CHANGEOVER<br />

THE OPERATION WITH TOWED TRAINS<br />

The operation with towed trains takes the following steps :<br />

1. Arrival of the train, detaching and parking tractor head.<br />

6 minutes.<br />

2. Passing of the first shaft through the changeover installation,<br />

normally using the force of gravity.<br />

3 minutes.<br />

3. Attaching the tractor head on the other side.<br />

4 minutes.<br />

4. Pulling the rest of the train through the changeover<br />

installation.<br />

2 minutes.<br />

Total used time<br />

15 minutes<br />

16<br />