Proposed - Massachusetts Water Resources Authority
Proposed - Massachusetts Water Resources Authority
Proposed - Massachusetts Water Resources Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Sub-phase<br />
Prison Point/Cottage<br />
Farm CSO<br />
Preliminary<br />
Design/Study<br />
Pump Station Rehab<br />
Preliminary<br />
Design/Study<br />
Prison Point Dry<br />
Weather Flow &<br />
Stripping Pump<br />
Improvements<br />
System Relief &<br />
Contingency Planning<br />
Study<br />
DeLauri Pump Station<br />
Electrical Room<br />
Cooling<br />
Caruso Pump Station<br />
Improvements<br />
Prison Point Pump and<br />
Gearbox Rebuilds<br />
Scope<br />
Preliminary design/study to replace and/or upgrade mechanical, electric, chemical feed,<br />
and instrumentation equipment. Additionally, need to replace diesel driven pumps with<br />
VFD electric pumps. This project will look to add more redundancy at Prison Point to<br />
ensure proper CSO discharge treatment. Preliminary design will be performed under a<br />
Technical Assistance As-Needed task order and is anticipated in early 2012. Final<br />
Design and Construction phases will be added to a future CIP cycle.<br />
Preliminary design/study for upgrades at Hayes, Hingham, Caruso, DeLauri Pump<br />
Stations, Wiggins-Castle Island Terminal, and the Somerville-Marginal CSO Facility.<br />
The project is to follow contract 7162, Pump Station and CSO Condition Assessment,<br />
which may result in other facility improvements. Upgrades to the facilities will ensure<br />
design output is met. Failure of a particular piece of equipment could lead to failure of<br />
another; such as failure of a grinder could negatively impact a pump. Upgraded<br />
facilities should result in fewer corrective maintenance calls. This is a system wide<br />
project designed to upgrade multiple facilities to ensure worker safety, equipment<br />
integrity, environmental protection, and ensure service is not interrupted. Design and<br />
Construction phases will be added to a future CIP cycle.<br />
This project is designed to determine the feasibility of replacing two dry weather<br />
pumps and adding a second wetwell stripping pump to ensure facility reliability and to<br />
pump down the wetwell at a faster rate.<br />
This project will investigate what can be done to avoid serious flooding issues.<br />
Increased capacity or controlled relief points must be identified in order to address<br />
flooding issues that occur during severe wet weather. Project will be designed to create<br />
increased capacity within the collection system in order to decrease SSO discharges.<br />
Scope may also include facility specific plans for a failure at MWRA facilities.<br />
During wet weather conditions when multiple pumps are operating, the Variable<br />
Frequency Drives overheat causing a reduction in pumping capacity. This problem is<br />
magnified during summer months, causing undesirable high temperatures in the<br />
electrical room. An HVAC evaluation was performed and recommendations made for<br />
additional electrical room cooling to eliminate VFD overheating and protect electrical<br />
equipment from damage. With the recent installation of a 1.5 megawatt wind turbine at<br />
the facility, security related improvements were recommended. A task order was<br />
executed in September 2011 to design the proposed HVAC and security related<br />
improvements.<br />
This project would replace the existing standby generator, HVAC system, and the fire<br />
detection system at the Caruso Pump Station. The standby generator is 20 years old<br />
and is one of a few existing generators of this type. The manufacturer is no longer<br />
making spare parts and there is only a limited quantity of available spare parts. The<br />
generator will be replaced with a newer model with readily available parts to ensure<br />
reliable back-up power. Technical Support evaluated the HVAC system and<br />
determined it was in need of replacement. Due to the age of the fire detection system,<br />
frequent problems, the fire protection system needs to be replaced. Design/CA/REI<br />
services will commence in 2012.<br />
Refurbishment of the Prison Point CSO Gearboxes based on an inspection report<br />
performed in May 2010 that indicated that the current gearbox condition could result in<br />
bearing failures. It is critical during major wet-weather events to have all four pumps<br />
operational which are driven by gearboxes to provide maximum station capacity and<br />
provide redundancy at this critical CSO facility.<br />
Interception and Pumping - 40