Government Contractors<br />
EVMS requirement<br />
� DoD recommends a project value threshold of $20M below which a full EVMS does not<br />
need to be used. Projects between $20M and $50M must use EVMS and above $50M<br />
the EVMS must be formally validated.<br />
� Office of Management and Budget (OMB) said that EVMS should be used on “All new<br />
major IT projects, ongoing major IT developmental projects, and high risk projects.”<br />
� OMB decided to leave thresholds to the discretion of the agencies<br />
� “EVMS application should be based on the particular agency facts and circumstances rather<br />
than specifying a threshold in the FAR. In accordance with OMB Circular A-11, Part 7, agencies<br />
have the authority to establish dollar thresholds and EVMS applicability criteria.”<br />
� NASA has adopted the same $20M / $50M thresholds as the DoD. Other agencies have<br />
specified the following:<br />
GSA and DOE: $20M<br />
FAA: $10M<br />
EPA: $5M<br />
DoT: $6M<br />
DoEd: $6M with a ‘lighter’ version