16.11.2012 Views

Analysis of Safety Approval Process Final Report WP2 - ERA

Analysis of Safety Approval Process Final Report WP2 - ERA

Analysis of Safety Approval Process Final Report WP2 - ERA

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Tender <strong>ERA</strong>/2006/ERTMS/OP/01<br />

Survey <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong>s for the first ERTMS implementations<br />

Subcontractors:<br />

<strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong><br />

<strong>Final</strong> <strong>Report</strong> <strong>WP2</strong>


Reference: BV-LZ-FW/KRTC316/<strong>WP2</strong><br />

Author<br />

Document <strong>Approval</strong><br />

Checker <strong>Approval</strong><br />

B. Vittorini F.Walenberg<br />

17 September 2007<br />

From the following organisations, the following persons contributed to the study:<br />

• KEMA Rail Transport Certification:<br />

o F. Walenberg, Project Manager<br />

o L. Zigterman, WP1-leader<br />

o R. te Pas<br />

• RINA:<br />

o F. Caruso, Technical Manager<br />

o B. Vittorini, <strong>WP2</strong>-leader<br />

• Cetren:<br />

o J. Figuera, WP4-leader<br />

o M. Carvajal<br />

o G. Moreno<br />

• Attica Advies:<br />

o J. Postmes, WP3-leader<br />

o H. Vas Visser<br />

o W. Oskam<br />

o J. Rimmelzwaan<br />

• EBC:<br />

o C. Glatt<br />

o H. Müller<br />

• Arsenal Research:<br />

o G. List<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

2/161


Summary<br />

This document contains a preliminary collection <strong>of</strong> information regarding the <strong>Safety</strong><br />

<strong>Approval</strong> <strong>Process</strong> followed in the different ERTMS projects included in the scope <strong>of</strong> this<br />

Project. The information is presented in a comparative format aiming at an easy outlining <strong>of</strong><br />

commonalities and differences. The process covers the system life cycle defined in the<br />

CENELEC Norm EN50126, although some <strong>of</strong> its phases may not be fully considered.<br />

The following main issues are included:<br />

• General information <strong>of</strong> the line under consideration;<br />

• System definition;<br />

• <strong>Safety</strong> aspects:<br />

o Risk analysis;<br />

o <strong>Safety</strong> requirements;<br />

o System requirements, including safety requirements for components, subsystems<br />

and operation;<br />

• Suppliers responsibility:<br />

o System design;<br />

o Manufacturing <strong>of</strong> generic components;<br />

o Installation, configuration and commissioning;<br />

• <strong>Approval</strong>:<br />

o Acceptance verification and tests;<br />

o Formal approval;<br />

• Operation, maintenance and monitoring <strong>of</strong> system performances in revenue service;<br />

• Modifications and retr<strong>of</strong>its.<br />

Note: The items in italics are not mandatory. The user <strong>of</strong> the guideline was asked to indicate<br />

why the “Non mandatory” subjects are not filled out (lack <strong>of</strong> information, unknown, not<br />

traceable etc.). In general, this information is deemed not necessary for the objectives <strong>of</strong> the<br />

study. The structure <strong>of</strong> this report contains the relevant chapter for each analysed project,<br />

even if it is not actually filled in for the above mentioned reasons.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

3/161


Contents<br />

SUMMARY......................................................................................................................................................... 3<br />

CONTENTS........................................................................................................................................................ 4<br />

1 PHASE 1 - SYSTEM CONCEPTS.......................................................................................................... 9<br />

1.1 SYSTEM CONTEXT.............................................................................................................................. 9<br />

The Austria-Italy project: the Brenner Basis Tunnel.................................................................................. 9<br />

The Austrian project: Vienna-Nickelsdorf .................................................................................................. 9<br />

The Belgian projects ................................................................................................................................. 10<br />

The French project: LGV-Est ................................................................................................................... 11<br />

The German project: Berlin-Halle-Leipzig............................................................................................... 13<br />

The Italian projects................................................................................................................................... 14<br />

The Dutch projects.................................................................................................................................... 17<br />

The Spanish projects................................................................................................................................. 21<br />

1.2 POLITICAL AND GEOGRAPHICAL CONSTRAINTS ............................................................................... 28<br />

The Austria-Italy project: the Brenner Basis Tunnel................................................................................ 28<br />

The Austrian project: Vienna-Nickelsdorf ................................................................................................ 30<br />

The Belgian projects ................................................................................................................................. 33<br />

The French project: LGV-Est ................................................................................................................... 36<br />

The German project: Berlin-Halle-Leipzig............................................................................................... 36<br />

The Italian Projects .................................................................................................................................. 38<br />

The Dutch projects.................................................................................................................................... 42<br />

The Spanish projects................................................................................................................................. 46<br />

1.3 SAFETY TARGETS / RAMS POLICY................................................................................................... 59<br />

The Austria-Italy project: the Brenner Basis Tunnel................................................................................ 59<br />

The Austrian project: Vienna – Nickelsdorf.............................................................................................. 60<br />

The Belgian projects ................................................................................................................................. 60<br />

The French project: LGV-Est ................................................................................................................... 61<br />

The German project: Berlin-HalleLeipzig................................................................................................ 61<br />

The Italian Projects .................................................................................................................................. 62<br />

The Dutch projects.................................................................................................................................... 62<br />

The Spanish projects................................................................................................................................. 65<br />

2 PHASE 2 - SYSTEM DEFINITION AND APPLICATION CONDITIONS .................................... 66<br />

2.1 THE MISSION PROFILE OF THE SYSTEM ............................................................................................. 66<br />

Austria-Italy project: Brenner Basis Tunnel project................................................................................. 66<br />

Austrian project: Vienna – Nickelsdorf .................................................................................................... 66<br />

The Belgian projects ................................................................................................................................. 67<br />

French project: LGV-Est .......................................................................................................................... 67<br />

German project: Berlin-HalleLeipzig....................................................................................................... 67<br />

The Italian Projects .................................................................................................................................. 69<br />

The Dutch projects.................................................................................................................................... 69<br />

The Spanish projects................................................................................................................................. 70<br />

2.2 THE SYSTEM DEFINITION.................................................................................................................. 71<br />

The Austria-Italy project: Brenner Basis Tunnel...................................................................................... 71<br />

The Austrian project: Vienna – Nickelsdorf.............................................................................................. 72<br />

The Belgian projects ................................................................................................................................. 72<br />

The French project: LGV-Est ................................................................................................................... 73<br />

The German project: Berlin-HalleLeipzig................................................................................................ 74<br />

The Italian Projects .................................................................................................................................. 76<br />

The Dutch projects.................................................................................................................................... 77<br />

The Spanish projects................................................................................................................................. 78<br />

3 PHASE 3 - RISK ANALYSIS................................................................................................................ 80<br />

3.1 HAZARD ANALYSIS AND SYSTEM LEVEL MITIGATIONS..................................................................... 80<br />

The Austria-Italy project: Brenner Basis Tunnel...................................................................................... 80<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

4/161


The Austrian project: Vienna – Nickelsdorf.............................................................................................. 80<br />

The Belgian projects ................................................................................................................................. 81<br />

The French project: LGV-Est ................................................................................................................... 81<br />

The German project: Berlin-Halle-Leipzig............................................................................................... 81<br />

The Italian Projects .................................................................................................................................. 83<br />

The Dutch projects.................................................................................................................................... 84<br />

The Spanish projects................................................................................................................................. 86<br />

3.2 SPECIFIC ISSUES ............................................................................................................................... 90<br />

The Austria-Italy project: Brenner Basis Tunnel...................................................................................... 90<br />

The Austrian project: Vienna – Nickelsdorf.............................................................................................. 90<br />

The Belgian projects ................................................................................................................................. 91<br />

The French project: LGV-Est ................................................................................................................... 91<br />

The German project: Berlin-HalleLeipzig................................................................................................ 91<br />

The Italian Projects .................................................................................................................................. 91<br />

The Dutch projects.................................................................................................................................... 92<br />

The Spanish projects................................................................................................................................. 92<br />

4 PHASE 4 - SYSTEM REQUIREMENTS............................................................................................. 94<br />

4.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL ................................................................ 94<br />

4.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF.......................................................................... 94<br />

4.3 THE BELGIAN PROJECTS................................................................................................................... 95<br />

4.4 THE FRENCH PROJECT: LGV-EST..................................................................................................... 95<br />

4.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG .............................................................................. 95<br />

4.6 THE ITALIAN PROJECTS.................................................................................................................... 95<br />

The Rome-Naples HSL.............................................................................................................................. 95<br />

The Torino-Novara HSL ........................................................................................................................... 96<br />

4.7 THE DUTCH PROJECTS...................................................................................................................... 96<br />

Betuweroute .............................................................................................................................................. 96<br />

Amsterdam - Utrecht................................................................................................................................. 96<br />

HSL ZUID................................................................................................................................................. 96<br />

4.8 THE SPANISH PROJECTS.................................................................................................................... 96<br />

5 PHASE 5 – APPORTIONMENT OF SYSTEM REQUIREMENTS................................................. 97<br />

5.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL ................................................................ 97<br />

5.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF.......................................................................... 97<br />

5.3 THE BELGIAN PROJECTS................................................................................................................... 97<br />

5.4 THE FRENCH PROJECT: LGV-EST..................................................................................................... 97<br />

5.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG .............................................................................. 97<br />

5.6 THE ITALIAN PROJECTS.................................................................................................................... 97<br />

The Rome-Naples HSL.............................................................................................................................. 97<br />

The Torino-Novara HSL ........................................................................................................................... 98<br />

5.7 THE DUTCH PROJECTS...................................................................................................................... 98<br />

Betuweroute .............................................................................................................................................. 98<br />

Amsterdam - Utrecht................................................................................................................................. 98<br />

HSL ZUID................................................................................................................................................. 99<br />

5.8 THE SPANISH PROJECTS.................................................................................................................... 99<br />

6 PHASE 6 – DESIGN AND IMPLEMENTATION ............................................................................ 100<br />

6.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 100<br />

6.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF........................................................................ 100<br />

6.3 THE BELGIAN PROJECTS................................................................................................................. 100<br />

6.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 100<br />

6.5 THE GERMAN PROJECT: BERLIN-HALLE-LEIPZIG........................................................................... 100<br />

6.6 THE ITALIAN PROJECTS.................................................................................................................. 100<br />

The Rome-Naples HSL............................................................................................................................ 100<br />

The Torino-Novara HSL ......................................................................................................................... 103<br />

6.7 THE DUTCH PROJECTS.................................................................................................................... 104<br />

Betuweroute ............................................................................................................................................ 104<br />

Amsterdam - Utrecht............................................................................................................................... 104<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

5/161


HSL ZUID............................................................................................................................................... 104<br />

6.8 THE SPANISH PROJECTS.................................................................................................................. 104<br />

7 PHASE 7 – MANUFACTURING........................................................................................................ 105<br />

7.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 105<br />

7.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF........................................................................ 105<br />

7.3 THE BELGIAN PROJECTS................................................................................................................. 105<br />

7.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 105<br />

7.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG ............................................................................ 105<br />

7.6 THE ITALIAN PROJECTS.................................................................................................................. 105<br />

The Rome-Naples HSL............................................................................................................................ 105<br />

The Torino-Novara HSL ......................................................................................................................... 106<br />

7.7 THE DUTCH PROJECTS.................................................................................................................... 106<br />

Betuweroute ............................................................................................................................................ 106<br />

Amsterdam - Utrecht............................................................................................................................... 106<br />

HSL ZUID............................................................................................................................................... 106<br />

7.8 THE SPANISH PROJECTS.................................................................................................................. 106<br />

8 PHASE 8 – INSTALLATION.............................................................................................................. 107<br />

8.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 107<br />

8.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF........................................................................ 107<br />

8.3 THE BELGIAN PROJECTS................................................................................................................. 107<br />

8.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 107<br />

8.5 THE GERMAN PROJECT: BERLIN-HALLE-LEIPZIG........................................................................... 107<br />

8.6 THE ITALIAN PROJECTS.................................................................................................................. 108<br />

The Rome-Naples HSL............................................................................................................................ 108<br />

The Torino-Novara HSL ......................................................................................................................... 108<br />

8.7 THE DUTCH PROJECTS.................................................................................................................... 108<br />

Betuweroute ............................................................................................................................................ 108<br />

Amsterdam - Utrecht............................................................................................................................... 108<br />

HSL ZUID............................................................................................................................................... 108<br />

8.8 THE SPANISH PROJECTS.................................................................................................................. 108<br />

9 PHASE 9 – SYSTEM VALIDATION................................................................................................. 109<br />

9.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 109<br />

9.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF........................................................................ 109<br />

9.3 THE BELGIAN PROJECTS................................................................................................................. 110<br />

The L3 and the L4 HSL ........................................................................................................................... 110<br />

The ETCS Level 1 lines........................................................................................................................... 110<br />

9.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 111<br />

9.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG ............................................................................ 111<br />

9.6 THE ITALIAN PROJECTS.................................................................................................................. 111<br />

The Rome-Naples HSL............................................................................................................................ 111<br />

The Torino-Novara HSL/HCL ................................................................................................................ 113<br />

9.7 THE DUTCH PROJECTS.................................................................................................................... 114<br />

Betuweroute ............................................................................................................................................ 114<br />

Amsterdam- Utrecht- HSL ...................................................................................................................... 115<br />

HSL ZUID............................................................................................................................................... 115<br />

9.8 THE SPANISH PROJECTS.................................................................................................................. 115<br />

Validation&Verification guidelines ........................................................................................................ 115<br />

Validation procedure .............................................................................................................................. 116<br />

Compatibility and Interoperability issues............................................................................................... 117<br />

10 PHASE 10 – SYSTEM ACCEPTANCE ............................................................................................. 119<br />

10.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 119<br />

10.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF........................................................................ 119<br />

10.3 THE BELGIAN PROJECTS................................................................................................................. 119<br />

The L3 and the L4 HSL ........................................................................................................................... 119<br />

The ETCS Level 1 lines........................................................................................................................... 120<br />

10.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 120<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

6/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


10.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG ............................................................................ 121<br />

10.6 THE ITALIAN PROJECTS.................................................................................................................. 122<br />

The Rome-Naples HSL............................................................................................................................ 122<br />

Torino-Novara HSL/HCL ....................................................................................................................... 123<br />

10.7 THE DUTCH PROJECTS.................................................................................................................... 124<br />

Betuweroute ............................................................................................................................................ 124<br />

Amsterdam - Utrecht............................................................................................................................... 125<br />

HSL ZUID............................................................................................................................................... 125<br />

10.8 THE SPANISH PROJECTS.................................................................................................................. 127<br />

Complementary tests............................................................................................................................... 127<br />

11 PHASES 11-12 OP<strong>ERA</strong>TION, MAINTENANCE AND MONITORING ...................................... 129<br />

11.1 THE AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL .............................................................. 129<br />

11.2 THE AUSTRIAN PROJECT: VIENNA – NICKELSDORF........................................................................ 129<br />

11.3 THE BELGIAN PROJECTS................................................................................................................. 129<br />

The L3 and the L4 HSL ........................................................................................................................... 129<br />

Belgian ETCS level 1 lines...................................................................................................................... 129<br />

11.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 130<br />

11.5 THE GERMAN PROJECT: BERLIN-HALLELEIPZIG ............................................................................ 130<br />

11.6 THE ITALIAN PROJECTS.................................................................................................................. 130<br />

The Rome-Naples HSL............................................................................................................................ 130<br />

Torino-Novara HSL ................................................................................................................................ 130<br />

11.7 THE DUTCH PROJECTS.................................................................................................................... 130<br />

Betuweroute ............................................................................................................................................ 130<br />

Amsterdam - Utrecht............................................................................................................................... 130<br />

HSL ZUID............................................................................................................................................... 130<br />

11.8 THE SPANISH PROJECTS.................................................................................................................. 130<br />

12 PHASE 13 – MODIFICATION AND RETROFIT............................................................................ 132<br />

12.1 AUSTRIA-ITALY PROJECT: BRENNER BASIS TUNNEL PROJECT ....................................................... 132<br />

12.2 VIENNA-NICKELSDORF .................................................................................................................. 132<br />

12.3 THE BELGIAN PROJECTS................................................................................................................. 132<br />

12.4 THE FRENCH PROJECT: LGV-EST................................................................................................... 132<br />

12.5 THE GERMAN PROJECT: BERLIN-HALLE-LEIPZIG........................................................................... 132<br />

12.6 THE ITALIAN PROJECTS.................................................................................................................. 133<br />

The Rome-Naples HSL............................................................................................................................ 133<br />

Torino-Novara HSL ................................................................................................................................ 133<br />

12.7 THE DUTCH PROJECTS.................................................................................................................... 133<br />

Betuweroute ............................................................................................................................................ 133<br />

Utrecht-Amsterdam HSL......................................................................................................................... 133<br />

HSL ZUID............................................................................................................................................... 133<br />

12.8 THE SPANISH PROJECTS.................................................................................................................. 133<br />

13 ANNEX .................................................................................................................................................. 134<br />

13.1 REFERENCES FOR THE AUSTRIAN PROJECTS .................................................................................. 134<br />

13.2 REFERENCES FOR THE GERMAN PROJECTS ..................................................................................... 134<br />

European Directives, Standards and Specifications...............................................................................134<br />

National Rules & Regulations................................................................................................................. 135<br />

DBAG Regulations................................................................................................................................. 135<br />

DBAG Pilot Documentation .................................................................................................................. 135<br />

Suppliers´ (“Consortium”) Documentation (RBC Docu as an example) ............................................... 136<br />

Verification & Validation ....................................................................................................................... 138<br />

Assessment .............................................................................................................................................. 138<br />

<strong>Approval</strong> & Acceptance .......................................................................................................................... 138<br />

Conformity .............................................................................................................................................. 141<br />

13.3 REFERENCES FOR THE ITALIAN PROJECTS ...................................................................................... 141<br />

Laws and Norms ..................................................................................................................................... 141<br />

European Norms and Standards............................................................................................................. 142<br />

RFI Norms and Standards ...................................................................................................................... 142<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

7/161


13.4 SPECIFIC REFERENCES FOR THE TURIN-NOVARA PROJECT ............................................................ 149<br />

RFI Specifications and assessment documents ....................................................................................... 149<br />

Suppliers Documents .............................................................................................................................. 154<br />

13.5 REFERENCES FOR THE DUTCH AND BELGIAN PROJECTS ................................................................. 156<br />

13.6 REFERENCES FOR THE SPANISH PROJECTS...................................................................................... 156<br />

LIST OF ABBREVIATIONS AND ACRONYMS...................................................................................... 157<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

8/161


1 Phase 1 - System Concepts<br />

1.1 System Context<br />

This section is intended to provide the following information:<br />

• Official identification <strong>of</strong> each individual project under consideration.<br />

• Project organisation: the infrastructure owner, the railway authority 1 , the system<br />

integrator, the train operators, the safety authority, the independent safety assessors,<br />

and the notified bodies.<br />

• Roles and responsibilities <strong>of</strong> each entity.<br />

The Austria-Italy project: the Brenner Basis Tunnel<br />

The line, presently in the final design phase, constitutes the central part <strong>of</strong> the Verona-<br />

Munich line that will be integrated in the TEN Corridor 1 from Berlin to Palermo. It is 55.6<br />

km long (32.6 km in Austria and 23 km in Italy) within a twin, single rail tunnel system<br />

from Fortezza-Italy to Innsbruck-Austria (circulation at left in Italy, at right in Austria).<br />

It is foreseen for mixed traffic: High speed traffic (200 km/h) for international passenger<br />

transport (20% <strong>of</strong> the overall traffic), conventional light (160 km/h) and heavy (100 km/h)<br />

freight trains (80% <strong>of</strong> the traffic). Traffic forecast: 140 trains per day and per running<br />

direction. The minimum heading has been set to 7.5 minutes. The line will be powered at<br />

2x25 kV/50 Hz.<br />

The Parties involved are:<br />

• Inframanager: BBT SE (Brenner Basis Tunnel, a company owned by RFI, OEBB<br />

and the Tyrolean Region)<br />

• System design: PGBB (an Austro-Italian Consortium)<br />

• Design Verification: RABBIT Consortium (RINA-ARSENAL) assessing the<br />

conformity <strong>of</strong> the design to the CC&S TSI and to the applicable Austro-Italian<br />

Norms and Specifications.<br />

• Operating companies: N/A in this phase<br />

• Suppliers: N/A in this phase<br />

The Austrian project: Vienna-Nickelsdorf<br />

The line characteristics are:<br />

• Conventional line from Vienna Southern Railway station (km 3.659) to Hungarian<br />

border after Nickelsdorf (km 67.506). It constitutes the Austrian part <strong>of</strong> the Vienna –<br />

Budapest line. As the station in Vienna (Vienna central station / Wien<br />

Zentralbahnh<strong>of</strong>) has currently started to be rebuilt, the line will be equipped into the<br />

station at a later time.<br />

1<br />

The term “Railway authority” is used here to refer to the body that is in charge <strong>of</strong> the safety approval<br />

according to the national law or regulations (sometimes not yet compliant with the Directives). This could be<br />

for instance an Infrastructure Manager, a NSA or an other body.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

9/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


• Rolling Stock: 13 (already nationally approved) locos <strong>of</strong> type 1116 are to be<br />

equipped with ETCS equipment<br />

The involved parties are:<br />

• Infrastructure owner: ÖBB BAU AG<br />

• Inframanager: ÖBB Betrieb AG<br />

• System integrator: ARGE Euroloop - contract with ÖBB<br />

• Suppliers: ARGE Euroloop consisting <strong>of</strong> Siemens AG-Österreich, responsible for the<br />

train-borne system and a small part <strong>of</strong> the trackside system and Thales (until end <strong>of</strong><br />

2006: Alcatel Austria AG), responsible for the large extent <strong>of</strong> the trackside<br />

subsystem) - contract with ÖBB<br />

• Train operators: ÖBB Traktion (currently the only one to be equipped with ETCS),<br />

Gysev, Wiener Lokalbahnen (WLB) - licenced railway undertakings<br />

• <strong>Safety</strong> Authority: Federal Ministry <strong>of</strong> traffic and information technologiesresponsible<br />

by law<br />

• Independent <strong>Safety</strong> Assessors: IPW - contract with manufacturer<br />

• Notified Body: Arsenal Research (0894) - contract with ÖBB<br />

The Belgian projects<br />

The L3 and the L4 HSL<br />

The high speed lines L3 (Luik – German/Belgian border) and L4 (Antwerp – Dutch/Belgian<br />

border) are built to achieve a performance <strong>of</strong> up to 300 km/h and a 3-minute headway under<br />

continuous speed supervision provided by ERTMS/ETCS Level 2. The ERTMS/ETCS<br />

Level 2 is supplemented with ERTMS/ETCS Level 1, which takes over in case the former<br />

experiences a failure, while <strong>of</strong>fering parallel operations in a mixed level application.<br />

These two separate lines are divided into three structural and two functional subsystems.<br />

These subsystems are subject to EC verification against their respective Technical<br />

Specifications <strong>of</strong> Interoperability (TSI) <strong>of</strong> Directive 96/48/EC.<br />

The L3 line is 139 km long, while the L4 line is 87 km long.<br />

Infrabel, part <strong>of</strong> NMBS-Holding, is the Infrastructure operator since January 1 st 2005.<br />

Infrabel is controlled by the Belgian Federal State. NMBS-Holding also exploits the train<br />

operation (NMBS).<br />

Certifer is the Notified Body for the L3 and the L4 lines, whereas Belgorail is the NoBo for<br />

the rest <strong>of</strong> the network and assessor <strong>of</strong> national functionalities (also for L3 and L4). Certifer<br />

also checks or prepares every decision (<strong>Safety</strong> Assessment) that is taken by a division <strong>of</strong> the<br />

responsible Ministry that acts as National <strong>Safety</strong> Authority (NSA).<br />

The ETCS Level 1 conventional lines<br />

The project concerns the roll-out <strong>of</strong> ETCS Level 1 (just the equipment) over the Belgian<br />

conventional railway network.<br />

The infrastructure owner/manager is Infrabel, which is part <strong>of</strong> the NMBS (SNCB) holding.<br />

The main train operator involved is NMBS (SNCB), which is the other entity under the<br />

NMBS (SNCB) holding.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

10/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


The <strong>Safety</strong> Authority is currently being organised within the Ministry <strong>of</strong> Transportation.<br />

For phase 2, KEMA Rail Transport Certification is the ISA and the Notified Body for the<br />

trackside equipment.<br />

The French project: LGV-Est<br />

This project is identified as « Pilote ERTMS Est Européen » (pilot East European ERTMS)<br />

(PEEE).<br />

This high speed line will connect Paris-Gare de l’Est to Frankfurt Main Station. In the final<br />

stage <strong>of</strong> implementation it will be 406 km long.<br />

The following project information has been derived from the PEEE <strong>Safety</strong> Plan [ “Project<br />

PEEE sous project Equipement Sol, plan de securité, v 02, 16 nov. 2004).<br />

Role and responsibilities <strong>of</strong> the involved organisations are as follows (see Figure 1):<br />

• The Infrastructure Owner is RFF (Réseau Ferré de France)<br />

• The National <strong>Safety</strong> Authority is SIST (Securité des Infrastructures)<br />

• The Notified Body is CERTIFER<br />

• The Independent <strong>Safety</strong> Assessor for the trackside systems is SNCF<br />

• The Independent <strong>Safety</strong> Assessor for the train borne systems is SNCF<br />

• The Independent <strong>Safety</strong> Assessor for the Integral <strong>Safety</strong> is SNCF<br />

The evaluation is carried out at two levels:<br />

• A safety team from SNCF engineering division ensures the overall coherence <strong>of</strong><br />

safety. The safety team’s tasks are described in the table below.<br />

• RFF has entrusted CERTIFER with the evaluation <strong>of</strong> the ERTMS system in the<br />

framework <strong>of</strong> the OSTI contract & Notified Body. (ref: Project PEEE: Sub-project<br />

<strong>Safety</strong> Plan Equipment, F3SJ0601, v. 011).<br />

RFF is the owner <strong>of</strong> LGV Est and the promoter <strong>of</strong> the PEEE project, and as such is<br />

responsible for safety on these projects.<br />

RFF entrusts the supply and implementation <strong>of</strong> equipment to LGV EST Européen to the<br />

manufacturers, who must provide evidence <strong>of</strong> the assured safety <strong>of</strong> the equipment delivered.<br />

In accordance with European regulations, this evidence must be evaluated by an<br />

independent organisation.<br />

RFF entrusts SNCF direction de l’Ingénierie (engineering division) with study and works<br />

management assignments, known as ‘engineering assignments’.<br />

In the context <strong>of</strong> the engineering assignments SNCF must in particular:<br />

• ensure, validate and approve the sub-system project,<br />

• establish all operational rules,<br />

• evaluate the safety evidence supplied by the manufacturers for each delivered<br />

component,<br />

• provide evidence to RFF that all safety requirements are complied with in the system<br />

(all components delivered to RFF).<br />

The tasks described above are also known as ‘integration tasks’.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

11/161


In observance <strong>of</strong> the decree [SRFN] RFF entrusts an OSTI (Certifer) with the task <strong>of</strong><br />

evaluating safety on the whole project. Certifer will also ensure the Notified Body<br />

assignment and must issue an EC verification declaration certifying that the command &<br />

control and signals sub-system complies with the provisions <strong>of</strong> decree 2001-129 (pending<br />

transposition <strong>of</strong> the directive 96/48/EC).<br />

An “Engineering Activities <strong>Safety</strong> File” is prepared on all the activities contributing to the<br />

demonstration and construction <strong>of</strong> industrial and engineering safety in the context <strong>of</strong> the<br />

PEEE.<br />

RFF supplies this file, which is subject to evaluation by CERTIFER (OSTI and ON), to<br />

SNCF IES who prepares the <strong>Safety</strong> File.<br />

RFF promotor <strong>of</strong> LPEEE projet, owner <strong>of</strong> LGV<br />

Est project<br />

Manufacturers<br />

Figure 1 – LPEE Project organisation<br />

SNCF Engineering<br />

OSTI/ON<br />

SNCF IES<br />

The engineering activities <strong>of</strong> the PEEE trackside project are entrusted to the ERTMS sector<br />

<strong>of</strong> technical division <strong>of</strong> engineering division. The ERTMS head <strong>of</strong> sector, the Project<br />

Manager, is responsible for the safety <strong>of</strong> the PEEE sub-project and must set up the<br />

organisation and means necessary for safety in all the activities <strong>of</strong> the PEEE sub-project in<br />

accordance with this plan.<br />

The OSTI/ON awarded for this project is Certifer. The identification number assigned by the<br />

European Commission is 942 (Notified Body - directive 96/48). The COFRAC accreditation<br />

certification number is 5-0023 (standard NF EN 45011 and COFRAC application rules –<br />

Section D – under section DM – Transport Materials). This accreditation is valid until<br />

31/11/2008.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

12/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


The German project: Berlin-Halle-Leipzig<br />

The line identification is “B-H/L”, Berlin-Halle-Leipzig.<br />

The infrastructure owner <strong>of</strong> the BHL line is “Deutsche Bahn Netz AG” (Theodor-Heuss-<br />

Allee 7, D-60486 Frankfurt am Main).<br />

The railway authority acting as a contact person and legal entity for all aspects like concept<br />

preparation, development, operational questions, etc. for the BHL project is the “Deutsche<br />

Bahn AG” (Potsdamer Platz 2, D-10785 Berlin) and their subsidiary companies,<br />

respectively.<br />

No "system integrator" has been explicitely defined, however the customer was undertaking<br />

most tasks <strong>of</strong> integration. The suppliers´ consortium as well played an important role in the<br />

processes <strong>of</strong> system integration. According to TSI CCS the railway undertaking and<br />

infrastructure manager have to declare conformity and EC-verification. Both acts <strong>of</strong><br />

declaration are planned to be committed to the suppliers´ consortium. More detailed<br />

information on this intention is not available in the moment.<br />

For the moment “DB Fernverkehr AG” (Stephensonstr. 1, D-60326 Frankfurt am Main),<br />

“DB Regio AG” (Stephensonstr. 1, D-60326 Frankfurt am Main), “Railion Deutschland<br />

AG” (Rheinstr. 2, D-55116 Mainz), “InterConnex” (Ostseeland Verkehr GmbH,<br />

Ludwigsluster Chaussee 72, D-19061 Schwerin) and “Dispolok GmbH” (Georg-<br />

Reismüllerstr. 32, D-80999 München) are present on the BHL line as railway undertakings.<br />

The safety authority charged with the national approval and acceptance procedures for BHL<br />

is the “Eisenbahn-Bundesamt EBA” (Vorgebirgsstr. 49, D-53119 Bonn).<br />

Nearly all verification, validation and assessment according to the refernced CENELEC<br />

norms (see Chap. 13.2) have been performed by inhouse test control centres<br />

("Prüfleitstelle" PLS) <strong>of</strong> the two main components´ suppliers SIEMENS and<br />

ALCATEL/THALES. Both have been accredited as Qualified Development Organisations<br />

("Qualifizierter Entwicklungsbetrieb") by the EBA, additionally fulfilling the requirements<br />

<strong>of</strong> [DB 9]. Hence they are permitted to operate their own - yet independent (conforming [DB<br />

4], [DB 5], [DB 6]) - proving and test departments for verification, validation and<br />

assessment tasks. Independency <strong>of</strong> verification, validation and assessment is ensured by<br />

self-responsibility and stringent EBA control. Some audits (according to module D, [DB<br />

16]) have been performed by TÜV InterTraffic GmbH (TÜV Rheinland Group).<br />

“Eisenbahn Cert EBC” (Vorgebirgsstr. 43, D-53119 Bonn) acts as “Notified Body<br />

Interoperability” according to EC directives, as well as to the national regulations [DB 19],<br />

[DB 20], that transfered the interoperability directives into German regulation. The EBC -<br />

located at the Eisenbahn-Bundesamt (EBA) and accredited as independent and autonomous<br />

organisation under public law – was commissioned for the conformity and EC examinations<br />

for both trackside and onboard equipment. However the two PLSs were subcontracted by<br />

EBC to perform most <strong>of</strong> the examinations. Some audits have been done by EBC himself or<br />

TÜV InterTraffic GmbH. EBC did not perform any technical examinations for BHL.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

13/161


The Italian projects<br />

The Rome-Naples HSL<br />

The Rome-Naples HSL is a section <strong>of</strong> the High Speed / High Capacity Line Milan-Naples.<br />

The entities/companies involved in the project and their roles are listed in the following<br />

Table 1.<br />

Company Role<br />

RFI Customer, <strong>Safety</strong> Authority, Railway Authority, <strong>Safety</strong> Assessor<br />

TAV Purchaser<br />

ITALFERR Work Director<br />

IRICAV General Contractor<br />

TRENITALIA Train Operator<br />

SATURNO Technological System Integrator and Trackside Subsystem Valuator. Saturno is a<br />

ANSALDO<br />

(ASF)<br />

consortium including Ansaldo, Alstom, Bombardier and Sirti.<br />

Supplier <strong>of</strong> Solid State Interlocking, Encoder and Eurobalise. For the supplied products –<br />

subsystems the company performed Design, Verification and Validation activities for the<br />

Generic Product, Generic and Specific Application. ASF supplied also the traffic<br />

supervisory system (SIL 0 system)<br />

ALSTOM Supplier <strong>of</strong> On-Board subsystem, RBC subsystem and wayside track-circuit sub-system.<br />

For the supplied products – subsystems the Company performed Design, Verification and<br />

Validation activities for the Generic Product, Generic and Specific Application.<br />

BOMBARDIER Supplier <strong>of</strong> Hot Axel Box Detector and Braked Wheels Detector subsystem<br />

SIRTI Supplier <strong>of</strong> Telecommunication sub-system (Long Distance network and GSM-R network<br />

– Nortel Technology)<br />

Table 1 – Entities/Companies involved in Rome-Naples HSL<br />

The RFI “Direzione Movimento” and “Direzione Manutenzione” are the Customers.<br />

Different departments <strong>of</strong> “Direzione Tecnica” had the following tasks:<br />

• System Requirement Specification delivery;<br />

• Assessment and Acceptance <strong>of</strong> the system.<br />

The Rome and the Naples “Direzione Compartimentale Movimento” are the Railway<br />

Authorities supported by the corresponding “Direzioni Compartimentali Infrastrutture”.<br />

The tasks <strong>of</strong> each RFI structure are indicated with more details in the following table:<br />

Dept. Structure Task<br />

PATC System specification; functional assessment and<br />

acceptance; SDT, SST and SSB system homologation;<br />

products functional assessment and homologation<br />

PATC “Specificazione Requisiti di Sistema e System specification; functional assessment and<br />

Applicazione Sistemi ATC”<br />

acceptance<br />

PATC “Omologazione Sottosistema di Terra<br />

(SDT/SST)“<br />

SDT/SST functional assessment and acceptance<br />

PATC “Omologazione Sottosistema di Bordo SDT/SSB functional assessment and acceptance<br />

(SDT/SSB)“<br />

PATC “Prodotti a Tecnologia Innovativa“ Product functional assessment and acceptance<br />

CESIFER SSB functional assessment and acceptance<br />

PACS Interlocking System functional assessment and acceptance<br />

CC Systems, subsystems, products <strong>Safety</strong> Integrity Level<br />

assessment; assessment <strong>of</strong> systems and components<br />

interoperability.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

14/161


Dept. Structure Task<br />

CC “Valutazione di Sicurezza (Assessment) “ Systems, subsystems, products <strong>Safety</strong> Integrity Level<br />

assessment<br />

CC “Certificazione Standard di Interoperabilità“ Assessment <strong>of</strong> systems and components interoperability.<br />

SS “Impianti“ Interlocking logic assessment and homologation<br />

SS “Tecnologie di Base Hot Axle Box Detector System and wayside objects<br />

assessment and homologation<br />

Table 2 - RFI departments related to the Rome-Neaples HSL Project<br />

The responsibilities <strong>of</strong> the RFI structures in the assessment process are shown with more<br />

details in the following Figure 2, Figure 3 and Figure 4.<br />

GA ETCS System - CC<br />

GA SST SDT - CC<br />

GA SDT<br />

CC - CSI<br />

GP RBC - CC<br />

GP RBC<br />

CC - CSI<br />

GP RBC<br />

CC - VdS<br />

GP RBC<br />

PATC - PTI<br />

Coulor Meaning:<br />

GA System -<br />

CC - VdS<br />

GA SDT<br />

CC - VdS<br />

Functional Assessment<br />

Interoperability Assessment<br />

<strong>Safety</strong> Assessment<br />

Overall Assessment<br />

GA SDT<br />

PATC - OSST<br />

Figure 2– Assessment process <strong>of</strong> the ETCS System<br />

GA SSB - CC<br />

GA SSB<br />

CC - VdS<br />

GP SSB - CC<br />

GP SSB<br />

CC - VdS<br />

GA System<br />

PATC - SRS<br />

GP SSB<br />

PATC - PTI<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

GA SSB<br />

PATC - OSST<br />

15/161


GA Interlocking Subsystem GdV - CC<br />

Coulor Meaning:<br />

Figure 3– Assessment process <strong>of</strong> the Interlocking System<br />

GA System SSAV - CC<br />

Coulor Meaning:<br />

GA SSAV<br />

CC - VdS<br />

Functional assessment<br />

<strong>Safety</strong> Assessment<br />

Overall Assessment<br />

GP NVP + GAT<br />

GP CC - VdS<br />

GP PACS- PTI<br />

Functional Assessment<br />

<strong>Safety</strong> Assessment<br />

Overall Assessment<br />

GA – CC VdS GA PACS<br />

Logic – SS I<br />

GA GdV<br />

(see f. 2)<br />

Wayside Objects<br />

SS - TB<br />

GA ETCS<br />

(see f. 1)<br />

GA SSAV<br />

DT<br />

Figure 4– Assessment process <strong>of</strong> the Rome-Naples CCS sub-system<br />

RTB System<br />

SS - TB<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

16/161


The Torino -Novara HSL<br />

The line characteristics are:<br />

• Typology: High speed/ High Capacity line for mixed passenger and freight trains<br />

linking Torino to Milano. The only section Torino-Novara is presently in operation<br />

at 300 km/h.<br />

• Maximum speed: 300 km/h<br />

The detailed organization is similar to the one in place for the Rome-Naples Project, with<br />

some differences in the suppliers.<br />

The involved parties are:<br />

• Infrastructure manager: RFI<br />

• <strong>Safety</strong> Authority: RFI<br />

• Assessor: RFI<br />

• Integration <strong>of</strong> existing rules with new rules applicable to ERTMS/ETCS Lev. 2: RFI<br />

and the Transportation Ministry.<br />

• Operating companies (to date): Trenitalia<br />

• General Contractor: Consortium CAVTOMI<br />

• System Integrator: Saturno Consortium composed <strong>of</strong> Ansaldo, Alstom, Bombardier<br />

and Sirti. In addition to System Integrator Saturno has also been the Trackside<br />

Subsystem Validator.<br />

• Suppliers:<br />

o Ansaldo Signal for RBC and Interlocking subsystem including ATIS audio<br />

frequency track circuit, Encoders and Eurobalises. For the supplied products<br />

– subsystems the company performed Design, Verification and Validation<br />

activities for the Generic Product, Generic and Specific Application. ASF<br />

supplied also the traffic supervisory system (SIL 0 system). The Ansaldo onboard<br />

sub-system is undergoing pre-operational acceptance tests.<br />

o Alstom Ferroviaria for the on board subsystem and wayside objects track<br />

circuits. For the supplied products – subsystems the Company performed<br />

Design, Verification and Validation activities for the Generic Product,<br />

Generic and Specific Application.<br />

o Bombardier for Hot Axle Detector and Braked Wheels Detector<br />

o Sirti for telecom subsystem including Long Distance Network and GSM-R<br />

Network (Siemens Technology)<br />

• EC Conformity verification: SciroTÜV Mod. SH2.<br />

• The organization <strong>of</strong> the assessment process has been very similar to the one adopted<br />

for the Rome –Naples line, described in the previous chapter.<br />

The Dutch projects<br />

Betuweroute<br />

The Betuweroute is a new international and domestic line designed for freight transport<br />

only. It is 160 km long and connects the Europe’s biggest harbour, Rotterdam, with the<br />

German border.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

17/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


It is equipped with a ERTMS Level 2 system only (no fall back). Some area’s, Kijfhoek en<br />

Zevenaar are equipped with ATB, the Dutch Legacy system, because in this area the<br />

Betuweroute is integrated in the national system.<br />

The line has been put into operation <strong>of</strong>ficially on June 16 th 2007 by the Dutch Queen. Until<br />

now, there is little operational experience.<br />

To date, the train-infrastructure integration tests have not yet been completed. Immediately<br />

after the <strong>of</strong>ficial opening <strong>of</strong> the line, trains were only allowed to enter into the line after the<br />

previous train had cleared it.<br />

Only the A15 section from Kijfhoek to Zevenaar (107 km) is equipped with ERTMS at this<br />

moment. The Western part (West <strong>of</strong> Rotterdam/Kijfhoek) will be equipped later.<br />

The number <strong>of</strong> trains per day will be limited heavily by the capacity <strong>of</strong> the German lines that<br />

connect the Dutch Betuweroute with the Corridor Rotterdam-Genoa.<br />

All trains will at least have to be equipped with ERTMS as there is no other system installed<br />

on the Betuweroute.<br />

About ten freight operating companies, such as Raillion by far the biggest one, will operate<br />

freight trains on the Betuweroute.<br />

Keyrail is a new company, established to manage the exploitation and maintenance <strong>of</strong> the<br />

Betuweroute, separately <strong>of</strong> the rest <strong>of</strong> the Dutch Infrastructure, managed by ProRail. ProRail<br />

however, still plays an important role in the transition <strong>of</strong> construction and tests to regular<br />

operating.<br />

The <strong>Safety</strong> Authority is IVW (www.ivw.nl). IVW which stands for “Inspectie Verkeer en<br />

Waterstaat”, is the National <strong>Safety</strong> Authority. It is a department <strong>of</strong> the Ministry <strong>of</strong><br />

Transportation, reporting directly to the Minister and is therefore independent <strong>of</strong> the<br />

Inframanager, Train Operating Companies and Suppliers. All infrastructures added to the<br />

Dutch infrastructure and all trains running on this infrastructure have to be admitted by this<br />

organisation.<br />

The trackside Supplier is the Consortium Alstom Movares<br />

Different safety assessors have been contracted for the integral Betuweroute project:<br />

• An ISA for the generic safety system Bev21(In this case the Dutch adaptation <strong>of</strong> an<br />

Alstom safety system)<br />

• An ISA for the Specific <strong>Safety</strong> Case <strong>of</strong> the Betuweroute. The BR A15 Trackside<br />

<strong>Safety</strong> Case is available, including ISA report, for Alstom Bev21 A15 v3.4<br />

configuration<br />

• Alstom has its own ISA for the <strong>Safety</strong> Case <strong>of</strong> its equipment included in the Bev21<br />

<strong>Safety</strong> Case.<br />

These companies are in al cases experienced independent companies on the area <strong>of</strong><br />

certification, contracted by each <strong>of</strong> the involved parties.<br />

Steps are not yet taken to have the track certified by a NoBo. Although the Infrastructure<br />

provider ProRail intends to approach the ideal situation as close as possible, the IMdeemes it<br />

impossible at this moment , due to the limited maturity <strong>of</strong> the TSI’s and lack <strong>of</strong> earlier<br />

references.<br />

The Trackside Assembly shall finally comply with ERTMS SRS vers. 2.3.0.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

18/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


At this moment about 100 locomotives (10 different types) are in different stages <strong>of</strong><br />

preparation for operation on the Betuweroute. Also in this case a process is followed that<br />

approaches the ERTMS type approval as close as possible.<br />

A starting requirement for the acceptance <strong>of</strong> a train type is a Declaration <strong>of</strong> Conformity <strong>of</strong><br />

all used ERTMS Interoperability Constituents, certified by a NoBo, and a Declaration <strong>of</strong><br />

Verification for the Train borne Subsystem, also certified by a NoBo, as well as a completed<br />

CENELEC <strong>Safety</strong> Case for the trainborne Command and Control On Board Assembly,<br />

assessed by an ISA, with no blocking findings.<br />

Amsterdam - Utrecht<br />

The Amsterdam – Utrecht is part <strong>of</strong> the Dutch Railway Network. Several operators (26) run<br />

on this line. The line has to fulfil all the present regulations <strong>of</strong> the existing railway network.<br />

ProRail – the infrastructure manager – is the system integrator as well.<br />

The maximum design speed for the line is 200 km/h. It is only for international and<br />

domestic passenger trains. The line speed is now 140 km/h.<br />

The line speed will be raised to 200 km/h when the trains and the infrastructure have<br />

switched over the traction voltage from 1500 Volt dc to 25 kV ac and the signaling system<br />

from ATB (ATP) to ERTMS level 2.<br />

The line is 30 km long and interconnects with the rest <strong>of</strong> the ProRail Network.<br />

The involved Parties are :<br />

• Infrastructure manager - ProRail<br />

• <strong>Safety</strong> Authority - Railway divison <strong>of</strong> IVW (Transport and Water management<br />

Inspectorate)<br />

• Suppliers Trackside: Bombardier has delivered the signalling equipment<br />

• Operating companies: There are at the moment 26 operators (International traffic,<br />

domestic passengers traffic and freight traffic)<br />

HSL ZUID<br />

Scope <strong>of</strong> the HSL ZUID project is the high speed transportation system at the south <strong>of</strong> the<br />

Netherlands towards Belgium.<br />

The HSL ZUID runs from Amsterdam via Schiphol and Rotterdam to the Belgian border,<br />

with connections to The Hague and Breda. On the HSL route, the high-speed trains run on<br />

newly laid, double track rails, wherever it is possible to travel at such high speeds. However,<br />

from Amsterdam to just beyond Schiphol Airport and at the other HSL stations, the high<br />

speed trains travel on existing tracks. Accordingly, the HSL line connects with existing lines<br />

in five locations: Ho<strong>of</strong>ddorp, Rotterdam-West , Rotterdam-Lombardijen, Zevenbergschen<br />

Hoek and Breda.<br />

Regular trains in the Netherlands use 1.5 kVdc and have a capacity <strong>of</strong> 6 MWatt. The high<br />

speed trains on the HSL-Zuid are fed with 25 kVac (50 Hz). Trains using both the regular<br />

Dutch network and the new European network must be able to switch between the two<br />

systems.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

19/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


Along the HSL track, spanning around 100 kilometres, no less than 170 civil engineering<br />

structures, such as viaducts, fly-overs, dive-unders, bridges and tunnels have been built.<br />

This Project has been contracted in several parts:<br />

• The Infraspeed provider for the superstructure including the CCS sub-system; the<br />

Infraspeed consortium delivers through a Design-Build-Finance-and-Maintain-<br />

Contract the Superstructure and provides the maintenance <strong>of</strong> superstructure and<br />

substructure over a period <strong>of</strong> 25 years. Payment <strong>of</strong> the Infraspeed Consortium will be<br />

related to the availability <strong>of</strong> the line.<br />

• The transport concession.<br />

• The contracts to provide the substructure.<br />

• The Railway Act: ProRail (Inframanager and also amongst others fulfilling the<br />

function <strong>of</strong> Traffic Control/Operation <strong>of</strong> the 25kV and Tunnel installations on the<br />

line.<br />

• The agreement with the Belgium State.<br />

The involved Parties are:<br />

• The Infrastructure Owner: the State <strong>of</strong> the Netherlands.<br />

• The Inframanager (=Railway Authority): ProRail (www.prorail.nl ).<br />

• The <strong>Safety</strong> Authority: the Railway division <strong>of</strong> the IVW (Transport and Water<br />

Management Inspectorate) (www.ivw.nl)<br />

• The train operator: the High Speed Alliance company - HSA (<br />

www.highspeedalliance.nl), with commercial name HIspeed (www.nshispeed.nl).<br />

• The system integrator: the project organisation HSL Zuid acting on behalf <strong>of</strong> the<br />

principal stakeholder, the State <strong>of</strong> the Netherlands<br />

• The Independent <strong>Safety</strong> Assessors:<br />

• For Infraspeed supplier <strong>of</strong> superstructure including CCS: Railcert and DeltaRail;<br />

• For HSA, the train operating company who has ordered rolling stock: safety<br />

assessors contracted by suppliers <strong>of</strong> the rolling stock.<br />

• The Notified Bodies:<br />

• For the trackside assembly: Railcert (www.railcert.nl )<br />

• For the trainside: suppliers <strong>of</strong> rolling stock who have contracted Lloyds.<br />

The Figure 5 below shows roles and responsibilities related to the CCS certification and<br />

safety approval.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

20/161


Integral <strong>Safety</strong> Case<br />

L 4 by Infrabel<br />

RWS / HSL<br />

Functionality<br />

Assessment<br />

Interoperability<br />

Assessment<br />

<strong>Safety</strong><br />

Assessment<br />

Integral <strong>Safety</strong> Case<br />

HSL Zuid traffic<br />

system<br />

Railcert (TÜV/EBC)<br />

Deltarail<br />

Availability Period <strong>Safety</strong><br />

Case<br />

Trackside assembly<br />

Overall Assessment<br />

RWS / HSL Lux-control<br />

IVW (inzetcertificaat)<br />

A il bilit P i d S ft<br />

Suppliers*<br />

Supplier*<br />

<strong>Safety</strong> case by supplier<br />

On board assembly<br />

Figure 5 – Relationship between diferent bodies in HSL ZUID<br />

RWS / HSL<br />

To be done by suppliers <strong>of</strong> rolling stock;<br />

Generic Application<br />

<strong>Safety</strong><br />

Case & Specific<br />

Application <strong>Safety</strong><br />

Case for conv. track<br />

• V250: Ansaldo delivers a certified train including<br />

ERTMS<br />

• Traxx: certified train delivered by Angels Trains,<br />

certification by Lloyds<br />

• Thalys, certified by France, Lloyds certified the<br />

STM-ATB<br />

The Integral <strong>Safety</strong> Case <strong>of</strong> the L4 and the HSL<br />

Zuid have to be aligned in order to assure the safety <strong>of</strong><br />

the interface between the two lines<br />

The Spanish projects<br />

This report provides basic information related to the implementation and safety approval <strong>of</strong><br />

the ERTMS projects that are currently under different status <strong>of</strong> development in Spain. They<br />

include High Speed and Conventional Railways projects as well:<br />

• Madrid-Zaragoza-Barcelona that connects the two biggest Spanish cities<br />

(>4.000.000 inhabitants each), and will be extended up to the French border, fully<br />

equipped with ERTMS. In service the sections Madrid-Zaragoza-Lleida and Lleida-<br />

Roda de Bará (Tarragona). It will be completed by the end <strong>of</strong> the year 2007.<br />

Maximum speed in this moment is 300 Km/h. Maximum planned speed is 350<br />

Km/h.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

21/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


• La Sagra Toledo: a small branch with the singularity <strong>of</strong> being equipped with LZB +<br />

ERTMS. Maximum speed is 300 Km/h.<br />

• Figueras-Perpignan: ERTMS, crossig border Project. Maximum speed is 350 Km/h.<br />

• Córdoba-Málaga: the Córdoba-Antequera section is already in operation. It will be<br />

completed by the end <strong>of</strong> the year 2007).<br />

• Madrid-Valladolid: presently under construction.<br />

Ownership <strong>of</strong> the Spanish Infrastructure<br />

In Spain, there are several publicly- owned railway networks. The owners <strong>of</strong> these networks<br />

are the State, the Autonomous Regions, or the Railway Infrastructure Administrator (ADIF).<br />

Spanish State has full powers over the General Interest Railway Network (RFIG). The<br />

General Interest Railway Network comprises all the essential railway infrastructures<br />

necessary to guarantee a common transport system throughout the national territory, or<br />

infrastructures whose joint administration is necessary for the correct operation <strong>of</strong> the<br />

common transport system, such as those connecting to international traffic routes, linking<br />

different autonomous regions and their connections and accesses to the main population<br />

centres and transport nodes, or to facilities which are vital to the economy and national<br />

defence. The General Interest Railway Network includes all the railway infrastructures<br />

managed by RENFE, before its reconversion on 1 January 2005, and those whose<br />

management has been assigned to the ADIF or is the responsibility <strong>of</strong> the Ports Authority in<br />

the general interest ports. The metric gauge network managed by FEVE is also a part <strong>of</strong> the<br />

RFIG.<br />

The decisions as to the inclusion or exclusion <strong>of</strong> railway infrastructures in the RFIG must be<br />

approved by the Ministry <strong>of</strong> Public Works, with a prior report from the autonomous regions<br />

implicated, whenever this is justified for reasons <strong>of</strong> general interest. The autonomous<br />

regions may request the transfer <strong>of</strong> any infrastructures which are agreed to be excluded from<br />

the RFIG.<br />

On the other hand the Autonomous Regions may assume powers on railway infrastructures<br />

whose routes are situated entirely in their territories.<br />

The Ministry <strong>of</strong> Transport (“Ministerio de Fomento”)<br />

The Ministry <strong>of</strong> Transport is in charge <strong>of</strong> the administration <strong>of</strong> the railway sector as a whole.<br />

According to the Railway Sector Act 39/2003 <strong>of</strong> 17 December, its main responsibilities are:<br />

• strategic planning for the railway sector, as regards both infrastructures and<br />

provision <strong>of</strong> services<br />

• general planning and regulation <strong>of</strong> the railway system, particularly in all matters<br />

relating to safety and the interoperability <strong>of</strong> the railway system, as well as to<br />

relations between the different agents in the sector<br />

• defining objectives and supervising the activity <strong>of</strong> the public railway companies,<br />

ADIF and RENFE, and their financing system<br />

For more details on the Ministry’s areas <strong>of</strong> responsibility, see art. 81 <strong>of</strong> the Act.<br />

As the Directive 2004/49/EC on Railway <strong>Safety</strong> has not yet been transposed to the Spanish<br />

Legislation, there is not any National <strong>Safety</strong> Authority (NSA). Its functions are fulfilled by<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

22/161


the Ministry <strong>of</strong> Transport through the Railway General Directorate according to the Railway<br />

Sector Act 39/2003, Real Decreto 2387/2004 and Orden Ministerial 233/2006.<br />

Railway Infrastructure Administrator (ADIF)<br />

ADIF was set up by the Railway Sector Act 39/2003 <strong>of</strong> 17 December. The ADIF by-laws<br />

were established in Royal Decree 2395/2004 <strong>of</strong> 30 December 2004. It began operating on 1<br />

January 2005. ADIF is a public company, independently managed within the limits<br />

established by its regulations, and is part <strong>of</strong> the Ministry <strong>of</strong> Public Works. It has its own<br />

separate legal personality, is fully qualified to operate in the fulfilment <strong>of</strong> its objectives, and<br />

has its own assets. Its primary purpose is the management and construction <strong>of</strong> railway<br />

infrastructures.<br />

ADIF manages the network owned by itself and almost the whole <strong>of</strong> the general interest<br />

railway network (RFIG). ADIF currently manages a) as a commercial operation, the new<br />

high-speed and UIC gauge lines which are included in their inventory (Madrid-Seville, with<br />

the Toledo branch line, and Madrid-Zaragoza-Lleida; a total <strong>of</strong> 1,010 Km) and, b) by<br />

assignment from the State, the conventional Iberian-gauge network (11,780 Km), through an<br />

agreement subscribed for the management <strong>of</strong> this nationally-owned network.<br />

ADIF, as well as administering (operation and maintenance) the railway infrastructures<br />

mentioned above, is also responsible for the construction <strong>of</strong> new lines by order <strong>of</strong> the State,<br />

either owned by ADIF itself, financed with their own resources, or nationally-owned and<br />

financed with resources from the national budget. ADIF is currently building the Madrid-<br />

Valladolid section <strong>of</strong> the Madrid-Valladolid-Vitoria-French border line, the Lleida-<br />

Barcelona and Barcelona-Figueras sections <strong>of</strong> the Madrid-Barcelona-French border line, the<br />

lines in the Madrid-Valencia Autonomous Region-Murcia corridor, the Cordoba-Malaga<br />

section <strong>of</strong> the Madrid-Andalusia corridor, and the tunnels in the Pajares and the Orense-<br />

Santiago section <strong>of</strong> the north-east corridor.<br />

For more information on the ADIF’s areas <strong>of</strong> responsibility and functions, see art. 21 <strong>of</strong> Act<br />

There is only one exception: the high speed connexion between Figueras (Spain) and<br />

Perpignan (France). In 1995 the Spanish government and the French government signed an<br />

agreement for the construction and the operation <strong>of</strong> this new line by a concession contract.<br />

The concession was given, by a public tender, to TP Ferro, a society under Spanish law<br />

shared by the Spanish holding ACS and the French holding Eiffage. The concession is for<br />

50 years, including the 5 years necessary for the construction.<br />

RENFE-Operadora<br />

The current RENFE was created as a public company by the Railway Sector Act 39/2003 <strong>of</strong><br />

17 December. RENFE’s by-laws were established in Royal Decree 2396/2004 <strong>of</strong> 30<br />

December 2004. It began operations on 1 January 2005.<br />

RENFE was created by the segregating <strong>of</strong> the business units providing railway services and<br />

other commercial activities from the previous vertical railway company.<br />

RENFE is a public company, independently managed within the limits established by its<br />

regulations, and is part <strong>of</strong> the Ministry <strong>of</strong> Public Works. It has its own separate legal<br />

personality, is fully qualified to operate in the fulfilment <strong>of</strong> its objectives, and has its own<br />

assets. Its purpose is to provide passenger and goods transport services by rail and other<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

23/161


complementary services, and activities connected to railway transport. It also is responsible<br />

for the maintenance <strong>of</strong> railway rolling stock.<br />

RENFE will continue to receive remuneration from the State for public service obligations<br />

in providing regional and local commuter passenger services. The long-distance and highspeed<br />

passenger units are managed as commercial operations, as is the cargo unit, the only<br />

one which has been opened to competition by other operators starting in 2006.<br />

RENFE has been granted a renewal <strong>of</strong> the licence authorising it to transport passengers and<br />

goods on the national railway network.<br />

Other railway companies<br />

According to European and Spanish regulations, since 1 January 2006, all railway<br />

companies with European licences will have unrestricted access to the whole <strong>of</strong> the General<br />

Interest State Network for providing international or national freight transport by rail. To<br />

qualify, they must apply for the corresponding capacity (slot) from the ADIF, following the<br />

established procedure. At the time the capacity is granted, they must also be in possession <strong>of</strong><br />

the safety certificate required for permission to operate, with their rolling stock and driving<br />

staff, on the requested routes.<br />

As <strong>of</strong> 1 January 2006, the Ministry <strong>of</strong> Transport has granted licences for new railway<br />

companies,. All these new railway companies will carry out their activities in freight<br />

transport by rail.<br />

At the present time ERTMS is implemented only in the High Speed Lines, which are<br />

foreseen for passenger traffic only. Freight companies operate in the conventional network<br />

that will not be equipped with ERTMS in the short term. Therefore the freight operators will<br />

not be affected by ERTMS regulations and rules.<br />

Railway Regulatory Committee<br />

The Railway Regulatory Committee is the regulatory body for the railway sector. It is a<br />

registered body which is part <strong>of</strong> the National Infrastructure and Planning Agency <strong>of</strong> the<br />

Ministry <strong>of</strong> Public Works. It comprises a president and four spokespeople who are highranking<br />

government employees in the Ministry <strong>of</strong> Transport and appointed by the Ministry,<br />

and a secretary, appointed by the committee itself. The length <strong>of</strong> the mandate, termination,<br />

incompatibilities and functions <strong>of</strong> the committee members are established in Royal Decree<br />

2387/2004.<br />

The objectives, functions and responsibilities <strong>of</strong> the committee are:<br />

• To safeguard the plurality <strong>of</strong> the railway services.<br />

• To guarantee the equality <strong>of</strong> all the operators in the conditions <strong>of</strong> access to the<br />

market.<br />

• To ensure that the instructions comply with the regulations and are not<br />

discriminatory.<br />

• To resolve any conflicts between the ADIF and the railway companies, in connection<br />

with:<br />

• The assignment and use <strong>of</strong> the safety certificate.<br />

• The application <strong>of</strong> the declaration’s criteria to the network.<br />

• The procedures for assigning capacity.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

24/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


• The amount, structure and application <strong>of</strong> tariffs to the operators.<br />

• Resolving conflicts between railway companies in the event <strong>of</strong> actions intended to<br />

obtain discriminatory treatment in the access to infrastructures or services.<br />

• Interpreting the clauses in licences and authorizations for providing public interest<br />

services, and providing information in the bidding process.<br />

• Informing and advising the Ministry <strong>of</strong> Transport and the regional authorities on<br />

railway matters, particularly those which may affect the development <strong>of</strong> a<br />

competitive railway market<br />

The Regulatory Committee will exercise its functions in accordance with the authority<br />

granted under Act 16/1989 to the bodies established for the defence <strong>of</strong> free competition.<br />

There is an information and coordination system in place between the Committee and the<br />

Service for the Defence <strong>of</strong> Free Competition.<br />

The Committee will act ex <strong>of</strong>fice or at the request <strong>of</strong> the interested party. The Committee’s<br />

resolutions are binding on the parties operating in the scope <strong>of</strong> the railway, but may be<br />

appealed before the Ministry <strong>of</strong> Public Works. Non-compliance with the resolutions will be<br />

penalised according to Act 39/2003.<br />

The <strong>Safety</strong> Authority<br />

At the present time, the National <strong>Safety</strong> Authority (NSA) in Spain is the Railway General<br />

Directorate, located at the Ministry <strong>of</strong> Public Works, according to the Railway Sector Act,<br />

Royal Decree 2387/2004 and Orden Ministerial 233/2006. This Railway General Directorate<br />

is in charge <strong>of</strong> delivering the safety authorizations for putting into service any Infrastructure<br />

and Rolling Stock. The technical support for safety aspects relies on the ADIF <strong>Safety</strong><br />

Directorate.<br />

There is an ongoing study for the creation <strong>of</strong> an independent Railway Agency which will<br />

assume those functions shortly. In the meantime, the ADIF is playing a double role in the<br />

safety authorization process. From one side, as infrastructure construction manager, is a<br />

demander <strong>of</strong> safety approval, so as the construction departments <strong>of</strong> the Ministry itself. On<br />

the other side, the <strong>Safety</strong> Direction <strong>of</strong> ADIF, acting as independent body, is in charge <strong>of</strong> the<br />

verification <strong>of</strong> the correct application <strong>of</strong> the safety prescriptions and delivers the<br />

certifications <strong>of</strong> the compliance with safety conditions required for the railway operation.<br />

The Independent <strong>Safety</strong> Assesors<br />

The interim provision <strong>of</strong> the Royal Decree 355/2006 <strong>of</strong> 29 March, on the interoperability <strong>of</strong><br />

the trans-European high-speed rail system, lays down that the projects which were submitted<br />

to the Royal Decree 1191/2000, shall remain submitted to this regulation after the Royal<br />

Decree 355/2006 has come into force. Both Royal Decrees establish that the subsystems<br />

shall be consistent with the TSIs.<br />

The Decision 2006/860/EC, <strong>of</strong> 7 November 2006, concerning a technical specification for<br />

interoperability relating to the control-command and signalling subsystem <strong>of</strong> the trans-<br />

European high speed rail is now in force. Its article 6 lays down:<br />

“Decision 2002/731/EC is hereby repealed. Its provisions shall however continue to apply<br />

in relation to the maintenance <strong>of</strong> projects authorised in accordance with the TSI annexed to<br />

that Decision and to projects for a new line and for the renewal or upgrading <strong>of</strong> an existing<br />

line which are at an advanced stage <strong>of</strong> development or the subject <strong>of</strong> a contract in course <strong>of</strong><br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

25/161


performance at the date <strong>of</strong> notification <strong>of</strong> the present Decision. Member States shall notify<br />

an exhaustive list <strong>of</strong> the sub-systems and interoperability constituents to which the<br />

provisions <strong>of</strong> Decision 2002/731/EC continue to apply to the Commission not later than six<br />

months after the date on which the present Decision becomes applicable.”<br />

According to the TSI set out in the Annex to Decision 2002/731/EC:<br />

• TSI § 6.1.1Conformity and suitability for use assessment procedure<br />

• TSI § 6.2.1 Control-command subsystem.<br />

“The independent assessment in the safety acceptance and approval process as described in<br />

Annex A, index 1 may be accepted by the Notified Body, without it being repeated”.<br />

Hence, <strong>Safety</strong>, which is an essential requirement, may be assessed by an ISA, which is not<br />

necessarily a Notified Body.<br />

Note that the scope <strong>of</strong> ISA assessment can be an Interoperability Constituent (IC), a<br />

subsystem, or a part <strong>of</strong> an IC or a subsystem such as an electronic board, s<strong>of</strong>tware, or a<br />

sensor.<br />

Therefore, it is important that an ISA involved in a Directive 96/48 conformity assessment<br />

procedure, meets minimum criteria to give confidence to the NoBo accepting the ISA<br />

results, and those accepting the ISA results in a cross acceptance situation.<br />

These minimum criteria were agreed by the NB Rail Plenary Meeting on 16 th February 2006<br />

and are gathered in the RFU 2-000-16 issued by NB Rail on first <strong>of</strong> April <strong>of</strong> 2006.<br />

The Notified Body<br />

The Association <strong>of</strong> Railway Action, CETREN, was created in 1980 as a non-pr<strong>of</strong>it<br />

organisation, with the aim <strong>of</strong> defending the interests <strong>of</strong> the 30 companies related with the<br />

railway sector who were its founder members. More than 70 companies are currently<br />

members <strong>of</strong> CETREN and its main objective is the technical standardisation and<br />

interoperability in the railway sector.<br />

CETREN is currently registered as a certifying body, and as such was reported by the<br />

Spanish State to the Commission and the rest <strong>of</strong> the member states, within the framework <strong>of</strong><br />

the interoperability guidelines (96/48 –high speed- and 2001/ 16 –conventional railway-).<br />

The ERTMS System suppliers<br />

The following companies are suppliers <strong>of</strong> ERTMS systems and components for the Spanish<br />

railways to date:<br />

• Ansaldo-CSEE Transport - Supplier <strong>of</strong> Trackside sub-system for Madrid-Lleida and<br />

for train-borne equipment for Trains S 120 dual gauge;<br />

• Alcatel – Invensys/Dimetronic - Supplier <strong>of</strong> Trackside sub-system for Lleida-Roda<br />

de Bará and On board GSM-R for Locos 252 and <strong>of</strong> the on-board ASFA equipment.<br />

• Bombardier - Supplier <strong>of</strong> train-borne equipment for Trains S130 (ETCS+STM LZB<br />

+ STM EBICAB)<br />

• Siemens - Supplier <strong>of</strong> the GSM-R network and <strong>of</strong> train-borne equipment for Trains S<br />

102 and S 103 (ETCS+STM LZB).<br />

The Figure 6 below shows the different roles played by the main parties <strong>of</strong> the Spanish<br />

Railway Sector.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

26/161


Infraestructure contracting<br />

Entities<br />

General Directorate <strong>of</strong><br />

Railways (Ministry <strong>of</strong><br />

Public Works) Construction<br />

Departments<br />

Infrastructure Manager(ADIF)<br />

Construction Departments<br />

Other Contracting Entities<br />

Application for getting<br />

Interoperability Certifications<br />

Notified Body<br />

Cetren<br />

Certifer<br />

EBC<br />

Interoperability Certification<br />

Train Operating<br />

Companies<br />

Figure 6 - Contracting Bodies and ERTMS Manufacturers<br />

Equipment manufacturers<br />

Renfe Operadora Alcatel<br />

Ansaldo<br />

Other TOC´s<br />

Alstom<br />

Bombardier<br />

Dimetronic<br />

Siemens<br />

……<br />

Application for getting the<br />

authorization for placing in<br />

service<br />

National <strong>Safety</strong> Authority<br />

General Directorate <strong>of</strong><br />

Railways<br />

(Ministry <strong>of</strong> Transport)<br />

Authorization for placing in<br />

service <strong>of</strong> ERTMS/ Rolling<br />

Stock<br />

ADIF (Railway Infrastructure<br />

Administrator)<br />

Authorization for<br />

running <strong>of</strong> Rolling<br />

Stock<br />

<strong>Safety</strong><br />

Certificate<br />

(Mandatory<br />

documentation<br />

attached to the<br />

application)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

<strong>Safety</strong> Authority-<br />

Technical Support<br />

ADIF Opertation <strong>Safety</strong><br />

Directorate<br />

Note:<br />

Authorisation to placing in service<br />

is granted by the <strong>Safety</strong> Authority<br />

when all the legal requirements are<br />

fulfilled.<br />

The authorisation for running is<br />

granted by the IM, (Adif), when all<br />

the operational constraints, are<br />

satisfied.<br />

27/161


1.2 Political and Geographical constraints<br />

This section is intended to provide the following information:<br />

• The regulatory framework (European Directives, National Railway Acts and Laws)<br />

applicable to the Project under consideration, the inter-governmental agreements,<br />

their scope and objectives, the time schedule and the major milestones and the<br />

present implementation/exploitation status.<br />

• Drawings/maps showing the whole line with interconnections with other lines,<br />

terminations, stations, tunnels, bridges, distances, international borders, etc.<br />

• The type, the category and the maximum speed <strong>of</strong> the line, according to the<br />

definitions <strong>of</strong> 96/48/EC or 01/16/EC directives: new high-speed line <strong>of</strong> category 1,<br />

new high speed/high capacity line, conventional line, etc.<br />

• The foreseen traffic typology: only passenger traffic or mixed passenger/freight<br />

traffic (relevant percentages), commercial speeds, fixed or variable time slot<br />

characteristics, minimum headway, etc.<br />

• The major physical characteristics <strong>of</strong> the line: length, double or single rails, main<br />

left/right running direction, double directivity, presence <strong>of</strong> important bridges/tunnels,<br />

curve radii, pr<strong>of</strong>iles, type <strong>of</strong> electrification, neutral sections etc.<br />

• The main constraints to the CC&S sub-system deriving from political, geographical<br />

and topological characteristics <strong>of</strong> the Project: the ERTMS level <strong>of</strong> application, to<br />

which TSI-version the certification took place, its actual baseline (SUBSET version),<br />

the upgrading policy, the fall-back modes and systems, the interoperating modes<br />

with neighbouring systems.<br />

The Austria-Italy project: the Brenner Basis Tunnel<br />

The Project is ruled by the High Speed European Directive 96/48/EC and by the Austrian<br />

and the Italian laws and Norms for all the aspects not included in the scope <strong>of</strong> the European<br />

Directive. In particular, the Italian Ministerial Decree <strong>of</strong> 28 th October 2005 giving<br />

mandatory requirements for the structural design <strong>of</strong> long tunnels and for all the related<br />

technical and security facilities must also be fulfilled.<br />

There is a special inter-governmental agreement between Austria and Italy that sets the basic<br />

political issues <strong>of</strong> the Project. In addition to the national design rules from OEBB (Austria)<br />

and RFI (Italy), there is a specific Italian Ministarial Decree (DM 28-10.2005) that imposes<br />

stringent mandatory requirements for the safety precautions to be adopted in the design long<br />

tunnel systems. It regards civil design rules as well as the use <strong>of</strong> high security measures.<br />

The Control-command and signalling sub-system foresees the ERTMS/ETCS/Level 2<br />

system, without fall back system. The interlocking and the signalling system will be based<br />

on Austrian-German rules/technology from Innsbruck down to Fortezza.<br />

Way-side signals will be installed only at the interconnections with the conventional lines.<br />

Virtual signals, with external marker boards, will be located at the border <strong>of</strong> the block<br />

sections along the line.<br />

The main Control Centre will be placed in Innsbruck. An auxiliary Control Centre planned<br />

in Verona (or Bologna) for fallback operation.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

28/161


A GSM_R mobile telecommunication system is foreseen for all mobile telecom duties from<br />

a single GSM-R Operator. Additional redundancy is ensured by public GSM managed by<br />

Austrian and Italian commercial providers and by the TETRA system managed by the<br />

regional authorities for civil protection duties. This high level <strong>of</strong> communication redundancy<br />

is due for managing possible emergengy situations inside the tunnels.<br />

For long tunnel hazards mitigation, the technical border (for the CCS and Operation subsystems)<br />

has been moved from the political border down to the Fortezza station. Moreover,<br />

a number <strong>of</strong> additional security systems are foreseen, including Hot Box Detectors, Axial<br />

Load Monitors, Train Gabarit Monitors, Security Access Control systems etc.<br />

Possible future Train Operators are any allowed international train operator (Train typology<br />

ICE, IC, EC, EN, RoLa, EG etc.).<br />

Public and private operators <strong>of</strong> freight trains are already active in the parallel historical line.<br />

The final project will be delivered for CE conformity verification based on TSI<br />

2002/731/EC and its amendment 2004/447/EC.<br />

Plans for Project updating to TSI 2006/860/EC are under discussion.<br />

No fall-back system is foreseen. The required level <strong>of</strong> availability will be achieved with an<br />

highly redundant ERTMS/ETCS/Lev.2 system.<br />

Interfacing with existing systems: The interconnection with the Italian hystorical line at the<br />

Fortezza Station: SCMT (v


Umfahrung<br />

Innsbruck<br />

Circonvallazione<br />

Innsbruck<br />

MFS Umfahrung<br />

Innsbruck<br />

MFS Steinach<br />

MFS Wiesen/Prati<br />

Bf. Innsbruck<br />

Bf Innsbruck<br />

/ Stazione<br />

Stazione<br />

di Innsbruck<br />

Bf. Franzensfeste Fortezza /<br />

Stazione di Fortezza<br />

15 kV 16 2 15 kV 16 / 3 Hz 2 / 3 Hz<br />

Umfahrung<br />

Innsbruck<br />

Circonvallazione<br />

Innsbruck<br />

MFS Umfahrung<br />

Innsbruck<br />

25 kV 50 Hz<br />

MFS Steinach<br />

MFS Wiesen/Prati<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

3 kV =<br />

Bf Innsbruck Stazione<br />

Fortezza<br />

Österreichische Technologie<br />

Technologia austriaca<br />

Figure 7 - Layout <strong>of</strong> the Brenner Basis Tunnel line<br />

Italienische Technologie<br />

Technologia italiana<br />

The Austrian project: Vienna-Nickelsdorf<br />

The line concerned is an existing line (No. 10118), equipped with signals and Indusi PZB<br />

system. It is the Austrian part up to the border <strong>of</strong> the Vienna-Budapest line. The<br />

ERTMS/ETCS level 1 system is an overlay system to the existing ones.<br />

The political and geographical constraints are just the European Directives - Directive<br />

96/48/EC + 2004/50/EC, TSI CC&S (2002/731/EC and amendment 2004/447/EC).<br />

The legal framework is the National Railway law: "Eisenbahngesetz 1957" in the currently<br />

valid edition.<br />

30/161


The Project is supported by EC in the framework <strong>of</strong> “Indicative Multi-annual Programme<br />

for the Trans-European Transport Network 2001-2006”.<br />

The main milestones are: Start <strong>of</strong> the Project, start <strong>of</strong> NoBo activity by end <strong>of</strong> 2001, planned<br />

to be completed by end <strong>of</strong> 2003; Srtart <strong>of</strong> trial phase on 29.12.2006.<br />

The actual Status is: on one hand the track side system on the line is completely finished; on<br />

the other hand the train-borne system currently has no certificate for the group <strong>of</strong><br />

interoperability components; the trial phase is running but not yet completed.<br />

The line is used for mixed traffic (freight and passengers).<br />

The maximum speed is 140 km/h - see VZG (summary <strong>of</strong> allowed speeds) <strong>of</strong> the line<br />

(No.10118). As for the freight/passengers mix, it actually depends <strong>of</strong> the specific sections:<br />

between Wien and Bruck a.d.L. approximately. 40%freight, 60% passengers, between Bruck<br />

a.d.L. and Hungarian border approximatly 50% each.<br />

The train frequency is: Wien - Gramtneusiedl: 140 trains/day - according to time tables and<br />

educated guess, Gramatneusiedl - Bruck a.d.L.: 120 trains/ day, Bruck a.d.L. - border: 50<br />

trains/day.<br />

As for the line characteristics: according to the "drawings" here below; further on there are<br />

no tunnels and no relevant bridges (only some short ones).<br />

As for the interconnections with other lines: see drawings below; TEN line: Gramtneusiedl -<br />

Wampersdorf, Parndorf - Kittsee (Petrcalka-Bratislava)<br />

The physical characteristics are: length: approximatly 65km, double rails, main running<br />

direction on right side, double directivity <strong>of</strong> both tracks, wide curves, total line electrified,<br />

no essential gradients, no important bridges or tunnels, Line pr<strong>of</strong>ile in Austria D4, in<br />

Hungary D3.<br />

Speeds, stations, signals, gradients, level crossings are given in the VZG (summary <strong>of</strong><br />

allowed speeds) <strong>of</strong> the line (No.10118).<br />

There are no particular political or geographical constraints for the choices <strong>of</strong> the CCS subsystem.<br />

The ERTMS/ETCS Level 1 (originally V. 2.0.0, during run <strong>of</strong> project changed to V 2.2.2 +<br />

several CRs <strong>of</strong> Subset 108 related to Level 1). Upgrading to V2.3.0 is envisaged.<br />

Fallback mode and neighbouring system is the conventional PZB system (also relevant for<br />

level transitions) - Customer requirements specification (Lastenheft-1-00 für das<br />

Zugbeeinflussungssystem ERTMS/ETCS Level 1 für die Strecke Wien – Hegyeshalom,<br />

10.12.2001). No other neighbouring ETCS (or similar) systems must be considered.<br />

System transition on the Hungarian border will be <strong>of</strong> the type ETCS/Level 1 to ETCS/Level<br />

1.<br />

The ERTMS architecture <strong>of</strong> the two track railway line Wien/Zentralverschiebebahnh<strong>of</strong> -<br />

Nickelsdorf is a dual signalling ERTMS level STM/L1 architecture. The dual signaling<br />

ERTMS level STM/L1 system consists <strong>of</strong> an ERTMS STM (conventional system with<br />

wayside signals and PZB) and an overlay ETCS Level 1 system. The suppliers are Thales<br />

(former Alcatel) and Siemens. The standard system with balises is supplemented by the<br />

“infill function” realised with Euroloops.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

31/161


LEUs are used to convert the signalling information derived from a lamp current interface,<br />

for each signal lamp, to Interface C information for Eurobalises and Euroloops. The infill<br />

information is mainly used in stations where the danger points are too near to the signal.<br />

This is the case for protection signals (Austrian “Schutzsignal”) and too short overlap.<br />

The driver - traffic control voice connection is ensured by a conventional train radio<br />

communication system, GSM-R is planned.<br />

Fall-back mode: As the ETCS level 1 system is an overlay to the existing signalling system,<br />

the existing system can be considered as its fall back system.<br />

Figure 8 – Layout <strong>of</strong> the Vienna-Nickelsdorf line<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

32/161


Figure 9 – Interconnections <strong>of</strong> the Vienna-Nickelsdorf line<br />

The Belgian projects<br />

The Belgian authorities/railways have taken the following decisions:<br />

• New high speed lines will be equipped with ETCS Level 2 (this applies to the<br />

connections to Netherlands and to Germany, respectively L4 and L3 – see the<br />

description <strong>of</strong> L3/L4).<br />

• The conventional network is to be equipped with ETCS Level 1 track side equipment<br />

with the following functionalities:<br />

• TBL1+ for the largest part: ETCS-balises sending Packet 44 with TBL-information;<br />

• ETCS Level 1 for specific lines (like the Freight Corridors)<br />

• This is the first step towards the implementation <strong>of</strong> ETCS all over the Belgian<br />

network.<br />

In the first phase, a total <strong>of</strong> 4.000 way-side signals (out <strong>of</strong> <strong>of</strong> the overall 10.000 ones) will be<br />

equipped with LEU and balises under a contract stipulated in 2006 with Siemens.<br />

The Italian SCMT system has been used as a reference for the system approach: The TBL1+<br />

information is embedded in Packet 44 <strong>of</strong> the ETCS-based telegram as step towards later use<br />

<strong>of</strong> full ETCS Level 1 telegrams. This is a national decision, as no direct impact to the<br />

national borders is involved.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

33/161


The latest TSI (Commission Decision 2006/860/EC <strong>of</strong> 7 November 2006) is used as<br />

reference scheme.<br />

The Figure 10 below shows the different levels <strong>of</strong> implementation <strong>of</strong> ERTMS/ETCS<br />

planned for the major Belgian lines, in combination with the national legacy systems.<br />

TVM<br />

TVM<br />

Basis=crocodile<br />

ETCS1<br />

L4(ETCS2)<br />

TBL2<br />

TBL2<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

L3(ETCS2)<br />

Figure 10 - Overview <strong>of</strong> the Belgian network: ETCS Levels 1 and 2, TVM, TBL2,<br />

TBL1+<br />

The Figure 11 below shows the medium term implementation plans <strong>of</strong> ERTMS/ETCS<br />

systems in the Belgian network.<br />

34/161


Figure 11 - Preliminary Planning for roll-out ETCS on Belgian network<br />

Milestones:<br />

• Contract between Infrabel and Siemens signed in June 2006;<br />

• Roll out is started, to be completed by 2015.<br />

• Actual status: “under construction”.<br />

Note: according to the agreements between Infrabel and the Ministry, the TBL1-system is<br />

considered as a “SIL-zero” system. Consequently, neither assessment nor certification is<br />

contracted for this system, although ETCS-equipment is used.<br />

The network under consideration is a conventional network (according to EU-Directive<br />

2001/16/EC) with a maximum line speed <strong>of</strong> 160 km/h. On this network both passenger<br />

services and freigt services are <strong>of</strong>fered.<br />

Most lines are equipped with a 3 kV DC power supply system. On the regional lines diesel<br />

traction is used.<br />

ETCS Level 1, according to the latest specifications (Commission Decision 2006/860/EC <strong>of</strong><br />

7 November 2006 concerning a technical specification for interoperability relating to the<br />

control-command and signalling subsystem <strong>of</strong> the trans-European High Speed rail system<br />

and modifying Annex A to Decision 2006/679/EC <strong>of</strong> 28 March 2006 concerning the<br />

technical specification for interoperability relating to the control-command and signalling<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

35/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


subsystem <strong>of</strong> the trans-European conventional rail system. (Notified under document<br />

number C(2006) 5211) – “Official Journal <strong>of</strong> the European Union L 342/1 <strong>of</strong> 7.12.2006”.).<br />

The French project: LGV-Est<br />

The complete project (see the Figure 12 below) includes 406 km <strong>of</strong> a new line between<br />

Vaires (Seine et Marne) and Vendenheim (Bas Rhin). The first stage, includes 300 km <strong>of</strong><br />

line from Vaires to Baudrecourt (Moselle), plus new links to the existing network in order to<br />

serve as many destinations as possible.<br />

The project also includes modifications to connecting lines and installations, in particular<br />

between Paris Gare de l'Est and Vaires sur Marne and on the line Strasbourg-Kehl in order<br />

to improve the link with the German network. The lines to Épinal and St. Dié in the Vosges<br />

will be electrified to allow the towns to be served by the TGV.<br />

Figure 12 – LGV-EST Line<br />

ERTMS L2 is implemented on the line.<br />

Trains equipped with ERTMS Level 2 will circulate on this line under ERTMS and trains<br />

equipped with TVM 430 only, under TVM.<br />

TVM 430 serves as a fall back system but only after a procedure has been followed by<br />

driver and dispatcher.<br />

The PEEE project thus covers three sub-projects:<br />

• One sub-project system ensuring coordination <strong>of</strong> the PEEE project at system level,<br />

• One sub-project supplying ERTMS Level 2 on TVM 430 trackside<br />

• One sub-project developing and supplying trains with bi-standard ERTMS/TVM.<br />

The commissioning authorisation applies to the system made up <strong>of</strong> the on board equipment<br />

(bi-standard ERTMS/TVM) installed on the POS trains and the trackside equipment<br />

regarding Level 2 superimposed on TVM430.<br />

The line is operated bidirectionally and is meant for passenger-transport only.<br />

The German project: Berlin-Halle-Leipzig<br />

The regulatory framework <strong>of</strong> the Project is summarised in the previous section.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

36/161


Since the BHL line does not touch or cross any national borders there is no need for any<br />

kind <strong>of</strong> intergovernmental agreement in the moment. BHL shall become part <strong>of</strong> an<br />

international high speed TEN connection from Stockholm/SE via Berlin and Munich to<br />

Verona/IT.<br />

As for the time schedule and milestones, a serial qualification period without safety<br />

responsibility started in 2003-03. The basic functions - trackside and onboard - should be<br />

tested and continuously amended at this phase, the concept should prove its practicality.<br />

On 7th <strong>of</strong> July and 11th <strong>of</strong> December 2003 first presentation runs took place for the<br />

customer and a UIC conference.<br />

Start <strong>of</strong> operational qualification period without safety qualification was in 2003-12. Within<br />

this phase the functions known from the Serial Qualification should be extended step-bystep<br />

up to the point that all functions depicted in the LH were realised.<br />

In 2004-10 the EBA issued the permission to start the safety qualification tests. The tests –<br />

still without safety responsibility - finally began in 2005-06 after it had been proven that the<br />

functions implemented equalled those defined in the LH. Meanwhile all preliminary safety<br />

cases had been assessed and the overall ETCS safety fulfilled the top level safety target<br />

calculated by the risk analysis. Level 2 operational and reliability qualification period under<br />

full safety relevance started in 2005-12.<br />

The national automatic train protection system LZB (LZB L72 CE2) was commissioned in<br />

2006-05.<br />

ETCS Referenzstrecke Berlin-Halle/Leipzig<br />

Streckenübersicht<br />

RBC-Bereich<br />

Bitterfeld<br />

Landsberg<br />

km 146,5<br />

Ab<br />

km 156,0<br />

Halle<br />

RBC-Bereich<br />

Wittenberg<br />

Mulde<br />

RBC<br />

Bitterfeld<br />

km 131,6 / 48,5<br />

Roitzsch<br />

km 138,7<br />

km 151,545 Po 159<br />

km 152,003, Po 160<br />

Burgkemnitz<br />

km 121,5<br />

Muldenstein<br />

km 126,2<br />

Delitzsch<br />

km 60,4<br />

Rackwitz<br />

km 70,0<br />

km 81,3<br />

RBC-Bereich<br />

Jüterbog<br />

RBC<br />

Wittenberg<br />

km 94,8<br />

Radis<br />

km 112,5<br />

Gräfenhainichen<br />

km 116,1<br />

Leipzig<br />

Figure 13 – Halle-Leipzig line<br />

Bergwitz<br />

km 104,2<br />

Pratau<br />

km 98,3<br />

RBC-Bereich<br />

Ludwigsfelde<br />

Zahna<br />

km 84,0<br />

Elbe<br />

RBC<br />

Jüterbog<br />

km 62,8<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

Niedergörsdorf<br />

km 69,2<br />

Teltow Teltow<br />

RBCWittenRBCWitten Jüterbog berg -Bereich LuSLuSLuLuberg Jüterbog -Bereich<br />

Trebbin dwigsfeldeBirkengrund-S dwigfelde dwigfelde charfenbrückkm34,3km39,5 charfenbrückkm34,3km39,5dwigsfeldeBirkengrund-S<br />

Trebbin<br />

RBC RBC ZahnaNiedergörsdorf RBC km 69,2 km 62,8Blönsdorfkm 75,1 LuckenJüterbogkm RBC km 69,2 km 62,8Blönsdorfkm 75,1 LuckenJüterbogkm ZahnaNiedergörsdorf<br />

walde walde 50,0 50,0<br />

BRBC-BereichBitterfeld Mulde RBC-BereichBitterfeld Mulde Wittenberg B WittenbergRadis Bergwitz PratauGräfenhainichen WittenbergRadis Bergwitz PratauGräfenhainichen urgkemnitz urgkemnitz<br />

Elbe Elbe<br />

km 94,8km 98,3km 104,2km 112,5km 116,1 km 94,8km 98,3km 104,2km 112,5km 116,1<br />

km 84,0 km 84,0<br />

Wittenberg<br />

Blönsdorf<br />

km 75,1<br />

Ludwigfelde<br />

Ludwigsfelde<br />

Luckenwalde<br />

km 50,0<br />

UZ Bitterfeld/Delitzsch<br />

Steuerbezirk 6 Leipzig<br />

Trebbin<br />

km 34,3<br />

Scharfenbrück<br />

km 39,5<br />

Teltow<br />

Birkengrund-Süd<br />

Berlin<br />

UZ Wittenberg<br />

Steuerbezirk 6 Leipzig<br />

LZB-Bereich<br />

Ludwigsfelde<br />

LZB-Bereich<br />

Jüterbog 40 km<br />

250 Balisen<br />

UZ Jüterbog<br />

Steuerbezirk 1 Berlin<br />

LZB-Bereich<br />

Wittenberg<br />

LZB-Bereich<br />

Bitterfeld<br />

15 km<br />

160 Balisen<br />

90 km<br />

795 Balisen<br />

The BHL relation was upgraded to a high speed line with mixed operation <strong>of</strong> passenger<br />

trains at Vmax =200 kph and freight trains at Vmax = 100 kph. It was equipped with both high<br />

speed and conventional train protection systems so that both ETCS trains and trains with<br />

legacy onboard CCS can run on the track.<br />

The length <strong>of</strong> the line is about 145 km, starting at Teltow in the south-west <strong>of</strong> Berlin, ending<br />

before Leipzig, via Ludwigsfelde, Jüterbog, Wittenberg and Bitterfeld. The main driving<br />

direction is 'right'. Trains run on double rails with crossovers at defined transfer points. The<br />

line is fitted with two legacy (national) signalling techniques: linear LZB and intermittent<br />

37/161


PZB train protection systems. Optical wayside signals "KS system" and track sections with<br />

axle counters are installed.<br />

The BHL line is equipped with ETCS Level 2. It is planned to connect the route to a Level<br />

1 section in the North.<br />

Momentarily the line is operated based on a national specification (“Rahmenlastenheft”,<br />

[DB 27]) and on UNISIG 2.2.2.<br />

The BHL line is the first German route being prepared with the new European train<br />

protection system. This was a special challenge, not only because <strong>of</strong> the new technology<br />

itself, but because <strong>of</strong> the fact that two approval/acceptance and certification processes had to<br />

be conciliated. Thus a “new” approval process had to be initiated, trying to assemble in a<br />

way that both national and European aspects with regard to technical, operational,<br />

economical and judicial demands were satisfied.<br />

Migration from LZB to ETCS is a costly long-term enterprise, since the German network is<br />

well equipped with modern, safe and effective automatic train protection systems for the<br />

main and high speed lines. Exchanging LZB to ETCS in one step would cause immense<br />

costs. Hence a period <strong>of</strong> double equipped lines and traction units are aspired by the German<br />

railway net and rolling stock operators. The re-investment in LZB and many other<br />

arguments are contrary discussed.<br />

The BHL line was initially not equipped with any type <strong>of</strong> LZB so that the specific migration<br />

at the pilot line became an “inversion <strong>of</strong> the usual migration situation”<br />

(Kollmannsberger/Kilian/Mindel, Signal & Draht, 2003-03): On the BHL pilot line ETCS<br />

was installed 3 years before LZB was added.<br />

The “Punktförmige Zugbeeinflussung” (PZB), German Class B intermittent train protection<br />

system, serves in case <strong>of</strong> ETCS malfunctions. Additionally the LZB is the part <strong>of</strong> the<br />

migration concept, allowing non-ETCS trains to run on the BHL track, too. Not all traction<br />

units running on the multifunctional line are equipped with LZB (or ETCS). In Germany<br />

some 2.000 km <strong>of</strong> track are equipped with LZB (5% <strong>of</strong> the network, all main lines).<br />

BHL, formerly named “J-H/L” (Jüterbog – Halle - Leipzig), was initially intended to be<br />

operated as a "Test Site" during the consolidation phase <strong>of</strong> the European ETCS<br />

specifications.<br />

The Italian Projects<br />

The Rome-Naples HSL<br />

The design <strong>of</strong> this line started much earlier than the entry into force <strong>of</strong> the 96/48/EC<br />

Directive. As a consequence a full EC certification was not strictly required. Nevertheless,<br />

RFI decided to pursue the EC conformity verification as a mean <strong>of</strong> anticipating activities<br />

that were to be required for the HSL projects to come.<br />

It must also be noticed that being the HSL in consideration fully contained in the national<br />

territory, the Rome-Naples HSL Project did not experience the technical and operational<br />

issues typical <strong>of</strong> a cross-border line.<br />

The regulatory framework applicable to Rome-Naples HSL project is outlined in the<br />

Annex:<br />

• European Directives regarding the HSL interoperability;<br />

• The Italian Law endorsing the Directive;<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

38/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


• The relevant CENELEC Norms and European Specifications;<br />

• The RFI Directives;<br />

• The RFI Procedures and Technical Norms.<br />

The line was put in revenue service since 12 th December 2005.<br />

The HS/HC Line Rome-Naples (see Figure 15 below) is integrated in the Italian High<br />

Speed Project which integrates the trans-European High Speed Network (see Figure 14).<br />

Figure 14 - European Corridors crossing Italy<br />

The line is new high speed/high capacity line <strong>of</strong> category 1. The maximum speed <strong>of</strong> the line<br />

is 300 km/hour.<br />

A mixed traffic typology (passengers and freight) is foreseen. The commercial speed is 300<br />

Km. per hour for passenger trains.<br />

The length <strong>of</strong> the line is 184 Km. To date, the high speed line starts in Rome from Termini<br />

Station and ends to the Gricignano interconnection whit the Foggia-Naples conventional<br />

line. The line is double track (minimum distance 5 meters) with left main running direction<br />

and the possibility <strong>of</strong> double directivity. There are a total <strong>of</strong> 40 Km. <strong>of</strong> bridges and 38 km.<br />

<strong>of</strong> tunnels the length <strong>of</strong> the longer tunnel is 6,628 Km. (Colli Albani). The minimum curve<br />

radius is 5 450 m. The maximum slope is 21 ‰. The power supply is <strong>of</strong> the type 2x25<br />

kVac-50 Hz. There are three interconnections with conventional line: Frosinone Cassino<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

39/161


Caserta. At each interconnection plus in Salone and in Gricignano there are Neutral<br />

Sections managed by ERTMS.<br />

Figure 15 - Interconnections <strong>of</strong> Rome-Naples HSL<br />

No specific constrains deriving from political, geographical and topological characteristics<br />

are present on the Rome Naples line.<br />

The adopted signalling system is based on Solid State Interlocking supplemented by jointless,<br />

audio-frequency track-circuits. No lateral signals are used. Only Marker Boards are<br />

used at the borders <strong>of</strong> each Block Section.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

40/161


The ERTMS/ETCS Level 2 system is used for all the train operation and protection<br />

functions (according to SUBSET026 version 2.2.2) without any other fallback system.<br />

The interconnected conventional lines are equipped with the Italian BACC/SCMT signalling<br />

system.<br />

This requires the on-board train control system to be equipped with the BACC/SCMT STM.<br />

Train entrance/exit from/to interconnections are managed as normal level transition STM �<br />

L2 or L2 � STM for the train equipped by STM or L0 � L2 or L2 � L0 for those trains<br />

not equipped with the STM.<br />

RFI foresees the upgrading from the SUBSET026 version 2.2.2 to version 2.3.0 in a near<br />

future. To date, RFI is discussing the migration strategy in accordance with the European<br />

strategy.<br />

The Torino -Novara HSL<br />

The line is, in all aspects, similar to the Rome-Naples case, with the following difference:<br />

the EC conformity certification was legally required, since the works started after the<br />

Directive entered in force. It is integrated in the Italian High Speed Line Project which is<br />

integrated in TEN corridor 5 linking Lisbon to Kiev.<br />

The line is in revenue service since February 6th 2006.<br />

One <strong>of</strong> the most remarkable events pushing for a quick and very effective completion <strong>of</strong> the<br />

test and acceptance process for the Turin-Novara line was the Turin Winter Olimpiads to be<br />

held just in the early 2006.<br />

Figure 16 – Turin/Novara High Speed Line<br />

The line is new high speed/high capacity line <strong>of</strong> Category 1. The maximum speed <strong>of</strong> the line<br />

is 300 Km per hour. A mixed traffic typology (passengers and freight) is foreseen. The<br />

commercial speed is 300 Km. per hour.<br />

The length <strong>of</strong> the line is 84 Km. It is double track (minimum distance 5 meters) with left<br />

main running direction and the possibility <strong>of</strong> double directivity. The maximum slope is 15<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

41/161


‰. The power supply is AC 2x25 Kv 50 Hz. There are two interconnections with<br />

traditional line: Stura and Novara.<br />

No special constrains deriving from political, geographical and topological characteristics<br />

are present on the Turin-Novara line. The signalling system is ERTMS Level 2 (Subset 026<br />

version 2.2.2) without fallback system. The interconnected traditional lines use the<br />

BACC/SCMT signalling system. The BACC/SCMT is the Italian STM agreed <strong>of</strong> TSI Class<br />

B systems. Train inputs or outputs from/to interconnections are managed as normal level<br />

transition STM � L2 or L2 � STM for the train equipped by STM or L0 � L2 or L2 � L0<br />

for those not equipped. RFI foresees the upgrading from SUBSET026 vers. 2.2.2 to version<br />

2.3.0. Nowaday RFI is discussing the migration strategy according to the European strategy.<br />

The Dutch projects<br />

Betuweroute<br />

The technical solutions chosen for this project are: ETCS Level 2 without any other fallback<br />

system;<br />

As far as the current status (May 2007) is concerned, the following applies: although the<br />

contract between Alstom and ProRail requires Alstom to build the system according to<br />

ERTMS SRS 2.2.2, there are NoBo statements declaring the status <strong>of</strong> implementation <strong>of</strong> the<br />

CR’s in SUBSET108. The trackside system can therefore be viewed as 2.3.0 compatible.<br />

• As for the fall-back mode: Simple ATB NG system with signals and very large<br />

sections, only allowing limited capacity has not bee implemented on A15, because<br />

there was enough confidence in ERTMS.<br />

• The interfaces with existing systems are: ATB-ERTMS Lev. 2 at entrance; ERTMS<br />

Lev. 2-ATB at exit.<br />

• The controlled balises are coupled with existing Interlocking via LEUs<br />

The Project Time Schedule (to May 2007) is:<br />

• A15 Trackside <strong>Safety</strong> Case is available for BR A15v3.4, approved by ISA (no<br />

blocking remarks) and ready to start revenue service from mid June 2007.<br />

• Bev21 update to A15v4 (version that includes HHT+workzones functionality)<br />

expected Q4 2007<br />

• Train Operating Company: <strong>Approval</strong> tests on Betuweline are foreseen in 2007.<br />

Official opening on June 16th 2007, with about 20 locomotives <strong>of</strong> different freight<br />

operators. The train-infrastructure integration tests will then not be finished<br />

completely<br />

The following figures show the pr<strong>of</strong>ile <strong>of</strong> the line toghether with its interconnections.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

42/161


Figure 17 - The Betuweroute overview<br />

Figure 18 - The Betuweroute, Western part<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

43/161


Figure 19 - The Betuweroute, Middle part<br />

Figure 20 - The Betuweroute, Eastern part<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

44/161


Amsterdam - Utrecht<br />

Figure 21 – Utrecht-Amsterdam HSL<br />

The Amsterdam - Utrecht line has the<br />

architecture <strong>of</strong> Dual Signaling consisting<br />

<strong>of</strong> a conventional system with wayside<br />

signals, ATB-EG and an overlay ETCS<br />

Level 2 system.<br />

The supplier will install the overlay ETCS<br />

Level 2 on the line by 2009. The<br />

ERTMS/ETCS architecture is part <strong>of</strong><br />

further negotiations. The supplier has<br />

developed a new and more powerful<br />

hardware for the Interlocking and the<br />

Radio Block Center and proposed to<br />

install the new hardware. The supplier has<br />

more ETCS projects and will come to<br />

RBC standard generic s<strong>of</strong>tware modules.<br />

The country specific functionality will be<br />

hosted in a country specific interface<br />

module. The supplier proposal is to install<br />

one Master / Slave interlocking and one<br />

Master / Slave RBC.<br />

The supplier proposes at the same time to<br />

migrate the system specification from the<br />

actual SUBSET026 version 2.2.2 to<br />

version 2.3.0.<br />

The fallback scenario for ETCS Level 2 is<br />

the conventional system with way-side<br />

signals and ATB (the Dutch ATP system).<br />

At the present date, the use <strong>of</strong> GSM-R is<br />

for voice communications only.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

45/161


HSL ZUID<br />

Figure 22 - HSL Zuid<br />

The following Figure 21 shows the route <strong>of</strong> the line<br />

from Amsterdam to the Belgian border.<br />

The signalling system is the ERTMS/ETCS Level 2,<br />

with a Level 1 fallback system. At the connecting<br />

locations with the existing tracks, a transition from<br />

Level STM to Level 2 is made, or from Level STM to<br />

Level 1 in fallback mode.<br />

The applicable CCS TSI is the 2006 version including<br />

Subset 108.<br />

The contract was initially based on TSI 2002, in a later<br />

stage it was decided to add subset 108.<br />

The applicable Operations TSI is the 2002 version.<br />

There are no derogations reported to the time being.<br />

The information about this project derives from the<br />

following <strong>of</strong>ficial documents:<br />

• Concept Register <strong>of</strong> Infrastructure ; Doc. nr:<br />

HSL-Zuid #743200<br />

• Operation <strong>Analysis</strong> including Capacity<br />

Simulation Doc. nr : IFS M011090085<br />

The Spanish projects<br />

The main legislation items that regulate the railway sector in Spain, including high-speed<br />

and conventional rail system, are:<br />

• Railway Sector Act 39/2003 <strong>of</strong> 17 December: the Railway Sector Act that transposes<br />

to the Spanish legislation the Directives 91/440/CEE, 2001/12/CE, 95/18/CE,<br />

2001/13/CE, 2001/14/CE and 2001/16/CE. This law puts the administration <strong>of</strong> the<br />

railway infrastructure under the responsibility <strong>of</strong> a new entity: Railway Infrastructure<br />

Administrator (ADIF). At the same time a new public entity named RENFE-<br />

Operadora is created as a railway transport enterprise to <strong>of</strong>fer all kind <strong>of</strong> railway<br />

services to the citizenship.<br />

• Royal Decree 2387/2004 <strong>of</strong> 30 December, approving the Railway Sector Regulation:<br />

Royal Decree that develops the Law 39/2003 and regulates the railway sector in<br />

Spain. This Royal Decree defines more precisely the procedures for the authorization<br />

to enter into service the infrastructure and the rolling stock.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

46/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


• Royal Decree 2395/2004 <strong>of</strong> 30 December approving the by-laws <strong>of</strong> the Railway<br />

Infrastructure Administrator (ADIF).<br />

• Orden FOM/897/2005 <strong>of</strong> 7 April, on the Network Statement and the procedure for<br />

allocating railway infrastructure capacity.<br />

• Orden FOM 233/2006 <strong>of</strong> 31 January regulating the conditions for the approval <strong>of</strong><br />

railway rolling stock and maintenance workshops and sets the certification fee<br />

amounts for this rolling stock.<br />

• Royal Decree 354/2006 <strong>of</strong> 29 March, on the interoperability <strong>of</strong> the trans-European<br />

conventional rail system.<br />

• Royal Decree 355/2006 <strong>of</strong> 29 March, on the interoperability <strong>of</strong> the trans-European<br />

high-speed rail system<br />

The first transitional provision <strong>of</strong> the Royal Decree 2387/2004 lays down that until the<br />

Ministry <strong>of</strong> Transport passes the regulations which will implement the Railway Sector Act<br />

39/2003, the applicable safety regulations are the following:<br />

• RENFE Operational Rules and Regulations.<br />

• Technical and Operating Requirements for Running and <strong>Safety</strong> on the Madrid-<br />

Zaragoza-Lleida section <strong>of</strong> the Madrid-Barcelona-French Border line, Version 2.<br />

All the technical regulations and standards applicable to the every different ERTMS projects<br />

are gathered in the Annex [see RENFE 1].<br />

The regulatory framework for ERTMS is the Decision 2002/731/EC <strong>of</strong> 30 May 2002<br />

concerning the technical specification for interoperability relating to the control-command<br />

and signalling subsystem <strong>of</strong> the trans-European high-speed rail system referred to in Article<br />

6(1) <strong>of</strong> Council Directive 96/48/EC, according to RENFE - Operadora´s tender<br />

specifications for rolling stock purchases, which figure on Annex II [see RENFE 2].<br />

The <strong>Safety</strong> approval process: Infrastructure<br />

The art. 16 <strong>of</strong> the Royal Decree 2387/2004 <strong>of</strong> 30 December ‘04, approving the Railway<br />

Sector Regulation, lays down the way to authorize the placing in service <strong>of</strong> the new railway<br />

infrastructures. According to this article, before the railway lines enter into service, its<br />

sections and the stations belonging to the general interest railway network (RFIG), must<br />

have the Ministry <strong>of</strong> Transport’s authorisation. In addition, this authorization has to declare<br />

that the line or the section <strong>of</strong> the line has to enter into service, when it fulfils all the safety<br />

requirements <strong>of</strong> the applicable regulations.<br />

This authorisation shall be granted by the Railway General Directorate, taking into account:<br />

• The report on the suitability <strong>of</strong> the works to the applicable technical rules and<br />

regulations. This report has to be issued by personal responsible for the construction<br />

and its supervision.<br />

• The certification <strong>of</strong> the compliance with the safety conditions required for the<br />

railway operation issued by the Railway Infrastructure Administrator or entity<br />

entitled to issue it.<br />

• The supporting documents relative to the compliance with the implementation <strong>of</strong> the<br />

testing plan at the request <strong>of</strong> ADIF or, where appropriate, the General Railway<br />

Directorate.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

47/161


The authorization to enter in service can be unrestricted, or subject to some restrictions, or<br />

an interim authorization (i. e. for test runs, maintenance….).<br />

The Royal Decree, RD 2387/2004, refers implicitly to the TSIs: The “Additional disposition<br />

1” <strong>of</strong> this RD states that the interoperability is regulated by the RD 1191/2000 and the RD<br />

646/2003, whch respectively transpose the HS and CR EC Directives.<br />

Due to the delay in the TSI completion, the Spanish Ministry <strong>of</strong> Transport has decided to put<br />

into service the HS lines in two phases: First opening the infrastructure on the basis <strong>of</strong> the<br />

safety certification, which allows the “national” operation <strong>of</strong> the line, and in a second step<br />

the infrastructure will get the Declaration <strong>of</strong> Verification when all the constituents have the<br />

Declaration <strong>of</strong> Conformity or Certificates and then could be open to international traffic.<br />

The following Figure 23 sumarizes the safety approval process for infrastructures.<br />

A similar process is being applied to rolling stock.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

48/161


Construction<br />

manager<br />

Application for<br />

getting the<br />

authorization for<br />

placing in service<br />

<strong>of</strong> ERTMS<br />

General Railway Directorate<br />

Authorization for placing in service<br />

<strong>of</strong> ERTMS<br />

Mandatory<br />

documentation<br />

attached to the<br />

application<br />

Construction manager<br />

Independent assessment<br />

report<br />

Figure 23 – <strong>Safety</strong> approval process for infrastructural works in Spain<br />

Construction manager<br />

<strong>Report</strong> on the suitability <strong>of</strong> the ERTMS<br />

subsystem to the applicable technical rules<br />

and regulations with reference to the<br />

applied technical regulations and rules<br />

Reference regulations:<br />

o Directive 2004/50/EC<br />

o Royal Decree 355/2006<br />

o Directive 96/48/EC<br />

o Directive 2001/16<br />

Adif <strong>Safety</strong> Directorate<br />

Certification <strong>of</strong> the compliance with<br />

safety conditions required for the<br />

railway operation<br />

Construction manager<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

Construction manager<br />

<strong>Safety</strong> Case<br />

Reference rules:<br />

CENELEC standards<br />

Supporting documents relative to the<br />

compliance with the implementation <strong>of</strong><br />

the testing plan at the request <strong>of</strong> Adif<br />

or, where appropriate, the General<br />

Railway Directorate:<br />

o Testing protocol<br />

o Subsystem integration report<br />

49/161


<strong>Safety</strong> approval process: rolling stock<br />

The article 4 <strong>of</strong> the Orden Ministerial 233/2006 lays down the requirements for placing in<br />

service <strong>of</strong> rolling stock.<br />

Article 4 <strong>of</strong> the above-mentioned Orden Ministerial states that:<br />

1. Every railway vehicle must get an authorization for placing in service, granted by the<br />

General Railway Directorate, and an authorization for running, granted by the<br />

Railway Infrastructure Administrator, before running on the general interest railway<br />

network (RFIG).<br />

2. There are two authorisation levels<br />

3. The ”first level authorization” for placing in service shall be granted having regard<br />

to:<br />

• The “EC” certificate <strong>of</strong> conformity issued by a Notified Body which gives<br />

evidence <strong>of</strong> the compliance with the applicable Technical Specifications <strong>of</strong><br />

Interoperabilty (TSI´s).<br />

• The validation report issued by a Certifying Body that gives evidence <strong>of</strong> the<br />

compliance with the applicable Technical Specifications for Homologation<br />

(Especificaciones Técnicas de Homologación – ETH). In fact, these<br />

specifications are under development now, refer to national requirements,<br />

and will be notified to the EC when ready).<br />

Rolling stock granted with a first level authorization is interoperable and suitable for<br />

running on the general interest railway network (RFIG).<br />

4. The ”second level authorization” for placing in service shall be granted when the<br />

applicant rolling stock has got a validation report issued by a Certifying Body that<br />

gives evidence <strong>of</strong> the compliance with the applicable ETH.<br />

Rolling stock granted with a second level authorization suitable for running on the<br />

general interest railway network (but is not interoperable).<br />

5. The Railway Infrastructure Administrator shall grant the authorization for running to<br />

the rolling stock that has got an authorization for placing in service and has passed<br />

satisfactorily the test runs requested by the Railway Infrastructure Administrator, in<br />

accordance with the applicable ETH´s.<br />

The ETH, now under development, are intended to complement the TSIs in safety aspects,<br />

trying to adapt the current Spanish operational rules to the TSI’s structure and philosophy.<br />

The ETH, when completed, will be notified to the EC.<br />

At the present time, any rolling stock has received the EC Declaration <strong>of</strong> verification.<br />

Consequently all the authorisations granted by the General Railway Directorate have been<br />

“second level authorisations”.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

50/161


Second level authorisation Step 1<br />

Rolling stock owner<br />

Application for<br />

getting the<br />

authorization for<br />

placing in service<br />

<strong>of</strong> Rolling Stock<br />

Mandatory<br />

document<br />

ation<br />

attached<br />

to the<br />

application<br />

Railways General Directorate<br />

Authorization for placing in service <strong>of</strong><br />

Rolling Stock<br />

without interoperability<br />

Certifying Entity<br />

Validation report giving<br />

evidence <strong>of</strong> the compliance<br />

with the applicable ETHs<br />

Figure 24 – <strong>Safety</strong> approval process (second level) for rolling stock in Spain<br />

With reference to the interoperability certification <strong>of</strong> new lines, it is necessary to consider<br />

the followings:<br />

• The new high speed lines have been built at the same time when the TSIs were being<br />

updated. This implies that the ERTMS installation was being adapted to the<br />

modification <strong>of</strong> the specifications. Consequently, the new lines are being placed into<br />

service with the required <strong>Safety</strong> Authorizations but without the Interoperability<br />

Certifications.<br />

• Nevertheless, as the verification and safety tests required for the <strong>Safety</strong> Certification<br />

have been established using the TSIs and the EEIG test specifications, no<br />

interoperability problems are to be expected during the NoBos Certification process.<br />

• The certification procedure <strong>of</strong> the line Figueras-Perpignan started in the beginning <strong>of</strong><br />

the year 2005, at the same time <strong>of</strong> the beginning <strong>of</strong> the construction. The certification<br />

procedures <strong>of</strong> the other lines started at the beginning <strong>of</strong> the year 2007.<br />

• As far as on board systems are concerned, the interoperability verification and<br />

certification procedures started in the year 2005 for some <strong>of</strong> the manufacturers.<br />

However, no certification has been issued yet.<br />

The geographical structure<br />

From the geographical point <strong>of</strong> view, it must be underlined that the Spanish railway network<br />

has essentially a radial structure, with Madrid as main centre. Besides this structure, there is<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

Rolling Stock Manufacturer<br />

<strong>Safety</strong> case<br />

Reference rules:<br />

CENELEC standards<br />

Rolling Stock Manufacturer<br />

<strong>Report</strong> on validation and<br />

verification<br />

Rolling Stock Manufacturer<br />

ISA report on safety<br />

Rolling stock owner<br />

To pass verification tests<br />

requested by Adif together with<br />

the General Railway Directorate<br />

51/161


an important line along most <strong>of</strong> the Mediterranean coast from the French border to Valencia,<br />

Alicante and Murcia.<br />

Since 1992 there is an intense development <strong>of</strong> new high speed lines using standard gauge<br />

and 25 KV AC power supply. The structure <strong>of</strong> this high speed network will follow the same<br />

radial principle. The main high speed lines are:<br />

• Madrid –Sevilla, built in 1992 to foster the development <strong>of</strong> a wide region not well<br />

communicated up to that time, equipped with LZB as at that time the ERTMS was<br />

not developed. Maximum speed: 300 Km/h.<br />

• Madrid- Zaragoza-LLeida- Roda de Bara (Tarragona) - Barcelona, that interconnects<br />

the two biggest Spanish cities (>4.000.000 inhabitants each), that will be extended<br />

up to the French border. It is equipped with ERTMS and is in service from Madrid to<br />

Roda de Bara. It will be completed by the end <strong>of</strong> the year 2007. Maximum speed in<br />

this moment is 300 Km/h. Maximum speed planned is 350 Km/h.<br />

• Madrid- Valladolid, under construction, will open the high speed way to the north<br />

and northwest at the end <strong>of</strong> 2007. Maximum speed planned: 350 Km/h.<br />

• La Sagra Toledo: Small branch with the singularity <strong>of</strong> being equipped with LZB +<br />

ERTMS Maximum speed: 300 Km/h.<br />

• Córdoba-Málaga branch also fitted with LZB+ERTMS. Maximum speed: 300 Km/h.<br />

• Zaragoza-Tardienta-Huesca: Interesting experience with ERTMS over hybrid line<br />

Spanish Broad Gauge + UIC gauge. Maximum speed: 300 Km/h.<br />

• Figueras-Perpignan, ERTMS, crossig border Project. Maximum speed: 350 Km/h.<br />

In the medium term, the high speed network will be completed with the Madrid-Valencia (in<br />

the year 2010) and Madrid-Lisbon lines.<br />

The high speed network, (with the exception <strong>of</strong> the Madrid-Sevilla line) is being equipped<br />

with ERTMS.<br />

The conventional railway lines will be progressively upgraded to ERTMS. All Spanish lines<br />

are equipped with ASFA as back up system.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

52/161


Figure 25 – High speed lines in Spain<br />

The characteristics and the status <strong>of</strong> each one <strong>of</strong> the ongoing ERTMS implementation<br />

projects are given in the followings.<br />

Madrid-Lleida Line<br />

• Passenger traffic only<br />

• Length : 492 Km<br />

• Max gradient: 25 o/oo<br />

• Tunnels: n. 26, with a total tunnel length: 29,5 Km<br />

• Viaducts: n.40, with a total viaduct length: 25,5 Km<br />

• Bridges: n. 48 with a total bridge length: 4,18 Km<br />

• Maximum speed: 350 Km/h<br />

• Permanent speed restrictions: 90 Km/h through Zaragoza station and 50 Km/h<br />

through Lleida station<br />

• Switches in main line and speed in side position n. 12 at 50 Km/h, n. 73 at 100<br />

Km/h, n. 9 at 150 Km/h, n. 9 at 160 Km/h and n. 89 at 220 Km/h<br />

• Stations: Madrid, Guadalajara, Calatayud, Zaragoza, Lleida<br />

• Interlockings: n.13 (Ansaldo)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

53/161


• ERTMS implementation: Level 1 and Level 2 with Specs vers. 2.2.2<br />

• ERTMS equipment: n. 361 LEU’s, n. 3262 Eurobalises, n. 5 RBC’s (Ansaldo) –<br />

GSM-R (Siemens)<br />

• Fall-back systems: ERTMS Level 1 and ASFA<br />

LLeida-Roda de Bara Line<br />

• Passengers traffic only<br />

• Length: 91 km<br />

• Tunnels: n. 7 (Lilla, 2000 m; la Riba 1971 m)<br />

• Viaducts: n.20<br />

• Maximum speed: 350 km/h<br />

The figure below shows the route <strong>of</strong> the line Madrid-Zaragoza-LLeida-Roda de Bara-<br />

Barcelona).<br />

Figure 26 - The “Madrid-Zaragoza-LLeida-Roda de Bara-(Barcelona) HSL<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

54/161


La Sagra-Toledo Line<br />

• Passengers traffic only<br />

• Length: 21 Km<br />

• Max slope: ±27,5 o/oo<br />

• Viaducts: n.1, total viaduct length: 1,6 Km;.<br />

• Maximum speed: 220 Km/h<br />

• Switches in main line and speed in side position: n. 2 at 80 Km/h,<br />

• Stations: Madrid, Toledo<br />

• Interlockings: n.1 Electronic Westrace interlocking (Dimetronic) and the extension<br />

<strong>of</strong> L 90 Interlocking (Alcatel) at La Sagra<br />

• ERTMS implementation: ETCS Levels 1 and Level 2 (Alcatel/Siemens) Versión<br />

2.2.2, SUBSET026, Version 2.2.2<br />

• ERTMS equipment: n.16 LEU’s (Alcatel); n. 80 Fixed Eurobalises (Siemens); n. 32<br />

Variable Eurobalises (Siemens); n. 1 RBC (Alcatel); n. 5 GSM-R BTS‘s (Siemens)<br />

• Fall-back system: ERTMS Level 1 and ASFA<br />

Figueras-Perpignan line<br />

• Mixed traffic<br />

• Length: 44,4 km (19,8 km in Spanish territory and 24,6 in French territory<br />

• Max slope: TBC<br />

• Tunnels: n.1 Pertús (8,3 km)<br />

• Viaducts: n. 9 (5 in Spain, 4 in France)<br />

• Bridges: TBC<br />

• Maximum speed: 350 km/h in passenger traffic<br />

• Permanent speed restrictions: At least 100 km/h in freight trains<br />

• Switches in main line and speed in side position: TBC<br />

• Stations: No stations<br />

• Interlockings: TBC<br />

• ERTMS implementation: Levels 2 and 1<br />

• ERTMS equipment: CSEE Transport<br />

• Fall-back system: ERTMS Level 1<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

55/161


Córdoba-Antequera line<br />

• Passengers traffic only<br />

• Length: 97,4 km<br />

• Max slope: 20 mm/m<br />

• Viaducts: n. 8, total length: 4,3 km, maximum length: 1,4 km<br />

• Tunnels: n. 2, total length: 329 m, maximum length: 275 m<br />

• Maximum speed: 350 km/h<br />

• Permanent speed restrictions: 220 km/h<br />

• Switches in main line and speed in side position: n.1 at 220 km, n. 2 at 100 km<br />

• Stations: Puente Genil, Antequera-Santa Ana<br />

• Interlockings: n. 4<br />

• ERTMS implementation: Levels 2 (Alcatel, Siemens) Vers. 2.22.2, Subset-026,<br />

Vers. 2.2.2<br />

• ERTMS equipment: n. 95 LEU’s; n. 370 fixed and variable Eurobalises; n. 22<br />

GSM-R BTS‘s<br />

• Fall-back system: ERTMS Level 1, LZB and ASFA<br />

The Figure 27 below shows the route <strong>of</strong> the line “Córdoba-Antequera-Málaga”.<br />

Figure 27 - Córdoba-Antequera-Málaga HSL<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

56/161


Madrid-Valladolid line<br />

The Figure 28 below shows the route <strong>of</strong> the line project “Madrid-Valladolid”. Its main<br />

characteristics are:<br />

• Passengers traffic only<br />

• Length: 226 Km<br />

• Max slope: 29,5 o/oo<br />

• Tunnels: n. 9, total tunnel<br />

length: 43,4 Km,<br />

maximum length 28,7<br />

Km<br />

• Viaducts: n.11, total<br />

viaducts length: 6035 km,<br />

maximum length: 1,7 km<br />

• Bridges: TBC<br />

• Maximum speed: 350<br />

Km/h<br />

• Permanent speed<br />

restrictions: 275 Km/h<br />

in some tunnels, 220 Km<br />

between,100 Km/h in<br />

Segovia station and<br />

Olmedo, 50 Km/h in<br />

Valladolid Station<br />

• Switches in main line:<br />

Speed in side position n.1<br />

at 30 km/h, n. 1 at 45<br />

km/h, n. 2 at 50 km/h, n.<br />

1 at 80 km/h, n. 5 at 100<br />

km/h, n. 2 at 160 km/h<br />

and n. 5 at 220 km/h<br />

• Stations: Madrid,<br />

Segovia, Valladolid<br />

• Interlockings: n. 9<br />

electronic Westrace<br />

Interlocking (Dimetronic)<br />

Figure 28 - Madrid-Valladolid HSL<br />

• ERTMS implementation: Levels 1 and Level 2 (Alcatel/Siemens) Version 4.20,<br />

Subset-026, Version 2.2.2<br />

• ERTMS equipment: n. 178 LEU’s (Alcatel); n. 689 fixed Eurobalises (Siemens); n.<br />

377 variable Eurobalises (Siemens); n. 3 RBC’s (Alcatel); n. 44 GSM-R BTS’s<br />

(Siemens)<br />

• Fall-back system: ERTMS Level 1 and ASFA<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

57/161


The tables below indicate the actual status <strong>of</strong> implementation <strong>of</strong> ERTMS/ETCS both on<br />

track-side and on board <strong>of</strong> Rolling Stock.<br />

Line Supplier ETCS<br />

level<br />

High speed lines<br />

Madrid-Lleida Ansaldo (CSEE)<br />

+Siemens<br />

Length<br />

(Km)<br />

Speed<br />

(Km/h)<br />

Status<br />

L2+L1 492 350 In operation (2004)<br />

Lleida- Barcelona Alcatel L2+L1 90 350 Lleida-Tarragona: In operation (2006)<br />

Tarragona-Barcelona under construction<br />

(end 2007)<br />

La Sagra-Toledo Alcatel +Siemens L2+L1 21 300 In operation (2006)<br />

Madrid-Segovia-Valladolid Alcatel + Siemens L2+L1 180 350 Under construction (2007)<br />

Córdoba-Málaga Invensys L2+L1 155 300 Under construction (2007)<br />

Zaragoza-Huesca Alstom L1 80 200 In operation (2006)<br />

Figueras-Perpignan Ansaldo (CSEE) L2+L1 30 300 Under construction (2009)<br />

Conventional lines<br />

Albacete-La Encina Bombardier L1 93 200 In operation (2000)<br />

Madrid conmuter L2+L1 160 120 Pending <strong>of</strong> award<br />

Table 3 - Status <strong>of</strong> ERTMS implementation – Infrastructure<br />

Series S-102 S-103 S-104 S-120 S-130 S-252<br />

Suppliers Talgo-Bombardier Siemens CAF- Alstom- CAF- Alstom Talgo-Bombardier Siemens<br />

Number <strong>of</strong> 16<br />

16<br />

20<br />

12<br />

27<br />

73<br />

trains<br />

30<br />

10<br />

13<br />

16**<br />

18<br />

Composition 2 tractive heads 8 powered cars 4 powered cars 4 powered cars 2 tractive heads<br />

12 cars<br />

11 cars<br />

Seats 314 (+2hp) 402 (+2hp) 236 (+1hp) 237 (+1hp) 298 (+1hp)<br />

346 (+2hp)<br />

229 (+1hp)<br />

Train length (m) 200 200 107 107 185 20,4<br />

Speed (Km/h) 330 350 250 250 (220)* 250 (220)* 200 Km/h<br />

Traction power<br />

(kw)<br />

8000 8800 4000 4000 (2500)* 4800 (4000)* 5600<br />

Signalling ERTMS+ STM ERTMS+STM ERTMS+ STM ERTMS+ ASFA ERTMS+ STM LZB + ERTMS +<br />

system<br />

LZB + ASFA LZB + ASFA LZB + ASFA<br />

ASFA + EBICAB STM LZB +<br />

ASFA<br />

Commissioning 2005 2007 2004 2005 2007-2008 1992<br />

Gauge track UIC UIC Spanish Spanish= 1668 mm<br />

values into brackets applies under 3000V DC<br />

Table 4 - Status <strong>of</strong> ERTMS implementation – Rolling stock<br />

The Technical solutions chosen for the projects are:<br />

• Current system version status: SUBSET026 Version 2.2.2 is applied although the<br />

Initial contracts were based on Version 2.0.0. Migration to Version 2.3.0 is under<br />

consideration. Due to concerns about the backwards compatibility between 2.3.0<br />

and 2.2.2. some mitigation measures were decided: Not using some additional<br />

functions on 2.3.0, applying additional engineering rules CR 458 non compatible,<br />

pending on UNISIG decision.<br />

• Fall-back mode: ETCS Level 1 when Level 2 will be in service. ASFA and<br />

conventional signals as secondary fallback<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

58/161


• Interfacing with interlocking and conventional signalling system: Level 1 balises are<br />

driven by the Interlocking system via LEU's. LEU's are concentrated at the<br />

interlocking buildings.<br />

• With ETCS Level 2, transition between Madrid-Lleida (RBC by Ansaldo) and<br />

Lleida-Roda de Bará (RBC by Alcatel) is made through Level 1 at max allowed<br />

speed <strong>of</strong> 300 km/h. No RBC-RBC interconnection is foreseen.<br />

The following implementation status is achieved to date:<br />

• Trackside system: <strong>Safety</strong> Certificate for Level 1 approved through lab tests and on<br />

line tests according to ADIF protocols, On-going lab and on-line tests for Level 2.<br />

<strong>Approval</strong> expected at mid 2007. NoBo Certification on process started on 2007.<br />

• Train borne systems: Trains series 102 (Siemens) approved on 2006 (16 units); series<br />

103 (SIEMENS ETCS + STM LZB) foreseen on April 2007 (16 units); series 120<br />

(Ansaldo) foreseen by the end <strong>of</strong> 2007 (12 units); series 130 (Bombardier ETCS +<br />

STM LZB + STM EBICAB) foreseen by 2008 (45 units); locos Series 252<br />

(INVENSYS/Dimetronic) (Number <strong>of</strong> units and approval date unknown).<br />

Conventional Rail Series 490 trains (INVENSIS) Unknown approval date (10 units)<br />

1.3 <strong>Safety</strong> targets / RAMS Policy<br />

This section is intended to provide the following information:<br />

• The main RAMS concepts applied to the Project: the system performances, the<br />

overall system availability, the maintenance policy, etc.<br />

• The higher-level documents used as input for the definition <strong>of</strong> the RAMS policy.<br />

The Austria-Italy project: the Brenner Basis Tunnel<br />

The document “Erhaltungskonzept Technischer Bericht - Concetto di Manutenzione -<br />

Relazione Tecnica” defines the basic concepts <strong>of</strong> line maintenance in accordance with the<br />

CENELEC Norm EN°13306. The maintenance is particularly critical for this particular line<br />

fully included in a long tunnel.<br />

The document “Ausrüstung Technischer Bericht Festlegung der RAM-Anforderungen -<br />

Attrezzaggio Relazione Tecnica Definizione dei Requisiti RAM” defines some basic concepts<br />

<strong>of</strong> system availability and then, apportions the required overall system availability figure <strong>of</strong><br />

Avtot =0.9995, into availability, reliability and maintainability requirements for all functions<br />

<strong>of</strong> the control-command, signalling, telecommunication, security and power supply system.<br />

Taking into account mission pr<strong>of</strong>ile <strong>of</strong> the line and the maintenance constraints recalled<br />

above, the final target for the availability <strong>of</strong> the CC&S sub-system has been preliminarily set<br />

to AVccs =0.999865 (this issue is still under discussion to date) with respect to all types <strong>of</strong><br />

immobilising failures.<br />

The safety requirements for the staff operating in the tracks imposes that the preventive and<br />

the corrective maintenance activities are only performed during the closure <strong>of</strong> the service,<br />

that will happen only for a couple <strong>of</strong> hours during the night. This imposes a high demand in<br />

the availability <strong>of</strong> the CC&S sub-system functionality that can only be achieved by a high<br />

level <strong>of</strong> redundancies.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

59/161


The document “Tunnelsicherheit Technischer Bericht-Sicherheitkonzept- Sicurezza in<br />

Galleria Relazione Tecnica-Concetto di sicurezza” provides a wide hazard analysis for all<br />

the risks possible in a long tunnel and defines the basic conter-measures able to minimise<br />

their consequences. This document is the master document for the tunnels layout design as<br />

well as for all the hazard analysis <strong>of</strong> the technical sub-systems.<br />

In particular, the document “Leit-und Sicherungstechnik-Technischer Bericht<br />

Sicherheitplan-Sistemi di Controllo e Comando – Relazione Tecnica – Piano di Sicurezza”<br />

defines in detail the overall design, implementation and verification/validation/approval<br />

process and responsibilities (in accordance with the EN50126 norm) to be followed during<br />

the whole life-cycle. In its annexes the document presents the results <strong>of</strong> a preliminary<br />

hazard analysis based on results <strong>of</strong> similar European projects, with the related countermeasures.<br />

It finally concludes that the ERTMS/ETCS safety targets <strong>of</strong> Subset091 are also<br />

applicable to this specific case.<br />

The Austrian project: Vienna – Nickelsdorf<br />

The following basic concepts have been adopted:<br />

• System performance will be increased by adopting the allowed speed limits<br />

according to the speed limit <strong>of</strong> the track and switches (the existing rule requires that<br />

a certain speed is valid form the location <strong>of</strong> the signal onwards).<br />

• Availability respectively unavailability requirements are given in the customer<br />

requirements specifications (document Lastenheft-1-00 für das Zugbeeinflussungssystem<br />

ERTMS/ETCS Level 1 für die Strecke Wien – Hegyeshalom, 10.12.2001);<br />

• The basic safety targets have been deduced form the carried out risk analysis (SIL4<br />

is appropriate) - risk analysis (document 3BU 81400 3003 DUAPC, 12.11.2002).<br />

The risk analysis shows that ETCS targets are acceptable for the tolerable risk level<br />

deduced from accident statistics in Austria.<br />

• The maintenance is and will be derived from the specifications and documents <strong>of</strong> the<br />

manufacturers <strong>of</strong> the interoperability components.<br />

The Belgian projects<br />

The TBL1+ system is considered as a “SIL 0” system. The aim <strong>of</strong> this project is to reduce<br />

the most important risks <strong>of</strong> at list 80 % <strong>of</strong> the existing status.<br />

For the lines to be equipped with the ETCS level 1, Infrabel conforms to the TSI,<br />

specifically to SUBSET-091.<br />

For each Project, the complete CENELEC life-cycle is followed, starting with generic safety<br />

cases with EC-verification <strong>of</strong> conformity, exporting hazards that originate from constituents.<br />

Every step <strong>of</strong> the process is closely monitored (according to EN50126, EN50128 and<br />

EN50129). There is a technical and operational HAZOP for the whole project as well as a<br />

FMEA (Failure Mode and Effect <strong>Analysis</strong>). A safety plan stipulates when and by whom<br />

safety tasks are performed.<br />

Every time there is a change, possibilities <strong>of</strong> export <strong>of</strong> hazards is considered. It is the<br />

intention <strong>of</strong> Infrabel to follow both V-cycles <strong>of</strong> <strong>Safety</strong> and Functionality in parallel. The<br />

whole process is supervised by an ISA. Pre-existing components are normally used.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

60/161


The safety cases issued by suppliers like Siemens, Alstom and Ansaldo are checked by<br />

ISA’s hired for that purpose by the same companies.<br />

For the <strong>Safety</strong> <strong>Approval</strong> <strong>of</strong> a line and its operation, the complete CENELEC cycle is<br />

follwed. Starting from safety cases <strong>of</strong> track-side constituents (e.g. RBCs, LEUs, Balises,<br />

track-circuits), generic ETCS Level 1 and Level 2 <strong>Safety</strong> Cases are developped. These<br />

safety cases are then taken as a basis for the L3 and L4 specific tracksiside system safety<br />

cases. The L3 and L4 Engineering and Programming Data <strong>Safety</strong> Cases are then added to<br />

the above safety cases,. After that, the L3 and L4 safety cases are made, including the<br />

operational rules. In parallel a safety case for the operating system EBP is made as well.<br />

The French project: LGV-Est<br />

The target operational availability <strong>of</strong> the ERTMS sub-system is set at 0.99973.<br />

The quantitative aspect to be demonstrated (connected to material breakdowns and<br />

transmission errors) is set at 0.99984. (Ref. Preliminary <strong>Safety</strong> File, 30 January 2004,<br />

F2SA891)<br />

On board<br />

Line<br />

Trackside<br />

Kernel (Vital functions) < 10 -6<br />

Kernel (non-Vital functions) < 10 -6<br />

BTM < 10 -8<br />

RTM < 10 -6<br />

MMI < 10 -7<br />

TIU < 10 -7<br />

Odometer < 10 -7<br />

Non-switchable Balise < 10 -7<br />

Switchable Balise < 10 -7<br />

LEU (Interoperable part) < 10 -7<br />

RBC < 10 -6<br />

Unavailability<br />

Table 5 – Unavailability targets for Interoperability Constituents <strong>of</strong> the PEEE project<br />

The German project: Berlin-HalleLeipzig<br />

Performance and reliability requirements are specified in the operational specification´s<br />

registers (“Teillastenhefte”, [DB 28]) no. 6 and 7, RAMS onboard equipment and RAMS<br />

trackside.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

61/161


The Italian Projects<br />

The Rome-Naples HSL<br />

The maintenance is and will be derived from the specifications and documents <strong>of</strong> the<br />

manufacturers <strong>of</strong> the interoperability components.Rome-Naples HSL. The line was designed<br />

for a maximum line-speed <strong>of</strong> 300 km/h and a minimum headway <strong>of</strong> 5 minutes. The basic<br />

requirements for the line were given in RFI 38. The main availability parameter for the<br />

trackside subsystem was given as:<br />

Aintr_HW_SST = MTBF/(MTBF + MTTR) = 0,9999959<br />

In full accordance with the requirements <strong>of</strong> SUBSET091, the overall safety target adopted<br />

for the implemented ERTMS/ETCS Level 2 system was: THR = 1*10-9 The maintenance policy is shortly described in document [RFI 21]. Both preventive and<br />

corrective maintenance is foreseen. The maintenance interventions have to be performed<br />

during the night, due to heavy diurnal traffic.<br />

The Torino-Novara HSL<br />

The line is designed to run to 300 km/h with minimum headway <strong>of</strong> 5 minutes. The main<br />

availability parameter for the trackside subsystem is [RFI 21]:<br />

Aintr_HW_SST = MTBF/(MTBF + MTTR) = 0,9999959<br />

Regarding the safety target the project adopted the target specified in SUBSET091.<br />

Both preventive and corrective maintenance is foreseen (see RFI MO-MA-CO-TC-IN DT<br />

INES 002A “Tratta AV/AC Torino-Milano subtratta Torino-Novara Caratteristiche<br />

Infrastrutturali e Programma di Esercizio Complessivo della Sub-Tratta Torino – Novara”<br />

25/11/2005). The maintenance interventions have to be performed during the night, due to<br />

heavy diurnal traffic.<br />

The Dutch projects<br />

Betuweroute<br />

A separate safety case was developed by ProRail for integration <strong>of</strong> Bev21 with Dutch<br />

Traffic Control system. At May 2007 it resuts available and ISA approved.<br />

ERTMS maintenance systems (LCS, etc) are part <strong>of</strong> Alstom delivery. <strong>Safety</strong> assessment is<br />

included in Alstom Bev21 Trackside <strong>Safety</strong> Case. Exported constraints are transferred to<br />

ProRail and incorporated in ProRail <strong>Safety</strong> Case (covering integration <strong>of</strong> the Dutch Traffic<br />

Control System, Bev21 and operation/maintenance).<br />

The compliance with contractual functional requirements is demonstrated in Alstom A15<br />

Trackside <strong>Safety</strong> Case.<br />

For ETCS, a trackside <strong>Safety</strong> Plan is available as part <strong>of</strong> Consortiums A15 Trackside <strong>Safety</strong><br />

Case, assessed by ISA (ADL). The <strong>Safety</strong> Plan addresses the V&V-process in conformity<br />

with CENELEC EN50126.<br />

For ETCS a trackside Quality Plan is available as part <strong>of</strong> Consortiums A15 Trackside <strong>Safety</strong><br />

Case.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

62/161


The ProRail Project Plan is part <strong>of</strong> the ProRail <strong>Safety</strong> Case and has been assessed by an ISA<br />

(Praxis).<br />

The Scope <strong>of</strong> the supplier Consortium Alstom-Movares Hazard-log is the Bev21 system,<br />

which includes the ETCS system. The Hazard-log also includes measures to be exported to<br />

infra manager and train operator.<br />

The ProRail Hazard-log covers Bev21 integration with Traffic Control and operational<br />

processes.<br />

An extensive hazard transfer process has taken place between ProRail and Consortium<br />

Alstom-Movares to formally transfer hazards/measures between the two organisations.<br />

Amsterdam – Utrecht<br />

ProRail has to provide the National Railway Authority <strong>of</strong> the Minister <strong>of</strong> Transport and<br />

Water management with the complete set <strong>of</strong> safety cases to demonstrate that the line fulfils<br />

all the technical rules, regulations and safety conditions required for the domestic railway<br />

network.<br />

Figure 29 – <strong>Safety</strong> case structure for the Amsterdam-Utrecht project<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

63/161


To build the Overall <strong>Safety</strong> Case, several related safety cases were tob e prepared in<br />

accordance with the Cenelec EN50129 norm and the transfer <strong>of</strong> SRAC’s (<strong>Safety</strong> Related<br />

Application Conditions) from lower level safety case to higher level ones. The following<br />

Figure 29 shows the safety case structure for this project, where PSC stands for Project<br />

<strong>Safety</strong> Case, GASC stands for Generic Application <strong>Safety</strong> Case and SASC for Specific<br />

Application <strong>Safety</strong> Case.<br />

The next Figure 30 shows the responsibility <strong>of</strong> ProRail for the system integration and, at the<br />

end <strong>of</strong> the project, for the Overall <strong>Safety</strong> Case.<br />

Figure 30 – Scope <strong>of</strong> ProRail Integration and Acceptance plans<br />

HSL ZUID<br />

This (optional) information is not presently available.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

64/161


The Spanish projects<br />

The requirements <strong>of</strong> the Terms <strong>of</strong> Reference <strong>of</strong> the different ERTMS contracts refer to the<br />

general ERTMS specifications, in particular:<br />

• The ERTMS/ETCS equipment shall conform to the ERTMS/ETCS Class 1 System<br />

Requirements Specification <strong>of</strong> the UNISIG group, version 2.2.2, or, where<br />

applicable, the latest valid version in force during the construction <strong>of</strong> the project. It<br />

will also fulfil additional national functions specified by Infrastructure Managers and<br />

in force during the construction <strong>of</strong> the projects.<br />

• The GSM-R equipment shall conform to EIRENE Projects Requirements<br />

Specification vers. 13 and MORANE for ERTMS/ETCS Class 1 <strong>of</strong> UNISIG or,<br />

where applicable, the latest approved version available during the construction phase<br />

<strong>of</strong> the projects. It will also be equipped with the “hands free functionality”.<br />

• The trains will be equipped with a static recorder for recording and storing traffic<br />

conditions and other events. The specifications and functions <strong>of</strong> this recording<br />

equipment are left to the suplier’s responsibility.. This equipment has to be<br />

compatible with the information supplied by ERTMS and will comply with the<br />

corresponding ERTMS specifications<br />

In connection with the RAMS Policy, the following standards are applicable to the Spanish<br />

projects:<br />

• EN 50126: “Railway applications – The specification and demonstration <strong>of</strong><br />

reliability, availability, maintainability and safety (RAMS)”.<br />

• EEIG 96S126: “ERTMS/ETCS RAMS Requirements Specification”. Vers. 6<br />

• EEIG 98S711: “ERTMS/ETCS RAMS Requirements” – Informative Part. Vers. 1.<br />

• IEC 62278: “Railway applications. The specification and demonstration <strong>of</strong> <strong>of</strong><br />

reliability, availability, maintainability and safety”.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

65/161


2 Phase 2 - System definition and application<br />

conditions<br />

2.1 The mission pr<strong>of</strong>ile <strong>of</strong> the system<br />

This section is intended to provide the main concepts <strong>of</strong> the line operation and maintenance:<br />

• Operational rules regarding the target ERTMS system and its fall-back modes;<br />

• The relationship with the applicable national rules;<br />

• The rules for international traffic (e.g. border crossing);<br />

• The rules and conditions for train/driver allowance in the line;<br />

• The way-side signal typology;<br />

• The voice communication via GSM-R and other fall-back systems;<br />

• The management <strong>of</strong> emergency and degraded situations,<br />

• The management <strong>of</strong> ordinary (preventive) and extraordinary (corrective)<br />

maintenance;<br />

• The scope and the role <strong>of</strong> the line control centres.<br />

• The V&V process to be followed for the validation and the approval <strong>of</strong> such rules<br />

together with the involved bodies and organisations.<br />

Austria-Italy project: Brenner Basis Tunnel project<br />

This line will be used for mixed traffic, passengers and freight trains. It is part <strong>of</strong> the TEN<br />

Corridor 1, and such it will be one <strong>of</strong> the most important link between Italy and the rest <strong>of</strong><br />

the North Europe.<br />

At the end <strong>of</strong> the implementation, an average traffic <strong>of</strong> 140 trains per day is foreseen. A<br />

peak headway <strong>of</strong> 7.5 minutes is foreseen. The passenger trains (length up to 400 m) will<br />

have a maximum speed <strong>of</strong> 200 km/h, while the freight trains (length up to 800 m) run at a<br />

maximum speed <strong>of</strong> 100 km/h.<br />

The line interconnects just at the Innsbruck main station with the Austrian Network and the<br />

high speed line towards Munich, presently under construction, while at South (at the<br />

Fortezza station) it is connected with the Italian Network and with the high speed line<br />

towards Verona, presently under study.<br />

Austrian project: Vienna – Nickelsdorf<br />

The main concepts <strong>of</strong> operation and maintenance are based on the classical operation <strong>of</strong> the<br />

line; additions concerning the operation <strong>of</strong> the ETCS level 1 are introduced (opeartional<br />

rules, system description and operating conditions for drivers): DV ETCS Level 1 (operation<br />

rule; DV=Dienstvorschrift), DB 823 (description and operation manual) (DB =<br />

Dienstbehelf), DV S80 (on maintenance).<br />

Fallback modes, national emergency rules and rules for degraded situations are based on the<br />

existing rules for the PZB/LZB system (LZB is not actually used in this line). The national<br />

rules DV V2 and DV V3 for the national signalling systems will be applicable. Border<br />

crossing is not considered for the time being.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

66/161


The way-side signal typology: use <strong>of</strong> fixed standard signals, not changed in any way by<br />

ETCS.<br />

Maintenance, line control centre: no ETCS specific regulations; just national situation and<br />

rules.<br />

V&V process: ·standard process according to the manufacturer’s rules, process supervised<br />

by NoBo during validation phase and additional checks by NoBo. Work to be laid down in<br />

test reports.<br />

The Belgian projects<br />

The L3 and the L4 Lines<br />

The high speed lines L3 (Luik–German/Belgian border) and L4 (Antwerp–Dutch/Belgian<br />

border) are built to achieve a performance <strong>of</strong> up to 300 km/h and a 3-minute headway under<br />

continuous speed supervision provided by ERTMS/ETCS Level 2, supplemented by<br />

ERTMS/ETCS Level 1, which takes over in case the former experiences a failure while<br />

<strong>of</strong>fering parallel operations in a mixed level application.<br />

The ETCS Level 1 lines<br />

Around the year 2000 the project started and received the name: EUROTBL. At that stage<br />

NMBS (SNCB) was one integrated railway company, i.e. Train Operating Company and<br />

Infrastructure Manager in one organisation.<br />

The basic concepts were:<br />

• Use <strong>of</strong> ETCS-equipment in the trackside: Eurobalises and LEUs;<br />

• New interface equipment in the rolling stock, which extracts “Packet 44” from<br />

ETCS-telegrams and hands the contents to the existing TBL-equipment in the rolling<br />

stock. From here the name EURO-TBL emerged – which is not to be used anymore.<br />

Currently the track-side implementation project is under management <strong>of</strong> Infrabel.<br />

Train Operating Company NMBS (SNCB) has two options under consideration for the train<br />

borne equipment:<br />

• The solution described above;<br />

• A “real” ETCS-on-board-equipment, complemented with an STM-TBL, which could<br />

deal with the “Packet 44” information.<br />

French project: LGV-Est<br />

This (optional) information is not presently available.<br />

German project: Berlin-HalleLeipzig<br />

Originally the line had mixed traffic <strong>of</strong> trains protected by PZB. ETCS Level 2 was installed<br />

in 2002/2003. Since 2006-06 the track is double-equipped with LZB/PZB and ETCS. PZB is<br />

also used as fall back mode in case <strong>of</strong> total ETCS failure. A dynamic transfer to LZB at<br />

ETCS failure is not implemented. Each train run starts in PZB mode, then being<br />

automatically transferred to ETCS L2 at defined trackside signal locations. In the moment 5<br />

BR 101 locomotives are tested and allowed to run on the BHL track. Apart from ETCS and<br />

LZB they are equipped with both PZB and level 0. The only allowed way to come into the<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

67/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


protection <strong>of</strong> ETCS is to start in PZB mode, for regulatory and operational reasons, not for<br />

technical reasons. On the German network no train is allowed to be run without PZB or<br />

PZB/LZB. And up to the present there is no exemption for BHL. Technically any train<br />

equipped with ETCS could also start in level 0. The MFD displays the signal aspects<br />

transferred to the command variables ceiling speed (guidance/supervision speed), target<br />

speed and target distance.<br />

ETCS controlled shunting is not available on BHL. (National) Subsidiary Signals<br />

(Ersatzsignale) allow only 40km/h in the moment. The (national) Caution Signal aspect<br />

(Vorsichtssignal) is displayed to the driver by a special indication. The speed pr<strong>of</strong>ile is<br />

controlled for 40 km/h. (Ptok/Bode, Signal & Draht, 2005-10, “Realisierung des ETCS-<br />

Stufe-2-Systems auf der deutschen Pilotstrecke“).<br />

One <strong>of</strong> the first tasks in the context <strong>of</strong> the development for BHL was the definition <strong>of</strong> the<br />

required operational processes, providing independency from the UNISIG specification as<br />

far as possible, considering the ETCS system as a ‘Black-box’. (Mense, Signal & Draht,<br />

2003-01/02, “European Train Control System – Von der UNISIG-Spezifikation zur<br />

Pilotanwendung”).<br />

The main functions have been gathered in a customer specification "Lastenheft" LH,<br />

consisting <strong>of</strong> eight registers [DB 28] explaining common requirements, operational<br />

requirements, technical system requirements, system environment line, RAMS onboard<br />

equipment, RAMS trackside and operational scenarios. The operational specification has<br />

been transferred to "Use Cases", that should [Mense, S&D, 2003/01+02) use the UNISIG-<br />

SRS functions.<br />

As a main basis for these requirements and the corresponding definition process the findings<br />

at a qualification test period on the test track, an operational analysis and various system<br />

tests have been taken.<br />

When the UNISIG SRS was revised and amended to release 2.2.2 the European spec<br />

became a basis for the technical implementation on BHL as well. Especially for the<br />

operational rules, the handling regulation for onboard and trackside equipment and the<br />

consistency <strong>of</strong> ETCS with the national rule book ("DB Konzernrichtlinie 408") was proved<br />

to conform to the national regular framework for PZB and LZB.<br />

Similarities and differences <strong>of</strong> ETCS in contrast to the national modes (LZB, PZB) have<br />

been structured and categorised. Common features <strong>of</strong> ETCS and LZB should be drafted<br />

equally to be handled in the same or a similar way. Well approved national principles should<br />

be generalised to become commonly valid.<br />

The ETCS pilot is an overlay system to the existing interlockings with a reduced functional<br />

range at the pilot system. [Leißner/Hansen/Beck/Kammel, Signal & Draht, “Erkenntnisse<br />

aus der Risikoanalyse für die ETCS-Pilotanwendung“, 2003-06).<br />

No international rules have been defined yet, since the track does not cross or touch any<br />

member states´ or European borders.<br />

At another phase (operational qualification) the staff (drivers and dispatchers) was trained.<br />

As a result <strong>of</strong> a national obligation in the allowance for qualification testing currently valid,<br />

drivers dispatchers and maintenance staff need to be trained on the specifics <strong>of</strong> the ETCS<br />

pilot to be licensed to operate on the BHL line.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

68/161


All national signals remained along the track. They are still used in the fall back mode and<br />

for trains protected in normal (non-ETCS) PZB- or LZB mode. In ETCS mode indication,<br />

discrepancy is accepted in the moment; wayside signals are not darkened in ETCS mode but<br />

still apparent to the train driver.<br />

The relation from Jüterbog to Halle was already intended to be equipped with GSM-R<br />

before ETCS had been specified, so that only some adaptations had to been done in this<br />

regard when ETCS was to be installed on the line.<br />

RBC-/LZB centres (Release 1.4) are located at Ludwigsfelde, Jüterbog, Wittenberg and<br />

Bitterfeld. The RBCs, LZB centres and existing interlockings are connected via the<br />

proprietary interface SZS/SAHARA.<br />

The Italian Projects<br />

The Rome-Naples HSL<br />

In the operative program [RFI 19] the main operative conditions are indicated.<br />

The maximum speed <strong>of</strong> the line is 300 Km/h. The minimum headway is 5 minutes, with all<br />

passenger trains running at the same speed (homo-kinetic train operation).<br />

To date, the line is mainly used for diurnal passenger traffic for medium and long distance<br />

journeys.<br />

Torino-Novara HSL<br />

In the operative program recalled above the main operative conditions are indicated. The<br />

maximum speed <strong>of</strong> the line is 300 Km/h with minimum headway <strong>of</strong> 5 minutes when all<br />

trains are running at the same speed. The line is mainly used for diurnal passenger traffic,<br />

medium and long distance journeys.<br />

The Dutch projects<br />

Betuweroute<br />

Basic information about the line is given above.<br />

Amsterdam – Utrecht<br />

The present system consists <strong>of</strong> eight Interlocking systems for the four tracks. For availability<br />

reasons the line is split up into four Interlockings for the two western tracks and four for the<br />

eastern tracks.<br />

The following Figure 31 gives an overview <strong>of</strong> the integrated track-side system. The supplier<br />

Bombardier has to interface with a lot <strong>of</strong> ProRail systems, the most important <strong>of</strong> which are:<br />

• Equipment <strong>of</strong> the traffic control;<br />

• ATM network, communication network between the Central Interlocking computers<br />

and the Object Controllers in the equipment houses along the line;<br />

• The object controllers and the outside equipment <strong>of</strong> ProRail.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

69/161


Figure 31 – Track-side architecture <strong>of</strong> the Amsterdam-Utrecht line<br />

HSL ZUID<br />

This (optional) information is not presently available.<br />

The Spanish projects<br />

The Figueras-Perpignan line is intended for mixed traffic between Spain and France. Traffic<br />

control will be located in Figueras and ERTMS rules will be applicable. Other rules have to<br />

be defined under the responsibility <strong>of</strong> the TP Ferro Consortium that has the concession <strong>of</strong><br />

the line.<br />

All other high speed lines are reserved to passenger traffic only. As they are entirely inside<br />

the Spanish territory ERTMS and Spanish national rules are applicable.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

70/161


2.2 The system definition<br />

This section is intended to provide the following information:<br />

• The architectural layout <strong>of</strong> the trackside and train-borne sub-systems, with the help<br />

<strong>of</strong> one or more block-diagrams showing the main system components and their<br />

relationships.<br />

• The identification and a short description <strong>of</strong> all the major constituents and interfaces<br />

<strong>of</strong> such layouts and their specific configurations.<br />

• The list <strong>of</strong> the basic project documentation regarding the safety process for the<br />

overall system that his available (e.g. the description <strong>of</strong> the track-side and train-borne<br />

CC&S assemblies, the preliminary hazard analysis, the criteria for risk tolerability,<br />

the list <strong>of</strong> applicable technical Norms and Specifications (both European and<br />

National), the V&V plans, the safety plans, the quality plans, the available safety<br />

cases and the interoperability certificates for constituents, the plans for system<br />

acceptance.<br />

The Austria-Italy project: Brenner Basis Tunnel<br />

The functional and architectural requirements <strong>of</strong> the control-command and signalling<br />

subsystem is described in the following basic documents:<br />

• The document “Betriebe Regelungen-Regolamento di Esercizio” provides the basic<br />

principle for remote operation <strong>of</strong> the line from the main Control Centre in Innsbruck,<br />

and, in case <strong>of</strong> its unavailability, from the fall-back system to be located in Verona or<br />

in Bologna. Operation in both normal and degraded conditions is considered. Some<br />

new operational rules for taking into account the ETCS Lev. 2 systems are<br />

considered as well.<br />

• The documents “Systemarchitektur – Architettura di Sistema” and “Leit-und<br />

Sicherungstechnik Technischer Bericht – Sistemi di Controllo e Comando Relazione<br />

Tecnica” provide detailed architectural layouts <strong>of</strong> the Control-command and<br />

signalling sub-system, including all the security equipment (e.g. emergency power<br />

supply, access control, emergency radio..) required by higher level safety<br />

requirements given in the document .<br />

• The document “Telekommunikation Technischer Bericht – Telecomunicazioni<br />

Relazione Tecnica”, provides a detailed description <strong>of</strong> the telecommunication subsystem<br />

(GSM-R, TETRA, public GSM, fixed telephony, fiber optics newtwork and<br />

all the interconnected security equpment).<br />

The track side CCS system has been designed in details, on the basis <strong>of</strong> such requirement<br />

specifications. It includes:<br />

• A centralised Control Centre to be located at Innsbruck main station supplemented<br />

by a reserve Centre to be located in Verona or Bologna;<br />

• A couple <strong>of</strong> Solid State Interlocking (SSI): one SSI to be located at Innsbruck main<br />

station, connected to the only RBC located in the same building and onother SSI to<br />

be located at Fortezza station;<br />

• A number <strong>of</strong> axle counters for train detection in the block sections along the line;<br />

• A number <strong>of</strong> fixed balises for train location references;<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

71/161


• The extension <strong>of</strong> the Austrian GSM-R network to cover the whole line up to the<br />

CC&S sub-system border in fortezza;<br />

• Harmonised Marker Boards at each block section extremity<br />

• A number <strong>of</strong> train protection devices like Hot Box Detectors, Axle Load Monitors<br />

etc.<br />

The Austrian project: Vienna – Nickelsdorf<br />

For ETCS trackside system, the System and <strong>Safety</strong> requirements specification can be found<br />

in the document "ETCS Level 1 ÖBB Projektierungsanforderungen Streckeneinrichtungen",<br />

3BU 81400 1005 BGAPC, 29.3.2005" and the “Lastenheft-1-00 für das Zugbeeinflussungssystem<br />

ERTMS/ETCS Level 1 für die Strecke Wien – Hegyeshalom, 10.12.2001”.<br />

The trackside balises are controlled by LEUs directly from the existing signal; the<br />

information is taken directly from the lamp current <strong>of</strong> the signal lamps. The main balise<br />

group consists <strong>of</strong> two balises per main signal. At each distance signal (infill), two in-fill<br />

balises are used. In the stations Euroloop is used as infill. The used interfaces are: the<br />

interface A and the national interface to the signals. Single Repositioning balises are used<br />

where necessary (not <strong>of</strong>ten).<br />

The train borne EVC is functionally independent from other equipment in the existing<br />

vehicle (locomotive type 1116). The existing Vehicle bus (MVB) is the interface between<br />

EVC and DMI. . Interface to the braking is via existing groups <strong>of</strong> components used for LZB.<br />

Further on interfaces are required for electric braking, switching <strong>of</strong>f function for emergency<br />

brake (Notbremsüberbrückung), and driver related operations.<br />

Trackside Interoperability Constituents: constituents are all certified according to the TSI<br />

together with the relevant specifications valid at the start <strong>of</strong> the project.<br />

Certificates <strong>of</strong> Interoperability Components:<br />

• LEUs (from Thales-Alcatel and Siemens): certificates by Arsenal are available.<br />

• Eurobalise (Siemens): certificate by EBC is available.<br />

• Euroloop (Siemens): certificate by Arsenal is available.<br />

• Trainborne equipment: Certificate will be delivered by EBC for only one group <strong>of</strong><br />

constituents. It is not yet available.<br />

The Belgian projects<br />

The L3 and the L4 HSL<br />

The high speed lines L3 (Luik – German/Belgian border) and L4 (Antwerp – Dutch/Belgian<br />

border) are built to achieve a performance <strong>of</strong> up to 300 km/h and a minimum headway <strong>of</strong> 3<br />

minutes under continuous speed supervision provided by ERTMS/ETCS Level 2,<br />

supplemented by ERTMS/ETCS Level 1, which takes over in case the former experiences a<br />

failure while <strong>of</strong>fering parallel operations in a mixed level application.<br />

The ETCS Level 1 lines<br />

The project started at around the year 2000 and received the name: EUROTBL.<br />

At that stage NMBS (SNCB) was one integrated railway company, i.e. Train Operating<br />

Company and Infrastructure Manager in one organisation.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

72/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


The basic concepts are:<br />

• To use <strong>of</strong> ETCS-equipment in the trackside: Eurobalises and LEUs;<br />

• New air-gap interface equipment in the rolling stock extracts the “Packet 44” from<br />

ETCS-telegrams and hands the contents to the existing TBL-equipment in the rolling<br />

stock.<br />

From here the name EURO-TBL emerged – which is not to be used anymore.<br />

Currently the track-side implementation project is under the management <strong>of</strong> Infrabel.<br />

The train operating company NMBS (SNCB) has two options under consideration for the<br />

train borne equipment:<br />

• The solution described above;<br />

• A “real” ETCS-on-board-equipment, complemented with an STM-TBL, which could<br />

deal with the “Packet 44” information.<br />

The French project: LGV-Est<br />

The Figure 32 below shows the overall architecture <strong>of</strong> track-side and train born systems<br />

foreseen for the PEEE project.<br />

Balise KVB*,<br />

crocodile*<br />

Other SEI*<br />

All<br />

captors/transmittor<br />

s : CDV, BSP*….<br />

Spacing Function<br />

TVM430<br />

SEI*<br />

Distance command<br />

station<br />

Engaging Function<br />

TVM430 / KVB loaded + ETCS level 2 loaded + GSM-R loaded…<br />

SILAM/SICAM*<br />

IT Systems Hubs<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

FFFIS<br />

Transmittors:<br />

Eurobalise noncommutable**<br />

Other LEU**<br />

FFFIS<br />

LEU**<br />

FFFIS<br />

Transmittors:<br />

Eurobalise<br />

commutable**<br />

Other RBC**<br />

* Equipment specific to TVM430<br />

** Equipment specific to ERTMS<br />

Equipment in-house, the other<br />

equipment is along the line<br />

GSM-R<br />

Trackside**<br />

Figure 32 – Overall Architecture ERTMS superimposed TVM 430/ SEI (ref. prel.<br />

safety file)<br />

FIS<br />

RBC**<br />

Temporar<br />

Signals<br />

Manageme<br />

*<br />

In contact w<br />

Connection<br />

managemen<br />

Interoperabil<br />

A more detailed architectural overview <strong>of</strong> the track-side system provided by Ansaldo Signal<br />

is given in Figure 33 below.<br />

73/161


Figure 33 – Track-side architecture <strong>of</strong> the PEEE project<br />

The German project: Berlin-HalleLeipzig<br />

Onboard equipment<br />

To date, five traction units BR 101, one DB train control test car BR 707 and the Siemens<br />

VT 1.0/1.5 "Desiro" (basing on BR VT 642) have been equipped with ETCS functions.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

74/161


Figure 34 Train-sets <strong>of</strong> DBAG equiped with ERTMS/ETCS systems<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

75/161


The European Vital Computer (EVC) “ETCS L1/L2 Inboard Unit (OBU) ZUB710”<br />

installed in these test trains has been developed by Siemens. The generic ZUB710 core<br />

system was modified for ETCS L1 and L2 applications. Further equipment: Juridical<br />

Recording Unit (JRU) JR DSE 32 Messma, Driver Machine Interface (DMI) E2 Messma,<br />

radar, odometer pulse generator, balise antenna unit S21, radio basis system and a braking<br />

unit.<br />

Trackside<br />

1200 balises S21 (Siemens), 4 RBCs, MMI and diagnostics computer, 20 BTS stations,<br />

marked by (signal) mast signs. Interlockings transmit the status messages in the yard to the<br />

RBCs for the MA generation. Train and RBC communicate via GSM-R, bidirectional.<br />

Leipzig/Halle-Jüterbog only: 100 points, 306 balise groups, 124 wayside signals, 258<br />

gradients, 99 speed ranges; 7300 element attributes, 13.000 data entities.<br />

The Italian Projects<br />

The Rome-Naples HSL<br />

The document [RFI 21] is the oldest and the highest level document <strong>of</strong> the Italian high speed<br />

line Project. In this document, the high level system architecture is described (see Figure 35)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

76/161


Figure 35 – Architectural layout <strong>of</strong> the CCS sub-system for high speed lines<br />

The Torino –Novara HSL<br />

The system architecture is basically the same as in the Rome-Naples HSL outlined in Figure<br />

35 above. This can be seen as a “Specific System Application”, while the Rome-Naples<br />

System can be considered the ERTMS/ETCS Level 2 “Generic Application” and the first<br />

Specific Application, according to the CENELEC definitions.<br />

The trackside subsystem (SST) consists <strong>of</strong> the following subsystems:<br />

• Interlocking (GdV) based on the generic product NVP+GAT supplied by ASF and<br />

wayside objects supplied by Alstom;<br />

• Train Separation System (DT) based on the generic product RBC and on the<br />

Eurobalise supplied by ASF;<br />

• Hot Axel Box detector and braked wheels detector subsystem (RTB) supplied by<br />

BMB;<br />

• TLC-LD e GSMR networks (communication systems) supplied by SIRTI.<br />

The Dutch projects<br />

PCS<br />

PP PP PP<br />

Central Supervisor Room<br />

Central Operative Room<br />

Betuweroute<br />

The Betuweroute is conceived as a pure ERTMS Level 2 system without fall back solutions<br />

for train control and signalling and without dual signalling. Therefore only ERTMS<br />

equipped trains will be admitted.<br />

Amsterdam – Utrecht<br />

This (optional) information is not presently available.<br />

N<br />

O<br />

D<br />

O<br />

PCS<br />

PP PP PP<br />

PCS<br />

PP PP PP<br />

Train Train Train Train Train Train<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

N<br />

O<br />

D<br />

O<br />

77/161


HSL ZUID<br />

The trackside architecture in a broader context is illustrated in Figure 36 below.<br />

Figure 36 – HSL ZUID Track-side Architecture<br />

The Spanish projects<br />

The system architecture follows closely the ERTMS definition according the TSIs that<br />

develop the EC interoperability Directives. The diagram below shows the main components<br />

and relationships in line with the Project definition.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

78/161


GSMR / EIRENE<br />

ASFA EVC DMI<br />

Interlocking<br />

RBC<br />

Command<br />

Interlocking<br />

RBC<br />

Command<br />

Conventional<br />

Interlocking<br />

RBC<br />

Command<br />

Figure 37 – Architectural layout <strong>of</strong> ETCS Lev. 2 and Lev. 1 lines in Spain<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

GSMR<br />

79/161


3 Phase 3 - Risk analysis<br />

3.1 Hazard analysis and system level mitigations<br />

This section is intended to provide the following information about:<br />

• The process for carrying out the system hazard analysis, the higher level documents<br />

that were considered as higher level inputs and the documents produced as output.<br />

Which organisation(s) is (are) involved in this analysis?<br />

• The results <strong>of</strong> the risk assessment: the mitigations introduced for the unacceptable<br />

risks (e.g. additional safety related requirements), the transposition <strong>of</strong> mitigations to<br />

other sub-systems (e.g. the security sub-system) or to the set <strong>of</strong> rules and procedures<br />

for operations and maintenance.<br />

• The management <strong>of</strong> the Hazard Log alongside the whole System life cycle, with<br />

emphasis to the adopted measures (procedural and technical) and their effective<br />

implementation, the organisation in charge <strong>of</strong> maintaining the Hazard Log. How are<br />

the exported constraints communicated to the parties (like Train Operating<br />

Companies) involved?<br />

• The relationship between the ETCS safety targets versus its reference mission pr<strong>of</strong>ile<br />

and the actual case.<br />

• Additional hazards, not included in the ERTMS list <strong>of</strong> hazards, that were eventually<br />

considered and the ways how they were handled.<br />

The Austria-Italy project: Brenner Basis Tunnel<br />

The Hazard <strong>Analysis</strong> has started with a document dealing with Trackside Tunnel <strong>Safety</strong><br />

Concept including an high level Hazard <strong>Analysis</strong> with mitigation requirements for the tunnel<br />

safety and protection functions. The CCS <strong>Safety</strong> Plan, the functional requirements and the<br />

RAM requirements are based on the conclusions <strong>of</strong> this Hazard <strong>Analysis</strong>.<br />

The Austrian project: Vienna – Nickelsdorf<br />

The Risk <strong>Analysis</strong> document (document 3BU 81400 3003 DUAPC, 12.11.2002) was set up<br />

by a project independent collaborator (author) <strong>of</strong> one manufacturer, on behalf <strong>of</strong> the Railway<br />

Operator ÖBB. Main basis for the risk analysis (numerical target) has been the statistics <strong>of</strong><br />

the total accidents on all lines <strong>of</strong> the railway operator. An independent safety assessor has<br />

assessed the Risk <strong>Analysis</strong> and found it appropriate.<br />

The outcome <strong>of</strong> the Risk analysis is that the specified ETCS safety level and the respective<br />

numerical target value for ETCS is, according to GAMAB/GAME, better than the existing<br />

safety level today.<br />

No specific considerations have been taken concerning procedures for operations and<br />

maintenance.<br />

No hazard log was set up. It seemed not to be required as ETCS is an overlay on the existing<br />

safe system and no further hazards (except the ETCS inherent ones can be introduced).<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

80/161


The Belgian projects<br />

For the TBL-application (usage <strong>of</strong> “Packet 44”), analyses have been taken place, which lead<br />

to the following technical solution:<br />

• Balises at each signal;<br />

• Advance (around 300 m) balises to give early signal-aspect-information.<br />

The advance balises constitute the “+” <strong>of</strong> the TBL1+ system.<br />

The advance balises and the respective locations are the results <strong>of</strong> thorough risks analyses.<br />

For the ETCS level 1 application, the HAZOP is nearly finished. The continuation <strong>of</strong> the<br />

HAZOP / risk analysis process is in progress.<br />

The French project: LGV-Est<br />

At the start <strong>of</strong> the project, before the contracting phase, a detailed risk analysis has been<br />

carried out.<br />

The risks are being monitored; a database is maintained in support <strong>of</strong> the process.<br />

Due to the “GAME” principal (dictating that no developments are allowed that will lead to a<br />

less safe operation) several studies have been conducted before contracting.<br />

This has lead to specific requirements, for example:<br />

• The train has to be stopped within 20 sec after loss <strong>of</strong> radio contact (thereby dictating<br />

the T_NV);<br />

• A double GSMR installation on the train is required mostly for RBC-to-RBC handover<br />

management.<br />

The German project: Berlin-Halle-Leipzig<br />

The risk analysis for ETCS BHL was performed to derive the targets for the safety<br />

requirements. That these, in turn, are met was demonstrated in the safety cases, supported by<br />

a hazard analysis (not to mix up with "hazard identification"), applied to apportion the safety<br />

requirements down to the subsystems and items <strong>of</strong> equipment.<br />

As a constraint the figures for random failure given for the onboard and trackside safety<br />

targets (TSI and SUBSET091) had to be adhered.<br />

Unfortunately an assertion to the acceptable amount <strong>of</strong> hazardous human error (i.e. collapse<br />

<strong>of</strong> procedures) was - and still is - missing for the analysis. This resulted in a wide scope <strong>of</strong><br />

discretion for the apportionment and even interoperability criteria, so that the BHL risk<br />

analysis was strongly influenced by national specifics. In a primary step every hazard was<br />

allocated a THR on basis <strong>of</strong> an equal distribution <strong>of</strong> the tolerable risks. Iteratively this<br />

distribution was adapted during the design process.<br />

The degree <strong>of</strong> itemisation <strong>of</strong> the risk analysis was limited to the levels above the suppliers´<br />

specific system designs. Hence the resulting operational and functional approach led to the<br />

hazard analysis <strong>of</strong> technical, human factors and procedures´ segments.<br />

The analysis was mainly performed by DB Systemtechnik, supported by (operational) data<br />

input from the railway authority. It was decided to use a functional hazard analysis<br />

approach, analogue the aviation process, subdivided into the sections system definition,<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

81/161


hazards´ identification, consequence analysis, risk acceptance analysis and safety<br />

requirements.<br />

The functions ‘plan train run’, ‘prepare train run’, ‘train run disposition’, ‘set up train run´s<br />

preconditions’, ‘accept train run’, ‘perform train run’ and ‘finish train run’ were defined and<br />

detailed down to a level where system specific (technical) design or operational procedures<br />

started. Relevance classifications for the ETCS pilot were added (directly relevant,<br />

indirectly relevant).<br />

At the hazards identification phase concrete hazards were assigned to each (detailed)<br />

function, assessed due to their safety relevance (three categories) and added to the hazard<br />

log. More than 70 hazards identified for the railway operation were filtered, finally 13<br />

remained for ETCS.<br />

The task to determine the accepted level <strong>of</strong> the new ETCS risk was initially tried to be<br />

solved by a joint study <strong>of</strong> SNCF and DB, but this intention failed since the results differed<br />

up to a factor <strong>of</strong> 100 for the acceptable risk.<br />

Hence the accepted risk could only be determined preliminarily, solely based on national<br />

estimation: DB should work out an obliging position as operator responsible for the safe<br />

transport <strong>of</strong> people and goods. This should be evaluated and authorised by the EBA.<br />

As a reference the current risk for a passenger at a one hour train journey was taken,<br />

conforming [DB 22] and [DB 6]. At an ETCS failure a hazard may not only aim at<br />

passengers, but also track workers, neighbours, third parties, goods and environment, but it<br />

can be assumed that if sufficient safety were provided for passengers, it were implicitly<br />

provided for the others, too.<br />

The hazardous situations stored at the STABAG (“Statisik der Bahnbetriebsunfälle und<br />

gefährlichen Unregelmäßigkeiten”, statistic <strong>of</strong> railway operation accidents and hazardous<br />

irregularities) database were investigated for those causes that would also have been causing<br />

hazardous failure <strong>of</strong> the future ETCS system.<br />

The tolerable individual risk for ETCS passengers long distance traffic TIRFETCS-SPFV could<br />

be determined that way. 70% <strong>of</strong> this risk budget was equally distributed on the 13 ETCS<br />

hazards in a first approximation, 30% left for possible future extensions or changes in ETCS<br />

specifications or the BHL implementation.<br />

By the very simple assumption that every hazard would immediately open out to an accident<br />

the factor for external risk reduction could be set to ‘1’. This reduced the effort for the<br />

consequence analysis to zero. In case the suppliers´ hazard analysis would not be able to<br />

attest the achievement <strong>of</strong> the THRs, calculated from TIRF, a specific consequence analysis<br />

would have been performed.<br />

CENELEC EN50129 necessitates the coordination <strong>of</strong> hazards evolved from an operator´s<br />

hazard identification process and those coming from a supplier´s hazard or failure analysis.<br />

Neither a clear borderline between operational and technical hazards is stated in the<br />

standard, nor are any methods proposed for this purpose. For that reason a complex and<br />

extensive "mapping" <strong>of</strong> one hazards type towards the other was performed. Unfortunately<br />

the underlying system definitions and boundaries were not congruent so this approach did<br />

not fully succeed. Anyhow the achievement <strong>of</strong> qualitative and quantitative safety targets -<br />

gained from the risk analysis - could be demonstrated. Parts <strong>of</strong> the "mapping"<br />

documentation become part <strong>of</strong> the safety case documentation.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

82/161


Several local specialities and certain operational frequencies <strong>of</strong> occurrence limit the validity<br />

<strong>of</strong> this risk analysis to the BHL line. As a consequence these specific features need to be<br />

controlled and monitored at revenue service and be adapted from time to time.<br />

As examples may be asserted:<br />

The handling <strong>of</strong> temporary speed restrictions has been specifically solved at BHL; the safety<br />

related context <strong>of</strong> a faulty input <strong>of</strong> such a restriction has not yet been fully captured.<br />

At a signal stop caused by any irregular situation it will be important for the safety <strong>of</strong> the<br />

system that the respective GSM-R message will not be delayed more than 5 sec in order to<br />

keep the calculated safety target. Hence the accordant GSM-R reliability needs to be<br />

assured.<br />

In case level crossings should be installed in future (for some reason), the RA/HA<br />

(risk/hazard analysis) needed to be recalculated, since no LC´s (and LC hazards) have been<br />

considered in the current RA/HA.<br />

The driver needs to be informed to switch <strong>of</strong>f traction in case an emergency braking is<br />

released by the system, otherwise the safety target could be compromised.<br />

While computing the system hazard analysis some missing vital requirements not being<br />

stated in the UNISIG specifications yet had been identified. Change requests were issued.<br />

Therefore on BHL the incompleteness <strong>of</strong> the UNISIG specifications had to be compensated<br />

by several differences to the UNISIG specs. Additionally some considerable operational<br />

restrictions needed to be accepted to guarantee a sufficient level <strong>of</strong> safety.<br />

The Italian Projects<br />

The Rome-Naples HSL<br />

RFI issued a Preliminary Risk <strong>Analysis</strong> [RFI 37]. This document was intended as an input<br />

for the Saturno Consortium to start working on System Hazard <strong>Analysis</strong>. Such activity was<br />

then carried out, under the responsibility <strong>of</strong> the Saturno Consortium, by a Working Group<br />

including experts <strong>of</strong> the signalling system suppliers and with the technical support <strong>of</strong> RFI.<br />

The risk analysis started from the system functions foreseen for the ERTMS/ETCS Lev. 2<br />

system and identifying the risk related to a missed or partial implementation <strong>of</strong> such<br />

functions.<br />

At the end <strong>of</strong> this activity the documents [RFI 119] and [RFI 120] were issued in version A.<br />

The documents were then reviewed prior to closing the project (version B).<br />

The deep experience <strong>of</strong> the work group participants and the working methodology has<br />

guaranteed the completeness <strong>of</strong> the analysis.<br />

Near the end <strong>of</strong> the project a final review <strong>of</strong> the analysis was performed. A new version <strong>of</strong><br />

the same documents (version C) and a new document containing the collection <strong>of</strong> the <strong>Safety</strong><br />

System Requirements [RFI 123] were issued<br />

The revealed hazards were inserted in the project Hazard-Log that has been kept alive<br />

during the whole duration <strong>of</strong> the project.<br />

Besides the two mentioned documents, System FTA and FMEA have been issued as well.<br />

The hazards needing operating procedures for mitigation have been evaluated by the<br />

competent structures <strong>of</strong> RFI that have issued the corresponding procedures.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

83/161


<strong>Final</strong>ly the document [RFI 121] was issued, in which the system HFR (Hazardous Failure<br />

Rate), evaluated in accordance with the methodology indicated in the UNISIG SUBSET091,<br />

is finally reported.<br />

The Torino-Novara HSL<br />

The Turin-Novara system design has been largely based on the ERTMS/ETCS experience<br />

gained in the first ERTMS/ETCS Rome-Naples project. The same safety process has been<br />

put in place for hazard and risk analysis ans well as for the safety approval.<br />

The Dutch projects<br />

Betuweroute<br />

Scope <strong>of</strong> Consortium Alstom-Movares hazard log is the Bev21 system, which includes the<br />

ETCS system. The hazard log also includes measures to be exported to infra manager and<br />

train operator.<br />

ProRail hazard log covers Bev21 integration with Traffic Control and operational processes.<br />

An extensive hazard transfer process has taken place between ProRail and the Consortium to<br />

formally transfer hazards/measures between the two organisations.<br />

Amsterdam - Utrecht<br />

The line is built in accordance with the present design, installation and test constrains. At<br />

present, the risk analysis is focussed more on the introduction <strong>of</strong> new signaling equipment<br />

than on the installation <strong>of</strong> ERTMS.<br />

HSL ZUID<br />

The project organisation HSL Zuid has issued an Integral <strong>Safety</strong> Plan [HSL Zuid<br />

HAVL/567392, versie 10, 30 September 2004] that outlines the main safety concepts and<br />

allocates risks to be mitigated to each party in the Transportation System.<br />

The following organisations were involved in this analysis:<br />

• Bouwdienst Rijkswaterstaat<br />

• Projectdirectie HSL-Zuid<br />

• Predecessor <strong>of</strong> IVW; Railned Spoorwegveiligheid<br />

• NS Railinfrabeheer<br />

The responsibility for mitigating risks related to the superstructure (including CCS) has been<br />

allocated to the supplier (Infraspeed consortium, in which Siemens provides the interlocking<br />

and Alcatel provides the RBC). Therefore no risk allocation within the scope <strong>of</strong> Infraspeed<br />

has been carried out by the Project Organisation; the design responsibility in this respect lies<br />

with the Infraspeed consortium. The interfaces have been designed based on a jointly<br />

established description <strong>of</strong> the operational system. The Integral <strong>Safety</strong> Case for the traffic<br />

system consists <strong>of</strong> prove that the the hazards related to the interfaces are correctly mitigated.<br />

For the Transportation System as a whole an Integral Hazard Log is maintained by the<br />

project organisation HSL Zuid. (ref. HSL document #603704).<br />

Infraspeed maintains the Hazard Log for the HSL Assets (that form the Superstructure<br />

including the CCS sub-system) and for the HSL Activities (that mainly consists <strong>of</strong><br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

84/161


maintenance and renewal activities). This is part <strong>of</strong> the Availability Period <strong>Safety</strong> Case that<br />

has to be updated by the Infraspeed Consortium on a regular basis during the 25 years <strong>of</strong> the<br />

Infraprovider Concession.<br />

Infraspeed has performed a risk analysis (ref. “EPC System Hazard <strong>Analysis</strong> (SHA) IDE<br />

(SYS$TEX&AFF” # 000001) in which 13 top-hazards have been identified.<br />

Two <strong>of</strong> these top hazards were allocated to the trackside CCS:<br />

• H4 - Undetected erroneous movement authority/train protection resulting in<br />

derailment or collision, related to function/failure mode:<br />

• Undetected Erroneous SIG (Signalling sub-system) communication to/from train via<br />

balises (due to overspeed)<br />

• Undetected Erroneous or uncommanded SIG communication to train via fixed Balise<br />

or GSM-R (ETCS Level 2)<br />

• Undetected Erroneous communication between SIG interlocking and RBCs<br />

• Undetected Erroneous or uncommanded communication between Neighbour RBC<br />

and RBC (ETCS Level 1)<br />

• Erroneous track pr<strong>of</strong>ile to RBC<br />

• Loss <strong>of</strong> earth<br />

• Creating <strong>of</strong> erroneous route map RBC<br />

• H5 - Undetected erroneous route protection, resulting in derailment or collision or<br />

fire, related to function/failure mode:<br />

• Undetected erroneous failure <strong>of</strong> trackside status monitoring for high water alarm<br />

• Undetected loss or failure <strong>of</strong> monitoring <strong>of</strong> trackside elements<br />

• Undetected Erroneous route setting<br />

• Undetected Erroneous or uncommanded Track occupancy (train integrity)<br />

• Undetected Erroneous communication between RAS (adjacent conventional track)<br />

interlocking and SIG (HSL) interlocking<br />

• Undetected loss <strong>of</strong> or erroneous information from SIG to AEM allows wrong escape<br />

doors to open when tunnels not train free<br />

• Loss <strong>of</strong> earth<br />

Other Top Hazards were partly allocated to the trackside CCS:<br />

• H2 – Loss <strong>of</strong> free space pr<strong>of</strong>ile due to:<br />

• Movable Water Barrier<br />

• Flood Doors<br />

• Jet Fan.<br />

• H3 – Loss <strong>of</strong> free space pr<strong>of</strong>ile due to objects on track:<br />

• Vehicles<br />

• Vandalism<br />

• Animals<br />

• TPD catenary system<br />

• Landslide/trees<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

85/161


• Subsystem parts<br />

• Maintenance Equipment<br />

• Window penetration.<br />

• H6 – Loss <strong>of</strong> incident mitigation<br />

• Self Rescue<br />

• Emergency Response<br />

• Derailment containment.<br />

• H7 – Failure to protect authorized staff (Staff/ Maintenance Personnel).<br />

• H8 Undetected flooding <strong>of</strong> tunnel, cutting or open track<br />

• H9 Undetected switch failures<br />

The Spanish projects<br />

The responsibility for the safety management during the design, manufacturing and<br />

integration has been left to the supplier.<br />

An ISA appointed by the customer (ADIF or RENFE) has made an assessment <strong>of</strong> the <strong>Safety</strong><br />

Documentation brought by the supplier (Risk analysis, <strong>Safety</strong> case, Test Results, Exported<br />

Rules).<br />

The System Validation and Verification, under ADIF and RENFE test requirements, have<br />

been performed by independent laboratories and safety assessors.<br />

The <strong>Safety</strong> File compiling all the safety related documents, has been delivered to the <strong>Safety</strong><br />

Directorate <strong>of</strong> Adif, and is the basis for the <strong>Safety</strong> Certificate that this body delivers to the<br />

National <strong>Safety</strong> Authority.<br />

The below gives the flowchart <strong>of</strong> the overall safety process in Spain.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

86/161


Contracts, regulations,<br />

directives, laws, safety<br />

requirements<br />

Experience in operation<br />

<strong>Safety</strong> case<br />

Make changes in the<br />

system<br />

No<br />

Figure 38 – <strong>Safety</strong> process in Spain<br />

Beginning<br />

<strong>Safety</strong> planning<br />

System description and<br />

delimitation, safety<br />

requirements.<br />

Hazard and risks<br />

analysis<br />

Have safety aims<br />

been achieved?<br />

(Validation<br />

process)<br />

<strong>Safety</strong> case conclusion<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

Yes<br />

End<br />

<strong>Safety</strong> case<br />

Hazard Log<br />

Conclusion<br />

documentation<br />

87/161


<strong>Safety</strong> is managed under the supervision <strong>of</strong> a suitable organisation, as shown in the figure<br />

below.<br />

TECHNICAL MANAGER OP<strong>ERA</strong>TING MANAGER<br />

HEAD<br />

SAFETY TECHNICIAN /<br />

CTC VERIFICATION<br />

ERTMS<br />

Tests/ERTMS CTC<br />

VALIDATION<br />

Figure 39 – <strong>Safety</strong> management organisation<br />

ENGINEERING<br />

CTC/ERTMS Design<br />

Once the system as a whole has been analysed, preliminary risk analysis is carried out, each<br />

manager dealing with reduction <strong>of</strong> their hazards.<br />

A Hazard Log is created with a record <strong>of</strong> all application hazards picked out, identified by<br />

techniques.<br />

These records are updated to include hazard monitoring, from their initial reduction to the<br />

final reduction. The following is specified for each hazard:<br />

• ID<br />

• Description<br />

• Severity, probability and risk initially assigned<br />

• Person responsible for risk reduction<br />

• Description <strong>of</strong> risk reduction<br />

• Severity and reduced probability and remaining risk<br />

• State: open, pending, closed<br />

The Hazard Log remains open throughout the life cycle <strong>of</strong> the project, it being possible to<br />

add new hazards and reopen closed hazards for repeated analysis if any conditions change.<br />

Hazards are closed by the <strong>Safety</strong> Manager once it is ensured that the remaining risk<br />

following reduction is tolerable according to the criteria established in CENELEC<br />

Standards.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

CONTRACTS<br />

(INSTALLATION)<br />

PROJECT MANAGER<br />

88/161


From the TOP hazards detected, top level safety requirements are determined and which are<br />

aimed at ensuring fulfilment <strong>of</strong> system safety functions.<br />

Figure 40 - Hazard <strong>Analysis</strong> Structure<br />

The preliminary risk analysis (ANNEX VII see RENFE 7) and the preliminary hazard<br />

analysis for the application (ANNEX VIII see RENFE 8) lead to the <strong>Safety</strong> Requirements<br />

list (ANNEX IX see RENFE 9).<br />

<strong>Safety</strong> Requirements<br />

The following list gives the top level safety requirements related to ERTMS:<br />

• The generic data generation process will ensure the right parameters for ERTMS<br />

data thanks to a SIL4 process. (Data entry) (REQ_APR_47)<br />

• ��ENCE<br />

and ERTMS system connection (interface) shall ensure information is<br />

transmitted properly. (REQ_APR_48)<br />

• ��In<br />

the event <strong>of</strong> a loss <strong>of</strong> communication between ERTMS and ENCE, the default<br />

state <strong>of</strong> each piece <strong>of</strong> information will ensure system safety. (REQ_APR_49)<br />

• ��The<br />

interface between ERTMS system components shall ensure information is<br />

transmitted properly. (REQ_APR_50)<br />

• ��Eurobalises<br />

will be installed on the line in accordance with diagrams <strong>of</strong> every 2 Km<br />

<strong>of</strong> track. (REQ_APR_51)<br />

• ��The<br />

generic data generation process will ensure the right parameter setting for<br />

ERTMS data thanks to a SIL4 process. (REQ_APR_52)<br />

• ��ERTMS<br />

L1/L2 system maintenance actions will be carried out in accordance with<br />

the adjustment and maintenance manual. (REQ_APR_53)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

89/161


• ��The<br />

ERTMS L1/L2 system will be installed in accordance with the manuals.<br />

(REQ_APR_54)<br />

• ��The<br />

functionality supported by the ERTMS L1/L2 shall be SIL4 (REQ_APR_55)<br />

<strong>Safety</strong> documents generated are checked by the <strong>Safety</strong> and Engineering managers,<br />

considering technical aspects (design, manufacturing, installation, etc.) and aspects related<br />

to safety (CENELEC standards, safety manual, etc.). Any change or enlargement <strong>of</strong> the<br />

system will be subjected to checks.<br />

For acceptance <strong>of</strong> the system installed it is necessary that:<br />

• All activities are carried out throughout the life cycle <strong>of</strong> the application are checked,<br />

filling in the corresponding inspection reports.<br />

• The validation phase is completed by the application <strong>of</strong> test protocols and<br />

justification that specified requirements have been observed, filling in the<br />

corresponding validation report.<br />

• The <strong>Safety</strong> Case is checked by technical staff for the project, and approved by the<br />

senior safety manager at the construction company.<br />

3.2 Specific issues<br />

This section is intended to provide information about the following specific issues:<br />

• Local needs (e.g., existence <strong>of</strong> level crossings along the line),<br />

• Specific judgement <strong>of</strong> risk (events that are considered “not dangerous” in one<br />

application might be judged differently in a different environment),<br />

• The responsibilities allocated to ERTMS (for example, in a certain application<br />

ERTMS could be responsible <strong>of</strong> sending emergency messages to stop trains in case<br />

objects are detected on the tracks, while in other applications a physical protection <strong>of</strong><br />

the infrastructure against intrusions could be considered sufficient to mitigate this<br />

kind <strong>of</strong> hazards).<br />

• Allocation <strong>of</strong> responsibility to the driver, with respect to data-entry and display <strong>of</strong><br />

information.<br />

The Austria-Italy project: Brenner Basis Tunnel<br />

The specificity <strong>of</strong> this line is due by its full extension within a double tube long tunnel. The<br />

safety mitigations in this case are somewhat different from the normal case. A particular<br />

point is due to the fact that, in case <strong>of</strong> serious accidents (e.g. fire on board) the trains must be<br />

allowed to run up to the next station, the only place where the possibility to escape to the<br />

other tube is existing for the passangers. This requires high availability <strong>of</strong> the controlcommand<br />

functions as well as specific redundant solutions fro telecomminications and<br />

remote control.<br />

The Austrian project: Vienna – Nickelsdorf<br />

As in the Austrian railway system there are many stopping points (e.g. protection signals –<br />

“Schutzsignale”, some standard signals) with too short (or even non-existing) overlap, these<br />

points are the sources <strong>of</strong> possible dangers.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

90/161


According to the ETCS safety principles that take into account inaccurate distance<br />

measurements (1) and the specified braking curves <strong>of</strong> the vehicle (2), calculated braking<br />

distances are always ending a certain distance before the scheduled stopping point.<br />

In the case <strong>of</strong> a signal showing a proceed aspect the scheduled stopping point can be reached<br />

by a continuous infill. In case <strong>of</strong> a stop aspect, this could have disadvantages in e.g. too<br />

short (in comparison with train length, that the rear passenger vehicle does not enter the<br />

station or platform completely) station lengths. Mostly the short stations or platforms cannot<br />

be lengthened due to lack <strong>of</strong> space.<br />

So the only method found for coping with this problem is the introduction <strong>of</strong> a certain<br />

release speed (in Austria 20km/h) even in case <strong>of</strong> 0 m overlap. Otherwise an appropriate<br />

operation <strong>of</strong> the traffic in the stations would not be possible.<br />

So in these cases the safety <strong>of</strong> ETCS could decrease due to the introduction <strong>of</strong> the release<br />

speed.<br />

As infill is only to be used to increase an MA, it could also be used in emergency cases to<br />

transmit a stop aspect to the train (consider that setting a signal immediately to a stop aspect<br />

is also possible in existing interlocking systems). In such an emergency case the effect could<br />

be useful or not (depending on the condition <strong>of</strong> train and reason), but if it is effective it<br />

could decrease a possible damage.<br />

Driver responsibility: Train data must be entered according to regulation “DV ETCS Level<br />

1”.<br />

The Belgian projects<br />

See Chap. 3.1.7 above.<br />

The French project: LGV-Est<br />

This (optional) information is not presently available.<br />

The German project: Berlin-HalleLeipzig<br />

This (optional) information is not presently available.<br />

The Italian Projects<br />

The Rome-Naples HSL<br />

There are no particular specific issues in the ERTMS/ETCS system deployed in this line.<br />

Voice communication beween Control Centre and Drivers is performed via GSM-R Cab<br />

Radio installed on board. A redundant on-board GSM-R Data Terminal is used for tracktrain<br />

data exchange. The redundant nature <strong>of</strong> the radio is due for increased availability as<br />

well as for improving availability and response time during the RBC to RBC hand-over<br />

functions.<br />

The Cab Radio and the Data Terminals used on the Alstom trains as well as the Data<br />

Terminal <strong>of</strong> the Ansaldo trains have got Interoperability Certification by RINA.<br />

The Torino-Novara HSL<br />

Similar considerations as above apply.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

91/161


The Dutch projects<br />

Betuweroute<br />

This (optional) information is not presently available.<br />

Amsterdam - Utrecht<br />

This (optional) information is not presently available.<br />

HSL ZUID<br />

Specific issues including allocation <strong>of</strong> safety responsibilities to ERTMS are described with<br />

more details in the WP3 <strong>Report</strong> <strong>of</strong> this <strong>ERA</strong> Survey Project.<br />

Specific local needs arise from:<br />

• Long tunnel (more than 7 km) that is build as a single tube in which the two tracks<br />

have been separated by a wall; the adjacent track is the safe haven in case <strong>of</strong><br />

emergency evacuation;<br />

• Risk <strong>of</strong> flooding <strong>of</strong> polders that lead to application <strong>of</strong> water barriers/flood doors;<br />

• Risk <strong>of</strong> derailment on the bridge over the Hollands Diep to be mitigated by<br />

measurement <strong>of</strong> wind speed and (eventually) automated alarm calls;<br />

• Driver responsibility, as far as data-entry procedures are concerned.<br />

The Spanish projects<br />

The Ministry <strong>of</strong> Transport has established the so-called National Functions, which are the<br />

packets and variables necessary to complete description <strong>of</strong> the national ERTMS<br />

functionality.<br />

These functions are deemed necessary by the gained experience on the operation <strong>of</strong> high<br />

Speed Lines. Nevertheless, the opinion <strong>of</strong> the experts is that National Functions should be<br />

avoided: if they are really necessary, they should be incorporated to TSIs, otherwise should<br />

be suppressed.<br />

These national packets and variables have to be dealt with by the ERTMS system or be<br />

addressed to other external systems, according to the values <strong>of</strong> the NID_C and NID_XUSER<br />

international variables.<br />

For authorising the commissioning <strong>of</strong> rolling stock, the latter shall comply with the above<br />

National Functions.<br />

National Infrastructure and Rolling Stock Rules introduce new risk control requirements,<br />

outlined in the Manufacturer’s Risk <strong>Analysis</strong>.<br />

National Functions, jointly defined by the Ministry <strong>of</strong> Transport and Adif are as follows:<br />

Ertms National Functions for Trainborne Equipment<br />

• FN-10: Emergency alert<br />

• FN-20: Separate management <strong>of</strong> temporary speed restrictions according to level<br />

• FN-23: Multiple revocation <strong>of</strong> LTV<br />

• FN-24: Eurobalise default message management<br />

• FN-26: Data input<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

92/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


• FN-27: ERTMS management <strong>of</strong> independent ASFA equipment<br />

• FN-35: Station stopping suggestion<br />

• FN-36: Door control supervision<br />

• FN-38: Tilting<br />

• FN-71: Automatic train operation (ATO)<br />

• FN-77: Degraded transition from Level 2 to Level 1 due to loss <strong>of</strong> contact with RBC<br />

when running on track with Level 1 equipment<br />

• FN-40: Degraded transition from Level 1 to STM ASFA Level, running on track<br />

with ASFA equipment<br />

• FN-79: Degraded transition from Level 2 to STM ASFA, running on track with<br />

ASFA equipment<br />

• FN-122: Degraded transition from Level 1 to Level 0 + ASFA, running on track with<br />

ASFA equipment<br />

• FN-123: Degraded transition from Level 2 to Level 0 + ASFA, running on track with<br />

ASFA equipment<br />

• FN-121: Inhibition <strong>of</strong> available levels<br />

• FN-124: Link response management<br />

Ertms National Functions for Level 1 track side equipment<br />

• Tunnel management<br />

• Viaduct and bridge management<br />

• Neutral zones management<br />

• Gauge changer management<br />

• Managing passing trains in tunnels<br />

• ERTMS/ETCS level transitions<br />

• TSR management<br />

• SR speed changes<br />

• Balise default message management<br />

• Detector management<br />

ERTMS introduction has meant the drafting and introduction <strong>of</strong> a series <strong>of</strong> rules into the<br />

General Traffic Regulations for using ERTMS, outlined in Chapter 24 <strong>of</strong> the Operating<br />

Manual (Annex no. 7 see RENFE 7).<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

93/161


4 Phase 4 - System requirements<br />

This section is intended to provide the following information about:<br />

• The process followed for defining the overall system requirements (including both<br />

the trackside and the train-borne sub-systems), based on the applicable ERTMS<br />

specifications and on the input documents produced in the previous phases, with<br />

consideration <strong>of</strong> the needs <strong>of</strong> a generic application case as well as <strong>of</strong> specific<br />

applications.<br />

• The available documents produced for identification <strong>of</strong> functional (ERTMS<br />

operational modes, ERTMS options, fall-back modes, interaction with non ERTMS<br />

signalling systems like train detection, interlocking, telecoms, etc.), environmental,<br />

EMC and detailed RAMS requirements for the project.<br />

• The documents produced for the project management, quality and safety assurance,<br />

version management, V&V, test and certification plans, pre-operation phases and<br />

formalities for the final system acceptance.<br />

4.1 The Austria-Italy project: Brenner Basis Tunnel<br />

This phase <strong>of</strong> the basic project is still in still progress to date. The system design activity is<br />

closely followed by the BBT Infrastructure Manager and the RABBIT Consortium <strong>of</strong><br />

NoBos in relation to the TSI conformity verification and to the fulfilment <strong>of</strong> the National<br />

Austrian-Italian regulations.<br />

4.2 The Austrian project: Vienna – Nickelsdorf<br />

This Project is as well as a new generic application as well as the first specific application <strong>of</strong><br />

ETCS in Austria. The used Subsets are according to V2.2.2.<br />

Basic document on Requirements Specifications on Data Engineering:<br />

• Lastenheft-1-00 für das Zugbeeinflussungssystem ERTMS/ETCS Level 1 für die<br />

Strecke Wien–Hegyeshalom, 10.12.2001.This documents specifies the Functional<br />

Requirements for the project. It is worth mentioning the specification <strong>of</strong> the optional<br />

ETCS requirements to be used in a mandatory way for the project (e.g. the use <strong>of</strong><br />

Euroloop infill) as well as for trackside requirements as the trainside requirements.<br />

• ETCS Level 1 ÖBB Projektierungsanforderungen Streckeneinrichtungen, 3BU<br />

81400 1005 BGAPC, 29.3.2005.<br />

Some <strong>of</strong> the considered issues are:<br />

• Braking distance, speed, gradients, infill,<br />

• Positioning <strong>of</strong> balises, loops and LEUs<br />

• Connections (interface C) with balises and loops<br />

• Announcement <strong>of</strong> loops, Ids<br />

• Coupling <strong>of</strong> signal information<br />

• End <strong>of</strong> platform,<br />

• Used level transistions<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

94/161


• Location reference points, danger points, speed optimization, national values, linking<br />

with link reaction and accuracy<br />

4.3 The Belgian projects<br />

The track side ETCS-sub-system (Balises and LEUs) has to interface with:<br />

• Existing relay interlocking systems; parallel inputs: via potential free contacts.<br />

• Existing electronic interlocking systems (PLP); the LEU is adapted for the serial<br />

connection (TFM) which is available from the PLP-system.<br />

The integration <strong>of</strong> the ETCS track-side subsystem includes:<br />

• Connection to existing interlocking systems.<br />

• Placing balises in the track, according to the Engineering and Dimensioning rules.<br />

As far as the balise installation aspect is considered, Infrabel has defined specific rules, to<br />

take into account other equipment already in the track, like existing TBL-balises, crocodile<br />

(<strong>of</strong>ficially: “Memor”) etc. Therefore, Infrabel concluded that a Balise Group can only<br />

consist <strong>of</strong> a maximum <strong>of</strong> three balises, due to the sum <strong>of</strong> all constraints for the On-board<br />

equipment: see Chap. 2.1.7.<br />

4.4 The French project: LGV-Est<br />

This (optional) information is not presently available.<br />

4.5 The German project: Berlin-HalleLeipzig<br />

Several parties were participating in the requirements define process. The Deutsche Bahn<br />

Netz AG ("Technik und Beschaffung" and "DB Projektbau") acted as the contracting body.<br />

DB authors <strong>of</strong> railway rules and frameworks gave input from the operational points <strong>of</strong> view.<br />

Contributions to the requirements came from trackside operators as well as from traction<br />

and rolling stock operators. Further on GSM-R operators influenced requirements building<br />

to a certain extent. The national safety authority EBA (departments for technical systems<br />

and operational safety) shadowed the progress.<br />

BHL may best be titled to be a Specific Application. Some <strong>of</strong> the constituents may be also<br />

called Generic Applications since they can be used as modifiable or configurable platforms<br />

or subsystems for the deployment in further specific applications.<br />

4.6 The Italian Projects<br />

The Rome-Naples HSL<br />

Starting from the high level UNISIG specifications listed in section, RFI has issued the<br />

following documents:<br />

• Functional Requirements <strong>of</strong> the CCS ETCS Lev. 2 system<br />

• System Requirements<br />

• Annexes to the system requirements<br />

• Requirements for the On Board System and its operational modes<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

95/161


Following the RFI specifications, the supplier issued the requirement documents:<br />

• <strong>Safety</strong> Requirements deriving from hazard analysis<br />

• Trackside Subsystem Requirements<br />

• On Board Subsystem Requirements<br />

Such functional requirements have been verified by the Saturno Consortium. Relevant<br />

verification reports have been issued at different stages.<br />

The lower level requirements have been traced against the corresponding upper level ones.<br />

The Torino-Novara HSL<br />

Similar considerations as above apply.<br />

4.7 The Dutch projects<br />

Betuweroute<br />

The ProRail's project plan is part <strong>of</strong> ProRail safety case and has been assessed by ISA<br />

(Praxis).<br />

The <strong>Safety</strong> Plan for ETCS trackside is available as part <strong>of</strong> Consortiums A15 Trackside<br />

safety case. It was assessed by ISA (ADL). <strong>Safety</strong> plan addresses V&V-process in<br />

accordance with EN50126.<br />

The Quality Plan for ETCS trackside is available as part <strong>of</strong> Consortiums A15 Trackside<br />

safety case.<br />

Amsterdam - Utrecht<br />

Basic system requirements are given in the above Chap.0.<br />

HSL ZUID<br />

The system requirements activity is carried out under the full responsibility <strong>of</strong> the Infraspeed<br />

Consortium.<br />

4.8 The Spanish projects<br />

All the technical regulations and standards applicable to the every different ERTMS projects<br />

are gathered in the Annex (see RENFE 1).<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

96/161


5 Phase 5 – Apportionment <strong>of</strong> system requirements<br />

This section is intended to provide the following information about:<br />

• The authority that monitored/assessed the suppliers work;<br />

• The monitoring procedures adopted;<br />

• The formal approving documents <strong>of</strong> this phase.<br />

5.1 The Austria-Italy project: Brenner Basis Tunnel<br />

This activity is in progress by the system designers, under close control <strong>of</strong> the Infrastructure<br />

Manager and the NoBos in charge <strong>of</strong> conformity verification <strong>of</strong> TSI as well as <strong>of</strong> national<br />

regulations.<br />

5.2 The Austrian project: Vienna – Nickelsdorf<br />

No special apportionments have been found necessary: just using the applicable UNISIG<br />

Subset documents.<br />

5.3 The Belgian projects<br />

This (optional) information is not presently available.<br />

5.4 The French project: LGV-Est<br />

This (optional) information is not presently available.<br />

5.5 The German project: Berlin-HalleLeipzig<br />

The procedure for apportioning the system requirements to subsystems needed to be altered<br />

from the standard process for several reasons.<br />

The change <strong>of</strong> accountabilities for part systems and substructures among companies with<br />

differing economical interests led to uncertainty, since no arrangement still exists for the<br />

global accountability for the system functions.<br />

Another hurdle for the application <strong>of</strong> a standard apportionment process seemed to be the<br />

stringent adherence to the TSI and the UNISIG Subsets; obviously there had been<br />

mandatory EU requirements conflicting to habits, economic interest or even national<br />

regulation.<br />

Missing stability <strong>of</strong> the requirements - both national and European - contributed to timeconsuming<br />

iterations, caused by the unfamiliar complexity <strong>of</strong> accountabilities and processes.<br />

5.6 The Italian Projects<br />

The Rome-Naples HSL<br />

The apportionment <strong>of</strong> the higher level requirements <strong>of</strong> the trackside system was done by RFI<br />

together with the suppliers, by issuing the specification <strong>of</strong> the on board ERTMS/ETCS Lev.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

97/161


2 sub-system: “Volume 3” [RFI 124] and the specification <strong>of</strong> the trackside ERTMS/ETCS<br />

Lev. 2 sub-system “Volume 2” [RFI 122].<br />

For the trackside specification, the structure <strong>of</strong> “Volume 2” was split into different subvolumes,<br />

so achieving a further apportionment <strong>of</strong> the trackside system requirement<br />

The different sub-volumes are:<br />

• Track-side system: – RAMS Requirements<br />

• Track-side system: Train separation<br />

• Track-side system: RBC sub-system<br />

• Track-side system: RBC sub-system - Interface RBC-IXL<br />

• Track-side system: RBC sub-system - Interfaces – Technical Description<br />

• Track-side system: Eurobalise Sub-system<br />

• Track-side system: RTB Sub-system<br />

• Requirements Specifications for the Interlocking Sub-system<br />

• TLC/LD Telecom Sub-system<br />

• TLC/GSM-R Sub-system<br />

The requirements apportionment has been followed by the responsible <strong>of</strong> the PATC<br />

department, with the assistance <strong>of</strong> the responsible <strong>of</strong> the structure “Specificazione Requisiti<br />

di Sistema e Applicazione Sistemi ATC”, by means <strong>of</strong> monitoring and technical meetings.<br />

All the Meeting Minutes became <strong>of</strong>ficial Project documents.<br />

The Torino-Novara HSL<br />

Similar considerations as above apply.<br />

For the trackside specification, the structure <strong>of</strong> “Volume 2” was split into different subvolumes.<br />

This realized explicitly an apportionment <strong>of</strong> trackside system requirement<br />

The different sub-volumes are:<br />

• Specificazione di Sistema<br />

• Sottosistema Distanziamento Treni<br />

• Sottosistema Interlocking<br />

• Interconnessioni<br />

• Sottosistema RTB<br />

• Sottosistema TLC/LD.<br />

5.7 The Dutch projects<br />

Betuweroute<br />

This (optional) information is not presently available.<br />

Amsterdam - Utrecht<br />

The apportionament <strong>of</strong> system requirements is carried out under the full responsibility <strong>of</strong> the<br />

System Provider, under high level indications <strong>of</strong> the Infrastructer Manager.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

98/161


HSL ZUID<br />

The activity regarding apportionment <strong>of</strong> requirements is carried out under the full<br />

responsibility <strong>of</strong> the Infraspeed Consortium.<br />

5.8 The Spanish projects<br />

As exposed in point 1.2.8.1, the Infrastructure Manager ADIF plays a double role in the<br />

safety monitoring process:<br />

• Adif (construction departments) is the author <strong>of</strong> the Terms <strong>of</strong> Reference for the<br />

supply and installation <strong>of</strong> safety equipment, including ERTMS for each line section,<br />

The corresponding contracts have been each awarded to an unique supplier (usually<br />

a consortium), who has been given the responsibility for the design, manufacturing<br />

and installation, as well as the safety management and the elaboration <strong>of</strong> the safety<br />

case <strong>of</strong> the whole delivery.<br />

• The supplier has developed and implemented all the needed equipment under the<br />

assessment <strong>of</strong> an ISA appointed by the supplier himself.<br />

• This task has been fully performed and validated by the suppliers.<br />

• ADIF (<strong>Safety</strong> Directorate) - at the request <strong>of</strong> Adif (construction departments) - does<br />

the Certification <strong>of</strong> the Compliance with safety conditions required for the railway<br />

operation (<strong>Safety</strong> Certificate). In this task it is assited by a Technical Committee and<br />

by an appointed ISA.<br />

• ADIF (Construction Department) applies to the National <strong>Safety</strong> Authority – the<br />

General Directorate <strong>of</strong> Railways within the Ministry <strong>of</strong> Transport – to get the<br />

authorization for placing in service <strong>of</strong> ERTMS. This application has to be<br />

accompanied by the <strong>Safety</strong> Certificate and the supporting documents relative to the<br />

compliance with the implementation <strong>of</strong> the testing plan at the request <strong>of</strong> Adif or,<br />

where appropriate, the Railways General Directorate.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

99/161


6 Phase 6 – Design and implementation<br />

This section is intended to provide the following information about:<br />

• The authority that monitored/assessed the suppliers work;<br />

• The monitoring procedures adopted;<br />

• The formal approving documents <strong>of</strong> the phase.<br />

6.1 The Austria-Italy project: Brenner Basis Tunnel<br />

This section is not applicable to the present stage <strong>of</strong> the Project.<br />

6.2 The Austrian project: Vienna – Nickelsdorf<br />

The document "Requirements Specifications on Data Engineering" (ETCS Level 1 ÖBB<br />

Projektierungsanforderungen Streckeneinrichtungen, 3BU 81400 1005 BGAPC, 29.3.2005)<br />

has been produced as common work between Railway Operator and the Manufacturers.<br />

The Manufacturer specific procedures for design have been assessed by the NoBo. The<br />

<strong>Safety</strong> Cases have been approved by an Independent <strong>Safety</strong> Assessor and after by the NoBo.<br />

6.3 The Belgian projects<br />

This (optional) information is not presently available.<br />

6.4 The French project: LGV-Est<br />

This (optional) information is not presently available.<br />

6.5 The German project: Berlin-Halle-Leipzig<br />

This (optional) information is not presently available.<br />

6.6 The Italian Projects<br />

The Rome-Naples HSL<br />

The design and implementation phase was monitored by ITALFER (Engineering Company<br />

owned by RFI) and the relevant RFI Departments. The supplier and the relevant RFI<br />

structure that assessed each subsystem/product from both the functional and the safety point<br />

<strong>of</strong> view are indicated in Table 6 and in Table 7 below.<br />

Subsystem Supplier RFI Structure in<br />

charge <strong>of</strong> functional<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

RFI Structure in<br />

charge <strong>of</strong> safety<br />

100/161


assessment assessment<br />

SST Saturno Consortium PATC - SRS CC<br />

SSB AF PATC - OSSB<br />

/CESIFER<br />

SDT AF PATC - OSST CC<br />

GdV/NVP+GAT ASF PACS/SS - I CC<br />

RTB BMB SS - TB CC<br />

Table 6 - Assessment <strong>of</strong> sub-systems<br />

AF stands for Alstom Ferroviaria, ASF for Ansaldo Segnalamento Ferroviario, BMB fore<br />

Bombardier.<br />

Product Supplier RFI Structure in charge<br />

<strong>of</strong> functional assessment<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

CC<br />

RFI Structure in charge<br />

<strong>of</strong> safety assessment<br />

RBC AF PATC- PTI CC<br />

EVC AF PATC- PTI CC<br />

NVP ASF PACS CC<br />

Wayside objects AF SS – TB CC<br />

Table 7 - Assessment <strong>of</strong> products<br />

Alstom Ferroviaria provided the main part <strong>of</strong> the track-side system including the RBC as<br />

well as the on-board system on the first set <strong>of</strong> trains enabled for the revenue service.<br />

Ansaldo provided the Interlocking system and the balises (mostly <strong>of</strong> the fixed type), with<br />

some Encoders for some controlled balises (informing the train about the status <strong>of</strong> the Hot<br />

Box Detectors).<br />

The project has been monitored, at system level, by the responsible <strong>of</strong> department PATC by<br />

means <strong>of</strong> monitoring and technical meetings. During the technical meetings the responsible<br />

<strong>of</strong> PATC has been assisted in his work by the responsible structures that managed the<br />

specific technical issue. All the Meeting Minutes became <strong>of</strong>ficial Project documents.<br />

The CENELEC norms have been used as reference for this activity. The assessment activity<br />

consisted in technical meetings, audits, tests witnessing and review <strong>of</strong> documents.<br />

The trackside subsystem (SST) consists <strong>of</strong> the following subsystems:<br />

• Interlocking (GdV) based on the generic product NVP+GAT supplied by ASF and<br />

wayside objects supplied by Alstom;<br />

• Train Separation System (DT) (based on the generic product RBC supplied by AF<br />

and on the Eurobalise supplied by ASF);<br />

• Hot Axel Box detector and braked wheels detector subsystem (RTB) supplied by<br />

BMB;<br />

• TLC-LD e GSMR networks (communication systems)supplied by SIRTI.<br />

In Figure 41 below the trackside system architecture is shown. Each dotted frame contains<br />

the set <strong>of</strong> the products included in a Generic Application (GdV, DT and SST).<br />

101/161


Figure 41 – Block diagram <strong>of</strong> the trackside subsystem<br />

The System is composed <strong>of</strong>:<br />

• A Central Operating Room (PCS) allocated to the overall line control and Peripheral<br />

Rooms (PPF) distribuited on the line;<br />

• The PPF’s control the wayside objects and are linked to PCS and to the neighbouring<br />

PPF’s (next and previous) with which exchanged vital data.<br />

• The Supervisor system (SCC AV) is linked with signalling system (IS) both with<br />

PPF and PCS. This system was considered out <strong>of</strong> the trackside signaling system<br />

during the safety approval process.<br />

• TLC-LD network is a ring built in optical fibres that connects all the PPF’s and the<br />

PCS.<br />

• The LF system is the power supplier for all the devices.<br />

The communication system between trackside and on-board is indicated with TT in the<br />

figure.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

102/161


The Torino-Novara HSL<br />

The same organisation for products supplying and system assessment as shown in the<br />

Rome-Naples case was put in place for this line, with the only difference that the most part<br />

<strong>of</strong> the track-side system including RBC and Interlocking were provided by Ansaldo. The<br />

high speed trains firstly used for the revenue service were provided by Alstom while<br />

Ansaldo trains are still under pre-operational service.<br />

In Figure 42 below, the implemented track-side system architecture is shown. Each dotted<br />

frame contains the set <strong>of</strong> the products included in a Generic Application (GdV, DT and<br />

SST).<br />

Figure 42 – Block diagram <strong>of</strong> trackside subsystem<br />

The System is composed <strong>of</strong>:<br />

• A Central Operating Room (PCS) allocated to the overall line control and Peripheral<br />

Rooms (PPF) distribuited on the line;<br />

• The PPF’s control the wayside objects and are linked to PCS and to the neighbouring<br />

PPF’s (next and previous) with which exchanged vital data.<br />

• The Supervisor system (SCC AV) is linked with signalling system (IS) both with<br />

PPF and PCS. This system was considered out <strong>of</strong> the trackside signaling system<br />

during the safety approval process.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

103/161


• TLC-LD network is a ring built in optical fibres that connects all the PPF’s and the<br />

PCS.<br />

• The LF system is the power supplier <strong>of</strong> all devices.<br />

The communication system between trackside and on-board is indicated with TT in the<br />

figure.<br />

6.7 The Dutch projects<br />

Betuweroute<br />

This (optional) information is not presently available.<br />

Amsterdam - Utrecht<br />

The design and implementation activity is carried out under the full responsibility <strong>of</strong> the<br />

System Provider. The line equipment does not completely fulfill the CCS TSI.<br />

HSL ZUID<br />

The design and implementation activity is carried out under the full responsibility <strong>of</strong> the<br />

Infraspeed Consortium.<br />

6.8 The Spanish projects<br />

The comment under Chapter 5.8 applies.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

104/161


7 Phase 7 – Manufacturing<br />

This section is intended to provide the following information:<br />

• The authority that monitored/assessed the suppliers work;<br />

• The monitoring procedures adopted;<br />

• The formal approving documents <strong>of</strong> this phase.<br />

7.1 The Austria-Italy project: Brenner Basis Tunnel<br />

This section is not applicable to the present stage <strong>of</strong> the Project.<br />

7.2 The Austrian project: Vienna – Nickelsdorf<br />

The Interoperability Constituents have been manufactured according to the certified process<br />

which has been assessed by the NoBo responsible for the component. The track-side<br />

installation is covered in the next chapter on phase 8.<br />

For the locomotive, the NoBo assessed the process <strong>of</strong> the equipment <strong>of</strong> the locomotive with<br />

the interoperability component (in this project the group <strong>of</strong> components).<br />

7.3 The Belgian projects<br />

This (optional) information is not presently available.<br />

7.4 The French project: LGV-Est<br />

This (optional) information is not presently available.<br />

7.5 The German project: Berlin-HalleLeipzig<br />

For the test trains momentarily running on the BHL line, Siemens AG was charged to<br />

develop/deploy the onboard equipment.<br />

Alcatel SEL AG (now: Thales) developed the trackside equipment.<br />

Bombardier Transportation carried out the adaptation <strong>of</strong> the machine-technical facilities<br />

(train control computer and machine-technical display).<br />

Deuta performed the adaptation <strong>of</strong> the recording equipment (DSK) and the displays for the<br />

train protection systems.<br />

7.6 The Italian Projects<br />

The Rome-Naples HSL<br />

The Saturno Consortium was the supplier responsible for the manufacturing and installation<br />

phases. ITALFER has been the controller. The Saturno Consortium issued a guideline for<br />

classifying against the criticality the devices. Furthermore the Consortium issued<br />

procedures/guidelines for managing the manufacturing, the assembly, the installation and<br />

the acceptance phases <strong>of</strong> the most critical devices.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

105/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


The ITALFER verification phases, the formal documents to be issued (“Piano Controllo<br />

Qualità” - PCQ) and their contents have been defined in these procedures. ITALFER has<br />

verified each single document that classified the devices. ITALFER has then witnessed the<br />

test phases on a sample basis.<br />

The main documents issued are “Piano Controllo Qualità” (Quality Control Plan).<br />

In addition to all PCQ’s, for both the supply and the installation phases, the following<br />

documents were issued:<br />

• “Elenco EPC/PCQ di fornitura - A104.00.CI1.CQ.IT.00.0.0.052 rev I” (Supply)<br />

• “Elenco PCQ di installazione - A104.00.CI1.CQ.IT.00.0.0.053 rev R” (Installation)<br />

The Torino-Novara HSL<br />

A similar manufacturing control process mainly managed by ITALFER, as for Rome-<br />

Naples, was put in place.<br />

7.7 The Dutch projects<br />

Betuweroute<br />

This (optional) information is not presently available.<br />

Amsterdam - Utrecht<br />

The manufacturing activity is carried out under the full responsibility <strong>of</strong> the System<br />

Provider, in accordance with the ProRail general regulations.<br />

HSL ZUID<br />

The manufacturing activity is carried out under the full responsibility <strong>of</strong> the Infraspeed<br />

Consortium.<br />

7.8 The Spanish projects<br />

This task has been fully performed and validated by the suppliers.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

106/161


8 Phase 8 – Installation<br />

This section is intended to provide the following information:<br />

• The authority that monitored/assessed the suppliers work;<br />

• The monitoring procedures adopted;<br />

• The formal approving documents <strong>of</strong> this phase.<br />

8.1 The Austria-Italy project: Brenner Basis Tunnel<br />

This section is not applicable to the present stage <strong>of</strong> the Project.<br />

8.2 The Austrian project: Vienna – Nickelsdorf<br />

The installation <strong>of</strong> the balises was performed partly by the Railway Operator and partly by<br />

the manufacturers. The NoBo assessed the quality <strong>of</strong> installation <strong>of</strong> balises by assessing each<br />

balise at the main signals and samples at the other locations outside <strong>of</strong> railway stations. This<br />

corresponds to a sort <strong>of</strong> “Module F” assessment <strong>of</strong> the installation, as the NoBo was not<br />

involved in the project from the very beginning.<br />

The installation <strong>of</strong> the loops was performed partly by the Railway Operator and partly by the<br />

manufacturer. All Loops have been assessed individually by the NoBo. This was due partly<br />

resulting because Module F for the certification <strong>of</strong> the loops has been used, partly because<br />

the installation <strong>of</strong> the loops presented problems in the beginning and the NoBo was not<br />

involved in the project from the very beginning.<br />

The results and component installations assessed will be contained in the NoBo report.<br />

8.3 The Belgian projects<br />

This (optional) information is not presently available.<br />

8.4 The French project: LGV-Est<br />

This (optional) information is not presently available.<br />

8.5 The German project: Berlin-Halle-Leipzig<br />

Apart from the operational framework for the parallel handling <strong>of</strong> all three modes (ETCS,<br />

LZB and PZB) a framework for the installation, acceptance procedure and maintenance has<br />

been set up.<br />

The installation was split into several steps, called "ETCS releases".<br />

The first release only served test purposes and was implemented in 2001-07. Experience was<br />

gathered with regard to the GSM-R infrastructure, odometry and general UNISIG<br />

procedures.<br />

Until 2003-07 further tree releases followed, when qualification tests were started in 2003-<br />

12.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

107/161


At that time the RBCs were connected to the interlockings and on-board CC infrastructure<br />

was integrated. The track was equipped with the balises. Further releases und upgrades<br />

followed.<br />

8.6 The Italian Projects<br />

The Rome-Naples HSL<br />

See above.<br />

The Torino-Novara HSL<br />

See above.<br />

8.7 The Dutch projects<br />

Betuweroute<br />

This (optional) information is not presently available.<br />

Amsterdam - Utrecht<br />

The installation activity is carried out under the full responsibility <strong>of</strong> the System Provider, in<br />

accordance with the ProRail general regulations.<br />

HSL ZUID<br />

The installation activity is carried out under the full responsibility <strong>of</strong> the Infraspeed<br />

Consortium.<br />

8.8 The Spanish projects<br />

This task has been fully performed and validated by the suppliers.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

108/161


9 Phase 9 – System validation<br />

This section is intended to provide the following information:<br />

• The authority that monitored/assessed the suppliers work;<br />

• The monitoring procedures adopted;<br />

• The formal approving documents <strong>of</strong> this phase.<br />

9.1 The Austria-Italy project: Brenner Basis Tunnel<br />

This section is not applicable to the present stage <strong>of</strong> the Project.<br />

9.2 The Austrian project: Vienna – Nickelsdorf<br />

<strong>Safety</strong> <strong>of</strong> the existing operational line is not influenced (approval <strong>of</strong> LEUs by safety<br />

authority) by the ETCS equipment. ISA report and safety cases for project specific design<br />

from manufacturers are available. Detailed technical validation (content <strong>of</strong> each telegram)<br />

performed by the NoBo.<br />

<strong>Safety</strong> Cases were delivered by suppliers for the project; V&V plans, quality plans are<br />

referenced therein.<br />

<strong>Final</strong> <strong>Safety</strong> Cases for ETCS train borne equipment are not yet available. The conventional<br />

part is nationally approved in 1116 type locomotives, enhanced by ETCS equipment by<br />

Siemens, whose certification work is ongoing.<br />

Compliance verifications with the functional and safety requirements have been carried out<br />

by NoBo. The physical installation <strong>of</strong> each LEU, balise and loop along the line has also been<br />

checked by the NoBo (see Chapter 8.2 above).<br />

Assessment by the NoBo <strong>of</strong> the procedures carried out by the manufacturers. A diverse way<br />

<strong>of</strong> testing all data (content <strong>of</strong> each telegram) was chosen and done by the NoBo itself but not<br />

with safety responsibility.<br />

The NoBo <strong>Report</strong> on testing and validation <strong>of</strong> the telegram data was basis for approval <strong>of</strong><br />

running operational tests with trains (locomotive double manned, no passenger transport).<br />

Because the approbatory tests have not fully been carried out up to now, the NoBo<br />

certificate is not available yet.<br />

For interoperability constituents and application related design EN50126 conform within the<br />

manufacturers.<br />

Availability <strong>of</strong> Certificates for track-side Interoperability Constituents:<br />

• Eurobalise issued by EBC in 2004<br />

• Euroloop issued by Arsenal Research in 2004 + 2005<br />

• LEU issued by Arsenal Research for both suppliers in 2004<br />

• Trainside not available now, foreseen from EBC<br />

Some sorts <strong>of</strong> cross tests have been carried out:<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

109/161


• Runs <strong>of</strong> the DB ETCS test car (with Siemens s<strong>of</strong>tware for the EVC) have been<br />

carried out successfully.<br />

• Test runs with a Hungarian vehicle from MAV (EVC level 1 without infill, produced<br />

by Alcatel) were successful and showed the necessity <strong>of</strong> the infill function within the<br />

train-borne equipment.<br />

9.3 The Belgian projects<br />

For the <strong>Safety</strong> <strong>Approval</strong> <strong>of</strong> a line and its operation, the complete CENELEC cycle is<br />

applied. Starting from safety cases for constituents as RBCs, LEUs, Balises and trackcircuits,<br />

generic application safety cases are made.<br />

These safety cases are then taken as a basis for the L3 and the L4 and level 1 on the<br />

conventional network specific application safety cases. The L3 and L4 Engineering and<br />

Programming data safety cases are added to these safety cases. After that, the L3 and L4<br />

safety cases are made, including the operational rules.<br />

In parallel a safety case for the operating system EBP is made.<br />

The L3 and the L4 HSL<br />

A complete RAMS analyses has been performed.<br />

The ETCS Level 1 lines<br />

KEMA Rail Transport Certification is the ISA (Independent <strong>Safety</strong> Assessor) for this project<br />

and the Notified Body for the track-side assembly.<br />

The contracting entity is: Infrabel, the Infrastructure Manager <strong>of</strong> the Belgian railway<br />

network.<br />

The lifecycle <strong>of</strong> CENELEC is used as framework for the ISA activities.<br />

The module SG is used for the EC conformity certification.<br />

KEMA Rail Transport Certification reports to Infrabel, where Infrabel reports to the<br />

Ministry. At important milestones, KEMA Rail Transport Certification presents its results to<br />

Infrabel and to the Ministry in joint meetings.<br />

The supplier is: Siemens for balises, LEUs and for the engineering data, which is required to<br />

program balises and LEUs.<br />

The following tests were carried out:<br />

• Firstly regarding EUROTBL2;<br />

• Secondly regarding TBL1+ (tests are still going on);<br />

• Tests regarding ETCS Lev. 1 are still to be executed.<br />

KEMA Rail Transport Certification (as ISA+NoBo) monitors the supplier’s tests and the<br />

tests executed by Infrabel.<br />

There have been some compatibility problems between the train-borne KVB-system (in<br />

Thalys trains) and Eurobalises. This problem is well known at European level and still under<br />

debate within UNISIG.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

110/161


Derogation is foreseen to deal with the KVB vs. Eurobalise compatibility problem, but not<br />

formally defined yet.<br />

Also the integration with LEU’s and existing interlocking systems are not flawless, partly<br />

related to EMC and not precisely defined signal levels.<br />

The safety cases <strong>of</strong> suppliers as Siemens, Alstom and Ansaldo are checked by ISA’s hired<br />

for that purpose by the same companies.<br />

9.4 The French project: LGV-Est<br />

The system validation has been done via a step by step process by the NSA. The safety case<br />

has been produced by SNCF and evaluated/checked by RFF.<br />

At the moment this report was drafted the safety case was not completed yet.<br />

In order to obtain approval <strong>of</strong> the safety case tests under real operational conditions, without<br />

real passengers, is necessary in order to have a new certificate. This also requires pro<strong>of</strong> <strong>of</strong><br />

the availability <strong>of</strong> the system. The exact procedure is being discussed with the NSA.<br />

9.5 The German project: Berlin-HalleLeipzig<br />

The Eisenbahn-Bundesamt (EBA) was monitoring the whole process from the beginning.<br />

9.6 The Italian Projects<br />

The Rome-Naples HSL<br />

The suppliers have performed the validation activities regarding the Generic Products, the<br />

Generic Application and the first Specific Application. The following <strong>Safety</strong> Cases were<br />

issued by the suppliers at the end <strong>of</strong> the validation activities:<br />

• <strong>Safety</strong> Case for the Trackside Sub-system (Generic and Specific Application);<br />

• <strong>Safety</strong> Case for the Train Separation Sub-system (Generic and Specific Application);<br />

• <strong>Safety</strong> Case for the On Board Sub-system.<br />

• <strong>Safety</strong> Case for the Interlocking Sub-system;<br />

The assessment <strong>of</strong> Generic Application / First Specific Application was performed on the<br />

Labico–S. Giovanni line stretch (km. 31+933 – km. 115+841) that is representative <strong>of</strong> all the<br />

characteristics and the equipment <strong>of</strong> the entire line. On the line stretch Labico–S. Giovanni<br />

all the ERTMS/ETCS lev. 2 functionalities have been tested with a high speed train<br />

especially equipped for functional test and verification purposes.<br />

In addition to the suppliers on field validation activities, RFI has performed some field test<br />

sessions to assess the correct implementation <strong>of</strong> the signalling system functionalities [see<br />

documents listed in the annex].<br />

The RFI trackside assessment activities are described in the document [RFI 107].<br />

For the first specific application, a Technical Committee <strong>of</strong> RFI verified, by means <strong>of</strong> on<br />

field test, the correctness <strong>of</strong> installation, assembly and system configuration. The activities<br />

<strong>of</strong> the Technical Committee were performed in compliance with the applicable RFI<br />

directives [see the annex].<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

111/161


A functional assessment <strong>of</strong> the Trains Separation System (SDT- both trackside and on board<br />

functions) was carried out. The assessment borders are highlighted by means <strong>of</strong> a grey box<br />

in Figure 43 below.<br />

Conventional<br />

Line<br />

SCC<br />

NVP RBC/<br />

SDT<br />

Figure 43 - Borders <strong>of</strong> the Train Separation System - SDT<br />

For the validation and the assessment <strong>of</strong> the field tests the general contractor has issued<br />

some operational rules to ensure the overall safety during the tests. A general contractor on<br />

board people (IBT) radio linked with a trackside safety responsible (RPT) has been foreseen.<br />

During the test the pertinent suppliers personnel have controlled on site all the interlockings<br />

and the RBCs. In the interconnection test the RFI personnel have ensured the safety <strong>of</strong> the<br />

trains on the conventional line momentarily closing the commercial services during the tests.<br />

SSB<br />

Information Points<br />

(Eurobalises)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

RTB<br />

TLC<br />

112/161


After the assessment <strong>of</strong> the products, the generic and the first specific application, on 2005<br />

September the 12 th , RFI proceeded to a preliminary acceptance (see phase 10) <strong>of</strong> the line to<br />

start the approbatory period in compliance with the procedure [RFI 35].<br />

During this period, RFI assessed the following issues:<br />

• Operational rules, especially developed for ERTMS/ETCS Lev. 2<br />

• Rolling stock and infrastructure functionalities and their interfaces<br />

• Organisational model for the commercial operation <strong>of</strong> the line<br />

• Infrastructure management (effectiveness <strong>of</strong> the organisation and diagnostic devices)<br />

• Potentiality <strong>of</strong> the line revenue service.<br />

Furthermore the train Operator TRENITALIA has carried out the assessment <strong>of</strong>:<br />

• Adequacy <strong>of</strong> service management;<br />

• Effectiveness <strong>of</strong> the training courses for the operative personnel;<br />

• Effectiveness <strong>of</strong> the rolling stock maintenance.<br />

During the approbatory period suppliers and RFI personnel have carried out all the tests<br />

together.<br />

A RFI test manager has been performed the test run on train borne together with IBT.<br />

During the test trains and RBC data have been collected by means <strong>of</strong> specific tools (Canapè<br />

for the on board data and LDR for RBC). A fine tuning on the products and configurations<br />

has been carried out after the completion <strong>of</strong> the tests.<br />

The results <strong>of</strong> the approbatory period tests were made available on monthly reports [RFI<br />

103].<br />

The Torino-Novara HSL/HCL<br />

The suppliers have performed the validation activities regarding the Generic Products,<br />

Generic and Specific Applications. The <strong>Safety</strong> Cases issued by the suppliers at the end <strong>of</strong><br />

the validation activities have been:<br />

• Trackside Subsystem;<br />

• Train Separation Subsystem;<br />

• Interlocking Subsystem;<br />

• On Board Subsystem.<br />

• System integration <strong>of</strong> Alstom On-bBoard sub-system versus Ansaldo Trackside subsystem.<br />

In addition to the field validation activities carried out by the suppliers, RFI performed some<br />

field test sessions to assess the implementation <strong>of</strong> the signalling system functionalities.<br />

For the specific application, a technical commission has verified, by means <strong>of</strong> field test, the<br />

correctness <strong>of</strong> the installation, the assembly and the system configuration.<br />

A functional assessment <strong>of</strong> the overall Train Separation System (trackside and on board), as<br />

described in the Rome-Naples line documents, has been carried out.<br />

A similar test management process, as the one adopted for the Rome – Naples line has been<br />

put in place also on the Turin-Novara line for validation and assessment <strong>of</strong> the field tests.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

113/161


After the assessment <strong>of</strong> the products, generic and specific applications, on 2005 november<br />

the 28 th RFI gave a preliminary acceptance <strong>of</strong> the line, enabling the start the approbatory<br />

period. The results <strong>of</strong> the approbatory period tests were made available on monthly reports.<br />

9.7 The Dutch projects<br />

Betuweroute<br />

The BR A15 Trackside <strong>Safety</strong> Case according to EN50126, including ISA report (ADL), for<br />

Alstom-Movares Bev21- A15v3.4 configuration (ERTMS Lev. 2 system), is available.<br />

A separate <strong>Safety</strong> Case was developed by Prorail for integration <strong>of</strong> Bev21 with Dutch<br />

Traffic Control system and results to date approved by ISA (Praxis).<br />

The safety assessment included in Alstom Bev21 Trackside <strong>Safety</strong> Case exported<br />

constraints transferred to ProRail and incorporated in the ProRail <strong>Safety</strong> Case (covering<br />

integration the Dutch Traffic Control System, Bev21 and operation/maintenance).<br />

The ERTMS maintenance system (LCS, etc) was part <strong>of</strong> the Alstom delivery.<br />

The compliance with contractual functional requirements is demonstrated in Alstom A15<br />

Trackside safety case. For ETCS a trackside <strong>Safety</strong> Plan is available as part <strong>of</strong> Consortiums<br />

A15 Trackside safety case, assessed by ISA (ADL). The safety plan addresses the V&Vprocess<br />

in conformity with EN50126.<br />

For ETCS a trackside Quality Plan is available as part <strong>of</strong> Consortiums A15 Trackside safety<br />

case.<br />

The ProRail project plan is part <strong>of</strong> the ProRail safety case and has been assessed by an ISA<br />

(Praxis).<br />

The Scope <strong>of</strong> the supplier Consortium Alstom-Movares hazard log is the Bev21 system,<br />

which includes the ETCS system. The hazard log also includes measures to be exported to<br />

infra manager and train operator.<br />

The ProRail Hazard Log covers Bev21 integration with Traffic Control and operational<br />

processes.<br />

An extensive hazard transfer process has taken place between ProRail and Consortium<br />

Alstom-Movares to formally transfer hazards/measures between the two organisations.<br />

After the NoBo statements and the safety cases for the trackside and train borne subsystem<br />

have been obtained, as well as permission for test exploitation has been granted, a technical<br />

and operational hazard analyses is performed for the integrated trackside and train borne<br />

systems.<br />

On this basis a specific test plan is made on the basis <strong>of</strong> a default track train integration<br />

testplan. This can lead to a “verklaring van geen bezwaar” (a declaration <strong>of</strong> no objection) by<br />

IVW.<br />

After a subsequent system qualification test the “inzetcertificaat” (operation certificate) can<br />

be issued. These tests include testing trainborne and trackside sub-systems for 10.000 km,<br />

absolved by a train <strong>of</strong> a specific type.<br />

The results from monitoring are needed to finalise the trackside as well as the train borne<br />

CENELEC safety cases.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

114/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


Amsterdam- Utrecht- HSL<br />

The line is built in accordance with the CENELEC procedures, but the line covers the rules,<br />

regulations and safety requirements <strong>of</strong> a domestic line. By the end <strong>of</strong> 2009, the line will be<br />

equipped with dual signaling ERTMS level STM / 2.<br />

ProRail has to provide the National Railway Authority <strong>of</strong> the Minister <strong>of</strong> Transport and<br />

Water management with the complete set <strong>of</strong> safety cases to demonstrate that the line fulfils<br />

all the technical rules, regulations and safety conditions required for the domestic railway<br />

network.<br />

All the safety cases are assessed by an ISA.<br />

HSL ZUID<br />

The authority that monitored the work <strong>of</strong> the CCS sub-system was the supplier itself (i.e. the<br />

Infraspeed Consortium).<br />

The risk for the performance <strong>of</strong> the systems is part <strong>of</strong> the Design-Build-Finance-and-<br />

Maintain Contract. This is taken into account by means <strong>of</strong> the Performance Payment<br />

Regime: payments will be done by the State <strong>of</strong> the Netherlands during the 25 years <strong>of</strong> the<br />

contract in accordance with the availability performance <strong>of</strong> the systems.<br />

9.8 The Spanish projects<br />

Validation&Verification guidelines<br />

The validation and verification process is evolving according to the experiences acquired in<br />

the implementation <strong>of</strong> the different ERTMS implementations. Up to now, the V&V process<br />

is performed following closely the prescriptions <strong>of</strong> the Railway Sector Act 39/2003 and the<br />

Ministry Order FOM 233/2006, under the survey <strong>of</strong> the Ministry <strong>of</strong> Transport.<br />

In particular, this Order develops the following concepts, as a transposition <strong>of</strong> the EC<br />

Directives:<br />

• Technical Specifications for Homologation (Especificaciones Técnicas de<br />

Homologación, ETH), that compile the <strong>Safety</strong> requirements, the essential<br />

requirements, the functional requirements including interoperability, maintenance<br />

requirements, and evaluation modules for the assessments <strong>of</strong> conformity and fitness<br />

for use. This ETH should be completed and published by August 2008. In the<br />

meantime, the STI and the National standards are applicable.<br />

• Validation procedures, to assess the conformity <strong>of</strong> constituents and subsystems with<br />

the ETH<br />

• CE Verification procedures, how the Notified Bodies certify the compliance with the<br />

Interoperability Directives<br />

In accordance with the above rules, the Validation and Verification processes can be<br />

summarized as follows:<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

115/161


Responsible body Certification Entity<br />

(Accredited by ENAC)<br />

Validation CE Verification<br />

Notified Body<br />

Applicable specifications ETH STI<br />

Object RAMS, Environment, Health Interoperability<br />

Scope National European Community<br />

Validation procedure<br />

The procedures and supporting documents for ERTMS trackside and on board equipment is<br />

very similar. In both cases the Declaration <strong>of</strong> Conformity is prepared by the supplier who is<br />

also the applicant versus the Certification Body. The Authorization for Operation is issued<br />

by ADIF. The figure below summarizes the procedure:<br />

Validation<br />

Issued by a Certification Entity<br />

Authorization to enter in service<br />

Issued by G. Dir. <strong>of</strong> Railways (NSA)<br />

Authorization for Operation<br />

Issued by Adif<br />

Figure 44 - Validation process<br />

CE Verification<br />

Issued by a Notified Body<br />

Interim Authorization for Operation<br />

Issued by Adif<br />

Running tests<br />

specified in ETH<br />

The Validation is organized in two separate parts, for the European and the National<br />

functions, as shown in the following table:<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

116/161


EC pre<br />

declaration<br />

Specific<br />

National<br />

Declaration<br />

Object File contents<br />

Generic product<br />

+<br />

Specific<br />

application<br />

+<br />

Specific trackside<br />

tests<br />

National<br />

Functions<br />

+<br />

Specific trackside<br />

tests<br />

Definition <strong>of</strong> the products and the application<br />

(according to the relevant consolidated TSI in force)<br />

Verification and Validation Dossier<br />

<strong>Safety</strong> Case<br />

Independent <strong>Safety</strong> Assessment report for the products<br />

and the trackside or on board unit<br />

Specific trackside tests report<br />

Definition <strong>of</strong> the national application according to NF<br />

Verification and Validation Dossier<br />

<strong>Safety</strong> case<br />

Independent <strong>Safety</strong> Assessment<br />

Specific trackside tests<br />

The most significant part in the whole process is the specification <strong>of</strong> the “complementary<br />

tests”, that has been a joint task <strong>of</strong> Adif, the manufacturers, the CEDEX laboratory (as<br />

reference laboratory) and Tifsa (as Independent <strong>Safety</strong> Assessor).<br />

The role <strong>of</strong> ISA has been played by different entities in each project:<br />

Train series ISA<br />

102 – 103 SAC<br />

120 Certifer - Tifsa<br />

100 – 104 Certifer - Cetren<br />

Complementary tests (for all series)<br />

Test realisation Renfe – Adif – Tifsa - CEDEX<br />

Test technical reports Tifsa - CEDEX<br />

At the present time there is not a consolidated policy related to the endurance tests. For<br />

instance for ERTMS Level 1, the trains <strong>of</strong> series 102 have had to run 100 000 kms without<br />

incidents before being authorized to operate (at the same time the trackside equipment was<br />

verified). But for trains <strong>of</strong> series 103 this requirement has been reduced to 50 000 kms. The<br />

criteria that is currently applied for other trains is to complete 30 000 kms under ERTMS<br />

plus 10 000 with STM, without incidents.<br />

Compatibility and Interoperability issues<br />

In all the Spanish ERTMS projects, the ERTMS/ETCS equipment installed is conform to<br />

the ERTMS/ETCS Class 1 System Requirements Specification <strong>of</strong> the UNISIG group, vers.<br />

2.2.2, plus a number <strong>of</strong> Change Requests included in the Subset 108.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

117/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


There were several technical discussions between the manufacturers, Adif and Renfe, to<br />

assess the interoperability aspects <strong>of</strong> these Change requests. No problems were identified in<br />

the trackside subassembly, but 15 change requests related to On board Unit require further<br />

analysis. These CR are:<br />

Level 1: CR218, CR219, CR231, CR234, CR633 y CR464<br />

Livel 2: CR226, CR475, CR633, CR441, CR458, CR508, CR512, CR50, CR146 y<br />

CR126.<br />

Alter the discussion it seems that the only CR that produces interoperability problems is the<br />

CR 458. It has been decided to wait for a clarification from UNISIG before its<br />

implementation.<br />

A survey on the implementation <strong>of</strong> the CRs by the different manufacturers has been done. It<br />

is summarized in the document CHANGE_REQUEST_LIST_.doc.<br />

The EC conformity certificates for the track-side system and the train borne systems are not<br />

yet available. CETREN will be in charge <strong>of</strong> this task.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

118/161


10 Phase 10 – System acceptance<br />

This section is intended to provide the following information about:<br />

• The process followed for the final acceptance <strong>of</strong> the trackside (and train-borne subsystems)<br />

by the Infrastructure manger, the relevant acceptance formalities regarding<br />

the fulfilment <strong>of</strong> the operational, functional, RAMS and interoperability<br />

requirements.<br />

• The authorisation process followed and the bodies involved in the acceptance <strong>of</strong><br />

minor non-conformities evidenced during the previous phases not endangering safety<br />

and interoperability <strong>of</strong> the sub-systems.<br />

• The formalities and the relevant bodies required for authorising the start <strong>of</strong> revenue<br />

service <strong>of</strong> the trackside and train-borne sub-systems.<br />

• Rules for the operational use;<br />

• Rules for (periodic) maintenance.<br />

10.1 The Austria-Italy project: Brenner Basis Tunnel<br />

This section is not applicable to the present stage <strong>of</strong> the Project.<br />

10.2 The Austrian project: Vienna – Nickelsdorf<br />

Trackside subsystem: NoBo Assessments and procedures described in the phases before,<br />

together with an interim report on the safety <strong>of</strong> the trackside data, the approval authority<br />

(Austrian Ministry for Traffic and Innovation Technologies) allowed the operation.<br />

The EC conformity certificate for the ETCS train-borne subsystem is still unavailable.<br />

Integration tests have been partly carried out together with the validation tests <strong>of</strong> the vehicle.<br />

Basis for approval <strong>of</strong> the Ministry is, on one hand, the documentation by the railway<br />

operator and the manufacturers and, on the other hand, the NoBo’s interim assessment<br />

report on the safety <strong>of</strong> the trackside system.<br />

Train-borne Subsystem: Assessment reports by the Independent <strong>Safety</strong> Assessors, one for<br />

the ETCS part and an other for the locomotive specific part (national integration <strong>of</strong> the<br />

ETCS equipment into the locomotive and changes resulting from the use <strong>of</strong> ETCS in the<br />

national system <strong>of</strong> the locomotive) led to approval for tests with certain conditions.<br />

Operational Rules: They are summarized in “DV ETCS level 1”, containing rules for the<br />

driver, especially the rules in case <strong>of</strong> errors <strong>of</strong> parts <strong>of</strong> the ETCS system with fallback to the<br />

national signalling system.<br />

No special periodic maintenance for the trackside subsystem is required.<br />

10.3 The Belgian projects<br />

The L3 and the L4 HSL<br />

There is no intention to establish an overall safety case for train-borne + track-side together<br />

with operations. There will not be such a document but the NSA will give separate<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

119/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


certificates for Rolling Stock after different tests. There is a process underway for Pro<strong>of</strong> <strong>of</strong><br />

<strong>Safety</strong>, but not a safety case. It is considered very complicated to match Phases 9 (system<br />

validation) and 10 (system acceptance) <strong>of</strong> the CENELEC lifecycle with the fulfilment <strong>of</strong> the<br />

safety requirements.<br />

Infrabel uses the GAME-principle (This stands for: Globalement Aussi Moins Equivalent; in<br />

English: globally at least as good as) with regard to the existing line L2. In principle,<br />

everything (Interlocking, Control Room, Detection, Hot Boxes, Points) is the same. The<br />

apportionment <strong>of</strong> risks is considered and the industry has to prove that new hazards, such as<br />

the ones related to the Interlocking-RBC interface do not result in greater overall risks.<br />

The ETCS Level 1 lines<br />

See previous chapter 9.1.7.<br />

No final acceptance has taken place to date.<br />

10.4 The French project: LGV-Est<br />

The following process has been followed regarding the system acceptance:<br />

The systems acceptance is done via a site-laboratory test in which two RBCs, one EVC and<br />

one BTS are used.<br />

Although cross-acceptance is welcomed, specific homologation tests are deemed<br />

unavoidable for the time being.<br />

<strong>Safety</strong> procedures plan<br />

TRACKSIDE ON BOARD<br />

DS<br />

LGV EE<br />

Without C/C<br />

and Signals<br />

DPS<br />

APR<br />

DS<br />

C/C and<br />

Signals<br />

DS<br />

Total mobile<br />

with full<br />

Bi Std<br />

DPS DPS<br />

APR<br />

ERTMS<br />

Overall APR<br />

APR<br />

Bi Standard<br />

APR<br />

TVM<br />

DS<br />

Total mobile<br />

with reduced Bi<br />

Std TVM<br />

Figure 45 – Plan for the PEEE safety acceptance<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

DS<br />

MR<br />

Train POS<br />

DPS<br />

APR<br />

120/161


10.5 The German project: Berlin-HalleLeipzig<br />

After comprehensive testing in the suppliers´ laboratories, integrative and field testing -<br />

mostly started in 2003 - both net operator and railway operator performed various system<br />

test runs.<br />

260 operational test scenarios have been derived from the national functional specification<br />

(LH) and the European specifications in order to demonstrate correct concurrence <strong>of</strong> rolling<br />

stock and network in both regular and fall back mode.<br />

For the purpose <strong>of</strong> evaluation and faults documentation an integrated fault data base was set<br />

up, depicting and classifying all faults and open points from suppliers´ tests, DB testing, as<br />

well as from risk- and hazard analysis and rules frameworks.<br />

<strong>Safety</strong> related topics have been extracted to a hazard log. Suppliers and operators assessed<br />

the findings at periodical reviews, corrected, decided upon and finally closed the faults and<br />

open points before the start <strong>of</strong> the safety probation period. <strong>Safety</strong> cases have also been<br />

finalized and assessed before starting the probation.<br />

Cross exchange tests on other member states lines or by other member states trains on the<br />

BHL line were not performed.<br />

Before starting full service on the line, qualification testing was conducted in several steps,<br />

accompanied by a theoretical verification <strong>of</strong> the safety cases. Test classes were defined and<br />

performed: a) Verification <strong>of</strong> functional requirements on components level and components<br />

interfaces. b) Common testing for principal system interrelations. c) Acceptance <strong>of</strong> balise<br />

assembly, route atlas, RBC projection, and onboard equipment (Distribution <strong>of</strong> roles acc. to<br />

national regulations. For every train route - signalling, locations <strong>of</strong> speed changes - a<br />

separate acceptance procedure was performed). d) System validation <strong>of</strong> overall system<br />

requirements. e) <strong>Safety</strong> probation/safety testing <strong>of</strong> the overall system (track and train) after<br />

successful theoretical safety case verification; performing step-by-step speed enhancements<br />

up to 160 and 200 km/h.<br />

Since the development <strong>of</strong> trackside and train born equipment went nearly hand-in-hand - the<br />

suppliers in the consortium were working in close contacts - both timeframe and formalities<br />

were very similar.<br />

BHL is in revenue service basing on a national allowance for qualification testing<br />

(“Zustimmung zur Erprobung”) according to [DB 21]. The underlying processes <strong>of</strong><br />

development, verification, validation and assessment comply with [DB 1], [DB 2] and [DB<br />

3]. (More detailed information on the approval/acceptance activity <strong>of</strong> the NSA will be<br />

provided in the final version <strong>of</strong> this report).<br />

A final approval on the basis <strong>of</strong> national regulations as well as European requirements [DB<br />

16] could not be issued yet, because no certificates and declarations <strong>of</strong> conformity or EUverification<br />

are available yet. The line is allowed to be run until 2007/12.<br />

Several limitations regarding the fulfilment <strong>of</strong> the functions as specified by UNISIG have<br />

been found for both trackside and onboard equipment, as e.g. being depicted in [DB 143] for<br />

the trackside equipment: Not all types <strong>of</strong> OBU messages, packets within the OBU messages,<br />

modes and levels the will be accepted by the RBC. Non-conformities were found, both<br />

resulting from deficiency in the UNISIG specifications and from “national add-ons”.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

121/161


In 2004 the suppliers´ consortium applied for conformity examinations at the EBC, Notified<br />

Body. To this day not all conformity and EC certificates could be issued; the process is still<br />

pending.<br />

The assessment <strong>of</strong> the safety cases started in the middle <strong>of</strong> 2003. Activity towards<br />

certification started later but was mainly restricted to the RBCs. There have not yet been<br />

issued any conformity or EC certificates and declarations by any Notified Body or operator,<br />

although some examinations have been performed. TÜV InterTraffic GmbH (TÜV<br />

Rheinland Group) performed a "quality assurance, production" investigation according to<br />

Module D for the ETCS2000 RBC at the supplier Alcatel SEL AG on behalf <strong>of</strong> the Notified<br />

Body EBC, ending up in an Independent <strong>Safety</strong> Assessment <strong>Report</strong> <strong>of</strong> the audit.<br />

For onboard equipment EC verification was not applied for at any Notified Body.<br />

In Germany there was uncertainty in the question if a Notified Body is intended to assess<br />

"the safety" on components and assembly level and if this may be part <strong>of</strong> any conformity or<br />

EU assessment. The TSI CCS requires the Notified Body "to ensure the completeness <strong>of</strong> the<br />

safety approval process" ([DB 16], table 6.1, 6.2). However, the German view is that a<br />

module for such an investigation or assessment is not been provided by the TSI. In addition,<br />

the German regulation still prohibits assessment by others than the "Eisenbahn-Bundesamt<br />

EBA" in any question <strong>of</strong> "safety judgement" ("Sicherheitliches Ermessen"). CENELEC<br />

verification, validation and assessment is mostly done by test control centres ("Prüfleitstelle<br />

PLS"), or independent assessors under strict control <strong>of</strong> the EBA.<br />

10.6 The Italian Projects<br />

The Rome-Naples HSL<br />

At the end <strong>of</strong> the assessment activities, carried out during the project lifecycle by the<br />

relevant RFI departments and structures, the signalling system has been accepted. The<br />

activation <strong>of</strong> the line has been carried out in two subsequent steps:<br />

• Approbatory Period;<br />

• Start <strong>of</strong> the revenue service.<br />

The suppliers <strong>of</strong>ficial documents issued for activating the line on the approbatory period<br />

have been three conformity declarations [from [RFI 142] to [RFI 144]), one document for<br />

each <strong>of</strong> the following subsystems:<br />

• Trains Separation Sub-system;<br />

• Interlocking sub-system;<br />

• Trackside CCS sub-system.<br />

The Generic Applications documents issued for the approbatory period line activation are<br />

listed in Annex. Moreover for the specific application <strong>of</strong> the Train Separation System, RFI<br />

have issued some technical reports [from RFI 142 to RFI 144] and the final declaration<br />

“Dichiarazione di Applicabilità Tecnica”.<br />

Following the test activities and the assessment <strong>of</strong> some minor modifications, carried out by<br />

the suppliers during the approbatory period, RFI has issued further documentation.<br />

For putting the line in revenue service, RFI has issued the following documents regarding<br />

the generic ETCS Lev. 2 application [RFI 107 to RFI 116]. These documents have been<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

122/161


ased on the suppliers’ documents [RFI 142 to RFI 144], meanwhile for the specific<br />

applications all the necessary technical reports have been updated.<br />

Moreover to put in service the line, as stated by the RFI directive [RFI 19], the units<br />

“Direzione Movimento”, “Direzione Tecnica” and “Direzione Investimenti e<br />

Manutenzione” have finally assessed the system vs. the maintenance and the service<br />

requirements.<br />

In Italy two track side assembly EC certificates <strong>of</strong> Verification (under module SH2) have<br />

been issued:<br />

• Roma - Napoli: CE Certificate no. 1287/6/SH2/2006/CCS/IT/ZN 39 27 0006 <strong>of</strong> 10<br />

July 2006.<br />

• Torino Novara: CE Certificate no. 1287/6/SH2/2006/CCS/IT/ZN 39 27 0009 <strong>of</strong> 27<br />

November 2006<br />

This two certificates are both included in the CIRCA Database <strong>of</strong> NB Rail.<br />

Torino-Novara HSL/HCL<br />

The suppliers have performed the validation activities regarding the Generic Products,<br />

Generic and Specific Applications. The <strong>Safety</strong> Cases issued by the suppliers at the end <strong>of</strong><br />

the validation activities regarded:<br />

• Trackside Subsystem (Ansaldo);<br />

• Train Separation Subsystem (Ansaldo);<br />

• Interlocking Subsystem (Ansaldo);<br />

• On Board Subsystem (Alstom and Ansaldo);<br />

• Integration <strong>of</strong> On Board equipment by Alstom with the Ansaldo Trackside system.<br />

Besides, the suppliers on field validation activities RFI have performed some on field test<br />

sessions to assess the implementation <strong>of</strong> the signalling system functionalities.<br />

For specific application a technical commission has verified, by means <strong>of</strong> on field test, the<br />

correctness <strong>of</strong> the installation, assembly and system configuration.<br />

A functional assessment <strong>of</strong> overall train separation system (trackside and on board) as<br />

described in the Roma Napoli line document has been carried out<br />

Test management<br />

Similar rules, issued by the General Contractor, as those applied on the Rome – Naples line<br />

have been adopted on the Torino Novara line for the validation and assessment on field<br />

tests. A general contractor on board people (IBT) radio linked with a trackside safety<br />

responsible (RPT) has been foreseen. During the test the pertinent supplier’s personnel have<br />

controlled on site all the interlockings and the RBCs. In the interconnection test the RFI<br />

personnel have ensured the safety <strong>of</strong> the trains on the traditional line suspending the<br />

commercial services during the tests.<br />

After the assessment <strong>of</strong> the products, generic and specific applications on 2005 November<br />

the 28 th RFI proceeded to a preliminary acceptance (see phase 10) <strong>of</strong> the line to start the<br />

probatory period.<br />

During this period RFI assessed the following issues:<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

123/161


• Operating rules<br />

• Rolling stock and infrastructure functionalities and their interfaces<br />

• Railway Operations model;<br />

• Infrastructure management (effectiveness <strong>of</strong> the organisation and diagnostic devices)<br />

• Potentiality <strong>of</strong> the line revenue service.<br />

Furthermore the transport company Trenitalia has carried out the assessment <strong>of</strong>:<br />

• Adequacy <strong>of</strong> service management;<br />

• Effectiveness <strong>of</strong> the training courses for the operative personnel;<br />

• Effectiveness <strong>of</strong> the rolling stock maintenance.<br />

During the probatory period suppliers and RFI personnel have carried out the tests together.<br />

A RFI test manager has been performed the test run on train borne together with IBT.<br />

During the test trains and RBC data have been collected by means <strong>of</strong> specific tools<br />

(“Canapè” for the on-board data and LDR for RBC).<br />

A fine tuning on the products and configurations has been carried out after the tests<br />

execution.<br />

The results <strong>of</strong> the probatory period tests have been reported on monthly reports.<br />

10.7 The Dutch projects<br />

Betuweroute<br />

Steps are not yet taken to have the track certified by a NoBo. Although the Infrastructure<br />

provider ProRail intends to approach the ideal situation as close as possible, it is deemed<br />

impossible at this moment by all parties involved, due to the limited maturity <strong>of</strong> the TSI’s<br />

and lack <strong>of</strong> earlier references.<br />

The same is valid for locomotives. At this moment about 100 locomotives (10 different<br />

types) are in different stages <strong>of</strong> preparation for operation on the Betuweroute. Also in this<br />

case a process is followed that approaches the ERTMS type approval as close as possible.<br />

A starting requirement, however, for a train type is a Declaration <strong>of</strong> Conformity <strong>of</strong> all<br />

ERTMS constituents used, certified by a NoBo and a Declaration <strong>of</strong> Verification for the<br />

Train borne Subsystem, certified by a NoBo as well as a completed CENELEC safety case<br />

for the trainborne Command and Control subsystem, assessed by an ISA, with no blocking<br />

findings.<br />

Also for the trackside certificates <strong>of</strong> conformance for ERTMS constituents are used as well<br />

as certificates for the trackside subassembly, all certified by NoBo’s.<br />

IVW and ProRail will not allow for operation on the ERTMS track with ERTMS trains on<br />

the basis <strong>of</strong> NoBo certificates only. Although the Infrastructure provider ProRail intends to<br />

approach the ideal situation as close as possible, it is deemed impossible at this moment by<br />

all parties involved, due to the limited maturity gained on the TSI and lack <strong>of</strong> earlier<br />

references.<br />

After the NoBo statements and the safety cases for the trackside and train borne subsystem<br />

have been obtained, as well as permission for test exploitation has been granted, a technical<br />

and operational hazard analyses is performed for the integrated trackside and train borne<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

124/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


systems. On this basis a specific test plan is made on the basis <strong>of</strong> a default track train<br />

integration test plan.<br />

This can lead to a “verklaring van geen bezwaar” (a declaration <strong>of</strong> no objection) by IVW.<br />

After a subsequent system qualification test the “inzetcertificaat” (operation certificate) can<br />

be issued. These tests include testing trainborne and trackside equipment for 10.000 km,<br />

absolved by a train <strong>of</strong> a specific type.<br />

The results <strong>of</strong> monitoring are needed to finalise the trackside as well as the train borne safety<br />

cases.<br />

Amsterdam - Utrecht<br />

ProRail is the system integrator, the responsible organization on behalf <strong>of</strong> the Ministry. As<br />

such, it is responsible for the commissioning <strong>of</strong> the system. The ProRail organization is<br />

responsible for all the activities including system acceptance.<br />

HSL ZUID<br />

The system acceptance consists <strong>of</strong> several stages.<br />

The first stage is the approval <strong>of</strong> the evidence that the system is working correctly and<br />

safely. <strong>Approval</strong> is given by the HSL-Zuid project by acceptance <strong>of</strong> the “Compliance<br />

Demonstration <strong>of</strong> the Infrastructure Supplier”.<br />

Important part <strong>of</strong> the Compliance Demonstration is the delivery <strong>of</strong> the “Availability Period<br />

<strong>Safety</strong> Case (APSC)” that has to be approved by an Independent <strong>Safety</strong> Assessor (i.e.<br />

DeltaRail) (ref. “<strong>Report</strong> on the safety assessment <strong>of</strong> the Availability <strong>Safety</strong> Case (rev E) <strong>of</strong><br />

the HSL Assets and HSL Activities”, 23 march 2007).<br />

The supplier has also to deliver interoperability certification for the Trackside Assembly.<br />

To date, the APSC has been approved with remarks; NoBo Conformity Certificates for the<br />

Interoperability Constituents regarding ETCS vers. 2.2.2 are available. Update <strong>Safety</strong> Case<br />

for vers. 2.3.0 and NoBo Certificates for vers. 2.3.0 are still to be determined.<br />

This approval by HSL-Zuid is a pre-condition for the next stage regarding “Test <strong>of</strong> Safe<br />

Usage”.<br />

In this stage the behaviour <strong>of</strong> the system is tested in the context <strong>of</strong> operational procedures<br />

carried out by operating personnel (i.e. signalmen and train driver). In addition endurance<br />

tests and cross exchange tests are executed during the same stage.<br />

On the base <strong>of</strong> the test results, Prorail (i.e. the Inframanager) gives the approval for the<br />

folowing stage.<br />

This regards Trial Exploitation. In this stage the train operating company tests its operations<br />

(e.g. logistics, commercial etc). At the successful completion <strong>of</strong> this stage, the approval has<br />

to be given by the Dutch <strong>Safety</strong> Authority IVW for the next, final stage that regards Normal<br />

Exploitation.<br />

For the HSL-Zuid the process is complicated by the fact that during this acceptance process<br />

the ERTMS system has to be upgraded from 2.2.2 to 2.3.0 via an intermediate step 2.3.0<br />

minus. After each upgrade, regression tests and delta tests have to be carried out.<br />

The picture below shows the relationship between the differet stages.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

125/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


<strong>Process</strong><br />

ERTMS 2.2.2<br />

ERTMS 2.3.0-<br />

ERTMS 2.3.0<br />

Building<br />

Building<br />

Building<br />

Test safe<br />

functioning<br />

Test safe function.<br />

Appr. for<br />

Testing<br />

HSL PR/IVW<br />

IVW<br />

Infra=OK<br />

Test safe<br />

useage<br />

Test safe<br />

useage<br />

Appr. Test<br />

Exploitation<br />

Headway=OK<br />

Appr.<br />

Expoitation<br />

Trial exploitation Normal<br />

exploitation<br />

Building Test safe function. Test safe useage Trial exploitation Normal exploitation<br />

Figure 46 – <strong>Safety</strong> approval proces in HSL ZUID<br />

Test safe function. Test safe useage Trial exploitation Normal exploitation<br />

For approval <strong>of</strong> Normal Exploitation a number <strong>of</strong> requirements have to be fulfilled, the most<br />

important <strong>of</strong> which are:<br />

• Acceptance <strong>of</strong> the Integral <strong>Safety</strong> Case, to be delivered by HSL-Zuid based on the<br />

underlying <strong>Safety</strong> Cases or <strong>Safety</strong> Evidence for Track, Rolling Stock and<br />

Operations;<br />

• NoBo Certificate for Track Assembly and OBU;<br />

• Certificate for Deployment (Inzetcertificaat) <strong>of</strong> Rolling Stock. <strong>Approval</strong> tests on<br />

HSL-Zuid are foreseen by 2007 with Traxx locomotives, Bombardier OBU, 160 km<br />

/hr. <strong>Approval</strong> tests for Thalys (CSEE EVS and Alstom STM) at 300 km/h are<br />

foreseen by 2008.<br />

Next to the above, in order to assure the interface <strong>of</strong> the L4 (connecting Belgium High<br />

Speed Line) and the HSL Zuid to be safe, the Integral <strong>Safety</strong> Cases <strong>of</strong> the two lines have to<br />

be aligned. The related process is under construction. To date, this report has been drafted.<br />

As far as rules for operational use are concerned, a number <strong>of</strong> documents were delivered by<br />

the supplier <strong>of</strong> the trackside systems (Infraspeed) to assure proper operation:<br />

• Signalling Rules for the Customer (SIGNALING SUBSYSTEM RULES FOR THE<br />

CUSTOMERS IDE (SIG=S$T&EEC # 000019)<br />

• <strong>Safety</strong> Related application Conditions (SAFETY RELATED APPLICATION<br />

CONDITIONS FOR OP<strong>ERA</strong>TION AND MAINTENANCE IDE<br />

(SIG=S$TEX&EQB # 000015)<br />

• Operational Restrictions (SIG TEMPORARY RULES FOR OP<strong>ERA</strong>TION IDE<br />

(SIG=S$T&EEC # 000027<br />

• Temporary Rules (in the phase that additions still have to be made to the deliveries)<br />

(SIG TEMPORARY RULES FOR OP<strong>ERA</strong>TION IDE(SIG=S$T&EEC # 000027)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

126/161<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007


These rules provide instructions how to use the system, but do not affect any rule in the<br />

referenced TSI’s.<br />

The supplier also is responsible for maintaining the superstructure and has also devised<br />

internal rules for maintenance. Under the performance contract this is the responsibility for<br />

the supplier.<br />

As far as the interoperability certification is concerned, the NoBo for the trackside assembly<br />

(integrated in the traffic system) was contracted in the acceptance phase.<br />

The certification <strong>of</strong> the on-board assemblies is determined by the rolling stock suppliers.<br />

10.8 The Spanish projects<br />

Complementary tests<br />

The acceptance process has already been described. What can be added here is the concept<br />

<strong>of</strong> “Complementary tests”<br />

Besides the internal tests performed by the manufacturer, and the agreed acceptance tests,<br />

that were carried out in the Madrid-Lleida line with ERTMS track-side and on-board<br />

equipment delivered by the same manufacturer, the Ministry <strong>of</strong> Transport, together with<br />

Adif and Renfe, have defined the so-called “Complementary tests”, additional tests to those<br />

already carried out and documented in the verification and validation dossier.<br />

The tests have been specially established for the new Madrid-Lleida line to check the<br />

functionality <strong>of</strong> the new trainborne equipment. They cover in particular the following topics:<br />

1. Speed and braking curves supervision<br />

2. Transitions between ERTMS application levels<br />

3. Mode transitions<br />

4. Management <strong>of</strong> Temporary Speed Restrictions<br />

5. Failures in balise detection<br />

6. Management <strong>of</strong> timing in Movement Authorizations<br />

7. Odometry<br />

8. Train Interface<br />

9. ATO and pre-fixed speed<br />

10. DMI<br />

11. National functions<br />

12. Signal balise group reading in PT mode<br />

This is an additional requirement from the Ministry <strong>of</strong> Transportfor authorising the<br />

commissioning <strong>of</strong> rolling stock.<br />

The phases 5 to 10 are summarised in the figure below.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

127/161


Delivery record/Receipt <strong>of</strong> Works<br />

Construction Manager Coordination Infrastructure Maintenance Directorate<br />

Investments Stations/Terminals<br />

Dossier on safety (<strong>Safety</strong> case, CENELEC standards)<br />

Construction Manager <strong>Safety</strong> Directorate Functional Projects, Verification and<br />

Placing in Service Directorate<br />

Instructions, Notices and News<br />

Installations Directorate<br />

Planning and Deveplopment <strong>of</strong> Networks Directorate Functional Projects, Verification<br />

Excutive Traffic Directorate and Placing in Service Directorate<br />

Executive Infrastructure Maintenance Directorate<br />

Maximum Speed Table<br />

Operative Assets Excutive Traffic Directorate Functional Projects, Verification<br />

Management Directorate and Placing in Service Directorate<br />

Infrastructures Verification and Recording<br />

(TSI´s )<br />

Functional Projects, Verification Ministry <strong>of</strong> Public Works<br />

and Placing in Service Directorate and the Distribution List<br />

Reliability Testing / Subsystems Interfaces/ <strong>Report</strong> on the placing in service<br />

Functional Projects, Verification Ministry <strong>of</strong> Public Works<br />

and Placing in Service Directorate and the Distribution List<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

128/161


11 Phases 11-12 Operation, maintenance and<br />

monitoring<br />

This section is intended to provide the following information about:<br />

• The process followed for collecting statistical data regarding functional and RAMS<br />

performances during the revenue service <strong>of</strong> the trackside and train-borne subsystems<br />

by the Infrastructure owner, for their subsequent evaluation and for planning<br />

the consequent maintenance actions.<br />

• The authorisation process followed and the bodies involved in the postponed<br />

solution <strong>of</strong> minor non-conformities evidenced during the previous phases without<br />

endangering safety and interoperability <strong>of</strong> the sub-systems.<br />

11.1 The Austria-Italy project: Brenner Basis Tunnel<br />

This section is not applicable to the present stage <strong>of</strong> the Project.<br />

11.2 The Austrian project: Vienna – Nickelsdorf<br />

No statement is available up to now as the system is not in operation.<br />

11.3 The Belgian projects<br />

The L3 and the L4 HSL<br />

In Belgium, the national operational rules are conceived for TBL 2. For ERTMS these rules<br />

had to be adapted. There are specific Belgian Rules as “grote beweging en kleine beweging”<br />

meaning large movement and small movement that do not exist in ERTMS. So the ERTMS<br />

term had to comply with one <strong>of</strong> this types <strong>of</strong> movement. As far as L3, L4 and other parts <strong>of</strong><br />

the network are not uniform, this might be an issue in future.<br />

Infrabel considers European rules to be insufficiently present. Therefore they considered<br />

their own adaptation <strong>of</strong> national rules necessary. It is self-understood that these rules won´t<br />

be interoperable.<br />

There was a problem to connect with the HSL/Zuid concerning Hot Box Axle Detection<br />

(HBAD). This is not required in the Netherlands. The Belgian party involved would not<br />

allow a train, coming from Holland on their L4 line without detecting possible hot axes.<br />

As a solution, a HBAD was placed on the Dutch side <strong>of</strong> the border.<br />

There has been joint work on a safety case “border” . <strong>Safety</strong> requirements and operational<br />

rules, only valid for this transition, were agreed upon jointly<br />

Belgian ETCS level 1 lines<br />

Not applicable, as the system did not pass phase 9 to the present date.<br />

No final acceptance has taken place to date.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

129/161


11.4 The French project: LGV-Est<br />

This (optional) information is not presently available.<br />

11.5 The German project: Berlin-HalleLeipzig<br />

Conforming [DB 24] the Operator is committed to gather any incidents and accidents at a<br />

database. The DB database served as a vital source <strong>of</strong> information for the risk and hazard<br />

analyses and the migration.<br />

11.6 The Italian Projects<br />

The Rome-Naples HSL<br />

The ERTMS trackside and on board subsystem have been monitored during the approbatory<br />

period. The results have been collected in four monthly reports issued by RFI [0] in<br />

accordance with the procedure [RFI 103]. The evaluations <strong>of</strong> the performances <strong>of</strong> the<br />

railway system are collected in such reports. For example, during the first two months <strong>of</strong> the<br />

approbatory period, 209 train runs between Rome and Naples or vice versa plus 109 not<br />

incomplete runs have been carried out with the following punctuality figures:<br />

• 21% <strong>of</strong> the trains have arrived on schedule;<br />

• 29% <strong>of</strong> the trains have suffered a delay up to 15 minutes<br />

• 50% <strong>of</strong> the trains have suffered a delay longer than 15 minutes.<br />

The summary <strong>of</strong> the approbatory period troubleshooting is in the [RFI 106].<br />

Torino-Novara HSL<br />

This (optional) information is not presently available.<br />

11.7 The Dutch projects<br />

Betuweroute<br />

This (optional) information is not presently available.<br />

Amsterdam - Utrecht<br />

On behalf <strong>of</strong> the Ministry, ProRail has the tasks <strong>of</strong> Operation, Maintenance and Monitoring<br />

<strong>of</strong> the line.<br />

HSL ZUID<br />

This (optional) information is not presently available.<br />

11.8 The Spanish projects<br />

The only reported malfunction has been the one related with the tele-powering <strong>of</strong> the<br />

balises.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

130/161


The problem has been temporary solved installing a second balise holding identical<br />

information, mounted in an adjacent sleeper. At the present time the origin <strong>of</strong> this<br />

malfunction is still unknown.<br />

The laboratory tests have always been satisfactory, and line tests performed during several<br />

months with balises <strong>of</strong> several manufacturers have proven that every balise, including the<br />

new ones developed by the previous manufacturer, works satisfactorily. After the test has<br />

been finished it is very probably that ADIF decides to remove the duplicated balises.<br />

In any case, this is not considered a safety, nor an interoperability problem, but an<br />

operational inconvenience. If a train fails to read a balise, the only consequence is an<br />

unwanted stop.<br />

The operation under ERTMS is very recent, there are not available statistics. There are only<br />

punctual observations that do not allow the deduction <strong>of</strong> any conclusion about ERTMS<br />

functional and RAMS performances The results <strong>of</strong> the operation <strong>of</strong> the Madrid-Lleida<br />

section since 19/06/2006 to 18/12/2006, and <strong>of</strong> the Madrid – Tarragona sectiom since<br />

10/12/06 to 08/03707 can be summarized as follows:<br />

• Number <strong>of</strong> train runs: 4.445<br />

• Number <strong>of</strong> kilometres: 1.767.553<br />

• Number <strong>of</strong> incidences (dealay greater than 5 min):26 (16 <strong>of</strong> which are due to<br />

odometry malfunction under ice and snow environment)<br />

• Punctuality index: 99,5 %<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

131/161


12 Phase 13 – Modification and retr<strong>of</strong>it<br />

This section is intended to provide the following information about:<br />

• The process followed for implementing change request procedures or for the system<br />

updating to the most recent ERTMS baseline, with due consideration <strong>of</strong> RAMS<br />

implications for such modifications and retr<strong>of</strong>it.<br />

• The authorisation process followed and the bodies involved in the implementation,<br />

validation and acceptance <strong>of</strong> modifications, without endangering safety and<br />

interoperability <strong>of</strong> the sub-systems.<br />

12.1 Austria-Italy project: Brenner Basis Tunnel project<br />

This section is not applicable to the present stage <strong>of</strong> the Project.<br />

12.2 Vienna-Nickelsdorf<br />

It seems to be envisaged by the Railway Operator to upgrade ETCS level 1 to version 2.3.0,<br />

but this is not <strong>of</strong>ficially fixed to date.<br />

Because <strong>of</strong> the use <strong>of</strong> Euroloop equipment (both track-side and train-borne equipment)<br />

produced and certified according to the old Euroloop Specifications (i.e. before the up-link<br />

signal frequency was changed), it will become necessary to update the frequency relevant<br />

components, according to the presently available Specifications, during a due time.<br />

Also one type <strong>of</strong> certified LEU doesn´t conform to the present Specifications, due to<br />

technical changes in the Specifications used for the certification. It has not been defined yet,<br />

to date, what will be done as the change <strong>of</strong> specification has in course <strong>of</strong> this project no<br />

influence on the function, the safety, the reliability <strong>of</strong> the component and most important<br />

also no influence on the interoperability <strong>of</strong> the ETCS railway system.<br />

12.3 The Belgian projects<br />

Not applicable, as the system did not pass phase 9 to the present date.<br />

12.4 The French project: LGV-Est<br />

This (optional) information is not presently available.<br />

12.5 The German project: Berlin-Halle-Leipzig<br />

This (optional) information is not presently available.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

132/161


12.6 The Italian Projects<br />

The Rome-Naples HSL<br />

Starting from the beginning <strong>of</strong> approbatory period, the following procedure has been defined<br />

to install new Sw versions or Hw modifications to the sub-systems or to the components:<br />

• The modification has to be agreed between RFI and the involved suppliers;<br />

• A revision plan has to be issued and agreed upon;<br />

• The supplier has to validate the modification, according to his Verification and<br />

Validation Plan (phase 13), and issue the related set <strong>of</strong> documents;<br />

• RFI has to perform the documental assessment;<br />

• Based on the extension <strong>of</strong> the modification, RFI and the suppliers have to carry out a<br />

on field validation and acceptance test session, prior to put in service the new<br />

version. The test sessions are carried out during the night when the commercial<br />

service is suspended.<br />

• A positive assessment report has to be issued and accepted by RFI.<br />

Torino-Novara HSL<br />

There are still some tests in progress regarding the evaluation <strong>of</strong> the Quality <strong>of</strong> Service <strong>of</strong><br />

the GSM-R communications, as a measure to quantify the level <strong>of</strong> availability <strong>of</strong> the<br />

complete ERTMS/ETCS system.<br />

12.7 The Dutch projects<br />

Betuweroute<br />

This (optional) information is not presently available.<br />

Utrecht-Amsterdam HSL<br />

This section is not applicable to the present stage <strong>of</strong> the Project.<br />

HSL ZUID<br />

This (optional) information is not presently available.<br />

12.8 The Spanish projects<br />

This (optional) information is not presently available.<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

133/161


13 Annex<br />

13.1 References for the Austrian Projects<br />

OEBB 1 DV V2 Signalvorschrift (signalling rules)<br />

OEBB 2 DV V3 Betriebsvorschrift (operation rules)<br />

OEBB 3 DV ETCS level 1 European Train Control System - ETCS Level 1<br />

OEBB 4 DV S80<br />

OEBB 5 DB 823 Beschreibung und Bedienung (description and operation manual)<br />

13.2 References for the German projects<br />

European Directives, Standards and Specifications<br />

EC-Directives<br />

DB 1. EC-directive 96/48/EC<br />

DB 2. EC-directive 2001/16/EC<br />

DB 3. EC-directive 1999/36/EC<br />

EC-Standards<br />

DB 4. EN 50126, Railway applications – The specification and demonstration <strong>of</strong><br />

dependability, reliability, availability, maintainability and safety (RAMS), 2000-03<br />

DB 5. EN 50128, Railway Applications – Communications, signalling and processing systems<br />

– S<strong>of</strong>tware for railway control and protection systems, 2001-11<br />

DB 6. EN 50129, Railway Applications: <strong>Safety</strong> related electronic systems for signalling, Issue:<br />

2000-11<br />

DB 7. EN 50159-1 Railway Applications – Communication, signalling and processing systems<br />

– Part 2: <strong>Safety</strong> related communication in closed transmission systems, 2001<br />

DB 8. EN 50159-2 Railway Applications – Communication, signalling and processing systems<br />

– Part 2: <strong>Safety</strong> related communication in open transmission systems, 2001-12<br />

DB 9. EN 45004<br />

DB 10. EN 50170-2<br />

DB 11. EN 29000<br />

DB 12. EN 29001<br />

DB 13. EN 50121-4<br />

DB 14. EN 50125-1<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

134/161


DB 15. EN 50155<br />

EC-Specifications<br />

DB 16. TSI Command Control Signalling, 2002-05-30<br />

DB 17. FFFIS STM<br />

DB 18. UNISIG Specifications V2.2.2 Class 1, 2002-05-30<br />

Subsets 026, 037, 039, 041, 055, 076, 091, 092, and further<br />

National Rules & Regulations<br />

DB 19. Eisenbahn-Interoperabilitätsverordnung (EIV), 1999-05-20<br />

DB 20. Konventioneller Verkehr – Eisenbahn Interoperabilitätsverordnung (KonVEIV)<br />

DB 21. Verwaltungsvorschrift für die Bauaufsicht über Signal-, Telekommunikation- und<br />

Elektrotechnische Anlagen BAU-STE; 2003-01-01<br />

DB 22. Eisenbahn-Bau- und Betriebsordnung (EBO); 1967-05-08 ff.<br />

DB 23. Allgemeines Eisenbahngesetz (AEG); 1993-12-27 ff.<br />

DB 24. Technische Grundsätze für die Typzulassung von Sicherungsanlagen (Mü 8004)<br />

DBAG Regulations<br />

DB 25. Konzernrichtlinie 408 (former “Fahrdienstvorschrift”)<br />

DB 26. further rules and regulations<br />

DBAG Pilot Documentation<br />

DB 27. Rahmenlastenheft der DB AG; 2.5.1; 2004-07-15<br />

DB 28. Teillastenhefte Teile 1 bis 8, inkl. Anhängen<br />

DB 29. Erprobungsplan ETCS Release 1.4/1.3.6 und Doppelausrüstung ETCS/LZB auf BHL<br />

DB 30. Inbetriebnahmekonzept für Ludwigfelde – Teltow und Lückenschlüsse auf der ETCS<br />

Pilotstrecke Berlin – Halle/Leipzig<br />

DB 31. Konzept für die Sicherheitserprobung (ZE) für die ETCS Teilsysteme Fahrzeug und<br />

Strecke<br />

Mapping” Risk <strong>Analysis</strong> – Hazard <strong>Analysis</strong><br />

DB 32. Systemdefinition<br />

DB 33. Beschreibung betrieblicher Situationen zu den Gefährdungen<br />

DB 34. Betriebliche Ursachenanalyse – Teil 1<br />

DB 35. Betriebliche Ursachenanalyse – Teil 2, mit Fehlerbäumen<br />

DB 36. Quantifizierung, Betriebs- und Infrastrukturparameter, mit Anlagen 1 und 2<br />

DB 37. Zusammenfassung<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

135/161


DB 38. Vorgehensweise<br />

DB 39. Gutachten zum Mapping RA/GA im Projekt ETCS2000 (not DB AG)<br />

Suppliers´ (“Consortium”) Documentation (RBC Docu as an example)<br />

Concepts and Plans<br />

DB 40. <strong>Safety</strong> Case Concept RBC<br />

DB 41. <strong>Safety</strong> Concept ETCS 2000 Crypto Module<br />

DB 42. Sicherheitskonzept des Kryptomoduls von ETCS2000<br />

DB 43. Sicherheitskonzept Core auf TAS Plattform, <strong>Safety</strong><br />

DB 44. Sicherheitskonzept zur Eingabe von Daten über den RBC Bedienplatz<br />

DB 45. Sicherheitsnachweiskonzept RBC Release 1<br />

DB 46. Verification Plan <strong>of</strong> ETCS2000 RBC<br />

DB 47. Validation Plan <strong>of</strong> ETCS 2000 RBC<br />

DB 48. RBC Validation Plan<br />

DB 49. Quality Assurance Plan, Project RBC<br />

DB 50. Sicherheitsplan ETCS 2000 RBC<br />

DB 51. RBC <strong>Safety</strong> Plan<br />

DB 52. RAM Plan (RAMP) System Radio Block Centre (RBC)<br />

DB 53. Datengenerierungsplan Streckendaten ETCS RBC<br />

DB 54. Datentestplan der Streckendaten ETCS RBC<br />

DB 55. Conformity Plan <strong>of</strong> ETCS2000 RBC<br />

Specifications and Descriptions<br />

DB 56. Systemanforderungsspezifikation ETCS 2000<br />

DB 57. <strong>Safety</strong> Requirements Specification <strong>of</strong> RBC<br />

DB 58. Descriptions <strong>of</strong> RBC equipment (core system, PC´s, monitors, switches, ...)<br />

DB 59. Anforderungen an die Planung der ETCS-Zentrale<br />

DB 60. RBC Operator Panel Requirement Specification<br />

DB 61. S<strong>of</strong>tware Architecture RBC Core<br />

DB 62. Requirement Specification and SW Architecture PCU, Protocol Converter SAHARA -<br />

RACOON<br />

DB 63. Interface Specification RBC-IL / Double Equipment /Application Level<br />

DB 64. Interface Specification RBC-IL / Presentation Layer<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

136/161


DB 65. Architecture Design Document Hardware<br />

DB 66. Insulation Coordination Hardware RBC<br />

DB 67. Hardware Beschreibung RCS für RBC<br />

DB 68. System Test Specification for RBC Transitions<br />

Manuals<br />

DB 69. Handbuch Bedienplatz ETCS-Zentrale<br />

DB 70. Handbuch Diagnoseterminal ETCS Zentrale<br />

DB 71. Meldungshandbuch ETCS Zentrale Release 1<br />

DB 72. Wartungs- und Instandhaltungshandbuch ETCS-Zentrale<br />

Conditions and Obligations<br />

DB 73. Betreiberhinweise für das ETCS2000 RBC Release x<br />

DB 74. <strong>Safety</strong> Application Conditions<br />

DB 75. Security Gateway: Sicherheitsbezogene Anwendungsvorschriften<br />

DB 76. Prüfvorschrift FZB Schrank Streckenzentrale<br />

DB 77. Projektierungsregeln der Streckendaten Release x<br />

Analyses<br />

DB 78. Systemgefährdungsanalyse ETCS2000 – Fehlerbaumanalyse<br />

DB 79. RAM Analyse RBC<br />

DB 80. Implication <strong>Analysis</strong> (assessment <strong>of</strong> changes from one RBC release to the next)<br />

<strong>Safety</strong> Cases<br />

DB 81. Sicherheitsnachweis Teil 1: Definition dess Systems<br />

DB 82. Sicherheitsnachweis Teil 2: Qualitätsmanagementbericht für ETCS2000 RBC Release<br />

x<br />

DB 83. Sicherheitsnachweis Teil 3: Sicherheitsmanagementbericht (SMR)<br />

DB 84. Sicherheitsnachweis Teil 4: Technischer Sicherheitsbericht (Technical <strong>Safety</strong> <strong>Report</strong>)<br />

DB 85. Sicherheitsnachweis Teil 4: Anhang A, Fehlerbaumanalyse (Fault Tree <strong>Analysis</strong>)<br />

DB 86. Sicherheitsnachweis Teil 4: Anhang B, FMEA<br />

DB 87. Sicherheitsnachweis Teil 4: Anhang B, FMEA Interface IL<br />

DB 88. Sicherheitsnachweis Teil 4: Anhang B, FMEA PCU<br />

DB 89. Verfahrenssicherheitsnachweis für den RBC-Bedienplatz<br />

DB 90. Ergänzende Betrachtung zum Bedienplatz Rel. 1: Einsatz im <strong>of</strong>fenen Netz<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

137/161


DB 91. Verfahrenssicherheitsnachweis für die sichere Kommunikation zwischen RBC –<br />

Stellwerk (Alcatel) unter Nutzung des CIRNet Protokolls<br />

DB 92. Technischer Sicherheitsbericht Verfahren Kommunikation OBU-RBC über EuroRadio<br />

ETCS2000<br />

DB 93. Verfahrenssicherheitsnachweis für die sichere Kommunikation in geschlossenen<br />

Netzen unter Nutzung des RACOON Stacks<br />

DB 94. Sicherheitsnachweis Teil 5: Beziehung zu anderen Sicherheitsnachweisen<br />

DB 95. Sicherheitsnachweis TFT-Monitor für den RBC Bedienplatz<br />

Verification & Validation<br />

DB 96. Journal Sicherheitslogbuch Projekt RBC<br />

DB 97. Gefährdungslogbuch RBC<br />

DB 98. Validation <strong>Report</strong> <strong>of</strong> ETCS2000 RBC<br />

DB 99. Hardware Validation <strong>Report</strong> <strong>of</strong> RBC Release x<br />

DB 100. Validation Test Database RBC <strong>Report</strong>s and Pro<strong>of</strong>s<br />

DB 101. Release Notes<br />

DB 102. Version Descriptions<br />

DB 103. Qualification Test <strong>Report</strong> Hardware RBC<br />

Assessment<br />

DB 104. Sicherheitsgutachten Alcatel SEL RBC Rel. 1<br />

DB 105. Nachweis der Rückwirkungsfreiheit im Testbetrieb auf der ETCS Teststrecke für die<br />

Zentralen Bitterfeld, Wittenberg und Jüterbog; Schrb. v. TS/AT<br />

DB 106. Nachweis der Rückwirkungsfreiheit im Testbetrieb auf der ETCS Teststrecke für die<br />

Zentrale Ludwigsfelde; Sicherheitsgutachten RBC Rel. 1<br />

DB 107. Feldtest-Bericht ETCS L2 Bitterfeld, RBC Wittenberg<br />

<strong>Approval</strong> & Acceptance<br />

DB 108. Zustimmung zur Betriebserprobung des Alcatel „Radio Block Centre“ (RBC) auf der<br />

Strecke Jüterbog – Halle/Leipzig, 2003-12-12<br />

DB 109. Zustimmung zur Betriebserprobung der Fahrzeugeinrichtung ETCS-OBU auf dem<br />

Testcar (BR 707) und DESIRO (BR 642) auf der Strecke Jüterbog – Halle/Leipzig,<br />

2003-12-12<br />

DB 110. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung für das SW<br />

Release 1.4 in den RBC-Zentralen Jüterbog, Wittenberg und Bitterfeld der ETCS<br />

Pilotstrecke J-H/L, 2005-05-02<br />

DB 111. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level<br />

2 (Strecke / RBC) auf der Pilotstrecke Jüterbog – Halle/Leipzig, 2005-09-14<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

138/161


DB 112. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level<br />

2 (Fahrzeug / OBU) auf der Pilotstrecke Jüterbog – Halle/Leipzig, 2005-09-14<br />

DB 113. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Strecke / RBC) auf der<br />

Pilotstrecke Jüterbog – Halle/Leipzig, 2005-11-21<br />

DB 114. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Fahrzeug / OBU) auf<br />

der Pilotstrecke Jüterbog – Halle/Leipzig, 2005-11-21<br />

DB 115. Zustimmung zur erweiterten Sicherheitserprobung mit Sicherheitsverantwortung von<br />

ETCS Level 2<br />

(Fahrzeug / OBU) zur Durchführung von Hochgeschwindigkeitsfahrten (200 km/h) auf<br />

der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Bitterfeld und<br />

Wittenberg; Fortschreibung des Bescheides vom 14.09.2005, 2006-01-31<br />

DB 116. Zustimmung zur erweiterten Sicherheitserprobung mit Sicherheitsverantwortung von<br />

ETCS Level 2<br />

(Strecke / RBC) zur Durchführung von Hochgeschwindigkeitsfahrten (200 km/h) auf<br />

der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Bitterfeld und<br />

Wittenberg;<br />

Fortschreibung des Bescheides vom 14.09.2005, 2006-01-31<br />

DB 117. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS<br />

Level 2<br />

(Strecke / RBC, Version 1.4) auf der Pilotstrecke Ludwigsfelde – Halle/Leipzig im<br />

Bereich der RBC Bitterfeld, Wittenberg und Jüterbog, 2006-02-14<br />

DB 118. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS Level<br />

2<br />

(Fahrzeugeinrichtung OBU BR 101) auf der Pilotstrecke Ludwigsfelde – Halle/Leipzig<br />

in den RBC Bereichen Bitterfeld, Wittenberg und Jüterbog, 2006-02-14<br />

DB 119. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS<br />

Level 2 (Fahrzeugeinrichtung OBU BR 101) auf der Pilotstrecke Ludwigsfelde –<br />

Halle/Leipzig im Bereich des RBC Jüterbog, 2006-03-01<br />

DB 120. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS<br />

Level 2 (Strecke / RBC, Version 1.4) auf der Pilotstrecke Ludwigsfelde – Halle/Leipzig<br />

im Bereich des RBC Jüterbog, 2006-03-01<br />

DB 121. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS<br />

Level 2 (Fahrzeugeinrichtung OBU BR 101) in den RBC-Zentralen Wittenberg und<br />

Bitterfeld der ETCS Pilotstrecke J-H/L, 2006-10-04<br />

DB 122. Zustimmung zur Sicherheitserprobung für das SW Release 1.4 in den RBC-Zentralen<br />

Wittenberg und Bitterfeld der ETCS Pilotstrecke J-H/L, 2006-04-10<br />

DB 123. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von ETCS<br />

Level 2 (Fahrzeugeinrichtung OBU BR 101) in den RBC-Zentralen Jüterbog,<br />

Wittenberg und Bitterfeld der ETCS Pilotstrecke J-H/L, 2006-05-02<br />

DB 124. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2<br />

(Fahrzeugeinrichtung OBU BR 101) im Bereich des RBC Jüterbog auf der ETCS<br />

Pilotstrecke J-H/L, 2006-05-02<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

139/161


DB 125. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung für das SW<br />

Release 1.4 im Bereich des RBC Jüterbog auf der ETCS Pilotstrecke J-H/L, 2006-05-<br />

02<br />

DB 126. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung für das SW<br />

Release 1.4 im Bereich der RBC Wittenberg und Bitterfeld auf der ETCS Pilotstrecke<br />

J-H/L, 2006-05-05<br />

DB 127. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level 2<br />

(Fahrzeugeinrichtung OBU BR 101) im Bereich der RBC Wittenberg und Bitterfeld auf<br />

der ETCS Pilotstrecke J-H/L, 2006-05-05<br />

DB 128. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 Streckenzentrale /<br />

RBC, Version 1.4, in Kombination mit der Fahrzeugeinrichtung / OBU, Version 1.3.5.1,<br />

auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg<br />

und Bitterfeld, 2006-07-03<br />

DB 129. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Fahrzeug / OBU,<br />

Version 1.3.5.1) in Kombination mit der Streckenzentrale / RBC, Version 1.4 auf der<br />

Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und<br />

Bitterfeld, 2006-07-03<br />

DB 130. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level<br />

2 (Streckenzentrale /RBC, Version 1.4, in Kombination mit der Fahrzeugeinrichtung /<br />

OBU, Version 1.3.6.2) auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der<br />

RBC Jüterbog, Wittenberg und Bitterfeld, 2006-07-26<br />

DB 131. Zustimmung zur Sicherheitserprobung mit Sicherheitsverantwortung von ETCS Level<br />

2 (Fahrzeug / OBU, Version 1.3.6.2 in Kombination mit der Streckenzentrale /RBC,<br />

Version 1.4) auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC<br />

Jüterbog, Wittenberg und Bitterfeld, 2006-07-26<br />

DB 132. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 Streckenzentrale /<br />

RBC, Version 1.4, in Kombination mit der Fahrzeugeinrichtung / OBU, Version 1.3.6.2,<br />

auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg<br />

und Bitterfeld, 2006-10-10<br />

DB 133. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Fahrzeug / OBU,<br />

Verision 1.3.6.2) in Kombination mit der Streckenzentrale / RBC, Version 1.4, auf der<br />

Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und<br />

Bitterfeld, 2006-10-10<br />

DB 134. Zustimmung zum Testbetrieb für das SW Release 1.4.1.6 in den RBC-Zentralen<br />

Bitterfeld, Wittenberg, Jüterbog sowie 1.4.1.4 in der RBC-Zentrale Ludwigsfelde der<br />

ETCS Pilotstrecke B-H/L, 2006-10-24<br />

DB 135. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 Streckenzentrale /<br />

RBC, Version 1.4, in Kombination mit der Fahrzeugeinrichtung / OBU, Version 1.3.6.2,<br />

auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg<br />

und Bitterfeld, 2006-11-17<br />

DB 136. Zustimmung zur Zuverlässigkeitserprobung von ETCS Level 2 (Fahrzeug / OBU,<br />

Version 1.3.6.2) in Kombination mit der Streckenzentrale / RBC, Version 1.4 auf der<br />

Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC Jüterbog, Wittenberg und<br />

Bitterfeld, 2006-11-17<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

140/161


DB 137. Zustimmung zum Testbetrieb für das SW Release 1.4.1.6 in den RBC-Zentralen<br />

Bitterfeld, Wittenberg, Jüterbog und Ludwigsfelde der ETCS Pilotstrecke B-H/L, 2006-<br />

11-21<br />

DB 138. Zustimmung zur Sicherheitserprobung ohne Sicherheitsverantwortung von Level 2<br />

(Fahrzeug / OBU, Version 1.3.6.2) in Kombination mit der Streckenzentrale / RBC,<br />

Version 1.4.1.6, auf der Pilotstrecke Jüterbog – Halle/Leipzig im Bereich der RBC<br />

Ludwigsfelde, Jüterbog, Wittenberg und Bitterfeld, 2006-12-21<br />

DB 139. Zustimmung zur Sicherheitserprobung für das SW Release 1.4.1.6 auf der ETCS<br />

pilotstrecke Berlin – Halle/Leipzig im Bereich der RBC-Zentralen Ludwigsfelde,<br />

Jüterbog, Wittenberg und Bitterfeld, 2006-12-21<br />

Warranty <strong>of</strong> documents (“Zusicherung”)<br />

DB 140. Zusicherung für Mapping Dokumente, 2005-11-21<br />

DB 141. Zusicherung für das Rahmenlastenheft der DB AG, 2.5.1 v. 2004-07-15<br />

DB 142. Zusicherung der Risikoanalyse<br />

Conformity<br />

DB 143. Conformity <strong>Report</strong> <strong>of</strong> ETCS2000 RBC Release 1.3<br />

DB 144. Unisig Conformity Matrix (for RBC)<br />

DB 145. TÜV Intertraffic GmbH: Bericht zum Modul D Audit ETCS2000 RBC<br />

13.3 References for the Italian projects<br />

Laws and Norms<br />

RFI 1.<br />

RFI 2.<br />

RFI 3.<br />

RFI 4.<br />

RFI 5.<br />

Direttiva 96/48/CE del Consiglio del 23 luglio 1996 relativa all'Interoperabilità del<br />

Sistema Ferroviario Transeuropeo ad Alta Velocità<br />

Direttiva 2001/16/CE del Parlamento Europeo e del Consiglio del 19/03/2001 relativa<br />

all’interoperabilità del Sistema Ferroviario Transeuropeo Convenzionale<br />

Decisione 2002/731/CE della Commissione Europea del 30 maggio 2002 relativa alle<br />

“Specifiche Tecniche di Interoperabilità per il sottosistema controllo-comando e<br />

segnalamento del sistema ferroviario transeuropeo ad alta velocità di cui all’articolo 6,<br />

paragrafo 1, della direttiva 96/48/CE”;<br />

Decreto Legislativo n. 299 del 24 Maggio 2001 “Attuazione della direttiva 96/48/CE<br />

relativa all’interoperabilità del Sistema Ferroviario Transeuropeo ad Alta Velocità<br />

Decreto Legislativo n. 268 del 30 Settembre 2004 “Attuazione della direttiva<br />

2001/16/CE in materia di interoperabilità del Sistema Ferroviario Transeuropeo<br />

Convenzionale<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

141/161


European Norms and Standards<br />

RFI 6.<br />

RFI 7.<br />

RFI 8.<br />

RFI 9.<br />

RFI 10.<br />

RFI 11.<br />

EN 50126, Railway applications – The specification and demonstration <strong>of</strong> dependability,<br />

reliability, availability, maintainability and safety (RAMS), Issue: September 1999<br />

EN 50129, Railway Applications: <strong>Safety</strong> related electronic systems for signalling, Issue:<br />

February 2003<br />

EN 50128, Railway Applications – Communications, signalling and processing systems<br />

– S<strong>of</strong>tware for railway control and protection systems, Issue: March 2001<br />

EN 50159-1 Railway Applications – Communication, signalling and processing systems<br />

– Part 2: <strong>Safety</strong> related communication in closed transmission systems, Issue: March<br />

2001<br />

EN 50159-2 Railway Applications – Communication, signalling and processing systems<br />

– Part 2: <strong>Safety</strong> related communication in open transmission systems, Issue: March 2001<br />

Subset 026 - issue 2.2.2 UNISIG ERTMS/ETCS - Class 1 – System Requirements<br />

Specification<br />

RFI 12. Subset 040 rev 2.0.0 Dimensioning and Engineering rules<br />

RFI 13. Subset 041 rev 2.0.0 Performance Requirements for Interoperability<br />

RFI 14.<br />

Subset 091 rev 2.2.2 <strong>Safety</strong> Requirements for the Technical Interoperability <strong>of</strong> ETCS in<br />

Levels 1 & 2<br />

RFI 15. EIRENE System Requirement Specification ver. 14<br />

RFI 16. A11 P6001.11 Morane Radio Trasmission FFFIS for Euroradio<br />

RFI 17. ERTMS/ETCS Class 1 FIS for the RBC/RBC Handover”, issue 2.0.0<br />

RFI Norms and Standards<br />

EC Directives<br />

RFI 18. Disposizione 16/2003 del 12/08/2003 Norme per il progetto di base, le verifiche, le<br />

consegne e l’attivazione all’esercizio degli impianti di sicurezza e segnalamento,<br />

di controllo e di regolazione della circolazione e di smistamento a gravità<br />

RFI 19. Disposizione n. 19 del 18 Aprile 2005 Messa in esercizio della tratta Roma-Napoli<br />

e della sub tratta Torino-Novara della linea AV/AC Torino-Milano-Napoli<br />

RFI 20. Disposizione n. 22 del 27 Aprile 2005 Disciplina operativa per la messa in<br />

esercizio della tratta Roma-Napoli e della sub tratta Torino-Novara della linea<br />

AV/AC Torino-Milano-Napoli<br />

RFI 21. Disposizione n. 29 del 15/10/2002 “Sviluppo e realizzazione di prodotti e sistemi<br />

tecnologici per il segnalamento ferroviario”<br />

RFI 22. Disposizione n. 32 del 12/11/2002 “Applicazione della normativa CENELEC di<br />

settore allo sviluppo e realizzazione di sistemi e prodotti elettronici in sicurezza<br />

per il segnalamento ferroviario”<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

142/161


Standards, Procedures and Specifications<br />

RFI 23.<br />

RFI 24.<br />

RFI 25.<br />

RFI 26.<br />

RFI 27.<br />

RFI TC PR IS 00 009 Applicazione della normativa CENELEC di settore di<br />

settore allo sviluppo e realizzazione di sistemi e prodotti elettronici in sicurezza<br />

per il segnalamento ferroviario” Rev A del 26/09/2003<br />

Istruzione per le verifiche che devono precedere l’attivazione degli impianti di<br />

segnalamento (IS46 Ed. 71)<br />

Norme tecniche per l’esecuzione e la certificazione di verifiche di impianti di<br />

segnalamento effettuate dalla ditta appaltatrice (IS717 Ed. 91),<br />

Norme tecniche per la progettazione, esecuzione, verifiche e prove di impianti di<br />

segnalamento (IS381 Ed.82),<br />

Nota RFI-DTC\A0011\P\2005\0000688 Tratta di linea AV/AC Roma-Napoli.<br />

Nomina delle Commissioni di Verifica Tecnica<br />

RFI 28. Linee Guida per le attività della CVT-SA.TLC del 25/05/2005<br />

RFI 29. RFI TC PSCC AVSC 27 002 B Istruzioni CVT SCC AV<br />

RFI 30.<br />

RFI TC.PATC VT AV02 R01 A “Specifica per verifica tecnica per l’attivazione<br />

degli impianti Rilevamento Temperatura Boccole (RTB) e Temperatura Freni<br />

(RTF) per tratte AV/AC del 13/06/2005<br />

RFI 31. Procedura “Impianti NVP – Procedura di Verifica Tecnica” Rev. 1 del 30/05/2005<br />

RFI 32.<br />

RFI 33.<br />

RFI 34.<br />

RFI 35.<br />

RFI 36.<br />

RFI TC.PATC PR AV 02 R21 Procedura di Valutazione Funzionale Progettazione<br />

e Realizz.ne Applic. Spec.che Sistema di Segnalamento. ERTMS-SST-SDT Rev B<br />

del 08/07/2005<br />

RFI TC.PATC PR AV 02 R02 Definizione dei Confini di Responsabilità sugli<br />

Elaborati di un Progetto di Base Applicazione Specifica ERTMS/SST/SDT Rev. A<br />

del 09/09/05<br />

RFI TC.PATC VV AV R12 Piano di omologazione Applicazione Generica – I<br />

Applicazione Specifica SST – ETCS Livello 2 Rev. A<br />

RFI MO-MA-TC DT PRES 001 Procedura per l’effettuazione del Pre-esercizio<br />

della Linea AV/AC Roma - Napoli Rev A del 02/09/2005<br />

RFI MO-MA-TC-IN DT INES 001 Tratta AV/AC Roma – Napoli Caratteristiche<br />

Infrastrutturali e Programma di Esercizio Complessivo della Tratta del 01/09/2005<br />

RFI Specifications<br />

RFI 37. Rif. 1 RFI TC.STEC RS AV 01 G01 Analisi Preliminare del Rischio per la Tratta<br />

AV Roma Napoli Rev 4 del 11/02/02<br />

RFI 38. XXXX 00 0 IF SP 000.01 001 Sistema Italiano Alta Velocità - Specifiche di Base<br />

del 29/05/1992<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

143/161


RFI 39. DI TC PATC SR AV 01 E02 Specifiche dei Requisiti Funzionali del Sistema di<br />

“Controllo Automatico della Marcia del Treno” per la linea ad alta velocità Roma<br />

Napoli Rev 0.2 + allegati<br />

RFI 40. TC PATC SR AV 01 D01/D02/D03 Linea AV ROMA-NAPOLI - Sistema di<br />

Comando/Controllo della marcia dei treni ERTMS/ETCS L2 - Specifica dei<br />

Requisiti di Sistema – Volume 1 Rev. B<br />

RFI 41. DI TC PATC AV 01 D06 A, Linea AV ROMA-NAPOLI - Sistema di<br />

Comando/Controllo della marcia dei treni ERTMS/ETCS L2 - Specifica dei<br />

Requisiti di Sistema – Volume 1 - Appendice Gestione Interconnessioni Rev. A01<br />

RFI 42. RFI TC.PATC AV 01 D07 Alimentazione delle Stazioni Radio Base GSM-R -<br />

Appendice Volume 1 Rev. A del 12/05/2004<br />

RFI 43. RFI TC PATC DC AV 01 R01 Funzionalità Essenziali per Attivazione Sistema di<br />

Segnalamento Rev. B del 17/11/2004<br />

RFI 44. RFI TC PATC AV 01 K01 Specifica dei Requisiti di SSB Generale - Volume 3<br />

Rev. A del 31/01/2003<br />

RFI 45. RFI TC PATC AV 01 K02 Specifica dei Requisiti di SSB Gestione Stati e Modi<br />

Operativi - Volume 3 Rev A del 31/12/2003<br />

System assessment and approvals<br />

RFI 46. RFI-DTC.PATC 032 Valutazione Funzionale Specifica dei Requisiti di Sistema Volume<br />

2 Rev. C del 30/01/2004<br />

RFI 47. RFI-DTC.PATC 126 Linea AV RM-NA. Gestione Interconnessioni - Approvazione<br />

Schemi di Principio per il Cambio Sistema del 29/03/2004<br />

RFI 48. RFI-DTC.PATC 322 Linea AV RM-NA. Gestione Interconnessioni - Approvazione<br />

Schemi di Principio per il Cambio Sistema del 07/07/2004<br />

RFI 49. RFI-DTC.PATC Approvazione Pr<strong>of</strong>ili di Linea RTB del 13/02/2004<br />

RFI 50. RFI TC.PATC VV AV R01 Piano di Valutazione Funzionale Applicazione Generica –<br />

Prima Applicazione Specifica SST ETCS Livello 2 Rev A<br />

RFI 51. RFI TC.PATC VV AV 02 R01 Valutazione Funzionale Specifiche di Test di Sistema<br />

Saturno Rev B del 02/02/2005<br />

RFI 52. RFI TC.PATC VV AV 02 R05 Logica RBC - Schemi di principio Rev B del 07/09/2005<br />

RFI 53. RFI TC.PATC VV AV 02 R04 Gestione Non Conformità/ Punti Aperti Rev D del<br />

09/12/2005<br />

RFI 54. RFI TC PATC ST AV 01 DBC A Valutazione Funzionale di Sistema ERTMS/ETCS<br />

livello 2 Tratta AV/AC Roma – Napoli, Rev A (presente documento) del 12/12/2005<br />

RFI 55. RFI TC PATC VV AV 02 R79 A Rapporto di Valutazione Funzionale Test in campo,<br />

Rev. A<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

144/161


RFI 56. RFI TC PATC VM AV 01 DBD A Test di Valutazione Funzionale sistema<br />

ERTMS/ETCS Livello 2 Tratta AV/AC Roma - Napoli, Rev. A del 14/12/2005<br />

RFI 57. Linea AC/AV Roma Napoli Sistema ACS AC/AV – Dossier di Assessment Funzionale –<br />

attivazione all’esercizio ferroviario Rev. A<br />

RFI 58. RFI TC.PATC VV AV 02 R16 Rapporto di Valutazione Funzionale. Prima Applicazione<br />

Specifica 2a Sottotratta Labico-S.Giovanni Rev C del 07/12/2005<br />

RFI 59. CVT-SA.SDT1 A104.24 Rapporto di valutazione funzionale Applicazione Specifica<br />

Sottosistema di Terra ETCS livello 2 Tratta AV/AC Roma-Napoli (2° Sottotratta) Rev B<br />

del 07/12/05<br />

RFI 60. CVT - AS.SS/TT Verbale Verifica Tecnica dell'applicazione Segnalamento/<br />

Telecomunicazione SST ETCS livello 2 Rev B del 15/12/2005<br />

RFI 61. CVT-SA.SDT1.A104.01 RdV Piani schematici ERTMS Rev A del 09/09/2005<br />

RFI 62. CVT-SA.SDT1.A104.02 RdV delle Tabelle delle Condizioni di RBC Rev B del<br />

06/09/2005<br />

RFI 63. CVT – SA.SDT1.A104.3 Rapporto di Valutazione degli Allacciamenti Rev A del<br />

15/07/2005<br />

RFI 64. CVT – SA.SDT1.A104.4 Rapporto di Valutazione del Layout Interfacce Operatore Rev<br />

A del 15/07/2005<br />

RFI 65. CVT – SA.SDT1.A104.5 Rapporto di Valutazione del Layout Apparecchiature nei<br />

Locali Rev A del 15/07/2005<br />

RFI 66. CVT – SA.SDT1.A104.6 Rapporto di Valutazione del Layout Armadi Rev A del<br />

15/07/2005<br />

RFI 67. CVT-SA.SDT1.A104.7 Rapporto di Valutazione funzionale PI ERTMS/ETCS Rev C del<br />

09/09/2005<br />

RFI 68. CVT-SA.SDT1.A104.11 Rapporto di Valutazione Funzionale - Misure in Campo Rev C<br />

del 09/09/2005<br />

RFI 69. CVT – SA.SDT1.A104.13 Rapporto di Valutazione dell’Interfacciamento TLC-LD Rev<br />

A del 09/09/2005<br />

RFI 70. CVT-SA.SDT1.A104.14 Rapporto di Valutazione sulla corretta fornitura, Installazione e<br />

Configurazione delle apparecchiature ERTMS/ETCS LIVELLO 2 presso PCS Rev B del<br />

09/09/2005<br />

RFI 71. CVT-SA.SDT1.A104.15 RdV Messaggi Radio Rev A del 04/07/2005<br />

RFI 72. CVT-SA.SDT1.A104.16 RdV Tabelle Intermedie RBC Rev A del 04/07/2005<br />

RFI 73. CVT-SA.SDT1.A104.18 Rapporto di Valutazione sulla correttezza concordanze NVP-<br />

RBC Rev B del 07/09/2005<br />

RFI 74. CVT – SA.SDT1.A104.19 Rapporto di Valutazione dell’Interfacciamento GSM-R Rev<br />

A del 09/09/2005<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

145/161


RFI 75. CVT-SA.SDT1.A104.20 Rapporto di Valutazione Funzionale - Configurazione RBC<br />

(MA, CES) Labico - Supino Rev A del 09/09/2005<br />

RFI 76. CVT-SA.SDT1.A104.21 Rapporto di Valutazione Funzionale - Configurazione RBC<br />

(MA, CES) Ceccano – S. Giovanni Rev A del 09/09/2005<br />

RFI 77. CVT-SA.SDT1.A104.22 Rapporto di Valutazione Funzionale - Configurazione RBC<br />

(MA, CES) Percorsi Deviatoi Labico – S. Giovanni Rev A del 09/09/2005<br />

RFI 78. CVT-SA.SDT1.A104.23 Rapporto di Valutazione Funzionale - Configurazione RBC<br />

(ED) Labico – S. Giovanni Rev A del 09/09/2005<br />

RFI 79. CVT – SA.SDT1.A104.25 Relazione Tecnica – Evoluzione della configurazione e<br />

relativa analisi di impatto e Non Regressione Rev D del 07/12/2005<br />

RFI 80. CVT – SA.SDT1.A104.26 Rapporto di valutazione funzionale sulla Progettazione<br />

Applicativa Eurobalise Rev A del 09/09/2005<br />

RFI 81. CVT – SA.SDT1.A104.27 Rapporto di valutazione funzionale telegrammi Allarmi RTB<br />

Rev B del 07/12/2005<br />

RFI 82. RFI TC.PATC RR AV 06 R01 Ricognizione sulla linea AV Roma Napoli, PJ Ceccano,<br />

per verifica anormalità CdB Digicode Rev A del 07/09/2005<br />

RFI 83. NVP Colleferro (PT) – <strong>Report</strong> CVT delle prove in ambiente reale CVT-SA.GdV C1.1<br />

RFI 84. NVP Labico (PC) – <strong>Report</strong> CVT delle prove in ambiente reale CVT-SA.GdV C1.1<br />

RFI 85. NVP Anagni (PM/PJ) – <strong>Report</strong> CVT delle prove in ambiente realeCVT-SA.GdV C1.1<br />

RFI 86. NVP Ceccano (PC) – <strong>Report</strong> CVT delle prove in ambiente reale CVT-SA.GdV C1.2<br />

RFI 87. NVP Ceprano (PT) – <strong>Report</strong> CVT delle prove in ambiente reale CVT-SA.GdV C1.2<br />

RFI 88. NVP Supino (PT) – <strong>Report</strong> CVT delle prove in ambiente reale CVT-SA.GdV C1.2<br />

RFI 89. NVP S. Giovanni (PM) – <strong>Report</strong> CVT delle prove in ambiente reale CVT-SA.GdV C1.2<br />

Permissions<br />

RFI 90. RFI TC.PATC VV AV 02 R10 Rapporto di Valutazione Funzionale SST per rilascio<br />

Nulla Osta Distanziamento Treni a velocità < 150 km/h sottotratta Labico-Supino Rev. A<br />

del 04/07/2005<br />

RFI 91. RFI TC.PATC VV AV 02 R10 Rapporto di Valutazione Funzionale SST per rilascio<br />

Nulla Osta Distanziamento Treni a velocità < 300 km/h sottotratta Labico S.Giovanni<br />

Rev. B del 18/07/2005<br />

RFI 92. RFI TC PATC SR AV 03 E02 <strong>Process</strong>o di Omologazione SSB ERTMS Rev. A<br />

RFI 93. Nulla Osta Installazione ETR 500 59 del 30/12/04<br />

RFI 94. Nulla Osta SSB per Distanziamento Treni v < 150 Km/h del 25/06/05<br />

RFI 95. Nulla Osta SSB per Distanziamento Treni v < 200 Km/h del 15/07/05<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

146/161


RFI 96. Nulla Osta SSB per Distanziamento Treni v < 275 Km/h del 26/07/05<br />

RFI 97. Nulla Osta SSB per Distanziamento Treni v < 300 Km/h del 08/08/05<br />

RFI 98. Linea Roma Napoli Sistema ACS AC/AV - Dossier di Assessment Funzionale –<br />

attivazione al pre-esercizio Rev. A<br />

RFI 99. RFI TC.PATC RR AV 03 E06 Relazione conclusiva per il rilascio del Nulla Osta al Pre -<br />

esercizio del Sotto Sistema di Bordo ERTMS/AV Alstom Rev. A<br />

RFI 100. RFI TC.PATC VV AV 02 R10 Rapporto di Valutazione Funzionale Sottosistema di<br />

Terra ETCS Livello 2 intera tratta Rev C del 09/09/2005<br />

RFI 101. RFI DT.PATC CO AV 02 Applicazione Generica Sottosistema di Terra ETCS livello 2<br />

della Impresa Alstom Ferroviaria SpA – Certificato per la Accettazione Preliminare Rev<br />

A del 12/09/2005<br />

RFI 102. RFI/TC.CC/2927 del 09/09/2005 – Risultanze del processo di <strong>Safety</strong> Assessment<br />

RFI 103. Rapporti mensili del pre-esercizio della Linea AV/AC Roma (n. 4 rapporti)<br />

RFI 104. RFI DTC A0011 P 2005 0002025 Rapporto finale sulla esaustività e idoneità del Sistema<br />

Regolamentare del 19/12/2005<br />

RFI 105. RFI TC PATC VV AV 02 R89 Relazione sull’esito del pre-esercizio della tratta AV/AC<br />

Roma Napoli emesso dalle Direzioni Compartimentali Movimento ed Infrastruttura di<br />

Roma e di Napoli Rev A del 09/12/2005<br />

RFI 106. RFI TC PATC VV AV 02 R89 Rapporto di Valutazione Funzionale Applicazione<br />

Generica SST ETCS Livello 2 – Risultanze del Pre-esercizio Rev. A<br />

RFI 107. RFI TC.PATC VV AV 02 R10 Rapporto di Valutazione Funzionale Sottosistema di<br />

Terra ETCS Livello 2 intera tratta Rev D del 09/12/2005<br />

RFI 108. Nota RFI/DTC – PATC.191 del 16/12/2004<br />

RFI 109. Nota DI/TC.SS.TB/009/425 del 29/11/1999<br />

RFI 110. Nota RFI-DTC A0011/P/2005/0001995 del 15/12/2005<br />

RFI 111. Nota RFI-DTC/A0011/P/2005/000663 del 16/05/2005<br />

RFI 112. Nota RFI DT PATC CO AV 02 E01 B Applicazione Generica Sottosistema di Terra<br />

ETCS Livello 2 della impresa Alstom Ferroviaria S.p.A. – Certificazione per<br />

l’Accettazione Preliminare<br />

RFI 113. RFI TC PATC ST AV 01 DBC Rev. A Valutazione Funzionale di Sistema<br />

ERTMS/ETCS Livello 2 – Applicazione Generica - Tratta AV/AC Roma Napoli del<br />

14/12/2005<br />

RFI 114. RFI TC CC RR AS 11 001 A Rapporto di Valutazione (Assessment <strong>Report</strong>) relativo al<br />

Sistema di Segnalamento Linea AV Roma – Napoli del 14/12/2005<br />

RFI 115. Linea AC/AV Roma Napoli Sistema ACS AC/AV - Dossier di Assessment Funzionale –<br />

attivazione all’esercizio ferroviario Rev. B<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

147/161


RFI 116. RFI TC PATC RR AV 03E09 Relazione conclusiva per il rilascio del Nulla Osta<br />

all’esercizio del Sotto Sistema di Bordo ERTMS/AV Alstom – Fase 1 (Progetto<br />

ATC/CESIFER) del 09/12/2005<br />

Suppliers Documents<br />

Hazard <strong>Analysis</strong><br />

RFI 117. A104 00 CI1 SQ IS 00 0 0 R07, Fault Tree <strong>Analysis</strong> – Sistema di Comando e Controllo<br />

della marcia dei treni ERTMS/ETCS Livello 2<br />

RFI 118. A104 00 CI1 SQ IS 00 0 0 R06, Analisi FMEA – Sistema di Comando e Controllo della<br />

marcia dei treni ERTMS/ETCS Livello 2<br />

RFI 119. A104 00 CI1 2Z IT 0000 020, Hazard <strong>Analysis</strong> delle Funzioni del SSAV-SST<br />

RFI 120. A104 00 CI1 2Z IT 0000 022, Hazard <strong>Analysis</strong> delle Funzioni del SSAV-SST - Allegato<br />

B - Hazard-Log relativo agli Hazard in Stato “Cancellato”<br />

RFI 121. A104 00 CI1 2Z IT 0000 039 Analisi dell' Hazardous Failure Rate (HFR) del<br />

Sottosistema di Terra ERTMS/ETCS L2 per la linea AV tratta Roma-Napoli<br />

RFI 122. Linea AV Roma-Napoli – Specifica dei Requisiti di Sistema, Vol.2 – Sottosistema di<br />

Terra<br />

RFI 123. A104 00 CI1 2Z IT 0000 063 SSAV-SST - Hazard <strong>Analysis</strong> delle Funzioni del Sistema<br />

SSAV-SST – Specifica dei Requisiti di Sicurezza, rev. A<br />

RFI 124. A104 00 CI1 SP IT 0000 003 Linea AV Roma-Napoli Specifica dei Requisiti di Sistema<br />

Volume 3 - Sotto Sistema di Bordo Rev A del 01/08/03<br />

RFI 125. A104 00 BI1 RP IS 0000 R14 Tabelle delle Condizioni (TdC) di Linea-Stazione 1-2-3<br />

Sottotratta Rev. A del 04/11/2005<br />

RFI 126. A104 Tabelle delle Condizioni RBC / Integrazione Funzionale di Sottosistema di Terra<br />

RFI 127. A104 00 BI 1 PX IS 00 00 R01 Piano Schematico As Build rev.B del 04/11/2005<br />

RFI 128. 37X.B22.C.IS.005641 Sottosistema NVP + GAT Applicazione Generica <strong>Safety</strong> Case<br />

(vers. Logica NVP 5.0) Rev. 00.00<br />

RFI 129. 37X.B22.C.IS.007-641 Sottosistema NVP + GAT Applicazione Generica <strong>Safety</strong> Case<br />

aggiornamento per le nuove versioni di logica NVP (successive a VLA 5.3C1) Rev.<br />

02.00 del 07/11/2005<br />

RFI 130. A104 00 CI1 SP IS 0000 AH2B001 Applicazione Generica Gestione della Via <strong>Safety</strong><br />

Case (25/01/2005)<br />

RFI 131. A104 00 CI1 IS0000 AJ0 Applicazione Generica Gestione della Via <strong>Safety</strong> Case<br />

Aggiornamenti successivi alla versione del 25/01/2005 Rev. C del 30/11/2005<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

148/161


RFI 132. A104 00 CI1 SP IS 0000 AJ2 Sottosistema Segnalamento Terra Gestione della Via -<br />

Applicazione Specifica seconda sottotratta e PPF di S.Giovanni in Carico <strong>Safety</strong> Case<br />

Aggiornamenti Successivi alla Versione del 16/03/05 Rev. D del 28/11/2005<br />

RFI 133. A104 00 CI1 IS0000 AJ2 Sottosistema Segnalamento Terra Gestione della Via -<br />

Applicazione Specifica seconda sottotratta e PPF di S.Giovanni in Carico <strong>Safety</strong> Case<br />

Aggiornamenti Successivi alla Versione del 16/03/05 Rev. D del 28/11/2005<br />

RFI 134. A104 00 CI1 IS0000 AJ2 Sottosistema Segnalamento Terra Gestione della Via -<br />

Applicazione Specifica seconda sottotratta e PPF di S.Giovanni in Carico <strong>Safety</strong> Case<br />

Aggiornamenti Successivi alla Versione del 16/03/05 Rev. D del 28/11/2005<br />

RFI 135. A104 00 CI1 SP IS 0000RG5 Tratta AV Roma Napoli Sottosistema Distanziamento<br />

Treni <strong>Safety</strong> Case di Applicazione Generica del 23/11/2005<br />

RFI 136. A104 00 CI1 SP IS 0000RN0 Tratta AV Roma Napoli <strong>Safety</strong> Case SDT Applicazione<br />

Specifica 2 sottotratta Rev G del 29/11/05<br />

RFI 137. A104 00 CI1 SP IS 0000 RP9 Tratta AV Roma Napoli SDT – Relazione tecnica di<br />

sicurezza Rev G del 06/12/2005<br />

RFI 138. A104 00 CI1 2Z IT0000036 Tratta AV Roma Napoli Applicazione Generica<br />

Sottosistema di Segnalamento di Terra <strong>Safety</strong> Case Rev. D del 29/07/2005<br />

RFI 139. A104 00 CI1 2Z IT0000056 Tratta AV Roma Napoli Sottosistema di Segnalamento di<br />

Terra Applicazione Specifica II Sottotratta - <strong>Safety</strong> Case Rev. D del 31/07/2005<br />

RFI 140. A104 00 CI1 2Z IT0000095 Tratta AV Roma Napoli Applicazione Generica –<br />

Applicazione Specifica II Sottotratta Sottosistema di Segnalamento di Terra - <strong>Safety</strong><br />

Case aggiornamento Rev. A del 09/12/2005<br />

RFI 141. [GATC_BSI_RAMS_0040] GATC Trainborne <strong>Safety</strong> Case, Version 5.4 del 28.10.2005<br />

RFI 142. Dichiarazione di Conformità di Consorzio Saturno DC/001 del 07/09/2005<br />

RFI 143. Dichiarazione di Conformità di Alstom Transport n. AV RM/NA 604/05 del 08/09/2005<br />

RFI 144. Dichiarazione di Conformità di Ansaldo Segnalamento Ferroviario Gestione della Via<br />

ASF/05/7501 del 07/09/2005<br />

RFI 145. DC002 Linea AV Roma Napoli Applicazione Specifica di I, II e III Sottotratta<br />

Dichiarazione di Conformità del Consorzio Saturno del 09/12/2005<br />

RFI 146. 7513300/1007/05 del 07/12/05 Dichiarazione di Conformità linea AV/AC Milano Napoli<br />

Tratta Roma Napoli (Alstom)<br />

RFI 147. ASF/05/10636 Linea AV Roma Napoli Applicazione Specifica di I, II e III Sottotratta<br />

Dichiarazione di Conformità di ASF del 09/12/2005<br />

13.4 Specific References for the Turin-Novara Project<br />

RFI Specifications and assessment documents<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

149/161


RFI 148. RFI TC PATC SR AV 01 E02 Linea AV Torino Novara Funzionalità essenziali per le<br />

attivazioni Rev. B del 17/11/2004<br />

RFI 149. RFI-DTC.PATC 187 Valutazione funzionale distanziamento tratta Torino-Novara<br />

Logica RBC del 14/012/2004<br />

RFI 150. RFI-DTC.PATC 003 Assessment Funzionale SST ETCS L2 Linea AV/AC Tratte Roma-<br />

Napoli e Torino-Novara. Non conformità/Punti Aperti del 21/01/2005<br />

RFI 151. RFI-DTC.PATC 078 Assessment Funzionale SST ETCS L2 Linea AV/AC Tratte Roma-<br />

Napoli e Torino-Novara. Non conformità/Punti Aperti del 21/03/2005<br />

RFI 152. RFI-DTC.PATC 032 Assessment Funzionale SST ETCS L2 Linea AV/AC Tratta<br />

Torino-Novara. Non conformità/Chiarimenti del 04/08/2005<br />

RFI 153. RFI-DTC.PATC 347 Sistema Distanziamento Treni ERTMS/ETCS L2 Assessment<br />

Funzionale SST ETCS L2 Tratta Torino – Novara: Azioni correttive e soluzioni per Non<br />

Conformità/Punti aperti del 17/10/2005<br />

RFI 154. RFI-DTC.PATC 362 Sistema Distanziamento Treni ERTMS/ETCS L2 Assessment<br />

Funzionale SST ETCS L2 Tratta Torino – Novara: del 21/10/2005<br />

RFI 155. RFI-DTC.PATC 364 Sistema Distanziamento Treni ERTMS/ETCS L2 Assessment<br />

Funzionale SST ETCS L2 Tratta Torino – Novara: del 21/10/2005 Lista delle Non<br />

Conformità del 25/10/2005<br />

RFI 156. RFI-DTC.PATC 126 Linea AV RM-NA. Gestione Interconnessioni - Approvazione<br />

Schemi di Principio per il Cambio Sistema del 29/03/2004<br />

RFI 157. RFI-DTC.PATC 322 Linea AV RM-NA. Gestione Interconnessioni - Approvazione<br />

Schemi di Principio per il Cambio Sistema del 07/07/2004<br />

RFI 158. RFI TC.PATC VV AV 02 R01 Piano di Valutazione Funzionale Applicazione Generica<br />

– I Applicazione Specifica SST ETCS Livello 2 Rev A<br />

RFI 159. RFI TC PATC VV AV 02 R79 Rapporto di Valutazione Funzionale Sottosistema di<br />

Terra Sottosistema di Bordo ETCS Liv. 2 Tratta AV/AC Torino Novara Rev. E del<br />

06/02/2006<br />

RFI 160. RFI TC.PATC VV AV 02 R82 Gestione Non Conformità/ Punti Aperti Rev C del<br />

06/02/2006<br />

RFI 161. RFI TC PATC VM AV 01 DBE A Valutazione Funzionale di Sistema ERTMS/ETCS<br />

livello 2 Tratta AV/AC Torino-Novara, Rev A (presente documento) del 06/02/2006<br />

RFI 162. RFI TC PATC VM AV 01 DA3 A Test di Valutazione Funzionale sistema<br />

ERTMS/ETCS Livello 2 Tratta AV/AC Torino – Novara, Rev. A del 06/11/2005<br />

RFI 163. RFI TC PATC VV AV 01 DA5 A Test <strong>Report</strong> di Valutazione Funzionale sistema<br />

ERTMS/ETCS Livello 2 Tratta AV/AC Torino – Novara, Rev. A del 04/02/2006<br />

RFI 164. RFI.TCPA RT SI 08 044 Linea AC/AV Tratta Torino-Novara Sistema ACS AC/AV -<br />

Dossier di Assessment Funzionale – attivazione all’esercizio ferroviario Rev. B<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

150/161


RFI 165. CVT – SA.SDT.A201.24 - Rapporto di valutazione funzionale Applicazione Specifica<br />

Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione<br />

Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. D del 06/02/06<br />

RFI 166. CVT – SA.SDT.A201.01 - CVT – SA.SDT Rapporto di Valutazione Funzionale Piano<br />

Schematico ERTMS/ETCS LIVELLO 2 Torino – Novara Tratta Settimo – Novara da<br />

km. 0+786 a km. 84+758 Rev.B del 16/01/06<br />

RFI 167. CVT-SA.SDT.A201.02 - CVT-SA.SDT Rapporto di valutazione funzionale Tabella<br />

delle Condizioni di RBC Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-<br />

Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758<br />

Rev. A del 25/10/05<br />

RFI 168. CVT-SA.SDT.A201.03 - CVT-SA.SDT Rapporto di valutazione funzionale Layout<br />

interfaccia operatore Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara<br />

Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del<br />

25/10/05<br />

RFI 169. CVT-SA.SDT.A201.04 - CVT-SA.SDT Rapporto di valutazione funzionale<br />

Allacciamenti Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara<br />

Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del<br />

25/10/05<br />

RFI 170. CVT-SA.SDT.A201.05 - CVT-SA.SDT Rapporto di valutazione funzionale Layout<br />

apparecchiature nei locali Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-<br />

Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758<br />

Rev. A del 25/10/05<br />

RFI 171. CVT-SA.SDT.A201.06 - CVT-SA.SDT Rapporto di valutazione funzionale Layout<br />

Armadi Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara<br />

Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. A del<br />

25/10/05<br />

RFI 172. CVT – SA.SDT.A201.07 - CVT – SA.SDT Rapporto di valutazione funzionale Punti<br />

Informativi ERTMS/ETCS Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. B<br />

del 16/01/06<br />

RFI 173. CVT – SA.SDT.A201.08 -CVT – SA.SDT Rapporto di valutazione funzionale Punti<br />

Informativi ERTMS/ETCS Tratta Settimo – Novara da km. 0+786 a km. 84+758 Letture<br />

Punti Informativi e Confronto con Telegrammi di Progetto Rev. A del 25/10/05<br />

RFI 174. CVT – SA.SDT.A201.09 - CVT – SA.SDT Rapporto di valutazione funzionale Misure<br />

in Campo ERTMS/ETCS LIVELLO 2 e non Tratta Settimo – Novara da km. 0+786 a<br />

km. 84+758 Tabelle misure (punte scambi, traverse limite, punti informativi, cartelli -<br />

EoA, giunti elettrici) Rev. A del 25/10/05<br />

RFI 175. CVT – SA.SDT.A201.11- CVT – SA.SDT Rapporto di valutazione funzionale Misure in<br />

Campo ERTMS/ETCS LIVELLO 2 e non Tratta Settimo – Novara da km. 0+786 a km.<br />

84+758 Rev. B del 16/01/06<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

151/161


RFI 176. CVT - SA.SDT.A201.13 - CVT-SA.SDT Rapporto di valutazione funzionale Corretta<br />

Configurazione delle Interfacce TLC-LD Sottosistema di Terra ETCS livello 2 Tratta<br />

AV/AC Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a<br />

km. 84+758 Rev. A del 25/10/05<br />

RFI 177. CVT - SA.SDT.A201.14 - CVT-SA.SDT Rapporto di Valutazione Funzionale Fornitura,<br />

Installazione e Configurazione delle apparecchiature ERTMS/ETCS Livello 2 presso<br />

PCS Rev. A del 19/10/05<br />

RFI 178. CVT-SA.SDT1.A201.15 - CVT-SA.SDT Rapporto di valutazione funzionale Tabelle<br />

delle MA Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara<br />

Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km. 84+758 Rev. B del<br />

17/01/06<br />

RFI 179. CVT-SA.SDT.A201.18 - CVT-SA.SDT Rapporto di valutazione funzionale<br />

Concordanza dati NVP – RBC Sottosistema di Terra ETCS livello 2 Tratta AV/AC<br />

Torino-Novara Applicazione Specifica Tratta Settimo – Novara da km. 0+786 a km.<br />

84+758 Rev. B del 13/01/06<br />

RFI 180. CVT - SA.SDT1.A201.19 - CVT - SA.SDT1.A201.19 - CVT-SA.SDT Rapporto di<br />

Valutazione Funzionale Configurazione delle Interfacce GSM-R Rev. A del 19/10/05<br />

RFI 181. CVT-SA.SDT.A201.20 - CVT-SA.SDT Rapporto di valutazione funzionale della<br />

Configurazione RBC (Tabelle delle Condizioni / Tabelle dei Messaggi Radio)<br />

Sottosistema di Terra ETCS livello 2 Tratta AV/AC Torino-Novara Applicazione<br />

Specifica Intera Sottotratta Rev. B del 17/01/06<br />

RFI 182. CVT – SA.SDT.A201. 25 - CVT – SA.SDT Relazione Tecnica SSAV To-No SDT<br />

ANSALDO Tratta Settimo – Novara da km. 0+786 a km. 84+758 Evoluzione della<br />

configurazione e relative analisi di impatto e non regressione Rev. D del 05/02/06<br />

RFI 183. CVT – SA.SDT.A201.26 - CVT – SA.SDT Rapporto di valutazione funzionale<br />

Progettazione Applicativa Eurobalise Tratta Settimo – Novara da km. 0+786 a km.<br />

84+758 Rev. B del 16/01/06<br />

RFI 184. CVT – SA.SDT.A201.27 - CVT – SA.SDT Rapporto di valutazione funzionale<br />

Progettazione Applicativa Eurobalise RTB Rev A del 21/11/05.<br />

RFI 185. CVT –SA.SDT/SA.TLC Rapporto di Valutazione Interrelazione CVT SDT – TLC – LD<br />

Rev. A del 09/11/2005<br />

RFI 186. RFI TC.PATC VV AV 02 R79 Rapporto di Valutazione Funzionale SST e SSB ETCS<br />

L2 per rilascio Nulla Osta Distanziamento Treni a velocità < 150 km/h Rev. B del<br />

30/12/2005<br />

RFI 187. RFI TC.PATC VV AV 02 R79 Rapporto di Valutazione Funzionale SST e SSB ETCS<br />

L2 per rilascio Nulla Osta Distanziamento Treni a velocità < 300 km/h Rev. D del<br />

02/02/2005<br />

RFI 188. RFI TC PATC SR AV 03 E02 <strong>Process</strong>o di Omologazione SSB ERTMS Rev. A<br />

RFI 189. Nulla Osta Installazione ETR 500 59 del 30/12/04<br />

RFI 190. RFI-DTC/A0011/P/2005/0001853 Nulla Osta SSB per Distanziamento Treni v < 150<br />

Km/h del 24/11/05<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

152/161


RFI 191. Nulla Osta SSB per Distanziamento Treni v < 200 Km/h del 15/07/05<br />

RFI 192. Nulla Osta SSB per Distanziamento Treni v < 275 Km/h del 26/07/05<br />

RFI 193. Nulla Osta SSB per Distanziamento Treni v < 300 Km/h del 08/08/05<br />

Documents about approbatory period<br />

RFI 194. RFI.TCPA RT SI 08 044 Linea AC/AV Tratta Torino-Novara Sistema ACS AC/AV -<br />

Dossier di Assessment Funzionale – attivazione al pre-esercizio Rev. A<br />

RFI 195. RFI TC.PATC VV AV 02 R79 Rapporto di Valutazione Funzionale SST e SSB ETCS<br />

L2 per Pre-esercizio Rev. A del 25/11/2005<br />

RFI 196. RFI DT PATC CO AV 02 E02 A Applicazione Generica Sottosistema di Terra ETCS<br />

Livello 2 della impresa Ansaldo Segnalamento Ferroviario S.p.A. – Certificazione per<br />

l’Accettazione Preliminare<br />

RFI 197. RFI/TC.CC/2972 del 28/10/2005 – Risultanze del processo di <strong>Safety</strong> Assessment<br />

Sistema di Segnalamento AV Torino – Novara<br />

RFI 198. RFI DTC A0011 P 2005 0002025 Rapporto finale sulla esaustività e idoneità del Sistema<br />

Regolamentare del 19/12/2005 (Attività svolta nella fase di pre-esercizio della Roma<br />

Napoli)<br />

RFI 199. RFI TC PATC VV AV 02 R91 Rapporto di Valutazione Funzionale Applicazione<br />

Generica SST ETCS Livello 2 Tratta Torino – Novara – Risultanze del Pre-esercizio<br />

Rev. A del 06/02/06<br />

Documents about revenue service<br />

RFI 200. Nota RFI/DTC – PATC.191 del 16/12/2004<br />

RFI 201. Nota DI/TC.SS.TB/009/425 del 29/11/1999<br />

RFI 202. Nota RFI-DTC/A0011/P/2006/0000184 del 02/02/2006<br />

RFI 203. Nota RFI-DTC/A0011/P/2005/000663 del 16/05/2005<br />

RFI 204. RFI TC.PATC VV AV 02 R79 Rapporto di Valutazione Funzionale SST e SSB ETCS<br />

L2 per Pre-esercizio Rev. E del 06/02/2006<br />

RFI 205. RFI.TCPA RT SI 08 044 Linea AC/AV Tratta Torino-Novara Sistema ACS AC/AV -<br />

Dossier di Assessment Funzionale – attivazione all’esercizio ferroviario Rev. B<br />

RFI 206. RFI DT PATC CO AV 02 E02 B Applicazione Generica Sottosistema di Terra ETCS<br />

Livello 2 della impresa Ansaldo Segnalamento Ferroviario S.p.A. – Certificazione per<br />

l’Accettazione Preliminare<br />

RFI 207. RFI TC PATC VM AV 01 DBE Rev. A Valutazione Funzionale di Sistema<br />

ERTMS/ETCS Livello 2 – Applicazione Generica - Tratta AV/AC Torino Novara del<br />

06/02/2006 (Presente report)<br />

RFI 208. RFI TC CC RR AS 11 002 A Rapporto di Valutazione (Assessment <strong>Report</strong>) relativo al<br />

Sistema di Segnalamento Linea AV Torino - Novara del 06/02/2006<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

153/161


RFI 209. RFI TC PATC RR AV 03E09 Relazione conclusiva per il rilascio del Nulla Osta<br />

all’esercizio del Sotto Sistema di Bordo ERTMS/AV Alstom – Fase 1 (Progetto<br />

ATC/CESIFER) del 09/12/2005<br />

Suppliers Documents<br />

Hazard <strong>Analysis</strong><br />

RFI 210. A104 00 CI1 SQ IS 00 0 0 R07, Fault Tree <strong>Analysis</strong> – Sistema di Comando e Controllo<br />

della marcia dei treni ERTMS/ETCS Livello 2<br />

RFI 211. A104 00 CI1 SQ IS 00 0 0 R06, Analisi FMEA – Sistema di Comando e Controllo della<br />

marcia dei treni ERTMS/ETCS Livello 2<br />

RFI 212. A104 00 CI1 2Z IT 0000 020, Hazard <strong>Analysis</strong> delle Funzioni del SSAV-SST<br />

RFI 213. A104 00 CI1 2Z IT 0000 022, Hazard <strong>Analysis</strong> delle Funzioni del SSAV-SST - Allegato<br />

B - Hazard-Log relativo agli Hazard in Stato “Cancellato”<br />

RFI 214. A104 00 CI1 2Z IT 0000 039 Analisi dell' Hazardous Failure Rate (HFR) del<br />

Sottosistema di Terra ERTMS/ETCS L2 per la linea AV tratta Roma-Napoli<br />

RFI 215. A201 19 C F2 IS 00 0B A01 F <strong>Safety</strong> Case della integrazione tra SST ASF e SSB<br />

ALSTOM tratto Torino Novara del 04/02/06<br />

Specifications<br />

RFI 216. A201 19 CF2 1S IS0000 A04 Volume 2 – Specifica Generale di Sistema –Sistema di<br />

Segnalamento Rev. A<br />

RFI 217. A201 19 CF2 1W IS0000 A01 Volume 2 – Sottosistema di Distanziamento Rev. E<br />

RFI 218. A201 09 CF2 1W IS0000 A01 Volume 2 – Sottosistema Interlocking Rev. A<br />

RFI 219. A201 09 CF2 1W IS0000 A01 Volume 2 – Sottosistema Interconnessioni AC/AV –LS<br />

(Transizione L2 LT) Rev. A<br />

RFI 220. A201 09 CF2 1RLD 0000 X01 Volume 2 – Sottosistema Lunga Distanza-Relazioni<br />

_Architettura di Rete e Descrizione Funzionale Sottosistema Lunga Distanza Rev. B<br />

RFI 221. A104 00 CI1 2Z IT 0000 063 SSAV-SST - Hazard <strong>Analysis</strong> delle Funzioni del Sistema<br />

SSAV-SST – Specifica dei Requisiti di Sicurezza, rev. A<br />

RFI 222. A104 00 CI1 SP IT 0000 003 Linea AV Roma-Napoli Specifica dei Requisiti di Sistema<br />

Volume 3 - Sotto Sistema di Bordo Rev A del 01/08/03<br />

RFI 223. A201 09 C F2 1T IS 00 0B A02 Tabella delle Condizioni RBC1 (Settimo – Balocco)<br />

Rev E<br />

RFI 224. A201 09 C F2 1T IS 00 0B A03 Tabella delle Condizioni RBC2 (Recetto – Novara<br />

Ovest) Rev.E<br />

RFI 225. A201 19 C F2 1P IS 00 00 A01 Piano Schematico di linea ERTMS Liv.2 Tratta Torino-<br />

Novara Rev. F<br />

<strong>Safety</strong> Cases<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

154/161


RFI 226. 37X.B22.C.IS.005641 Sottosistema NVP + GAT Applicazione Generica <strong>Safety</strong> Case<br />

(vers. Logica NVP 5.0) Rev. 00.00<br />

RFI 227. 37X.B22.C.IS.007-641 Sottosistema NVP + GAT Applicazione Generica <strong>Safety</strong> Case<br />

aggiornamento per le nuove versioni di logica NVP (successive a VLA 5.3C1) Rev.<br />

02.00 del 07/11/2005<br />

RFI 228. A104 00 CI1 SP IS 0000 AH2B001 Applicazione Generica Gestione della Via <strong>Safety</strong><br />

Case (25/01/2005)<br />

RFI 229. A104 00 CI1 IS0000 AJ0 Applicazione Generica Gestione della Via <strong>Safety</strong> Case<br />

Aggiornamenti successivi alla versione del 25/01/2005 Rev. C del 30/11/2005<br />

RFI 230. A201 19 C F2 1S IS 00 00 A33 APPLICAZIONE GENERICA GESTIONE DELLA<br />

VIA <strong>Safety</strong> Case Rev.C 25/10/05<br />

RFI 231. A201 19 C F2 3W IS 00 00 A21 SOTTOSISTEMA SEGNALAMENTO TERRA -<br />

GESTIONE DELLA VIA - APPLICAZIONE SPECIFICA - Tratta Torino – Novara -<br />

SAFETY CASE Rev C del 24/11/05<br />

RFI 232. A201 19 C F2 3W IS 00 00 A11 Tratta AV Torino-Novara - Applicazione Generica<br />

Sottosistema di Distanziamento Treni - <strong>Safety</strong> Case Rev. M 15/12/06<br />

RFI 233. A201 19 C F2 3W IS 00 00 A20 Tratta AV Torino-Novara - Applicazione Specifica<br />

Sottosistema di Distanziamento Treni - <strong>Safety</strong> Case Rev L Emesso in data: 15/12/06<br />

RFI 234. A201 19 CF2 3W IS0000 A15 Tratta AV Torino Novara Applicazione Generica<br />

Sottosistema di Segnalamento di Terra <strong>Safety</strong> Case Rev. D del 31/01/2006<br />

RFI 235. A201 19 CF2 3W IS0000 A19 Tratta AV Torino Novara Applicazione Specifica<br />

Sottosistema di Segnalamento di Terra - <strong>Safety</strong> Case Rev. C del 31/01/2006<br />

RFI 236. [GATC_BSI_RAMS_0040] GATC Trainborne <strong>Safety</strong> Case, Version 5.4 del 28.10.2005<br />

RFI 237. A201 19 C F2 IS 00 0B A01 F <strong>Safety</strong> Case della integrazione tra SST ASF e SSB<br />

ALSTOM tratto Torino Novara del 04/02/06<br />

RFI 238. A201 19 C F2 IS 00 0B A01 F <strong>Safety</strong> Case della integrazione tra SST ASF e SSB<br />

ALSTOM tratto Torino Novara del 04/02/06<br />

Conformity declarations for the approbatory period<br />

RFI 239. ASF/2005/10062 Tratta AV Torino Milano Sottotratta Torino Novara Sottosistema di<br />

Segnalamento di Terra Applicazione Specifica Dichiarazione di conformità del 25/11/05<br />

RFI 240. A201 19 C F2 IS 00 0B A01 A Rapporto delle Verifiche di integrazione tra SST ASF e<br />

SSB ALSTOM del 25/11/05<br />

Conformity declarations for the revenue service<br />

RFI 241. ASF/RMS 726/2006 Tratta AV Torino Milano Sottotratta Torino Novara Sottosistema di<br />

Segnalamento di Terra Applicazione Specifica Dichiarazione di conformità del 06/02/06<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

155/161


13.5 References for the Dutch and Belgian projects<br />

PROR 1. Wikipedia (General information)<br />

PROR 2. www.infrabel.be<br />

PROR 3. Implementing ERTMS on the Betuweroute, Signal+Draht 5/2007<br />

PROR 4. ERTMS/ETCS/GSM-R on the Belgian high speed lines L3 and L4, Signal+Draht<br />

6/2007<br />

PROR 5. ProRail ERTMS trainborne integration plan A15 tracé, Version 2.0<br />

PROR 6. www.prorail.nl<br />

13.6 References for the Spanish projects<br />

RENFE 1 Annex 1 – GIF “III Normativa y Recomendaciones de Aplication”<br />

RENFE 2 Annex II – “Condiciones tecnicas de los trenes (CTT)”<br />

RENFE 3 Annex III – SIEMENS TS Rolling Stock “Estudio de la seguridad funcional<br />

Vehiculos Ferroviarios AVE S103”<br />

RENFE 4 Annex IV – SIEMENS “Sicherheitsnachweis S103 EVC España AVE<br />

S102/S103 TRAINGUARD 200 EVC”<br />

RENFE 5 Annex V – SIEMENS “Informe de validacion del sistema del S103 EVC<br />

España AVE S102/S103 TRAINGUARD 200 EVC”<br />

RENFE 6 Annex VI – SIEMENS TS Rolling Stock “Estudio de la seguridad funcional<br />

Vehiculos Ferroviarios AVE S103 – Exported rules ”<br />

RENFE 7 Annex VII – “Alta Velocidad Cordoba-Malaga Analisis preliminar de riesgos<br />

de la aplication especifica de la linea Cordoba-Malaga”<br />

RENFE 8 Annex VIII – “Analisis preliminar de amenacas de la aplication especifica de<br />

la linea Cordoba-Malaga de Dimetronic ”<br />

RENFE 9 Annex IX – “Caso de seguridad-Applicacion Especifica Cordoba-Malaga”<br />

RENFE 10 Annex X – ADIF “Sistema Europeo de circulation de trenes ERTMS/ETCS”<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

156/161


List <strong>of</strong> abbreviations and acronyms<br />

AC Alternating Current<br />

ACS Apparato Centrale Statico (Italy)<br />

ADIF Administrador de Infrastructuras Ferroviarias (Spain)<br />

ADL Arthur D. Little<br />

AEIF Association Européenne pour l’Interopérabilité Ferroviaire<br />

AF Alstom Ferroviaria (Italy)<br />

APR Analyse Préliminaire des Risques (Preliminary Risk <strong>Analysis</strong>)<br />

ASF Ansaldo Segnalamento Ferroviario (Italy)<br />

ASFA Anuncio de Señales y Frenado Automáticoe (Spain)<br />

ATB Automatische TreinBeïnvloeding<br />

ATO Automatic Train Operation<br />

ATP Automatic Train Protection<br />

B Belgium<br />

BACC Blocco Automatico a Correnti Codificate (Italy)<br />

BBT Brenner Basis Tunnel<br />

BHL Berlin Halle Leipzig<br />

BMB Bombardier<br />

BSC Base Station Controller<br />

BTM Balise Transmission Module<br />

BTS Base Transceiver Station<br />

CCS Command, Control and Signalling<br />

CERTIFER French Notified Body<br />

Cetren Spanish Notified Body<br />

CIRCA Communication & Information Resource Centre Administrator<br />

CR Change Request<br />

CSI Concentrateur de Systèmes Informatiques (IT Systems Hub)<br />

CTT Condiciones Tecnica de los Trenes (Spain)<br />

DB Deutsche Bahn (German Railways)<br />

DC<br />

Direct Current<br />

Designers choice<br />

DMI Driver Machine Interface<br />

DPS Dossier Préliminaire de Sécurité (Preliminary <strong>Safety</strong> File)<br />

DS Dossier de Sécurité (<strong>Safety</strong> File)<br />

DTS Directives pour Travaux de Signalisation (Signalling Works Directives)<br />

DTT Direction des Transports Terrestres (Land Transport Division)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

157/161


DV Dienstvorschrift (Service order)<br />

EBC German Notified Body<br />

EC European Commission<br />

EEIG European Economic Interest Group<br />

EIRENE European Integrated Railway radio Enhanced NEtwork<br />

ENCE Enclavamiento Electrónico (Electronic interlocking)<br />

EOA End Of movement Authority<br />

EOQA<br />

Expert ou Organisme Qualifié, Agréé (Qualified Approved Expert or<br />

Organisation)<br />

<strong>ERA</strong> European Railway Agency<br />

ERTMS European Rail Traffic Management System<br />

ETCS European Train Control System<br />

ETG Elément à Turbine à Gaz (Gas Turbine Element)<br />

ETH<br />

Especificacion Técnica de Homologación (Technical Specification for<br />

Homologation)<br />

EU European Union<br />

EVC European Vital Computer<br />

FDMS<br />

Fiabilité, Disponibilité, Maintenabilité, Sécurité (Reliability, Availability,<br />

Maintainability, <strong>Safety</strong>)<br />

FFFIS Form Fit Function Interface Specification<br />

FIS Functional Interface Specification<br />

FMEA Failure Mode Effect <strong>Analysis</strong><br />

FN Funcion Nacional (National Function)<br />

FS Full Supervision mode<br />

FTA Fault Tree <strong>Analysis</strong><br />

GAMAB Globalement Au Moins Aussi Bon (Overall At Least As Good)<br />

GAME Globalement Au Moins Equivalent (Overall At Least Equivalent)<br />

GASC Generic Application <strong>Safety</strong> Case<br />

GAT Gestione ATtuatori (Italy)<br />

GdV Gestione della Via (Italy)<br />

GEST<br />

Poste de Gestion des Signalisations Temporaires (Temporary Signals<br />

Management Station)<br />

GSM-R Global System for Mobile Communications - Railways<br />

HA Hazard <strong>Analysis</strong><br />

HABD Hot Axle Box Detector<br />

HC/HSL High Capacity/High Speed Line<br />

HSL High Speed Line<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

158/161


IC Interoperability Constituent<br />

ICE 3 Inter City Express – 3 rd generation<br />

IM Infrastructure Manager<br />

IS Impianto di Segnalamento (Italy)<br />

ISA Independent <strong>Safety</strong> Assessor<br />

IVW Inspectie Verkeer en Waterstaat (Dutch <strong>Safety</strong> Authority)<br />

IXL Interlocking<br />

KMAC Authentication Key<br />

KMC Key Management Centre<br />

KVB Contrôle de Vitesse par Balise (Balise Speed Control)<br />

LAV Línea de Alta Velocidad (High speed line)<br />

LC Level crossing<br />

LD Long Distance<br />

LEU Line side Electronic Unit<br />

LGV-Est Ligne à Grande Vitesse Est (French High Speed Line to the East)<br />

LTV Limitation Temporaire de Vitesse (Temporary Speed Limit)<br />

LZB Linien ZugBeeinflüssung (German ATP-system)<br />

MA Movement Authority<br />

MISTRAL<br />

Modules Informatiques de Signalisation, de Transmission et d’Alarmes<br />

(Signal, Transmission and Alarm IT Modules)<br />

MSC Mobile-services Switching Centre<br />

MTBF Mean Time Between Failures<br />

MTTR Mean Time To Repair<br />

NL The Netherlands<br />

NMBS Nationale Maatschappij der Belgische Spoorwegen (Belgian Railways)<br />

NoBo Notified Body<br />

NSA National <strong>Safety</strong> Authority<br />

NVP Nucleo Vitale Periferico (Italy)<br />

OBB Österreichische Bundesbahn (Austrian Railways)<br />

OBU On Board Unit<br />

ON Organisme Notifié (Notified Body)<br />

OS On Sight mode<br />

OSTI<br />

Organisme ou Service Technique Indépendant (Independent Technical<br />

Organisation or Service)<br />

PCS Posto Centrale Satellite (Italy)<br />

POS<br />

Paris-Ost-Frankreich-Süd-Deutschland (Paris – Eastern France – Southern<br />

Germany)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

159/161


PPF Posto Periferico Fisso (Italy)<br />

PRCI Poste a Relais a Commande Informatisée (France)<br />

PSC Project <strong>Safety</strong> Case<br />

PZB Punktförmige ZugBeeinflüssung (German ATP-system)<br />

QoS Quality <strong>of</strong> Service<br />

RA Risk <strong>Analysis</strong><br />

RAMS Reliability, Availability, Maintainability, <strong>Safety</strong><br />

RBC Radio Block Centre<br />

RENFE Red Nacional de Ferrocarriles Españoles (Spain)<br />

RFF Réseau Ferré de France (French Infrastructure Manager)<br />

RFI Rete Ferroviaria Italiana (Italian Infrastructure Manager)<br />

RFIG Red Ferroviaria de Interes General (Main Railway Network <strong>of</strong> Spain)<br />

RFU Recommendation For Use<br />

RTB Rilevatore Temperature Boccole (Hot Axle Box Detector)<br />

SAM Système d’Aide à la Maintenance (Maintenance Support System)<br />

SCC-AV<br />

Sistema Controllo e Comando - Alta Velocità (Control-Command System<br />

– High Speed)<br />

SCMT Sistema Controllo Marcia Treno (Italian ATP-system)<br />

SDT Sistema Distanziamento Treni (Italy)<br />

SEI Système d’Enclenchements Intégrés (France)<br />

SH SHunting mode<br />

SIST<br />

Sécurité des Infrastructures et des Systèmes de Transport (Infrastructure<br />

and Transport Systems <strong>Safety</strong>)<br />

SMB StopMerkBorden (Marker Boards)<br />

SNCB Société Nationale des Chemins de fer Belges (Belgian Railways)<br />

SNCF Société Nationale des Chemins de Fer (French Railways)<br />

SNCF IES<br />

SNCF IG.SF<br />

SNCF<br />

IG.T.ERTMS<br />

SNCF<br />

IG.T.SE<br />

SNCF Direction Déléguée Système d’Exploitation et Sécurité (SNCF<br />

Operational and <strong>Safety</strong> System Delegated Division)<br />

SNCF Direction de l’InGénierie - Signalisation Ferroviaire (SNCF<br />

Engineering Division – Rail Signals)<br />

SNCF direction de l’InGénierie – Projet ERTMS (SNCF Engineering<br />

Division – ERTMS Project)<br />

SNCF direction de l’InGénierie – Systèmes et Exploitation (SNCF<br />

Engineering Division – Systems and Operation)<br />

SR Staff Responsible mode<br />

SRAC <strong>Safety</strong> Related Application Condition<br />

SRFN Sécurité du Réseau Ferré National (France)<br />

SRS System Requirement Specification<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

160/161


SSB Sottosistema di Bordo (On Board assembly)<br />

SST Sottosistema di Terra (Track side assembly)<br />

STM Specific Transmission Module<br />

STTE<br />

Signalisations Temporaires propres à la Traction Electrique (Electronic<br />

Traction Temporary Signals)<br />

TAF Track Ahead Free<br />

TBL Transmission Balise Locomotive (Belgian ATP-system)<br />

THR Tolerable Hazard Rate<br />

TIRF Tolerable Individual Rate <strong>of</strong> Fatalities<br />

TIU Train Interface Unit<br />

TLC Telecommunication<br />

TOC Train Operating Company<br />

TSI Technical Specification for Interoperability<br />

TSI CR Technical Specification for Interoperability Conventional Rail system<br />

TSI HS Technical Specification for Interoperability High Speed Rail system<br />

TSI OPE<br />

Technical Specification for Interoperability <strong>of</strong> the subsystem Traffic<br />

Operation and Management<br />

TSR Temporary Speed Restriction<br />

TVM430 Track to Train Transmission 430 (French ATP-system)<br />

UN UNfitted mode<br />

UNISIG UNion Industry <strong>of</strong> SIGnaling<br />

WP Work Package<br />

ZN Zona Neutra (Neutral Zone in catenary system)<br />

Survey <strong>of</strong> safety approvals for the first ERTMS implementations<br />

<strong>WP2</strong> <strong>Final</strong> <strong>Report</strong> on <strong>Analysis</strong> <strong>of</strong> <strong>Safety</strong> <strong>Approval</strong> <strong>Process</strong> – 17 September 2007<br />

161/161

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!