06<br />
rosa:<br />
aN oPTIMIZED<br />
DEVELoPMENT sCHEME<br />
KEy DaTEs<br />
December 2005:<br />
> Start of the drilling campaign by the<br />
drillship Saipem 10000.<br />
> Arrival of the flotel Regalia and<br />
<strong>com</strong>mencement of integration works<br />
onboard the Girassol FPSO.<br />
June 18, 2007:<br />
First oil from the <strong>Rosa</strong> E reservoir.<br />
July 21, 2007:<br />
Start production from the <strong>Rosa</strong> D reservoir.<br />
september 2007:<br />
Start of the drilling campaign by<br />
the drillship Pride Angola.<br />
october 2007:<br />
Start of water injections.<br />
A drilling campaign begun in December<br />
2005, scheduled to last until mid-2008,<br />
mobilizing two drillships.<br />
Two subsea installation campaigns: one<br />
from February to May 2006 and the other<br />
from November 2006 to March 2007.<br />
Two lifting campaigns to install the modules<br />
in October 2006 and February 2007.