16.7 Where the quantity or value set out in Scope <strong>of</strong> <strong>Services</strong> is described as ‘approximate’ it shall be<br />

regarded only as an estimate <strong>of</strong> the quantity or value which may be required under this <strong>Contract</strong> and the<br />

Principal shall not be required to take or accept said nominated approximate quantity or value <strong>of</strong><br />

<strong>Services</strong>.<br />

16.8 The <strong>Contract</strong>or acknowledges and agrees that the Principal may enter into arrangements or agreements<br />

with third parties for the purchase <strong>of</strong> goods or <strong>Services</strong> the same as and/or similar to the Goods and/or<br />

<strong>Services</strong>.<br />

16.9 If the <strong>Contract</strong>or:<br />

(a)<br />

(b)<br />

delivers more Goods than the quantity specified in this <strong>Contract</strong>, the Principal may return any<br />

quantity <strong>of</strong> Goods provided by the <strong>Contract</strong>or in excess <strong>of</strong> that specified in this <strong>Contract</strong> to the<br />

<strong>Contract</strong>or at the <strong>Contract</strong>or's sole risk and expense; or<br />

performs more <strong>Services</strong> than the quantity specified in this <strong>Contract</strong>, the Principal is not liable to<br />

pay for the additional quantity.<br />

17 PLANT AND EQUIPMENT<br />

17.1 The <strong>Contract</strong>or must provide (at its cost) all Plant and Equipment, labour and haulage necessary for the<br />

performance <strong>of</strong> the <strong>Contract</strong>or’s obligations under this <strong>Contract</strong>.<br />

17.2 The <strong>Contract</strong>or must ensure that all Plant and Equipment and any other items which the <strong>Contract</strong>or uses<br />

or supplies in conjunction with the <strong>Services</strong> are <strong>of</strong> merchantable quality, comply with this <strong>Contract</strong> and all<br />

Legislative Requirements, and are fit for their usual and intended purpose.<br />

18 TIME FOR PERFORMANCE AND EXTENSIONS OF TIME<br />

18.1 The <strong>Contract</strong>or shall deliver the Goods in full to the Delivery Points and perform the <strong>Services</strong> at the times<br />

stated in this <strong>Contract</strong>. In this respect time shall be <strong>of</strong> the essence <strong>of</strong> this <strong>Contract</strong>.<br />

18.2 Subject to Clauses 18.3, 18.4 and 18.5 and if the <strong>Services</strong> are unlikely to be completed and/or that the<br />

Goods will not be delivered to the Delivery Point by the Completion Date the <strong>Contract</strong>or is entitled to an<br />

extension to the Completion Date if the delay is due to:<br />

(a)<br />

(b)<br />

(c)<br />

(d)<br />

breach by the Principal <strong>of</strong> its obligations under this <strong>Contract</strong>;<br />

delay or disruption caused by the Principal or the Principal’s Representative, but does not<br />

include any delay or disruption caused by the Principal or the Principal’s Representative acting<br />

in accordance with this <strong>Contract</strong>;<br />

a Force Majeure Event occurring before the Completion Date;<br />

suspension <strong>of</strong> this <strong>Contract</strong> under Clause 28, other than suspension <strong>of</strong> this <strong>Contract</strong> for breach<br />

<strong>of</strong> this <strong>Contract</strong> by the <strong>Contract</strong>or or the <strong>Contract</strong>or’s Personnel; or<br />

(e) a Variation being granted under Clause 27.<br />

18.3 The <strong>Contract</strong>or may only claim an extension to the Date for Delivery under Clause 18.1 if the <strong>Contract</strong>or:<br />

(a)<br />

(b)<br />

(c)<br />

could not reasonably have been expected to foresee the delay at the date <strong>of</strong> signing this<br />

<strong>Contract</strong>;<br />

has taken all reasonable steps to mitigate the delay and the effect <strong>of</strong> the delay; and<br />

or the <strong>Contract</strong>or’s Personnel, did not cause the delay, whether by breach <strong>of</strong> this <strong>Contract</strong> or<br />

otherwise.