Table Ir1: Target area for development into irrigation scheme as against achievement<br />
2008/09<br />
S/N/ Activity Target Target<br />
Achievement<br />
Percent achievement<br />
(ha)<br />
(ha)<br />
1. Increasing<br />
na 27,000 21,500 78%<br />
irrigated area<br />
2 Feasibility<br />
na 68* 47** 69%<br />
study <strong>and</strong><br />
design of<br />
irrigation<br />
schemes<br />
3 Construction na 2 (one in Nyamilangano (Kahama) <strong>and</strong><br />
2 100%<br />
works for<br />
another Maswale District (Babati District)<br />
dams<br />
3 Construction na 2 (one in Muheza District & another in<br />
2 40%<br />
works for<br />
Msoga (Bagamoyo District)<br />
dams<br />
Schemes<br />
formulation<br />
na - 283***<br />
* This was targeted to irrigate 200,000 hectares<br />
** expected to comm<strong>and</strong> an area of 137,744<br />
*** Out of these 94 were for District Irrigation Development Fund (DIDF); <strong>and</strong> the rest for DADPs funding<br />
Nevertheless, while the <strong>Ministry</strong> is to be commended for its achievement for the particular year,<br />
there is still huge number of irrigation potential hectares in the country. There are 7 million<br />
hectares of high <strong>and</strong> medium potential irrigation l<strong>and</strong>. Thus, given the present level of resource<br />
allocation to the <strong>Ministry</strong> it will take some 330 years (3.3 centuries) to develop the whole high<br />
<strong>and</strong> medium irrigation potential l<strong>and</strong>.<br />
What to be done<br />
- at national level<br />
The government needs to create an enabling environment to attract medium <strong>and</strong> large scale<br />
serious investors in this area.<br />
What kind of enabling environment is needed<br />
i) Government should try <strong>and</strong> provide a bigger budget for developing irrigation infrastructure<br />
ii) Government should consider increasing level of tax holiday to medium <strong>and</strong> large scale<br />
investors in irrigation.<br />
iii) The newly established L<strong>and</strong> Bank should have at h<strong>and</strong> large tracts of irrigable potential<br />
l<strong>and</strong>, ready for investment by serous farming investors; <strong>and</strong> no red-tape to potential, serious<br />
investors wishing to have long-term lease for sizable l<strong>and</strong> for irrigation investment. Title deeds,<br />
in particular, should be readily available.<br />
iv) L<strong>and</strong> for irrigation investment should be in reasonable size blocks of say about 4,000 ha for<br />
large scale farming <strong>and</strong> 500 to 1,000 ha for medium scale farming (this latter being largely for<br />
39