27.11.2012 Views

Author: Professor, Dr. Dietrich Stein - TrenchlessOnline

Author: Professor, Dr. Dietrich Stein - TrenchlessOnline

Author: Professor, Dr. Dietrich Stein - TrenchlessOnline

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

INTERNATIONAL<br />

A pear-shape, brick sewer, 1,800 x 2,250-mm I.D., was rehabbed with<br />

the Trolining Double-System.<br />

was limited to 85 m in the past, the mentioned distances<br />

required additional efforts from both Trolining’s liner manufacturer<br />

and the installation crew. Trolining engineers and<br />

site experts tackled the situation and presented the solution<br />

after a number of technical meetings and process improvements.<br />

Insertion of the 2.5-ton weighting liners occurred from<br />

the intermediate manhole, which separated the 210 m of<br />

egg-shape pipe into 103 and 107 m, both into the up-stream<br />

and downstream direction.Large triangle stands were placed<br />

next to the insertion pit to hang up the liner coils. For drawing<br />

the liners into the pipe,diversion rollers had to be placed<br />

right above the manhole chamber. After insertion of both<br />

studded liners, the resulting annulus was sealed by manual<br />

extrusion welding. Inflatable egg-shape packers were then<br />

used to plug the liner-package at both ends and water was<br />

fed in to build up a defined hydrostatic pressure. Special<br />

attention had to be given to the plug bracing — with a water<br />

column of 8 m (equal to 11.6 psi back pressure) and a crosssectional<br />

area of 2.45 sq m.An equivalent horizontal force of<br />

approximate 20 tons had to be taken by the construction<br />

that held the plugs in place.<br />

The 103- and the 107-m long pipe sections were<br />

rehabbed separately. Grouting of both occurred with the<br />

Trolining-specific mixing technology. Three standard mixing<br />

units were employed to prepare the injection grout.<br />

The Double System’s outer annular void space was filled<br />

first, needing approximately 1.5 hours for completion.The<br />

inner annulus could then be grouted within just one hour.<br />

After an additional 16 hours of curing, the high-strength<br />

grout attained the necessary short-term strength necessary<br />

for releasing the inside pressure from the lining system.<br />

Right afterward, the incoming house connections could be<br />

re-opened and connected.<br />

Jens Kirste is with technical sales at Trolining GmbH, which<br />

is headquartered in Troisdorf, Germany.<br />

Circle 44 on reader service card. Circle 45 on reader service card.<br />

50 TRENCHLESS TECHNOLOGY September 2007 www.trenchlessonline.com

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!