12.07.2015 Views

Transmission Network Performance Report 2005 - National Grid

Transmission Network Performance Report 2005 - National Grid

Transmission Network Performance Report 2005 - National Grid

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

FY<strong>2005</strong><strong>Transmission</strong> Reliability1.10 System Availability• Availability is calculated based on the total length of planned, unplanned,and disturbance durations and the total hours the system or circuitshould have been available in a given period. The availability of thesystem measures the increased reliability of the system and is importantin case of an 'unplanned' event. High availability provides feweropportunities and less compromising situations in the event of failurewhen back up (redundant circuits) are in service (available). Thepotential risk is higher for line and customer related outages when allcircuits are not available.• In order to maintain a high level of Availability, circuits are returned toservice as quickly as possible in the event of unplanned disturbances. Inthe case of planned outages which require work over several days,circuits are returned to service at the end of each work day.• The value of System Availability for FY<strong>2005</strong> 98.63 for New England and98.60 for New York. The following figure indicates the availability of theLoad, Bulk and the <strong>Transmission</strong> System in FY<strong>2005</strong>.Figure 1-8: Bulk, Load and System Availability for FY<strong>2005</strong>100.00%99.00%98.00%97.00%96.00%95.00%94.00%Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb MarLoad Bulk System System FYTD<strong>National</strong> <strong>Grid</strong> <strong>Performance</strong> <strong>Report</strong> 11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!