Essar Steel
Essar Steel
Essar Steel
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
History of HBI making at Essar
“A Brief Review of technological
developments”
1
ESSAR Group- A diversified multinational conglomerate
2
ESSAR Group- A diversified multinational conglomerate
3
ESSAR Group- A diversified multinational conglomerate
4
ESSAR Group- A diversified multinational conglomerate
5
Various iron making Routes at EStIL- Hazira
MIDREX
6 Modules
6.7 MTPA
COREX
2 Module
1.74 MTPA
BF-1.75 MTPA
6
History of HBI making at EStIL- Hazira
1988 Inception
1989-1990 Erection and commissioning
1991-1992 Expansion-I
1992-1999 Innovations and improvements
1999-2000 Breakthrough Concept of energy Saving
2005-2011 Expansion-II
7
Inception
• 1980-81- KORF Engineering of Germany led a consortium to construct a Direct
Reduced Iron (DRI) production facility, Nord Ferro Stahlwerke (NFW), at Emden,
Germany.
• 1981- NFW began early operations with two Midrex 400 series plants producing
DRI but due to bad market scenario Module 1 operated for approximately nine
months and Module 2 for approximately six months before the entire operation
was closed.
• 1982 to 1988- The plants were “mothballed”.
• 1988- In late 1988 Essar contracted with the court receivers in Emden Germany
for the purchase of the failed NFW direct reduction plants. Site preparation and
civil work was taken up in earnest at Hazira with the first column for the Module 1
furnace being erected in November 1988.
8
Erection and commissioning
• 1989- Hazira and Bombay became the
focus of the project with civil works
continuing and erection of structures at
Hazira. Hazira was the focus of construction
activities while procurement of new
equipment was headquartered in the
Bombay office. By the end of 1989 Module 1
was complete mechanically and being
commissioned in preparation for starting the
process.
9
Erection and commissioning
• 1990- The first months of 1990 saw a
flurry of activity as Module 1 was
prepared for “start-up”. After months of
around the clock activity Module 1
achieved production status on March 28
1990.
• Module 2 was brought online in
August 1990 completing the major part
of the project.
10
Expansion-I
• 1991- A process license was signed with the technology supplier, Midrex, for the Module 3 project.
Work began with the first furnace column being erected in January 1991.
• 1992- Mod 3 was commissioned with production beginning in August of 1992 – only 19 months after
erection of the first column.
Module 1 2 3
Capacity(MTPA) 0.44 0.44 0.44
Innovations and improvements
•1992- New hydrocarbon injection scheme installed in the furnaces to allow maximum Fe3C production
(In-house design)- Mod- 1,2,3.
•1992- Reformer design modified during construction to 336 tubes for a 16% increase in reformer
capacity (In-house design) - Mod- 3.
•1992- Liquid ring seal gas compressors replaced the screw type compressors – (In-house design)
Features both energy savings and lower maintenance. - Mod- 3.
•1992- Top gas duct redesigned to minimize oxide fines losses- (In-house design) - Mod- 3.
11
Innovations and improvements
• 1996- Turbo expander, a second hand plant was commissioned to take care of rich gas supply.
• 1997- For process monitoring, process software package ,called FIXDMACS started for better
Process evaluation with the help of historical data.
• 1997- Thin wall refractory liner installed in the furnace increasing the furnace ID from 5.0 meters to
5.15 meters – Midrex design.- Mod-1
• 1999- Reformer expanded from 288 tubes to 336 tubes providing 16% additional reforming capacity
(In-house design)- Mod-1
• 1999- Oval Top Gas duct replaced standard off-take providing an additional 0.3 meters of reduction
zone height – Midrex design- Mod-1,2.
• 1999- Reformed Gas cooler was replaced by modified temperature control system – Midrex concept
and (In-house design)- Mod-1,2,3.
• 1999- Oxygen injection equipment installed to allow operation at elevated reduction temperatures to
maximize production – Midrex concept and (In-house design). Mod-1,2,3.
• 1999- Naphtha injection to the furnace cone trails were carried out. The concept was a success and
the other modules have been similarly equipped. At this time naphtha can be utilized as a natural gas
substitute in all three modules.
• 1999- An additional set of heat recovery bundles were designed in house and placed in service to .
improve energy efficiency (In-house design). Mod-2
12
Breakthrough Concept of energy Saving
• 1999-2000- Module 3 – Hot DRI was taken from the furnace discharge upstream of the briquetters
for “hot charging” to an EAF. The trials were very successful and the facility was built into the other two
modules.
• Hot DRI (HDRI) development continues to be the top priority project at Essar
•Energy saving at EAF (@ 100 to 120 KWH/ton of liquid steel).
•Zero %age moisture as against 1.5 to 2 % in HBI.
•Reduction in briquetting system maintenance expenses.
45 T Container
13
Expansion-II
• 2003 - Mod-4 erection started
• 2004- Mod-4 commissioned in July
• Capacity- 1MTPA
• Modified design of heat recovery system owing to
better heat utilization.
• 2005 - Mod-5 erection started
• 2006- Mod-5 commissioned in October.
• Capacity- 1.6 MTPA
• Equipped with VPSA system to help in
consuming COREX gas
Mod-4
Mod-5
14
Expansion-II
• 2008 - Mod-6 erection started
• 2010- Mod-6 commissioned in November.
• Capacity- 1.7 MTPA (CDRI)
• Equipped with VPSA system to help in
consuming COREX gas
• 2009 - VPSA erection started
• 2011- VPSA commissioned in November.
• Purpose -- Designed for removal of CO2 and
H2O from Top Gas Fuel.
• Capacity --- 1,35,000 Nm3/Hr
• Power Consumption – 55 Kwh/t
Mod-6
VPSA
15
Production across the Years
16
Major cost drivers across the years
17
Product quality across the years- Metallization
18
Product quality across the years- Carbon
19
Highlights and way forward
• Crossed 50Mmt of production in FY 12-13.
• Startup of 19MW power generation facility by utilizing flue gas waste
heat of MIDREX plant.
• Process tuned for safe use of BF grade pellets in our furnace.
• Fine tuning the operation of VPSA to optimize it’s usage with the
help of in-house talents and developed concepts.
• Reduction in natural gas consumption per ton after usage of COREX
gas In reformer.
• Effective contribution towards ZERO waste policy of EStIL
20
THANK YOU
21