13.07.2015 Views

final report : reconnaissance study of energy requirements and ...

final report : reconnaissance study of energy requirements and ...

final report : reconnaissance study of energy requirements and ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

,--Cr~~~~' "===" ~-''''''==:=--'''-====-"===:="'-"'==='=""-"=='=' '_~' __ -=-=' ___ ==:"'=='_ ~~==~=--", - '-_'" ,,-."----I •!i \FINAL REPORT :RECONNAISSANCE STUDY OFENERGY REQUIREMENTSAND ALTERNATIVESFOR CORDOVAPREPARED FOR:II THE CITY OF CORDOVAANDSTATE OF ALASKAALASKA POWER AUTHORITYPREPARED BY :,~ 1 ~O!'~O~K~D~Jci~A~Y ALE N GIN E E R I N G COM PAN Y, INC.~ ROBERT W. RETHERFORD ASSOCIATES DIVISIONANCHORAGE, ALASKAJUNE 1981


ALASKA I-OWEn. AUTUOUITYRECONNAISSANCE STUDYOFEl'-lERGY RmUIREMENrS AND ALTERNATIVESFURCOROOVAFINDINGS AND RE'.CC:MMENDATIONSBA.CKGROUNDThis <strong>reconnaissance</strong> <strong>study</strong> addresses the total <strong>energy</strong> needs <strong>of</strong> the peoplein Cordova. Prior to this <strong>report</strong> most studies evaluated a specifical ternati ve to produce <strong>energy</strong>. An exception was an overall <strong>study</strong> <strong>of</strong> the<strong>energy</strong> <strong>requirements</strong> <strong>of</strong> Cordova conducted by Marks Engineering forCordova Public utilities in 1977. That <strong>report</strong> recommended adiesel-hydro combination to meet Cordova's needs if the Power Creekhydroelectric potential was feasible. Subsequently, the Corps <strong>of</strong>Engineers began a <strong>study</strong> <strong>of</strong> the alternatives in the Cordova area whichaddresses Power Creek specifically. Through the Corps' geologicalinvestigations, it has been found that only a run-<strong>of</strong>-river plant appearsfeasible with the <strong>final</strong> results <strong>of</strong> their <strong>study</strong> due in late spring.Cordova Electric Cooperative cwns, operates, <strong>and</strong> maintains the poNersystem in U1e Cordova area which consists <strong>of</strong> five diesel engine drivengenerators totalling 8450 Kw:1 @ 600 Kw 1 @ 1950 Kw1 @ 750 Kw 1 @ 2650 Kw1 @ 2500 Kw (New, installed 1979)Sorre <strong>of</strong> the units are in poor condition <strong>and</strong> are considered to beunreliable. After taking account <strong>of</strong> reserve <strong>requirements</strong> <strong>and</strong> unreliableunits, the capacity available to neet peak load <strong>requirements</strong> is about5000 Kw.In 1980 the peak power dem<strong>and</strong> was approximately 3400 Kw <strong>and</strong> the total<strong>energy</strong> dem<strong>and</strong> was about 16,400 MNH. The cost <strong>of</strong> diesel is approxirrately$1. 05/gallon with approximate cost to the residential consumer presentlyat $0.23/kwh.FINDINGSApproxlina.tely 20 percent <strong>of</strong> the total <strong>energy</strong> used in Cordova goes towardthe generation <strong>of</strong> electrical <strong>energy</strong>. About 26 percent <strong>of</strong> the total<strong>energy</strong> is used for space heating. In the production <strong>of</strong> electrical<strong>energy</strong>, at least two-thirds <strong>of</strong> the <strong>energy</strong> potent.ial is lost in the form<strong>of</strong> waste heat.The projected electrical peak denBnd for 1985 ranges between 5,700 kw<strong>and</strong> 4100 kw. The respective <strong>energy</strong> dem<strong>and</strong>s for 1985 are forecast atbetween 26,300 MVH <strong>and</strong> 18,500 MiH. The range <strong>of</strong> peak dem<strong>and</strong> for theyear 2000 is 8,000 kw to 16,500 kw. The <strong>energy</strong> dem<strong>and</strong> for the year 2000


...is projected to range between 27 ,800 ~'WH <strong>and</strong> 80 ,OOO~. These figuresexclude space heating <strong>requirements</strong> which, if provided by electrical<strong>energy</strong>, would add another 140 ,000 ~ required in the year 2000.Hydroelectric projects, coal-fired generation, transmissioninterconnection, waste heat utilization <strong>and</strong> cogeneration are among thepower production alternatives available to Cordova.The Silver Lake Hydroelectric developrent alternative would be the lastmajor construction during the planning period <strong>and</strong> would be expected totie into the transmission line in 1991. The follONing table ShONS thetotal discounted cost <strong>of</strong> each plan based on a 50 year period <strong>of</strong> analysis(from initial operation <strong>of</strong> the last major developrent) <strong>and</strong> FY 81 PONerAuthority evaluation parameters. The table summarizes the scheduling<strong>and</strong> cost implications <strong>of</strong> the most viable alternative plans.mSTS OF ALTERNATE DEVElOPMENT PlANSAlternate PlanDiesel Generation - Base CaseCoal-fired Generation -Carbon CreekDiesel Generation w/waste heatCoal-fired Generation - Healy CoalIntertie/Valdez surplusSilver LakePower Creek, Crater Lakew/ supplemental dieselEar liest Year<strong>of</strong> Operation198119831983198319831983AccumulatedPresent Worth168,527,000165,634,000148,968,00093,065,00089,297,00061,720,000The surplus <strong>energy</strong> cost from the Valdez area was recomputed <strong>and</strong> found tobe in the range <strong>of</strong> 4-5 cents per KwH. This cost is somewhat less thanthe 6.25 cents per KwH used by the consultant. The difference is notsufficient to alter the rank order <strong>of</strong> the alternative plans.TechnicalAll <strong>of</strong> the alternatives evaluated appear to be technically feasible.The only area <strong>of</strong> concern is the transmission line between Cordova <strong>and</strong>Valdez. There are three alternative routes which were proposed;(a) submarine cable, (b) along the old EI Paso gas line route, (c) alongCopper River. Each <strong>of</strong> the alternatives would entail a certain degree <strong>of</strong>risk <strong>and</strong> there is some question as to the reliability, all <strong>of</strong> which willimpact the cost.'TWo newer rrethods <strong>of</strong> transmission are the Single Wire Ground Return(SWGR) <strong>and</strong> three phase transmission with the utilization <strong>of</strong> long spanswithout clearings <strong>and</strong> with helicopter placerrent <strong>of</strong> towers <strong>and</strong>conductors. The SWGR has been utilized sarewhat in Alaska <strong>and</strong> much morein Europe. Three phase transmission without clearing has been utilizedrecently south <strong>of</strong> Anchorage <strong>and</strong> poses f~er environrrental problems thanthe conventional three phase transmission line with clearing. This type<strong>of</strong> construction may be suitable for the overl<strong>and</strong> routes.


"-The development <strong>of</strong> a coal fired generating plant in the Cordova area hasthe potential <strong>of</strong> being econanically feasible utilizing Healy Coal. Itmay require a minimum <strong>of</strong> one year <strong>of</strong> air quality data prior to anyconstruction.EnvironrrentalThe coal alternative would probably have the most potential forenvironrrental degradation. Along with air quality constraints, therewould also be the need to treat the water which would run <strong>of</strong>f thestockpiled coal. Although these concerns exist, the technology isavailable to protect the environrrent <strong>and</strong> still provide <strong>energy</strong> toCordova.EconanicDiesel generation appears to be the only immediate alternative toproduce <strong>energy</strong> for Cordova. The cost <strong>of</strong> continuing with dieselgeneration is expensive <strong>and</strong> will in all probability continue toescalate. The developrent <strong>of</strong> a hydroelectric plant, coal plant, <strong>and</strong>/oran intertie with Valdez could produce <strong>energy</strong> in the long term forCordova at lesser cost.RFX:.'(M.1ENDATIONSThe Power Authority recommends that a detailed feasibility analysis beconducted to formulate a preferred power supply plan. This analysiswould include the following alternatives:1. Coal-fired generating plant utilizing the least cost coalsource,2. Power Creek run-<strong>of</strong>-river hydroelectric plant, <strong>and</strong>3. An intertie betwee.n the cornnuni ties <strong>of</strong> Cordova <strong>and</strong> Valdez withthe option <strong>of</strong> developing hydroelectric sites along the line.The alternatives should be evaluated in a manner which will identify thepreferred sequence <strong>of</strong> development required to meet the Cordova <strong>energy</strong>dem<strong>and</strong>s for the next twenty years.Eric P. YouldExecutive Director(" \;;, \ ~.0Date: _ \ . \. ,_",A.\


FINAL REPORT:RECONNAISSANCE STUDY OFENERGY REQUIREMENTS AND ALTERNATIVESFOR CORDOVAPresented to:THE CITY OF CORDOVAANDSTATE OF ALASKAALASKA POWER AUTHORITYPrepared by:ROBERT W. RETHERFORD ASSOCIATESDIVISION OF INTERNATIONAL ENGINEERING COMPANY,CONSULTING ENGINEERSANCHORAGE, ALASKAINC.June 1981


PREFACE...This <strong>reconnaissance</strong> <strong>study</strong> has been conducted by Robert W. RetherfordAssoci ates to i dent ify the <strong>energy</strong> requi rement needs <strong>of</strong> the City <strong>of</strong>Cordova, Alaska, <strong>and</strong> to formulate <strong>and</strong> analyze alternative <strong>energy</strong> projectsreasonably expected to be available to Cordova through the year 2000.The format <strong>of</strong> this <strong>study</strong> <strong>report</strong> is intended to conform with Alaska PowerAuthority Reconnaissance Study Regulations <strong>and</strong> incorporates comments <strong>of</strong>individuals <strong>and</strong> agencies that reviewed the February 1981 draft version<strong>of</strong> thi s <strong>report</strong>.iAPA25/jl


•-..-ACKNOWLEDGEMENTSWe would like to express our thanks to the citizens <strong>of</strong> the City <strong>of</strong>Cordova, in both <strong>of</strong>ficial <strong>and</strong> private capacities, for their valuableinputs <strong>and</strong> support <strong>of</strong> this work. The comments <strong>of</strong> reviewers <strong>of</strong> the draft<strong>report</strong> have helped significantly in assuring relevance to Cordova'sneeds.Information on coal, oil, gas, <strong>and</strong> geothermal resources was provided byC. C. Hawley <strong>and</strong> Associates.....-..........-•...•..APA25/j2ii•-


TABLE OF CONTENTSSECTIONSPAGEI. INTRODUCTION AND SUMMARYII. ENERGY BALANCEIII. ENERGY REQUIREMENTSIV. ENERGY RESOURCE ALTERNATIVESV. ENERGY TECHNOLOGY ALTERNATIVESVI. EVALUATION OF FEASIBILITY OF ENERGY ALTERNATIVESVII. CONCLUSIONS AND RECOMMENDATIONS1-1II-I111-1IV-lV-IVI-lVII-lAPPENDICESA. ENERGY BALANCE AND REQUIREMENTS - DETAILSB. RESOURCE COSTSC. ENERGY TECHNOLOGY PROFILESD. ECONOMIC ANALYSES - DETAILSE. BIBLIOGRAPHYF. COMMENTSPAGEA-IB-1C-l0-1E-lF-lAPA25/iiii


LIST OF FIGURES- ..FIGURE# TITLE PAGE1 VICINITY MAP 1-32 CORDOVA PETROLEUM BASED ENERGY BALANCE IN 1979 11-2WI3 POPULATION PROJECTIONS - CITY OF CORDOVA 111-4 ..4 PROJECTED YEARLY ELECTRIC CONSUMPTION - CITY OF ....CORDOVA 111-55 PROJECTED YEARLY PEAK POWER DEMAND - CITY OF CORDOVA 111-6•..6 CITY OF CORDOVA - HEATING PROJECTIONS 111-77 INTERTIE - TRANSMISSION ROUTES AND HYDROELECTRIC SITES IV-78 BERING RIVER COAL FIELD DEVELOPMENT IV-19 •9 PRESENT WORTH COST OF ALTERNATIVE PLANS VI-3lOa PEAK POWER - DIESEL ONLY SCENARIO - CITY OF CORDOVA VI-4 lIPlOb ELECTRICAL ENERGY REQUIREMENT - DIESEL ONLY SCENARIO - ..CITY OF CORDOVA VI-5 .,11a PEAK POWER - COAL SCENARIO - CITY OF CORDOVA VI-7..litlIb ELECTRICAL ENERGY REQUIREMENT - COAL SCENARIO - CITY..OF CORDOVA VI-812a PEAK POWER - INTERTIE SCENARIO - CITY OF CORDOVA VI-10-..12b ELECTRICAL ENERGY REQUIREMENT - INTERTIE SCENARIO -CITY OF CORDOVA VI-II-13a PEAK POWER - ELECTRICAL HEATING SCENARIO - CITY OF..CORDOVA VI-13..13b ELECTRICAL ENERGY REQUIREMENT - ELECTRIC HEATING-SCENARIO - CITY OF CORDOVA VI-14..14a PEAK POWER - LOCAL HYDRO WITH DIESEL SCENARIO - CITYOF CORDOVA VI-IS..-14b ELECTRICAL ENERGY REQUIREMENT - LOCAL HYDRO WITHDIESEL SCENARIO - CITY OF CORDOVA VI-1615 CITY OF CORDOVA - CURRENT ENERGY USE PROJECTIONS VII-5..16 CITY OF CORDOVA - PROJECTIONS OF CURRENT PETROLEUM •..FUEL USE REPLACEABLE BY OTHER RESOURCES VII-6..17 CITY OF CORDOVA - PROJECTIONS OF CURRENT PETROLEUMFUEL USE WITH GENERATION WASTE HEAT RECOVERY VII-7 ..18 CITY OF CORDOVA - IMPACT OF WASTE HEAT USE VII-8•...MISC13/Ul .,...."",.-.....


LIST OF FIGURESFIGURE#TITLEPAGEB 7-1C.3.2.1-1C.3.4.1-1C.3.5.2-1C.3.5.2-2C.3.5.4-1C.3.6-1C.3.6-2C.3.7-1CITY OF CORDOVA - POWER CREEK vs. DEMANDHYDROELECTRIC POWER DEVELOPMENT DIAGRAMDIAGRAM OF RUDIMENTARY STEAM POWER PLANTJACKET WATER & EXHAUST WASTE HEATRECOVERY SYSTEMJACKET WATER WASTE HEAT RECOVERY SYSTEMRESIDENTIAL ENERGY CONSUMED FOR VARIOUS SIZESAND TYPES OF CONSTRUCTION - CITY OF CORDOVAWIND TURBINE GENERATORWECS vs. DIESEL GENERATION - 18 kw INDUCTIONGENERATIONHEAT PUMP FOR BUILDING HEATINGB-18C.3.2.1-8C.3.4.1-6C.3.5.2-2C.3.5.2-3C.3.5.4-6C.3.6-2C.3.6-8C.3.7-2MISCI3/U2


iii>;.,..MISCI3/U3 .,••LIST OF TABLES ....TABLE # TITLE PAGEIII!.........V-I FUEL ENERGY CONTENT V-2III!VI-l COST OF ALTERNATE DEVELOPMENT PLANS VI-lII!.VI-2 EVALUATION MATRIX - ELECTRIC SCENARIOS VI-22 .,VI-3 EVALUATION MATRIX - NON-ELECTRIC SCENARIOS VI-23 .....III'A-I 1979 PETROLEUM BASED ENERGY BALANCE - CORDOVA AREA A-IA-2 1979 PETROLEUM BASED ENERGY SOURCE AND USE -...,CORDOVA AREA A-2A-3 SUMMARY ELECTRICAL FORECASTS TO YEAR 2000 -CITY OF CORDOVA A-3..•A-4 LOW ELECTRICAL LOAD FORECAST - CITY OF CORDOVA A-4A-5 MEAN ELECTRICAL LOAD FORECAST - CITY OF CORDOVA A-5 .,..A-6 HIGH ELECTRICAL LOAD FORECAST - CITY OF CORDOVA A-6A-7 LOW HEAT ENERGY FORECASTS TO YEAR 2000 -..CITY OF CORDOVA A-7 •A-8 MEAN HEAT ENERGY FORECASTS TO YEAR 2000 --CITY OF CORDOVA A-8A-9 HIGH HEAT ENERGY FORECASTS TO YEAR 2000 -.,CITY OF CORDOVA A-9 •A-I0 CURRENT ENERGY USE PROJECTED TO YEAR 2000 - ...CITY OF CORDOVA A-I0- ..,B.l-lSUMMARY ESTIMATES FOR COST OF CARBON CREEKCOAL PER TON B-3•.....B.I-2 INITIAL GEOLOGIC RECONNAISSANCE PROGRAM TOOUTLINE TARGETS B-4ill!B.I-3 DRILLING PROGRAM TO PROVE RESERVES B-5..B.I-4 CAPITAL COST DETAILS - CONSTRUCTION, TRANS-..PORTATION AND MAINTENANCE EQUIPMENT B-5..B.I-5 MINING EQUIPMENT B-6


LIST OF TABLESTABLE #TITLEPAGEB.1-6B.3-1B.3-2B.4-1B.5-1CAMP FACILITIESHEALY COAL COSTSBARGING COSTSKATALLA OIL AND GAS DEVELOPMENT COSTSPROJECTED SURPLUS MWh AT VALDEZB-6B-88-8B-10B-13C.3.5.2-1C.3.5.2-2WASTE HEAT AVAILABILITYHEATING OIL USEC.3.5.2-4C.3.5.2-6D-1D-2aD-2bD-3D-4D-5D-6aD-6bDIESEL GENERATION ONLY - ECONOMIC ANALYSISDIESEL PLUS INTERTIED SURPLUSPLUS SILVER LAKE HYDRO (SURPLUS ENERGYCOST $0.0625/kWh) - ECONOMIC ANALYSISDIESEL PLUS INTERTIED SURPLUSPLUS SILVER LAKE HYDRO (SURPLUS ENERGYCOST $.Ol/kWh) - ECONOMIC ANALYSISLOCAL HYDRO PLUS DIESEL - ECONOMIC ANALYSISHEALY COAL GENERATION - ECONOMIC ANALYSISCARBON CREEK COAL GENERATION - ECONOMIC ANALYSISELECTRIC HEATING BY INTERTIED HYDRO(SURPLUS ENERGY COST $0.0625/kWh) - ECONOMICANALYSISELECTRIC HEATING BY INTERTIED HYDRO (SURPLUSENERGY COST $.Ol/kWh) - ECONOMIC ANALYSISD-1D-2D-3D-4D-5D-6D-7D-8MISC13/U4


I. INTRODUCTION ANDSUMMARYI. INTRODUCTION AND SUMMARY1. IntroductionCordova, population about 2500, is located on the east side <strong>of</strong> Alaska1sPrince William Sound, on the Orca Inlet. Elevation ranges from sealevel to 400 feet <strong>and</strong> the marine influenced climate ranges from a Januaryaverage temperature <strong>of</strong> 26°F to a July average <strong>of</strong> 54°F. Rai nfall isheavy, with an annual average precipitation <strong>of</strong> 90 inches (over 7 feet).The area1s economy is chiefly supported by fishing <strong>and</strong> crabbing activitiesin the Prince William Sound <strong>and</strong> by the long <strong>and</strong> diversified canning<strong>and</strong> freezing season for this harvest.Cordova, like many communities in Alaska, depends almost entirely onimported petroleum products for its electrical <strong>energy</strong> <strong>and</strong> heating needs.As the continually escalating cost <strong>of</strong> petroleum fuels in small Alaskacommunities is among the highest in the United States, it is obviousthat high priority should be given to developing community independencefrom these fuels or, at least, reducing community dependence on petroleumby implementation <strong>of</strong> reasonable alternatives.Without at least astabilization <strong>of</strong> <strong>energy</strong> costs in the near term, Cordova risks significantloss <strong>of</strong> population <strong>and</strong> industry to other, cheaper <strong>energy</strong> sites.This <strong>final</strong> <strong>report</strong> describes work performed at a <strong>reconnaissance</strong> level toidentify <strong>and</strong> evaluate the suitability <strong>of</strong> utilizing various existing<strong>and</strong> potential non-petroleum <strong>energy</strong> resources for the Cordova area.This <strong>report</strong> is based on <strong>reconnaissance</strong> investigations, verbal communicationswith people who live in <strong>and</strong> are familiar with the area, informationavailable from existing <strong>report</strong>s, publications <strong>and</strong> maps, comments <strong>of</strong>reviewers, <strong>and</strong> engineering calculations <strong>and</strong> estimations.The overall <strong>study</strong> area discussed in this <strong>report</strong> is shown on Figure 1.APA24/klI-I


2. SummaryI. INTRODUCTION ANDSUMMARY-• Preparation <strong>of</strong> pr<strong>of</strong>iles for <strong>energy</strong> alternatives for Cordova,the i r comb i nat ion into reasonab 1 e a 1 ternat i ve plans, <strong>and</strong>technical, economic, <strong>and</strong> environmental analyses <strong>of</strong> these plans.• Recommendations for specific data collection programs <strong>and</strong>feasibility level studies required to increase the confidence<strong>of</strong> analyses.--••••..The work <strong>report</strong>ed on in this <strong>study</strong> consists <strong>of</strong> the following:••Performance <strong>of</strong> site <strong>reconnaissance</strong> <strong>and</strong> data gathering.Establishment <strong>of</strong> an <strong>energy</strong> balance for Cordova.• Forecast <strong>of</strong> e 1 ectri ca 1 <strong>energy</strong> <strong>and</strong> peak power requi rementsfor the area to the year 2000...•....-..~"..- - ..APA24/k21-2


I I.ENERGY BALANCEI I.ENERGY BALANCEIn order to establish a basic picture <strong>of</strong> <strong>energy</strong> use in the Cordova area,a petroleum based <strong>energy</strong> balance has been compiled for the year 1979, thelast year for which full year data was available. Energy forms used arediesel fuel, gasoline, #1 fuel oil, aviation gasoline, <strong>and</strong> propane.It is recognized that coal, wood, wind, <strong>and</strong> natural gas are <strong>energy</strong> sourceswhich have been used on a small scale; utilization data was available onlyfor wood, however. In the past few years, many residents <strong>of</strong> Cordovahave installed wood stoves for primary <strong>and</strong> secondary heating uses. Thepresent use <strong>of</strong> wood in Cordova is estimated to be between 800 <strong>and</strong> 1000cords per year, equivalent to about 17.1 x 10 9 Btu per year based onU. S. Forest Service estimates for spruce. Wood <strong>energy</strong> consumed inCordova, then, amounts to a little less than 2 percent <strong>of</strong> annualpetroleum use; it is projected to maintain this level through theyear 2000 <strong>and</strong> not significantly impact the development <strong>of</strong> non-petroleumbased alternative <strong>energy</strong> plans.The following pictorial graph (Figure 2) summarizes the petroleum based<strong>energy</strong> balance in Cordova <strong>and</strong> the immediately surrounding area by <strong>energy</strong>form <strong>and</strong> end-use category. The data used as the basis for this graph istabulated in Appendix A. Data was obtained from several local sources <strong>and</strong>best estimates were made for some aspects <strong>of</strong> the breakdown shown in Figure 2 ....APA24/LlII-I


ENERGY ASWASTE HEATEFFICIENCIES ASSUMED:TRANSPORTATION 30 %ELECTRIC GENERATION 30 %INDUSTRY* a HEATING 70 %* FISH PROCESSING6r--r.G~A~SONL~I~N~E--~~O~T~HE~R~TR~A~N~S~P~O~R~TA~J~IO~N~I~.~IO~.~~~S;~T AV GAS 19.2%AL1.3xI0 6 GAL.E BOAT TRANSPORTATION 36.1 %NE~ DIESEL FUE LY #1 HEATING FUELINDUSTRY, " ",/ / /7.9 %C PROPANEo 80.8%N 5.2x106 GAL.SU.~HEATING 25.7%;/" /////~~ ________ E]~ruffiggruffiggillllffiffi~~~~~~~~~~~DCORDOVA PETROLEUM BASED ENERGY BALANCE IN 1979FIGURE 2ENERGYUTILIZED'1 , , f. , f Ir , t • " • , , • 'I " , , ,. , ,'. '1 , • , , "


III.ENERGY REQUIREMENTSIII. ENERGY REQUIREMENTSThe future <strong>energy</strong> needs <strong>of</strong> Cordova to the year 2000 were projected basedon the high, low <strong>and</strong> mean population growth scenarios shown in Figure 3.These population growth projections are based on projections made forOuter Continental Shelf (OCS) leasing impacts as follows: low = no OCSimpact scenario; mean = most probable OCS impact scenario; <strong>and</strong> high =maximum probable OCS impact scenario.The growth projections used in this <strong>study</strong> were selected after review <strong>of</strong>exi st -j ng appropri ate studi es i ndi cated that the growth proj ect ionsarrived at in the Alaska OCS Socioeconomic Studies Technical ReportNumber 33, October 1979, were the most reasonable. In the low projection,it is assumed that there will be no OCS leasing <strong>and</strong> that approximatelyhalf <strong>of</strong> the new growth for Cordova would come from new developments <strong>and</strong>improvements in the fish processing industry, while the other half wouldcome through development <strong>of</strong> the local service sector. The mean <strong>and</strong> highgrowth projections use the same growth bases as above. In addition,they assume that Cordova will serve as a home base for the work force <strong>of</strong>a marine oil terminal on Hinchinbrook Isl<strong>and</strong>; the sharp increase inpopulation noted on the curves is a result <strong>of</strong> marine terminal construction<strong>and</strong> this home base activity. The high growth projection curve incorporatesthe assumptions that the impact <strong>of</strong> the Hinchinbrook terminal will beabout twice as great as the mean case <strong>and</strong> will occur later in the 1980·s.The growth in power need for the last two decades has greatly surpassedthe growth in population for the City <strong>of</strong> Cordova. This is consistentwith the increase in fishing <strong>and</strong> seafood processing activities in thearea.The Cordova Public Utilities board operates <strong>and</strong> maintains the powersystem whi ch extends from the southwestern shore <strong>of</strong> Eyak Lake nearAPA24/rlII I-I


III.ENERGY REQUIREMENTSCopper River Highway, south to Three Mile Bay, north to the MunicipalDock, <strong>and</strong> east to Cordova Airport on Mile 13 <strong>of</strong> Copper River Highway.The existing plant contains the following diesel engine driven generators:Total capacityLess Largest Unit = -2650 kWIIFirm" Capacity = 5800 kW1 @ 600 kW1 @ 750 kW1 @ 1950 kW1 @ 2650 kW1 @ 2500 kW (new, installed 1979)= 8450 kWDue to the poor <strong>and</strong> unreliable condition <strong>of</strong> some <strong>of</strong> the units, the truefirm capacity is estimated to be approximately 5,000 kW.The existing firm capacity is such that no new generation facilitieswill be required until 1985 to meet the projected system peak dem<strong>and</strong>.Figures 4 <strong>and</strong> 5 show the estimated yearly total electrical <strong>energy</strong> consumption<strong>and</strong> corresponding peak power dem<strong>and</strong>s for the three population growthcases; the data used to create these figures are tabulated in Appendix A..,....•....•..-..In making these electrical projections, certain key factors <strong>and</strong> assumptionsinfluenced trends. These fqctors are:• Actual population growth based on census figures has historicallybeen less than projected figures. Use <strong>of</strong> the OuterContinental Shelf leasing impact scenarios discussed was usedas the most realistic base <strong>of</strong> projection.• The seafood process i ng industry is expected to grow at aslower rate than population because <strong>of</strong> impacts <strong>of</strong> high <strong>energy</strong>costs. While the total volume <strong>of</strong> processing is assumed toincrease slightly, the increased use <strong>of</strong> freezing rather thancanning by many processors is expected to increase the amounts•'"..-IIIAPA24/r2111-2• ..


III.ENERGY REQUIREMENTS<strong>of</strong> <strong>energy</strong> used by the processors.It should be noted thatonly one large processor has plans for expansion; the othersexpressed concern that rising fuel prices might drive themout <strong>of</strong> business in Cordova.• Chugach Alaska Fisheries, Inc., a wholly owned subsidiary<strong>of</strong> Chugach Natives, Inc., at present has its own electricalgeneration capability.Negotiations are presently in processfor addition <strong>of</strong> this generating load to the Cordova ElectricalCooperative system in 1983; in our projections a dem<strong>and</strong> <strong>of</strong> 1 MW<strong>and</strong> load <strong>of</strong> 1.6 MWhannually have been included in the 1983 figures<strong>and</strong> projected thereafter at the same growth rate as otherfishing related activities.• No known plans currently exist for new commercial or industrialfacilities to be constructed in Cordova. We have consideredit realistic that one new commercial/industrial facilitywould come on line in 1992 with a maximum dem<strong>and</strong> <strong>of</strong> 600 kW<strong>and</strong> annual electrical load <strong>of</strong> 1 MWh.• Growth in the government (public) sector is expected to besteady at a rate lower than that <strong>of</strong> popul ati on increase.• The rate <strong>of</strong> increase in per consumer residential electricaluse has slowed in recent years due to the ri sing cost <strong>of</strong>electricity.This trend is projected to continue untilcheaper alternatives are realized.In line with the risingcost <strong>of</strong> <strong>energy</strong>, consumers are expected to implement reasonable<strong>energy</strong> conservation measures.In order to examine all petroleum based <strong>energy</strong> uses in Cordova that canreasonably be replaced with other <strong>energy</strong> sources, projections were madefor heating <strong>requirements</strong> in both British thermal units (Btu) <strong>and</strong> thenumber <strong>of</strong> MWh that would be required for electrical provision <strong>of</strong> suchheat. Figure 6 shows the heating <strong>requirements</strong>; projections are tabulatedin Appendix A.APA24/r3III-3


55000004 !5004 O~--~............z 3 ""..,o...-c 2500..J~CLo 2CL 0"" ..,...500000500-1 --I- --"----t------+ IU-I-r--tI-----rjI~--- - --- -..,g"'f #/I ~. i""""""'" --MEANd .-~ ~.- t----HIGH/ --- ,--~_. LOW.... -....01980981 ,1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000YEARPOPULATION PROJCTIONSCITY OF CORDOVAFIGURE 3, .r 1 , I , I , I ,.,' ,. ,. ••'I ,. '11, , I 11 IF' I ,'I "


8 07 5,~7 v6 ~6 05 5/~/ v/ VJV/ '/5 0~,.,3 ~3 02 52 05V"""~ ,. V-~ .V./ VV ~./----- _.---I-'"_.r----- ------.--/V L,/V '\ ~H'GH-1-- .--AV~ .... V--flMEAN./--- ----"I----- . ~ ~.-.1-I.. --...... 1.---rtLOW~ .. ~PROJECTED YEARLYELECTRIC CONSUMPTIONCITY OF CORD~FIGURE


'",",17'''''''''--~14 00013 000Innt'I,-100010 000t 9 ."""": '--_....--7 0006 OO~~O4 0 ........~~- - ..-/V~ ~ --- -~-----1-~~ ~ .....1-~.----~ 1'--'-~ ~- ---/./ ViI""lX~~/ HIGH)/ vV~V ,.,.""./ // V/ /.....-- ~."",-,.-~/,....-~ ... ,-~ .v LOW.."",.~,.-.J,. ... MEAN ~..",.,. ~~ ..,.",..".. ~ ..,.""..-- '"~10-.""'-PROJECTED YEARLY PEAKPOWER DEMANDCITY OF CORDOVAFIGURE 51980 I_I 1S'82 1983 1'B4 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000YEAR",. ,. 1'1 ,. II.' II rl '1'1 I. ,e"" '. f,""/l~


"' ;I I I I II I I I ,I---Q:.....J500.... 400CD~oI-I--- 300~2501980;::-----I-~;:.;------I ~IY--~1982 1984 1986 1988~ ~~ v./ ~--V ".."", . ~ -",- ~V.".",." ~EAN ./~~ ~~,/./Kow .'~.--- ~.~ -CITY OF CORDOVAHEATING PROJECTIONSFIGURE 61990 1992 1994 1996 1991 2000


IV. ENERGY RESOURCE ALTERNATIVESIV.ENERGY RESOURCE ALTERNATIVESThe following <strong>energy</strong> <strong>and</strong> power resource alternatives for Cordova wereexamined in the course <strong>of</strong> this <strong>study</strong>:• hydroelectricity• coal• oil <strong>and</strong> gas• geothermal• wind• solar• tidal• biomass• waste heat <strong>and</strong> cogeneration• conservation• other resourcesThese resource alternatives are briefly described in the remainder <strong>of</strong>this section. Appendix B contains amplified descriptions <strong>and</strong> costingdetails concerning those <strong>energy</strong> resources found potentially suitablefor Cordova's twenty year electrical needs <strong>and</strong>/or heating needs;"resources" locally suitable for heating applications as cascadedor secondary uses, such as waste or low grade heat applications, arediscussed in detail in Appendix C.1. Hydroelectric Resourcesa. Large Hydroelectric SitesThere are several large hydroelectric sites along the Copper Riverdrainage which conceivably could be developed at some future time. Arecent listing (Alaska Power Administration) giving the hydroelectricpotential <strong>of</strong> these Copper River sites shows the following:(1) Million Dollar - 440,000 kW(2) Cleve - 820,000 kW(3) Woods Canyon - 3,600,000 kWAPA25/AlIV-l


IV. ENERGY RESOURCE ALTERNATIVESWithin the perspective <strong>of</strong> this <strong>study</strong> these hydro sites are not consideredas potential <strong>energy</strong> sources for Cordova due to substantialenvironmental barriers, <strong>and</strong> the fact that these projects would befar too large for Cordova's <strong>requirements</strong>.b. Run-<strong>of</strong>-River Hydroelectric DevelopmentA run-<strong>of</strong>-river hydroelectric development at Power Creek could conceivablybe developed in two stages: a first stage <strong>of</strong> 6600 kW <strong>and</strong> a secondstage <strong>of</strong> 6000 kW capacity. The dam would be near stream Mile 3.0 (upstream<strong>of</strong> Ohman Falls) <strong>and</strong> the powerhouse would be near Mile 2.0.The U.S. Army Corps <strong>of</strong> Engineers' investigations to date regarding abaseline 6000 kW run-<strong>of</strong>-river project indicate potential project feasibility.The Corps has test drilled two Power Creek hydro sites <strong>and</strong> isscheduled to test drill the third (Ohman Falls) during the summer <strong>of</strong>this year; the first two drilled sites were ruled out due to the extremedepth to bedrock. The Corps is also <strong>study</strong>ing the second stage developmentfor Power Creek <strong>and</strong> the possibility <strong>of</strong> a storage project at thesame Ohman Falls site.Only the first stage conceptual development <strong>of</strong> 6600 kW run-<strong>of</strong>-riverPower Creek plant is considered for further analysis in this <strong>reconnaissance</strong><strong>study</strong>.A run-<strong>of</strong>-river hydroelectric development on the Copper River appearstoo complex for serious consideration as a viable <strong>energy</strong> alternative.A cursory review <strong>of</strong> some <strong>of</strong> the problems <strong>and</strong> environmental concernsare:(1) The minimum economic head for a bulb turbine is about 15 feet.The gradient <strong>of</strong> the lower Copper River is approximately 5 feetper mile. With a head <strong>of</strong> 15 feet, the flow <strong>requirements</strong> areapproximately one cfs per kW or 5000 cfs for a 5 MW unit. Arun-<strong>of</strong>-river plant would require a long pipeline <strong>of</strong> large diameteror a barrage across the river to develop the head..'.....'..•.,..•.,•••..••....•...........,..APA2S/A2IV-2..


IV. ENERGY RESOURCE ALTERNATIVES(2) There are numerous glacier-dammed lakes in the basin, <strong>and</strong>breakout flooding from these lakes has caused large floodflowsin the lower Copper River.(3) Past experience on bridge destruction by spring ice flowsindicates any structure in the Copper River would have toresist these strong forces.(4) Winter icing would result in seasonal operation without adeep reservoir to draw from.(5) The Copper River is by far the most important salmon fisheryin the area. The construction <strong>of</strong> a barrage would requiresuitable fishways. Pipeline construction with associatedblasting would have to be carefully monitored to controlsiltation <strong>and</strong> shock waves while fish are in the river.(6) The cost <strong>of</strong> low head hydroelectric plants are usually marginalunder far more favorable conditions.c. Transmission Intertied Small Hydroelectric SitesA transmission intertie between Cordova <strong>and</strong> Valdez could provide for anexchange <strong>of</strong> electrical <strong>energy</strong> <strong>and</strong> capacity <strong>and</strong> also provide connectionto a series <strong>of</strong> potential hydroelectric sites that exist in the regionbetween the two communities.Estimates <strong>of</strong> surplus <strong>energy</strong> available at Valdez are subject to considerablevariation depending on developmental assumptions made. The Corps <strong>of</strong>Engineers <strong>report</strong>s that their recent <strong>study</strong> for Valdez shows that surplus<strong>energy</strong> would become available after the completion <strong>of</strong> the Solomon Gulchhydroelectric project <strong>and</strong>, with the addition <strong>of</strong> <strong>energy</strong> available frominstallation <strong>and</strong> operation <strong>of</strong> the proposed Pressure Reducing Turbine(PRT) in the Trans-Alaska Pipeline, would remain available until theValdez-Glennallen area needs additional power in 1990 for winter peakdem<strong>and</strong>s.APA25/A3IV-3


IV. ENERGY RESOURCE ALTERNATIVESThe PRT is a system for recovering <strong>energy</strong> from the pipeline by using thepressure developed by change in pipeline elevation on the south side <strong>of</strong>Thompson Pass to turn a turbine <strong>and</strong> generate electricity. PRT <strong>energy</strong> isconsidered a secondary (interruptable) <strong>energy</strong> source; but <strong>of</strong>fers significantshort range <strong>energy</strong> potential until the supply <strong>of</strong> oil from theNorth Slope is depleted.A currently uncompleted <strong>study</strong> by Robert W. Retherford Associates for theCopper Valley Electric Association (CVEA), serving the Valdez-Glennallenareas, is investigating surplus <strong>energy</strong> available to CVEA from the SolomonGulch hydroelectric project <strong>and</strong> operation <strong>of</strong> the proposed PRT. Energyforecasts based on CVEA growth projections for the area, current pipelineflow rates, <strong>and</strong> oil supply expectations from 1983 to 1996 were developedfor that <strong>study</strong>. Projections derived in that <strong>study</strong> are used in this<strong>study</strong> <strong>and</strong> are detailed in Appendix B; they provide a reasonable assumptionbase for surplus projections <strong>and</strong> are not at significant variance withother plans.If a transmission intertie between Cordova <strong>and</strong> Valdez could be madefeasible there would be substantial benefits to both communities immediately<strong>and</strong> increasing benefits as hydro sites along the route are developed.Major benefits include balancing <strong>of</strong> <strong>energy</strong> dem<strong>and</strong>s, sharing <strong>of</strong> reserves,<strong>and</strong> increasing reliability.-..........•.,-•Three general corridors can be found that represent physically possibleroutes for such an interconnection. They are described briefly asfollows:(1) Submarine route following the eastern perimeter <strong>of</strong> PrinceWilliam Sound from Cordova to Valdez - a distance <strong>of</strong> approximately84 miles (3 miles <strong>of</strong> which is overhead line)...1Iiio,-APA25/A4IV-4


IV. ENERGY RESOURCE ALTERNATIVES(2) An overl<strong>and</strong> route on a portion <strong>of</strong> the eastern perimeter <strong>of</strong>Prince William Sound crossing from the head <strong>of</strong> Port Fidalgo tothe Lowe River via the approximate routing proposed in 1974 bythe El Paso Alaska Company for a 42-inch diameter gas line - adistance <strong>of</strong> about 59 miles.(3) An overl<strong>and</strong> route following the Copper River Highway to theTasnuna River, up that river, over Marshall Pass <strong>and</strong> down theLowe River to Valdez - a distance <strong>of</strong> about 130 miles.All three routes <strong>and</strong> the hydro sites are shown on Figure 7, Intertie -Transmission Route <strong>and</strong> Hydroelectric Sites.The submarine Route (1) is substantially longer <strong>and</strong> could not readilyconnect with the series <strong>of</strong> potential hydroelectric sites along the way.To use such a cable system at AC voltages would require sUbstantialcompensation (shunt reactors) at several points along the route. Thecable system would need to come up to shore for connections to suchcompensation stations. A DC submarine system would not require compensation,could use lower voltage cables, but could not readily connectto the hydro sites along the route.The long overl<strong>and</strong> Route (3) is clearly much more expensive, but may bemore accessible depending on the <strong>final</strong> route chosen to complete theCopper River Highway. There are several streams <strong>and</strong> lakes along theroute which could be considered potential hydroelectric sites. A briefdiscussion <strong>of</strong> the most promising <strong>of</strong> these sites is presented as follows:(1) Van Cleve Lake at elevation 801 is apparently dammed by MilesGlacier. The lake has a large drainage area. However, thesurface is approximately 200 feet below the ice dam. A possibilityexists that top <strong>of</strong> bedrock controls the elevation <strong>of</strong>the lake <strong>and</strong> run<strong>of</strong>f occurs under the ice <strong>of</strong> Miles Glacier. Ifthis is indeed the case, development would requireAPA25/A5IV-5


IV. ENERGY RESOURCE ALTERNATIVESa tunnel approximately 5 miles in length <strong>and</strong> a lake tap. Thewriter cannot find any information on the lake depth to computestorage capacity or the nature <strong>of</strong> the outlet. With only500 feet <strong>of</strong> head, this lake does not warrant recommending asa feasible site at this time.(2) Tiekel River from the junction with the Tsina River (Mile 13.9)to its mouth, flows through a rugged canyon <strong>and</strong> falls about55 feet per mile. A dam approximately 100 feet high located atriver mile 10.5 would provide a usable storage <strong>of</strong> about 50,000acre-feet which would regulate the flow to yield a sustaineddischarge <strong>of</strong> 250 cfs. A tunnel 6.5 miles in length to a powerhouseat river mile 4.1 would develop a total head <strong>of</strong> 700 feet.About 10,000 kW <strong>of</strong> prime power could be generated.....--.......This plan would involve relocating a portion <strong>of</strong> the RichardsonHighway <strong>and</strong> the Trans-Alaska oil pipeline. For this reasonalone, the Tiekel River is not considered further as a primesource <strong>of</strong> <strong>energy</strong>.Without the storage reservoir, development would be run-<strong>of</strong>river<strong>and</strong> seasonal in nature. This type <strong>of</strong> development doesnot appear feasible due to the long tunnel required todevelop sufficient head.(3) Cleave Creek, Heiden Canyon, Brown Creek <strong>and</strong> Sheep Creekdo not have feasible hydroelectric sites along them, eithernow or in the foreseeable future. Nearly all <strong>of</strong> theusable head would have to be developed by a high dam or anextremely long flume or tunnel <strong>and</strong> would be a seasonaloperation as storage capacity is very limited.-.,..-----..APA25/A6IV-6


LEGEND:............---INTERTIE ROUTE 1INTERTIE ROUTE 2INTERTIE ROUTE 3BERING RIVER COAL POWERTRANSMISSION ROUTESILVER LAKE TRANSMISSIONROUTEROUTES & HYDROELECTRICSITESFIGURE - 7


IV. ENERGY RESOURCE ALTERNATIVESOf the three, Route (2) is considered the only potentially viableroute within the perspective <strong>of</strong> this <strong>study</strong> which considers electricalloads up to about 50,000 kW (including electric heat). This route withits length <strong>of</strong> 59 miles is the shortest <strong>and</strong> lowest cost routing, but itdoes have more difficult access than the other two routings. Route (2)passes within easy reach <strong>of</strong> a number <strong>of</strong> small hydroelectric sites. Abrief discussion <strong>of</strong> these sites with estimated power capacity <strong>and</strong>annual <strong>energy</strong> production follows. The sites are listed in order fromCordova towards Valdez.(1) Sheep River LakesLocation: - A chain <strong>of</strong> three lakes, elevation 2,026, 1,022<strong>and</strong> 649, discharge into Sheep River at mile 1.0 in Section 23,Range 4 West, Township 13 South, Copper River Meridian. Theupper <strong>and</strong> middle lakes outlets are in Section 21 <strong>and</strong> the lowerlake outlet is in Section 22.Drainage area: - The upper lake has a drainage area <strong>of</strong>0.75 square miles; the middle lake has a drainage area <strong>of</strong>2.0 square miles; <strong>and</strong> the lower lake has a drainage area <strong>of</strong>4.0 square miles as measured from the U.S.G.S. map "Cordova(C-6) Alaska", 1963 revision.Run <strong>of</strong>f: - Discharge measurements have not been made for any<strong>of</strong> these lake outlets. The mean discharge is estimated tobe in the same order as Power Creek near Cordova which hasan average discharge <strong>of</strong> 12 cfs per square mile over a 32year run-<strong>of</strong>f record period. The average discharge is conservativelyestimated as 9 cfs for the upper lake, 24 cfsfor the middle lake <strong>and</strong> 48 cfs for the lower lake.APA25/A8IV-8


IV. ENERGY RESOURCE ALTERNATIVESRegulation: - Complete regulation is not considered economicallyfeasible for the watershed. The upper lake would require4500 acre-feet <strong>of</strong> storage by raising the lake level 175 feet;the middle lake would require 8700 acre-feet by raising thelake level 210 feet; <strong>and</strong> the lower lake would require 13,900acre-feet by raising the lake level 230 feet. Lake taps arenot considered feasible for these small developments.A dam raising the upper lake level 85 feet would provide80% regulation; the middle lake level raised 78 feet wouldprovide 75% regulation; <strong>and</strong> the lower lake level raised51 feet would provide 70% regulation....,.'... ,..•Dam Sites: - A field <strong>reconnaissance</strong> <strong>of</strong> the power sites hasnot been made, but a <strong>study</strong> <strong>of</strong> the U.S.G.S. map 1:63,360suggests that a plan similar to the following is feasible.The upper lake level would be raised 85 feet with a rockfilldam <strong>and</strong> a 16-inch diameter penstock 2,400 feet in lengthwould convey the water from the dam to the powerhouse atelevation 1,100 on the maximum shoreline <strong>of</strong> the middle lake.The middle lake would be raised 78 feet with a rockfill dam<strong>and</strong> a 24-inch diameter penstock 1,000 feet in length wouldconvey the water from the dam to a powerhouse at elevation700 on the maximum shoreline <strong>of</strong> the lower lake. The lowerlake would be raised 51 feet with a rockfill dam <strong>and</strong> a36-inch diameter penstock 2,600 feet in length would conveythe water from the dam to a powerhouse on the Sheep River atelevation 50.•....-......--..APA25/A9Power Capacity: - The power capacity for the upper lake isestimated at 480 kW pr"imary <strong>and</strong> 600 kW average; power capacityfor the middle lake is estimated at 425 kW primary <strong>and</strong> 570kW average, <strong>and</strong> the power capacity for the lower lake isestimated at 1,411 kW primary <strong>and</strong> 2,016 kW average. The totalcapacity for the three lake development is 2,316 kW primaryIV-9-.....It


IV. ENERGY RESOURCE ALTERNATIVES<strong>and</strong> 2,581 kW average. This would provide about 20,288 MWh <strong>of</strong>prime <strong>energy</strong> <strong>and</strong> 2,312 MWh <strong>of</strong> secondary <strong>energy</strong> annually.(2) Lake 1488 Elevation - Near Beartrap BayLocation: - The lake is located mainly in Sections 9 <strong>and</strong> 10,<strong>of</strong> Range 4 West, Township 13 South, Copper River Meridian.The discharge stream is a tributary to the main creekthat discharges into the upper end <strong>of</strong> Beartrap Bay.Drainage Area: - There is 3.0 square miles <strong>of</strong> drainage areainto the lake as measured from the U.S.G.S. map "Cordova0-6) Alaska", 1965 revision.Run-<strong>of</strong>f: - Discharge measurements have not been made.mean discharge is estimated to be in the same order as PowerCreek near Cordova which has an average discharge <strong>of</strong> 12 cfsper square mile over a 32 year run<strong>of</strong>f record period.average discharge is estimated at 36 cfs.TheTheRegulation; - Complete regulation would require a storagecapacity <strong>of</strong> 16,940 acre-feet. This would require raising thelake level about 100 feet. Raising the lake level 37 feetwould provide about 5,550 acre-feet <strong>of</strong> storage <strong>and</strong> 75%regulation.Dam Site: - A field <strong>reconnaissance</strong> <strong>of</strong> the power site has notbeen made, but a <strong>study</strong> <strong>of</strong> the U.S.G.S. map 1:63,360 suggestsa plan similar to the following is feasible. A rockfilldam near the outlet raising the normal maximum lake levelto elevation 1,525 would provide storage for 75% regulation.A 30-inch diameter penstock 3200 feet in length would conveythe water westerly from the dam to a powerhouse at elevation150. The average effective head would be about 1,325 feet.APA25/A10IV-10


IV. ENERGY RESOURCE ALTERNATIVESPower capacity: - The power capacity is estimated at 2,505kW primary <strong>and</strong> 3,340 kW average. This would provide about21,940 MWh <strong>of</strong> prime <strong>energy</strong> <strong>and</strong> 7,320 MWh <strong>of</strong> secondary <strong>energy</strong>annually...•..(3) Dead Creek - Gravina River TributaryLocation: - The Dead Creek power site is located in Section 7,Range 4 West, Township 12 South, Copper River Meridian.Dead Creek discharges into Gravina River at river mile 4.5.The dam site is 0.5 stream miles from the mouth <strong>of</strong> Dead Creek.Drainage Area: - There are 35 square miles <strong>of</strong> drainage areaabove the dam site as measured from the U.S.G.S map "Cordova(0-6) Alaska", 1965 revision.III


IV. ENERGY RESOURCE ALTERNATIVESPower capacity: - The power capacity is estimated at 5,730kW primary <strong>and</strong> 7,644 kWaverage. This would provide about50,195 MWh <strong>of</strong> prime <strong>energy</strong> <strong>and</strong> 16,767 MWh <strong>of</strong> secondary <strong>energy</strong>annually.Remarks: - The Alaska Department <strong>of</strong> Fish <strong>and</strong> Game <strong>report</strong>sthat the Gravina River supports a good run <strong>of</strong> pink <strong>and</strong> chumsalmon. Fish mitigation measures, probably in the form <strong>of</strong> ahatchery, may be required for Dead Creek hydro development.A dock <strong>and</strong> approximately four miles <strong>of</strong> construction accessroad <strong>and</strong> clearing <strong>of</strong> the reservoir are other factors to beconsidered.(4) Lake 1975 Elevation - Dead Creek TributaryLocation: - Lake 1975 is located in Section 31, Range 5 West,Township 11 South, Copper River Meridian. The outlet streamdischarges into Dead Creek at stream mile 1.2.Drainage Area: - There is 0.80 square miles <strong>of</strong> drainage areainto the lake as measured from the U.S.G.S map "Cordova (0-6)Alaska, 1965 revision.Run-<strong>of</strong>f: - Discharge measurements have not been made. It isestimated that the run<strong>of</strong>f in the area is 12 cfs per squaremile or an average discharge <strong>of</strong> 9.6 cfs.Regulation: - Complete regulation would require 5,200 acrefeet<strong>of</strong> storage. About 900 acre-feet <strong>of</strong> storage could beobtained by raising the normal maximum water surface toelevation 2,000 which would provide about 45% regulation <strong>of</strong>the run<strong>of</strong>f.APA25/AI2IV-12


IV. ENERGY RESOURCE ALTERNATIVESDarn Site: - A field <strong>reconnaissance</strong> <strong>of</strong> the power site has notbeen made, but a <strong>study</strong> <strong>of</strong> the U.S.G.S. map 1:63,360 suggestsa plan similar to the following may be feasible. A rockfilldam raising the lake to a normal maximum water surface <strong>of</strong>2,000 feet elevation would provide storage for 45% regulation.A 16-inch diameter penstock 3,700 feet in length would conveythe water to a power house at elevation 350 in the DeadCreek valley. The average effective head would be about1,600 feet...-..•..Power Capacity: - The power capacity is estimated at 484kW primary <strong>and</strong> 1,075 kW average. This would provide about4,240 MWh <strong>of</strong> prime <strong>energy</strong> <strong>and</strong> 5,177 MWh <strong>of</strong> secondary <strong>energy</strong>annually.(5) Lake 1878 Elevation - Fidalgo Creek TributaryLocation: - The lake outlet is located in Section 22, Range 5West, Township 11 South, Copper River Meridian. The outletstream discharges into Fidalgo Creek at stream mile 4.1.Drainage Area: - There are 2.25 square miles <strong>of</strong> drainagearea at the outlet <strong>of</strong> the lake as measured from the U.S.G.S.map "Cordova (0-6) Alaska", 1965 revision.•.....,.....,..APA25/A13Run-<strong>of</strong>f: - Discharge measurements have not been made. It isestimated that the run<strong>of</strong>f in the area is 12 cfs per squaremile or an average discharge <strong>of</strong> 27 cfs.Regulation: - Complete regulation would require 14,600acre-feet <strong>of</strong> storage. Raising the normal maximum water surfaceto elevation 1,950 would provide 3,600 acre-feet <strong>of</strong> storage<strong>and</strong> provide for 50% regulation.IV-13II'..-........


IV. ENERGY RESOURCE ALTERNATIVESDam Site: - A field <strong>reconnaissance</strong> <strong>of</strong> the power site has notbeen made, but a <strong>study</strong> <strong>of</strong> the U.S.G.S. map 1:63,360 suggestsa plan similar to the following may be feasible. A rockfilldam raising the lake to a normal maximum water surface <strong>of</strong> 1,950feet elevation would provide storage for 50% regulation. A26-inch diameter penstock 5,300 feet in length would conveythe water from the dam to a powerhouse located at the 500 footcontour in the Fidalgo Creek basin. The average effectivehead would be about 1,375 feet.Power Capacity: - The power capacity is estimated at 1,300kW primary <strong>and</strong> 2,600 kW average. This would provide about11,388 MWh <strong>of</strong> prime <strong>energy</strong> <strong>and</strong> 11,388 MWh <strong>of</strong> secondary <strong>energy</strong>annually.(6) Fidalgo Creek - Run <strong>of</strong> River Plant.Location: -The dam site is located in Section 15, Range 5West, township 11 South, Copper River Meridian. The powerhouselocation is approximately 1,100 feet downstream fromthe dam at the 500 foot contour.Drainage Area: - There are 7.5 square miles <strong>of</strong> drainage areaabove the dam site as measured from the U.S.G.S. map "Cordova(0-6) Alaska," 1965 revision.Run-Off: - Discharge measurements have not been made. Itis estimated that the run<strong>of</strong>f in the area is 12 cfs per squaremile or an average discharge <strong>of</strong> 90% cfs.Regulation: - the site does not provide sufficient storagefor regulation. Preliminary estimates are made by utilizing50% <strong>of</strong> the water over a 6-month period.APA25/A14IV-14


APA25/A15IV. ENERGY RESOURCE ALTERNATIVESDam Site: - A field <strong>reconnaissance</strong> <strong>of</strong> the power site has notbeen made, but a <strong>study</strong> <strong>of</strong> the U.S.G.S. map 1:63,360 suggestsa plan similar to the following may be feasible providingno transmission costs are charged to the project. A rockfilldam at the 600 foot contour that would provide a normalmaximum water surface at the 900 foot elevation would providefor most <strong>of</strong> the potential head. A 36-inch diameter penstockapproximately 1,100 feet in length would convey the water fromthe dam to a powerhouse at the 500 foot elevation. The averageeffective head would be about 360 feet.Power Capacity: - The power capacity is estimated at 1,140 kWannual average utilized in a 6-month period. This would provideabout 10,000 MWh <strong>of</strong> secondary <strong>energy</strong> annually.(7) Silver Lake - Duck RiverLocation: - The lake outlet is located in Section 6, Range 7 West,Township 11 South, Copper River Meridian. Duck River dischargesinto The·Lagoon <strong>of</strong>f Galena Bay in Section 1, Range 8 West,Township 11 South, Copper River Meridian.Drainage Area: - There are 25 square miles <strong>of</strong> drainage areaat the lake outlet as measured from U.S.G.S. map IICordova(0-7) Alaska,1I 1965 revision.Run-<strong>of</strong>f: - The U.S. Geological Survey gaged Duck River forthe 7-month period, June through December in 1913. The totaldischarge was 158,690 acre-feet for this period or 5,943.4acre-feet per square mile. The average discharge <strong>of</strong> PowerCreek for these months are 154,710 acre-feet or 7,546.8IV-15.......•••Ill


IV. ENERGY RESOURCE ALTERNATIVESacre-feet per square mile. This insufficient data indicatesthat the discharge per square mile is 79% <strong>of</strong> that for PowerCreek on 9.5 cfs per square mile. A lower discharge per squaremile is expected as the basin is protected on the south, east,<strong>and</strong> north by mountains. For this preliminary <strong>study</strong>, 9.5 cfsper square mile or an average discharge from Silver Lake <strong>of</strong>237.5 cfs is used.Regulation: - Complete regulation would require 90,000 acrefeet<strong>of</strong> storage. Raising the normal maximum water surfaceto elevation 395 would provide 102,000 acre-feet <strong>of</strong> storage.Dam Site: - A field <strong>reconnaissance</strong> <strong>of</strong> the power site has notbeen made, but a <strong>study</strong> <strong>of</strong> the U.S.G.S. map 1:63,360 suggestsa plan similar to the following would be feasible. A rockfilldam at the lake outlet raising the normal maximum water surfacefrom elevation 306 to 395 would provide storage for completeregulation. A 76-inch diameter pipeline 5,300 feet in lengthwould convey the water from the dam to a surge tank on thehill overlooking The Lagoon. A penstock 1,100 feet in lengthwould then convey the water to the powerhouse at tidewaterapproximately 1,000 feet south <strong>of</strong> the mouth <strong>of</strong> Duck River.The average effective head would be about 335 feet.Power Capacity: - The power capacity is estimated at 5,645kW prime <strong>and</strong> average power. This would provide about49,450 MWh <strong>of</strong> prime <strong>energy</strong> annually.Transmission Line: - A transmission line approximately18 miles long would need to be constructed between thehydroelectric site <strong>and</strong> the intertie transmission line.Because the terrain is similar to the intertie route itis envisioned that configuration, construction methods,<strong>and</strong> costs would be similar to the intertie transmissionline.APA25/A16IV-16


IV. ENERGY RESOURCE ALTERNATIVESStudies <strong>of</strong> possible single wire ground return (SWGR) electric lines havebeen made which show potential benefits for transmission systems undersome conditions. There is a small demonstration SWGR project operatingtoday that is successfully delivering electricity from Bethel to Napakiak.The project is also demonstrating a single phase to three phase state<strong>of</strong>-the-artconverter which is in use supplying three phase power to theBIA school in Napakiak. Construction costs for the line to Napakiakwere found to be about one third <strong>of</strong> the cost <strong>of</strong> conventional construction...The transmission system <strong>of</strong> Route (2) could obtain substantial savings inthe line costs by using this SWGR concept. Without an in-depth analysis,it is estimated that the overhead line costs can be reduced by up to onefifth<strong>and</strong> that the single phase sUbstations will cost 70% <strong>of</strong> the threephase equivalent. To these costs must be added the estimated singlephase to three phase conversion costs.In summary, a potentially feasible transmission intertie to connect theCordova <strong>and</strong> Valdez areas is represented by Route (2). Along this routeare potential hydroelectric sites which could supply <strong>energy</strong>. The intertiecould provide the opportunity to share capacity reserves <strong>and</strong> developlower cost <strong>energy</strong> in the communities <strong>of</strong> Cordova <strong>and</strong> Valdez.d. Local Small Hydroelectric DevelopmentCrater Lake, close to Cordova, <strong>of</strong>fers the possibility <strong>of</strong> a 435 kW primepowerplant with high head. Only a small dam would be required to damthe neck <strong>of</strong> the lake.•.....,..• ..,- ...It should be noted that the cannery at Orca has a water right <strong>of</strong> onecubic foot per second; a dual purpose water supply <strong>and</strong> hydropowerproject is attractive for Crater Lake discharge toward Orca.APA25/A17IV-I7..•••


IV. ENERGY RESOURCE ALTERNATIVES2. Coal ResourcesCoal is a viable alternative <strong>energy</strong> resource for Cordova. Two sources<strong>of</strong> coal for Cordova have been considered. 1) the Bering River CoalFields east <strong>of</strong> the Copper River Delta, <strong>and</strong> 2) the Healy Coal Fieldssouth <strong>of</strong> Fairbanks. Without large scale development for a world market,the Bering River Coal Fields, with an estimated delivered cost <strong>of</strong> $120 perton, do not appear capable <strong>of</strong> delivering coal or <strong>energy</strong> to Cordova atcompetitive prices. The coal from the Usibelli Mine at Healy could bedelivered to Cordova in 1981 for about $45/ton. The near future development(5-8 years) <strong>of</strong> the Beluga Coal Fields on Cook Inlet may reducethe cost <strong>of</strong> delivered coal still further.Despite the projected high cost <strong>of</strong> Bering River coal, these fields are<strong>of</strong> great local interest <strong>and</strong>, consequently, are <strong>report</strong>ed on in somedetail following. Development <strong>and</strong> production costs are identified inAppendix B.The Bering River Coal Fields are located 55 miles east <strong>of</strong> Cordova in therugged terrain around Kushtaka Mountain (see Figure 8). Exposures <strong>of</strong>coal have been mapped over an area <strong>of</strong> 45 square miles. While the fieldshave been investigated several times over the years by various governmental<strong>and</strong> private agencies <strong>and</strong> some small scale mining took place inthe early 1900 1 s, several problems have plagued development: 1) accessto a good shipping point is difficult; 2) the coal is faulted <strong>and</strong> foldedto the extent that it is difficult to follow anyone seam for more thana few hundred feet; 3) high annual precipitation, deep snowpacks, avalanching,flooding, <strong>and</strong> high winds are common in the area; <strong>and</strong> 4) recently,many <strong>of</strong> the l<strong>and</strong>s through which access might pass have been classifiedas environmentally sensitive.Despite these problems, the fields still hold an allure. This is principallybecause estimated reserves are great (S<strong>and</strong>ers, 1976, estimatedspeculative resource for a 2 square mile area near Carbon Creek at 1.6million short tons) <strong>and</strong> the quality <strong>of</strong> the coal is very high, yielding10-15,000 Btu/lb.APA25/A18IV-18


1I!t'$i'•...BERING RIVERCOAL FIELD DEVELOPMENTFIGURE!ISI!II'......,........ ""..••..•.......-..••......'........ '....• ..


IV. ENERGY RESOURCE ALTERNATIVESThe best known deposits in the Bering River area are those adjacent toCarbon Creek, which flows southwesterly along Kushtaka Ridge. The coalsare Tertiary in age <strong>and</strong> range in grade from semibituminous to semianthracite.The coal ranges in heat content from 10,000 to 15,000 Btu/lb.,has an average moisture content <strong>of</strong> 4% or less, <strong>and</strong> a relatively low ash<strong>and</strong> sulfur content. It should be noted that because <strong>of</strong> the shearednature <strong>of</strong> the deposits, considerable mixing <strong>of</strong> the coal with the countryrock may be expected. If washing is not effective in removing theforeign material, the overall character <strong>of</strong> the product will suffer.The coal is exposed on the surface in isolated pods <strong>and</strong> lenses thatusually occur near the apex <strong>of</strong> folds or along associated faults. Thethickness <strong>and</strong> persistence <strong>of</strong> beds is so variable that S<strong>and</strong>ers estimatescoal-to-waste ratios for a small mine may run as high as 1:20. Anymining operation would have to be prepared to h<strong>and</strong>le vast quantities <strong>of</strong>waste rock. A vigorous exploration program would be necessary to keepahead <strong>of</strong> mining. Hydraulic mining methods, such as those used at theKaiser Mine in British Columbia, have been suggested for the Carbon Creekcoals. The abundance <strong>of</strong> natural ground water expected in any undergroundoperation may become a positive factor for hydraulic mininginstead <strong>of</strong> a negative one for traditional mining techniques.In the unlikely case that Bering River coal is mined, a mine mouth plantcould be constructed for 25-50% more cost than a plant at Cordova. Ifthe mine mouth power plant was built in the Carbon Creek area, a transmissionline approximately 63 miles in length would be required todeliver the electric power to the Cordova diesel plant vicinity.The transmission line route would be mostly at elevations below 100 feet<strong>and</strong> would roughly parallel the road system that would connect the coalmining area to Cordova. About 37 miles <strong>of</strong> this road system alreadyexists (a portion <strong>of</strong> the Copper River Highway). (See Figures 7 <strong>and</strong> 8).APA25/A20IV-20


IV. ENERGY RESOURCE ALTERNATIVES3. Oi 1 <strong>and</strong> Gas ResourcesThe potential for economic exploitation <strong>of</strong> oil <strong>and</strong> gas resources within theimmediate vicinity <strong>of</strong> Cordova in the near future is low. The Katallaoil fields, about 50 miles southeast <strong>of</strong> Cordova, have produced oil inthe past, but current exploration <strong>and</strong> development costs would be extremelyhigh in relation to expected production. There is good potential forpetroleum reservoirs in the eastern Gulf <strong>of</strong> Alaska from 50 to 100 milesaway, although initial stratigraphic test wells in the closer, westernparts <strong>of</strong> this province have shown discouraging results. While development<strong>of</strong> these fields would undoubtedly bring indirect economic benefits toCordova, world dem<strong>and</strong> will regulate price <strong>and</strong> thus direct savings on thecost <strong>of</strong> fuel is unlikely. The Copper River Basin (120 miles inl<strong>and</strong>) israted very low in potential for oil <strong>and</strong> gas <strong>and</strong> is hardly any closerthan currently producing wells in Cook Inlet. A closer look at theproblems confronting the exploitation <strong>of</strong> the Katalla oil fields follows.Oil <strong>and</strong> gas from seeps along the shore were <strong>report</strong>ed at Katalla in 1853.Between 1920 <strong>and</strong> 1933, the Katalla area produced a total <strong>of</strong> 154,000barrels <strong>of</strong> oil from 16 shallow wells ranging in depth from 300 feet to2000 feet. The light (37.96 API), clean (O.OO%+S) oil furnished fuel<strong>and</strong> lubrication oil to Cordova <strong>and</strong> the McCarthy copper mines until therefinery at Katalla burned down in 1933. Since that time there has beenno recorded production. Through the years, claims <strong>and</strong>/or leases havebeen held by Chilkat Oil Company, St<strong>and</strong>ard Oil <strong>of</strong> California, <strong>and</strong> ArabianShield. Little activity has occurred in the area since 1961 when RichfieldOil Company drilled two unsuccessful wildcat wells (each about 6000 feetdeep) along the Bering River ten miles east <strong>of</strong> Katalla.With available information, potential reserves are difficult to estimate.There are no accurate subsurface structural maps <strong>and</strong> drillinglogs for the original wells have been lost. Past wells were drilledover known oil <strong>and</strong> gas seeps <strong>and</strong> usually produced about 100 to 300barrels per day for the first few hours, then subsequently dropped to....•..••......APA25/A21IV-21•


IV. ENERGY RESOURCE ALTERNATIVESless than 10 barrels per day. Pay zones were most commonly found between360 feet <strong>and</strong> 750 feet in depth. The reservoir rocks are complexlyfaulted <strong>and</strong> folded s<strong>and</strong>stones, conglomerates <strong>and</strong> calcareous shales.Many, thin, intercalated organic-rich shales <strong>and</strong> coal partings are theprobable source <strong>of</strong> the oil <strong>and</strong> gas. Numerous local seepages suggestthat traps are small <strong>and</strong> scattered. Therefore, while there may be asubstantial amount <strong>of</strong> petroleum trapped below the surface, it is probablynot concentrated in anyone spot. If production were similar to theearly days, it is possible that another 200,000 or more barrels mightstill be available.Production rates would be extremely slow unless some method <strong>of</strong> enhancingflow within the reservoir were used; 1/2 to 2 barrels per day per well.Previous attempts at enhancing flow by suction produced mostly saltwater.R.H. McMullin <strong>of</strong> the U.S. Geological Survey has estimated that th~onshore Gulf <strong>of</strong> Alaska province could have as much as 0.8 billionbarrels <strong>of</strong> crude oil <strong>and</strong> 0.9 trillion cubic feet <strong>of</strong> associated gas.These figures are based on a general knowledge <strong>of</strong> the lithologic,stratigraphic <strong>and</strong> structural disposition <strong>of</strong> Tertiary section from IcyBay north to the Copper River. These figures, however, do not reflectthe statistical probability <strong>of</strong> actually finding the oil or gas.Exploration for oil <strong>and</strong> gas, by its very nature, is a game against theodds. An oil company executive might consider it a worthy gamble ifhe can expect to strike oil in one <strong>of</strong> five or ten or perhaps even morewells drilled. At the costs involved in a single well, the stakes arevery high indeed for the small entrepreneur, cooperative, or utility.Other complications at Kata11a include access, transportation, <strong>and</strong> l<strong>and</strong>status. The shoreline is exposed <strong>and</strong> shallow so a port facility wouldbe costly. Access overl<strong>and</strong> would need to cross rugged terrain, manymiles <strong>of</strong> swamp, <strong>and</strong> several rivers. In addition, the route wouldcross environmentally sensitive areas. A cursory examination <strong>of</strong> l<strong>and</strong>status records <strong>and</strong> the historical index at the Bureau <strong>of</strong> L<strong>and</strong> ManagementAPA25/A22IV-22


IV. ENERGY RESOURCE ALTERNATIVESshows that since the turn <strong>of</strong> the century numerous applications for coal,oil <strong>and</strong> gas permits <strong>and</strong> leases have been filed in this area. It appearsfor the most part that existing rights have either expired or been cancelled.L<strong>and</strong> status <strong>and</strong> current leasing procedure would need to be addressedcarefully before specific sites might be considered. However, to identifyall outst<strong>and</strong>ing mineral rights would require an intensive l<strong>and</strong> statusreview beyond the scope <strong>of</strong> this <strong>report</strong>.Besides the natural gas that occurs along with the oil at Katalla,several observations <strong>of</strong> natural gas have been made in the Cordova area.Reportedly, geysers <strong>of</strong> mud <strong>and</strong> gas were observed on the Copper RiverDelta during <strong>and</strong> shortly after the 1964 earthquake. The most reasonableexplanation is methane "gas derived from buried organic debris was releasedduring settlement <strong>of</strong> the loose Delta sediment. There is little chancethat any methane could be collected from shallow wells in the Delta.Pe~odically,large exhalations <strong>of</strong> gas have been noted from beneath thesurface <strong>of</strong> Kushtaka Lake. In winter the gases have been known to burstthrough the ice. The gases here are probably related to buried coalseams which are prevalent in the area. While these gas occurrences area curiosity, it is unlikely that any use can be made <strong>of</strong> them in the nearfuture.It should be noted at this point that Chugach Natives, Inc., is the AlaskaNative Regional Corporation for the area encompassed in this <strong>study</strong>. OnceChugach receives its Alaska Native L<strong>and</strong>s Claim Act <strong>of</strong> 1971 entitlement<strong>of</strong> about 377,000 acres, Chugach will become primarily a natural resourcescompany. L<strong>and</strong>s currently under consideration for transfer to Chugachinclude several <strong>of</strong> the small potential hydroelectric sites discussedin this <strong>study</strong>, along with the Bering River coal field area <strong>and</strong> theKatalla oil <strong>and</strong> gas area.Chugach Natives, Inc., has determined that neither the Bering Riveror Katalla resources show sufficient economic promise to justify developmentsolely for local use. However, as a natural resources company, ChugachAPA2S/A23IV-23.........ar••..•......••-..•..•••


IV. ENERGY RESOURCE ALTERNATIVEShas begun <strong>and</strong> intends to continue to pursue the development <strong>of</strong> theseresources for non-local consumption. If Chugach's negotiations aresuccessful on the coal resource in particular, then the economics <strong>of</strong>utilizing a portion <strong>of</strong> the coal for local use are altered radically <strong>and</strong>could become a viable <strong>energy</strong> alternative for Cordova.4. Geothermal ResourcesThe possibility <strong>of</strong> utilizing geothermal <strong>energy</strong> for generation <strong>of</strong>electric power or for heating in Cordova is very remote. No geothermalresources have been recorded in the literature or <strong>report</strong>ed by localresidents to exist within a reasonable distance <strong>of</strong> Cordova.5. Wind ResourcesWind generating <strong>and</strong> heating devices are generally uneconomic unless meanannual wind speeds are at least 12-15 miles per hour (mph). The meanspeed at the Cordova Mile 13 Airport is 4.4 mph <strong>and</strong> Corps <strong>of</strong> Engineersdata for Cordova indicates a mean wind speed <strong>of</strong> 7.9 mph at the smallboat harbor. This resource has thus been eliminated as <strong>of</strong>fering anysignificant contribution to Cordova's <strong>energy</strong> future. However, WindEnergy Conversion Systems are discussed at length in Appendix C because<strong>of</strong> a great deal <strong>of</strong> locally expressed interest in such systems.It has been estimated that fuel oil will have to rise to more than $5 pergallon before wind heating becomes economic in areas with significantlyhigher wind speeds than Cordova.The only two proximate sources <strong>of</strong> wind with possibly sufficient speedsare the adiabatic winds <strong>of</strong>f glaciers <strong>and</strong> high winds verbally <strong>report</strong>ed inthe Copper River Delta. However, no data is currently available forthese resources <strong>and</strong> both resources are considerable distances fromCordova.APA25/A24IV-24


6. Solar ResourcesIV. ENERGY RESOURCE ALTERNATIVES.'" .......A comparable <strong>study</strong> indicates that with proper new design considerations,passive solar heating can provide 40% <strong>of</strong> the heat required by an averageresidence, even in the coldest months. Active solar collectors <strong>and</strong> heatstorage facilities installed in newly built homes have been found to becompetitive with fuel oil furnaces only if the cost for diesel oil ismore than $2.50 per gallon at present equipment cost. Solar photovoltaic<strong>energy</strong> conversion is still uneconomical at an estimated $l/kWh for thepresent state-<strong>of</strong>-the-art.7. Tidal ResourcesLarge tidal currents were verbally <strong>report</strong>ed in The Narrows area nearCordova. However, our present underst<strong>and</strong>ing is that these currents are<strong>of</strong> insufficient magnitude for economic <strong>energy</strong> capture. Furthermore,tidal facilities are very capital cost intensive <strong>and</strong> require expensivestorage facilities unless they are part <strong>of</strong> a large power grid. Thesefactors serve to eliminate this resource for further consideration forCordova.8. Biomass ResourcesDue to Cordova's location in the Chugach National Forest, wood is inquite abundant supply. However, the magnitude <strong>of</strong> wood supply requiredto fulfill all <strong>of</strong> Cordova's present <strong>and</strong> future <strong>energy</strong> needs would greatlydecimate this protected (<strong>and</strong> likely environmentally unobtainable) resource.Use <strong>of</strong> wood for residential heating is expected to continue to provide about2 percent <strong>of</strong> such needs in Cordova.Another biomass resource available in Cordova is the use <strong>of</strong> cannerywaste to produce biogas (two-thirds methane) by anaerobic digestion.The wastes are decomposed in atmospherically sealed <strong>and</strong> heated tanks,resulting in biogas <strong>and</strong> a high quality fertilizer effluent. However, arough calculation for wastes at the large St. Elias Ocean ProductsAPA25/A25IV-25...'....It..•....•.... .........---


IV. ENERGY RESOURCE ALTERNATIVESfacilities indicated that only about 20 kW <strong>of</strong> base load generation couldbe obtained. This contribution to the overall Cordova <strong>energy</strong> picture isessentially negligible.9. Waste Heat <strong>and</strong> Cogeneration ResourcesThe present use <strong>of</strong> fossil fuels (coal, gas, oil) to produce more usefulforms <strong>of</strong> <strong>energy</strong> (electricity or motive power) is far less than 100percent efficient. For example, if a machine burns a certain quantity<strong>of</strong> fossil fuel <strong>and</strong> produces useful output (shaft horsepower or electrical<strong>energy</strong>) equivalent to 30% <strong>of</strong> the fuel burned, the <strong>energy</strong> representedby the remaining 70% <strong>of</strong> the fuel will appear as unused or "waste"heat. Such heat most <strong>of</strong>ten appears as hot exhaust gas, tepid to warmwater (65°F-180°F), hot air from cooling radiators, <strong>and</strong> direct radiationfrom the machine in question such as a steam turbine or diesel engine.a. Diesel Waste HeatDiesel waste heat can be recovered from engine cooling water <strong>and</strong>exhaust or from either source separately. The waste heat is typicallytransferred to a water-glycol circulating system in Alaskan applications.The heated circulating fluid can be used for space,water, or process heating. Capture <strong>of</strong> diesel waste heat to powerbinary cycles could provide about 300 kW based on current dieselusage. Several binary cycle projects are currently in the planningstage in Alaska.b. Gas Turbine Waste HeatGas turbine waste heat is typically recovered from the exhauststream passing through commercially available waste heat boilers<strong>and</strong> producing steam or a heated water-glycol mixture.APA25/A26IV-26


IV. ENERGY RESOURCE ALTERNATIVES.,..Small combustion turbines with waste heat recovery are manufacturedboth domestically <strong>and</strong> overseas. Current installed capital costsfor cogeneration equipment depend on site conditions, local laborcosts, <strong>and</strong> ancillary equipment; however, average values for systemsare <strong>report</strong>ed to range from about $350/kW to $700/kW....c.Steam Turbine CogenerationApproximately 30% to 40% <strong>of</strong> the heat supplied by the fuel in aconventional fossil steam electric generating station is convertedinto electric <strong>energy</strong>. These losses can be reduced when one <strong>of</strong> anumber <strong>of</strong> alternate schemes for converting power plants into cogenerationplants is implemented. For example, the total loss can bereduced to less than 25% if cogeneration <strong>of</strong> steam is employed.Such steam could be used for district heating.The actual annual fuel savings achievable in a district heatingsystem are determined by such factors as the percentage <strong>of</strong> totalsystem heat load to be supplied by peak heating plants, the operatingpoint <strong>of</strong> each cogeneration unit, loading sequence selectedfor the cogeneration units, total heat <strong>of</strong> the steam extracted fromeach cogeneration unit, fuel differential required to replace thereduced electric generation <strong>of</strong> cogeneration turbines by less efficientunits, <strong>and</strong> unit availabilities.Results obtained from an analysis <strong>of</strong> these variables will vary fromsystem to system depending on the type <strong>of</strong> cogeneration units <strong>and</strong>district heating equipment installed. A recent <strong>study</strong> for a planneddistrict heating system using modified turbines indicated thatslightly more than 50% fuel savings can be achieved over a typicalannual heating cycle...iii·.......•..........-....10. ConservationConstruction <strong>of</strong>, or retr<strong>of</strong>it for, well insulated homes in the Cordovaarea can provide significant residential fuel savings. Estimates for aAPA25/A27IV-27.......,.......•


IV. ENERGY RESOURCE ALTERNATIVES1000 square foot IItypical" home indicate: a well insulated home usesabout 540 gallons <strong>of</strong> oil per year; a home with average insulation woulduse about 830 gallons per year; <strong>and</strong> a poorly insulated home would requirenearly 1380 gallons per year. Clearly, individual savings can be significant.Current commercial equipment allows recycling <strong>of</strong> diesel lubricating oilto replace 5% <strong>of</strong> the diesel fuel. At current prices, this could saveabout $75,000 <strong>and</strong> 65,000 gallons <strong>of</strong> diesel fuel per year. Such a systemis currently being implemented in Cordova on a limited scale.11. Other ResourcesThe following resources <strong>and</strong> technologies are either still in need <strong>of</strong>technology development for economic utilization or <strong>of</strong>fer only small,decentralized applications that will serve to replace some diesel fueluses.a. UraniumNo commercial technology exists in the 10 MWrange.b. Coal Gasi fi cati onThe technology is costly <strong>and</strong> unproven commercially.c. Fuel CellsThe technology is costly <strong>and</strong> still in the developmental stage.d. HydrogenHydrogen can be produced from surplus hydroelectric power; thistechnology is expected to become economic in the 1990's.APA25/A28IV-28


•IV. ENERGY RESOURCE ALTERNATIVESHydrogen stored as hydrides may make significant impact in thetransportation sector in the long term.,.J»e.Heat for Heat PumpsThis is a proven small scale technology <strong>and</strong> is discussed indetail in Appendix C.....••..•.................APA25/A29IV-29•..


V. ENERGY TECHNOLOGY ALTERNATIVESV. ENERGY TECHNOLOGY ALTERNATIVESAppendix C contains detailed pr<strong>of</strong>iles <strong>of</strong> appropriate <strong>energy</strong> conversiontechnologies for Cordova, including descriptions, performance characteristics,costs, special <strong>requirements</strong> <strong>and</strong> impacts, <strong>and</strong> a summary <strong>and</strong>critical discussion. Brief abstracts <strong>of</strong> the following relevant pr<strong>of</strong>ilesare presented in this section.• diesel-electric generation• oil heating• hydroelectric generation• electrical heating• transmission interties• coal fired steam-electric generation• coal <strong>and</strong> wood heating• diesel lube oil recycling• diesel waste heat recovery <strong>and</strong> use• steam cogeneration systems• conservation• wind <strong>energy</strong> conversion systems.• heat pumpsA general summary <strong>of</strong> <strong>energy</strong> available in the primary resources consideredis shown in the following table, Table V-I.APA25/bIV-I


V. ENERGY TECHNOLOGY ALTERNATIVESTABLE V-IFUEL ENERGY CONTENT..Fuel TypeEnergy Contentin Btu/pound....No.6 Fuel Oil (Diesel)BiogasBituminous CoalSub-Bituminous CoalLignitic CoalWoodWater at 100 Foot HeadHot Water at 1°F Temperature DifferenceAir Moving at 22 mph (stp)17 ,400 19,00015,000 15,70013,000 13,60011,0006,500 7,0005,000 8,60081.02.....•....1. Diesel-Electric GenerationIn the diesel fueled engine, air is compressed in a cylinder to a highpressure. Fuel oil is injected into the compressed air, which is at atemperature above the fuel ignition point, <strong>and</strong> the fuel burns, convertingthermal <strong>energy</strong> to mechanical <strong>energy</strong> by driving a piston.....--Diesel engines driving electrical generators are one <strong>of</strong> the most efficientsimple cycle converters <strong>of</strong> chemical <strong>energy</strong> (fuel) to electrical <strong>energy</strong>.2. Oil Heati ng.. ..•Fuel oil is burned with air in a burning unit which produces hot airor hot water for space heating. This is the most widespread heatingtechnology practiced in Cordova.APA25/b2 V-2


V. ENERGY TECHNOLOGY ALTERNATIVES3. Hydroelectric GenerationHydroelectric generation involves water turning a turbine which in turndrives a generator. Several families <strong>of</strong> turbines exist; application isa function <strong>of</strong> flow <strong>and</strong> head (distance from the top <strong>of</strong> the water surfaceto the turbine).Development <strong>of</strong> hydroelectric sites in the Arctic encounters many problemswhich are not present in more temperate areas <strong>of</strong> the world.Logistics problems associated with engineering <strong>and</strong> construction <strong>of</strong>hydroelectric projects in the harsh Arctic environment are certainlyamong the most difficult <strong>and</strong> challenging <strong>of</strong> any in the world. Inaddition, construction itself is a challenge, since only in protectedlocations, such as heated enclosures <strong>and</strong> underground, can constructionproceed with any efficiency during the cold period.Hydroelectric sites must be chosen which have adequate storage to allowfor generation during the cold months when inflow is diminished, as wellas to provide carry-over storage for dry years.4. Electric HeatingSince the capacity <strong>of</strong> the hydro project is typically relatively largecompared to the initial dem<strong>and</strong> <strong>of</strong> the supplied area, the cost per kWhis rather high since the large investment has to be paid for whetherits capacity is used or not. Utilization <strong>of</strong> this surplus capacity inelectric home heating (at a rate comparable to cost for heating withother systems) is an attractive possibility. The problem arises whenat a later point in time -- the area dem<strong>and</strong> (minus the electric heat)approaches the capacity <strong>of</strong> the hydroplant.APA25/b3 V-3


•V. ENERGY TECHNOLOGY ALTERNATIVES•The following scheme appears to allow for all the benefits <strong>and</strong> avoidsmost <strong>of</strong> the problems electric home heating can have for a utility <strong>and</strong>the homeowner:iii!1.2.The homes are built with a conventional heating system plus electricheat.The utility pays for the installation <strong>of</strong> the electric heat <strong>and</strong> itscontrol.•3.The utility sells the <strong>energy</strong> for the electric heat at a rate equalor lower than the other heat supply fuel cost.4.The utility is allowed to control utilization <strong>of</strong> the electricheat -- that is, turn it <strong>of</strong>f during times <strong>of</strong> peak dem<strong>and</strong>. Duringthese times the IInormalll heating system supplies comfort heatingfor the home. The existing alternate home heating system actuallyprovides peaking capacity to the utility.5. Transmission IntertiesTransmission interties provide electrical power connections betweencommunities <strong>and</strong> electrical generation sources. The electricity istransmitted by wires or a single wire with ground return.The large (50 MW) transmission intertie discussed in the previous sectionis <strong>of</strong> size proven to be economic in other locales. Costs couldconceivably be lowered by using single wire ground return (SWGR) transmission.Demonstration projects utilizing this type <strong>of</strong> transmission arepresently under contract with the State <strong>of</strong> Alaska, Divison <strong>of</strong> Energy <strong>and</strong>Power Development. As SWGR is increasingly proven technically <strong>and</strong> economicallyfeasible in Alaska, this type <strong>of</strong> construction holds great promisefor providing less costly electric <strong>energy</strong>.•....- ..APA25/b4 V-4•


V. ENERGY TECHNOLOGY ALTERNATIVES6. Coal-Fired Steam-Electric GenerationFor coal-fired steam-electric generation, coal is ground to roughly2-inch diameter or less chunks <strong>and</strong> fed into a boiler or pulverized<strong>and</strong> blown into a boiler. The coal is then burned in the boiler toproduce steam that is then exp<strong>and</strong>ed in a turbine which drives a generatorto produce electricity.Steam plants account for the majority <strong>of</strong> electrical generation in theUnited States today. Although steam plants can accommodate a wide range<strong>of</strong> loads, U.S. economies <strong>of</strong> scale indicate that the cost per unitincreases sharply in sizes below about 50 MW. It should be noted thatEuropean coal-steam generation units are more economically employed in theless than 10 MW range.A 5 MW coal-steam plant for Cordova could be constructed at a capitalcost <strong>of</strong> about $I,700/kW; a 10 MW plant could cost about $I,200/kW.Operating costs for such plants are relatively high due to the need forhighly skilled operators.It should also be noted that storage <strong>requirements</strong> for a coal plant inCordova could be a stockpile 20 feet high <strong>and</strong> 250 feet square. Due tothe high rainfall in the Cordova area, a 20,000 gallon per day (nominal)treatment plant would be required to treat run<strong>of</strong>f from the stockpile.A similar plant at Elmendorf Air Force Base operated well enough todischarge water to Ship Creek, a salmon spawning area.7. Coal <strong>and</strong> Wood HeatingCoal or wood is mechanically or h<strong>and</strong> fed into a combustion chamber whereit is burned with air to produce hot air or heated water for space heating.APA25/b5 V-5


V. ENERGY TECHNOLOGY ALTERNATIVES•8. Diesel Lube Oil RecyclingA number <strong>of</strong> proven commercial systems exist for cleaning <strong>and</strong> recyclingdiesel engine lubricating oil for use as diesel fuel when blended as 1part recycled oil to 20 parts diesel fuel. These systems are generallysuited to fleets <strong>of</strong> diesel engines (25, more or less) as fewer units donot produce enough used lube oil for the 1:20 ratio <strong>of</strong> the fuel mix.9. Diesel Waste Heat Recovery <strong>and</strong> UseTypically 30% <strong>of</strong> the fuel <strong>energy</strong> supplied to a diesel-electric set isconverted to electricity, 30% is transferred to cooling water, 30% isexhausted as hot gas, <strong>and</strong> 10% is radiated directly from the engineblock. The exhaust heat in a diesel is <strong>of</strong> higher temperature <strong>and</strong> moreeasily used than the cooling water heat, but higher initial costs <strong>and</strong>increased operating complexities are encountered when attempting torecover <strong>energy</strong> from the exhaust.10. Steam Cogeneration•.,..IIII•••Cogeneration involves use <strong>of</strong> some <strong>of</strong> the steam used to drive turbinegeneratorsfor heating or industrial process loads. Cogeneration iswidely used, particularly in the Sc<strong>and</strong>anavian countries, to providesteam for district heating systems.11. Conservation...Conservation measures for Cordova would mainly be <strong>of</strong> the passive type:insulation, arctic entrances, double or triple glazed windows, <strong>and</strong> thelike.These measures decrease heating <strong>energy</strong> <strong>requirements</strong> for thetypical residence.12. Wind Energy Conversion SystemsAs has been noted in the previous section, the wind speeds at Cordovaare apparently too low for economic generation <strong>of</strong> <strong>energy</strong> from the wind..,APA25/b6 V-6•


V. ENERGY TECHNOLOGY ALTERNATIVESHowever, a detailed pr<strong>of</strong>ile <strong>of</strong> the technology is presented in Appendix Cbecause <strong>of</strong> local interest <strong>and</strong> the possibility <strong>of</strong> properly locatedresidences adapting this intermittent <strong>energy</strong> source.13. Heat PumpsA heat pump operates much like a refrigerator or air conditioner.The heat pump extracts heat from a source at low temperature (air orwater) <strong>and</strong> rejects it to a sink (a building, for example) at a highertemperature by input <strong>of</strong> electrical <strong>and</strong> mechanical work.APA25/b7 V-7


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVESVI.EVALUATION OF FEASIBILITY OF ENERGY ALTERNATIVESThis section outlines the six electrical plans <strong>and</strong> a combined electricalwasteheat recovery plan formulated to meet Cordova's <strong>energy</strong> <strong>requirements</strong>to the year 2000. These plans, or scenarios, are designed to meet AlaskaPower Authority "St<strong>and</strong>ard Criteria" for <strong>reconnaissance</strong> studies; a basecase plan is developed that results from a continuation <strong>of</strong> current <strong>energy</strong>practices <strong>and</strong> serves as a basis for comparing alternative plans that alsomeet forecasted <strong>requirements</strong>. All plans are intended to provide a commonlevel <strong>of</strong> reliability.The following development scenarios are necessarily speculative. Theyimplicitly contain various assumptions regarding resource availabilities,development costs, market prices, <strong>and</strong> technology state-<strong>of</strong>-the-art. Theyare based on the data available for this <strong>study</strong> <strong>and</strong> engineering experiencewith other projects in Alaska. The scenarios have been presented in a waywhich allows easy adjustment <strong>of</strong> parameters used for the analyses as morespecific data become available.Only the utilization <strong>of</strong> local hydro, transmission intertie with Valdez(with <strong>and</strong> without small hydro development) <strong>and</strong> Healy Coal, appear tobe technically <strong>and</strong> economically feasible for Cordova's overall needsat this time. Table VI-1 summarizes the alternative plans evaluatedbased on APA recommended economic factors <strong>and</strong> Figure 9 graphicallycompares the present worth cost <strong>of</strong> the alternatives. Appendix D containsdetails <strong>of</strong> the analyses.TABLE VI-1COSTS OF MEAN ALTERNATE DEVELOPMENT PLANSEARLIEST YEAR YEARYEAR OF 2000 ACCUMULATED 2041 ACCUMULATEDALTERNATE PLAN OPERATION PRESENT WORTH PRESENT WORTHElectric w/heating (Surplus@ 6.25¢/kWh) 1983 $104,734,000 $237,571,000Electric w/heating (Surplus@ l¢/kWh) 1983 96,758,000 229,595,000APA25/C1VI-l


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVESDiesel Generation - Base Case 1981 64,383,000 168,527,000Coal Generation - Carbon Creek 1983 76,190,000 165,634,000Diesel Generation w/Waste Heat 1983 56,507,000 148,968,000Coal Generation - Healy Coal 1983 43,236,000 93,065.000Intertie (Surplus @ 6.25¢/kWh) 1983 45,076,000 89,297,000Intertie - (Surplus @ l¢/kWh) 1983 37,194,000 81,415,000Local Hydro 1983 28,220,000 61,720,000•..•lit.1.Diesel Generation Base Case Plana. Plan ComponentsDiesel generation for power <strong>and</strong> fuel oil for heating.b. Timing <strong>of</strong> System Additions2500 kW additions in 1985 <strong>and</strong> 1995.IIIc. Plan DescriptionThis base case plan assumes exclusive continuation <strong>of</strong> dieselgeneration for power <strong>and</strong> fuel oil for heating; this plan resultsfrom continuation <strong>of</strong> present practices in Cordova <strong>and</strong> serves asthe basis for comparison <strong>of</strong> the alternative plans following.All plans are based on the mean growth scenario as it is the mostprobable scenario <strong>and</strong> provides the most meaningful base forcomparisons...•2.Figures lOA <strong>and</strong> lOB follow illustrate this oil based plan.Healy Coal Generation Alternative Plana. Plan ComponentsCoal-fired steam-electric generation at Cordova with dieselgeneration supplement.b. Timing <strong>of</strong> System Additions5 MW coal-fired generating units in 1983 <strong>and</strong> 1991.-•.. .,..APA25/C2VI-2


oo--.l~~(JI o~ ~ ~ ~ 9 ID 0000 0 0 0I I I I j I I~~~~~~~~~~~~~~~~~~~~~I1~1!1!1~II~I~I~II!I!I!I~I~I~I~I~1~1~1~1~1~1~1~1j1!1j1I~1~1~~l~jll~lIl~Il~11111111~~~l~~~~~l~~II~~I~~I~~~~IiACCUMULATED PRESENT WORTH (MILLION DOLLARS)N (JI :;; Ui c;; Iio o o0 0 ~~ i ~ I I IELECTRIC WITH HEATING (SURPLUS @ 6.25 t I KWH)NID 00 0 0I I I~0INN0IN(JI0IN~0I~~~~~~~~~~~~jI~~~~~~I~j~j~j~~~l~lII~~~~~~tl~~~~j~~~~~~I~~~I~~~l~~~I~~~~1II~~~Ilf~1~l~1~1~1~1~111~II~1~1~~~iELECTRIC WITH HEATING (SURPLUS@ It IKWH)1,~j1j1j~jljl~I~I~1jljl~I~I~1~1~1~1~ll1l1l1~1~1~IIll~1~1~1l1~lj1~1~1~11111~1I1I1I~11~j~DIESEL GENERATION -BASE CASE:l~III~~~~111~!~1~1~I~~~1~111~1~1~1~1~111~1~1i1i1j!j!i!i!I1j1j!i1j1ij!~~~!jlj1j1jjj~iji~i~~~~i~i~~~ti "]COAL GENERATION - CARBON CREEK..,~lI~lll1~1l1jlj~~~~1l1~~j1~1~1~1l1i1jljlj1jl~lI~I~~~illl~I~i~l~l~l~~~~~i~~11:DIESEL GENERATION WITH WASTE HEAT0""'T1::oo fll- l> en-i r fll-< -i Zfll-i~~l>0-i::<strong>of</strong>ll-i,,~rOl>0Zenen-i.,,0C;"'T1c~OfT'!0(0::0o:jll~l1lll1ll~1lll~~I~l~~l~l~l~l~l1l~1~ll~~lll~~l~~~~lll~~1l] 1COAL GENERATION - HEALY COAL~1~j~j~~~~~1~~II~1Il~~1~I1~1~~1~ljljl11j~1Ilj~j111j~1INTERTIE (SURPLUS ~ 6.25 '/KWH)'~I~I~ljIl11j~j~1~11l~jl~lilili1I~ljljljlIjlilINTERTIE (SURPLUS @ I $/KWH)~jlillIl~l~~lljl~~1~1~1~111jlllLOCAL HYDROIIJ""0-


1700016 non15 00014000130 0012 00"1100010 0000" ,-0070 006 0004000 3000-1980/'VHIGH)/ // ~~ ~PROJECTIONi- -/ V/ /., /DIESELCAPACITY\. /- ~----- " filii"'"~--~. /' 1.. .......... ,.,."".-- ",.-.......-X~',/'/' --- ,.----~.--.PEAK~il -----DEMAND~-,."~ ~....IBASE LOAD!-'~- - -» .---PEAK,/ ~EAN PROJECTION ................,..""'"_e',. ............. ~ .....- """-·~Gc LOWPROJECTION~.- 1981----- POWERDIESEL ONLY SCENARIO~ ~-----FIGURE lOA.-- .- CITY OF COAOOVA1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1996 1999 200YEAR'111 ' I 'I " 'I •• • 111 " ,. '. 'I ". ,.. II 'II , I • • f' ,.,." .-...-/.~


o ...... --............... ~~--1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 199~ 1996 1997 1998 1999 2000YEARELECTRICAL ENERGYREQUIREMENTDIESEL ONLY SCENARIOCITY OF CORDOVAFIGURE lOB


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVES,II"c. Plan DescriptionThis plan is based on mean population growth <strong>and</strong> assumes retirement<strong>of</strong> present diesels except for back-up <strong>and</strong> peaking use.Coal-fired units are sized in 5 MW increments, a reasonable economicsize. This plan attempts to keep the required reserve capacitylow <strong>and</strong> to phase the transition to a totally coal-fired plant insuch a manner as not to render the existing diesel plant obsoleteat an early date.Figures 11A <strong>and</strong> lIB depicts this alternate electrical generationplan.3. Carbon Creek Coal Generation Alternative PlanThis plan is identical to the preceding Healy coal plan except thepower plant is located at the Carbon Creek mine mouth <strong>and</strong> electricityis transmitted to Cordova..,..•....- •4. Intertie with Valdez Alternative Plana. Plan ComponentsSurplus electrical <strong>energy</strong> by intertie with Valdez supplemented bySilver Lake hydroelectricity almost entirely replacing dieselgeneration.b. Timing <strong>of</strong> System AdditionsThe intertie is assumed to be operational <strong>and</strong> surplus <strong>energy</strong>available in 1983 <strong>and</strong> Silver Lake is assumed on line in 1991.c. Plan DescriptionDiesel generation would be supplemented by surplus <strong>energy</strong> availableby intertie with Valdez <strong>and</strong> briefly replaced by the surplus in 1986...•..•APA25/C6VI-6....lilt.


7"""6"""'"/---,,.,..,...14000/ /1500'"/ ~1 -~101000--,,,,,,,,",'.......,,..,..,..•--6 """,..~~EXPAND 1 RETIV HIGH}- COAL 8r4 PLANT DIESEL PROJECTION..... ---- ......... - ""--- -///'/// /".~ ~ "","'"MEAN"",.," i"""'" ~~• ....-1- /'-7"""""11-""""""- ~.",."..-..000-,....-// ;A ... PROJECTI~ ~.~ ./1 ~ ,..PEAK jDEMAND_I ~~_ ~ ~ !L ---... ."".....",...~ ---- ~-----..."". lc"ow- .,.-.L' ~ 1- PROJECTION~- . ( ~ ...... ~~ PEAK POWER~........-COAL SCENARIOr- ,'M1URE II AV ___.--~ .- CITY OFCORDOVAI" 1,.1 "82 1981 I'" 1985 1 .. 6 1987 I'" M9 I9to 1991 1992 1993 1994 1995 &96 1997 ItlII 1999 2000YU~."".."..


:I:• 220//////////////////////////////////////////////f)Q..10'/////////// ///////////////////////////////1980 19811984 19851986YEAR1991 1992 1995 19M1997lIN 2000ELECTRICAL ENERGYREQUIRNENTCOAL SCENARIOCITY Of COADOVA, I , . , , , .f I , ,I , I ,• • , . , , , . I• I , , .FIGURE liB, , I • , I , ,


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVESDiesel generation would be utilized as supplement until the 1991addition <strong>of</strong> conservatively estimated Silver Lake hydroelectricpotential <strong>and</strong> would then be retired except for slight use in1997-2000.Figures 12A <strong>and</strong> 12B depict this alternate electrical generationplan.5. Intertie Alternative Plan with Electrical Heatinga. Plan ComponentsSurplus electrical <strong>energy</strong> by transmission intertie with Valdezcombined with new intertied hydroelectric projects replacingdiesel generation.b. Timing <strong>of</strong> System AdditionsSurplus available in 1983. Hydroelectric additions in 1985(optimistic Dead Creek estimate); 1988-(Silver Lake); 1990(Lake 1488), 1992 (Lake 649), <strong>and</strong> 1995 (Lake 1878).c. Plan DescriptionThis alternative plan is not directly comparable with the otheralternative plans <strong>and</strong> the base case diesel only plan: this planassumes the development <strong>of</strong> sufficient intertied hydroelectricprojects to provide all electrical generation <strong>requirements</strong> for Cordova<strong>and</strong> most <strong>of</strong> the electrical capacity required for total conversion<strong>of</strong> Cordova to electric resistance heating. It is recognized thatall alternative plans would have to be formulated to meet the totaldem<strong>and</strong> that includes the space heating <strong>energy</strong> <strong>requirements</strong> in orderfor plans to be strictly comparable; however, the magnitude <strong>of</strong> thetotal <strong>energy</strong> requirement is such as to make the other alternativeshighly impractical <strong>and</strong> <strong>of</strong> little relevance to this <strong>reconnaissance</strong><strong>study</strong>. This alternative case is presented as illustrative <strong>of</strong> the costAPA25/C9VI-9


7000.oon /~OOO1400013000•-000•I.I ~ ....~,~ ...../~~,~ /'I ~ /~100" ,".. r- -/100010000.- SILVER LAKE HYDRO"'''' .... ...,1'-....cl // .--", '


40~--------~----~----~--~~--~----~----~--~~--~-----r----~----r---~----~----~----~--~r---~----~oW1980 1982 Utl3//////////////////////////////////////////////////1984 1 .. 5 1 .. 7 IMI 1189/////////////////////////////////////////////////1990YEAR1991 1992 1,.3ELECTRICAL ENERGYREQUIREMENTINTERTIE SCENARIOCITY OF CORDOVAFIGURE 128


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVESpenalty <strong>of</strong> continued reliance on diesel generation. The accumulatedpresent worth cost to provide an equivalent amount <strong>of</strong> heating withfuel oil over the same period would be $72,800,000. Adding thisamount to the present worth cost for the base case diesel generationproves that it would cost less to have electricity plus electricalheating by hydroelectricity than continuation <strong>of</strong> current practice,i.e., electricity with diesel generation <strong>and</strong> heating with fueloi 1...II..Figures 13A <strong>and</strong> 13B depict this alternative plan <strong>and</strong> reflect arelatively even rate <strong>of</strong> hydro site development <strong>and</strong> the fact thatnot all <strong>of</strong> Cordova is expected to utilize electric space heating.6. Local Hydroelectric Alternative Plana. Plan ComponentsDiesel generation eventually supplementing hydroelectricity fromtwo local projects.b. Timing <strong>of</strong> System AdditionsHydroelectric projects in 1983 <strong>and</strong> 1985.••..•c. Plan DescriptionDevelopment <strong>of</strong> hydroelectricity from Power Creek <strong>and</strong> Crater Lakewill require supplemental diesel generation to meet seasonalhydro MWH deficits.•Figures 14A <strong>and</strong> 14B depict this plan.7. Diesel Generation With Waste Heat Recovery Plana. Plan Components•..•Waste heat recovery equipment installed in the existing powerplant to provide steam to 1evelize heat load <strong>of</strong> two canneries;APA25/C12VI-12....•


50ADD LAKE 1878~ ~.--~- ~---40r20 ~4tDD LAKE 64 :J"-....~- ~---- -ADD LAKE 1488"\l~-.-r--~IIIIPEAK DEMAND'-.....J...----~ ELECTRICITY 8- ELECTRIC HEATING~ MEAN PROJECTION~R/ t>------ t- -ADD SILVER LAKE~ CAPACITYI"""'"I- ....... I'-0~o1980• -~ I.~."~ADD SURPLUSADD DEAD CREEK~RETIRE [)IESELDlESEr [ I 1985 1990YEAR1995 2000PEAK POWERELECTRICAL HEATING SCENARIOCI TY OF CORDOVAFIGURE 13A


180~--~~--~----~-----+-----+-----+----~----4-----+-----~----~--~----~-----+-----r----~----4-----+-----+---~160~--~~--~----~-----f-----+-----t----~----4-~--+-----t-----~--~----~~~~----~~~~::::~::==t-----t---~ECTRICITY INCLUOIATING, MEANPROJECTION20."~~~~~~//// ////o //// ////1980 1981 1982 1983 1984 1985 1986 1988 1989 1990 1991 1992 1993 I~ 1995 1996 1997 1998 1999 2000YEARELECTRICAL ENERGY REQUIREMENTELECTRIC HEATING SCENARIOCITY OF CORDOVAFIGURE 138,. • I , 1 , 1 , . , , , , , , , , , . , , , ,, , , , , 11 , I , , I ,


17 0001615000 r---- /V000// /1400013000127000CRATER LAKE",oon ...,110001090"" ...,...,OO~8 ""'"-/,--.--- - I-~--- --~---~--7... - ~-..1/


40r----r----~--_,----_.----r_--_r----._--~----~--~----~----r_--~----._--~----~--~~--_r----~--~30r---_+----+----1----~----~--_+----+_--_+----+_--_;----~----~--_+--__±ENERGY REQUIREMENTMEAN PROJECTIONo\980 19811982 1983 1984 1985 1986 1987 1988 1989 1990 1991YEAR1992 1993 1994 1995 1996 1997 1998 1999 2000ELECTICAL ENERGYREQUfPt£MENTLOCAL HYDROWITH DIESEL SCENARIOCITY OF CORDOVAFIGURE 148•• ,."., 'I 'I"" ,." ,. 'I ,.1:, '. 'I '. II"


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVESprovide hot water for space heating <strong>of</strong> a motel, the communitycenter building, <strong>and</strong> the swimming pool; <strong>and</strong> heat the city watersupply. (See Example 1, Appendix C.3.S.2).b. Timing <strong>of</strong> System AdditionsSystem installed <strong>and</strong> operational in 1983c. Plan DescriptionThis plan assumes continuation <strong>of</strong> diesel generation for power <strong>and</strong>,except as described in "a" above, fuel oil for heating. Wasteheat recovery equipment would be installed on the existing generationequipment.8. Evaluation <strong>of</strong> Alternative Plansa. INTRODUCTIONIn accordance with Alaska Power Authority (APA) ReconnaissanceStudy Regulations, the alternative plans presented have beenevaluated on the basis <strong>of</strong> the economic, environmental, <strong>and</strong> technicalfactors following:• EconomicPresent worth <strong>of</strong> plan costs using "APA AnalysisParameters for FY 181"• EnvironmentalCommunity preferencesImpact on community infrastructureTiming in relation to other capital projectsAir qualityWater qualityFish <strong>and</strong> wildlife impactAPA25/C17VI-17


L<strong>and</strong> useTerrestrial impacts.VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVES.' .i•..• TechnicalSafetyRe 1 i abil ityAva il abil i tyb.ECONOMIC FACTORSThe costs <strong>of</strong> each alternative plan, both capital <strong>and</strong> operating,were assigned to their appropriate years in the 20 year planningperiod beginning in 1981. These costs were then discounted at3 percent per year <strong>and</strong> summed to determine the present value <strong>of</strong>plan costs.Potential plan outputs other than electrical <strong>energy</strong>, such as heatfor space or water heating, are considered as separate economiccases. The net benefits <strong>of</strong> these outputs or I residua1s" areestimated by assessing their market value or the value <strong>of</strong> the savingrealized in the residual's displacing some other <strong>energy</strong> source lessthe costs directly required to actually realize the benefit <strong>of</strong>the residuals. The net benefits were then discounted at 3 percentper year <strong>and</strong> summed to determine the present value <strong>of</strong> plan costs.The inflation rate used is zero.The costs <strong>of</strong> diesel oil, fuel oil, <strong>and</strong> other petroleum fuelsare assumed to escalate over the 20 year planning period at anannual rate <strong>of</strong> 3.5 percent over inflation.All other costs arenot escalated over the assumed zero percent inflation rate.•••....••••..-Appendix 0 presents details <strong>of</strong> the economic factor analyses <strong>of</strong> thealternative plan costs.....APA25/C18VI-18..


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVESc. ENVIRONMENTAL FACTORSCommunity preference evaluations were based on the preferences <strong>of</strong>Cordova citizens as expressed in private <strong>and</strong> public meetings.Naturally, the more vocal members <strong>of</strong> the community most influencedthis evaluation.The evaluation <strong>of</strong> impact on community infrastructure - infrastructureis here taken as the underlying framework <strong>of</strong> the community as awhole - is highly subjective at the <strong>reconnaissance</strong> <strong>study</strong> level<strong>and</strong> is largely based on the least disturbance being best for thecommunity.Evaluation <strong>of</strong> alternative plan timing in relation to other capitalprojects is chiefly a measure <strong>of</strong> how soon <strong>and</strong> easily a plan canbe realized.Air quality impacts are largely <strong>of</strong> two classes, hydro impacts(minimal) <strong>and</strong> fossil fueled impacts (average). The fossil optionsare assumed to have average performance emission abatement equipment;relaxation or tightening <strong>of</strong> typical emission abatement designscan have significant impact on the plan costs used in this <strong>study</strong>.The impacts <strong>of</strong> coal storage run<strong>of</strong>f due to precipitation are themajor considerations in water quality evaluation.Fish <strong>and</strong> wildlife impacts were chiefly evaluated based on waterquality impacts, air quality impacts, <strong>and</strong> habitat disruptionimpacts.The major criteria for the l<strong>and</strong> use impact evaluation was theamount <strong>of</strong> "local" (within 100 miles) l<strong>and</strong> converted to strictlypower production use <strong>and</strong> its proximity to Cordova proper.Hydroelectric facilities, it should be noted, <strong>of</strong>fer secondaryrecreational uses.APA25/C19VI-19


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVES.,..The terrestrial impact evaluation is a measure <strong>of</strong> overall disruption<strong>of</strong> organic life on earth, any long-term change from present beingtaken as negative. This evaluation reflects the perception <strong>of</strong>worldwide carbon dioxide production from coal-fired power plantsas the most significant terrestrial impact.Appendix C presents details <strong>of</strong> many environmental impacts <strong>of</strong> thecomponents <strong>of</strong> alternative plans.- .......d.TECHNICAL FACTORSSafety is evaluated on the basis <strong>of</strong> risk <strong>of</strong> catastrophic accidentsto workers <strong>and</strong> the normally proximate public...Reliability is taken as the measure <strong>of</strong> consistency <strong>of</strong> performance.Availability is taken as the measure <strong>of</strong> readiness for performance..'e. EVALUATION MATRICESEvaluation <strong>of</strong> the above factors has resulted in the followingevaluation matrices, Tables VI-2 <strong>and</strong> VI-3. Economic evaluationsresulted in the quantitative present worth costs previously indicated<strong>and</strong> are ranked alphabet i ca lly, II All bei ng best.•-."It is recognized that the evaluation <strong>of</strong> many environmental factorsis necessarily subjective <strong>and</strong> that the technical factors areactually qualitative in relative evaluation. The following valueswere used in the relative evaluation <strong>of</strong> these subjective orqualitative factors:APA2S/C20Value123InterpretationBest Possible PlanVery Good PlanAbove Average PlanVI-20••.,


VI.EVALUATION OF FEASIBILITY OFENERGY ALTERNATIVESValueInterpretation456789Barely Above Average PlanAverage Plan (Neutral value)Barely Below Average PlanBelow Average PlanVery Poor PlanWorst Possible PlanThe evaluation matrix results show advantages for the local hydro plan<strong>and</strong> intertied surplus plus hydro plans.The reader should note that no economic rankings have been assigned tothe non-electric scenarios as such evaluation would require a separatefeasibility <strong>study</strong>. However, the following examples <strong>of</strong> residual benefitspoint out the savings inherent in substitution <strong>of</strong> coal for diesel <strong>and</strong> inutilization <strong>of</strong> diesel waste heat.Based on costs developed in this <strong>report</strong>, the substitution <strong>of</strong> Healy coal at8,000 Btu/pound for diesel heating saves the equivalent <strong>of</strong> $8.91 - 2.81 =$6.10 per million Btu. This means a saving <strong>of</strong> $0.84 per gallon <strong>of</strong> dieseldisplaced at 1981 costs, or an equivalent annual savings <strong>of</strong> $1.38 pergallon displaced, assuming coal heat comes on line in 1983 <strong>and</strong> dieselprice escalates at 3.5% per year.The sUbstitution <strong>of</strong> Carbon Creek coal at 12,000 Btu/pound for diesel heatingsaves the equivalent <strong>of</strong> $8.91 - 5.00 = $3.91 per million Btu. Thismeans a savings <strong>of</strong> $0.54 per gallon displaced, or an equivalent annualsavings <strong>of</strong> $1.07 per gallon displaced.Actual benefits <strong>of</strong> coal heating will be a direct function <strong>of</strong> amount <strong>of</strong>diesel displaced, cost to convert heating systems to accept coal, <strong>and</strong>environmental impacts associated with it.APA25/C21VI-21


APA 25L1TABLE VI-2EVALUATION MATRIXELECTRIC SCENARIOSCARBONHEALYCREEKDIESEL- LOCAL ELECTRIC COAL INTERTIED COAL DIESEL ELECTRICFACTOR ELECTRIC HYDRO HEATING ELECTRIC HYDRO ELECTRIC W/WASTE HEAT(A) ECONOMIC (Present Worth) F A G C B E D(B) ENVIRONMENTAL(1) CommunityPreferences 9 1 5 5 3 2 9(2) Infrastructure 3 4 5 5 2 7 3(3) Timi ng 1 3 6 2 4 2 2(4) Ai r Qual ity 5 1 1 5 1 5 5(5) Water Quality 2 1 1 7 2 7 2(6) Fish <strong>and</strong> Wildlife 2 3 4 7 4 7 2(7) L<strong>and</strong> Use 2 4 5 6 4 6 2(8) Terrestrial Impacts 2 4 5 6 4 6 2Total 26 21 32 43 24 42 27ENVIRONMENTAL RANKING 3 1 5 7 2 6 4(C)TECHNICAL(1) Safety 2 1 1 3 2 3 2(2) Rel iabil ity 2 1 3 2 1 2 2(3) Avai 1 abil i ty 1 1 3 2 2 2 1Total 5 3 7 7 5 7 5TECHNICAL RANKING 2 1 4 4 2 4 2OVERALL RANKING F-3 ~ G-5 C-7 .6..:..2 E-6 D-4,. f • f I , , • , i , " ' , , , " ., " " f , f, f , f , r 1 t 1


APA 25L2TABLE VI-3EVALUATION MATRIXNON-ELECTRIC SCENARIOSDIESEL COAL LUBE OIL CO-HEATING HEATING RECYCLING GENERATION CONSERVATION WECS(A) ECONOMIC N/A N/A N/A N/A N/A N/A(B) ENVIRONMENTAL(1) CommunityPreferences 9 6 2 3 1 3(2) Infrastructure 5 4 5 2 3 5(3) Timing 1 2 2 2 1 7(4) Air Quality 6 7 5 5 1 1(5) Water Qua 1 ity 2 6 2 7 1 1(6) Fish <strong>and</strong> Wildlife 2 6 2 7 1 2(7) L<strong>and</strong> Use 2 5 2 6 1 3(8) Terrestrial Impacts 2 6 2 6 1 3Total 29 42 22 38 10 25ENVIRONMENTAL RANKING 5 7 3 6 1 4(C)TECHNICAL(1) Safety 2 3 1 3 1 2(2) Re 1 i abil ity 2 2 1 3 1 7(3) Avail abil i ty 1 1 3 2 1 9- -Total 5 6 5 8 3 18TECHNICAL RANKING 2 4 2 5 1 7OVERALL RANKING ~ ~ f ~ 1 ~


VII.CONCLUSIONS AND RECOMMENDATIONSVII. CONCLUSIONS AND RECOMMENDATIONSUtilization <strong>of</strong> anyone <strong>of</strong> the previously listed resources depends oneconomic feasibility, l<strong>and</strong> status <strong>of</strong> the site, <strong>and</strong> environmental considerations.Location <strong>of</strong> several resources within National Forest l<strong>and</strong>sprecludes development in the foreseeable future, as does possible disturbance<strong>of</strong> the fisheries if mitigation cannot be achieved. Economicfeasibility is chiefly determined by the cost <strong>of</strong> construction for thenecessary facilities, the cost <strong>of</strong> operation, <strong>and</strong> the intensity <strong>of</strong> use inrelation to capacity <strong>of</strong> the project.Approximate 1981 construction costs <strong>of</strong> those alternatives meritingdetailed feasibility analyses for Cordova are:• Crater Lake Hydro - $2,975,000.• Power Creek Hydro - $21,600,000 first stage, $12,300,000second stage, plus distribution costs.• Intertied Hydro with Valdez - $12,120,000 for single wireground return transmission plus about $5000/kW installed forhydroelectric developments along the route.• Healy Coal Power Plant - $12,000,000 for an optimistic 10 MWdesign; environmental mitigation costs could add $5,000,000 tothis.Note that the coal at $45/ton (delivered) could providean economic means <strong>of</strong> heating homes.The three most viable alternative <strong>energy</strong> sources to supplement or replacethe use <strong>of</strong> diesel fuel for electrical power generation have been foundto be local hydro, hydroelectric <strong>energy</strong> intertied with Valdez, <strong>and</strong> Healycoal. In addition, the very attractive option <strong>of</strong> local natural gas productionmerits further investigation, based on strongly expressed localinterest.APA25/DlVII-l


VII. CONCLUSIONS AND RECOMMENDATIONSThe economic analysis indicates that coal development can compete withdiesel generation <strong>and</strong> that hydro development would eventually producethe cheapest electric <strong>energy</strong>. The uncertainties involved in the assumptionsmade for the evaluation <strong>of</strong> these resources indicate the requirementfor base information such as:.,....1.2.Investigations <strong>of</strong> Healy coal in regard to:a) Availabilityb) Transportation methodsc) Environmental impactsField <strong>reconnaissance</strong> <strong>of</strong> the small hydro sites to assess:a) Technical feasibility, including geology <strong>and</strong> accessb) Environmental impacts.... •.,iii.,....3. Geophysical surveying <strong>of</strong> potential gas sites followed by drilling<strong>and</strong> testing <strong>of</strong> at least one well.The field investigations then have to be followed by:•..4. Individual feasibility studies <strong>of</strong>:a) Methods <strong>of</strong> utilizationb) Capacity <strong>and</strong> dem<strong>and</strong>c) Economic aspectsd) Equipment availabilitye) Constraints5. Creation <strong>of</strong> generating plant waste heat utilization systems inconsonance with residential <strong>and</strong> industrial conservation programsmerit prompt implementation as such scenarios <strong>of</strong>fer immediate,short term relief to increasing diesel fuel use <strong>and</strong> costs.APA25/02VII-2•......""........•


VII.CONCLUSIONS AND RECOMMENDATIONSIt is recognized that the use <strong>of</strong> petroleum fuels for transportationappears to be the only viable <strong>energy</strong> resource in Cordova for this usesector. Furthermore, even if a large portion <strong>of</strong> the community were toswitch to coal heating or district heating from a coal-fired plant,diesel use for heating will likely not be totally eliminated in Cordova.Hence, the efficient use <strong>of</strong> this resource cannot be over emphasized ifcosts for <strong>energy</strong> are to be kept as low as possible.As existing <strong>energy</strong> technologies are being improved <strong>and</strong> further developed<strong>and</strong> new technologies are introduced, results <strong>of</strong> resource evaluations inthis <strong>report</strong> may become obsolete <strong>and</strong> inadequate. Periodic review istherefore advised in order to maintain the usefulness <strong>of</strong> this <strong>study</strong>.Approximate costs for determination <strong>of</strong> feasibility <strong>of</strong> the most attractivesignificant <strong>energy</strong> resources for Cordova are:• Natural Gas - a minimum <strong>of</strong> $1,500,000 in field work is anticipated.• Intertied Hydro - costs could reach $1,400,000 for meeting year2000 needs. This cost would include evaluating the transmissionline route <strong>and</strong> three (3) potential hydroelectricsites. The evaluation would include hydrologic studies,<strong>and</strong> archaeological assessment, geology, preliminary design<strong>and</strong> economic analysis.• Power Creek - if drilling by the Corps <strong>of</strong> Engineers provessuccessful, feasibility work to the point <strong>of</strong> beginning FERClicensing applications would run $300,000 to $400,000.• Crater Lake - feasibility costs would run $300,000 to $400,000.•Healy Coal - feasibility could be determined for $400,000 to$600,000 depending on the amount <strong>of</strong> environmental monitoringrequired by regulatory agencies.APA25/D3VII-3


VII.CONCLUSIONS AND RECOMMENDATIONSClose contact between the City <strong>of</strong> Cordova <strong>and</strong> Robert W. RetherfordAssociates will permit selection <strong>of</strong> a milestone type feasibilityapproach which will enable early client decision as to which majordirection to pursue.It cannot be overemphasized that if Cordova wants to at least stabilize,<strong>and</strong> hopefully reduce the local cost <strong>of</strong> <strong>energy</strong>, immediate short term,small scale measures should be implemented to at least "hold the line"until the feasibilities <strong>of</strong> larger projects are determined <strong>and</strong> largescale <strong>energy</strong> projects are constructed. These small scale measures canbe generally called "conservation" measures <strong>and</strong> <strong>of</strong>fer the potential <strong>of</strong>reducing current non-transportation fuel use on the order <strong>of</strong> up to 15%.These measures are: lube oil recycling; waste heat recovery <strong>and</strong> use;residential conservation; wood use for residental heating; <strong>and</strong> improvedindustrial heat efficiencies. If these measures are implemented in theshort term, the long term development <strong>of</strong> the Cordova area can proceed ina deliberate <strong>and</strong> consistent manner.•..III•..•..The <strong>final</strong> figures underscore the importance <strong>of</strong> implementing non-petroleum<strong>energy</strong> technologies for Cordova: these figures show the <strong>requirements</strong> <strong>of</strong>continuation <strong>of</strong> current fuel use practices <strong>and</strong> the savings possible withwaste heat recovery.•-•.............APA25/D4VII-4..


132% INCREASE15.0 ~-------------------------.....p::====;;::::=~C/)z0-.J-.J


15.0r---------------------------------------------------------------------~NOTE:IIOTHER" COMPRISES ALL USESOTHER THAN TRANSPORTATIONOR GENERATION ..,zo...J...JC~!...J...J•CITY OF CORDOVA111. LOW 2000 MEAN 2000 HIGH 2000PROJECTIONS OF ~RENTPE' AOLElM FUEL USE~PLACEA8LE BYOTHEft RE80URCES' .... 16,. " • If, I I 'I " f J I' ", I I • I '" f. ,tI ,II" " , , , •


15.0r-------------------------------------------------------------------~NOTE: "OTHER" COMPRISES ALL USESOTHER THAN TRANSPORTATIONOR GENERATION.ASSUMES V3 OF GENERATIONFUEL INPUT EQUIVALENT ISRECOVERABLE.CI)z0-.J-.Jcr(.!)10.0z163% INCREASE0-.J-.J- 25.01-------------------BASELINE1979 LOW 2000MEAN 2000 HIGH 2000CITY OF CORDOVAPROJECTIONS OF CURRENTPETROLEUM FUEL USEWITH GENERATIONWASTE t£AT RECOVERYFIGURE 17


100OTHER TRANSPORTATIONNOTE:SCENARIO ASSUMING 50·/. OFGENERATION WASTE HEAT ISONLY UTILIZABLE HEAT.80BOAT TRANSPORTATION>-C)0::LaJzLaJ60INDUSTRY~• 40 (1979: 228.2 It 10 9 BTU)20HEATING(2000 I 528.0 It 10 9 BTU)ELECTRIC IT Y(1979 I 165.6 It 109 BTU)REDUCED HEATING ENERGY(2000 I 383.2 It 10 9 BTU)...UTILIZABLE WASTE HEATI (1179 SAVINGS:62.6 It 109 BTU)I (2000 SAVINGS:144.8 It 10 9 BTU).. 10CITY OF CORDOVAIMPACT OF WASTE HEAT USEFIGURE 18" I, f , • , , 1 ., '. , , , , " ,. ,. " 'I • , , , ~ , f , ~ 1


ENERGY BALANCE ANDREQUIREMENTS - TABLES--228.0 70.0 320.6 -- 89.6 179.825.7 7.9 36.1 10.1 20.2APPENDIX ATABLE A-I1979 PETROLEUM BASED ENERGY BALANCE*CORDOVA AREABOAT OTHER ELECTRICTRANSPOR- TRANSPOR- GENERA-HEATINGINDUSTRY TATION TATION TION10 9 BTU 10 9 BTU 10 9 BTU 10 9 BTU 10 9 BTU% <strong>of</strong> Total % <strong>of</strong> Total % <strong>of</strong> Total % <strong>of</strong> Total % <strong>of</strong> TotalTOTAL10 9 BTU% <strong>of</strong> Total888.0100* Note that wood for residental heating provides 17.1 x 10 9 Btu.,'"APA21/B1A-I


CONSUMERTYPE #RESIDENTIAL 731TABLE A-21979 PETROLEUM BASED ENERGY SOURCE AND USECORDOVA AREAENERGY FORM CONSUMEDDIESEL GASOLINE PROPANE HEATING FUEL AVIATION GAS TOTAL ELECTRICITY$2 $ $ $ $1000 Gal/Gal 1000 Gal/Gal 1000 Gal/Gal 1000 Gal/Gal 1000 Gal/Gal 1000 Gal No. Cons1/MWH10 9 $Ave. kWhSTU/ lO!BTU 10 9 BTU/ 106BTU 10 9 STU/ lO!BTU 10 9 BTU/ 10!STU 10 9 BTU/ lO!BTU 10 9 BTU/% <strong>of</strong>month / Ave. ¢totalcons kWh462.0/1. 12 271. 1/ 1. 41 65.3/ 1. 90 630.4/ 1. 09 20.0/na 3 1,448.8 696/ 4,23063.8/8.1 34.6/11.1 5.9/20.9 84.8/12.0 2.6/na 191. 7/21. 6 506/ 17COMMERCIALI!76666.5/1. 12 203.3/ 1. 41 2.0/ 1.90 160.8/na 2,032.6 234/ 4,009BUSINESSES- 0 -230.1/ 8.1 26.0/11.1 0.2/20.920.4/na 276.6/31.1 1,428/ 17INDUSTRIAL5574.0/1.12 46.9/ 1. 41- 0 - - 0 - - 0 -620.9 9/ 5,367USERS 79.2/8.1 6.0/11.1 85.2/9.6 49,694/ 11FISHING6501,736.3/1.12 633.6/ 1.41- 0 - - 0 - - 0 -2,369.9 na / naVESSELS 239.7/na 80.9/11.1 320.6/36.1 na / naPUBLIC10100.0/1.12BUILDINGS 13.8/8.1- 0 - - 0 - - 0 -- 0 -100.0 8/ 80013.8/ 1. 6 8,333/ naTOTALS 1,4724,538.8/1. 12 1,154.9/ 1.41 67.3/ 1. 90 630.4/ 1. 09 180.8/na 6,572.2 947/14,406626.6/8.1 147.5/11.1 6.1/20.9 84.8/20.9 23.0/na 888.0/100.0 1,268/ na% OF TOTAL BTU 70.6 16.6 0.7 9.5 2.6 100.0 inc 1 in DieselCANNERY i ncl in large incl in large(self generating)usersusers1Consumers2 1980 retail cost3 not available1 / 1,365na na na 450 / na


KEA08/D4TABLE A-3SUMMARY ELECTRICAL FORECASTS TO YEAR 2000*CITY OF CORDOVAYear: 19801985 19901995 2000ScenarioLow Mean High Low Mean HighLow Mean High Low Mean HighMaximum Dem<strong>and</strong>(MW) 3.44.1 5.0 5. 7 5.0 5.8 8.36.6 7.4 11.8 8.0 8.6 16.5Energy Usage(10 3 MWH) 16.718.5 22.0 26.3 20.2 24.7 39.024.8 30.1 58.2 27.8 35.9 80.0*not including heat (see Tables A-7, A-8, <strong>and</strong> A-9)


KEA08/D2TABLE A-4LOW ELECTRICAL LOAD FORECASTCITY OF CORDOVAYEAR: 1980 1985 1990 1995 2000A. Number & Type<strong>of</strong> Consumer:1. Residential 719 756 795 835 8782. Small Commercial «50 kVA) 247 1 260 273 287 3013. Large Commercial (50 to 350 kVA) 7 8 8 9 104. Large Commercial (>350 kVA) 3 3 3 4 45. Public Lights, etc. 2 2 3 4 46. Unaccounted Power 10% 10% 10% 10% 10%B. Average Consumption (KWH)Per Year Per Consumer1. Residential 5,833 5,800 5,500 5,500 5,3002. Small Commercial 20,615 2 22,750 25,100 27,750 30,6003. Large Commercial 280,000 2 309,000 341,000 377,000 416,0004. Large Commercial 1,212,000 2 1,340,000 1,477,000 1,631,000 1,800,0005. Public Lights, etc. 9,000 9,000 9,000 9,000 9,0006. Unaccounted Power 12% 10% 10% 10% 10%C. Total Energy (10 3 MWH): 16.7 18.5 20.2 24.8 27.8D. Maximum Dem<strong>and</strong> (MW): 3.4 3 4.1 5.0 6.6 4 8.01Increase <strong>of</strong> 1% a year.2 Increase <strong>of</strong> 2% a year.3 Increase <strong>of</strong> 4% a year.4 Addition <strong>of</strong> 500 kW load." , .. ! , , , I , 1 • ~ 'I 'I , I , • J , , , , , , I , ,


TABLE A-5MEAN ELECTRICAL LOAD FORECASTCITY OF CORDOVAYear:19BO19B2198319841985198719891990199119931994199519961997199819992000A. Number <strong>and</strong> Type <strong>of</strong> Consumers1. Residential2. Small Commercial« 50 kVA)3. Large Commercial(> 50 < 350 kVA)4. Large Commercial(> 350 kVA)5. Public Lighting, etc.6. Unaccounted Loads (X)(city, plant & losses)B. Average Consumption (kWh)Per Consumer Per Year7192473212740 1252 23211763257921178526294 •412'80926794412833 3272104412846278104410 B858284104410871290114510884295114510897 5300 3114510906305124612 9915309125 6612924314135612933318135612942323135612952328145610 1096133314561097133B1556109Bl3431656109913481756101. Residential 5,8332. Small Commercial 20,6153. Large Commercial 280,0004. Large Commercial 1,212,0005. Public Lighting, etc. 9,0006,00020,615297,000 11,212,0009,0006,00021,000306,0001,220,0009,0006,00021,000315,0001,315,000 •9,0006,00021,500325,0001,341,300 29,0006,00021,500335,0001,368,0009,0005,500 1122 ,000344,0001,395,5009,0005,50022,000355,0001,423,0009,0005,50022,500365,0001,452,0009,0005,50022,500377,0001,480,0009,0005,BOO 223,0003B8,0001,510,0009,0005,80023,000400,0001,540,0009,0005,BOO23,500412,0001,432,000 69,0005,80024,000424,0001,462,0009,0005,BOO24,500437,0001,490,0009,0005,80024,500450,0001,520,0009,0006,00025,000463,0001,550,0009,0006,00025,500477 ,0001,5B2,0009,0006,00026,000490,0001,610,0009,0006,00026,500506,0001,646,0009,0006,00027,000521,0001,680,0009,000C. Total EnergY, Consumption(10 3 x MHW) 16.717.518.220.521. 222.021.822.323.323.824.726.027.728.929.630.131.031.833.034.535.9D. Maximum Dem<strong>and</strong> (MW) 3.4 13.53.64.74.95.05.15.35.45.65.86.06.87.07.27.47.67.9B.lB.38.6Notes:1 A growth rate <strong>of</strong> 3% is assumed during this period.2 A growth rate <strong>of</strong> 2~ is assumed during this period.3 A growth rate <strong>of</strong> 1.5~ is assumed during this period.• Addition 1,000 kW, 1.6 MWh load <strong>of</strong> Chugach Fisheries to CEA.S A growth rate <strong>of</strong> 1~ is assumed during this period.S Addition <strong>of</strong> a 600 kW, 1 MWh future customer ..7 Increase in transmission network.B Decrease due to system improvements.9 Expansion <strong>of</strong> transmission network.10 Transmission line improvements.11 Drop due to rising cost.


.. t.KEA08/D1TABLE A-6HIGH ELECTRICAL LOAD FORECASTCITY OF CORDOVAYear: 1980 1985 1990 1995 2000A. Number & Type<strong>of</strong> Consumer:1. Residential 719 1 834 966 1,120 1,2982. Small Commercial «50 kVA) 247 1 286 273 332 3853. La rge Commerc i a 1 (50 to 350 kVA) 7 10 15 18 204. Large Commercial (>350 kVA) 3 4 6 8 105. Public Lights, etc. 2 4 6 8 106. Unaccounted Power 10% 10% 10% 10% 10%B. Average Consumption (KWH)Per Year Per Consumer1. Residential 5,833 2 7,100 8,600 10,500 12,7502. Small Commercial 20,615 2 25,000 30,500 37,100 45,0003. Large Commercial 280,000 2 340,600 415,000 504,000 614,0004. Large Commercial 1,212,000 2 1,475,000 1,794,000 2,183,000 2,656,0005. Public Lights, etc. 9,000 9,000 9,000 9,000 9,0006. Unaccounted Power 12% 10% 10% 10% 10%C. Total Energy (10 3 MWH): 16.7 26.3 39.0 58.2 80.0D. Maximum Dem<strong>and</strong> (MW): 3.4 3 5.7 8.3 11.8 16.513% increase every year.24% increase in consumption.3 6% increase + large loads (1 MW in 1983 for Chugach Fisheries& 350 kW per customer thereafter.)


""..,.,..,TABLE A-7LOW HEAT ENERGY FORECASTS TO YEAR 2000-CITY OF CORDOVA ..,.Year POEulation Heating ""10 9 BTU 10 6 kWh .....1980 2386 295.5 88.3 ..•1981 2446 300.4 89.8..1982 2488 304.9 91. 2...1983 2529 308.3 92.2..1984 2571 312.0 93.3..1985 2613 315.6 94.4 -1986 2659 319.7 95.6..1987 2706 324.0 96.91988 2755 335.1 100.2-.,1989 2802 346.2 103.51990 2850 351.4 105.1 1991 2907 357.9 107.0 ..1992 2967 364.9 109.1 •1993 3026 371. 6 111.1-1994 3091 379.1 113.3-...,1995 3154 386.3 115.5...1996 3221 394.0 117.8...1997 3294 402.6 120.4...1998 3364 410.8 122.81999 3438 419.4 125.4-2000 3521 429.1 128.3 .. "III!..""III!KEA08/AA-7 til..II'


TABLE A-8MEAN HEAT ENERGY FORECASTS TO YEAR 2000CITY OF CORDOVAYearPopulationHeating10 9 BTU 10 6 kWh1980198119821983198419851986198719881989199019911992199319941995199619971998199920002406 298.0 89.12452 302.0 90.32499 306.2 91. 52547 310.5 92.82592 314.5 94.02639 318.7 95.32703 325.0 97.22760 330.5 98.83208 384.4 114.93289 392.8 117.43338 397.3 118.83433 407.2 121. 73495 413.3 123.63566 420.4 125.73632 427.2 127.73695 433.2 129.53773 441.3 131.93847 449.5 134.43920 456.9 136.63990 464.1 138.84073 472.9 141. 4A-8KEA08/A


TABLE A-9 ...HIGH HEAT ENERGY FORECASTS TO YEAR 2000CITY OF CORDOVA....Year Po~ulation Heating10 9 BTU 10 6 kWh ..1980 2408 298.2 89.2 ....'"1981 2455 302.4 90.41982 2506 307.1 91. 81983 2555 311. 5 93.11984 2607 316.3 94.6....1985 2649 319.9 95.6...1986 2688 323.2 96.61987 2799 335.2 100.2.-1988 2928 350.8 104.9 ...1989 3285 392.3 117.31990 3938 458.4 137.1 •""',1991 3992 464.6 138.9 •1992 4006 466.3 139.4 .....1993 4065 473.1 141.41994 4166 478.1 142.9 ...'1995 4254 486.0 145.3.~.'1996 4332 492.8 147.3...1997 4406 499.0 149.21998 4479 505.1 151. 0..1999 4549 510.8 152.72000 4616 516.1 154.3 ....A-9 ....KEA08/A..",•........•'


TABLE A-10CURRENT ENERGY USE PROJECTED TO YEAR 2000CITY OF CORDOVA1979Low EstimateYear 2000Mean EstimateYear 2000High EstimateYear 2000Population EstimatesEstimate <strong>of</strong> No. <strong>of</strong> Homes2450731352l1050 (1.4% increase)40731216 (1.7% increase)46161378 (1. 9% increase)Diesel FuelResidentialCommercialCanneriesFishing BoatsPublic BuildingsHeating Fuel#1 FuelPropaneResidentialCommercialGasolineFishingOther TransportationAviation GasElectric GenerationGallons/10 9 BTU462,000/ 63.8364,000/ 50.2574,000/ 79.21,736,273/239. 7100,000/ 13.8630,447/ 84.865,250/ 5.92,048/ 0.2633,597/ 80.9521,406/ 66.6181,8321 23.01,302,474/179.7% Incrl/Gallons/109 BTU1.4 / 647,000 / 89.21.4 / 510,000 / 70.21.4 / 804,000 /111. 01.4 /2,431,000 /335.41. 45 / 145,000 / 20.01.4 / 883,000 /118.71.4 / 91,000 / 8.31.4 / 3,000 / 0.31.4 / 887,000 /112.71.4 / 730,000 / 92.71.4 / 255,000 / 32.3N/A2 /2,208,000 /304. 7% Incr/Gallons/10 9 BTU1.71.71. 451. 451. 451.71.71.71. 451.71.7N/A/ 785,000 / 108.4/ 619,000 / 85.4/ 832,000/114.9/2,518,000 / 347.4/ 145,000 / 20.0/1,072,000 / 144.2/ 111,000 / 10.1/ 3,000 / 0.3/ 919,000/116.7/ 886,000 / 112.6/ 304,000 / 39.3/2,812,000 / 388.0% Incr/Gallons/10 9BTU1.9 / 878,000 / 121. 11.9 / 692,000 / 95.41.5 / 861,000 / 118.81.5 /2,604,000 / 359.41. 45 / 145,000 / 20.01.9 /1,198,000/161.11.9 / 124,000 / 11. 31.9 / 4,000 / 0.41.5 / 950,000 / 120.71.9 / 991,000 / 125.81.9 / 345,000 / 43.9N/A /6,354,000 / 876.816.1/887.827.8/1295.535.9/1487.380.0/2054.7Note:Fuel consumption figures were increased the same percentage as population incI'ease estimates except for canneries, fishery relateduses, <strong>and</strong> public buildings which were increased at the lower percentages shown as these facilities appear closer to saturation <strong>and</strong>therefore would have more limited growth.1 Increase2 Not Appropriate


APPENDIX BRESOURCE COSTSOUTLINEPAGEB.1 CARBON CREEK COALB.2 TRANSMISSION OF CARBON CREEK ELECTRICITYB.3 HEALY COALB.4 KATALLA OIL AND GASB.5 INTERTIE WITH VALDEZB.6 INTERTIED SMALL HYDROB.7 POWER CREEK HYDROELECTRICITYB.8 CRATER LAKE HYDROELECTRICITYB-1B-7B-8B-9B-10B-11B-13B-15


APPENDIX BRESOURCE COSTS1. CARBON CREEK COALAn estimation <strong>of</strong> the costs involved in mining the coals at Carbon Creekhas been undertaken to enable comparison to other resources, as well asto other coals. Coals at Carbon Creek could be developed in the followingfashion:1) An initial exploration program would be required to determineoverall feasibility <strong>and</strong> the areas to be mined, followed by a drillingprogram to prove reserves <strong>and</strong> determine the distribution <strong>and</strong>character <strong>of</strong> the coal.2) Construction <strong>of</strong> a 38-mi1e access road from Mile 39 on theCopper River Highway would then take place. Construction equipment<strong>and</strong> materials would be brought in <strong>and</strong> camp facilities established.It should be noted that the construction <strong>of</strong> this road is m<strong>and</strong>atoryfor the establishment <strong>of</strong> a mining operation, <strong>and</strong> that a small scaleoperation such as the one proposed cannot economically build itsown road. Other uses for the road such as the development <strong>of</strong>logging by Chugach Natives, Inc., may justify construction.3) Development <strong>of</strong> the mine <strong>and</strong> mine-mouth power plant wouldoverlap with construction <strong>of</strong> the camp.The mine itself wouldinvolve adits driven along the trend <strong>of</strong> coal stringers <strong>and</strong> lenseswith raises or stopes when necessary to mine <strong>of</strong>fshoots. Mostequipment would operate from electricity provided by the powerplant.The coal would be conveyed directly from the mine into abeneficiating system which would probably include sorting, crushing,screening, <strong>and</strong> drying. After drying, the coal could godirectly into the power plant or into a stockpile.Note that toeliminate sUbstantial transportation costs, a mine-mouth powerplant with transmission lines to Cordova was decided on, ratherthan trucking the coal 77 miles to Cordova.Geology, terrain, climate <strong>and</strong> economics dictate that underground miningmethods be employed.To extract 20,000 tons <strong>of</strong> coal in the first yearAPA25/fl B-1


APPENDIX BRESOURCE COSTS.....<strong>of</strong> production, approximately 18 personnel would mine 96 tons <strong>of</strong> coal perday, five days per week, on a year round basis.on a slight uphill grade to allow drainage.Adits would be advancedCoal <strong>and</strong> the shale wasterock would be mined from the face with a coal cutting machine.tram would haul the coal to a truck which would take it to the mineA scoopconveyer for transport to the beneficiating plant <strong>and</strong> power plant orstockpi 1 e.•Due to the inconsistency <strong>of</strong> the coal occurrences, several relativelyshort tunnels (6,000 to 8,000 feet) may be required over a 25-yearperiod.for most mines.Coal production per man per hour will be less than is commonThe costing figures in the tables which follow are based on new equipmentquotes from various Alaskan dealers <strong>and</strong> inflated values for certainunderground machinery as quoted in Bottge's 1977 <strong>report</strong> (See Appendix E).Road construction, camp <strong>and</strong> mining development were roughly estimatedbased on current in-house projects with input from several engineers<strong>and</strong> construction managers.Mining methods <strong>and</strong> effective costs arehypothetical, as the actual deposits are not known.In general, costingwas done conservatively at each stage so no contingency is added at theend.Exploration <strong>and</strong> drilling costs were based on a program that wouldencounter minimal weather problems <strong>and</strong> waste only a small percentage <strong>of</strong>the drill footage.•...,....- ..-APA25/f2 B-2


APPENDIX BRESOURCE COSTSTABLE B.1-1SUMMARY ESTIMATES FOR COST OFCARBON CREEK COAL PER TONDevelopment CostsA. Initial ExplorationB. Drilling Program to Prove DepositsC. Road Construction ($200,000/mile x38 miles) plus 6 Bridges @ $500,000D. Initial Site, Camp <strong>and</strong> MineDevelopmentE. Mine Engineering <strong>and</strong> ConstructionF. ContingenciesG. Environmental Allowance (10%)Subtotal - Development Costs$ 271,000824,00010,600,0001,000,000850,0001,000,0001 1400 1000$15,945,000Capital CostsA. Mining EquipmentB. Construction, Transportion <strong>and</strong> RoadMaintenance Equipment (New Cost)C. Beneficiation <strong>and</strong> ProcessingEquipmentD. Camp Facilities, (Temporary <strong>and</strong>Permanent)E. FreightF. Total Interest on 25-Year Loan forAbove at 8%Subtotal Capital CostsTotal Fixed Costs1,280,000823,000150,000944,000100,0007 1240 1000$10,537,000$26,482,000Subtotal Fixed Cost/ton Calculated over25-year Life <strong>of</strong> Mine, Assuming 15,000 tons/year,Escalated to Total Production <strong>of</strong> 600,000 tonsin 25 Years$44. 14/tonAPA25/f3 B-3


Annual Operating CostA. Personnel (18 men, modified fromB.C.D.E.F.Bottge 77)SuppliesDepreciation <strong>and</strong> MaintenanceInsuranceFuel (excluding coal)Continued ExplorationAPPENDIX BRESOURCE COSTS760,000300,000300,00080,00010,00020,000$1,470,000......•....'...Cost/ton calculated for 20,000 tonsin first year; per ton cost per year$73.50/tonTransporation CostA. Beneficiating Process, H<strong>and</strong>lingto PlantCost/tonSubtotal Variable Costs/tonTotal Cost/ton2.00/ton75.50/ton$119. 64/ton••....TABLE 8.1-2INITIAL GEOLOGIC RECONNAISSANCEPROGRAM TO OUTLINE TARGETS2 Drillers, limited drilling (60 days,2,000 feet)Project GeologistGeologistCookCamp RentalTransportationMiscellaneous CostsTotal$120,00031,00028,0005,00025,00060,0002,000$271,000•.....,.,.....APA25/f48-4•


",,*APPENDIX BRESOURCE COSTSTABLE B.1-3DRILLING PROGRAM TO PROVE RESERVESDrilling, Additional 10,000 feet @ $60/ft,(80 Days Camp, 4 Drillers, 1 Mechanic)1 Project Geologist, 120 days @ $350/day2 Assistant Geologists, 120 days @ $200/dayCookCamp Rental, $70/day/manTransportationMiscellaneous CostsTotal$600,00042,00036,0006,00056,00080,0004,000$824,000TABLE B.1-4CAPITAL COST DETAILSCONSTRUCTION, TRANSPORTATION AND MAINTENANCE EQUIPMENTNo. Description Cost1 0-8 Full Cab, Ripper $252,0001 End Dumps, 20 yd 3 100,0001 Fuel Truck 40,0001 Front Loaders, 3 yd 3 65,0001 Grader, 14-G 152,0001 4-wheel Drive Pickup 12,0001 4-wheel Drive Crew Rig 12,0001 Forkl ift 40,0001 Crane, 13 ton 150 z 000Total $823,000APA25/f5 B-5


APPENDIX BRESOURCE COSTSTABLE B.1-5MINING EQUIPMENT"',DescriptionCostCoal Drills, Cutting Machines, Scoop Trams,Supply Vehicles, etc.Ventilation System <strong>and</strong> Dust FacilityConveyor SystemSafety EquipmentFuel StorageSite PreparationConcrete PortalTABLE B.1-6CAMP FACILITIESTotal(Both Temporary (T) <strong>and</strong> Permanent (P)for up to 25 Men)No. Description Unit Cost1 (T) Mobile Bunkhouse (6-8 men) $26,0001 (T) Galley/Shower 48,0001 (P) Bunkhouse <strong>and</strong> Cookhouse(3,000 square feet) 500,0001 (P) Office (20 ft x 20 ft) 40,0001 (P) Shop (60 ft x 60 ft) 300,0002 (P) Storage building 15,000Total$700,000150,000150,00080,000100,00050,00050.000$1,280,000Extension$26,00048,000500,00040,000300,00030 1000$944,000••.,•...,.......APA25/f6 B-6.,


APPENDIX BRESOURCE COSTS2. TRANSMISSION OF CARBON CREEK COAL ELECTRICITYIf a mine mouth power plant was built in the Carbon Creek area (about 15miles northeast <strong>of</strong> Katalla) a transmission line approximately 63 milesin length would be required to deliver the electric power to the Cordovadiesel plant vicinity.The route <strong>of</strong> such a transmission line would be mostly at elevationsbelow 100 feet <strong>and</strong> would roughly parallel the road system that wouldconnect the coal mining area to Cordova. About 37 miles <strong>of</strong> this roadsystem already exists (a portion <strong>of</strong> the Copper River Highway).With a potential power requirement in Cordova <strong>of</strong> 30 to 50 Megawatts <strong>of</strong>peaking capacity by year 2000 a transmission line configuration <strong>of</strong>138 kV with a 556.5 KCM ACSR conductor is necessary. It is estimatedthat such a line constructed in the location described above would costabout $150,000 per mile in today's dollars (1981). With the addition <strong>of</strong>sUbstations at the generating plant ($800,000) <strong>and</strong> at Cordova ($800,000)the total transmission investment would be $11,050,000.Operation <strong>and</strong> maintenance <strong>of</strong> a transmission system in this location willpose no unusual problems for a utility familiar with Alaskan conditions.3. HEALY COALThe Healy coal fields are located about 90 miles south <strong>of</strong> Fairbanks onthe Pa~ks Highway <strong>and</strong> are connected to Anchorage, Seward, <strong>and</strong> Whittierby the Alaska Railroad. The coal near Healy has been mined by theUsibelli Coal Company for over 25 years.While the coals <strong>of</strong> the Healy area are considerably lower in Btu content(8,000 + Btu/lb) than the Bering River coals, they are available insufficient quantity now at a much lower cost than the cost estimated fordevelopment <strong>and</strong> use <strong>of</strong> Bering River coals. Large reserves (in excess <strong>of</strong>100 million tons) <strong>and</strong> a burgeoning market for coal should tend to keepthis coal at competitive prices.APA25/f7 B-7


APPENDIX BRESOURCE COSTSCosts for delivery <strong>of</strong> Healy coal to Cordova are shown in the tablebelow. It has been assumed that 20,000 tons <strong>of</strong> coal at 8,000 Btu/lbwould provide most <strong>of</strong> Cordova1s electrical <strong>energy</strong> requirement in 1981.TABLE B.3-1HEALY COAL COSTSCoal Purchase (1981)Rail Freight to WhittierBarge Freight to CordovaH<strong>and</strong>ling (Docks <strong>and</strong> Stockpile)Total$23.00/ton9. 72/ton7. 38/ton4.00/ton$44.10/tonCoal purchase <strong>and</strong> rail freight costs were direct quotes. H<strong>and</strong>ling costswere estimated based on capital costs for provision <strong>and</strong> operation <strong>of</strong> afacility that could load <strong>and</strong> unload loose coal from rail cars onto abarge. Barging costs were initially quoted; however, a review <strong>of</strong> thefollowing method <strong>of</strong> operation shows that considerable savings are possibleby utilization <strong>of</strong> an Alaska based barge: costs are based on usage<strong>of</strong> an 8,000 ton barge with a 3,000 hp tug, delivered <strong>and</strong> returned toSeattle; it would require three trips to move 20,000 tons <strong>of</strong> coal; <strong>and</strong>each trip would be nearly 200 miles round trip, taking 28 hours. Thesecosts are detailed in the following table:•.......,•..•......TABLE B.3-2BARGING COSTSBarge Delivery <strong>and</strong> Return Time <strong>of</strong> 16 days x $6,500/day28 hrs/trip x 3 trips @ $270/hr40 hrs/trip St<strong>and</strong>by Time x 3 trips @ $175/hr$104,00022,68021,000$147,680......Cost/ton for Barging = $147,680/20,000 tons = $7.38/tonAPA25/f8 B-8....


APPENDIX BRESOURCE COSTS4. KATALLA OIL AND GASTo explore <strong>and</strong> develop either old or new wells at Kata11a would be veryexpensive. In either case, a he1i-portab1e drill would be necessarywith the capability <strong>of</strong> drilling, casing, logging, <strong>and</strong> cleaning, 6 to10-inch diameter holes to depths <strong>of</strong> 1,000 feet. The cost for a singlenew well could be on the order <strong>of</strong> $300,000 to $500,000 with no guarantee<strong>of</strong> production. Without knowing the condition <strong>of</strong> the old wells, itshould be assumed that re-entering an old well would be about the samecost.Currently, the City <strong>of</strong> Cordova uses 1.3 million gallons <strong>of</strong> fuel oil peryear for electrical generation. By the year 2000, its needs are projectedto be 2.8 million gallons per year for electrical generationusing the mean growth scenario. At the estimated production rates <strong>of</strong>2 barrels per day (84 gallons) it can be quickly calculated that itwou1 d take 43 we 11 s to produce enough fue 1 to supp 1y current needs!Development costs would soar to 25 to 30 million dollars <strong>and</strong> the price<strong>of</strong> a single barrel <strong>of</strong> unrefined fuel would be $200.00 or more. Operationalexpense, transportation <strong>and</strong> tariffs would add still further tothe cost. Obviously, this approach is uneconomical. Even if convincingarguments could be made for potential <strong>of</strong> more productive new discoveriesin the Kata11a area, exploration costs would still run from 10 to 20million dollars for geophysical work <strong>and</strong> drilling.There is little information on the local gas reserves occasionally foundwith Kata1la oil. Local inquiry revealed that Katalla village used thenatural gas directly from the wellhead for heating <strong>and</strong> lighting. Thegas burned fairly easily, but noisily, in lanterns; the oil was barreled<strong>and</strong> barged to customers.APA25/f9 B-9


APPENDIX BRESOURCE COSTS...The following table summarizes rough estimates <strong>of</strong> costs which would beinvolved in development <strong>of</strong> oil or gas as an <strong>energy</strong> source for Cordova.These estimates are based on work in the Barrow area for development<strong>of</strong> NPRA gas by Husky Oil engineers Robert Hall <strong>and</strong> Max Brewer, <strong>and</strong>discussions with Chat Chatterton <strong>of</strong> Rowan Drilling.•TABLE B.4-1KATALLA OIL AND GAS DEVELOPMENT COSTSa.Assumptions(1) The reservoir rocks <strong>of</strong> the Katalla area are as highly deformedat depth as they are near the surface. In fact, the results <strong>of</strong>past drilling both at Katalla <strong>and</strong> in nearby areas along the BeringRiver bear this out.(2) Deformation consists <strong>of</strong> tight folds <strong>and</strong> many associated faults.Traps therefore are expected to be small <strong>and</strong> dispersed.(3) Production would depend on tapping a series <strong>of</strong> these smalltraps through a gridwork <strong>of</strong> wells.(4) Production rates will be low. Some enhancement <strong>of</strong> productionmay be feasible using modern methods, but it is still unlikelythat the needs <strong>of</strong> Cordova could be met with less than 15-20well s.(5) Compressor stations will probably be necessary to pump theproduct to Cordova. The shallow depth <strong>of</strong> the reservoir <strong>and</strong>the many faults in the area will tend to decrease reservoirpressures.•.,-•..-...I ...APA25/flO B-10.,


APPENDIX BRESOURCE COSTSTABLE B.4-1 (Cont1d)b. Cost Estimates• Geophysical Exploration (seismic)<strong>and</strong> Geologic Analysis$ 2,500,000( \• Drilling <strong>of</strong> a trageted area from above<strong>study</strong>:6 holes (2-4000 1 each)4,600,000• Well completion <strong>and</strong> testing (this is a verytenuous estimate, but assume 15 wells totalwill give the production necessary <strong>and</strong> thatyou have 100% success rate including thei nit; a 1 6 we 11 s! )9,000,000• Access <strong>and</strong> Physical Facility; port roads;buildings to house machinery for compressorseparating facility <strong>and</strong> personnel; collectingsystem to wells.•Pipeline, 40 miles x $20/foot•Distribution within Cordova (3,000 people)2,500,00012,000,0003,000,000TOTAL 33,600,000NOTE:There is a very high risk factor involved in gas explorationin the Katalla area.5. INTERTIE WITH VALDEZA transmission intertie between Cordova <strong>and</strong> Valdez could provide for anexchange <strong>of</strong> electrical <strong>energy</strong> <strong>and</strong> capacity <strong>and</strong> also provide connectionto a series <strong>of</strong> potential hydro sites that exist in the region betweenthe two communities.APA25/f11B-ll


APPENDIX BRESOURCE COSTSTable B.5-1 shows projected surplus MWh at Valdez from the Solomon Gulchhydroelectric project <strong>and</strong> the proposed Pressure Reducing Turbine (PRT).The cost or even availability <strong>of</strong> this "surplus" <strong>energy</strong> to Cordova isnot known at this time, but will have a major impact on the feasibility<strong>of</strong> the intertie alternatives..,......."",An agreement pending approval <strong>of</strong> the respective voting members, hasbeen reached between Copper Valley Electric Association <strong>and</strong> the City<strong>of</strong> Valdez for the City to take over the power utility for Valdez.The actual disposition <strong>of</strong> <strong>energy</strong> from Solomon Gulch hydroelectricproject will not be determined until the agreement is approved ordisapproved.Additionally, the PRT concept was discussed with AlyeskaPipeline Service Company during design <strong>and</strong> construction <strong>of</strong> the Trans­Alaska Pipeline <strong>and</strong> Alyeska even provided valves in the pipe for installinga PRT system; however, current estimated cost <strong>of</strong> <strong>energy</strong> from SolomonGulch <strong>and</strong> the PRT varies from 1¢ to 12¢ per kWh depending on manyfactors which have not yet been determined. To ill~strate the sensitivity<strong>of</strong> this cost on those alternatives in which surplus <strong>energy</strong>is a part <strong>of</strong> the scenario, two different economic analyses weredeveloped.If a transmission intertie could be made feasible, there would be asubstantial benefit to both comm~nities immediately <strong>and</strong> increasingbenefits as hydro sites along the route are developed. The followingpreliminary analysis is intended to provide a <strong>reconnaissance</strong> levelestimate <strong>of</strong> parameters <strong>and</strong> costs to provide a basis for considering amore in-depth <strong>study</strong> if feasibility seems attainable.....--..APA25/f12 B-12....•


APPENDIX BRESOURCE COSTSTABLE B.5-1PROJECTED SURPLUS MWH AT VALDEZ(to nearest 100 MWH)YEARHYDRO MWHPRT MWHTOTAL SURPLUS MWH19811982198319841985198619871988198919901991199219931994199519961997199819992000-0- -0-9,400 -0-2,300 12,5001,300 12,5001,900 12,5007,400 16,6006,200 15,3004,900 14,2003,500 13,0002,100 12,500600 12,500-0- 11,400-0- 9,700-0- 7,900-0- 6,000-0- -0--0- -0--0- -0--0- -0--0- -0--0-9,40014,80013,80014,40024,00021,50019,10016,50014,60013,10011,4009,7007,9006,000-0--0--0--0--0-APA25/f13B-13


APPENDIX BRESOURCE COSTS6. INTERTIED SMALL HYDRO..A preliminary estimate <strong>of</strong> cost for the three transmission routes describedpreviously in Section IV, "Energy Resource Alternatives," for50 MW transfer capability is:Route (1):Route (2):Route (3):$57,300,000$12,220,000$35,000,000A more in-depth description <strong>of</strong> how these estimates were developed ispresented in Appendix C.It is clear that Route (2) is the most viable alternate based on theassumptions made.Studies <strong>of</strong> possible single wire ground return (SWGR) electric lines havebeen made which show potential benefits for transmission systems undersome conditions. There is a small demonstration project operating todayusing this principle <strong>and</strong> successfully delivering electricity from Bethelto Napakiak. The project is also demonstrating a single phase to threephase state-<strong>of</strong>-the-art converter which is in use supplying three phasepower to the BIA school in Napakiak. Construction costs for the line toNapakiak were found to be about one third <strong>of</strong> the cost <strong>of</strong> conventionalconstruction.The transmission system <strong>of</strong> Route (2) could obtain substantial savings inthe line costs by using this SWGR concept. Without an in-depth analysisit will be assumed that the overhead line costs can be reduced by onefifth<strong>and</strong> that the single phase SUbstations will cost 70% <strong>of</strong> the threephase equivalent. To these costs will be added the estimated singlephase to three phase conversion costs. This SWGR concept is thus estimatedto cost $12,120,000 for Route (2). The SWGR concept appearsworth more in-depth consideration.",........,••..•...........APA25/f14 B-14


APPENDIX BRESOURCE COSTSTransmission Route (2) passes within easy reach <strong>of</strong> a number <strong>of</strong> potentialhydroelectric sites. It is estimated that these hydro sites could bedeveloped at an overall cost <strong>of</strong> about $5,000 per kW. A <strong>reconnaissance</strong>level estimated overall cost to develop these hydro-power sites is$5,000 per kW installed. It is difficult to refine the estimated costanymore than what is given without actually visiting each site. However,even though increasing the estimated cost per kW by 50 percent, to $7,500,would change the relative year 2041 economic ranking <strong>of</strong> the Intertiealternatives <strong>and</strong> the coal generation with Healy coal alternatives, it wouldnot change the recommendation that these alternatives be considered formore indepth feasibility studies.A brief summary <strong>of</strong> the estimated capacity <strong>and</strong> corresponding estimatedcost for the hydroelectric sites follows. These sites are listed inorder from Cordova towards Valdez.(a) Sheep River LakesLake 20261200 kW Installed Capacity4,200 MWh Prime <strong>and</strong> 5,260 MWh AverageCost: $6,000,000Lake 1022 -1200 kW Installed Capacity3,720 MWh Prime <strong>and</strong> 5,000 MWh AverageCost: $6,000,000Lake 649 -4000 kW Installed Capacity12,360 MWh Prime <strong>and</strong> 17,660 MWh AverageCost: $20,000,000APA25/f15B-15


(b)Lake 1488 - <strong>of</strong>f Beartrap Bay6700 kW Installed Capacity21,940 MWh Prime <strong>and</strong> 29,260 MWh AverageCost: $33,500,000APPENDIX BRESOURCE COSTS.............(c) Dead Creek - Gravina River Tributary(d)15,500 kW Installed Capacity50,200 MWh Prime <strong>and</strong> 66,960 MWh AverageCost: $77,500,000Lake 1975 - above Dead Creek2,200 kW Installed Capacity4,240 MWh Prime <strong>and</strong> 9,420 MWh AverageCost: $11,000,000.....1IiI!'•(e)Lake 1878 - above Fidalgo Creek5,000 kW Installed Capacity11,390 MWh Prime <strong>and</strong> 22,780 MWh AverageCost: $25,000,000•(f) Fidalgo Creek - Run-<strong>of</strong>-River Plant5,000 kW Installed Capacityo MWh Prime <strong>and</strong> 10,000 MWh AverageCost: $25,000,000(g) Silver Lake - Duck River12,000 kW Installed Capacity49,450 MWh Prime <strong>and</strong> AverageCost:Hydro Site - $60,000,000Transmission Line - 3,240,000$63,240,000.,....APA25/f16B-16


APPENDIX BRESOURCE COSTS7. POWER CREEK HYDROELECTRICITYA run-<strong>of</strong>-river hydroelectric development at Power Creek could possiblybe developed in two stages: a first stage <strong>of</strong> 6600 kW <strong>and</strong> a second stage<strong>of</strong> 6000 kW capacity. Estimated cost for the first stage is $21,600,000(about $3300/kW) <strong>and</strong> for the second stage is $12,300,000 (about $2100/kW).The dam would be near stream Mile 3.0 (upstream <strong>of</strong> Ohman Falls) <strong>and</strong> thepowerhouse would be at about Mile 2.0.The Corps <strong>of</strong> Engineers has test drilled two dam sites <strong>and</strong> will test thethird (Ohman Falls) this year. If drilling at this third site showspotential, a <strong>final</strong> <strong>report</strong> will be prepared <strong>and</strong> Federal funds will berequested to begin specification work. Apparently the Power Creekproject will be ab<strong>and</strong>oned by the Corps if drilling proves this OhmanFalls site unsuitable. Excessive depth to bedrock <strong>and</strong> seepage eliminatedthe previous sites investigated on Power Creek.Figure B.7-1 shows the relation <strong>of</strong> first stage Power Creek power toCordova's recent loads. This figure clearly shows the need for otherbase load power for much <strong>of</strong> the year when flows are quite low.8. CRATER LAKE HYDROELECTRICITYThe small watershed <strong>of</strong> Crater Lake, proximate to Cordova, could provideabout 435 kW <strong>of</strong> prime power <strong>and</strong> 3,800 MWh per year. A small dam to raisethe lake level about 10 feet, would <strong>of</strong>fer the possibility <strong>of</strong> totally regulatedflows, rather than run-<strong>of</strong>-river type flows. The power plant wouldrequire a small penstock (less than 12 inches in diameter) for the highhead, easy access plant. Discharge toward Orca would permit the projectfulfilling the dual purposes <strong>of</strong> hydropower <strong>and</strong> water supply for the canneryat Orca; discharge to Eyak Lake faces topographical problems.The Corps <strong>of</strong> Engineers plans to install a gauge on the outflow fromCrater Lake in the summer <strong>of</strong> 1981.Actual installed capacity would be 800 to 900 kW at a cost estimatedat roughly $3500 per kW.APA25/f17 B-17


APPENDIX C.lINTRODUCTIONOUTLINEC.l INTRODUCTIONC.2 EXPLANATORY NOTESC.3 ENERGY TECHNOLOGY PROFILESC.3.lC.3.2C.3.3C.3.4C.3.SC.3.6C.3.7Current Petroleum TechnologyC.3.l.1 Diesel-Electric GenerationC.3.1.2 Oil HeatingHydroelectric TechnologiesC.3.2.1 Hydroelectric GenerationC.3.2.2 Electric HeatingElectrical Transmission IntertiesCoal TechnologiesC.3.4.1 Coal-Fired Steam-Electric GenerationC.3.4.2 Coal <strong>and</strong> Wood HeatingConservation TechnologiesC.3.S.1 Diesel Lube Oil RecyclingC.3.S.2 Diesel Waste Heat UtilizationC.3.S.3 Steam CogenerationC.3.S.4 ConservationWind Energy Conversion Systems (WECS)Heat Pumpsapa26/hlC.l-l


APPENDIX C.1INTRODUCTION..C.1. INTRODUCTIONThe <strong>energy</strong> technology pr<strong>of</strong>iling effort involves the development <strong>of</strong> aconsistent set <strong>of</strong> site specific assumptions to provide a truly comparabledata base. Although at least several data sources are availablefor each technology, the data generally is quite variable (<strong>of</strong>ten basedon incompatible assumptions) <strong>and</strong>, perhaps more important, does not applyto systems <strong>of</strong> the size or nature which would be utilized in Cordova inparticular.Data discrepancies for the so-called alternative <strong>energy</strong>technologies are also strongly influenced by the simple lack <strong>of</strong> experiencein constructing <strong>and</strong> operating facilities utilizing these technologies....'..The technology pr<strong>of</strong>iles which follow are an attempt to provide a consistent,appropriate data base relevant to Cordova's <strong>energy</strong> needs to theyear 2000. We are engineers, not visionaries, <strong>and</strong> unforeseen progressin the more developmental technologies could cause radical need forreassessment <strong>of</strong> these technologies. We can reasonably expect little <strong>of</strong>such progress until at least 1985 <strong>and</strong>, most likely, after 1990.•..•These pr<strong>of</strong>i 1 es are in conformance wi th the recommended APA format.-•....apa26/h2C.1-2..


"ojAPPENDIX C.2EXPLANATORY NOTESC.2. EXPLANATORY NOTESSevera 1 explanatory notes apply to the pr<strong>of</strong>il i ng effort in general:1. Factors that cause differences in electrical generating plantcapital costs per kW include:project scope• regulatory <strong>requirements</strong>• local cost variations• plant size• single versus multiple unit plants• construction time• interest rates2.The availability factor is used as a measure <strong>of</strong> reliability <strong>and</strong> isthe percentage <strong>of</strong> time over a specified period (typically one year)that the power plant was available to generate electricity. Creditfor availability is given if the plant is shut down for any reason.3. Net Energy as used here is typi cally referred to as the "heat rate"in the case <strong>of</strong> electric generation <strong>and</strong> is expressed as the ratio <strong>of</strong>Btu in to kWh out in this case. For direct heat application cases,this ratio is Btu in to Btu out.apa26/mlC.2-1


APPENDIX C.3.1.1DIESEL-ELECTRICC.3.1.1DIESEL-ELECTRIC GENERATION(A)General Description1) Thermodynamic <strong>and</strong> engineering processes involvedIn the diesel engine, air is compressed in a cylinder to ahigh pressure. Fuel oil is injected into the compressed air,which is at a temperature above the fuel ignition point, <strong>and</strong>the fuel burns, converting thermal <strong>energy</strong> to mechanical <strong>energy</strong>by driving a piston. Pistons drive a shaft which in turndrives the generator....-(B)2) Current <strong>and</strong> future availabilityDiesel engines driving electrical generators are one <strong>of</strong> themost efficient simple cycle converters <strong>of</strong> chemical <strong>energy</strong>(fuel) to electrical <strong>energy</strong>. Although the diesel cycle intheory will burn any combustible matter, the practical fact <strong>of</strong>the matter is that these engines burn only high grade liquidpetroleum or gas, except for multi-thous<strong>and</strong> horsepower engineswhich can burn heated residual oil. Diesel generating unitsare usually built as an integral whole <strong>and</strong> mounted on skidsfor installation at their place <strong>of</strong> use.Performance Characteristics1)Energy outputa) Quality - temperature, formIn addition to electricity, diesel generators produce twokinds <strong>of</strong> capturable waste heat: from the cooling water<strong>and</strong> from the exhaust. The cooling water normally is inthe 160-200 o F range, but it can be 250°F or higher with.........II'...............II'apa26/d1C.3.1.1-1..


APPENDIX C.3.1.1DIESEL-ELECTRICslight engine modification. Engines today are usuallyrun at the cooler temperatures because <strong>of</strong> design simplicity,simpler operating routines, <strong>and</strong> first cost economy.The exhaust heat in a diesel is <strong>of</strong> higher temperature <strong>and</strong>consequent ly more easily used than the cool i ng waterheat, but higher initial costs <strong>and</strong> increased operatingcomplexities are encountered when attempting to recover<strong>energy</strong> from the exhaust gases.b) QuantityTypically 30% <strong>of</strong> the fuel <strong>energy</strong> supplied to a dieselelectricset is converted to electricity, 30% is transferredto cooling water, 30% is exhausted as hot gas, <strong>and</strong>10% is radiated directly from the engine block. TypicalAlaska diesel installation range from about 50 to 2500kW.c)Dynamics - daily, seasonal, annualDiesel units are typically base loaded ( not subject todynamic variations).2)Re 1 i abil itya) Need for back-upProper install at ion <strong>and</strong> mai ntenance allow continuous1 oadi ng.b) Storage <strong>requirements</strong>Tanks located nearby the power plant.apa26/d2C.3.1.1-2


APPENDIX C.3.1.1DIESEL-ELECTRIC3) Thermodynamic efficiency• Typically 17-31% overall plant efficiency without heatrecovery.4) Net <strong>energy</strong>.'(C)Costs• 11,000 - 20,000 Btu/kWh1) Capital••$400/kW (AVEC)$265-530/kW (Bristol Bay 1979 $ X 1.32 for units up to500 kW)• $220/kW (Cordova bid)2) Assembly <strong>and</strong> installation• $400/kW (AVEC)• $230-690/kW (Bristol Bay 1979 $ X 1.32)•3) Operation$950/kW (Kake capital <strong>and</strong> installation)$220/kW (Cordova Estimate).... '.,..- ..•4-8% <strong>of</strong> investment per year (Bristol Bay operation)4) Maintenance <strong>and</strong> replacement...apa26/d3•••20 years)•2% <strong>of</strong> investment per year (Bristol Bay maintenance)$7.44/MWH (THREA records, maintenance)9.4% <strong>of</strong> investment per year (replacement at 7% for$150,000 in salaries + $7/MWH (Cordova estimate)C.3.1.1-3••


APPENDIX C.3.1.1DIESEL-ELECTRIC5) Economies <strong>of</strong> scaleDiesel electric units range from around 1 kW to around 2.5 MW.(D)Special Requirements <strong>and</strong> Impacts1) Siting - directional aspect, l<strong>and</strong>, heightA 1000 kW unit is typically skid mounted, is about 8 feet high,6 feet wide, <strong>and</strong> 18 feet long. The unit requires foundation,enclosure, <strong>and</strong> provision for cooling <strong>and</strong> combustion air.2) Resource needsa) RenewableN/Ab) Non-renewableNo.2 diesel fuelinstallations.is typically used for stationary3) Construction <strong>and</strong> operating employment by skillConstruction can be done with supervised typical local labor<strong>and</strong> equipment. Operation requires operator/mechanics.4)Environmental residualsThe composition <strong>of</strong> the exhaust is a function <strong>of</strong> the air-fuelratio <strong>and</strong> the hydrogen-carbon ratio <strong>of</strong> the fuel. Residualsinclude: carbon dioxide, carbon monoxide, hydrogen, <strong>and</strong> traces<strong>of</strong> nitrogen oxides <strong>and</strong> unburned hydrocarbons.apa26/d4C.3.1.1-4


APPENDIX C.3.1.1DIESEL-ELECTRIC5) Health or safety aspectsFuel tanks require spill protection, <strong>of</strong>ten difficult in remoteinstallations. Major consideration is potential impact fromsuch spills.III'(E)Summary <strong>and</strong> Critical Discussion1)2)Cost per million BTU or kWh (fuel & lube oil costs only)••10-11¢/kWh (Kotzebue <strong>and</strong> Bethel)22-25¢/kWh (Small Villages)• 17¢/kWh (Cordova residential)• 11¢/kWh (Cordova commercial)Resources, <strong>requirements</strong>, environmental residuals per millionBTU or kWh..... '....- ..•From 0.07 to 0.12 gallons <strong>of</strong> fuel per kWh.Environmental residuals per million Btu: N/A.....3)Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong>its availabilityDiesel units are typically stocked by several manufacturers<strong>and</strong>, as such, have relatively short lead times for use. Whilethis technology is a widely used application, lack <strong>of</strong> qualifiedoperators <strong>and</strong> availability <strong>of</strong> spare parts have posed problemsinA 1 aska.If..•..-apa26/d5C.3.1.1-5"'",...


APPENDIX C.3.1.2OIL HEATINGC.3.1.2OIL HEATING(A)General Description1) Thermodynamic <strong>and</strong> engineering processes involvedAn oil burner is a mechanical device for preparing fuel oilto combine with air under controlled conditions for combustion.Two methods (atomization <strong>and</strong> vaporization) are used for thepreparation <strong>of</strong> fuel oil for the combustion process.combustion is supplied by natural or mechanical draft.Air forIgnitionis generally accomplished by an electric spark or pilot flame.Operation may be continuous, intermittent, modulating, or highlowflame.2) Current <strong>and</strong> future availabilityLong history <strong>of</strong> practice in Cordova.The majority <strong>of</strong> residential burner production (over 95%) is <strong>of</strong>the high pressure atomizing gun burner type. Substantialnumbers <strong>of</strong> other types <strong>of</strong> burners are still in operation, butonly a few <strong>of</strong> these types are currently in production.(B)Performance Characteristics1) Energy outputa) Quality - temperature, formSpace heat or hot water for hydroni c space heatingsystems ....APA26/J1C.3.1.2-1


APPENDIX C.3.1.2OIL HEATING..•b) QuantityResidential heating burners typically operate in the 0.5to 3.5 gallon per hour range.No.2 fuel oil is generally used, although burners in theresidential size range can also operate on NO.1 fuel oil.......Output ratings <strong>of</strong> 64,000 - 150,000 Btu/hour are typical.c) Dynamics - daily, seasonal, annualAvailable whenever fuel oil is available...2)Reliabilitya) Need for back-upNone usually required.b) Storage <strong>requirements</strong>....3)Requires fuel storage tanks.Thermodynamic efficiencyAbout 70%.4) Net <strong>energy</strong>About 1.4 units in for 1.0 units out.-....-....APA26/J2C.3.1.2-2•


APPENDIX C.3.1.2OIL HEATING(C)Costs1) CapitalA typical residential unit costs on the order <strong>of</strong> $800-1000 forair heating units.2) Assembly <strong>and</strong> installationAbout equal to 2 to 3 times the capital cost.3) OperationNegligible, as this is performed by the homeowner.4) Maintenance <strong>and</strong> replacementEasily maintained; units have a typical 10-20 year 1 He.5) Economies <strong>of</strong> scaleNot appropriate.(D)Special Requirements <strong>and</strong> Impacts1) Siting - directional aspects, l<strong>and</strong>, heightNeeds to be isolated from flammable materials.2) Resource needsa) RenewableNone.APA26/J3 c. 3.1. 2-3


APPENDIX C. 3.1. 2OIL HEATINGII"b) Non-renewableFuel oil...lit3) Construction <strong>and</strong> operating employment by skill4)Installed by local services; operated by residents.Annual inspection <strong>of</strong> burner equipment is recommended to assuregood adjustment <strong>and</strong> operating condition.Environmental residualsCarbon dioxide, carbon monoxide, hydrogen, <strong>and</strong> traces <strong>of</strong>nitrogen oxides <strong>and</strong> unburned hydrocarbons.5) Health or safety aspectsII'........••Fuel tanks require spill protection. Units must be located asafe distance from flammable materials.(E)Summary <strong>and</strong> Critical Discussion1) Cost per million Btu or kWh•Fuel oil now costs about $13.00 per million Btu taking intoaccount heating efficiency.2)Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWh..Requires 7.25 gallons per million Btu.Environmental residualsper million Btu not available.... ,.....APA26/J4C. 3.1. 2-4•


APPENDIX C.3.1.2OIL HEATING3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong> itsavailabiltiyThe technology is commercially available, reliable, <strong>and</strong> providesmost <strong>of</strong> Cordova's heating needs.The rising cost <strong>of</strong> fuel oil is, however, making this technologyless <strong>and</strong> less desirable.APA26/J5C. 3.1. 2-5


APPENDIX C.3.2.1HYDROELECTRICC.3.2.1 HYDROELECTRIC GENERATION(A) General Description1. Thermodynamic <strong>and</strong> engineering processes involvedI n the hydroe 1 ectri c power development, fl owi ng water isdi rected into a hydraul i c turbi ne where the <strong>energy</strong> in thewater is used to turn a shaft, which in turn drives a generator.In their action, turbines involve a continuous transformation<strong>of</strong> the potential <strong>and</strong>/or kinetic <strong>energy</strong> <strong>of</strong> the waterinto usable mechanical <strong>energy</strong> at the shaft. Water stored atrest at an elevation above the level <strong>of</strong> the turbine (head)possesses potential <strong>energy</strong>; when flowing, the water possesseskinetic <strong>energy</strong> as a function <strong>of</strong> its velocity.2. Current <strong>and</strong> future availability.........••Hydroelectric developments in the United States, as <strong>of</strong> January1978, totaled 59 million kilowatts, producing an estimatedaverage annual output <strong>of</strong> 276 billion kilowatt hours accordingto the U.S. Department <strong>of</strong> Energy (DOE). Hydropower providesabout 10% <strong>of</strong> Alas ka IS elect ri c <strong>energy</strong> needs. Deve 1 opmentsrange in size from over a million kilowatts down to just a fewkilowatts <strong>of</strong> installed capacity. Hydropower is a time provenmethod <strong>of</strong> generation that <strong>of</strong>fers unique advantages. Fuelcost, a major contributor to thermal plant operating costs, iseliminated.• .....'Another advantage <strong>of</strong> hydropower developments is that they lastmuch longer than do other plant types. Hydropower deve 1 opmentsare, however, initially costly <strong>and</strong> require around5 years <strong>of</strong> lead time, from <strong>reconnaissance</strong> to start-up. Licensingprocedures, particularly for smaller projects, are beingstreamlined. Streamlining licensing procedures can significantlyreduce the amount <strong>of</strong> lead time needed to bring a projecton-line.III'.."",..........APA/26/BC.3.2.1-1•


APPENDIX C.3.2.1HYDROELECTRIC(B)Performance Characteristics1. Energy outputa) Quality - temperature, formHydropower provides readily regulated electricity. Waterquality is not affected. A slight temperature differentialmay exist between discharge water <strong>and</strong> the receivingwaters. The effect <strong>of</strong> the temperature change on spawningsalmon normally requires investigation.b) QuantityApproximately 60% <strong>of</strong> the <strong>energy</strong> stored in the water willresult in saleable electricity. The remaining 40% willbe lost in the water conduit, turbine, generator, stationservice, transformers, <strong>and</strong> the transmission line. Typicalinstalled capacities in Alaskan power plants range from1-20 MW.c) Dynamics - daily, seasonal, annualHydropower plants can be base loaded <strong>and</strong>/or peak loaded.In smaller installations, the operating mode may beadjusted seasonally, depending on the availability <strong>of</strong>water <strong>and</strong> the dem<strong>and</strong> for electricity.2. Reliabilitya) Need for back-upThe reliability <strong>of</strong> the hydroplant itself is very high.The transmi ss ion 1 i nes are <strong>of</strong>ten routed through veryrugged terrain <strong>and</strong> are consequently subject to a variety<strong>of</strong> natural hazards. Repairs to damaged lines can usuallyAPA/26/BC.3.2.1-2


APPENDIX C.3.2.1HYDROELECTRICbe accomplished relatively quickly. It is customary toprovide sufficient installed diesel generation capacityto provide emergency electricity to the utility's customersin the event that the transmission line or the powerplantshould go down. The amount <strong>of</strong> backup required canbe reduced by building an alternate transmission line.b) Storage <strong>requirements</strong>•..- ..A reservoir is usually used to store water except forrun-<strong>of</strong>-river pl ants. Typi cal reservoi rs wi 11 range insize from a few acres to several hundred acres.3.Thermodynamic efficiencyNot appropriate...(C)4. Net <strong>energy</strong>CostsApproximately 4800 kWh/installed kW will be generated annually.Saleable <strong>energy</strong> will be about 10% less when stationservice, transformer, transmission line <strong>and</strong> other losses areincluded.1. Capi ta 1• $14,000/kW installed Lake Elva near Bristol Bay(feasibility estimate)•$1,800/kW installed - Solomon Gulch near Valdez$50,000/kW installed (<strong>reconnaissance</strong> estimate)$5,OOO/Kw installed for hydro along Cordova-Valdezintertie route$3,500/kW installed for Crater Lake•• $3,300/kW installed for Power Creek first stage•..••....,.,APA/26/BC.3.2.1-3•


APPENDIX C.3.2.1HYDROELECTRIC2. Assembly <strong>and</strong> installationSee above.3. OperationOperation <strong>and</strong> maintenance costs are normally combined whenevaluating a hydropower development.4. Maintenance <strong>and</strong> replacementOperation <strong>and</strong> maintenance costs for a hydroelectric developmentnormally depend on the size <strong>of</strong> the installation <strong>and</strong> themethod <strong>of</strong> operation. Most large installations (76,000 kW)will be attended full-time while many <strong>of</strong> the smaller installationsare operated remotely <strong>and</strong> visited only occasionally formaintenance. Estimated annual operation <strong>and</strong> maintenance costfor large installations is $100.00 + $7.00/kW. For small plantsthe estimated cost is $25,000 + $7.00/kW.Annual replacement cost for a hydroelectric plant with 50-year economic life is $3.00 per kW installed.5. Economies <strong>of</strong> scaleThe cost per kW i nsta 11 ed generally decreases for 1 argerinstallations. Further economics <strong>of</strong> scale can be realizedwhen the operation <strong>of</strong> several small hydropower developmentscan be integrated.(D)Special Requirements <strong>and</strong> Impacts1. Siting - directional aspect, l<strong>and</strong>, heightAPA/26/BC.3.2.1-4


..APPENDIX C.3.2.1HYDROELECTRICA suitable site for any hydropower development must, <strong>of</strong> course,be found. Requirements include an adequate water supply <strong>and</strong> areasonable proximity to the load center (consumers). Sitepreparation for a hydropower development involves modification<strong>of</strong> the existing terrain <strong>and</strong> results in changes in both thetopography (cuts <strong>and</strong> fills), <strong>and</strong> in the natural or existingdrainage pattern. The project boundary (the outer limits <strong>of</strong>the 1 <strong>and</strong> di rect ly affected by the project) may encompassseveral hundred acres. The impacts <strong>of</strong> a hydropower developmentcover a wi de spectrum. They affect man, vegetation,wil dl ife, <strong>and</strong> fi sheri es. The speci a 1 advantage <strong>of</strong> a hydropowerdevelopment is that it is effectively non-polluting.........2.Resource needsa)RenewableWater.b)Non-renewableSome <strong>of</strong> the construction <strong>and</strong> maintenance resources (suchas steel <strong>and</strong> lube oil) are non-renewable resources.-..3.Construction <strong>and</strong> operating employment by skillII!Construction <strong>of</strong> a hydropower development requires the employment<strong>of</strong> both highly skilled individuals experienced in thedes i gn <strong>and</strong> construction <strong>of</strong> thi s type <strong>of</strong> project <strong>and</strong> 1 essexperienced individuals who usually come from the local workforce.Operators <strong>of</strong> hydroplants are <strong>of</strong>ten local diesel powerplant operators who receive a minimal amount <strong>of</strong> additionaltraining to qualify them to work as hydroplant operators.II'.....APA/26/BC.3.2.1-5


APPENDIX C.3.2.1HYDROELECTRIC4. Environmental residualsNone5. Health or safety aspectsPublic safety, legal liabilities, insurance, <strong>and</strong> l<strong>and</strong> useissues must be addressed prior to construction <strong>of</strong> a hydropowerdevelopment.(E)Summary <strong>and</strong> Critical Discussion1. Cost per mi 11 i on Btu or kWhSee Appendix B for cost per kWh.2. Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWh.N/A.3. Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong> itsavailability.Hydroelectric power generation is a well established technology.Each project, <strong>and</strong> many <strong>of</strong> its components, are "custom"design jobs. Because <strong>of</strong> this <strong>and</strong> because <strong>of</strong> the large scale<strong>and</strong> the long lead time associated with a project, hydropoweris a capital intensive investment with high field explorationcosts. Few utilities alone can afford to provide long term<strong>and</strong> interim financing. The State <strong>of</strong> Alaska, the Rural ElectrificationAdministration, <strong>and</strong> others provide assistance to utilitiesto bring worthwhile projects forward.Hydroplants can be remotely operated from a central station.An operator is usually stationed at the power plant to takecare <strong>of</strong> routine maintenance. Safety <strong>of</strong> hydropower develop-APA/26/BC.3.2.1-6


••APPENDIX C.3.2.1HYDROELECTRICments has long been a concern <strong>of</strong> the Federal <strong>and</strong> State governments.Criteria for safe design <strong>and</strong> operation <strong>of</strong> hydropowerdevelopments are well established <strong>and</strong> major failures are veryrare.The hydraulic turbine, <strong>and</strong> its component parts, isdesigned <strong>and</strong> are built to exacting specifications <strong>and</strong> isextremely reliable; the turbine has a useful life <strong>of</strong> upwards<strong>of</strong> 30 years..,.,..............,•.,.....•APA/26/BC.3.2.1~7•


PRECIPITATIONaRUNOFFWATERSTOIItAl(RESERVOIRWATERCONDUITHYDRAULICTURBINESHAFTI--__ ~ POWERWATERTAILRACETALWATERHYDROELECTRIC POWER DEVELOPMENT DIAGRAMFIGURE C.3.2.1-1


APPENDIX C.3.2.2ELECTRIC HEATINGC.3.2.2ELECTRIC HEATING(A)General Description1) Thermodynamic <strong>and</strong> engineering processes involved.....Electricity is passed through resistance wiring <strong>and</strong> gives <strong>of</strong>fheat in encountering such resistance. The heat is transferredto air or water.2) Current <strong>and</strong> future availabilityElectric heat is clean, noiseless, easily controllable <strong>and</strong>relatively efficient. Electric heat is recognized as a soundmeans <strong>of</strong> heating buildings where heat losses are held to asound, economical level <strong>and</strong> the cost <strong>of</strong> electricity is notprohibitive.•(B)Performance Characteristics1)Energy output..a) Quality - temperature, formHeat or hot water for space heating applications.b) Quantity3413 Btu in per kWh out. Typical residential furnacesare <strong>of</strong> capacities in the range <strong>of</strong> 20,000 to 120,000 Btuper hour...-II'.....•APA26/CC.3.2.2-1


APPENDIX C.3.2.2ELECTRIC HEATINGc) Dynamics - daily, seasonal, annualAvailable whenever there is electricity.2) Re1 iabil itya) Need for back-upTypically, none.b) Storage <strong>requirements</strong>None.3) Thermodynamic efficiencySo far as the convers i on <strong>of</strong> e 1 ectri c <strong>energy</strong> into heat isconcerned, all types <strong>of</strong> electric resistance heaters are equallyefficient. They all produce 3413 Btu per kilowatt-hour <strong>of</strong>electrical <strong>energy</strong> used. From a thermodynamic efficiencyst<strong>and</strong>point, electric heaters are 100 percent efficient.However, different types <strong>of</strong> heaters differ in effectiveness;the effectiveness is determined by the means used to transferthe heat generated into the area that is to be heated.4) Net <strong>energy</strong>Overall, say about 1.02 units in to 1.00 unit out.(C)Costs1) CapitalAbout $800-1000 for a central home unit.APA26/CC.3.2.2-2


APPENDIX C.3.2.2ELECTRIC HEATING.....2) Assembly <strong>and</strong> installationAbout equal to capital cost.3) OperationA function <strong>of</strong> the cost <strong>of</strong> electricity.4) Maintenance <strong>and</strong> replacement,"'(D)Virtually maintenance free; replacement life estimated to be20 years.5) Economies <strong>of</strong> scaleNot appropriate.Special Requirements <strong>and</strong> Impacts1) Siting - directional aspect. l<strong>and</strong>. heightIn typical residential installations, a metal casing, in thesame confi gurat i on as convent i ona 1 baseboard along wall s •contains one or more heating elem"ents placed horizontally.The vertical dimension is usually less than 9 inches, <strong>and</strong>projection from wall surface is less than 3.5 inches. Unitsare available from 1 to 12 feet long with ratings from 100 to400 watts per foot <strong>of</strong> length <strong>and</strong> are designed to be fittedtogether to make up any desired continuous length or rating.••Ia·•....•........APA26/CC.3.2.2-3..


APPENDIX C.3.2.2ELECTRIC HEATING2) Resource needsa) RenewableHydroelectricity is currently the only cost effectiverenewable resource.b) Non-renewableFossil fuels used for electrical generation.3) Construction <strong>and</strong> operating employment by skillSimple to install <strong>and</strong> effectively automatic.4) Environmental residualsNone.5) Health or safety aspectsNone.(E)Summary <strong>and</strong> Critical Discussion1) Cost per million Btu or kWhCost is a function <strong>of</strong> the cost <strong>of</strong> electricity.The most economical electric heating systems from an operatingst<strong>and</strong>point are <strong>of</strong> a decentralized type, with a thermostatprovided on each unit or for each room. This permits eachAPA26/CC.3.2.2-4


2)3)APPENDIX C.3.2.2ELECTRIC HEATINGroom to compensate for heat contributed by sources auxiliarysuch as sunshine, lighting, <strong>and</strong> appliances. This arrangemental so gives a better diversity <strong>of</strong> the power dem<strong>and</strong> due tononcoincidence <strong>of</strong> electric load from all units <strong>of</strong> an installation.Manual switches are <strong>of</strong>ten provided to permit cutting<strong>of</strong>f heat or reducing temperature in rooms when not in use.When such operation is practiced, consideration should begiven to provide extra time for warm-up.Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWhA function <strong>of</strong> the resource used to generate electricity.appropriate Appendix C pr<strong>of</strong>iles.Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong> itsavailabil itySee--.'.'.......•......In summary, a simple list <strong>of</strong> some <strong>of</strong> the benefits <strong>and</strong> advantages<strong>of</strong> electric heat includes the following:"',0 Dependable0 No fuel deliveries0 No fuel storage problems0 Clean0 No venting required0 No oxygen consumption0 Individual room-by-room control0 Quiet0 Easy to install0 Space-saving...•..•..III'0 "Flameless ll C.3.2.2-5.... ,APA26/CIll.•.,


APPENDIX C.3.3INTERTIESC.3.3(A)ELECTRICAL TRANSMISSION INTERTIESGeneral Description1) Thermodynamic <strong>and</strong> engineering processes involvedElectric transmission is the most efficient <strong>and</strong> low cost means<strong>of</strong> delivering useful <strong>energy</strong> (except heat) to homes <strong>and</strong> communityenterprises.The outdoor, overhead, open-wire line is the least costly <strong>and</strong>least resource consuming electric line that exists. Thetypical open-wire overhead electric line consists <strong>of</strong> supportingstructures that carry the electrical conductors (3 wires for 3phase current) at a safe height in air that also provides theinsulation required.A single wire ground return (SWGR) transmission system canbest be described as single-phase, single wire transmissionsystem using the earth as a return circuit. SWGR is not a newtechnology; thous<strong>and</strong>s <strong>of</strong> miles <strong>of</strong> line have been in successfuloperat i on for more than thi rty years, mostly outs i de theUnited States (India, New Zeal<strong>and</strong>, Australia, Canada <strong>and</strong> inareas <strong>of</strong> the USA during World War II.) The SWGR lines suggestedhere are point-to-point connections with a carefully establishedgrounding system at each end point.The single wire configuration can be designed for minimum costby utilizing high-strength conductors that require a minimumnumber <strong>of</strong> structures <strong>and</strong> still retain the st<strong>and</strong>ards for highre 1 i ab il i ty.apa26/w1C.3.3-1


APPENDIX C.3.3INTERTIES..2) Current <strong>and</strong> future availabilityConvent i ona 1 transmi ss i on i ntert i es serve the lower 48 <strong>and</strong>major Alaskan popul at i on centers. Technology is well known....""(B)A demonstration project to supply Bethel central stationelectricity by SWGR to the village <strong>of</strong> Napakiak, a distance <strong>of</strong>8.5 miles, is presently in operation. This project has provideda demonstration <strong>of</strong> the technical <strong>and</strong> cost feasibility <strong>of</strong> theSWGR system in small scale Alaska situations. European singlephase systems exist in the 70 MW range.Performance Characteristics.'.....1)Energy outputa) Quality - temperature, form.,...Electricityb) Quantity..SWGR transmission to about 70 MW; conventional transmissionabove 70 MW.Electric lines deliver quantities <strong>of</strong> <strong>energy</strong> that areapproximately proportional to the square <strong>of</strong> the voltage<strong>of</strong> the circuit. For example, this means that an electricaltransmission line <strong>of</strong> 138 kV rating could beexpected to deliver 30 times as much power as a 25 kV1 i ne.WI'..-.,....apa26/w2C.3.3-2•


APPENDIX C.3.3INTERTIESc) Dynamics - daily, seasonal, annualAvailable whenever the electrical generating source is.2) Rel iabil itya) Need for back-upTransmission line reliability generally exceeds 99 percent.Diesel generators, currently installed in Cordova,would provide back-up should the transmission line betemporarily out <strong>of</strong> service.b) Storage <strong>requirements</strong>None required or applicable.3) Thermodynamic efficiencyNot appropriate.4) Net <strong>energy</strong>Line loss typically does not exceed 3-5% <strong>of</strong> gross <strong>energy</strong>transfer.(C)Costs1. CapitalA preliminary estimate <strong>of</strong> cost for the three transmissionroutes previously described for 50 MW transfer capability inthe conventional mode is:Route (1) Submarine, 3e, 60 Hz, 138 kV,81 mi. 4 sic Cables @ $650,000/mi. $52,650,0002 terminals @ $250,000) ea. 500,000apa26/w3C.3.3-3


3 mi. overl<strong>and</strong> @ $150,000/mi.Compensation (90 MVAR)Substations (100 MVA)TotalRoute (2) Overl<strong>and</strong>, 30, 60 Hz, 138 kV59 mi. 556.5 KCM ACSR equiv.APPENDIX C.3.3INTERTIES450,0002,100,0001,600,000$57,300,000@ $180,000/mi. $10,620,000CompensationSubstationso1,600,000Total$12,220,000...............Route (3) Overl<strong>and</strong>, 30, 60 Hz, 230 kV130 mi. 795 KCM ACSR equiv.@ $240,000/mi. $31,200,000Compensation (40 MVAR) 1,400,000Substations (@ 1.5 x 138 kV) 2,400,000Total $35,000,000The construction cost breakdown for IInormalll transmission lines,i.e., transmission lines with relatively short spans «1,500 feet)<strong>and</strong> wheeled or tracked vehicle access is about 50% labor <strong>and</strong> equipment<strong>and</strong> 50% materials. It is envisioned that the short section <strong>of</strong> overl<strong>and</strong>line needed for Route (1) <strong>and</strong> the transmission line from the CarbonCreek coal plant to Cordova, discussed elsewhere in this <strong>report</strong>, wouldbe <strong>of</strong> this type construction, at an estimated cost <strong>of</strong> $150,000 per mile -$75,000 per mile labor <strong>and</strong> equipment, <strong>and</strong> $75,000 per mile materials....•..It is estimated that the overall material costs for the Route (2)intertie will be the same since the transmission lines are carryingthe same amount <strong>of</strong> <strong>energy</strong>. However, the labor <strong>and</strong> equipment costswill be higher because <strong>of</strong> different construction techniques...apa26/w4C.3.3-4...


APPENDIX C.3.3INTERTIESThe construction techniques for the Route (2) intertie are envisionedas helicopter supported operations with line structures <strong>and</strong> footingsmodified for such equipment. Because <strong>of</strong> the mountainous terrain,it is anticipated that there will be many long spans which couldreduce the number <strong>of</strong> structures per mile <strong>and</strong> right-<strong>of</strong>-way clearing<strong>and</strong> thus the costs associated with each. It is estimated thatlabor <strong>and</strong> equipment costs for this type <strong>of</strong> construction will be 40%higher than I/normall/ or $105,000 per mile. This gives an estimatedtotal construction cost <strong>of</strong> $180,000 per mile.The transmission system <strong>of</strong> Route (2) could obtain substantialsavings in line costs by using this SWGR concept. Without anin-depth analysis, it will be assumed that the overhead line costscan be reduced by one-fifth <strong>and</strong> that the single phase substationswill cost 70% <strong>of</strong> the three phase equivalent. To these costs willbe added the estimated 1B to 3B conversion costs. This SWGR conceptwould then cost as follows:Route (2) 18, 60 Hz SWGR 161 kV l-G,59 mi. 1590 KCM ACSR @ $144,000/mi. $8,500,000Compensation 0Substations (100 MVA) 1,120,000Converters 18/38, 60 Hz,for 1/3 <strong>of</strong> 50 MWTotal2,500,000$12,120,0002. Assembly <strong>and</strong> install ati onsee above3. Operationnegligable4. Maintenance <strong>and</strong> replacementAnnual maintenance cost for transmission lines isestimated to be $200 per mile.apa26/w5C.3.3-5


APPENDIX C.3.3INTERTIESAnnual replacement cost estimated to be 1.% <strong>of</strong> the capitalinvestment..."",(D)Special Requirements <strong>and</strong> Impacts1)Siting - directional aspect, l<strong>and</strong>, heightThe physical dimensions <strong>of</strong> electric lines are determinedprimarily by the voltage <strong>of</strong> the line which requires thatsufficient air space between wires exist to prevent costlyelectric losses through <strong>energy</strong> leaks <strong>and</strong> provide safe clearancesabove ground, other structures, vehi cl es, flora <strong>and</strong>fauna....2)3)Electric lines that can be placed underground or carried atlesser spacings than open-wire lines must replace the insulationprovided by the air with other non-conducting materials<strong>of</strong> equivalent electrical strength <strong>and</strong> smaller dimension.Insulated electric cables typically use a rubber or plasticcompound or a high-grade paper saturated with insulating oil.Insulated electric cable transmission lines are typically muchmore costly (5 to 40 times) than open-wire lines.Resource needsTransmission <strong>of</strong> electrical <strong>energy</strong> generated from either renewableor non-renewable resources.Construction <strong>and</strong> operating employment by skill...............-..For a transmission intertie from Cordova to Valdez, highlyskilled pr<strong>of</strong>essional construction labor supervisors will berequired to direct locally available personnel. Operationalemployment consists chiefly <strong>of</strong> qualified maintenance personnel....apa26/w6


APPENDIX C.3.3INTERnES4) Environmental residualsRight-<strong>of</strong>-way clearing is the major impact in forested areas;some soil disturbance is required during installation.5) Health or safety aspectsCurrent aspects are widespread in acceptability.The use <strong>of</strong> the earth as the return circuit for SWGR would inno way create an operating system wi th 1 esser safety thanthose now accepted.(E)Summary <strong>and</strong> Critical Discussion1) Cost per million BTU or kWhNot appropriate2) Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWh.Not available.3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong>its availability.Convent i ona 1 three phase t ransmi s s ion is we 11extremely widely used.proven <strong>and</strong>The successful construction <strong>and</strong> operation <strong>of</strong> the SWGR transmissionline between Bethel <strong>and</strong> Napakiak has proven the technicalfeasibility <strong>of</strong> the SWGR concept in Alaska. Additionaloperation <strong>of</strong> the line should prove the reliability <strong>of</strong> the linedesign, enhance potential user confidence <strong>and</strong> encourage additionalconstruction.Materials used in the construction <strong>of</strong>apa26/w7C.3.3-7


•APPENDIX C.3.3INTERTIES~_'_tthe line are, for the most part, st<strong>and</strong>ardized distribution <strong>and</strong>transmission line hardware. Materials are generally availablefrom manufacturers within a reasonable time period...,......III......apa26/w8C.3.3-8


APPENDIX C.3.4.1COAL-ELECTRICC.3.4.1COAL FIRED STEAM-ELECTRIC GENERATION(A)General Description•1) Thermodynamic <strong>and</strong> engineering processes involvedCoal is ground to roughly less than 2 inch diameter chunks <strong>and</strong>mechanically loaded onto a boiler grate after which it iscombusted in the boiler to heat incoming water to steam. Thesteam is then exp<strong>and</strong>ed in a turbine which drives a generatorto produce electricity. Figure 3.1.1-1 shows a basic steampower cycle.2) Current <strong>and</strong> future availabilitySteam plants account for the majority <strong>of</strong> electrical generationin the United States today. Although steam plants can accomodatea wide range <strong>of</strong> loads, U.S. economies <strong>of</strong> scale indicatethat the cost per unit increases sharply in sizes below about50 MW. It should be noted that European coal-steam generationunits are employed in the less than 10 MWrange.(B)Performance Characteristics1) Energy outputa) Quality - temperature, formElectricityapa26/a1C.3.4.1-1


1iI>"APPENDIX C.3.4.1COAL -ELECTRIC-b) Quantity....Typically 5-50 MW; rarely as small as 1 MW (1000 kW).c) Dynamics - daily, seasonal, annualCoal fired steam plants are typically used for base powerwithout respect to time <strong>of</strong> year.2) Re 1 i ab il i tya) Need for back-up65% capacity factor....b) Storage <strong>requirements</strong>Typical storage is sufficient supply for 90 days <strong>of</strong>operation. For village areas, up to 9 months worth <strong>of</strong>coa 1 storage may be requi red to guarantee continuoussupply irrespective <strong>of</strong> weather.3) Thermodynamic efficiencyup to 33%4) Net <strong>energy</strong>9,500 - 17,500 Btu/kWh......".....-apa26/a2C.3.4.1-2..,....


APPENDIX C.3.4.1COAL-ELECTRIC(C) Costs (1980 $)1) Capital• $1350/kW (Kotzebue 5000 kW, 1980)• $1700/kW installed (Cordova 5 MW)• $2100/kW installed (Carbon Creek 5 MW)2) Assembly <strong>and</strong> installation• $770/kW (Kotzebue 5000 kW)• See above for Cordova <strong>and</strong> Carbon Creek3) Operation• $450,000/year (Kotzebue 2500 kW <strong>and</strong> 5000 kW)• $360,000/year (Cordova)• $450,000/year (Carbon Creek)4) Maintenance <strong>and</strong> replacement• 2% <strong>of</strong> investment per year (Bri stol Bay mai ntenance)• 2.5% <strong>of</strong> investment per year (Cordova maintenance)• 9.4% <strong>of</strong> investment per year (replacement @ 7% for20 years).5) Economies <strong>of</strong> scaleEconomies <strong>of</strong> scale favor larger scale plants, particularlywith respect to coal h<strong>and</strong>ling facilities. (Upcoming plants inthe lower 48 are typi ca lly <strong>of</strong> 500 MW size.) Economi es inoperator <strong>requirements</strong> also favor large plants.apa26/a3C.3.4.1-3


APPENDIX C.3.4.1COAL-ELECTRIC...(D)Special Requirements <strong>and</strong> Impacts1)Siting - directional aspect, l<strong>and</strong>, height......2)Coal plants require space for storage <strong>of</strong> fuel, typically a 3to 9 month supply. If the plant is sited at the mine, h<strong>and</strong>ling<strong>and</strong> storage <strong>requirements</strong> are lessened; storage <strong>of</strong> a month'sfuel is adequate.Resource needsa) RenewableN/Ab) Non-renewable......' ......3)Typical Alaskan coal ranges from 6500 to 15,000 Btu perpound.Construction <strong>and</strong> operating employment by skill..Requires highly skilled construction <strong>and</strong> operation personnel.4) Environmental residuals• Solid wastes: include slag, bottom ash, scrubber sludge.•Gaseous wastes: NO x' SOxCurrent environmental requlations regarding sulfur dioxideemissions from conventional coal-steam plants generallyrequire abatement processes which significantlyincrease the cost <strong>of</strong> such plants...•..-..- ....apa26/a4C.3.4.1-4


APPENDIX C.3.4.1• COAL-ELECTRIC5) Health or safety aspectsCoal fired plants emit the following, as yet unregulated,atmospheric pollutants: toxic <strong>and</strong> carcinogenic trace elements,radionuclides, <strong>and</strong> organic <strong>and</strong> metal-organic compounds.Considerations include impact <strong>of</strong> transport <strong>and</strong> storage <strong>of</strong>fuel, risk <strong>of</strong> spontaneous combusion, <strong>and</strong> coal pile run <strong>of</strong>f.(E)Summary <strong>and</strong> Critical Discussion1) Cost per million BTU or kWh• 20.3¢/kWh (Kotzebue 2500 kW busbar cost in 1984).2) Resources, <strong>requirements</strong>, environmental residuals per millionBTU or kWh• For coal at 10,000 Btu per pound <strong>and</strong> plant at 17,500Btu/kWh, 1.8 pounds <strong>of</strong> coal are needed per kWh.• NO emissions are about 0.15 lbs/million Btu.x• SO emissions are about 0.067 lbs/million Btu.x• Particulate emissions are about 0.006 lbs/million Btu.• Solid wastes are about 10% <strong>of</strong> fuel burned.3) Critical discussion <strong>of</strong> the technology, its reliab"ility <strong>and</strong>its availabilityIn general, the conventional boiler-fired steam turbine systemis the most economic <strong>and</strong> technologically developed systemavailable to the power industry. Operational economics requirea minimum plant size <strong>of</strong> S MW, however. Lead time is significantlylonger than for diesel or gas turbine installation.apa26/a5C.3.4.1-S


STEAM HEADERr---~------,III+I EXHAUST GASES II OUTIIIITURBINECOAL INBOILER+--... ASHOUT...........••..."..STEAMCONDENSERCONDENSATEDIAGRAM OF RUDIMENTARY STEAM POWER PLANTfiGURE C.3.4.1-1.......• ..


APPENDIX C.3.4.2COAL AND WOOD HEATINGC.3.4.2COAL AND WOOD HEATING(A)General Description1) Thermodynamic <strong>and</strong> engineering processes involvedA mechanical stoker is a device that feeds coal or wood into acombustion chamber. It provides a supply <strong>of</strong> air for burningthe fuel under automatic control <strong>and</strong>, in some cases, incorporatesa means <strong>of</strong> removing the ash <strong>and</strong> refuse <strong>of</strong> combustion automatically.Coal <strong>and</strong> wood can be burned more efficiently by amechanical stoker than by h<strong>and</strong> firing because the stokerprovides a uniform fuel feed rate, better distribution in thefuel bed, <strong>and</strong> positive control <strong>of</strong> the air supplied for combustion.2) Current <strong>and</strong> future availabilityCommercially available <strong>and</strong> widespread in use, particularly inthe Eastern United States.(B)Performance Characteristics1) Energy outputa) Quality - temperature, formHot air for space heating or hot water for hydronic spaceheating.b) QuantityResidential units are typically sized in the75,000-150,000 Btu per hour range.-APA26/KlC.3.4.2-1


APPENDIX C.3.4.2COAL AND WOOD HEATING..c) Dynamics - daily, seasonal, annual.'Available whenever the coal or wood supply is available.2)Re 1 i ab il i tya) Need for back-upNone usually required.b) Storage <strong>requirements</strong>Storage is required. A one month supply for a largeresidential unit run continuously is on the order <strong>of</strong> 5tons.3) Thermodynamic efficiencyAbout 25% (h<strong>and</strong> fired) to about 70% (automated).4) Net <strong>energy</strong>.,•........About 1. 4 to 4.0 units in to 1.0 units out.(C)Costs1) Capital..About $1200-1500 per unit.2) Assembly <strong>and</strong> installation..About equal to two to three times capital costs...APA26/K2C.3.4.2-2


APPENDIX C.3.4.2COAL AND WOOD HEATING3) OperationNegligible cost as operation is provided by the resident.Stokers for residential operation are usually screw fed underfeedtypes, <strong>and</strong> are designed for quiet, automatic operation.4) Maintenance <strong>and</strong> replacementUseful life is 10-20 years with simple maintenance. Sootdeposits on flue surfaces <strong>of</strong> a boiler or heater act as aninsulating layer over the surface, reducing heat transfer tothe water or air. Soot can also clog flues, reduce the draft,<strong>and</strong> prevent proper fuel selection <strong>and</strong> combustion. Soot accumulationcan be held to a minimum by proper burner adjustment<strong>and</strong> periodic cleaning.5) Economies <strong>of</strong> scaleNot appropriate.(D)Special Requirements <strong>and</strong> Impacts1) Siting - directional aspects, l<strong>and</strong>, heightFuel storage is the major siting impact.isolated from flammable material.The burner should be2) Resource needsa) RenewableWood.APA26/K3C.3.4.2-3


APPENDIX C.3.4.2COAL AND WOOD HEATING.,b) Non-renewableCoal.3) Construction <strong>and</strong> operating employment by skillInstalled by locally available services; operated by thehomeowner.4) Environmental residualsCarbon dioxide, carbon monoxide, soot, ash, oxides <strong>of</strong> nitrogen,<strong>and</strong> sulfur oxides.5) Health or safety aspectsFuel should be sheltered to prevent run<strong>of</strong>f from precipitation.Units must be located a safe distance from flammable material s.•••..•..(E)Summary <strong>and</strong> Critical Discussion1) Cost per million Btu or kWhCarbon Creek coal at $120/ton <strong>and</strong> 12,000 Btu/pound costs $7.00per million Btu; Healy coal at $45/ton <strong>and</strong> 8,000 Btu/poundcosts $4.00 per million Btu, taking into account heatingefficiency. Wood costs were not available.•..2) Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWh.APA26/K4Requires 83.3 pounds <strong>of</strong> Carbon Creek coal or 125 pounds <strong>of</strong>Healy coal per million Btu; for dried wood at a nominal8000 Btu/pound, 125 pounds per million Btu are required.Environmental residuals for coal <strong>and</strong> wood, based on boilerfiring to produce steam for electrical generation, are asfo 11 ows.C.3.4.2-4..,...•


APPENDIX C.3.4.2COAL AND WOOD HEATINGCOAL:•NO Xemissions are about 0.15 lbs/million Btu.SOX emissions are about 0.067 lbs/million Btu.Particulate emissions are about 0.006 lbs/million Btu.Solid wastes are about 10% <strong>of</strong> fuel burned.WOOD••NO Xemissions are about 0.25 - 1.18 lbs/million Btu.SOX emissions are about 0.07 - 0.18 lbs/million Btu.Particulate emissions are about 0.02 lbs/million Btu.Residual ash from wood-firing is not classified as ahazardous waste; firing wood actually decreases the amount<strong>of</strong> solid waste in the environment.3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong> itsavai 1 abil ityThe technology is commercially available <strong>and</strong> reliable.Implementation <strong>of</strong> coal technology in Cordova is dependent uponthe availability <strong>of</strong> Carbon Creek or Healy coal at prices notedfor power production.Although dry wood (at about 8000 Btu/pound) has about the samepotential heat content as Healy coal, most wood is naturallysufficiently moist to reduce this heat value by 40 to 50percent. In addition to the moisture content, the relativevolume to weight ratio <strong>of</strong> wood is disadvantageous as comparedto coal, with consequent increased gathering, transportation,<strong>and</strong> h<strong>and</strong>ling <strong>energy</strong> <strong>requirements</strong>.There has been a noticeable shift in Cordova in the lasttwo years from heating oil to wood stoves. It has been<strong>report</strong>ed that the main restriction on wood harvesting inthe Chugach National Forest is that the l<strong>and</strong> available hasAPA26/K5C.3.4.2-5


•APPENDIX C.3.4.2COAL AND WOOD HEATINGbeen IIselectedll by Eyak Village Corporation <strong>and</strong> ChugachNatives, Inc. Wood gathering by permit or fee might be allowedafter title has been fully transferred to the Native groups.•......•........IIIAPA26/K6C.3.4.2-6"'.


APPENDIX C.3.S.1LUBE OIL RECYCLINGC.3.5.1DIESEL LUBE OIL RECYCLING(A)General Description1) Thermodynamic <strong>and</strong> engineering processes involvedCommercially available units automatically remove water, rust,dirt, <strong>and</strong> other contaminants from used diesel lubricating oil.This recycled oil is then mixed at one part oil to 20 partsdiesel fuel.2) Current <strong>and</strong> future availabilityCurrently scheduled to be employed in Cordova(B)Performance Characteristics1) Energy outputa) Quality - temperature, formOil at about 130,000 Btu/lb.b) QuantityA function <strong>of</strong> the size <strong>and</strong> number <strong>of</strong> diesel units.c) Dynamics - daily, seasonal, annualCan be made to operate continuously.apa26/e1C.3.5.1-1


2) Re 1 i ab il i tya) Need for back-upAPPENDIX C.3.S.1LUBE OIL RECYCLINGIn the event <strong>of</strong> breakdown, pure diesel fuel is utilized.b) Storage <strong>requirements</strong>Typically 40 gallons.3) Thermodynamic efficiency......••N/A(C)4) Net <strong>energy</strong>CostsN/A...,1) CapitalAbout $4000 for a powerplant size unit.2) Assembly <strong>and</strong> installationPortable.3) OperationNot avail ab 1 e....•-......If"apa26/e2C.3.5.1-2..


APPENDIX C.3.S.1LUBE OIL RECYCLING4) Maintenance <strong>and</strong> replacementNot available.5) Economies <strong>of</strong> scaleA typical unit is rated at 6 gallons per minute.(D)Special Requirements <strong>and</strong> Impacts1) Siting - directional aspects, l<strong>and</strong>, heightNeeds about four square feet <strong>of</strong> floor space, st<strong>and</strong>s about fourfeet high.2) Resource needsa) RenewableNone.b) Non-renewableUsed diesel lubricating oil.3) Construction <strong>and</strong> operating employment by skillEasily installed <strong>and</strong> virtually automatic in operation.4) Environmental residualsRust, dirt, sediment, dirty water.apa26/e3C.3.5.1-3


5) Health <strong>and</strong> safety aspectsAPPENDIX C.3.5.1LUBE OIL RECYCLING•It.•Negligible.(E)Summary <strong>and</strong> Critical Discussion1) Cost per million Btu or kWh""Not available.2)Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWh..Unavailable.3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong> itsavailabil ityDue to increased fuel costs <strong>and</strong> the lack <strong>of</strong> adequate means todispose <strong>of</strong> used lubricants, this reliable, commercially availabletechnology is becoming increasingly more widely used.iii,•- ••Tests by diesel engine manufacturers have found no noticeabledifference in performance or life for engines run on theblended mixture as compared to those run on straight dieselfuel. The blended fuel seems to deliver better cold weatherperformance with less freeze-up as compared to #2 diesel fuel.II.. ..apa26/e4C.3.5.1-4"""•..•


APPENDIX C.3.S.2WASTE HEATC.3.S.2DIESEL WASTE HEAT UTILIZATION(A)General Description1) Thermodynamic <strong>and</strong> engineering processes involvedThe present use <strong>of</strong> fossil fuels to produce electricity is far1 ess than 100 percent effi c i ent. For example, an averagedi ese 1 generator burns foss il fuel <strong>and</strong> produces e 1 ectri ca 1output equivalent to about 30% <strong>of</strong> the fuel burned; the <strong>energy</strong>represented by the remaining 70% <strong>of</strong> the fuel appears as unusedor "waste" heat.Such heat most <strong>of</strong>ten appears as hot exhaustgas, tepid to warm jacket water (about 180°F), hot air fromexhaust, <strong>and</strong> direct radiation from the machine.Diesel waste heat can be recovered from engine cooling water<strong>and</strong> exhaust (as shown in Figure C.3.S.2-1), or either sourceseparately. The waste heat is typically transferred to awater-glycol circulating system in Alaskan applications. Theheated ci rcul at i ng fl ui d can be used for space, water, orprocess heating.2) Current <strong>and</strong> future availabilityPractice in Alaska is growing as a result <strong>of</strong> sharp increasesin cost <strong>of</strong> diesel fuels. Recovery <strong>of</strong> jacket water heat onlyis most common in Alaska <strong>and</strong> is shown in Figure C.3.S.2-2.(B)Performance Characteristics1) Energy outputa) Quality - temperature, formCooling water is typically 160-200 o F. Exhaust heatvaries with engine speed <strong>and</strong> load <strong>and</strong> ranges from about300 to 600°F.apa26/s1C.3.S.2-1


••..EXHAUST GASCHEAT ~ECOVER -SILENCER• _..L~-----'------- -+OL-.-f--FROM REMOTE(--HEAT LOOPEXPANSIONTANKRADIAToRAIRFLoW••..BOOSTERPUMP,---THERMOSTATICCONTACTOR...III...II.JACKET WATER 8 EXHAUST WASTE HEAT RECOVERY SYSTEMFIGURE C.3.5.2-1II'


SPACE HEAT--ENGINE !I---FL!- -THEMIOSTATICSWITCHAIR0wJACKET WATER WASTE HEAT RECOVERY SYSTEMFIGURE C.3.5.2-2


APPENDIX C.3.5.2WASTE HEAT..•..b) QuantityAll <strong>of</strong> the cooling water heat, about half <strong>of</strong> the exhaustheat, <strong>and</strong> all <strong>of</strong> the radiation can be usefully capturedif space heat needs are in economic proximity.Table C.3.5.2-1 indicates the annual recoverable wasteheat for various diesel unit sizes <strong>and</strong> generating efficiencies(ie. kWh/gal <strong>and</strong> heat rates in Btu/kWh) <strong>and</strong> assumesthat one-third <strong>of</strong> the fuel heat ;s recoverable.TABLE C.3.5.2-1WASTE HEAT AVAILABILITylII'..y •....,10 6 Btu/year Available at Indicated Generating EfficiencykWkWh/year14 kWh/gal(9,900 Btu/kWh)12 kWh/gal(11,500 Btu/kWh)10 kWh/gal(13,800 Btu/kWh)8 kWh/gal(17,250 Btu/kWh)5007501000200025001,752,000 5,756 6,716 8,059 10,0742,628,000 8,634 10,074 12,089 15,1113,504,000 11,512 13,432 16,118 20,1487,008,000 23,024 26,864 32,236 40,2968,760,000 28,780 33,580 40,295 50,370...•..1Assumes 138,000 Btu/gall on fuel, 0.40 load factor.. ,...apa26/s4C.3.5.2-4•••


APPENDIX C.3.5.2WASTE HEATc) Dynamics - daily, seasonal, annualWaste heat is available whenever its diesel generationsource is in operation.2) Re 1 i abil itya) Need for back-upHeat recovery systems require a back-up heat source 'incase <strong>of</strong> system shutdown. This is typically provided byheaters that ex is ted pri or to ins ta 11 at i on <strong>of</strong> therecovery system <strong>and</strong> were consequently idled by it.b) Storage <strong>requirements</strong>Waste heat is generally utili zed as it is recovered;storage <strong>of</strong> heat is currently atypical.3) Thermodynamic efficiencyN/A4) Net <strong>energy</strong>N/A(C)Costs1) Capitalapa26/s5Costs <strong>of</strong> waste heat recovery <strong>and</strong> uti 1 i zat i on systems aregreat ly i nfl uenced by the specifi c area served.In responseto local interest, three example systems specific to Cordovaare presented following; the first two examples presented <strong>and</strong>three others are treated in detail in Final Report, PowerPlant Site Investigation, Cordova, Alaska by Robert W. RetherfordAssociates (1980).C.3.S.2-S


APPENDIX C.3.5.2WASTE HEATTable C.3.5.2-2 lists the facilities discussed in the examples<strong>and</strong> their estimated annual heating oil consumption values...TABLE C.3.5.2-2HEATING OIL USElIPFACILITYESTIMATED ANNUALHEATING OILUSE, GALLONS1, 21.2.3.4.5.6.7.8.9.Reluctant Fisherman MotelMorpac, Inc. (Cannery)North Pacific Processors (Cannery)St. Elias Ocean Products (Cannery)City HallB. Korn PoolDomestic Water HeatingHospitalElementary School36,00071,000106,000131,00013,00027,000255,000 318,00020,000IIi1 Rounded to nearest 1000 gallons2 1979 values except for hospital <strong>and</strong> elementary school whichare 1980 values3 Does not currently exist...apa26/s6C.3.5.2-6.. ......, .•••


APPENDIX C.3.S.2WASTE HEATOnly a portion <strong>of</strong> the steam requirement <strong>of</strong> the canneries can besupplied by the waste heat recovery systems under discussion.Based on use <strong>of</strong> the existing power plant site, steam would besupplied only to North Pacific <strong>and</strong> St. Elias canneries.Heating that could potentially be supplied to the City1s watermains depends upon the plan selected. We have assumed anincrease in water mains temperature <strong>of</strong> 10°F, <strong>and</strong> that SO% <strong>of</strong>all water used is heated before being used. The SO% figure isconservative, even in summer. It has been stated that manyres i dents keep faucets runni ng duri ng the wi nter to helpprevent freezing <strong>of</strong> water lines; although it is most difficultto derive a II va l ue ll for the water thusly wasted, a higherwater mains temperature would greatly decrease that area <strong>of</strong>waste. Based on conservative assumptions, then, the annualamount <strong>of</strong> equivalent annual <strong>energy</strong> to heat the water mains isabout 25S,000 gallons <strong>of</strong> fuel oil. 1Since the City water system is not now heated, any waste heatintroduced into the water system would not directly replacefuel. However, it would indirectly displace fuel in that less<strong>energy</strong> in the form <strong>of</strong> electrical or oil heating <strong>of</strong> water wouldbe used by individual consumers. All consumers would benefitto some extent because <strong>of</strong> savings in water heating <strong>and</strong> fewerproblems with freezing <strong>of</strong> water mains <strong>and</strong> taps.1 Assumi ng further, 1, sao, 000 ga 11 ons <strong>of</strong> heated water heated at 6S%efficiency using 138,000 Btu/gallon fuel oil.apa26/s7C.3.S.2-7


APPENDIX C.3.S.2WASTE HEATEXAMPLE 1Waste heat recovery equipment installed in the existing powerplant would serve to provide:• Steam generation to serve the sustained year-round levelizedload <strong>of</strong> two canneries. (The peak steam loads <strong>of</strong> each cannerywould continue to be served by their existing steam boilers.)Buried insulated steam lines would be routed underground toconnect to the existing mains in each plant.return lines are to be provided.No condensate• Space heating by use <strong>of</strong> pumped hot water mains to servethe motel, the Community Center building <strong>and</strong> the swimmingpool. These facilities are all heated by compatible hotwater heating systems.•Heating <strong>of</strong> the City's cold water mains to raise the temperaturefrom an average <strong>of</strong> 40°F up to about SOoF to reducefuel consumption by all water users north <strong>of</strong> the powerplant which would include all three canneries exceptduring their two-month seasonal peak. An allowance isincluded in this alternate for a limited amount <strong>of</strong> reconfiguration<strong>of</strong> the water system to circulate heated waterthrough some portions <strong>of</strong> the water system south <strong>of</strong> thepower pl ant....t.-•0,III.The existing diesel generation plant would be provided withheat exchangers for waste heat recovery from engi ne jacketcool ing water systems <strong>and</strong> from the engine exhaust systems.The existing jacket-water systems would be manifolded together<strong>and</strong> connected to a cooling water loop containing a heat recoveryheat exchanger, thus providing a supply <strong>of</strong> heating water up toapproximately 190°F maximum.This heat recovery loop would beconnected to a new air cooled heat radiator circuit for st<strong>and</strong>bycooling <strong>of</strong> the engine jacket water during emergency periods.... ,..."',apa26/sSC.3.S.2-S


APPENDIX C.3.5.2WASTE HEATAn exhaust gas waste heat recovery boiler would have an intakemanito 1 d to co 11 ect exhaust gases from the three 1 argestdiesel units. The exhaust gas boiler would boost the heatingwater supply temperature to 240 D F <strong>and</strong> the surplus heat remainingwould generate 150 psi steam for delivery to the canneries.Plant auxiliaries would include a make-up water treatmentunit.A buried, insulated steam main would be routed to twocanneries, with no condensate return piping.Parallel to thesteam main in the same trench would be heating water supply<strong>and</strong> return mai ns for space heating 1 arge oil users in thecommunity.The low temperature heating water would supply aheat exchanger so that the municipal cold water main would beheated from 40 D F to 50 D F under year-round average conditions.This alternate would require an investment <strong>of</strong> $1,900,000 forheat recovery equipment, would displace 76,000 gallon per year<strong>of</strong> fuel for space heating, 189,000 gallons per year <strong>of</strong> fueloil for steam heat at canneries, <strong>and</strong> can supply heat to theCity water system equivalent to 195,000 gallon <strong>of</strong> fuel oil peryear.EXAMPLE 2The heat recovery aspects <strong>of</strong> this example are similarto Example 1.However, the heat produced would be used toheat only the City water system rather than to heat commercialloads. During the winter months the temperature <strong>of</strong> 1 milliongallons per day could be increased from 37°F to 56°F, <strong>and</strong>during the summer 2 million gallons per day could be warmedfrom 45 D F to 54°F.Since the City water mains are relativelynear the power plant, investment in heat distribution facilitieswould be much less than for other alternates.This alternate would require an investment <strong>of</strong> about $160,000<strong>and</strong> would supply heat equivalent to 255,000 gallons <strong>of</strong> oil peryear to the City water system.apaZ6/s9C.3.S.2-9


APPENDIX C.3.5.2WASTE HEAT2)EXAMPLE 3A simple heat recovery system utilizing only a portion <strong>of</strong> heatrecoverable from existing diesel jacket water heat wouldprovide hot water for space heating the hospital <strong>and</strong> elementaryschool in Cordova. Cost for this system is estimated to be$270,000; fuel oil displaced is about 38,000 gallons per year.Assembly <strong>and</strong> installation......See above.3)OperationI.4)5)Not available.Maintenance <strong>and</strong> replacement•2% <strong>of</strong> capital investment per year (maintenance)•9.4% <strong>of</strong> investment per year (replacement at 7% for 20 years)Economies <strong>of</strong> scaleSmall systems may be as beneficial economically as very largesystems because required equipment is less sophisticated <strong>and</strong>consequently less costly.Cost <strong>of</strong> redundancy <strong>requirements</strong> istypically lower (per unit recovered) in smaller systems, also.••...........(0) Special Requirements <strong>and</strong> Impacts1) Siting - directional aspect, l<strong>and</strong>, heightShould be immediately adjacent to diesel engine.....apa26/s10C.3.5.2-10...,


APPENDIX C.3.5.2WASTE HEAT2) Resource needsa) RenewableWaste heat, according to the Third Law <strong>of</strong> Thermodynamics,is a continually increasing resource (a "self-renewing"resource) .b) Non-renewableDoes not increase non-renewable resource <strong>requirements</strong>above the already established diesel fuel usage forgeneration.3) Construction <strong>and</strong> operating employment by skillJacket water heat recovery systems are installable <strong>and</strong> operableby local personnel qualified for similar work with dieselgenerators.4) Environmental residualsEnvironmental residuals are those associated with dieselgeneration.5) Health or safety aspectsNo negative health or safety aspects except those associatedwith the heat source.(E)Summary <strong>and</strong> Critical Discussion1) Cost per million Btu or kWhSee (C) above.apa26/s11C.3.5.2-n


APPENDIX C.3.5.2WASTE HEAT...2)Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWh...These items are whatever is attributable to diesel generation.3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong>its availabilityWaste heat capture can provide significant savings in overallfuel use.Was te heat ut i 1 i zat ion, however, is not free, even thoughthere may not actually be a direct charge for the heat. Theequipment for utilizing this heat requires a sizeable capitalinvestment <strong>and</strong> is feasible only when the cost for associatedequipment is less than the cost <strong>of</strong> the fuel saved.The cri t i ca 1 poi nt <strong>of</strong> any efforts to evaluate waste heatrecovery is that point at which the equivalent annual cost <strong>of</strong>recovering heat will be less than the cost <strong>of</strong> generating heatby other means. Low grade waste heat cannot be transportedvery far for its actual resale value.""", ... "-apa26/s12C.3.5.2-12•


APPENDIX C.3.S.3COGENERATIONC.3.S.3STEAM COGENERATIONCA)General Description1) Thermodynamic <strong>and</strong> engineering processes involvedCogeneration involves use <strong>of</strong> some <strong>of</strong> the steam used to driveturbines for heating or industrial process loads. Two types<strong>of</strong> specialized steam turbines are used: back-pressure turbines<strong>and</strong> extraction turbines.In the back-pressure turbines, the exhaust steam is employedfor some heating process, <strong>and</strong> the turbine work may be a byproduct.If all the exhaust steam is condensed in heatabsorbingapparatus <strong>and</strong> returned to the system, the thermalefficiency <strong>of</strong> the system may be over 90 percent.With extraction turbines, partly exp<strong>and</strong>ed steam is extractedfor external process use at one or more points. The turbinesmay be either condensing or noncondensing. Extraction turbinesare usually designed to sustain full rated output, withor without extraction, <strong>and</strong> are provided with automatic regulatingmechanisms to deliver steam from the extraction pointsat constant pressure, as long as there is sufficient powerload to permit the necessary flow.2) Current <strong>and</strong> future availabilityCogeneration is employed worldwide.APA26/flC.3.S.3-1


(B)Performance CharacteristicsAPPENDIX C.3.5.3COGENERATION.......I} Energy output...a} Quality - temperature, formSteamb} QuantityBased on heating <strong>requirements</strong> <strong>and</strong> turbine design.c} Dynamics - daily, seasonal, annualAvailable whenever steam ;s passed through the turbine.2} ReHabil ityIt.a} Need for back-upCogeneration systems are typically utilized with noback-up. Capacity factor is 70%.b} Storage <strong>requirements</strong>None, other than fuel storage for the boiler... ,......•3} Thermodynamic efficiencyCan exceed 90%, particularly if the heat loads are the basis<strong>of</strong> steam sizing, rather than electrical loads....APA26/f2C.3.5.3-2.."...


APPENDIX C.3.S.3COGENERATION4)Net <strong>energy</strong>4700 Btu/kWh (typical)(C)Costs1)Capital$730/kW (California)2)Assembly <strong>and</strong> installationNot avail abl e.3)OperationNot available.4)Maintenance <strong>and</strong> replacementNot avail abl e.5)Economies <strong>of</strong> scaleEconomic in the 1-7 MWrange representative <strong>of</strong> Cordova.The economies <strong>of</strong> scale should have a decided effect upon theunit cost <strong>of</strong> larger coal burning, steam producing facilitiesin the area <strong>of</strong> fuel transportation <strong>and</strong> coal terminal facilities.There shoul d be ample economi c i ncent i ves to createlarge cogeneration facilities <strong>and</strong> thereby gain the advantage<strong>of</strong> lower unit costs per pound <strong>of</strong> steam.APA26/f3C.3.S.3-3


APPENDIX C.3.5.3COGENERATION(0) Special Requirements <strong>and</strong> Impacts1) Siting - directional aspect, l<strong>and</strong>, heightSteam turbines require about 3000 square feet <strong>of</strong> associatedplant space. See also Appendix C.3.4.1-2) Resource needsa) RenewableNone.b)Non-renewable...Fuel used to fire boilers; coal is considered for use inCordova. See also Appendix C.3.4.1.3) Construction <strong>and</strong> operating employment by skill...Requires highly skilled construction <strong>and</strong> operation personnel.4) Environmental residualsSee Appendix C.3.4.1.5) Health or safety aspectsSee Appendix C.3.4.1.APA26/f4C.3.5.3-4"'r


APPENDIX C.3.S.3COGENERATION(E)Summary <strong>and</strong> Critical Discussion1) Cost per million Btu or kWhNot available.2) Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWhSee Appendix C.3.4.1.3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong> itsavailabil ityThe technology is well established, reliable, <strong>and</strong> commerciallyavailable. Many <strong>of</strong> the small cogeneration systems for industryuse combustion turbines; steam turbine cogeneration is widelypract iced at the 10 MW 1 eve 1 in the Sc<strong>and</strong>anavi an countri es.Most applications involve small systems. This is due largelyto the fact that industrial steam loads are small <strong>and</strong> theeconomics <strong>of</strong> cogeneration systems are usually optimized bysizing the system to closely meet industrial process steam<strong>requirements</strong>. Electrical generation is usually not the factordetermining the choice <strong>of</strong> size for the turbine.Economics also determine the choice <strong>of</strong> prime mover (i .e.,combustion vs. steam turbine), but other factors such as theratio <strong>of</strong> the industrial customer's heat to power requirementare important determinants <strong>of</strong> equipment selection.Becausecombustion turbines have heat to power ratios similiar to mostindustrial loads, they have become the major option for proposedcogeneration applications.lower, steam turbines are normally indicated.However, when the ratio isFifty percent fuel savings are typically possible with conventionalturbines when modified for cogeneration-based districtheat i ng.APA26/fSC.3.S.3-S


Section C.3.S.4CONSERVATION.,.'C.3.S.4 CONSERVATION(A) General Description.....1)Thermodynamic <strong>and</strong> engineering processes involvedConservation measures for the 13 villages considered here aremainly classified as "passive". Passive measures are intendedto conserve <strong>energy</strong> without any further electrical, thermal, ormechanical <strong>energy</strong> input. Typical passive measures are insulation,double glazing or solar film, arctic entrances <strong>and</strong>weather stripping. Energy conservation characteristics <strong>of</strong>some passive measures degrade with time, which must be consideredin the overall evaluation <strong>of</strong> their effectiveness foran intended life cycle.....2)Current <strong>and</strong> future availability(B)Passive measures are commercially available <strong>and</strong> increasing inuse allover the United States due to the rapidly escalatingcost <strong>of</strong> <strong>energy</strong>.Performance Characteristics--1)Energy outputa) Quality - temperatures, formNo <strong>energy</strong> output per se; rather a reduction <strong>of</strong> <strong>energy</strong>types input.•......b) QuantitySee above..,... ..APA26/LC.3.5.4-1..II1II


Section C.3.S.4CONSERVATIONc) Dynamics - daily, seasonal, annualPassive conservation measures "operate" year round.2) Reliabilitya) Need for back-upNone requi red.b) Storage <strong>requirements</strong>None required.3) Thermodynamic efficiencyNot appropriate.4) Net <strong>energy</strong>Not appropriate.(C)Costs1) CapitalResidential installations run from several hundred to severalthous<strong>and</strong> dollars.2) Assembly <strong>and</strong> installationSee above.APA26/LC.3.S.4-2


3)OperationSection C.3.5.4CONSERVATION.......None.4)Maintenance <strong>and</strong> replacementEffectively maintenance free; 10-15 year life.•5)Economies <strong>of</strong> scaleII'(D)Amenable <strong>and</strong> appropriate to single dwellings or large industrialcomplexes.Special Requirements <strong>and</strong> Impacts..1) Siting - directional aspect, l<strong>and</strong>, heightNo special <strong>requirements</strong>.2) Resource needsa) RenewableSolar insolation.b) Non-renewableMaterials used for conservation modes employed.II'.,..3)Construction <strong>and</strong> operating employment by skillCan <strong>of</strong>ten be installed by the resident; locally specializedservices (for example, insulation skills) may be employed.No...operation required.APA26/LC.3.5.4-3• •.....,•


Section C.3.5.4CONSERVATION4) Environmental residualsNone.5) Health or safety aspectsNone except care should be taken to assure proper air changerates for occupant health.(E)Summary <strong>and</strong> Critical Discussion1) Cost per million Btu or kWhNot available.2) Resources, <strong>requirements</strong>, environmental residuals per millionBtu or kWhNot available.3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong> itsavailabilityResidences generally require the availability <strong>of</strong> <strong>energy</strong> at alltimes. Before 1973, the cost <strong>of</strong> <strong>energy</strong> was 3 to 10% <strong>of</strong> totalannual expenses; now that percentage has soared to perhaps40%.Although some dynamic measures (notably solar <strong>energy</strong>) meritconsideration in this class <strong>of</strong> structure, the prime emphasisshould be on passive <strong>energy</strong> conservation measures. As awhole, this market is not geared to sophisticated or costlyequipment or to any measure that requires special operating ormaintenance procedures or attention. Generally, simplicity<strong>and</strong> low cost, with moderate <strong>energy</strong> benefits, should be pursued.APA26/LC.3.5.4-4


Section C.3.5.4CONSERVATION•As far as commercial <strong>and</strong> industrial facilities are concerned,dynamic conservation measures may <strong>of</strong>ten warrant consideration,but major <strong>energy</strong> savings are achieved in: (1) restructuring themanufacturing process or reclaim <strong>energy</strong> that in the past hasbeen wasted, <strong>and</strong>/or (2) modifying the timing cycle <strong>of</strong> the processto reduce <strong>energy</strong> usage during idling or other nonpeak <strong>energy</strong>use-periods...'.


I­UJUJ24222018I.L. 16UJa::


APPENDIX C.3.6WECSC.3.6WIND ENERGY CONVERSION SYSTEMS (WECS)(A)General Description1) Thermodynamic <strong>and</strong> engineering processes involvedNo thermodynamic process is involved with the use <strong>of</strong> windpower for generation <strong>of</strong> electrical <strong>energy</strong>. The process relieson wind flowing over an air foil assembly to create differentialpressure which results in rotation <strong>of</strong> the assembly around thefixed axis to which it is attached. Power from the wind istransmitted through the connection shaft <strong>and</strong> accompanying gearbox to an electrical generator. (See Figure C.3.6-1).Three types <strong>of</strong> generators are presently in use with wind<strong>energy</strong> systems. These are the DC generator, the AC inductiongenerator <strong>and</strong> the AC synchronous generator. Of the threetypes the AC induction generator is the most widely used: aninduction generator is not a st<strong>and</strong>-alone generator <strong>and</strong> must beconnected to an external power system <strong>of</strong> relatively constantfrequency <strong>and</strong> voltage to operate properly.2) Current <strong>and</strong> future availabilityAvailability <strong>of</strong> small size units in the 1.5 kW to 20 kW rangeis good. Larger units in the 100-200 kW range are currentlyundergoing tests in both the government <strong>and</strong> private sector <strong>and</strong>should be commercially available in the near future. Demonstrations<strong>of</strong> multi-megawatt sizes are in process, although majorproblems have been recently encountered.apa26/q1C.3.6-1


•HIGHSPEEDSHAFT•....BRAKESECONDARV PITCHACTUATOR CRANKTHRUST BEARINGSECONDARV PITCHCONT ACTUATORI NBOARD PROFILE.,•iii ...WIND TURBINE GENERATORFIGURE C-3.6-1......


APPENDIX C.3.6WECS(B)Performance Characteristics1) Energy outputa) Quality - temperature, formElectricityb) QuantityAnnual kWh output for following machine sizes for averageannual wind speed <strong>of</strong> 12 mph:1. 5 kW 3 , 120 kWh18 kW45 kW20,000 kWh50,000 kWHc) Dynamics - daily, seasonal, annualOutput <strong>of</strong> WECS dependent on seasonal wind flow patterns.2) Re 1 ; ab; 1 itya) Need for back-upIn general, except for the small, single dwelling windsystems, wind power generation is not a st<strong>and</strong> alonesystem. Diesel or another form <strong>of</strong> back-up generationmust be provided for days the wind does not blow withsufficient velocity to produce <strong>energy</strong> from the WECS.apa26/q3C.3.6-3


APPENDIX C.3.6WECS3)b) Storage <strong>requirements</strong>Battery storage or, possibly, pumped hydro can be usedfor storage; both constitute considerable expense. Todaythe concensus is that the most cost effective way to usewind power is in a utility grid to displace fuel onlywhen the wind blows <strong>and</strong> not to try to store the wind<strong>energy</strong>.Thermodynamic efficiencyN/A...........III·•(C)4) Net <strong>energy</strong>N/ACosts..iii·1)Capital...Machine size Cost $/kW1.5 kW $ 7,000 1 $4,66718 kW 19,000 1,05445 kW 38,000 8431 Includes cost <strong>of</strong> conversion equipment......••...apa26/q4C.3.6-4II'•


APPENDIX C.3.6WECS2) Assembly <strong>and</strong> installation1.5 kW - $ 8,60018 kW - $11,00045 kW - $21,0003) Operation1. 5 kW - N/A18 kW - N/A45 kW - N/A4) Maintenance <strong>and</strong> replacementUnit SizeMaintenance1.5 kW $240018 kW $310045 kW $3800ReElacement 2$1470$2820$5570Total$3870$5920$93702 Depreciation, 20 years at 7%5) Economies <strong>of</strong> scaleEconomies <strong>of</strong> scale likely favor installation <strong>of</strong> large centralizedwind generators over the small individually ownedwind generators. The total installed WECS instantaneousoutput should not exceed 30 percent <strong>of</strong> the total system load.apa26/q5C.3.6-5


APPENDIX C.3.6WECS..•(D)Special Requirements <strong>and</strong> Impacts1)Siting - directional aspect, l<strong>and</strong>, heightSiting requires the selection <strong>of</strong> a location with an averageannual wind speed in excess <strong>of</strong> 10 mph. Height <strong>of</strong> the mountingtower will vary depending on location <strong>and</strong> machine size, butwill generally exceed 30 feet in height....2)Resource needsa) RenewableAverage annual wind speed in excess <strong>of</strong> 10 mph....b) Non-renewableN/A3)Construction <strong>and</strong> operating employment by skill4)Certain aspects <strong>of</strong> construction (foundation work <strong>and</strong> towerinstallation) could be performed by unskilled labor underclose supervision. An operator would not be required as WECSare designed to operate unattended.Environmental residualsIII'apa26/q6Little environmental impact is anticipated when operating onlya few machines within a small geographic area.C.3.6-6".....


APPENDIX C.3.6WECS5) Health or safety aspectsPublic safety, legal liabilities, insurance <strong>and</strong> l<strong>and</strong> useissues must be addressed prior to installation <strong>of</strong> a utilityowned <strong>and</strong> operated WECS.(E)Summary <strong>and</strong> Critical Discussion1) Cost per mi 11 i on BTU or kWhThe 1981 cost per kWh for the various system sizes is asfollows.1.5 kW - $1.21/kWh18 kW - $O.29/kWh45 kW - $O.18/kWhThese costs can be misleading as they are for secondary (interruptable)<strong>energy</strong>, not prime power. These figures are notcomparable to firm <strong>energy</strong> costs, but rather should only beused for comparison with cost <strong>of</strong> fuel displaced. No allowanceis made for cost <strong>of</strong> back-up power.See Figure C.3.6-2, WECS versus Diesel Generation, to determinethe breakeven cost at which an 18 kW WECS becomeseconomically competitive with diesel generation.2) Resources, <strong>requirements</strong>, environmental residuals per millionBTU or kWhN/Aapa26/q7C.3.6-7


1.00.....----------r-------r------r-----""'"""T------,-------r----""lDIESELGENERATIONAT 8KWH/GALi 0.75L-------I---------+-------+------+------+--------::~rfIIIC-----~lit.........zl­I/)ou~0.5,aL--------t-----------~------------~--------~~~----------r_------~~1r~--------~ILl•W£C:. UTILIIATtON'ACTOR (1)OtESELGENE~ATIONAT IZ KWH/GAL.0~~=-------L----------~----------~3-----------±4----------~~--------~6;_--------~7o 2DIESEL FUEL COST IN $/GALLON(1) UTILIZATION FACTOR IS DEFINED AS THE PERCENTAGEOF AVAILABLE ELECTRICAL ENERGY PRODUCED BY THEWECS WHICH IS ACTUALLY UTILIZED.WECSVSDIESEL GENERATION18 KW INDUCTION CiENE~ATlONFIGUftE C-3.6-2'1 , , , , f , , I r • ,. B , , ,, , f I 'I ., f , I , , ~ p , , , , I


APPENDIX C.3.6WECS3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong>its availability.Wind power suffers from one obvious disadvantage: the intermittent<strong>and</strong> fluctuating nature <strong>of</strong> wind. A small utility mustinstall sufficient primary generation at additional costs tomeet dem<strong>and</strong>s on those days when the wind does not blow withsufficient velocity to produce rated output <strong>of</strong> the WECS.Besides the fickleness <strong>of</strong> local wind conditions, technical,environmental, <strong>and</strong> social problems must be addressed. Technical<strong>and</strong> social barriers that must be dealt with includepower system stability; voltage transients, harmonics; faultinterruptioncapability; effects on communications <strong>and</strong> TVtransmissions, public safety; legal liabilities <strong>and</strong> insurance,<strong>and</strong> l<strong>and</strong> use issues.apa26/q9C.3.6-9


APPENDIX C.3.7HEAT PUMPS•C.3.7 HEAT PUMPS(A) General Description..1)Thermodynamic <strong>and</strong> engineering processes involved.,2)A heat pump extracts heat from a source at a low temperature<strong>and</strong> rejects it to a sink at a higher temperature by input <strong>of</strong>mechanical <strong>and</strong> electrical work.The heat pump basicallyoperates much like a refrigerator or air conditioner: itutilizes coils <strong>and</strong> a refrigerant that soaks up heat <strong>energy</strong> inchanging from liquid to gas, then gives up the heat to indoorair. Figure C.3.7-1 shows a heat pump schematic diagram.Current <strong>and</strong> future availability..•Heat pumps have been in existence for more than 100 years.The U.S. DOE projects market growth through the year 2000 at 2percent per year...(B)Performance Characteristics1) Energy Outputa) Quality - temperature, formHeated air.b) Quantity......'0.....1.5 to 2.5 units <strong>of</strong> heat for each heat unit <strong>of</strong>electricity used.apa26/U1c)Dynamics - daily, seasonal, annualC.3.7-1..........


FROM HEAT SOURCE-~_..a. HOT AIR TO BUILDINGCOMPRESSOREXPANSION VALVEREJECT HEAT~---EVAPORATOR(" SOURCE ")~-COOL AIR FROM aUILDINGCONDENSER(II SINK ")HEAT PUMP FOR BUILDING HEATINGFIGURE C.3.7-1


APPENDIX C.3.7HEAT PUMPSHeat pumps are more efficient at higher heat sourcetemperatures. To satisfy heating <strong>requirements</strong> attimes <strong>of</strong> maximum dem<strong>and</strong>, most installations usesupplementary electric resistance heaters. Thepoint at which additional heat is supplied is knownas the IIbalance point ll <strong>and</strong> is pre-set for eachinstallation based on pump characteristics<strong>and</strong> location variables.2) Reliabilitya) Need for back-upSee IIDynamics ll above.......-•......b) Storage <strong>requirements</strong>None.3) Thermodynamic efficiencyDepending on the heat source temperature, a heat pump supplies150 to 250 percent as much heat <strong>energy</strong> as the elect ri ca 1<strong>energy</strong> it uses..' .....4)Net <strong>energy</strong>1.0 kWh in 5,120 to 8,532 Btu out.(C)Costs...1)Capital$3,200.",apa26/U3C.3.7-3


APPENDIX C.3.7HEAT PUMPS2) Assembly <strong>and</strong> installationNot available3) Operation$430/year4) Maintenance <strong>and</strong> replacement• Maintenance cost included in operation• Replacement cost is 9.4% <strong>of</strong> investmentper year based on 20 year life <strong>and</strong> 7% discount.5) Economies <strong>of</strong> scaleCommercial units range in capacity from less than10,000 Btu/hour to over 10 million Btu/hour.(D)Special Requirements <strong>and</strong> Impacts1) Siting - directional aspect, l<strong>and</strong>, heightUnits for home use are compact <strong>and</strong> occupy a similar amount<strong>of</strong> space as an air conditioning unit. Units are installedimmediately adjacent to the user building <strong>and</strong> require spaceinternally <strong>and</strong> externally.2) Resource needsa) RenewableIf the heat source is heated water, the heat can beprovided by renewable or non-renewable resources. Ifthe heat source is air, the resource is renewable.apa26/U4C.3.7-4


APPENDIX C.3.7HEAT PUMPSElectricity from renewable or non-renewable resourcesis required for operation.•...,...b) Non-renewable.See above.3) Construction <strong>and</strong> operating employment by skillCan be installed by local heating services.basically automatic.4) Environmental residuals.Operation is.,Environmental residuals are those attributable to the resourcesused for heating <strong>and</strong> electricity.5) Health or safety aspects.Operat ion is safe <strong>and</strong> without negative health impacts.Resources used for heating <strong>and</strong> electricity have impactsdiscussed in the appropriate <strong>energy</strong> technology pr<strong>of</strong>iles.....(E)Summary <strong>and</strong> Critical Discussion1) Cost per million Btu or kWh• From 40 to 70 percent <strong>of</strong> the cost <strong>of</strong> equivalent electricheating to which must be added the cost <strong>of</strong> heat sourceprovision.",.....2) Resource <strong>requirements</strong>, environmental residuals permillion Btu or kWh• Whatever is attri butab 1 e to the e 1 ectri ca 1 <strong>and</strong> heatsources used.apa26/U5C.3.7-5...,


APPENDIX C.3.7HEAT PUMPS3) Critical discussion <strong>of</strong> the technology, its reliability <strong>and</strong>its availabilityAt least 15 domestic manufacturers produce commerciallyreliable heat pumps.The most common units use air as aheat source; water heat source heat pumps are most generallybased on groundwater heat, but operate more efficiently withheated water <strong>and</strong> are currently being actively promoted by majormanufacturers.Use inA 1 aska is expected to increase asmore information on local heat pump applications is disseminated.The Alaska Power Administration has been conducting <strong>and</strong>evaluating air <strong>and</strong> water source heat pumps in Juneau for thelast two years <strong>and</strong> <strong>report</strong>s efficiencies <strong>of</strong> electrical useby heat pumps to by 2.5 to 2.6 times as high as resistiveelectrical heating.apq~6/U6


APPENDIX DECONOMIC ANALYSES - DETAILSThe following parameters were used in the economic analyses for electricalgeneration plans which follow.All costs are 1981 values.Planning Periodo 1981 to 2000Economic Analysis Periodo 1981 to 2041Economic Life0 Diesel - 20 years0 Waste Heat -20 years0 Transmission <strong>and</strong> Intertie - 30 years0 Hydroelectric - SO years0 Coal Plant - 30 yearsInvestmentCosts presented are constructed plant or "turn-key" costs. Theyinclude costs for designing <strong>and</strong> constructing the projects. Theydo not include such costs as finance charges, administration costs,l<strong>and</strong> acquisition fees <strong>and</strong> permit fees.o Diesel: $430/kWoIntertie:Transmission line <strong>and</strong> substations = $12,220,000Hydroelectric plant at $S,OOO/kW.0 Power Creek Hydro: $3,300/kW.0 Crater Lake Hydro: $3,SOO/kW.0 Healy Coal Plant: $1,700/kW.0 Carbon Creek Coal:Power Plant @ $2,100/kWTransmission line <strong>and</strong> sUbstations $l1,OSO,OOOapa26/Z1


APPENDIX DECONOMIC ANALYSES - DETAILS.,Fuelo Diesel: Base = $1.23/gallon for 13 kWh/gal. Cost escalated@ 3.5% per year.o Healy Coal: $0.0225/pound for 0.58 kWh/pound.o Carbon Creek Coal: $0.0600/pound for 0.88 kWh/pound.o Hydro: No fuel costs.o Surplus Energy: 1¢/kWh <strong>and</strong> 6. 25¢/kWh...--Operation <strong>and</strong> Maintenance - Annualo Diesel: $150,000 + $7.00/MWH.o Healy Coal: $360,000 + 2.5% <strong>of</strong> investmento Carbon Creek Coal: $450,000 + 2.5% <strong>of</strong> investment.o Intertie <strong>and</strong> Transmission line: $200/mileo Hydroelectric Plant:< 6,000 kW: $25,000 + $7.00/kW> 6,000 kW: $100,000 + $7.00/kWReplacement - Annualo Diesel: 2% <strong>of</strong> investmento Coal Plant: 4% <strong>of</strong> investmento Intertie <strong>and</strong> Transmission: 1% <strong>of</strong> investmentoAnalysesHydroelectric Plant: $3.00 per kW•.......•..•oPer APA regulations.Ill'-III,apa26/Z2


TABLE D-lDIESEL GENERATION ONLYRECONNAISSANCE STUDY OFENERGY REQUIREMENTS AND ALTERNATIVES FOR CORDOVAECONOMIC ANALYSIS19:=:4 19::::9 1990 1991DEMAND -- I


TABLE D-2ADIESEL PLUS INTERTIED Sl~PLlJS PLUS SILVER LAKE HYDRO(SURPLUS ENERGY DJST •. 0625/KWHIREDJNNAI~3ANCEENERGY RE~JIREMENTSSTUDY OFAND ALTERNATIVES FOR CORDOVAECONOMIC ANALYSIS••..DEMAND -- f


TABLE D-2BDIESEL PLUS INTERTIED SURPLUS PLUS SILVER LAVE HYDRO(SURPLUS ENERGY C~3T $.OI/KWH)ENERGY RE~JIREMENTSRECONNAISSANCE STUDY OFAND ALTERNATIVES FOR CORDOVAECONOMIC ANALYSIS1985 1987 1990 1 '::'91DEMAND -ENEFiGY .-I


TA8LE D-3LOCAL HYDRO PLUS DIESELRECONNAISSANCE STUDY OFENERGY REQUIREMENTS AND ALTERNATIVES FOR CORDOVAEDJNOMIC ANALYSIS•..•19';> 1DEMAm) -ENERGYf


TABLE [1-4HEALY COAL, GENEFATIONRECONNA I :=SANCE :=;TU[)Y OFENERGY PEOUIREMENTS AND AL.TERNATIVES FOR CORDOVAECONOMIC ANALYSISl'~/861 '~90DEMAND -ENERGY ,-V~JM~JH3,50() 3,601) 4,700 4,900 5,00(1 5,100 5,300 5,400 5,600 5,800 6,00016,9001:::,000 20,:iOO :21,:200 22,000 21,:::00 :227:~:(lO 23,:;':00 23,::::00 24,700 21.:.,,000EXISTING DIESEL VWADDITIONAL S[~RCES - VWJ..INIT 1.UNITUNIT :,':5,()OO 5,000 5,000 5,(100 5,000 5,000 5,000 5,000 5,000 5,000 5.0005,(100 5,000 ~;, 000 ~i,OOO 5.000 ~i, 000 5,000 5,000 5,0005,(100MWI"'I DI E:,;EL.MWH - COAL11:.'7 '?'(J() 1::::, 000 :~;:(JO 1, :;':00 1, :300 2,7(1020,500 21,200 22,ClOO 21,800 22,000 22,000 22,000 22,000 26,000COAL INVESTMENT (000)COAL E~JIV AN COST (000)TON:'; [W COALCO:=;T PER TO~I('OAL FIJEl_ COST (000)COAL O&M COST (I)O!)COAL REPLACEMENT (000)45:::;;, ::iOO43417,622 18,222 18,91145 45 45793 820 851573 573 573340 340 34043418,75645:,:44~;7:::::~:404~:41::::,91145:::5157:3:~:404:341 :,:,9114':,:::51573:3404:=:41:,:,',/1145:,:515733408,5004341:::::, '~Jl1 22, :35(:.45 45:=:51 1,00657:3 785340 6:30DIESEL INVESTMENT (000)DIESEL. EOUIV AN COST (000)[;ALLON::; D I E:,;EL F'U[L (000)f:'''Y,;T PU( [iALLCINDI[SEL FUEL COST (000)DI83EL O&M COST (000)DIESEL REPLACEMENT (om))1, :;:001 • 2:~:1, 7~;',1268431,3:,':41. 271, 9:3:~:276431.321011. :::61011. 411011.4(,.1011. 51431001. :;6172591 :3:31.6224(,.63431.6'=::~:::::46'~}431. 74101!\N~IUAl CO r,;PRES WORT ANNUAL DJSTACCUM PRE WORTH,070,070,070, 1 :::'fe,:,2562, 1 :;12., 02:::6,2:,'42,17::: 2,20i 2,3:31 2,472 2,5.503,3491, 99~: 1, 9/.:,~: 1, :::9'~J 1,952 2,010 2,013 2,0(:,5 2,492::::,277 1


TABLE [1-5CARBON CREEK COAL GENERATIONRECONNAH:"::ANCE ~:TUDY OFENERGY RE';IUI REMEN1::: AND ALTERNATIVE::: FOR CORDOVAECONOM I CANAL Y::: I:::•1 'S"'82 19:=:4 1986 1'-:'':. 26,1)00EX I ,=:TING DIE'=:EL KWADD IT IONAL '::OURCE:::UNIT 1UNIT 2UNIT 3KW5.,000 5.,000 5~OOO 5,000 5,000 5,000 5,0005~OOO 5,000 5,000 ~;1000 5,000 !5,OOO5,0005,0005,0005,0005,0005,0005,000MWHMWH -DIE8ELCOALCOAL INVESTMENT (000)COAL EG'UIV AN CO::;T (000)TON:;;: OF COALCOST PER TONCOAL FUEL COST (000)COAL OlkM COST (000)COAL REPLACEMENT (000)16,900 181000 '300 1~~:OO 1,::'=:00 2,700201500 21,200 22,000 211800 22,000 221000 22~000 221000 26,00021,5501,27011,683120 120 120 1201,4507121,4027128621,270 1,270121~5421201,505712:3621,27012,42~;1201,491711,,27012,~'421201 7 ~)057121,,270l,2,5421201, ~;057121,27012,5421201, ~~057121,27012,5421201,50571286210,5001, '"'7614,8171201,778,;j741) 2a2'JIi,.'DIESEL INVESTMENT (000)DIE:3EL EOUIV AN COST (000)GALLONS D I E:;;:EL FUEL (000)COST PER GALLONDIESEL FUEL COST (000)DIESEL m,M COST (000)D I E-=:EL REPLACEMENT «100)1,3(1C>1 .. 2:31,75'y2c,9431, 3:::~41. 271.321011. :361011. 411011.461011. 51381001. ~56172591:381.622466:;:4'"2081.1. 74101•..ANNUAL COSTSPRES WORTH ANNUAL COSTACCUM PRES WORTH2,0702,0702,(>702,2522,1864,2564,2':;74,0138,2694,3053,'74012,2094,:3603,8741t:.1 08:~:4.346 4,4:::2 4,6233,749 3,753 3,7591 '7J .. 8:32 2:~: , 5::::5 27 7 3444,7013,71131,0554,.8453,71334,7686,0214,4:::0..DEMAND -ENERGY -KWMWHEXISTING DIESEL KWADD IT I ONAL :30URCE:3UNIT 1UNIT 2UNIT ::::KW1993(;., :'::00 7, 00027,700 28,9005,0005,0005,000~'?OOO5,0005,00019957,200 7,400 7,60029,500 :30,100 31,000510005,0005,0005~OOO5,0005.,0005,0005,00019977,900 8,100:;: 1 , ::::(>0 :3:37 0005,0005,000,5,0005.,0005,000~I,OOO2000::;:, :300 ::::, c·(lo34,500 :35,900~;,ooo~;., 0005,0005,0000005~OOO20(11THRU20418",600351'i'OO5,0005,0005,000•..MWHMWH -DIESELCOAL27,70029.,50030,10031,00031, :;::003:;:,00035,90035~ '''00COAL INVESTMENT (000)COAL EOUIV AN COST (000)TONS OF COALCOST PER TONCOAL FUEL CO:;;:T (000)COAL m,M COST (000)COAL REPLACEMENT (000)DIESEL I NVE:::TMENT (000)DIESEL EG!UIV AN COST WOO)GALLONS DIESEL FUEL (00(»(:O:;T PER OALLONDIESEL FUEL CO:;;;T (000)DIESEL OlkM CO:::T (000)DIESEL REPLACEMENT (000)ANNUAL COSTSPRES WORTH ANNUAL COSTACCUM PRES WORTH1,';>7615,7921201, 8~.;t59741,2821, ''77616,4751201,977'3'741,2821,97616,:=;171202,1)189741,2!:::21, 97617,15:::1202,0599741,2821,97617, (:,671202,120S"741 .. 80 1.86 1.92 1.99 2 .. 0610 10 10 10 101 1 1 1 1";;',1:38 6,220 6.,261 /:..,:~:02 t·,:;:6:34.434 4,362 4,264 4,166 4,0:::443.,682 48.,044 52,:~:O:::: 56,474 6(),55::::1, ';)761:::,1251202,1759741,2:::21,9761:::" :;::OB1202,2579741,2821,';>7619.6671202, ~360974172822. 1:3 2~ 21 2.2810 10 101 1 1t,,418 6,500 6,6034,000 8.,933 3,87964, 55~:: 6::;:,491 721 :~i701,9762014t.71202,456~)741,2822. 3~,101:;;~82076,1901,'77620,4671202,4569741,2:322 .. :36101(:.,699::::91444165,634......


92TABLE D-(:,AELECTRIC HEATING BY INTERTIED HYDROSURPLUS ENERGY COf;T $.0625/KWH)RECONNAI,::;SANCE ~;TUDY OFENERGY REC!UIREMENT~; AND ALTERNATIVES FOR CORDOVAECONOMIC ANALYSIS1982198:319S519901991AVAILABLE - KWENERGY MWH5,00016"J9005,0001:=:,1008,400 ::;:,200201400 21,2001::t, SOO64,50::'52(J,50074,1';152(1,40071,69531.,900118,745:~:1., 30011(:,,145377500136,18537,200134.,685EXISTING DIESEL KWADDITIONAL SOURCES -SURPLlY=;DEAD (:REEf(~3ILVER LAKELAf(E 1488LAI00::::.,:30015,50012,0006,7003,00015,50012~OOO6,700MWHMWHD I E~::ELHYDRO F'LUS ~::;URPLUS11:.,,900 la,100 5,600 7,40014,800 1::::,800 64,595 74,195 71,695 118,745 116,145 1:'::6'1185 1:34,685HYDROIINTERTIE INVESTMENTEG!UIV AN COST (000)OS-.M COST (000)REF'LACEMENT COST (000)SURPLUS ENERGY COST (000)12,220622121292577,500(:.22 :3., (:.3412 22112 598l:,2 -;"00::;:,634221591,500;":,634221591,34463,240e·, 092405951,194{,,092405951,031:33 .. 5007,3945511159127,:3945,51115819DIESEL INVESTMENT «>00)DIESEL. EC!UIV AN COST (000)GAL.LONS DIESEL. FUEL (000)CO~3T PE::R GALLONDIESEL FUEL COST (000)DIESEL m,M COST (000)DIESEL REPLACEMENT (000)1., :3001.231'175926'::'4'":1,3921.271,9452764:34:311 .. 32(:,2610435~,/~1.36851104:31. 411. 461. 11 .. 561.621. 74ANNUAL. C(",,:TSPRES WORTH ANNUAL. COSTACCUM PRES WORTH2,0702,0702,0702,2642.,2502,1212,41:2:2,2078,596,4 .. 81:;:4,2765~41,'34,/:;,6;J17,5415.,2574,40221,9437,7:356, ::'::307,6226,017:34, ::;;'''~/(J8,972"" 87641,166818796,60747,77:319921993199520002001THRU2041AVA I U\BL.E KWENERGY ~lWH40.,.:::;:00145,34540,400143,64540,000141, '~'454:3., 200 4:3,200 4::::::,200151,333 145,333 145.,3:3:::: 145,:333 145,48 .. 200145, :3';:34~1, 200145,333EXISTING DIESEL. KWADDITIONAL SOURCES -~:::URPL.US:DEAD GREEt00)1 .. 801. :361 R1.992.062.21£.'.36ANNUAL COSH;PRES ,,!ORTH ANNUAL COSTACCUM PRE~; WORTH9,6146,94654,7199, 50:~;6, 6~,'~J/c,l,38'::'6,82574,(:,119,949I..~., :38/::.·::::0, ':;r'~/7'~" 949/::..,200':'7,1979.,949/:...,0199:3.,211:.,9,949 9,949 9,949~t' :::44 5,674 132,837~/'i', 01:..0 104,7:34 2371571


TABLE [i-6BELECTRIC HEATING BY INTERTIED HYDRO(SURPLUS ENERGY (nST 1.0l/KWH)ENERGY RE~JIREMENTSRECONNAISSANCE STUDY OFAND ALTERNATIVES FOR CORrnJVAECONOMIC ANALYSIS1990 1991......AVA I LABLE - f(WENERGY - MWHEXISTING DIESEL kWADDITIONAL ~JURCES - kW'::URF'LU~;DEAD CREEkSILVER LAfTLAkE 14B:=:LAf(E 649LAf(E 1 :0:7:::MWH ._. DIE',:ELMWH - HYDRO PL~3 SURPL~3HYDRO/INTERTIE INVESTMENTEQUIV AN DJST (000)08~M CO~=;T (000)REPLACEMENT D)ST(OOO)SURPLUS ENERGY COST (000)DIESEL INVESTMENT (000)DIE~~L E~JIV AN COST (000)GALLONS DIESEL FUEL (000)CO',:T PER GALLONDIESEL FUEL COST (000)DIESEL O&M COST (000)DIESEL REPLACEMENT (000)ANNUAL CO',:T';PRES WORTH ANNUAL COSTACCUM PRES WORTH5,000 5,000 8,400 8,20() 1~:,8()() 20,500 20,400 31,900 31,300 37,500 37,20016,900 18,100 20,400 21,200 64,595 74! 195 71,695 118,745 116,145 136,185 134,6855,000 5,000 5,000 5,000:~:, 400 3,20016,90() 18,100 5,600 7,4ClO14.BOO 13.800 64.59 5 74.195 71,695 11:0:.745 116.145 136.1:0:5 134.6851,3001.231.75','26:,:4::;:,070,070,0701 , ~::'~)21.271.94527~,432. ~?64~~, 19::::4.26:::12, ~:2062212121484:~: 11.32«:610431.47:c:1. ::;::::::;:3,300 5,000 4,90015,500 15,500 15,5()O77, ~iOO6~~2 3. ~"3412 ~:2112 5':"1-:;::::: 144~;~.93.6342Z1592403.634Z?l2151.36 1.41 1.46 1.51:,:5110431.68 4,057 4.153 4.1281.54 3,~~5 ~.~~L 3.4577,20 10.:::~6 14.3~3 17.8454,40015,50012,00063.240(:., 0'~J240~i1911.5(,{,.7:':25.514:3, ::::0015,50012,0006,0924051651.625,3::':::3:3, :30015,50012,0006,lOO33,5007,394551115146:=:,206(:., ~~::::::'~i:,:4,9;0:1::':,00015,50012,000/:..,7007.3','4~;511151::;:11.748,1916, 09~!41.07/c,....•.....'-..Iii!19931 ':;'95 19972000~~~oo 1THF


TABLE D-7DIESEL GENERATION WITH WA':::TE HEATRECONNAI',:SANCE STUDY OFENERGY REC!UIREMENTS AND ALTERNATIVE',,; FOR CORDOVAECONOMIC ANALYSIS1984 198719:::819901991DEMANDENERGYKWMWH:3,50016,900:3,6·0018,0004,700 4,900 5,000 5,100 5,30020,~i(H) 21,200 22,000 21,800 22,:~:OO514002:~:, :3005,600 5,S002:;f t :300 24, 7006 .. 0002'::.,000EXISTING DIESEL KWADDITIONAL SOURCESUNIT 1UNn 2UNIT 3KW5,000!:;,OOO5.,0005,0005'100027·500510002,5005,0002,5005~OOO2~5(lf)5 .. 0002,5005,0002,5005~OOODIESEL I NVP3TMENT (000)DIESEL EQUIV AN COST (000)GALLONS DIE~:EL FUEL (000)COST PEr, GALLONDIESEL FUEL COST (000)DIESEL O&M COST (~)O)DIESEL REPLACEMENT (000)DIE'3EL ANNUAL COST (000)1, :3001 ~ 2:31, 75'~432,0701,3:::41. 271 , 9:::::32764~;:2,2521,5761 .. :321.,6:":01.362,43::::2984:?~2,77';11,075721,6921.412,624:30465;3,065721,6761.462,6923,132721.,7151 .. ~:; 13066531292721, T?21.51:...3~075'~ll :3/.:.5,-, :M COST (000)REPLACEMENT cm::r (000)GALLON',: DIESEL D I SF'LACED (000)DOLLAR VALUE (000)WA,,:TE HEAT AN CU,:T (000)1,900l27 .. ;?,Jl7.538uO4/,,(1(60'


APPENDIX EBIBLIOGRAPHYCoal ResourcesAveritt, P.; Coal Resources <strong>of</strong> the United States; U.S. Geological SurveyBulletin 1412; 1975.Barnes, F.F., ~ Review <strong>of</strong> the Geology <strong>and</strong> Coal Resources <strong>of</strong> the BeringRiver Coal Field; U.S. Geological Survey Circular 146; 1951.Barnes, F.F.; Coal Resources <strong>of</strong> Alaska; U.S. Geological Survey Bulletin1242-B; 1967.Bottge, R.G.; Coal as an Energy Source for Barrow, Alaska; U.S. Bureau<strong>of</strong> Mines Report for the Alaska Power Authority; 1977.Clark, P.R.; Transportation Economics <strong>of</strong> Coal Resources <strong>of</strong> Nothern SlopeCoal Fields lAlaska; University <strong>of</strong> Alaska M.I.R.L Report No. 31;1973.Cooper, H.M., et ali Analysis <strong>of</strong> Alaska Coals; U.S. Bureau <strong>of</strong> Mines Tech.Paper 682; 1946.Hankinson, F.C.; Petrographic Evaluation <strong>of</strong> Coking Potential <strong>of</strong> SelectedAlaskan Coals <strong>and</strong> Blends; University <strong>of</strong> Alaska M.I.R.L. Report No.3; 1965.Howell, S.B.; Cost Study: Chignik Bay Coal Field; U.S. Bureau <strong>of</strong> MinesInternal Report; 1979.Janson, Lone; The Copper Spike; Northwest Alaska Publishing Co.;Anchorage; 1975.Kachadorian, Reuben; Engineering Geology <strong>of</strong> the Katalla Area, Alaska;U.S. Geological Survey Miscellaneous Geologic Investigations Map1-308; 1969.apa26/01 E-1


APPENDIX EBIBLIOGRAPHYKennedy, Andrew; Report on Field Examination <strong>of</strong> the 33 Cunningham AlaskaCoal Entries; U.S. Congress, Investigation <strong>of</strong> the Department <strong>of</strong> theInterior <strong>and</strong> <strong>of</strong> the Bureau <strong>of</strong> Forestry; 1910.Martin, G.C.;Al aska;Geology <strong>and</strong> Mineral Resources <strong>of</strong> Controller Bay Region,U.S. Geological Survey Bulletin 335; 1908.McGee, D.L., <strong>and</strong> OIConner, Kristina M.; Mineral Resources <strong>of</strong> Alaska <strong>and</strong>the Impact <strong>of</strong> Federal L<strong>and</strong> Policies on Their Availability--Coal;State <strong>of</strong> Alaska, DNR, Division <strong>of</strong> Geological <strong>and</strong> Geophysical SurveysOpen File Report 51; 1976.Miller, D.J.; Geology at the Site <strong>of</strong> ~ Proposed Dam <strong>and</strong> Reservoir onPower Creek ~ Cordova, Alaska; U.S. Geological Survey Circular136; 1951.Miller, D.J.; Geology <strong>of</strong> the Katalla District, Gulf <strong>of</strong> Alaska TertiaryProvince, Alaska; U.S. Geological Survey, Open File Report 206; 1961.•••........III.-Miller, D.J., Payne, T.G., Gryc, George, with Annotated Bibliography byCobb, E.H.; Geology <strong>of</strong> Possible Petroleum Provinces in Alaska;U.S. Geological Survey Bulletin 1094; 1969.Plafker, George; Geologic Map <strong>of</strong> the Gulf <strong>of</strong> Alaska Tertiary Province,Alaska; U.S. Geological Survey Miscellaneous Geologic InvestigationsMap 1-484; 1967.Rao, Dharma; Washability Charateristics <strong>of</strong> Low-Volatile Bituminous Coalfrom Bering River Field, Alaska; University <strong>of</strong> Alaska M.I.R.L.Report No. 21; 1959..,...Robert W. Retherford Associates; Assessment <strong>of</strong> Power Generation Alternativesfor Kotzebue; Alaska Power Authority; 1980.Robert W.Retherford Associates; Bristol Bay Energy <strong>and</strong> Electric PowerPotential, Phase 1; u.s. Department <strong>of</strong> Energy; 1979.apa26/02 E-2.,.t."


APPENDIX EBIBLIOGRAPHYS<strong>and</strong>ers, R.B.; The ~ Resources 2f the Kushtaka Mountain ~includingCarbon Creek) ~ <strong>of</strong> the Bering ~ £2!l~; U.S. GeologicalSurvey General Report; 1976.Oil <strong>and</strong> Gas ResourcesPublications:American Petroleum Institute; IIReserves <strong>of</strong> Crude Oil, Natural Gas Liquids<strong>and</strong> Natural Gas in the United States <strong>and</strong> Canada as <strong>of</strong> December 31,1968"; American Gas Association <strong>and</strong> Canadian Petroleum Association;V. 23, p. 31i 1969.Blasko, D. P.; ft History <strong>of</strong> Bureau 2f Mirr!! Oil !nB §!! ResourceInvestigations in Alaska with ~ Index 2f Published ~ UneublfshedReeorts Containing Information £n Alaska's Qil <strong>and</strong> §2! Resources;U.S. Department <strong>of</strong> Interior Bureau <strong>of</strong> Mines, Informational H<strong>and</strong>out19201974; 1975.Dolton, G.l., et. a1.; Estimates <strong>of</strong> Undiscovered Recoverable Resources<strong>of</strong> Conventionally Producible Oil <strong>and</strong> Gas in the United States;U.S. Geological Survey Open File Report 81·192; 1981.Gates, G.O., Grantz, Arthur <strong>and</strong> Patton, W.W., Jr.; Geology <strong>and</strong> NaturalGas <strong>and</strong> Oil Resources in Alaska; Natural ~ <strong>of</strong> North America,Edited by B.W. Beebe <strong>and</strong> F. Curtis; Amer. Assoc. Petrol. GeologistsMemoir 9, V. 9, p. 3-48; 1968.Grantz, Arthur; UPetroleum <strong>and</strong> Natural Gas - Southern A1aska ll ; Mineral<strong>and</strong> ~ Resources 2f Alaska; U.S. Congress, Senate Committee onInterior <strong>and</strong> Insular Affairs, 88th Congress, 2nd Session, CommitteePrit. t p. 44-62; 1964.apa26/03 E-3


APPENDIX EBIBLIOGRAPHYGryc, George; "Summary <strong>of</strong> Potential Petroleum Resources <strong>of</strong> Region I(Alaska <strong>and</strong> Hawaii) - Alaska"; Future Petroleum Provinces <strong>of</strong> theUnited States - Their Geology <strong>and</strong> Potential; ed. by I.H. Gram;Amer. Assoc. Petrol. Geol. Memoir IS, V. 1, p. 55-67; 1971.LeMay, W.J.; IIA Perspective on Alaska's Oil Potentials"; Qil <strong>and</strong> GasJournal; V. 67, No.8 .• p. 114-120; 1969.•....Martin, G.C.; Geology <strong>and</strong> Mineral Resources <strong>of</strong> the Controller BayRegion, Alaska; U.S. Geological Survey Bulletin 335; 1908.McConkey, W., Lane, D .• Quinlan, C., Rahm, M., <strong>and</strong> Rutledge, G.;Alaska's Energy Resources: Inventory <strong>of</strong> Oil, Gas, Coal, Hydroelectric<strong>and</strong> Uranium Resources; Vol. I <strong>and</strong> Vol. II; 1977.Miller, D.J., Payne, T.G., <strong>and</strong> Gryc, George; Geology <strong>of</strong> PossiblePetroleum Provinces in Alaska; with annotated bibliography by E.H.Cobb; U.S. Geological Survey Bulletin 1094; 1959.Moore, Billy J.; IITables on Alaskan Gases"; Analyses <strong>of</strong> Natural Gases;U.S. Department <strong>of</strong> Interior Bureau <strong>of</strong> Mines; p. 4-8; 1975.State <strong>of</strong> Alaska, Department <strong>of</strong> Natural Resources, Division <strong>of</strong> Geological<strong>and</strong> Geophysical Surveys; Estimated Speculative RecoverableResources <strong>of</strong> Oil <strong>and</strong> Natural Gas in Alaska; Open File Report 44;1974.U.S. Department <strong>of</strong> Interior Bureau <strong>of</strong> Mines; Alaska 1/250,000 ScaleQuadrangle Map Overlays Showing Exploratory Oil <strong>and</strong> ~ ~Drilling Locations ~ Productive Oil <strong>and</strong> Gasfield Locations; OpenFile Report 69-73 (updated yearly); 1973.•..•-"•....apa26/04 E-4•


APPENDIX EBIBLIOGRAPHYU.S. Department <strong>of</strong> Interior Bureau <strong>of</strong> Mines; Minerals, Fuels, Geology-­Resources Analyses f2! ~ Federal-State ~ Use Planning f2!:mission for Alaska; Volume 4: Inventory Report - SouthcentralRegion <strong>and</strong> Volume 6: Inventory Report - Southcentra1 Region; edited<strong>and</strong> assembled by Arctic Environmental Information <strong>and</strong> Data Center;1974.U.S. Department <strong>of</strong> Interior Geological Survey; Oil <strong>and</strong> Gas Regions <strong>and</strong>Provinces, State £f Alaska~; Resources Appraisal Group. Branch<strong>of</strong> Oil <strong>and</strong> Gas Resources for U.S.G.S. Circular 725; 1974.Personal Communications:Brewer, Max, Director, National Petroleum Reserve Development for HuskyOil Co., Anchorage.Chatterton, C.V., President, Rowan Drilling Co., Anchorage.Mangus, Martin, Petroleum Geologic Consultant, Anchorage.McMullin, Robert, Geologist, U.S. Geological Survey, Anchorage.Geothermal ResourcesForbes, R.B.; Geothermal Energy <strong>and</strong> Wind Power, Alternate Energy Sources~ Alaska; Alaska Energy Office <strong>and</strong> Geophysical Institute, University<strong>of</strong> Alaska; p. 144; 1976.Godwin, L.H.; Classification <strong>of</strong> Public ~ Valuable for Geothermal~ ~ Associated Geothermal Resources; U.S. Geological SurveyCircular 647; p. 18; 1971.McConkey, W., Quinlan, C., Rutledge, G., Lane, D., <strong>and</strong> Rahm, M.;Alaska's Energy Resources: Findings <strong>and</strong> Analysis; Alaska Division<strong>of</strong> Energy <strong>and</strong> Power Development; p. 244; 1977.apa26/05 E-5


APPENDIX EBIBLIOGRAPHYMcFadden, W.A., Jr., Wanek, A.A., <strong>and</strong> Callahan, J.E.; Alaska GeothermalResources Minutes #1; Minutes <strong>of</strong> Mineral L<strong>and</strong> Classification Board;1971.....McFadden, W.A., Jr., Wanek, A.A., <strong>and</strong> Callahan, J.E.; Alaska GeothermalResources Minutes #2; Minutes <strong>of</strong> Mineral L<strong>and</strong> Classification Board;1971.Miller, T.P.; Distribution <strong>and</strong> Chemical Analyses <strong>of</strong> Thermal Springs inAlaska; U.S. Geological Survey Open File Report; 1972.Miller, T.P., Barnes, F., <strong>and</strong> Patton, W.W., Jr.; Geologic Setting <strong>and</strong>Chemical Characteristics <strong>of</strong> Hot Springs in Central <strong>and</strong> WesternAlaska; U.S. Geological Survey Open File Report; 1972.Miller, T.P., <strong>and</strong> Barnes, Ivan; Potential for Geothermal Energy Oevelop­~ in Alaska--Summary; Circum-Pacific Energy <strong>and</strong> Mineral ResourcesMem. 25, A.A.P.G.; 1976.Muffler, L.J.P.; Assessment <strong>of</strong> Geothermal Resources <strong>of</strong> the United States;U.S. Geological Survey Circular 790; 1978.Ogle W.E.; Geothermal Energy Possibilities in Alaska; Consultant, Anchorage,Alaska; 1974.U.S. Code <strong>of</strong> Federal Regulations; Title 43, Public L<strong>and</strong>s, Sect. 3200,Geothermal Leasing, Part 2310, Withdrawals.............U.S. Congress; Geothermal ~ Act, Public Law 91-581; 84 Stat. 1566;1970.Waring, G.A.; Mineral Springs <strong>of</strong> Alaska; U.S.Geological Survey WaterSupply Paper 492; 1917.apa26/06 E-6..Ii


APPENDIX EBIBLIOGRAPHYWhite, D.F .• <strong>and</strong> Williams, D.L.; Assessment ~ Geothermal Resources <strong>of</strong>~ United States; U.S. Geological Survey Circular 726. p. 155;1975.Energy TechnologiesAlaska Department <strong>of</strong> Commerce <strong>and</strong> Economic Development; Jobs <strong>and</strong> Power---f2! Alaskans; July 1978.Alaska Division <strong>of</strong> Energy <strong>and</strong> Power Development, Department <strong>of</strong> Commerce<strong>and</strong> Economic Development; Minimizing Consumption <strong>of</strong> ExhaustibleEnergy Resources through Community Planning ~ Design; FinalReport for U.S. Energy Research <strong>and</strong> Development Administration;Anchorage; October 1977.Alaska OCS Socioeconomic Studies Program; Northern ~ £f Alaska PetroleumDevelopment Scenarios, local Socioeconomic Impacts; for Bureau <strong>of</strong>L<strong>and</strong> Management Alaska Outer Continental Shelf Office; TechnicalReport No. 33; October 1979.Anonymous; IIEnergy from Biomass"; EPRI Journal; December 1980.Anonymous; "Photovoltaic Review ll ; .illf Spectrum; February 1980.ASHRAE; H<strong>and</strong>book <strong>of</strong> Fundamentals; Amercian Society <strong>of</strong> Heating, Refrigerating,<strong>and</strong> Air-Conditioning Engineers, Inc.,; New York; 1977.ASHRAE; ~ Systems; American SOCiety <strong>of</strong> Heating, Refigerating, <strong>and</strong>Air-Conditioning Engineers, Inc.; New York; 1980.ASHRAE; 1979 Equipment; American Society <strong>of</strong> Heating, Refrigerating, <strong>and</strong>Air-Conditioning Engineers, Inc.; New York; 1979.apa26/07 E-7


APPENDIX EBIBLIOGRAPHYBerman, Ira M., <strong>and</strong> Schmidt, Philip S.; IIFuel Cells <strong>and</strong> Coal-DerivedFuel"; Power Engineering; October 1980.Black, Theodore W.; UPP&L Test Power from the Wind"; ~ Engineering;July 1979.Babcock <strong>and</strong> Wilcox Company; ~: l!! Generation <strong>and</strong> Use; New York;1955.....- ....-Baumeister, Theodore, Avallone. Eugene A., <strong>and</strong> Baumeister III, Theodore,Editors; Marks' St<strong>and</strong>ard H<strong>and</strong>book f£! Mechanical Engineers; EighthEdition; McGraw-Hill Book Company; New York; 1978..,8renman, J.E.; Treatment <strong>of</strong> liquid Wastes from Fossil ~ ~ Plants;Ecodyne Industrial Waste Treatment Division; 1977.Budwani, Ramesh H.; "Power Plant Capital Cost Analysis"; Power Engineering;May 1980.Bueche, Arthur M.; "Energy Conservation, Efficiency, <strong>and</strong> Substitution!!;EPRI Journal; December 1980.....,.California Energy Commission; Commercial Status: Electrical Generation<strong>and</strong> Nongeneration Technologies; Staff Draft; September 1979.California Energy Commission; Electricitx Tomorrow:Summary; February 1981.1981 ~ ReeortCalifornia Energy Commission, Nontraditional Energy Technologies:Issues <strong>and</strong> Actions; Staff Report; December 1980...-California Energy Commission; Volume!: Technical Assessment Manual,Electrical Generation, Version One; Staff Draft with Appendices;September 1979.apa26/08 E-8..


APPENDIX EBIBLIOGRAPHYCanter, Larry W. <strong>and</strong> Hill, Loren G.; ................... H<strong>and</strong>book <strong>of</strong> Variables for Environ-;,..;.....;..... - -.;;;.;.;..........;..;.;-mental Impact Assessment; Ann Arbor Science Publishers, Inc.; AnnArbor, Michigan; 1979.Power Engineer­Comtois, Wilfred H.; "Economy <strong>of</strong> Scale in Power Plants U ;ing; August 1977.Creager. W. P .• <strong>and</strong> Justin, 0.; HYdroelectric H<strong>and</strong>book; Second Edition;John Wiley & Sons, Inc.; New York; 1950.Davis, C. V., <strong>and</strong> Sorensen, K. E., Editors; H<strong>and</strong>book £! Applied Hydraulics;Third Edition; McGraw-Hill Book Company; New York; 1969.Denesdi, L,; "Fuel Savings wHh Turbines Modified for District Heatinglt.~ Engineering; February 1980.Earting, J. P., <strong>and</strong> Seifort. R. D.; ~ Energy Resource Potential inAlaska; University <strong>of</strong> Alaska Institute <strong>of</strong> Water Resources; 1978.Edison Electric Institute; Electric Heating <strong>and</strong> Cooling H<strong>and</strong>book; NewYork; 1966.Gas Turbine World; Gas Turbine ~ H<strong>and</strong>book 1980-81; Pequot Publishing.Inc.; Framingham. Massachusetts; 1980.Geothermal Resources Council; Direct Utilization 2f Geothermal Energy:~ Technical H<strong>and</strong>book; Special Report No.7; 1979.Gilles, Theodore C.; "Air-to-Air Heat Pumps"; ~ Engineering;April 3, 1980.Godfrey, Robert Sturgis, Editor-in-Chief; Building Construction f2!!Data 1980; Robert Snow Means Company, Inc.; 1979.apa26/09 E-9


APPENDIX EBIBLIOGRAPHYGolden, Jack; Ouellette, Robert P.; Saari, Sharon; <strong>and</strong> Cheremisin<strong>of</strong>f,Paul H.; Environmental Impact Data Book; Ann Arbor SciencePublishers, Inc.; Ann Arbor, Michigan; 1979.•..•Grumman Energy Systems, Inc.; Wind Stream 33 ~ Turbine Generator.Hanks, David J.; IlHeat Pumpsll; Specifying Engineer; February 1981.Harkins. H. L.; IIApplying Cogeneration to Solve Tough Energy Problems ll ;Specifying Engineer; December 1979.Lihach, Nadine; IILifting Hydrois Potential ll ;1980.EPRI Journal; DecemberMerritt, F. S., Editor; St<strong>and</strong>ard H<strong>and</strong>book for £!!il Engineers; SecondEdition; McGraw-Hill Book Company; New York; 1976.Niess, Richard C.; tlHigh Temperature Heat Pumps Can Accelerate the Use<strong>of</strong> Geothermal Energyll; Commercial Uses <strong>of</strong> Geothermal Heat; GeothermalResources Council Special Report No.9; June 1980...• ....-..Norelli, Patrick; IIIndustrial Heat Pumpstl; Plant Engineering; August 21<strong>and</strong> September 18, 1980.Olds, F. C.; uCoal Resources <strong>and</strong> Outlookll; Power Engineering; October1979.Reeder. John W., Coonrod, Patti L., Bragg, Nola I. I Denig-Chakr<strong>of</strong>f,Dave, <strong>and</strong> Markle, Donald R.; Alaska Geothermal Implementation~;Draft for U.S. Department <strong>of</strong> Energy; July 1980.Robert W. Retherford Associates; Alternate Energx StudX: Angoon, Alaska;Preliminary Report for State <strong>of</strong> Alaska Division <strong>of</strong> Energy <strong>and</strong> PowerDevelopment; Anchorage; November 1980.•....apa26/010 E-10..


APPENDIX EBIBLIOGRAPHYRobert W. Retherford Associates; Assessment <strong>of</strong> ~ Generation Alternativesfor Kotzebue; for Alaska Power Authority; Anchorage; June1980.Robert W. Retherford Associates; Bristol Bay Energy <strong>and</strong> Electric ~Potential ~ 1; for U.S. Department <strong>of</strong> Energy; Anchorage;December 1979.Robert W. Retherford Associates; ~ Report: ~ fl!D! Site Investigation,Cordova, Alaska; for Cordova Electric Cooperative;February 1980.Robert W. Retherford Associates; ~ Kuskokwim Single ~ GroundReturn Transmission System ~ I Report; for State <strong>of</strong> Alaska,Department <strong>of</strong> Commerce <strong>and</strong> Economic Development; June 1980.Robert W. Retherford Associates; Transmission Intertie Kake-Petersburg,Alaska: ~ Reconnaissance Report; for Alaska Power Authority;Anchorage; October 1980.Robert W. Retherford Associates; ~ Heat Capture Study for State <strong>of</strong>Alaska; Anchorage; June 1978.R. W. Beck <strong>and</strong> Associates; Investigation <strong>of</strong> Alternative ~ WasteManagement Systems; for City <strong>of</strong> Cordova; October 1979.Schweiger, Robert G. j IIBurning Tomorrow's Fuels"; Power; February 1979.Singh, Ram Bux; Bio-Gas Plant; Mother1s Print Shop; Hendersonville,North Carolina; 1975.Stoner, Carol Hupping, Editor; Producing ~ Own ~; Rodale Press,Inc. j Emmaus, Pennsylvania; 1976.apa26/011E-ll


APPENDIX EBIBLIOGRAPHYTechnical Publishing; Plant Engineering Directory <strong>and</strong> SpecificationsCatalog; 1980.U.S. Army Corps <strong>of</strong> Engineers; Feasibility Studies for Small ~ HydroAdditions; 1979.U.S. Army Corps <strong>of</strong> Engineers; Hydropower Computer Model; 1981.United States Department <strong>of</strong> Commerce, National Oceanic <strong>and</strong> AtmosphericAdministration Environmental Data Service; Monthly Normals <strong>of</strong>Temperature, Precipitation ~ Heating <strong>and</strong> Cooling Degree Days1940-1970 for Alaska.U.S. Department <strong>of</strong> Energy <strong>and</strong> FERC; Hydroelectric Power Evaluation;1979.United States Department <strong>of</strong> Labor; Dictionary <strong>of</strong> Occupational Titles;Fourth Edition; 1977.University <strong>of</strong> Alaska Institute <strong>of</strong> Social <strong>and</strong> Economic Research; ElectricPower in Alaska 1976·1995; August 1976.University <strong>of</strong> Oklahoma Science <strong>and</strong> Public Policy Program; Energy Alternatives:~ Comparative Analysis; Federal Energy Administration;Washington, DC; May 1975.Yould, E. P.; "The Alaska Hydropower Resource"; Alaska Business Trends;Alaska Pacific Bank Corporation.Young, Arthur <strong>and</strong> Company; ~ Discussion <strong>of</strong> Considerations Pertaining toRural Energy Policy Options; State <strong>of</strong> Alaska Department <strong>of</strong> Commerce<strong>and</strong> Economic Development, Division <strong>of</strong> Energy <strong>and</strong> Power Development;April 1979...............-........apa26/012 E-12..•


Phone: (907) 424·3237or 424·3238CITY OF CORDOVBox 1210 602 Railroad Ave.CORDOV A, ALASKA 99574"The Friendly City"~ Repyto:C ...~Warren Eyneart, P.E.Robert W. RetherfordInternational Eng~ing Co.813 liD" StreetAncl:orage, AI{ 99501April 13, 1Dear Mr. Enyeart:I am writing to provide sorre conm:mts <strong>and</strong> guidelines for preparation<strong>of</strong> the <strong>final</strong> refOrt <strong>of</strong> the Cordova Alternate Energy Study. I haverevie~ the various a::mtents received on the draft <strong>and</strong> feel theyare very reasonable. In particular, I would like to call yourattention to the Pt::Mer Authority's conm:mt No.9, which stressedthe need to prepare alternative plans. Several <strong>of</strong> your pr<strong>of</strong>Osals(local hydro) could work in conjunction with oontinued dieselgeneration, but the draft did not discuss the capital costs oro & M <strong>of</strong> such plans. One area that needs rrore discussion is wasteheat reoovery fran the existing plant. The "Power Site SelectionStudy, Cordova" by Retherford, discussed this in detail. The use<strong>of</strong> the waste heat for manufacturing electricity 'or sale for heatinghorres should be addressed in rrore detail.In accordance with past paractices <strong>of</strong> the Alaska Power Authority,you sh:>uld include each agency's a::mtents <strong>and</strong> specifically addressthem in an Appendix in the <strong>final</strong> refOrt. Although, I realize itmay require ~ delay in printing the <strong>final</strong> refOrt, I would likeyou to provide three copies <strong>of</strong> the <strong>final</strong> draft <strong>of</strong> the refOrt for theCity <strong>of</strong> Cordova, Cordova Electric Cooperative <strong>and</strong> Alaska PowerAuthority for review <strong>and</strong> approval prior to printing 75 copies <strong>of</strong>the <strong>final</strong> refOrt. We will conm:mt within five (5) working daysafter receiving t.l:'lE:! <strong>final</strong> draft so you may continue close toschedule.Very truly yours,cc: Doug Bechtel - c:ocBrent Petrie - APA


UNITED STATES DEPARTMENT OF COMMERCENational Oceanic <strong>and</strong> Atmospheric AdministrationNationaZ Marine Fisheries ServiceP.O. Box 1668Juneau~ AZaska 99802Apri 1 10, 1981~i; mI 1# -z...-7z.g\f~~' -~~."- -Mr. Warren L. Enyeart, P.E. ~Project ManagerInternational Engineering Company, Inc. --813 110" StreetP.O. Box 6410Anchorage, Alaska 99502Dear Mr. Enyeart:We have received your letter <strong>of</strong> February 27, 1981, requesting ourcomments on the Draft Reconnaissance Study <strong>of</strong> Energy Requirements <strong>and</strong>Alternatives for Cordova. We have reviewed the Draft Report <strong>and</strong> haveno comment to <strong>of</strong>fer at this time.Thank you for the opportunity to comment.Sincerely,~ ~~.R er W. McVey~r. Alaska RegIon


RECEIVEDAPR 1 "J 1981ALASKA POWER AUTHORITYHr. Perry I,ovett. City HanagerCity <strong>of</strong> CordovaP.O. JO'l( 12J.0Cor~ova. AK 99574Pear t!r. Love t t :!~~re are our COCltlleuts on the draft Reconnaissance Study <strong>of</strong> Hydropower::':1 tea near Cordova, Alaskn, as requested by Mr. Enyeart frol"..l the Hobert~1. Retherford Division <strong>of</strong> Internatiunnl En~ineering Company, Inc.The <strong>study</strong> appears to be logically presented, co~prehensive aud thesuppurting information \:e11 docu.t::leoted in the appendix. It points outthat the resources for electric pov;er in the area are very lir:d.ted.Recotll1leud..atioIlS as to further <strong>study</strong> include: the local identified hydroaltarnative:s; an intertie to Valdez (\-/ith the possibility <strong>of</strong> developingsUlull hydroelectric potentials along the routin~); a.nd a snaIl scalecoal-fired ateamplant.IJe certainly agree with the recoo~ndations for further <strong>study</strong> <strong>of</strong> thelocal hydroa <strong>and</strong> the interconnection. Ho...,ever. we feel tbat the recO"QlOOndationto <strong>study</strong> the potential <strong>of</strong> using a ~T.lall Beale coal-fired uteul'Jplantshould be given lower <strong>study</strong> priority. This is pril:larily due to the costuncertainties associated with stlall staamplants.\·ie note. that the a'tudy identified ,.'I..~nc:! u~o foJ:' 3pace heating .'15 apossiblt-: alternative to oil. This may have a si;;nificont it;:pact on thefuture use <strong>of</strong> oil, <strong>and</strong> we suggest that in future studies, it be analyz~din \;\Orc de tail.The projected yearly peak dem<strong>and</strong> 01lJ <strong>energy</strong> use estimated in the <strong>study</strong>is generally 60mewha t lO11er than our tlseIlcy estio.:l ted in coajuIlc tionwith Corps <strong>of</strong> Engineors studies for Pover Creek. However. it 1s <strong>of</strong> thosaue general ~gnitud~. <strong>and</strong> the variation does not appear aignif1cant.


....The co~t <strong>of</strong> $JOO.OOO to $400, GOO for i1 feasibility 5 t;;dy <strong>of</strong> t;l~ Lt3S-k;·;Crater Lak~ hydropo\o/el' site seeus hi(.11 to) us.We apprec1~tethe oppurtunity to co~rnent.Siecer~ly,Robert J. CrossAdr.linlstca tor...cc:Eric You!u, Alaska POw-er Authorityl~obert 1':. Retherford AssociatesDG07SCHALL:\1S•WI•..1M-......., ..-....


333 WEST 4th AVENUE - SUITE 31 - ANCHORAGE, ALASKA 99501Mr. Warren Enyeart, P.E. ~IICRobert W. Retherford DivisionInternational Engineering Company813 D StreetAnchorage, Alaska 99501Dear Mr. Enyeart:April-------- -Your Draft Report: Reconnaissance Study <strong>of</strong> Energy Requirements <strong>and</strong> AlternativesFor Cordova is generally comprehensive <strong>and</strong> thorough. However, we feelthe following points should be cleaned up or addressed in the <strong>final</strong> <strong>report</strong>:1. Intertie to Valdez. Your costs for intertie route #2 for 59 miles oververy rugged country at $12.2 million seemed questionable when comparedto the 63 mile Cordova to Carbon Creek line (much less rugged country<strong>and</strong> 37 miles <strong>of</strong> existing road access) at $11,050,000. Bob Retherford'sexplanation at the public meeting pointed out that very different constructiontechniques would be used for each line. Some additionalexplanation in the text <strong>of</strong> the possible construction technique forintertie route #2 would help clarify this seeming inconsistency.2. Intertie route 3 also includes smaller hydro sites in addition to thelarge hydro potential at Woods Canyon, Cleve, <strong>and</strong> Million Dollar. Suchsmaller projects may be more suitable for a Cordova-Valdez market <strong>and</strong>should be discussed at a recon level. They might include Cleave Creek,Tiekel River, Van Cleve Lake, Heiden Canyon (Lowe River headwaters),Brown Creek, <strong>and</strong> an unnamed creek in T.10S. R. 5W, Copper River Meridian.3. Based on comments received <strong>and</strong> the recon flight <strong>of</strong> intertie route #2, wesuggest you reexamine the proposed costs for a detailed feasibility <strong>study</strong><strong>and</strong> make sure it is sufficient for necessary engineering <strong>and</strong> geotechnicalfeasibility studies. We also suggest you double check the estimate forfeasibility studies <strong>of</strong> the coal fired plants, to make sure it will providefor the necessary environmental studies in addition to engineering<strong>and</strong> economic feasibility studies.4. There was considerable discussion at the public meeting that the Valdezarea may not have a significant surplus <strong>of</strong> power even with the pressurereducing turbine <strong>and</strong> Allison Creek hydro project in place. This needsto be clarified in the <strong>final</strong> <strong>report</strong> as it affects the viability <strong>of</strong> theintertie. In addition, other benefits <strong>of</strong> an intertie such as the sharing<strong>of</strong> reserves <strong>and</strong> increasing reliability should be discussed.


••Mr. Warren Enyeart, P. E.Apri 1 6, 1981Page 25. Ref. pp. IV-5 Crater Lake is described as possibly <strong>of</strong>fering Iia 435 KWprime" hydroelectricity plant. We underst<strong>and</strong> "prime power" from a hydroelectricityplant as synonomous with continuous power. Continuouspower from a hydroplant is generally defined as the power available froma plant on a continuous basis under the most adverse hydraulic (low flow)conditions. When one considers the very small watershed <strong>of</strong> Crater Lake,it seems that the 435 kW <strong>of</strong> prime power <strong>and</strong> 38,000 MWh per year for CraterLake generation (po B-15) is an error. Figure 4 "Projected Yearly ElectricalConsumption, City <strong>of</strong> Cordova" shows only 16,000 MWh <strong>of</strong> totalconsumption for the year 1980. Crater Lake surely cannot generate morethan twice the present yearly consumption <strong>of</strong> Cordova.6. Ref. pp.IV-16. Heat Pumps. This section should be exp<strong>and</strong>ed so that thelay reader knows what heat pumps are, how they work, <strong>and</strong> their availabilityfor Cordova. The Alaska Power Administration has been conducting a demonstration<strong>and</strong> evaluation <strong>of</strong> air <strong>and</strong> water source heat pumps in Juneau forthe past two years. According to a verbal presentation by Bob Cross inJuneau on March 28, 1981, their data show the heat pumps to be 2.5 to 2.6times as efficient in use <strong>of</strong> electricity as resistive electric space heating.You should check with the Alaska Power Administration on this. Heatpumps may be more economic heating alternative for Cordova than resistiveelectric space heating or heating oil <strong>and</strong>, if so, should be described morefully under technology alternatives (Chapter V) <strong>and</strong> <strong>energy</strong> technology pr<strong>of</strong>iles(Appendix C).7. Ref. pp. IV-3. Item 3 Intertie with Valdez. This paragraph states thatthe Valdez area surplus is expected to decrease by 6% per year <strong>and</strong> refersthe reader to Figure 11 in Chapter VI. However, Figure 11 shows a straightline <strong>of</strong> Valdez area surplus for 1983-1990. This should be corrected. Furthermore,Figure 12 does not match up with Figure 11, i.e., the Figure 12surplus shows about a 15 MW surplus vs. 9 MW surplus on Figure II, <strong>and</strong>the addition <strong>of</strong> Dead Creek shows a 25 MW peak capacity on Figure 12 vs.a 15 MW peak on Figure 11.8. Reference Chapter IV. Wood as a space heating fuel deserves exp<strong>and</strong>ed mentionsince many people in Cordova mentioned that there had been a noticeableshift in the last two years from heating oil to wood stoves. For lack <strong>of</strong>a better figure, I suggest you use estimates provided by the U. S. ForestService in Ken Kilborn's comment. Furthermore, I was told by a local resident,whose name I cannot recall, that the main restrictions on woodharvesting in the nearby Chugach National Forest were due to the factthat the l<strong>and</strong> was selected by Eyak Village Corporation <strong>and</strong> Chugach Natives,Inc. They indicated that wood gathering by permit or fee might be allowedafter title had been transferred to the Natives. While it seems obviousthat wood alone cannot provide for Cordovals <strong>energy</strong> needs it seems likeit may continue to be a viable option for several years on an individualbasis.•••••.,•'"".,..


Mr. Warren Enyeart, P. E.Apri 1 6, 1981Page 3..-9. Chapter VI. This portion does present a series <strong>of</strong> plans to meet Cordova's<strong>energy</strong> <strong>requirements</strong>, but is not in complete conformance with "Alaska PowerAuthority Reconnaissance Study Regulations" which were provided to you atthe beginning <strong>of</strong> the contract. The following excerpts from the <strong>reconnaissance</strong><strong>study</strong> regulations should be used as guidelines in preparing the analysis<strong>and</strong> format for Chapter VI.(c) In order to allow comparative analysis <strong>of</strong> alternativepower sources the authority in conducting a <strong>reconnaissance</strong> <strong>study</strong>will, to the extent applicable, use the following st<strong>and</strong>ardcriteria <strong>and</strong> measures:(1) a "base case" plan will be developed that wouldmeet the forecasted electric power <strong>requirements</strong> <strong>of</strong> the communityor region <strong>and</strong> that would result from a continuation <strong>of</strong> presentpractices in th.e community or region <strong>and</strong>/or from a reliance onliqu:id foss.jJ f..,e1 generation modes. The "base case" plan wills{!rVe·as a basis forcomp~rlng alternative plans.. (2)0 ......•... ternatives, either Singly or lflFombinabe. d into two or. more plans eac~()f whichthe ....... ted requirement$.To tbe ~tent possible.11. b'. ate(.r·t(Jp.rovid~ .•·a C01llDOQ J4ivel <strong>of</strong> rel i-.""; '," " . '" -;' " ','- ---


•Mr. Warren Enyeart, P. E.Apri 1 6, 1981Page 4Please refer to your firm1s recent draft <strong>report</strong> on Thirteen Western AlaskaVillages, Chapters 6 <strong>and</strong> 7, for a format for presentation <strong>of</strong> base case <strong>and</strong> alternativeplans .. The Cordova <strong>report</strong> seems to have all the necessary numbers forpreparation <strong>of</strong> such plans but some revision in the presentation format would behelpful.Please feel free to contact me if you have any questions on the above comments.All comments which you have received on the draft should be includedin an appendix in the <strong>final</strong> <strong>report</strong>.•-•..-•FOR THE EXECUTIVE DIRECTORBrent N. PetrieProject Manager•1.1•IIIII1.1•III..IIIIIIi•


JA r s. HAMMOND, GOVERNORMa rch 27, 1981DEPt\RT,. ..:NT o .. ~ .'ISII !\ND Gt\MEOFFICE OF THE COMMISSIONERCity <strong>of</strong> CordovaP.O. Box 1210Cordova, Alaska 99574Attention: Mr. Perry Lovett, City ManagerGentlemen:Re: Draft Report: Reconnaissance Study <strong>of</strong> Energy Requirements <strong>and</strong>Alternatives for CordovaThe Alaska Department <strong>of</strong> Fish <strong>and</strong> Game has reviewed the above referenced<strong>study</strong> <strong>and</strong> <strong>of</strong>fers no specific comments. We request, however, the opportunityto review any subsequent studies or <strong>report</strong>s regarding <strong>energy</strong> relatedproj~cts for Cordova.If you have any questions,!please do not hesitate to contact us.Sincerely,';{;;n


.... .March 16, 1981[tIGlISH I.lA yMr. Brent Petrie, Project ManagerAlaska Power Authority333 West ,4th Av,enue, Suite 31Anchorage, Alaska 99501Dear Mr. Petrie:I have reviewed your D~aft Report: Reconnaissance Study <strong>of</strong> EnergxRequirements <strong>and</strong> Alternatives for Cordova. Unfortunately, I will not beable to attend the March 19.meeting on this <strong>report</strong> in Cordova, so thefollowing remarks summarize my reaction to this draft.Chugach Natives, Inc., is the Alaska Native regional corporationfor the area encompassed in this <strong>study</strong>. For a myriad <strong>of</strong> reasons ourcorporation has yet to receive the entitlement <strong>of</strong> some 377,000 acres <strong>of</strong>l<strong>and</strong> promised to us under the Alaska Native Claims Settlement Act <strong>of</strong>1971. Once this transfer is completed, Chugach will be primarily anatural resources company.A considerable amount <strong>of</strong> the l<strong>and</strong> which Chugach will eventuallyreceive title to will be located in the general vicinity <strong>of</strong> Cordova.L<strong>and</strong>s currently under consideration for transfer to Chugach includeseveral <strong>of</strong> the small potential hydro-electric sites located betweenCordova <strong>and</strong> Valdez which were mentioned in this <strong>study</strong>, along withthe Bering River c~al field area <strong>and</strong> the Katalla oil. <strong>and</strong> gas area.We readily admit that in pure economic terms neither the BeringRiver coal field nor the Katalla oil <strong>and</strong> natural gas resources justifydevelopment solely for local use. However, as a natural resources company,Chugach has begun <strong>and</strong> intends to continue pursuing the development<strong>of</strong> these resources for non-local consumptio'n.· For instance, negotiationsare actively underway with a number <strong>of</strong> major domestic <strong>and</strong> foreign companiesconcerning the development <strong>of</strong> the Bering River coal field at this time.If any <strong>of</strong>


:11". Brel1 t Pl'tric~ld rdl 1 u, 1 ~l':;lPage Twois determined to be feasible, then the economics <strong>of</strong> utilizing a portion<strong>of</strong> the coal for local use are altered radically. What had heret<strong>of</strong>orebeen an uneconomical <strong>energy</strong> resource, given the high capital costs <strong>and</strong>the low dem<strong>and</strong>, would suddenly become a very viable <strong>energy</strong> alternative.Therefore, in general we do not disagree with your conclusions,based on the assumptions given. But somewhere in your <strong>study</strong> you shouldprovide the latitude for a scenario such as that sketched above for theBering River coal field. Such latitude would lend more credibility toyour <strong>report</strong> under a wider variety <strong>of</strong> future <strong>energy</strong> scenarios for Cordova.Also, one specific statement which should be corrected in your<strong>final</strong> <strong>report</strong> is where you state on page 111-3 that the Eyak NativeVillage Coop owns Chugach Alaska Fisheries. This should read thatChugach Alaska Fisheries, Inc., is a wholly-owned subsidiary <strong>of</strong> ChupachNatives, Inc.Chugach looks forward to a continuing involvement in Cordova's<strong>energy</strong> affairs.Sincerely,Director<strong>and</strong> Natural Resourcescc;Perry LovettDoug ~echtel•II'..•Mil•.......•- .....lilt,..11/..•..•.,II.,...,.......-•""•iii>•..til..III


REPLYTOATTENTION OF,NPAEN-PL-RDEPARTMENT OF THE ARMYFiLE # --Z 7 z-SI'~ti~120 MAR 19B1Mr. Perry LovettCity ManagerP.O. Box 1210Cordova, Alaska 99574Dear Mr. Lovett:Thank you for providing us the opportunity <strong>of</strong> reviewing the Draft Report:Reconnaissance Study <strong>of</strong> Energy Requirements <strong>and</strong> Alternatives for Cordova. Wedo not have the expertise to comment on most <strong>of</strong> the alternatives presented butwould like to furnish the following comments on the hydropower alternative:1. Reference Section IV, paragraph 1.a. Besides environmental problems,the Million Dollar, Cleve <strong>and</strong> Woods Canyon projects should be excluded becausethey are too large for the Cordova market. However, other sites in the CopperRiver area might be included. These are Tieke1 River, Sheep Creek <strong>and</strong> CleveCreek.2. Reference Section IV, paragraph 1.b. The Corps' investigations todate on Power Creek indicate that a 6,000 kw run-<strong>of</strong>-river project may befeasible. We are also <strong>study</strong>ing the possibility <strong>of</strong> a storage project at thesame site at Ohman Falls. Other sites on Power Creek have been ruled out dueto the extreme depth to bedrock.3. Reference Section IV, paragraph 1.c. The recent Corps' <strong>study</strong> forValdez shows that there would be no surplus <strong>energy</strong> at Valdez until after theSolomon Gulch project is completed <strong>and</strong> that even if the pressure reducingturbine is installed in the Trans Alaska pipeline, the Valdez-Glennallen areawill need additional power in 1990 for the winter peak dem<strong>and</strong>s. It should bementioned that a pressure reducing turbine is only a short range <strong>energy</strong> sourcesince the supply <strong>of</strong> oil from the North Slope is limited.The intertie proposal should be studied, to determine the feasibility <strong>of</strong> thenumerous sites along the intertie route, <strong>and</strong> other benefits from an intertiesuch as balancing <strong>energy</strong> dem<strong>and</strong>s.4. Reference Figure 7. Silver Lake <strong>and</strong> Simpson Creek could be added toRoute 2. Route 3 Intertie could have projects tied into it such as CleveCreek, Tiekel River, Sheep Creek <strong>and</strong> Van Cleve Lake.


NPAEN-PL-RMr. Perry Lovett20MAR 198\5. Reference Section IV, paragraph l.d. For Crater Lake it should bementioned that the cannery at Orca has a water right <strong>of</strong> one cfs. A dualpurpose project <strong>of</strong> water supply <strong>and</strong> hydropower should be recommended.6. Reference Section VIII page 1 <strong>and</strong> Figure 13. The second stage forPower Creek is still under <strong>study</strong>. The cost <strong>of</strong> $5,000/kw to develop smallhydropower sites along the intertie line <strong>and</strong> $11,200,000 for the SWGR lineappear to be low for this terrain.7. Reference Appendix B, page B-15. Discharge from Crater Lake to EyakLake is more difficult due to adverse topography. It should discharge towardOrca. Our estimates indicate the cost for this project is higher than the$3,500 stated.Other than these comments, the Draft Report is very good. We are stillplanning to drill the site on Power Creek this summer <strong>and</strong> also install a gageon the outflow from Crater Lake. We hope to discuss this with you when youcome to the harbor bid opening next month.If we can be <strong>of</strong> further assistance, please do not hesitate to contactMr. Ken Hitch <strong>of</strong> our Planning Branch at 752-3461.Copy Furn ished: /­Brent Petr; e Jr/Alaska Power AuthoritySincerely,lSI HARLAN E. MOORgHARLAN E. MOOREChief, Engineering Division........•......• ....•..•••...........'2..


....~,,,,,' -" 1596790..U.S. DEPARTMENT OF AGRICULTURESPEED MEMOFROM..!SICNATURE______-L_*~=-=====-____ ~~~~~~--------.----------------------REPl Y (USE THIS CE FOR REPL y, SIGN AND DATE. RETURN PART 3 TO SENDER. RETAIN PART I)RECEIVED..r ,'1AR 1 > 19 81FILE # _ '2.-:( zB..DATE


Phone: ~907) 424-3237or 424-3238~Warren Enyeart, P.E. 11~Project ManagerRobert W. Retherford Assoc.Box 6410Anchorage, AK 99502Dear Mr. Enyeart:CITY OF CORnOV ~f~~28~~~Box 1210 602 Railroad Ave.f\f \~ ~ 1y to:CORDOVA, ALASKA 9957"~ ~~\ t\\ ~"1Jte Friendly Cily" .... ~ \\\t\\~t\l :\~ \\~ "\~.9IMarChI thought the public hearing went well with several goodcomments <strong>and</strong> suggestions.23~fo~HM-----"""$[ lit e, ~\. \,\0 Z?ZB','\NR -"V' _____fo- ~k1-'Some areas that Iare:feel should be tightened up <strong>and</strong> developed1. Check projected planning budget costs for Valdez intertie.Several comments that budget costs are low. I agree that we don'twant inflated costs--only best realistic estimated possible.2. Coal fire plant. There should be planning budget costsfor a new plant--5, 10, 15, 20 year estimated costs <strong>of</strong> operation<strong>and</strong> coal costs with consideration <strong>of</strong> the Healy, Beluga <strong>and</strong>Bering River Fields as sources.3. Coal for heating. Same resources for residential <strong>and</strong> industrialheating--costs <strong>and</strong> availability <strong>of</strong> coal.Both <strong>of</strong> these should address the environmental conditions you broughtup on rain run<strong>of</strong>f from the stockpile.4. Copper River Run <strong>of</strong> River. What are the probabilities,problems, costs <strong>and</strong> environmental concerns (fish, etc.).5. Pressure reducing turbine. There should be a more definitestatement about the present <strong>and</strong> future plans for this project.Who will do it, when <strong>and</strong> how will power be utilized.6. Discussion <strong>of</strong> statement that Valdez will be power-leanby 1984.7. Dead Creek. What is environmental position, fish spawningstream, l<strong>and</strong> ownership, costs, etc. A good vigorous discussion<strong>of</strong> this subject is certainly warranted.8. ALPETCO. What are the probabilities <strong>of</strong> this project beingbuilt in Valdez. Effect on power needs.


••.,..•.,..page 29. Ownership map <strong>of</strong> l<strong>and</strong>s near Katella, Bering River Coal Fields<strong>and</strong> patented natural gas fields.The frank discussion <strong>of</strong> these issues are necessary before wetake dead aim at selecting one or more items for a detailedfeasibility <strong>study</strong>.We look forward to reviewing your interpretation <strong>of</strong> theseitems.Very truly yours,cc:Brent Petrie, APADoug Bechtel, CEC......,.,••••..•.,•..


MIS 44313 MAR 198'Per~ lovett, City ManagerCity <strong>of</strong> CordovaP. O. Box 1210Cordova, Alaska 99574----- -Subject: Oraft Report: Reconnaissance Study <strong>of</strong> Energy Requirements <strong>and</strong>Alternatives for CordovaDear Mr. lovett:Thank you for giving us the opportunity to review the above draft <strong>study</strong>.We have no comments on the <strong>study</strong>, though we thought it was quite welldone <strong>and</strong> interesting.We would appreciate the opportunity to review future feasibility studieswhich may be prepared on any <strong>of</strong> the hydroelectric or coal-fired powerplant alternatives since we could have a role in the federal permitswhich may be required for such facilities.Please feel free to contact either myself or Judi Schwarz <strong>of</strong> my staff ifyou have any questions. We can be reached at (206) 442-1285.Sine ere 1 y yt'lurs,Elizabeth Corbyn. ChiefEnvironmental Evaluation Branch~~cc: Warren l. Enyeart, International Engineering CompanyJSchwarz:blm 03-13-81TEWilson

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!