<strong>Boggs</strong> <strong>Mountain</strong> <strong>Demonstration</strong> <strong>State</strong> <strong>Forest</strong> <strong>Draft</strong> Management Plan, June 2008<br />

ROAD 501<br />

Mileage begins at the junction of Road 210 and proceeds south to junction of Road 500.<br />

Site 1: Mile 0.0 to 0.2 (1056 ft.)<br />

Priority: High<br />

This section of road is insloped with an outside berm. Drainage structures are mainly waterbars,<br />

which are degraded and only partially functional. Some rilling is occuring on road surface<br />

resulting in exposed rocks and roots. Water bars need to be maintained, especially at the .2 mile<br />

mark.<br />

Remedial treatments include:<br />

1. Outslope road<br />

2. Install rolling dips<br />

3. Excavate outside berm and smooth over roadway<br />

4. Armor outfalls<br />

Site 2: Mile 0.2 to 0.3 (528 ft.)<br />

Priority: High<br />

This section of road was constructed on a flat hillslope with no cross-grade. Waterbars are the<br />

drainage structures in place and are functioning properly; however, winter use has degraded the<br />

road bed. The road surface has low rock content, so erosion potential is high. The road grade in<br />

this section is approx. 1-2%. Road grade is nearly flat, some exposed rocks.<br />

Remedial treatments include:<br />

1. Crown or slope road surface<br />

2. Install sharp-angled rolling waterbars<br />

3. Armor waterbar outfalls with rock<br />

4. Excavate outside berm and smooth over roadway<br />

5. Rock surface<br />

6. Re-route road<br />

Site 3: 0.3 to 0.4 (528 ft.)<br />

Priority: High<br />

This section of road is insloped with an outside berm. There is no inboard ditch in this section.<br />

Existing waterbars are responsible for all road surface drainage. Road grade on this section is<br />

approx. 12%<br />

Remedial treatments include:<br />

1. Outslope road surface<br />

2. Replace existing waterbars with rolling dips<br />

3. Excavate outside berm and smooth over roadway<br />

4. Armor drainage outlets<br />

74