Update on Clean Fuels Projects<br />

� Ultra Low Sulfur Diesel Plant (ULSD) 88.0 % Completion Expected Commissioning Date October <strong>2012</strong><br />

� Gasoline Optimization Project (GOP) 99.4 % Completion Expected Commissioning Date End Feb. <strong>2012</strong><br />

GOP ULSD<br />

US$ MM Production<br />

Isomerisation Plant 88.9 May 2009<br />

CCR Plant 228.6 March 2010<br />

Acid/Alkylation Plant 349 March <strong>2012</strong><br />

FCCU 457 March <strong>2012</strong><br />

Utilities and Offsites 278_ March <strong>2012</strong><br />

Total Project Cost 1,480<br />

Challenges<br />

� Cost reimbursable contract<br />

� Contractors performance<br />

� Working on live plant and many unknowns<br />

� Design issues<br />

� Quality issues<br />

� Project cost – US$ 355 MM<br />

� Construction five months behind schedule<br />

Challenges/Action taken<br />

� Due to late 3-D model reviews, piping design<br />

and deliveries were delayed which has delayed<br />

piping installation<br />

� Challenges with providing the OSBL utilities and<br />

services in time to support ISBL turnover. We are<br />

actively looking for resources and work-around<br />

solutions.<br />

� Setting up the resources and processes to<br />

accommodate the volume of hydro-tests<br />

packages and walk downs expected.<br />

� OSBL/ISBL Staffing – suitable personnel being<br />

identified from refinery/contractors<br />

33