12.07.2015 Views

Final report for One North East And NEPIC 21/12/10 - The Carbon ...

Final report for One North East And NEPIC 21/12/10 - The Carbon ...

Final report for One North East And NEPIC 21/12/10 - The Carbon ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

POLICY & REGULATORYTECHNICAL & OPERATIONALECONOMIC & MARKET<strong>The</strong> case <strong>for</strong> a Tees CCS network<strong>Final</strong> Reportexpected lifetime. As it is extremely unlikely that insurance <strong>for</strong> technology failure will beavailable, commercial lenders will there<strong>for</strong>e require equipment vendors to stake theirreputation on providing per<strong>for</strong>mance guarantees <strong>for</strong> equipment. This will ensure that it is inthe vendor‟s interest to overcome any operational problems. To the best of our knowledge,few if any of these conditions are in place at present.A further element to consider <strong>for</strong> shared infrastructure is the risk of change of ownership.This could affect incumbent contracts, and potentially prevent access to the system. Useof non-disturbance agreements will typically be required to manage this risk.Table 6 summarises some of the key project risks associated with developing the CCSnetwork and the range of potential approaches to managing them. <strong>The</strong> table shows thatwhile many of the risk management options can be dealt with primarily by the privatesector (through various commercial and legal arrangements typical of large multi-partyinvestment projects), other areas of risk will likely require government policy and regulatorysupport. In this context, it is important to note that some CCS risks are viewed by investorsas potential „deal-breakers‟ unless addressed by the policy framework (e.g. EU Allowanceprice, long-term liability) whereas others can be managed through well understood existingapproaches (CO 2 supply and demand risk, tariff arrangements).Table 6 Summary of project risk and risk management optionsKey risk factorCommercial & legal (private sector)Risk management approachPolicy instruments (public sector)Uncertain CCS policy framework Contingency planning and insurance Long-term policy committmentsUncertain CCS regulatory framework Contingency planning and insurance Robust regulatory regime <strong>for</strong> CCSInsufficient EOR incentives - Fiscal support <strong>for</strong> tertiary O&G productionLong-term liability arrangements - Arrangements acceptable to CCS operatorsPlanning process challenges Coordinated approach to planning procedures -Lack of public acceptance Communicating benefits of CCS Communicating benefits of CCS"First of a kind" technology riskEquipment vendor per<strong>for</strong>mace guaranteesEPC contractor insuranceGovernment guaranteesDisruption of plant operation Contingency planning and insurance Compensation <strong>for</strong> loss of outputNon-supply risk Long-term supply contracts Government guaranteesNon-demand risk Long-term supply contracts Government off-take agreementsPhasing and sequencing risksProject-on-project riskLoss of CO 2 containmentTemporary tanker storage in initial stagesCompletion guarantees / arrangementsCommerical and legal insulation fromcounterparty risk and project failture (nondisturbanceclauses, completion guaranteesetc)Financial provision arrangements / liabilitytransfer--Financial provision arrangements / liabilitytransferProject cost overruns Completion guarantees Government guaranteesLow carbon price & price volatilityEUA price hedging instrumentsGovernment carbon price guarantees (pricefloors, contract <strong>for</strong> differences etc)Increased stringency of EU ETS capsEconomics of EOR - Fiscal support <strong>for</strong> tertiary O&G productionEnergy price increases Energy price hedging instruments -Sector-specific cost risks Contingency planning and insurance Compensation <strong>for</strong> loss of outputRevenue risk (cost recovery) Robust cost recovery and tariff arrangements Government guaranteesBarriers to markey entry and exitNetwork capacity rights with secondarymarketThird party access arrangementsGovernment, if it wishes to leverage private finance into CCS projects, clearly needs toprovide the required framework <strong>for</strong> addressing those risks that are genuinely46

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!