 g/s. In view of the above, the Consultants<br />
may need to consider reviewing the suitability of<br />
siting a gas production facility in TKO 137 given that<br />
both the I hour and 24 hours AQOs for nitrogen<br />
dioxide are considerably tower than the<br />
corresponding AQOs for sulphur dioxide.<br />
Based on the existing Ma Tau Kok gas production plant, a<br />
typical X0 a emissioa rate of 15 g/m : /day has been derived.<br />
This assumed emission rate thus corresponds to a cyclic<br />
catalytic gas production facility of about five times the<br />
capacity of Ma Tau Kok. With the same assumptions as<br />
presented in Section 9.4.5, the NOj concentration exposed by<br />
the Srs at Tseung Kwan 0 New Town due to the emissioa<br />
from the site will reach 32 /ig/m 3 (24 hour average). Since<br />
the final report on TKOFSOFD predkted maximum SO 5<br />
concentrations of 220 /tg/m* (after relocation of Shiu Wing<br />
phis 1 g/m 2 /day) at the southeast comer of the Tseung Kwan<br />
0 Mew Town, the corresponding maximum NO^<br />
concentration will be 8 Mg/ui 5 with the assumption of fuel oil<br />
(Oo% sulphur content). Hence it is likely that the nitrogen<br />
dioxide emitted by the proposed gas plant will not impact on<br />
Srs.<br />
(3)<br />
Section 9.4.5<br />
Given that the Deep waterfront Industries (DWI) uses<br />
have not been finalised and that the Potentially<br />
Hazardous Installations (JPHIs) uses are considered by<br />
the Consultants as unlikely to include combustion<br />
equipment except of course the gas production<br />
facility, it is appropriate to include a statement in the<br />
report to highlight that "No Fuel Intensive 1 * uses<br />
should be allowed in the TKO 137 as a land use<br />
constraint. The last statement of this section says<br />
that the emission of the gas production facility at area<br />
137 will not impact on SRs. I have reservation on<br />
this assertion as the main emission of concern from<br />
a town gas production plant is nitrogen oxides apart<br />
from the sulphur dioxide.<br />
Noted. Please refer to response an Section 9.43.<br />
(4)<br />
Section 9.4.8<br />
I support the Consultants' recommendation of<br />
conducting individual air quality impact studies for<br />
major industrial development when specific details<br />
are ioiown. Regarding the issue of ensuring an air<br />
quality impact assessment be carried out for an<br />
industrial development in TKO 137 wiih air pollution<br />
potential, EPD would look after its implementation<br />
through the ER/EIA process and the prospective land<br />
user of TKO 137 should be alerted on the land use<br />
constraint in respect of fuel usage prior to starting<br />
any ER/EIA process.<br />
Noted.<br />
APH Consultants<br />
Appendix Do
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(5) Table 9.5, Air Quality, Particulars, compliance<br />
monitoring<br />
As the 24 hours AQO for TSP is not to be exceeded<br />
more than once per year, it is desirable to set the<br />
action level below the 24-hour TSP AQO.<br />
Noted.<br />
(ED<br />
NOISE IMPACTS<br />
(1) Section 1.1- Area 131 development and traffic effect<br />
on WCR.<br />
It is noted that noise impact from preferred dockyard<br />
facilities in Area 131 has not been included in this<br />
DFR. For the noise mitigation measures on Western<br />
Coast Road, it is considered prudent that* the<br />
dockyard related traffic should be taken into<br />
consideration in formulating the required noise<br />
mitigation measures. Could the Consultants con Arm<br />
whether such traffic have been considered <br />
The traffic generated by a possible four floating drydocks in<br />
Area 131 has been included in the assessment. Consideration<br />
of the noise generated by the development itself is beyond the<br />
scope of the Brief.<br />
(2)<br />
Section 8.6.1 - Noise impact from Western Coast<br />
Road<br />
We concur with the noise impact assessment<br />
contained in this Section 8.6.1. It Is therefore vital<br />
that ail recommended noise mitigation measures in<br />
connection with Option B which include opentextured<br />
road surface, semi-road enclosures and full<br />
road enclosures shown in Figure 8.4 must be<br />
incorporated and in place before the operation of the<br />
road in order to realize a reasonable landuse<br />
redevelopment arrangement contiguous to the<br />
Western Coast Road. Relevant departments such as<br />
Highway, Transport and Housing should be advised<br />
of the recommendation and agreement in principle<br />
sought for the sake of a coherent planning allowing<br />
busy roads to run near noise sensitive residential<br />
buildings. Fine-tuning of road alignment to precisely<br />
determine the extent of noise mitigation measures is<br />
appreciated. However, it is unlikely that the<br />
recommended form of noise mitigation measures<br />
could be substantially changed.<br />
Noted.<br />
(3)<br />
Section 9.5.3<br />
137<br />
Operation noise impact from Area<br />
The para, does not indicate whether further operation<br />
noise from Area 137 will be of concern. On the<br />
basis of landuse arrangement shown in Figure 3.4 t<br />
the Consultants must be able 10 quantify noise from<br />
the proposed storage operations. A statement<br />
advising further operators to comply with the<br />
guidelines contained in the HKPSG is tar from<br />
satisfactory.<br />
The worst-affected sensitive receivers are located at Siu Sai<br />
Wan, about 13 km from the boundary of *Vrea 137.<br />
According to HKSPG the day-dune and night-time criteria<br />
for operational noise are 60 dB(A) and 50dB(A) respectively.<br />
To achieve this leyei at the SRs at Siu Sai Wan the Area 137<br />
boundary sound power levels, for all of the noise sources<br />
should not exceed 129 (day-time) and 119 dB(A) (night-time).<br />
It is considered that these site boundary sound power levels<br />
would not be exceeded by the operation of Area 137.<br />
However simple measures such as factory and building<br />
orientation, etc. should be used to minimise noise levels at<br />
the site boundary.<br />
APH Consultants Appendix D-6
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(4) Section 9.5.4 - Construction noise impact<br />
It is noted that noise assessment was based on the<br />
anticipated numbers and types of PME shown in<br />
Tables 8.15 and 8.16 of the Preferred Concepts<br />
report. The question is whether the same numbers of<br />
PME will be operational within the restricted hours.<br />
Given the many kinds of activities in Table 9.4 that<br />
will exceed the nighttime NCO statutory noise level,<br />
I would prefer the Consultants to realistically review<br />
the numbers of PME likely to operate during<br />
restricted hours and adjust the predicted noise levels<br />
at the sensitive uses.<br />
At present insufficient details regarding the construction<br />
method and plant to be used are known. It is recommended<br />
that during the detailed design/tender stage, specific<br />
proposals will be made by the Contractors which will be<br />
examined for compliance.<br />
It is also necessary to distinguish between "daytime"<br />
of the restricted hours under the definition of the<br />
NCO and the general daytime of weekdays.<br />
Although there is not statutory noise limit on general<br />
daytime of weekdays, it is now a practice that a 75<br />
Db(A) Leq(30min) from the related construction<br />
alone (or 10dB(A) excess of the L90 at rural setting<br />
receiver) should not be exceeded at a receiver. The<br />
Consultants may like to incorporate the limit for the<br />
purpose of subsequent monitoring use at Chai Wan.<br />
(5) Table 9.5<br />
Following the comment on daytime within restricted<br />
hours/weekdays, it is obvious that amendments to the<br />
contents under respective columns of "Objective",<br />
"Standard" and "Frequency/Timing" are required.<br />
Target levels within the restricted hours are ANLs<br />
and not ANL-lO suggested in the footnote. Trigger<br />
and action levels are normally below the target level.<br />
However, it is reported that sometimes It is<br />
impractical to set the levels lower than the ANL due<br />
to enforcement difficulties. Instead, trigger is set<br />
against ONE complaint received and action is set<br />
against more than ONE complaint received from the<br />
construction concerned. Should measured noise<br />
levels initiated by "trigger" exceed the "target",<br />
mitigation will be provided. On the contrary, step<br />
up/frequent noise monitoring will be provided under<br />
the requirement of "action".<br />
Noted, these tables will be amended for the final report.<br />
OT><br />
WATER QUALITY IMPACTS<br />
(1) Section 5.9.4<br />
Since there is only preliminary treatment at the<br />
existing TKO STW, is the primary treatment a new<br />
proposal by the Consultants <br />
Agreed, text will be amended.<br />
09 Section 9.3.3 - Impact on Tung Lung Chau FCZ<br />
It is said in the report that the worst case scenario<br />
will give a suspended solids concentration of 1.6<br />
mg/l. We think this is not necessarily the worst case<br />
because the calculations previously submitted by the<br />
Consultants showed that a value of 4 - 5 mg/l may be<br />
reached under the assumptions. Nevertheless, both<br />
figures exceed the 30% increase in WQO.<br />
Some early working notes were provided prior to a proposed<br />
meeting for the purpose of speeding up the consultation<br />
process which should not now be treated as 4 formal<br />
submission of calculations. The Eastern Buffer WCZ in<br />
which the Tung Lung Chau FCZ is situated had suspended<br />
solids concentrations for 1990 in the range of 0.67mg/i to<br />
12mgA with an average of 3 Jmg/L The i.6 mg/l is
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
and compliance monitoring and enforcement of Action Plans<br />
win be essential.<br />
(3) Referring to our previous comments on Section 8.4,3<br />
& 8.9.1 of the Preferred Concept Report* the<br />
Consultants do not make clear in this DFR what<br />
dredging methods and field measures will be used to<br />
mitigate the water quality impacts during dredging<br />
and reclamation. Also, no specifications regarding<br />
this requirements of water quality monitoring<br />
programmes for dredging and reclamation are given.<br />
It is understood that grab dredging will be employed. Some<br />
mitigation measures are recommended in the Report for this<br />
method. However it is further recommended that silt<br />
curtains are employed and overflowing of barges is<br />
prohibited. These further recommendations will be included<br />
in the Final Report along with water quality Monitoring<br />
programmes.<br />
(IV)<br />
VISUAL IMPACTS<br />
If the objective of section 9.7 is to assess the visual<br />
impacts of the preferred option then the report has<br />
certainly failed to achieve that.<br />
There is no assessment of any kind on what are the<br />
potential impact and how serious they are, and there<br />
is not even one figure to illustrate the problem.<br />
When responding to our previous comments on the<br />
Preferred Concept Report the Consultants have<br />
agreed that the visual impact is "both significant and<br />
undesirable". Devoting only one page of general<br />
comments in this report doesn't seem to reflect that<br />
kind of assessment.<br />
Section 9.7 is a summary of the longer visual impact section<br />
in the Preferred Concept Report. It does acknowledge that<br />
the development will be visually significant. There is a lack<br />
of detail regarding what the development will ultimately<br />
comprise. However the visual section will be enlarged and<br />
illustrated and the suggested discussions will be undertaken.<br />
Soft landscaping is not the only measure to solve a<br />
visual problem. In fact this is often only used as a<br />
complementary measure. Site formation levels, area<br />
layout, site and plant layout and height restriction are<br />
the things that should be considered first (very<br />
appropriate at this stage), complemented by soft<br />
landscaping with perhaps planting at strategic<br />
locations. It is clear that unless the problem is<br />
tackled at the earliest design stage many of the<br />
options will be gone.<br />
To summarize, it is considered that the visual section<br />
is unacceptable, not even close. A more detailed<br />
assessment should be required. We shall be happy to<br />
discuss with the Consultants if they would contact<br />
our Mr. Simon Hui at S3 5 1105.<br />
(V)<br />
RISK ASSESSMENTS<br />
(I) Section 3.3.8, Pg 3-5<br />
CCPHI has just completed a review of the Interim<br />
Risk Guidelines (IRG) taking into account the<br />
experience in implementing and enforcing the<br />
guidelines. The review recommends that the IRG<br />
should now be finalised, which means that the<br />
individual risk guideline should remain at 1 in<br />
100,000 per year, i.e. 1 x 10* per year. The 1,000<br />
fataliry cut-off limit in the societal risk guideline<br />
should be retained. In addition, an "as low as<br />
reasonably practicable (ALARF)* region in two<br />
orders of magnitude is incorporated in the societal<br />
risk guideline. This is to ensure that ail reasonably<br />
practicable measures which can reduce nsk should be<br />
considered unless the measures are not cost effective.<br />
Noted. Text will be amended.<br />
APR Consultants Appendix D-8
Engineering Feasibility Study of Development of Tseung Kmn 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(2) Section 3.3.9, Pg. 3-5<br />
At its 32nd Meeting held on 24.11.1992, one CCPHI<br />
member pointed out that since the risks reported in<br />
the supplementary information (i.e. the risks<br />
associated with the berthing of vessels) were not<br />
incorporated into the findings of the Working Paper<br />
No. 7, the risk assessment in the WP No. 7 did not<br />
reflect the complete picture. As a follow up action,<br />
PM(SENT) undertook to ask the Consultants to<br />
prepare a further report on the combined effect of the<br />
risk identified in the WP No. 7 as well as those<br />
assessed in the supplementary information note (i.e.<br />
Annex 3 to WP No. 7).<br />
In accord with the comments made and a formal request<br />
from PM(SENT), a combined risk assessment including those<br />
associated with shipping incidents at or dose to the Jetty,<br />
Adke wfll be sought from PM(SENT) as to the extent of<br />
inclusion required in the final Report.<br />
After the Consultants have responded to the issue<br />
raised at the meeting, CCPHI will discuss the case<br />
further at iu next meeting before coming to a<br />
conclusion.<br />
It is noted that the risk associated with the shipment<br />
of hazardous substances approaching the jetties has<br />
not been addressed in the Draft Final Report and<br />
therefore further clarification is required from the<br />
Consultants in this aspect.<br />
(VI)<br />
WASTE MANAGEMENT<br />
(1) Section 5.4<br />
The Consultants identified a number of possible<br />
additional fill resources for the captioned project.<br />
However, no preferred option is specified. It should<br />
be noted that the options of screened construction<br />
waste or public dumping will fall in line with our<br />
current waste management policy and are therefore<br />
preferred from the environmental point of view.<br />
The preference for screened construction waste/public<br />
dumping is noted.<br />
(2) Section 9.6.1<br />
"Waste Management Plan": in the third line of this<br />
paragraph should read "Waste Disposal Plan".<br />
Noted. The text will be amended accordingly.<br />
(3) Section 9.6.2<br />
Instead of leaving the problem until the specific<br />
industries are known, the Consultants should take a<br />
more positive approach to discuss the MARPOL<br />
Waste management strategy in terms of, for example,<br />
the different possible scenarios of MARPOL Waste<br />
arising in the area and the capacity of the CWTF to<br />
handle such waste, etc.<br />
Further detail with regard to waste management is contained<br />
in the Preferred Concept Report. The CWTF is designed to<br />
treat likely wastes arising. While the capacity of the CWTF<br />
is known the available capacity to treat waste when Area 137<br />
becomes operational is unknown and depends on how well<br />
the CWTF is used by various industries.<br />
(VH)<br />
SENT LANDFILL INTERFACE<br />
(1) Section 2.3.2, 1st and 2nd paragraphs<br />
The description of SENT landfill and Advance<br />
Works Contract is not entirely accurate. Our<br />
previous comments on the corresponding sections in<br />
Working Paper No. 4 and die Alternative Concepts<br />
Report have not been adopted.<br />
Noted. Text will b« amended.<br />
APH Consultants Appendix D-9
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(2) Section 2.3.4, 3rd paragraph<br />
The construction programme of Road D6 is<br />
inaccurate. I suggest this paragraph be re-written as<br />
follows :<br />
Noted. The text will be amended accordingly.<br />
"Road D6 will be constructed initially to a<br />
roundabout in the north of the TKODE to provide<br />
access to the industrial estate. A stub will be<br />
provided from which temporary access to the<br />
adjacent SENT Landfill site will be provided. The<br />
present proposals as regards the southern extension<br />
of D6 are that the section of road reserve between<br />
TKQIE and SENT Landfill up to and including the<br />
tip of Fat Tong Chau will be handed over to the<br />
SENT Landfill contractor as working areas once<br />
TKOffi contract works in the area are complete,<br />
anticipated to be early 1995.<br />
(2) Section 2.3.4, 3rd paragraph ... cont'd<br />
The landfill contractor will then complete the<br />
formation of this section of Road D6 and hand the<br />
area back to Territory Development Department for<br />
the construction of road within 11 months or receipt<br />
of notice. Completion of the D6 extension to the<br />
south of Area 137 would therefore be anticipated by<br />
mid 1997."<br />
(3) Section 10.3.2, 3rd paragraph<br />
Regarding the consideration of constraints, it should<br />
be noted that the section of road reserve to be handed<br />
over byTKOGE to SENT Landfill contractor by early<br />
1995 will not yet be formed. PM(SENT) previously<br />
agreed that the SENT Landfill contractor will be<br />
given 12 months* possession of this section to<br />
excavate Fat Tong Chau and carry out the road<br />
formation work.<br />
Noted.<br />
(4) Section 10.3.5, 3rd paragraph, Initial Works<br />
The proposed joint use of the Road D6 reserve seems<br />
not feasible. The whole of the reserve will not be<br />
handed over to EPD until early 1995. In mid-1995,<br />
site formation work at the reserve will still be in<br />
progress. It is not desirable and may not be<br />
practicable, to allow traffic to pass through the<br />
unformed reserve, I must reiterate my previous<br />
comments regarding seeking permission from the<br />
HKIEC to allow the Area 137 construction trarfic to<br />
gain access through the TKOIE area, which seems<br />
not to have been taken up by the consultants.<br />
As a result of further discussions with PM(SENT), the<br />
combined use of the Road 06 reserve will not be considered<br />
further.<br />
(5) Hg. 4.1 & similar<br />
The SENT Landfill barging point will be used by 3<br />
separate parties and each of them will require a 50-<br />
metre wide working area behind the seawall.<br />
Independent access to each of the 3 users should be<br />
provided.<br />
The layout of the reprovisioned access facilities is ia<br />
accordance with previously advised requirements. We<br />
consider that the internal layout of this area is a matter for<br />
the SENT Landfill operator to resolve.<br />
APH Consultants Appendix D~10
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(Vffl) ENVIRONMENTAL MONITORING &<br />
AUDITING<br />
General<br />
(1) The Consultants should provide sufficient directions<br />
and recommendations on how the project<br />
Environmental Monitoring and Audit (EM&A)<br />
Manual is to be prepared and should include, inter<br />
alia, the following :<br />
Noted; the text will be amended to cover these new<br />
requirements.<br />
(a)<br />
(b)<br />
(c)<br />
The Project Proponent should be required<br />
to prepare an EM&A Manual. The<br />
Manual is an important management tool<br />
to follow up the environmental issues of<br />
the ftjture construction contract, and the<br />
recommendations of the EIA study, etc.<br />
The Manual should be designed to<br />
provide guidance to environmental site<br />
staff to undertake the EM&A works.<br />
These staff should be independent from<br />
the Contractor.<br />
Environmental monitoring equipment for<br />
the project works should be provided by<br />
the project proponent/Engineer, with<br />
availability on award of contract to<br />
enable, inter alia, recovery of<br />
baseline/backgroundmonitoring data prior<br />
to the commencement of construction<br />
works. Experiences with the Airport<br />
Core Projects revealed that to ensure the<br />
timely implementation of the monitoring<br />
works, under no account should the<br />
construction contractor be made<br />
responsible for the purchase of<br />
equipment.<br />
The EM&A Manual should be submitted<br />
to DEP one month after commencement<br />
of the Contract, in advance of the<br />
commencement of baseline monitoring.<br />
(d) Monthly EM&A reports should be<br />
submitted after submission of the EM&A<br />
Manual, and the recovery and reporting<br />
of baseline data. The first report should<br />
preferably be submitted one month after<br />
the commencement of construction works.<br />
(e)<br />
The timings are for guidance only, but it<br />
is important that the relative timings<br />
between the submission of the EM&A<br />
Manual, the commencement of baseline<br />
monitoring, the commencement of works<br />
and submission of the list monthly<br />
EM&A report are compiled with.<br />
Notwithstanding the above, consideration<br />
should be given to the recovery of<br />
baseline data pnor to the award of<br />
contract to enable the recovery of more<br />
representative baseline conditions.<br />
Appendices which provide guideline in<br />
the following areas are attached :<br />
AfH Consultants<br />
Appendix D-ll
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Guidelines -<br />
Definition<br />
forEM&A -<br />
EM&A Manual<br />
Format - Appendix<br />
A<br />
EM&A Monthly<br />
Report Format -<br />
Appendix B<br />
Monitoring Data<br />
Report Format -<br />
Appendix C<br />
Appendix D<br />
(2) In addition to providing details of site management,<br />
project programme and environmental protection<br />
requirements in contract documents, land lease and<br />
engineering conditions, etc. the Manual should<br />
provide, inter alia, guidance/instruction to resident<br />
environmental site staff on EM&A procedures and<br />
protocols with respect to the following area :<br />
(a)<br />
(D)<br />
(c)<br />
(d)<br />
(e)<br />
(f)<br />
(g)<br />
the construction programme and the<br />
required EM&A programmes to assess the<br />
environmental impacts at Tseung Kwan O<br />
Area 137 with time;<br />
the location, frequency and type of<br />
environmental monitoring and audit<br />
requirements to assess environmental<br />
impacts of the construction;<br />
the form/content of event/action plans<br />
(including any emergency plans) tor air<br />
and water quality, and noise impacts;<br />
review of pollution sources and working<br />
practices/procedures required in the event<br />
of environmental pollution levels being<br />
exceeded;<br />
the content/presentation of monitoring<br />
data, their audit, and actions taken with<br />
respect of non-compliance with<br />
environmental pollution levels;<br />
appropriate report formats/frequency of<br />
submission/special event report, ate.;<br />
complaints/consultation procedures;<br />
(h) equipment service/calibration<br />
requirements;<br />
(5) sensitive receiver locations,<br />
(3) The concept of event/action plans should be<br />
developed (and tabulated), including the<br />
aiscrimination of the responses (trigger/action/target<br />
levels) required for increasing pollution levels.<br />
Staged implementation of remedial measures is seen<br />
as a means to avoid as far as possible senous<br />
deterioration of snvironmentai quality to the point<br />
where conflicts may arise between the Project<br />
Engineer (Client) and the Contractor,<br />
APH Consultants Appendix D-12
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(4) Careful consideration should be given to the timing<br />
of submission of the EM&A Manual and EM
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
GOVERNMENT SECRETARIAT - ECONOMIC SERVICES BRANCH<br />
Section 10<br />
On "Implementation Programme I", would the consultants please<br />
clarify what they mean by "Government funding" I presume<br />
that the land lot* for deep waterfront industriei (DWI) and<br />
potentially hazardous installations (PHI) will still have to be<br />
disposed in the free market and hence they will fetch full market<br />
values. I understand that this can be achieved without much<br />
difficulties because, according to this study, the demand for PHI<br />
sites and, to a lesser extent, DWI sites in Hong Kong is strong.<br />
Also related to implementation, I think the discount rate used by<br />
the consultants, at 2.5% in real terms, is on the low side.<br />
Normally we use 4% for Government projects.<br />
"Government funding** refers to Government funding or<br />
financing the development of the site leading to disposal of<br />
lots* rather than this role being taken by a developer.<br />
We have been recently asked by a Government Department<br />
to adopt a test discount rate of 2.5%. However, the figures<br />
will be reworked at 4%.<br />
GOVERNMENT SECRETARIAT - TRANSPORT BRANCH<br />
GO<br />
Cm)<br />
(YD<br />
(vii)<br />
Para. 2,2.1 - there are a few mis-typings of "OOP"<br />
asOPD".<br />
Para. 7.2.3 - regarding the suggested toll increase for<br />
TKO Tunnel, what shall be the fare level required to<br />
achieve a more rational traffic distribution among the<br />
external road links <br />
Para. 7.2.4 - what is the original level of selfcontainment<br />
assumed <br />
Para. 7.2 - why is it that Po Lam Road will have a<br />
reduced traffic volume for a higher population <br />
Farm. 7.29 - among the scenarios proposed, it is not<br />
understood why for the same population level, a<br />
reduction in Metroplan employment will allow an<br />
increase in industrial employment. Apparently, high<br />
Metropian employment for the same population<br />
should reduce external traffic needs thus giving way<br />
to more industrial developments. Furthermore, if as<br />
stated in the Use paragraph that the growth level at<br />
2011 should be maintained at 2006 levels for no<br />
MTR/WCR* then how can the additional scenarios<br />
39-312 be possible <br />
As a related issued to (v) above, could the traffic<br />
impact within the Area of Influence be addressed for<br />
the no MTR/WCR scenario;<br />
Pan. S.6.I - has it been confirmed with FSD that a<br />
gap width of 10m is adequate to allow each section<br />
of complete enclosure be considered as a separate<br />
entity <br />
Noted. Text wiU be amended.<br />
The toll assumed for the traffic forecasts was $3 in 1990<br />
prices. The more rational traffic distribution would be<br />
achieved at a toll level between this and a doubling of the<br />
toll. The traffic analysis indicates that almost a doubling of<br />
the toll would be required. However, recent research from<br />
the Travel Characteristics Survey has indicated attitudes to<br />
travel demand conditions, which if correct would mean the<br />
balance would be achieved at a lower increase over the base<br />
figure.<br />
There are several alternative ways of defining selfcontainment*<br />
The definition adopted for this Study takes the<br />
proportion of trios which have both origin and destination<br />
within the Study Area. This can be seen to be 31% from<br />
Table 7.6<br />
This is a typing error which will be corrected.<br />
The scenarios show alternative methods of arranging landuse<br />
developments within the transport capacity budget. The<br />
Metroplan employment is "swapped' with the industrial<br />
employment under different scenarios.<br />
B9-B12 were designed to illustrate the extra scenarios for<br />
2011 if the population development went ahead as planned<br />
beyond 2006. In this case, there would be a reduction in<br />
employment from the 2006 scenarios, which logically would<br />
imply that the employment levels reached in 2006 should not<br />
be planned for at that time.<br />
This is outside the scope of the Brief.<br />
FSD were contacted prior to the submission of the report*<br />
Subsequently no comment has been received on the<br />
unaccepubflity of the gap from FSD.<br />
APR Consultants<br />
Appendix D-14
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(viii)<br />
Para. 8.8 - Since it ia concluded that none of the two<br />
alignments are considered optimum, it would be<br />
useful to list out the impacts that need to be<br />
addressed in any further studies.<br />
It is considered that the present Brief ade
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Please clarify how the 40m of buffer distance should<br />
be measured between the portaJ and the SR. Please<br />
delete the sentence of "It is understood that this is<br />
not in line with Housing Department planning*, as<br />
the layout plans for both Yau Tong Estate and Ko<br />
Chiu Road Estate Ph. 3 are yet to be determined.<br />
However, the proposed buffer distance may affect the<br />
design of the layout plans and reduce the<br />
development potential of the site.<br />
Para S.7 Please include a table showing the detail breakdown<br />
of the costs for both options as in Table 6.17 and<br />
Table 6.18 of the Working Paper No. 9A.<br />
The buffer distance should be measured from the nearest<br />
edge of the end of the enclosure.<br />
Sentence will be deleted.<br />
Agreed. The cost breakdown as presented in Working Paper<br />
No. 9A wffl be included.<br />
HONG KONG INDUSTRIAL ESTATES CORPORATION<br />
Section 5.93<br />
No provision has been made in the TKOIE sewers to<br />
accept any flows from Area 137, even on a<br />
temporary basis. Details have to be submitted to<br />
DSD and HKEEC for consideration.<br />
The temporary pumped flows from Area 137 to the TKOIE<br />
sewer system wifl be less than 1% of capacity and therefore<br />
may be treated as insignificant. Your comment regarding<br />
the submission of details would be taken up at the Detailed<br />
Design.<br />
Section 103.4<br />
It would be useful to factories on our industrial estate<br />
if they have access to the berthing facilities and<br />
possibly a pipeline for conveying liquid feedstock<br />
from the pier through your Sites 39 and 31 to the<br />
TKOIE. We would like to explore this further with<br />
the further 'Area 137 developer".<br />
Noted. This can be explored further at the Detailed Design.<br />
Section 10.4.1<br />
The expenditure forecast should not concern us but<br />
we wish to suggest that the interest component<br />
(which is missing in the forecast) may be quite<br />
significant whereas the land premium will be affected<br />
by many factors.<br />
Agreed, interest payments will be significant, however this is<br />
reflected in the selection of the test discount rate.<br />
MARINE DEPARTMENT<br />
Para 6*3.3 - The preceding paragraph states that<br />
vessels will berth "bow-in"* but there is concern as to<br />
whether this is practicable for ballasted arrivals on<br />
flood tide and with southerly wind as stated at the<br />
top of page 6-5. It is felt that under such conditions<br />
a "portside to* berthing would be more practicable.<br />
Text will be amended as suggested.<br />
It is acknowledged that the various ship manoeuvres<br />
have been carried out on a simulator. However, as<br />
the H,K. Pilot's Association are a private<br />
independent body they are not participants in the<br />
consultancy process and would most likely have their<br />
own independent comments. I suggest to insert a<br />
sentence to the sffeci that "It is accepted that<br />
discussions with the H.K. Pilot's Association will be<br />
necessary to establish berthing procedures and<br />
criteria for the specific berths dependent on the type<br />
and size of vessels using such facilities".<br />
APH Consultants Appendix D~16
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
ii)<br />
iii)<br />
iv)<br />
Para 6.7.2 - it is felt that the current DGA south of<br />
Lamma is too far removed from this TKO area. To<br />
reduce crossing traffic situations consultants should<br />
propose the establishment of a new DGA in the<br />
vicinity, possibly between Tung Lung Chau and the<br />
Ninepins;<br />
Para 6.7.3 - referring to the second sub-para., whilst<br />
this would be the preferred scenario, reference<br />
should be made to the fact that currently this is NOT<br />
done in H.K. and Immigration Department have<br />
expressed concern on their resource limitations to<br />
enaole them to carry out such duties;<br />
and<br />
Para 6.8.2 - Recent developments have indicated that<br />
MD will probably lose the facilities currently<br />
provided by the ASDE radar at Kai Tak. The<br />
establishment of a replacement and the timing and<br />
siting of this new facility have yet to be finalised.<br />
Until such details are available it may be optimistic<br />
to state that VTS will be able to monitor all marine<br />
traffic. I suggest a proviso that further consultation<br />
will be necessary with MD to determine the future<br />
marine traffic levels and capability of the VTS at the<br />
time the TKO development is scheduled to be<br />
implemented.<br />
Whflst acknowledging the validity of your comment on<br />
crossing traffic, we consider likely usage of a aew DGA does<br />
not warrant its creation. However, we propose to introduce<br />
to the text that the situation should be monitored and if<br />
required an additional DGA should be created as suggested<br />
in your comment.<br />
Text wfll be amended to include reference as suggested.<br />
Additional comment will be included as suggested.<br />
PLANNING DEPARTMENT<br />
Executive gammarv ri -..<br />
Concept Plan<br />
Section on Preferred<br />
I suggest that the land use budget shown in Table 3.3<br />
of the Draft Final Report be incorporated in the text<br />
of the Executive Summary so as to make it clearer<br />
why the current layout plan proposed to reserve a<br />
total of 22.29ha for DWI, which is roughly the same<br />
as that recommended in the Preferred Concept,<br />
instead of the initial suggestion of 60ha.<br />
Figure I in the Executive Summary and Figure 2.1<br />
in the Draft Final Report should also be updated to<br />
incorporate the recommendedlayout for the dockyard<br />
in Area 131 as shown in Figure 3,3 in the Draft<br />
Final Report to eliminate possible confusion.<br />
Agreed. Text will be amended to incorporate comment.<br />
Layout depicted in Figure 1/2.1 shows the Study Area land<br />
use as covered by the TKO OOP and is part of the Brief for<br />
the Study. PM(SENT) will be requested to confirm the<br />
suitability of amendment of this Figure.<br />
Draft Final Report<br />
Section 4 J<br />
I presume that the measurements of site area quoted<br />
tn this section are only rough figures in hectare<br />
rather than actual measurements. In this respect, I<br />
suggest the figures on GFA should also be rounded<br />
up to hundredth to maintain consistency.<br />
The measurements are actual. However, at your suggestion<br />
GFA figures will be rounded.<br />
APR Consultants<br />
Appendix D-L7
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Table 4.1<br />
Table 4.1 lays down the measurements of all land<br />
use parcels for Area 137. As the berth is also one of<br />
land uses, I suggest that the length and depth of both<br />
the deep water and protected berths should also be<br />
included in this table.<br />
Reference win he added to the text regarding the extent of<br />
seawall provided. However, the extent of berthing provided<br />
should be regarded as indicative based on potential user<br />
requirements. This is likely to be modified with regard to<br />
ultimate user requirements.<br />
Table 7.8 and 7.12<br />
Table 7.8 shows the predicted flows on the roads at<br />
the western screeniine for the am peak bour which is<br />
the critical hour of the day. They are the base case<br />
flows with which other case flows are compared, as<br />
can be seen from Tables 7.10, 7.11 and 7.13.<br />
However, the base case flows in Table 7.12 are<br />
different from those shown in Table 7.8. Can some<br />
explanations be given <br />
The Base Figures shown in Table 7.12 refer to previous<br />
model runs which are now replaced. The table will be<br />
amended.<br />
Para 7 J .7<br />
It is not realistic to assume an increase of about<br />
100,000 residents in TKO without any increase in<br />
population related jobs for the purpose of the<br />
sensitivity test. The increase of 15,000 industrial<br />
jobs is barely population related and hence cannot<br />
provide supporting services to the additional 100,000<br />
residents.<br />
It is agreed that an increase in population would bring some<br />
additional service jobs to TKO. However the extent of such<br />
jobs is a matter of discussion. This test was developed to<br />
illustrate the worst case of higher population without seeking<br />
to discuss employment. It should be noted that the test<br />
results and assumptions were presented in WP$.<br />
Para. 7.2.8<br />
Table 7.14 in this para, appears to show that without<br />
the Area 137 development, the total flow on each of<br />
the roads would be respectively reduced. In reality,<br />
this is not the case because increase in traffic due to<br />
the Area 137 development could displace traffic due<br />
to other departments. To address the impact of the<br />
Area 137 development, it is more realistic to<br />
compare the flows without the development with the<br />
flows with the development.<br />
The figures shown in Table 7.14 have been taken from the<br />
comparison of traffic flows with and without the Area 137<br />
development, as suggested by the Comment. These<br />
assignments take account of the presence of other movements<br />
and allow for the displacement of traffic, also as suggested<br />
in the Comment.<br />
Table 7.16<br />
The figures in Table 7.16 appear to imply some<br />
unrealistic assumptions as follows :<br />
a. The traffic generations of the additional<br />
industrial developments are assumed to<br />
remain constant over time while the CTS<br />
Model assumes that traffic generations<br />
will increase as GDP grows, though not<br />
entirely in line with ihe GDP growth.<br />
These two assumptions are not consistent.<br />
b. The extra bus flow due to deletion of the<br />
MTR is assumed to be 600 pcu/hr in both<br />
2006 and 2011 while the population is<br />
assumed to vary from 243,000 in 2006 to<br />
333,000 in 20 U. Please clarify the logic<br />
behind these two assumptions.<br />
The methodology follows the standard traffic impact<br />
approach of measuring trip rates at specific existing land use<br />
sites, and applying the rates to the new industrial<br />
developments in TKO. These rates have neither been<br />
reduced to reflect restraint nor increased to reflect GDP.<br />
The CTS estimates of goods vehicles are produced in an<br />
entirely different manner, not appropriate for the specific<br />
areas of interest to this Study; it has been used to indicate<br />
the background traffic flows.<br />
The calculations are based on 2011 with an occupancy of 170<br />
per vehicle. The same number of buses has been assumed<br />
for 2006 where population is 25% lower as in practice bus<br />
frequencies are not so rapidly changed in direct response to<br />
traffic demand. The figures imply a lower occupancy of<br />
around 125 in 2006. The alternative approach of reducing<br />
die number of buses would give a saving of about 150 pens,<br />
which is about 1.5%, of the screeniine flows and well within<br />
the margin of error.<br />
AfH Consultants Appendix D-18
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Para 7 JS.9<br />
If the proposed industrial developments have not<br />
been included in Metroplan, they cannot be regarded<br />
as developments to fulfil any identified need. On the<br />
odier hand, the population and employment<br />
anticipated by Metroplan for 2001 can be regarded as<br />
committed. As such the proposed industrial<br />
developments should be treated as a floating quantum<br />
to be addressed in the context of the TDS Review.<br />
It should be noted that both the MTR and WCR are<br />
not assumed as committed in the TDS Review. Your<br />
views and proposals should have regard to this<br />
assumption.<br />
The ranking of priority between Metroplan employment and<br />
development of Area 137 is a matter of policy. The traffic<br />
analysis can only examine the scenarios required to satisfy<br />
the Brief and any additional instruction to the Consultants as<br />
conveyed through the Working and Steering Groups.<br />
Para 7.2.10<br />
(a)<br />
(b)<br />
(c)<br />
At the end of the first sentence on the<br />
first main finding, an *If clause" should<br />
be added as follows :<br />
"The Western Coast Road ... overloaded<br />
TKO Tunnel, if the proposed additional<br />
industrial developments are implemented<br />
by. 2001".<br />
As it stands, the first main finding<br />
appears to suggest that the requirement of<br />
the WCR by 2001 is not directly caused<br />
by the proposed additional industrial<br />
developments, which is not correct. This<br />
is apparent from the figures shown in<br />
Table 7.16.<br />
The third main finding could not be<br />
agreed with. It is clear from the figures<br />
in Table 7.16 that provision of the WCR<br />
by 2001 or earlier is caused by the<br />
proposed additional industrial<br />
developments but not possibly by any<br />
change in self containment, A change in<br />
self containment would have impact on<br />
both the external and internal road<br />
network. The impact on the external<br />
roads has been shown to be small by the<br />
Consultants, but that on the internal road<br />
network, under the assumption of a<br />
greater self containment, has not yet been<br />
assessed. It is important to ensure that<br />
the internal road network would work<br />
with adequate capacity under the greater<br />
self containment assumption which could<br />
materialise when trips are forced to be<br />
made within the town due to congestion at<br />
the external roads.<br />
The forth main finding is generally true.<br />
It should however be expanded to indicate<br />
what measures should be taken if the<br />
MTR is not provided, in order to make it<br />
meaningful and useful.<br />
The major traffic generator is the TKOIE. Therefore the<br />
amendment should refer tc "all proposed 1 * developments. If<br />
Area 137 is constructed and TKO IE development is deferred<br />
then WCR may also be deferred for a few years depending<br />
on the revised time scale of TKOIE. The development<br />
phasing of the TKOIE is the major factor.<br />
Noted. It is considered that the finding is valid for a<br />
reduction is self-containment.<br />
The report has indicated the areas which ae«d further<br />
analyses. However the majority of the comment would<br />
require the consultants to address comments outside the<br />
Brief.<br />
APH Consultants<br />
Appendix D-19
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(d)<br />
On the sixth main finding, any conclusion<br />
drawn or proposal made relating to a<br />
population of 440,000 in TKO are<br />
considered premature as the population<br />
figure was considered to be the maximum<br />
design capacity under the TKO Outline<br />
Development Plan which may not be<br />
attainable without the corresponding<br />
upgrading of transport link.<br />
Noted. HoweTer the consultant has been requested to<br />
comment on the population level.<br />
(e)<br />
Section 73<br />
The recommendation in the last main<br />
finding is not supported. If the WCR is<br />
delayed/not provided, the proposed<br />
additional industrial developments should<br />
not be permitted or reduced to a level<br />
appropriate to the capacities of the<br />
external and internal road networks.<br />
It is difficult to check the capacities of the junctions<br />
within the internal road networks, because the<br />
junction flows and layouts are not given. I trust that<br />
TD would check the capacities of the junctions to<br />
ensure that they would work with adequate<br />
capacities.<br />
This is a policy issue* However the consultants have an<br />
obligation to point out the advantages of the Area 137<br />
development compared with other plans for TKO. The site<br />
offers water-front access whkh is a limited resource in the<br />
Territory; also there are prospective developers for the<br />
TKO IE. Also to be taken into account is the findings of the<br />
recent Travel Characteristics Survey that employment<br />
development in the New Towns is lagging behind the<br />
scheduled plans. It is dearly possible that these<br />
developments wifl go ahead as opposed to the more general<br />
employment development embodied in Metro plan for other<br />
sites in TKO.<br />
Noted. These have been supplied to Transport Department<br />
in December 1992.<br />
Section S.4<br />
The marginal improvement on traffic flows shown in<br />
Table S.I cannot provide sufficient evidence to<br />
conclude that Option S is better than Option A. It is<br />
difficult to explain why traffic flows at TKO Tunnel<br />
and the WCR should differ between Options A and<br />
B, since accessibility to/from the WCR would be<br />
similar for both options, when the road network in<br />
Yau Tong is unbiasedly improved as required<br />
differently by each of the options. As the Lei Yue<br />
Mun Road/WCR Connector would diverge from the<br />
WCR earlier, Option A would appear to be better in<br />
case accidents occur on the section of the WCR<br />
between both diverge points defined by both options.<br />
Having regard to the above, it is considered that in<br />
transport terms, Option B is as good (or bad) as<br />
Option A.<br />
I would like 10 see somewhere in Chapter 7 your<br />
recommended population thresholds for TKO with :<br />
(a) the existing external roads<br />
(b) (a) plus iMTR<br />
(c) (a) plus the WCR and<br />
(d) Ob) plus the WCR<br />
Section 8,4 concludes that the improvement in traffic flows<br />
is marginal, yet there is a preference for Option B. The<br />
preference arises from other items of the evaluation* in<br />
particular the consideration of environmental issues. The<br />
discussion on accident location should equally be applied to<br />
both Option A and 3, although the issue of accidents is not<br />
normally applied to highway evaluation in the form<br />
contained in the comment.<br />
These alternatives are presented in Section 7X9. The results<br />
wilt be summarised into a separate table with the suggested<br />
format.<br />
APR Consultants<br />
Appendix
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
PLANNING DEPARTMENT - DISTRICT PLANNING QFFTCE/KOWLQQN<br />
Chapter 8 - Western Coast Road<br />
(a) Para 3.5.1<br />
Please be suggested to amend the second sentence as<br />
'•Option A requires utilizing land reserved for<br />
the proposed Lei Yue Mun Supplementary Housing<br />
Scheme *<br />
Amendments will be undertaken as suggested*<br />
(b)<br />
Para 8.5.3 (Yau Tong Road Link to Lei Yue Mun<br />
Road)<br />
The development potential of the proposed East<br />
Kowioon Hospital will also be affected as the site<br />
area will be largely reduced for the construction of<br />
the Western Coast Road.<br />
Noted. This would be true if self protective building designs<br />
were not adopted.<br />
(c) Para 8.5.4<br />
Please note that for existing land uses, Option B<br />
impinges not only on the Po Chiu College, but also<br />
on the St. Antonius Primary School. For planned<br />
[and uses. Option B will also encroach on the Yau<br />
Tong Bay Redevelopment.<br />
Option B would abut the embankment below the Primary<br />
School. Both Options would encroach on the proposed Yau<br />
Tong Bay Redevelopment. Text win be augmented to reflect<br />
this impact.<br />
(d) Para 8.7<br />
Other than the demolition of 2 industrial buildings,<br />
there is a doubt on why the cost comparison of both<br />
the 2 options does not include the resumption costs<br />
of some of the Yau Tong Marine Lots upon which<br />
would be encroached by the Western Coast Road.<br />
Should the reprovisioning cost of the Lei Yue Mun<br />
Supplementary Housing Site be included into the cost<br />
comparison analysis, there would be no reasons to<br />
exclude the reprovisioning costs of part of the<br />
proposed East Kowioon Hospital site, Yau Tong Bay<br />
Redevelopment, fire station as well as the two<br />
affected schools that would be affected by the<br />
Western Coast Road from the cost comparison.<br />
In view of this partial comparison, I have reservation<br />
on the concluding statement that "Option B is thus<br />
shown to be the more cost effective option*.<br />
Resumption costs should not be payable in the event the<br />
present lots are rezoned for the proposed Yau Tong Bay<br />
Redevelopment. See Section $.5.2. Whilst a reduction in<br />
premiums would result from the land taken for road<br />
construction, this would be similar for both Options.<br />
Government Departments were, as noted, requested for these<br />
inputs in this regard. Those received were incorporated into<br />
the evaluation equation.<br />
On the basis of comparative costs and information received<br />
Option B was shown to be the most cost effective option.<br />
APH Consultants Appendix D-21
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Find Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
PLANNING DEPARTMENT - DISTRICT PLANNING OFFICE/SAI KUNG AND TSEUNG KWAN O<br />
General<br />
! havereservationon the method of determining the<br />
proposed landuse solely by surveys of the demand<br />
for DWIs and PHIs. There is no prima facie why all<br />
PHI demands should be met within the Hong Kong<br />
Territory. Afterall, Hong Kong is much more<br />
densely populated than its neighbouring territory; and<br />
as such, more vulnerable to potential disasters,<br />
however slight its chance of happening may be.<br />
From district planning point of view, priority should<br />
be given to those existing PHIs in more populous<br />
areas within other parts of the Territory (e.g. the gas<br />
works in To Kwa Wan) to be relocated to Area 137.<br />
Introduction of new PHIs should be exercised with<br />
The author may not be too familiar with the planning<br />
system in Hong Kong. Section 2.2.3, for instance,<br />
describes the purpose of the OZP as "to revise and<br />
update the OOP", which is in fact not the case. The<br />
statement in the same paragraph: The time scale for<br />
02 circulation and approval will most likely allow<br />
for the incorporation of the enclosed<br />
recommendations of this Study" is also an unfounded<br />
assertion. The Consultant is probably unaware of the<br />
fact that the TKO OZP S/TKO/l adopted by RNTPC<br />
of TPB on 4.9.92 was gazetted on 11.12,92.<br />
The validity of the comment is noted. However, the Study<br />
Brief requires the identification of PHI and DWI operators<br />
with an interest in locating in Area 137 and to ensure that<br />
such users are eniironmentafly acceptable. Major emphasis<br />
has been placed on the identification of potential users who,<br />
as identified by Industry Department would provide a<br />
positive benefit to the economy of Hong Kong. During the<br />
course of the study we also sought to identify existing PHPs<br />
who may wish to relocate to Area 137. With the exception<br />
of HK China Gas most PHIs operations saw little advantage<br />
in relocation and would not do so unless obliged to and<br />
possibly convinced by Government. Thus, a Government<br />
policy initiative would be required to implement what you<br />
suggest.<br />
The OZP should ideally incorporate the latest planning<br />
information available to ensure, once gazetted, that its<br />
proposals are not immediately redundant. Thank you for<br />
informing us of the OZP gazzetal. Please note the suggested<br />
amendments to the ODP which may impact on the OZP<br />
proposals.<br />
Specific<br />
Section 2.2.1<br />
"OPP's" in first line of second paragraph should read<br />
"OOPs". Similarly for OPDs in first and sixth lines<br />
of the fourth paragraph.<br />
Noted. Text will be amended.<br />
5.<br />
Section 2.3.2<br />
If it is the intention that the marine access for SENT<br />
Landfill be relocated outside Area 137, the<br />
Consultant should make detailed recommendations.<br />
As can be seen from the adopted ODP, the SENT<br />
Landfill is bounded by the TKO Industrial Estate in<br />
the west and Area 137 in the south, there is not<br />
much scope for an alternative access to be designed.<br />
The report should elaborate farther on the specific<br />
design controls/measures which are required to be<br />
adopted.<br />
This issue was discussed during the course of the Study to see<br />
if» by appropriate siting from the outset, reprovisioning<br />
could be avoided almost as soon as the facilities are<br />
provided. Solutions discussed included siting the facilities<br />
front the outset in the proposed Area 137 location as well as<br />
further north within the bay. However, the Study was<br />
directed to assume that reprovisioning will take place and<br />
that this should be provided for within Area 137.<br />
These are outlined in Section 4.0 and within the written<br />
statements*<br />
APH Consultants Appendix D-22
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Section 2.3.4<br />
I share the author's view that the nature of traffic<br />
generated by the proposed DWIs and PHIs within<br />
Area 137 is such that it is desirable to confine this<br />
traffic to high standard express routes which include<br />
the Western Coast Road and the Cross Bay Bridge.<br />
These routes will be separated from the residential<br />
and commercial areas in Tseung Kwan O and ensure<br />
that environmental impacts are minimized. Similar<br />
comments were received from the District Board<br />
members when the Tseung Kwan 0 OZP was<br />
presented to the Sai Kung District Board in early<br />
1992.<br />
Noted.<br />
Section .4.2<br />
Site 1 which has been allocated for gas production<br />
purposes may more appropriately be zoned "Industry<br />
Group 3(I(B))" as the proposed "Industry Group<br />
C(I(C))* is mainly intended for warehouse and<br />
godown purposes.<br />
The site will be used for gas production and storace.<br />
However, at your suggestion we will modify the zoning and<br />
the respective landuse budget.<br />
Since the Western Coast Road unavoidably has<br />
significant impact on the Kowloon Hast area, the<br />
District Planing Offlcer/Kowloonshould be consulted<br />
on whether the proposed WCR could link with Kwun<br />
Tong Bypass or other proposed road network in the<br />
South East Kowloon Development Statement<br />
presently undertaken by the Consultants.<br />
The SEKS consultants advise that outline provision has been<br />
made for strategic routes which have a bearing on their<br />
study area.<br />
9.<br />
SectionJLI<br />
In order to have a better understanding of the visual<br />
impact and glare nuisance, it is suggested that a<br />
visual impact assessment with photo-montages be<br />
conducted.<br />
Photo montage preparation is unfortunately beyond the<br />
terms of our Brief. Nevertheless* a horizontal profile sketch<br />
of the site as viewed from Chai Wan will be prepared.<br />
REGIONAL SERVICES DEPARTMENT<br />
Para 5.3.2<br />
The revetted slope with rock armour seawall should be of a type<br />
that will not easily trap floating refuse brought ashore by wave.<br />
It is hoped that such a design will not cause cleansing problem.<br />
Noted. This should be acted upon at Detailed Design.<br />
ROYAL HONG KONG POLICE FORCE<br />
Section3. para 3.3.9<br />
The suggestion that jetty operations be suspended,<br />
for the annual festival at Joss House Bay, is<br />
supported;<br />
Noted.<br />
APH Consultants Appendix D-23
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(b)<br />
Section 4<br />
0)<br />
(ii)<br />
The recommended planning layout (fig.<br />
4.1) is noted, particularly the R2/D6<br />
alignment - I trust this will be<br />
development early to ensure that adequate<br />
alternative routes to and from the PHI<br />
area in the south are available as quickly<br />
as possible;<br />
The additional EVA's and proposed<br />
restrictive parking and loading/unloading<br />
arrangements are most welcome;<br />
The provision of access along D2/D6 will be provided from<br />
the outset. However, the alternative routing to the PHI<br />
development wfll depend upon the completion of Rl. The<br />
completion of this latter road will depend upon the rate of<br />
supply, at that time, of public dumping material. During<br />
imptem elation a view will need to be taken on the urgency<br />
for the provision of the road in the light of the actual rate of<br />
supply.<br />
Noted.<br />
(c)<br />
Section 5<br />
Potential sources of fill are noted;<br />
Noted.<br />
(
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
3. The general principle should be to provide as much<br />
greenery as possible such as buffer and screen<br />
planting and simple planting on road verges. The<br />
use of natural earthmound instead of raised planter is<br />
a more suitable approach to the area and to use as<br />
little ornamental shrubs as possible except in<br />
designated open spaces.<br />
The use of raised planters has been limited as far as possible<br />
within the design, in order to keep costs down and reduce<br />
the visual extent of the hard landscape. They have, however,<br />
a number of practical purposes which make their use, in this<br />
situation, essential:<br />
* to prevent casual parking along roadsides;<br />
* to visually and physically separate pedestrian and<br />
vehicular traffic;<br />
» to raise roadside planting above a level where it<br />
might be affected by splash back from vehicles,<br />
and so avoid unsightly edges to roadside planting<br />
beds;<br />
» to increase the height, and thereby the screening<br />
effect of the roadside planting;<br />
* to help reduce the impact of noise generated at<br />
road level.<br />
Primary Structure Planting<br />
4. I do not see how using indigenous tree and shrub<br />
species will provide the buffer zone or the main<br />
vegetation infrastructure as intended. It is not that I<br />
agree with the use of only indigenous tree and shrub<br />
species but many species listed in Table 4.2 for<br />
primary structure planting are not indigenous and<br />
wrong tree species for the area. The consultants<br />
need to check and a bit of more research before they<br />
specify the recommendation. This office does not<br />
agree with shrub species recommended and would be<br />
interested to know how many of these are indigenous<br />
shrubs. One also has to consider whether these<br />
recommended species will grow well in such a harsh<br />
environmental such as in area 137.<br />
The use of the word "indigenous" is, unfortunately<br />
misleading and will be omitted from the text. It was used to<br />
identify one of the aims of the proposed planting, that
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Roadside planting<br />
6. Para. 2 states that tree planting along the roads will<br />
provide shade to pedestrians and reduce glare from<br />
hard surfaces and yet they recommend the use of<br />
raised planters. Earthmounds will do the job and<br />
cheaper and more natural and more suited to the<br />
area. Furthermore, earthmounds will provide<br />
uninterrupted root developmentwhich is important in<br />
such an environment. The consultants should review<br />
the recommended species for roadside planting.<br />
More thought needs to be given to replace the<br />
recommended species as shown in Table 4.2.<br />
Noted, as point 3 in this series.<br />
While we agree that the use of earthmounds would provide<br />
a softer appearance in screening the development and roads,<br />
there is insufficient space within the development to create<br />
mounds large enough to provide suitable screening, as well<br />
as allowing space for servkes, access and emergency access,<br />
Plant species for roadside locations, in particular shrub<br />
species were chosen to create additional interest and a more<br />
human-scale environment than the main structure planting.<br />
These, however, have been reconsidered with a view to the<br />
likely maintenance*<br />
Maintenance Considerations<br />
7. By introducing amenity shrubs and ornamental shrubs<br />
and roadside planters, they entail intensive<br />
maintenance requirements such as watering, pruning,<br />
weeding etc. which the maintenance authority (in this<br />
case RSD) does not favour. Self-maintenance type of<br />
planting will be more suitable in such a low<br />
population density area such as PHIs and DWIs sites.<br />
Noted, as previously.<br />
The section on landscaping needs revision. The<br />
design solution is over-simplified even though the<br />
main concept is clearly stated. A more thorough<br />
approach to the type of planting and the choice of<br />
species are warranted.<br />
Noted* as previously.<br />
TERRITORY DEVELOPMENT DEPARTMENT ~ SOUTH EAST NEW TERRITORIES DEVELOPMENT OFFICE<br />
Volume I<br />
1. In the Table of Contents, insert the word "Section*<br />
as heading of the section column.<br />
Agreed.<br />
2. Section 2.24 foage 2-2^ 1st oara.<br />
Replace the 2nd sentence by<br />
"An interim upgrading of the plant i* scheduled to<br />
commence in late 1993. On completion in mid 1995,<br />
the additional facilities will be able to cope with the<br />
effluent generated by the TKOE. Additional amount<br />
of effluent generated by development in TKO will<br />
require further upgrading of the plant."<br />
Agreed,<br />
3- Section 5.9.1 and 5.9.3 /'page 5-14. 5-15 & 5-16)<br />
These sub-sections do not depict precisely the present<br />
position of the study on Tseung Kwan O Sewage<br />
Treatment & Disposal undertaken by Messrs Mott<br />
MacDonaid Hong Kong Ltd. You agreed to update<br />
the said sub-section in consultation with Messrs Mott<br />
MacDonaid Hong Kong Ltd.<br />
Noted. The sub-section will be updated in consulation with<br />
Mott MacDonaid Hong Kong Ltd.<br />
APH Cansutimts Appendix D~26
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
4.<br />
Section 7. 12 (page 7-3}<br />
3rd para. - second sentence should read "However,<br />
in accordance with the implementation programme,<br />
the completion date for Road D6 is required to be<br />
brought forward to 1997. *<br />
Agreed.<br />
Section 7. 1.3 (page 7-3)<br />
1st para. - Planning Area 85 should read Planning<br />
Area 86.<br />
Agreed.<br />
6.<br />
Section 10.3 .2 (page<br />
3rd para should read<br />
Agreed.<br />
8.<br />
9.<br />
10.<br />
II.<br />
12.<br />
" - reclamation of the road reserve by SENT<br />
Landfill Contractor from mid 1995;<br />
one year notice to SENT Landfill<br />
Contractor for release of the road reserve;<br />
release of the reserve to TDD for the<br />
construction of the road by mid 1996."<br />
The subsequent sentences in paragraph 3 should be<br />
amended in accordance with the above constraints.<br />
Section 10.3.5 (page 10-4)<br />
3rd para<br />
Initial Works should read "Initial Development*<br />
The 2nd sentence under this sub-para should be<br />
amended in line with the comment in the above para.<br />
Implementation programme 1 should be deleted.<br />
Implementation programme 2 should be amended in<br />
line with the suggestion given to you on 17<br />
December 1993.<br />
In all the Tables under Section 10, programme 1<br />
should be deleted and programme 2 should read<br />
programme.<br />
Table 10.3 (page 10-6)<br />
The expenditure for Phase I and remaining phasing<br />
should be split.<br />
In view of the substantial nature of amendments<br />
involved, you agreed to amend and re-circulate<br />
Section 10 of the draft final report (Volume 1) in line<br />
with our suggestions for discussion and endorsement<br />
in the coming Steering Group Meeting which is<br />
presently scheduled at the end of this month.<br />
Accepted.<br />
Accepted.<br />
Accepted.<br />
Agreed.<br />
Agreed.<br />
In the above discussion, we also suggested that the Location<br />
Plan (Drg. No. TKO/1237/001 in Volume 2) should be amended<br />
to show the study site in relation to the whole Tseung Kwan O<br />
New Town. In particular, its relation to the two important<br />
neighbouring sites, i.e. the Tseung KwanO Industrial Estate and<br />
SENT Landfill, should be shown clearly.<br />
The drawing will be amended.<br />
APH Consultants Appendix D-27
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
I refer to CE/MS DSD's letter ref. (26) in D(MS) 10/5/61 m<br />
dated 16 December 1992 which was addressed to you and<br />
copied to this office commenting on the draft final report.<br />
I wish to supplement the information containing in para (b) of<br />
the said letter as follows :<br />
The detailed design of interim works and outline design of Phase<br />
n works for the Tseung Kwan 0 Sewage Treatment Works<br />
commenced on 27.11.92. The Consultants Messrs Mott<br />
McDonald Hong Kong Ltd are required to consider treatment of<br />
the effluent generated by the Area 137 development in<br />
accordance with the Revised Design Statement ofTseung Kwan<br />
O development Sewage Treatment and Disposal, a copy of<br />
which was given to you satiy this year. As such, please<br />
urgently provide the quantity of sewage flow from the Area 137<br />
development to Messrs Mott McDonald Hong Kong Ltd. Please<br />
be advised that it is not until the completion of the Phase n<br />
stage 1 of the Sewage Treatment Works by 1998 that the plant<br />
is capable of coping with treatment of the effluent from the Area<br />
137 development.<br />
Please see attached Figure which illustrates Area 137<br />
predicted levels in relation to the revised Design Statement<br />
No2 and the total allocation for Areas 137, 85 and 86. A<br />
copy of the Figure has also been passed to Mott MacDonald<br />
for confirmation.<br />
The issue of sewage flows from Area 137 has subsequently<br />
been resolved with DSD. The revised Report contains ihe<br />
updated and agreed information.<br />
TRANSPORT DEPARTMENT - PORT AND AIRPORT DEVELOPMENT OFFICE<br />
A. Draft Executive Summary<br />
PagejS<br />
(1)<br />
How firm are the population build-up assumptions<br />
for the future design years. Reference to housing<br />
programme, new town development programme<br />
should be given.<br />
The figures reflect the Housing<br />
Metro plan.<br />
Programme and the<br />
(2)<br />
In view of the substantial difference between the two<br />
population forecasts, (333,000 vs 440,000), the<br />
report should clearly state that the traffic and<br />
transport studies have been based essentially on an<br />
ultimate level of 333,000 by 201 i in accordance with<br />
the Metroplan. A sensitivity test was carried out for<br />
the higher population forecast.<br />
Agreed.<br />
(3)<br />
The assumption in respect of MTR extension should<br />
be mentioned in the context of external network, as<br />
it will form a major component of the transport<br />
infrastructure for Tseung Kwan 0.<br />
Agreed.<br />
(4)<br />
Page<br />
(1)<br />
The traffic and transport impacts to East Kowloon<br />
should be addressed.<br />
TKO Tunnel is said to be "marginally above its<br />
practical capacity" at the top of the page but it<br />
"would be heavily overloaded in the Am peak* in the<br />
middle of the of the page. This appears<br />
inconsistent.<br />
This b contained in the Main Report.<br />
The first comment refers to a scenario which includes the<br />
MTR extension to TKO. The second reference refers to a<br />
scenario which assumes the provision of an MTR link is<br />
delayed beyond 2011.<br />
(2) For clarity sake, I propose to amend the first<br />
sentence in the third paragraph to read :<br />
APH Consultants Appendix: D-28
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
"For the 333,000 population, the western screenline<br />
will operate below capacity if ail planned transport<br />
infrastructure improvements are implemented as<br />
scheduled."<br />
Furthermore do the external links mentioned in the<br />
second sentence refer to the western screen <br />
(3) What is the percent change in the level of selfcontainment<br />
(4) How much overloaded would the TKO Tunnel in the<br />
AM peak and in what year <br />
(5) In order to highlight the importance of the timely<br />
provision of the Western Coast Road, the finding that<br />
the total screenline would be overloaded by mow<br />
than 30% if WCR is not completed by 2001 should<br />
be added in the fifth paragraph.<br />
(6) Po Lam Road is a steep road and runs through major<br />
residential areas. It is clearly undesirable for<br />
dangerous goods traffic to use this road. The fifth<br />
paragraph should be amended accordingly.<br />
(7) In the evaluation of the Western Coast Road<br />
connections, can the effects of either options upon<br />
the existing land uses be described as marginal <br />
(8) The potential impacts of the possible delay to the<br />
implementation of Western Coast Road and the MTR<br />
extension, which have been studied in some depth,<br />
should be presented in the Executive Summary. The<br />
timely provision of these transport facilities is critical<br />
to the development of Tseung Kwan O including<br />
Area 137. More specifically, the findings in Tables<br />
7.17 and 7.IS of the Main Report should be<br />
incorporated in the Executive Summary.<br />
Agreed.<br />
Agreed.<br />
The analysis was carried out for a 20% reduction in selfcontainment.<br />
If the MTR extension were delayed beyond the 2011 year,<br />
then the TKO tunnel would become overloaded in the period<br />
between 2006-2011.<br />
Agreed.<br />
Agreed, but there is no legal alternative road for certain<br />
categories of dangerous goods.<br />
The text refers to marginal additional effects on land uses of<br />
Option B.<br />
Agreed* text will be amended.<br />
(1) The second paragraph does not appear to be true as<br />
far as the Western Coast Road connections in the<br />
East Kowloon are concerned.<br />
(2) The issue of how practical the proposal in the third<br />
paragraph would be in terms of feasibility and timing<br />
should be addressed.<br />
This paragraph reefers specifically to Area 137 which is the<br />
main subject of the Study*<br />
As stated, it is essential that an early decision is reached and<br />
the road constructed.<br />
B. Draft Final Report<br />
Section 2 Planning Base<br />
Para 2.2.1 What are I(A), I(B) and I(C) Brief<br />
descriptions should be given.<br />
(1) Why is the MTR extension not<br />
mentioned <br />
(2) The different planning horizon<br />
should also be given.<br />
These are standard terms used within Government to<br />
describe different classes of industry and development.<br />
The MTR link inflneneces the growth of TKO and indirectly<br />
that of Area 137. Note reference to MTR link in para 2 J.I.<br />
The different planning horizons cannot be defined at this<br />
stage beyond stating that there is early demand for PHI sites.<br />
The remainder of the horizons will be dictated by the future<br />
take up of sites within Area 137.<br />
APH Consultants Appendix D~29
Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Section 4 Land Use Planning<br />
Table 4.1 The total number of workers should be shown in the<br />
table.<br />
Noted. Total will be giYen.<br />
Section 7 Traffic and Transport Study<br />
Para 7.1.1 (1) While the transport modelling<br />
methodology is based on CTS-2, the<br />
planing data adopted should be confirmed<br />
by Planning Department rather than just<br />
simply inferred from a transport model.<br />
It should also be noted that the original<br />
metropian data are continuously being<br />
updated.<br />
(2) What is the effect (in percentage terms) of<br />
the minor variation in the degree of<br />
vacancy and take-up of flats on the<br />
population forecasts <br />
(3) If the forecast employment rate is prone<br />
to higher error, the external traffic to and<br />
from TKO will be greater since less jobs<br />
available in TKO would mean more<br />
people travelling to the urban areas. The<br />
consultant should carry out a sensitivity<br />
test to investigate the effect of this.<br />
From a regional perspective, the ultimate<br />
design population of 440,000 by 2011<br />
should be taken into account in planning<br />
for adequate road capacity. In this<br />
connection, I must state our position that<br />
the pace and scale of development should<br />
be compatible with the transport<br />
infrastructure available.<br />
(2) The forecast population for Sai Kung<br />
shows a decreasing trend which is<br />
illogical and inconsistent with ongoing<br />
development proposals and observed<br />
increasing traffic flows.<br />
(3) Presumably the forecast for CWB of '99*<br />
for 1996 was typed wrongly.<br />
Para 1.2 &<br />
(1) To tie in with the development<br />
programme for Area 137, Road PI<br />
between Tl and D4 should also be<br />
brought forward to 1996 such that the<br />
industrial traffic could avoid the Hang<br />
Haix Area. Furthermore, as commented<br />
before, D6 should be completed up to<br />
LS71 junction by 1996.<br />
(2) Why are TKO Tunnel and Hang Hau<br />
Road depicted as completion by 2011 in<br />
Rgure : The quality of this figure should<br />
be improved.<br />
Agreed. The input planning data assumptions are<br />
documented in the modelling report.<br />
Vacancy is assumed to be between 5% and 7%.<br />
This has been examined in an alternative way by lowering<br />
self-containment.<br />
This is a matter of planning policy as to the number of<br />
residents in TKO.<br />
This comment would be better answered by Planning<br />
Department. However, in tae context of the current Study,<br />
the majority of traffic from Sai Kung is assumed to use<br />
CWB rather than pass through TKO.<br />
Agreed. The correct figure is 19. Table will be amended.<br />
Agreed. Text will be expanded.<br />
Figure will be amended.<br />
APH Consultants<br />
Appendix D-3Q
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
To supplement Table 7.4. a plan showing<br />
the zoning and developing layout in Area<br />
137 should be included.<br />
(2) More details about the Survey from the<br />
trip rates in Table 7.3 are derived should<br />
be provided.<br />
(3) The Consultant should elaborate on how<br />
the travel patterns shown in Figure 7.2<br />
are obtained.<br />
(4) & Table 7.6, the forecast "private* traffic<br />
appears low. What is the unit for this<br />
table Does the figure include buses,<br />
coaches, taxis etc The composition<br />
showing just "private" and "goods" traffic<br />
is too crude.<br />
Para 7 2.2 (1) It would be illustrative to present<br />
graphically the screeniine described in the<br />
second sub-paragraph. The screeniine<br />
referred to in the second sub-paragraph<br />
should be specified. Likewise, a plan to<br />
indicate the proposed improvements in<br />
Yau Tong area should also be provided.<br />
(2) Would the proposed improvements in Yau<br />
Tong area be funded and carried out by<br />
TDD in connection with the construction<br />
of WCR By copy of this letter,<br />
PM/SENT is invited to comment.<br />
(3) Did the consultant assume the Option B of<br />
WCR connection in deriving the figures<br />
" in Table 7.7 Why is there a general<br />
reduction in the traffic figures when<br />
compared with table 6.1 and table 6.2 of<br />
woricing paper no. 9 What changes<br />
bring about the reduction<br />
To support the conclusion that the<br />
Western Coastal Road (WCR) is to be in<br />
operation in 2001, it is necessary to<br />
include WCR in the network and to<br />
produce the forecast of the daily, AM and<br />
PM traffic volumes in 2001 on WCR,<br />
TKO Tunnel and Po Lam Road. These<br />
traffic forecasts should be used to justify<br />
the aeed for WCR.<br />
(2) The traffic forecasts in Tables 7.8 and 7.9<br />
clearly demonstrated the need for WCR<br />
by 2001 since both the TKO Tunnel and<br />
the total screeniine would be overloaded<br />
by 39% and 32% respectively. There<br />
will be no choice of routes left for the<br />
motorists* This couples with the almost<br />
equal east and westbound traffic will<br />
make any traffic management scheme<br />
such as tidal flow futile.<br />
Noted.<br />
Noted. Text wffl b« amended to include mention of the sites<br />
surreyed.<br />
The text will be expanded. The traffic from A137 is assumed<br />
to hare the same pattern as other traffk from TKO of the<br />
same vehicle type*<br />
Private vehicles includes taxis, cars and the special purpose<br />
buses. Vehicles operating franchise*! routes are not shown<br />
on this table.<br />
Noted. Text will be expanded.<br />
PM(SENT) to advise.<br />
Option B has been assumed as it is the preferred alignment.<br />
Working Paper No. 9 contains the traffic figures prior to the<br />
preferred concept and the revision in land use assumptions<br />
arising from the more detailed analysis.<br />
This has been carried out and a paragraph to support the<br />
need for WCR on 2001 will be produced.<br />
Agreed. However this must contain the proviso of "if TKO<br />
develops as currently planned, and the industrial<br />
developments are in place 11 .<br />
APH Consultants Appendix D-31
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(3) It appears desirable to include in die 2001<br />
scenario a test for having one carriageway<br />
of WCR. I suspect this could help<br />
demonstrate the need of WCR by 2001 -<br />
with the first carriageway only or with the<br />
full dual three carriageway.<br />
(4) Why is there no assessment on the traffic<br />
conditions along Hang Hau Road and<br />
Clearway Bay Road <br />
(5) The traffic forecasts indicate that the<br />
westbound (Kowloon Bound) traffic is<br />
lower than the eastbound traffic in the<br />
AM peak and vice versa in the PM peak.<br />
However, they are in contradiction with<br />
the existing traffic patterns where the<br />
westbound traffic is about 50% higher<br />
than the eastbound traffic in the AM peak<br />
and the latter is about 35% higher than<br />
the westbound traffic in the PM peak for<br />
both Po Lam Road and TKO Tunnel.<br />
The Consultants are requested to clarify<br />
the major differences in traffic patterns<br />
and make any necessary model validation<br />
and amendments.<br />
(6) Please check the 2006 forecast of the PM<br />
eastbound traffic for TKO Tunnel in<br />
Table 7.9.<br />
(7) As regards the TKO tunnel congestion<br />
problem, the conditions of the vicinity of<br />
the tunnel should be mentioned.<br />
(8) The Western Coast Road should be<br />
viewed as critical to the development of<br />
TKO including Area 137.<br />
Para 7.2.4 (1) The choice of 20% reduction in selfcontainment<br />
was explained in response to<br />
a comment from the Planning<br />
Department. This should be included in<br />
this section.<br />
The assumption that MTR TKO Extension<br />
would be opened by 2006 is noted.<br />
Could the Consultants advise on the<br />
minimum population threshold that would<br />
support the rail extension and the<br />
maximum population threshold that would<br />
not overload the extension.<br />
This is a matter of implementation to establish whether this<br />
is a viable approach given the short time span between the<br />
opening of one carriageway and the time when both are<br />
required. Given the non-directional nature of the traffic as<br />
currently forecast, there would be operational problem with<br />
this configuration.<br />
Some comments win be included, bat it should be noted that<br />
there are questions over the planning data underlying the<br />
traffic forecasts for this corridor, and it is not the main focus<br />
of the study.<br />
The traffic forecasts come directly from Government's own<br />
traffic projections. It should be noted that the scale of<br />
future development is very different from that currently<br />
existing in Tseung Kwan 0. The Consultants compared the<br />
1991 figures from the model and observed flows; these are<br />
reported in the Technical Note on Modelling.<br />
This Table includes under the Base column traffic figures<br />
arising from the land use prior to the preferred concept;<br />
these will be amended to reflect the final figures.<br />
Text will be amended.<br />
Noted.<br />
Agreed.<br />
Whilst interesting questions, these are outside the Study<br />
Brief.<br />
(2)<br />
Apart from the problems and difficulties<br />
as mentioned in this paragraph regarding<br />
the non-provision of MTR, the local<br />
sentiments should be taken into account.<br />
There will be strong political pressure for<br />
the MTR Extension.<br />
Agreed. This is a matter of policy.<br />
APH Consultants Appendix D-32
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(3)<br />
(4)<br />
(2)<br />
(3)<br />
(4)<br />
(5)<br />
(6)<br />
(7)<br />
Are the "600 extra pcus" mentioned in the<br />
second sub-paragraph all bus trips In<br />
the same sub-paragraph, what is the<br />
resulting v/c ratio if the extra traffic is<br />
taken into account<br />
Can the problems mentioned in the third<br />
sub-paragraph such as bus congestion in<br />
TKO and Kwun Tong and interchange<br />
problems be quantified <br />
What is the unit for Table 7.11 <br />
The Consultants should explain why the<br />
traffic forecast for Po Lam Road would<br />
decrease (rather than increase) as a result<br />
of higher population based on the SENT<br />
Development Programme.<br />
It ts doubtful that an increase in<br />
population of about 110,000 would<br />
generate only 1100 pcu traffic during the<br />
AM peak. This forecast appears to be too<br />
low.<br />
Furthermore, it must be pointed out<br />
clearly that even with the scteenltne v/c at<br />
1.0 (which corresponds to the design<br />
population of 432,000), the v/c at TKO<br />
Tunnel would probably be still higher<br />
than 1.2 which means severe congestion.<br />
The consultants mentioned that about<br />
2000 pcu's would use the CWB<br />
Road/Hang Hau Road corridor. Please<br />
amplify whether this is one way or two<br />
way flow. What is the expected v/c ratio<br />
along these two road corridors I<br />
envisage that this traffic flow would<br />
overload the existing CWB Road taking<br />
into the account the trips originating in<br />
the CWB peninsula.<br />
What is the MTR assumption for the<br />
forecasts given in Table 7.13.<br />
Do the 2000 pcus mentioned in the 6th<br />
sub-paragraph refer to a daily or peak<br />
hour flow<br />
In addition to Table 7.13, forecasts of<br />
daily and PM peak traffic flows on WCR,<br />
TKO Tunnel and Po Lam Road should<br />
also be presented.<br />
The 600 pcus are buses, TKO tunnel would operate at 1.25<br />
v.c. ratio in 2011 as shown in Table 7.11.<br />
This is a matter for a much more detailed study to assess; it<br />
would have to address pedestrian movements, layouts of the<br />
bus interchanges, etc.<br />
The unit is PCU's; the table heading win be amended.<br />
A revised table will be produced.<br />
The test assumption only included extra population, with ao<br />
further employment, and therefore cannot be compared with,<br />
say, an existing New Town of around 100,000 people as these<br />
normally include some employment. It should be noted as<br />
well that the majority of people leaving TKO in the morning<br />
peak will be in publk transport, and the presence of the<br />
MTR extension has been assumed. Therefore the extra<br />
110,000 people have a low impact on the road volumes for<br />
the external screenline for TKO, given this context.<br />
Agreed.<br />
This is a one way flow and includes the Sai Kung Traffic.<br />
The v/c ratio on CWB east of Hiram's Highway is 1J7, and<br />
0.93 on Hang Hau Road.<br />
The MTR is assumed to be present on both cases shown in<br />
Table 7.13<br />
These are peak hour flows.<br />
The analysis has been restricted to peak conditions.<br />
APH Consultants<br />
Appendix B-J3
Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />
final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(8) Since the vehicle ferry has not been<br />
tested, the consultants should substantiate<br />
how the ferry service can provide the<br />
release to the traffic burden. This<br />
comment also applies to the Executive<br />
Summary.<br />
In examining the traffic impact in the<br />
Area of Influence, the Consultants should<br />
also look Into the impact on the critical<br />
junctions in East Kowloon and Kwun<br />
Tong which would be the main capacity<br />
constraints to the proposed WCR and<br />
would be adversely affected by the<br />
additional traffic generated.<br />
(2) In Table 7.14, why are there no v/c<br />
figures for Hiram's Highway To which<br />
sections of CWB Road and New CWB<br />
Road does this table refer The most<br />
critical section of CWB Road within the<br />
Area of Influence would be the one<br />
between Hang Hau Road and University<br />
Road, which is currently a single<br />
carriageway.<br />
Should Total Traffic - MTR open in<br />
2001" in Table 7.16 read Total Traffic -<br />
MTR open in 2006" <br />
(2) Table 7 16 demonstrates that even with<br />
MTR in 2006 the "without WCR"<br />
scenario would still result in a v/c ratio of<br />
about 1.43 which is totally unacceptable.<br />
(3) The consultant should assess the scenario<br />
of having no Area 131, 137 development<br />
but with full metroplan population and<br />
100% other industrial development. I<br />
envisage that this scenario could help<br />
demonstrate the need for WCR by 2001 if<br />
developments in Area 131/137 are to<br />
proceed.<br />
(4) Surely, B3 and B7 in Table 7.17 would<br />
lead to strong criticism from the pubic<br />
that the Government allows their<br />
"preferred" developments to proceed but<br />
at the same time limiting participation of<br />
the private sector.<br />
(5) The forecasts of the daily* AM and PM<br />
traffic flows on WCR, TKO Tunnel and<br />
Po Lam Road for the scenarios of delay<br />
of WCR in 2006 and 2011 should be<br />
presented.<br />
(6*) As regards the second sub-paragraph on<br />
page 7-15, the combination of MTR and<br />
no Western Coast Road is a possible<br />
option.<br />
The TKOFSOFD examined the vehicle ferry and suggested<br />
it could attract about 200 pens per hour. Whilst this study<br />
has not examined this service in detail, if the route could<br />
attract 200 pcus it would assist in reducing the screenline<br />
over capacity and would attract some vehicles given the<br />
condition of near-congestion on the external road links.<br />
The modelling of the Area of Influence considered junction<br />
capacity in calculating the We ratios shown in Table 7.14.<br />
The traffic from Area 137 disperses widely over the external<br />
network. The impact of WCR on individual junction design<br />
on East Kowloon is outside the Brief.<br />
V/C ratios for Hiram's Highway will be added to the table.<br />
However it must he noted that this is at the edge of the Study<br />
Area and there is some question on the realism of the<br />
planning assumptions for Sai Kung.<br />
Agreed.<br />
Agreed.<br />
This conclusion is shown by the source of traffic shown in<br />
the first column of Table 7.16.<br />
Agreed.<br />
The scenario exercise reported in Section 7.2.9 has been<br />
developed as a sensitivity test and such figures are not<br />
available.<br />
Whilst physically possible, the lack of the WCR would limit<br />
development, and in such circumstances it may well be that<br />
the MTR would not be such an attractive investment. In<br />
deciding the priority between MTR and WCR in attracting<br />
funds, the potential for WCR serving ail sections of travel<br />
demand inchiffamy commercial movements must be borne ui<br />
mind*<br />
APHConsultants Appendix D-34
Engineering Feasibility Study of Development ofTseung Kyvan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Para 7.2.10 (1)<br />
The Consultant may consider to amplify<br />
the first finding on WCR after assessing<br />
my comment (3) on para. 7.2.9 above.<br />
The construction of WCR by 2001 should<br />
be considered as a p re-requisite of<br />
allowing the Area 137/131 development.<br />
It is the presence of other industrial developments which<br />
require the WCR by 2001.<br />
(2) Presumably the S3 toll for TKO Tunnel in<br />
respect of the second finding refers to the<br />
1991 price. Furthermore, as the<br />
problems occur in peak hours only,<br />
differential tolls may be more appropriate.<br />
(3) As regards the 4th finding, the wording<br />
should be amended such that without the<br />
MTR Extension the TKO Tunnel would<br />
result in further congestion. The original<br />
wording is misleading as it seems to<br />
suggest that the heavily overloaded<br />
situation is due solely to the lack of the<br />
MTR extension. This is not the actual<br />
case. As the base v/c ratio is forecast to<br />
be 1.16 TKO Tunnel is already<br />
overloaded.<br />
(4) Please add "design" before "population of<br />
440,000" in the second last finding.<br />
Furthermore, I have reservation on this<br />
finding since there is no amplification on<br />
what improvements, at what scale, would<br />
the Hang Hau corridor be improved. As<br />
commented above, the forecast population<br />
in Sai Kung was underestimated. This<br />
would result in lower estimates of trips on<br />
Hiram's Highway and CWB Road. Has<br />
MTR extension been assumed for this<br />
finding <br />
It is considered desirable to indicate the<br />
road width of fig 7.4 in accordance with<br />
section 5.6 of the report. The possible<br />
future extension of Road D6 eastward<br />
should be shown and a suitable reserve<br />
maintained.<br />
The tolls are in fact in 1990 prices. Noted, although it has<br />
not yet been implemented in Hong Kong.<br />
Agreed.<br />
Agreed. The improvements to Hang Hau are these assumed<br />
in the TKO Development Programme. The Sai Kung<br />
population is a matter for discussion with Planning<br />
Department. The MTR is assumed to be present from 2006<br />
onward.<br />
Noted.<br />
Para 7,3.2 (1) This paragraph assess the traffic<br />
conditions in various design years with<br />
the assumption that WCR would be<br />
completed by 2001. However, this seems<br />
not consistent with the previous sections<br />
in this chapter that "in order to critically<br />
examine the timing of provision of WCR<br />
it has been assumed to be deferred until<br />
2006* (see para. 7.1.2). Though t fully<br />
support the inclusion of the assessment as<br />
presented {i.e. with WCR by 2001), it is<br />
considered necessary to show the<br />
"without" scenario in the 2001 year. I<br />
envisage there will be severe congestion<br />
in the internal road system and large scale<br />
improvements would be required.<br />
The last line of 5th para of 7.1.2 is misleading. The<br />
junctions hare been evaluated on the assumption that WCR<br />
is present from 2001. Earlier working papers examined year<br />
2001 without WCR. Notwithstanding the screenline links<br />
will be overloaded in 2001 without the WCR and the road<br />
network would not be able to perform adequately.<br />
APH Consultants<br />
Appendix D-J5
Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
(2) It if desirable to show the various v/c<br />
ratios on plans corresponding to fig. 7.7,<br />
7.9 and7.il.<br />
Noted.<br />
(3) It seems chat there is no assessment on the<br />
junctions T1/P1/P2 and P2/D4 (2001<br />
year). These two are grade separated<br />
junctions.<br />
(4) The report should include plans to show<br />
the recommended junction Improvements<br />
at S3 and R4. In the assessment of R4,<br />
did the consultant include the flyover on<br />
PI At what year is the flyover assumed<br />
to be built Consideration should be<br />
given to junctions SI, S2, S3, S4 and S5<br />
being roundabouts which would probably<br />
have a higher reserve capacity than<br />
signalised junctions.<br />
(5) I think R3 in Table 7.15 and 7.17 should<br />
be junction D9/P2 instead of D9/D3.<br />
(6) I would like to see the detailed junction<br />
assessments for all design years instead of<br />
only 2011. Please submit them direct to<br />
Traffic Engineering (NTE) Division of<br />
this Department for checking.<br />
(7) It appears that Table 7.15 and 7.17 in this<br />
section should read 7.19 and 7.21.<br />
(8) The design v/c ratio for roundabouts<br />
should not exceed 0.35. In Tables 7.15,<br />
7.16 and 7.17, roundabouts with v/c<br />
ratios in excess of this value would<br />
require improvement measures.<br />
Para 7 4 (1) Please amplify which residential area is<br />
referred to and where the small bus<br />
terminus is. Also I assume "Area 314"<br />
should be "Area 3/4".<br />
Assessment win be included.<br />
Junction improvement schemes for S3 and R4 are described<br />
in the tact and proposed plans have been given to Transport<br />
Department. The flyover on PI was included in the<br />
assessment of R4. The flyover is assumed to be completed<br />
by 2001 as currently planned. The junction control for SI,<br />
§2, S3 and S4 and S5 are as currently planned.<br />
Agreed.<br />
These have been supplied to Transport Department.<br />
Tables will be amended accordingly.<br />
Noted. The v/c ratios given in Tables 7.15, 7.16 and 7.17<br />
are based on ARC AD Y models for the worst 15 minutes<br />
interval in the peak period. V/C ratios based on hourly<br />
figures will be given.<br />
The residential area is Area 78 and the bus terminal in Area<br />
86". Area 314 should be Area 3/4.<br />
Section S Western Coast Road<br />
Para 8.4 (1) Table S.I shows that Lei Yue Mun Road<br />
attracted more traffic in Option B than<br />
Option A. This should not be the case<br />
since the WCR is only connected to Lei<br />
Yue Mun Road in Option A. The same<br />
query is applicable to Cha Kwo Ling<br />
Road.<br />
(2) The evaluation in respect of traffic and<br />
roads contained here is too brief. The<br />
evaluation analysis given in Section 6.2<br />
(such as Table 6.2, Table 6.6 and Para.<br />
6.2.6) of the Working Paper No. 9 on<br />
"Western Coast Road Connection" should<br />
be included and discussed here.<br />
Moreover, the adverse traffic impacts<br />
caused by both options to the local road<br />
network downstream of the WCR in the<br />
The Lei Yue Mun Road is connected to the WCR under both<br />
Option A and Option B, as is Cha Kwo Ling Road.<br />
However the location of the connection is different for the<br />
two options, see Figures. 8.1 and 8.2.<br />
The traffic evaluation relating to the requirement for the<br />
WCR together with various sensitivity tests is covered in the<br />
Traffic and Transport Study in Section 7 of the Report, as<br />
is the requirement for improvements in the Yau Tong area.<br />
Text will he expanded to clarify this.<br />
APH Consultants Appendix D-36
Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />
Final Report - Main Report<br />
COMMENTS<br />
RESPONSES<br />
Yau Tong and Kwun Tong area should be<br />
mentioned.<br />
Para 8.7 (1) For comparison, cost breakdowns for the<br />
two Options should be presented.<br />
Para. 8.8 (1) The need for the further study on the<br />
preferred alignment is appreciated. In<br />
view of the adverse impacts on land use<br />
and environment, and the critical role of<br />
the WCR in providing an essential<br />
external link for the further development<br />
of Tseung Kwan O including Areas 131<br />
and 137, this point should be highlighted<br />
with sufficient clarifications.<br />
Furthermore, the further study should be<br />
carried out to confirm the engineering<br />
feasibility should full development of<br />
TKO be contemplated. Such information<br />
should also be included in the Executive<br />
Summary.<br />
The cost breakdowns as included in Working Paper 9 A will<br />
be included.<br />
It is considered that the critical need for the WCR has been<br />
sufficiently highlighted in Section 7. The purpose of Section<br />
3 was to present the findings of the comparative evaluation<br />
of the two proposed connections only.<br />
Section 10 Implementation<br />
Para 10.5<br />
Necessary improvements to the internal roads and<br />
ihe areas of influence should also be included.<br />
Text will be amended to include required<br />
improvements/impikations for junctions and area of<br />
influence.<br />
URBAN SERVICES DEPARTMENT<br />
Draft Final Report - Volume I<br />
As previously conveyed to you, this department is more<br />
concerned about the proposed adoption of Option B of the<br />
Western Coast Road Connection, since two large-scale UC<br />
projects namely Sam Ka Tsuen Recreation Ground and Sam Ka<br />
Tsuen Complex, will be adversely affected. Moreover, I am<br />
also concerned about the environmental impacts generated to the<br />
areas close to the road alignments for Option B m view of the<br />
anticipated busy vehicular traffic, in particular the heavy truck<br />
vehicles.<br />
In the light of the additional points raised by District Planning<br />
Officer/Kowloon vide his letter addressed to you dated 23<br />
December 1992, I think, the cost comparison for the two<br />
schemes i.e. Option A & B as stated in para. 8.7 of the Draft<br />
Final Report - Volume I, should be revised to reflect fully all<br />
relevant factors tor consideration by the Steering Group before<br />
a final decision is taken.<br />
Reference should be made to responses to DPO/K.<br />
APR Consultants Appendix D-37