3. The BUYER undertakes to purchase a minimum of at least 2,000 fan blades under this<br />

Agreement, expressing at the same time the firm intention to purchase further units in<br />

subsequent years.<br />

Section 3 DELIVERY<br />

1. The SELLER agrees to produce and deliver 2,000 TRF 192-I swept fan blades by 14<br />

January 2015.<br />

[…]<br />

Section 4 PURCHASE PRICE<br />

1. The purchase price is calculated on a cost-plus basis according to the following formula<br />

• Production Costs per blade ≤ 9,500 US$: 9,975 US$<br />

• Production Costs per blade: 9,500 – 10,500 US$: Costs + 475 US$ (5% of 9,500)<br />

• Production Costs per blade: 10,501 – 11,500 US$: Costs + 420 US$ (4% of 10,500)<br />

• Production Costs per blade: 11,501 – 12,000 US$: Costs + 345 US$ (3% of 11,500)<br />

• Production Costs per blade: 12,001 – 12,500 US$: Costs + 240 US$ (2% of 12,000)<br />

• Production Costs per blade: 12,501 – 13,000 US$: Costs + 125 US$ (1% of 12,500)<br />

• Production Costs per blade ≥ 13,125 US$: 13,125 US$<br />

The minimum price per fan blade irrespective of production costs is US$ 9,975 while the<br />

maximum price to be charged per fan blade is US$ 13,125.<br />

Should the production costs per fan blade exceed US$ 13,125 due to extraordinary<br />

unforeseeable circumstances and result in unbearable hardship for the Seller the Parties will<br />

enter into good faith negotiations to determine a price which is financially acceptable to<br />

both parties.<br />

2. The price is due upon delivery of the fan blades and payment should be confirmed by the<br />

BUYER as soon as possible.<br />

3. The BUYER will deposit the purchase price in full into the SELLER’s account at the<br />

Equatorianian National Bank, Ocean Promenade 3, Equatoriana, IBAN 1209 3456 6798;<br />

SWIFT EQXPL6. The bank charges for the transfer of the amount are to be borne by<br />

the BUYER.<br />

[….]<br />

Section 20 CHOICE OF LAW<br />

This Agreement is governed by the UN Convention on the International Sale of Goods<br />

(“CISG”). For issues not dealt with by the CISG the UNIDROIT Principles are applicable.<br />

© Association for the Organisation and Promotion of the Willem C. Vis International Commercial Arbitration Moot 10<br />

Prof. Dr. Stefan Kröll

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!