27.11.2012 Views

Author: Professor, Dr. Dietrich Stein - TrenchlessOnline

Author: Professor, Dr. Dietrich Stein - TrenchlessOnline

Author: Professor, Dr. Dietrich Stein - TrenchlessOnline

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

INTERNATIONAL<br />

Motorized Small Boring Units Power<br />

Through Rock on U.K. Pipeline By Desiree Willis<br />

One of the U.K.’s largest pipeline projects is getting<br />

a boost from some high-powered tunneling<br />

machines. The Milford Haven Gas Connection<br />

Project — a 300-km long behemoth stretching<br />

across South Wales, United Kingdom — will require more<br />

than 110 crossings located under roads, major rivers and<br />

environmentally sensitive areas.<br />

Local contractor B&W Tunnelling is currently excavating<br />

24 hard rock crossings ranging from 20 to 80 m in length<br />

for Phase II of the project. B&W is utilizing five hard rock<br />

boring machines, known as small boring units (SBUs), to<br />

excavate the crossings in record time and with minimum<br />

environmental impact.<br />

B&W Tunnelling opted to use two 1.2-m motorized SBUs for the four<br />

longest crossings due to site set up and bore specifications.<br />

Project Overview<br />

The Milford Haven Pipeline will support the United<br />

Kingdom’s increasing requirements for imported gas.<br />

Liquefied natural gas (LNG) will be imported from international<br />

sources to two LNG terminals located in Milford<br />

Haven.Tankers will offload the LNG, where it will then be<br />

converted back to its gaseous form at the terminals before<br />

entering the pipeline. By 2009, the pipeline will transport<br />

up to 20 percent of the U.K.’s natural gas for owner<br />

National Grid.<br />

Constructed in two phases, work began on the pipeline<br />

in early 2006. Phase I involved a 120-km long stretch from<br />

the towns of Milford Haven to Aberdulais. B&W Tunnelling<br />

was sub-contracted by the NACAP/Land & Marine JV to<br />

excavate a total of 38 crossings using SBU technology.As of<br />

August 2007, Phase I is nearly complete, with more than 95<br />

percent of the pipeline in place.<br />

Phase II of the project will extend the pipeline another<br />

185 km from Felindre to Tirley in Gloucestershire. B&W<br />

signed the contract for this phase in December 2006, which<br />

consists of 24 crossings to be bored with SBUs under roadways<br />

and nearly a dozen rivers — 57 trenchless crossings in<br />

total. Many of these crossings are line and grade critical,<br />

requiring careful machine setup and continuous monitoring.<br />

The large number of crossings is one way that general<br />

contractor NACAP/Land & Marine is working to maintain<br />

environmentally sensitive areas. Tunneling under features<br />

such as rivers and woodland minimizes disturbances to the<br />

indigenous flora and fauna found in the region. Vibration<br />

and movement are being closely monitored, and the working<br />

area is restricted at several points to minimize disruption<br />

of the surrounding landscape.<br />

Machine Selection<br />

Two 1.2-m diameter SBU-As are being used for a total of 20<br />

crossings on Phase II of the pipeline project.The machines are<br />

a type of rock boring attachment that utilizes a full-face auger<br />

to excavate crossings for utility installations.The machine is<br />

welded to the lead casing and an auger boring machine (ABM)<br />

provides both torque and forward thrust to the cutting head.<br />

Disc cutters allow the machine to excavate medium to<br />

hard rock from 25 to more than 170 MPa UCS. In mixed<br />

ground conditions, another type of cutterhead can be used.<br />

This cutterhead uses disc cutters, two-row carbide cutters<br />

and carbide cutter bits with larger muck openings to<br />

accommodate soft ground and boulders. The SBU-A, available<br />

in diameters from 600 mm to 1.8 m, is typically used<br />

on drives less than 100 m in length.<br />

Boring for Accuracy<br />

B&W Tunnelling opted to use two 1.2-m motorized SBUs<br />

for the four longest crossings due to the site setup and bore<br />

specifications.“We needed an increased degree of accuracy<br />

given the shaft depths and the line and grade of the crossings,<br />

so we felt the most confident with the SBU-M,” said<br />

Steve Williams, managing director of B&W Tunnelling.<br />

The motorized SBU is a manned-entry, hard rock boring<br />

machine used for longer bores (exceeding 100 m) and for lineand<br />

grade-critical crossings.The machine is used in conjunction<br />

with a standard auger boring machine and is welded to<br />

the lead casing in the same fashion as SBU-As.While both SBU-<br />

As and SBU-Ms are used with ABMs, the SBU-M utilizes a small<br />

invert auger for spoils removal rather than a full-face auger.<br />

The cutterhead is supported by a heavy-duty bearing<br />

housing assembly, which is driven by either a hydraulic<br />

motor or a water-cooled, variable speed electric motor.The<br />

motor provides torque to the drive train and contains a<br />

torque limiter to reduce cutterhead jams in fractured or broken<br />

ground conditions. Power cables in 30-m lengths run<br />

from the machine connection box to a surface-mounted<br />

electrical disconnect cabinet.<br />

Available in diameters from 1.2 to 2 m, the SBU-M can be<br />

steered from an operator’s console inside the machine’s<br />

rear shield. Articulation cylinders and manually adjustable<br />

52 TRENCHLESS TECHNOLOGY September 2007 www.trenchlessonline.com

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!