HANDOUT for the Regular <strong>Board</strong> Meeting of April 13, 2010<br />

FINANCIAL IMPACT:<br />

On June 9, 2009, the <strong>Board</strong> approved a budget of $801,000 for phase one of the <strong>Catholic</strong><br />

Central boiler replacement/HVAC upgrade project to be funded from the GPL Stage 3<br />

(GPL3) allocation of $5,249,917. At this same meeting, the <strong>Board</strong> further approved a<br />

budget of $1,100,000 for phase two this project to be funded from the GPL Stage 4 (GPL4)<br />

allocation of $2,140,427. The total approved project budget was $1,901,000.<br />

The cost projection for the boiler system replacement at <strong>Catholic</strong> Central is now estimated<br />

at $2.5M, an increase of $599,000 from the original $1.901M <strong>board</strong> approved budget. The<br />

cost estimate has increased due to a change in assumptions inherent in the original project<br />

budget. The $1.901M original budget assumed current steam radiators could be used,<br />

however an engineering <strong>report</strong> has subsequently determined that they cannot be used, and<br />

as a result new radiators will need to be installed.<br />

In addition to the GPL3 and GPL4 allocations, the Ministry of Education announced in April<br />

2009 a two year funding program for Energy Efficiency projects. WECDSB has been<br />

allocated $1,728,789 in 2009-10 and $2,330,455 in 2010-11 under this program, for a total<br />

of $4,059,244 over two years. These Energy Efficiency funds are divided into the following<br />

three categories:<br />

2009-10 2010-11 Total<br />

Operating Efficiency $ 258,056 $ 0 $ 258,056<br />

Small Equipment 360,323 412,474 772,797<br />

Renewal of Building Components 1,110,410 1,917,981 3,028,391<br />

TOTAL $1,728,789 $2,330,455 $4,059,244<br />

As charges to the <strong>Catholic</strong> Central boiler project are consistent with the mandate of the<br />

Renewal of Building Components Energy Efficiency program, Administration recommends<br />

that the $2.5M project be funded, in part, from this source leaving available room in the GPL<br />

program to address other, less specific, urgent and high renewal needs and improvements<br />

to school facilities.<br />

A <strong>report</strong> to the <strong>Board</strong> detailing the recommended list of projects to fully expend the Energy<br />

Efficiency allocations listed above is forthcoming. To date, $1,222,881 of the total<br />

$3,028,391 of Renewal of Building Components allocation has been committed, leaving<br />

$1,805,510 available for the <strong>Catholic</strong> Central boiler project. Administration therefore<br />

recommends the project be funded as follows:<br />

Funded from 2010-11 Renewal of Building Component Allocation $1,805,510<br />

Funded from 2009-10 GPL3 Allocation 694,490<br />

Total project budget $2,500,000<br />

TIMELINES:<br />

The majority of the project is to be done in the summer with completion in October, 2010<br />

APPENDICES:<br />

None<br />

REPORT REVIEWED BY:<br />

EXECUTIVE COUNCIL Review Date: April 12, 2010<br />

SUPERINTEDENT Approval Date: April 10, 2010<br />

DIRECTOR OF EDUCATION: Approval Date: April 13, 2010<br />

(Page 2 of 2)<br />

WALK-ON Agenda Item 12e<br />

Page 2 of 2