i. The GFA (Gross Fixed Assets) of Rs. 12,232 Crores, as per transfer scheme, has<br />

been considered as opening balance as on 1st November 2010 which also<br />

includes SLDC.<br />

ii. For the purpose of Return on Equity, Equity Capital of Rs. 1928 Crores has been<br />

considered as per the second provisional transfer scheme. The RoE has been<br />

calculated based on the opening balance as notified for the transmission<br />

business.<br />

iii. Long Term Loan has been considered as Rs. 12348 Crores in line with the<br />

notified balance sheet and interest is calculated on the actual basis which was<br />

accrued from 1 st November 2010 to 31 st March 2011. Some of the generic<br />

loans such as bonds, loan from HUDCO, LIC, Tamil Nadu Powerfin and Medium<br />

Term Loan is availed by erstwhile TNEB and has been considered as the long<br />

term loan of TANTRANSCO.<br />

iv. TANTRANSCO submits that the opening balance sheet as per second<br />

provisional transfer scheme has been considered for the calculation of ARR in<br />

the given tariff petition.<br />

v. TANTRANSCO submits to the Hon’ble Commission that once the final transfer<br />

scheme is notified by the State Government, the revision in the opening<br />

balance of Fixed Assets, Loan and equity may be allowed which will have a<br />

resultant effect on the Depreciation, Interest on Loan and equity.<br />

TANTRANSCO request the Hon’ble Commission to allow such expenses with<br />

retrospective effect and allow to adjust in the ARR in the next tariff petition or<br />

at the time of separate petition which can be filed by TANTRANSCO. The<br />

direction of the Hon’ble Commission is requested for the same.<br />

vi. The revenue from open access is only from consumer using the transmission<br />

system of TANTRANSCO. All customers seeking open access to Transmission<br />

System are classified under two categories i.e. long term open access<br />

customers and short term open access customers. Currently as per the<br />

direction provided in the tariff order of the TANGEDCO dated 30 th March 2012,<br />

the transmission charges as determined for TANTRANSCO is recovered in a<br />

monthly installments from TANGEDCO.<br />

vii. In the event, the Government of Tamil Nadu issues the final Notification for<br />

transfer of assets and liabilities to the successor Utilities under rule 9(1) of<br />

Tamil Nadu Power Sector Reforms Transfer Scheme, 2010, during the<br />

pendency of this petition, TANTRANSCO shall submit revised figures of the ARR<br />

and tariff for consideration of the Hon’ble Commission.<br />