28 Appendix 6<br />
project area. Viet Nam will ensure that baseline data is collected within 6 months of the<br />
Effective Date, with a second survey to be conducted upon Project completion and a third<br />
survey to be conducted 3 years after Project completion to establish Project impact.<br />
F. Reporting<br />
75. HCMC PC, through MAUR, will: (i) collect and consolidate all Project progress reports,<br />
site reports, technical and financial reports and submit them to ADB; (ii) review and submit<br />
quarterly progress reports, a baseline Project evaluation report and an overall Project<br />
completion report; and (iii) review and submit other reports as may be reasonably requested by<br />
ADB. Quarterly reports will include updated implementation, financial and procurement-related<br />
information. Quarterly reports shall be submitted to ADB within 30 days of the end of each<br />
quarter.<br />
76. Within 6 months of Project completion, HCMC PC, through MAUR, will submit to ADB, a<br />
Project completion report providing a detailed evaluation of Project design, costs, performance<br />
of Project consultants, and contractors, the performance indicators described above, social and<br />
environmental impacts, economic and financial assessments, and such other information as<br />
may be requested by ADB.