20.11.2012 Views

MEMORANDUM FOR CLAIMANT

MEMORANDUM FOR CLAIMANT

MEMORANDUM FOR CLAIMANT

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Rheinische Friedrich-Wilhelms-Universität Bonn<br />

the refusal was meant to be definite. Thus, the statement RESPONDENT made in its fax of<br />

2 May 2001 can reasonably be interpreted only as an express and definite refusal to perform<br />

any obligation under the contract.<br />

C. RESPONDENT was not entitled to refuse performance<br />

79. Since the contract concluded on 3 April 2001 contained a 4% discount, RESPONDENT<br />

had no right to make its performance dependent on an 8% discount. Furthermore,<br />

<strong>CLAIMANT</strong> had complied with all of its own obligations under the contract until receiving<br />

RESPONDENT’s fax of 2 May 2001. There can be no doubt that <strong>CLAIMANT</strong> was ready,<br />

willing and able to perform its obligations, and that it would have done so absent<br />

RESPONDENT’s anticipatory repudiation. <strong>CLAIMANT</strong> had already booked space for<br />

shipment of the first installment [<strong>CLAIMANT</strong>’s Exhibits No. 6, No. 9]. Thus, there was neither<br />

breach of contract nor any other misconduct on behalf of <strong>CLAIMANT</strong> that could have given<br />

RESPONDENT a right to avoid the contract according to Art. 49 CISG. Likewise,<br />

RESPONDENT had no right to claim that the contract was invalid for any reason under the<br />

domestic law of Equatoriana, which applies to the contract as far as its validity is concerned,<br />

Art. 4(a) CISG. In particular, the domestic law of Equatoriana does not provide for invalidity<br />

of the contract under theories of mistake or otherwise [Procedural Order No. 2, Clarification<br />

No. 36]. Consequently, RESPONDENT had no right to repudiate the contract or to refuse<br />

performance of its obligations respectively. Thus, its fax of 2 May 2001 constituted a breach<br />

of contract.<br />

VII. EQUAFILM is entitled to claim damages for lost<br />

profit in the amount of $ 575,477.98<br />

80. As a consequence of RESPONDENT’s breach, <strong>CLAIMANT</strong> is entitled to claim damages<br />

(A.). Since the damages have to be calculated according to Art. 74 CISG, <strong>CLAIMANT</strong> has<br />

the right to recover its loss of profit, i.e. $ 575,477.98 (B.). RESPONDENT could foresee that<br />

it would cause such damages by its repudiation of the contract (C.). Since <strong>CLAIMANT</strong> was<br />

in a lost volume situation, it did not fail to take measures to mitigate its loss (D.). Thus,<br />

<strong>CLAIMANT</strong> is entitled to claim damages in the amount of $ 575,477.98.<br />

28

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!