14.09.2016 Views

PRACTICES

nastt-ne-journal-2016

nastt-ne-journal-2016

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

NEIL HANDLER, EPA SENIOR ENFORCEMENT<br />

COORDINATOR, STATED, “THE EPA IS ENCOURAGED<br />

TO SEE THAT LATERAL LINING TECHNOLOGY<br />

HAS PROGRESSED TO A POINT WHERE IT CAN<br />

FURTHER ELIMINATE INFLTRATION ISSUES AND<br />

EXFLTRATION ISSUES.”<br />

Until recently, the focus of sanitary sewer<br />

rehabilitation was primarily on relining the<br />

main sewer pipe manhole to manhole, and<br />

then sealing the manhole structures. Laterals<br />

were reinstated, and groundwater allowed<br />

back into the system. In some instances,<br />

lateral connections were grouted, but a<br />

permanent solution was never applied, and<br />

lateral pipes were neglected because of the<br />

complexities. First was the issue of ownership.<br />

Who is responsible for the connection<br />

and lateral pipe, and to what extent? Second<br />

was the limited technology available in the<br />

market place which could permanently rehabilitate<br />

the lateral with minimal disturbance<br />

to residents, sewer service and surrounding<br />

environment.<br />

Technology has caught up to the demand<br />

in the market place and now allows the<br />

lateral to be lined and a watertight mainline<br />

connection to be made during the same<br />

installation. The integration of lateral lining<br />

into a comprehensive rehabilitation approach<br />

is a new and effective solution. Lateral lining<br />

is the final rehabilitation step which yields the<br />

The integration of lateral lining into a comprehensive rehabilitation approach is a new and effective solution<br />

Technology now allows the lateral to be lined and<br />

a watertight mainline connection to be made during<br />

the same installation<br />

most cost-effective use of public expenditures<br />

by permanently sealing the sanitary sewer<br />

collection system, reducing/eliminating<br />

infiltration, and also eliminating exfiltration<br />

- the final piece of the “comprehensive” sewer<br />

rehabilitation puzzle.<br />

Issues of lateral pipe ownership were<br />

discussed when designing the scope of work<br />

for the Norwood project. The town owns<br />

the connection and the lateral pipe up to the<br />

property line (approximately a lateral length<br />

of 20 feet from the mainline to property<br />

line). However, infiltration and exfiltration<br />

problems were not only occurring in<br />

the first 20 feet, they were also occurring<br />

beyond this limit and needed to be resolved<br />

once and for all. The town’s engineering<br />

personnel took the leadership role and made<br />

the decision to line up to within 10 feet of<br />

the house foundation.<br />

This design decision pushed the limits of<br />

the trenchless technology available for lining<br />

the lateral from host pipe without need for<br />

secondary access (i.e. no cleanout installed).<br />

The EPA was on board supporting the approach<br />

and was pleased to see the town take<br />

a leadership role permanently addressing the<br />

environmental issues facing its aging collection<br />

system. The town took a leap of faith the<br />

trenchless market could rise to the occasion<br />

and, by using the comprehensive approach to<br />

sewer rehabilitation, could execute its vision<br />

to get this crucial work done with minimal<br />

disruption to the homeowner.<br />

During Phase 1 of the project in 2011,<br />

the installation contractor was still required<br />

to install a secondary means of access (i.e.<br />

cleanouts) in order to rehabilitate the lateral<br />

to the lengths that the town desired. From<br />

2012 – 2014, National Water Main Cleaning<br />

Company (NWMCC) was the successful low<br />

bidder on the subsequent project Phases 2, 3<br />

& 4. Each project Phase focused on a specific<br />

subarea and required the entire network to<br />

be sealed – mainline, manholes and laterals.<br />

While the quantities for each subarea varied,<br />

the total approximate quantities for the 3<br />

subarea Phases were 27,600 feet of mainline,<br />

185 manholes and 490 laterals rehabilitated.<br />

Each Phase of the project was unique<br />

and presented several challenges because a<br />

high proportion of the lateral connections<br />

were break in connections that entered the<br />

main pipe at various angles. Additionally, the<br />

majority of the laterals did not have access via<br />

a clean out. Many of the property lots were<br />

large with houses situated far back in the lot<br />

resulting in long lateral lengths. The average<br />

lateral length was in the mid 40-foot range<br />

with several laterals reaching lengths up to<br />

100 feet long. The town required the lateral<br />

pipe to be cleaned, inspected and relined<br />

from the main sewer pipe, and wanted to<br />

avoid any disruption to private property<br />

(installation of a cleanout).<br />

42 NASTT-NE NORTHEAST JOURNAL OF TRENCHLESS TECHNOLOGY <strong>PRACTICES</strong> 2016 | WWW.NASTT-NE.ORG

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!