27.01.2015 Views

J - HKU Libraries

J - HKU Libraries

J - HKU Libraries

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

TERRITORY DEVELOPMENT DEPARTMENT<br />

SOUTH EAST NEW TERRITORIES DEVELOPMENT OFFICE<br />

Agreement No. CE 59/90<br />

ENGINEERING FEASIBILITY STUDY<br />

OF DEVELOPMENT OF<br />

TSEUNG KWAN O AREA 137<br />

Final Report<br />

EXECUTIVE SUMMARY<br />

MAIN REPORT<br />

DRAWINGS<br />

March 1993<br />

APH CONSULTANTS<br />

Acer Consultants (Far East) Ltd.<br />

Au Posford Consultants Ltd.<br />

Frederick R. Harris (Far East) Ltd.<br />

in association with<br />

UrbisTravers Morgan Ltd.<br />

MVA Asia Ltd.


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

ENGINEERING FEASIBILITY STUDY OF DEVELOPMENT OF<br />

TSEUNG KWAN O AREA 137<br />

MAIN REPORT<br />

CONTENTS<br />

Section<br />

Page<br />

INTRODUCTION<br />

1.1 Background<br />

1.2 Study Objectives<br />

1.3 Study Stages<br />

1.4 Report Structure<br />

1 . 5 Acknowledgement<br />

PLANNING BASE<br />

2.1 The Study Area<br />

2.2 Planning Context of Study Area<br />

2.3 Interfaces and Constraints<br />

THE PREFERRED CONCEPT<br />

3.1 Planning Background<br />

3.2 Alternative Concepts<br />

3.3 Risk Assessment of PHI Industries<br />

3.4 Preferred Concept<br />

LAND USE PLANNING<br />

4.1 Detailed Planning Layouts<br />

4.2 PHI and PHI Related Development<br />

4.3 DWI Development<br />

4.4 Supporting Development and Facilities<br />

4.5 Provision of Berthing Facilities<br />

4.6 Landscaping<br />

M<br />

1-1<br />

1-2<br />

1-2<br />

1-3<br />

2-1<br />

2-1<br />

2-3<br />

3-1<br />

3-1<br />

3-3<br />

3-7<br />

4-1<br />

4-1<br />

4-3<br />

4-4<br />

4-6<br />

AfH Consultants Page 1


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

5 ENGINEERING STUDIES<br />

5.1 Engineering Investigations<br />

5.2 Land Formation.<br />

5.3 Edge Structures<br />

5.4 Fill Requirements and Sources<br />

5.5 Dredging Requirements and Disposal<br />

5.6 Cavern Development<br />

5.7 Highways and Roads<br />

5.8 Stormwater Drainage<br />

5.9 Water Supply<br />

5.10 Sewerage<br />

5.11 Public Utilities<br />

6 MARINE STUDY<br />

6.1 Introduction<br />

6.2 Marine Traffic<br />

6.3 Ship Handling Operations<br />

6.4 Interaction Effects of Passing Ships<br />

6.5 Downtime Considerations<br />

6.6 Pilotage and Aids to Navigation<br />

6.7 Anchorages<br />

6.8 Navigational Risk and Vessel Traffic Control<br />

7 TRAFFIC AND TRANSPORT STUDY<br />

7.1 Traffic Forecasts<br />

7.2 The External Network<br />

7.3 Internal Road Network<br />

7.4 Public Transport Requirements<br />

8 WESTERN COAST ROAD<br />

8.1 Introduction<br />

8.2 Western Coast Road Connections<br />

8.3 Evaluation of Options<br />

8.4 Traffic and Roads<br />

8.5 Land Use Impacts<br />

8.6 Environmental Impacts<br />

8.7 Cost Comparison<br />

8.8 Evaluation Summary<br />

5-1<br />

5-5<br />

5-7<br />

5-10<br />

5-10<br />

5-11<br />

5-11<br />

5-12<br />

5-13<br />

5-15<br />

5-17<br />

6-1<br />

6-1<br />

6-3<br />

6-5<br />

6-6<br />

6-9<br />

6-9<br />

6-10<br />

7-1<br />

7-6<br />

7-17<br />

7-22<br />

8-1<br />

8-1<br />

8-2<br />

8-2<br />

8-3<br />

8-7<br />

8-13<br />

8- 15<br />

APH Consultants 2


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

9 ENVIRONMENTAL ASSESSMENT<br />

9.1 Introduction<br />

9.2 Key Impact Sources and Sensitive Receivers<br />

9.3 Water Quality<br />

9.4 Air Quality<br />

9.5 Noise<br />

9.6 Waste Management<br />

9.7 Visual Impact and Glare Nuisance<br />

9.8 Environmental Monitoring and Audit Schedules<br />

10 IMPLEMENTATION<br />

10.1 Introduction<br />

10.2 Preliminaries<br />

10.3 Implementation Schedule<br />

10.4 Capital Expenditure and Revenue Streams<br />

10.5 Study Implications<br />

10.6 Study Findings<br />

9-1<br />

9-1<br />

9-2<br />

9-7<br />

9-10<br />

9-13<br />

9-13<br />

9-18<br />

10-1<br />

10-1<br />

10-2<br />

10-5<br />

10-8<br />

10-9<br />

APPENDIX A STUDY REPORTS AND WORKING PAPERS<br />

APPENDIX B WRITTEN STATEMENTS<br />

APPENDIX C SUGGESTED MODIFICATIONS TO TSEUNG KWAN O ODP<br />

APPENDIX D DRAFT FINAL REPORT COMMENTS AND RESPONSES<br />

APH. Consultants Page 3


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

SECTION 1<br />

INTRODUCTION<br />

1.1 BACKGROUND<br />

The Port and Airport Development Strategy (PADS), October 1989, provides for future growth of port<br />

and air traffic up to 2011 and beyond. The strategy sets out in broad terms development proposals to<br />

support port and airport development as well as to satisfy the forecast strategic demands for industrial<br />

land. Within the PADS context, Area 137, to the south of Tseung Kwan 0 on the eastern side of the bay,<br />

is to be developed for port facilities supporting Deep Waterfront Industries (DWIs) and Potentially<br />

Hazardous Installations (PHIs).<br />

The Final Report of the Tseung Kwan O Feasibility Study of Opportunities for Further Development<br />

outlined two possible links from the proposed Western Coast Road to East Kowloon. It was agreed that<br />

the need for additional transport links for Tseung Kwan O would be considered in the context of the<br />

feasibility study for the proposed development of Areas 131 and 137. In October 1991, the Port Progress<br />

Committee decided that only the Area 137 study should proceed but that the possible future development<br />

of Area 131 should be taken into consideration in the study.<br />

Accordingly, APH Consultants were commissioned in February 1992 to investigate the feasibility of<br />

developing Area 137 forDWI and PHI industries, to assess the likely impacts of such a development and<br />

to produce an outline engineering design and land use plan for the site. The assessments were required<br />

to take into consideration the possible development of Area 131 as a dockyard facility and particular<br />

attention was required to be given to the selection of the Western Coast Road connections.<br />

This Final Report gives details of the recommended development layout and the outline engineering<br />

design. The Report documents the findings of the Study and describes the analysis and considerations<br />

which support the findings. The Final Report consists of three documents, an Executive Summary of the<br />

Study, the Main Report, containing the text of the analysis and the Drawings document, containing the<br />

land use and outline engineering design drawings.<br />

1.2 STUDY OBJECTIVES<br />

The prime objective of the Study is to produce an outline engineering design of the recommended layout<br />

for Area 137 in sufficient detail to allow progression to detailed planning and design of the development.<br />

Major issues required to be examined under the Brief include:<br />

> an assessment of land use demand and constraints and the development of a land use plan,<br />

together with infrastructure requirements;<br />

* engineering solutions for the reclamation of the site and determination of a berth layout*<br />

compatible with user demand and providing safe and efficient marine traffic arrangements;<br />

> assessment of traffic and transport impacts and the provision of transport infrastructure, both<br />

within and outside the area of development;<br />

> marine and environmental impacts of the development;<br />

* outline design for the provision of services and utilities to the site;<br />

APH Consultants Page 1-


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

> preparation of a development programme together with revenue and expenditure forecasts.<br />

Of particular concern is the interface with the SENT Landfill and the Tseung Kwan O Industrial Estate<br />

(TKOEE) to the north of the Site. The development of Area 137 also has to be incorporated into the<br />

framework of overall strategic development and planning requirements of the area.<br />

1.3 STUDY STAGES<br />

The Study has been carried out in three main stages:<br />

The Alternative Concepts Stage, reviewed the existing background data and determined the level of<br />

potential interest in the site to enable the first conceptual plans to be drawn up. These were then evaluated<br />

and two alternatives selected for development and refinement within the next stage.<br />

The Preferred Concept Stage, the selected''layouts were subjected to detailed assessments including<br />

WAHMO and ship manoeuvring modelling and environmental assessments of the impacts associated with<br />

the development. On the basis of this, the Preferred Concept was identified.<br />

The Final Stage, completed all required evaluations and studies and defined the Recommended<br />

Development Layout including implementation programming.<br />

Each of the above stages was completed with the preparation of a Report, with the last stage being covered<br />

by this Final Report for the Study. In addition a total of nine working papers have been produced during<br />

the course of the Study covering the major issues and a schedule of these documents is provided in<br />

Appendix A.<br />

1.4 REPORT STRUCTURE<br />

This document presents the recommended development layout for Area 137 together with the findings of<br />

the Study in support of its selection. In so doing, the Report draws on the detailed information and<br />

assessments contained in the previous Study Reports as well as in the Discussion and Working Papers<br />

produced under the Study.<br />

Section 2, Planning Base, describes the Study Area and provides the planning context within which the<br />

proposed development has been accommodated. Constraints which affect the development of the site are<br />

also established.<br />

Section 3, the Preferred Concept, describes the stages leading up to the selection of the Recommended<br />

Development Layout. The rationale behind the selection of this layout is given together with the<br />

engineering and planning issues and constraints which underlie the concept.<br />

The subsequent Sections (4 to 9) give details of the studies that have been undertaken for the proposed<br />

development. These studies are:<br />

> Land Use Study, detailing the envisaged DWI and PHI industries and supporting facilities, risk<br />

assessment and landscaping proposals;<br />

+ Engineering Considerations, including land formation, marine structures, site road network and<br />

provision of services and utilities;<br />

APH Conmitaats


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

final Report - Main Report<br />

> Marine Study, in which the suitability of the berthing arrangements and marine traffic safety<br />

issues are addressed;<br />

> Traffic and Transport Study, which assesses the internal and external road network and traffic<br />

impacts on these roads;<br />

> The Western Coast Road connection;<br />

> Environmental Aspects which considers the relevant issues arising from the environmental<br />

assessment, including impacts and mitigation measures as well as monitoring and audit<br />

requirements.<br />

Finally, in Section 10, the development phasing and implementation issues are discussed and revenues and<br />

cash flows estimated.<br />

1.5 ACKNOWLEDGEMENT<br />

The Study Team wish to express their gratitude to all in Government and the private sector who have<br />

provided assistance or advice during the course of the Study. Thanks are especially due to the members<br />

of the Steering and Working Groups, PM SENT and the staff of the Territory Development Department,<br />

South East New Territories Development Office. All have assisted the Team in a supportive and positive<br />

manner which has made a major contribution to the Study work and progress.<br />

APH Consultants Pag* 1-


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

SECTION 2<br />

PLANNING BASE<br />

2.1 THE STUDY AREA<br />

Area 137 is located almost 8 km southeast ofTseung Kwan O New Town, at the entrance to the Tseung<br />

Kwan O bay. Figure 2.1 indicates the Study Area and land use as covered by the Tseung Kwan O ODP,<br />

The implementation of Area 137 will require the reclamation of an area of open sea between Fat Tong<br />

Chau (Junk Island) and Tit Cham Chau. Once formed, the site will abut the Clearwater Bay Country Park<br />

to the east. The Park is a designated country park which is governed by a series of regulations structured<br />

to conserve its natural features and amenity. To the north of the site, Fat Tong Chau is being partially<br />

excavated to provide reclamation material for the Tseung Kwan O Industrial Estate (TKOIE). The<br />

proposed SENT Landfill site, to the southeast of the TKOIE, demarcates the northeast boundary of Area<br />

137.<br />

To the west of the site, the Tathong Channel separates Area 137 from Hong Kong Island and Chai Wan.<br />

This channel, which has a Traffic Separation Scheme, provides access to Victoria Harbour from the east.<br />

2.2 PLANNING CONTEXT OF STUDY AREA<br />

2.2.1 Tseung Kwan O Outline Development Plan (ODP)<br />

Subsequent to the endorsement of the Tseung Kwan O New Town Study by the Land Development Policy<br />

Committee (LDPC) in July 1982, the Executive Council approved in principle the development ofTseung<br />

Kwan O into a New Town. The Tseung Kwan O New Town Outline Development Plan (ODP) was<br />

approved by LDPC in August 1983 as a basis for the overall development.<br />

Throughout the 1980*s several revised OOP's were prepared and approved to reflect and encompass the<br />

findings of various studies which were undertaken in relation to specific aspects of the New Town<br />

Development and with respect to physical changes which had an impact on planning intentions for the<br />

area.<br />

The latest ODP was approved by the Development Progress Committee (DPC) in November 1990 and<br />

provides the planning context for the present Study area.<br />

The ODP proposes that residential and town centre development will be concentrated on existing and<br />

reclaimed land at the head of the Tseung Kwan O bay. Almost 20% of the total land use budget is given<br />

to residential and commercial/residential development. The achievement of the target population of<br />

440,000 is largely dependent on the upgrading of transport links to the N"ew Town. These include the<br />

construction of the Western Coast Road and the development of a MTR link. Anticipated population<br />

thresholds may not therefore be achieved within the timescale anticipated by the ODP if transport<br />

connections are not upgraded when and as expected. Furthermore, the absence of new transport links may<br />

constrain the efficient passage of products from Area 137.<br />

The ODP proposes that industrial development will comprise almost 22% of the total land use budget and<br />

will be confined to sites south east of the New Town, separated from residential development by the<br />

Tseung Kwan O Stage 1 Landfill.<br />

APH Consultants Page 2-1


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

Industrial development I(A) (high density high intensity commonly associated with flatted factory type<br />

development) is proposed immediately south of the Stage I Landfill. Adjacent to this area is the Tseung<br />

Kwan O Sewage Treatment Works. An interim upgrading of the plant is scheduled to commence in late<br />

1993. On completion in mid 1995, the additional facilities will be able to cope with the effluent generated<br />

by the TKOEE. Additional effluent generated by development in Tseung Kwan O will require further<br />

upgrading of the plant. Further south, reclamation is underway for the TKOIE. The site is being<br />

developed in two phases and will provide for I(B) class industries. Inland from the TKOIE is the site of<br />

the SENT Landfill, for which marine access is provided from the south, through Area 137.<br />

Further to the findings of PADS, the ODP incorporated a recommendation that Area 137 be reserved for<br />

DWI including a site amounting to almost 20 ha reserved for the estimated demand for PHIs. The<br />

relatively isolated location of the site and the availability of deep water, renders the site well suited to<br />

DWI and PHI use. The site will not only provide new industrial lots but will also provide for the removal<br />

of existing installations which, by virtue of the processes they utilise, are incompatible with adjacent land<br />

uses in existing Urban Areas. Area 137 is zoned for I(B) (typically low density land extensive industries<br />

which normally have special site and technological requirements) and I(C) (industries normally comprising<br />

warehousing, bulk storage and dangerous goods storage developments) purposes under the operative ODP<br />

which will allow for the development of land extensive industry and premises for warehousing or storage.<br />

2.2.2 The Port and Airport Development Strategy (PADS)<br />

The PADS Development Statement No.5 'Tseung Kwan O Port Development" sets out the requirements<br />

which are to be met by the proposed port facilities in Tseung Kwan O. The Development Statement was<br />

endorsed by the LDPC in August 1990 as a basis for detailed development study.<br />

An implementation programme for the site was defined which proposed that site formation works in Area<br />

137 should commence in late 1993 to allow availability of sites for Pffl's in early 1995. The PADS<br />

development programme is summarised in Table 2.1.<br />

TABLE 2.1 : PADS DEVELOPMENT PROGRAMME : AREA 137<br />

Development Phase<br />

Potentially Hazardous Installations<br />

Phase 1<br />

Phase 2<br />

Phase 3<br />

Gross Area (ha)<br />

20<br />

30<br />

30<br />

40<br />

Proposed Availability<br />

early 1995<br />

7/1995<br />

4/1996<br />

1/1997<br />

120<br />

Source: PADS Development Statement No.5<br />

The total site area given to Area 137 was subsequently reduced to 108 ha to cater for the southward<br />

expansion of the proposed SENT Landfill.<br />

2.2.3 Planning Issues<br />

The Hong Kong Planning Standards and Guidelines (HKPSG) provide for a maximum average plot ratio<br />

for I(C) industries in New Towns of 5.0. Nevertheless, the range of plot ratios permitted for this category<br />

APH Consultants Page 2-2


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

extends from 3.5 to 9.5. A maximum plot ratio of 2.5 is suggested for I(B) industries in New Towns with<br />

scope for lower plot ratios to be employed as appropriate.<br />

The ODP proposes that plot ratios applied to I(B) and I(C) industrial sites should be 2.5 and 5.0<br />

respectively. The Written Statement does recognize that there may be a need for higher or lower plot<br />

ratios "depending on local circumstances' 1 . In Area 137, where industrial site requirements are likely to<br />

be land extensive, fairly nominal plot ratios may be appropriate due to risk consideration and the nature<br />

of operations which may be undertaken.<br />

The construction of lower density, high technology industries accords well, not only with the provisions<br />

of the HKPSG, but also with Planning Department's recently published Metropolitan Development<br />

Strategy (Metroplan: The Selected Strategy, October 1991). However, low density DWI and PHI<br />

development may have to be encouraged by lower premiums being levied on lease agreements. Without<br />

this incentive it is likely that potential operators would want to locate outside the Territory where land<br />

acquisition costs and development conditions are comparatively less restrictive.<br />

An Outline Zoning Plan (OZP) covering the subject area was gazetted on 11 December 1992. The OZP<br />

will give statutory effect to the land use proposals for the area.<br />

23 INTERFACES AND CONSTRAINTS<br />

23.1 The Tseung Kwan O Industrial Estate (TKOIE)<br />

The TKOIE is being developed in two phases in Area 87, north of Fat Tong Chau. The estate will<br />

ultimately provide for 75 ha of industrial lots on reclaimed land. The first phase is anticipated to be<br />

completed by 1993/94 and the Phase II reclamation by 1995.<br />

Reclamation material within the TKOIE will be retained by rubble revetments. No vertical seawalls are<br />

being constructed, although provision exists for the construction of mooring facilities to be undertaken by<br />

a private developer if required. However, the Hong Kong Industrial Estates Corporation (HKIEC) would<br />

regard this as a private initiative and would not wish to become involved in the management of marine<br />

related facilities.<br />

While the provision of berthing facilities could conceivably put the TKOIE in direct competition with<br />

envisaged DWI lots in Area 137, it is likely that the TKOIE development will be confined to medium<br />

density, high to medium technology, industries. HKIEC specifically prohibits the establishment of any<br />

operation which confines itself to storage or godown operations. Furthermore, lot sizes within the TKOIE<br />

are unlikely to be sufficiently large to meet DWI or PHI spatial requirements. It is considered more likely<br />

that industrial development within TKOIE is likely to be compatible with that on Area 137.<br />

HKIEC have indicated that they are concerned at the interface between industrial sites on the TKOIE and<br />

PHI development on Area 137. The Corporation would be strongly opposed to the construction of any<br />

PHI or dangerous goods facility immediately adjacent to their site, as this may have a significant impact<br />

on the site's viability.<br />

23.2 SENT Landfill<br />

The SENT Landfill is located to the north east of Area 137. The Advance Works Contract is currently<br />

underway and the Landfill is due to be implemented in 1993 with the first waste material being received<br />

in 1994. Twenty percent of all material will be delivered by sea with the balance being delivered by road.<br />

Material to be deposited will include construction waste and treated sludge from Drainage Services<br />

Department's Stonecutters Treatment facility. The latter will be delivered to site by barge. The life of<br />

APH Consultants ~~ r rage 2-


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

the Landfill is dependent on the volume of waste likely to be generated in the Territory and availability<br />

of other landfill sites. Current estimates envisage the Landfill having a minimum life of 8 years and a<br />

maximum life of 20 years, with a probable life of 13 years. During the 30 year aftercare period there will<br />

be ongoing site maintenance and landscaping work as well as collection and treatment of leachate and<br />

landfill gas. The SENT Landfill Contract is programmed to be completed by approximately 2038.<br />

The Advance Works Contract will provide basic site works including a 100 metre quay wall along the<br />

southern perimeter of the landfill site and a seawall extending south from the eastern tip of Fat Tong<br />

Chau. A works area is to be established behind the seawall to provide for the supervision, construction<br />

and maintenance of the Landfill. The alignment of the seawall running south from Fat Tong Chau<br />

coincides with the proposed alignment of Road D6 which is required to provide access to Area 137.<br />

Furthermore, 150 m of quay wall will be required along the seawall to provide moorings for barges<br />

delivering waste and treated sludge to site upon implementation of the Landfill.<br />

The SENT Landfill Contract requires marine access to be maintained throughout the duration of the<br />

Contract, ie until approximately 2038. Reclamation of Area 137 will therefore require the reprovisioning<br />

of the access facilities to a suitable alternative location. Whilst it has been agreed that the SENT Landfill<br />

marine access will be incorporated within Area 137 in the planning of the development, the relocation of<br />

the access outside Area 137 should also be considered in the light of the constraint imposed.<br />

2*33 Physical Constraints<br />

An important element of the planning Brief is that the integrity of existing physical features should be<br />

preserved as far as practicable. The adjacent islands and Clearwater Bay Country Park are important<br />

features or areas of recreational amenity. Careful consideration is therefore required that the character<br />

of these features is not substantially undermined.<br />

This requires appropriate attention to be given to interface treatments which are capable of mitigating both<br />

physical and visual impacts. These aspects have been considered in the preparation of landscape proposals<br />

for the development, particularly at interfaces with sensitive or important landmark features.<br />

Urban design considerations are of similar significance. Defined parameters are required to ensure that<br />

the density, height and composition of industrial development on Area 137 is assembled in a manner<br />

complementary to its surroundings and that on-site industrial interfaces are mutually compatible.<br />

It is important also that the development of the site is undertaken with sensitivity to ensure, as far as<br />

practicable, that visual impacts are attenuated. Of particular concern are the likely visual impacts to<br />

existing and proposed residential development in Chai Wan. Again these can only be reduced through<br />

the application of specific design controls and with the utilisation of appropriate design and landscape<br />

measures.<br />

Finally, a further constraint to the development results from land drainage measures required by the SENT<br />

Landfill, At least two major culverts will discharge initially from the seawall constructed to the south of<br />

the landfill site. These will subsequently require extension through Area 137. Under Drainage Service<br />

Department requirements, no development is permitted on or over culvert reserves.<br />

2.3,4 Access Constraints<br />

Access to Area 137 will be provided via a new district distributor, Road D6, which will function as a<br />

southerly extension of Road PI, serving, in addition to Area 137, Industrial Area 86, TKOIE and the<br />

SENT Landfill site.<br />

APH Consultants Page 2-4


Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

Road PI presently consists of a single carriageway from its junction with Chiu Shun Road (Road D4) to<br />

Area 86. By 1994 it is expected that this route will be extended southwards (as Road D6) to serve<br />

TKOIE. Although D6 will be constructed initially as a single carriageway, a dual 2 lane carriageway is<br />

envisaged with estimated capacity of 6300 pcu^hr. The second carriageway to Road PI is expected to be<br />

constructed by the year 2001.<br />

Road D6 will be constructed initially to a roundabout in the north of the TKOIE to provide access to the<br />

industrial estate. A stub will be provided from which temporary access to the adjacent SENT Landfill site<br />

will be provided. The present proposals as regards the southern extension of D6 are that the section of<br />

road reserve between TKOIE and SENT Landfill up to and including the tip of Fat Tong Chau will be<br />

handed over to the SENT Landfill contractor as a working area once the TKOIE contract works in the area<br />

are complete, anticipated to be mid 1995. The landfill contractor will then complete the formation of this<br />

section of Road D6 and hand the area back to Territory Development Department for the construction of<br />

the road within 12 months of receipt of notice. Completion of the D6 extension to the south of Area 137<br />

would therefore be anticipated by mid 1997.<br />

This Study gives further consideration to the need for junction improvements along route D6/P1 which<br />

is seen as one of the key access routes to Area 137 as it links directly to Tseung Kwan 0 Tunnel and<br />

thence to East Kowloon. In the Tseung Kwan 0 Feasibility Study of Opportunities for Further<br />

Development (TKOFSOFD) the question of access to Tseung Kwan O from the urban area was examined.<br />

Options to provide additional road capacity were evaluated, and as a result a recommendation was made<br />

that a Western Coast Road link should be provided. For Area 137 the Western Coast Road combined with<br />

the proposed Cross-Bay Bridge (Road D9), is seen as the other key access route to East Kowloon,<br />

particularly if the Western Coast Road links up with the Kai Tak Connector. The nature of traffic<br />

generated by the proposed DWIs and Pffls within Area 137 is such that it is desirable to confine this<br />

traffic to high standard expressway routes. These routes, which will include the Western Coast Road and<br />

the Cross Bay Bridge, will be separated from the residential and commercial areas in Tseung Kwan 0 and<br />

ensure that environmental impacts are minimised.<br />

The development of Area 137 will be dependent on the successful and expeditious resolution of access<br />

constraints. Potential operators have expressed a view that Area 137 is required urgently and that demand<br />

will tail off dramatically if the site is not formed promptly and suitable access arrangements provided.<br />

APH Consultants ' ' '<br />

:<br />

' ' '• • '. ': • ,<br />

!<br />

~ ' ~ —;<br />

Page 2-5


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

SECTION 3<br />

THE PREFERRED CONCEPT<br />

3.1 PLANNING BACKGROUND<br />

The planning for a marine related industrial development must cater for the needs of the identified<br />

industrial land demand together with the provision of safe and efficient port facilities. Within the area<br />

designated for development, land uses and berth configurations need to be integrated to form an efficient<br />

and cost effective unit.<br />

The initial planning for Area 137, for the definition of land use requirements, focused on identifying<br />

potential operators and the likely split in demand between DWIs and Pffls. The split between DWI and<br />

PHI was determined by surveys which indicated that the demand for PHI sites may be stronger than<br />

originally envisaged under PADS. Therefore, for planning purposes, an allocation of 50 ha for PHI was<br />

recommended with the remaining 60 ha allocated to DWI as well as site services, roads, quay working<br />

areas, etc. It was recognised that flexibility would need to be inherent in any land use proposals in order<br />

that the final layout could be responsive to future changes in demand.<br />

Several key PHI developments were identified for potential location in Area 137, These included:<br />

+ a bulk chemical storage facility;<br />

> fuel storage facility;<br />

> a naphtha storage and gas production facility;<br />

*• an LPG storage and bottling facility.<br />

The PHI related activities included chemical processing and dangerous goods godowns. Based on research<br />

undertaken, the demand for DWI did not appear as robust as that for PHI, although it was felt that the<br />

site provided considerable opportunities which could generate strong demand over time. Possible DWI<br />

facilities included concrete batching and precasting works as well as warehousing.<br />

The PHI development was located to the south of Area 137 to avoid interface problems with adjacent land<br />

uses, in particular the TKOIE. The balance of the site was allocated to DWI development, other industrial<br />

uses, and identified supporting land uses such as:<br />

* public transport interchange;<br />

> truck/container storage area;<br />

* service centre accommodating administration offices, food stalls, banks etc;<br />

* pipeline and drainage reserves;<br />

> possible water treatment plant;<br />

> saltwater pumping station to provide water for flushing;<br />

* open space;<br />

+ reserves for other infrastructure including sewerage pumping stations, electricity substations etc.<br />

3.2 ALTERNATIVE CONCEPTS<br />

The findings of the initial planning studies enabled the preparation of a series of conceptual layouts<br />

incorporating several port berthing configurations, with each providing marine facilities of varying degrees<br />

of protection, efficiency and ship utility. Seven alternative layout options were presented in the<br />

Alternative Concepts Report based on planning, demand, engineering, marine and environmental<br />

APH Consultants Pag* 3~1


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

considerations. The layouts produced were conceptual in nature and did not preclude detail changes in<br />

later stages of the Study. All Options, bar one, provided for the reprovisioning of marine access to the<br />

SENT Landfill with a 250 m berthing facility and a 50 m wide working area behind the quay for back up<br />

facilities.<br />

Each Option produced a varying extent of DWI and PHI provision dependent on the land provided behind<br />

the seawall and the configuration of the seawall itself. The extent of land provided was also, to some<br />

degree, governed by the alignment of the proposed extension to Distributor Road D6. In all instances a<br />

landscape buffer was maintained around the perimeters of Area 137 to provide a reasonable interface<br />

between industrial development on the site and the rural hinterland, and to maintain the integrity of key<br />

physical features.<br />

The quay wall alignments and berthing layouts were determined primarily in relation to marine constraints.<br />

In the initial assessment, the predominant wave direction was assumed to be parallel to the Tathong<br />

Channel fairway orientation. A similar orientation was therefore assumed for the quay wall to reduce<br />

downtime due to wave action.<br />

Other constraints which affected the berth layouts related to navigational manoeuvring in cross currents,<br />

provision of re-entrants and basins for more sheltered berthing facilities, separation from shipping lanes<br />

and interaction with other ships.<br />

A comprehensive evaluation was undertaken to select the options for further refinement, namely Option<br />

B(i) and Option D (Figures 3.1 and 3.2). These layouts allowed for flexibility in later planning in the<br />

balance of provision of DWI and PHI land and in the nature of marine facilities required. Option B(i)<br />

maximised land for development with lesser emphasis on sheltered berthing for smaller vessels. The land<br />

provided was suited to the spatial requirements of PHI development. Option D placed emphasis on the<br />

provision of protected berthing facilities with the land provided being suited to greater DWI development.<br />

Land allocation and lengths of berths provided by these two options are shown in Table 3.1.<br />

TABLE 3.1 :<br />

LAND AREAS AND BERTH LENGTHS OF SELECTED ALTERNATIVE CONCEPTS<br />

Gross site area (ha)<br />

PHI site area (ha)<br />

DWI site area (ha)<br />

Deepwater berth length (m)<br />

Protected berth length (m)<br />

OPTION B(i)<br />

111<br />

51<br />

38<br />

2020<br />

550<br />

OPTION D<br />

39<br />

51<br />

20<br />

2470<br />

1350<br />

In addition, consideration was given to the proposed dockyaid development in Area 131. An assessment<br />

was carried out to determine the preferred layout of dockyard fecilities in terms of the wave climate and<br />

tidal flow, based on information available at the time. A recommended layout, Figure 3.3, was selected<br />

for use in die tidal flow and water quality modelling required for the Study.<br />

Implementation of the recommended dockyard arrangement would require the realignment of Road D9<br />

at its junction with Road P2. Although mis would appear to introduce no additional technical problems,<br />

a modification of the ODP would be required.<br />

'<br />

APH Consultants ' ~ " ; — —~<br />

Page 3-2


Figure 3.1<br />

SENT Landfill<br />

FAT TONG CHAU<br />

( Junk Island )<br />

SENT Landfill Access<br />

c.'.spaca-.v,<br />

and services<br />

Clearwater Bay<br />

Country Park<br />

Passible future<br />

extension of 06<br />

„ Bulk chemical storage<br />

X * X * X * " '<br />

LEGEND<br />

Potentially hazardous installations<br />

Deep water frontage industry<br />

CHAM<br />

HAU<br />

Open soace and services<br />

[' ..... " | Boundary of Area 137<br />

Interface landscaping<br />

Proposed dredged level<br />

Scale 1:10.000<br />

n 100 200 300 400 500<br />

ALTERNATIVE CONCEPTS, OPTION B(i)<br />

APH CONSULTANTS


Figure 3.2<br />

FAT TONG CHAU<br />

( Junk Island )<br />

SENT Landfill Access -,_<br />

Jv:>\ .' ; 0p«n spact..','<br />

pSv^VV'."


Figure 3.3<br />

INDUSTRIAL<br />

DEVELOPMENT<br />

APCAC<br />

AREA 131 RECOMMENDED DOCKYARD LAYOUT<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

33 RISK ASSESSMENT OF Pffl INDUSTRIES<br />

3.3,1 Overview<br />

An assessment of the risks associated with the PHIs on Area 137 has been carried out. In essence, this<br />

work provided a basis against which to consider the following questions:<br />

* Is Area 137 suitable for the location of PHIs<br />

>> What restrictions, if any, should be placed on the nature of such PHIs<br />

* Given the presence of PHIs, what planning controls would be appropriate in the vicinity<br />

Three separate reports were prepared in relation to:<br />

> risks associated with land-based operations at each of the PHI sites;<br />

> risks associated with a "worst-case analysis" of marine incidents at or close to, the jetties; and<br />

> risks associated with both land-based operations and marine incidents at or close to, the jetties.<br />

These reports have been presented and discussed at CCPffl meetings held on 24 November 1992 and 3<br />

February 1993. The following sections summarise the endorsed results of the latter report; namely the<br />

risks associated with both land-based operations and marine incidents at or close to the jetty.<br />

33*2 Risks and Risk Assessment<br />

Modern facilities which handle hazardous materials including gases, oil products and chemicals, are<br />

designed, constructed and operated to ensure that the chances of a major incident are very low.<br />

Nevertheless, there remains the possibility that a major incident could occur which represents a risk to<br />

people beyond the boundary fence.<br />

Such risks are differentiated between individual and societal risks. Individual risk represents the chances<br />

of being killed at a particular location from the effects of a number of different postulated accidents. A<br />

complementary method is to summate the likelihoods of the various accidents with their associated<br />

consequences, in terms of the numbers of fatalities, to give a picture of the overall risk to people nearby.<br />

This is referred to as the societal risk.<br />

3.3.3 The Pffls<br />

In order to provide a basis for the risk assessment, it was assumed that the following Pffls would be<br />

located on Area 137:<br />

> an oil product terminal;<br />

* a bulk chemical storage facility (BCSF);<br />

» an LPG (liquefied petroleum gas) terminal;<br />

* a gas production facility.<br />

Further assumptions were then made as to the likely throughput of materials, the transport of materials<br />

to and from the sites and the storage/processing fecilities as shown in Table 3.2 below.<br />

APH Consultants "~ ""<br />

Page J- 3


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 3.2 :<br />

BASELINE ASSUMPTIONS USED IN THE ANALYSIS<br />

PHI:<br />

OIL TERMINAL<br />

BCSF<br />

LPG TERMINAL<br />

GAS<br />

FACILITY<br />

Throughput<br />

(raVyr)<br />

1,000,000<br />

500,000<br />

100,000<br />

500,000<br />

(naphtha)<br />

Vessel Size<br />

(imports)<br />

30-45,OOQdwt<br />

40,000


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Operations at, or close to, the jetty were determined to be the major contributors to the overall risks. The<br />

risks were derived for a spectrum of accidents ranging from the more likely but less serious incidents to<br />

very remote, but credible, and severe incidents. In particular, large and unignited, spills of several<br />

hundred tonnes of the more hazardous materials could lead to the generation of significant quantities of<br />

toxic fumes. Depending on the prevailing weather conditions, such events could result in 100 or more<br />

fatalities amongst those on Area 137. In the extreme, it was possible to identify a sequence of events<br />

which could lead to fatalities in Siu Sai Wan; a residential area of Chai Wan some 1.5 km to the west of<br />

the proposed jetties.<br />

More likely but less severe incidents with the potential for off-site fatalities, included flash fires in the<br />

vicinity of the jetty and a major explosion involving highly reactive chemicals which would have serious<br />

consequences in the immediate area.<br />

3.3.6 LPG Terminal<br />

The LPG is assumed to arrive in small coastal tankers and be transferred to horizontal pressure vessels,<br />

bullets. The bullets would be of the latest semi-mounded design with additional protection to prevent any<br />

damage associated with nearby fires or explosions. There would also be LPG bottling/storage/dispatch<br />

facilities.<br />

Incidents involving multi-tonne releases of LPG at the jetty, from the storage area or during the loading<br />

of bulk road tankers could aU lead to off-site fatalities. The most severe events identified were vapour<br />

cloud explosions which could lead to 100 or more fatalities amongst those on Area 137, and, in the worst<br />

case, a large vapour cloud could be ignited near the Siu Sai Wan shore-line.<br />

33.7 Gas Production Facility<br />

This facility was be assumed to be broadly similar to the existing Tai Po plant. Naphtha would arrive in<br />

tankers and be stored in three large tanks located at the southern edge of Area 137. There would be<br />

processing units to convert the naphtha to town gas and gas export facilities via pipeline.<br />

The risks were dominated by those associated with large releases of naphtha at the jetty which could lead<br />

to off-site fatalities. In the worst cases, a flash fire could result in 20 or more fatalities in Area 137 and,<br />

in the extreme, the Siu Sai Wan area could be affected.<br />

33.8 Risk Results and Risk Criteria<br />

Individual Risks<br />

In accord with the recommendations of the CCPffl, the assessed individual risks for each Pffl were<br />

compared to the Individual Risk Guideline which suggests that the off-site individual risk should not<br />

exceed 1 chance in 100,000 per year of becoming a fatality.<br />

The results of the risk assessment indicate that there would be negligible individual risks to people outside<br />

Area 137. With regard to workers on Area 137, the individual risks associated with each of the Pffls<br />

were below the Guideline value of 1 in 100,000 per year,<br />

Societal Risks<br />

The results of the risk assessment were also evaluated in respect of societal risks The Societal Risk<br />

Guideline is more complex than that for individual risk, but, in essence, comprises three regions:<br />

* a region within which the risks may be regarded as unacceptable;<br />

APH Consultants "~~ —:<br />

Page Jo


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

> a region within which the risks may be regarded as acceptable; and<br />

> a region between the two in which measures should be taken to ensure that the risks are "as low<br />

as reasonably practicable" (ALARP).<br />

Numerically, the upper bound of the ALARP region and hence the borderline of "unacceptabiiity", can<br />

be summarised as:<br />

> 1 chance in 1,0(30 per year of an incident resulting in 1 or more fatalities;<br />

+ 1 chance in 10,000 per year of an incident resulting in 10 or more fatalities;<br />

> 1 chance in 100,000 per year of an incident resulting in 100 or more fatalities; and<br />

> not more than 1,000 fatalities at a frequency of greater than 1 chance in a billion (1,000,000,000)<br />

per year.<br />

For three of the sites, the BCSF, the LPG Terminal and the Gas Production Facility, the societal risk<br />

results may be summarised as follows:<br />

>•<br />

a region associated with incidents which could result in a few off-site fatalities. In broad terms,<br />

the societal risks were close to the Societal Risk Guideline. In one case, the LPG Terminal, the<br />

Guideline was very slightly exceeded. It is considered that this was due to a combination of the<br />

pessimistic assumptions made and the nature of the calculation methods used. On this basis, it<br />

is not considered that these assessed risks should be deemed "unacceptable" at this stage.<br />

Furthermore, should the outline development plans proceed to firm detailed proposals, the<br />

operators should be able to demonstrate compliance with this part of the Societal Risk Guideline<br />

in due course;<br />

> a region associated with less likely but more serious incidents which could lead to tens, or more,<br />

of fatalities amongst people on other facilities on Area 137. Such incidents, as would be<br />

expected, were found to be very unlikely, typically less than 1 chance in 100,000 per year and<br />

the associated societal risks fell within the ALARP region of this part of the Societal Risk<br />

Guideline; and<br />

> a region associated with extremely remote incidents but with potentially severe consequences<br />

including fatalities in the Chai Wan area under the worst conditions. At this low frequency/high<br />

consequence end of the societal risk spectrum, the calculations are uncertain and, as a result, the<br />

Consultants cannot guarantee that, at this conceptual stage, the three PHIs will be able to<br />

demonstrate compliance with the Guideline in this region should detailed proposals be put<br />

forward, particularly in respect of the Bulk Chemical Storage Facility.<br />

Due to the limited hazards associated with the fourth site, the Oil Terminal, the associated societal risks<br />

were well within the ALARP/acceptafale regions of the Societal Risk Guideline - particularly since no<br />

event was identified which could lead to ten or more fatalities.<br />

3.3.9 Key Findings<br />

Is Area 137 Suitable for PHIs<br />

There are no areas of significant residential population within 1 km of Area 137 and, as such, the risks<br />

associated with the proposed PHIs would be expected to be tolerable. In broad terms, this view was<br />

reinforced by the results of the risk assessment which generally comply with the Risk Guidelines adopted<br />

by the Hong Kong Government (through the CCPHI). As such, it is considered that Area 137 is a suitable<br />

site for the development of PHIs. Nevertheless, there remains a possibility that the Societal Risk<br />

Guideline will be exceeded in relation to extremely remote, but credible, events associated with marine<br />

incidents at, or close to, the jetties.<br />

APH Consultants Pag* 3-6


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

final Report - Main Report<br />

Restrictions on ihe Nature ofPHIs<br />

Apart from a BCSF, there is practical operational experience and associated risk assessments in Hong<br />

Kong of the PHIs considered. There is little to suggest either from this experience or from the results of<br />

this assessment that any restrictions should be placed upon the nature of the PHIs which could be located<br />

on Area 137.<br />

Nevertheless, there are three broad principles which apply to any PHI development:<br />

> quantities of hazardous materials to be stored (and handled) should be minimised;<br />

> practical measures should be taken to minimise both on and off site risks where practicable;<br />

> the development of a particular PHI would normally be subject to a further and more detailed risk<br />

assessment.<br />

Planning Controls<br />

As already indicated, within the scope of the work undertaken, the results suggest that no specific planning<br />

controls need to be exercised on risk grounds for areas outside Area 137. In other words, the presence<br />

of PHIs on Area 137 should not impose restrictions, on risk grounds, on the TKOIE and the SENT<br />

Landfill sites immediately to the north, nor would planning controls for the Chai Wan area be appropriate.<br />

Within Area 137, it would be prudent to limit the worker densities to those used as a basis for the<br />

analysis, namely 20/ha on the PHI sites, and 30/ha on other sites within Area 137.<br />

Finally, there is an annual festival at nearby Tai Miu Wan (Joss House Bay) which attracts thousands of<br />

visitors. Although the level of individual risk in this area will be minimal, the presence of so many people<br />

close to Area 137 introduces the remote possibility of a major multi-fatality accident. Given that the risks<br />

are dominated by incidents at the jetties, it is suggested that it would be prudent to suspend all jetty<br />

operations for the day.<br />

3.4 PREFERRED CONCEPT<br />

Additional detailed studies have been undertaken in the refinement and selection of the Preferred Planning<br />

Concept. These included:<br />

* planning issues;<br />

* wave modelling;<br />

> tidal flow and sUtation modelling;<br />

> water quality modelling;<br />

> air quality measurement;<br />

+ geotechnical and geophysical site investigation;<br />

> marine and navigational assessment study;<br />

> assessment of alternative quay structures;<br />

> dredging and reclamation issues;<br />

> traffic and transport issues.<br />

The planning research indicated interest in the site by the bulk chemical storage industry and the Hong<br />

Kong China Gas Company (HKCGC). The latter are currently undertaking a detailed study into future<br />

gas requirements in the Territory, the findings of which will be incorporated into their 5 year<br />

Development Plan. The HKCGC regard Area 137 as a potential site for a gas production facility.<br />

APH Consultants "" ' ~~ T ~TI<br />

Page 3-7


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

The interest in the site has been matched by an overwhelming concern expressed with regard to the likely<br />

site implementation schedule. The view has been repeatedly stressed that if Hong Kong is to remain<br />

competitive as a port then new deep water berthing and industrial facilities are urgently required. This<br />

is particularly the case with regard to the storage and distribution of chemicals which have a high value<br />

added component. Operators have stressed that if provision of such facilities is not implemented soon then<br />

they will divert investment elsewhere. In addition to timing considerations, a number of operators have<br />

cited the absence of a railway connection as being a constraint to successful implementation. It is more<br />

likely, however, that timing considerations will weigh more heavily than the provision of rail links to the<br />

site.<br />

A major influence on the planning and layout of the development resulted from the risk assessment and<br />

the findings were considered to be a pre-requisite to the further refinement of planning layouts for the site.<br />

Further, the basic planning premise was adopted that PHI layouts similar to those used in the risk<br />

assessment should be utilised to maintain the validity of the results and recommendations of the risk<br />

assessment study.<br />

The selected alternative Options B(i) and D were further developed as Options 1 and 2 respectively and<br />

were refined to incorporate the results of the additional studies outlined above. The refinement of options<br />

also incorporated the addition of a provisional road network together with the subdivision of the site into<br />

notional industrial lots. Both options incorporated worker densities of 20 persons per ha for PHI lots and<br />

30 persons per ha for DWI lots. In conformity with Government Planning Standards and to avoid<br />

exceedence of the recommended worker densities, it was recommended that the plot ratio applied to the<br />

site should not exceed 2.5.<br />

3.4.1 Option 1 (Figure 3.4)<br />

The detailed wave modelling and analysis revealed that the predominant residual swell direction is not<br />

parallel to the traffic separation fairways, as previously assumed, but in fact lies further to the west, thus<br />

negating the benefits of the initially proposed quay orientation. In addition, the setback in the quay wall<br />

was shown to introduce added complexity to the departure manoeuvre requiring good vessel and tug<br />

control to bring the vessel off the southern berth and swing it onto the required departure alignment. The<br />

setback was also shown to be undesirable in the event that a berthing manoeuvre needed to be aborted.<br />

Taking into account the results of both the wave modelling and marine study, the quay wall alignment was<br />

modified in order to provide a more desirable berthing layout, both improving navigational aspects and<br />

minimising downtime due to wave action. The principle of the straight line seawall was retained, with<br />

a small basin in the north, primarily for the provision of the SENT Landfill marine access.<br />

A possible extension of Road D6 through Area 137 providing future access to Joss House Bay was allowed<br />

for on the revised layout. Access to and within Area 137 was proposed via a spine road. It was<br />

envisaged that the road would access the site from a proposed roundabout located on Road D6 south of<br />

the SENT Landfill and extend southward through the project area. Secondary site access was provided<br />

off the spine road. An access road to the SENT Landfill was provided to the north of the site.<br />

The land use layout within the site was maintained in accordance with the findings of the risk assessment.<br />

This required that naphtha storage and gas production facilities are located at the south of the site with<br />

LPG bottling and storage, bulk chemical storage and fuel storage further north. Site configuration was<br />

governed to some extent by berthing requirements related to each of the PHI sites and to the spatial<br />

requirements of each operation to reduce industrial risks to a minimum. An emergency vehicle access<br />

(EVA) was provided to the PHI sites along the edge of the development. This area would also act as a<br />

drainage reserve behind the seawall to cater for overtopping drainage in extreme storm conditions. In all,<br />

some 50 ha net of land for PHI development was provided which accounted for almost 48% of the total<br />

available site area.<br />

APH Consultants Page 3-8


Figure 3.4<br />

TONG CHAU<br />

To Taaung Kwan O<br />

f<br />

SENT Landfill<br />

TKOIE<br />

SENT Landfill<br />

marine<br />

50m general<br />

working area<br />

Ciearwater Bay<br />

Country Park<br />

Qhemical storage<br />

Possible extension of 06<br />

to Joss House Say<br />

3*w«raa« Pumping<br />

Station<br />

27.3m EVA and<br />

no build area<br />

EVA reserve {7.3m<br />

LEGEND<br />

TIT CHAM<br />

CHAU<br />

Potentially hazardous installations<br />

:::;;::: 1 Deep water frontage industry<br />

PH.! related Industry<br />

Open space and Interfaca landscaping<br />

Services<br />

EVA i Emergency vehicle access<br />

OPTION 1 CONCEPTUAL LAYOUT<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

To complement PHI development, a number of sites were zoned for PHI related development. These were<br />

located east of the north-south spine road and accounted for about 4 ha or approximately 4.0% of the total<br />

land use budget.<br />

Some 28 ha of land was allocated to DWI development in the northern portion of the site. Marine access<br />

to these sites was provided via a General Working Area adjacent to the marginal quays. This included<br />

a 50 m reserve behind the quay for marine related and cargo working activities.<br />

Remaining land uses included roads and road reserves, a reservation for the SENT Landfill marine access<br />

and backup site, on-site services designated to include commercial retail provision and some 5 ha allocated<br />

to open space and interface landscaping reserves. Landscape buffers were maintained at the fringes of the<br />

site to preserve the integrity of the adjacent Country Park, Fat Tong Chau and Tit Cham Chau.<br />

The total site area comprised some 105 ha which provided adequately for the PHI and DWI development<br />

requirements identified. The land use budget for Option 1 is summarised below in Table 3.3.<br />

3.4.2 Option 2 (Figure 3.5)<br />

The results of the marine and wave studies outlined in Option 1 above dictated similar modifications to<br />

the quay wall alignment to give a more efficient berthing and land use layout. The outer berths were<br />

modified to provide a straight line quay wall along the same alignment as that of the Option 1, while<br />

retaining the basin protected by a finger pier.<br />

The road network for Option 2 comprised a centrally located reservation for Road D6 with the primary<br />

site access road looping around the east of the site. Access to the external road network was again from<br />

a roundabout on Road D6 at the south of the SENT Landfill. Secondary access within the site was<br />

provided, as in Option 1, off the main road.<br />

In order to maintain the site layout in accordance with the assumptions and results of the risk assessment,<br />

it was not possible to provide for all identified Pffls due to the limited land area available under the<br />

Option. Provision for a naphtha plant, LPG bottling and storage plant and a chemical storage facility were<br />

made in the southern portion of the site. An EVA and drainage reserve was again provided along the edge<br />

of the development.<br />

A total of some 31 ha, or 32% of total site, was provided for PHI development. DWI development<br />

accounted for 33 ha or 35% of total site area. PHI related sites (4.10 ha) were provided to the east of<br />

Road D6 reserve. A 50 m General Working Area was provided adjacent to the marginal quay walls. The<br />

greater area of marine related working space provided under this Option would prove advantageous if<br />

emphasis was placed on the provision of DWI industries.<br />

The total land area provided under Option 2 comprised some 95 ha. The land use budget for Option 2<br />

is summarised in Table 3.3 below.<br />

Each Option allowed for a phased development. Moreover, the initial phasing envisaged under both<br />

Options specifically did not preclude the realization of one or other Option at the full development stage.<br />

This flexibility would allow the development to be responsive to changing industrial demand.<br />

APH Consultants Page 3-9


Figure 3.5<br />

To Tseung Kwan 0<br />

SENT Landfill<br />

~ Reserve for<br />

| possible<br />

alignment of 06<br />

Clearwater Bay<br />

Country Park<br />

50m general<br />

working area<br />

Possible extension of D6<br />

to Joss House Bay<br />

LEGEND<br />

Potentially hazardous installations<br />

JnllSlJI Deep water frontage industry<br />

PHI related industry<br />

Open space and Jnterface landscaping<br />

Services<br />

27.3m HVA and<br />

no build area<br />

•V- '•"• *•"'.*•*."• *•"-.'•'V'. 4 - '•"•."•'•/• '.'•/••<br />

/>;. •.••.• *. •:» *.••,•'. •;* *. • \^z^s.<br />

EVA reserve (7.3m<br />

TIT CHAM<br />

CHAU<br />

£VA 1 Hniergency vehicle access<br />

OPTION 2 CONCEPTUAL LAYOUT<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 3.3 :<br />

LAND USE BUDGET BY OPTION<br />

LAND USE OPTION 1<br />

Area % of total<br />

PHI<br />

49.95<br />

47.6<br />

DWI<br />

2S.10<br />

26.8<br />

PHI Related Industry<br />

4.05<br />

3.9<br />

Open Space<br />

4.98<br />

4.7<br />

Services<br />

2.30<br />

2 2<br />

SENT Access<br />

2.25<br />

2.1<br />

General Working Area<br />

3.65<br />

3.5<br />

Roads & Road Reserves<br />

9.72<br />

9.3<br />

OPTION 2<br />

Area % of total<br />

30.80 32.4<br />

33.00 34.7<br />

4.10 4.3<br />

6.57 6.9<br />

1.60 1.7<br />

2.30 2.4<br />

7.10 7.5<br />

9.53 10.0<br />

105.00<br />

100<br />

95.00<br />

100<br />

3*4.3 Selection of Preferred Concept<br />

Option 1 and Option 2 were evaluated in terms of engineering and marine, land planning, traffic and<br />

transport and environmental criteria. In most respects, both options were found to be similar in provision<br />

of facilities and impacts of the development. The main difference between the two lay in their ability to<br />

meet industrial land demand.<br />

Option 1 provided adequately for identified PHI demand whereas Option 2 fell short of target spatial<br />

requirements. Conversely, Option 2 provided more DWI sites and would, therefore, be a more viable<br />

option if, over time, DWI site demand and requirement for greater cargo working areas were found to be<br />

stronger than is presently the case.<br />

Cost estimates were carried out for the two options for the construction of the reclamation, edge structures<br />

and roads, and the provision of services and drainage to the individual site entrances. The order of capital<br />

cost estimates were:<br />

Option 1<br />

Option 2<br />

HKS 2,067M<br />

HK$ 2,190M<br />

Through the process of optimisation of the layouts there had been a considerable convergence of the two<br />

Options, with effectively equivalent developments in the south. In the selection of the Preferred Concept,<br />

therefore, considerable weight was attached towards the balance of the split between DWI and PHI<br />

requirements. The land use demand surveys indicated a very positive interest in PHI development and<br />

related industries and it is considered that the balance should be directed towards these industries. Area<br />

137 is, possibly, one of the few remaining sites suitable for PHI development in Hong Kong whereas<br />

DWI, involving non-PHI activities, could be accommodated at alternative sites recently considered but<br />

found unsuitable for PHI.<br />

In terms of the full development, the preference must therefore lie with the greater provision for PHI<br />

activities. As such, Option I was recommended as the Preferred Concept, It has therefore been agreed<br />

that outline engineering design will be carried out for this concept with the proposed implementation based<br />

on a rolling programme of development with the PHI sites in the south developed first.<br />

APH Consultants Page 3-10


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

SECTION 4<br />

LAND USE PLANNING<br />

4,1 DETAILED PLANNING LAYOUTS<br />

The planning process outlined in the foregoing Sections has involved the progressive refinement of initial<br />

planning concepts into more detailed planning layouts. This Section concludes the land use planning<br />

process with the presentation of the Recommended Development Layout.<br />

The size and configuration of the site required the preparation of three layout plans at the prescribed scale<br />

of 1:1000 to adequately cover the entire planning area as presented in the accompanying Drawings. The<br />

Written Statements are included as Appendix B. Figure 4.1 provides an overall presentation of the<br />

proposed land uses.<br />

Accompanying the land use proposals is a Landscape Master Plan at scale 1:2500 which depicts landscape<br />

proposals for the site. Details of the landscaping measures proposed are provided within this Section and<br />

within the Written Statements for each of the planning layouts.<br />

The Recommended Development Layout encompasses new information which has become available since<br />

the submission of the Preferred Concept Report and the refinements to the layout in response to comments<br />

received from Government Departments. The proposed road network has been revised to accord with<br />

planning intentions for the area. Road alignments, radii and widths fully accord with current highway<br />

standards. Infrastructural provision has now been extensively revised to accommodate current planning<br />

proposals, Storm water culvert alignments have been shown where they exert an influence or constraint<br />

on proposed land use or landscaping measures. Finally, berthing arrangements and site configurations<br />

have been jointly refined to ensure that an efficient marine to land use relationship is achieved.<br />

4.2 PHI AND Pffl RELATED DEVELOPMENT<br />

Four sites comprising a total area of 41.37 ha have been specifically reserved for PHI development and<br />

are zoned Industry Group B (I(B)) and Industry Group C (I(C)). Three sites adjacent to the Clearwater<br />

Bay Peninsula have been reserved for PHI related industrial activities. Spatial provision and allocation<br />

per site has been determined with reference to the findings of the previous land planning studies, ongoing<br />

contacts with interested operators and with particular cognisance of the findings of the risk assessment.<br />

Nevertheless, lot boundaries have been indicated with a broken line to provide flexibility and to allow for<br />

any alteration in spatial requirements related to specific sites.<br />

Site 1, comprising a total area of 10.95 ha and zoned I(B), has been allocated for gas production purposes.<br />

In conformity with the HKPSG a minimum building setback of 6.0 m has been applied to the northern<br />

boundary of the site. A 15.0 m setback has been proposed along the eastern boundary adjacent to Road<br />

Rl in order to effectively set development well back from a public thoroughfare. Along the southern and<br />

western boundaries there is a 20 m Emergency Vehicle Access (EVA) and seawall maintenance reserve.<br />

A plot ratio of 1.25 is suggested for the site which produces 4 Gross Floor Area (GFA) amounting to<br />

136,900 nr. In accordance with the findings of the risk assessment worker density has been fixed at 20<br />

workers per ha. This density produces a total site workforce of 219 workers.<br />

A dolphin berth suitable for the offloading of naphtha to the proposed gas production plant has been<br />

provided adjacent to the seawall. The design of the berth is sufficient to accommodate classes of vessels<br />

which are likely to off-load at the gas production facility. It is envisaged that no major structure, except<br />

APH Consultants Page 4~l


Figure 4.1<br />

OEARWATER 3AY<br />

COUNTRY PARK<br />

TATHONO CHANNEL<br />

LEGEND;<br />

Potentially hazardous installation<br />

0««p waterfront industry<br />

TA1 UU! WAN<br />

PHI related industry<br />

Open 3pac« and interface landscaping<br />

Services<br />

TSEUNG KWAN 0 AREA 137<br />

RECOMMENDED PLANNING LAYOUT<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

for stacks or flues, will be constructed to height exceeding 30 m. The positioning, design, and massing<br />

of the required stacks and flues should be subject to a visual and environmental assessment when firm<br />

development proposals are known.<br />

Site 2 has been allocated to an LPG storage and bottling facility and comprises a total of 9.61 ha, zoned<br />

I(C). A plot ratio of 1.25 is recommended which produces a GFA amounting to 120,100 m 2 . Berthing<br />

arrangements of this and adjacent sites along the seawall have determined the H L" shaped site<br />

configuration.<br />

Worker density on the site is recommended not to exceed 20 workers per ha. This density results in a<br />

total estimated site workforce of 192 persons. A 6.0 m setback is maintained along the northern and<br />

southern boundaries for emergency and fire fighting purposes. A 15.0 m setback reserve is proposed<br />

adjacent to Road Rl. Access to the site will be achieved via two access points from Road Rl located at<br />

the eastern boundary of the site.<br />

As for Site 1, the height of development should not exceed 30.0 m. Stacks and flues may be permitted<br />

in exceedence of this height subject to an appropriate visual and environmental study. A jetty berth has<br />

been provided for the importation of LPG.<br />

Site 3 has an "L" shaped configuration with a site area of 10.72 ha and is zoned I(C). The site is<br />

proposed for chemical storage purposes. Two dolphin berths will be required for the bulk import of<br />

chemicals and transhipment to regional markets. A plot ratio of 1.25 is suggested for the site which<br />

produces an estimated GFA amounting to 134,000 m 2 . Worker density will be restricted to 20 workers<br />

per ha producing a maximum on-site workforce of 214. Height restrictions and conditions appertaining<br />

to flues and stacks will apply to the site development as for Sites 1 and 2.<br />

Site 4, with a total site area of 10,09 ha, zoned I(C), is reserved for the bulk storage of oil and petroleum<br />

products. Again a plot ratio of 1.25 is suggested resulting in a GFA amounting to 126,100 m 2 . A<br />

building setback of 6,0 m is proposed adjacent to the northern and southern boundaries of the site while<br />

a 15.0 m setback is recommended adjacent to Road Rl. Conditions regarding height, massing, and the<br />

installation of flues and stacks should be applied as above.<br />

A 20 m EVA and seawall maintenance reserve is proposed to the west of the PHI sites adjacent to the<br />

seawall and is included within the curtilage of the adjacent lots. The EVA will require to be kept clear<br />

at all times to allow for the passage of emergency vehicles.<br />

The Study has identified a likely requirement for industrial sites with a direct product relationship to the<br />

PHI sites, for operations such as high value added (HVA) chemical processing. There is a potential<br />

demand for three sites for such purposes with a spatial allocation of around 3.0 ha per site. Three sites<br />

zoned I(B) have been reserved for PHI related industries to the east of the PHI sites. However, due to<br />

planning and site layout constraints, only 7.18 ha has been allocated to the PHI related industrial activities.<br />

From the recommendations of the risk assessment, worker density in the PHI related sites is 30 workers<br />

per ha. This results in a total worker density for the three sites estimated at 193 workers. Reduced risk<br />

operations which are likely to be undertaken on these sites allows for the application of a higher plot ratio.<br />

A plot ratio of 2,5 is. therefore, recommended which produces a total GFA across the three sites<br />

amounting to 179,500 m 2 . Building height will be restricted to 30 m and applications for stacks or flues<br />

exceeding this limitation should be considered on a site by site basis and with regard to visual and<br />

aesthetic considerations. On a broad basis, given the interface with the adjacent Country Park, it is not<br />

generally recommended that the 30.0 m height restriction be breached.<br />

It is proposed that a 10.0 m building setback be applied to each site adjacent to the Road R2/D6 reserve,<br />

a 6.0 m setback on the northern and southern boundaries and a 15,0 m setback on the boundaries abutting<br />

APR Consultants Page 4-2


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

Road Rl. This will ensure adequate access in the event of an emergency, secure the safe disposition of<br />

buildings and allow for a desirable blocking and massing of buildings. All loading and unloading of<br />

vehicles will be undertaken within the curtilage of each site and appropriate provision should be made in<br />

this regard. Similarly, parking provision in conformity to the HKPSG should be made on each site. No<br />

parking or loading and off-loading operations should be permitted on estate roads. No access to any lot<br />

shall be permitted from Road R2.<br />

To ensure that the development and layout of buildings and storage facilities on PHI sites satisfies current<br />

practices and standards, the operators should make an appropriate submission to CCPHI and comply with<br />

the requirements of EPD Advice Note 2/92 with regard to the presentation of on-site environmental<br />

safeguards which will be applied to each site. An application to the Town Planning Board may also be<br />

required. It is suggested, however, that a means be found to expedite the application process in order to<br />

avoid discouragement of investors.<br />

4.3 DWI DEVELOPMENT<br />

A total of 22 sites have been allocated to DWI development. In broad conformity with the provisions of<br />

the HKPSG, 20% of the sites have been zoned for I(C) purposes and the balance allocated to I(B) purposes<br />

which accords with the intentions of the OOP. By definition DWI development comprises industrial or<br />

warehousing operations which, by virtue of their nature require access to deep water berths. Activities<br />

which cannot prove such a requirement will be precluded from the DWI lots. Operators who have shown<br />

an interest in this regard include the bulk heavy oil storage and packing industry, the break bulk chemical<br />

industry and the concrete batching and prefabrication industry. Other activities which could be allowed<br />

would include dangerous goods godowns. Government is currently seeking the removal of such facilities<br />

from the existing urban areas and the provision of alternative sites would aid the realisation of this<br />

objective. Site boundaries have been indicated with broken lines to render the plan flexible and to provide<br />

for further consolidation or subdivision of lots.<br />

Because of risk and visual considerations the density of development in DWI areas has been limited. A<br />

mean lot size of 1 ha has been assumed. Nevertheless, this would not preclude the subdivision or<br />

consolidation of lots in relation to demand where this is physically practicable. A plot ratio of 2.5 is<br />

suggested which results in a total GFA for the 22 sites amounting to 557,300 nor. In accordance with the<br />

findings of the risk assessment worker density has been maintained at 30 workers per Ha. This results<br />

in a total projected DWI workforce amounting to 668 workers. Building height in DWI areas will be<br />

restricted to 30 m in order to limit visual impacts and to maintain the backdrop and integrity of the<br />

Country Park.<br />

Proposed access points to each site are indicated in the detailed layout plans. No access to DWI sites will<br />

be obtained from Road D6 or Road R2/D6 reserve. The SENT Landfill operation requires a private road<br />

for access to the barge berth which precludes use of this road for the Area 137 development. This reduces<br />

the planning efficiency of the DWI sites. Should this limitation be removed, it is recommended that<br />

affected lots be replanned to form more efficient configurations.<br />

A 9.1 m EVA access is provided to the rear of lots 12 to 16. Elsewhere, emergency access on more than<br />

one side of each lot can be obtained via public roads or cargo working areas. Access arrangements would<br />

have to be reviewed if several lots are consolidated. A 9.1 m EVA reserve should will be established<br />

along the working area fronting lots 25 to 30 to ensure through passage for emergency vehicles in the<br />

event of an incident. To aid emergency access and to produce a satisfactory arrangement of buildings on<br />

site, building setbacks have been proposed. These comprise a 6.0 m setback around the lots except at the<br />

sides where one lot abuts another, where a 4.5 m setback should be applied.<br />

APH Consultants<br />

page


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

A 50 m marine working area has been provided to service all DWI lots. It is not intended that there<br />

should be any exclusivity of use or access. Lots 25 to 30 inclusive which front the working area have,<br />

however, an advantageous location when compared to other DWI lots. It is suggested that this<br />

consideration is reflected in the premium levied on these sites.<br />

Although no firm commitment has been expressed with regard to DWI take up, the general view among<br />

operators is that, as deep water moorings are at such a premium in Hong Kong, DWI sites in Tseung<br />

Kwan O would be well received by the market.<br />

4.4 SUPPORTING DEVELOPMENT AND FACILITIES<br />

Road RIO provides access to the SENT Landfill marine access facility and working area. A marginal<br />

quay of 250 m has been reserved for SENT Landfill use with a 50 m working area provided to the rear<br />

of the quaywaiL Once SENT Landfill operations are complete, the site could be handed over to another<br />

user for industrial development.<br />

Site 8 has been reserved for service and recreational facilities. The HKPSG requires the allocation of<br />

0.5m 2 of open space per industrial worker (5 ha per 10,000 svorkers). As this standard would only<br />

produce nominal open space, additional recreational facilities have been provided given the relatively<br />

isolated location of Area 137. Details of open space facilities are given in Section 4.6 below. Site 8 will<br />

also provide for offices and small scale commercial premises. It is not, however, anticipated that these<br />

will need to be large scale facilities and only two to three storey structures should be permitted.<br />

Two sewage pumping stations are provided on the site. A 225 m 2 reserve is provided adjacent to Site 3<br />

to accommodate the full development of Area 137 and a 100 nr site reserve is provided adjacent to Road<br />

RIO for a temporary pumping station for the SENT Landfill marine facility. A 2,400 m : reserve has been<br />

provided in the southern portion of the site for an electrical sub-station.<br />

Several storm water culverts dissect the planning area. Drainage reserves are demarcated on the planning<br />

layout plans. No development or hard planting will be permitted on or over these reserves.<br />

Areas on the periphery of the site have been maintained as buffer areas. The treatment of these areas and<br />

roadside planting measures are described in Section 4.6 which describes the landscape master plan.<br />

Table 4.1, overleaf, provides a breakdown of development and land use by site. The site numbers used<br />

in the Table correspond to the site numbers depicted in Figure 4.1.<br />

4.5 PROVISION OF BERTHING FACILITIES<br />

Some 1000 m of deepwater frontage has been provided for the PHI sites. The berths as indicated in<br />

Figure 4.1 should be regarded as indicative, based on potential user requirements. These may be modified<br />

with regard to ultimate user requirements.<br />

Multi-user marginal quays have been provided to serve the PHI related and DWI sites. These consist of<br />

200 m of aeepwater outer marginal quay wall and 800 m of basin marginal quay wall (including SENT<br />

Landfill access berths).<br />

The outer deepwater berths will be dredged to -14 mPD, while the basin will be dredged to -10 rnPD.<br />

APH Consultants Page 4-4


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 4.1 :<br />

AREA 137 LAND USE, GROSS FLOOR AREA & WORKER<br />

DENSITY BY SITE<br />

SITE No.<br />

LAND USE<br />

SITE AREA<br />

(ha)<br />

PLOT<br />

RATIO<br />

GFA<br />

(m : )<br />

No.<br />

WORKERS<br />

1<br />

PHI (gas)<br />

10.95<br />

1.25<br />

136900<br />

219<br />

2<br />

PHI (LPG)<br />

9.61<br />

1.25<br />

120100<br />

192<br />

3<br />

PHI (chem)<br />

10.72<br />

1.25<br />

134000<br />

214<br />

4<br />

PHI (oil)<br />

10.09<br />

1.25<br />

126100<br />

202<br />

Sub Total<br />

41.37<br />

517100<br />

827<br />

5<br />

PHI related<br />

2.82<br />

2.5<br />

70500<br />

85<br />

6<br />

PHI related<br />

2.10<br />

2.5<br />

52500<br />

63<br />

7<br />

PHI related<br />

2.26<br />

2.5<br />

56500<br />

45<br />

Sub Total<br />

7.18<br />

179500<br />

193<br />

8<br />

Services<br />

1.00<br />

9<br />

DWI<br />

0.93<br />

2.5<br />

23300<br />

28<br />

10<br />

DWI<br />

0.75<br />

2.5<br />

18800<br />

22<br />

11<br />

DWI<br />

1.70<br />

2.5<br />

42500<br />

51<br />

12<br />

DWI<br />

0.60<br />

2.5<br />

15000<br />

18<br />

13<br />

DWI<br />

0.45<br />

2.5<br />

11300<br />

13<br />

14<br />

DWI<br />

0.50<br />

2.5<br />

12500<br />

15<br />

15<br />

DWI<br />

0.48<br />

2.5<br />

12000<br />

14<br />

16<br />

DWI<br />

0.44<br />

2.5<br />

11000<br />

13<br />

17<br />

DWI<br />

0.70<br />

2.5<br />

17500<br />

21<br />

18<br />

19<br />

DWI<br />

DWI<br />

0.82<br />

0.93<br />

2.5<br />

2.5<br />

20500<br />

23300<br />

25<br />

28<br />

20<br />

21<br />

T><br />

23<br />

24<br />

25<br />

26<br />

27<br />

23<br />

29<br />

30<br />

Sub Total<br />

DWI<br />

DWI<br />

DWI<br />

DWI<br />

DWI<br />

DWI<br />

DWI<br />

DWI<br />

DWI<br />

DWI<br />

DWI<br />

1.36<br />

1.57<br />

1.13<br />

1.05<br />

0,71<br />

0.57<br />

1.05<br />

LOO<br />

1.01<br />

2.32<br />

1 T><br />

22 ^9<br />

2.5<br />

2.5<br />

2.5<br />

2.5<br />

2.5<br />

2.5<br />

2.5<br />

2.5<br />

2.5<br />

2.5<br />

2.5<br />

34000<br />

39300<br />

28300<br />

26300<br />

17800<br />

14300<br />

26300<br />

25000<br />

25300<br />

58000<br />

55500<br />

557800<br />

41<br />

47<br />

34<br />

31<br />

21<br />

17<br />

32<br />

30<br />

30<br />

70<br />

67<br />

668<br />

Page 4-5


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

TABLE 4.1 (CONTINUED)<br />

SITE No.<br />

LAND USE<br />

31 FatTongChau<br />

Buffer (a)<br />

32 Fat Tong Chau<br />

Buffer (b)<br />

33 Tit Cham Chau<br />

Buffer t- EVA<br />

34 Clearwater Buffer<br />

Sub Total<br />

35 SPS<br />

38 SENT Working<br />

Area<br />

39 DWI Working<br />

Area -r EVA<br />

36 SPS<br />

37 ESS<br />

Sub Total<br />

Road and Footpaths<br />

SITE AREA PLOT GFA No.<br />

(ha) RATIO (or) WORKERS<br />

0.89<br />

2.12<br />

1.41<br />

4.18<br />

8.60<br />

0.01<br />

1.25<br />

3.58<br />

0.02<br />

0.24<br />

5.10<br />

16.24<br />

Total<br />

101.78 1254400 1688<br />

4,6 LANDSCAPING<br />

4,6.1 Introduction<br />

The landscape proposals are illustrated in the Landscape Master Plan contained in the Drawings document.<br />

The primary aims of the landscape proposals are:<br />

* to ameliorate the assessed visual impact of the industrial development views from Rennies Mill<br />

and Hong Kong Island to the west and from the Clearwater Bay Country Park to the east;<br />

> to create an appropriate landscape setting for the development within the context of the<br />

surrounding coastal landscape;<br />

+ to enhance the quality of the environment within the development itself,<br />

The landscape proposals seek to fulfil these aims through a comprehensive framework of woodland<br />

structure planting. Larger blocks of woodland around the perimeter of the site and along the new<br />

waterfront will help to provide a buffer screen at ground level and to tie into the pockets of existing<br />

vegetation on adjacent hill slopes. Planting strips along individual lot boundaries and along road corridors<br />

will help break up the visual extent of the development and create a more attractive setting within.<br />

APH Consultants Page 4-6


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

No specific landscape treatment has been indicated within the lots as this will be developed, as<br />

appropriate, within the detailed design of the individual plots.<br />

4.6.2 Landscape Framework<br />

Structure Planting<br />

The structure planting will be composed of broad swathes of woodland type planting, using tree and shrub<br />

species that will be tolerant of the anticipated exposed conditions, high air borne pollution levels and low<br />

maintenance regimes.<br />

Perimeter Planting<br />

The planting around the site perimeter will flank the development and act as an interface between it and<br />

Clearwater Bay Country Park, Tit Cham Chau and Fat Tong Chau. The planting can be used as a visual<br />

extension of the country park, thus avoiding the abrupt change from countryside to industry, by extending<br />

fingers of vegetation into the development. The integrity of the islands can be maintained by using planting<br />

to reinforce the existing vegetation.<br />

Along the waterfront zones, intermittent planting will be used to break up the impact of the industrial<br />

buildings from the distant views across the bay. This will help to create a gradual transition from the sea<br />

to the backdrop of the hills.<br />

Internal Planting<br />

Within the body of the site, the internal structure planting will be implemented along landscape belts<br />

between the major access roads and industrial plots. These "fingers" of vegetation will be important in<br />

maintaining visual and physical connections with the scenic backdrop of the hills of Clearwater Bay<br />

Peninsula to the east, Fat Tong Chau to the north and Tit Cham Chau to the south.<br />

The planting will also act as an extension of the perimeter structure planting, breaking up the scale of the<br />

development and reducing the effects of abrupt changes in land use. The planting will be similar in<br />

composition to the external structure planting but will include some less proven species to increase the<br />

options to create more interest and identity at the detailed design stage.<br />

The landscape belts will also give some opportunity to introduce low mounding into the development,<br />

which will contribute towards ameliorating visual conflict between adjacent land uses.<br />

Roadside Planting<br />

The road network has a strong influence on the physical structure of the development and the landscape<br />

treatment will play an important role in creating a "green" framework for the development. The physical<br />

quality of the road system will, to an extent, dictate the quality of the environment within the<br />

development. Typical examples of roadside planting are shown in Figure 4.2.<br />

Tree and shrub planting is proposed along all the major access roads within the site. The planting will<br />

be used to define route ways as well as acting as visual barriers. Tree planting along the roads wiE<br />

provide shade to pedestrians and reduce glare from hard surfaces. It will help to provide visual relief<br />

from the extent of the roads and the adjacent industry.<br />

Trees and shrubs will be planted at ground level alongside the road with a high kerb to act as a physical<br />

barrier to deter casual parking and to protect the planting from splash back. A minimum width of 2.0 in<br />

service free zone will be allowed for the planters to enable uninterrupted root development.<br />

APH Consultants


Figure 4.2<br />

FOOTPATH<br />

PRIMARY<br />

STRUCTURE ORNAMENTAL<br />

ROADSIDE<br />

EXISTING HILLSIDE A VEGETATION , PLANTING SHRUBS |<br />

PLANTER<br />

t ACCESS ROAD<br />

VARIES 3M 2.SM<br />

GROUND COVER<br />

ORNAMEHTA1 SHRUBS<br />

ORNAMENTAL SHRUBS<br />

ROADSIDE TREE<br />

DEEP WATEH INDUSTRY<br />

FOOTPATH<br />

WTEBFACEZONE<br />

SECONDARY STRUCTURE PLANTING<br />

ROADSIDE<br />

PLANTER<br />

1 I<br />

i SM 3M ' 2.5M<br />

TYPICAL LANDSCAPE PLANTING<br />

APH CONSULTANTS


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

A number of more ornamental tree and shrub species have been included in the list to allow the planting<br />

design to be accentuated in the open space area and at traffic islands and roundabouts,<br />

Plant Speties<br />

Table 4.2 lists suggested plant species for the woodland structure planting, roadside planting, open space<br />

and roundabout areas. The use of individual species will be determined at the detailed design stage.<br />

All plant species have been chosen on the basis of being tolerant of the expected site climatic and substrate<br />

conditions and the anticipated low maintenance regimes.<br />

TABLE 4.2 :<br />

SUGGESTED SPECIES FOR LANDSCAPE PLANTING<br />

Location Trees Shrubs<br />

Structure Planting<br />

Acacia auricuiiformis<br />

A confusa<br />

Castanopsis fissa<br />

Eucalyptus torelliana<br />

Ficus microcarpa<br />

Hibiscus tiliaceus<br />

Litsea glutinosa<br />

Litsea raonopetala<br />

Leucanea leucaccphala<br />

Macaranga tanarius<br />

Melaleuca leucadendron<br />

Tristania conferta<br />

Duranta repens<br />

Gordonia axillaris<br />

Hibiscus schizopetalus<br />

Jasminum mesnyi<br />

Callistemon rigidus<br />

Pittosporum revoiutum<br />

Tamarix chinensis<br />

Roadside Planting and Amenity<br />

Planting<br />

Aleurites moluccana<br />

Casuarina equisetifolia<br />

Cinnamonum camphora<br />

Dracontomelon dao<br />

Erythrina crista-galli<br />

Eucalyptus citriadora<br />

Grevillea banksii<br />

Melia azedarach<br />

Pongamia pinnata<br />

Reevesia thrysoidea<br />

Thespesia populunea<br />

Schefflera octophyila<br />

Stercuiia lanceolata<br />

Rhododendron spp<br />

Gardenia jasminoides<br />

Ficus microcarpa "Golden Lear<br />

Schefflera arboricola<br />

Hamelia patens<br />

Lagerstroemia speciosa<br />

Rosa multiflora<br />

Parthenocissus himalayana<br />

Livistonia chinensis<br />

APH Consultants<br />

Page 4-8


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

SECTION 5<br />

ENGINEERING STUDIES<br />

5.1 ENGINEERING INVESTIGATIONS<br />

5.1.1 Introduction<br />

Site investigations and mathematical modelling have been carried out to establish the engineering and<br />

marine parameters needed for the planning and outline design of the development. These include:<br />

> Geophysical and geotechnical site surveys<br />

> Wave modelling<br />

> Tidal flow modelling<br />

+ Siltation modelling<br />

5.1.2 Geotechnical Data<br />

A geophysical survey was carried out in June 1992, from which the contoured seabed levels and contoured<br />

levels of the underlying soil strata, together with isopaches of dumped material, have been obtained. A<br />

borehole survey was completed in July 1992 which provided a visual identification of the soil strata<br />

supported by in-situ and laboratory tests.<br />

An assessment of the site investigation data indicates the general lithological sequence from the seabed as<br />

being fill (previously dumped material), manne deposits, alluvium, completely decomposed volcanic tuff<br />

and bedrock of moderately to slightly decomposed tuff. The following levels and thicknesses can be<br />

expected:<br />

Seabed level<br />

Fill (dumped material):<br />

Marine Deposits<br />

Alluvium<br />

Rock<br />

generally -3 mPD to -12 mPD, with high seabed levels occurring<br />

towards the north of the site in the dumping ground area.<br />

fill of unknown sources occurs over a large area of the northern site, up<br />

to 10 m thick and comprising poorly sorted clayey silt, sand, gravel and<br />

cobbles.<br />

generally 11 m to 15 rn thick, reducing to zero at the edges of the site<br />

where the bedrock nses to the adjacent peninsula and island cliffs. The<br />

marine deposits are classified as slightly sandy clayey silt. The base of<br />

the marine deposits is at approximately -26 mPD.<br />

17 to 30 m thick, generally 26 m thick over the western half of the site,<br />

reducing to zero towards the eastern (peninsula) edge and along the<br />

northern and southern (island) edges. The alluvium is classified as a<br />

sandy very clayey silt.<br />

the bedrock comprises a moderately to slightly decomposed volcanic tuff<br />

at levels -55 mPD to -60 mPD along the western edge (berthing line) of<br />

the site, rising towards the eastern, northern and southern cliff edges of<br />

the site. Overlying the bedrock is a layer of highly decomposed<br />

volcanic tuff, varying in thickness between 1 m and 8 m but generally<br />

about 3 m to 4 m thick.<br />

APH Consultants<br />

Page


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Typical geological cross-sections through the site and borehole locations are shown in Figures 5.1 and 5,2.<br />

The geophysical survey included a localised, close-spaced seismic survey giving full coverage over an area<br />

of the dumped fill material. While there was some evidence of magnetic anomalies in this layer, the<br />

survey revealed no evidence of obstructions. Although this is not conclusive evidence that the entire site<br />

is free of obstructions in the fill layer, it would appear unlikely that operations such as the installation of<br />

wick drains will prove problematical.<br />

It should be noted that only a limited borehole investigation has been carried out for this Study and<br />

further, more detailed site investigation will be required for the detailed design stage of the development.<br />

5.1.3 Tidal Flow Modelling<br />

Modelling Computations<br />

Tidal flow simulations have been performed for the dry season with the well mixed water condition and<br />

for the wet season with the stratified condition. Only spring tides have been considered, as it is adjudged<br />

that these tides will produce the highest and most critical flow conditions. The simulations were<br />

performed with a 100 m grid model of the Study Area and were carried out for the following cases:<br />

* the baseline condition, without any development in Area 137 but including all planned and<br />

committed projects in the model's area of influence (included in all subsequent development<br />

simulations);<br />

* the Area 137 development;<br />

* Area 137 and the proposed Area 131 developments;<br />

> an initial development in the south of Area 137;<br />

> an initial development of Area 137, with the proposed Area 131 development.<br />

Flow Modelling Results<br />

Figures 5.3 to 5.5 detail the vector plots for the dry season peak tidal currents in the upper layer for the<br />

baseline condition, for the Area 137 development and Area 131 development,<br />

A detailed assessment of the changes in the flow condition between the baseline and the development<br />

scenarios has been derived by analysis of the current velocity time histories. The assessment analysed<br />

changes in flow conditions at Lei Yue Mun, within Tseung Kwan O, in the Tathong Channel opposite<br />

Area 137, at the fishculture zone to the north of Tung Lung Chau and in the south Tathong Channel.<br />

GeneraEy, the Area 137 development will have little if any effect on the overall tidal flow conditions in<br />

the area. An initial development in the south of Area 137 would have virtually the same effect on the flow<br />

conditions as the full development.<br />

The main effect of the Area 131 development is on the flow conditions inside Tseun* Kwan O. Whilst<br />

resulting in lower velocities at the entrance to the bay, the configuration of the breakwater results in the<br />

diversion of flow deeper into the northern areas of the bay.<br />

5,1*4 SHtation Modelling<br />

SUtation simulations have been performed by means of a 250 m grid mud flow model The cases<br />

considered are the same as those simulated with the tidal flow model. As siltation occurs mainly during<br />

the wet season and changes in siltation will be largest with spring tides, the simulations have been carried<br />

out for these conditions. Ills approach is considered sufficient to determine the -eneral impact oa<br />

siltation of the development of Area 137. *<br />

APH Consultants "~ — TT<br />

Page >2


Figure 5.3<br />

SPRING TIDE<br />

Peak abb currants<br />

SPRING TIDE<br />

0 !<br />

Peak flood currants<br />

DRY SEASON PEAK TIDAL CURRENTS<br />

BASELINE CONDITION<br />

APH CONSULTANTS


Figure 5.4<br />

SPAING TIDE<br />

Peak abb currants<br />

SPRING TIDE<br />

Peak Hood currants<br />

DRY SEASON PEAK TIDAL CURRENTS<br />

WITH AREA 137<br />

253 APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

The results show low suspended sediment concentrations in the Study Area. At the modelled output<br />

stations the concentrations in the upper layer are generally less than 5 ppm. The same applies to the lower<br />

layer with the exception of the mid-Tathong Channel where the concentration increases to 8 ppm during<br />

peak flood conditions and the south Tathong Channel where the concentration is about 10 ppm during the<br />

full tidal cycle. Changes in the concentration with all the development scenarios compared to the baseline<br />

are very small.<br />

With all the modelled cases, the suspended sediment concentrations are very low by most estuarine<br />

standards. Because of this limited natural sediment supply, siltation rates in the area susceptible to<br />

deposition of fine sediments will be low, which is confirmed by the simulation results. Figure 5.6<br />

presents the mud deposition contour plot for the baseline simulation. As the Figure indicates, in most of<br />

the Tseung Kwan O area the deposition rate is in the range of 0.0 to 0.05 kg/nr per tide. This rate<br />

corresponds to a siltation in the order of 1 cm per year. In the area northwest and south of Tung Lung<br />

Chau the deposition rate is 0.05 to 0.10 kg/m 2 per tide, corresponding to a siltation in the order of 2.5<br />

cm per year.<br />

The mud deposition contour plot for the case with Area 137 development is presented in Figure 5.7.<br />

Compared to the baseline, there is a limited increase of deposition rate west of Tung Lung Chau and a<br />

decrease of the deposition rate in the area west of Area 137. These changes are relatively small, the more<br />

so in view of the generally very low deposition rates in the area. The cases with an initial development<br />

and with Area 131 showed almost identical deposition rate patterns as above.<br />

It is therefore concluded that the Area 137 and Area 131 developments will have a very limited impact<br />

on sediment movement and siltation. In the overall area the changes in siltation rate will be effectively<br />

negligible.<br />

5.1.5 Wave Modelling<br />

Mean. Annual Wave Climate Analysis<br />

The offshore mean annual wave climate is based on VOS data for the area off Hong Kong covering the<br />

period from 1949 to 1991.<br />

When propagating from deep water to Area 137, the wave heights will reduce, mainly by refraction and<br />

the sheltering effects of the offshore islands and headlands. Other phenomena which will affect the wave<br />

height are dissipation by bottom friction and wave generation by wind.<br />

The refraction and the sheltering effects have been established by means of the OUTDJF model. Results<br />

from the computations were obtained for locations adjacent to the Area 137 quay wall. Effects of bottom<br />

friction on the wave height have been established by means of the ENDEC wave model. Computations<br />

were performed for inshore wave heights from Hs=0.5 up to 4 m. The bottom friction effects were found<br />

to be small as the water depth in the Tathong Channel is relatively deep in relation to the mean annual<br />

waves. Wave generation by wind was analysed by means of the JONRAY model.<br />

By use of the results of the OUTDDF, ENDEC and JONRAY modelling the offshore mean annual wave<br />

climate was transformed to the local wave climate adjacent to the Area 137 quay wall as given in Table<br />

5J. Wave directions will range between 160 and 195 degrees N. The local generated wave climate at<br />

Area 137, based on the wind climate and the results of the JONRAY computations is presented in the<br />

Table 5.2. Periods of the local generated waves will be less than 5.0 s.<br />

APH Consultants<br />

fagg


Figure 5.6<br />

HO<br />

Tung Lung j —<br />

oo<br />

0.00 to 0.05 !cg/m**2 / el da<br />

-/o o o ao o<br />

0.05 to 0,10 kg/m**2 /<br />

00<br />

OO<br />

O O<br />

O O 0-15 to 0.20 kg/m**2 /<br />

aa<br />

a<br />

0-20 to 0.25 kg/m^2 / tide<br />

O O 0 O O<br />

00-^0000^0<br />

oooooooooo<br />

oooooooo<br />

MUD DEPOSITION CONTOUR PLOT<br />

BASELINE CONDITION<br />

APH CONSULTANTS


Figure 5.7<br />

< 0.00 kg/n»**2 / tld*<br />

0,00 kg/»**2 /tide<br />

0,00 to 0.05 kg/»**2 / eld»<br />

0,05 to O.JO kg/m**2 / crd«<br />

0.10 to 0.15 Seg/flM>*2 / tick<br />

0,15 to 0.20 kg/»**2 / trd-<br />

0*20 to 0.25 kg/m**2 / tfd«<br />

> 0.25 kg/»**2 / «ld«<br />

00000<br />

^OOOO<br />

O<br />

MUD DEPOSITION CONTOUR PLOT<br />

WITH AREA 137<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 5.1 : MEAN ANNUAL WAVE CLIMATE AT AREA 137<br />

Exceedence of wave height in percentage of time<br />

Hs(m)<br />

0.10<br />

0.20<br />

0.30<br />

0.40<br />

Tp>0s<br />

29.80<br />

21.42<br />

14.71<br />

8.48<br />

Tp>5s<br />

15.92<br />

12.92<br />

962<br />

5.95<br />

Tp>7s<br />

5.83<br />

5.04<br />

4.13<br />

3.06<br />

Tp>9$<br />

1.64<br />

1.49<br />

1.28<br />

1.06<br />

Tp>13s<br />

0.22<br />

0.18<br />

0.13<br />

0.10<br />

0.50<br />

5.62<br />

4.24<br />

2.21<br />

0.74<br />

0.08<br />

0.60<br />

3.64<br />

2.87<br />

1.60<br />

0.58<br />

0.07<br />

0.70<br />

1.82<br />

1.50<br />

0.99<br />

0.40<br />

0.06<br />

O.SO<br />

1.37<br />

1.08<br />

0.82<br />

0.31<br />

0.03<br />

0.90<br />

0.83<br />

0.71<br />

0.51<br />

0.21<br />

0.03<br />

1.00<br />

0.63<br />

0.55<br />

0.42<br />

0.16<br />

0.03<br />

1.25<br />

0.24<br />

0.21<br />

0.19<br />

0.10<br />

0.02<br />

1.50<br />

0.06<br />

0.05<br />

0.04<br />

0.02<br />

0.00<br />

1.75<br />

0.01<br />

0.01<br />

0.00<br />

0.00<br />

0.00<br />

200<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

0.00<br />

TABLE 5.2 :<br />

LOCAL GENERATED WAVE CLIMATE<br />

Exceedence of wave height in percentage of time<br />

Hs(m)<br />

Direction<br />

SE<br />

S<br />

NW<br />

0.1<br />

6.0<br />

2.7<br />

1.2<br />

0.2<br />

0.9<br />

0.6<br />

0.4<br />

0.3<br />

0.2<br />

0.1<br />

0.1<br />

0.4<br />

-<br />

-<br />

-<br />

Extreme Wave Climate Analysis<br />

The offshore extreme wave climate was derived from a hindcast study undertaken by the Hong Kong<br />

Polytechnic through the use of a parametric wave prediction tnodei with input data from 14 selected<br />

typhoons which have occurred during the last 42 years.<br />

Table 5.3 presents the resulting extreme wave climate at Area 137. The direction of these extreme waves<br />

will be between 170 degrees N and 190 degrees N. Wave periods will range from 10 s to 16 s.<br />

APH Consultants Page 5-4


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 5 J :<br />

INSHORE EXTREME WAVE CLIMATE<br />

Return Period<br />

(jrs)<br />

1<br />

10<br />

20<br />

50<br />

100<br />

200<br />

Hs<br />

(m)<br />

1.8<br />

2.7<br />

3.2<br />

3.7<br />

4.0<br />

4.3<br />

The local generated wave climate, established from the extreme wind climate and the JONRAY results<br />

is presented below in Table 5.4. Periods of these local generated waves will range between 3 s and 6 s,<br />

TABLE 5.4 :<br />

EXTREME LOCAL GENERATED WAVE CLIMATE<br />

Significant Wave Height Hs (m)<br />

Return Period<br />

Direction<br />

(yrs)<br />

SE<br />

S<br />

SW<br />

1<br />

0.5<br />

0.5<br />

0.4<br />

10<br />

0.8<br />

1.2<br />

0.7<br />

20<br />

1.0<br />

1.5<br />

0.8<br />

50<br />

1.2<br />

1.9<br />

0.9<br />

100<br />

1.3<br />

2.1<br />

1.0<br />

200<br />

1.4<br />

2.4<br />

1.1<br />

5.2 LAND FORMATION<br />

5.2.1 Method of Site Reclamation<br />

The site reclamation can be undertaken with or without the removal of the soft marine deposits. Removal<br />

of this layer and replacement with a granular fill would give a reclamation base with stronger and more<br />

certain engineering properties and reduce considerably the time required for consolidation. This method<br />

would, however, involve the dredging and disposal of a large volume (some 10 to 15 Mm 3 ) of the soft<br />

marine deposits, with associated environmental impacts. The dredged material would then require<br />

replacement by additional fill.<br />

It is proposed that the site reclamation should be undertaken with the minimum removal of the marine<br />

deposit layer, thus reducing the environmental impacts, fill requirements and minimising the extent of mud<br />

disposal.<br />

APR Consultants Page 5-5


Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

The placement of fill material over the marine deposit and underlying alluvium will result in the<br />

consolidation of these materials and the consequential settlement of the reclamation. This consolidation<br />

would normally take place over a very long period of time and accelerated consolidation will therefore<br />

be required in order to complete the reclamation within an acceptable timescale.<br />

5.2,2 Settlement and Consolidation Time<br />

The settlement of the underlying layers has been calculated using geotechnical data determined from the<br />

site investigation. For a finished reclamation level of -1-5.0 mPD, total settlement has been estimated to<br />

range from 1.8 m in the north of the site to 3.1 m in the south, with consolidation in both the marine<br />

deposit and alluvium layers. The difference in settlement is due to the varying thickness of marine<br />

deposits and because the dumped material in the north of the site has already induced a certain amount<br />

of consolidation in the underlying soft layers.<br />

The rate of consolidation of the soft cohesive'material is dictated primarily by the rate of drainage within<br />

the layer ie the rate at which excess pore water pressures can dissipate. In order to accelerate the<br />

consolidation process, it is proposed that vertical (wick) drains be installed in the soft material. The<br />

spacing of these drains together with the weight of the fill will determine the rate of consolidation.<br />

Using a preload surcharge of 1.5 m and with vertical drains installed to -24 mPD, spaced at 1.7 m in a<br />

triangular pattern, full primary consolidation could be achieved within 6 months of completion of the<br />

reclamation construction. The small amount of the remaining secondary compression will occur over an<br />

indefinite period of time and would not normally present any significant design or construction problems.<br />

In the north of the site where some consolidation of the marine deposits has already taken place, full<br />

primary consolidation could be achieved within 2 years without the installation of wick drains or<br />

accelerated through the introduction of vertical drains as outlined above.<br />

The design should be confirmed by further site investigation during the detailed design stage of the<br />

project. In addition, when installing the drains, the spacing should be checked and optimised during the<br />

first phase of the installation by adopting different wick drain spacings and monitoring the consolidation<br />

results.<br />

5.2*3 Construction Methodology<br />

The primary constraint when filling on top of the marine deposit is the low shear strength. In order to<br />

avoid instability and mixing of mud and fill material it is necessary to ensure that:<br />

+ the fill is placed in layers of uniform thickness;<br />

* the leading edge of the fill forms a shallow slope, typically 1:6 or less.<br />

Water depths in the general fill area are insufficient to permit access by loaded trailer dredgers and it is<br />

therefore envisaged that the base sand fill layers would be placed by using a spreader barge supplied by<br />

a cutter suction dredger or a trailer dredger with a self unloading facility. These base layers should be<br />

built up to provide a 2 m thick sand blanket.<br />

Once die base layers have been placed, the bulk filling can commence. The fill should be placed in<br />

relatively low lifts (2 to 3 m) to an initial level of -f 2.0 mPD, which is considered high enough for the<br />

installation of vertical drains and placing of the surcharge fill. For the staged construction of the site a<br />

50 m wide embankment, with temporary bund walls if necessary and a flat 1:6 (minimum) fill slope, is<br />

placed along the edges of the reclamation area, where not contained by permanent edge structures.<br />

Construction of the embankment around die reclamation area should be completed first, or ahead of the<br />

reclamation between the embankments. Installation of vertical drains and subsequent placing of the<br />

APH Consultants Page 5*6


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

surcharge fill should start at the embankments and continue into the reclamation area. Figure 5.8 indicates<br />

such a construction sequence.<br />

After raising the reclamation level from 4-2.0 mPD to 4-5.0 mPD, a surcharge fill is placed which<br />

incorporates the 3,1 m fill required to take up the predicted settlement and a 1.5 m preload fill. The total<br />

(theoretical) height of the finished elevation of the surcharge would then be 4-9.6 mPD.<br />

In view of the restrictions of water depth, it is likely that most of the bulk fill would be placed either by<br />

a cutter suction dredger pumping ashore from a rehandling basin supplied by barges or trailers or by<br />

trailer dredgers pumping ashore through floating pipelines.<br />

In the event that a land sourced fill material is utilised, or where the reclamation site is used for public<br />

dumping, the first layers over the sand blanket would need to be placed by careful bottom dumping from<br />

barges so as to build up a layer with minimal disturbance to the previously placed sand or fill. Once this<br />

barge-dumped material has reached a level of -2.0 mPD, end tipping from land can commence.<br />

Installation of vertical drains is assumed to take place in the dry, after the initial fill has reached a level<br />

of -f 2.0 mPD. This presumes that the fill material is either sand, or, if land sourced material is used,<br />

that the maximum particle size is less than 50 mm. For fill materials which do not meet the above stated<br />

requirements, the vertical drains will have to be installed by marine based equipment after the 2 m sand<br />

blanket has been placed.<br />

5.3 EDGE STRUCTURES<br />

53.1 Method of Construction<br />

Removal of the marine deposits from beneath the seawalls has been considered necessary at this stage.<br />

The reasons for this are twofold:<br />

*• from a structural point of view, removal of the soft marine deposit layer eliminates the uncertainty<br />

associated with the use of this material as a foundation layer - settlement of the quay structure<br />

could be critical to its performance;<br />

+ in comparing the construction of gravity structures, retaining structures and open piled structures,<br />

removal of the marine deposits has been found to be more cost effective.<br />

However, it is possible that during the detailed design stage, a more thorough site investigation of the<br />

seawall alignment could indicate that the marine deposits may have a higher strength than normally<br />

associated with this material, and time and cost effective retention could be considered.<br />

The construction methodology for removal of marine deposits involves dredging a trench along the line<br />

of the edge structure and replacing the marine deposits with a granular fill. The site characteristics<br />

suggest that most of the dredging is likely to be undertaken using grab dredgers, possibly supplemented<br />

by trailers in those areas where access permits.<br />

The method which is employed to backfill trenches will largely depend on the nature of the material used<br />

as backfill. In the case of rock, it is likely that the fill would be delivered in conventional dump barges<br />

or on pontoons. Backfilling would be achieved by dumping from the barge or by bulldozing the fill off<br />

the pontoon. In the case of sand backfill, filling would be carried out by controlled bottom dumping from<br />

barges, or trailers where there are no access constraints, or by direct delivery to the bottom of the trench<br />

using downpipes.<br />

APH Consultants<br />

p ^


Figure 5.8<br />

TEMPORARY -~v<br />

8UNDWA1LS \ SO PD<br />

A \J^<br />

-^^i^1<br />

wrWSnWG Sg'A BOTTOM i<br />

i<br />

VERTICAL NICK 1<br />

DRAINS {<br />

_ — . , — — !„<br />

50m CM8ANKWENT ARQUNO<br />

RECLAMATION SECTIONS<br />

4-2.0 mP.O.<br />

i i qftmru<br />

in:::<br />

—uu I Iiii<br />

H-hfHHH-H<br />

f4- ill ii —^s^--<br />

}<br />

i<br />

I<br />

!1<br />

iiii<br />

Mi!<br />

Mil<br />

iiil<br />

1111<br />

Mi!<br />

HIM<br />

illll<br />

Iiii!<br />

11 1 !! EMBANXilENT J<br />

Hi |f SLOPE<br />

Hill<br />

lit! ill!<br />

1M1 LLLJJ<br />

1MM<br />

LUU<br />

{Hi!<br />

LLLLJ ,<br />

STAGE 1 • PLACING FILL FOR EMBANKMENT AND INSTALLATION OF WICK DRAIN<br />

STAGE 2 - RECLAMATION BET\VEEN EMBANKMENT AND INSTALLATION OF WICK DRAINS<br />

50m EMBANKMENT AROUND<br />

RECLAMATION SECTIONS<br />

TEWPOARAY -v<br />

BUNOWAU.S \<br />

\ * 5 0 mP 0<br />

+• 9 8 mP O<br />

. ,r-r- "^ l<br />

£ +ZO mP.O. ^V<br />

, \ _^^ffi^MHiffmin<br />

^sfr^"*^7^i-rcji'^i*m<br />

v - 1 — ii i f i —:i i<br />

•>• ISs**."" TITT^ "~ T ,.""<br />

{• ' !f] j^*^15^1^-----<br />

__ r«Tvv "..T~-~^^ . ^f^lSTWC SE4_30nQH.J_ LJ _LJ LI^ LLLL Li_Ll<br />

«"' r i i ^*~i-**.<br />

-i - — 1 1 j jj. . .. _ i<br />

! i MM! (Hi {(lit Mi ii EW8ANKMEKT J<br />

VERTICAL -WICK 1 I I I i 1 1 II I I Mill ill!! SLOP^<br />

MAINS ! I Hill 111! HIM II! ii<br />

I i iiiii Hi!<br />

i M i M 1 1 1 m i<br />

iim<br />

mil<br />

Ml ii<br />

nin<br />

STAGE 3A -<br />

PLACING PRELOAD FILL ON EMBANKMENT AND SUBSEQUENTLY<br />

ON RECLAMATION AREAS<br />

TEMPORARY RETENTION —-v<br />

EMBANKMENT / SEAWAUL \<br />

—- ORIGINAL SURFACE FROM WHICH TMCX<br />

ORAJNS MERE tNSTAUJEO<br />

+ S.OmPD. HNISHED SURFACE AFTER<br />

REMOVAL OF EXCESS SURCHACE HLL<br />

i-SETTLED PROFILES<br />

i—SETTLEMENT<br />

STAGE 38 - SETTLED PROFILE / SURFACE AFTER PRELOADING<br />

RECLAMATION WITHOUT REMOVAL OF MARINE DEPOSITS<br />

993 APH CONSULTANTS


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Thereafter, for revetment structures, a bund wall is constructed and the bulk filling behind the edge<br />

structure is undertaken in low lifts of 2 to 3 m. The increased stability afforded by the greater shear<br />

strength of the granular trench material means that the edge bund can be constructed to the required design<br />

slope (1:2). Wick draining and surcharging behind the edge structure are the same as previously<br />

described. The quay structure is constructed on completion of the filling operation. For sheet pile walls,<br />

the rock bund is not required and after construction of the sheet piling the landward fill is placed up<br />

against the wall, together with installation of anchors.<br />

5*3.2 Selection of Edge Structure<br />

There is a wide range of structural concepts available for the provision of the quay structures, which can<br />

be divided broadly into gravity structures, anchored retaining structures and open piled structures. The<br />

suitability of each type will vary as a function of the design requirements and the physical and<br />

environmental characteristics at the site. In general, the least cost alternative types of edge structures have<br />

been selected where these are technically appropriate. The selection and design of these edge structures<br />

will be subject to further analysis in the detailed design stage when more information with respect to soils<br />

properties and design loadings is available.<br />

Seawalls<br />

The type of seawall proposed for locations where no berthing structure is required is a revetted slope with<br />

rock armour. This is the normal type of seawall construction in the Territory for locations exposed to<br />

moderate wave action, since the wave run-up, overtopping and reflection is reduced from that associated<br />

with a vertical faced structure. It is also proposed that the seawall behind the dolphin berths along the<br />

PHI frontage should be a revetted slope with rock armour.<br />

The crest level of the seawall is 4-6.5 mPD, to prevent overtopping for the mean annual wave conditions.<br />

Any overtopping that may occur due to runup during extreme storm events will be contained in a drainage<br />

catchment behind the wall crest. At the more exposed southern corner of the site, off Tit Cham Chau,<br />

the crest level is raised to 4-7.5 mPD.<br />

Details of the seawalls are shown in Figure 5.9.<br />

Dolphin Berths<br />

It is proposed that the deep water bulk liquid berths (chemical, LPG, fuel and naphtha) should be dolphin<br />

berths, situated in front of a revetted slope seawall (Figure 5.9). It is normal practice to provide dolphin<br />

berths for bulk liquid vessels, since the pipe manifolds are located amidships, and the loading/unloading<br />

platforms can therefore be of limited length. Breasting dolphins with appropriate fendering are located<br />

on either of the loading platform and are set slightly seaward of it, so that the berthed vessel is kept clear<br />

of the loading platform. Mooring dolphins are also provided on either side of the berth, set back 30 m<br />

behind the berthing line, to take the breast, head and stern lines from the berthed ship. Catwalks are<br />

provided for access to the breasting and mooring dolphins.<br />

limited vehicle access to the loading platform would be provided by a short access bridge, which would<br />

also carry the pipelines to the shore. The level of the deck of the loading platform and access bridge<br />

would be 4-6.5 mPD to avoid excessive overtopping under extreme conditions and to reduce wave forces<br />

on the underside of the structures.<br />

The loading platform, breasting dolphins and mooring dolphins would all be piled structures. Most of the<br />

reinforced concrete work would be tn-situ, but there is some scope for precasting beams and slab soffits.<br />

There is no need for the removal of marine deposits under the piled structures.<br />

APH Consultants<br />

pag€


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

The dredged level of these berths would be -14 mPD.<br />

The berth layouts have been based on utilisation by the following "design" ships:<br />

Berth No.l - Naptha tankers, LOA 200 m 30,000 DWT<br />

Berth No.2 - LPG tankers, LOA 80 m 1,200 DWT<br />

Berth No.3 - Chemical transhipment tankers, LOA 120 m 8,000 DWT<br />

Berth No.4 - Chemical parcel tankers, LOA 185 m 40,000 DWT<br />

Berth No.5 - Fuel oil tankers, LOA 225 m 45,000 DWT<br />

Outer Marginal Berths<br />

A deep water marginal berth is proposed for the northernmost 200 m of the outer berthing line. The<br />

dredged level at this berth would be -14 mPD. The berth would be used by ocean-going vessels serving<br />

the DWFs at Area 137, or by smaller coastal and river trade vessels. Since the import, transhipment or<br />

export cargoes handled at these berths will be break-bulk general cargo, or possibly small quantities of<br />

dry bulk cargo, there is a need for a wide apron immediately behind the berthing face on which mobile<br />

cranes, forklift trucks, tractors and trailers and lorries may operate. No requirement is envisaged for fixed<br />

or travelling cranes to serve this multi-user berth.<br />

The type of quay proposed is an open deck on piles with a rock armoured revetted slope (see Figure<br />

5.10). The location is exposed to some wave action and a sloping revetment with open-piled structure is<br />

therefore preferred to a vertical faced structure. In addition, wave conditions during construction may,<br />

on occasions, make it difficult to construct alternative forms of quay such as sheet piling at this location.<br />

The reinforced concrete deck could be cast in situ; again there is scope for precasting the beams, slab<br />

soffits, fender and rear downstands.<br />

Basin Marginal Berths<br />

The basin berths in the north of the site would be used for transhipment and export of PHI related<br />

products in containers, and for the import, transhipment and export of DWI goods. The SENT Landfill<br />

marine access berth would be dedicated to the unloading of the SENT Landfill. The basin would be<br />

dredged to -10 mPD.<br />

A large degree of protection from wave action is afforded by the configuration of the basin. There is<br />

therefore not the same need to ensure minimal wave reflections at the berths as at the outer berthing line.<br />

In addition, conditions during construction will be calmer.<br />

An anchored steel sheet piled retaining wall, with removal of marine deposits, has been found to be more<br />

economical than other forms of marginal quay wall construction. It is therefore proposed that the basin<br />

marginal quays should be constructed with steel sheet piles anchored to suitable anchorages set back<br />

behind the quay (see Figure 5.11).<br />

A 50 m wide apron behind the berthing fece is required for the operation of cargo handling equipment<br />

and lorries. Again, no requirement for fixed or travelling cranes to serve the berths is envisaged.<br />

The cope level would be 4-5.0 mPD. The limited wave action in the basin reduces the likelihood of runup<br />

and overtopping.<br />

APH Consultants Page 5-9


5.9<br />

QUAY STRUCTURES<br />

SECTION THROUGH DOLPHIN BERTH JETTY AND REVETMENT<br />

APH CONSULTANTS


Figure 5.11<br />

QUAY STRUCTURES<br />

SECTION THROUGH SHEET PILE WALL<br />

APH CONSULTANTS


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

5.4 FILL REQUIREMENTS AND SOURCES<br />

Estimates of fill requirements for the proposed development in Area 137 indicate a total requirement for<br />

approximately 15 Mm 3 , based on the assumption that the marine deposits will be left in place in the<br />

general fill areas.<br />

Whilst no allocation of marine fill has yet been made for Area 137, it is possible that fill may be available<br />

in the borrow areas of North, Mid and South Tathong and East Tung Lung Chau. These borrow areas<br />

are already allocated to projects which are either in progress or about to commence and it is therefore not<br />

possible to identify at this stage those parts of the borrow areas which will still contain economic resources<br />

when they are handed back and become available for Area 137 and other projects. In the event that<br />

insufficient marine fill is available, land sourced fill would need to be used. Land sourced fill may be<br />

available from Anderson Road Quarry, where some 6.7 Mm 3 of overburden will need to be disposed of<br />

from 1994 onwards. However, it is not certain at this stage whether this material would be available for<br />

the Area 137 development. The formal allocation of fill for Area 137 would be made by FMC at the<br />

detailed design stage.<br />

An alternative source of fill material is screened construction waste, or public dumping. The use of this<br />

material is attractive not only because it would be a very low cost fill but it also saves valuable landfill<br />

space. Whilst the volume of construction waste material produced in the Territory is not sufficient to meet<br />

the demands of a fast track construction programme, this would be a useful source of fill for on-going<br />

reclamation after, for example, the early establishment of an initial development.<br />

5.5 DREDGING REQUIREMENTS AND DISPOSAL<br />

Dredging in Area 137 will be required to deepen the berthing areas and approach channels and to remove<br />

unsuitable material from beneath the seawalls and quay structures. The total volume to be dredged has<br />

been estimated to be around 2.9 Mm 3 for the construction of the full development. This is made up of<br />

0,5 Mm 3 to be dredged from berthing areas and approach channels and 2.4 Mm 3 from seawall trenches.<br />

The disposal of unsuitable materials which will be dredged in the Territory in the coming years is<br />

becoming a matter of increasing concern. The FMC Database of Fill Requirements and Surpluses (March<br />

1992) estimates the volume of mud which will arise from dredging and reclamation projects during the<br />

period 1992 to 2000 to be 330 Mm 3 . Set against this volume, the disposal of 2.9 Mm 3 of dredged material<br />

from Area 137 should not present any particular difficulty. The material may be disposed of in redundant<br />

borrow pits that are expected to be available at the time; alternately, the material may have to be disposed<br />

of at gazetted dumping grounds.<br />

Dredging of Contaminated Sediments<br />

From sampling and testing in this area prior to this Study and from testing carried out as part of the Area<br />

137 site investigation, it is apparent that some sediments to be dredged from Area 137 are likely to contain<br />

significant concentrations of trace elements.<br />

Given this conclusion, the dredging and disposal of these sediments requires particular care to minimise<br />

the release and resuspension of contaminated materials. Suitable dredging procedures would include fitting<br />

grab dredgers with closed grabs and operating grabs within silt curtains.<br />

The disposal of contaminated material would depend on the availability of disposal sites for contaminated<br />

material at the time. Capping the contaminated material with non-contaminated spoil is the most likely<br />

solution to disposal problems but this will depend to a large extent on the release of suitable allocations<br />

for spoil disposal and the comparative timing of the various projects producing spoil.<br />

APH Consultants<br />

Page >lti


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

5.6 CAVERN DEVELOPMENT<br />

The feasibility of rock cavern development in the vicinity of Area 137 has been examined for storage of<br />

dangerous goods.<br />

GEO have carried out a preliminary study of the geological potential for cavern development in the<br />

vicinity of Area 137. Three sites have been identified of which the closest and most suitable is within the<br />

Clearwater Bay Country Park adjacent to the site. Four caverns could be constructed at this location,<br />

generating a storage area of some 1.6 ha and producing some 325,000 m 3 of rockfill for use within the<br />

reclamation.<br />

The approach to the minimisation of risks for each PHI site, as discussed in Section 3, has been to<br />

concentrate the high risk activities and storage in one area and use lower risk activities as buffers on the<br />

boundaries between each site. The marine related import/export of materials has, naturally, lead to the<br />

location of the higher risk activities in close proximity to the berths. The adoption of further removed<br />

cavern storage would significantly increase' the land transfer distances and hence, spread the area of<br />

potentially high risk activities. This could move the boundary of acceptable risk further north and possibly<br />

into the TKOEE and SENT Landfill areas. Moreover, material import and export from the storage tanks<br />

would be effectively continuous. This may well be a departure from the more conventional use of caverns<br />

for the long term storage of potentially hazardous products, often in small unitised volumes.<br />

The total quantity of excavated material from the caverns is small in relation to the site reclamation<br />

requirements and would not form a significant contribution. The cost of formation of the caverns would<br />

depend upon the nature of the lining and tunnel support requirements, but is likely to be an order of<br />

magnitude higher than that associated with conventional reclamation.<br />

It is therefore considered that the relative remoteness of the potential sites for cavern development, as well<br />

as cost considerations, effectively rules out the adoption of caverns for storage in this instance.<br />

5.7 HIGHWAYS AND ROADS<br />

5.7.1 Site Access<br />

External road access to Area 137 will be from the proposed Road D6, which will run southwards between<br />

the TKOIE and the SENT Landfill boundaries to Area 137. The proposed cross-section of D6 comprises<br />

a 7.3 m dual two lane carriageway with wide verges incorporating 3.5 m footpaths, 3.0 m planting areas<br />

and a 3.5 m cycle track. Initially, only one carriageway will be constructed to provide access to Area<br />

137. This road will be extended into Area 137 to a roundabout in the north of the site.<br />

Provision has been made in the Area 137 planning for an extension of D6 to the south of the site, along<br />

the edge of the Clearwater Bay Peninsula. Access to the south of the site is proposed by constructing the<br />

southbound carriageway of this road, ie a 7.3 m two way single carriageway road, to the southern<br />

roundabout.<br />

5.7.2 Internal Road Network<br />

Road Hierarchy<br />

The internal road network in Area 137 consists of a 13,5 m single carriageway principal access road and<br />

10.3 m (two way) and 7.3 m (one way) single carriageway secondary access roads. For all roads, verges<br />

incorporating 3,5 m footpaths and 2.0 m planting areas are provided on both sides of the road. Design<br />

APR Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

speeds adopted for the internal road network are 70 kph and 50 kph for the principal and secondary access<br />

roads respectively.<br />

Principal Access Road<br />

The 13.5 m single carriageway principal access is the main arterial road for the proposed development.<br />

It runs some 800 m from the northern roundabout intersection to the roundabout at the south of the<br />

development. The secondary access roads feed off this road to serve the individual sites.<br />

Secondary Access Roads<br />

The 10.3 m and 7.3 m (one way) secondary access roads feed off both the principal access road and the<br />

northern roundabout. Junction spacings in the north of the site are close due to the constraints of the<br />

planning layout but nevertheless maintain the standards laid down in the Transport Planning and Design<br />

Manual. Turning circles are provided at the ends of cul-de sacs. Along the northern site boundary, an<br />

access road to the SENT Landfill marine access facility is provided off Road D6.<br />

Emergency Vehicle Access (EVA)<br />

Additional reserves for Emergency Vehicle Access are provided, in particular along the seawalls. These<br />

would be paved areas which must be kept clear at ail times in the event of emergencies; they do not form<br />

part of the road network.<br />

5.8 STORMWATER DRAINAGE<br />

5.8.1 Existing Catchment Areas<br />

The study area contains two catchment types :<br />

*> areas on the south side of Fat Tong Chau and south of Tin Ha Village, consist of short steep<br />

catchments falling directly to the reclamation area;<br />

> the area around Tin Ha Village will be recontoured as part of the SENT Landfill and will<br />

discharge to Area 137 at two locations.<br />

5.3.2 Existing Drainage<br />

Two drainage culverts discharging surface water from the SENT Landfill will traverse Area 137. Flow<br />

from these culverts will be incorporated as part of the surface water drainage system for Area 137.<br />

Leachate from the SENT Landfill is collected separately and directed to the sewage treatment works.<br />

5.3.3 Drainage Requirements<br />

The following specific requirements represent a summary of the objectives for the drainage system in Area<br />

137:<br />

> security from flooding by heavy rainfall and typhoon surge with a freeboard allowance to<br />

accommodate settlement and wave action;<br />

» mitigation or at least maintaining status quo of flooding conditions in existing undeveloped areas;<br />

*• the provision of adequate surface water drainage to avoid ponding of water;<br />

* reclamation works and stoonwater outfall to be designed for 1 in 200 year storm recurrence<br />

interval;<br />

APR Consultants Page 5-12


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

+ appropriate allowance for deterioration of system performance of 10 to 15% of design discharge<br />

capacity;<br />

* no overtopping of road kerbs;<br />

> trunk drainage systems to accommodate flows from 1 in 200 year storm recurrence intervals with<br />

subsidiary drainage designed for 1 in 50 years.<br />

5.8*4 Proposed Drainage<br />

Stormwater runoff will be collected by a system of channels at the interface with undeveloped land and<br />

by box culverts discharging to sea at specific drainage outfalls constructed in the seawall. Several<br />

subcatchments are combined to minimise the requirement for drainage reserves across developable land<br />

and box culverts are located along roads wherever possible. Drainage outfalls and box culverts are<br />

designed to maintain a freeboard above high tide level (2.25 mPD) of 500 mm for large culverts and 300<br />

mm for small culverts. Figure 5.12 shows the proposed drainage layout of the site together with the<br />

catchment areas.<br />

To minimise pollutants in stormwater runoff discharging to sea in the vicinity of the development, runoff<br />

from PHI and related industry will be controlled by on-site treatment facilities. Stormwater runoff from<br />

existing undeveloped slopes will be intercepted by a system of *U* channels and silt traps, so that the<br />

initial flows from any storm will discharge only minimal accumulated debris from the road network.<br />

Significant areas of the PHI sites will be bunded and after suitable treatment, stormwater runoff from these<br />

areas will be discharged from each site to the sea by surface drainage outlets through the sea wall.<br />

5.9 WATER SUPPLY<br />

5*9.1 Existing Fresh Water Supply System<br />

An existing 150mm diameter freshwater main, along the Tai Miu Tsiu Road, serves villages on the<br />

Clearwater Bay Peninsula. Villages adjacent to the Study Area obtain their supply from this source but<br />

will be cleared under the SENT Landfill project. The existing water supply system which will supply new<br />

development on reclamation areas has been extended along Road D6 only as far as the Tseung Kwan 0<br />

Sewage Treatment Works in Area 85.<br />

5.9.2 Future Fresh Water Supply Distribution<br />

It is anticipated that the fresh water supply facilities which are proposed as part of the development of the<br />

TKODE in Area 87 will be extended south to also service Area 137. Water Services Department have<br />

advised that although initial stages of TKOIE will be supplied from existing service reservoirs, water<br />

supply to Area 137 will be made available via the principal distribution main along Road D6, from the<br />

proposed Tseung Kwan O East Low Level Service reservoir to be located in Area 106.<br />

According to the WSD programme, the service reservoir should be completed by early 1996, which is<br />

consistent with the anticipated requirements of the initial PHI development on Area 137.<br />

Fresh water-supply requirements for Area 137 have been estimated with factors used by WSD, as given<br />

in Table 5.5. Consumption rates for DWIs and PHI Related Industries are based on comparative rates<br />

for I(B) Industry. General working areas are considered low water consumers and an equivalent I(C)<br />

Industry consumption rate has been adopted in this instance.<br />

APfl Consultants<br />

p


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

TABLE 5.5 :<br />

ESTIMATED FRESH WATER USAGE<br />

Development Type<br />

Gross<br />

Area (ha)<br />

Net Area<br />

(ha)<br />

Consumption<br />

(m 3 /ha/day)<br />

Daily<br />

Usage<br />

Potentially Hazardous Industry I(C) (storage of<br />

chemicals, oil, LPG)<br />

Potentially Hazardous Industry (naptha and gas<br />

production plant)<br />

30-42<br />

10.95<br />

19.77<br />

-<br />

30<br />

•<br />

601<br />

2500<br />

Deep Water Industry I(B)<br />

22.29<br />

14.49<br />

110<br />

1594<br />

PHI Related Industry I(B)<br />

7.18<br />

4.67<br />

110<br />

514<br />

Services<br />

1.00<br />

0.65<br />

30<br />

20<br />

General Working Areas<br />

4.83<br />

3.14<br />

30<br />

94<br />

5323<br />

PHI areas will be predominantly (75%) used for storage of chemicals, oil and LPG, which are considered<br />

to have low water consumption. These industries use extensive dedicated tanking and distribution piping<br />

to minimise their water requirements for cleaning purposes.<br />

A gas production plant is proposed for the remaining PHI area. For planning purposes it has been<br />

assumed that the water consumption of such a plant will be similar to that of the existing facility at Tai<br />

Po which has a daily fresh water consumption of approximately 2,500 m 3 .<br />

The estimated fresh water consumption of 5,323 nrVday for Area 137 is greater than the present WSD<br />

allowance of 4,700 m 3 /day for this area. Although the planned 600 mm diameter trunk main along Road<br />

D6 is likely to be adequate, a further review of the adequacy of the system is appropriate when major<br />

water consumers in Area 137 and the adjacent TKOIE have been identified.<br />

Moreover, the Hong Kong and China Gas Co Ltd have advised that should a more extensive gas<br />

production facility be constructed in Area 137, overall water consumption by the gas production plant<br />

could be of the order of 8,000 m 3 /day, which would require WSD to reassess the supply provisions in this<br />

area especially with respect to the capacity of the proposed fresh water service reservoir at Tseung Kwan<br />

O East. A review of the system, including the water main feeding the service reservoir, the capacity of<br />

the service reservoir and the 600 mm diameter main leading to Area 137, will be necessary,<br />

5.9.3 Proposed Salt Water Supply<br />

Supply of salt water for flushing purposes wfll be provided to all low level areas from the fixture Tseung<br />

Kwan O East salt water pumping station located in Area 86. Further extension of these facilities is<br />

required to provide supply to both the TKOBE and Area 137. A provision for future salt water flushing<br />

has been made as part of the development of the TKOIE by a proposed 500 mm diameter main to be<br />

located in Road D6.<br />

WSD advise that the proposed salt water supply system in the area will cater for the estimated flushing<br />

water demand in Area 137.<br />

APH Consultants Page 5-14


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

5.9.4 Firefighting Water Supply<br />

WSD advise that under abnormal operation mode, the principal main on Road D6 can deliver FSD<br />

requirement of 33,000 m 3 /day for fire fighting purposes. This may, however, result in temporary inability<br />

of the distribution mains in the area to meet other water supply requirements at the same time.<br />

5.10 SEWERAGE<br />

5.10.1 Existing Sewerage Facilities<br />

No existing sewerage facilities are located within close proximity to the Study Area.<br />

The Tseung Kwan O Sewage Treatment Works is located some two kilometres north of Area 137. This<br />

plant accepts sewage from the developing Tseung Kwan O New Town. Phase I of the Tseung Kwan O<br />

Sewage Treatment Works was commissioned in 1989 and it is understood that the plant is presently<br />

operating at approximately 60% of its capacity.<br />

5.10.2 Future Sewerage Facilities<br />

A Revised Design Statement for Tseung Kwan 0 Sewage Treatment and Disposal has recently been<br />

documented. This review outlines proposed strategies for construction of the Sewage Treatment Works<br />

which are required to meet the projected New Town growth and the development of the TKOEE and other<br />

industrial developments.<br />

From the Design Statement, full development of Phase II Stage 1 of the Sewage Treatment Works will<br />

provide for 88,000 mVday in 1998. Phase n Stage 2 of the Sewage Treatment Works (2001) should<br />

provide a further increase in capacity of 50%, to around 120,000 nrVday. The ultimate planning for the<br />

Sewage Treatment Works (2011) provides for a total capacity of 192,000 m 3 /day. It is probable that the<br />

timing of the next phase of the Sewage Treatment Works will be determined by the rate of development<br />

of the Tseung Kwan 0 New Town and the TKOEE and is unlikely to be affected by the rate of<br />

development of Area 137. Variations in flows from Area 137 represent only a minor proportion of the<br />

total flow at the Sewage Treatment Works.<br />

Provision has been made for sewage flows from the Area 137 development in the Revised Design<br />

Statement. An allowance of 3,125 nrVday has been made within the design of Phase H Stage 1, increasing<br />

to 4,500 nrVday, for Phase H Stage 2 in 2001 when the full development can be expected to become<br />

operational. This is in line with WSD's estimated water supply provision for Area 137. Further, for the<br />

ultimate planning horizon, an allowance of some 36,000 nrVday from Area 137 has been made, based on<br />

the assumption of a change of land use from that currently under study to a high density industrial<br />

development such as the TKOIE.<br />

Sewage flows from the development are based on site areas as given Section 4 (Table 4J). Using the<br />

ultimate per capita daily water demand and industrial water usage rates from the Civil Engineering Manual<br />

for the various classes of consumers, dry weather sewage flows (DWF) from Area 137 have been<br />

estimated as shown in Table 5.6.<br />

APH Cojtsutiants Page 5-15


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

final Report - Main Report<br />

TABLE 5.6 :<br />

ESTIMATED SEWAGE FLOWS<br />

Land Use<br />

Gross Site Area<br />

(ha)<br />

Net Site Area<br />

(65% of Gross)<br />

(ha)<br />

Water Consumption<br />

per hectare<br />

(m 3 /day)<br />

Sewage Flows<br />

(m 3 /day)<br />

(DWF)<br />

PHI (gas)<br />

10.95<br />

7.12<br />

112.0<br />

797.44<br />

PHI (LPG/chcm/oil)<br />

30.42<br />

19.77<br />

112.0<br />

2214.24<br />

PHI related<br />

7. IS<br />

4.67<br />

112.0<br />

523.04<br />

DWI<br />

22.29<br />

14.50<br />

112.0<br />

1624.00<br />

Services<br />

LOO<br />

0.65<br />

0.08<br />

0.05<br />

Total<br />

say<br />

5,156 rrrVday<br />

5,200 mVday<br />

Should the gas production facility be more extensive than planned, Hong Kong and China Gas Co Ltd<br />

have advised that additional waste water discharge from the ultimate plant could be in the order of 2,000<br />

mVday (DWF). Together with the other planned facilities this would require that an allowance of about<br />

7,200 arVday DWF be made in the design of the Sewage Treatment Works for flows from Area 137.<br />

Advice from the consultants for the Sewage Treatment Works indicates that this increase is not expected<br />

to present any difficulties as these flows form a very small proportion of the total design flows and can<br />

be easily accommodated.<br />

In the event of a future change of land use for Area 137, there may be a significant increase of sewage<br />

flow volumes; however, adequate provision has been made in the ultimate planned capacity of the Sewage<br />

Treatment Works.<br />

No provision has been made within proposed gravity sewers in the TKOIE for flows from Area 137,<br />

which will therefore need to discharge to the treatment plant by separate sewer.<br />

5.10*3 Sewerage Network<br />

Area 137 is remote from the Tseung Kwan 0 Sewage Treatment Works, therefore sewage will be directed<br />

to a centrally located pumping station and then discharged to the Sewage Treatment Works via a rising<br />

main located within the services reserve of Road D6. To enable relocation of the SENT Landfill marine<br />

access facilities, temporary pumping of flows from these facilities into the TKOIE sewers is envisaged.<br />

Alternately, it may be possible to utilise self-contained (chemical) units, which would eliminate these<br />

sewage flows. A review of the proposed sewerage system wiU be necessary once specific operators for<br />

the development have been identified.<br />

The anticipated PHI development in Area 137 may require the inclusion of on-site treatment facilities, the<br />

extent of which can only be assessed on an individual industry needs basis.<br />

5.10.4 Sewage Disposal<br />

Initially sewage flows from the Study Area will undergo preliminary treatment at the Tseung Kwan 0<br />

Sewage Treatment Works and will then be discharged via the existing Tseung Kwan 0 submarine outfall<br />

into the Tathong Channel, Options exist for future upgrading of the Sewage Treatment Works to<br />

secondary treatment or alternatively discharging directly to the Strategic Sewage Disposal Scheme interim<br />

outfall.<br />

APH Consultants Page 5-16


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

5.11 PUBLIC UTILITIES<br />

China Light and Power Company propose to supply Tseung Kwan O from a major 400 kV substation to<br />

be established near Tseung Kwan O Town Centre. A feeder network of 132 kV circuits will then supply<br />

primary substations to be located in areas of new development. Extension of electricity services will occur<br />

as part of the staged development of the new TKOIE. Supply to Area 137 will be an extension of these<br />

facilities.<br />

Hong Kong Telephone Company intends to extend its services to areas of development as demand<br />

requires. It is intended that the regional telephone exchange is located in the Tseung Kwan 0 New Town<br />

Centre and that extension to the TKOIE and to SENT Landfill areas occurs progressively. It is understood<br />

that sufficient capacity exists within the present network for the requirements of the development in Area<br />

137.<br />

Two gas connections to the Tseung Kwan O New Town are currently available. One extends from<br />

Kowloon via Po Lam Road and the other proceeds via Clear Water Bay Road and provides for<br />

development in Area 31. A new supply via the Tseung Kwan O Tunnel is anticipated to ensure sufficient<br />

capacity for future development of the New Town. Utilisation of gas production from SENT Landfill and<br />

gas supply from the proposed gas production facility in Area 137 may also be possible.<br />

Adequate service reserves will need to be provided in road D6 for the provision of these utilities.<br />

APH Consultants Page 5-17


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

SECTION 6<br />

MARINE STUDY<br />

6.1 INTRODUCTION<br />

The recommended development layout has been studied in relation to the marine operational requirements<br />

of the development itself as well as its interaction with the other marine operations in the area. This<br />

includes the impact of shipping generated by the proposed development on the shipping in the Tathong<br />

channel; likewise the effects of passing vessels and the effects of the marine climate conditions on ships<br />

berthed at Area 137. An investigation has been carried out on the feasibility of safe arrival and departure<br />

manoeuvres under various environmental conditions, including typhoon evacuation. Navigational safety<br />

is assessed together with the requirements for existing and new anchorage facilities.<br />

During detailed design, discussions with the Hong Kong Pilots Association will be necessary to establish<br />

berthing procedures and criteria for the specific berths dependent on the type and size of vessels using<br />

such facilities.<br />

6.2 MARINE TRAFFIC<br />

6.2.1 Present Situation<br />

The present volume of ocean going traffic using the Tathong Channel is relatively small, at some 12%<br />

of the current level of arrivals in Hong Kong. This corresponds to some 2,500 arrivals per year.<br />

A traffic count was carried out to establish the movements of vessels through Lei Yue Mun and Tathong<br />

Channel. The results of this counting are summarised in Table 6.1.<br />

TABLE 6.1 :<br />

DAILY VESSEL MOVEMENTS TATHONG CHANNEL<br />

(as recorded on 14 April 1992, 06.00 - 18.00 hrs)<br />

Vessel Type<br />

East Bound<br />

West Bound<br />

Total<br />

Percentage<br />

Ocean going<br />

3<br />

3<br />

6<br />

1.2<br />

River trade<br />

16<br />

21<br />

37<br />

7.3<br />

Towed barge<br />

16<br />

13<br />

29<br />

5.7<br />

Femes<br />

1<br />

1<br />

2<br />

0.4<br />

Fishing boats<br />

64<br />

124<br />

188<br />

37.1<br />

Small craft<br />

114<br />

85<br />

199<br />

393<br />

Dredgers<br />

10<br />

8<br />

IS<br />

3.6<br />

Speed boats<br />

14<br />

14<br />

28<br />

5.5<br />

Totals<br />

238<br />

269<br />

507<br />

100.0<br />

The survey showed that vessel movements are generally constant throughout the day apart from fishing<br />

boat movements, which peak during the morning with the return of the fishing fleet. The predominant<br />

APH Consultants<br />

Page


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Find Report - Main Report<br />

traffic through the Tathong Channel is fishing boats and small vessels, which account for over 75% of the<br />

total daily vessel movements.<br />

The survey also showed that the fishing boats and small craft tend to use the Inshore Traffic Zone past<br />

Chai Wan, while the other vessels use the main Tathong Channel. The number of vessel movements<br />

within the Traffic Separation Scheme (TSS) of the Tathong Channel at present amounts to some 240 per<br />

day. The present ocean going traffic accounts for some 15 vessel movements per day.<br />

6.2.2 Future Situation<br />

The marine traffic through the Tathong Channel will increase due to the expected growth of the total<br />

traffic calling at Hong Kong and due to Vessel Traffic Management regulations and guidelines. An<br />

assumed 20% traffic share for the Tathong Channel in 2011, will result in some 7,500 arrivals or 15,000<br />

ocean going vessel movements per year (ref. Lantau Port and Western Harbour Development Study,<br />

Working Paper No. 9). This would correspond to some 40 ocean going vessel movements per day.<br />

The Area 137 development will generate additional shipping traffic in the waters to the East of Hong Kong<br />

Island. The fleet mix calling at Area 137 has been estimated based on the identified industry/land use<br />

allocation and the expected marine traffic is presented in Table 6.2. The number of river trade vessels<br />

is based on a ratio of (arbitrarily) 5 times the number of ocean going traffic.<br />

TABLE 62 : ESTIMATED MARINE TRAFFIC FOR AREA 137<br />

Ship Type Ship Size (DWT) Number of Vessel Calls Number of Vessel<br />

Per Year<br />

Movements per Year<br />

Naphtha tanker<br />

30,000<br />

12<br />

24<br />

LPG tanker<br />

1,200<br />

50<br />

100<br />

Product tanker<br />

3,000<br />

50<br />

100<br />

Product tanker<br />

30-45,000<br />

100<br />

200<br />

Chemical tanker<br />

30-45,000<br />

100<br />

200<br />

Miscellaneous<br />


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

The total marine traffic (i.e. ocean going, river trade, barges) related to the development of Area 137 will<br />

result in an increase of some 30 to 35 vessel movements per day, which is also considered to be a<br />

relatively small increase compared to present traffic intensities (240 movements per day).<br />

The river trade traffic for Area 137 and the SENT Landfill barges will be handled in the northern basin<br />

berths and will therefore have limited interaction with the ocean going traffic destined for the deep water<br />

berths in the south of Area 137. Similarly, the proposed development at Area 131 will generate, typically,<br />

one to two ocean going vessel movements per day and can be effectively discounted in terms of the overall<br />

future movement patterns of the area.<br />

6.3 SHIP HANDLING OPERATIONS<br />

6*3.1 Introduction<br />

Ship manoeuvring simulations have been carried out to assess the manoeuvring behaviour of ships when<br />

arriving and departing from the proposed berths. The input to the simulations comprises an intended track<br />

to be followed by the vessel under specified wind, wave and current conditions. Further, the use of<br />

engine and scope of tug assistance is specified. During the simulations the vessel is controlled by an<br />

autopilot which calculates required rudder angles, engine settings and tug forces in order to follow the<br />

intended track as closely as possible.<br />

6.3.2 Input Conditions<br />

Arrivals and departures are presented for Berth 4 (parcel tanker berth), which is typical of the tanker<br />

berths, with a loaded and a ballasted 37,500 DWT tanker. Principal dimensions of the simulated tanker<br />

are indicated in Table 6.3.<br />

TABLE 6.3 :<br />

PRINCIPAL SHIP DIMENSIONS<br />

Dimension<br />

Unit<br />

Loaded<br />

Ballasted<br />

Length Overall<br />

Length P'ends<br />

Beam<br />

Draft<br />

m<br />

m<br />

m<br />

m<br />

180<br />

171<br />

25.5<br />

10.4<br />

180<br />

171<br />

25.5<br />

5.4 (tnmmed)<br />

The ocean going vessels for Area 137 will carry potentially hazardous cargoes and will require sufficient<br />

tugs when approaching or leaving the berths to effectively guarantee safe manoeuvres. Tankers for Berths<br />

1, 4 and 5 will require at least 3 tugs upon arrival and 2 tugs when departing. The smaller LPG carriers<br />

and chemical transhipment tankers (Berths 2 and 3) will need the assistance of 2 tugs and 1 tug for arrivals<br />

and departures respectively. In the simulations a maximum tug force of 40 tons has been assumed to be<br />

available at the bow as well as at the stem of the tankers for arrival and departure manoeuvres.<br />

Arrival manoeuvres commence in the centre of the Inbound Traffic Lane of the Tathong Channel abeam<br />

of Nga Ying Pai with starting speeds of 6 to 8 ktn depending on the weather conditions. Tankers proceed<br />

through the Tathong Channel and make a 30 degree starboard turn, followed almost immediately by a port<br />

turn for lining up for the final approach to the berths. The manoeuvre simulation was terminated once<br />

the tanker is stopped and well under control in front of the berth. It is assumed that tankers will berth<br />

bow in as is common practice in Hong Kong.<br />

APH Consultants Page 6-3


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Departing tankers will be cleared off the berths with tugs and swung over some 30 to 50 degrees to port<br />

in order to line up for departure. Simulations were commenced at this position and continued with a large<br />

port turn towards the Outbound Traffic Lane of the TSS in the Tathong Channel. The manoeuvre<br />

simulation was terminated once passage in the Tathong Channel had been achieved.<br />

Manoeuvres were studied under normal operating wind conditions of 20 ktn from the prevailing directions,<br />

north, east and southwest. Emergency departures were simulated under northwesterly and northeasterly<br />

winds of 30 ktn.<br />

Local generated waves in the Study Area are generally less than 0.3m with periods below 5 sec and will<br />

therefore not affect manoeuvring tankers. Residual swells come from a southerly direction and a typical<br />

wave height of 0.5 m was selected for this navigation study.<br />

Current speeds at the present pilot boarding station are generally 0.6 ktn for ebb and flood tides.<br />

However, during the wet season with spring ebb conditions the current speeds can be as high as 1.2 ktn.<br />

For the simulations 0.6 ktn flood and ebb currents were used as well as a L2 ktn ebb current.<br />

6.33 Ship Manoeuvres<br />

Operating Conditions<br />

Safe arrivals are considered practicable with loaded and ballasted tankers during any stage of the tide and<br />

under normal operating conditions.<br />

An arrival manoeuvre for a loaded tanker is made with moderate use of engine and rudder. After a<br />

smooth approach manoeuvre the tanker is lined up for a final approach to the berth and is stopped well<br />

in time with half astern engine power. When arriving during (strong) ebb tide conditions more engine<br />

power is required to counteract winds and currents. The tanker could be stopped in time and kept under<br />

control with limited tug assistance. For arrivals on a flood tide and in southerly winds, the speeds should<br />

be taken off well before the final approach to the berth. Sufficient tug assistance is required (30 tons at<br />

bow and stern) to counteract the starboard swing of the tanker when half (and occasionally full) astern<br />

power is given.<br />

A ballasted arrival in calm weather is shown in Figure 6.1. The arrival track is closely followed with<br />

engine at half and slow ahead and moderate rudder angles are required to make the starboard and port turn<br />

respectively. Slow astern power is applied to stop the ship. Safe arrivals at ebb tides in northerly or<br />

easterly winds can also be made with moderate tug assistance (e.g. 30 tons tug at bow and stern) during<br />

the final stage of the manoeuvre to keep the tankers under control.<br />

Ballasted arrivals in flood tides and southerly winds should be undertaken with care. When approaching<br />

the berth and slowing down, the ballasted tankers will swing to starboard due to the wind and tide. To<br />

keep the tanker under control at least two 30 tons tugs at the stern and one at the bow are needed. Under<br />

such conditions, some vessels may find berthing "portside to" more practicable.<br />

Safe departures from the berth with ballasted tankers are practicable under normal wind conditions at any<br />

stage of the tide. Ballasted departure manoeuvres from Berth No.4 commenced with the tankers well<br />

cleared from the berth and lined up for departure by the assisting tugs. The engine was put at dead slow<br />

ahead.<br />

The port turn towards the Tathong Channel was made with moderate rudder angles between 10 and 15<br />

degrees with the engine at dead slow and slow ahead. The speed during this turn amounted to some 4 ktn.<br />

No tug assistance was required under this condition following the initial berth clearance.<br />

APH ComuItaMs<br />

f


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

When departing on an ebb tide and in a northerly wind the departing tanker should be lined up heading<br />

into the wind and current. During the first phase of the manoeuvre the speed is approx 2 ktn and<br />

moderate tug forces are required to keep the vessel under control. The port turn is made with the engine<br />

on slow ahead and with rudder angles between 10 and 20 degrees.<br />

During the first phase of departure for manoeuvres at flood tides and south-westerly winds, tugs are<br />

required to keep the tankers under control by pulling to port with some 8 to 10 tonne at bow and stern.<br />

During the turn to port only limited tug assistance is required.<br />

The crossing time of departing vessels of the Inbound Traffic Lane of the TSS is restricted to some 5<br />

minutes.<br />

Emergency Departures (typhoon evacuation)<br />

The more critical ballasted departures from the berths are safe and practicable, provided that sufficient<br />

tugs (2 tugs of 30 tonnes each) are available to pull the vessel from the berth and align the vessel for<br />

departure. The tankers should be lined up in such a way that they stay well clear of any berth structure<br />

and other moored ships when they commence their departure manoeuvres and port swings.<br />

Figure 6.2 shows a departure at spring flood in a 30 ktn northwesterly wind. A safe departure manoeuvre<br />

is possible provided that the vessel is well cleared of the berth and lined up for departure. At the initial<br />

stage of the manoeuvre up to 10 tonne of tug assistance to port side at bow and stern is required to<br />

counteract wind and current.<br />

Under conditions of wet season spring ebb tides the tankers need to be lined up with the currents prior<br />

to commencing the departure manoeuvres. The port turn is made with engine on (dead) slow ahead and<br />

with rudder angles of approx 15 degrees. Tug boat forces at bow and stern amounted to 20 tonne.<br />

6.4 INTERACTION EFFECTS OF PASSING SHIPS<br />

Ships moored at berths may be subjected to interaction effects caused by passing ships. These interaction<br />

effects are experienced as longitudinal and transverse forces combined with a yaw movement and are most<br />

pronounced in shallow water with the passing ships in close proximity of the moored ship and moving at<br />

speed. Interaction forces combined with other external forces acting on the moored ship may cause the<br />

moored ship to range on its moorings, with the possibility of mooring lines parting.<br />

The governing parameters affecting the interaction of passing ships are the ship sizes, separation distances<br />

between moored and passing ships and the sailing speeds.<br />

> Ship Sizes; the largest tankers moored at the outer berths of Area 137 are expected to range from<br />

30,000 up to 45,000 DWT. Ships sailing in the Inbound Traffic Lane and passing the Area 137<br />

port facilities are assessed to be typically 30,000 to 40,000 DWT. Maximum ship sizes are<br />

determined by the allowable draught in the Victoria Harbour area, which amounts to 11.0 m. The<br />

maximum ship size passing Area 137 is selected at 65,000 DWT.<br />

> Separation Distances; for the determination of the separation distances it is assumed that, on<br />

average, the inbound passing ships will sail in the centre of the Inbound Traffic Lane. The<br />

calculation assumes a separation distance between the passing and moored ships of 600 m.<br />

»* Sailing Speeds; the maximum speed of inbound vessels when passing Area 137 is taken at 10 ktn.<br />

Actual sailing speeds are most probably lower considering the fact that these vessels will be under<br />

pilotage at this location.<br />

APH Consultants<br />

P&g*


Figure 6.1<br />

SHIP MANOEUVRES -<br />

BALLASTED ARRIVAL<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

The mean longitudinal and transverse interaction forces on the moored tankers, for the above conditions,<br />

are given in Table 6.4.<br />

TABLE 6.4 :<br />

MEAN INTERACTION FORCES ON MOORED TANKERS<br />

Passing Ships<br />

30,000-40,000 DWT<br />

65,000 DWT<br />

Longitudinal<br />

Transverse<br />

Longitudinal<br />

Transverse<br />

Interaction Forces (tf)<br />

(Separation Distance 600m)<br />

1.6<br />

7.0<br />

4.5<br />

20.0<br />

In addition to the interaction forces the moored tankers may be subjected to wind, wave and current forces<br />

which may amount to 7.0 to 15 tonnes depending upon wind direction.<br />

The mooring restraint forces are defined as the maximum allowable forces acting on a moored ship before<br />

mooring lines break. These forces are dependent on the type and number of mooring lines used as well<br />

as on the mooring arrangement but are assessed at 47 tonnes longitudinal and 300 tonnes transverse force<br />

for the moored tanker.<br />

The mooring restraint safety factor is defined as the mooring restraint forces divided by the total mean<br />

disturbing force on the moored ship. It is considered that this factor of safety should be at least 4 to allow<br />

for dynamic and other effects. The mooring restraint safety factors are calculated for the various<br />

conditions and are presented in Table 6.5.<br />

TABLE 6.5 :<br />

MOORING RESTRAINT SAFETY FACTOR<br />

(Separation Distance 600 m)<br />

Passing Ships<br />

30,000-40,000 DWT<br />

65,000 DWT<br />

Interaction Forces<br />

Longitudinal<br />

Transverse<br />

Longitudinal<br />

Transverse<br />

Safety Factor<br />

5.5<br />

13.6<br />

4.1<br />

8.6<br />

With the given 600 m separation distance, adequate safety margins are present for passing ships of typical<br />

size 30,000 to 40,000 DWT. For maximum ship sizes of up to 65,000 DWT passing Area 137, the safety<br />

margin is also satisfactory.<br />

6.5 DOWNTIME CONSIDERATIONS<br />

6*5,1 Introduction<br />

Vessels moored at the berths are exposed to locally generated waves and residual waves and swells coming<br />

from southerly directions. When wave induced ship motions are too large, cargo handling operations will<br />

APH Consultants Page 6-6


Figure 6.2<br />

SHIP MANOEUVRES - TYPHOON DEPARTURE<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

have to slow down or even cease, resulting in operational downtime. Acceptable ship motions are,<br />

amongst others, dependent on the ship types and sizes, type of cargoes handled and cargo handling<br />

equipment. Mainly oil and gas tankers are to be expected at the deep water berths of Area 137 and their<br />

products will be handled by loading arms.<br />

At the most northern berths general cargo vessels and small coasters can be expected. Cargo is anticipated<br />

to be handled using cranes, either onshore or onboard.<br />

6.5.2 Wave Conditions<br />

Local generated waves come from northeasterly, southeasterly and southerly directions with wave heights<br />

below 0.5 m. Residual ocean waves and swells enter through the Tathong Channel and come from a<br />

southerly direction. With the berth orientation of SSE/NNW these wave directions result in (port) stern<br />

quartering seas on the moored ships. It is assumed that vessels will be berthed bow inwards (northerly<br />

heading) as discussed in Section 6.3.<br />

The exceedence frequencies of the residual waves and swell are indicated in Table 6.6.<br />

TABLE 6.6 : WAVE EXCEEDENCE FREQUENCIES (%)<br />

Wave<br />

Height Hs<br />


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

final Report - Main Report<br />

6.5.4 Operational Downtime<br />

The operational downtime for the various vessels expected to call at Area 137, based on the above wave<br />

conditions and downtime criteria, are presented in Table 6.8.<br />

TABLE 6.8 : OPERATIONAL DOWNTIME AREA 137<br />

Vessel Type<br />

Tanker<br />

LPG Carrier<br />

General Cargo Vessel<br />

Coaster<br />

Vessel Size (DWT)<br />

30,000 - 45,000<br />

8,000 - 10,000<br />

1,200<br />

5,000 - 8,000<br />

2,000<br />

Downtime (%)<br />

0.35<br />

1.2<br />

3.4<br />

1.2<br />

3.4<br />

The operational downtimes for the various ships are all below 5%. The highest downtimes occur for the<br />

small LPG tankers and coasters. Considering the frequency of vessel calls at the port facilities (see Table<br />

6.2) the actual downtimes for all vessels will be very limited.<br />

SENT Landfill Barges<br />

The wave conditions at the Sent Landfill quays have been analysed to determine what change in<br />

operational conditions would occur in relocating the marine access from the present planned location to<br />

the proposed location at the north of the Area 137 development.<br />

The wave exceedence frequencies of the residual waves and swell, calculated at the present SENT Landfill<br />

location and at the reprovisioned location during both an initial development and for the full development,<br />

are indicated in Table 6.9.<br />

TABLE 6.9 : WAVE EXCEEDENCE FREQUENCIES AT SENT LANDFILL QUAYS (%)<br />

Wave Height<br />

Hs(m)<br />

Landfill<br />

5 sec<br />

Location<br />

7 sec<br />

Area 137 Initial<br />

Wave Period Tp<br />

5 sec 7 sec<br />

Area 137 Final<br />

5 sec 7 sec<br />

0.5<br />

0.55<br />

0.42<br />

0.21<br />

0.19<br />

0.60<br />

0.42<br />

0.7<br />

0.05<br />

0.04<br />

0.01<br />

.<br />

0.06<br />

0.05<br />

1.0<br />

~<br />

,<br />

-<br />

.<br />

,<br />

.<br />

There will be minimal change in wave conditions between the alternative quay locations. In all cases, the<br />

frequency of the critical wave heights and periods is less than 1 %, and downtime for the SENT Landfill<br />

barges will be very limited and effectively unchanged.<br />

APH Consultants<br />

fage


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

6.6 PILOTAGE AND AIDS TO NAVIGATION<br />

6.6.1 Pilotage<br />

The pilot station for shipping traffic using the Tathong Channel is at present located approximately<br />

between Hak Kok Tan and Tit Cham Chau. With the development of Area 137, and possibly also Area<br />

131, this pilot boarding station will need to be relocated to a position off Tai Long PaL<br />

This relocation would result in an additional sailing distance of some 1.75 nm for the pilot cutter.<br />

Considering the marine traffic intensity in the Tathong Channel in 2011 and the number of vessels<br />

requiring a pilot (over 1,000 GRT for vessels with dangerous cargoes), this additional sailing distance<br />

appears acceptable for a high speed pilot cutter.<br />

Wave and weather conditions at the proposed site are only slightly more onerous than at the present<br />

location and it is not expected that pilot boatding operations would be significantly affected by relocating<br />

the boarding station.<br />

6.6*2 Aids to Navigation<br />

The approach routes to the new port facilities are all located in deep water and no specific aids to<br />

navigation to mark these routes are required.<br />

The port facilities will be marked by shore based beacons as indicated on Figure 6,3.<br />

6.63 Tathong Channel Traffic Separation System (TSS)<br />

In order to maintain the 600 m separation distance between passing ships in the Inbound Traffic Lane of<br />

the TSS and vessels berthed at Area 137, and to separate as much as possible passing ships from ships<br />

manoeuvring for the berths, a realignment of the TSS off the berthing face is required. This involves<br />

easing the present course change of some 35° by "cutting the corner 11 and reducing the present course<br />

change to two smaller course changes, about 0.8 run apart. Figure 6.3 indicates the nature of this<br />

realignment, together with the aids to navigation requirements. IMO approval will be required for this<br />

revised channel alignment.<br />

6,7 ANCHORAGES<br />

6.7.1 Tseung Kwan O Mooring Buoys<br />

The Study is required to consider the continued use of the three mooring buoys (A60, A61 and A62) in<br />

Tseung Kwan O in conjunction with the development of Area 137 facilities.<br />

The PHI development and operation of the Area 137 port facilities will not require the use of these<br />

mooring buoys, since the handling of hazardous cargoes at the mooring buoys would be inappropriate and<br />

not permitted under the existing ordinances, The lack of definition of the requirements for DWI<br />

operations do not permit recommendations to be made upon the suitability of retaining these buoys in<br />

relation to these operations.<br />

6*7*2 Dangerous Goods Anchorage<br />

The dangerous goods anchorage in Tseung Kwan O is presently used by a limited number of vessels:<br />

approximately one to two vessels per week. The vessels utilising the proposed Area 137 facilities will<br />

be carrying potentially hazardous cargoes. It is considered that the use of the existing dangerous goods<br />

APH Consultants Page 6*9


Figure 6.3<br />

TSEUNG<br />

(Junk Bay)<br />

KWAN<br />

r» Long Wan M<br />

Wave Bay}<br />

PROPOSED FAIRWAY REALIGNMENT<br />

AND AIDS TO NAVIGATION<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

anchorage would introduce unnecessary risks and in the occasional circumstances when a waiting<br />

anchorage is required then the vessel should utilise the existing dangerous goods anchorage to the south<br />

of Lamma Island. The frequency of this usage should, however, be monitored and, if required, a new<br />

dangerous goods anchorage could be established nearer Area 137, possibly between Tung Lung Chau and<br />

the Ninepins.<br />

6*7*3 Quarantine and Immigration<br />

The existing quarantine and immigration anchorage for vessels approaching from the east is located in<br />

Kowloon Bay off Kai Tak. Any requirement for vessels carrying dangerous goods or potentially<br />

hazardous cargoes to utilise this anchorage would again introduce unnecessary risks. The designation of<br />

an alternative anchorage seaward of the proposed development would be equally inappropriate given the<br />

nature of the current method of clearance.<br />

It therefore recommended that pre-entry clearance should be granted wherever possible and failing this,<br />

clearance should be granted when the vessel is on the berth as is the current practice in many international<br />

ports. This is not currently done in Hong Kong and Immigration Department's resources may therefore<br />

be limited for such duties.<br />

6.8 NAVIGATIONAL RISK AND VESSEL TRAFFIC CONTROL<br />

6.8.1 Introduction<br />

The development of Area 137 port facilities will generate additional marine traffic in the Tathong Channel.<br />

Ocean going vessels will arrive from the south and river trade vessels and barges will pass through Lei<br />

Yue Mun.<br />

In addition, the marine traffic in this area will increase due to the expected growth of the total marine<br />

traffic calling at Hong Kong and due to Vessel Traffic Management regulations (as discussed in Section<br />

6.2).<br />

6.8.2 Navigation Risks<br />

Arriving ocean going vessels for Area 137 have minimal interference with other marine traffic. Pilots will<br />

board in the approaches and follow the Inbound Traffic Lane of the Tathong Channel. After passing Tung<br />

Lung Chau they make their approach to the berths of Area 137, The number of vessels within the TSS<br />

and in the Eastern Inshore Traffic Zone is very low and the risk of collision with these vessels is equally<br />

low.<br />

During the final approaches to the berths, it is considered that safe arrival and berthing manoeuvres can<br />

be made when sufficient tug assistance and clear aids to navigation (on the quays) are provided.<br />

Ships should be unberthed with sufficient tug assistance and should be well lined up for departure.<br />

Departing ships have to cross the Inbound Traffic Lane to join other marine traffic in the Outbound Traffic<br />

Lane of the TSS in the Tathong Channel. As is discussed in Section 6.3 the time required to cross the<br />

Inbound Traffic Lane is short and amounts to some 5 minutes.<br />

During these departure manoeuvres there is a potential risk of collision with inbound or outbound traffic<br />

in the Tathong Channel and a proper timing and monitoring procedure will be essential. The probabilities<br />

of collision are very low in view of the traffic intensities in the Tathong Channel and frequency of<br />

departure manoeuvres from Area 137. Nevertheless, unberthing and departure manoeuvres should not<br />

commence prior to receiving advice from the VTS on committed vessel movements in the Tathong<br />

APH Consultants Page 6-10


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

Channel. In particular during typhoon evacuations the departure manoeuvres should be closely monitored<br />

by VTS.<br />

River trade vessels and barges destined for Area 137 will all be handled at the northern basin and there<br />

will therefore be little interference with the ocean going ships for Area 137.<br />

Vessels destined for Area 137 and coming through Lei Yue Mun, sailing in the Outbound Traffic Lane,<br />

have to cross the Inbound Traffic Land when entering the northern basin. During these crossings potential<br />

collisions with other traffic is present. A proper timing of manoeuvres, monitored by the VTS, is hence<br />

required.<br />

6.8.3 Marine Support<br />

The requirements for tug assistance for the different classes of vessels utilising the proposed facility have<br />

been discussed in Section 6.3.2. Tugs are presently based in the vicinity of Tsing Yi and there are<br />

proposals for relocating their base to Lantau Port. Thus there is a response time for the tugs of the order<br />

of 1 hr, which would be acceptable under normal operating conditions. However, in an emergency<br />

involving the need for immediate departure or fire fighting assistance then a more rapid response would<br />

be required.<br />

It is recommended that a minimum of 2 tugs, with fire fighting capabilities, should be stationed at the<br />

proposed facility and provision should be made for quayside support and a berth allocation of some 30m.<br />

6.8.4 Vessel Traffic Control<br />

All vessel traffic movements to and particularly from the planned port facilities of Area 137 should be<br />

monitored by the VTS. A good radar coverage of the approach routes is hence required. The present<br />

Vessel Traffic Services system and location of radar sites in Hong Kong is indicated in Figure 6.4.<br />

It is understood that the proposed berthing line of Area 137 is located just inside the blind sector of the<br />

Waglan radar coverage. However discussions with the Marine Department have indicated that this minor<br />

limitation would be acceptable and that no additional radar locations would be required.<br />

Recent developments have, however, indicated that Marine Department may lose the facilities currently<br />

provided by the ASDE radar at Kai Tak. The establishment of a replacement and the timing and siting<br />

of the new facility have yet to be finalised; further consultation will therefore be necessary with Marine<br />

Department to determine the future marine traffic levels and capability of the VTS at the time the Area<br />

137 development is scheduled to be implemented.<br />

APH Consultants<br />

Page


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

SECTION 7<br />

TRAFFIC AND TRANSPORT STUDY<br />

7.1 TRAFFIC FORECASTS<br />

7.1.1 Development Assumptions<br />

Traffic forecasts in Hong Kong are generally made within the context of the Comprehensive Transport<br />

Study (CTS-2) model, which enables the forecasts to be placed within an agreed framework of assumptions<br />

which are consistent between studies. This Study has made use of the CTS-2 forecasts provided by<br />

Government. The population and employment levels underlying the forecasts are summarised in Tables<br />

7.1 and 7.2.<br />

The implied development assumptions are consistent with Metroplan objectives and represent the<br />

assumptions in general use for transport planning studies in Hong Kong at the time of the current Study.<br />

The figures are under review, partly as a result of the 1991 Census showing lower population figures than<br />

had been expected, with the implication of lower population growth rates. There is also the possibility that<br />

Phase 3 of Tseung Kwan 0 could be developed to a higher level leading to a population of the order of<br />

440,000 by 2011. Sensitivity tests have investigated the impact on the Study findings of changes in the<br />

population assumptions.<br />

TABLE 7.1 :<br />

POPULATION DISTRIBUTION UNDERLYING THE FORECASTS<br />

(Units; OWs)<br />

Year<br />

Area<br />

1991 1996 2001 2006 2011<br />

Tseung Kwan 0<br />

Sai Kung<br />

Clear Water Bay<br />

New Territories<br />

Hong Kong Island<br />

Kowloon<br />

84<br />

30<br />

3<br />

2250<br />

1295<br />

2144<br />

153<br />

34<br />

19<br />

2581<br />

1359<br />

1955<br />

241<br />

26<br />

12<br />

2641<br />

1316<br />

2099<br />

243<br />

25<br />

12<br />

2701<br />

1362<br />

2160<br />

333<br />

24<br />

11<br />

2746<br />

1362<br />

2151<br />

Total 5811 6101 6335 6503 6627<br />

APH Consultants Page 7-1


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 72 :<br />

EMPLOYMENT DISTRIBUTION UNDERLYING THE FORECASTS<br />

(Units; OOO's)<br />

Area<br />

1991<br />

1996<br />

Year<br />

2001<br />

2006<br />

2011<br />

Tseung Kwan 0<br />

34<br />

38<br />

57<br />

76<br />

85<br />

Sai Kung<br />

13<br />

7<br />

5<br />

5<br />

5<br />

Clear Water Bay<br />

4<br />

9<br />

11<br />

10<br />

11<br />

New Territories<br />

95S<br />

991<br />

1051<br />

1092<br />

1130<br />

Hong Kong Island<br />

781<br />

922<br />

916<br />

931<br />

893<br />

Kowloon<br />

1030<br />

1042<br />

1091<br />

1092<br />

1123<br />

Total<br />

2820<br />

3009<br />

3131<br />

3206<br />

3247<br />

The Metroplan based assumptions indicate that Tseung Kwan O is expected to quadruple in size between<br />

1991 and 2011 in terms of population, with the major growth between 1991 and 2001, and then between<br />

2006 to 2011. The employment figures suggest about 30,000 jobs were planned to be located there by<br />

1991; recent results from the Travel Characteristics Survey indicate this may be on the high side with the<br />

current figure of around 10,000 reflecting the reluctance of employers to relocate to the New Towns<br />

unless there are specific opportunities associated with the move. The Metroplan assumptions indicate<br />

about 85,000 jobs by 2011 would be located in Tseung Kwan O.<br />

The forecast of population in Tseung Kwan O is largely based on Housing Department plans as the<br />

Housing Programme is well defined; although there is the potential for a major variation in the extent of<br />

completion of Phase 3, and the implications of this have been examined. A minor variation could occur<br />

in the degree of vacancy and take-up of flats, but this is expected to be small and well within the limits<br />

of accuracy in forecasting. It should also be noted that the population forecast for 1991 was similar to<br />

what was recorded in the 1991 Census and the 1992 Travel Characteristics Survey. The population<br />

forecast can therefore be viewed as firm and reliable.<br />

As discussed above, the forecasts of employment are less definitive. There is no corresponding control<br />

on employment location other than planning permission on land use. This cannot specify the number or<br />

detailed type of jobs, or encourage employment to be relocated to areas such as Tseung Kwan O, The<br />

forecast of about 30,000 jobs to be located in Tseung Kwan O by 1991 has not been met. The target of<br />

85,000 jobs by 2011 excludes the industrial developments considered in this Study. There must be some<br />

doubt as to whether or not this target will be met, although the Area 137 and TKOIE developments may<br />

be the necessary stimulus to achieve this figure.<br />

7*1.2 Infrastructure Assumptions<br />

The major infrastructure development over the next fifteen to twenty years is likely to concentrate on<br />

improving access through West Kowloon for the Airport related projects and also providing access to areas<br />

of new reclamation. The items of highway construction which most effect Tseung Kwan O are as follows:<br />

* completion of Lung Cheung Road Improvements (by 2001);<br />

* Hung Horn Bypass and Princess Margaret Road Link (by 2001);<br />

> Kai Tak Connector between Kai Tak and Kwun Tong (by 2006);<br />

» Kowloon Bay Reclamation Roads (by 2011).<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

It should be noted that the Kai Tak Connector as currently proposed is planned to terminate at the junction<br />

with Cha Kwo Ling Road.<br />

Assumptions for the phasing of the future year networks for the New Town are based on information from<br />

Plan TK2019C - Road Completion Dates, Tseung Kwan 0 (dated 23.3.92), supplied by TDD's SENT<br />

Development Office. The current programme of road development is illustrated in Figure 7.1.<br />

Area 137 would be connected by a single road, proposed as Road D6, which is scheduled to be completed<br />

by 1999. However, in accordance with the development programme for Area 137, the completion date<br />

for Road D6 is required to be brought forward to 1997.<br />

By 2011, all the major roads connecting external accesses to Road D6 would be completed. These include<br />

the following:<br />

> Cross Bay Bridge Road D9 (Dual-2 lane)<br />

> Road PI, North of D6 (Dual-2 lane)<br />

> Easterly Link Road connecting PI and D3 (Single lane)<br />

The Cross Bay Bridge Road is indicated on plan TK2019C as constructed by 2003-2004; for the purposes<br />

of network testing it is assumed to be completed by 2006, The Western Coast Road is shown on the plan<br />

as having the first carriageway completed by 2000 and the second carriageway completed by 2002. This<br />

is in accordance with the findings of the TKOFSOFD which identified a need for this road by 2001.<br />

However, for the purposes of critically examining the implications of the timing of the provision of the<br />

Western Coast Road it has been assumed to be deferred until 2006.<br />

Road PI between Tl and D4, programmed for completion by 2001, wouid need to be brought forward<br />

in line with the industrial developments in TKO if industrial traffic is to avoid the Hang Hau area.<br />

The proposed MTR extension to Tseung Kwan O is assumed to be open by 2006 and to be operated by<br />

means of split working of the Kwun Tong line service between the Tseung Kwan O line and the Eastern<br />

Harbour Crossing to Quarry Bay. There would be four stations at Tiu Keng Leng, Tseung Kwan 0 Town<br />

Centre, Hang Hau and Po Lam, Whilst the opening of the MTR extension by 2006 comes from the<br />

assumptions for the CTS-2 Update Study, and confirmed by the provisional findings of the Rail<br />

Development Study, there is as yet no firm commitment that it will be constructed,<br />

7.1.3 Industrial Development<br />

The CTS-2 forecasts do not make any allowance for travel associated with the following specific sites.<br />

These are;<br />

* Planning Area 87; this site is planned as the location of the TKOIE<br />

> Planning Area 101; this has been identified as a landfill site<br />

* Planning Area 137; this is the subject of the Study<br />

> Planning Area 131; this has been proposed for dockyard development<br />

»• Planning Area 86; assumed light industry<br />

It is estimated that about 1,700 jobs are associated with Area 137, while the TKOIE would provide of the<br />

order of 10,000 to 15,000 jobs. With the Metroplan employment levels this would give a total of some<br />

100,000 jobs in Tseung Kwan 0 in 2011.<br />

The traffic forecasts include the trips generated and attracted by each of these sites. These have been<br />

forecast by applying trip rates to the estimates of development at each of the sites. Area 137 was<br />

disaggregated into 18 detailed zones prior to estimating the trip making in order to provide sufficient detail<br />

APH Consultants Page 7-3


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

final Report - Main Report<br />

in the traffic analysis to plan the detailed network serving the area. The trip rates were derived from<br />

observation of trip making elsewhere in Hong Kong at locations of similar land use to that planned in<br />

Tseung Kwan 0. The sites surveyed include the Tai Po Industrial Estate and the Tsing Yi Oil Depot Area<br />

22; trip rates have also been abstracted from the SENT Landfill Study, NWNT Open Storage Areas<br />

Traffic Impact Study and surveys of container storage areas in the Castle Peak Road Corridor Study. Trip<br />

rates are summarised in Table 7.3 below.<br />

The trip rates relate the volume of goods vehicle traffic generated and attracted to a site to the extent of<br />

development expressed per 100 square metres of development area. The volume of private vehicles is<br />

related to the number of workers and represents the journey to work by car and business travel.<br />

TABLE 7.3 :<br />

TRIP RATES FOR PEAK PERIODS (pcus per hour)<br />

Land Use<br />

Goods Vehicle Rates per 100m 3<br />

Potential Hazardous Industry<br />

Deep Water Industry<br />

Private Vehicle Rates per Worker<br />

Average Industry<br />

AM Peak<br />

Attraction Generation<br />

0.042 0.071<br />

0.270 0.270<br />

0.114 0.066<br />

PMPeak<br />

Attraction Generation<br />

0.023 0.032<br />

0.270 0.270<br />

0.057 0.127<br />

The land use pattern assumed for Area 137 is summarised in Table 7.4 below by the 18 traffic zones,<br />

together with the number of trips generated by the development. The full development is expected to<br />

increase traffic volumes in the AM peak by about 900 pcu's per direction.<br />

Figure 7.2 illustrates the travel patterns for Area 137 trips in the AM and PM peaks. These have been<br />

estimated by assigning the forecast travel to and from Area 137 to the highway networks.<br />

The total generation and attractions produced by all the industrial developments on the peninsula are<br />

summarised in Table 7.5 below. The increase in traffic is about 3,100 pcus in the peak direction; goods<br />

vehicles form about 56% of the traffic, a proportion which is similar to other industrial areas. The<br />

majority of this traffic is expected to travel to or from areas outside of Tseung Kwan O, rather than be<br />

short intra New Town trips. The goods vehicles are likely to be distributing or carrying loads to all parts<br />

of the Territory, whilst the car trips are typically in-course-of-work trips by senior managers; many of<br />

these trips will also be external. Of the extra 3,100 pcus in the AM peak direction, 80% are expected to<br />

be external trips.<br />

The impact of the industrial areas on the total travel demand from Tseung Kwan O in 2011 is shown in<br />

Table 7.6 below by internal/external movements. The developments increase the extent of internal trips,<br />

but by a small proportion. Total external travel increases by 23%. Goods vehicles form the majority of<br />

the traffic stream.<br />

There is more travel associated with the industrial developments in the PM peak, but travel volumes for<br />

Tseung Kwan O, as a whole, are highest in the morning, with journeys to and from work. The majority<br />

of the subsequent traffic analysis therefore concentrates on the AM peak.<br />

APH Consultants Page 7-4


Figure 7.2<br />

NENT<br />

AM PEAK<br />

TRAVEL PATTERN<br />

W/NWNT<br />

& Lantau<br />

TKO<br />

Rest of<br />

Kowloon<br />

Hong Kong<br />

Island<br />

W/NW NT<br />

NENT<br />

PM PEAK<br />

TRAVEL PATTERN<br />

Rast of<br />

Kowloon<br />

Hong Kong<br />

Island<br />

LEGEND:<br />

36 PCUS FROM AREA 137<br />

(28) PCUS TO AREA 137<br />

TRAVEL PATTERN OF TRIPS FOR AREA 137<br />

APH CONSULTANTS


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

TABLE 7.4 :<br />

DEVELOPMENT OF TRAVEL DEMANDS FOR AREA 137 {pcus per hour)<br />

Zone* Land Use<br />

1 Fuel Storage<br />

Area (m 2 )<br />

100900<br />

Gen.<br />

87<br />

AM Peak<br />

Att.<br />

69<br />

PM Peak<br />

Gen. Att.<br />

62<br />

36<br />

2 Chemical Storage<br />

107200<br />

92<br />

73<br />

65<br />

39<br />

3 LPG<br />

96100<br />

83<br />

65<br />

59<br />

35<br />

4 Gas<br />

109500<br />

95<br />

75<br />

67<br />

39<br />

5 PHI-Related<br />

49200<br />

43<br />

34<br />

30<br />

17<br />

6 PHI-Rckted<br />

22600<br />

19<br />

15<br />

14<br />

8<br />

7 DWI<br />

17000<br />

34<br />

35<br />

36<br />

33<br />

8 DWI<br />

9500<br />

18<br />

20<br />

20<br />

18<br />

9 DWI<br />

15200<br />

29<br />

31<br />

31<br />

29<br />

10 DWI<br />

24500<br />

48<br />

50<br />

51<br />

47<br />

11 DWI<br />

13600<br />

26<br />

23<br />

28<br />

26<br />

12 DWI<br />

50300<br />

99<br />

104<br />

106<br />

98<br />

13 DWI<br />

30600<br />

60<br />

63<br />

64<br />

59<br />

14 DWI<br />

23200<br />

46<br />

48<br />

49<br />

45<br />

15 DWI<br />

22200<br />

43<br />

46<br />

47<br />

43<br />

16 SENT Landfill Access<br />

12500<br />

27<br />

28<br />

29<br />

27<br />

17 Services<br />

10000<br />

22<br />

23<br />

23<br />

21<br />

IS<br />

DWI<br />

16800<br />

33<br />

34<br />

35<br />

32<br />

Total<br />

730900<br />

904<br />

841<br />

816<br />

652<br />

* Locations of zones are shown in Figure 7 5<br />

TABLE 7.5 :<br />

ADDITIONAL TRAVEL FROM THE INDUSTRIAL DEVELOPMENT (pcus per hour)<br />

AM Peak<br />

PMPeak<br />

Planning Area<br />

Gen.<br />

Att<br />

Gen.<br />

Att.<br />

87<br />

764<br />

1226<br />

750<br />

432<br />

137<br />

904<br />

841<br />

816<br />

652<br />

101<br />

138<br />

151<br />

390<br />

377<br />

131<br />

297<br />

342<br />

345<br />

296<br />

36<br />

372<br />

550<br />

569<br />

372<br />

Total<br />

2475<br />

3110<br />

2870<br />

2129<br />

APH Consultants Page 7-5


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report • Main Report<br />

TABLE 7.6 :<br />

COMPOSITION OF TSEUNG KWAN O TRAFFIC, 2011 (pcus per hour)<br />

External<br />

Total<br />

Percent<br />

Internal<br />

Outbound<br />

Inbound<br />

Internal<br />

Without Industrial<br />

Development<br />

AM Private<br />

AM Goods<br />

AM Total<br />

1958<br />

1298<br />

3256<br />

2260<br />

5223<br />

7483<br />

2184<br />

4992<br />

7176<br />

6402<br />

11613<br />

17915<br />

31%<br />

11%<br />

18%<br />

PM Private<br />

256<br />

1900<br />

847<br />

3003<br />

9%<br />

PM Goods<br />

1106<br />

4524<br />

4199<br />

9829<br />

11%<br />

PM Total<br />

1362<br />

6424<br />

5046<br />

12832<br />

11%<br />

With Industrial<br />

Development<br />

AM Private<br />

3654<br />

2655<br />

3358<br />

9667<br />

38%<br />

AM Goods<br />

2061<br />

7472<br />

7031<br />

16564<br />

12%<br />

AM Total<br />

5715<br />

10127<br />

10389<br />

26231<br />

22%<br />

PM Private<br />

529<br />

2807<br />

1086<br />

44°2<br />

12%<br />

PM Goods<br />

1876<br />

6581<br />

6158<br />

14615<br />

13%<br />

PM Total<br />

2405<br />

9388<br />

7244<br />

19037<br />

13%<br />

Note:<br />

Private vehicles include taxis, cars and special purpose buses. Fixed route public transport services are omitted.<br />

7.1.4 Framework of the Analysis<br />

The traffic flows have been analysed at three levels of detail. The territory-wide flows have been analysed<br />

to set the boundary volumes for the Kowloon network, including Tseung Kwan O. The Kowioon network<br />

has been used to examine the strategic flows. This has then been followed by a more detailed analysis<br />

of the traffic flow within Tseung Kwan 0 to examine the movements at individual junctions, and<br />

determine the impact of the development on the road system .<br />

7.2 THE EXTERNAL NETWORK<br />

7,2.1 External Links<br />

The three existing links which provide access between Tseung Kwan O and Kowloon are Po Lam Road,<br />

Tseung Kwan O Tunnel and Hung Hau Road. Hung Hau Road provides access to Tseung Kwan 0 in the<br />

east from Clear Water Bay Road and carries traffic from the Sai Kung area. While Hang Hau Road is<br />

planned to be improved to a dual two lane standard by 2011, its capacity is limited by the roundabouts<br />

at Road D3 and Clearwater Bay Road. The proposed Western Coast Road will provide an additional<br />

access route across the western screenline.<br />

APH Consultants Page 7-6


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

The performance of the western external links are shown in Table 7.7 in terms of their peak hour<br />

voiume-to-capacity ratio (v/c ratio). A v/c ratio of 1.0 indicates the threshold of overloading, and<br />

corresponds to a level of service for operation of D. This is characterised as high density but stable flow;<br />

small increases will cause operational problems. Links can generally function up to a v/c ratio of about<br />

1.2, but with likelihood of increasing congestion and unstable flow. The capacity used is the minimum<br />

of mid-block and junction capacity.<br />

7.2.2 Improvements in Yau Tong Area<br />

The initial traffic forecasts assumed that there were no improvements to the road network in the Yau Tong<br />

area to carry the increased traffic volumes resulting from the construction of the Western Coast Road.<br />

This would lead to serious congestion in the Yau Tong area and the Western Coast Road not being fully<br />

utilised whilst the Tseung Kwan O tunnel would be seriously overloaded. Clearly there would need to<br />

be improvements in capacity in the Yau Tong area to match the increased through traffic.<br />

Table 7.7 also shows the travel demand and v/c ratios for the major links in the AM peak when Lei Yue<br />

Mun Road is assumed to be upgraded to dual 3-lane for the section between Western Coast Road and<br />

Kwun Tong Road, and Cha Kwo Ling Road is assumed to be upgraded to dual 2-lane for the section<br />

between Western Coast Road and Kwun Tong Bypass. With these improvements the flows across the<br />

screenline (Western Coast Road, Po Lam Road, TKO Tunnel and Hang Hau Road) are better balanced<br />

and the Western Coast Road is better utilised. These upgradings are illustrative of the scale and type of<br />

improvements which would be required in order to ensure that the capacity offered by the Western Coast<br />

Road is used to its full. Further detailed examination of these improvements will be required.<br />

TABLE 7.7 :<br />

2011 TRAFFIC FLOWS, AM PEAK, WITH AND WITHOUT IMPROVEMENTS IN YAU TONG<br />

(pcus per hour, v/c ratio in brackets)<br />

Link<br />

Practical Link<br />

Capacity<br />

Direction<br />

Not Improved<br />

Improved<br />

Cha Kwo Ling Road/WCR<br />

Connector<br />

3600<br />

3600<br />

W<br />

E<br />

1550(0.43)<br />

1400(0.39)<br />

1800(0.50)<br />

2000(0.56)<br />

Lei Yue Mun Road/<br />

WCR Connector<br />

3600<br />

3600<br />

W<br />

E<br />

2250(0.63)<br />

2350(0.65)<br />

2850(0.79)<br />

2600(0.72)<br />

Western Coast Road<br />

5400<br />

5400<br />

W<br />

E<br />

3750(0.69)<br />

3750(0.69)<br />

4650(0.86)<br />

4600(0.85)<br />

Po Lam Road<br />

1500<br />

1300<br />

W<br />

E<br />

1050(0.70)<br />

1200(0.92)<br />

1000(0.67)<br />

1000(0.77)<br />

Tseung Kwan O Tunnel<br />

3600<br />

3600<br />

W<br />

E<br />

4850(1.35)<br />

4800(1.33)<br />

4050(1.13)<br />

4250(1.18)<br />

Hang Hau Road<br />

2200<br />

1600<br />

N<br />

S<br />

1900(0.86)<br />

1650(1.03)<br />

1850(0.84)<br />

1550(0.97)<br />

7.2.3 External Access<br />

Tables 7.8 and 7.9 summarise forecast traffic demand on external access links for AM peak and PM peak<br />

respectively. The major underlying assumptions in the analysis are:<br />

> population of 333,000 and 85,000 jobs in Tseung Kwan O by 2011;<br />

*• inclusion of traffic from ail the industrial developments;<br />

APH Consultants Page 7*7


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

improvements in road capacity in the Yau Tong area as discussed above in Section 7.2.2;<br />

dangerous goods vehicles will use Po Lam Road prior to the opening of the Western Coast Road;<br />

the Western Coast Road is assumed to be delayed until 2006.<br />

TABLE 7.8 :<br />

AM PEAK TRAFFIC VOLUMES ON EXTERNAL ACCESS<br />

(We ratio in brackets)<br />

External Access<br />

Dir<br />

Practical<br />

Capacity<br />

1996<br />

2001<br />

Volume (pcu)<br />

2006<br />

2011<br />

Po Lam Road<br />

W<br />

E<br />

1500<br />

1300<br />

950


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

southern Tseung Kwan 0. This clearly points to the need for the Western Coast Road to be in operation<br />

by 2001.<br />

Traffic flows across the external screenline in 2001 with and without the Western Coast Road are shown<br />

in Table 7.10. The opening of the Western Coast Road in 2001 provides the required relief to the<br />

overloaded external links, with the v/c ratio for the screenline as a whole in the AM peak of around 0.65<br />

and all links on the screenline within capacity. Flow across this western screenline now also attracts an<br />

additional 400 pcus thereby providing relief to Hang Hau Road and Clearwater Bay Road.<br />

TABLE 7 JO :<br />

TRAFFIC VOLUMES IN 2001 WITH AND WITHOUT THE WESTERN COAST ROAD<br />

(pcus per hour)<br />

External Access<br />

Without WCR<br />

With WCR<br />

AM<br />

PM<br />

AM<br />

PM<br />

Po Lam Road<br />

W<br />

E<br />

1600(1.07)<br />

1450(1.12)<br />

1350(0.90)<br />

900(0.69)<br />

1100(0.73)<br />

1100(0.85)<br />

1100(0.73)<br />

700(0.54)<br />

TKO Tunnel<br />

W<br />

E<br />

4700(1.31)<br />

5000(1.39)<br />

4450(1.24)<br />

4150(1.15)<br />

2650(0.74)<br />

3250(0.90)<br />

2600(0.72)<br />

2600(0.72)<br />

WCR<br />

W<br />

E<br />

-<br />

-<br />

2950(0.55)<br />

2550(0.48)<br />

2350(0.44)<br />

2000(0.37)<br />

Screenline Total<br />

W<br />

E<br />

6300(1.24)<br />

6450(1.32)<br />

5800(1.14)<br />

5050(1.03)<br />

6700(0.64)<br />

6900(0.66)<br />

6050(0.53)<br />

5300(0.51)<br />

Subsequent traffic analyses assumes that the Western Coast Road will be provided by 2001, in line with<br />

the recommended road development programme.<br />

Road D9, the Cross Bay Bridge Road, is currently programmed for construction at 2003-2004. The<br />

impact of bringing forward this link to 2001 has also been examined. Table 7.11 shows that in overall<br />

terms, its construction has marginal impact on total traffic volume using the western external access links.<br />

However, the balance of flows between the Western Coast Road and the TKO Tunnel is changed, with<br />

between 400 and 600 additional pcus now using the Western Coast Road.<br />

TABLE 7.11 :<br />

TRAFFIC VOLUMES IN 2001 WITH AND WITHOUT THE CROSS BAY BRIDGE ROAD<br />

(ROAD D9) (pcus per hour)<br />

External Access<br />

Without Road D9<br />

With Road D9<br />

AM<br />

PM<br />

AM<br />

PM<br />

Po Lam Road<br />

W<br />

E<br />

1100(0.73)<br />

1100(0.85)<br />

1100(0.73)<br />

700(0.54)<br />

1100(0.73)<br />

1050(0.31)<br />

1100(0.73)<br />

750(0.58)<br />

TKO Tunnel<br />

W<br />

E<br />

2650(0.74)<br />

3250(0.90)<br />

2600(0,72)<br />

2600(0.72)<br />

2250(0.63)<br />

3000(0.83)<br />

2000(0.56)<br />

2000(0.56)<br />

WCR<br />

W<br />

E<br />

2950(0.55)<br />

2550(0.48)<br />

2350(0.44)<br />

2000(0.37)<br />

3350(0.62)<br />

3000(0.33)<br />

3000(0.85)<br />

2600(0.72)<br />

Screeniine Total<br />

W<br />

E<br />

6700(0.64)<br />

6900(0.66)<br />

6050(0.58)<br />

5300(0.51)<br />

6700(0.64)<br />

7050(0.67)<br />

6100(0.58)<br />

5350(0.51)<br />

AfH Consultants Page 7-9


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

A proportion of the external traffic uses Hang Hau Road, including travellers to Sai Kung and to parts of<br />

the North East New Territories via Hiram's Highway. There is also a small amount of through traffic<br />

from these areas, amounting to some 700 pcus, which uses Hang Hau Road and either TKO Tunnel or<br />

Western Coast Road. Traffic on Hang Hau Road by 2011 is of the order of 1600 to 1900 pcus per<br />

direction, which is close to its practical capacity at that time.<br />

Traffic volumes along the Clearwater Bay Road are forecast to be some 1600 to 2500 pcus depending on<br />

the section. This is made up of Tseung Kwan O traffic to Sai Kung and North East New Territories and<br />

non-Tseung Kwan O traffic from Sai Kung and North East New Territories heading for the urban area.<br />

The major movements are to and from Sai Kung and vehicles using Hiram's Highway. Higher traffic<br />

volumes than forecast may occur along this corridor as the pressure for additional residential development<br />

in its catchment area is not reflected in the planning inputs.<br />

7*2.4 Sensitivity Test for 2011 Network on Reduced Level of Self-Containment<br />

Self-containment is an indicator of the ability of a town or city to cater for the needs of its residents. The<br />

planning of a New Town strives for a high level of self-containment, but in Hong Kong the competition<br />

from other urban attractors tends to reduce this, and there are generally significant movements between<br />

the New Towns and the urban area.<br />

The main series of traffic analyses have used the amount of self-containment implied for Tseung Kwan<br />

O by the CTS-2 forecasts. However, if self-containment is over-estimated, an under-provision of transport<br />

capacity may result. An analysis of the CTS-2 travel demands indicated that in the forecasts of private<br />

vehicles the self-containment for Tseung Kwan O was somewhat higher than for other areas such as<br />

Shatin, Kwun Tong and Aberdeen/Wong Chuk Hang. Whilst there may well be good reasons why this<br />

could come about, a sensitivity test was undertaken to demonstrate the impact of reduced self-containment<br />

for private vehicles on traffic volumes.<br />

The test was carried out by reducing the level of self-containment by 20%. The most significant impact<br />

of the change in self-containment is on the external access to Tseung Kwan O. Table 7.12 shows the<br />

resultant traffic demand volumes for 2011 network for the AM peak. The additional external traffic puts<br />

marginally more pressure on the external links with total external travel increasing by 6%. The screenline<br />

as a whole is at capacity in the AM peak, but the imbalances within the screenline make the TKO Tunnel<br />

more overloaded than for the base condition, further strengthening the need for measures such as increased<br />

tolls to encourage diversion to the Western Coast Road.<br />

TABLE 7.12 :<br />

IMPACT OF REDUCED SELF-CONTAINMENT, 2011 AM PEAK (flows in pens per hour)<br />

External Access<br />

Dir<br />

Practical<br />

Capacity<br />

Ftow<br />

Base Case<br />

v/c<br />

Reduced<br />

Self- Containment<br />

Flow<br />

V/C<br />

Pa Lam Road<br />

W<br />

E<br />

1500<br />

1300<br />

1000<br />

1000<br />

0.67<br />

0.77<br />

1150<br />

1100<br />

0.77<br />

0.88<br />

TKO Tminci<br />

WCR<br />

W<br />

E<br />

W<br />

E<br />

3600<br />

3600<br />

5400<br />

5400<br />

4050<br />

4250<br />

4650<br />

4600<br />

1.13<br />

1.1S<br />

0.86<br />

0.85<br />

4150<br />

4400<br />

5000<br />

4950<br />

1.15<br />

1.22<br />

0.93<br />

0.92<br />

Screenline<br />

Total<br />

W<br />

E<br />

10500<br />

10300<br />

9700<br />

9S50<br />

0,92<br />

0.96<br />

10300<br />

10450<br />

0.98<br />

1.01<br />

APH Consultants Page 7-10


Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

7.2.5 The MTR Tseung Kwan O Extension<br />

The traffic analysis has assumed the construction of the MTR and its opening by 2006. The implication<br />

for external links if there is no MTR Extension is shown in Table 7.13. It is assumed that most of the<br />

would-be MTR passengers would switch to the bus service.<br />

In this scenario, some 600 extra pcus would cross the external screenline in the AM peak. In 2006 the<br />

external screenline operates at a v/c ratio of 0.73 overall and can therefore accommodate the extra traffic.<br />

For 2011, the additional traffic would cause the total screenline to operate at a v/c ratio of 1.02, but TKO<br />

Tunnel would be heavily overloaded.<br />

It must be noted that there would be many other difficulties associated with this scenario: interchange at<br />

Lam Tin with MTR, bus congestion in TKO and Kwun Tong, and internal implications for TKO with<br />

regard to provision of bus termini, bus stops, walkways, and other pedestrian facilities etc. The majority<br />

of planning for the New Town has been undertaken on the assumption that the MTR Extension would be<br />

constructed.<br />

TABLE 7.13 :<br />

IMPACT OF MTR EXTENSION<br />

AM Peak East Bound Flows (pcus), 2011<br />

Corridor/Link<br />

Base (with MTR)<br />

Volume V/C<br />

No MTR<br />

Extra Buses<br />

Traffic<br />

v/c<br />

Po Lam Road<br />

1000<br />

0.77<br />

200<br />

1200<br />

0.92<br />

TKO Tunnel<br />

4250<br />

1.18<br />

250<br />

4500<br />

1.25<br />

WCR<br />

4600<br />

0.85<br />

150<br />

4750<br />

088<br />

Total Screenline<br />

9850<br />

0.96<br />

600<br />

10450<br />

1.02<br />

7.2*6 Impact of Development Area 131 and Development Area 137<br />

The capacity offered by the three direct links between Tseung Kwan O and Kwun Tong is 10500 pcus per<br />

hour. The demand in 2011 for westbound travel in the AM peak is 9700 pcus in totaL Therefore the<br />

screeniine as a whole can function at just under capacity. Area 131 only contributes about 1.5% of the<br />

external westbound traffic in the AM peak, whilst Area 137 contributes about 6.6%. Areas 131 and 137<br />

are clearly attracted to the Western Coast Road but are not the dominant users of the facility. The results<br />

are summarised in Table 7.14. Area 131 would make minimal use of the TKO Tunnel About one third<br />

of Area 137 traffic would use the tunnel, contributing about 6% of the total tunnel volume.<br />

TABLE 7,14 :<br />

IMPACT OF LANDUSE DEVELOPMENT AREAS 131,137 (2011 Flows, AM Peak Westbound)<br />

Corridor Base Traffic from Area 131 Traffic from Area 137<br />

(pens) Volume Percent Volume Percent<br />

Pa Lara Road<br />

1000<br />

0<br />

0<br />

0<br />

0<br />

TKO Tunnel<br />

4050<br />

0<br />

0<br />

250<br />

6.2%<br />

WCR<br />

4650<br />

150<br />

32%<br />

400<br />

3.6%<br />

Total Screenline<br />

9700<br />

150<br />

1.5%<br />

650<br />

6.7%<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

7.2.7 Sensitivity Test on Ultimate Level of Population Forecasts<br />

The Draft 1992 Tseung Kwan 0 Development Programme implies an ultimate population figure in 2011<br />

of 440,000 whereas the corresponding population assumed in CTS-2 (Metroplan) is 333,000.<br />

It should be noted that the population figures quoted in the Development Programme are basically the<br />

design population capacity. This is the theoretical population if all apartments at any time are occupied<br />

with average family sizes. In normal circumstances, this would rarely happen and a 5% vacancy rate is<br />

considered appropriate for Tseung Kwan O. However the impact on 2011 network for an active<br />

population of 440,000 has been assessed. No extra employment has been assumed, as the industrial<br />

developments have already added about 15,000 jobs to the base figure.<br />

Table 7.15 gives 2011 AM peak demand traffic volume and volume/capacity ratio for external access<br />

links. The demand flow on the TKO Tunnel would exceed maximum capacity (V/C = L26) whilst the<br />

demand flow on the Western Coast Road is still within the limit of ultimate capacity (V/C = 1.01).<br />

TABLE 7.15 :<br />

2011 DEMAiND TRAFFIC VOLUMES WITH HIGH POPULATION, AM PEAK<br />

BASE (Metroplan Forecast)<br />

SENT Forecast<br />

External Access Direction Flow (pcu) V/C Flow(pcu) V/C<br />

Po Lam Rd<br />

TKO Tunnel<br />

WCR<br />

Screeniine<br />

Total<br />

W<br />

E<br />

W<br />

E<br />

W<br />

E<br />

W<br />

E<br />

1000<br />

1000<br />

4050<br />

4250<br />

4650<br />

4600<br />

9700<br />

9850<br />

0.67<br />

0.77<br />

1.13<br />

1.18<br />

0.86<br />

0.85<br />

0.92<br />

0.96<br />

1200<br />

1100<br />

4550<br />

4550<br />

5050<br />

4800<br />

10800<br />

10450<br />

0.80<br />

0.85<br />

1.26<br />

1.26<br />

0.94<br />

0.89<br />

1.03<br />

1.01<br />

The morning peak demand in the westbound direction would be in excess of the screenline capacity for<br />

2011 as residents leave for work. The increase in population from 333,000 to 440,000 will add about<br />

11.3% of extra traffic and load the screenline to 3% above practical capacity. The source of the<br />

screeniine traffic is as follows for the westbound AM peak:<br />

Source<br />

AM Peak Westbound<br />

Traffic from 333,000 population and 85,000 jobs 7,100<br />

Traffic from SENT Landfill and TKOIE 1,800<br />

Traffic from Areas 137 and 131 800<br />

Extra traffic from increase from 333,000 to 440,000 population 1,100<br />

As a guiding principle the screeniine covering the access to Tseung Kwan O from the west should not<br />

exceed practical capacity; improved balance within the screeniine can be achieved through toll adjustments<br />

on TKO Tunnel. The critical period in respect of increasing population is the AM peak in the westbound<br />

direction. The v/c ratio for the screeniine increases from 0.92 to 1.03 which indicates that, in terms of<br />

practical capacity of the screenline, the increase in population level should be limited to around 78,000<br />

giving a theoretical total of 411,000. However, by inclusion of an assumed 5% vacancy rate, a design<br />

population of around 432,000 could be achieved.<br />

APR Consultants Page 7


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Alternative access to Tseung Kwan O could be provided by Clear Water Bay Road and either Hang Hau<br />

Road or a new northern access such as a route from Road D2 via Tseung Lan Shue, although it is<br />

understood that the latter gives problems in alignment and may give downstream problems on Clear Water<br />

Bay Road. The Hang Hau Road capacity is limited by its north and south junctions. It is also an indirect<br />

route for much of the traffic to and from Tseung Kwan O, As a result only some 2,000 pcu's are<br />

expected to use this link in the peak hour, mainly for trips to Sai Kung. Improvements to the junctions<br />

would provide a more attractive alternative if the congestion on the western access reaches a high level.<br />

There is also a possible provision of direct access to Hong Kong Island via a vehicle ferry between Area<br />

131 and Sai Wan Ho. The availability of this link has not been included in the traffic forecasts; a practical<br />

traffic volume could be between 100 to 200 pcus in the peak hour and this would make the screenline<br />

function within capacity.<br />

It is proposed that the design population is not lowered, rather that the options of providing the vehicle<br />

ferry link and the improvements to the Hang Hau access are safeguarded, as these could accommodate<br />

the excess 300 pcus required to place the western screenline in balance.<br />

7,2.8 Traffic Impact in Area of Influence<br />

Traffic impact caused by Area 137 is mostly concentrated on two major connecting routes, route<br />

D6/P1/T1 leading to Tseung Kwan O Tunnel and the Cross Bay Bridge/Western Coast Road route to East<br />

Kowloon. From these routes the traffic dissipates rapidly through the Kowloon road network. Figure 7.3<br />

illustrates the dissipation of the Area 137 traffic. Table 7.16 summarises the traffic impact within the<br />

Area of Influence for year 2011 in the morning peak.<br />

TABLE 7.16 :<br />

TRAFFIC IMPACT AT STRATEGIC LOCATIONS<br />

1.<br />

2.<br />

3.<br />

4.<br />

5.<br />

6.<br />

7.<br />

8.<br />

9.<br />

10.<br />

11.<br />

Road<br />

Junk Bay Road<br />

Wai Yi Street<br />

Cha Kwo Ling Road<br />

Lei Yue Mun Road<br />

Eastern Harbour Crossing<br />

Kwun Tong Road<br />

Lung Cheung Road<br />

New Clear Water Bay Road<br />

Clear Water Bay Road<br />

(becwm Han* HMI fci art Uwvwwiy Rd)<br />

Hiram's Highway<br />

Kai Tak Connector<br />

Dir<br />

W<br />

E<br />

W<br />

E<br />

W<br />

E<br />

W<br />

E<br />

N<br />

S<br />

N<br />

S<br />

W<br />

E<br />

W<br />

E<br />

W<br />

E<br />

N<br />

S<br />

W<br />

E<br />

Total<br />

(pcu)<br />

6100<br />

6300<br />

2000<br />

3400<br />

2300<br />

1800<br />

3700<br />

5200<br />

5400<br />

5700<br />

3900<br />

4800<br />

4700<br />

4800<br />

3400<br />

3400<br />

1900<br />

2000<br />

1000<br />

1200<br />

2700<br />

3600<br />

V/C<br />

Ratio<br />

1.13<br />

1.16<br />

0.76<br />

1.32<br />

o.so<br />

0.63<br />

0.94<br />

1.31<br />

1.49<br />

1.59<br />

0.73<br />

0.88<br />

1.30<br />

1.33<br />

1.12<br />

1.13<br />

0.71<br />

0.50<br />

0.34<br />

0.41<br />

0.75<br />

0.99<br />

Area 137<br />

Traffic<br />

160<br />

180<br />

20<br />

30<br />

100<br />

110<br />

190<br />

160<br />

80<br />

90<br />

60<br />

40<br />

30<br />

40<br />

30<br />

30<br />

40<br />

70<br />

20<br />

20<br />

170<br />

130<br />

% Trips<br />

2.6<br />

2.9<br />

1.0<br />

0.9<br />

4.3<br />

6.1<br />

5.1<br />

3.1<br />

1.5<br />

1.6<br />

1.5<br />

0.8<br />

0.6<br />

08<br />

0.9<br />

0.9<br />

2.1<br />

3.5<br />

2.0<br />

1.7<br />

6.3<br />

3.6<br />

APH Consultants


Figure 7.3<br />

BANDWIDTH SCALE:<br />

1 OOOPCU3<br />

IMPACT OF AREA 137 TRIPS<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Find Report - Main Report<br />

There are some impacts on strategic locations outside Tseung Kwan O. The flow contribution from Area<br />

137 at these locations is small, with maximum 6% of the total traffic. The more significant contributions<br />

to overloading as a result of Area 137 are Junk Bay Road (2.9%) and Lei Yue Mun Road (3.1%).<br />

The Study has been consistent with the TKOFSOFD in assuming that improvements to Clearwater Bay<br />

Road will be made during the period 2006 to 2011. The traffic volumes are well within the capacity of<br />

the improved Clearwater Bay Road, although there is some concern that the traffic in this area may<br />

develop faster than currently forecast.<br />

7.2.9 Delays in Construction of Western Coast Road<br />

Consideration has been given to the consequences of delaying the construction of the Western Coast Road<br />

in terms of the planned forecast for population and employment build up. The analysis of permissible<br />

development levels is, however, more approximate as there will be a radical change in the type of<br />

development associated with Tseung Kwan O. Rather than striving to attract development, constraints will<br />

need to be placed on the extent of development for the New Town.<br />

The discussion of alternative scenarios is presented from the traffic planning point of view. Planning<br />

assumptions which affect traffic and transport demand are primarily population levels and employment.<br />

The external travel demand arising from these will need to be accommodated on the existing access routes<br />

between Tseung Kwan O and East Kowloon. In developing alternative scenarios, it is assumed that traffic<br />

demand needs to be maintained below the capacity of the western screenline. The absence of any other<br />

transport mode, in this case the MTR extension, will also increase traffic volumes and thereby reduce<br />

access road capacity. Table 7.17 lists the planning assumptions and the forecast travel demand for Tseung<br />

Kwan 0, together with the limitations on screenline capacity.<br />

TABLE 7.17 :<br />

FORECAST TRAVEL DEMAND AND ASSUMPTIONS<br />

ITEM<br />

YEAR<br />

2001<br />

2006<br />

2011<br />

Population (Metropian)<br />

241,000<br />

243,000<br />

333,000<br />

Employment (Metropian)<br />

57,000<br />

76,000<br />

85,000<br />

Extra Industrial Employment (approx.)<br />

20,000<br />

20,000<br />

20,000<br />

Tseung Kwan 0 Traffic (Metropian) (pcus)<br />

3,700<br />

4,700<br />

7,100<br />

TKO Area 137/131 Traffic (pcus)<br />

800<br />

800<br />

800<br />

TKO Other Industrial Traffic (pcus)<br />

1,800<br />

1,300<br />

1,800<br />

Total Traffic - MTR open in 2006<br />

Total Traffic - MTR not open<br />

6,300<br />

7,300<br />

7,900<br />

9,700<br />

10,300<br />

Capacity - Without WCR<br />

Capacity - With WCR<br />

5,100<br />

10,500<br />

5,100<br />

10,500<br />

5,100<br />

10,500<br />

To meet the forecast traffic demand for the planned population and employment, the Western Coast Road<br />

would be required in 2001 to give sufficient screenline capacity. If the Western Coast Road is delayed<br />

until 2006, constraints on population, employment or industrial growth would need to be imposed.<br />

Consideration has been given to different scenarios by which this can be achieved.<br />

APH Consultants<br />

Pa s e 7 ~ 14


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

The choice between scenarios must bear in mind that the planning forecasts implicit in Metroplan represent<br />

desirable targets rather than the output of a detailed plan; this is especially the case for employment figures<br />

which are essentially non-specific. The inherent problem in planning for non-specific employment<br />

developments is whether they would be implemented and how this would occur. In contrast, the industrial<br />

developments proposed for Tseung Kwan O are already planned and fulfil an identified need. Therefore,<br />

when reducing employment levels, alternatives which permit the proposed industrial developments and cut<br />

back on other employment must be preferred.<br />

The range of scenarios considered for the delay of the Western Coast Road to 2006 and 2011, are given<br />

in Table 7.18 and 7,19 respectively.<br />

TABLE 7.18 : SCENARIOS FOR DELAY OF WESTERN COAST ROAD TO 2006<br />

Scenarios for 2006 are:<br />

MTR<br />

Present<br />

Metroplan<br />

Population<br />

Metroplaa<br />

Employment<br />

A137<br />

A131<br />

Empl.<br />

Other<br />

Industrial<br />

Employment<br />

Bl<br />

Full Metroplan<br />

2006<br />

Yes<br />

243,000<br />

76,000<br />

50%<br />

None<br />

B2<br />

Half Metroplan<br />

2006<br />

Yes<br />

120,000<br />

43,000<br />

100%<br />

100%<br />

S3<br />

Full Metroplan<br />

2006<br />

Yes<br />

243,000<br />

28,000<br />

100%<br />

100%<br />

B4<br />

75% Population<br />

2006<br />

Yes<br />

180,000<br />

36,000<br />

100%<br />

100%<br />

B5<br />

Full Metroplan<br />

2006<br />

No<br />

243,000<br />

72,000<br />

None<br />

None<br />

B6<br />

Half Metroplan<br />

2006<br />

No<br />

120,000<br />

30,000<br />

100%<br />

100%<br />

B7<br />

Full Metroplan<br />

2006<br />

No<br />

243,000<br />

15,000<br />

100%<br />

100%<br />

B8<br />

75% Population<br />

2006<br />

No<br />

180,000<br />

23,000<br />

100%<br />

100%<br />

TABLE 7.19 : SCENARIOS FOR DELAY OF WESTERN COAST ROAD TO 2011<br />

Additional Scenarios for 2011:<br />

MTR<br />

Present<br />

Metroplan<br />

Population<br />

Metroplan<br />

Employment<br />

A137<br />

A131<br />

Other<br />

B9<br />

Full Metroplan Population<br />

Yes<br />

333,000<br />

40,000<br />

None<br />

None<br />

BIO<br />

Full Metroplan Population<br />

Yes<br />

333,000<br />

20,000<br />

100%<br />

None<br />

Bll<br />

Full Metroplan Population<br />

No<br />

333,000<br />

27,000<br />

None<br />

None<br />

B12<br />

Full Metroplan Population<br />

No<br />

333,000<br />

7,000<br />

100%<br />

None<br />

To some extent the scenarios at 2006 and 2011 are mutually exclusive, in that permitting industrial<br />

employment at 2006 would exclude the deletion of this demand at 2011. In determining the preferred long<br />

term approach a view needs to be taken at the outset on the strategy to be adopted. If the ultimate<br />

objective is to provide for the Metroplan population of 333,000 and it is considered realistic that the<br />

Western Coast Road will not be implemented even by the 2011, then no industrial development should<br />

be permitted from the outset. Clearly this will be in direct contravention of the ongoing development of<br />

TKODE and eliminate the proposed Area 137 development. Alternatively these developments could be<br />

permitted, provided the population growth was constrained to its 2006 level. This approach effectively<br />

draws the decision point back to the 2006 scenarios and consideration of the implications of the delay of<br />

construction of the Western Coast Road to 2006.<br />

APH Consultants Page 7-15


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

In endorsing any recommendations on the preferred scenario to be adopted, Government will be required<br />

to take a view on the priority attached to the three main components; should industrial and other<br />

employment be promoted in preference in population growth, for instance.<br />

There is clearly a balance to be struck between population and employment. The extent of employment<br />

(other than industrial) which can be attributed to the New Town development is less definitive than the<br />

population forecasts. Current experience would appear to indicate that, with the increasing switch in<br />

employment to the financial and service sectors and the preference for these jobs to be located in CBD<br />

areas, the take up of development opportunities for manufacturing and commercial activities may not<br />

achieve its forecast levels. Thus in striking the balance between population and employment, it is<br />

considered that the preference should lie with permitting the population build up in accordance with the<br />

development planning if possible, albeit at the same time making a reasonable provision for employment.<br />

The recommended population threshold levels for differing levels of infrastructure provision as derived<br />

from the above sensitivity analysis are summarised in Table 7.20. In presenting this data, a ratio of<br />

population to total employment in the range of 4:1 to 8:1 has been adopted. The employment levels given<br />

include both industrial (TKOIE, Area 137 and 131) and general Metroplan employment.<br />

TABLE 7.20 :<br />

POPULATION THRESHOLD LEVELS<br />

External Infrastructure<br />

Population Threshold<br />

Employment Level<br />

Comments<br />

Existing<br />

243,000<br />

30,000<br />

B7 from Table 7.18<br />

Existing 4- MTR<br />

243,000<br />

43,000<br />

B3 from Table 7. 18<br />

Existing i- WCR<br />

380,000<br />

90,000<br />

Existing •f MTR -f WCR<br />

411,000<br />

100,000<br />

Section 7.2.7<br />

As discussed, the above thresholds have recognised the advanced and more definitive nature of the<br />

population planning for the developments in TKO and have used employment levels as the main variable.<br />

If, however for the existing situation, a more balanced relationship between population and employment<br />

at around 4:1 was considered desirable for planning purposes, then the population level would need to be<br />

reduced to around 180,000 (employment 38,000) as covered by scenario B8 of Table 7,18,<br />

It should be noted that the analysis is for sensitivity purposes and as such is indicative only. However,<br />

it does indicate that if no further external links are provided then the population level would need to be<br />

constrained. It is concluded that the recommended approach is B3/B7, namely, to encourage the full 2006<br />

population of 243,000 together with the development of the industrial areas including TKOIE and Area<br />

137, while limiting other employment. A ceiling of 28,000 (against a planned level of 76,000) on other<br />

employment would be required if the MTR were constructed. No MTR would reduce the employment<br />

figure'to 15,000.<br />

The combination of MTR and no Western Coast Road would seem an unusual transport investment<br />

strategy as generally the MTR is provided for areas of high growth rather than those where growth is<br />

being deliberately constrained. The strategy of mo Western Coast Road would therefore be expected to<br />

parallel a strategy of no MTR. Therefore, it (B7) must be considered that the lower Metroplan<br />

employment level of 15,000 would be the most realistic of the two.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

7.2.10 Summary of findings<br />

The construction of the Western Coast Road is critical to the future development of Tseung Kwan 0.<br />

Without this route not only will access to the proposed industrial developments be restricted, but the<br />

development of the New Town will be severely constrained. The traffic study is therefore based on the<br />

assumption that the Western Coast Road will be constructed to meet infrastructure and traffic demand.<br />

The main findings of the traffic study are:<br />

> The Western Coast Road is required by 2001 to serve Tseung Kwan O and to relieve the<br />

overloaded TKO Tunnel, for a New Town population of 241,000 and if all proposed industrial<br />

developments are implemented. It is essential that the Western Coast Road has high capacity and<br />

effective connections in Yau Tong in order to promote its use.<br />

» The present toll level on the TKO Tunnel of S3 should be increased to encourage a better balance<br />

of traffic across the western screenline.<br />

* A change in level of self-containment, i.e. more outcommuting, would require the timing of the<br />

provision of the Western Coast Road to be brought forward marginally. It would have no major<br />

impact on internal roads.<br />

*> Without the MTR Extension there would be additional congestion at the TKO Tunnel which<br />

would be heavily overloaded in the AM peak, although the screenline as a whole would operate<br />

at capacity.<br />

> The development of Area 137 increases the screenline flows by about 6%. The Area 131<br />

development increases screenline flows by about 1.5%. For the 333,000 population level and<br />

with the developments in Areas 137 and 131, the screenline will operate below capacity.<br />

* A design population of 440,000 for Tseung Kwan 0 would overload external links by 3% overall<br />

in the morning peak if the industrial developments are present. However, a vehicle ferry service<br />

and improvements to the Hang Hau corridor would provide sufficient additional capacity to allow<br />

the design population of 440,000 to be retained.<br />

* If the Western Coast Road has to be delayed beyond 2001, it is recommended that the target<br />

population figure for 2006 should be maintained together with the industrial developments at<br />

TKOIE and Area 137 whilst limiting other Metroplan employment to 15,000 against a planned<br />

level of 76,000, This level of employment would increase to 28,000 if the MTR was constructed.<br />

The latter situation is considered to be unlikely given that the development is being deliberately<br />

constrained.<br />

73 INTERNAL ROAD NETWORK<br />

7.3,1 Tseung Kwan O Area 137<br />

Area 137 is planned to be developed as a rolling programme with the first release of sites mid 1996 to<br />

1997. With due allowance for operator development of the sites, it is considered that traffic generation<br />

will commence in 1999 and progressively build up to a maximum around 2001. This has therefore been<br />

adopted as the first horizon year for the assessment of traffic from Area 137.<br />

It is estimated that some 70-80% of the development traffic will be heavy goods vehicles. Subject to the<br />

detailed use and operation of the PHI sites, the likely maximum volumes of vehicles carrying dangerous<br />

APH Consultants<br />

Page 7^


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

final Report - Main Report<br />

goods of Categories 1, 2 and 5 are expected to be some 500 pcus/hr 2-way and 250 pcus/hr 2-way in the<br />

AM and PM peak respectively. These vehicles are restricted from passing through Tseung Kwan 0<br />

Tunnel under the current Government tunnel regulations for safety reasons.<br />

The road network within Area 137 is shown in Figure 7.4. Access to the site is via Road D6, planned<br />

as a dual 2-lane but constructed initially as a 7.3 m single carriageway.<br />

Figure 7.5 shows the traffic assignments within Area 137 on completion of the full development in 2001.<br />

Highest link flows occur on the section of Road D6 immediately north of Area 137 as it is the only<br />

vehicular entry and exit. From there, development traffic is distributed throughout the internal road<br />

network.<br />

A roundabout is provided at the intersection of Road D6 and the site distributor roads to handle the major<br />

turning movement flows. The volume/capacity ratios at the roundabout are 0.52 and 0.40 during the AM<br />

and PM peak hours respectively. Other junctions have lower flows and therefore priority control is<br />

considered appropriate.<br />

7.3.2 Road Network within Tseung Kwan O<br />

Traffic forecasts were prepared for all the major links and junctions within TKO for years 2001, 2006 and<br />

2011, in order to assess the traffic impact of the proposed development. The Western Coast Road is<br />

assumed to be present from 2001, in accordance with the external access requirements.<br />

The critical elements of the highway network are generally the junctions and the traffic analysis has<br />

concentrated on examining the operation of the junctions on the major roads in Tseung Kwan 0. The link<br />

volumes have also been examined to establish whether there are elements of the strategic and primary<br />

network with insufficient capacity. For 2001 and 2006, with the Western Coast Road in place by 2001,<br />

the traffic volumes on all such links are below their design capacity. However, as noted earlier, by 2011<br />

the TKO Tunnel and Road Tl between the Tunnel and the junction with P2/P1 would be overloaded unless<br />

measures were taken to make the Western Coast Road relatively more attractive. The volume capacity<br />

ratio for Tl would be highest in the eastbound direction in the AM peak with a value of 1.26.<br />

By Year 2001<br />

Figure 7.6 shows the road network within TKO in 2001 and the affected junctions. The 2001 traffic<br />

forecasts are shown in Figure 7.7. The development in Area 137 will be fully completed in 2001 which<br />

gives maximum development traffic generations.<br />

Capacity calculations for the affected junctions were made and the results are summarised in Table 7.21.<br />

The calculations were based on the detailed junction layouts.<br />

APH Consultants<br />

Fa S e 7 ~ 18


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 121 :<br />

CAPACITIES OF AFFECTED JUNCTIONS IN TSEUNG KWAN 0 IN 2001<br />

Signalised Junctions<br />

SI Road D6/Road L373<br />

S2 Road D6/Road L371<br />

S3 Road D6/Road D9<br />

S4 Road D6/Road L9<br />

S6 Po Lam Road/Road L2<br />

S7 Po Lam Road/Po Fung Road<br />

S8 Po Lam Road/Po Hong Road<br />

Roundabouts<br />

Rl Road D9/Arca 86 Eastern Access<br />

R4 Road Pi/Road D4<br />

R5 Road D4/Road D3<br />

R6 Road D3/Road L30<br />

R7 Road P2/Road D2/Road D3<br />

With TKO 137<br />

AM Peak<br />

Reserve Capacity (%)<br />

+ 67<br />

+ 5<br />

+ 47<br />

+ 9<br />

4-32<br />

-f 67<br />

+ 30<br />

Volume/Capacity Ratio<br />

0.068<br />

0.979<br />

0.392<br />

0.841<br />

0.885<br />

PMPeak<br />

4-137<br />

+ 19<br />

+ 43<br />

+ 58<br />

+ 74<br />

+ 103<br />

+ 76<br />

0.043<br />

0.959<br />

0.368<br />

0.620<br />

0.605<br />

It can be seen that all the affected junctions are expected to operate within capacity level in 2001.<br />

By Year 2006<br />

Figure 7.8 shows the road network within TKO in 2006 and the affected junctions. The 2006 traffic<br />

forecasts are shown in Figure 7.9. As development in Area 137 have been completed in 2001, traffic<br />

growth in TKO is mainly due to the development in the rest of TKO.<br />

Capacity calculations for the affected junctions were made and the results are summarised in Table 7.22,<br />

APH Consultants Page 7-19


o<br />

"0<br />

*<br />

O<br />

c<br />

33<br />

Tl<br />

r*<br />

O


Figure 7.8<br />

S1<br />

SIGNALISED JUNCTION KEY JUNCTIONS<br />

AFFECTED 8Y AREA 137<br />

ROUNDABOUT KEY JUNCTIONS<br />

AFFECTED 3Y AREA 137<br />

31 JUNCTION NUMBER<br />

2006 TSEUNG KWAN 0 AND AREA 137 HIGHWAY NETWORK<br />

APH CONSULTANTS


Figure 7.9<br />

960 AM PEAK<br />

«00) PM PEAK<br />

2006 PEAK HOUR LINK FLOWS<br />

993 APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

TABLE 722 : CAPACITIES OF AFFECTED JUNCTIONS IN TSEUNG KWAN 0 IN 2006<br />

With TKO 137<br />

Signalised Junctions<br />

SI Road D6/Road L373<br />

S2 Road D6/Road L371<br />

S3 Road D6/Road D9<br />

S4 Road D6/Road L9<br />

$6 Po Lam Road/Road L2<br />

S7 Po Lam Road/Po Fung Road<br />

S8 Po Lam Road/Po Hong Road<br />

Roundabouts<br />

Rl Road D9/Area 86 Eastern Access<br />

R2 Road D9/Area 86 Western Access<br />

R3 Road D9/Road P2<br />

R4 Road Pi/Road D4<br />

R5 Road D4/Road D3<br />

R6 Road D3/Road L30<br />

R7 Road P2/Road D2/Road D3<br />

AM Peak<br />

Reserre Capacity (%)<br />

-*• 71<br />

4- 7<br />

-11(4-6)<br />

4* 17<br />

4* 22<br />

x 72<br />

T 26<br />

Volume/Capacity Ratio<br />

0.616<br />

0.699<br />

0.677<br />

0.735<br />

0.422<br />

0.780<br />

0.780<br />

PMPeak<br />

M37<br />

4- 20<br />

- 15 (4-3)<br />

4- 73<br />

4- 60<br />

4-118<br />

4- 80<br />

0.691<br />

0.647<br />

0.644<br />

0.603<br />

0.419<br />

0.618<br />

0.589<br />

Note:<br />

Figures in brackets assume junction improvements.<br />

The calculations suggest that the junction of Road D6/Road D9 (Junction S3) will be overloaded in 2006,<br />

assuming the current junction design, at -11 % and -15% during the AM and PM peak respectively. It is<br />

proposed that the Road D6 northbound approach be widened to 3 lanes. This will increase junction<br />

reserve capacity to 4-6% and 4*3% during the AM and PM peaks.<br />

By Year 2011<br />

Figure 7.10 shows the road network within TKO in 2011 and the affected junction. The 2011 traffic<br />

forecasts are given in Figure 7.11. The results of the junction capacity assessment are summarised in<br />

Table 7.23,<br />

APH Consultants Page 7-20


Figure 7.10<br />

PO LAMft<br />

SIGNALISED JUNCTION KEY JUNCTIONS<br />

AFFECTED BY AREA 137<br />

ROUNDABOUT KEY JUNCTIONS<br />

AFFECTED BY AREA 137<br />

31 JUNCTION NUMBER<br />

2011 TSEUNG KWAN 0 AND AREA 137 HIGHWAY NETWORK<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 7.23:<br />

CAPACITIES OF AFFECTED JUNCTIONS IN TSEUNG KWAN 0 IN 2011<br />

Signalised Junctions<br />

SI Road D6/Road LS73<br />

S2 Road D6/Road L871<br />

S3 Road D6/Road D9<br />

S4 Road D6/Road L9<br />

S5 Road D6/Road PI<br />

S6 Po Lam Road/Road L2<br />

37 Po Lam Road/Po Fung Road<br />

S8 Po Lam Road/Po Hong Road<br />

Roundabouts<br />

Rl Road D9/Area 86 Eastern Access<br />

R2 Road D9/Area 86 Western Access<br />

R3 Road D9/Road P2<br />

R4 Road Pi/Road D4<br />

R5 Road D4/Road D3<br />

R6 Road D3/Road L30<br />

R7 Road P2/Road D2/Road D3<br />

With TKO 137<br />

AM Peak<br />

Reserve Capacity (%)<br />

-r66<br />

+ 4<br />

-K+23)<br />

4-29<br />

+ 6<br />

+35<br />

•r44<br />

4-26<br />

Volume/Capacity Ratio<br />

0.532<br />

0.705<br />

0.709<br />

1.257(0.860)<br />

0.713<br />

0.821<br />

0.948<br />

PMPeak<br />

4-137<br />

4- 19<br />

-l(+26)<br />

4- 87<br />

4-56<br />

-*-39<br />

4-113<br />

4- 68<br />

0.589<br />

0.582<br />

0.603<br />

0.527(0.447)<br />

0.567<br />

0.693<br />

0.859<br />

Note:<br />

Figures in brackets assume junction improvements.<br />

The roundabout at Road Pi/Road D4 (Roundabout R4) is forecast to have capacity shortfall in 2011. It<br />

is proposed to widen the PI southbound approach to 3 lanes to bring the V/C ratios to below 1.0. All<br />

other junctions are expected to operate within capacity with the current junction design.<br />

The junctions T1/P1/P2 and P2/D1 are both grade separated junctions. The link flows as shown in<br />

Figures 7.7, 7.9 and 7.11 are within the link capacities.<br />

The Transport Planning Design Manual principles suggest that the hourly v/c ratio for roundabouts should<br />

be less than 0.35. V/C ratios have been examined for all years on an hourly basis for the roundabouts<br />

which are approaching capacity. The results are indicated in Table 7.24. V/C ratios for Roundabout R4<br />

in 2011 assumes that the improvements suggested above have been implemented.<br />

APH Consultants Page 7-21


Figure 7.11<br />

750 AM PEAK<br />

(460) PM PEAK<br />

2011 PEAK HOUR LINK FLOWS<br />

APH CONSULTANTS


Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

TABLE 7JA :<br />

HOURLY V/C RATIOS FOR ROUNDABOUTS<br />

Volume/Capacity Ratio<br />

2001<br />

2006<br />

2011<br />

Roundabout<br />

AM<br />

PM<br />

AM<br />

PM<br />

AM<br />

PM<br />

R4<br />

R6<br />

R7<br />

0.826<br />

0.682<br />

0.791<br />

0.850<br />

0.562<br />

0.545<br />

0.659<br />

0.637<br />

0.698<br />

0.536<br />

0.560<br />

0.530<br />

0.765<br />

0.746<br />

0.845<br />

0.461<br />

0.630<br />

0.771<br />

7*4 PUBLIC TRANSPORT REQUIREMENTS<br />

Although Area 137 is only anticipated to support approximately 1,700 jobs by 2011, it will be at the<br />

southern end of a peninsula of development forecast to contain almost 50,000 jobs. At the north of this<br />

industrial corridor will be a residential area (Area 78) with a forecast population of 27,000, and a small<br />

bus terminus (in Area 86).<br />

The peninsula will attract heavy public transport demand at shift change times, sufficient to justify<br />

provision of ftanchised services. A bus terminus in Area 137 should be provided to cater for routes<br />

servicing the peninsula as a whole. This should be sited near the southern end of the peninsula.<br />

The Final Report of TKOFSOFD proposed such a terminus to cater for two internal routes (from Area<br />

3/4 and Area 38) and three external routes (from Wan Chai Ferry, Ngau Tau Kok and Tsz Wan Shan).<br />

This appears to be a reasonable planning assumption. Most of these routes would not be justified for all<br />

day operation; possibly only the internal routes, or none at all if local GMB service is provided.<br />

Consideration should be given to extending proposed route 95K (from China Ferry Terminal to Area 86),<br />

to Area 137 at peak periods.<br />

Figure 7.12 shows the suggested arrangements for routing and terminal location for the proposed bus<br />

service.<br />

APH Consultants P&S* 7-22


Figure 7.12<br />

CLEARWATCR SAY<br />

COUNTRY PARK<br />

TATHOHC CHANNEL<br />

UUI WAN<br />

BUS ROUTES AND TERMINAL IN AREA 137<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

final Report - Main Report<br />

SECTION 8<br />

WESTERN COAST ROAD<br />

8.1 INTRODUCTION<br />

The analysis in Section 7 has identified that the existing access to Tseung Kwan O would have insufficient<br />

capacity to cater for the projected external traffic flows by 2001 and that the Western Coast Road will<br />

need to be constructed by that date in order to avoid any constraints being imposed on the level of<br />

development of Tseung Kwan O.<br />

It has been proposed that the Western Coast Road will connect to both the existing Lei Yue Mun Road<br />

and Cha Kwo Ling Road in Yau Tong. Two alternatives were put forward in the TKOFSQFD for the<br />

alignment of the Western Coast Road through Yau Tong for these connections :<br />

*•<br />

Option A, the direct connection to Lei Yue Mun Road and Cha Kwo Ling Road;<br />

> Option B, connection to Lei Yue Mun Road via Yau Tong Road.<br />

Under this Study, a comparative assessment of these two alternative connections was required, leading to<br />

the identification of the most suitable option and the finalisation of a road reserve.<br />

As part of the strategic highway network, the Western Coast Road will link Roads P2 and D9 in Tseung<br />

Kwan 0 with the Kai Tak Connector, the Kwun Tong Expressway and the Eastern Harbour Crossing in<br />

East Kowloon. The provision of the Western Coast Road complements the Tseung Kwan O external<br />

routes by providing an alternative for traffic generated by the industrial developments in Tseung Kwan<br />

O. This will be of particular benefit to dangerous goods traffic from the potentially hazardous installations<br />

of Area 137 which will not be able to use the TKO Tunnel. This latter requirement only serves to<br />

reinforce the need for the early provision of the Western Coast Road to ensure that any risks associated<br />

with such traffic using the Po T>Tfr Road in the interim, are minimised.<br />

8.2 WESTERN COAST ROAD CONNECTIONS<br />

8.2.1 Option A, Direct Connection to Lei Yue Mun Road (Figure 8.1).<br />

The Western Coast Road divides into two, 2-lane, dual carriageways south of the village of Sam Ka Tsuen<br />

on the Lei Yue Mun headland. The Cha Kwo Ling Road Link follows the alignment of Cha Kwo Ling<br />

Road at an elevated level before joining the existing carriageway north of Yau Tong Bay. From this point<br />

the road will eventually connect to the Kai Tak Connector.<br />

The Lei Yue Mun Road Link passes over a new roundabout intersection on Ko Chiu Road and Yan Wing<br />

Street, before joining the existing 2-lane dual carriageway of Lei Yue Mun Road between the Ko Chiu<br />

Road and Yau Tong Estates.<br />

The existing at-grade Cha Kwo Ling Road will require re-alignment throughout to accommodate the<br />

location of the supports for the elevated structure. Realignment will be possible by the construction of<br />

retaining structures along the route, which will then allow for the provision of two at-grade traffic lanes<br />

in each direction.<br />

APH Consultants<br />

Page


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

8.2.2 Option B, Connection to Lei Yue Mun Road via Yau Tong Road (Figure 8.2).<br />

In Option B, the Western Coast Road does not divide at Sam Ka Tsuen village, but instead follows the<br />

alignment of Cha Kwo Ling Road, at an elevated level, as in Option A. After Sze Shan Street, the route<br />

divides and a connection to Yau Tong Road is made by elevated slip roads. From the point of diversion<br />

of the slip roads, the elevated Cha Kwo Ling Road continues as a 2-lane dual carriageway until it joins<br />

the existing at-grade dual 2-lane carriageway to the north of Yau Tong Bay.<br />

The existing, single carriageway, Yau Tong Road will be reconstructed as a 2-lane dual carriageway along<br />

the same alignment as the existing road until it joins Lei Yue Mun Road just north of the Yau Tong<br />

playground. The intersection of these roads, including the re-aligned link to the Eastern Harbour<br />

Crossing, is catered for by provision of an at-grade roundabout.<br />

As for Option A, the existing at-grade Cha Kwo Ling Road will require realignment throughout to<br />

accommodate the location of the supports for the elevated structure. In so doing, two traffic lanes in each<br />

direction will be provided.<br />

8.3 EVALUATION OF OPTIONS<br />

The Western Coast Road Options will have significant impacts on existing land uses in the Lei Yue Mun<br />

and Yau Tong areas in East Kowloon. The increased volume of traffic anticipated under each Option will<br />

exert significant environmental impacts along the road alignment and the structure, form and width of each<br />

road alignment will have major physical and visual implications. Numerous Government, Institutional and<br />

Community (GIC) facilities are located along each alignment together with a number of recreational and<br />

residential land uses. Mitigation measures will be required wherever development is adversely affected<br />

by the new road development.<br />

In order to select the preferred Option, the two alternatives have been evaluated against a number of<br />

criteria. These are grouped under the following key categories:<br />

* Traffic and Roads<br />

> Land Use Impacts<br />

> Environmental impacts<br />

> Cost comparison<br />

In a number of cases the performance of the Options or the magnitude of their impacts are similar and<br />

these criteria do not provide a clear basis for selection of a preferred Option. The selection is therefore<br />

based on an evaluation of those criteria which do indicate sufficiently clearly a preferred alignment for<br />

the connection.<br />

8.4 TRAFFIC AND ROADS<br />

The traffic evaluation relating to the requirement for the Western Coast Road as part of the strategic road<br />

network has been reported in Section 7, along with various sensitivity tests to examine the impacts of f<br />

among others, the Area 137 and Area 131 developments, the construction of the MTR Extension,<br />

increases of population levels and delays in the construction of the Western Coast Road, The effects on<br />

traffic flows of improvements downstream of the connections were also examined.<br />

The traffic analysis found that it is essential that the Western Coast Road has high capacity and effective<br />

connections in Yau Tong in order to promote its use. This requires improvements in the Yau Tong area<br />

which include the upgrading of the Lei Yue Mun Road to dual 3 lane for the section between Western<br />

APH Consultants P


Figure 8.2<br />

"\ *•->*" "V .<br />

- "Via >.-L 5 »'^<br />

«« _*»:;,... P. —.<br />

jr...- T. -. • •^•^•sM<br />

WESTERN COAST ROAD CONNECTION - OPTION B<br />

APH CONSULTANTS


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Coast Road and Kwun Tong Road and upgrading of the Cha Kwo Ling Road between the Western Coast<br />

Road and Kwun Tong Bypass. Table 8.1 shows the demand flows and volume/capacity ratios for major<br />

links in the AM peak with these improvements to Lei Yue Mun Road and Cha Kwo Ling Road.<br />

TABLE 8.1 :<br />

2011 DEMAND FLOWS ON IMPROVED NETWORKS FULL DEVELOPMENT (PCU/HOUR)<br />

Link<br />

Practical Link<br />

Capacity<br />

Direction<br />

Option A<br />

AM Peak<br />

Option B<br />

Cha Kwo Ling Road/<br />

WCR Connector<br />

3600<br />

3600<br />

W<br />

E<br />

2050(0.57)<br />

2200(0.61)<br />

1800(0.50)<br />

2000(0.56)<br />

Lei Yue Mun Road<br />

WCR Connector<br />

3600<br />

3600<br />

W<br />

E<br />

2500(0.69)<br />

2100(0.58)<br />

2850(0.79)<br />

2600(0.72)<br />

Western Coast Road<br />

5400<br />

5400<br />

W<br />

E<br />

4550(0.33)<br />

4300(0.80)<br />

4650(0.86)<br />

4600(0.85)<br />

Po Lam Road<br />

1500<br />

1300<br />

W<br />

E<br />

1050(0.70)<br />

1000(0.77)<br />

1000(0.67)<br />

1000(0.77)<br />

Tseung Kwan 0 Tunnel<br />

3600<br />

3600<br />

W<br />

E<br />

4150(1.15)<br />

4500(1.25)<br />

4050(1.13)<br />

4250(1.18)<br />

Hang Hau Road<br />

2200<br />

1600<br />

N<br />

S<br />

1800(0.82)<br />

1550(0.97)<br />

1850(0.34)<br />

1550(0.97)<br />

Note : Volume/Capacity ratio in brackets<br />

Option B provides a better connection of the Western Coast Road to East Kowloon than Option A in terms<br />

of traffic flows on the network. In so doing, Option B attracts a greater volume of traffic and thereby<br />

relieves congestion at the TKO Tunnel to a greater extent. Whilst this improvement is only marginal, it<br />

does indicate a preference for Option B.<br />

8.5 LAiND USE IMPACTS<br />

8.5.1 Land Requirements<br />

The construction of the Western Coast Road through Yau Tong and Lei Yue Mun will require<br />

considerable land take with associated impacts on both existing developments and planned land uses. Both<br />

Options encroach on adjacent land uses along Cha Kwo Ling Road. Existing embankments need to be<br />

cut back for road widening, requiring retaining walls and slope stability works. Option A requires<br />

additional land from the Ko Chiu Road and Yau Tong Estates as well as utilising land reserved for the<br />

proposed Lei Yue Mun Supplementary Housing Scheme, while the widening of Yau Tong Road for Option<br />

B encroaches on land to the north side of the existing road.<br />

8.5.2 Implications of Option A on Existing and Planned Land Use<br />

Cha Kwo Ling Road Link<br />

The construction of an elevated carriageway through the built up residential, commercial and industrial<br />

area along Cha Kwo Ling Road will result in severe environmental impact intrusions. Noise and air<br />

impacts will impinge on the utility of a proposed District Open Space east of the road alignment, the<br />

APH Consultants Page 8-3


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

adjacent 1C reserve within which is included a Roman Catholic Church and a kindergarten as well as the<br />

Sam Ka Tsuen Recreation ground on the west of Cha Kwo Ling Road.<br />

The Yau Tong Commercial Centre adjacent to the Roman Catholic Church reserve comprises commercial<br />

and recreational (cinema) provision. The ODP depicts the site developed for R(l) residential development;<br />

the proposed road will impact heavily on residential development on this site and noise mitigation<br />

measures will be required. Likewise, environmental impacts will affect the redevelopment proposals for<br />

Yau Tong Public Housing Estate.<br />

St Antonius Primary School abuts the Estate while Po CMu College is located west of Yau Tong Road.<br />

Both facilities have low levels of noise tolerance and will be adversely affected by the alignment of the<br />

Western Coast Road along Cha Kwo Ling Road. Noise impacts will be significant for each school and<br />

Po CMu College will suffer significant visual impacts. Traffic safety measures would be necessary to<br />

ensure the safe passage of children to and from each school.<br />

Noise and air quality impacts on the industrial buildings to the west of Cha Kwo Ling Road will also be<br />

particularly severe, particularly as in this case noise mitigation measures would not be required.<br />

Similarly, the utility of the Yau Tong Marine Lots sites would be contingent on a satisfactory air quality<br />

environment.<br />

The proposed Western Coast Road will also result in physical intrusions into adjacent properties. The Cha<br />

Kwo Ling Road link passes through an area of development whose tenure is largely served by short term<br />

tenancy arrangements. A number of these short term tenancies will be affected but there should be no<br />

resumption implications as they can all be terminated prior to the commencement of the site investigation<br />

or construction.<br />

The Cha Kwo Ling Road link then proceeds northwards encroaching on the USD Sain Ka Tsuen Complex.<br />

This development comprises a proposed combined market, indoor recreation centre and library complex.<br />

The proposed development will be physically constrained by the road alignment and noise and air quality<br />

impacts will require appropriate measures to be taken.<br />

Adjacent to the USD site is a *G* reserve for a proposed multi-storey car park. The carriageway passes<br />

over this site requiring a modification of development proposals.<br />

The Sam Ka Tsuen Recreation ground currently under construction to the west of the alignment will lose<br />

a marginal strip along the Cha Kwo Ling Road.<br />

On the west side of Cha Kwo Ling Road there is insufficient clearance between the Sunray Industrial<br />

Centre and Yau Tong Industrial Building Block 3 and the proposed elevated roadway. Clearances would<br />

vary between 4 m and 1 m, while Fire Services Department require a 5m clear access. This will<br />

necessitate the demolition of these buildings, with resultant loss of workspace. Resumption costs will be<br />

high, estimated to be in the order of HKS 250M (excluding any incentive payments),<br />

Another serious land take implication resulting from the alignment of Option A relates to the present<br />

configuration of the Yau Tong Marine Lots. 18 Lots will be affected by the encroachment of the new<br />

roads into their lots. This would necessarily result in a cost to Government if property is adversely<br />

affected by the road alignment. There is a proposal to rezone the Yau Tong Bay Area and a surrender<br />

of the existing lots and a new lot with revised boundaries could be granted if the registered lot owners<br />

wished to proceed with redevelopment. Although resumption costs may not then be payable, the use of<br />

land for road construction would result in a reduction of premiums accruabie to Government. Air quality<br />

set backs may effect the operation and utility of each site. Excepting these concerns, note should also be<br />

made of the loss of livelihood that would be incurred due to the alignment of the road through the Lots.<br />

APH Consultants<br />

p age


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

Lei Yue Mun Road Link<br />

Along the Lei Yue Mun branch of Option A, there would be severe impacts on proposed and existing land<br />

uses. Development of the proposed Lei Yue Mun Supplementary Housing Site would be largely blighted<br />

by the road alignment. The proposed alignment dissects the site creating two land parcels. Development<br />

of the resultant sites would be difficult due to the physical and environmental impacts. A reduction of the<br />

environmental impacts could be made by road enclosures and the construction of adjacent housing on<br />

podium development, although this would bring with it problems relating to ventilation of the enclosures,<br />

traffic management and road maintenance; in addition, Highways Department would be reluctant to allow<br />

the construction of an enclosure over an operating road.<br />

The proposed Option A alignment will also impact on the northern portion of Yau Tong Estate and the<br />

southern portion of Ko Chiu Road Estate. Again these are public housing estates and would require noise<br />

mitigation methods together with the use of mitigation measures at source and receiver. The physical<br />

intrusion of the road into proposed estate boundaries will not be as significant as in the Supplementary<br />

Housing Site. Nevertheless, the proposed residential layout may require revision due to the proximity of<br />

residential blocks to the road alignment. Similarly optimal building orientation would be required to<br />

afford maximum protection from noise impacts.<br />

A preliminary estimate by Housing Department indicates a loss of some 4,500 flats if Option A is adopted.<br />

This assumes that the Lei Yue Mun Supplementary Housing Site is totally undevelopable and part of Ko<br />

Chiu Road and Yau Tong Estates will be affected. The social costs of the construction of this link should<br />

also be borne in mind; these relate to the delay to the redevelopment of Yau Tong Estate, the inability to<br />

rehouse the affected tenants locally and the delay to HD's Comprehensive Redevelopment Programme.<br />

North of these estates is an open space reserve granted to USD for a rest garden and recreational<br />

purposes. Noise and air quality impacts may impinge upon the utility of the site. The Yau Tong Road<br />

Playground will be similarly affected. Physical encroachment into the site is not anticipated but access<br />

to the site may be constrained through the upgrading of the road network and additional pedestrian<br />

crossings may have to be provided.<br />

8.53 Implications of Option B on Existing and Planned Land Use<br />

Cha Kwo Ling Road Link<br />

The alignment of Option B is largely concentrated along Cha Kwo Ling Road. A connection to Lei Yue<br />

Mun Road is made along the alignment at the junction of Cha Kwo Ling Road and Yau Tong Road.<br />

Elevated road links will provide free flow access from Cha Kwo Ling Road to Yau Tong Road, The<br />

consequence of this Option will be that noise and air impacts will be more extensively concentrated along<br />

Cha Kwo Ling Road and there will be greater physical intrusion into adjacent properties.<br />

In addition to the land use impacts that Option A would have, as described in the Section above, the<br />

following further impacts will arise as a consequence of Option B.<br />

The new Cha Kwo Ling Road alignment will intrude further into the Sam Ka Tsuen Recreation ground,<br />

disrupting the proposed facilities and requiring their replanning.<br />

The north bound slip road at the junction of Cha Kwo Ling Road and Yau Tong Road will encroach into<br />

the area occupied by the Sunray Industrial Centre and Yau Tong Industrial Building Block 3 requiring,<br />

as for Option A, their demolition. The slip road will also severely encroach into the Po Chiu College site.<br />

Whilst no physical effect on existing buildings is anticipated, noise impacts are likely to be profound and<br />

part of the college playground will be lost. Substantial environmental mitigation measures will be required<br />

APH Consultants<br />


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

to ensure that a satisfactory environment can be obtained. Detailed assessment will be required for a<br />

decision on whether or not the college should remain at its present location.<br />

The northern section of the Cha Kwo Ling Road link of Option B will result in similar impacts to the Yau<br />

Tong Marine Lots as outlined above in the context of Option A, and will also impinge on the Cha Kwo<br />

Ling Road fire station.<br />

Yau Tong Road Link to Lei Yue Mun Road<br />

A site north west of the Po Chiu College has been reserved for open space purposes and has been<br />

allocated to Government. No planning has yet been undertaken for the site but its use would be in some<br />

doubt if the Yau Tong link of Option B were constructed.<br />

Further north along Yau Tong Road is a site reserved for the proposed East Kowloon Hospital. The<br />

design of the hospital would have to adopt self protective design measures in the vicinity of the Western<br />

Coast Road. A low noise open textured road surface and other 4 at source* mitigation measures would also<br />

be required if the proposed hospital were to be implemented.<br />

8.5.4 Land Use Impacts Summary<br />

A major advantage of Option B is that the sphere of influence and therefore the concomitant impact on<br />

existing and future land use will more limited than that of Option A. Option B would not, for example,<br />

preclude the development of Lei Yue Mun Supplementary Housing Site, Both Options will require the<br />

demolition of two industrial buildings.<br />

In terms of a comparative evaluation of the two Options the following assessment is made:<br />

> for existing land uses, including housing developments, public facilities etc, Option A is<br />

considered to have marginally less impact. Option B encroaches further into the Sam Ka Tsuen<br />

Recreation Ground (under construction) and impinges on the Po Chiu College and the Cha Kwo<br />

Ling Road fire station. Option A encroaches on the grounds of the Yau Tong and Ko Chiu Road<br />

Estates. Both Options encroach on the existing Yau Tong Marine Lots, Option B slightly more<br />

so;<br />

* for planned land uses, both Options encroach on the proposed Sam Ka Tsuen Complex and multistorey<br />

car park, as well as the proposed Yau Tong Bay Redevelopment. Option B will encroach<br />

on the proposed hospital site along Yau Tong Road. However, the major impact is that of Option<br />

A passing through the planned Lei Yue Mun Supplementary Housing Site, which would be<br />

severely disrupted if not rendered unsuitable due to the proposed road alignment, with significant<br />

loss (4,500) of flat production;<br />

> for industrial land uses, both Options have similar impacts with the required demolition of two<br />

industrial buildings.<br />

Options A and B are road options which, regardless of which is implemented, will have a major impact<br />

on an existing urban area- As has been shown, the utility of existing and planned development will be<br />

substantially affected by physical and environmental impacts. Valuable open space and public facilities<br />

will be lost or at least encroached upon and much needed housing development and upgrading proposals<br />

will be constrained by the loss of land and the need to provide environmental mitigation measures. From<br />

a land use planning perspective the selection of a link should not simply be cost driven. Substantial<br />

consideration should be given to the impact on people's livelihood and on the impact on the environment<br />

in which people live, work and relax.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

8.6 EN^VIRONSVIENTAL IMPACTS<br />

8.6.1 Noise Impacts<br />

The routes for each Option have been divided into segments for which noise levels were predicted in<br />

accordance with forecast peak traffic flows. Traffic flow forecasts used in this assessment are for morning<br />

peak flow in year 2011. Road traffic noise levels were calculated in terms of the L 10 (1-hr) in dB(A),<br />

using the U.K. Department of Transport procedures "Calculation of Road Traffic Noise" (CRTN), 1988.<br />

The maximum permissible road traffic noise level at the facade of domestic premises is 70 dB(A) L, 0 (1-<br />

hr). For educational institutions the suggested maximum noise level is 65 dB(A) L 10 (1-hr). Both<br />

domestic premises and educational institutions are considered to be noise sensitive receivers (NSRs). Of<br />

the many NSRs potentially affected by either Option, those likely to receive the greatest impact or those<br />

representative of a class of receiver were selected for impact modelling. Predicted noise levels were<br />

calculated based on the assumption that the road surface is of impervious concrete. Results of the<br />

modelling are shown below in Tables 8.2 and 8.3.<br />

TABLE 8.2 :<br />

OPTION A - PROJECTED TRAFFIC NOISE LEVELS AT MODELLED NSRs<br />

Major NSRs<br />

Major Separation from Predicted facade<br />

Traffic Noise the road kerb LlO(l-hr) dB(A)<br />

Contributor<br />

(m)<br />

Yau Tong Centre (West) (R1A)<br />

Yau Tong Estate (Block 17) (R2A)<br />

St. Antonius Primary School (R3A)<br />

Po Chiu College (R4A)<br />

Ko Chiu Road Estate (Block 1) (R5A)<br />

Yau Tong Est (Block 24) (R6A)<br />

Yau Tong Estate (Block 21) (R7A)<br />

20<br />

Cha Kwo<br />

Ling Road 26<br />

30<br />

16<br />

24<br />

Lei Yuc<br />

Mun Road 16<br />

42<br />

30<br />

79<br />

78<br />

SI<br />

35<br />

36<br />

80<br />

TABLE 8.3 :<br />

OPTION B - PROJECTED TRAFFIC NOISE LEVELS AT MODELLED NSRs<br />

Major NSRs<br />

Major<br />

Traffic Noise<br />

Contributor<br />

Separation from the<br />

road kerb<br />

(m)<br />

Predicted facade<br />

LlO(l-hr) dB(A)<br />

Yau Tong Centre (West) (RIB)<br />

Yau Tong Estate (Block 17) (R2B)<br />

Cha Kwo<br />

Ling Road<br />

26<br />

33<br />

84<br />

82<br />

St. Antonius Primary School (R3B)<br />

9<br />

36<br />

Po Chiu College (R4B)<br />

North bound slip<br />

road to Yau Tong<br />

Road<br />

15<br />

34<br />

Yau Tong Estate (Block 1) (R5B)<br />

Yau Tong Road<br />

3<br />

87<br />

APH Consultants Page 8-7


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

All predicted L 10 (1-hr) noise levels shown in the above tables exceed the 70 dB(A) limit recommended<br />

in HKPSG. In Option A, Ko Chiu Road Estate and Yau long Estate are the worst affected NSRs with<br />

predicted L 10 (1-hr) levels as high as 86 dB(A). In Option B, the worst affected NSRs are Yau long<br />

Estate (Block 1) and St. Antonius Primary School on Cha Kwo Ling Road, where the L 10 (1-hr) level is<br />

predicted to reach 87 dB(A) and 86 dB(A) respectively.<br />

Noise contours of typical sections of the roads for both Options have been defined. In all noise contour<br />

plots the 70 dB(A) contour was predicted to be at least 100 m from the centre line of the road. In the<br />

absence of noise control or mitigation measures, excessive noise levels within the 70 dB(A) contour<br />

distance of the roadway would preclude educational and/or residential development, thereby exerting a<br />

severe constraint on land use.<br />

Noise Mitigation Measures<br />

The use of pervious macadam road surface, rather than the concrete used in the generation of predicted<br />

noise levels, would reduce traffic noise by up to 3 dB(A), depending on traffic volume, speed and mix<br />

of light and heavy vehicles. Although attenuation of 3 dB(A) would not reduce the very high predicted<br />

noise levels to the limit set by HKPSG, use of pervious macadam would still be required on either Option<br />

A or B as an initial mitigation measure. However, additional measures would be required to achieve<br />

HKPSG limits.<br />

Road realignment to increase the setback distance of NSRs would be desirable, but not possible in either<br />

option due to space limitations. Distance separations shown in Tables 8.2 and 8.3 would need to be<br />

increased from their current range of between 8 m to 42 m, to over 120 m to achieve acceptable noise<br />

levels. Realignment to mitigate impacts to existing NSRs would also cause previously unaffected NSRs<br />

to be affected.<br />

Because limited space availability precludes adequate set backs, reduction of noise levels has been<br />

considered for a variety of mitigation measures at the noise source:<br />

> Roadside Barrier (4 m).<br />

+ Semi Enclosure, single carriageway.<br />

> Semi Enclosure, both carriageways.<br />

* Complete Road Enclosure (NSRs on both sides).<br />

Roadside barriers offer protection to low level receivers. The alignment and proximity of high rise<br />

residential development renders this kind of barrier ineffective. Use of semi-enclosure is considered to<br />

be a minimum requirement for noise reduction and can involve coverage of either a single or both<br />

carriageways. Single carriageway semi-enclosures are only effective when NSRs are on one side of the<br />

road and less than 20 m above the road surface. For receivers which are located more than 20 m above<br />

the road surface a noise reduction of only 2-3 dB(A) can be attained. Combining a pervious macadam<br />

surface with semi-enclosure yields a total noise reduction in the order of 5-6 dB(A) for receivers more<br />

than 20 m above road surface. A noise reduction of 5-6 dB(A) is however inadequate for both Options<br />

as NSRs require noise attenuation of more than 6 dB(A) to meet HKPSG limits. Where single<br />

carriageway semi-enclosures are ineffective but where NSRs are sited on one side of the alignment only,<br />

a semi-enclosure over both carriageways offers the protection of a total enclosure whilst allowing free<br />

venting of pollutants. Where high level NSRs are sited on either side of the alignment, complete road<br />

enclosure should be provided.<br />

Figures 8.3 and 8.4 show the locations of principal NSRs and the proposed noise enclosures. Breaks or<br />

openings have been introduced wherever the enclosures are not required for noise mitigation purposes.<br />

The minimum opening between the full enclosures is 10 m, for Option A.<br />

APH Consultants p e 8-3


Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

Fire regulations dictate that for any enclosure in excess of 230 metres forced ventilation is required to<br />

ensure that smoke generated in a fire is removed. For enclosures in excess of 450 metres full provision<br />

of fire safety equipment is required. The maximum length of enclosure, at 175 m (Option B), is less than<br />

these requirements and therefore would not be classed as a tunnel.<br />

Double glazing combined with air-conditioning for NSRs is an alternative noise mitigation measure.<br />

Provision of Type n glazing could reduce noise levels by 10-15 dB(A) according to HKPSG. For NSRs<br />

protected by semi-enclosures and higher than 20 m above road surfaces Type II glazing would achieve<br />

compliance with HKPSG noise standards and would obviate the need for total road enclosure. However,<br />

current Government policy is to undertake mitigation measures at source only.<br />

Construction Phase<br />

The Noise Control Ordinance (NCO) provides for control of noise from general construction work during<br />

evenings (1900-2300 hrs), night-time hours (2300 to 0700 hrs) and public holidays. Noise control<br />

regulations do not apply to non-holiday, daytime hours (0700-1900 hrs). Therefore, noise impacts can<br />

only be assessed with reference to a construction management plan and schedule. Because such details<br />

will not be available until the time of implementation, the construction impacts and mitigation measures<br />

are discussed in general terms only.<br />

For both Options A and B there are many NSRs which could be subjected to excessive noise levels during<br />

road construction. Of particular importance are the two educational institutions along Cha Kwo Ling Road<br />

(St Antonius Primary School and Po Chiu College). Construction methods and activities will require<br />

careful planning and execution to minimise disturbance to these establishments. Because both of the<br />

Options also require construction in the immediate vicinity of numerous residential blocks, construction<br />

methods and activities will also require careful coordination in these areas.<br />

Noise control methods which limit effects on NSRs include:<br />

* use of silenced equipment<br />

» siting equipment as far as possible from NSRs<br />

> use of temporary moveable acoustic barriers and machinery enclosures<br />

> proper maintenance and operation of plant<br />

> scheduling of works<br />

If piling is required, the use of percussive piling would give rise to excessive noise impacts particularly<br />

given the proximity of the NSRs. Consideration should be given to the use of bored piles which provide<br />

less of a noise impact.<br />

8,6*2 Air Quality Impacts<br />

As discussed in Section 8,6.2, total enclosures have been proposed to ameliorate the road traffic noise.<br />

In so doing, concern has turned to the likely air quality impact in the vicinity of the portals of these<br />

enclosures.<br />

For Option A t the worst case will be from the two enclosed sections and two separate modelling cases<br />

have been investigated. For end portal emissions the pollution is assumed to be generated within the two<br />

enclosures. For the 10 metre central opening, between the enclosures, a second exercise has been carried<br />

out which assumes that 33 % of pollutant generated within the two enclosures escapes through the opening.<br />

In summary this means that for portal emissions the SR at Yau Tong Estate (Block 24) will be subjected<br />

to 50% of the pollutants generated within the two enclosures and for the vent opening a separate "worst<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

case" is used which results in SR at Ko Chiu Road Estate (Block 1A) being subjected to 33% of the<br />

pollutants from the two enclosed sections.<br />

For Option B, it is the 175 m length of dual enclosure which has been identified as critical. To model<br />

the worst case it has been necessary to take account of carry over of pollutants from adjacent enclosed<br />

sections. At Yau Tong Estate (Block 2) it is assumed that 50% of the 175 m enclosure and 30% of the<br />

115 m enclosure contribute to the portal emission. At Po Chiu College 50% of the 175 m and 70% of<br />

the 115 m enclosures are assumed. For St. Antonius' Primary School 100% of the 110 m enclosure is<br />

assumed.<br />

In order to predict potential impacts, critical sensitive receptors have been identified for the two options<br />

and modelling has been carried out to quantify the air pollution condition at the receptor. Nine existing<br />

receptors have been identified which are likely to be affected by the portal emissions as indicated on<br />

Figures 8.4 and 8.5.<br />

The pollutant levels derived from the modelling exercise have been compared against the Hong Kong Air<br />

Quality Objectives (HKAQO). The HKAQO sets hourly concentrations of 30,000 jig/m 3 for carbon<br />

monoxide and 300 /ig/m 3 for nitrogen dioxide which shall not be exceeded on more than three occasions<br />

per annum.<br />

For emissions of Carbon Monoxide (CO) the worst case condition has been identified at Yau Tong Estate<br />

(Option B). The predicted CO level is 2,888 /ig/m 3 which is within the AQO requirement. It is therefore<br />

assumed that CO concentrations will not be critical for this assessment. For NO 2 , exceedences have been<br />

identified and the full results of the modelling exercise are reproduced in Tables 8.4 and 8.5 below.<br />

Generally, the SRs for Option A are sited close to the proposed roadway and experience air quality<br />

exceedences at the portal areas, Ko Chiu Road Estate (Block 1) and Yau Tong Estate (Block 24). In<br />

Option B the more substantial setbacks, for the majority of the receptors, allows compliance with the<br />

AQO, with the exception of a major exceedence at the Yau Tong Estate (Block 2).<br />

Since the road and SRs are fixed, for both Options, mitigation must involve removal of the pollution<br />

source. Two methods of mitigation have been identified. The first involves extending enclosures, to<br />

move the pollution away from the SRs, and the second involves venting the enclosure along its length<br />

while retaining the noise attenuation characteristics.<br />

TABLE 8.4 :<br />

NO 3 CONCENTRATIONS AT RECEPTORS IN OPTION A<br />

NO 2 Concentration, /ig/m 3 due to<br />

Receptors<br />

Road Emissioin<br />

Portal Emissioii<br />

Total Emission<br />

Ko Chiu Road Estate Block 1A<br />

66<br />

173<br />

239<br />

Ko Chiu Road Estate Block 1<br />

164<br />

156<br />

320 #<br />

Yau Tong Estate Block 24<br />

1S6<br />

205<br />

391 #<br />

Yau Tong Estate Block 21<br />

53<br />

131<br />

134<br />

# denotes an exceedence of the AQO<br />

APH Consultants p ag€ s-10


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

TABLE 8.5 :<br />

NO 3 CONCENTRATIONS AT RECEPTORS IN OPTION B<br />

NQ 2 Concentration, /ig/m 3 , due to<br />

Receptors<br />

Road Emission<br />

Portal Emissk3ti<br />

Total Emission<br />

Yau Tong Estate Block 2<br />

257<br />

200<br />

457 #<br />

Yau Tong Estate Block 11<br />

33<br />

147<br />

235<br />

Po Chiu College<br />

100<br />

154<br />

254<br />

St. Antonius" Primary School - EB<br />

110<br />

111<br />

221<br />

St. Antonius' Primary School - WB<br />

141<br />

114<br />

255<br />

# denotes an exceedence of the AQO<br />

Mitigation for Option A<br />

Ko Chiu Road Estate Block 1<br />

At this location, the predicted total NO 2 concentration is 32Qjig/m 3 and exceeds HKAQO. This worst case<br />

condition assumes that all pollutants generated within the enclosure escape from the portal. There is no<br />

allowance for venting through the 10 metre opening at the mid point. There is no proven modelling<br />

technique to confinn the loss at this point but it seems likely that the actual NO 2 level will be less than<br />

predicted and it is stressed that this is a worst case.<br />

A practical mitigation to remove the NQ 2 impact is to extend the northern end of the 130 m enclosure by<br />

20 m. The increased path distance would reduce the NQ 2 level at the SR to 272 jig/m 3 which is within<br />

the AQO.<br />

Yau Tong Estate Block 24<br />

This receptor is predicted to be exposed to NCk levels of 391 /xg/m 3 . This does not take into effect the<br />

presence of the semi enclosure between the source and receptor. The additional path distance is predicted<br />

to reduce the pollutant level at the receptor to 336 /ig/m 3 , though this still exceeds the AQO. Again, a<br />

portion of pollutants will escape through the opening between the two enclosures and the NO 2 level at this<br />

receptor would be further reduced.<br />

In order to produce AQO compliance, increasing the width of the semi-enclosure across the full width of<br />

Lei Yue Mun Road would increase path distance, increase separation and reduce NO 2 concentration to 277<br />

/ig/m 3 , which is within the AQO.<br />

Mitigation for Option B<br />

There is a single exceedence of the AQO for NO 2 at Yau Tong Estate (Block 2). This particular SR<br />

experiences a major exceedence at 457 /ig/m 3 . The following mitigation has been identified to overcome<br />

this impact.<br />

> extension of the enclosure by 40m will increase the path distance to a point where air quality<br />

impact on the identified SR is acceptable. However, the emission will then impact on the Yau<br />

Tong Playground and will cause exceedence of the AQO.<br />

Consultants<br />

Page


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

> use of semi-enclosure to allow free venting of traffic generated pollutants and remove the<br />

concentration effect at the portal. Though overcoming the air quality impact this could,<br />

potentially, expose the Po Chiu College and the proposed hospital to noise levels in excess of the<br />

HKPSG. It should be possible to remove the potential noise impact on the new hospital through<br />

its design, ie present a non-sensitive facade to the road. However, in the case of the existing Po<br />

Chiu College, the use of sealed windows and air conditioning systems should be considered. A<br />

similar alternative would be to design a noise cover which allows free venting of air pollutants<br />

while retaining noise integrity. Louvre noise protection systems are designed to allow free<br />

venting above the roadway but conventional designs produce protected and non protected "sides"<br />

for high level noise sensitive receivers (NSRs). The louvre system offers good protection but<br />

would have to be considered in the light of the hospital design. It is believed that a design could<br />

also be produced which provides the required venting and noise integrity requirement.<br />

Mitigation by employing semi-enclosure or enclosure with free venting louvres would require an<br />

extension of the northern end of the 175 m enclosure by 20 m. With this extension, the NO 2 level<br />

would be reduced to 250 /xg/m 3 for enclosure with free venting louvres while that for semi<br />

enclosure would be expected to be lower than 250 /ig/m 3 .<br />

Air Quality within Enclosures<br />

An assessment of the air quality impacts within the enclosed sections was made by comparison with a<br />

study of the air quality in a proposed enclosed section of Route 5 in Tsuen Wan. This assessment was<br />

carried out using the most critical working conditions. The nominal dimensions of vehicles were estimated<br />

based on the traffic mix. Using these and the road details, the vehicle emissions within the enclosure were<br />

calculated using the procedures as outlined in the Road Tunnels Report (1987) by the Permanent<br />

International Association of Road Congresses (PIARC). The conversion of NO to NO> was assumed to<br />

be 10%.<br />

The resultant concentrations of CO, NO 2 and NO were less than one-third of the air quality limits as<br />

stipulated by EPD for the design of tunnels. The 200 m enclosure of Route 5 is expected to carry 3,444<br />

veh/hr with 68% of heavy vehicles. On the other hand, both the 130 m and 135 m long enclosures in<br />

Option A will have a traffic flow of 3,036 veh/hr with 62% of heavy vehicles. By comparison, it is<br />

unlikely that the air quality within the proposed enclosures will exceed EPD's criteria. Similarly, in<br />

Option B, the air quality within the 115 m and 110 m long enclosures should meet the above criteria.<br />

Construction Phase<br />

The major air quality impact during the construction of the Western Coast Road and the associated<br />

connecting road network will result from dust emissions measurable as total suspended particulates (TSP)<br />

and respirable suspended particulates (RSP). Major dust sources are likely to be:<br />

> site preparation;<br />

> excavation;<br />

+ wind erosion of stockpiled materials and working areas;<br />

* material transfer to and from trucks/barges;<br />

» vehicle/plant movements on unpaved roads and over the sites;<br />

* concrete batching; and<br />

> concrete finishing.<br />

Because construction schedules and equipment usage data are not available, dust levels arising from<br />

construction work cannot be quantified at this stage of evaluation. However, construction dust can be<br />

significantly reduced through appropriate site practices. The two Options are expected to be<br />

approximately comparable in terms of dust emission during the construction phase.<br />

APH Consultants p age #.£2


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

8.6.3 Visual Impacts<br />

An assessment of visual impacts includes the following aspects:<br />

> the apparent size of the development from selected viewpoints<br />

> distances from the development to the sensitive receivers<br />

> the number of sensitive receivers affected<br />

» the change in the visual amenity of the area<br />

The consideration of these visual aspects involves essentially a subjective assessment. Given the elevated<br />

nature of certain sections of the roads, the close proximity of the roads to sensitive receivers, the large<br />

numbers of sensitive receivers affected and the likely change in the visual amenity, it is considered that<br />

the visual impacts will be very significant and in some cases severe for both Options A and B.<br />

8.6.4 Environmental Impacts Summary<br />

For noise impacts, both Options would require extensive construction of semi or total road enclosures to<br />

reduce the noise levels to within the HKPSG limits. This is due to the existence of many noise sensitive<br />

receivers in the immediate proximity of both proposed alignments.<br />

In terms of a comparative evaluation, the two Options are considered with their required noise mitigation<br />

measures in place. The assessment is therefore based on residual noise effects as compared with the<br />

existing situation. In this respect, Option B is considered more suitable, as the residual traffic noise<br />

occurs over an area where traffic is already present, while Option A will generate traffic noise over a<br />

wider area, including where little or no traffic occurs at present.<br />

The assessment has identified exceedences of the Air Quality Objectives (AQO) for both Options and<br />

mitigation has been proposed to overcome the exceedence. In Option A the receptors are, generally, closer<br />

to the WCR and mitigation has involved extension of enclosure and semi enclosure to increase path<br />

distance to receptors and reduce pollutant concentrations to levels which do not exceed the AQO. In<br />

Option B there is a single, major, AQO exceedence at a single receptor. Mitigation to protect the affected<br />

receptor would require an integrated design approach and involves the layout and design of the hospital<br />

to the west of Yau Tong Road, It is proposed that the main enclosure is designed to be free venting<br />

through louvres which allow a measure of noise protection to elevated noise sensitive receivers.<br />

Significant permanent visual impacts will be generated by the construction of both Options, The<br />

installation of noise mitigation measures, in the form of road enclosures, will exacerbate the significant<br />

visual impacts of elevated major roadways.<br />

8.7 COST COMPARISON<br />

Indicative construction costs for the Western Coast Road, Options A and B, have been estimated for the<br />

comparative assessment of these Options. The estimated costs include the noise mitigation measures<br />

recommended in Section 8.6.1. Summaries of these costs are shown in Table 8.6 below.<br />

APH Consultants


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

TABLE 8.6 :<br />

CONSTRUCTION COSTS<br />

PRELIMINARIES<br />

EARTHWORKS<br />

Rock Excavation<br />

Soft Excavation<br />

Fill Material<br />

ROADWORKS<br />

Site Clearance<br />

Drainage<br />

Roads & Paving<br />

Footways & Kerbing<br />

STRUCTURES<br />

Elevated<br />

Retaining Walls<br />

SLOPE PROTECTION WORKS<br />

MITIGATION MEASURES<br />

SUB TOTAL<br />

ADD 10% CONTINGENCIES<br />

TOTAL ESTIMATE<br />

OPTION A<br />

HKS (MILLIONS)<br />

66.1<br />

11.6<br />

3.2<br />

9.2<br />

0.1<br />

7.4<br />

36.0<br />

2.0<br />

345.0<br />

28.0<br />

2.0<br />

217.0<br />

727.6<br />

72.8<br />

8004<br />

OPTION B<br />

HK$ (MILLIONS)<br />

68.4<br />

10.0<br />

2.0<br />

0.0<br />

0.1<br />

8.0<br />

31.0<br />

2.0<br />

383.0<br />

10.0<br />

4.0<br />

234.0<br />

752.5<br />

75.3<br />

827.8<br />

The construction cost of Option B is therefore about 3% more than that of Option A. For both Options,<br />

the cost of noise mitigation measures accounts for nearly 30% of the total construction cost.<br />

Resumption costs represent a significant addition to the total project costs. Major resumption costs<br />

applicable to both Options A and B are those relating to the demolition of the Sunray Industrial Centre<br />

and the Yau Tong Industrial Building Block 3. These have been estimated as being about HKS 250M,<br />

excluding any incentive payments,<br />

"Lost opportunity costs" have also been considered. Relevant Government Departments have been<br />

requested to supply the estimated abottive/reprovisioning/lost opportunity costs that would arise from the<br />

construction of either Option A or Option B.<br />

Urban Services Department have estimated these costs to be:<br />

> HKS 1.2M for the Sam Ka Tsuen Complex, This cost would be applicable to Option A and<br />

Option B as they both impinge on this site.<br />

> HKS 3.0M for the Sam Ka Tsuen Recreation Ground. This cost would be applicable to Option<br />

B. Option A encroaches only slightly and would not cause excessive disruption.<br />

Housing Department have estimated their reprovisioning costs to be:<br />

* HKS 260M for the reprovisioning of the Lei Yue Mun Supplementary Housing Site. This cost<br />

would be applicable to Option A. Option B does not affect this site.<br />

AfH Consultants<br />

p ag€


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

Project costs for the two schemes, based upon the above additions, are therefore estimated to be of the<br />

order of:<br />

> Option A: HK$ 1.311M<br />

* OptionB : HK$ 1,082M<br />

Option B is thus shown to be the more cost effective option,<br />

8.8 EVALUATION SUMMARY<br />

The above discussion of the two connections under the main criteria permits the following conclusions to<br />

be drawn:<br />

> Traffic and Roads: Option B is shown to have a marginal benefit in terms of traffic flow.<br />

+ Land Use Impacts: Both Options have severe impacts.<br />

Existing Land Use; Option A is considered to have marginally less impact.<br />

Planned Land Use; Option B, in avoiding the major impact to the Lei Yue Mun Supplementary<br />

Housing Estate, is considered have less impact.<br />

Industrial Land Use; both options have similar impacts.<br />

> Environmental Impacts: Both Options have severe impacts.<br />

Noise; Option B is considered more suitable on the basis of the residual impacts.<br />

Air Quality; Option B is considered to be more suitable in view of the limited number of receivers<br />

effected.<br />

Visual; both options have similar and severe impacts.<br />

» Cost Comparison: Option B has been shown to be the most cost effective.<br />

In all instances, bar the marginal additional effects upon existing land uses, Option B has been adjudged<br />

to have a lesser impact and is the most cost effective in project cost terms. It should be noted that both<br />

Options have extensive impacts and this preference must be measured in terms of a reduction in the<br />

severity of the impact rather than the identification of a optimum solution.<br />

Notwithstanding, Option B is recommended as the preferred alignment of the two required to be studied<br />

under the Brief. However, to establish as to whether this alignment does in fact represent the optimum<br />

for the connection of the Western Coast Road to East Kowloon, further study would be required over a<br />

wider area.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

SECTION 9<br />

ENVIRONMENTAL ASSESSMENT<br />

9.1 INTRODUCTION<br />

This assessment evaluates the environmental impacts associated with the construction and operation of<br />

Area 137. For significant impacts, mitigation measures are identified and, in addition, environmental<br />

monitoring and audit schedules are recommended. The potential impacts and mitigation are discussed<br />

under the following environmental indicator categories :<br />

+ Water quality;<br />

> Air quality;<br />

> Noise;<br />

> Waste Management; and<br />

> Visual Impact and Glare Nuisance<br />

9,2 KEY IMPACT SOURCES AND SENSITIVE RECEIVERS<br />

In the baseline studies the key impacts and existing and committed sensitive receivers (SRs) were<br />

identified. In this report only sources which have potential to create impact and potentially impacted users<br />

are identified.<br />

9*2-1 Impact Sources<br />

The development of Area 137 will, inevitably, create new environmental impact sources. Most<br />

construction phase impacts can be broadly defined, including the likely dredging and reclamation<br />

techniques. The impact of the operation phase is less well defined and potential impacts are less clear.<br />

As part of the Study, potential users of Area 137 have been identified and these are broadly split into two<br />

types of use. Both rely on the need for berthing facilities, but one use, by nature of the products to be<br />

handled is identified as PHI.<br />

In addition to the construction and operation impacts of Area 137 existing and known committed<br />

developments within Tseung Kwan O and adjacent areas have been assessed for significance. Of the<br />

numerous potential impact sources identified only four are believed to have a potentially significant<br />

bearing on the development and operation of Area 137. The location of the key impact sources are shown<br />

in Figure 9.1. The specific impact sources are :<br />

Tseung Kwan O Industrial Estate which is sited immediately to the north of Area 137. It is predicted<br />

that the operation of industry on the TKOIE site will generate noise, air quality, water quality and solid<br />

waste impacts though the impact on Area 137 is anticipated to be minimal.<br />

SENT Landfill is sited immediately to the north and east of the Area 137 development. During the<br />

construction and operation phases of Area 137 it is a requirement that road access to a sea berth, provided<br />

for the delivery of solid waste is maintained through the site. There are potential impacts on the noise,<br />

air and water environments.<br />

APH Consultants<br />

Page


Figure 9.1<br />

:-\'y ; u 6 V^A;*3<br />

TKOIE<br />

Junk Bay Landfill<br />

SENT Landfill<br />

Spoil Ground<br />

1 • •' v ' '•iLr'- •<br />

*\ ^/rx::-<br />

,xvm ; >..<br />

11 -* « ..'y«^Hrtiw»w<br />

KEY IMPACT SOURCES<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Find Report - Main Report<br />

Tseung Kwan O (Junk Bay) Landfill is sited to the north of Area 137 beyond the TKOIE site. The<br />

landfill is split into three phases with Phases I and II completed and Phase HI scheduled for completion<br />

in early 1994. Shortage of landfill space has dictated that the Phase I/H landfill will be reopened to accept<br />

a limited further input of waste. The landfills have potential impacts oa water quality from seepage of<br />

leachate into the receiving waterbody.<br />

Spoil Ground Beneath Area 137 represents, potentially, the most significant impact area. The spoil<br />

ground lies under part of the Area 137 development and may be affected by dredging and reclamation.<br />

Impact on water quality by disturbance of material and disposal of any contaminated material represent<br />

potential impact areas. The location of the spoil ground is shown in Figure 9.2.<br />

9.2.2 Sensitive Receivers<br />

As part of the environmental baseline study all potential sensitive receivers (SRs) within the Study Area<br />

were identified. Of these SRs only a limited number were identified as having potential to suffer impact<br />

from the construction and operation of Area 137, some were too remote from the impact sources others,<br />

though identified as sensitive were found to have been relocated or were in the process of relocation. The<br />

location of the sensitive receivers are set out in Figure 9.3. The potentially significant SRs are identified<br />

and described in the following paragraphs.<br />

Tung Lung Chau Fish Culture Zone (FCZ). A fish culture zone operates off the north western coast<br />

of Tung Lung Chau. Fish culture requires good water quality and is susceptible to impact at both the<br />

construction and operation phases of the project. This sensitive receiver is sited 2 km to the south east<br />

of Area 137.<br />

Siu Sai Wan and Chai Wan* The closest residential areas to Area 137 are sited to the south west across<br />

the Tathong Channel on Hong Kong Island. Residential areas are defined as SRs susceptible to both noise<br />

and air quality impact in the Hong Kong Planning Standards and Guidelines (HKPSG); in addition visual<br />

impacts will be significant. In order to allow predictions of impact to be made, two locations were<br />

identified at residential properties, Siu Sai Wan and Heng Fa Chuen. SRs are approximately 1.5 Km from<br />

Area 137.<br />

Tseung Kwan O New Town. The new residential areas to the north, within Tseung Kwan O, represent<br />

a significant grouping of SRs. The significance of Area 137 is diminished by the distance to SRs and the<br />

location of the TKOIE site, and established industry, between Area 137 and the SRs.<br />

93 WATER QUALITY<br />

93.1 Background<br />

Tseung Kwan O exhibits water quality conditions which reflect its geographical location as an embayed<br />

area close to Victoria harbour and also the effects of significant local effluent loadings. The water is<br />

organically enriched, and has relatively high levels of nitrogenous compounds and bacterial concentrations<br />

which are confirmed by the ongoing EPD water quality monitoring programme. Traditionally Tseung<br />

Kwan O has suffered significant effluent loadings and linked to the poor water exchange capacity, has<br />

experienced poor water quality. Junk Bay was declared a Water Control Zone (WCZ) in 1989. Following<br />

declaration of a WCZ effluent discharges require licensing to standards which are set out in the Technical<br />

Memorandum, An outfall from the sewage treatment works was constructed into the Tathong Channel<br />

to remove nutrient loading from Tseung Kwan O and this has resulted in improvements to the water<br />

quality. However, water quality conditions remain poor and are exacerbated by the additional loadings<br />

of leachate from the Junk Bay landfills and industrial discharges from Rennies Mill.<br />

APH Consultants Pag* 9-2


Figure 9.2<br />

Study Area<br />

Spoil Ground<br />

SPOIL GROUND BENEATH STUDY AREA<br />

APH CONSULTANTS


Figure 9.3<br />

ra yjMt. i \<br />

'/'£*.'. %'W|^<br />

^r^N^-.i^/' Mtt»<br />

»..V.«_v*AT.' J.. ,< Urwirwwo<br />

t>


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

The organic enrichment of the bay gives rise to elevated levels of chlorophyll-a, and blooms of toxic<br />

dinoflageiiates have been recorded in the past, the so called "red tides". Detailed reviews of water quality<br />

in Tseung Kwan O have been carried out in other studies, most notably the EA for the Tseung Kwan 0<br />

Development Sewage Treatment and Disposal Study. For this Study, water quality has been fully<br />

documented in the Environmental Background Paper and the Preferred Concept Report and is not detailed<br />

here, except in areas which have a direct bearing on Area 137.<br />

9.3.2 WAHMO Modelling<br />

The modelling evaluated the effects of the Area 137 reclamation on water quality in Tseung Kwan 0. In<br />

addition, several model runs were employed to provide data on the impacts of an additional reclamation,<br />

off Area 131 to the southwest of the bay.<br />

Previous studies of other developments in this area, using models from the WAHMO suite, have shown<br />

that worst case water quality conditions generally occur in predictions for the wet season and spring tides.<br />

However, due to other considerations, the water quality modelling included additional simulations for dry<br />

seasons/spring tides.<br />

The scenarios modelled were as follows:<br />

> Existing Conditions: based on present reclamations within the modelled area using estimated<br />

pollution loads for 1996.<br />

> Baseline: composing all committed reclamations within the modelled area.<br />

> Scenario 1: overlaying the baseline with the Area 137 reclamation.<br />

> Scenario 2: overlaying the baseline with the Area 137 development and Area 131.<br />

> Scenario 3: overlaying the baseline with an initial development of Area 137.<br />

» Scenario 4: overlaying the baseline with an initial development of Area 137 and Area 131.<br />

To assist interpretation of the water quality data from the modelling, 12 reference stations were set up as<br />

shown on Figure 9.4. These serve as reference sites for the production of water quality data in the form<br />

of CVT (concentration versus time) plots, which may then be employed to permit comparisons between<br />

the predictions for the existing situation and those for baseline conditions and for the various development<br />

scenarios.<br />

Water quality predictions are presented for existing conditions compared to those for the other scenarios<br />

under the worst case conditions of wet season spring tides. The parameters included are dissolved oxygen;<br />

BOD 5 ; various chemical species of nitrogen; chlorophyll-a; and £. colL<br />

Dissolved Oxygen<br />

Significant changes to dissolved oxygen levels were predicted for the baseline conditions and all<br />

development scenarios compared to existing conditions. However, there were essentially no differences<br />

between the model output for the baseline conditions and any of the development scenarios. In each of<br />

these cases, dissolved oxygen levels were predicted to increase significantly over those modelled for<br />

existing conditions at all reference sites other than numbers 1 and 11. These increases were most marked<br />

at reference sites 5 to 10, which are generally located in Tseung Kwan O and the Tathong Channel area.<br />

Evidence of supersaturation of oxygen was produced at reference sites 6 to 10 and 12, indicating the<br />

existence of significant algal growth (see the discussion of chlorophyil-a levels below).<br />

BOD 3<br />

Again, differences between the predictions for the baseline conditions and those for the development<br />

scenarios were minor and generally insignificant. However, the model output for each of these exhibited<br />

APH Consultants p age $-3


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Fined Report - Main Report<br />

significant differences from the predictions for existing conditions. Thus, BOD 5 levels were modelled to<br />

increase at most reference sites by comparison to the levels predicted for existing conditions. These<br />

changes were less marked at reference sites 1, 10 and 12 and were generally absent or very minor at<br />

reference site 11, whilst they were most evident at reference sites 6 and 7. For example, average BOD 5<br />

levels at reference site 6 increased from about 4 mg/1 in predictions for existing conditions to about 5 mg/1<br />

in output for the baseline conditions or the various development scenarios. It is notable that the increases<br />

in BOD 5 levels recorded here for wet season/spring tide conditions contrast markedly to the decreases in<br />

such levels noted for dry season/spring tide simulations.<br />

Nitrogenous Species<br />

Differences between the wet season/spring tide and dry season/spring tide simulations were again apparent.<br />

In the case of the wet season/spring tide output, concentrations of total nitrogen predicted for the baseline<br />

conditions or the various development scenarios increased at most reference sites by comparison to those<br />

predicted for existing conditions. These increases in inorganic nitrogen were accompanied by comparable<br />

elevations in levels of organic nitrogen and oxidised nitrogen, whereas predicted concentrations of<br />

ammoniacal nitrogen decreased in the baseline conditions and the development scenarios by comparison<br />

to existing conditions. These changes in the predicted concentrations and speciation of nitrogenous<br />

compounds were no doubt a contributory factor to the general increases in chlorophyll-a predicted for the<br />

development scenarios compared to existing conditions.<br />

Chlorophyll-a<br />

There were no significant differences between the predicted chlorophyil-a levels for the baseline conditions<br />

and the various development scenarios. However, each of these differed from predictions for existing<br />

conditions, most reference sites exhibiting increases in chlorophyll-a levels. Only reference site 11 was<br />

unaffected by these changes, although sites 10 and 12 to the south of Tathong Channel exhibited minor<br />

changes rather than the more marked alterations observed elsewhere. It may be noted here that WAHMObased<br />

studies on other developments have suggested that chlorophyll-a predictions are highly sensitive to<br />

small changes in the other parameters modelled. Nevertheless, the prediction that chlorophyll-a levels are<br />

likely to increase substantially in the eastern reaches of Victoria Harbour and in northern Tathong Channel<br />

consequent to the construction of the baseline reclamations is of some concern.<br />

E. coli<br />

By contrast to the other parameters modelled, very few changes were predicted for levels of E. coll in the<br />

Study Area, either for the baseline conditions or the various development scenarios. The only alterations<br />

of note occurred at reference sites 6 and 7, and these constituted small increases (less than one log value)<br />

in E. coli numbers over those predicted for existing conditions.<br />

These results give rise to several important conclusions concerning the options for the development of<br />

Tseung Kwan 0 as a whole. These are as follows:<br />

» Predicted water quality for the baseline conditions differed substantially from that for existing<br />

conditions. In the wet season/spring tide simulations in particular, the addition of the baseline<br />

reclamations (without altering assumed pollutant loads) created a significant reduction in water<br />

quality, with marked increases in several species of nitrogen and in predicted chlorophyll-a levels.<br />

These changes gave rise to increases in dissolved oxygen in the Study Area, reaching<br />

supersaturation levels in reference sites in Tseung Kwan O and Tathong Channel.<br />

* Such changes in predicted water quality are of considerable concern, as it would appear likely that<br />

the committed reclamations could lead to non-compliance with Water Quality Objectives in the<br />

Study Area, even in the absence of increased pollutant loadings. It should be re-stated that the<br />

APH Consultants p a g$


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report • Main Report<br />

reclamations giving rise to these predicted effects are the committed projects, and not those<br />

associated with either the Area 137 or the Area 131 developments.<br />

The differences between the predictions for the various future development options for Areas 137<br />

and 131 (and between these and baseline conditions) were ail minor. This implies that the<br />

alteration in shape of the Area 137 reclamation (involving either its phasing or its detailed design)<br />

has no material effect on water quality in the Study Area. The same is seen to be the case for<br />

the Area 131 reclamation, when this is present in combination with the Area 137 development.<br />

Thus, the various development scenarios were modelled to exhibit very similar water quality to<br />

the baseline scenario.<br />

9.3.3 Dredging and Disposal of Sediments<br />

Background<br />

It is known that the sediments within Junk Bay are contaminated due to historical industrial practises and<br />

the influence of contaminants from Victoria Harbour. Potentially more significant is the fact that Area<br />

137 will be sited on a former spoil ground. The information relating to the types of material which were<br />

dumped is not well documented. A limited sampling and testing programme has been carried out as part<br />

of this Study and, together with, results from other studies, has been used to identify potential impacts.<br />

The dredging for Area 137 is likely to be carried out by grab dredgers and will involve the removal of<br />

some 2.9 Mm 3 from the area to form the berthing areas, approach channels and the seawall trenches. It<br />

will be necessary to ensure that any grab dredgers used are fitted with tightly closing grabs in a well<br />

maintained condition, all dredging occurs within silt curtains and that ao overflowing of the barges is<br />

allowed. Water quality schedules and action plans are provided in Section 9.8.<br />

It is believed that more intensive survey work will be necessary in the detailed design phases of the project<br />

implementation to investigate the contaminated aspect further. The closest SR to Area 137 is the fish<br />

culture zone sited off the north western coast of Tung Lung Island section.<br />

Contaminated Sediments<br />

The marine sediments at Tseung Kwan 0 are routinely monitored by the Environmental Protection<br />

Department and show significant metal contamination. However, the EPD sampling does not cover the<br />

Area 137 site. As part of the Contaminated Spoil Management Study (CSM) sampling on the old spoil<br />

ground beneath Area 137 was carried out and testing showed elevated levels of lead and zinc and excessive<br />

mercury contamination. The location of CSM sampling sites in relation to area 137 are shown in Figure<br />

9.5 and results of the testing programme are reproduced in Table 9.1.<br />

TABLE 9.1 :<br />

CSM STUDY ANALYTICAL RESULTS OF SEDIMENT SAMPLES FROM THE STUDY AREA<br />

Cu Cr Cd Pb Zn Ni Hg<br />

Site bulk


Figure 9.5<br />

0 Study Sample Point<br />

CSM Sample Point<br />

SEDIMENT SAMPLING POINTS<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

As part of this Study additional sampling and testing was carried out and this confirmed the elevated levels<br />

of metal contamination, particularly lead. The sampling results are reproduced as Table 9.2.<br />

TABLE 9.2 :<br />

AREA 137 STUDY ANALYTICAL RESULTS OF SEDIMENT SAMPLES<br />

Site<br />

Metal<br />

Cd<br />

Pb<br />

Ni<br />

Zn<br />

Cr<br />

Hg<br />

Cu<br />

Jltop<br />


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Impact on Tung Lung Chau FCZ<br />

In determining the impact of dredging on marine ecology at Tung Lung Chau a worst case situation is<br />

assumed. The seawall trench is assumed to be formed by a grab dredger of 10 m 3 capacity working at<br />

a production rate of 50,000 m 3 /week in a 10 m water depth with maximum currents of 0.6 m/s.<br />

Dredging without the use of silt curtains and using an open grab will result in a loss of sediment, (the S-<br />

factor), of 10-15 kg/m 3 of mud dredged. Assuming 130 operational hours, the rate of sediment release<br />

will be 4,800 kg/hr. At a maximum current speed of 0.6 m/s, 2.2 kg of sediment will be injected into<br />

the plume per metre. The initial plume width is assumed to be approximately 50 m at a distance of 50 m<br />

from the dredger. If the current velocity and direction remains constant, sediment would reach the FCZ<br />

in approximately 55 minutes.<br />

Diffusion of the plume is inevitable and at 2 km distance the plume is assumed to have increased its initial<br />

width by a factor of 3 giving a worst case scenario of, at most, a suspended solids concentration of 1.6<br />

ing/l above the background at the FCZ.<br />

In addition, Work by Yagi et al., 1976 and Harris et al., 1988, has demonstrated the decline in suspended<br />

solids concentration downstream of a grab dredger. Typically, suspended solids values will fall by as<br />

much as 80% over a distance of 100 metres. This would support the above as a worst case, and therefore<br />

it is most unlikely that suspended solids will have an effect at the FCZ.<br />

Despite this, it is recommended that the following mitigation measures are adopted to minimise the<br />

potential dredging impacts, since incorporation of specific requirements within contract conditions offer<br />

an effective method of controlling impact, if strictly enforced :<br />

* utilising a grab which closes tightly preventing sediment loss as it ascends;<br />

> avoiding sediment overflow from die barge where possible; and<br />

* using a slower hoisting speed, (research by Yagi et al., has shown that a hoisting speed of 0.85<br />

m/s as opposed to 1.25 m/s, can reduce the suspended solids in the upper water column by 20<br />

to 30%.<br />

9,4 AIR QUALITY<br />

9.4.1 Background<br />

Area 137 is situated on the southern fringe of the Tseung Kwan O confined airshed. Confined airsheds<br />

have limited potential to disperse pollutants generated within the airshed. The reclamation work,<br />

construction and operation of Area 137 have the potential to introduce pollutants into the airshed and<br />

therefore impact on air quality. In addition there are also potential impacts on closer SRs at Chai Wan,<br />

across the Tathong Channel, to the south west.<br />

The meteorological characteristics of the southern fringe of the TKO confined airshed, and therefore Area<br />

137, had not been investigated in any detail prior to this Study. In order to determine if Area 137 was<br />

withui the confined airshed and therefore if pollutants generated by Area 137 would influence air quality,<br />

a limited air monitoring programme was carried out and compared with the results from EPD's Junk Bay<br />

monitoring station. It is recorded in the EPD publication Environment Hong Kong 1992 ttiat annual<br />

average and maximum daily pollutant concentrations recorded at the Junk Bay air quality monitoring<br />

station did not exceed the Air Quality Objective (AQO) in 1991.<br />

APS Consultants p age 9.7


Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

9.4.2 Monitoring<br />

A monitoring station was set up and operated at Tin Ha, immediately to the north of area 137 on the<br />

Clearwater Bay Peninsula, for the period 10 to 27 July 1992. The data obtained was compered to that<br />

recorded at the EPD monitoring station situated at the head of Junk Bay at the Haven of Hope Sanatorium.<br />

It is appreciated that such a short monitoring period does not allow definitive conclusions to be drawn<br />

though there appeared to be general correlation between the air quality data recorded at each of the<br />

monitoring stations. The results of the survey suggested that air quality was similar at both stations and<br />

it was therefore concluded that emissions from Area 137 would enter the TKO airshed. However, it was<br />

noted that there was a difference between the results for S0 2 pollutant levels, which were higher at the<br />

EPD station.<br />

Meteorological conditions were monitored at both stations and here there was very significant variance.<br />

Although the information was of interest, it did not influence the outcome of the assessment but confirmed<br />

that meteorological monitoring for Area 137 would have to be carried out at the site, over water, to<br />

remove the effect of local irregularities in air movements. The location of the EPD monitoring station<br />

and the Study monitoring station are shown in Figure 9.6.<br />

9.4.3 Assessment<br />

Air quality impacts will be generated during both the construction and operating phases of the project.<br />

Three distinct impact areas have been identified, two during operation and one during construction<br />

> road traffic accessing the Area 137;<br />

* potential emissions from industry;<br />

> dust from construction.<br />

Since the actual details of end users at Area 137 are undefined, the air quality assessment has involved<br />

a number of assumptions which will need to be confirmed fay specific assessment work as users come<br />

forward with development proposals. Generally the industry to be located here is unlikely to be air<br />

polluting, or, in the case of most PHIs, will be specified processes which are subject to controls set out<br />

in the Air Pollution Control Ordinance. A special case, which has been assessed as an indicator of<br />

significance, is town gas manufacture from naphtha. This process has potentially significant air quality<br />

impacts relating to SO 2 and NO 2 emissions. Port related industry is unlikely to involve manufacturing<br />

processes and is more likely to be involved in the receipt and packing / unpacking of material received<br />

/ dispatched by road or sea which will not impact on air quality.<br />

9.4.4 Road Traffic<br />

For air pollution initiated by road vehicles the vehicles numbers have been obtained from the Traffic and<br />

Transport Assessment carried out as part of the Study. Vehicle movements are relatively low but with<br />

a high proportion of heavy vehicles, which make up 74-78% of the traffic flow. Nitrogen oxide (NO),<br />

carbon dioxide (COn) and particulates are the main air pollutants arising from heavy vehicle movements.<br />

HKPSG notes that the buffer distance required for active and passive recreational uses is 20 metres from<br />

the kerb of either Trunk or Primary Distributor Roads. The closest SRs are located at Stu Sai Wan and<br />

Heng Fa Chuen which are over 1.5 km from Area 137 and will not be adversely affected by gaseous<br />

pollution generated by road traffic.<br />

9.4.5 Industry<br />

DWI uses have not been finalised but given the distance to SRs and the types of activities, these industries<br />

are unlikely to cause impact. In the case of PHI certain facilities have been identified for planning<br />

purposes and these include:<br />

APH Consultants Page 9-8


Figure 9.6<br />

EPD Monitoring Station<br />

Havea of Hope Sanitorium<br />

^""^s4"f$ ''fa<br />

mt*$Mw<br />

' • - » l .\TX I '\ J *»*<br />

Study Monitoring Station<br />

Tin Ha Village<br />

•^Y;-i^.,; N v:Rdl<br />

AIR QUALITY MONITORING STATIONS<br />

APH CONSULTANTS


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

» fuel storage;<br />

> bulk chemical storage;<br />

> Liquified Petroleum Gas storage<br />

> naphtha storage and gas production facility<br />

Of these identified developments the significant air polluting source is taken to be from the naphtha<br />

processing plant. This is designated as a Specified Processes under the Air Pollution Control Ordinance<br />

(APCO), which require the best practicable means to prevent emission of pollutants and to render such<br />

emissions harmless and inoffensive. The other facilities are unlikely to include combustion equipment and<br />

therefore no emissions of S0 2 or NO X are anticipated. Should these land uses be replaced by fiiel intensive<br />

industries, at a later stage, additional air quality assessment will be required.<br />

Sulphur Dioxide (SO^ and Nitrogen Dioxide Q^O^) are the major air pollutants arising from the town gas<br />

manufacture from naphtha and have been chosen as air quality indicators in this assessment. The scale<br />

and layout of the gas production plant has not yet been finalised, thus a typical S0 2 emission rate from this<br />

proposed plant is assumed as 10 g/m 2 /day. The emission rate corresponds to 18.5 g/s of SO 2 generated<br />

from a 16 ha area. For comparison the existing Ma Tau Kok gas production plant capacity is 3,0 x 10 5<br />

m 3 /day which corresponds to a maximum S0 2 emission rate of 3.9 g/s. Hence the assumed emission rate<br />

of 10 g/mVday for the Area 137 site corresponds to a cyclic catalytic gas production facility of about five<br />

times the capacity of Ma Tau Kok.<br />

For N0 2 , a typical emission rate of 15 g/nr/day has been derived, based on the existing Ma Tau Kok gas<br />

production plant. This assumed emission rate also corresponds to a cyclic catalytic gas production facility<br />

of about five times the capacity of Ma Tau Kok.<br />

The Industrial Source Complex Short Term Model (ISCST), has been used in the assessment with the<br />

following parameters:<br />

Emission Strength (SOJ 10 g/m 2 /day<br />

Emission Strength (NO 2 ) 15 g/mr/day<br />

Emission Height<br />

10 m<br />

Area<br />

16 ha<br />

Working Hours<br />

24 hrs/day<br />

Wind Speed<br />

2 m/s<br />

Wind Direction<br />

Downwind<br />

Atmospheric Stability 4 (D)<br />

Mixing Height<br />

500 m<br />

Temperature 25°C<br />

SRs at Tseung Kwan O New Town within the confined airshed have been identified in this assessment as<br />

being potentially critical. SRs are approximately 4 km north west of Area 137.<br />

Results and Implications<br />

The results show that the SO-, concentrations which SRs at Tseung Kwan O New Town could experience<br />

due to emissions from the activities of Area 137 would be 22/ig/in 3 (24 hour average), whilst the NO 2<br />

concentrations would reach 32 /ig/m 3 (24 hour average). The final report on TKOFSOFD predicted<br />

maximum S0 2 concentrations of 220 /ig/m 3 (after relocation of Shiu Wing) plus Ig/m 2 /day at the southeast<br />

corner of the Tseung Kwan O New Town. The corresponding maximum NO 2 concentration wouid^S<br />

/ig/m 3 (24 hour average) with the assumption of fuel oil (0.5% sulphur content). The AQO^s of 350<br />

/ig/mVday for SO 2 and 150 /ig/m 3 /day for NO 2 can therefore be achieved andit is therefore predicted chat<br />

town gas production at Area 137 will not impact on SRs.<br />

APR Consultants


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

9*4.6 Construction<br />

No detailed construction plans have been formulated, but it is assumed that dust would arise from the<br />

following activities:<br />

* general construction operations;<br />

> truck movements on unpaved roads;<br />

* aggregate storage piles; and<br />

* concrete batching.<br />

The Industrial Source Complex (ISC2) short-term model has been used to predict dust concentration from<br />

sources associated with these operations. Analysis carried out for the Preferred Concept identified the<br />

likely processes and predicted highest hourly concentrations for TSP at different distances from the source<br />

boundary, assuming worst-case meteorological conditions. There are no statutory criteria for construction<br />

dust, but a maximum hourly TSP concentration of 500 jig/m3 is generally adopted as a guideline for<br />

assessment. The closest SRs are located beyond the Tathong Channel at Siu Sai Wan and Heng Fa Cheun.<br />

Analysis suggests that SRs could be exposed to a dust level of up to 240 /ig/m 3 TSP due to vehicles<br />

operating on unpaved roads and this was identified as being the activity which would generate worst case<br />

conditions. This level is well within the advisory guideline of 500 pg/w for TSP from construction<br />

activity.<br />

Though identified SRs are not directly affected, simple dust mitigation methods can reduce impact further<br />

in the interests of the health and safety of workers on site, efficiency and visual impact. This mitigation<br />

can include imposition of speed limits, covering stockpiles/aggregates, providing water spraying and wheel<br />

washing facilities, and locating dust producing plant as far away from SRs as practicable. All mitigation<br />

measures can be implemented without significant cost implications and would in fact be normal practise<br />

on a well run construction site.<br />

9.4,7 Odour<br />

Potential odour sources may include aliphatic and aromatic hydrocarbons, sulphides and mixed chemical<br />

vapours. Given the distance to SRs odour nuisance is not anticipated to be a problem.<br />

9.4.$ Summary<br />

It is concluded that the air quality in Tseung Kwan 0 New Town will not change significantly due to the<br />

construction and operation of Area 137, and will continue to meet the AQO. However, due to the<br />

confined nature of the airshed individual air quality impact studies are recommended for major industrial<br />

developments when specific details are known. It is considered that any such study should include a<br />

period of background monitoring at or near the development site and not merely rely on the EPD Junk<br />

Bay Air Quality Monitoring Station data.<br />

9.5 iNOISE<br />

9.5.1 Background<br />

The characteristics of the site will be subject to dramatic change as new reclamations are created and<br />

development opportunities offered. This is particularly relevant to the TKODE industrial area immediately<br />

to the north of Area 137. Hie aoise assessment is limited due to the lack of specific details of end users<br />

for area 137. An assessment has therefore been made based on assumptions of probable end uses<br />

identified during discussions with Government and the private sector. In the future it will be necessary<br />

to carry out further assessments to confirm that developments comply with the requirements of HKPSG.<br />

APS Consultants<br />

p ag€


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Noise may impact on sensitive uses within Tseung Kwan O, however, the closest sensitive receivers are<br />

beyond the TKODE and of more immediate concern are the sensitive receivers to the south west of Area<br />

137, across the Tathong Channel, at Chai Wan. In line with the air quality study the assessment has<br />

considered both the construction and operation phases of the project and considered noise from road<br />

traffic, industry and construction as potentially the most significant impact areas.<br />

9*5.2 Road Traffic<br />

Traffic data for the year 2011 has been used in this assessment and is set out in Table 9.3. The high<br />

proportion of heavy vehicles should be noted reflecting the industrial nature of the area.<br />

TABLE 9.3 :<br />

FORECAST PEAK TRAFFIC FLOWS<br />

Options<br />

Good Vehicle<br />

(vch/hr)<br />

Private Vehicle<br />

(veh/hr)<br />

% Heavy Vehicle<br />

AM Peak<br />

1202<br />

303<br />

80<br />

PM Peak<br />

1194<br />

303<br />

SO<br />

Notes:<br />

1 goods vehicle (GV) equals 1.75 passenger car units (PCU)<br />

average speed, 30 kph<br />

normal road surface<br />

4-2.5 dB(A) correction for facade effect<br />

90° angle of view<br />

The SR at Siu Sai Wan is approximately 2 km from the noise source and Hang Fa Chuen is approximately<br />

3 km from the noise source.<br />

The predicted noise levels are between 55 and 57 dB(A). These values are well below the HKPSG of 70<br />

dB(A) at the facade of new dwellings, and 65 dB(A) at the facade of new schools.<br />

9.5.3 Industry<br />

The worst affected SRs are located at Siu Sai Wan, about L5 km away from the boundary of Area 137.<br />

According to HKPSG the day time and night time criteria for operational noise are 60 dB(A) and 50 dB(A)<br />

respectively. To achieve this level at the SRs at Siu Sai Wan the Area 137 boundary sound power levels<br />

for all of the noise sources should not exceed 129 dB(A) (day time) and 119 dB(A) (night time).<br />

Whilst land-uses for Area 137 are still largely undecided and detailed assessments will be required when<br />

developments are confirmed, it is considered that these site boundary sound power levels would not be<br />

exceeded by the operation of the development. Simple measures such as factory and building orientation,<br />

etc should be used to minimise noise levels at the site boundary.<br />

9.5 % 4 Construction<br />

In the Preferred Concept Report construction activities associated with Area 137 reclamation were<br />

identified, The numbers and items of machinery were quantified and the level of noise predicted for<br />

particular construction activities. The sound power levels for Powered Mechanical Equipment (PME)<br />

were derived from the Technical Memorandum (TM2) on Noise from Construction Works other than<br />

Percussive Piling, or from BS5228, Noise Control on Construction and Open sues.<br />

APE Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Noise levels at the representative NSRs for non-piling construction activities comply with the day-time<br />

criteria of 65 dB(A) set in TM2, as shown in Table 9.4. For these same activities during the hours 2300 -<br />

0700 hr, some exceedence of the night-time criteria of 50 dB(A) at the representative SR would occur.<br />

If night time construction work is necessary, suitable mitigation measures will need to be adopted or some<br />

activities restricted. Night work requires that a Construction Noise Permit (CNP) be issued.<br />

TABLE M :<br />

CORRECTED NOISE LEVELS DUE TO NON-PILING CONSTRUCTION<br />

NOISE LEVEL AT SENSITIVE USE<br />

Activity Description SIU SAI WAN HENG FA CHUEN<br />

1. Channel and Trench Dredging<br />

2. Trench Filling<br />

3. Wick Drains- Berth<br />

4. Berth Rock Bunds and Armour<br />

5. Marine Fill Reclamation<br />

6. Construction Waste Reclamation<br />

7. Quay Wall Construction<br />

S. Works Area<br />

9. Road Construction<br />

S. Infra-Structure<br />

44<br />

43<br />

46<br />

45<br />

62#<br />

61#<br />

63#<br />

54#<br />

54#<br />

58#<br />

40<br />

39<br />

42<br />

41<br />

58#<br />

58#<br />

59#<br />

50<br />

5i#<br />

54#<br />

exceeding the criteria of 50 dB(A) for night-time penod (2300-0700 hours)<br />

Based on the worst-affected NSRs at Siu Sai Wan, the recommended maximum sound power levels arising<br />

from the construction activities at the site boundary are:<br />

> all daytime (0700 to 1900 hours) of normal working day, 144 dB(A);<br />

> all days during the evening (1900 to 2300 hours), and general holidays (including Sundays) during<br />

the day time and evening (0700 to 2300 hours), 134 dB(A);<br />

> all days during the night time (2300 to 0700 hours), 119 dB(A).<br />

The above sound power levels should not be exceeded during construction operations and may be used<br />

as a guideline when selecting types and numbers of PME plant during later design stages.<br />

Percussive piling is restricted fay the Noise Control Ordinance and requires issue of a CNP.<br />

percussive piling the results show no exceedence of the noise standard of 85 dB(A) at any NSR.<br />

For<br />

Although there is compliance with HKPSG for daytime activities, to minimise potential for impact and<br />

to reduce night time impact to acceptable levels, the following procedures are proposed:<br />

* the construction programme should be carefully planned to minimise the accumulative noise<br />

impact;<br />

* noisy equipment should be located as far from Siu Sai Wan as possible;<br />

* use should be made of acoustic enclosures, silencers or noise barriers, where appropriate;<br />

> quiet items of equipment should be employed;<br />

APH Consultants<br />

p ag€


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

during the contract tender stage, specific construction method proposals should be made by the<br />

Contractors which will be examined for compliance of noise levels;<br />

a general day time noise limit of 75 dB(A) L^ (30 min) at SRs is recommended.<br />

9.6 WASTE MANAGEMENT<br />

9.6.1 General<br />

The quantities of waste arisings are anticipated to be relatively small (4 tonnes/day or 1,500 tonnes/annum)<br />

and can be disposed of at the existing or committed disposal facilities, i.e. SENT Landfill and the<br />

Chemical Waste Treatment Centre on Tsing Yi. This is in accordance with the Waste Disposal Plan for<br />

Hong Kong (1989). Environmental impacts are not anticipated provided that good operational standards<br />

and legislative requirements are adhered to.<br />

9.6.2 Marpol Wastes<br />

Until such time as the specific industries present their proposals, it is not possible to specify the waste<br />

storage and treatment facilities required. The potential environmental impacts associated with Annex I<br />

(Oily Residues) and Annex II (Noxious Liquids) will relate to:<br />

> spillages;<br />

> inadequate storage;<br />

> treatment processes;<br />

> transportation.<br />

Where possible, storage and treatment facilities should be shared between a number of operators,<br />

particularly for Annex I wastes.<br />

9.7 VISUAL IMPACT AND GLARE NUISANCE<br />

9.7,1 Introduction<br />

Area 137 is located on the south eastern tip of Tseung Kwan 0, on the west side of the Clear Water Bay<br />

peninsula. This is an extremely attractive area of the New Territories which is well used for recreational<br />

pursuits. The rocky coastline and high peaks create a spectacular landscape and overall the area is<br />

generally of a rural nature.<br />

To the north, east and west, the area is surrounded by high steep sided hills, which form an almost<br />

continuous ridgeline providing a dramatic backdrop to the Study Area. The hill sides are well vegetated<br />

with scrub and some localized wooded areas. The land to the east of Area 137 forms part of the<br />

extensively used Clear Water Bay Country Park.<br />

Looking southwards, from Area 137, towards Hong Kong Island, across the Tathong Channel, various<br />

residential developments are visible including the high rise areas of Chai Wan and Hang Fa Cheun and<br />

the low rise developed areas of Cape D* Aguilar.<br />

The proposed development within Area 137 includes a bottling and storage facility for LPG canisters, a<br />

storage area for chemicals, a naphtha plant and a number of godown facilities. Due to the nature of these<br />

facilities it is likely that much of Area 137 will be well lit on a 24 hour a day basis.<br />

APH Consultants<br />

p &g* 9-13


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

The major visual impacts are expected to be nuisance created by the glare of flood lighting and also the<br />

effect of placing an industrial development in what is currently a rural area.<br />

9.7.2 Methodology<br />

This sub-section examines the visual impact of the development of Area 137 on the main visual receivers.<br />

There is no recognised quantitative methodology for assessing visual impacts and, therefore, the<br />

assessment is largely subjective. Area 137 will be visible from a number of different viewpoints, detailed<br />

in the next sub-section. The visual impact from each of the major viewpoints will be assessed and where<br />

practicable appropriate mitigation measures described and proposed.<br />

9.7 J Sensitive Receivers<br />

Areas from which the development at Area 137 would be readily visible have been identified as being the<br />

sensitive receivers (SRs). These SRs can be divided into three main visual categories;<br />

*> Distant/long views; these include views from Cape D'Aguilar and Shek O;<br />

» Approaching views; views from the many passing ships and recreational and pleasure craft; and<br />

» Near views; views from the residential developments of eastern Hong Kong Island and the Clear<br />

Water Bay Country Park.<br />

The locations of the major land based SRs are given in Figure 9.7.<br />

Distant/Long Views<br />

Long views towards the Study Area will be possible from Shek O and Cape D* Aguilar. At present open<br />

seascape and the relatively undeveloped Clear Water Bay peninsula are seen from these viewpoints.<br />

Approaching Views<br />

Area 137 is visible from any vessels -approaching along the Tathong Channel. The current view from<br />

these points is essentially rural in character and the ridge of the Clear Water Bay peninsula slopes down<br />

to the coastline.<br />

Near Views<br />

The major sensitive receivers are on Hong Kong Island and include the Chai Wan and Heng Fa Cheun<br />

residential areas. Approximately 2 to 3 km from the Study Area, these areas will be susceptible to visual<br />

impacts and nuisance from glare.<br />

Views from the Clear Water Bay Country Park, which is extensively used by the general public for<br />

recreational activities such as hill walking, will also be affected by the development of Area 137.<br />

Potential sensitive receivers exist in Tseung Kwan O, these include the Haven of Hope Hospital, Tiu Keng<br />

Leng (Kennies Mill) and the existing and proposed residential developments of Tseung Kwan 0 New<br />

Town.<br />

9.7.4 Visual Impacts<br />

The proposed development within Area 137 is of low to medium rise in nature being generally limited to<br />

a maximum of 30 m in height. It is intended that any requirements to exceed this height will be<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

final Report * Main Report<br />

considered on an individual basis. As such the proposed development should not significantly affect the<br />

overall view towards the Tseung Kwan 0 area which is dominated by steep sided and relatively high hills<br />

which are typically between 80 m and 105 m high.<br />

An impression of the visual effect from a typical sensitive receivers viewpoint is given in Figure 9.8.<br />

This viewpoint is taken to be the 20th floor of a residential block in Chai Wan.<br />

Distant/Long viewpoints<br />

The Study Area is positioned such that there are a limited number of distant/long viewpoints which would<br />

be affected by the development, and the area is often obscured by mist and cloud for much of the year.<br />

However, on clear days it is possible to see that the area is largely undeveloped and distinctly different<br />

from the urban areas of Hong Kong and Kowloon. Long views towards the Study Area will be possible<br />

from Shek 0 and Cape D'Aguilar. The existing view from these areas is of an open seascape and the<br />

relatively undeveloped and scenic Clear Water Bay peninsula. It should be noted that planned<br />

development for Tseung Kwan 0 new town the Tseung Kwan O Industrial Estate and the SENT landfill<br />

will alter the rural nature of the area to urban.<br />

The proposed development at Area 137 is low to medium rise with extensive landscaping intended to<br />

create integration with the existing environment. These characteristics, coupled with the 5.5 to 8 km<br />

distance between these viewers and Area 137, mean impacts to distant/long viewpoints will be minimised.<br />

Approaching Viewpoints<br />

Pleasure craft and ships navigating the Tathong Channel will frequently pass the Study Area and the Area<br />

137 development will have an effect on the view of this section of coastline. Adoption of careful design<br />

in layout, contouring and landscaping will be used to mitigate the visual impact of the development in<br />

order to blend in with the rural background. The rural nature of the area will be altered significantly with<br />

the overall development of Tseung Kwan 0, thus the lower rise, landscaped nature of Area 137 will have<br />

comparably less impact in the future.<br />

Near Viewpoints<br />

A series of local views of the development at Area 137 can be obtained from the residential developments<br />

at Chai Wan and Heng Fa Cheun on Hong Kong Island. Generally the views from these areas are of high<br />

visual quality, mainly comprising of open seascapes and the undeveloped and scenic Clear Water Bay<br />

peninsula- These views and those from viewpoints in Clear Water Bay Country Park will be undesirably<br />

affected by the visual impact of development in Area 137.<br />

These impacts will be mitigated by careful and sympathetic design and landscape design. Use of<br />

contoured landscaping and structure planting using height variation and mounding within the development<br />

will be implemented to create a gradual and integrated transition from the sea to the backdrop of hills.<br />

It is intended that the incorporation of these measures will alleviate visual impact to sensitive receivers<br />

across the bay. Impacts to viewpoints on the Clear Water Bay peninsula will be mitigated by the<br />

incorporation of the integrated design theme. In addition this will include breaking up' within the<br />

development, introducing contoured green areas more in keeping with the surrounding area.<br />

There may be visual impact to potential sensitive receivers in Tseung Kwan O. However the majority of<br />

these are shielded from Area 137 by Fat Tong Chau (Junk Island), which is in direct line of sight, and<br />

any impacts on the developments within this area are not expected to be significant. It is understood that<br />

proposals are being considered for the further removal of Fat Tong Chau as a part of the Territories land<br />

formation activities and careful consideration will need to be given to the extent of removal if the benefits<br />

of this natural screening are not to be lost.<br />

APH Consultants pae 9-15


I—<br />

Figure 9.8<br />

PERSPECTIVE VIEW<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

9.7.5 Glare Impacts<br />

The quantitative assessment of glare from industrial developments is not meaningful at the feasibility and<br />

outline design stage when the required details are not available. The assessment is therefore of a<br />

subjective nature. Previous attempts to semi quantify glare have been made using the British Glare Index<br />

however this is only of use in operational circumstances.<br />

To represent a 'worst* case scenario it has been assumed that Area 137 will be in operation 24 hours a<br />

day and consequently the majority of the area will be flood-lit during the night. Impacts from lighting will<br />

be visible for a much larger area than the visual impacts, this is due to reflection off the sea and "lighting'<br />

of the cloud base.<br />

Impacts on Hong Kong Island<br />

Area 137 is in line of sight from the residential areas of Chai Wan and Heng Fa Cheun. At present the<br />

Study Area has no significant light sources' and consequently the presence of a brightly lit area on the<br />

horizon win significantly alter the night-time views currently enjoyed by these areas. In addition to these<br />

areas, other parts of eastern Hong Kong Island will, on cloudy nights, be affected by the reflected light<br />

from the cloud base.<br />

Impacts on Tseung Kwan O<br />

Although the majority of the existing and proposed developments in Tseung Kwan O are not in direct line<br />

of sight of Area 137, due to Fat Tong Chau blocking the view, the developments will be affected fay the<br />

light reflected down from the cloud base. This will add to the high night sky light levels already produced<br />

by the urban areas of Kowloon and Hong Kong Island and those that will arise from new developments<br />

in the area.<br />

Impacts on other areas<br />

As already stated before there are currently no significant light sources in the vicinity of Area 137, the<br />

presence of a flood-lit area and associated 'cloud lighting* could potentially alter the night time views<br />

currently enjoyed from areas such as Shek O and Lei Yue Mun.<br />

9.7.6 Mitigation of Impacts<br />

Mitigation of Visual Impacts<br />

The existing rural and scenic nature of the Study Area warrants the implementation of measures to mitigate<br />

the visual impact of the proposed development. It would not be practicable to hide the development behind<br />

bunding or screening but the visual severity of the development can be reduced with the incorporation of<br />

trees placed around the edges of the facilities of Area 137.<br />

Height variation, using mounding within the development and intermittent structure planting is proposed<br />

to break up impact of industrial buildings from distant views across the bay. Primary Structure planting<br />

will also reduce visual impacts and is discussed in Section 4.6 landscaping.<br />

New safety measures have introduced a design shape for liquefied petroleum gas which is lower in height<br />

than traditional round pressure vessels. The new horizontal pressure vessels or 'bullets' sit lower into the<br />

landscape which, in conjunction with landscaping features mentioned earlier, will encourage integration<br />

into the existing landscape. Creation of a gradual transition from the sea to the backdrop of hills is<br />

suggested to mitigate the visual impact of the industrial development both from long and short range view<br />

points.<br />

APH Consultants<br />

p age


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Mitigation of Clare Impacts<br />

Although it is difficult to assess the impact of glare from Area 137 the proposals are such that the lighting<br />

would be directly visible from a number of locations on Hong Kong Island and Kowloon and indirectly<br />

visible, through cloud reflection, from Tseung Kwan O and other areas of the Territory.<br />

It is possible to calculate a Glare Rating when the details of lighting requirements are available (these<br />

include type, location and number of light sources, intensities, direction the lights will face etc). However<br />

the best way to minimise (and in some cases eliminate) glare is by careful design of the lighting system<br />

for each site. In this way it is possible to achieve acceptable glare ratings for sensitive receivers located<br />

outside of the site boundaries.<br />

General recommendations for the enforcement of mitigation of glare include:<br />

> the use of low level lighting wherever possible;<br />

» the design and location of lighting should ensure that light is directed only where needed and<br />

generally facing east; and<br />

» the strength of light should be kept to a minimum level, at which the facilities can operate safely.<br />

The proposed intermittent structure planting would, when the trees reach sufficient height and maturity,<br />

help reduce the impact especially from low level sources.<br />

9,7.7 Conclusions<br />

The nature of the Area 137 development contrasts significantly with the surrounding environment. The<br />

development which is essentially industrial in nature is proposed for an area which is at present rural in<br />

nature. Views from areas on Hong Kong island in particular Chai Wan and Hang Fa Cheun, will be<br />

subject to the most significant visual impacts due to the development and potential glare from operational<br />

lighting.<br />

Distant/long views will also be affected but SRs are fewer and at a distance 5 to 8 km away. Views from<br />

vessels navigating the Tathong Channel will also be subject to detrimental visual impact, however, the<br />

exposure of such receivers is transient.<br />

The visual impact of the development can be mitigated by the use of building height restriction, layout<br />

and landscape measures to screen integrate the development.<br />

Careful design of floodlighting to minimise the amount of glare produced should be incorporated and<br />

specified during the detailed design stage. Landscape contouring by mounding and intermittent structure<br />

planting, buffer and screen planting, will promote integration into the existing landscape and alleviate the<br />

visual impact of the industrial development both from long and short range viewpoints, by creating a<br />

gradual transition from the sea to the backdrop of hills. These landscape measures plus careful positioning<br />

and design of lighting can mitigate to some extent the impact from the night lighting.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

9.8 ENVIIIONMENTAL MONITORING AND AUDIT SCHEDULES<br />

9.8.1 Introduction<br />

Environmental monitoring schedules and audit procedures are essential in order to:<br />

> ensure that any environmental impacts resulting from the construction and operation of the Area<br />

137 development are minimised or kept to * acceptable' levels at all times;<br />

+ establish procedures for checking that mitigation measures have been applied and are effective,<br />

and that the appropriate corrective action is undertaken if and when required; and<br />

* provide a means of checking compliance with environmental objectives, recording anomalies and<br />

documenting corrective action.<br />

This sub-section outlines monitoring and audit requirements for the construction and operation of the<br />

development in relation to air quality, noise and water quality, the details of which may be referred to in<br />

the appropriate sub-sections. Monitoring and audit activities for both construction and operation should<br />

be consistent and complimentary.<br />

Monitoring schedules have been provided for the necessary environmental parameters (Table 9.5 to 9.8),<br />

however at this stage it is only possible to provide outline schedules as guidance. Detailed monitoring<br />

schedule and audit requirements should be incorporated into the construction contract(s) and lease<br />

conditions for the Axea 137 development in the form of environmental clauses which should be prepared<br />

at the detailed design stage. These clauses should be agreed in consultation with EPD before being<br />

finalised.<br />

9.8.2 Technical/Personnel Requirements<br />

Responsibilities<br />

Ensuring that the environmental monitoring and audit requirements are met during the construction and<br />

operation of the development is the responsibility of the developer and operator(s) respectively.<br />

As the various facilities will inevitably be operated by a number of organisations, it is suggested that a<br />

body be established to oversee and co-ordinate monitoring and audit requirements and activities. This<br />

would help with consistency, reduce duplication and costs and be more likely to address cumulative<br />

impacts.<br />

Staff Organisation and Structure<br />

The monitoring and audit work should be carried out by suitably qualified and experienced personnel.<br />

This should be contracted to an independent organisation. The personnel would need to include a<br />

supervisor {who reports directly to nominated senior member(s) of the developer/operator's management),<br />

and include sufficient support staff to carry out the tasks. The supervisor will need to liaise with the<br />

resident site engineer (RE) during construction and the general site managers during operation.<br />

While the monitoring and audit personnel will be required to possess appropriate technical knowledge and<br />

training to carry out Hie tasks, they should also have access to a specialist advisor for each main aspect<br />

(Le aoise, air quality, water quality). It would be advisable for details such as qualifications and<br />

experience of these personnel to be sent to EPD for information/comment.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

Equipment<br />

The developer/operator should be responsible for providing appropriate monitoring and sampling<br />

equipment and facilities immediately upon award of the construction contracts to enable the monitoring<br />

to be carried out. The equipment should be approved in advance by EPD.<br />

Monitoring and Audit Manual<br />

The developer/operator should be required to prepare an environmental monitoring and audit (EM & A)<br />

manual, the content of the manual will have to be agreed with EPD prior to the start of the construction<br />

works, but it should include the following:<br />

> the construction programme and the required EM & A programmes to assess the environmental<br />

impacts due to the development with time;<br />

> the location, frequency and type of environmental monitoring and audit requirements to assess the<br />

environmental impacts of the construction:<br />

* the form/content of event/action plans (including any emergency plans) for air, water and noise<br />

impacts;<br />

> review of pollution sources and working practices/procedures required in the event of<br />

environmental pollution levels being exceeded;<br />

* the content/presentation of monitoring data, their audit and the actions taken with respect to noncompliance<br />

with environmental pollution levels;<br />

> appropriate report formats/frequency of submission/special event reports, etc.;<br />

> complaints/consultation procedures ;<br />

* equipment service records and calibration requirements; and<br />

> the locations of sensitive receivers.<br />

EPD also require that the EM & A should also provide for site management, project programme and<br />

environmental protection requirements in contract documents, land lease and engineering conditions.<br />

9.8.3 Reporting<br />

A monthly monitoring and audit report should be prepared by the monitoring and audit personnel within<br />

7 days of the end of each month and commencing 1 month after the commencement of construction.<br />

Copies of the report should be submitted to the senior management representative and simultaneously sent<br />

to EPD.<br />

The report should be a relatively brief and concise account of the environmental monitoring during the<br />

previous month and should include a summary of:<br />

*•<br />

Project Data - A synopsis of the project organisation; project programme; management liaison<br />

structure;<br />

+ Monitoring/Audit Requirements - Summary of monitoring parameters; Trigger/Action/Target<br />

Levels; Action Plans; environmental protection requirements in contract documents; land lease<br />

and engineering conditions;<br />

> Monitoring Methodology - Monitoring equipment used; locations; duration/frequency; standards<br />

to which the methodology refers;<br />

* Monitoring Results - Parameter; date; time; environmental and weather conditions; location;<br />

equipment calibration date; activities being carried out on site; etc.;<br />

APH Consultants fa& 9-19


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

> Audit Results - Review of pollution sources, working procedures in the event of non-compliance<br />

with environmental monitoring levels; action taken in the event of non-compliance; follow-up<br />

procedures related to earlier non-compliance actions;<br />

» Complaints - Liaison and consultation undertaken; subsequent action; database of telephone<br />

/written complaints, location of complaints; action plan and follow-up procedures etc.; and<br />

> Appendices - Appropriate drawings/tables of monitoring locations, sensitive receiver locations,<br />

environmental monitoring and audit requirements etc..<br />

The monthly monitoring and audit reports should be supported by submission of a six monthly and annual<br />

summary.<br />

9.8.4 Environmental Monitoring Schedules<br />

General<br />

Environmental monitoring falls broadly into two categories: firstly baseline monitoring which should be<br />

undertaken to establish or update/confirm the existing conditions in the Study Area (this makes it possible<br />

to set limits for the construction and operational phases); and secondly compliance monitoring, which<br />

should be carried out during both the construction and operational phases of the development to achieve<br />

the following 'general* objectives:<br />

» to assess the performance of construction/operation activities in environmental terms;<br />

> to obtain early warning of potential problem areas, permit timely remedial action and identify any<br />

environmental impacts;<br />

* to comply with appropriate standards and environmental objectives; and<br />

> to provide reassurance to local communities.<br />

As part of the monitoring schedules three levels have been devised to monitor compliance with<br />

environmental objectives and to provide early warning of potential problem areas, thus stimulating the<br />

implementation of mitigation before the regulatory standards are reached. The three levels are described<br />

below:<br />

> the Target Level is the maximum permissible level which will achieve compliance with the<br />

appropriate regulatory standards, and is therefore the upper boundary/limit which is acceptable<br />

in terms of environmental quality. Consequently, achievement of this level is undesirable and may<br />

lead to the cessation of activities. Compliance monitoring schedules are therefore devised such<br />

that remedial action is taken to prevent this level being attained.<br />

+ the Trigger Level is a reference value to be used as an 'early warning 7 of a deterioration in<br />

environmental quality. Achievement of this level may stimulate increasing the frequency of<br />

monitoring and undertaking preliminary investigation (for example to identify any obvious causes)<br />

and possibly remedial action if appropriate; and<br />

> the Action level indicates that deterioration is significant and that urgent corrective action is<br />

required.<br />

Monitoring will be required to measure noise levels, particulate levels (for air quality), total suspended<br />

solids and dissolved oxygen (for water quality). In addition, monitoring will involve checking on general<br />

working practices and compliance with the various control and mitigation measures. Results should be<br />

reported to the developer/operator and EPD, and reviewed on a regular basis.<br />

APH Consultants<br />

p age


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

The requirements for each of the environmental parameters are different, and therefore it is not possible<br />

to propose a single monitoring programme for all aspects. Requirements for individual parameters are<br />

summarized below, and where appropriate outline schedules are presented in Tables 9.5 to 9.8.<br />

Construction<br />

Environmental monitoring during construction will be the responsibility of the developer. For each<br />

construction site a check list should be prepared relating to each of the environmental issues as identified<br />

in the EIA. Together with environmental clauses in the contract documents, this check list will form the<br />

basis of a proforma for the environmental monitoring programme; these are sometimes collectively<br />

referred to as the EM & A.<br />

Air Quality Monitoring<br />

A programme of particulate monitoring should be developed to ensure both the effectiveness of dust<br />

control measures and to highlight any associated deterioration of air quality during the construction phases.<br />

This will necessarily involve simultaneous wind direction and wind speed monitoring. Baseline monitoring<br />

will need to be undertaken at the appropriate SRs prior to commencing construction. Compliance<br />

monitoring will subsequently be undertaken during dust generating construction activities to check that<br />

appropriate air quality standards are maintained.<br />

An outline ak quality monitoring schedule is presented in Table 9.5. The Target Level comprises the<br />

accepted TSP limits for construction sites, of 500ptg/m 3 (1 hr average) and 260/ig/m 3 (24 hr average).<br />

Definitions of Trigger and Action levels are given by the exceedence of the sample in relation to the<br />

baseline for the Study Area plus 30%, thereby allowing for fluctuating ambient levels. The Action Level<br />

is defined by the average of the Trigger and Target values. On breaching any of these warning levels,<br />

action should be taken as described in an outline action plan (Table 9.9).<br />

It is recommended that the baseline should consist of data from 12 months monitoring in the Study Area<br />

prior to commencing construction activities.<br />

Compliance monitoring should be carried out at the construction site boundary, with samplers located<br />

down wind of active working areas. Location of samplers should be remote from influencing factors such<br />

as roads, local obstructions, etc. As a minimum, 24 hr samples should be taken at each monitoring<br />

location once every six days and hourly samples should be taken at least three times every six days. The<br />

frequency and location of monitoring may alter in accordance with local meteorological conditions and<br />

the nature of construction activities.<br />

In addition, it will also be necessary to monitor and check the effectiveness of mitigation measures, this<br />

will involve monitoring the efficiency, maintenance and use of:<br />

> wheel washers;<br />

+ water sprays;<br />

> dust covers;<br />

> plant with filtration equipment; and<br />

* barriers and enclosures.<br />

Regular checks should be made to ensure:<br />

* enforcement of speed limits;<br />

> regular servicing of plant and site vehicles;<br />

+ appropriate construction methods are being utilised and work sites are located away from SRs;<br />

* site cleanliness and the implementation of good site practice.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Noise Monitoring<br />

Noise monitoring will be required to verify compliance with the guidelines for construction noise and with<br />

requirements of any construction noise permits (CNP) and criteria contained in the contract documents.<br />

In the absence of statutory controls relevant to unrestricted day-time hours (0700-2300hrs Monday to<br />

Saturday inclusive), it is generally accepted that a limit of 75 dB(A) 1^(30 min) should be used as a<br />

guideline. Consequently, for daytime noise, the Target, Trigger and Action Levels have been devised<br />

such that the Target is 75 dB(A) 1^(30 min). Trigger and Target Levels should be 65 dB(A) and 70<br />

dB(A) L^(30 min) respectively.<br />

Due to the inevitable and gradual transition of parts of the Study Area from a rural to an urban/industrial<br />

environment, these levels may need to be adjusted in accordance with EPD requirements. In such<br />

circumstances the Trigger and Action levels would be defined according to the occurrence and frequency<br />

of complaints (Table 9.6).<br />

Construction noise during restricted hours i.e. night-time (2300-0700hrs), public holidays and Sundays<br />

will be controlled under the provisions of a CNP. The Target is therefore the relevant ANL in the Noise<br />

Control Ordinance. Where a CNP is in force, monitoring results should be submitted to the developer<br />

and EPD immediately they are available. On breaching the permit, action should be taken as described<br />

in an outline action plan (Table 9.10).<br />

Day-time compliance monitoring should be undertaken, three times per week and involve measurement<br />

of 30 minute time periods during typical activity. Periods of high ambient noise, such as during peak<br />

traffic flows should be avoided. Restricted hour monitoring should be undertaken at least twice during<br />

the restricted hours, (per 24hr period, once in the evening and once in the night-time), for a 5 minute time<br />

period, in accordance with the Technical Memorandum on Noise From Construction Work, Other Than<br />

Percussive Piling. Measurements should be taken (1 m from the external facade) at the worst affected<br />

NSRs.<br />

Regular checks will also be required to establish the implementation and effectiveness of mitigation<br />

measures. This will require checking and monitoring on a regular basis of:<br />

> the use, maintenance and efficiency of silenced construction equipment;<br />

> the appropriate location of noisy plant/equipment;<br />

* the hours of operation;<br />

> the use and effectiveness of noise enclosures and barriers; and<br />

> the implementation of good site practice.<br />

Water Quality Monitoring<br />

The objective of water quality monitoring is to minimise adverse impacts on water quality which may<br />

result from construction activities. Monitoring is required to check the impacts resulting from dredging<br />

and will involve measurement of dissolved oxygen and suspended solids and turbidity.<br />

In addition to EPD's water quality monitoring programme, ambient levels will be determined by baseline<br />

monitoring at two locations close to the areas to be dredged.<br />

Compliance monitoring will be undertaken to establish compliance with the water quality objectives<br />

(WQOs). Target, Trigger and Action Levels have been defined according to the WQOs for Junk Bay and<br />

Eastern Buffer WCZ such that for both parameters (dissolved oxygen and suspended solids) the Target<br />

is the appropriate WQO.<br />

APH Consultants<br />

p ag€


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

In order to account for the significant seasonal variations in water quality, Trigger and Action Levels have<br />

been defined according to background levels as monitored at a number of representative control stations.<br />

The Trigger Level is 20% above the running background for suspended solids and 20% below the running<br />

background for dissolved oxygen. The running background is derived from the mean of monitored data<br />

taken at the control stations. The Action Level is the average of the Trigger and Target values.<br />

As a minimum, 2-3 designated monitoring stations should be established 100 m from the active<br />

dredging/reclamation areas, 1-2 control monitoring stations should be established at appropriate locations<br />

which will not be influenced by the project or any other development activities. Samples should be taken<br />

at both the control and designated monitoring stations at least 3 times per week.<br />

In order to check the effectiveness of mitigation measures it will be necessary to ensure:<br />

* drainage channels, settlement tanks and other construction phase water pollution control measures<br />

are being used and maintained;<br />

* the effectiveness and maintenance of oil/grease interceptors;<br />

» the use of equipment for removing floatabies; and<br />

> the use and adequacy of any waste reception facilities.<br />

Operation<br />

Environmental monitoring during the operation of the Area 137 development is necessary to verify the<br />

findings of the EIA, and is the responsibility of the Operator(s) in accordance with the lease conditions.<br />

An outline monitoring schedule for air, noise and water quality is presented in Table 9.8. In addition to<br />

the operational monitoring requirements presented in this table and described below, it will be necessary<br />

for the port operator to continue monitoring working practices, plant efficiency and site cleanliness, to<br />

ensure that mitigation measures are in place and are effective.<br />

Air Quality Monitoring<br />

In order to assess the long term air quality impacts resulting from the operations, it is necessary to<br />

undertake air quality monitoring during the early years of operation. To effectively monitor these impacts<br />

it is necessary to supplement existing air quality data with additional air quality monitoring (to include<br />

wind speed and direction, NO 2 , SO 2 , TSP and RSP as a minimum).<br />

Noise Monitoring<br />

Operational noise monitoring should be undertaken by the operators to ensure compliance with the relevant<br />

NCO requirements. It is proposed that extensive noise monitoring be carried out during the early years<br />

of operation. Monitoring should also be carried out in response to complaints where appropriate.<br />

Water Quality<br />

It is envisaged that other than EPD's regular monitoring programme, minimal water quality monitoring<br />

will be required during the operation of the development. However, in the event of a major spillage or<br />

pollution incident, it is proposed that a pre-detennined monitoring programme (devised by the operator)<br />

be implemented with the necessary adjustments to suit the requirements of individual cases*<br />

Action Plans<br />

Action Plans should be devised to facilitate the appropriate and immediate response by relevant personnel,<br />

in the event that the Target, Action and Trigger Levels are either attained or exceeded. The appropriate<br />

action is determined by the frequency of exceedence of the compliance monitoring levels.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

The requirement for action plans should be contained in the contract and lease conditions and suitable<br />

plans should subsequently be submitted by the developer/operator to EPD. Examples of appropriate Action<br />

Plans for the development are outlined in Table 9.9 to 9.1 L<br />

9.8.5 Environmental Auditing<br />

General<br />

The purpose of environmental auditing is to review the effectiveness of the overall environmental<br />

protection programme (both construction and operation) in terms of monitoring, mitigation and corrective<br />

action. The audit process should not be divorced from general management activities, and should promote<br />

a pro-active approach to environmental protection.<br />

Construction Phase Auditing<br />

Construction phase auditing should be carried out in conjunction with the construction monitoring<br />

programme.<br />

The audits should be conducted monthly during the development. It is also considered prudent to conduct<br />

some audits to coincide with major construction activities.<br />

Records of environmental monitoring should be maintained by the developer, and the environmental audit<br />

should seek to check:<br />

* records of environmental monitoring procedures;<br />

+ records of environmental monitoring results;<br />

» records of exceedence of any regulatory requirements;<br />

» details of control and mitigation action taken in response to unacceptable environmental impacts;<br />

* records of any complaints from residents/SRs in the Study Area.<br />

Assessment of monitoring records will ensure that any unanticipated impacts are being addressed and that<br />

any improvements required for future monitoring programmes are identified.<br />

A monthly Monitoring and Audit Report should be compiled and submitted to the developer and EPD,<br />

These monthly reports should be supported by six monthly and annual summaries.<br />

Operational/Post-Project Auditing<br />

A post-project audit should be carried out after completion of the development.<br />

The post-project audit should be undertaken after a sufficient time period from the development becoming<br />

operational (e.g. 12 months), such that any findings are representative of the development's activities.<br />

Post project auditing should verify the findings of the EIA and provide a mechanism for:<br />

> reviewing the effectiveness of, and requirement for on-going monitoring programmes;<br />

> reviewing environmental management practices in terms of achieving environmental objectives;<br />

> reviewing the effectiveness of environmental mitigation; and<br />

* recommending improvements in environmental controls and operations in the event that<br />

environmental objectives are not achieved and environmental impacts are unacceptable.<br />

A post- project audit report and executive summary should be submitted to EPD and the operator(s) within<br />

5 weeks of completing the audit.<br />

APR Consultants p age 9-24


TABLE 9.5 I<br />

PARAMETER<br />

Particulutes<br />

AIR QUALITY MONITORING SCHEDULE (CONSTRUCTION)<br />

OBJECTIVE TRIGGER LEVEL ACTION LEVEL<br />

'Baseline N/A N/A<br />

assessment<br />

TARGET LEVEL<br />

N/A<br />

SRs<br />

LOCATION<br />

FREQUENCY/TIMING<br />

One year prior to<br />

commencing construction<br />

activities. **24hr samples<br />

every 6 days.<br />

|l<br />

f I<br />

^ s<br />

"**<br />

t<br />

1*<br />

Partieulates<br />

***Wind speed<br />

Compliance Ihr TSP, 24hr TSP Average of Trigger<br />

monitoring ^ """baseline 4-30% and Target Levels<br />

Assessment N/A N/A<br />

parameter/<br />

compliance<br />

monitoring<br />

SOOjig/m*<br />

Monitoring stations at Site<br />

Ihr average Boundary in line with nearest<br />

260/j g/in* SKb, locations to be reviewed<br />

24hr average monthly to take account of dust<br />

generating activities<br />

N/A<br />

Air Quality Monitoring Station<br />

and where necessary to account<br />

for wind direction with respect<br />

to SRs<br />

One 24hr sample once every<br />

6 days, hourly samples 3<br />

limes every 6 days or more<br />

frequently depending on site<br />

and wind conditions<br />

Continuous<br />

^£3<br />

<<br />

J-<br />

I<br />

g.<br />

^<br />

£*l<br />

1<br />

***Wind direction<br />

Note : *<br />

»+<br />

SRs<br />

N/A<br />

Assessment N/A N/A<br />

parameter/<br />

compliance<br />

monitoring<br />

N/A<br />

Air Quality Monitoring Station<br />

and where necessary to account<br />

for wind dttccUon with respect<br />

to SRs<br />

Continuous<br />

In the event that a permanent monitoring station is established in the Study Area, this will form part of the baseline assessment. As a minimum the baseline should comprise<br />

data taken from 12 months monitoring in the Study Area,<br />

US EPA Ambient Air Quality Surveillance Regulations<br />

No values recommended, potential impacts are dependant on the nature of the construction activity. High wind speeds during dusty activities and/or wind direction towards<br />

an SR should act as u trigger<br />

Sensitive Receivers<br />

Not Applicable<br />

$<br />

g<br />

**<br />

o<br />

1<br />


TABLE 9.6 t<br />

NOISE MONITORING SCHEDULE (CONSTRUCTION)<br />

PARAMETER OBJECTIVE "TRIGGER 'ACTION<br />

LEVEL LEVEL<br />

TARGET<br />

LEVEL<br />

LOCATION<br />

FREQUENCY/TIMING<br />

*f<br />

L l(|l Baseline Assessment N/A<br />

N/A<br />

N/A<br />

NSRs<br />

One 24hr period during a normal working day<br />

LI«» L^j LyQ,<br />

^Ae<br />

Check Baseline<br />

N/A<br />

N/A<br />

N/A<br />

NSRs<br />

Every 3 months or as near as possible. When<br />

construction activities are not taking place<br />

££'<br />

I<br />

Spot Cheek<br />

65dB(A)<br />

70dB(A)<br />

75dB(A)<br />

NSRs<br />

Minimum of once per week for each NSR during<br />

construction activities<br />

tJO naid<br />

Compliance monitoring<br />

(non-restncied daytime<br />

hours)<br />

65dB(A)<br />

70dB(A)<br />

75dB(A)<br />

NSRs<br />

Minimum of 3 times per week between 0700 and<br />

1900hrs during general construction work;<br />

as appropriate during noisy activities<br />

(5 MM*<br />

Compliance monitoring CNP (ANL) CNP (ANL)<br />

(restricted hours)<br />

CNP (ANL)<br />

NSRs<br />

Minimum of twice per 24-hour period (continuous),<br />

(evening and nighUtnie)<br />

Response to complaints 65dB(A) 70dB(A)<br />

(non-restricted daytime<br />

hours)<br />

75dB(A) Complainant As appropriate<br />

o<br />

4s „„„><br />

Response to complaints CNP (ANL) CNP (ANL)<br />

(restricted hours)<br />

CNP (ANL) Complainant As appropriate<br />

^§<br />

Note ; NSRs<br />

N/A<br />

Noise Sensitive Receivers<br />

Not Applicable<br />

In light of creeping ambient levels resulting from the transition of a rural to an urban environment, it may be necessary to introduce Trigger and Action Levels<br />

which are defined according to the frequency of complaints such that the Trigger Level = 1 complaint (either directly to the developer or via EPD), and the<br />

Action Level = 2 independent complaints (either directly to tiie developer or via EPD). An independent complaint is defined such that only one complaint is<br />

allowed trom a single address<br />

Is*


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

Z<br />

O<br />

C<br />

CJ<br />

at<br />

55<br />

1<br />

a^><br />

FVI<br />

Ml<br />

3<br />

C/5<br />

'CUING<br />

Z<br />

55<br />

-><br />

>t<br />

, .1 ••*<br />

«$<br />

o»<br />

* il<br />

i<br />

•*<br />

l><br />

ax<br />

a<br />

*•*<br />

Q<br />

H<br />

i i<br />

1a<br />

1o<br />

M-V<br />

H*4<br />

*" -<br />

U t)<br />

a) VI 2 5<br />

J3 3<br />

o *o "3<br />

2<<br />

'is is<br />

91 « J2 Q O -3 g 0 0 —<br />

- "J3 O U 3 '- O S><br />

.2 .2 -5 3-3 -<br />

S T3 5 T3<br />

|<br />

0 T3 * -J2 -2<br />

l ! J 3 3 ^ ^ 3 g<br />

ja 3 ^ «3 2 -3 «» j» c "3 " «•<br />

OJO ^>— «D afl »-• > ^^ O<br />

*- SP-S*<br />

-g a -5 5<br />

0 ^3 0 T3 QSu^^-g Qau^^l<br />

*c .2 "1 J cn .2 oi s .3 q cn .2 c^4 s 3<br />

o -° o - 0<br />

ff<br />

So s: a<br />

,3.^5- «^.5s^<br />

Ml !*• «*><br />

«4<br />

^1<br />

^a < j<br />

&4 "**<br />

Z<br />

J<br />

U<br />

w<br />

^<br />

z<br />

o<br />

a «*f* **c<br />

1<br />

s<br />

»J<br />

AS<br />

r£<br />

X<br />

X<br />

&a ><br />

j<br />

£2}<br />

MM<br />

5 ««4<br />

/•^<br />

W<br />

2C<br />

ii<br />

d<br />

2 •< i^X<br />

^f2<br />

I«4 M<br />

,2 a<br />

s a<br />

J « -2 -<br />

o o "o "i><br />

S I 2 |<br />

s8.<br />

gȤ.<br />

ts > ^ > •a J -a 3<br />

C ^ C TC<br />

g M 3 3D 1 i 1 If<br />

ao .2 ao -S<br />

.s § .s g<br />

o S ^ S<br />

C '3 C »«3<br />

5 X li X<br />

e 2 s s<br />

53 C. P d,<br />

Q 3» «*> Q «t »»<br />

§ | § |<br />

o * o *•<br />

A tJ *% "9<br />

2 o 3 o<br />

u *C u 'u<br />

I 8 --! 8 0U as CU ca-<br />

1 §<br />

01 OS<br />

O O<br />

< ^S<br />

*<br />

Z<br />

i s<br />

z z<br />

< <<br />

z z<br />

c c<br />

g s H S<br />

13 35 •"» 33<br />

i> U 2<br />

«" ^ « ^<br />

^-H .2 >».«<br />

S-3 § 13 g<br />

P cn S<br />

Q cn S<br />

^<br />

C r<br />

^> •"•<br />

"C "C<br />

•3 1 1 2 § •§ 1 1 s s<br />

Cl »a — ' * i i \ Ol aS — » i i i<br />

g<br />

§ gO'<br />

* £<br />

u. u<br />

•U y*<br />

ad — 2<br />

3 ^<br />

*J !rt<br />

-a J3<br />

S S s w r i s3<br />

i<br />

•y»<br />

3<br />

S— .<br />

^<br />

> s "i<br />

S | i<br />

w» X 2<br />

w<br />

OS X<br />

CA X<br />

:l 1 If<br />

> o -r g<br />

•*3 3 .is<br />

|l *!<br />

1 8 -si<br />

11 *<br />

•si 1 £<br />

2 ^ Z *<br />

0 00 0 30<br />

§ * s *»<br />

.2 cx<br />

* £<br />

U V*<br />

O M<br />

an —<br />

*-> -J*<br />

5ii ^2<br />

.3 § . g<br />

'""• S *-* o<br />

H j H j<br />

'*- _•<br />

f ~* «j<br />

O 'J<br />

O U<br />

a 2 * £<br />

£ S2<br />

u, c* u r*<br />

5J 3<br />

< 5<br />

2 < 3<br />

aO 54}<br />

^ wi C yj<br />

s "o<br />

'S U<br />

S > G ><br />

2 -H S 3<br />

i 3 * 3<br />

li ii<br />

•^ afl * 50<br />

g "y ^ IS<br />

O =J O sa<br />

<br />

•S S<br />

-II<br />

o — | H "<br />

£ §* sa I S* «<br />

•" O «<br />

•** 3 M<br />

§ ° "a § ' J "g<br />

a "3 i 0-33<br />

— 2 'S ^ .2 's<br />

«** '—• »«J<br />

3 5 2<br />

•" *W ~\<br />

o *j 2<br />

^^ <br />

"£s<br />

J<br />

*2<br />

0<br />

1<br />

§2<br />

"f<br />

"•3<br />

37S<br />

•<br />

.•i<br />

•3 g J<br />

« ^ ^><br />

"^3 3 S<br />

-8 ^ 7 .2 ~ .—<br />

i. 8 s<br />

3 § §<br />

aj •"• J3<br />

.2 -H<br />

| 1 1<br />

J<br />

'***'<br />

"ah ^<br />

>M g<br />

"ajj Tf CM<br />

C u u<br />

> 01 va<br />

X<br />

•Sail<br />

-> 3 J J<br />

O ^ 75 Tt<br />

s -3 i i<br />

'•3 ^ ^3 S<br />

,, !! § a, H o H<br />

o<br />

u - « r5<br />

-3 S . -<br />

^ •— Q O<br />

a ° aa<br />

a > ><br />

•^ 3 > ><br />

tS "^ > *<br />

^ 2 J-2<br />

S 5 -3 j<br />

S3 «• ^^<br />

x g .22 .2<br />

^ lo o<br />

^ 1 Q a<br />

G ""* T3 "3<br />

i*l|<br />

o o i 2<br />

^ cn so ^0<br />

«i "«^ «i 2 ^<br />

-O _4 -s —<br />

Q — . — M<br />

^ x§ 1 I<br />

1 '1 '•§ 5 5<br />

-H 3 S<br />

•^ 0» *<br />

— 1 1 S^f<br />

II<br />

ilieS<br />

^ o<br />

< a><br />

z> *<br />

APS Consultants Page 9-27<br />

**<br />

3i<br />

Z<br />

^


TABLE 9.8 i<br />

ENVIRONMENTAL MONITORING SCHEDULE (OPERATION)<br />

PARAMETER OBJECTIVE STANDARD LOCATION<br />

* AIR QUALITY<br />

NO 2 Establish baseline data and trends AQOs Near to Site<br />

SO 2<br />

ISP<br />

RSP<br />

FREQUENCY/TIMING<br />

Continuously for gaseous Every 6 days<br />

for particulates<br />

Requirement for on going monitoring to be<br />

assessed in the audit procc;ss<br />

-<br />

NOISE<br />

WATER QUALITY<br />

Compliance with NCO Appropriate AN Li Worst NSRi **Over a 24hr period approximately every<br />

month Requirement for on going<br />

monitoring to be assessed in the audit<br />

process<br />

1<br />

dn»:»olvcd oxygen<br />

Monitor the eHeUb of maintenance<br />

dredging, compliance with WQOb<br />

WQOs<br />

Designated monitoring stations<br />

near to the area to be dredged<br />

Duiing maintenance dredging<br />

Note : * NO 2 » SO 2 , TSP and RSP should represent the minimum parameters to be sampled<br />

frequency of momlormg should d^erease it NCO standards are consistently niu, or increasing in frequency if the NCO maxima is exceeded<br />

N/A Not appropriate<br />

I he water quality monitoring requirements during maintenance dredging will be similar to those m Table 9 7<br />

f<br />

o


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

1<br />

.s%i<br />

i<br />

i<br />

J<br />

*<br />

5. .1<br />

1<br />

3<br />

1<br />

3<br />

«<br />

o<br />

•>. O '£*<br />

1 C ^<br />

lg S .1<br />

8 1 '= 1<br />

1 ^ § ^<br />

* Q- a o<br />

H ! 1<br />

Jo 0 a<br />

.H^ 5 H<br />

» -a 1 3<br />

afi 3 c3 5<br />

<br />

" S<br />

*<br />

s.<br />

"13!, M •€ S "3<br />

••a 3 i •« 3 s-ll^i<br />

M-- 11 ^ M 1<br />

ill II- fri i= 1<br />

S.isll 'JgrSll<br />

- o<br />

2 g 1<br />

1 - ^ 1 1<br />

1 12 1 1<br />

> 3 CL O<br />

S a f 1 3* a.<br />

^1 5 j] 1 i,<br />

-— y •— • Q > 3<br />

5<br />

2,<br />

1<br />

1 2<br />

i .;<br />

d O s<br />

« i<br />

r<br />

«<br />

* jo<br />

n<br />

i<br />

-;<br />

53 § § S^ ^<br />

5 S 3 2^ S<br />

a I - - * - i-<br />

5 S | " -2 § a«<br />

a. i- .- ao * 2 aa<br />

y s ^ £ 2" s^<br />

^ 3 - 3 « C .S * -s a<br />

5 = * " i § 5 2 2 £<br />

•* -i 1 § *5 « § r=<br />

i S ! 1 1 11 ,<br />

1 1 ! I S! !! !<br />

at<br />

JU<br />

s s<br />

«\ *J><br />

-= = ><br />

f<br />

J i<br />

S<br />

I<br />

•a<br />

S<br />

2 3<br />

II<br />

O\<br />

3d<br />

5<br />

^<br />

fi«<br />

M>*H<br />

S<br />

^<br />

g<br />

15<br />

11<br />

« ><br />

1<br />

**M<br />

O<br />

1 i £. »<br />

ca ^<br />

APff Consultants Page 9-29<br />

1<br />

£ o<br />

f*<br />

n<br />

O3 .T<br />

i*4 «


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

2<br />

S<br />

5<br />

z<br />

0 "**•<br />

33<br />

^^ •2<br />

2<br />

2<br />

SN<br />

55<br />

jpjcr<br />

ACTION<br />

s*<br />

i<br />

£3<br />

1.<br />

1 t<br />

Monitor big Pen&ntwl<br />

HSmSite Open<br />

cu<br />

a<br />

'j0,<br />

"a<br />

'j<br />

3<br />

O<br />

«££<br />

1<br />

G jt *\<br />

f J<br />

= f -<br />

III<br />

a -3:-<br />

us eiO<br />

1<br />

i •§<br />

| S<br />

*i s<br />

"3 J<br />

a £<br />

1 "8<br />

*n o<br />

r 4 P*<br />

1 &<br />

33<br />

1 | | s<br />

»H<br />

o<br />

1 o<br />

o 2<br />

33 U<br />

CM O V*<br />

i |i<br />

•1 o 1<br />

1 2^<br />

Check working<br />

identify causes,<br />

remedial action<br />

I<br />

S S<br />

«3 <br />

§ J<br />

o .<br />

2 «2<br />

c£ o<br />

CO -«=<br />

* 1<br />

1 §<br />

ll<br />

g ||<br />

.333<br />

ill<br />

ill<br />

.2^<br />

J <<br />

"•5 — s<br />

> 3<br />

55 o<br />

3fi JS<br />

ll n<br />

1 «<br />

21 o 4 S ^<br />

|3M a i -9 ><br />

s<br />

M<br />

cS<br />

"3<br />

1<br />

u<br />

O<br />

1<br />

S<br />

ts<br />

||<br />

"Submit report to EPD within two weeks of receipt of<br />

complaint should the measured noise level exceed the Ta<br />

proposals to reduce noise should be recommended in the<br />

_<br />

J2<br />

!<br />

g<br />

VI<br />

T3 1<br />

si<br />

a 2<br />

fl<br />

"3* QA<br />

"T3<br />

j» *<br />

if<br />

a §.<br />

> 3<br />

S 1<br />

aa<br />

1<br />

><br />


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

!X<br />

«<br />

"c —<br />

| .2<br />

1 «<br />

Sf «l .3 **<br />

3" a<br />

1 1 =<br />

§ 3 2<br />

2 li<br />

t> 2 —<br />

05 0, £<br />

inform developer RSE, EPD<br />

U9<br />

^ 2<br />

C 3<br />

3 3 -1 H §<br />

!i«s s = B<br />

f .S x.S 2f» §<br />

M S "7 J2 .5 -Si<br />

Confirm monitoring result and<br />

measurement for a further 15 i<br />

min) and 30 minutes respectivt<br />

exceedeiice of Target level wit<br />

outside restricted hours follow!<br />

implementation of noise reduct<br />

"3 i><br />

.H<br />

*u*<br />

1 u*<br />

f 3<br />

i §<br />

ll<br />

i-<br />

c; H 2<br />

^ ^3<br />

_ O i«<br />

1 il<br />

u -u -5<br />

a -31<br />

^<br />

s<br />

Increase frequency of monitori<br />

&o<br />

•g 2<br />

4> *3<br />

.2 a<br />

11 i<br />

il <<br />

S 8L 3<br />

H 1<br />

11 1<br />

tl §<br />

'i-l s<br />

5 1 S .5<br />

u 2 I 5<br />

.1 | 50<br />

1.1 •§<br />

- •= 2.<br />

S =<br />

g'5<br />

§ 1 1 i<br />

a t 8 .S<br />

It<br />

11 §.!<br />

*y >«<br />

|<br />

2 x<br />

«<br />

75<br />

1<br />

ca r:<br />

1 |<br />

u,<br />

3 .2 « o «<br />

Vj CU «. > v»<br />

§ S .2 " 5 on<br />

u<br />

s*<br />

**"' t: .2 c<br />

il 1 Jit<br />

i 2<br />

Q*<br />

J2 S<br />

Ji ! Ill<br />

Ji<br />

s<br />

"J3<br />

OI<br />

i<br />

II<br />

o<br />

.2 "o<<br />

"S,<br />

s<br />

il<br />

3 o<br />

0 J»<br />

1 §<br />

3 |<br />

*ua u<br />

|1<br />

51<br />

*-l<br />

II S *<br />

1 I<br />

APH Consultants Page 9-31<br />

tM ^<br />

*<br />

* *<br />

JJ<br />

^


TABLE 9. Hi<br />

WATEU QUALITY ACTION FLAN - SUSPENDED SOLIDS AND DISSOLVED OXYGEN<br />

EVENT<br />

Bieach of Trigger<br />

Value<br />

FREQUENCY<br />

One sample<br />

MonUoilng<br />

inform developer £. RSE<br />

fano/i/wl<br />

ACTION<br />

kSK/SUe Operator<br />

Developer<br />

ffs * §•<br />

Two consecutive<br />

samples<br />

Inform EPD, developer and RSE; resample to<br />

confirm result<br />

Check working methods/practices to identify any<br />

immediate causes, take apptopriate remedial action if<br />

necessary<br />

Bieach of Action<br />

level<br />

Due sample<br />

samples<br />

Inform EPD, developer and RSE; tesample to<br />

confum result<br />

Inform EPD, developer and RSE; resample to<br />

confirm rebutt<br />

Increase frequency of monitoring<br />

Check working methods/practices to identify any<br />

immediate causes; take appiopriate remedial action if<br />

necessary<br />

Undertake detailed check of working methods and<br />

practices<br />

Review plant, equipment<br />

and working piocedures<br />

I<br />

Biea Ji of Target Level One sample<br />

Propose remedial action<br />

Continue monitoring after completion of<br />

remedial auion to contain action is effective<br />

Record event in monitoring report for<br />

submission to developer and I<br />

Inform EPD, developer and RSE;<br />

Confirm result £ increase monitoring frequency<br />

Propose remedial action<br />

Undertake monitoring at nearest water quality<br />

SR<br />

Continue monitoring after completion of<br />

remedial action to contain action is ettecttve<br />

Carry out appropriate remedial action as<br />

recommended by environmental monitoring team<br />

Ensuie coneuive action has been undertaken and is<br />

eifective<br />

Amend method statement, if appropriate<br />

Under take immediate check of activities and employ<br />

any appropriate mitigation.<br />

In extteme casea cease activities<br />

Ensure corrective action has been undertaken as<br />

proposed by (monitoring team) and is effective<br />

Amend method statement, it appropriate<br />

Ensure implementation of remedial<br />

action<br />

Inform EPD of remedial action<br />

Review plant, equipment and working<br />

procedures<br />

Ensure immediate implementation of<br />

remedial action<br />

inform EPD of remedial action<br />

§<br />

o<br />

Complete Monitoring Report and submit to<br />

developer and EPD


Engineering Feasibility Study of Development o/Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

SECTION 10<br />

IMPLEMENTATION<br />

10.1 INTRODUCTION<br />

This Section discusses the implementation of the development covering the activities from the completion<br />

of this Report to the point at which the various areas are released to operators for the further development<br />

of their sites. As such, it addresses the following topics:<br />

> preliminaries which have to be allowed for in order to carry the findings of this Report through<br />

planning and design to construction;<br />

» a review of the likely arrangements required for implementation;<br />

> implementation scheduling including the key demand horizons, constraints upon the development<br />

and phasing potential;<br />

> capital expenditure and revenue streams for the development.<br />

10.2 PRELIMINARIES<br />

Scheduling for the implementation of the works must allow for Government approval and sanctioning<br />

procedures. The steps that the these procedures entail will vary as a function of the way in which the<br />

various developments will be realised, thus, for example, whether the works are actually executed under<br />

direct Government control or entrusted to a private sector developer.<br />

The preliminaries under Government funding cover the following activities:<br />

+ DPC, PPC and LDPC endorsement;<br />

> Public Works Sub-Committee and Finance Committee sanctions for the undertaking of the detailed<br />

design and construction;<br />

> consultant selection;<br />

» detailed planning and final design;<br />

and under private sector funding:<br />

* DPC, PPC and LDPC endorsement;<br />

> Public works Sub-Committee and Finance Committee sanctions for undertaking technical<br />

assessments;<br />

+ consultant selection;<br />

* technical assessments;<br />

»• preparation of lease conditions;<br />

+ ExCO endorsement of privatisation proposals;<br />

* processing and award of development rights and land sales.<br />

Gazetting under the various Ordinances will be required for the development. In addition, the<br />

development involves the adjustment of the existing traffic separation scheme within the Tathong Channel<br />

and early application to the IMO for the proposed amendment will be required.<br />

Consultants<br />

Fa S e 10 ' 1


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

These procedures, apart from the time needed to undertake the detailed design and site investigations, can<br />

be protracted and a high degree of priority will be required to achieve a start to construction in accordance<br />

with the requirements discussed in the following sections.<br />

10.3 IMPLEMENTATION SCHEDULE<br />

10.3.1 Facility Requirements<br />

The discussion of the identified demand for facilities in Section 3 has indicated that there is considerable<br />

pressure for the provision of a site to accommodate PHI activities. These include naphtha import and gas<br />

production, LPG import and bottling and a bulk chemical storage facility. Associated with the latter<br />

facility in particular, is a requirement to provide PHI related facilities. The demand for DWI has been<br />

shown to be less forthcoming.<br />

The three main PHI sites have therefore been adopted as the core demand requiring early provision with<br />

the remaining facilities being made available on a rolling programme basis.<br />

In view of the PHI nature of the core demand it has been located in the south of Area 137 to maximise<br />

the separation distance from the TKOIE and SENT Landfill sites. As such the early provision of these<br />

sites will require the creation of land access via a coastal causeway. In addition, and irrespective of this<br />

approach, the proposed marine access to the SENT Landfill site would be affected by the commencement<br />

of the development and reprovisioning of these facilities would be required.<br />

The Master Layout Plan for the proposed development is presented in Figure 10.1.<br />

10.3.2 Implementation Constraints<br />

The main implementation constraints are the need for the reprovisioning of the SENT Landfill marine<br />

access and those associated with the provision of the main land access along Road D6.<br />

The reprovisioning of the marine access represents a significant financial burden for the early stages of<br />

development. Alternative means by which marine access can be maintained until a later stage have been<br />

discussed with the appropriate Government Departments, including the provision of a temporary road<br />

access to Area 137 through the SENT Landfill site and initial construction of the marine access outside<br />

the development area. It was concluded that a separate study should be undertaken to examine alternative<br />

sites for the location or reprovisioning of the marine access to the SENT Landfill site, taking into account<br />

transportation and development cost as well as the environmental implications. However, for the purposes<br />

of this Study it is assumed that the marine access will be retained at its proposed location and that<br />

reprovisioning will be within Area 137.<br />

The current programme for the provision of road D6 involves the following steps:<br />

» reclamation of the road reserve by SENT Landfill contractor from mid 1995;<br />

> one year notice to SENT Landfill contractor for release of the road reserve;<br />

> release of the reserve to TDD by mid 1996 for the construction of the road.<br />

The above sequence of events has the potential to impose a constraint upon the early development of the<br />

main core sites.<br />

APH Consultants p age 10-2


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

10,3.3 Phasing Potential<br />

The implementation of the development is characterised by the need for the early provision for the core<br />

demand followed by a slower release of land to meet the remaining PHI and DWI requirements. It is<br />

considered that this need lends itself to the adoption of appropriate construction techniques rather than the<br />

definition of discrete phases.<br />

For planning purposes the initial construction element, or development, is assumed to relate to the<br />

provision of land for the identified core demand at the earliest opportunity. As such the Initial<br />

Development provides for:<br />

> Site 1, Naphtha import and gas production;<br />

> Site 2, LPG import and bottling facilities;<br />

> Site 3, Bulk Chemical Storage Facility;<br />

* Sites 5 and 6, PHI related activities.<br />

Access to the site would be obtained through the reclamation of a coastal margin to provide a platform<br />

for a single lane road and services corridor. The reclamation of the site has been based upon the use of<br />

dredged marine sand in order to achieve the earliest possible hand over of the plots.<br />

Through the adoption of an effectively continuous development programme, it is considered that no<br />

provision needs to be made for armouring the temporary face of the reclamation following the completion<br />

of the initial reclamation works, although a return to the seawall revetment will be required in the north<br />

to limit local scour.<br />

The Initial Development, as outlined, will provide a total site operating area of some 36 ha with a further<br />

4.3 ha associated with the provision of access as shown on Figure 10.2.<br />

It is proposed that the creation of the remaining land area would be centred around the use of public<br />

dumping or overburden material from the Anderson Road quarry. The timing of the commencement of<br />

the dumping is variable, with an early start as soon as the initial filling is completed in any particular area.<br />

It is, however, recommended that the start should not be delayed beyond the completion of the Initial<br />

Development. This would ensure that the existence of an embayment in the north of the site is limited<br />

to that of a construction sequence within an overall implementation programme rather than a permanent<br />

or semi-permanent feature.<br />

All seabed and preparatory works would be completed prior to the commencement of the dumping<br />

operations. A barge dumping operation would be required to raise the level of the seabed in a uniform<br />

manner which would be followed by end tipping as a shore based operation. It is proposed that the<br />

sequence of plot creation would work progressively northwards.<br />

Temporary provision will be required for the extension of the proposed SENT Landfill drainage during<br />

the dumping operations. It is considered that this can best be achieved by permitting open ditch flow as<br />

the filling progresses with the permanent works constructed upon completion of the filling. Similarly, the<br />

provision of roads and services would commence upon the completion of filling or sequentially if the<br />

demand dictates.<br />

APR Cowutomte<br />

p age


Figure 10.2<br />

TKOIE<br />

39 , V'5^r^" ltltt N<br />

1<br />

27 M 18 v 12 \|<br />

tl 14 i - p " * 9 "<br />

^, •r^-""i\ 8 " I<br />

CUURWA7ER 3AY<br />

COUNTRY PARK<br />

TATHONG CHANNEL<br />

V<br />

£><br />

TA1 MUI WAN<br />

KEY:<br />

Extent of Initial Development<br />

AREA 137 INITIAL DEVELOPMENT<br />

APH CONSULTANTS


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

10.3.4 Implementation Arrangements<br />

Government has not generally shown favour towards private land reclamations as, theoretically, this would<br />

give the developer control over the land he has created. This would be contrary to the historic practice<br />

in Hong Kong where land, inclusive of reclaimed land, is vested under the authority of the Crown.<br />

In some instances, it can be suggested that a developer could form land as entrusted works for subsequent<br />

handover to Government. However, the core PHI demand amounts to some 30 ha with each individual<br />

facility allocated approximately 10 ha, being some 10% of the total site area. As such it is questionable<br />

as to whether one of the interested operators would take on the role of developer involving entrustment<br />

of their non-allocated areas unless there is a substantial increase in the land requirement for a single<br />

operator. It is possible that, subject to review, one of the identified operators may well indeed amend<br />

their indicated land requirements and this could alter the perception of the viability of operator<br />

development involving entrustment.<br />

It is considered that time frame and practicability effectively rules out the formation of an equivalent to<br />

the Hong Kong Industrial Estates Corporation or the amalgamation of a number of operators to take on<br />

the role of developer.<br />

Reclamation by Government would appear to be the most attractive and least complicated way forward.<br />

Land disposal is conventionally the responsibility of Buildings and Lands Department (BLD). BLD would<br />

determine the level of premium appropriate to individual lots and would be responsible for the preparation<br />

of lease conditions restricting land use and operation. BLD also have the option of disposing of land by<br />

competitive tender or auction.<br />

Notwithstanding, it is recommended that Government invite expressions of interest to be registered for<br />

the whole or partial development of the site. It is further recommended that this call for interest should<br />

be run in parallel with the progression of the development on a Government funded basis.<br />

10.3.5 Implementation Programme<br />

The proposed implementation programme is shown on Figure 10.3 and is generated around the release<br />

of road D6 reserve to TDD by mid 1996 requiring notice to be issued to the SENT Landfill contractor<br />

immediately after receipt of the reserve from TKOIE and allows the release of the main core PHI sites<br />

by mid 1997.<br />

The key elements this programme are:<br />

Preliminaries<br />

Appointment of Consultants is required in third quarter of 1993 to enable the<br />

detailed design to commence upon approval of design/investigation expenditure.<br />

Within the design/investigations, initial priority will have to be given to<br />

reprovisioning of the SENT Landfill marine access.<br />

SENT Marine Access<br />

The key target within this element of the programme is the completion of the<br />

reprovisioning prior to the release of road D6 reserve under the Initial<br />

Development programme when marine access to the proposed facilities would be<br />

lost. A float of three months has been built into the programme for the<br />

completion of the SENT Landfill marine access reprovisioning prior to the<br />

commencement of the site roads and paving under the Initial Development<br />

programme.<br />

APH Consultants p ag€ 10-4


Figure 10.3<br />

ii<br />

'.ii<br />

i<br />

II<br />

! Ill<br />

S5li<br />

ii! hi<br />

I | i<br />

'II<br />

II<br />

IMPLEMENTATION PROGRAMME<br />

333 APH CONSULTANTS


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Initial Development<br />

Site Completion<br />

Tender Documents would be issued early 1995 with an award of Contract some<br />

4 months later. Release of the main core sites to operators is programmed for<br />

early to mid 1997.<br />

The award of the Site Completion works is programmed to coincide with the end<br />

of the Initial Development. As discussed above, the commencement of the<br />

associated public dumping could commence earlier, if disposal or site demand<br />

justified. The programme has been developed for an assumed rate of supply of<br />

public dumping material at 1 MmVyr. Clearly, works could be completed,<br />

either earlier or later, depending upon the actual rate of supply achieved.<br />

10*3.6 Employment Build Up<br />

No specific consolidation period has been indicated within this phase of work due<br />

to the slower rate of filling as well as the fact that this site is centred on the old<br />

dump ground and the preliminary boreholes have indicated that partial<br />

consolidation has already occurred.<br />

The risk assessment for the site has recommended the adoption of a worker density within the development<br />

of 20 per ha and 30 per ha for PHI and DWI facilities respectively. These densities have been used to<br />

generate the maximum theoretical employment levels. The employment build up, assuming that the labour<br />

force is brought onto the sites 2 years after site formation, is detailed in Table 10.1.<br />

TABLE 10.1 :<br />

EMPLOYMENT BUILD UP<br />

Year<br />

Employment<br />

1988<br />

1999 773<br />

2000<br />

2001 247<br />

2002 334<br />

2003 334<br />

TOTAL 1688<br />

10.4 CAPITAL EXPENDITURE AND REVENUE STREAMS<br />

10.4.1 Capital Expenditure<br />

Cost estimates have been prepared for the various work packages covering the main construction elements.<br />

These include engineering, investigations, preliminaries, dredging, site formation, revetted seawalls,<br />

common user berth facilities, roads, services, drainage, GIC facilities and contingencies. The costs of the<br />

specific user berthing facilities have been excluded on the basis that they are user defined and would be<br />

undertaken by the operators as part of the development of the sites. The cost estimates have been<br />

prepared at March 1992 prices and are summarised*in Table 10.2,<br />

APH Consultants p age 20-5


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

TABLE 10.2 :<br />

SUMMARY OF CAPITAL COSTS<br />

(March 1992 prices, HK$ millions)<br />

Item<br />

SENT Landfill<br />

Access<br />

Initial Development<br />

Site Completion<br />

Investigatiort/Prelims/Contingencies<br />

Dredging<br />

Filling and Associated Works for<br />

Reclamation<br />

40<br />

.<br />

48<br />

263<br />

-<br />

4SS<br />

175<br />

12<br />

93<br />

Revetted Edge Structures<br />

-<br />

132<br />

33<br />

Quaywalls<br />

42<br />

-<br />

206<br />

Roads, Services, Drainage<br />

Landscaping<br />

30<br />

.<br />

132<br />

-<br />

120<br />

36<br />

TOTAL<br />

160<br />

1015<br />

675<br />

These costs have been converted into capital expenditure streams for the proposed implementation<br />

programme as shown in Table 10.3.<br />

TABLE 10.3 :<br />

CAPITAL EXPENDITURE STREAMS (HKS millions)<br />

YEAR<br />

1993<br />

1994<br />

1995<br />

1996<br />

1997<br />

1998<br />

1999<br />

2000<br />

TOTAL<br />

INITIAL DEVELOPMENT *<br />

30<br />

72<br />

385<br />

500<br />

188<br />

1173<br />

SITE COMPLETION<br />

103<br />

202<br />

202<br />

168<br />

675<br />

* Includes reprovisioning of SENT Landfill Marine Access<br />

The Present Day Value of the expenditure has been discounted at 4.0% to give PD values of HKS 1,493M<br />

with an annual allowance for maintenance expenditure of HKS 2M between completion and 2011.<br />

10.4.2 Revenues<br />

The Government would expect to receive revenues or premiums from the sale of land or grants of<br />

development rights associated with the development. In addition, the development will give rise to a<br />

marginal increase in the number of vessels visiting the Port of Hong Kong from which Government will<br />

receive Port Facility and Light dues.<br />

The levels of premium that Government may expect to receive could be assessed on the basis of operator<br />

profitability or current market levels. The diversity and undefined scale of the proposed operations,<br />

AfH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

however, effectively rules out the operator profitability approach. As a result a review has been made<br />

of the current premiums for serviced land with appropriate allowance for plot ratio and nature of use.<br />

The premiums are based on March 1992 values and are presented purely for illustrative purposes:<br />

For serviced land<br />

» PHI sites HK$ 30M per ha<br />

> PHI related sites HK$ 50M per ha<br />

> DWI sites HK$ 50M per ha<br />

The results of applying the premiums to the proposed implementation programme with the assumption that<br />

the premium is received within 1 year of the creation of serviced land for PHI's and 1 to 2 years for the<br />

main DWI sites, is given in Table 10.4.<br />

TABLE 10,4 :<br />

REVENUE STREAMS (HKS millions)<br />

Year<br />

Revenue<br />

1996<br />

1997<br />

1998 1134<br />

1999<br />

2000 415<br />

2001 557<br />

2002 557<br />

The equivalent Present Day Value (at a discount rate of 4.0 %) of the revenues is HKS 1,929M.<br />

10.4,3 Viability<br />

On the basis of the estimated serviced land premiums it is evident that the proposed development has a<br />

good rate of return with an IRR of 13.4% or 17.8% excluding the reprovisioning of the SENT Landfill<br />

marine access. The project could withstand further delayed premium payments or a reduction in premium<br />

levels of some 22% and show a positive net present value at a discount rate of 4%. However, this relates<br />

to the full development of the site and it is considered more appropriate to examine the viability of the<br />

Initial Development and also the minimum level of interest required to establish viability.<br />

Any initial development would involve the construction of a coastal road to the site and the reprovisioning<br />

of the SENT Landfill as currently envisaged. The results of this evaluation, assuming no net cost to<br />

Government (discount rate 4%) are as follows:<br />

> an 11 ha operational site would require a premium of HKS 65M per ha.<br />

> a 21 ha operational site would require a premium of HKS 43M per ha.<br />

> the Initial Development as outlined in Section 10.3.3 involving 31 ha of PHI and 5 ha of PHI<br />

related operational area would require an area averaged premium of HKS 36M per ha.<br />

The above premium values could be reduced to HKS 49M, HKS 35M and HKS 31M per ha, if the<br />

provisioning of the SENT Landfill marine access could be avoided through its relocation to a nonconstraining<br />

site.<br />

APH Consultants p ae 1Q-7


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Find Report - Main Report<br />

From the above analysis and assumed premium levels, it would appear that the minimum initial<br />

development would need to be of the order of the proposed 36 ha, if it is to be realised at no net cost to<br />

Government.<br />

10.5 STUDY IMPLICATIONS<br />

The previous Sections of this Report contain a number of related recommendations and action<br />

requirements which should be recognised in the further implementation of the development. These are<br />

listed below, by Section, for ease of reference:<br />

> Implementation of the recommended layout for Area 131 would require the realignment of Road<br />

D9 at its junction with Road P2; modification of the ODP would be required.<br />

Within Area 137 it would be prudent to limit worker densities to 20 per ha and 30 per ha for PHI<br />

and DWI sites respectively and marine operations should be suspended for the day of the festival<br />

at Tai Miu Wan. The development of a particular PHI should be subject to the results of a<br />

farther and operator specific risk assessment.<br />

> The positioning and design of the site specific facilities should be subjected to further visual and<br />

environmental assessments.<br />

* A comprehensive site investigation will be required for the detailed design of the development and<br />

early commencement of the survey would ease the design programme. Further definition is<br />

required for the sources of fill and dredge disposal including contaminated material.<br />

A reassessment of water supplies would be required if HK&CG should implement a more<br />

extensive gas plant than currently envisaged.<br />

Adequate services reserves will need to be provided in the design of Road D6 to accommodate<br />

the development requirements in addition to TKOIE.<br />

> A relocation of the pilotage boarding point will be required to serve the development and IMO<br />

approval of the proposed modification to the Traffic Separation Scheme should be sought.<br />

Pre-entry clearance for quarantine and immigration is recommended for vessels carrying<br />

hazardous materials to Area 137.<br />

fr-<br />

it is recommended that the Western Coast Road should be implemented by 2001 and this should<br />

be accompanied by improvements in the Yau Tong area.<br />

If the Western Coast Road has to be delayed beyond 2001, it is recommended that the target<br />

population figure for 2006 should be maintained together with the industrial developments at<br />

TKOEE and Area 137 whilst constraining the Metroplan forecast for employment to around<br />

15,000.<br />

The contribution of Area 137 to traffic flows within the area of influence is small, with the most<br />

significant contributions to overloading being Junk Bay Road (2.9%) and Lei Yue Mun Road<br />

(3.1%). The internal TKO network will require improvements to the Road D6/Road D9 junction<br />

in 2006 and improvements to the roundabout at Road Pi/Road D4 by 201L<br />

AfH Consultants<br />

Pa & 10 ~ 8


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Both of the proposed Western Coast Road connections have been found to have severe<br />

environmental impacts. Whilst Option B is recommended as the preferred alignment of the two,<br />

further study would be required to establish the optimum solution.<br />

Further survey work is required to establish the extent of contaminated mud removal required in<br />

relation to the Recommended Development Layout.<br />

Air quality impact studies are recommended for major industrial developments when specific<br />

details are known.<br />

Further discussions should be held with the Government Department responsible for the SENT<br />

Landfill to ascertain if the release of the Road D6 reserve can be brought forward and if the<br />

marine access could be relocated to avoid reprovisioning almost immediately after its construction.<br />

Expressions of interest for the partial or total development of the site should be called at the<br />

earliest opportunity.<br />

10.6 STUDY FINDINGS<br />

The Study has demonstrated that the proposed development is both feasible and viable in terms of land<br />

use planning, engineering and marine operations. A risk assessment for the assumed land use has been<br />

presented to the CCPffl for information purposes. Whilst it is acknowledged that further risk analyses<br />

will be required for the detailed proposals of the operators f the acceptability of this more generalised<br />

approach provides a sound basis for the generation of interest for the site.<br />

The evaluation has identified no major environmental concerns as regards the development of Area 137<br />

save the visual intrusion of an industrial development upon an otherwise generally rural area. Mitigating<br />

measures and landscaping have been introduced, which will soften to some extent the intrusion.<br />

The Study has confirmed the need for the provision of the Western Coast Road by 2001 to avoid<br />

constraining the development of Tseung Kwan O as a whole. It is recommended that a high priority is<br />

attached to the confirmation of proposals and routing for the Western Coast Road and that detailed design<br />

should be commenced to ensure the timely provision of this critical element in the external links to Tseung<br />

Kwan 0.<br />

The Study has identified positive demand for early provision for a bulk chemical storage facility and it<br />

is known that the Hong Kong and China Gas Co. are considering the potential of the site within their<br />

current planning exercise. The combination of these two requirements, possibly including an increased<br />

provision for gas production, would approach the minimum viable development referred to in Section<br />

10.4, Equally, the relocation of existing PHI activities, including LPG and fuel oil, to a lower risk area<br />

must be considered within the overall planning context of Hong Kong. The site provides for these<br />

opportunities and it is considered that the development should be progressed as a priority to ensure that<br />

they are realised in the general interest of Hong Kong.<br />

APS Consultants<br />

p ag€


,&&£ ^ • • ' • • / ^fc'SS^>/'^' S^%;.^<br />

Study Reports and<br />

Working Papers


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

final Report - Main Report<br />

APPENDIX A<br />

STUDY REPORTS AND WORKING PAPERS<br />

Study Reports, Working Papers and Discussion Papers which have been completed prior to this Final<br />

Report and upon which it is based are:<br />

Study Reports:<br />

* Inception Report.<br />

» Alternative Concepts Report.<br />

> Preferred Concept Report.<br />

Working Papers:<br />

» Working Paper No. 1 - Wave Modelling Requirements, which sets out the required wave<br />

modelling to be undertaken in the evaluation of the selected concepts.<br />

> Working Paper No. 2 - WAHMO Modelling Requirements, which sets out the mathematical<br />

modelling required for the evaluation of the hydraulic flow, siltation and with particular emphasis<br />

on water quality modelling.<br />

* Working Paper No. 3 - Environmental Background, which discusses the extent of the existing<br />

baseline data for the area and highlights the need for additional baseline surveys as necessary,<br />

> Working Paper No. 4 - Opportunities and Constraints, which presents an inventory of the existing<br />

marine and land uses, the findings of the review of potential land use demand and constraints and<br />

sets out the basis for the land use planning of Area 137.<br />

> Working Paper No. 5 - Transport Modelling Approach, which defines the modelling approach<br />

to be adopted, together with the revised input assumptions including Territory land use and<br />

network data and other model parameters.<br />

> Working Paper No. 6 * Marine Structures, Dredging and Reclamation, which discusses<br />

geotechnical, dredging and reclamation issues and assesses possible edge structures for<br />

incorporation in the outline design.<br />

+ Working Paper No. 7 - Risk Assessment, which studies the risks, both societal and individual,<br />

arising from the possible PHI development in terms of the CCPffl Guidelines.<br />

* Working Paper No. 8 - Strategic Network Forecasts, which assesses the levels of traffic and<br />

impact on the strategic road network for the design horizon years of the Study.<br />

> Working Paper No. 9 - Western Coast Road Connection, which compares the two proposed<br />

connections of the Western Coast Road to East Kowloon for the selection of a preferred route.<br />

APH Consultants<br />

Appendix A-l


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

Discussion Papers:<br />

> Discussion Paper No. la - Site Investigations, which identifies and examines geotechnical data<br />

for Tseung Kwan O Area 137, and makes recommendations regarding further site investigations<br />

that are required for the Study.<br />

APS Consultants — . , , .. _—, ; —__. -—<br />

Appendix A-2


CD 12.<br />

CD


Engineering Feasibility Study of Development o/Tseung Kvan 0 Area 137<br />

Final Report - Main Report<br />

APPENDIX B<br />

WRITTEN STATEMENTS<br />

Bl LAYOUT PLAN 1<br />

B1.1 INTRODUCTION<br />

Layout Plan 1 forms a composite part of the overall planning for Area 137 which has been undertaken<br />

under the Study. Following submission of the Preferred Concepts Report which identified a preferred land<br />

use layout for Area 137, layout plans at scale 1:1000 have been produced to reflect the Study findings.<br />

Area 137 is covered by 3 layout plans which comprehensively define land use for the proposed<br />

development.<br />

BL2<br />

OBJECTIVES OF THE PLAN<br />

Layout Plan 1 predominantly provides for Potentially Hazardous Installations (PHI) and PHI related<br />

industrial land use. The main objective of the plan is to depict land use proposals defined in the Study<br />

and to provide a formal basis for land disposal.<br />

BL3<br />

THE PLANNING AREA<br />

Area 137 is located to the southeast of Tsuen Kwan 0 New Town and is located between Fat Tong Chau<br />

and Tit Tarn Chau. The total planning area amounts to 101.78 hectares which will be composed of<br />

reclaimed land with a mean formation level of 4-5 mPD. Layout Plan 1 is located in the southern portion<br />

of the proposed reclamation. The total land area covered by the subject plan amounts to 29.60 hectares.<br />

The boundaries of the area covered by the plan are defined by the proposed new seawall to the west,<br />

Clearwater Bay Country Park to the east, Tit Tarn Chau to the south and the northern boundary of<br />

proposed lots 2/1 and 3/1 to the north.<br />

BL4<br />

LAND USE PROPOSALS<br />

To avoid confusion all layouts are numbered according to a common format. Site 3/2 refers to Site 3 on<br />

layout plan 2; similarly Site 8/3, refers to Site 8 on layout plan 3. The numbering system is intended to<br />

aid the identification of specific lots on a given layout plan without cumbersome cross referencing,<br />

Bl.4.1 Industry I(B) (13.77 Hectares)<br />

Site 1/2 with a total area of 10.95 hectares has been allocated for industry Class B use. It is intended that<br />

the site will be developed for PHI purposes. The site, subsequent to the findings of the Study, has been<br />

tentatively earmarked as a gas production facility to be operated by the Hong Kong and China Gas<br />

Company (HKCGC).<br />

The site area allocated has been determined with regard to discussions held with the HKCGC. The site<br />

has not, however, been formally allocated to the gas company who are currently undertaking a study of<br />

APR Consultants<br />

a « e


Engineering Feasibility Study of Development o/Tseung Kwan O Area 137<br />

final Report - Main Report<br />

future gas production requirements in Hong Kong. As the precise land area required has not been<br />

formally confirmed, site boundaries have been indicated with a strong broken line to allow flexibility in<br />

future planning.<br />

In conformity with the Hong Kong Planning Standards and Guidelines (HKPSG) a minimum building set<br />

back of 6.0 metres has been applied to the northern boundary of the site. A 15.0 metre set back has been,<br />

proposed adjacent to road Rl to effectively set development back from the road and to enhance emergency<br />

vehicle circulation and access. No development will be permitted within 20 metres of the seawall to the<br />

west of the site. The reserve is required for emergency vehicle access purposes and as a seawall<br />

maintenance reserve. No formal set backs are applied along the southern boundary of the site which is<br />

abutted by a 7.3 emergency vehicle access (EVA) and a landscape buffer. The EVA has been provided<br />

to allow emergency vehicle access in the event of an incident. The EVA provides direct access to the<br />

seawall which will allow emergency vehicles access to berthing areas if required.<br />

Typical mooring arrangements sufficient to the requirements of a Naphtha Plant have been depicted on<br />

the plan for indicative purposes. Given the anticipated frequency of vessel arrivals, a single dolphin berth<br />

is considered adequate. The length of marine frontage has been determined by the anticipated length of<br />

vessels which are likely to service the Naphtha Plant.<br />

A plot ratio of 1.25 is suggested for the site which produces a GFA amounting to 136,875 m : . In<br />

accordance with the findings of the risk assessment worker density, should not exceed 20 workers per<br />

hectare. This density provides a total site workforce amounting to 219 workers. Maximum building<br />

height should not exceed 30 metres. Applications for stacks, flues or other structures in exceedence of<br />

this height will be subject to visual and environmental impact assessments. It is recommended that the<br />

maximum building height recommendation is rigorously applied. Everyday access to the site will be<br />

obtained from Road Rl.<br />

Site 3/1 comprises a total area of 2.82 hectares. A plot ratio of 2,5 will apply resulting in GFA of 70,500<br />

m 2 . Due to the reduced risk implications related to the processes envisaged on PHI related sites, worker<br />

density is recommended at 30 workers per hectare maximum. A 10.0 metre building setback is<br />

recommended adjacent to road R2, a 15.0 metre setback adjacent to road Rl, and a 6.0 metre setback<br />

elsewhere. The setbacks are intended to enhance traffic visibility and for safety and other considerations<br />

cited in connection with I(C) class industries. Building height will be limited to 30 metres maximum to<br />

correspond with adjacent PHI sites. No access to the site will be permitted from road R2 as this may be<br />

widened in the future to form a portion of district distributor D6. Access to the site will, therefore, be<br />

confined to Road Rl as indicated.<br />

To ensure that the development and layout of buildings and storage facilities on PHI and PHI related sites<br />

is satisfactory to prevailing practices and standards, it is recommended that individual developers seek<br />

CCPHI approval and conform to the requirements of EPD Advice Note 2/92.<br />

BL4.2 Industry I(Q (9.61 Hectares)<br />

A single reserve has been made for I(C) class industry. Site 2/1 comprises a total area of 9.61 hectares<br />

and has been reserved for Industry Class C use. In accordance with the findings of the Study, Site 2/1<br />

is envisaged to be allocated to a LPG storage and bottling facility. The facility will only require a single<br />

berth. This requirement combined with the berthing adjacent sites has dictated the *L* shaped site<br />

configuration.<br />

A plot ratio of 1.25 is recommended which results in a GFA amounting to 120,100 m 2 . On site worker<br />

density is recommended not to exceed 20 workers per hectare. This results in a total estimated workforce<br />

of 192 persons. A 6.0 metres set back is maintained along the northern and southern boundaries for the<br />

purpose of emergency vehicle access. Set backs employed behind the seawall and adjacent to road Rl are<br />

APH Consultants<br />

p age


Engineering Feasibility Study of Dwtlopmtnt of Tstung Kwan O Ana 137<br />

Find Report - Main Report<br />

identical to those described in the context of Site I/I. Access to the site will be obtained from road Rl<br />

located to the east of the site. Height limitations and conditions described in the context of Site 1/1 should<br />

be similarity applied to Site 2/1. Site boundaries have been indicated with a strong broken line to allow<br />

future flexibility should revision be required to the planning layout.<br />

B1.43 Government Institutional and Community Provision (0,24 Hectares)<br />

A single 1C reserve has been provided within the layout. The reserve comprises a 0,24 hectare lot for<br />

the construction of an electricity substation. The substation is required to ensure adequate power<br />

reticulation within Area 137.<br />

Bl.4,4 Open Space and Amenity (235 Hectares)<br />

A single amenity reserve amounting to 2.35 ha has been provided adjacent to Cleaiwater Bay Country<br />

Park and Tit Cham Chau. The reserve will permit adjacent buffer planting to ensure that the integrity of<br />

existing natural features is maintained.<br />

B1.5 ACCESS AiND CIRCULATION (3.63 Hectares)<br />

Access to Area 137 will initially be achieved by an extension of road D6, which will be extended as road<br />

R2. In the subject planning area R2 will connect to road Rl via a roundabout in the southern area of the<br />

layout. No site access will be permitted from road R2. AH road and footpath reserves have been<br />

indicated on Layout Plan L No parking will be permitted along site primary and secondary roads.<br />

Loading and unloading facilities and parking provision sufficient to the requirements of the HKPSG should<br />

be provided on each site. A bus terminus has been indicated adjacent to the eastern boundary of Site 2/1<br />

which is intended to service site employers.<br />

B1.6 IMPLEMENTATION<br />

BL6.1 Site Formation<br />

Area 137 is proposed to be constructed as part of a roiling programme. Land formation will commence<br />

in the area covered by LP1 and commence northward. Under current planning the first parcels of land<br />

could be formed by 1996. No firm date has yet been decided.<br />

Bl*6,2 Stormwater Drainage and Services<br />

Stonnwater culverts and their respective reserves have been indicated on LPL The culverts will collect<br />

run-off from Clearwater Bay Country Park and Tit Cham Chau Respectively and discharge into the sea,<br />

Mains service reticulation will be provided incrementally upon the adequate consolidation of die<br />

reclamation.<br />

Consultant*<br />

Pag *


Engineering Feasibility Study of Development of Tseiwg Kwax 0 Area 137<br />

Final Report - Main Report<br />

B1.7 LANDSCAPE PROPOSALS<br />

Layout Plan 1 covers the southern portion of Area 137 from mid site to Tit Cham Chau Island in the<br />

south, Clearwater Bay Country Park to the east, and Clearwater Bay to the West*<br />

The area covered is proposed for gas production and LPG industry, and smaller PHI related units. Both<br />

zones are served by Road Rl.<br />

Road Rl has a 15 m interface along both sides of its length. Mounding up to 2.5m and dense planting<br />

will be incorporated to reduce the scale of the development both on and off site by creating a significant<br />

green corridor.<br />

The area abutting Tit Cham Chau and Clearwater Bay Country Park will allow opportunities for extensive<br />

structure planting, buffering and development containment. An Emergency Vehicle Access runs through<br />

the buffer zone. Where feasible, grass block paving (Grass Crete) should be used to minimise the expanse<br />

of hard surface on the site.<br />

Along the water front some intermittent structure planting will be incorporated to help the development<br />

merge against the hill side. The interface at the boundaries is 4.5m for each zone resulting in a 9m strip.<br />

A 1.5m high bund will be incorporated with structure planting. These will form fingers of vegetation<br />

maintaining a visual and physical connection with the hill side.<br />

A detailed schedule of land use by site, area plot ratio and GFA is provided on Attachment 1 following.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

ATTACHMENT 1, LAYOUT 1<br />

AREA 137 LAND USE, PLOT RATIO AND GROSS FLOOR AREA<br />

Site No.<br />

Land Use<br />

1/1 I(B)<br />

2/1 KC)<br />

3/1 I(B)<br />

4/1 IC(ESS)<br />

5/1 A<br />

Roads and<br />

Footpaths<br />

Total<br />

Site Area<br />

(Hectares)<br />

10.95<br />

9.61<br />

2.82<br />

0.24<br />

2.35<br />

3.63<br />

29.60<br />

PR<br />

GFA (ra2)<br />

1.25 136,900<br />

1.25 120,100<br />

2.50 70,500<br />

-<br />

-<br />

-<br />

327.500<br />

APH Consultants<br />

Page *" 5


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

B2 LAYOUT PLAN 2<br />

B2.1 INTRODUCTION<br />

Layout Plan 2 (LP2) forms a composite part of the overall planning for Area 137 which has been<br />

undertaken under the Study. Following submission of the Preferred Concepts Report which identified a<br />

preferred land use layout and transport network for Area 137 layout plans at scale 1:1000 have been<br />

produced to reflect study findings.<br />

Area 137 is covered by 3 layout plans which comprehensively define land use for the proposed<br />

reclamation. The subject layout plan (LP2) depicts land use proposals for the central portion of the<br />

proposed Area 137 development.<br />

B2.2 OBJECTIVES OF THE PLAN<br />

Layout Plan 2 provides sites for Potentially Hazardous Installations (PHI's), PHI related industry, Industry<br />

Class B and amenity reserves. The main objective of the plan is to depict land use proposals defined in<br />

the Study and to provide a formal basis for land disposal.<br />

B23<br />

THE PLANNING AREA<br />

Area 137 is located to the southeast of Tsueng Kwan O New Town and is located between Fat Tong Chau<br />

and Tit Cham Chau. The total planning area amounts to 101.78 hectares which will be composed of<br />

reclaimed land with a mean formation level of -r5 mPD. Layout Plan 2 is located in the central portion<br />

of the proposed reclamation. The total land area covered by the subject plan amounts to 35.05 hectares.<br />

The boundaries of the area covered by the plan are defined by the proposed new seawall to the west,<br />

Clearwater Bay Country Park to the east, the southern boundaries of Site 1/2 and 8/2 to the south and the<br />

northern boundaries of Sites 3/2, 4/2, 5/2 and 6/2 to the north.<br />

B2.4 LAND USE PROPOSALS<br />

To avoid confusion all layouts are numbered according to a common format. Site 3/2 refers to Site 3 on<br />

Layout Plan 2; similarly Site 8/3, refers to Site 8 on Layout Plan 3. The numbering system is intended<br />

to aid the identification of specific lots on a given layout plan without cumbersome cross referencing.<br />

B2.4.1 Industry I(Q (20,31 Hectares)<br />

Lot 1/2 with a total area of 10,72 hectares has been allocated for Industry Class C use. It is intended that<br />

the site will be developed for PHI purposes. The site, subsequent to the findings of the Study, has been<br />

tentatively earmarked for chemical storage purposes to be operated by a private developer. The need for<br />

bulk chemical storage sites has been highlighted by the Industry Department. It is intended that the<br />

chemicals stored will be used by industries in Hong Kong and within the region.<br />

In conformity with the Hong Kong Planning Standards and Guidelines (HKPSG), a minimum building<br />

setback of 6.0 metres has been applied to the northern and southern boundaries. A 15.0 metre setback<br />

has been proposed adjacent to road Rl to effectively set development back from the road and to enhance<br />

emergency vehicle access and circulation. No development will be permitted to the west of the site within<br />

20 metres of the seawall. This reserve is required for emergency vehicle access purposes and as a seawall<br />

APH Consultants<br />

p age


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

maintenance access reserve. The EVA adjacent to the seawall will allow emergency access to berthing<br />

areas if required.<br />

Indicative typical mooring arrangements sufficient to the requirements of the envisaged chemical storage<br />

facility have been shown on the plan. The operation of a chemical storage facility requires two berths,<br />

hence two dolphin berths with sufficient mooring separation have been shown. The length of the site<br />

marine frontage has been determined by the estimated length of vessels likely to service the storage<br />

facility.<br />

A plot ratio of 1.25 is suggested for the site which produces a GFA amounting to 134,000 m 2 . In<br />

accordance with the findings of the Study risk assessment worker density will not exceed 20 workers per<br />

hectare. This density provides for a total site workforce of 214 workers. Maximum building height will<br />

not exceed 30 metres. Applications for stacks, flues or other structures in exceedence of this height will<br />

be subject to visual and environmental impact assessments. It is recommended that the maximum building<br />

height recommendation is rigorously applied. Access to the site will be obtained from roads Rl and R4.<br />

Suggested access points are depicted on Layout Pfan 2.<br />

Site 3/2 comprises a total area of 10.09 hectares and has been reserved for Industry Class C use. In<br />

accordance with the findings of the Study, Site 3/2 is envisaged to be allocated to a bulk oil storage<br />

facility. The facility will only require a single berth and a typical mooring arrangement has been depicted<br />

on Layout Plan 2.<br />

A plot ratio of 1.25 is recommended which results in a GFA amounting to 126,100 m 2 . On site worker<br />

density is recommended not to exceed 20 workers per hectare. This results in a total estimated workforce<br />

of 202 persons. A 6.0 metre set back is maintained along the northern and southern boundaries for the<br />

purpose of emergency vehicle access. Set backs employed behind the seawall and adjacent to road Rl are<br />

identical to those described in the context of Site 1/2, Access to the site will be obtained from road R4<br />

located to the south of the site. Height limitations and conditions described in the context of Site 1/2<br />

should be similarly applied to Site 3/2. Site boundaries have been indicated with a strong broken line to<br />

allow future flexibility should revision be required to the planning layout.<br />

B2.4.2 Industry I(B) PHI Related Industry (4.36 Hectares)<br />

Two PHI Related I(B) industry reserves have been made for I(B) class industry allocated for PHI related<br />

industrial purposes. It is intended that such operations will be mutually linked to adjacent PHI sites and<br />

utilise PHI products in production.<br />

Site 7/2 comprises a total area of 2.26 hectares. A plot ratio of 2.5 will apply resulting in GFA of 56,500<br />

or. The remaining I(B) Site (8/2) comprises a total area of 2.10 hectares with a resultant GFA of 52,500<br />

m 2 . Due to the reduced risk implications related to the processes envisaged on PHI related sites, worker<br />

density is recommended at 30 workers per hectare maximum. This results in a workforce of 45 for Site<br />

7/2 and 63 workers for Site 8/2. For each site a 10.0 metre building setback is recommended adjacent<br />

to road R2, a 15.0 metre setback adjacent to road Rl, and a 6.0 metre setback elsewhere. The setbacks<br />

are intended to enhance traffic visibility and for safety and other considerations cited in connection with<br />

I(C) class industries. Building height should be limited to 30 metres maximum to correspond with<br />

adjacent PHI sites. No access to the site will be permitted from road R2 as this may be widened In the<br />

future to form a portion of district distributor D6, Access to the site will, therefore, be confined to Road<br />

Rl as indicated.<br />

To ensure that the development and layout of buildings and storage facilities on PHI and PHI related sites<br />

conform to prevailing practices and standards, it is recommended that individual developers seek CCPffl<br />

approval and conform to the requirements of EPD Advice Note 2/92.<br />

APH Consultants


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

B2.4.3 I(B) Deep Water Industry (DWI) Related Sites (1.68 Hectares)<br />

Sites 5/2 and 6/2 have been allocated to DWI purposes. By definition DWI development comprises<br />

industrial or warehousing operations which, by virtue of their nature require deep water berths. Activities<br />

which cannot prove such a requirement may be precluded from the acquisition of DWI lots. Facilities<br />

falling into this category include the bulk heavy oil storage and packing industry, the break bulk chemical<br />

industry, and the concrete batching and prefabrication industry.<br />

Each I(B) site is ascribed a plot ratio of 2,5 which results in a GFA of 23,300 m 2 and 18,800 or for lots<br />

5/2 and 6/2 respectively. Worker density should not exceed 30 persons per hectare according to the<br />

recommendations of the Study risk assessment. This will result in a total workforce of 50 persons for the<br />

two sites. The same height conditions applied to I(C) and PHI related sites are also recommended for the<br />

I(B) sites. Building setbacks of 6.0 metres have been applied to roadside lot frontages and 4.5 metres on<br />

all other boundaries. This has been undertaken to ensure adequate emergency vehicle access and to create<br />

adequate separation between buildings. A detailed site schedule is shown on Attachment 2.<br />

B2.4.4 Government Institutional and Community Provision (0*02 Hectares)<br />

A 225 m 2 4 G* reserve is provided on Site 2/2 and is intended for the construction of a sewage pumping<br />

facility. This is required to pump sewage for treatment at the Tseung Kwan 0 Treatment works.<br />

Site 4/2 is a combined reserve (G and LO) providing site servicing and recreational facilities. Details of<br />

open space provision are provided below. Services anticipated would comprise estate related offices and<br />

small scale commercial premises. It is not, however anticipated that these will be large scale facilities and<br />

only two to three storey structures wiU be permitted. A suggested treatment is provided in the landscape<br />

master plan accompanying the Study Final Report. No GFA is suggested as this should be decided with<br />

respect to demand upon the implementation of Area 137.<br />

B2.4.5 Open Space and Amenity (1.0 Hectares)<br />

A single amenity reserve amounting to 2.03 ha has been provided adjacent to Clearwater Bay Country<br />

Park. The reserve will permit adjacent buffer planting to ensure that the integrity of existing natural<br />

features is maintained.<br />

The HKPSG requires the allocation of 0.5 m 2 of open space per industrial worker (5 ha per 10,000<br />

workers). As this standard would only provide nominal open space generous provision is made on Site<br />

4/2 given the relatively isolated location of Area 137. The open space will be highly compatible to the<br />

service centre anticipated on the same site.<br />

B2.S<br />

ACCESS AND CIRCULATION (5,15 Hectares)<br />

Access to Area 137 will initially be achieved by an extension of Road D6 which will be extended as road<br />

R2. A reserve for D6 has been indicated on the plan. In the subject planning area, R2 will connect to<br />

road Rl via a roundabout in the southern area of the layout. No site access will be permitted from road<br />

R2. All road and footpath reserves have been indicated on Layout Plan 2. No parking will be permitted<br />

along site primary and secondary roads. Loading and unloading facilities and parking provision sufficient<br />

to the requirements of the HKPSG should be provided on each site. In order to avoid vehicular conflicts,<br />

road R5 will be limited to west-east one way traffic flow providing access to adjacent sites. Road R4 will<br />

culminate in a turning circle and will provide access to Sites 1/2 and 3/2.<br />

APH Consultants p age B~8


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

B2.6 IMPLE3VIENTATION<br />

B2.6.1 Site Formation<br />

Area 137 is proposed to be constructed as part of a rolling development programme. Land formation will<br />

commence in the area covered by LP1 and commence north via the area occupied by Layout Plan 2.<br />

Under current planning the first parcels of land could be formed by 1996. No firm date has yet been<br />

decided.<br />

B2*6.2 Stormwater Drainage and Services<br />

Stormwater culverts and their respective reserves have been indicated on LP2. The culverts will collect<br />

run-off from Clearwater Bay Country Park and site roads and discharge into the sea.<br />

Mains service reticulation will be provided incrementally upon the adequate consolidation of the<br />

reclamation.<br />

B2.7 LANDSCAPE PROPOSALS<br />

Layout Plan 2 provided for PHI and PHI related industry in the central section of the site. Within this<br />

section is a services reserve and smaller industrial units served by roads Rl, R4, R5 and R2 located at<br />

the foot of the Clearwater Bay Country Park.<br />

R2 and R4 have a 6m interface between the footpath and the developments allowing dense tree and shrub<br />

planting to be implemented. This will act in conjunction with planting immediately alongside the road to<br />

create smaller green fingers linking into to the main vegetation infrastructure.<br />

The service area will be primarily used for recreation although buildings will be incorporated for support<br />

facilities. A grassed area with seating will be incorporated to form a green pocket within the site, with<br />

space for some ball court facility to be developed at a later date.<br />

APH Consultants Page B-9


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

ATTACHMENT 2, LAYOUT 2<br />

AREA 137 LAND USE, PLOT RATIO AND GROSS FLOOR AREA<br />

Site No.<br />

1/2<br />

2/2<br />

3/2<br />

4/2<br />

5/2<br />

6/2<br />

7/2<br />

8/2<br />

9/2<br />

Roads and<br />

Footpaths<br />

Total<br />

Land Use<br />

Site Area<br />

(Hectares)<br />

I(C) 10.72<br />

G(Pumping 0.02<br />

Station<br />

Reserve)<br />

I(C) 10.09<br />

LO+G 1.00<br />

I(B) • 0.93<br />

I(B) 0.75<br />

I(B) 2.26<br />

I(B) 2.10<br />

A 2.03<br />

5.15<br />

35.05<br />

PR GFA<br />

1.25 134,000<br />

-<br />

1.25 126,100<br />

-<br />

2.50 23,300<br />

2.50 18,800<br />

2.50 56,500<br />

2.50 52,500<br />

-<br />

411.200<br />

APH Consultants Page B-10


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Find Report - Main, Report<br />

B3 LAYOUT PLAN 3<br />

B3J<br />

INTRODUCTION<br />

Layout Plan 3 (LP3) forms a composite part of the overall planting for Area 137 which has been<br />

undertaken under the Study. Following submission of the Preferred Concepts Report which identified a<br />

preferred land use layout for Area 137, layout plans at scale 1:1000 have been produced to reflect the<br />

Study findings.<br />

Area 137 is covered by 3 layout plans which comprehensively define land use for the proposed<br />

reclamation. The subject Layout Plan (LP3) depicts land use proposals for the northern portion of the<br />

proposed Area 137 development.<br />

B3.2 OBJECTIVES OF THE PLAN<br />

Layout Plan 3 provides for Deep Water Industry (DWI), reprovisioning of the SENT Landfill marine<br />

access, and areas of amenity. The main objective of the plan is to depict land use proposals defined in<br />

the Study and to provide a formal basis for land disposal.<br />

B33<br />

THE PLANNING AREA<br />

Area 137 is located to the south east of Tseung Kwan 0 New Town and is located between Fat Tong Chau<br />

and Tit Cham Chau. The total planning area amounts to 101.78 hectares which will be composed of<br />

reclaimed land with a mean formation level of -f 5 mPD. Layout Plan 3 is located in the northern portion<br />

of the proposed reclamation. The total land area covered by the subject plan amounts to 37.13 hectares.<br />

The boundaries of the area covered by the plan are defined by the proposed new seawall to the west,<br />

Clearwater Bay Country Park to the east, Road R6 to the south and Fat Tong Chau, TKOEE and the SENT<br />

Landfill to the north.<br />

B3.4 LAND USE PROPOSALS<br />

To avoid confusion all layouts are numbered according to a common format. Site 3/2 refers to Site 3 on<br />

Layout Plan 2; similarly Site 8/3, refers to Site 8 on Layout Plan 3. The numbering system is intended<br />

to aid the identification of specific lots on a given layout plan without cumbersome cross referencing.<br />

B3.4.1 I(B) Deep Water Industry (DWD Sites (15.85 Hectares)<br />

A total of 15 sites have been allocated to DWI purposes by definition. DWI development comprises<br />

industrial or warehousing operations which, by virtue of their nature require deep water berths. Activities<br />

which cannot prove such a requirement may be precluded from the acquisition of DWI lots. Facilities<br />

falling into this category include the bulk heavy oil storage and packing Industry the break bulk chemical<br />

industry, and the concrete batching and prefabrication industry.<br />

All 15 I(B) sites have been ascribed a plot ratio of 2.5 which results in a total GFA amounting to 396,600<br />

m 2 (See Attachment 3 for breakdown). Worker density will not exceed 30 persons per hectare in<br />

accordance with the recommendations of the Study risk assessment. Maximum building height should not<br />

exceed 30 metres. Applications for stacks, flues or other structure in exceedence of this height will be<br />

Consultants<br />

Pa % e B ' L1


Engineering Feasibility Study of Development of Tseung Kwan O Arm 137<br />

Final Report - Main Report<br />

subject to visual and environmental impact assessments. It is recommended that the maximum building<br />

height recommendation is rigorously applied.<br />

Proposed access arrangements to each I(B) site have been depicted on Layout Plan 3. Although mean lot<br />

size amounts to 1.0 hectare, the boundaries of each site have been demarcated with a strong broken line.<br />

This prescribes an indicative lot boundary and provides flexibility to future planning by permitting the<br />

consolidation or subdivision of lots.<br />

A 6.0 metre building set back has been applied along front and rear boundaries and 4.5 metres along other<br />

boundaries. Set backs will ensure emergency vehicle access, provide adequate building separation and<br />

provide important breezeways.<br />

B3.4.2 I(Q Deep Water Industry (DWI) Sites (4.76 Hectares)<br />

Almost 20% of all deep water industry sites have been allocated to Industry Class (C) purposes. It is<br />

intended that these be reserved for storage purposes with the particular objective of realising Government's<br />

policy to remove existing dangerous goods godowns from the urban area.<br />

It is intended that 5 sites amounting to a total site area of 4.76 hectares be designated for I(C) DWI<br />

purposes. A plot ratio of 2.5 will apply which will generate a total GFA amounting to 119,000 nr.<br />

Building height restrictions and building set back recommendations applicable to I(B) DWI sites should<br />

also be applied to I(C) DWI sites.<br />

It is intended that all sites will have access to the 50 metre multi-user berth working area abutting the sea<br />

wall to the west of the site. The working area will be administered by Government to ensure that<br />

equitable access to the seawall is obtained. Emergency Vehicle Access to the Working Area will be<br />

provided from road R6 to the south of the layout and roads R9 and RIO to the north of the layout.<br />

B3.43 Government, Institutional and Community Provisions (3.59 Hectares)<br />

Two Government reservations have been provided an Layout Plan 3. An 100 m 2 reserve has been made<br />

for a sewage pumping station on lot 9/3 adjacent to Road RIO, The pumping station is required to provide<br />

a temporary facility for the SENT Landfill marine facility.<br />

A 3,58 hectare reservation has been provided adjacent to the seawall to provide for a multi-user berth<br />

working area. This will be used by lots which require access to deep water berths. It is anticipated that<br />

the facility will be administered by the Marine Department.<br />

B3.4.4 Open Space and Amenity (4.22 Hectares)<br />

Two amenity reserves of area 4.22 hectares have been provided adjacent to Clearwater Bay Country Park<br />

and Fat Tong Chau. The reserve will permit adjacent buffer planting to ensure that the integrity of<br />

existing natural features is maintained.<br />

B3.4.5 Other Specified Use (1.25 Hectares)<br />

A L25 hectare reserve has been reserved for the reprovisioning of SENT Landfill marine access which<br />

is required upon implementation of Area 137. The reserve comprises a 250 metre marginal quay with a<br />

50 metre working area provided to the rear of the quaywaE, Once SENT Landfill operations are complete<br />

the site could be handed over to another user for industrial development. Access to the site wiE be<br />

obtained from road RIO which will be maintained as a private road for the life of the landfill.<br />

APH Consultants Page 3*12


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

B3.5 ACCESS AND CIRCULATION (7.46 Hectares)<br />

Access to Area 137 will initially be achieved by an extension of Road D6 which will be extended as Road<br />

R2. In the subject planning area R2 will connect to road Rl via a roundabout located to the east of the<br />

layout. No site access will be permitted from roads R2 and RIO. Road RIO win be maintained as a<br />

private road for the life of the SENT Landfill. All road and footpath reserves have been indicated on<br />

Layout Plan 3. No parking will be permitted along site primary and secondary roads indicated on the<br />

plan. Loading and unloading facilities and paiidng provision sufficient to the requirements of the HKPSG<br />

should be provided on each site. Recommended points of access to each site have been indicated on<br />

Layout Plan 3.<br />

B3*6 IMPLEMENTATION<br />

B3.IJ.1 Site Formation<br />

Area 137 is proposed to be constructed as part of a rolling development programme. Land formation will<br />

commence in the area covered by LP1 and commence northwards to sites depicted on Layout Plan 3.<br />

Under current planning the first parcels of land could be formed by 1996. No firm date has yet been<br />

decided.<br />

83.6,2 Stormwater Drainage and Services<br />

Stormwater culverts and their respective reserves have been indicated on LP3. The culverts will collect<br />

run-off from SENT Landfill, Clearwater Bay Country Park and Fat Tong Chau respectively and discharge<br />

into the sea.<br />

Mains service reticulation will be provided incrementally upon the adequate consolidation of the<br />

reclamation.<br />

B3.7 LANDSCAPE TREATMENT<br />

Layout Plan 3 covers the northern section of the site adjacent to Fat Tong Chau and the SENT Landfill.<br />

This area incorporates Deep Water Industries and a 50 metre wide working area. The area is served by<br />

feeder roads R6, R7, R9 leading from a major roundabout on road D6. The roundabout and planters will<br />

be provided with ornamental shrub treatment.<br />

An extensive area of buffer planting will be implemented at the base of Fat Tong Chau and along a 7m<br />

strip at the interface to the SENT Landfill site. A 6m wide planting zone has been allocated along the<br />

working area, but planting will be intermittent to allow for access and to form a gentle merger with the<br />

hilly backdrop.<br />

Consultants Page 3-13


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

ATTACHMENT 3, LAYOUT 3<br />

AREA 137 LAND USE, PLOT RATIO AND GROSS FLOOR AREA<br />

Site No.<br />

1/3<br />

2/3<br />

3/3<br />

4/3<br />

5/3<br />

6/3<br />

7/3<br />

8/3<br />

9/3<br />

10/3<br />

11/3<br />

12/3<br />

13/3<br />

14/3<br />

15/3<br />

16/3<br />

17/3<br />

18/3<br />

19/3<br />

20/3<br />

21/3<br />

22/3<br />

23/3<br />

24/3<br />

25/3<br />

26/3<br />

Road and Footpaths<br />

Total<br />

Land Use<br />

G(Multi-User<br />

Berth Working<br />

Area)<br />

KB)<br />

I(C)<br />

KQ<br />

KB)<br />

I(B)<br />

ou'<br />

A<br />

G{Pumping<br />

Station<br />

Reserve)<br />

A<br />

I(B)<br />

KB)<br />

I(B)<br />

I(B)<br />

KB)<br />

KB)<br />

I(B)<br />

KB)<br />

KB)<br />

KB)<br />

KQ<br />

I(C)<br />

I(C)<br />

I(B)<br />

A<br />

1(B)<br />

-<br />

Site Area<br />

(Hectares)<br />

3.58<br />

2.22<br />

2.32<br />

1.01<br />

1.00<br />

1.05<br />

1.25<br />

2.12<br />

0.01<br />

0.89<br />

0.57<br />

0.71<br />

1.05<br />

1.13<br />

1.57<br />

1.36<br />

0.93<br />

0.82<br />

0.70<br />

0.44<br />

0.48<br />

0.50<br />

0.45<br />

0.60<br />

1.21<br />

1.70<br />

7.46<br />

37.13<br />

PR<br />

-<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

-<br />

-<br />

-<br />

-<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

2.50<br />

-<br />

2.50<br />

-<br />

GFA<br />

(m2)<br />

«.<br />

55,500<br />

58,000<br />

25,300<br />

25,000<br />

26,300<br />

-<br />

.<br />

_<br />

-<br />

14,300<br />

17,800<br />

26,300<br />

28,300<br />

39,300<br />

34,000<br />

23,300<br />

20,500<br />

17,500<br />

11,000<br />

12,000<br />

12,500<br />

11,300<br />

15,000<br />

.<br />

42,500<br />

-<br />

515,700<br />

APE Consultants<br />

Page B-14


Suggested Modifications<br />

to Tseung Kwan 0 OOP


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

final Report - Main Report<br />

APPENDIX C<br />

SUGGESTED MODIFICATIONS TO TSEUNG KWAN O ODP<br />

Cl<br />

IMPLICATIONS FOR THE CURRENT ODP<br />

The planning brief requires that impacts on the current ODP which arise during the course of the Area<br />

137 Study should be highlighted in the Final Report. The impacts identified may have a corresponding<br />

impact on the approved Outline Zoning Plan (QZP), The main planning impacts are listed below.<br />

The extent of land formally allocated to PHI development amounted to 20 hectares. The Study has<br />

established that the demand for PHI sites may be substantially stronger than that originally identified. The<br />

outcome of this is that the land use budget outlined in the ODP is significantly different from that<br />

recommended by the Consultants, Similarly, the findings of the Risk Assessment undertaken under the<br />

Study, have suggested that worker densities are restricted to 20 workers per hectare for PHI development<br />

and 30 workers per hectare for DWI development. Modification to the employment assumptions made<br />

in the ODP are therefore required.<br />

Upon acceptance of the Consultants layout plans, the ODP can be modified to reflect the disposition and<br />

composition of land uses. The preferred seawall alignment should also be depicted.<br />

The proposed road alignment depicted in the preferred layout plans should be incorporated on the ODP.<br />

Road details should include the proposed extension of distributor road D6 through Area 137.<br />

Work undertaken with regard to the Western Coast Road has indicated that population thresholds assumed<br />

in the ODP may not be achieved if improvements of the existing external road network, including the<br />

Western Coast Road, are not promptly implemented. It has also transpired that capacity of current road<br />

links has been based not on the ODP population, but that derived by the Metro Planning Group. This<br />

implies that the ODP target population may not be achievable within the time period envisaged and with<br />

regard to the currently planned transport links. Review of the ODP in this respect is therefore, required<br />

and planning assumptions should be modified as appropriate.<br />

The Study has provided an indicative layout for Area 13 L The layout, subject to further study, should<br />

be incorporated on the ODP. The layout requires the realignment of road D9.<br />

Finally, all of the above should be reflected in modification and amendment of the ODP written statement.<br />

APH Consultants


m<br />

•"<br />

Draft Final Report<br />

Comments & Responses


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

CIVIL ENGINEERING DEPARTMPvr<br />

Your response to my previous comment on providing<br />

more reference for the downtime criteria is not<br />

satisfactory. More specific source for establishing<br />

the downtime criteria should be given. It is not clear<br />

whether the excess of both the critical Hs and Tp is<br />

required for causing suspension of operation.<br />

I would like to reiterate that access for future<br />

maintenance of the seawall underneath the quay<br />

structures should be taken into account in the design<br />

of these structures.<br />

The report should address if land resumption and<br />

clearance would be required for the proposed<br />

developments in Area 137.<br />

Please assess the possibility to open a public dump in<br />

area 137 and indicate the timing in the<br />

implementation programme as appropriate (Figure<br />

10.2 & 10.3 refer).<br />

It is understood that Director of Planning has written<br />

to PM/SENT recently, raising the issue of the<br />

possibility of rock caverns behind Area 137.<br />

The definition of operational downtime criteria is highly site<br />

specific and there are no general sources of information.<br />

The values as presented are based on APH experience and if<br />

required could only be refined by detailed physical model<br />

tests. Generally, it may be anticipated that Tp is more<br />

critical in the suspension of operations than Hs.<br />

Noted.<br />

No land resumption or clearance would be required for the<br />

development of Area 137.<br />

As discussed in Section 10, Public dumping Is proposed for<br />

the completion stage of the project commencing late 1997.<br />

A comment on the possible use of caverns behind Ami 137<br />

will be included in the text.<br />

ii) Section 2.2.1<br />

"OPD" in para. 2 and 4 should read "OOP".<br />

Text will be amended.<br />

Figure 3.3<br />

The report should address if typhoon moorings would<br />

need to be planned in conjunction with the proposed<br />

floating docks facilities in Area 131.<br />

Section 5.2.1<br />

I fully support the proposal to adopt the reclamation<br />

methods within minimum removal of the marine mud<br />

at the site.<br />

The Area 131 layout was developed for hydraulic modelling<br />

purposes only. Consideration of typhoon moorings is not a<br />

requirement of the Brief or the additional work performed<br />

for Area 131.<br />

Noted.<br />

Section 5,2.2<br />

The assessment of total consolidation settlement of up<br />

to 3.1 m and the design of vertical drains to<br />

accelerate the settlement are based on limited ground<br />

investigation data. I concur with your<br />

recommendation that the design (settlement and<br />

vertical drain design) should be confirmed/reassessed<br />

by further ground investigation at the detailed design<br />

stage and also during the first phase of vertical dram<br />

installation.<br />

Noted.<br />

There Is a major natural slope, with cliff, to the east<br />

of the proposed internal access road, R2, which runs<br />

along the edge of the Clearwater Bay Peninsula. The<br />

stability of this slope should be investigated, with<br />

remedial works proposed as necessary, at the detailed<br />

design stage.<br />

APH Consultants<br />

Appendix D-J


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Section 53.1<br />

The two reasons stated in the report to justify the<br />

removal of marine deposits along the edge structures<br />

are superficial. This has been commented upon at<br />

the Preferred Concept Plan Report, and I suggested<br />

that the alternative of founding the edge structures on<br />

the marine mud by pretreatment of the foundation<br />

with deep chemical mixing should be kept open.<br />

You responded that this would be reviewed in the<br />

light of the site investigation laboratory results.<br />

Perhaps, you should carry out the review before<br />

finalising the Final Report.<br />

The possibility of marine deposit being stronger than<br />

normal has been noted in the Draft Executive<br />

Summary (DES, page 5) but this has not been noted<br />

in the report. The alternative construction method,<br />

as noted above, should also be highlighted in the<br />

Draft Executive Summary.<br />

Please note that under WBTC Nos. 6/92 and 22/92,<br />

the need to dredge OJ Mm* of uncontaminated mud<br />

or any qualities of contaminated mud should be<br />

justified and agreed by the FMC.<br />

The preliminary site investigations have indicated a marine<br />

deposit layer thickness on the proposed seawall alignment of<br />

11 to 15m, with an average of 12m. Farther, it would not be<br />

necessary to remove more than this layer to provide adequate<br />

seawall stability. As such the findings of WP6 remain valid;<br />

the more so if fun depth removal due to higher strengths is<br />

not confirmed as being necessary.<br />

Equally, the possible retention and drainage of the layer<br />

should be kept open at the detailed design stage.<br />

Noted. Text will be amended.<br />

Noted.<br />

Section 533,<br />

Anchored steel sheet piled retaining wall Is proposed<br />

for seawall construction inside basin. Please clarify<br />

if the maintenance cost has been compared with other<br />

types of seawall construction.<br />

Recognition has been given to the potentially higher<br />

maintenance costs associated with a sheet piled solution. The<br />

adoption of a lower maintenance solution if required<br />

(blockwork) would have a 1% effect on project costs.<br />

In adopting an anchored sheet pile retaining wall as<br />

the edge structure for the basin berths, particular<br />

attention should be given to corrosion protection<br />

under the marine environment.<br />

Section 5.4<br />

The report states (also on page 5 of DES) that 9 Mm 3<br />

of marine fill has been provisionally allocated to<br />

Area 137 by the FMC and that the shortfall (6 Mm 3<br />

out of 15 Mm 3 ) could be made up with a larger<br />

allocation. This is not correct, as advised before at<br />

ihe Prelerred Concept Report Plan report stage. The<br />

FMC has not yet allocated or reserved any marine<br />

borrow areas for Area 137 and the allocation would<br />

likely be made at the tender document stage. The<br />

report should be amended to reflect the actual<br />

situation.<br />

A misunderstanding has arisen over the information given at<br />

our earlier discussions with FMC. Hence the earlier<br />

comment on the Preferred Concept Report was equally<br />

misinterpreted. FMC have been contacted and the position<br />

clarified. The text will be amended to eliminate reference to<br />

the preliminary allocation.<br />

Section 5.5<br />

It :s not possible to identify 4 dumping ground for<br />

the dredged material at this feasibility study stage.<br />

It is possible that the dredged material may be<br />

disposed of in redundant marine borrow pits, as<br />

suggested in the report, but it is also possible that the<br />

material may have to be disposed of to gazetted<br />

dumping grounds.<br />

Text win be amended to include reference to gazetted<br />

dumping grounds.<br />

APH Consultants Appendix D-2


Engineering FeasMity Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Section 5.7 J<br />

It is understood that Area 137 will be reclaimed<br />

generally to 4-0.5mPD with crest of the seawall at<br />

4-6.5 or 4-7.5 mPD and may lead to ponding of<br />

water. The report should address the provision of<br />

adequate surface drainage to avoid ponding of water.<br />

Text will b« amended to include avoidance of ponding as an<br />

objective. The preliminary design has taken this into<br />

account where appropriate.<br />

DRAINAGE SERVICES DEPARTMENT • MAINXANB SOUTH DrVTSTOIV<br />

(a)<br />

(b)<br />

(c)<br />

As indicated in paragraph 3 of Section 5.9.2, the<br />

sewage flows from Area 137 could be increased by<br />

2000 cum/d, which is over 60% of the estimated<br />

total flow from Area 137, should the gas production<br />

facility be more extensive than planned. Please<br />

advise what allowance or contingency will be made<br />

in the sewerage design of Area 137, and accordingly<br />

the capacity of the Treatment Works, to account for<br />

the capacity of the Treatment Works, to account for<br />

variations of such kind in development and future<br />

land use.<br />

The detailed design of interim works and outline<br />

design of Phase II Works for Tseung Kwan 0<br />

Sewage Treatment Works will be commenced<br />

shortly. Please urgently confirm the quantity of<br />

sewage flow from Area 137 to be allowed within the<br />

said designs. Perhaps, PM/SENT, as the client<br />

department for both the subject study and the said<br />

designs, may wish to pursue further.<br />

It appears that the unit tlow rates adopted in Table<br />

5.6 do not conform with those recommended in Civil<br />

Engineering Manual or Sewage Strategy Study.<br />

Your elaboration will be appreciated.<br />

rVefiminary sewerage design for Area 137 is based on the<br />

provisions contained in the land use plan. Final sewerage<br />

design will be based on firm proposals for the planned<br />

facilities. It is considered that adequate allowance in the<br />

design statement for TKO sewage treatment plant has been<br />

made as noted below.<br />

Adequate allowance has been made in the design statement<br />

for TKO sewage treatment plant Phase II for anticipated<br />

flows from Area 137. The allowance is 4,500 nrVday in 2001<br />

''Stage 11" and 6 J50 m 3 /day in 2011.<br />

Unit flow rates are based on Sewage Strategy Study except<br />

for gas production where the rate is based on equivalent<br />

existing facilities. Estimated Sewage flows (Table 5.61 have<br />

been derived for year 2011 by interpolation from the Sewage<br />

Strategy Study as shown below:<br />

WIT FLOW FACTORS * SSS<br />

TKO AREA 137 -<br />

DRAFT FINAL<br />

REPORT<br />

FlowTyp*<br />

Unit<br />

l»*<br />

(mtfday)<br />

2021<br />


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(d)<br />

However, it is worth noting that unit flow factors as<br />

suggested in SSS are apparently for global<br />

consideration and it may not be appropriate for using<br />

them for detailed design in a local area such as Area<br />

137 development.<br />

It is suggested in para 2 of Section 5.9.3 that flows<br />

from Area 137 will be temporarily pumped into the<br />

sewer system of Tseung Kwan O Industrial Estate.<br />

As there is no provision made within the sewers of<br />

TKODB for flows from Area 137, please clarify how<br />

this temporary arrangement can be done without<br />

causing adverse consequence.<br />

Noted: In this case, it is considered most appropriate to use<br />

these factors for outline design of Area 137 development,<br />

until specific (and more exact) information is available about<br />

the actual industry which will use Area 137.<br />

Temporary pumped flows from the SENT landfill marine<br />

access in Area 137 to TKO sewers will less than 1% of<br />

capacity and therefore insignificant. Alternatively, it may be<br />

possible to utilize self-contained (chemical) units which would<br />

eliminate these sewage flows.<br />

ENVIRONMENTAL PROTECTION DEPARTMENT<br />

(I)<br />

AIR QUALITY IMPACTS<br />

Section 8 - Western Coast Road<br />

(1) Section 8.6.2<br />

The results of air quality impact assessment for both<br />

options in Tables S.4 & 8.5 are consistent with the<br />

data previously presented and the modelling<br />

methodology agreed with EPD.<br />

For mitigation for both options by extension of<br />

enclosure, would the Consultants please confirm that<br />

the methodology used tor the assessment of the<br />

residue air quality impact is the same as the<br />

methodology previously agreed with EPD and advise<br />

on the length of extension required For mitigation<br />

by employing semi-enclosure or enclosure with free<br />

venting louvres, would the Consultants please<br />

provide us with further details in respect of the<br />

mitigation measures, the assessment methodology of<br />

the residue air quality impact and the predicted value<br />

of the residue air pollution level at the sensitive<br />

receptions upon the implementation of the mitigation<br />

Regarding the air quality inside the enclosure, would<br />

the Consultants please confirm that the air quality<br />

within the road enclosure would comply meet with<br />

the EPD 1 Tunnel Air quality guidelines which are as<br />

follows :<br />

Pollutant<br />

CO<br />

N


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Both 13Cm and 135m enclosures for Option A will carry<br />

3036 vebkle/hr with 62% of heavy vehicles while Route 5<br />

extension (200m tunnel) is expected to carry 3444 vehicle/hr<br />

with 68% of heavy vehicle. By comparison, it is expected that<br />

it is unlikely to violate the EPD's Tunnel Air Quality<br />

Guidelines for 130m and 135m enclosures in Option A.<br />

In Option B, the predkted air quality values for the 115m<br />

enclosure are 12 ppm (CO), 0.15 ppm (N0 2 ), and 1.5 ppm<br />

(NO). Since the 110m enclosure is expected to operate under<br />

similar traffic condition, both of them will comply with the<br />

EPD's Tunnel Air Quality Guidelines for 115m enclosure.<br />

Section 9 - Environmental Assessment<br />

(2)<br />

Section 9.4.3<br />

The main air pollutants emitted from the town gas<br />

manufacture from naphtha is Nitrogen Oxides. The<br />

maximum emission rate from the plant is merely<br />

about 3 g/s. In view of the above, the Consultants<br />

may need to consider reviewing the suitability of<br />

siting a gas production facility in TKO 137 given that<br />

both the I hour and 24 hours AQOs for nitrogen<br />

dioxide are considerably tower than the<br />

corresponding AQOs for sulphur dioxide.<br />

Based on the existing Ma Tau Kok gas production plant, a<br />

typical X0 a emissioa rate of 15 g/m : /day has been derived.<br />

This assumed emission rate thus corresponds to a cyclic<br />

catalytic gas production facility of about five times the<br />

capacity of Ma Tau Kok. With the same assumptions as<br />

presented in Section 9.4.5, the NOj concentration exposed by<br />

the Srs at Tseung Kwan 0 New Town due to the emissioa<br />

from the site will reach 32 /ig/m 3 (24 hour average). Since<br />

the final report on TKOFSOFD predkted maximum SO 5<br />

concentrations of 220 /tg/m* (after relocation of Shiu Wing<br />

phis 1 g/m 2 /day) at the southeast comer of the Tseung Kwan<br />

0 Mew Town, the corresponding maximum NO^<br />

concentration will be 8 Mg/ui 5 with the assumption of fuel oil<br />

(Oo% sulphur content). Hence it is likely that the nitrogen<br />

dioxide emitted by the proposed gas plant will not impact on<br />

Srs.<br />

(3)<br />

Section 9.4.5<br />

Given that the Deep waterfront Industries (DWI) uses<br />

have not been finalised and that the Potentially<br />

Hazardous Installations (JPHIs) uses are considered by<br />

the Consultants as unlikely to include combustion<br />

equipment except of course the gas production<br />

facility, it is appropriate to include a statement in the<br />

report to highlight that "No Fuel Intensive 1 * uses<br />

should be allowed in the TKO 137 as a land use<br />

constraint. The last statement of this section says<br />

that the emission of the gas production facility at area<br />

137 will not impact on SRs. I have reservation on<br />

this assertion as the main emission of concern from<br />

a town gas production plant is nitrogen oxides apart<br />

from the sulphur dioxide.<br />

Noted. Please refer to response an Section 9.43.<br />

(4)<br />

Section 9.4.8<br />

I support the Consultants' recommendation of<br />

conducting individual air quality impact studies for<br />

major industrial development when specific details<br />

are ioiown. Regarding the issue of ensuring an air<br />

quality impact assessment be carried out for an<br />

industrial development in TKO 137 wiih air pollution<br />

potential, EPD would look after its implementation<br />

through the ER/EIA process and the prospective land<br />

user of TKO 137 should be alerted on the land use<br />

constraint in respect of fuel usage prior to starting<br />

any ER/EIA process.<br />

Noted.<br />

APH Consultants<br />

Appendix Do


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(5) Table 9.5, Air Quality, Particulars, compliance<br />

monitoring<br />

As the 24 hours AQO for TSP is not to be exceeded<br />

more than once per year, it is desirable to set the<br />

action level below the 24-hour TSP AQO.<br />

Noted.<br />

(ED<br />

NOISE IMPACTS<br />

(1) Section 1.1- Area 131 development and traffic effect<br />

on WCR.<br />

It is noted that noise impact from preferred dockyard<br />

facilities in Area 131 has not been included in this<br />

DFR. For the noise mitigation measures on Western<br />

Coast Road, it is considered prudent that* the<br />

dockyard related traffic should be taken into<br />

consideration in formulating the required noise<br />

mitigation measures. Could the Consultants con Arm<br />

whether such traffic have been considered <br />

The traffic generated by a possible four floating drydocks in<br />

Area 131 has been included in the assessment. Consideration<br />

of the noise generated by the development itself is beyond the<br />

scope of the Brief.<br />

(2)<br />

Section 8.6.1 - Noise impact from Western Coast<br />

Road<br />

We concur with the noise impact assessment<br />

contained in this Section 8.6.1. It Is therefore vital<br />

that ail recommended noise mitigation measures in<br />

connection with Option B which include opentextured<br />

road surface, semi-road enclosures and full<br />

road enclosures shown in Figure 8.4 must be<br />

incorporated and in place before the operation of the<br />

road in order to realize a reasonable landuse<br />

redevelopment arrangement contiguous to the<br />

Western Coast Road. Relevant departments such as<br />

Highway, Transport and Housing should be advised<br />

of the recommendation and agreement in principle<br />

sought for the sake of a coherent planning allowing<br />

busy roads to run near noise sensitive residential<br />

buildings. Fine-tuning of road alignment to precisely<br />

determine the extent of noise mitigation measures is<br />

appreciated. However, it is unlikely that the<br />

recommended form of noise mitigation measures<br />

could be substantially changed.<br />

Noted.<br />

(3)<br />

Section 9.5.3<br />

137<br />

Operation noise impact from Area<br />

The para, does not indicate whether further operation<br />

noise from Area 137 will be of concern. On the<br />

basis of landuse arrangement shown in Figure 3.4 t<br />

the Consultants must be able 10 quantify noise from<br />

the proposed storage operations. A statement<br />

advising further operators to comply with the<br />

guidelines contained in the HKPSG is tar from<br />

satisfactory.<br />

The worst-affected sensitive receivers are located at Siu Sai<br />

Wan, about 13 km from the boundary of *Vrea 137.<br />

According to HKSPG the day-dune and night-time criteria<br />

for operational noise are 60 dB(A) and 50dB(A) respectively.<br />

To achieve this leyei at the SRs at Siu Sai Wan the Area 137<br />

boundary sound power levels, for all of the noise sources<br />

should not exceed 129 (day-time) and 119 dB(A) (night-time).<br />

It is considered that these site boundary sound power levels<br />

would not be exceeded by the operation of Area 137.<br />

However simple measures such as factory and building<br />

orientation, etc. should be used to minimise noise levels at<br />

the site boundary.<br />

APH Consultants Appendix D-6


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(4) Section 9.5.4 - Construction noise impact<br />

It is noted that noise assessment was based on the<br />

anticipated numbers and types of PME shown in<br />

Tables 8.15 and 8.16 of the Preferred Concepts<br />

report. The question is whether the same numbers of<br />

PME will be operational within the restricted hours.<br />

Given the many kinds of activities in Table 9.4 that<br />

will exceed the nighttime NCO statutory noise level,<br />

I would prefer the Consultants to realistically review<br />

the numbers of PME likely to operate during<br />

restricted hours and adjust the predicted noise levels<br />

at the sensitive uses.<br />

At present insufficient details regarding the construction<br />

method and plant to be used are known. It is recommended<br />

that during the detailed design/tender stage, specific<br />

proposals will be made by the Contractors which will be<br />

examined for compliance.<br />

It is also necessary to distinguish between "daytime"<br />

of the restricted hours under the definition of the<br />

NCO and the general daytime of weekdays.<br />

Although there is not statutory noise limit on general<br />

daytime of weekdays, it is now a practice that a 75<br />

Db(A) Leq(30min) from the related construction<br />

alone (or 10dB(A) excess of the L90 at rural setting<br />

receiver) should not be exceeded at a receiver. The<br />

Consultants may like to incorporate the limit for the<br />

purpose of subsequent monitoring use at Chai Wan.<br />

(5) Table 9.5<br />

Following the comment on daytime within restricted<br />

hours/weekdays, it is obvious that amendments to the<br />

contents under respective columns of "Objective",<br />

"Standard" and "Frequency/Timing" are required.<br />

Target levels within the restricted hours are ANLs<br />

and not ANL-lO suggested in the footnote. Trigger<br />

and action levels are normally below the target level.<br />

However, it is reported that sometimes It is<br />

impractical to set the levels lower than the ANL due<br />

to enforcement difficulties. Instead, trigger is set<br />

against ONE complaint received and action is set<br />

against more than ONE complaint received from the<br />

construction concerned. Should measured noise<br />

levels initiated by "trigger" exceed the "target",<br />

mitigation will be provided. On the contrary, step<br />

up/frequent noise monitoring will be provided under<br />

the requirement of "action".<br />

Noted, these tables will be amended for the final report.<br />

OT><br />

WATER QUALITY IMPACTS<br />

(1) Section 5.9.4<br />

Since there is only preliminary treatment at the<br />

existing TKO STW, is the primary treatment a new<br />

proposal by the Consultants <br />

Agreed, text will be amended.<br />

09 Section 9.3.3 - Impact on Tung Lung Chau FCZ<br />

It is said in the report that the worst case scenario<br />

will give a suspended solids concentration of 1.6<br />

mg/l. We think this is not necessarily the worst case<br />

because the calculations previously submitted by the<br />

Consultants showed that a value of 4 - 5 mg/l may be<br />

reached under the assumptions. Nevertheless, both<br />

figures exceed the 30% increase in WQO.<br />

Some early working notes were provided prior to a proposed<br />

meeting for the purpose of speeding up the consultation<br />

process which should not now be treated as 4 formal<br />

submission of calculations. The Eastern Buffer WCZ in<br />

which the Tung Lung Chau FCZ is situated had suspended<br />

solids concentrations for 1990 in the range of 0.67mg/i to<br />

12mgA with an average of 3 Jmg/L The i.6 mg/l is


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

and compliance monitoring and enforcement of Action Plans<br />

win be essential.<br />

(3) Referring to our previous comments on Section 8.4,3<br />

& 8.9.1 of the Preferred Concept Report* the<br />

Consultants do not make clear in this DFR what<br />

dredging methods and field measures will be used to<br />

mitigate the water quality impacts during dredging<br />

and reclamation. Also, no specifications regarding<br />

this requirements of water quality monitoring<br />

programmes for dredging and reclamation are given.<br />

It is understood that grab dredging will be employed. Some<br />

mitigation measures are recommended in the Report for this<br />

method. However it is further recommended that silt<br />

curtains are employed and overflowing of barges is<br />

prohibited. These further recommendations will be included<br />

in the Final Report along with water quality Monitoring<br />

programmes.<br />

(IV)<br />

VISUAL IMPACTS<br />

If the objective of section 9.7 is to assess the visual<br />

impacts of the preferred option then the report has<br />

certainly failed to achieve that.<br />

There is no assessment of any kind on what are the<br />

potential impact and how serious they are, and there<br />

is not even one figure to illustrate the problem.<br />

When responding to our previous comments on the<br />

Preferred Concept Report the Consultants have<br />

agreed that the visual impact is "both significant and<br />

undesirable". Devoting only one page of general<br />

comments in this report doesn't seem to reflect that<br />

kind of assessment.<br />

Section 9.7 is a summary of the longer visual impact section<br />

in the Preferred Concept Report. It does acknowledge that<br />

the development will be visually significant. There is a lack<br />

of detail regarding what the development will ultimately<br />

comprise. However the visual section will be enlarged and<br />

illustrated and the suggested discussions will be undertaken.<br />

Soft landscaping is not the only measure to solve a<br />

visual problem. In fact this is often only used as a<br />

complementary measure. Site formation levels, area<br />

layout, site and plant layout and height restriction are<br />

the things that should be considered first (very<br />

appropriate at this stage), complemented by soft<br />

landscaping with perhaps planting at strategic<br />

locations. It is clear that unless the problem is<br />

tackled at the earliest design stage many of the<br />

options will be gone.<br />

To summarize, it is considered that the visual section<br />

is unacceptable, not even close. A more detailed<br />

assessment should be required. We shall be happy to<br />

discuss with the Consultants if they would contact<br />

our Mr. Simon Hui at S3 5 1105.<br />

(V)<br />

RISK ASSESSMENTS<br />

(I) Section 3.3.8, Pg 3-5<br />

CCPHI has just completed a review of the Interim<br />

Risk Guidelines (IRG) taking into account the<br />

experience in implementing and enforcing the<br />

guidelines. The review recommends that the IRG<br />

should now be finalised, which means that the<br />

individual risk guideline should remain at 1 in<br />

100,000 per year, i.e. 1 x 10* per year. The 1,000<br />

fataliry cut-off limit in the societal risk guideline<br />

should be retained. In addition, an "as low as<br />

reasonably practicable (ALARF)* region in two<br />

orders of magnitude is incorporated in the societal<br />

risk guideline. This is to ensure that ail reasonably<br />

practicable measures which can reduce nsk should be<br />

considered unless the measures are not cost effective.<br />

Noted. Text will be amended.<br />

APR Consultants Appendix D-8


Engineering Feasibility Study of Development of Tseung Kmn 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(2) Section 3.3.9, Pg. 3-5<br />

At its 32nd Meeting held on 24.11.1992, one CCPHI<br />

member pointed out that since the risks reported in<br />

the supplementary information (i.e. the risks<br />

associated with the berthing of vessels) were not<br />

incorporated into the findings of the Working Paper<br />

No. 7, the risk assessment in the WP No. 7 did not<br />

reflect the complete picture. As a follow up action,<br />

PM(SENT) undertook to ask the Consultants to<br />

prepare a further report on the combined effect of the<br />

risk identified in the WP No. 7 as well as those<br />

assessed in the supplementary information note (i.e.<br />

Annex 3 to WP No. 7).<br />

In accord with the comments made and a formal request<br />

from PM(SENT), a combined risk assessment including those<br />

associated with shipping incidents at or dose to the Jetty,<br />

Adke wfll be sought from PM(SENT) as to the extent of<br />

inclusion required in the final Report.<br />

After the Consultants have responded to the issue<br />

raised at the meeting, CCPHI will discuss the case<br />

further at iu next meeting before coming to a<br />

conclusion.<br />

It is noted that the risk associated with the shipment<br />

of hazardous substances approaching the jetties has<br />

not been addressed in the Draft Final Report and<br />

therefore further clarification is required from the<br />

Consultants in this aspect.<br />

(VI)<br />

WASTE MANAGEMENT<br />

(1) Section 5.4<br />

The Consultants identified a number of possible<br />

additional fill resources for the captioned project.<br />

However, no preferred option is specified. It should<br />

be noted that the options of screened construction<br />

waste or public dumping will fall in line with our<br />

current waste management policy and are therefore<br />

preferred from the environmental point of view.<br />

The preference for screened construction waste/public<br />

dumping is noted.<br />

(2) Section 9.6.1<br />

"Waste Management Plan": in the third line of this<br />

paragraph should read "Waste Disposal Plan".<br />

Noted. The text will be amended accordingly.<br />

(3) Section 9.6.2<br />

Instead of leaving the problem until the specific<br />

industries are known, the Consultants should take a<br />

more positive approach to discuss the MARPOL<br />

Waste management strategy in terms of, for example,<br />

the different possible scenarios of MARPOL Waste<br />

arising in the area and the capacity of the CWTF to<br />

handle such waste, etc.<br />

Further detail with regard to waste management is contained<br />

in the Preferred Concept Report. The CWTF is designed to<br />

treat likely wastes arising. While the capacity of the CWTF<br />

is known the available capacity to treat waste when Area 137<br />

becomes operational is unknown and depends on how well<br />

the CWTF is used by various industries.<br />

(VH)<br />

SENT LANDFILL INTERFACE<br />

(1) Section 2.3.2, 1st and 2nd paragraphs<br />

The description of SENT landfill and Advance<br />

Works Contract is not entirely accurate. Our<br />

previous comments on the corresponding sections in<br />

Working Paper No. 4 and die Alternative Concepts<br />

Report have not been adopted.<br />

Noted. Text will b« amended.<br />

APH Consultants Appendix D-9


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(2) Section 2.3.4, 3rd paragraph<br />

The construction programme of Road D6 is<br />

inaccurate. I suggest this paragraph be re-written as<br />

follows :<br />

Noted. The text will be amended accordingly.<br />

"Road D6 will be constructed initially to a<br />

roundabout in the north of the TKODE to provide<br />

access to the industrial estate. A stub will be<br />

provided from which temporary access to the<br />

adjacent SENT Landfill site will be provided. The<br />

present proposals as regards the southern extension<br />

of D6 are that the section of road reserve between<br />

TKQIE and SENT Landfill up to and including the<br />

tip of Fat Tong Chau will be handed over to the<br />

SENT Landfill contractor as working areas once<br />

TKOffi contract works in the area are complete,<br />

anticipated to be early 1995.<br />

(2) Section 2.3.4, 3rd paragraph ... cont'd<br />

The landfill contractor will then complete the<br />

formation of this section of Road D6 and hand the<br />

area back to Territory Development Department for<br />

the construction of road within 11 months or receipt<br />

of notice. Completion of the D6 extension to the<br />

south of Area 137 would therefore be anticipated by<br />

mid 1997."<br />

(3) Section 10.3.2, 3rd paragraph<br />

Regarding the consideration of constraints, it should<br />

be noted that the section of road reserve to be handed<br />

over byTKOGE to SENT Landfill contractor by early<br />

1995 will not yet be formed. PM(SENT) previously<br />

agreed that the SENT Landfill contractor will be<br />

given 12 months* possession of this section to<br />

excavate Fat Tong Chau and carry out the road<br />

formation work.<br />

Noted.<br />

(4) Section 10.3.5, 3rd paragraph, Initial Works<br />

The proposed joint use of the Road D6 reserve seems<br />

not feasible. The whole of the reserve will not be<br />

handed over to EPD until early 1995. In mid-1995,<br />

site formation work at the reserve will still be in<br />

progress. It is not desirable and may not be<br />

practicable, to allow traffic to pass through the<br />

unformed reserve, I must reiterate my previous<br />

comments regarding seeking permission from the<br />

HKIEC to allow the Area 137 construction trarfic to<br />

gain access through the TKOIE area, which seems<br />

not to have been taken up by the consultants.<br />

As a result of further discussions with PM(SENT), the<br />

combined use of the Road 06 reserve will not be considered<br />

further.<br />

(5) Hg. 4.1 & similar<br />

The SENT Landfill barging point will be used by 3<br />

separate parties and each of them will require a 50-<br />

metre wide working area behind the seawall.<br />

Independent access to each of the 3 users should be<br />

provided.<br />

The layout of the reprovisioned access facilities is ia<br />

accordance with previously advised requirements. We<br />

consider that the internal layout of this area is a matter for<br />

the SENT Landfill operator to resolve.<br />

APH Consultants Appendix D~10


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(Vffl) ENVIRONMENTAL MONITORING &<br />

AUDITING<br />

General<br />

(1) The Consultants should provide sufficient directions<br />

and recommendations on how the project<br />

Environmental Monitoring and Audit (EM&A)<br />

Manual is to be prepared and should include, inter<br />

alia, the following :<br />

Noted; the text will be amended to cover these new<br />

requirements.<br />

(a)<br />

(b)<br />

(c)<br />

The Project Proponent should be required<br />

to prepare an EM&A Manual. The<br />

Manual is an important management tool<br />

to follow up the environmental issues of<br />

the ftjture construction contract, and the<br />

recommendations of the EIA study, etc.<br />

The Manual should be designed to<br />

provide guidance to environmental site<br />

staff to undertake the EM&A works.<br />

These staff should be independent from<br />

the Contractor.<br />

Environmental monitoring equipment for<br />

the project works should be provided by<br />

the project proponent/Engineer, with<br />

availability on award of contract to<br />

enable, inter alia, recovery of<br />

baseline/backgroundmonitoring data prior<br />

to the commencement of construction<br />

works. Experiences with the Airport<br />

Core Projects revealed that to ensure the<br />

timely implementation of the monitoring<br />

works, under no account should the<br />

construction contractor be made<br />

responsible for the purchase of<br />

equipment.<br />

The EM&A Manual should be submitted<br />

to DEP one month after commencement<br />

of the Contract, in advance of the<br />

commencement of baseline monitoring.<br />

(d) Monthly EM&A reports should be<br />

submitted after submission of the EM&A<br />

Manual, and the recovery and reporting<br />

of baseline data. The first report should<br />

preferably be submitted one month after<br />

the commencement of construction works.<br />

(e)<br />

The timings are for guidance only, but it<br />

is important that the relative timings<br />

between the submission of the EM&A<br />

Manual, the commencement of baseline<br />

monitoring, the commencement of works<br />

and submission of the list monthly<br />

EM&A report are compiled with.<br />

Notwithstanding the above, consideration<br />

should be given to the recovery of<br />

baseline data pnor to the award of<br />

contract to enable the recovery of more<br />

representative baseline conditions.<br />

Appendices which provide guideline in<br />

the following areas are attached :<br />

AfH Consultants<br />

Appendix D-ll


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Guidelines -<br />

Definition<br />

forEM&A -<br />

EM&A Manual<br />

Format - Appendix<br />

A<br />

EM&A Monthly<br />

Report Format -<br />

Appendix B<br />

Monitoring Data<br />

Report Format -<br />

Appendix C<br />

Appendix D<br />

(2) In addition to providing details of site management,<br />

project programme and environmental protection<br />

requirements in contract documents, land lease and<br />

engineering conditions, etc. the Manual should<br />

provide, inter alia, guidance/instruction to resident<br />

environmental site staff on EM&A procedures and<br />

protocols with respect to the following area :<br />

(a)<br />

(D)<br />

(c)<br />

(d)<br />

(e)<br />

(f)<br />

(g)<br />

the construction programme and the<br />

required EM&A programmes to assess the<br />

environmental impacts at Tseung Kwan O<br />

Area 137 with time;<br />

the location, frequency and type of<br />

environmental monitoring and audit<br />

requirements to assess environmental<br />

impacts of the construction;<br />

the form/content of event/action plans<br />

(including any emergency plans) tor air<br />

and water quality, and noise impacts;<br />

review of pollution sources and working<br />

practices/procedures required in the event<br />

of environmental pollution levels being<br />

exceeded;<br />

the content/presentation of monitoring<br />

data, their audit, and actions taken with<br />

respect of non-compliance with<br />

environmental pollution levels;<br />

appropriate report formats/frequency of<br />

submission/special event report, ate.;<br />

complaints/consultation procedures;<br />

(h) equipment service/calibration<br />

requirements;<br />

(5) sensitive receiver locations,<br />

(3) The concept of event/action plans should be<br />

developed (and tabulated), including the<br />

aiscrimination of the responses (trigger/action/target<br />

levels) required for increasing pollution levels.<br />

Staged implementation of remedial measures is seen<br />

as a means to avoid as far as possible senous<br />

deterioration of snvironmentai quality to the point<br />

where conflicts may arise between the Project<br />

Engineer (Client) and the Contractor,<br />

APH Consultants Appendix D-12


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(4) Careful consideration should be given to the timing<br />

of submission of the EM&A Manual and EM


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

GOVERNMENT SECRETARIAT - ECONOMIC SERVICES BRANCH<br />

Section 10<br />

On "Implementation Programme I", would the consultants please<br />

clarify what they mean by "Government funding" I presume<br />

that the land lot* for deep waterfront industriei (DWI) and<br />

potentially hazardous installations (PHI) will still have to be<br />

disposed in the free market and hence they will fetch full market<br />

values. I understand that this can be achieved without much<br />

difficulties because, according to this study, the demand for PHI<br />

sites and, to a lesser extent, DWI sites in Hong Kong is strong.<br />

Also related to implementation, I think the discount rate used by<br />

the consultants, at 2.5% in real terms, is on the low side.<br />

Normally we use 4% for Government projects.<br />

"Government funding** refers to Government funding or<br />

financing the development of the site leading to disposal of<br />

lots* rather than this role being taken by a developer.<br />

We have been recently asked by a Government Department<br />

to adopt a test discount rate of 2.5%. However, the figures<br />

will be reworked at 4%.<br />

GOVERNMENT SECRETARIAT - TRANSPORT BRANCH<br />

GO<br />

Cm)<br />

(YD<br />

(vii)<br />

Para. 2,2.1 - there are a few mis-typings of "OOP"<br />

asOPD".<br />

Para. 7.2.3 - regarding the suggested toll increase for<br />

TKO Tunnel, what shall be the fare level required to<br />

achieve a more rational traffic distribution among the<br />

external road links <br />

Para. 7.2.4 - what is the original level of selfcontainment<br />

assumed <br />

Para. 7.2 - why is it that Po Lam Road will have a<br />

reduced traffic volume for a higher population <br />

Farm. 7.29 - among the scenarios proposed, it is not<br />

understood why for the same population level, a<br />

reduction in Metroplan employment will allow an<br />

increase in industrial employment. Apparently, high<br />

Metropian employment for the same population<br />

should reduce external traffic needs thus giving way<br />

to more industrial developments. Furthermore, if as<br />

stated in the Use paragraph that the growth level at<br />

2011 should be maintained at 2006 levels for no<br />

MTR/WCR* then how can the additional scenarios<br />

39-312 be possible <br />

As a related issued to (v) above, could the traffic<br />

impact within the Area of Influence be addressed for<br />

the no MTR/WCR scenario;<br />

Pan. S.6.I - has it been confirmed with FSD that a<br />

gap width of 10m is adequate to allow each section<br />

of complete enclosure be considered as a separate<br />

entity <br />

Noted. Text wiU be amended.<br />

The toll assumed for the traffic forecasts was $3 in 1990<br />

prices. The more rational traffic distribution would be<br />

achieved at a toll level between this and a doubling of the<br />

toll. The traffic analysis indicates that almost a doubling of<br />

the toll would be required. However, recent research from<br />

the Travel Characteristics Survey has indicated attitudes to<br />

travel demand conditions, which if correct would mean the<br />

balance would be achieved at a lower increase over the base<br />

figure.<br />

There are several alternative ways of defining selfcontainment*<br />

The definition adopted for this Study takes the<br />

proportion of trios which have both origin and destination<br />

within the Study Area. This can be seen to be 31% from<br />

Table 7.6<br />

This is a typing error which will be corrected.<br />

The scenarios show alternative methods of arranging landuse<br />

developments within the transport capacity budget. The<br />

Metroplan employment is "swapped' with the industrial<br />

employment under different scenarios.<br />

B9-B12 were designed to illustrate the extra scenarios for<br />

2011 if the population development went ahead as planned<br />

beyond 2006. In this case, there would be a reduction in<br />

employment from the 2006 scenarios, which logically would<br />

imply that the employment levels reached in 2006 should not<br />

be planned for at that time.<br />

This is outside the scope of the Brief.<br />

FSD were contacted prior to the submission of the report*<br />

Subsequently no comment has been received on the<br />

unaccepubflity of the gap from FSD.<br />

APR Consultants<br />

Appendix D-14


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(viii)<br />

Para. 8.8 - Since it ia concluded that none of the two<br />

alignments are considered optimum, it would be<br />

useful to list out the impacts that need to be<br />

addressed in any further studies.<br />

It is considered that the present Brief ade


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Please clarify how the 40m of buffer distance should<br />

be measured between the portaJ and the SR. Please<br />

delete the sentence of "It is understood that this is<br />

not in line with Housing Department planning*, as<br />

the layout plans for both Yau Tong Estate and Ko<br />

Chiu Road Estate Ph. 3 are yet to be determined.<br />

However, the proposed buffer distance may affect the<br />

design of the layout plans and reduce the<br />

development potential of the site.<br />

Para S.7 Please include a table showing the detail breakdown<br />

of the costs for both options as in Table 6.17 and<br />

Table 6.18 of the Working Paper No. 9A.<br />

The buffer distance should be measured from the nearest<br />

edge of the end of the enclosure.<br />

Sentence will be deleted.<br />

Agreed. The cost breakdown as presented in Working Paper<br />

No. 9A wffl be included.<br />

HONG KONG INDUSTRIAL ESTATES CORPORATION<br />

Section 5.93<br />

No provision has been made in the TKOIE sewers to<br />

accept any flows from Area 137, even on a<br />

temporary basis. Details have to be submitted to<br />

DSD and HKEEC for consideration.<br />

The temporary pumped flows from Area 137 to the TKOIE<br />

sewer system wifl be less than 1% of capacity and therefore<br />

may be treated as insignificant. Your comment regarding<br />

the submission of details would be taken up at the Detailed<br />

Design.<br />

Section 103.4<br />

It would be useful to factories on our industrial estate<br />

if they have access to the berthing facilities and<br />

possibly a pipeline for conveying liquid feedstock<br />

from the pier through your Sites 39 and 31 to the<br />

TKOIE. We would like to explore this further with<br />

the further 'Area 137 developer".<br />

Noted. This can be explored further at the Detailed Design.<br />

Section 10.4.1<br />

The expenditure forecast should not concern us but<br />

we wish to suggest that the interest component<br />

(which is missing in the forecast) may be quite<br />

significant whereas the land premium will be affected<br />

by many factors.<br />

Agreed, interest payments will be significant, however this is<br />

reflected in the selection of the test discount rate.<br />

MARINE DEPARTMENT<br />

Para 6*3.3 - The preceding paragraph states that<br />

vessels will berth "bow-in"* but there is concern as to<br />

whether this is practicable for ballasted arrivals on<br />

flood tide and with southerly wind as stated at the<br />

top of page 6-5. It is felt that under such conditions<br />

a "portside to* berthing would be more practicable.<br />

Text will be amended as suggested.<br />

It is acknowledged that the various ship manoeuvres<br />

have been carried out on a simulator. However, as<br />

the H,K. Pilot's Association are a private<br />

independent body they are not participants in the<br />

consultancy process and would most likely have their<br />

own independent comments. I suggest to insert a<br />

sentence to the sffeci that "It is accepted that<br />

discussions with the H.K. Pilot's Association will be<br />

necessary to establish berthing procedures and<br />

criteria for the specific berths dependent on the type<br />

and size of vessels using such facilities".<br />

APH Consultants Appendix D~16


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

ii)<br />

iii)<br />

iv)<br />

Para 6.7.2 - it is felt that the current DGA south of<br />

Lamma is too far removed from this TKO area. To<br />

reduce crossing traffic situations consultants should<br />

propose the establishment of a new DGA in the<br />

vicinity, possibly between Tung Lung Chau and the<br />

Ninepins;<br />

Para 6.7.3 - referring to the second sub-para., whilst<br />

this would be the preferred scenario, reference<br />

should be made to the fact that currently this is NOT<br />

done in H.K. and Immigration Department have<br />

expressed concern on their resource limitations to<br />

enaole them to carry out such duties;<br />

and<br />

Para 6.8.2 - Recent developments have indicated that<br />

MD will probably lose the facilities currently<br />

provided by the ASDE radar at Kai Tak. The<br />

establishment of a replacement and the timing and<br />

siting of this new facility have yet to be finalised.<br />

Until such details are available it may be optimistic<br />

to state that VTS will be able to monitor all marine<br />

traffic. I suggest a proviso that further consultation<br />

will be necessary with MD to determine the future<br />

marine traffic levels and capability of the VTS at the<br />

time the TKO development is scheduled to be<br />

implemented.<br />

Whflst acknowledging the validity of your comment on<br />

crossing traffic, we consider likely usage of a aew DGA does<br />

not warrant its creation. However, we propose to introduce<br />

to the text that the situation should be monitored and if<br />

required an additional DGA should be created as suggested<br />

in your comment.<br />

Text wfll be amended to include reference as suggested.<br />

Additional comment will be included as suggested.<br />

PLANNING DEPARTMENT<br />

Executive gammarv ri -..<br />

Concept Plan<br />

Section on Preferred<br />

I suggest that the land use budget shown in Table 3.3<br />

of the Draft Final Report be incorporated in the text<br />

of the Executive Summary so as to make it clearer<br />

why the current layout plan proposed to reserve a<br />

total of 22.29ha for DWI, which is roughly the same<br />

as that recommended in the Preferred Concept,<br />

instead of the initial suggestion of 60ha.<br />

Figure I in the Executive Summary and Figure 2.1<br />

in the Draft Final Report should also be updated to<br />

incorporate the recommendedlayout for the dockyard<br />

in Area 131 as shown in Figure 3,3 in the Draft<br />

Final Report to eliminate possible confusion.<br />

Agreed. Text will be amended to incorporate comment.<br />

Layout depicted in Figure 1/2.1 shows the Study Area land<br />

use as covered by the TKO OOP and is part of the Brief for<br />

the Study. PM(SENT) will be requested to confirm the<br />

suitability of amendment of this Figure.<br />

Draft Final Report<br />

Section 4 J<br />

I presume that the measurements of site area quoted<br />

tn this section are only rough figures in hectare<br />

rather than actual measurements. In this respect, I<br />

suggest the figures on GFA should also be rounded<br />

up to hundredth to maintain consistency.<br />

The measurements are actual. However, at your suggestion<br />

GFA figures will be rounded.<br />

APR Consultants<br />

Appendix D-L7


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Table 4.1<br />

Table 4.1 lays down the measurements of all land<br />

use parcels for Area 137. As the berth is also one of<br />

land uses, I suggest that the length and depth of both<br />

the deep water and protected berths should also be<br />

included in this table.<br />

Reference win he added to the text regarding the extent of<br />

seawall provided. However, the extent of berthing provided<br />

should be regarded as indicative based on potential user<br />

requirements. This is likely to be modified with regard to<br />

ultimate user requirements.<br />

Table 7.8 and 7.12<br />

Table 7.8 shows the predicted flows on the roads at<br />

the western screeniine for the am peak bour which is<br />

the critical hour of the day. They are the base case<br />

flows with which other case flows are compared, as<br />

can be seen from Tables 7.10, 7.11 and 7.13.<br />

However, the base case flows in Table 7.12 are<br />

different from those shown in Table 7.8. Can some<br />

explanations be given <br />

The Base Figures shown in Table 7.12 refer to previous<br />

model runs which are now replaced. The table will be<br />

amended.<br />

Para 7 J .7<br />

It is not realistic to assume an increase of about<br />

100,000 residents in TKO without any increase in<br />

population related jobs for the purpose of the<br />

sensitivity test. The increase of 15,000 industrial<br />

jobs is barely population related and hence cannot<br />

provide supporting services to the additional 100,000<br />

residents.<br />

It is agreed that an increase in population would bring some<br />

additional service jobs to TKO. However the extent of such<br />

jobs is a matter of discussion. This test was developed to<br />

illustrate the worst case of higher population without seeking<br />

to discuss employment. It should be noted that the test<br />

results and assumptions were presented in WP$.<br />

Para. 7.2.8<br />

Table 7.14 in this para, appears to show that without<br />

the Area 137 development, the total flow on each of<br />

the roads would be respectively reduced. In reality,<br />

this is not the case because increase in traffic due to<br />

the Area 137 development could displace traffic due<br />

to other departments. To address the impact of the<br />

Area 137 development, it is more realistic to<br />

compare the flows without the development with the<br />

flows with the development.<br />

The figures shown in Table 7.14 have been taken from the<br />

comparison of traffic flows with and without the Area 137<br />

development, as suggested by the Comment. These<br />

assignments take account of the presence of other movements<br />

and allow for the displacement of traffic, also as suggested<br />

in the Comment.<br />

Table 7.16<br />

The figures in Table 7.16 appear to imply some<br />

unrealistic assumptions as follows :<br />

a. The traffic generations of the additional<br />

industrial developments are assumed to<br />

remain constant over time while the CTS<br />

Model assumes that traffic generations<br />

will increase as GDP grows, though not<br />

entirely in line with ihe GDP growth.<br />

These two assumptions are not consistent.<br />

b. The extra bus flow due to deletion of the<br />

MTR is assumed to be 600 pcu/hr in both<br />

2006 and 2011 while the population is<br />

assumed to vary from 243,000 in 2006 to<br />

333,000 in 20 U. Please clarify the logic<br />

behind these two assumptions.<br />

The methodology follows the standard traffic impact<br />

approach of measuring trip rates at specific existing land use<br />

sites, and applying the rates to the new industrial<br />

developments in TKO. These rates have neither been<br />

reduced to reflect restraint nor increased to reflect GDP.<br />

The CTS estimates of goods vehicles are produced in an<br />

entirely different manner, not appropriate for the specific<br />

areas of interest to this Study; it has been used to indicate<br />

the background traffic flows.<br />

The calculations are based on 2011 with an occupancy of 170<br />

per vehicle. The same number of buses has been assumed<br />

for 2006 where population is 25% lower as in practice bus<br />

frequencies are not so rapidly changed in direct response to<br />

traffic demand. The figures imply a lower occupancy of<br />

around 125 in 2006. The alternative approach of reducing<br />

die number of buses would give a saving of about 150 pens,<br />

which is about 1.5%, of the screeniine flows and well within<br />

the margin of error.<br />

AfH Consultants Appendix D-18


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Para 7 JS.9<br />

If the proposed industrial developments have not<br />

been included in Metroplan, they cannot be regarded<br />

as developments to fulfil any identified need. On the<br />

odier hand, the population and employment<br />

anticipated by Metroplan for 2001 can be regarded as<br />

committed. As such the proposed industrial<br />

developments should be treated as a floating quantum<br />

to be addressed in the context of the TDS Review.<br />

It should be noted that both the MTR and WCR are<br />

not assumed as committed in the TDS Review. Your<br />

views and proposals should have regard to this<br />

assumption.<br />

The ranking of priority between Metroplan employment and<br />

development of Area 137 is a matter of policy. The traffic<br />

analysis can only examine the scenarios required to satisfy<br />

the Brief and any additional instruction to the Consultants as<br />

conveyed through the Working and Steering Groups.<br />

Para 7.2.10<br />

(a)<br />

(b)<br />

(c)<br />

At the end of the first sentence on the<br />

first main finding, an *If clause" should<br />

be added as follows :<br />

"The Western Coast Road ... overloaded<br />

TKO Tunnel, if the proposed additional<br />

industrial developments are implemented<br />

by. 2001".<br />

As it stands, the first main finding<br />

appears to suggest that the requirement of<br />

the WCR by 2001 is not directly caused<br />

by the proposed additional industrial<br />

developments, which is not correct. This<br />

is apparent from the figures shown in<br />

Table 7.16.<br />

The third main finding could not be<br />

agreed with. It is clear from the figures<br />

in Table 7.16 that provision of the WCR<br />

by 2001 or earlier is caused by the<br />

proposed additional industrial<br />

developments but not possibly by any<br />

change in self containment, A change in<br />

self containment would have impact on<br />

both the external and internal road<br />

network. The impact on the external<br />

roads has been shown to be small by the<br />

Consultants, but that on the internal road<br />

network, under the assumption of a<br />

greater self containment, has not yet been<br />

assessed. It is important to ensure that<br />

the internal road network would work<br />

with adequate capacity under the greater<br />

self containment assumption which could<br />

materialise when trips are forced to be<br />

made within the town due to congestion at<br />

the external roads.<br />

The forth main finding is generally true.<br />

It should however be expanded to indicate<br />

what measures should be taken if the<br />

MTR is not provided, in order to make it<br />

meaningful and useful.<br />

The major traffic generator is the TKOIE. Therefore the<br />

amendment should refer tc "all proposed 1 * developments. If<br />

Area 137 is constructed and TKO IE development is deferred<br />

then WCR may also be deferred for a few years depending<br />

on the revised time scale of TKOIE. The development<br />

phasing of the TKOIE is the major factor.<br />

Noted. It is considered that the finding is valid for a<br />

reduction is self-containment.<br />

The report has indicated the areas which ae«d further<br />

analyses. However the majority of the comment would<br />

require the consultants to address comments outside the<br />

Brief.<br />

APH Consultants<br />

Appendix D-19


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(d)<br />

On the sixth main finding, any conclusion<br />

drawn or proposal made relating to a<br />

population of 440,000 in TKO are<br />

considered premature as the population<br />

figure was considered to be the maximum<br />

design capacity under the TKO Outline<br />

Development Plan which may not be<br />

attainable without the corresponding<br />

upgrading of transport link.<br />

Noted. HoweTer the consultant has been requested to<br />

comment on the population level.<br />

(e)<br />

Section 73<br />

The recommendation in the last main<br />

finding is not supported. If the WCR is<br />

delayed/not provided, the proposed<br />

additional industrial developments should<br />

not be permitted or reduced to a level<br />

appropriate to the capacities of the<br />

external and internal road networks.<br />

It is difficult to check the capacities of the junctions<br />

within the internal road networks, because the<br />

junction flows and layouts are not given. I trust that<br />

TD would check the capacities of the junctions to<br />

ensure that they would work with adequate<br />

capacities.<br />

This is a policy issue* However the consultants have an<br />

obligation to point out the advantages of the Area 137<br />

development compared with other plans for TKO. The site<br />

offers water-front access whkh is a limited resource in the<br />

Territory; also there are prospective developers for the<br />

TKO IE. Also to be taken into account is the findings of the<br />

recent Travel Characteristics Survey that employment<br />

development in the New Towns is lagging behind the<br />

scheduled plans. It is dearly possible that these<br />

developments wifl go ahead as opposed to the more general<br />

employment development embodied in Metro plan for other<br />

sites in TKO.<br />

Noted. These have been supplied to Transport Department<br />

in December 1992.<br />

Section S.4<br />

The marginal improvement on traffic flows shown in<br />

Table S.I cannot provide sufficient evidence to<br />

conclude that Option S is better than Option A. It is<br />

difficult to explain why traffic flows at TKO Tunnel<br />

and the WCR should differ between Options A and<br />

B, since accessibility to/from the WCR would be<br />

similar for both options, when the road network in<br />

Yau Tong is unbiasedly improved as required<br />

differently by each of the options. As the Lei Yue<br />

Mun Road/WCR Connector would diverge from the<br />

WCR earlier, Option A would appear to be better in<br />

case accidents occur on the section of the WCR<br />

between both diverge points defined by both options.<br />

Having regard to the above, it is considered that in<br />

transport terms, Option B is as good (or bad) as<br />

Option A.<br />

I would like 10 see somewhere in Chapter 7 your<br />

recommended population thresholds for TKO with :<br />

(a) the existing external roads<br />

(b) (a) plus iMTR<br />

(c) (a) plus the WCR and<br />

(d) Ob) plus the WCR<br />

Section 8,4 concludes that the improvement in traffic flows<br />

is marginal, yet there is a preference for Option B. The<br />

preference arises from other items of the evaluation* in<br />

particular the consideration of environmental issues. The<br />

discussion on accident location should equally be applied to<br />

both Option A and 3, although the issue of accidents is not<br />

normally applied to highway evaluation in the form<br />

contained in the comment.<br />

These alternatives are presented in Section 7X9. The results<br />

wilt be summarised into a separate table with the suggested<br />

format.<br />

APR Consultants<br />

Appendix


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

PLANNING DEPARTMENT - DISTRICT PLANNING QFFTCE/KOWLQQN<br />

Chapter 8 - Western Coast Road<br />

(a) Para 3.5.1<br />

Please be suggested to amend the second sentence as<br />

'•Option A requires utilizing land reserved for<br />

the proposed Lei Yue Mun Supplementary Housing<br />

Scheme *<br />

Amendments will be undertaken as suggested*<br />

(b)<br />

Para 8.5.3 (Yau Tong Road Link to Lei Yue Mun<br />

Road)<br />

The development potential of the proposed East<br />

Kowioon Hospital will also be affected as the site<br />

area will be largely reduced for the construction of<br />

the Western Coast Road.<br />

Noted. This would be true if self protective building designs<br />

were not adopted.<br />

(c) Para 8.5.4<br />

Please note that for existing land uses, Option B<br />

impinges not only on the Po Chiu College, but also<br />

on the St. Antonius Primary School. For planned<br />

[and uses. Option B will also encroach on the Yau<br />

Tong Bay Redevelopment.<br />

Option B would abut the embankment below the Primary<br />

School. Both Options would encroach on the proposed Yau<br />

Tong Bay Redevelopment. Text win be augmented to reflect<br />

this impact.<br />

(d) Para 8.7<br />

Other than the demolition of 2 industrial buildings,<br />

there is a doubt on why the cost comparison of both<br />

the 2 options does not include the resumption costs<br />

of some of the Yau Tong Marine Lots upon which<br />

would be encroached by the Western Coast Road.<br />

Should the reprovisioning cost of the Lei Yue Mun<br />

Supplementary Housing Site be included into the cost<br />

comparison analysis, there would be no reasons to<br />

exclude the reprovisioning costs of part of the<br />

proposed East Kowioon Hospital site, Yau Tong Bay<br />

Redevelopment, fire station as well as the two<br />

affected schools that would be affected by the<br />

Western Coast Road from the cost comparison.<br />

In view of this partial comparison, I have reservation<br />

on the concluding statement that "Option B is thus<br />

shown to be the more cost effective option*.<br />

Resumption costs should not be payable in the event the<br />

present lots are rezoned for the proposed Yau Tong Bay<br />

Redevelopment. See Section $.5.2. Whilst a reduction in<br />

premiums would result from the land taken for road<br />

construction, this would be similar for both Options.<br />

Government Departments were, as noted, requested for these<br />

inputs in this regard. Those received were incorporated into<br />

the evaluation equation.<br />

On the basis of comparative costs and information received<br />

Option B was shown to be the most cost effective option.<br />

APH Consultants Appendix D-21


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Find Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

PLANNING DEPARTMENT - DISTRICT PLANNING OFFICE/SAI KUNG AND TSEUNG KWAN O<br />

General<br />

! havereservationon the method of determining the<br />

proposed landuse solely by surveys of the demand<br />

for DWIs and PHIs. There is no prima facie why all<br />

PHI demands should be met within the Hong Kong<br />

Territory. Afterall, Hong Kong is much more<br />

densely populated than its neighbouring territory; and<br />

as such, more vulnerable to potential disasters,<br />

however slight its chance of happening may be.<br />

From district planning point of view, priority should<br />

be given to those existing PHIs in more populous<br />

areas within other parts of the Territory (e.g. the gas<br />

works in To Kwa Wan) to be relocated to Area 137.<br />

Introduction of new PHIs should be exercised with<br />

The author may not be too familiar with the planning<br />

system in Hong Kong. Section 2.2.3, for instance,<br />

describes the purpose of the OZP as "to revise and<br />

update the OOP", which is in fact not the case. The<br />

statement in the same paragraph: The time scale for<br />

02 circulation and approval will most likely allow<br />

for the incorporation of the enclosed<br />

recommendations of this Study" is also an unfounded<br />

assertion. The Consultant is probably unaware of the<br />

fact that the TKO OZP S/TKO/l adopted by RNTPC<br />

of TPB on 4.9.92 was gazetted on 11.12,92.<br />

The validity of the comment is noted. However, the Study<br />

Brief requires the identification of PHI and DWI operators<br />

with an interest in locating in Area 137 and to ensure that<br />

such users are eniironmentafly acceptable. Major emphasis<br />

has been placed on the identification of potential users who,<br />

as identified by Industry Department would provide a<br />

positive benefit to the economy of Hong Kong. During the<br />

course of the study we also sought to identify existing PHPs<br />

who may wish to relocate to Area 137. With the exception<br />

of HK China Gas most PHIs operations saw little advantage<br />

in relocation and would not do so unless obliged to and<br />

possibly convinced by Government. Thus, a Government<br />

policy initiative would be required to implement what you<br />

suggest.<br />

The OZP should ideally incorporate the latest planning<br />

information available to ensure, once gazetted, that its<br />

proposals are not immediately redundant. Thank you for<br />

informing us of the OZP gazzetal. Please note the suggested<br />

amendments to the ODP which may impact on the OZP<br />

proposals.<br />

Specific<br />

Section 2.2.1<br />

"OPP's" in first line of second paragraph should read<br />

"OOPs". Similarly for OPDs in first and sixth lines<br />

of the fourth paragraph.<br />

Noted. Text will be amended.<br />

5.<br />

Section 2.3.2<br />

If it is the intention that the marine access for SENT<br />

Landfill be relocated outside Area 137, the<br />

Consultant should make detailed recommendations.<br />

As can be seen from the adopted ODP, the SENT<br />

Landfill is bounded by the TKO Industrial Estate in<br />

the west and Area 137 in the south, there is not<br />

much scope for an alternative access to be designed.<br />

The report should elaborate farther on the specific<br />

design controls/measures which are required to be<br />

adopted.<br />

This issue was discussed during the course of the Study to see<br />

if» by appropriate siting from the outset, reprovisioning<br />

could be avoided almost as soon as the facilities are<br />

provided. Solutions discussed included siting the facilities<br />

front the outset in the proposed Area 137 location as well as<br />

further north within the bay. However, the Study was<br />

directed to assume that reprovisioning will take place and<br />

that this should be provided for within Area 137.<br />

These are outlined in Section 4.0 and within the written<br />

statements*<br />

APH Consultants Appendix D-22


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Section 2.3.4<br />

I share the author's view that the nature of traffic<br />

generated by the proposed DWIs and PHIs within<br />

Area 137 is such that it is desirable to confine this<br />

traffic to high standard express routes which include<br />

the Western Coast Road and the Cross Bay Bridge.<br />

These routes will be separated from the residential<br />

and commercial areas in Tseung Kwan O and ensure<br />

that environmental impacts are minimized. Similar<br />

comments were received from the District Board<br />

members when the Tseung Kwan 0 OZP was<br />

presented to the Sai Kung District Board in early<br />

1992.<br />

Noted.<br />

Section .4.2<br />

Site 1 which has been allocated for gas production<br />

purposes may more appropriately be zoned "Industry<br />

Group 3(I(B))" as the proposed "Industry Group<br />

C(I(C))* is mainly intended for warehouse and<br />

godown purposes.<br />

The site will be used for gas production and storace.<br />

However, at your suggestion we will modify the zoning and<br />

the respective landuse budget.<br />

Since the Western Coast Road unavoidably has<br />

significant impact on the Kowloon Hast area, the<br />

District Planing Offlcer/Kowloonshould be consulted<br />

on whether the proposed WCR could link with Kwun<br />

Tong Bypass or other proposed road network in the<br />

South East Kowloon Development Statement<br />

presently undertaken by the Consultants.<br />

The SEKS consultants advise that outline provision has been<br />

made for strategic routes which have a bearing on their<br />

study area.<br />

9.<br />

SectionJLI<br />

In order to have a better understanding of the visual<br />

impact and glare nuisance, it is suggested that a<br />

visual impact assessment with photo-montages be<br />

conducted.<br />

Photo montage preparation is unfortunately beyond the<br />

terms of our Brief. Nevertheless* a horizontal profile sketch<br />

of the site as viewed from Chai Wan will be prepared.<br />

REGIONAL SERVICES DEPARTMENT<br />

Para 5.3.2<br />

The revetted slope with rock armour seawall should be of a type<br />

that will not easily trap floating refuse brought ashore by wave.<br />

It is hoped that such a design will not cause cleansing problem.<br />

Noted. This should be acted upon at Detailed Design.<br />

ROYAL HONG KONG POLICE FORCE<br />

Section3. para 3.3.9<br />

The suggestion that jetty operations be suspended,<br />

for the annual festival at Joss House Bay, is<br />

supported;<br />

Noted.<br />

APH Consultants Appendix D-23


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(b)<br />

Section 4<br />

0)<br />

(ii)<br />

The recommended planning layout (fig.<br />

4.1) is noted, particularly the R2/D6<br />

alignment - I trust this will be<br />

development early to ensure that adequate<br />

alternative routes to and from the PHI<br />

area in the south are available as quickly<br />

as possible;<br />

The additional EVA's and proposed<br />

restrictive parking and loading/unloading<br />

arrangements are most welcome;<br />

The provision of access along D2/D6 will be provided from<br />

the outset. However, the alternative routing to the PHI<br />

development wfll depend upon the completion of Rl. The<br />

completion of this latter road will depend upon the rate of<br />

supply, at that time, of public dumping material. During<br />

imptem elation a view will need to be taken on the urgency<br />

for the provision of the road in the light of the actual rate of<br />

supply.<br />

Noted.<br />

(c)<br />

Section 5<br />

Potential sources of fill are noted;<br />

Noted.<br />

(


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

3. The general principle should be to provide as much<br />

greenery as possible such as buffer and screen<br />

planting and simple planting on road verges. The<br />

use of natural earthmound instead of raised planter is<br />

a more suitable approach to the area and to use as<br />

little ornamental shrubs as possible except in<br />

designated open spaces.<br />

The use of raised planters has been limited as far as possible<br />

within the design, in order to keep costs down and reduce<br />

the visual extent of the hard landscape. They have, however,<br />

a number of practical purposes which make their use, in this<br />

situation, essential:<br />

* to prevent casual parking along roadsides;<br />

* to visually and physically separate pedestrian and<br />

vehicular traffic;<br />

» to raise roadside planting above a level where it<br />

might be affected by splash back from vehicles,<br />

and so avoid unsightly edges to roadside planting<br />

beds;<br />

» to increase the height, and thereby the screening<br />

effect of the roadside planting;<br />

* to help reduce the impact of noise generated at<br />

road level.<br />

Primary Structure Planting<br />

4. I do not see how using indigenous tree and shrub<br />

species will provide the buffer zone or the main<br />

vegetation infrastructure as intended. It is not that I<br />

agree with the use of only indigenous tree and shrub<br />

species but many species listed in Table 4.2 for<br />

primary structure planting are not indigenous and<br />

wrong tree species for the area. The consultants<br />

need to check and a bit of more research before they<br />

specify the recommendation. This office does not<br />

agree with shrub species recommended and would be<br />

interested to know how many of these are indigenous<br />

shrubs. One also has to consider whether these<br />

recommended species will grow well in such a harsh<br />

environmental such as in area 137.<br />

The use of the word "indigenous" is, unfortunately<br />

misleading and will be omitted from the text. It was used to<br />

identify one of the aims of the proposed planting, that


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Roadside planting<br />

6. Para. 2 states that tree planting along the roads will<br />

provide shade to pedestrians and reduce glare from<br />

hard surfaces and yet they recommend the use of<br />

raised planters. Earthmounds will do the job and<br />

cheaper and more natural and more suited to the<br />

area. Furthermore, earthmounds will provide<br />

uninterrupted root developmentwhich is important in<br />

such an environment. The consultants should review<br />

the recommended species for roadside planting.<br />

More thought needs to be given to replace the<br />

recommended species as shown in Table 4.2.<br />

Noted, as point 3 in this series.<br />

While we agree that the use of earthmounds would provide<br />

a softer appearance in screening the development and roads,<br />

there is insufficient space within the development to create<br />

mounds large enough to provide suitable screening, as well<br />

as allowing space for servkes, access and emergency access,<br />

Plant species for roadside locations, in particular shrub<br />

species were chosen to create additional interest and a more<br />

human-scale environment than the main structure planting.<br />

These, however, have been reconsidered with a view to the<br />

likely maintenance*<br />

Maintenance Considerations<br />

7. By introducing amenity shrubs and ornamental shrubs<br />

and roadside planters, they entail intensive<br />

maintenance requirements such as watering, pruning,<br />

weeding etc. which the maintenance authority (in this<br />

case RSD) does not favour. Self-maintenance type of<br />

planting will be more suitable in such a low<br />

population density area such as PHIs and DWIs sites.<br />

Noted, as previously.<br />

The section on landscaping needs revision. The<br />

design solution is over-simplified even though the<br />

main concept is clearly stated. A more thorough<br />

approach to the type of planting and the choice of<br />

species are warranted.<br />

Noted* as previously.<br />

TERRITORY DEVELOPMENT DEPARTMENT ~ SOUTH EAST NEW TERRITORIES DEVELOPMENT OFFICE<br />

Volume I<br />

1. In the Table of Contents, insert the word "Section*<br />

as heading of the section column.<br />

Agreed.<br />

2. Section 2.24 foage 2-2^ 1st oara.<br />

Replace the 2nd sentence by<br />

"An interim upgrading of the plant i* scheduled to<br />

commence in late 1993. On completion in mid 1995,<br />

the additional facilities will be able to cope with the<br />

effluent generated by the TKOE. Additional amount<br />

of effluent generated by development in TKO will<br />

require further upgrading of the plant."<br />

Agreed,<br />

3- Section 5.9.1 and 5.9.3 /'page 5-14. 5-15 & 5-16)<br />

These sub-sections do not depict precisely the present<br />

position of the study on Tseung Kwan O Sewage<br />

Treatment & Disposal undertaken by Messrs Mott<br />

MacDonaid Hong Kong Ltd. You agreed to update<br />

the said sub-section in consultation with Messrs Mott<br />

MacDonaid Hong Kong Ltd.<br />

Noted. The sub-section will be updated in consulation with<br />

Mott MacDonaid Hong Kong Ltd.<br />

APH Cansutimts Appendix D~26


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

4.<br />

Section 7. 12 (page 7-3}<br />

3rd para. - second sentence should read "However,<br />

in accordance with the implementation programme,<br />

the completion date for Road D6 is required to be<br />

brought forward to 1997. *<br />

Agreed.<br />

Section 7. 1.3 (page 7-3)<br />

1st para. - Planning Area 85 should read Planning<br />

Area 86.<br />

Agreed.<br />

6.<br />

Section 10.3 .2 (page<br />

3rd para should read<br />

Agreed.<br />

8.<br />

9.<br />

10.<br />

II.<br />

12.<br />

" - reclamation of the road reserve by SENT<br />

Landfill Contractor from mid 1995;<br />

one year notice to SENT Landfill<br />

Contractor for release of the road reserve;<br />

release of the reserve to TDD for the<br />

construction of the road by mid 1996."<br />

The subsequent sentences in paragraph 3 should be<br />

amended in accordance with the above constraints.<br />

Section 10.3.5 (page 10-4)<br />

3rd para<br />

Initial Works should read "Initial Development*<br />

The 2nd sentence under this sub-para should be<br />

amended in line with the comment in the above para.<br />

Implementation programme 1 should be deleted.<br />

Implementation programme 2 should be amended in<br />

line with the suggestion given to you on 17<br />

December 1993.<br />

In all the Tables under Section 10, programme 1<br />

should be deleted and programme 2 should read<br />

programme.<br />

Table 10.3 (page 10-6)<br />

The expenditure for Phase I and remaining phasing<br />

should be split.<br />

In view of the substantial nature of amendments<br />

involved, you agreed to amend and re-circulate<br />

Section 10 of the draft final report (Volume 1) in line<br />

with our suggestions for discussion and endorsement<br />

in the coming Steering Group Meeting which is<br />

presently scheduled at the end of this month.<br />

Accepted.<br />

Accepted.<br />

Accepted.<br />

Agreed.<br />

Agreed.<br />

In the above discussion, we also suggested that the Location<br />

Plan (Drg. No. TKO/1237/001 in Volume 2) should be amended<br />

to show the study site in relation to the whole Tseung Kwan O<br />

New Town. In particular, its relation to the two important<br />

neighbouring sites, i.e. the Tseung KwanO Industrial Estate and<br />

SENT Landfill, should be shown clearly.<br />

The drawing will be amended.<br />

APH Consultants Appendix D-27


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

I refer to CE/MS DSD's letter ref. (26) in D(MS) 10/5/61 m<br />

dated 16 December 1992 which was addressed to you and<br />

copied to this office commenting on the draft final report.<br />

I wish to supplement the information containing in para (b) of<br />

the said letter as follows :<br />

The detailed design of interim works and outline design of Phase<br />

n works for the Tseung Kwan 0 Sewage Treatment Works<br />

commenced on 27.11.92. The Consultants Messrs Mott<br />

McDonald Hong Kong Ltd are required to consider treatment of<br />

the effluent generated by the Area 137 development in<br />

accordance with the Revised Design Statement ofTseung Kwan<br />

O development Sewage Treatment and Disposal, a copy of<br />

which was given to you satiy this year. As such, please<br />

urgently provide the quantity of sewage flow from the Area 137<br />

development to Messrs Mott McDonald Hong Kong Ltd. Please<br />

be advised that it is not until the completion of the Phase n<br />

stage 1 of the Sewage Treatment Works by 1998 that the plant<br />

is capable of coping with treatment of the effluent from the Area<br />

137 development.<br />

Please see attached Figure which illustrates Area 137<br />

predicted levels in relation to the revised Design Statement<br />

No2 and the total allocation for Areas 137, 85 and 86. A<br />

copy of the Figure has also been passed to Mott MacDonald<br />

for confirmation.<br />

The issue of sewage flows from Area 137 has subsequently<br />

been resolved with DSD. The revised Report contains ihe<br />

updated and agreed information.<br />

TRANSPORT DEPARTMENT - PORT AND AIRPORT DEVELOPMENT OFFICE<br />

A. Draft Executive Summary<br />

PagejS<br />

(1)<br />

How firm are the population build-up assumptions<br />

for the future design years. Reference to housing<br />

programme, new town development programme<br />

should be given.<br />

The figures reflect the Housing<br />

Metro plan.<br />

Programme and the<br />

(2)<br />

In view of the substantial difference between the two<br />

population forecasts, (333,000 vs 440,000), the<br />

report should clearly state that the traffic and<br />

transport studies have been based essentially on an<br />

ultimate level of 333,000 by 201 i in accordance with<br />

the Metroplan. A sensitivity test was carried out for<br />

the higher population forecast.<br />

Agreed.<br />

(3)<br />

The assumption in respect of MTR extension should<br />

be mentioned in the context of external network, as<br />

it will form a major component of the transport<br />

infrastructure for Tseung Kwan 0.<br />

Agreed.<br />

(4)<br />

Page<br />

(1)<br />

The traffic and transport impacts to East Kowloon<br />

should be addressed.<br />

TKO Tunnel is said to be "marginally above its<br />

practical capacity" at the top of the page but it<br />

"would be heavily overloaded in the Am peak* in the<br />

middle of the of the page. This appears<br />

inconsistent.<br />

This b contained in the Main Report.<br />

The first comment refers to a scenario which includes the<br />

MTR extension to TKO. The second reference refers to a<br />

scenario which assumes the provision of an MTR link is<br />

delayed beyond 2011.<br />

(2) For clarity sake, I propose to amend the first<br />

sentence in the third paragraph to read :<br />

APH Consultants Appendix: D-28


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

"For the 333,000 population, the western screenline<br />

will operate below capacity if ail planned transport<br />

infrastructure improvements are implemented as<br />

scheduled."<br />

Furthermore do the external links mentioned in the<br />

second sentence refer to the western screen <br />

(3) What is the percent change in the level of selfcontainment<br />

(4) How much overloaded would the TKO Tunnel in the<br />

AM peak and in what year <br />

(5) In order to highlight the importance of the timely<br />

provision of the Western Coast Road, the finding that<br />

the total screenline would be overloaded by mow<br />

than 30% if WCR is not completed by 2001 should<br />

be added in the fifth paragraph.<br />

(6) Po Lam Road is a steep road and runs through major<br />

residential areas. It is clearly undesirable for<br />

dangerous goods traffic to use this road. The fifth<br />

paragraph should be amended accordingly.<br />

(7) In the evaluation of the Western Coast Road<br />

connections, can the effects of either options upon<br />

the existing land uses be described as marginal <br />

(8) The potential impacts of the possible delay to the<br />

implementation of Western Coast Road and the MTR<br />

extension, which have been studied in some depth,<br />

should be presented in the Executive Summary. The<br />

timely provision of these transport facilities is critical<br />

to the development of Tseung Kwan O including<br />

Area 137. More specifically, the findings in Tables<br />

7.17 and 7.IS of the Main Report should be<br />

incorporated in the Executive Summary.<br />

Agreed.<br />

Agreed.<br />

The analysis was carried out for a 20% reduction in selfcontainment.<br />

If the MTR extension were delayed beyond the 2011 year,<br />

then the TKO tunnel would become overloaded in the period<br />

between 2006-2011.<br />

Agreed.<br />

Agreed, but there is no legal alternative road for certain<br />

categories of dangerous goods.<br />

The text refers to marginal additional effects on land uses of<br />

Option B.<br />

Agreed* text will be amended.<br />

(1) The second paragraph does not appear to be true as<br />

far as the Western Coast Road connections in the<br />

East Kowloon are concerned.<br />

(2) The issue of how practical the proposal in the third<br />

paragraph would be in terms of feasibility and timing<br />

should be addressed.<br />

This paragraph reefers specifically to Area 137 which is the<br />

main subject of the Study*<br />

As stated, it is essential that an early decision is reached and<br />

the road constructed.<br />

B. Draft Final Report<br />

Section 2 Planning Base<br />

Para 2.2.1 What are I(A), I(B) and I(C) Brief<br />

descriptions should be given.<br />

(1) Why is the MTR extension not<br />

mentioned <br />

(2) The different planning horizon<br />

should also be given.<br />

These are standard terms used within Government to<br />

describe different classes of industry and development.<br />

The MTR link inflneneces the growth of TKO and indirectly<br />

that of Area 137. Note reference to MTR link in para 2 J.I.<br />

The different planning horizons cannot be defined at this<br />

stage beyond stating that there is early demand for PHI sites.<br />

The remainder of the horizons will be dictated by the future<br />

take up of sites within Area 137.<br />

APH Consultants Appendix D~29


Engineering Feasibility Study of Development ofTseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Section 4 Land Use Planning<br />

Table 4.1 The total number of workers should be shown in the<br />

table.<br />

Noted. Total will be giYen.<br />

Section 7 Traffic and Transport Study<br />

Para 7.1.1 (1) While the transport modelling<br />

methodology is based on CTS-2, the<br />

planing data adopted should be confirmed<br />

by Planning Department rather than just<br />

simply inferred from a transport model.<br />

It should also be noted that the original<br />

metropian data are continuously being<br />

updated.<br />

(2) What is the effect (in percentage terms) of<br />

the minor variation in the degree of<br />

vacancy and take-up of flats on the<br />

population forecasts <br />

(3) If the forecast employment rate is prone<br />

to higher error, the external traffic to and<br />

from TKO will be greater since less jobs<br />

available in TKO would mean more<br />

people travelling to the urban areas. The<br />

consultant should carry out a sensitivity<br />

test to investigate the effect of this.<br />

From a regional perspective, the ultimate<br />

design population of 440,000 by 2011<br />

should be taken into account in planning<br />

for adequate road capacity. In this<br />

connection, I must state our position that<br />

the pace and scale of development should<br />

be compatible with the transport<br />

infrastructure available.<br />

(2) The forecast population for Sai Kung<br />

shows a decreasing trend which is<br />

illogical and inconsistent with ongoing<br />

development proposals and observed<br />

increasing traffic flows.<br />

(3) Presumably the forecast for CWB of '99*<br />

for 1996 was typed wrongly.<br />

Para 1.2 &<br />

(1) To tie in with the development<br />

programme for Area 137, Road PI<br />

between Tl and D4 should also be<br />

brought forward to 1996 such that the<br />

industrial traffic could avoid the Hang<br />

Haix Area. Furthermore, as commented<br />

before, D6 should be completed up to<br />

LS71 junction by 1996.<br />

(2) Why are TKO Tunnel and Hang Hau<br />

Road depicted as completion by 2011 in<br />

Rgure : The quality of this figure should<br />

be improved.<br />

Agreed. The input planning data assumptions are<br />

documented in the modelling report.<br />

Vacancy is assumed to be between 5% and 7%.<br />

This has been examined in an alternative way by lowering<br />

self-containment.<br />

This is a matter of planning policy as to the number of<br />

residents in TKO.<br />

This comment would be better answered by Planning<br />

Department. However, in tae context of the current Study,<br />

the majority of traffic from Sai Kung is assumed to use<br />

CWB rather than pass through TKO.<br />

Agreed. The correct figure is 19. Table will be amended.<br />

Agreed. Text will be expanded.<br />

Figure will be amended.<br />

APH Consultants<br />

Appendix D-3Q


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

To supplement Table 7.4. a plan showing<br />

the zoning and developing layout in Area<br />

137 should be included.<br />

(2) More details about the Survey from the<br />

trip rates in Table 7.3 are derived should<br />

be provided.<br />

(3) The Consultant should elaborate on how<br />

the travel patterns shown in Figure 7.2<br />

are obtained.<br />

(4) & Table 7.6, the forecast "private* traffic<br />

appears low. What is the unit for this<br />

table Does the figure include buses,<br />

coaches, taxis etc The composition<br />

showing just "private" and "goods" traffic<br />

is too crude.<br />

Para 7 2.2 (1) It would be illustrative to present<br />

graphically the screeniine described in the<br />

second sub-paragraph. The screeniine<br />

referred to in the second sub-paragraph<br />

should be specified. Likewise, a plan to<br />

indicate the proposed improvements in<br />

Yau Tong area should also be provided.<br />

(2) Would the proposed improvements in Yau<br />

Tong area be funded and carried out by<br />

TDD in connection with the construction<br />

of WCR By copy of this letter,<br />

PM/SENT is invited to comment.<br />

(3) Did the consultant assume the Option B of<br />

WCR connection in deriving the figures<br />

" in Table 7.7 Why is there a general<br />

reduction in the traffic figures when<br />

compared with table 6.1 and table 6.2 of<br />

woricing paper no. 9 What changes<br />

bring about the reduction<br />

To support the conclusion that the<br />

Western Coastal Road (WCR) is to be in<br />

operation in 2001, it is necessary to<br />

include WCR in the network and to<br />

produce the forecast of the daily, AM and<br />

PM traffic volumes in 2001 on WCR,<br />

TKO Tunnel and Po Lam Road. These<br />

traffic forecasts should be used to justify<br />

the aeed for WCR.<br />

(2) The traffic forecasts in Tables 7.8 and 7.9<br />

clearly demonstrated the need for WCR<br />

by 2001 since both the TKO Tunnel and<br />

the total screeniine would be overloaded<br />

by 39% and 32% respectively. There<br />

will be no choice of routes left for the<br />

motorists* This couples with the almost<br />

equal east and westbound traffic will<br />

make any traffic management scheme<br />

such as tidal flow futile.<br />

Noted.<br />

Noted. Text wffl b« amended to include mention of the sites<br />

surreyed.<br />

The text will be expanded. The traffic from A137 is assumed<br />

to hare the same pattern as other traffk from TKO of the<br />

same vehicle type*<br />

Private vehicles includes taxis, cars and the special purpose<br />

buses. Vehicles operating franchise*! routes are not shown<br />

on this table.<br />

Noted. Text will be expanded.<br />

PM(SENT) to advise.<br />

Option B has been assumed as it is the preferred alignment.<br />

Working Paper No. 9 contains the traffic figures prior to the<br />

preferred concept and the revision in land use assumptions<br />

arising from the more detailed analysis.<br />

This has been carried out and a paragraph to support the<br />

need for WCR on 2001 will be produced.<br />

Agreed. However this must contain the proviso of "if TKO<br />

develops as currently planned, and the industrial<br />

developments are in place 11 .<br />

APH Consultants Appendix D-31


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(3) It appears desirable to include in die 2001<br />

scenario a test for having one carriageway<br />

of WCR. I suspect this could help<br />

demonstrate the need of WCR by 2001 -<br />

with the first carriageway only or with the<br />

full dual three carriageway.<br />

(4) Why is there no assessment on the traffic<br />

conditions along Hang Hau Road and<br />

Clearway Bay Road <br />

(5) The traffic forecasts indicate that the<br />

westbound (Kowloon Bound) traffic is<br />

lower than the eastbound traffic in the<br />

AM peak and vice versa in the PM peak.<br />

However, they are in contradiction with<br />

the existing traffic patterns where the<br />

westbound traffic is about 50% higher<br />

than the eastbound traffic in the AM peak<br />

and the latter is about 35% higher than<br />

the westbound traffic in the PM peak for<br />

both Po Lam Road and TKO Tunnel.<br />

The Consultants are requested to clarify<br />

the major differences in traffic patterns<br />

and make any necessary model validation<br />

and amendments.<br />

(6) Please check the 2006 forecast of the PM<br />

eastbound traffic for TKO Tunnel in<br />

Table 7.9.<br />

(7) As regards the TKO tunnel congestion<br />

problem, the conditions of the vicinity of<br />

the tunnel should be mentioned.<br />

(8) The Western Coast Road should be<br />

viewed as critical to the development of<br />

TKO including Area 137.<br />

Para 7.2.4 (1) The choice of 20% reduction in selfcontainment<br />

was explained in response to<br />

a comment from the Planning<br />

Department. This should be included in<br />

this section.<br />

The assumption that MTR TKO Extension<br />

would be opened by 2006 is noted.<br />

Could the Consultants advise on the<br />

minimum population threshold that would<br />

support the rail extension and the<br />

maximum population threshold that would<br />

not overload the extension.<br />

This is a matter of implementation to establish whether this<br />

is a viable approach given the short time span between the<br />

opening of one carriageway and the time when both are<br />

required. Given the non-directional nature of the traffic as<br />

currently forecast, there would be operational problem with<br />

this configuration.<br />

Some comments win be included, bat it should be noted that<br />

there are questions over the planning data underlying the<br />

traffic forecasts for this corridor, and it is not the main focus<br />

of the study.<br />

The traffic forecasts come directly from Government's own<br />

traffic projections. It should be noted that the scale of<br />

future development is very different from that currently<br />

existing in Tseung Kwan 0. The Consultants compared the<br />

1991 figures from the model and observed flows; these are<br />

reported in the Technical Note on Modelling.<br />

This Table includes under the Base column traffic figures<br />

arising from the land use prior to the preferred concept;<br />

these will be amended to reflect the final figures.<br />

Text will be amended.<br />

Noted.<br />

Agreed.<br />

Whilst interesting questions, these are outside the Study<br />

Brief.<br />

(2)<br />

Apart from the problems and difficulties<br />

as mentioned in this paragraph regarding<br />

the non-provision of MTR, the local<br />

sentiments should be taken into account.<br />

There will be strong political pressure for<br />

the MTR Extension.<br />

Agreed. This is a matter of policy.<br />

APH Consultants Appendix D-32


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(3)<br />

(4)<br />

(2)<br />

(3)<br />

(4)<br />

(5)<br />

(6)<br />

(7)<br />

Are the "600 extra pcus" mentioned in the<br />

second sub-paragraph all bus trips In<br />

the same sub-paragraph, what is the<br />

resulting v/c ratio if the extra traffic is<br />

taken into account<br />

Can the problems mentioned in the third<br />

sub-paragraph such as bus congestion in<br />

TKO and Kwun Tong and interchange<br />

problems be quantified <br />

What is the unit for Table 7.11 <br />

The Consultants should explain why the<br />

traffic forecast for Po Lam Road would<br />

decrease (rather than increase) as a result<br />

of higher population based on the SENT<br />

Development Programme.<br />

It ts doubtful that an increase in<br />

population of about 110,000 would<br />

generate only 1100 pcu traffic during the<br />

AM peak. This forecast appears to be too<br />

low.<br />

Furthermore, it must be pointed out<br />

clearly that even with the scteenltne v/c at<br />

1.0 (which corresponds to the design<br />

population of 432,000), the v/c at TKO<br />

Tunnel would probably be still higher<br />

than 1.2 which means severe congestion.<br />

The consultants mentioned that about<br />

2000 pcu's would use the CWB<br />

Road/Hang Hau Road corridor. Please<br />

amplify whether this is one way or two<br />

way flow. What is the expected v/c ratio<br />

along these two road corridors I<br />

envisage that this traffic flow would<br />

overload the existing CWB Road taking<br />

into the account the trips originating in<br />

the CWB peninsula.<br />

What is the MTR assumption for the<br />

forecasts given in Table 7.13.<br />

Do the 2000 pcus mentioned in the 6th<br />

sub-paragraph refer to a daily or peak<br />

hour flow<br />

In addition to Table 7.13, forecasts of<br />

daily and PM peak traffic flows on WCR,<br />

TKO Tunnel and Po Lam Road should<br />

also be presented.<br />

The 600 pcus are buses, TKO tunnel would operate at 1.25<br />

v.c. ratio in 2011 as shown in Table 7.11.<br />

This is a matter for a much more detailed study to assess; it<br />

would have to address pedestrian movements, layouts of the<br />

bus interchanges, etc.<br />

The unit is PCU's; the table heading win be amended.<br />

A revised table will be produced.<br />

The test assumption only included extra population, with ao<br />

further employment, and therefore cannot be compared with,<br />

say, an existing New Town of around 100,000 people as these<br />

normally include some employment. It should be noted as<br />

well that the majority of people leaving TKO in the morning<br />

peak will be in publk transport, and the presence of the<br />

MTR extension has been assumed. Therefore the extra<br />

110,000 people have a low impact on the road volumes for<br />

the external screenline for TKO, given this context.<br />

Agreed.<br />

This is a one way flow and includes the Sai Kung Traffic.<br />

The v/c ratio on CWB east of Hiram's Highway is 1J7, and<br />

0.93 on Hang Hau Road.<br />

The MTR is assumed to be present on both cases shown in<br />

Table 7.13<br />

These are peak hour flows.<br />

The analysis has been restricted to peak conditions.<br />

APH Consultants<br />

Appendix B-J3


Engineering Feasibility Study of Development ofTseung Kwan 0 Area 137<br />

final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(8) Since the vehicle ferry has not been<br />

tested, the consultants should substantiate<br />

how the ferry service can provide the<br />

release to the traffic burden. This<br />

comment also applies to the Executive<br />

Summary.<br />

In examining the traffic impact in the<br />

Area of Influence, the Consultants should<br />

also look Into the impact on the critical<br />

junctions in East Kowloon and Kwun<br />

Tong which would be the main capacity<br />

constraints to the proposed WCR and<br />

would be adversely affected by the<br />

additional traffic generated.<br />

(2) In Table 7.14, why are there no v/c<br />

figures for Hiram's Highway To which<br />

sections of CWB Road and New CWB<br />

Road does this table refer The most<br />

critical section of CWB Road within the<br />

Area of Influence would be the one<br />

between Hang Hau Road and University<br />

Road, which is currently a single<br />

carriageway.<br />

Should Total Traffic - MTR open in<br />

2001" in Table 7.16 read Total Traffic -<br />

MTR open in 2006" <br />

(2) Table 7 16 demonstrates that even with<br />

MTR in 2006 the "without WCR"<br />

scenario would still result in a v/c ratio of<br />

about 1.43 which is totally unacceptable.<br />

(3) The consultant should assess the scenario<br />

of having no Area 131, 137 development<br />

but with full metroplan population and<br />

100% other industrial development. I<br />

envisage that this scenario could help<br />

demonstrate the need for WCR by 2001 if<br />

developments in Area 131/137 are to<br />

proceed.<br />

(4) Surely, B3 and B7 in Table 7.17 would<br />

lead to strong criticism from the pubic<br />

that the Government allows their<br />

"preferred" developments to proceed but<br />

at the same time limiting participation of<br />

the private sector.<br />

(5) The forecasts of the daily* AM and PM<br />

traffic flows on WCR, TKO Tunnel and<br />

Po Lam Road for the scenarios of delay<br />

of WCR in 2006 and 2011 should be<br />

presented.<br />

(6*) As regards the second sub-paragraph on<br />

page 7-15, the combination of MTR and<br />

no Western Coast Road is a possible<br />

option.<br />

The TKOFSOFD examined the vehicle ferry and suggested<br />

it could attract about 200 pens per hour. Whilst this study<br />

has not examined this service in detail, if the route could<br />

attract 200 pcus it would assist in reducing the screenline<br />

over capacity and would attract some vehicles given the<br />

condition of near-congestion on the external road links.<br />

The modelling of the Area of Influence considered junction<br />

capacity in calculating the We ratios shown in Table 7.14.<br />

The traffic from Area 137 disperses widely over the external<br />

network. The impact of WCR on individual junction design<br />

on East Kowloon is outside the Brief.<br />

V/C ratios for Hiram's Highway will be added to the table.<br />

However it must he noted that this is at the edge of the Study<br />

Area and there is some question on the realism of the<br />

planning assumptions for Sai Kung.<br />

Agreed.<br />

Agreed.<br />

This conclusion is shown by the source of traffic shown in<br />

the first column of Table 7.16.<br />

Agreed.<br />

The scenario exercise reported in Section 7.2.9 has been<br />

developed as a sensitivity test and such figures are not<br />

available.<br />

Whilst physically possible, the lack of the WCR would limit<br />

development, and in such circumstances it may well be that<br />

the MTR would not be such an attractive investment. In<br />

deciding the priority between MTR and WCR in attracting<br />

funds, the potential for WCR serving ail sections of travel<br />

demand inchiffamy commercial movements must be borne ui<br />

mind*<br />

APHConsultants Appendix D-34


Engineering Feasibility Study of Development ofTseung Kyvan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Para 7.2.10 (1)<br />

The Consultant may consider to amplify<br />

the first finding on WCR after assessing<br />

my comment (3) on para. 7.2.9 above.<br />

The construction of WCR by 2001 should<br />

be considered as a p re-requisite of<br />

allowing the Area 137/131 development.<br />

It is the presence of other industrial developments which<br />

require the WCR by 2001.<br />

(2) Presumably the S3 toll for TKO Tunnel in<br />

respect of the second finding refers to the<br />

1991 price. Furthermore, as the<br />

problems occur in peak hours only,<br />

differential tolls may be more appropriate.<br />

(3) As regards the 4th finding, the wording<br />

should be amended such that without the<br />

MTR Extension the TKO Tunnel would<br />

result in further congestion. The original<br />

wording is misleading as it seems to<br />

suggest that the heavily overloaded<br />

situation is due solely to the lack of the<br />

MTR extension. This is not the actual<br />

case. As the base v/c ratio is forecast to<br />

be 1.16 TKO Tunnel is already<br />

overloaded.<br />

(4) Please add "design" before "population of<br />

440,000" in the second last finding.<br />

Furthermore, I have reservation on this<br />

finding since there is no amplification on<br />

what improvements, at what scale, would<br />

the Hang Hau corridor be improved. As<br />

commented above, the forecast population<br />

in Sai Kung was underestimated. This<br />

would result in lower estimates of trips on<br />

Hiram's Highway and CWB Road. Has<br />

MTR extension been assumed for this<br />

finding <br />

It is considered desirable to indicate the<br />

road width of fig 7.4 in accordance with<br />

section 5.6 of the report. The possible<br />

future extension of Road D6 eastward<br />

should be shown and a suitable reserve<br />

maintained.<br />

The tolls are in fact in 1990 prices. Noted, although it has<br />

not yet been implemented in Hong Kong.<br />

Agreed.<br />

Agreed. The improvements to Hang Hau are these assumed<br />

in the TKO Development Programme. The Sai Kung<br />

population is a matter for discussion with Planning<br />

Department. The MTR is assumed to be present from 2006<br />

onward.<br />

Noted.<br />

Para 7,3.2 (1) This paragraph assess the traffic<br />

conditions in various design years with<br />

the assumption that WCR would be<br />

completed by 2001. However, this seems<br />

not consistent with the previous sections<br />

in this chapter that "in order to critically<br />

examine the timing of provision of WCR<br />

it has been assumed to be deferred until<br />

2006* (see para. 7.1.2). Though t fully<br />

support the inclusion of the assessment as<br />

presented {i.e. with WCR by 2001), it is<br />

considered necessary to show the<br />

"without" scenario in the 2001 year. I<br />

envisage there will be severe congestion<br />

in the internal road system and large scale<br />

improvements would be required.<br />

The last line of 5th para of 7.1.2 is misleading. The<br />

junctions hare been evaluated on the assumption that WCR<br />

is present from 2001. Earlier working papers examined year<br />

2001 without WCR. Notwithstanding the screenline links<br />

will be overloaded in 2001 without the WCR and the road<br />

network would not be able to perform adequately.<br />

APH Consultants<br />

Appendix D-J5


Engineering Feasibility Study of Development of Tseung Kwan 0 Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

(2) It if desirable to show the various v/c<br />

ratios on plans corresponding to fig. 7.7,<br />

7.9 and7.il.<br />

Noted.<br />

(3) It seems chat there is no assessment on the<br />

junctions T1/P1/P2 and P2/D4 (2001<br />

year). These two are grade separated<br />

junctions.<br />

(4) The report should include plans to show<br />

the recommended junction Improvements<br />

at S3 and R4. In the assessment of R4,<br />

did the consultant include the flyover on<br />

PI At what year is the flyover assumed<br />

to be built Consideration should be<br />

given to junctions SI, S2, S3, S4 and S5<br />

being roundabouts which would probably<br />

have a higher reserve capacity than<br />

signalised junctions.<br />

(5) I think R3 in Table 7.15 and 7.17 should<br />

be junction D9/P2 instead of D9/D3.<br />

(6) I would like to see the detailed junction<br />

assessments for all design years instead of<br />

only 2011. Please submit them direct to<br />

Traffic Engineering (NTE) Division of<br />

this Department for checking.<br />

(7) It appears that Table 7.15 and 7.17 in this<br />

section should read 7.19 and 7.21.<br />

(8) The design v/c ratio for roundabouts<br />

should not exceed 0.35. In Tables 7.15,<br />

7.16 and 7.17, roundabouts with v/c<br />

ratios in excess of this value would<br />

require improvement measures.<br />

Para 7 4 (1) Please amplify which residential area is<br />

referred to and where the small bus<br />

terminus is. Also I assume "Area 314"<br />

should be "Area 3/4".<br />

Assessment win be included.<br />

Junction improvement schemes for S3 and R4 are described<br />

in the tact and proposed plans have been given to Transport<br />

Department. The flyover on PI was included in the<br />

assessment of R4. The flyover is assumed to be completed<br />

by 2001 as currently planned. The junction control for SI,<br />

§2, S3 and S4 and S5 are as currently planned.<br />

Agreed.<br />

These have been supplied to Transport Department.<br />

Tables will be amended accordingly.<br />

Noted. The v/c ratios given in Tables 7.15, 7.16 and 7.17<br />

are based on ARC AD Y models for the worst 15 minutes<br />

interval in the peak period. V/C ratios based on hourly<br />

figures will be given.<br />

The residential area is Area 78 and the bus terminal in Area<br />

86". Area 314 should be Area 3/4.<br />

Section S Western Coast Road<br />

Para 8.4 (1) Table S.I shows that Lei Yue Mun Road<br />

attracted more traffic in Option B than<br />

Option A. This should not be the case<br />

since the WCR is only connected to Lei<br />

Yue Mun Road in Option A. The same<br />

query is applicable to Cha Kwo Ling<br />

Road.<br />

(2) The evaluation in respect of traffic and<br />

roads contained here is too brief. The<br />

evaluation analysis given in Section 6.2<br />

(such as Table 6.2, Table 6.6 and Para.<br />

6.2.6) of the Working Paper No. 9 on<br />

"Western Coast Road Connection" should<br />

be included and discussed here.<br />

Moreover, the adverse traffic impacts<br />

caused by both options to the local road<br />

network downstream of the WCR in the<br />

The Lei Yue Mun Road is connected to the WCR under both<br />

Option A and Option B, as is Cha Kwo Ling Road.<br />

However the location of the connection is different for the<br />

two options, see Figures. 8.1 and 8.2.<br />

The traffic evaluation relating to the requirement for the<br />

WCR together with various sensitivity tests is covered in the<br />

Traffic and Transport Study in Section 7 of the Report, as<br />

is the requirement for improvements in the Yau Tong area.<br />

Text will he expanded to clarify this.<br />

APH Consultants Appendix D-36


Engineering Feasibility Study of Development of Tseung Kwan O Area 137<br />

Final Report - Main Report<br />

COMMENTS<br />

RESPONSES<br />

Yau Tong and Kwun Tong area should be<br />

mentioned.<br />

Para 8.7 (1) For comparison, cost breakdowns for the<br />

two Options should be presented.<br />

Para. 8.8 (1) The need for the further study on the<br />

preferred alignment is appreciated. In<br />

view of the adverse impacts on land use<br />

and environment, and the critical role of<br />

the WCR in providing an essential<br />

external link for the further development<br />

of Tseung Kwan O including Areas 131<br />

and 137, this point should be highlighted<br />

with sufficient clarifications.<br />

Furthermore, the further study should be<br />

carried out to confirm the engineering<br />

feasibility should full development of<br />

TKO be contemplated. Such information<br />

should also be included in the Executive<br />

Summary.<br />

The cost breakdowns as included in Working Paper 9 A will<br />

be included.<br />

It is considered that the critical need for the WCR has been<br />

sufficiently highlighted in Section 7. The purpose of Section<br />

3 was to present the findings of the comparative evaluation<br />

of the two proposed connections only.<br />

Section 10 Implementation<br />

Para 10.5<br />

Necessary improvements to the internal roads and<br />

ihe areas of influence should also be included.<br />

Text will be amended to include required<br />

improvements/impikations for junctions and area of<br />

influence.<br />

URBAN SERVICES DEPARTMENT<br />

Draft Final Report - Volume I<br />

As previously conveyed to you, this department is more<br />

concerned about the proposed adoption of Option B of the<br />

Western Coast Road Connection, since two large-scale UC<br />

projects namely Sam Ka Tsuen Recreation Ground and Sam Ka<br />

Tsuen Complex, will be adversely affected. Moreover, I am<br />

also concerned about the environmental impacts generated to the<br />

areas close to the road alignments for Option B m view of the<br />

anticipated busy vehicular traffic, in particular the heavy truck<br />

vehicles.<br />

In the light of the additional points raised by District Planning<br />

Officer/Kowloon vide his letter addressed to you dated 23<br />

December 1992, I think, the cost comparison for the two<br />

schemes i.e. Option A & B as stated in para. 8.7 of the Draft<br />

Final Report - Volume I, should be revised to reflect fully all<br />

relevant factors tor consideration by the Steering Group before<br />

a final decision is taken.<br />

Reference should be made to responses to DPO/K.<br />

APR Consultants Appendix D-37

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!